Opinion

D-STAR Engineering Corporation

Court
Armed Services Board of Contract Appeals
Filed
Oct 14, 2021
Status
Published
On the bench
Witwer
Cited by
0 cases
Authority
More cited than 21.8%

finding that penalties assessed under 31 U.S.C. § 3717, unlike interest and administrative costs assessed under the same section, are “imposed as a punitive measure for late payment”

How later courts described this case

  • finding that penalties assessed under 31 U.S.C. § 3717, unlike interest and administrative costs assessed under the same section, are “imposed as a punitive measure for late payment”
  • “The United States has not waived sovereign immunity with regard to punitive damages.”
  • acknowledging “the long-held principle that pleadings drafted by pro se litigants are generally held to ‘less stringent standards’ than pleadings filed by trained attorneys” (quoting Haines v. Kerner, 404 U.S. 519, 520-21 (1972))

Written by the judges who cited it.

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - )

)

D-STAR Engineering Corporation ) ASBCA Nos. 62075, 62780

)

Under Contract No. FA8650-12-C-7243 )

APPEARANCE FOR THE APPELLANT: Mr. S. Paul Dev

President

APPEARANCES FOR THE GOVERNMENT: Arthur M. Taylor, Esq.

DCMA Chief Trial Attorney

Michael T. Patterson, Esq.

Trial Attorney

Defense Contract Management Agency

Chantilly, VA

OPINION BY ADMINISTRATIVE JUDGE WITWER ON

THE GOVERNMENT’S MOTION FOR PARTIAL DISMISSAL

The government moves to partially dismiss these appeals for lack of subject matter

jurisdiction. Specifically, the government seeks to dismiss appellant’s request for a

“penalty” on the basis that it constitutes a request for punitive damages. The government

also seeks to dismiss multiple requests for compensation on the basis that appellant did

not submit these requests to the contracting officer prior to raising them before the Board.

For the reasons set forth below, the Board grants the government’s motion to dismiss

appellant’s request for a penalty. The Board defers the remainder of the government’s

motion until after the presentation of evidence on the merits.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

1. On July 16, 2012, the Department of the Air Force awarded a cost-plus-fixed-

fee contract to appellant, D-STAR Engineering Corporation (DSEC) (R4, tab 1 at G-1,

G-2). The contract required appellant to build a fuel-to-power generation system for an

unmanned air vehicle (R4, tab 1 at G-42). The Defense Contract Management

Agency (DCMA) administered the contract (R4, tab 1 at G-1), and represents the

government in these appeals.

2. On November 1, 2013, the government terminated the contract for its

convenience (R4, tabs 4-5). Between December 2013 and November 2015,

appellant submitted several termination settlement proposals (app. supp. R4, tab 3;

R4, tabs 6-8, 10). Appellant’s final proposal, dated November 21, 2015, requests a net

payment of $442,783.01 (R4, tab 10 at G-80).

3. The parties were unable to reach an agreement regarding the amount, if any,

due to appellant. Accordingly, in December 2015, DCMA asked the Defense Contract

Audit Agency (DCAA) to perform an audit of appellant’s November 2015 proposal

(R4, tab 11 at G-84). DCAA released its report in December 2016, questioning $925,624

in claimed costs and settlement expenses (id.). 1

4. In February 2018, the DCMA contracting officer issued a debt determination

and demand for repayment letter to appellant (hereinafter “demand letter”) (R4, tab 13).

In the demand letter, the contracting officer asserted that appellant was indebted to the

government in the amount of $482,841 for overpayments (id.). Relevant here, the

demand letter also provided that a penalty would be imposed if appellant failed to satisfy

the debt in full within 90 days. More precisely, the demand letter stated, in pertinent part:

The debt may be subject to administrative charges in

accordance with the requirements of 31 U.S.C. 3717(e) . . . .

If payment is not received within 90 days from the date of

this letter, the debt will be transferred to the DFAS Columbus

Debt Management Office (DMO) for collection. If the debt is

not paid in full within 90 days from the due date stated in the

demand letter, then in addition to the interest and

administrative charges, a penalty of 6 percent per annum will

be assessed on the unpaid principal.

(R4, tab 13 at G-176) (emphasis added)

5. Approximately one year later, in March 2019, the contracting officer issued a

final decision responding to appellant’s November 2015 proposal (R4, tab 37). The final

decision stated that it rescinded and replaced the February 2018 demand letter (R4, tab 37

at GS-1669). The contracting officer concluded, once again, that appellant was indebted

to the government (R4, tab 37 at GS-1667). The amount of indebtedness, however, was

reduced to $326,583 (id.).

