Opinion

G4s Secure Integration LLC v. United States

Court
United States Court of Federal Claims
Filed
Apr 8, 2022
Status
Published
On the bench
Richard A. Hertling
Cited by
0 cases
Authority
More cited than 8.2%

evaluating an agency’s corrective action under the rational-basis 7 standard

How later courts described this case

  • evaluating an agency’s corrective action under the rational-basis 7 standard
  • finding prejudice when the agency failed to engage in a required price analysis
  • granting an injunction under RCFC 62(d)

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

No. 21-1817C

Filed: April 8, 2022*

FOR PUBLICATION

G4S SECURE INTEGRATION LLC, et

al.,

Plaintiffs,

v.

UNITED STATES,

Defendant,

and

CGS-ORSA SECURITY LLC,

Defendant-Intervenor.

Richard P. Rector, DLA Piper LLP, Washington, D.C., for the plaintiffs, with C. Bradford

Jorgensen, Thomas E. Daley, Ryan P. Carpenter, and Christie M. Alvarez, of counsel.

Daniel A. Hoffman, Commercial Litigation Branch, Civil Division, U.S. Department of Justice,

Washington, D.C., for the defendant, with John W. Cox, Office of the Legal Adviser, U.S.

Department of State, of counsel.

Robert Nichols, Nichols Liu LLP, Washington, D.C., for the defendant-intervenor, with Michael

Bhargava, Madison Plummer, and Andrew Victor, of counsel.

*

Pursuant to the protective order in this case, the Court initially filed this opinion under seal

on April 5, 2022, and directed the parties to propose redactions of confidential or proprietary

information. The parties have jointly submitted to the Court proposed redactions. (ECF 73.)

The Court adopts those redactions, as reflected in this public version of the opinion. Redactions

are denoted with three asterisks in square brackets, [* * *].

MEMORANDUM OPINION

HERTLING, Judge

The plaintiffs (G4S Secure Integration LLC; G4S Secure Solutions International, Inc.;

and G4S Serviços de Segurança Angola LDA) move for an injunction pending appeal under Rule

62(d) of the Rules of the Court of Federal Claims (“RCFC”). In this post-award bid protest, the

Court found that the plaintiffs had demonstrated that the evaluation of a contract awarded by the

U.S. Department of State (“State”) to the defendant-intervenor, CGS-ORSA Security LLC

(“CGS-ORSA”), violated Federal Acquisition Regulation (“FAR”) 52.204-7. The Court denied

the plaintiffs’ motion for judgment on the administrative record, however, because the plaintiffs

had not demonstrated prejudice on the merits.

In this pending RCFC 62(d) motion, the plaintiffs have not demonstrated that they either

are likely to succeed on appeal or have presented a substantial case on the merits. Even if the

plaintiffs had made either showing, other equitable factors weigh against awarding injunctive

relief. Accordingly, the Court denies the plaintiffs’ motion for an injunction pending appeal.

I. BACKGROUND

The facts are recounted in detail in the Court’s opinion on the merits of this case, G4S

Secure Integration, LLC v. United States, No. 21-1817C, 2022 WL 211023 (Fed. Cl. Jan. 24,

2022). Briefly, the plaintiffs filed a post-award bid protest challenging a contract award issued

by State for security services for the U.S. Embassy in Luanda, Angola. The plaintiffs submitted

a proposal as a joint venture (“G4S”) comprised of G4S Secure Integration LLC; G4S Secure

Solutions International, Inc.; and G4S Serviços de Segurança Angola LDA. State awarded the

contract to the defendant-intervenor, CGS-ORSA, a joint venture owned by Continuity Global

Solutions, LLC (“CGS”) and Omega Risk Solutions Angola (“ORSA”).

G4S argued that CGS-ORSA did not comply with FAR 52.204-7, which was

incorporated into the solicitation, rendering CGS-ORSA ineligible for award. FAR 52.204-

7(b)(1) provides that “[a]n Offeror is required to be registered in [System for Award

Management (“SAM”)] when submitting an offer or quotation . . . .”1 (Emphasis added.) Until

FAR 52.204-7(b)(1) was amended in 2018, offerors were permitted to register in SAM at any

time prior to award. When the FAR Council amended FAR 52.204-7 in 2018, it published a

response to a comment stating that this provision applied equally to joint ventures. See “Federal

Acquisition Regulation: System for Award Management Registration,” 83 Fed. Reg. 48,691-01,

48,692 (Sept. 26, 2018).

At the time that CGS-ORSA submitted its offer to State, its joint venture was not

registered in SAM. CGS-ORSA purported to have created a separate legal entity for its joint

venture and later registered its joint venture as a Limited Liability Company (“LLC”). CGS and

1

SAM is a government database that maintains information on prospective and actual

awardees of federal contracts. See FAR 52.204-13(a).

2

ORSA each maintained separate active SAM registrations. Following a pre-award survey

conducted by State, CGS-ORSA registered its joint venture in SAM prior to award.

G4S submitted an offer as a “contractor team arrangement,” so it did not create a separate

legal entity for its joint venture.2 (See ECF 32 at 3.) Accordingly, G4S never registered its joint

venture in SAM. All three entities owning the joint venture maintained separate SAM

registrations.

State conducted a pre-award survey and determined that both CGS-ORSA and G4S were

eligible for award. The solicitation indicated that State would select the awardee with the lowest

priced, technically acceptable proposal. State determined that G4S’s and CGS-ORSA’s

proposals were both technically acceptable. State selected CGS-ORSA for award because its

proposed price was eight percent lower than G4S’s proposed price.

The Court held that the plaintiffs had standing to sue because they were actual offerors

claiming that they were eligible for award. If State had determined that CGS-ORSA was

ineligible for the award, as the plaintiffs allege it should have, G4S would have had a substantial

chance of being awarded the contract.

The plaintiffs further demonstrated that State had violated FAR 52.204-7 when State did

not require CGS-ORSA’s joint venture to be registered in SAM at the time it submitted its offer.

