Opinion

In re: NTE Connecticut, LLC

  • 26 F.4th 980
Court
Court of Appeals for the D.C. Circuit
Filed
Feb 24, 2022
Status
Published
Cited by
16 cases
Authority
More cited than 72.7%

“[W]e have recognized that financial injury can be irreparable where no adequate compensatory or other corrective relief will be available at a later date, in the ordinary course of litigation.”

How later courts described this case

  • “[W]e have recognized that financial injury can be irreparable where no adequate compensatory or other corrective relief will be available at a later date, in the ordinary course of litigation.”

Written by the judges who cited it.

The opinion

United States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

Decided February 24, 2022

No. 22-1011

IN RE: NTE CONNECTICUT, LLC,

PETITIONER

ISO NEW ENGLAND INC.,

INTERVENOR

On Petition for an Emergency Stay Pursuant to the All Writs

Act

David W. DeBruin, Suedeen G. Kelly, and Zachary B.

Cohen were on the petition and the reply.

Matthew R. Christiansen, General Counsel, Federal

Energy Regulatory Commission, Robert H. Solomon, Solicitor,

Beth G. Pacella, Deputy Solicitor, and Matthew W.S. Estes,

Attorney, were on the response to the petition.

Before: WILKINS, RAO and JACKSON, Circuit Judges.

Opinion for the Court filed by Circuit Judge RAO.

Dissenting opinion filed by Circuit Judge WILKINS.

RAO, Circuit Judge: Petitioner NTE Connecticut, LLC

(“NTE”) acquired valuable authorization to sell electricity

2

from its new power plant. The Federal Energy Regulatory

Commission (“FERC”) revoked that authorization and, in so

doing, very likely fell short of its obligation under the

Administrative Procedure Act (“APA”) to explain the reason

for its decision. See Motor Vehicle Mfrs. Ass’n v. State Farm

Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983). Absent emergency

relief from this court, FERC’s order would have irreparably

harmed NTE, preventing it from participating in a February 7,

2022, auction to sell future electricity capacity to New England

consumers. On February 4, 2022, we granted NTE’s petition

for an emergency stay of FERC’s order, with an opinion to

follow. This is that opinion.

I.

A.

For the past seven years, NTE has been working to build a

new natural gas fueled power plant in Killingly, Connecticut.

In order to sell electricity on the New England grid, NTE had

to work with ISO New England Inc. (“ISO-NE”) to have the

project “qualified.” ISO-NE is the independent system operator

authorized by FERC to manage the regional grid. ISO-NE

oversees annual “forward capacity auctions” at which the

owners of generation facilities bid for the right to sell electricity

on the grid in the future. See NextEra Energy Res., LLC v.

FERC, 898 F.3d 14, 17 (D.C. Cir. 2018) (describing this

process). The right to provide “capacity” (i.e., the ability to

produce electricity), in the quantity and at the price fixed at

auction, is called a facility’s “capacity supply obligation”

(“CSO”). The CSO is tied to a one-year “capacity commitment

period” that begins three years after the auction. In concrete

terms, a generation facility awarded a CSO at the 2022 auction

gains the right to sell electricity for one year beginning June 1,

3

2025. A facility with a CSO is automatically “qualified” to

participate in future ISO-NE auctions.

After locating a suitable parcel of land, designing the

facility, and preparing a timeline for the project’s financing and

construction, NTE applied to have the Killingly plant

“qualified.” ISO-NE approved the application, and in the 2019

auction NTE secured a CSO for the 2022 commitment period.

Under ISO-NE’s rules at the time, a newly qualified facility

was permitted to “lock in” the terms of its initial CSO for six

subsequent capacity commitment periods (i.e., for seven years

total). See ISO New England Inc., 173 FERC ¶ 61,198 at PP 2–

4 (2020). NTE exercised this option, giving it a guaranteed

income stream for the first seven years of the Killingly plant’s

operation, which in turn made it more attractive to potential

investors. NTE thereafter participated in the 2020 and 2021

auctions, securing contract rights to supply electricity for the

2023 and 2024 commitment periods.

Initially, NTE had planned for the Killingly facility to

come online in early 2022. But soon after securing its first CSO

in 2019, NTE encountered a series of setbacks that prevented

it from meeting its financing and construction goals. First, just

after the 2019 auction, incumbent energy generators in New

England asked FERC to review ISO-NE’s qualification of the

Killingly plant, placing NTE’s CSO in jeopardy. FERC

eventually upheld NTE’s rights, but the results of the 2019

auction did not become final until September 2019. Second,

while the incumbent competitors’ challenge was pending

before FERC, several environmental groups sued in state court

to block the Connecticut Siting Council’s decision to approve

the Killingly plant. One of them, a nonprofit called Not

Another Power Plant, appealed the case to the Connecticut

Supreme Court, which did not issue a decision in NTE’s favor

until September 2021—some thirty-one months after the 2019

4

auction. See Not Another Power Plant v. Conn. Siting Council,

265 A.3d 900 (Conn. 2021). In the interim, NTE had located a

potential investor for the Killingly plant. But because the

project’s viability depended on a favorable legal ruling, NTE

was unable to finalize financing while the case was under

review. Third, the arrival of the COVID-19 pandemic in early

2020 caused further complications. Disruptions to supply

chains and labor markets required NTE and its potential

investor to frequently recalculate the project’s shifting costs,

while pandemic related delays slowed NTE’s ability to secure

necessary construction permits. Because of these obstacles,

NTE was repeatedly forced to revise its timeline for the

Killingly plant’s construction.