6. In May 2019, appellant appealed the final decision to the Board, which we

docketed as ASBCA No. 62075.

1

Per the DCAA report, the net payment requested by appellant ($442,783) less the

amount of costs and expenses questioned by DCAA ($925,624) resulted in an

overpayment by the government in the amount of $482,841 (R4, tab 11 at GS-90).

2

7. After reviewing the 131-page complaint filed by appellant, the Board noted

that appellant raised a number of issues pertaining to the administration and termination

of the contract that did not appear to have been the subject of a claim submitted to the

contracting officer. Consequently, the Board ordered the parties to address whether these

issues were properly before the Board (Bd. Order dtd. Nov. 1, 2019).

8. In June 2020, appellant informed the Board that it intended to submit a claim

to the contracting officer (app. corr. dtd. June 18, 2020).

9. On August 17, 2020, appellant submitted a 141-page claim to DCMA

(R4, tab 38), which the contracting officer denied on November 16, 2020 (R4, tab 39).

In the final decision, the contracting officer continued to maintain that appellant was

indebted to the government in the amount of $326,583 (id.).

10. In January 2021, appellant appealed the final decision to the Board, which we

docketed as ASBCA No. 62780 and consolidated with ASBCA No. 62075.

11. In February 2021, appellant filed a 60-page complaint in the new appeal.

Importantly, the complaint in ASBCA No. 62780, as well as the previous complaint,

includes a request that the Board impose a “penalty” on the government for

“inappropriate” actions. 2 (ASBCA No. 62075 (62075) compl. at 50-51; ASBCA

No. 62780 (62780) compl. at 12, 48-49)

12. In April 2021, DCMA filed the instant motion for partial dismissal.

DCMA asserts that the Board should dismiss appellant’s request for a penalty because it

constitutes a request for punitive damages, which the Board has no authority to award

(gov’t mot. at 2, 19-21). 3 DCMA also asserts that the Board should dismiss multiple

requests for compensation raised in ASBCA No. 62075 because the requests were not

submitted to the contracting officer in a claim before being submitted to the Board in

appellant’s complaint (id. at 1-2, 17-19). The government recognizes, however, that

“[t]hese additional counts are largely duplicative of counts currently before the Board

2

The amount requested in the two complaints differs (see 62075 compl. at 51 (requesting

a penalty of $94,645); 62780 compl. at 12 (requesting a penalty of $194,033)).

Based on appellant’s explanation of how it calculated the amounts, we believe the

difference is due merely to the passage of time (see R4, tab 38 at GS-1699;

62075 compl. at 51; 62780 compl. at 48).

3

Although the government focuses almost exclusively on appellant’s request for a

penalty in ASBCA No. 62780 (see e.g., gov’t mot. at 2-3, 19-21), the government

also correctly notes that appellant raised the identical request in ASBCA

No. 62075 (id. at 19 n.3). (See 62075 compl. at 50-51; 62780 compl. at 48-49)

Thus, the government seeks to strike the penalty request from both appeals (gov’t

mot. at 19 n.3).

3

under ASBCA No. 62780, which the Board has consolidated with ASBCA No. 62075”

(id. at 18 n.2).

13. In May 2021, appellant filed an 82-page response to the government’s motion,

in which appellant predominantly addresses the merits of these appeals. In the scant

portions addressing the jurisdictional issues pending before the Board, appellant

seemingly recognizes that the Board lacks the authority to award punitive damages.

(See app. opp’n at 19) (stating that “DSEC Appeal 62780 recognizes that ASBCA may

not be able to award punitive damages against the government”). 4 Regarding the

additional basis for partial dismissal, appellant appears to argue that, even if it failed to

submit a claim prior to filing its complaint in ASBCA No. 62075, any alleged

jurisdictional deficiency was cured by the subsequent submission of its August 2020

claim (see generally app. opp’n at 2, 21). In this regard, appellant argues that its

August 2020 claim incorporated the multiple requests for compensation that the

government now seeks to dismiss. (Id. at 2) (arguing that the “previous DSEC Complaint

62075 [has] been subsumed into and superseded by the Revised DSEC Claim of

17 Aug. 2020, the [final decision] of 16 Nov. 2020 and DSEC Complaint 62780 of

16 Feb. 2021”); (id. at 21) (contending that “the Appeal 62075 has been subsumed and

superseded by Appeal 62780”). For this reason, appellant asserts that the Board should

focus primarily on ASBCA No. 62780 and deny as moot this aspect of the government’s

motion (id. at 2, 21).