State lacked discretion to overlook or waive the requirements of FAR 52.204-7.

The Court held, however, that this error was not prejudicial because G4S had not

registered its own joint venture in SAM. G4S had benefited from the same unlawful discretion

from which the awardee benefited. The plaintiffs argued that because all three entities

participating in the G4S joint venture were listed as separate offerors, their proposal met the

requirements of FAR 52.204-7. The comment in the Federal Register, however, does not

distinguish the applicability of FAR 52.204-7 based on the type of joint venture submitting an

offer. Even if State had found CGS-ORSA to be ineligible for award, G4S did not prove that it

had a substantial chance of receiving the contract because its own proposal suffered from the

same defect as CGS-ORSA’s.

In the absence of any prejudice to the plaintiffs, the Court granted the defendant’s and

defendant-intervenor’s motions for judgment on the administrative record and denied the

plaintiffs’ motion for judgment on the administrative record. (ECF 39, 40.) The plaintiffs filed a

notice of appeal. (ECF 50.)

On March 2, 2022, the plaintiffs filed a motion for an injunction pending appeal under

RCFC 62(d). (ECF 51, 52.) The defendant and defendant-intervenor filed responses to the

2

At oral argument on this motion, the plaintiffs analogized the structure of this arrangement

to a partnership.

3

plaintiffs’ motion. (ECF 61, 62.) The plaintiffs filed a combined reply brief on March 24, 2022.

(ECF 66.) The Court heard oral argument on March 30, 2022.

II. STANDARD OF REVIEW

Under RCFC 62(d), while an appeal is pending from a final judgment refusing an

injunction, “the court may suspend, modify, restore, or grant an injunction on terms for bond or

other terms that secure the opposing party’s rights.” The moving party bears the burden of

demonstrating that an injunction pending appeal is appropriate. See, e.g., Telos Corp. v. United

States, 129 Fed. Cl. 573, 575 (2016). An injunction pending appeal is an “‘extraordinary and

drastic remedy,’” which is not granted lightly. See id. (quoting Akima Intra–Data, LLC v. United

States, 120 Fed. Cl. 25, 27 (2015)).

In determining whether the moving party has met its burden of showing that a stay

pending appeal is appropriate, a court considers four factors:

(1) whether the stay applicant has made a strong showing that [it] is

likely to succeed on the merits; (2) whether the applicant will be

irreparably injured absent a stay; (3) whether issuance of a stay will

substantially injure the other parties interested in the proceeding;

and (4) where the public interest lies.

Hilton v. Braunskill, 481 U.S. 770, 776 (1987) (citations omitted). Because these “traditional

stay factors contemplate individualized judgments in each case, the formula cannot be reduced to

a set of rigid rules.” Id. at 777.

In evaluating whether to grant a stay pending appeal, the Federal Circuit “assesses [a]

movant’s chances for success on appeal and weighs the equities as they affect the parties and the

public.” E.I. DuPont de Nemours & Co. v. Phillips Petroleum Co., 835 F.2d 277, 278 (Fed. Cir.

1987).

The Federal Circuit elaborated the governing test in Standard Havens Prods., Inc. v.

Gencor Indus., Inc., 897 F.2d 511 (Fed. Cir. 1990). Under the test, which the Circuit described

as “effectively merg[ing]” the four factors outlined in Hilton, “[e]ach factor . . . need not be

given equal weight.” Id. at 512-13. When the “harm to the applicant is great enough, a court

will not require ‘a strong showing’ that applicant is ‘likely to succeed on the merits.’” Id. at 513

(quoting Hilton, 481 U.S. at 776). The Federal Circuit described this standard as a “‘sliding

scale approach.’” Id. (quoting Roland Mach. Co. v. Dresser Indus., Inc., 749 F.2d 380, 387-88

(7th Cir. 1984)). Under the Circuit’s approach, “‘[t]he more likely the [applicant] is to win, the

less heavily need the balance of harms weigh in [its] favor; the less likely [it] is to win, the more

need it weigh in [its] favor.’” Id. (quoting Roland Mach., 749 F.2d at 387-88). Thus, a stay

pending appeal may be appropriate even when the moving party has not shown that it is likely to

succeed on the merits if the moving party has demonstrated a substantial case on the merits, and

the other factors tilt decidedly toward the moving party. Telos, 129 Fed. Cl. at 575.

4

III. DISCUSSION

The plaintiffs’ motion for a stay pending appeal must be considered under the four Hilton

factors. The first and most important factor to consider is whether the plaintiffs have shown a

likelihood of success on the merits of their appeal or have shown that their appeal presents a

substantial case on the merits.

A. Success on the Merits

The plaintiffs argue that they are likely to succeed on the merits of their appeal. (ECF 52

at 3-7.) Although an injunction pending appeal is an extraordinary remedy, the plaintiffs argue

that the Court’s equitable powers exist for a reason. See PDS Consultants, Inc. v. United States,

133 Fed. Cl. 810, 818 (2017) (granting an injunction under RCFC 62(d)).3

G4S and CGS-ORSA were the only offerors that State found to be eligible in the

protested procurement, and neither offeror met the requirements of FAR 52.204-7 because

neither offeror’s joint venture was registered in SAM when the offers were submitted. State

lacked the discretion to ignore or waive FAR 52.204-7. The plaintiffs argue that instead of

upholding the award of the contract to CGS-ORSA, an ineligible offeror, the Court should have

remanded the procurement to State. The plaintiffs assert that, on remand, State would have

needed to reopen the procurement because there was no eligible offeror. The plaintiffs claim that

G4S would have a substantial chance of award in any new competition.

In support of this motion, the plaintiffs do not directly challenge the Court’s finding that

the plaintiffs’ proposal violated FAR 52.204-7, although they explain that they intend to pursue

that argument on appeal. Rather, the plaintiffs argue that they were prejudiced by State’s error in

making an award to an ineligible offeror and that the Court erred in upholding that award.