If the Killingly plant was not operational by May 31, 2024,

ISO-NE had the right to request that FERC terminate NTE’s

existing CSO, disqualifying it from participating in future

auctions. ISO-NE Tariff § III.13.3.4A.1 By September 2021,

ISO-NE was concerned that NTE was running out of time to

meet that deadline. As revised, NTE’s timetable required it to

finalize equity financing for the Killingly plant in mid-January

2022, to finalize debt financing in early March 2022, and to

begin commercial operation of the plant on May 31, 2024. NTE

also planned to issue full notices to proceed to its contractors

by January 1, 2022, before financing was finalized.

ISO-NE hired a consultant to assess whether these plans

were feasible. After reviewing NTE’s timeline and conferring

with the parties, the consultant concluded that if NTE issued

full notices to proceed by January 1, 2022, “commercial

1

“[I]f, as a result of milestone date revisions, the date by which a

resource will have achieved [operations] is more than two years after

the beginning of the Capacity Commitment Period for which the

resource first received a [CSO],” ISO-NE may request that FERC

terminate the resource’s CSO. ISO-NE Tariff § III.13.3.4A.

5

operation of [the Killingly plant] could occur on or about the

stated proposed commercial operation date of May 31, 2024.”

Issuing full notices on January 1, 2022, would give NTE

twenty-nine months to build the Killingly facility—“an

aggressive, but achievable schedule for a project of this scope.”

However, according to the consultant, full notices to proceed

typically cannot be issued before financing is secured. NTE’s

“assumption” that it would be able to issue full notices by

January 1, 2022, was therefore “unlikely.” Under a more

“realistic scenario,” the consultant concluded, NTE would be

able to issue full notices only after securing financing in mid-

January, resulting in a “likely commercial operation date”

beyond the deadline of May 31, 2024.

On November 4, 2021, shortly after receiving the

consultant’s report, ISO-NE met with NTE to review its plans

for the Killingly plant. At the meeting, NTE told ISO-NE that

it remained confident it could complete construction on time.

It also produced a letter from its equity investor, indicating that

the investor would soon be ready to issue full notices to

proceed to major contractors and that those notices did not

depend on finalizing the project’s financing details with NTE.

B.

Later that same day, ISO-NE asked FERC to terminate the

Killingly plant’s CSO. Such a termination would have voided

NTE’s rights to collect revenues for the 2022, 2023, and 2024

commitment periods. It would also have made NTE ineligible

to participate in the 2022 capacity auction, depriving NTE of

the “locked in” CSO for the 2025 commitment period.

ISO-NE claimed that because of NTE’s timeline changes,

the Killingly facility would not achieve commercial operation

by the May 31, 2024, deadline. In support of this claim, ISO-

NE provided FERC with NTE’s most recent construction

6

timeline, ISO-NE’s consultant’s report, and the letter from

NTE’s equity investor. NTE’s timeline, ISO-NE observed,

“indicates that NTE will issue full notices to proceed on

January 1, 2022[,] … [which] assumes that those notices can

be issued without financing in place”—an assumption that

ISO-NE, relying on its consultant, rejected. Because “it is

unlikely that these notices to proceed will be executed without

financing in place,” ISO-NE argued, NTE “will be unable to

achieve commercial operation of Killingly” by the deadline.

In response, NTE explained that the assumption on which

ISO-NE and its consultant relied—that NTE would not be able

to issue full notices to proceed until its equity financing was in

place in mid-January—was erroneous. At the time of ISO-NE’s

filing, NTE’s investor had expected to approve the transaction

in December 2021 and was willing to issue full notices to

contractors before financing was finalized, allowing NTE to

meet the January 1, 2022, target. ISO-NE had failed to

recognize, in other words, that NTE’s project had a unique

financing structure. NTE provided FERC with a declaration

from the Killingly plant’s lead developer, explaining that NTE

and its investor had agreed to issue full notices before financing

closed and that the parties had been on track to do so by January

1, 2022. NTE also submitted a declaration from the project’s

lead contractor, indicating that if full notices to proceed had

been issued on schedule, “it would have been feasible to

complete the project by May 31, 2024.” NTE further argued

that ISO-NE had not “met its burden … to show that Killingly

will not enter service by June 1, 2024,” but had “only

speculate[d] that Killingly will not meet the … deadline, which

is not the objective standard required by the Tariff.” ISO New

England Inc., 178 FERC ¶ 61,001 at P 19 (2022) (describing

NTE’s argument).