14. In June 2021, the government informed the Board that it did not intend to file a

reply in support of its motion for partial dismissal.

DECISION

DSEC bears the burden of establishing the Board’s jurisdiction by a

preponderance of the evidence. Globe Trailer Manufacturing, Inc., ASBCA No. 62594,

21-1 BCA ¶ 37,795 at 183,497 (citing Reynolds v. Army & Air Force Exch. Serv.,

846 F.2d 746, 748 (Fed. Cir. 1988)). For the reasons below, we conclude that appellant

4

In lieu of punitive damages, appellant suggests the possibility of alternative forms of

compensation under different legal theories (app. opp’n at 19 (identifying “the

alternative of invoking the Fair Compensation Principle to ensure DSEC has been

fairly compensated for all costs incurred in good faith as well as for the harm

caused DSEC by various inactions and inappropriate actions of the government”);

see id. at 22 (same); see also 62780 compl. at 49 (suggesting that, if the “payment

of the claimed penalty is prevented by some FARs, then the ASBCA can increase

the fee payable to DSEC, or include the penalty in an overall amount payable to

DSEC without breakdown into sub-items”)). These alternative requests are not

relevant to our resolution of the government’s pending motion. Accordingly,

we do not address them further herein.

4

has failed to meet its burden with respect to its request for a penalty. We defer ruling on

the remainder of the government’s motion for partial dismissal.

Appellant’s Request for a Penalty

In its August 2020 claim, appellant requests a “[p]enalty, at the standard rate of

6% per annum, for [the] Government’s unreasonable delays and inappropriate actions

that have caused considerable harm to DSEC” (R4, tab 38 at GS-1672). Appellant

repeats this request nearly verbatim in its two complaints (62075 compl. at 50-51;

62780 compl. at 12, 48-49). Appellant calculates the current amount of the penalty at

$194,033 (62780 compl. at 12).

At first glance, the exact nature of the requested penalty is difficult to ascertain.

In this regard, appellant’s lengthy claim and pleadings are not a model of clarity.

When describing the requested penalty, appellant often utilizes shifting and ambiguous

language, making it difficult to decipher what the penalty represents. Moreover, the

government’s motion for partial dismissal provides little help. 5

The Board is mindful, however, that appellant is appearing without a lawyer,

entitling it to certain leniencies afforded to parties proceeding pro se. Steffen v. United

States, 995 F.3d 1377, 1380 (Fed. Cir. 2021) (acknowledging “the long-held principle

that pleadings drafted by pro se litigants are generally held to ‘less stringent standards’

than pleadings filed by trained attorneys” (quoting Haines v. Kerner, 404 U.S. 519,

520-21 (1972))); Butt v. United States, No. 05-1187C, 2007 WL 5161797, at *2 (Fed. Cl.

Feb. 12, 2007) (“If the court were to require pro se parties to make their arguments as

clearly and in the same format as those made by counsel, it would be a simple matter to

dismiss virtually every pro se case.”). For this reason, and to ensure that justice is done,

the Board has carefully examined appellant’s filings to determine the exact nature of the

penalty requested and to discharge our responsibility to extract legal significance from

the various theories appellant advances without making appellant’s case for it. Having

done so, however, we conclude that appellant has failed to meet its burden of establishing

the Board’s jurisdiction. John Shaw LLC d/b/a Shaw Building Maint., ASBCA

No. 61379, 61585, 19-1 BCA ¶ 37,216 at 181,185 (“While pro se litigants, such as

appellant, are often held to less stringent pleading standards than by those represented by

counsel, they are not exempt from meeting jurisdictional prerequisites.”) (citation

omitted).

5

DCMA’s argument is comprised of a recitation of case law regarding punitive damages

followed by a cursory statement that appellant’s claim is “most certainly a request

for the award of punitive damages” (gov’t mot. at 21). Thus, the government

leaves to the Board the task of interpreting the exact nature of the requested

penalty and determining whether the penalty is “most certainly” a request for

punitive damages.