The Court considers whether the plaintiffs have demonstrated that they are likely to

succeed in proving prejudice on the merits upon their appeal before analyzing whether the

plaintiffs have met their burden to show a substantial case on the merits.

1. Prejudice on the Merits

The Federal Circuit has rejected the proposition that “if the government makes any

mistake in a procurement process . . . , no matter how slight or unharmful, then it must nullify the

contest and begin anew.” Labatt Food Serv., Inc. v. United States, 577 F.3d 1375, 1380 (Fed.

Cir. 2009). “[N]on-prejudicial errors in a bid process do not automatically invalidate a

3

During oral argument and in their brief in support of this motion, the plaintiffs rely on a

cursory one-page order granting a stay pending appeal in CGI Fed. Inc. v. United States. (No.

14-355, ECF 53.) An unexplained order cannot be used to support the plaintiffs’ argument in the

present case, except to show, as a general matter, that injunctions under RCFC 62(d) are

appropriate when the test for such an injunction is met, and RCFC 62(d) itself provides all the

support necessary for that proposition.

5

procurement.” Id. Whether State needed to recompete the procurement therefore depends on

whether State’s misinterpretation of FAR 52.204-7 was prejudicial to the plaintiffs. Id.; see also

Bannum, Inc. v. United States, 404 F.3d 1346, 1351 (Fed. Cir. 2004) (emphasis added) (“A bid

protest proceeds in two steps. First, . . . the trial court determines whether the government acted

without rational basis or contrary to law when evaluating the bids and awarding the contract.

Second, . . . if the trial court finds that the government’s conduct fails the [Administrative

Procedure Act] review under 5 U.S.C. § 706(2)(A), then it proceeds to determine, as a factual

matter, if the bid protester was prejudiced by that conduct.”).

In Labatt, the Federal Circuit ruled that a protestor had not established prejudice when

the government accepted bid revisions via e-mail rather than fax, even though the solicitation

required revisions to be made via fax. 577 F.3d at 1380-81. The protestor had submitted its

proposal late, providing the agency with “a separate and independently sufficient ground for

rejection.” Id. at 1381. The Federal Circuit held that “[a]ll errors are not equal. . . . There is no

connection between the government’s method of transmission error and Labatt’s failure to secure

the contract. Without a showing of harm specific to the asserted error, there is no injury to

redress, and no standing to sue.” Id.

Although the court in Labatt addressed prejudice as it relates to standing rather than

prejudice on the merits, the Federal Circuit has since clarified that the question of whether the

error is related to action adverse to the protestor is also relevant to the issue of whether the

protester suffered prejudice on the merits. In American Relocation Connections, LLC v. United

States, the Federal Circuit explained, “‘The correction of an error must yield a different result in

order for that error to have been harmful and thus prejudice a substantial right of a party.’”

789 F. App’x 221, 228 (Fed. Cir. 2019) (quoting Munoz v. Strahm Farms, Inc., 69 F.3d 501, 504

(Fed. Cir. 1995)). Review of agency action in a bid protest requires “courts to disregard ‘errors

or defects which do not affect the substantial rights of the parties.’” Id. (quoting 28 U.S.C.

§ 2111). To succeed in a bid protest, a plaintiff must show “a greater-than-insignificant chance”

of prevailing absent agency error. Id.

In this case, State’s misapplication of FAR 52.204-7 did not prejudice the plaintiffs. The

SAM-registration status of neither CGS-ORSA nor the plaintiffs affected State’s award decision.

State evaluated both proposals, despite the lack of SAM registrations. CGS-ORSA secured the

award because its proposal was technically acceptable, and its proposed price was lower than

G4S’s proposed price. Neither joint venture adhered to the requirements of FAR 52.204-7, and

neither offeror gained a competitive advantage in the procurement resulting from the status of its

SAM registration. As in Labatt, there was therefore no connection between the error the

plaintiffs asserted and their failure to secure the contract.

The plaintiffs offer three reasons why this case is distinct from Labatt. First, the

plaintiffs underscore that in Labatt, there was a “‘separate and independently sufficient ground’”

for eliminating that plaintiff from the competition; the plaintiff had submitted its proposal late.

(ECF 66 at 8 (quoting Labatt, 577 F.3d at 1381).) In this case, both CGS-ORSA and the

plaintiffs were ineligible for award for the same reason.

6

Although the plaintiffs were never eliminated from the competition, their proposal was

rejected for a reason different from the alleged error: their price. State had separate and

independently sufficient grounds, setting the SAM-registration issue aside, for selecting CGS-

ORSA’s proposal for award. As in Labatt, both G4S and CGS-ORSA had a full and equal

opportunity to compete for the contract.

Second, the plaintiffs seek to distinguish Labatt because the plaintiff in that case “sat on

its rights regarding whether email was an acceptable method of transmission . . . .” (ECF 66 at

9.) That fact does not appear to have been material to the Federal Circuit’s ruling that “non-

prejudicial errors in a bid process do not automatically invalidate a procurement.” Labatt, 577

F.3d at 1380.

Finally, at oral argument on this motion, the plaintiffs argued that Labatt is distinct

because the awardee in that case was eligible for award. In this case, on the other hand, the

initial decision upheld the award of a contract to an ineligible offeror.

The plaintiffs’ attempt to distinguish Labatt on this third ground distorts the facts

underlying that case. A judge of this court had found that the agency’s “deviation from the

solicitation render[ed] the proposal revisions from all offerors unable to be considered by the

agency,” i.e., ineligible for award. Labatt Food Serv., Inc. v. United States, 84 Fed. Cl. 50, 59

(2008). The Federal Circuit did not disturb that finding and assumed in its analysis of prejudice

that the government’s acceptance of e-mailed revisions was “unauthorized” and “erroneous.”