7

On January 3, 2022, FERC issued an order terminating

Killingly’s CSO, which stripped NTE of its existing right to

provide electricity generation capacity for the 2022, 2023, and

2024 commitment periods, and which barred it from

participating in the 2022 auction—effectively nullifying

NTE’s vested right to generation revenues for the 2025

commitment period. See id. P 23. After recounting some of the

parties’ arguments, FERC concluded that, “[b]ased on a review

of the record, including the confidential information provided

by ISO-NE and NTE, … the relevant condition for termination

set forth in [ISO-NE’s] Tariff … has been met.” Id. P 25.

FERC’s only reason for this conclusion was that it was

“persuaded by the evidence provided by ISO-NE that, the

milestone date revisions indicate that Killingly will not have

achieved … commercial operation[] until after June 1, 2024.”

Id. P 26. In a footnote, FERC asserted that “[b]ecause much of

the pertinent information has been filed on a non-public basis,

this public order cannot go into detail regarding the specifics of

the triggering event or the basis for ISO-NE’s judgment that

Killingly will not be able to achieve … commercial operations

by June 1, 2024 as required by the tariff. Our review of these

non-public materials, however, satisfies us that this is the case.”

Id. P 26 n.39.

NTE filed a combined emergency motion for a stay and

application for rehearing before FERC on January 10, 2022.

NTE argued that it would be irreparably injured without a stay

of FERC’s termination order: it would lose its right to future

revenues under Killingly’s existing CSO and would be

ineligible to participate in the upcoming 2022 auction.

Together, it alleged, these penalties would effectively kill the

project. FERC denied NTE’s motion for a stay on January 28,

2022. See ISO New England Inc., 178 FERC ¶ 61,063 (2022).

FERC reasoned that, because “economic loss does not

constitute irreparable harm,” the “[l]oss of potential capacity

8

market revenues … [was] insufficient” to warrant a stay. Id.

PP 14, 16. It further found that NTE’s assertion that its order

had “effectively killed” the Killingly project was too

speculative to support a finding of irreparable harm. Id. PP 5,

16. FERC did not respond to NTE’s request for rehearing and

had not done so at the time of our decision in this case.

NTE filed a petition for emergency relief in this court,

asking us to stay FERC’s order until thirty days after FERC

addresses NTE’s application for rehearing. It requested that we

decide its petition in time for NTE to participate in the 2022

auction, to be held on February 7, 2022. For the reasons

outlined below, we granted that petition on February 4.

II.

The All Writs Act gives this court the power to “issue all

writs necessary or appropriate in aid of [its] … jurisdiction[].”

28 U.S.C. § 1651(a). In an ordinary FERC case, we have

jurisdiction only after the agency issues a final order on

rehearing, see 16 U.S.C. § 825l(b), or after thirty days have

lapsed from a party’s application for rehearing, see id.

§ 825l(a). But this court has an “inherent” power under the All

Writs Act to stay agency action in order to preserve its

prospective jurisdiction. See Nken v. Holder, 556 U.S. 418, 427

(2009) (explaining that this authority is “firmly imbedded in

our judicial system, consonant with the historic procedures of

federal appellate courts, and a power as old as the judicial

system of the nation”) (cleaned up); see also Reynolds Metals

Co. v. FERC, 777 F.2d 760, 762 (D.C. Cir. 1985).

At the time NTE petitioned this court for relief, FERC had

not acted on NTE’s application for rehearing, nor had the

requisite thirty days lapsed since NTE’s application for

rehearing. All parties agreed, therefore, that we could not stay

FERC’s order under the Federal Power Act’s ordinary

9

provisions for judicial review. At the time we granted NTE’s

request for a stay, however, our prospective jurisdiction was

certain: if FERC did not publish a rehearing order addressing

NTE’s objections, we would have jurisdiction after thirty days

to review a petition from NTE. We therefore had the authority

to consider NTE’s petition for emergency relief. See Am. Pub.

Gas Ass’n v. Fed’l Power Comm’n, 543 F.2d 356, 357–58

(D.C. Cir. 1976) (per curiam) (“[T]he authority of the appellate

court is not confined to the issuance of writs in aid of a

jurisdiction already acquired by appeal but extends to those

cases which are within its appellate jurisdiction although no

appeal has been perfected.”) (cleaned up).