5

As explained above, appellant often employs shifting and ambiguous language

when discussing the requested penalty. For instance, in various places, appellant uses

language suggesting that the penalty it seeks might represent interest for delayed

payments (see, e.g., R4, tab 38 at GS-1698-99; 62780 compl. at 48) or costs incurred as a

result of an alleged breach of the implied duty of good faith and fair dealing (see e.g., R4,

tab 38 at GS-1698; 62780 compl. at 48-49). After a close review of appellant’s

August 2020 claim and its two complaints, however, we conclude that the requested

penalty is neither. 6 Rather, we conclude that appellant is requesting a penalty under the

penalty provisions of the Debt Collection Act, 31 U.S.C. § 3717(e).

More specifically, appellant points the Board to the government’s February 2018

demand letter—which provides that “a penalty of 6 percent per annum will be assessed

on the unpaid principal” under 31 U.S.C. § 3717(e) if appellant’s debt is not paid in full

within 90 days—and asks the Board to impose the same penalty against the government

(see R4, tab 38 at GS-1699 (quoting R4, tab 13 at G-176); 62075 compl. at 50-51; 62780

compl. at 48). As an example, in the complaint filed in ASBCA No. 62075, appellant

argues, as follows:

Considering that it is the government terminations team that

has repeatedly delayed the processes, taken no action when

needed, taken unreasonable actions, made false allegations,

engaged in repeated delaying tactics, and done anything and

6

Briefly, we conclude that the penalty is not a request for interest because appellant

expressly requests “interest on payments due” in addition to a “penalty, at a

standard rate, payable by the Government to DSEC” (R4, tab 38 at GS-1671).

(See id. at GS-1672 (requesting interest for the government’s delayed payment

of appellant’s incurred costs as well as a “penalty . . . for [the] Government’s

unreasonable delays and inappropriate actions that have caused considerable

harm to DSEC”); see also id. at GS-1674, 1704; 62075 compl. at 50; 62780

compl. at 9, 12)

Similarly, although there is isolated language that, at first glance, might suggest

the penalty represents a request for breach damages, appellant explains that the

government “is liable to pay DSEC both compensation for harm caused as well as

a penalty for inappropriate behavior” (R4, tab 38 at GS-1698) (emphasis added).

Appellant calculates the former at $2,949,426, the latter at $194,033 (id.).

Importantly, appellant also expressly represents that the requested penalty does not

include any incurred costs. (62780 compl. at 48 (clarifying that the “claim for the

penalty to be paid by the government for unreasonable delays and inappropriate

actions by the government is not an ‘expense’ incurred by DSEC, but is

nevertheless payable by the government due to delayed payment” (emphasis

added))).

6

everything possible to avoid paying DSEC for costs incurred

by DSEC in good faith, should the government be assessed

with administrative changes and 6% [per annum] penalties?

DSEC believes such determination by the ASBCA would be

fair and reasonable. If the ASBCA determines that the

government should, indeed, pay the same penalty, then the

penalty at 6% [per annum] over 42.75 months, from

23 Nov 2015 to 16 Jun 2019, for a principal of $442,783,

would be $94,645.

(62075 compl. at 51) (emphasis omitted) Appellant makes the same argument in its

August 2020 claim and complaint filed in ASBCA No. 62780, increasing its calculation of

the penalty to $194,033 (R4, tab 38 at GS-1699 (asserting that “the government be

assessed . . . the same 6% [per annum] penalties” as those provided for in the

government’s demand letter); 62780 compl. at 48 (contending that “[t]his penalty is

similar to, and calculated at the same rate as, that indicated by the [termination contracting

officer], as being payable to DSEC, in the [] Demand letter of 12 Feb 2018”)). The Debt

Collection Act, however, does not provide jurisdiction to the Board to award such

penalties.

The Act requires agency heads to “assess on a claim owed by a person . . .

a penalty charge of not more than 6 percent a year for failure to pay a part of a debt more

than 90 days past due.” 31 U.S.C. § 3717(e)(2). For purposes of subsection 3717(e),

a “claim” or “debt” constitutes “any amount of funds or property that has been

determined by an appropriate official of the Federal Government to be owed to the

United States by a person, organization, or entity other than another Federal agency.”

31 U.S.C. § 3701(b)(1). The term “person” expressly excludes an agency of the Federal

government. 31 U.S.C. § 3701(c). “The purpose of the act was to ensure that the

government did not lose the benefit of the use of monies owed to it by contractors[.]”