Labatt, 577 F.3d at 1381. The facts of Labatt are therefore analogous to those of this case: the

agency committed an error, but that error did not affect the plaintiffs’ loss of the contract award.

The plaintiffs were not awarded the contract for reasons, such as price here or lateness in Labatt,

unrelated to the agency’s error.

In addition, the plaintiffs’ attempt to divert the focus of the prejudice analysis from their

own ineligibility to the ineligibility of the awardee is misplaced. The plaintiffs must show a

substantial chance of award absent agency error, and that inquiry requires some examination of

the plaintiffs’ own eligibility. For example, in Alfa Laval Separation, Inc. v. United States, the

Federal Circuit held that a plaintiff was prejudiced when its proposed price was lower than the

awardee’s proposed price and the plaintiff’s proposal was “‘irrefutably compliant’” with the

terms of the solicitation. 175 F.3d 1365, 1368 (Fed. Cir. 1999) (quoting Alfa Laval Separation,

Inc. v. United States, 40 Fed. Cl. 215, 230 (1998)). When determining whether the plaintiffs

have shown prejudice on the merits, the plaintiffs’ own eligibility matters.

The plaintiffs also have not explained how State’s failure to follow FAR 52.204-7

affected their substantial rights and is not therefore a harmless error. See Am. Relocation

Connections, 789 F. App’x at 228. The plaintiffs argue that if the Court ordered an injunction

pending appeal, State would have broad discretion in deciding how to recompete the contract,

and State “could, for example, take corrective action by reopening discussions and permitting

G4S and CGS-ORSA to submit revised proposals that comply with FAR 52.204-7 and provide

updated, lower pricing.” (ECF 66 at 4 (emphasis added).) Agencies have broad discretion in

determining how to take corrective action. See Dell Fed. Sys., L.P. v. United States, 906 F.3d

982, 992-97 (Fed. Cir. 2018) (evaluating an agency’s corrective action under the rational-basis

7

standard); ANHAM FZCO v. United States, 149 Fed. Cl. 427, 438 (2020) (holding that “the court

will not substitute its judgment for that of the agency” in determining the appropriate scope for

corrective action). The plaintiffs also quote FAR 6.101 for the proposition that State should

“‘promote and provide for full and open competition.’” (ECF 66 at 4-5.)

In determining whether the plaintiffs have been prejudiced on the merits, the question is

not whether the agency could possibly reach another result if it were to recompete a solicitation.

The question is whether the plaintiffs “show that there is a greater-than-insignificant chance” that

the agency would reach a different result “had it not committed the alleged errors.” Am.

Relocation Connections, 789 F. App’x at 228. Because of the substantial price differential

between the plaintiffs’ proposal and CGS-ORSA’s proposal, the plaintiffs’ speculation on the

possible outcome of the procurement were State to recompete the solicitation does not meet their

burden set forth by the Federal Circuit. There is little connection between the broad discretion

agencies have in taking corrective action and the plaintiffs’ burden to prove prejudice. The

plaintiffs have already had an opportunity to participate in a full and open competition for award;

the plaintiffs lost that competition because they proposed a higher price than the awardee did, not

because of any of the offerors’ SAM-registration status.

In Bannum, the Federal Circuit held that a plaintiff had not demonstrated prejudice on the

merits when there was “nothing besides [the plaintiff’s] conjecture to support the contention that

another review, comporting with the FAR, would provide it a substantial chance of prevailing in

the bid. [The plaintiff’s] argument rests on mere numerical possibility, not evidence.” 404 F.3d

at 1358. The test for prejudice “is more lenient than showing actual causation,” but a plaintiff

must show that there was a “substantial chance” of receiving the award but for the agency’s

errors. Id. The plaintiff in Bannum had advocated for a different calculation of its score which,

even if employed, would not have allowed the plaintiff to be awarded the contract. Although the

plaintiff successfully argued on the merits that the government had violated a regulation and the

terms of its solicitation, the error was harmless and therefore not prejudicial.

As in Bannum, the probability that G4S would prevail if State recompeted the

procurement is based on “conjecture” and “mere numerical possibility.” See id. Finding that the

plaintiffs were prejudiced requires jumping through multiple theoretical hoops: if the Court

remanded its decision to the agency and the agency decided to recompete the contract and the

agency decided to ask for revised pricing, then it is possible that G4S would win the contract

award. This mere possibility does not meet the bar the Federal Circuit set for prejudice in

Bannum. Although the plaintiffs need not show that State’s violation of FAR 52.204-7 caused

them to lose the contract, they must show a “substantial chance” of award absent agency error.

Not all agency errors are prejudicial, and the plaintiffs have not demonstrated how State’s

unlawful waiver of FAR 52.204-7 impaired their chance to receive the contract award.

In Safeguard Base Operations, LLC v. United States, the Federal Circuit noted that an

offeror’s omissions in its proposal “would have been prejudicial to other bidders unless the same

omissions were waived for them as well.” 989 F.3d 1326, 1347 (Fed. Cir. 2021). The Court

deduces from this quotation that when an agency waives requirements equally for different

offerors, no prejudice results. Because State waived the requirements of FAR 52.204-7 equally

for both CGS-ORSA and G4S (even if State lacked discretion to do so), G4S was not prejudiced.

8

The plaintiffs argue that Tinton Falls Lodging Realty, LLC v. United States, 800 F.3d

1353 (Fed. Cir. 2015), required the award to CGS-ORSA to be vacated and State to recompete

the solicitation because neither offeror was qualified. (ECF 52 at 5.) In Tinton Falls, the Federal

Circuit held that the plaintiff had demonstrated prejudice for the purpose of standing when, if the

plaintiff were to prevail, the agency would need to recompete the solicitation and would likely

need to alter its scope. Tinton Falls, 800 F.3d at 1359-60. The Federal Circuit limited its

discussion to prejudice for standing and its holding to the facts of that case:

We need not determine whether, in all circumstances, a protester can

“compete” for a reopened bid for the purposes of standing . . . when

the protester was not a qualified bidder for the initial bid and would

be a qualified bidder for the reopened bid only if the contract was

solicited with substantially different eligibility requirements. We

hold only that under the particular facts of this case, the Claims

Court did not clearly err in finding that Tinton Falls had a substantial

chance of winning a reopened bid should it prevail in its bid protest.