“[R]elief under the All Writs Act is an extraordinary

remedy that may be invoked only if the statutorily prescribed

remedy is clearly inadequate.” Reynolds, 777 F.2d at 762

(cleaned up). When an agency’s order is “not yet final, [such

that] no direct appeal from it yet [lies], and a stay pending

appeal [is] not available to prevent irreparable injury,” the

aggrieved party lacks an adequate statutory remedy. Id. NTE

and FERC agreed that, absent relief from this court, NTE

would have been unable to participate in the 2022 capacity

auction. NTE alleged that such a result would have led to an

irreparable injury: its Killingly plant would have been deprived

of a CSO for the 2025 commitment period that is worth

“millions of dollars” and that could not be recovered after the

auction. Further, because FERC had not acted on NTE’s

application for rehearing before the February 7 auction, NTE

was precluded from petitioning for direct judicial review of the

order or a judicial stay pending such review. NTE therefore

satisfied the “preliminary condition distinctive to All Writs

relief.” Id.

Accordingly, we must next decide whether NTE has

satisfied the “well established requirements that we routinely

10

apply to motions for stay pending appeal.” Id. We must

consider “(1) whether the stay applicant has made a strong

showing that [it] is likely to succeed on the merits; (2) whether

the applicant will be irreparably injured absent a stay; (3)

whether issuance of the stay will substantially injure the other

parties interested in the proceeding; and (4) where the public

interest lies.” Nken, 556 U.S. at 434 (cleaned up).2

A.

We begin with NTE’s likelihood of success on the merits.

NTE alleged that the termination order was arbitrary and

capricious because FERC did not explain why it adopted ISO-

NE’s argument for termination and ignored NTE’s arguments

to the contrary. FERC’s orders will be “set aside” if they are

“arbitrary [or] capricious.” 5 U.S.C. § 706(2)(A); see United

Airlines, Inc. v. FERC, 827 F.3d 122, 127 (D.C. Cir. 2016).

While FERC’s order need not be “a model of analytic precision

to survive a challenge,” Dickson v. Sec’y of Def., 68 F.3d 1396,

1404 (D.C. Cir. 1995), it must be “reasonable and reasonably

2

This court has characterized various requests for relief under the

All Writs Act as petitions for mandamus, and our order granting

NTE’s petition reflected that practice. Strictly speaking, however,

NTE has not asked for a writ of mandamus—it does not ask us to

compel FERC to take some action—but for a stay of FERC’s order

to preserve the status quo. See Nken, 556 U.S. at 426–27

(distinguishing a stay pending further agency review from an

affirmative order to the Executive Branch to act). As explained

above, when a party requests a stay under the All Writs Act and “the

statutorily prescribed remedy is clearly inadequate,” we evaluate the

petition for relief like an ordinary application for a stay. Reynolds,

777 F.2d at 762 (cleaned up). To avoid confusion, with the

publication of this opinion we also revise the February 4 order to

remove the reference to mandamus and to clarify that we granted an

emergency petition for a stay pursuant to the All Writs Act.

11

explained,” Nw. Corp. v. FERC, 884 F.3d 1176, 1179 (D.C.

Cir. 2018). Because FERC’s termination order almost certainly

fell short of these requirements, NTE had a substantial

likelihood of success on the merits.

First, FERC’s order did not provide a “reasoned

explanation” of the decision to terminate Killingly’s CSO.

FCC v. Fox Television Stations, Inc., 556 U.S. 502, 516 (2009).

Indeed, FERC hardly provided any reason at all. Its termination

order simply summarized some of the parties’ arguments in

broad strokes and then announced, without elaboration, that

FERC was “persuaded by the evidence provided by ISO-NE

that … Killingly will not [become operable] until after June 1,

2024.” ISO New England, 178 FERC ¶ 61,001 at P 26. The

order gives no explanation of why FERC found ISO-NE’s

evidence persuasive. FERC was entitled to reach that

conclusion (if the record supported it, of course, see 5 U.S.C.

§ 706(2)(E)). But it could not simply rubberstamp ISO-NE’s

analysis, especially since ISO-NE bore the burden below. As

we held in a similar case, an agency’s “unquestioning reliance”

on a third party’s “defense of its own actions is not enough” to

survive an arbitrary and capricious challenge. Susquehanna

Int’l Grp., LLP v. SEC, 866 F.3d 442, 447 (D.C. Cir. 2017)

(considering agency reliance on a self-regulatory

organization). An agency must either “critically review[]” the

third party’s analysis or “perform[] its own.” Id. Here, FERC

did neither.

In place of such reasons, FERC cryptically asserted that it

could not explain its decision because “much of the pertinent

information [was] filed on a non-public basis.” ISO New

England, 178 FERC ¶ 61,001 at P 26 n.39. In the first instance,

it is unclear why, if confidentiality concerns prevented FERC

from publishing a more complete analysis, it could not simply

redact its order before public release, as federal courts routinely

12

do, and as FERC has done in the past. See, e.g., White Cliffs

Pipeline, LLC, 168 FERC ¶ 63,033 (2019), aff’d, 173 FERC

¶ 61,155 (2020). More fundamentally, we reject the premise

that if a matter implicates confidential information an agency

is somehow absolved of its responsibility to explain its

decision. It is “inherent in the doctrine of judicial review” that

an agency must “articulate with clarity and precision its

findings and the reasons for its decisions.” WAIT Radio v. FCC,

418 F.2d 1153, 1156 (D.C. Cir. 1969). We see no reason here

to depart from the bedrock principle that, “in all cases, the

Commission must explain its reasoning.” Emera Me. v. FERC,

854 F.3d 9, 23 (D.C. Cir. 2017) (cleaned up). The APA does

not contain a confidentiality loophole.