Cap. Dev. Co. v. United States, 49 Fed. Cl. 178, 186 (2001) (citing S. Rep. No. 97-378

at 3) aff’d sub nom. Seaboard Lumber Co. v. United States, 308 F.3d 1283 (Fed.

Cir. 2002).

Appellant points to no provision in the Act authorizing the Board, apart from its

Contract Disputes Act (CDA) jurisdiction, to decide disputes over the payment of

penalties on federal agency debts, nor is any such provision apparent to the Board.

The sole provision of the Act addressing penalties, subsection 3717(e), prescribes

payment of penalties to the government. This provision does not mention government

payment of penalties, and does not confer jurisdiction on any contract appeals board to

decide issues of payment of such penalties. Thus, we conclude that we do not possess

jurisdiction to entertain appellant’s claim. See Lockheed Martin Corp., ASBCA

No. 53834, 03-2 BCA ¶ 32,304 at 159,834-35 (holding that the Debt Collection Act does

7

not confer jurisdiction on the Board to adjudicate disputes regarding interest payments

under section 3717).

As a final matter, we also conclude that penalties assessed under

subsection 3717(e) are intended to be punitive. See Am. Airlines, Inc. v. United States,

77 Fed. Cl. 672, 684 (2007) (finding that penalties assessed under 31 U.S.C. § 3717,

unlike interest and administrative costs assessed under the same section, are “imposed as

a punitive measure for late payment”). Thus, as the government argues in its motion

(albeit in summary fashion), appellant seeks the award of punitive damages. Damages,

Black’s Law Dictionary (11th ed. 2019) (Punitive damages are those that are “assessed

by way of penalizing the wrongdoer.”).

Appellant, however, has identified no basis for such a demand. “Absent express

consent of Congress, no punitive damages can be recovered against the United States.”

John Shaw LLC d/b/a Shaw Bldg. Maint., ASBCA No. 61379, 61585, 19-1 BCA

¶ 37,216 at 181,185 (quoting Janice Cox d/b/a Occupro Ltd., ASBCA No. 50587,

01-1 BCA ¶ 31,377 at 154,930-31); see also Mastrolia v. United States, 91 Fed. Cl. 369,

382 (2010) (“The United States has not waived sovereign immunity with regard to

punitive damages.”). The CDA, under which we derive our jurisdiction, does not contain

such a waiver. See John Shaw LLC d/b/a Shaw Bldg. Maint., 19-1 BCA ¶ 37,216

at 181,185 (“Congress has not expressly consented to the Board awarding punitive

damages.”). Accordingly, we dismiss appellant’s request for a penalty because it

constitutes a request for punitive damages, which the Board has no authority to award.

Appellant’s Requests for Compensation in ASBCA No. 62075

The government also moves to dismiss several requests for compensation raised

in ASBCA No. 62075 because the requests were not submitted to the contracting officer

in a claim before being submitted to the Board in appellant’s complaint. DSEC argues

that these requests were subsequently submitted to the contracting officer in the

August 2020 claim and are pending before the Board in ASBCA No. 62780—an

argument with which the government generally concurs. (Gov’t mot. at 18 n.2; see also

id. at ex. G-1 (comparing the two complaints)) Given these positions, and for the sake of

efficiency, we defer ruling on this aspect of the government’s motion to dismiss until

after the presentation of evidence on the merits. 7

7

The Board has compared appellant’s complaint in ASBCA No. 62075 to its

August 2020 claim and the resulting complaint in ASBCA No. 62780, and we

conclude that the requests DCMA seeks to dismiss are, for the most part, included

in the August 2020 claim and subsequent complaint. That said, without further

clarification and briefing from the parties—in particular from appellant—

8

CONCLUSION

The government’s motion to dismiss appellant’s request for a penalty is granted.

The Board strikes appellant’s request for a penalty from ASBCA Nos. 62075 and 62780.

We defer ruling on the remainder of the government’s motion.

Dated: October 14, 2021

ELIZABETH WITWER

Administrative Judge

Armed Services Board

of Contract Appeals

I concur I concur

RICHARD SHACKLEFORD J. REID PROUTY

Administrative Judge Administrative Judge

Acting Chairman Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA Nos. 62075, 62780, Appeals of

D-STAR Engineering Corporation, rendered in conformance with the Board’s Charter.

Dated: October 14, 2021

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

we cannot say with certainty that the two appeals are entirely duplicative in this

respect.

9

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.