Id. at 1360 n.3 (emphasis added). The Federal Circuit thus acknowledged that a situation in

which no offerors are allegedly eligible for award in a procurement does not necessarily give rise

to prejudice on standing, let alone prejudice on the merits. Id.

The Federal Circuit recently relied on Tinton Falls in VAS Realty, LLC v. United States,

26 F.4th 945 (2022). In the latter case, the Federal Circuit held that a plaintiff whose proposal

was deemed technically unacceptable nonetheless had standing to protest because, if the plaintiff

prevailed, the government would need to rebid the procurement. The plaintiff had “a substantial

chance of winning the lease for purposes of standing.” Id. at 950 (emphasis added).

Under Tinton Falls and VAS Realty, the plaintiffs demonstrated a substantial chance of

award for the purposes of standing. The Court so found in its initial decision. G4S Secure

Integration, 2022 WL 211023, at *4. That finding does not relieve the plaintiffs from their

separate and distinct burden of demonstrating that State’s failure to enforce FAR 52.204-7 was

prejudicial to G4S on the merits. See Am. Relocation Connections, 789 F. App’x at 228. It was

in failing to show prejudice necessary to prevail on the merits, rather than the prejudice needed

for standing, that the plaintiffs’ claim foundered, and neither Tinton Falls nor VAS Realty speaks

to that issue.

Furthermore, in Tinton Falls and VAS Realty, there was a stronger connection between

the challenged agency error and the plaintiffs’ likelihood of success. The plaintiff in Tinton

Falls challenged the agency’s interpretation of a “small business concern,” and the plaintiff’s

proposal was rejected because it was not a “small business concern” eligible to compete for the

solicitation. 800 F.3d at 1359. The plaintiff in VAS Realty challenged aspects of the awardee’s

proposal allegedly containing errors that the plaintiff did not also make. 26 F.4th at 950. Here,

as noted, the plaintiffs cannot show they were prejudiced by the agency error when that error did

not affect the plaintiffs’ failure to secure the award. Accordingly, the principle in Labatt that

there must be a connection between the procurement error and harm to the plaintiff still stands

and applies here to negate a finding that the plaintiffs were prejudiced.

9

Implicit in the plaintiffs’ argument is the inference that the Court’s decision was

hypocritical: the Court found that State could not waive FAR 52.204-7, but the Court then

effectively waived FAR 52.204-7 by upholding the award of a contract to an ineligible offeror

when the Court should have remanded to the agency for further consideration. This argument

conflates an agency’s discretion to waive informalities with a plaintiff’s burden to prove

prejudice on the merits. An agency can waive minor informalities or irregularities when the

irregularity is one of “‘form and not of substance,’” and the defect is immaterial with respect to

price, quantity, quality, or delivery. Safeguard Base Operations, 989 F.3d at 1347-48 (quoting

FAR 14.405).4 Judges of this court have held that when a requirement “serves a substantive

purpose,” it is material and thus not waivable by the agency. ManTech Advanced Sys. Int’l, Inc.

v. United States, 141 Fed. Cl. 493, 507 (2019).

An agency’s discretion to waive defects is a distinct and separate inquiry from prejudice

on the merits. The Government Accountability Office has repeatedly explained that even when

an agency abuses its discretion in waiving a material term, a plaintiff must show that the

agency’s abuse of discretion was prejudicial.5 As the Federal Circuit has noted, “there is no

presumption of prejudice when a protestor demonstrates irrationality in an agency decision.”

Sys. Stud. & Simulation, Inc. v. United States, 22 F.4th 994, 998 (Fed. Cir. 2021). There is a

fundamental difference between an agency’s discretion to waive defects under the law and the

Court’s review of whether that waiver caused any injury. Once a court determines that the

agency’s action did not prejudice a protester, the court’s role is at an end. Accordingly, the

Court’s decision that State lacked discretion to waive FAR 52.204-7 did not necessitate a remand

to the agency when the plaintiffs did not otherwise demonstrate prejudice.

The plaintiffs rely on cases in which the government was obligated to reopen

procurements for reasons that are not applicable to this case. For example, in Centerra Group,

LLC v. United States, the agency had engaged in a “mockery of fundamental fairness and

competitive principles” by holding improper discussions with one offeror in response to a bid

protest brought by another offeror. 138 Fed. Cl. 407, 417-18 (2018). In Manus Medical, LLC v.

United States, the agency took unlawful “corrective” action by permitting one offeror to correct

4

FAR 14.405 applies only to sealed bids and not to negotiated procurements. Nonetheless,

the solicitation in this case permitted State to waive minor irregularities or informalities.

5

22nd Century Techs., Inc., B-417478.5, 2020 CPD ¶ 153 (Comp. Gen. Apr. 28, 2020)

(“Unfair competitive prejudice from a waiver or relaxation of the terms and conditions of the

RFP for one offeror exists where the protester would have altered its proposal to its competitive

advantage had it been given the opportunity to respond to the altered requirements.”); Glem Gas

S.p.A., B-414179, 2017 CPD ¶ 60 (Comp. Gen. Feb. 23, 2017) (“[C]ompetitive prejudice is an

essential element of a viable protest” to an agency’s discretion to waive compliance with the

solicitation); Lockheed Martin Corp., B-411365.2, 2015 CPD ¶ 294 (Comp. Gen. Aug. 26, 2015)

(“An agency may waive compliance with a material solicitation requirement in awarding a

contract only if the award will meet the agency's actual needs without prejudice to other

offerors.”).