Nor did FERC acknowledge, let alone reasonably reject,

NTE’s central argument against termination—namely, that its

plan to issue full notices to proceed by January 1, 2022, was

viable, and that ISO-NE’s assertion to the contrary was

unsupported by the record. ISO-NE’s argument for termination

was expressly predicated on the very assumption that NTE

contested. Moreover, NTE submitted additional evidence to

FERC supporting the viability of its construction timeline and

explaining its project’s unique financing structure, which

allowed full notices to be issued before the financing was

finalized. Again, FERC was entitled to conclude that NTE’s

evidence was unpersuasive or that its timeline was unfeasible

for other reasons. But it could not simply ignore NTE’s central

objection to ISO-NE’s analysis.3 “An agency’s failure to

3

The dissent faults NTE for submitting new evidence to FERC that

was not previously considered by ISO-NE. But there is no dispute

that the evidence was properly before FERC. The fact that evidence

on a key point of dispute was previously unaddressed by ISO-NE

only accentuates FERC’s obligation to provide independent analysis.

The dissent denigrates NTE’s submissions as “eleventh hour, self-

13

respond meaningfully to objections raised by a party renders its

decision arbitrary and capricious. We have stressed that unless

the agency answers objections that on their face seem

legitimate, its decision can hardly be classified as

reasoned.” PPL Wallingford Energy LLC v. FERC, 419 F.3d

1194, 1198 (D.C. Cir. 2005) (cleaned up). FERC’s failure to

address NTE’s facially legitimate arguments was especially

concerning given that its decision upended the status quo ante,

threatening to deprive NTE of “millions of dollars” of future

revenues to which it had been entitled.

Second, FERC failed to articulate a discernable legal

standard under ISO-NE’s Tariff to govern the termination of

NTE’s valuable right to a CSO for the 2025 commitment

period. As the party moving to terminate the CSO, ISO-NE

bore the burden of showing why the Tariff’s conditions for

termination were met. See 5 U.S.C. § 556(d) (“Except as

otherwise provided by statute, the proponent of a rule or order

has the burden of proof.”); cf. Ala. Power Co. v. FERC, 993

F.2d 1557, 1571 (D.C. Cir. 1993) (“[T]he party filing a rate

serving, uncorroborated hearsay.” Even if the dissent’s criticisms

were fair, FERC did not make them but merely ignored NTE’s

submissions. And although we are permitted and indeed required to

look at the administrative record when evaluating APA challenges,

that does not excuse FERC from its duty to explain the reasons for

its actions. Nor does it justify this court making what are effectively

de novo evidentiary determinations about the credibility or weight of

the evidence. See, e.g., Phoenix Herpetological Soc’y, Inc. v. U.S.

Fish & Wildlife Serv., 998 F.3d 999, 1006 n.14 (D.C. Cir. 2021)

(“We hesitate … to endorse the district court’s rejection of the …

affidavit as ‘uncorroborated hearsay,’ particularly since the agency

did not offer this rationale during the adjudication.”).

We further note that FERC has not been ambushed by

arguments it did not have a chance to consider. The agency had

weeks to respond to NTE’s application for rehearing, which raised

the same arguments considered by the court in granting this stay.

14

adjustment with the Commission under [Section] 205 bears the

burden of proving the adjustment is lawful.”). In addition, ISO-

NE bore the burden of showing that termination of NTE’s CSO

was “just and reasonable.” 16 U.S.C. § 824d(a), (e); see, e.g.,

ISO New England Inc., 165 FERC ¶ 61,137 at P 31 (2018).

The Tariff, however, does not explicitly state the standard

that ISO-NE must satisfy to justify termination. The Tariff

permits ISO-NE to request termination “if, as a result of

milestone date revisions, the date by which a resource will have

achieved [commercial operation] is more than two years after

the beginning of [its first] Capacity Commitment Period.” ISO-

NE Tariff § III.13.3.4A (emphasis added). Under these terms,

must ISO-NE show that, “as a result of milestone date

revisions,” it will be impossible for NTE to meet its deadline?

Do the new milestone dates have to make timely completion

unlikely? Is there some other standard? FERC’s failure to

identify the burden that ISO-NE was required to carry further

supports the conclusion that FERC did not adequately explain

why it was satisfied in this case.

ISO-NE’s consultant found that NTE’s construction

timeline was “aggressive, but achievable.” In other words, if

NTE had issued full notices to proceed by January 1, 2022,

commercial operation of the plant by May 1, 2024, was at least

possible. FERC’s laconic order gives no indication of how

ISO-NE could meet its burden under the Tariff given the

consultant’s finding. Perhaps FERC simply did not believe

NTE would meet its own deadlines, but even if FERC relied on

that credibility finding, it needed to explain its conclusion. The

Tariff does not expressly give ISO-NE the right to terminate a

CSO simply because it believes the facility’s developer will not

meet its otherwise acceptable milestone dates. Rather, the CSO

is a valuable allocation of rights to provide electricity, and ISO-

NE must request that FERC terminate it. FERC, in turn, must

15

comply with the APA’s rationality requirements and find the

termination of such rights “just and reasonable.”

Were this order before us on direct review, we would very

likely find it unreasoned, and therefore unlawful. Indeed,

FERC concedes that it provided an “admittedly limited

explanation in the Termination Order.” Without further

explanation, we had no reason to believe that FERC reasonably

exercised its discretion. We therefore found that NTE is almost

certain to succeed in its challenge to FERC’s termination order.

B.

We next consider whether NTE faced irreparable harm in

the absence of a stay. Nken, 556 U.S. at 434. As a result of

FERC’s termination order, NTE would have been ineligible to

participate in the 2022 capacity auction. But before FERC

issued its order, NTE was guaranteed to secure a CSO at the

2022 auction, entitling it to provide the same amount of

capacity, at the same price, that it secured in the 2019 auction.

This future revenue stream is worth “millions of dollars,” and

FERC does not dispute that it is significant.

Ordinarily, “economic loss does not, in and of itself,

constitute irreparable harm.” Wis. Gas Co. v. FERC, 758 F.2d

669, 674 (D.C. Cir. 1985) (per curiam). That is because in most

circumstances financial harms can be remedied through

subsequent legal action. See id. Nonetheless, we have

recognized that “financial injury [can be] irreparable where no

‘adequate compensatory or other corrective relief will be

available at a later date, in the ordinary course of

litigation.’” Mexichem Specialty Resins, Inc. v. EPA, 787 F.3d

544, 555 (D.C. Cir. 2015) (quoting Wis. Gas Co., 758 F.2d at

674).

16

This is such a case. If NTE had been barred from the 2022

auction, the capacity rights to which it was formerly entitled

would have been allocated to other generators on the New

England grid. Given the reliance interests involved, FERC does

not generally direct entities like ISO-NE to vacate the results

of earlier auctions and rerun them to include new entrants. See

PJM Interconnection, LLC, 161 FERC ¶ 61,252 at P 55 (2017)

(“The Commission generally does not order a remedy that

requires rerunning a market [auction] because market

participants … expect[] that the rules in place and the outcomes

will not change after the results are set.”). If NTE had been

excluded from the auction and FERC’s order were later found

to be unlawful, the capacity that NTE would have received at

the 2022 auction could not later be clawed back. Without the

capacity allocation, it is unlikely that NTE would have had a

claim to lost revenue streams. FERC has made no

representation to the contrary, and we are aware of no other

mechanism through which NTE could have recovered these

losses.

The circumstances and timing here are unusual because, in

order to realize its vested contractual rights, NTE had to take

part in a regulatory auction with other participants. Absent

emergency relief, FERC’s termination order would have

irreparably and permanently stripped NTE of very significant

future revenues to which it was entitled before FERC issued its

(likely unlawful) order.

C.

Next we consider “whether issuance of the stay will

substantially injure the other parties interested in the

proceeding” and balance the equities. Nken, 556 U.S. at 434

(cleaned up). As explained above, our emergency stay

permitted NTE to participate in the 2022 ISO-NE auction and

17

to acquire a CSO for the Killingly plant for the 2025

commitment period. The stay also paused FERC’s termination

of NTE’s already acquired CSO for the commitment periods

running from June 1, 2022, to May 31, 2025.

FERC pointed to possible third-party harms that may

befall incumbent electricity generators. Specifically, it asserts

that NTE’s participation in the 2022 auction would provide

additional energy supply in the region, driving down electricity

costs on the New England grid in the 2025 commitment period.

Because of our stay, incumbent generators would accordingly

be paid less for the electricity they generate and would be able

to sell less overall capacity. Such third-party harm, however,

will be short-lived if FERC’s order is sustained in the future,

because the capacity NTE secured at the 2022 auction can be

reallocated among existing facilities through a

“reconfiguration auction.” FERC does not contest the

feasibility of such a limited reauction.

Finally, we must decide “where the public interest lies.”

Id. NTE’s participation in the 2022 auction was expected to

lower energy costs for New England consumers by generating

more supply and competition in the electricity market. One

goal of a forward capacity auction is to “incentivize and

account for new entry by more efficient generators, while

ensuring a price both adequate to support reliability and fair to

consumers.” NextEra, 898 F.3d at 20 (cleaned up). Our

temporary stay pending agency rehearing simply ensured that

FERC did not impose unrecoverable losses of millions of

dollars and potentially jeopardize a new facility without

fulfilling the basic requirements of reasoned explanation.