10

its incomplete solicitation. 115 Fed. Cl. 187, 194 (2014). In Ernst & Young, LLP v. United

States, the agency provided an offeror with proprietary nonpublic government information,

giving that competitor a competitive advantage in securing a contract. 136 Fed. Cl. 475, 509

(2018).

State’s error in this case contains no similar tint of bias or unequal treatment. Rather, the

plaintiffs and CGS-ORSA benefited from the same mistake in the same manner. State

overlooked both offerors’ failure to register their joint ventures in SAM at the time they

submitted their offers. This distinction renders the cases on which the plaintiffs rely inapposite.

The cases cited by the plaintiffs do not support the conclusion that State has to recompete the

procurement at issue to remedy the defect here, as State’s error did not jeopardize the integrity of

the procurement.

The plaintiffs also rely on CW Government Travel, Inc. v. United States, in which Judge

Somers explained that “if an agency were obligated to rebid a contract following protest, and the

successful protestor ‘could compete for the contract once again,’ then the protestor has satisfied

the ‘substantial chance’ standard.” 154 Fed. Cl. 721, 747 (2021) (quoting Impresa Construzioni

Geom. Domenico Garufi v. United States, 238 F.3d 1324, 1334 (Fed. Cir. 2001)). In that case,

the agency had not conducted a required price analysis, leaving the court with “‘nothing to

review and no way of determining whether [the plaintiff] was prejudiced.’” Id. (quoting Active

Network, LLC v. United States, 130 Fed. Cl. 421, 429 (2017)); see also Al Ghanim Combined

Grp. Co. Gen. Trad. & Cont. W.L.L. v. United States, 56 Fed. Cl. 502, 516 (2003) (finding

prejudice when the agency failed to engage in a required price analysis).

The facts here are different, and the difference is crucial. The plaintiffs did not allege

that State failed to engage in a required price analysis. Indeed, the plaintiffs lost the procurement

due to the price differential between their offer and the winning offer. The administrative record

in this case was complete and enabled the parties and the Court to conduct a thorough review.

Because of this stark difference, CW Government Travel and Al Ghanim do not support the

conclusion that State must recompete the procurement at issue.

The plaintiffs also argue that two cases upon which the Court relied in its memorandum

opinion are distinguishable. The Court relied on Blue Origin Federation, LLC v. United States,

157 Fed. Cl. 74 (2021), for the proposition that a plaintiff has not shown prejudice when its

proposal would be unawardable without further negotiations. G4S Secure Integration, 2022 WL

211023, at *8-9. The plaintiffs argue that negotiations in Blue Origin would be discretionary,

whereas in this case, they are mandatory because State lacked the discretion to waive FAR

52.204-7. (ECF 52 at 5-6.) The plaintiffs have not demonstrated, however, that State was

required to reopen the procurement when the only two offerors State had deemed eligible had not

registered their joint ventures in SAM. The plaintiffs were not prejudiced when the requirements

of FAR 52.204-7 were waived equally for everyone.

The Court also relied on VS2, LLC v. United States, 155 Fed. Cl. 738, 767-79 (2021), in

which Judge Solomson rejected a plaintiff’s claim when it had committed the same alleged error

in its offer as the awardee had committed. G4S Secure Integration, 2022 WL 211023, at *8-9.

The plaintiffs argue that this case is distinct because other offerors in the procurement at issue in

11

VS2 besides the plaintiff and defendant-intervenor were eligible for award. (ECF 52 at 6-7.) The

rationale in VS2 does not depend on the plaintiffs’ proffered distinction; rather, Judge Solomson

emphasized that the protestor could not complain about a government misinterpretation of the

solicitation when the protestor “relied upon the very same interpretation when preparing its

proposal.” VS2, 155 Fed. Cl. at 768. Like CGS-ORSA, G4S relied on State’s interpreting FAR

52.204-7 to mean that joint ventures themselves did not need to be registered in SAM. The

analogy to VS2 is therefore apt.

Even if the plaintiffs’ argument distinguishing Blue Origin and VS2 is correct, that

argument fails to address the crux of the shortcoming in the plaintiffs’ case, the failure to show

prejudice, as the Federal Circuit’s precedents require for a party to obtain relief.

In sum, the plaintiffs have not met their burden of showing that they are likely to succeed

on the merits because they have not shown prejudice on the merits. The Court still finds that

G4S benefited from State’s misinterpretation of FAR 52.204-7 in the same way that CGS-ORSA

did. Accordingly, State was not required to reopen the competition.

2. Substantial Case on the Merits

A party seeking an injunction pending appeal may prevail without showing that it is

likely to succeed on the merits if it makes a lesser showing that it has a substantial case on the

merits. See, e.g., Telos, 129 Fed. Cl. at 575. A moving party demonstrates that it has a

substantial case on the merits by showing that “the question raised is novel or close,” Acrow

Corp. of America v. United States, 97 Fed. Cl. 182, 184 (2011), or that “‘the plaintiff has raised

questions going to the merits so serious, substantial, difficult and doubtful, as to make them a fair

ground for litigation.’” Standard Havens Prods., 897 F.2d at 513 (quoting Hamilton Watch Co.

v. Benrus Watch Co., 206 F.2d 738, 740 (2d Cir. 1953)).

When delivering the ruling orally to the parties during a status conference before filing

the written opinion, the Court remarked that this case was “a challenging case with a distinctive

and unusual set of facts in a novel, largely unexplored area of the law.” (ECF 54 at 29:24–30:1.)

This case turned on the interpretation of FAR 52.204-7, a regulation of relatively recent vintage,

and its application to joint ventures. The parties and the Court found scant law applying to the

questions raised by this litigation. The only plausible reading of FAR 52.204-7 the Court could

construe seems to close the door to informal joint ventures. (See id. at 34:23–35:14.)

The plaintiffs clarified during oral argument that, although they intend to argue on appeal

that the Court misapplied FAR 52.204-7 to G4S but not to CGS-ORSA, the application of FAR

52.204-7 is not at issue in this motion. In support of this motion, the plaintiffs focus on the

question of whether the Court erred in its decision regarding the absence of prejudice to the

plaintiffs on the merits of their claim. The plaintiffs argue that with both CGS-ORSA and G4S

ineligible under the Court’s interpretation of FAR 52.204-7, State was required to reopen the

procurement, and that the Court erred in affirming the award of the contract to CGS-ORSA, an

ineligible offeror.

12

The questions raised by the plaintiff on this motion are neither novel nor close. As

rehearsed above, the principle is well-settled that to show prejudice on the merits, a party must

show a “greater-than-insignificant chance” of receiving the contract award absent agency error.

Am. Relocation Connections, 789 F. App’x at 228. Courts must “disregard ‘errors or defects

which do not affect the substantial rights of the parties.’” Id. (quoting 28 U.S.C. § 2111). A

plaintiff is not prejudiced by an error when there is no “harm specific to the asserted error,”

Labatt, 577 F.3d at 1381, and when their likelihood of success upon recompetition of the

procurement “rests on mere numerical possibility, not evidence.” Bannum, 404 F.3d at 1358.

Although the underlying issue of the effect of FAR 52.204-7 is novel and its outcome

uncertain, given the well-established standards for finding prejudice to an unsuccessful offeror,

the plaintiffs have not demonstrated that they are raising a substantial and novel question of law.

Accordingly, the plaintiffs have not prevailed on the first factor for an injunction pending appeal.

B. Irreparable Harm

The plaintiffs argue that they will suffer irreparable harm absent injunctive relief,

including the loss of [* * *] jobs performed under the incumbent contract, approximately

$[* * *] million in revenue for each year of performance, and the cost to hire and train new staff

if the plaintiffs succeed on appeal. (ECF 52 at 7.)

The defendant and defendant-intervenor do not dispute that the plaintiffs will lose

employees and revenue absent an injunction, but they argue that those harms are not the type of

irreparable harm warranting an injunction pending appeal.6 (ECF 61 at 5-6; ECF 62 at 11.)

An injunction is inappropriate when “the harms alleged by plaintiff are the sorts of things

that any incumbent would experience upon the loss of a successor contract.” CRAssociates, Inc.

v. United States, 103 Fed. Cl. 23, 26 (2012). “No federal contractor has a right to maintain its

incumbency in perpetuity. It follows, a fortiori, that the potential loss of the benefits of

incumbency does not give plaintiff some sort of automatic right to a stay pending appeal.” Id.

6

The defendant also argues that the fact that the plaintiffs waited 37 days after the filing of

the initial decision before moving for an injunction undercuts their arguments regarding the

harms they will endure in the absence of a stay. (ECF 62 at 11-12); see HVF W. LLC v. United

States, 148 Fed. Cl. 45, 57 (2020); Lawson Env’t Servs., LLC v. United States, 128 Fed. Cl. 14,

19 (2016). The plaintiffs did not immediately file an appeal and move for a stay following the

issuance of the Court’s opinion. Instead, the plaintiffs sought new counsel. The new counsel

then had to be admitted to the protective order and review the administrative record before

deciding whether to file an appeal. The plaintiffs moved with sufficient speed given their change

of counsel. More importantly, they moved for a stay well in advance of the May 31, 2022, end

of the current bridge contract the plaintiffs are performing and State’s estimated notice to

proceed date of June 1, 2022, for the new contract. In these circumstances, the Court finds that

the delay in filing this motion weighs neither for nor against the factor of irreparable harm.

13

More specifically, an incumbent contractor’s loss of employees does not automatically

warrant injunctive relief. In PGBA, LLC v. United States, Judge Lettow noted that although the

loss of employees causes “significant” harm, an incumbent contractor’s “reliance on the loss of

its current employees as a basis for irreparable injury would require this Court to consider any

incumbent contractor’s loss of a successor contract to be irreparable harm.” 60 Fed. Cl. 196,

221, reconsideration denied, 60 Fed. Cl. 567, aff’d, 389 F.3d 1219 (Fed. Cir. 2004).

To the same effect is Akima Intra–Data, in which Judge Firestone declined to find that

the moving party could demonstrate irreparable harm from the loss of significant revenue.

120 Fed. Cl. at 28-29. As Judge Firestone noted, “the loss of a contract cannot serve as the basis

for finding irreparable harm.” Id. at 28. This Court agrees; to hold otherwise would grant an

incumbent contractor that failed to retain the contract the power to freeze the new award in place

just by filing a bid protest and then an appeal if the protest is unsuccessful.

This is not to say that incumbent contractors may never face irreparable harm. For

example, in PDS Consultants, Judge Firestone found irreparable harm when the incumbent

contractor’s loss of its contracts would undermine its mission as a nonprofit to “provide

employment, training, and services to persons who are blind.” 133 Fed. Cl. at 817. Denial of an

injunction would raise no similar concerns in this case.

The harms on which the plaintiffs rely to support their motion for a stay, the loss of

revenue and employees, are no different from the harms that incumbent contractors regularly

confront when they lose a contract. The prospective harms to the plaintiffs are not unusually

distinctive or compelling. Accordingly, the plaintiffs have not demonstrated that they risk

suffering irreparable harm to the point that the Court should grant “extraordinary and drastic”

relief. See Telos, 129 Fed. Cl. at 575.

C. Injury to Other Parties

The plaintiffs argue that the harm to them from denying a stay “greatly outweighs the

harm” to State because G4S, as the incumbent contractor for 11 years, has the capacity to

continue to perform under a bridge contract while the appeal is pending. (ECF 52 at 7-8.) State

“would not suffer any harm if it were enjoined, as it has a capable contractor in place to perform

the local guard force work.” (Id.) State could further avoid the costs of transitioning the contract

from G4S to CGS-ORSA, a transition which State may need to fund and implement twice if the

plaintiffs prevail on appeal. The plaintiffs argue that CGS-ORSA would not be harmed by an

injunction, “as it does not have a right to perform a contract it was not eligible to be awarded.”