FERC protested that to permit NTE to participate in the

2022 auction, even though the Killingly facility will not be able

to provide electricity in the relevant commitment period, would

18

distort market competition and “undermine the basic

functioning of [ISO-NE’s] capacity market, including its

ability to send accurate price signals to guide entry and exit.”

As the facts here demonstrate, however, entry and exit into the

electricity market hardly moves at a rapid pace. And entities

like ISO-NE regularly reallocate capacity if a facility is unable

to fulfill its commitments, allowing for a correction of any

market distortion. More to the point, nothing in FERC’s

reasoning suggests the risk that incumbents may have to

reallocate electricity capacity amongst themselves outweighs

the harm of delaying NTE’s years-long electricity

infrastructure project that could benefit consumers in the region

through more efficient (i.e., less expensive) electricity.

***

For the foregoing reasons, we granted NTE’s petition to

stay FERC’s termination order until thirty days after FERC

resolves the pending application for agency rehearing.

WILKINS, Circuit Judge, dissenting: Because I believe that

the petition for relief should have been denied, I dissent.

To demonstrate entitlement to relief, the first and foremost

consideration is “‘whether the stay applicant has made a strong

showing that he is likely to succeed on the merits[.]’” Nken v.

Holder, 556 U.S. 418, 434 (2009) (emphasis added) (quoting

Hilton v. Braunskill, 481 U.S. 770, 776 (1987)). In addition,

we must consider whether NTE has shown that it will suffer

irreparable harm absent a stay, whether a stay will substantially

injure other parties and whether a stay is in the public interest.

Nken, 556 U.S. at 434. The public interest and balance of

equities factors merge when, as here, the government is the

opposing party. Id. at 435. In my view, NTE failed to meet its

burden of making a “strong showing” that it is likely to succeed

on the merits, which in turn undermines its showing that the

public interest and balance of equities support a stay. See

Hilton, 481 U.S. at 776; cf. Shawnee Tribe v. Mnuchin, 984

F.3d 94, 102 (D.C. Cir. 2021) (“A party’s likelihood of success

on the merits ‘is a strong indicator that a preliminary injunction

would serve the public interest’ because ‘[t]here is generally no

public interest in the perpetuation of unlawful agency action.’”)

(quoting League of Women Voters of United States v. Newby,

838 F.3d 1, 12 (D.C. Cir. 2016)).

Prior to the agency action under review, NTE had delayed

the date for Killingly’s financing milestone fourteen times,

resulting in multiple delays of the expected commercial

operating date of the power plant. In January of 2021, FERC

warned NTE that ISO-NE had a duty under the Tariff “to

monitor Killingly’s critical path schedule,” and that further

delays in financing milestones could result in ISO-NE

exercising its right to seek termination of NTE’s CSO. ISO

New England, Inc., 174 FERC ¶ 61,046 P 40 & n.63 (2021).

As FERC explained, the Tariff permits ISO-NE to seek

termination of NTE’s CSO if, as a result of milestone date

revisions, “the date by which [NTE] will achieve all critical

2

path schedule milestones is more than two years after the

beginning of the first Capacity Commitment Period for which

it acquired a CSO.” Id. at n.63.

Because NTE’s subsequent reports indicated further

financing delays, ISO-NE hired an expert consultant “to assist

in reviewing Killingly’s critical path schedule.” ISO-NE Term.

Filing 6. The consultant’s report was not favorable for NTE.

As ISO-NE explained, “[the consultant’s] review supports that

the date by which Killingly will achieve all its critical path

schedule milestones is more than two years after the beginning

of the Capacity Commitment Period for which Killingly first

received a CSO.” Id. ISO-NE therefore asked FERC to accept

its request to terminate NTE’s CSO.

FERC accepted ISO-NE’s termination filing. FERC

explained that it agreed with ISO-NE’s assessment of the

evidence:

We are persuaded by the evidence provided by

ISO-NE that, the milestone date revisions

indicate that Killingly will not have achieved all

of its critical path schedule milestones,

including commercial operation, until after June

1, 2024, i.e., more than two years after June 1,

2022—the beginning of the 2022-2023

Capacity Commitment Period.

ISO New England, Inc., 178 FERC ¶ 61,001 P 26 (2022). As

FERC explained, the consultant’s report, which is in the record,

supported ISO-NE’s conclusion. Id. at PP 25–26.

FERC’s explanation was sufficient. “Our only task is to

determine whether the Commission has considered the relevant

factors and articulated a rational connection between the facts

3

found and the choice made.” Baltimore Gas & Elec. Co. v.

Nat. Res. Def. Council, Inc., 462 U.S. 87, 105 (1983). This is

a “‘narrow’ standard of review[.]” FCC v. Fox Television

Stations, Inc., 556 U.S. 502, 513 (2009) (quoting Motor

Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S.

29, 43 (1983)). The instances where we have set aside agency

action for insufficient explanation are where the explanation

was “neither logical nor rational,” “[in]coherent,”

“incomprehensible,” or where the agency completely failed to

explain inconsistencies with the governing statute, its prior

precedent, or the evidence. NBCUniversal Media, LLC v.

NLRB, 815 F.3d 821, 823 (D.C. Cir. 2016); see CSI Aviation

Servs., Inc. v. U.S. Dep’t of Transp., 637 F.3d 408, 416 (D.C.

Cir. 2011).

None of those circumstances are present here. NTE does

not seriously contend that the expert consultant’s report did not

constitute substantial evidence to support FERC’s Order, nor

could it. The best argument that NTE can muster is that FERC

did not set forth in detail why it accepted the consultant’s report

over NTE’s interpretation of the evidence. But that argument

hardly presents a “strong showing” of success. See Hilton, 481

U.S. at 776. First, the FERC Order explained the competing

arguments made by NTE and ISO-NE in some detail, 178

FERC ¶ 61,001 at PP 12–19, so there is no question here that

FERC considered NTE's arguments and all the record

evidence. Furthermore, FERC’s Order need not be “a model

of analytic precision to survive a challenge,” Dickson v. Sec’y

of Def., 68 F.3d 1396, 1404 (D.C. Cir. 1995), and we may

“uphold a decision of less than ideal clarity if the agency’s path

may reasonably be discerned.” State Farm, 463 U.S. at 43

(citations and internal quotation marks omitted).

FERC’s reasoning is discernible because FERC explained

that it agreed with ISO-NE’s analysis of the

4

evidence. Furthermore, we can look at the reasoning appearing

in the text of the ISO-NE Order to help us discern FERC’s

path. See Citizens to Preserve Overton Park, Inc. v. Volpe, 401

U.S. 402, 420 (1971) (directing the lower court to examine the

record that was before the agency at the time of decision to

determine whether it “disclose[d] the factors that were

considered”); Tourus Recs., Inc. v. Drug Enf’t Admin., 259

F.3d 731, 738 (D.C. Cir. 2001) (considering contemporaneous

agenda memoranda in the record because they illuminate the

“agency’s decisionmaking rationale”). ISO-NE rejected

NTE’s reliance on a November 4, 2021 letter from its equity

investor, because the letter said that full notices to proceed with

construction would not issue until financing was approved by

the investor’s board of directors, but the letter did not specify a

date by which such board approval was expected to occur. ISO-

NE Term. Filing 7 & n.19. NTE later proffered a declaration

stating that “[i]n conversations with NTE, [the equity investor]

specified that it expected to obtain Board approval and to issue

Final Notices [to proceed] in December[.]” NTE Pet. Attach.

B ¶ 15. But NTE did not provide this declaration to ISO-NE

before ISO-NE decided to terminate Killingly’s capacity

supply obligation, nor did NTE provide FERC any

corroborating evidence from the equity investor.

As the majority concedes, NTE proffered a “unique”

financing structure where NTE claimed it could fully proceed

with construction prior to having funds in hand. ISO-NE’s

expert consultant explained, and FERC credited, that “on most

projects,” a full notice to proceed does not issue until “after

financing has closed with the lending institutions that are

providing the funds, often on the same day and part of the

closing proceedings.” NTE Pet. Attach. F at 3. It stands to

reason that on a project costing hundreds of millions of dollars,

contractors would require proof of financing and the actual

payment of deposits prior to starting work and ordering

5

equipment, rather than promises that financing and funds will

be forthcoming soon. FERC acted well within its discretion to

find it was “persuaded by the evidence provided by ISO-NE,”

178 FERC ¶ 61,001 at P 26, and to reject NTE’s eleventh-hour,

self-serving uncorroborated hearsay that construction would

proceed in a manner contrary to ordinary industry practice. See

Phoenix Herpetological Soc’y, Inc. v. United States Fish &

Wildlife Serv., 998 F.3d 999, 1006 (D.C. Cir. 2021).

When rejecting a similar challenge to FERC’s predecessor

many decades ago, the Supreme Court observed:

The findings of the Commission in this regard

leave much to be desired since they are quite

summary and incorporate by reference the

Commission’s staff’s exhibits on allocation of

cost. But the path which it followed can be

discerned. And we do not believe its findings

are so vague and obscure as to make the judicial

review contemplated by the Act a perfunctory

process.

Colorado Interstate Gas Co. v. Fed. Power Comm’n, 324 U.S.

581, 595 (1945). The Court’s reasoning has been followed in

State Farm, FCC v. Fox Television Stations, and countless

times since. We are duty bound to follow it here. I respectfully

dissent.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.