(Id.)

The defendant argues that an injunction will substantially injure State and CGS-ORSA.

State and CGS-ORSA initiated a transition of the contract on February 9, 2022, and they “have

expended resources to facilitate an estimated notice to proceed date of June 1, 2022.” (ECF 62 at

12.) The defendant asserts that State will also suffer harm because it organizes local guard force

contracts for competition according to a phased schedule. When contract awards are delayed,

“the carefully phased schedule established by [State] to manage security at installations around

14

the world becomes more difficult to manage.” (Id.) The delay can impair security at U.S.

embassies around the world.

The plaintiffs note that State and CGS-ORSA are still in the early stages of transitioning

the contract, so the harm would be “minimal.” (ECF 66 at 13.) The plaintiffs also argue that

“any administrative inconvenience the Government would suffer is of the Government’s own

making.” (Id.)

The defendant-intervenor argues that State will be harmed by entering a bridge contract

with an offeror it did not select and paying higher prices for those services. (ECF 61 at 6-7.)

The defendant-intervenor has already been deprived of the ability to perform the contract it was

awarded for seven months while the bid protest was pending.

The plaintiffs dispute the defendant-intervenor’s assertion that State will need to pay

higher prices, as State and G4S could negotiate pricing under a bridge contract based on its

incumbent pricing.

Injury to other parties weighs against injunctive relief when the defendant would be

forced into a more expensive contract and the defendant-intervenor would suffer a delay in

performing and profiting from its contract. See Telos, 129 Fed. Cl. at 579; CRAssociates, Inc.,

103 Fed. Cl. at 28; NetCentrics Corp. v. United States, 145 Fed. Cl. 371, 377 (2019).

The defendant and defendant-intervenor have already delayed transitioning the contract

for seven months while this bid protest was pending. The plaintiffs have, in effect, already

benefited for seven months from their protest. By seeking to extend this benefit when they have

not met their burden, the plaintiffs attempt to place the burden of defeating an injunction on the

parties opposing the motion. That is backwards.

The plaintiffs assert that denial of the requested injunction would benefit CGS-ORSA,

which was not qualified for the award it won. That argument proves too much because the

plaintiffs were themselves not qualified for the award. And the plaintiffs’ proposal was rejected

because of its price. This argument cannot bear the weight the plaintiffs put on it.

The plaintiffs emphasize their status as the incumbent and experienced contractor.

Incumbency, however, has never guaranteed a future award of that contract or that the incumbent

could hold the contract in perpetuity. Under the new status quo, following State’s award of the

contract and the Court’s decision upholding the award, CGS-ORSA performs the contract for

security services in Angola. State and CGS-ORSA are already transitioning the contract in

reliance on that regime. The Court refuses to disturb the status quo to the defendant and

defendant-intervenor’s detriment.

The injunction the plaintiffs seek would cause logistical and financial harm to the

defendant and, especially, to the defendant-intervenor, which secured the award by besting the

plaintiffs’ proposed price. The government’s obligation to carry out procurements in compliance

with the FAR is part of its cost of doing business, but that does not change the fact that State

would be harmed by an injunction, even if the harm to State does not outweigh the potential

15

harm to the plaintiffs. The burden is on the plaintiffs, and they have failed to make the necessary

showing.

The harm from an injunction pending appeal to the defendant-intervenor outweighs the

harm to the plaintiffs, as the Court would upend the status quo and exceed its discretion by

essentially favoring the interests of one unqualified offeror over another unqualified offeror.

This factor of injury to other parties thus counsels against an injunction pending appeal.

D. Public Interest

The plaintiffs argue that an injunction would further the public interest by ensuring that

the procurement for security services complied with the FAR. (ECF 52 at 8.) In Heritage of

America, LLC v. United States, a judge of this court explained, “Because the procurement

process at issue in this case did not conform to the requirements of the FAR, it is in the public

interest to take action to redo the flawed procurement and, in doing so, correct the errors that

occurred in the initial procurement process.” 77 Fed. Cl. 66, 80 (2007).

The defendant claims that the public interest would be harmed by an injunction because

of potential harm to State, as described above. (ECF 62 at 12.)

The defendant-intervenor argues that the public interest could best be served “by letting

[State] transition to the lowest cost technically acceptable proposal.” (ECF 61 at 7.)

The public interest in this case does not favor the plaintiffs. A stay pending appeal may

promote compliance with the FAR, but only if the plaintiffs ultimately prevail in their argument

on appeal that their proposal complied with FAR 52.204-7. If the plaintiffs do not prevail, an

injunction would undermine principles of fairness by allowing an ineligible bidder who was not

prejudiced by the procurement the opportunity to remain under contract for services. Because

the Court has found that the plaintiffs are unlikely to prevail on appeal, this factor supports

preserving the status quo. See NetCentrics, 145 Fed. Cl. at 378 (holding that the public interest

was “served by allowing the government to use the more efficient and less expensive contract

while the matter is before the court of appeals”).

The public interest weighs neither in favor of nor against injunctive relief. Because the

plaintiffs bear the burden of demonstrating the appropriateness of an injunction pending appeal,

they have not prevailed on this final factor.

16

IV. CONCLUSION

Under RCFC 62(d), the plaintiffs have not demonstrated that an injunction pending

appeal is appropriate. Because State’s misinterpretation of FAR 52.204-7 did not prejudice the

plaintiffs, they have not shown that they are likely to succeed on the merits or that they have a

substantial case on the merits. In addition, any harm to the plaintiffs that will result from the

absence of an injunction is outweighed by the harm that would result to the defendant and

defendant-intervenor if an injunction were granted.

Accordingly, the Court denies the plaintiffs’ motion for an injunction pending appeal.

The Court will enter an order in accordance with this Memorandum Opinion.

s/ Richard A. Hertling

Richard A. Hertling

Judge

17

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.