Opinion

Save our Access etc. v. Watershed Conservation Authority

Court
California Court of Appeal
Filed
Aug 19, 2021
Status
Published
Cited by
0 cases
Authority
More cited than 16.8%

The opinion

Filed 8/19/21

CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION EIGHT

SAVE OUR ACCESS–SAN B303494

GABRIEL MOUNTAINS,

Plaintiff and Appellant, (Los Angeles County

Super. Ct. No. 18STCP02984)

v.

WATERSHED CONSERVATION

AUTHORITY,

Defendant and Appellant.

SAVE OUR ACCESS—SAN B307701

GABRIEL MOUNTAINS,

Plaintiff and Respondent,

v.

WATERSHED CONSERVATION

AUTHORITY,

Defendant and Appellant.

APPEALS from a judgment and a postjudgment order of

the Superior Court of Los Angeles County, Daniel S. Murphy,

Judge. Judgment reversed with directions to enter a new

judgment denying petition for writ of mandate in its entirety;

order awarding attorney fees reversed.

Leibold McClendon & Mann and John G. McClendon for

Plaintiff and Appellant in B303494 and for Plaintiff and

Respondent in B307701.

Richards, Watson & Gershon and Ginetta L. Giovinco for

Defendant and Appellant.

____________________________________

SUMMARY

This case concerns environmental review of an

improvement project in the Angeles National Forest. Defendant

Watershed Conservation Authority (WCA or defendant) certified

the environmental impact report (EIR) for the project under the

California Environmental Quality Act (CEQA, Pub. Resources

Code, § 21000 et seq.). (Further unspecified statutory references

are to the Public Resources Code.)

Plaintiff Save Our Access–San Gabriel Mountains

challenged defendant’s certification of the EIR. The EIR

addressed the usual extensive range of potential impacts on the

environment, on biological resources, cultural resources, water

quality, air quality, and more. This appeal addresses only three

points: a reduction in available parking; the fact the EIR did not

analyze multiple alternatives to the project, instead analyzing a

single “no project” alternative; and alleged conflicts with land

management plans.

The trial court rejected plaintiff’s claims that CEQA

required defendant to consider additional project alternatives,

and that the project was inconsistent with applicable land use

plans, but issued a writ of mandate requiring defendant to

2

“articulat[e] and substantiat[e] an adequate parking baseline” for

the project, and to “reassess[] the significance of the impacts

resulting from the . . . project’s parking reduction.” The court

found those two issues were severable and the rest of defendant’s

project activities do not violate CEQA.

Both parties appealed from the judgment. The trial court

later awarded plaintiff attorney fees, and defendant appealed

from that order. We conclude the trial court erred in its analysis

of the parking issue and should have denied plaintiff’s petition in

its entirety. This conclusion requires reversal of the attorney fee

order as well.

FACTUAL AND PROCEDURAL BACKGROUND

1. The Project and Its Genesis

We describe at some length the history of this wilderness

recreation and preservation project. We quote extensively from

environmental reports, the comments of consultants, members of

the public and members of defendant’s board, the contentions of

the parties, and the findings of the trial court, so as to provide a

thorough historical context for our legal analysis.

The project under review is called the San Gabriel River

Confluence with Cattle Canyon Improvements Project. The

project is in the Angeles National Forest, the first national forest

in California, created by Presidential proclamation in 1892. In

October 2014, President Barack Obama designated 342,177 acres

of the Angeles National Forest and 4,002 acres of the San

Bernardino National Forest as the San Gabriel Mountains

National Monument. The monument was established “to expand

recreational access, to increase investments in restoring

landscapes, and to protect resources important to the history and

heritage of the United States.”

3

The project site is within the monument and consists of

198 acres along a 2.5-mile stretch of the East Fork of the San

Gabriel River. It encompasses “the riverbed, public roads . . . ,

and all existing recreational facilities within the project site.” It

is among the most popular recreation areas for weekend use, and

“heavy use combined with the lack of facilities has resulted in the

degradation of the area,” including damage to vegetation, soil

compaction and erosion, stream alteration, high levels of litter

deposition, and water quality impairment due to excessive trash.

The project was proposed “to better manage the heavy recreation

use while balancing the need for long-term resource protection.”

The project was developed over several years of

collaboration between the Angeles National Forest and

defendant.1 “The intent is to provide recreational improvements

and ecological restoration to address resource management

challenges with a focus on reducing impacts along the most

heavily used section of the river.”2 Proposed enhancements

1 Defendant is a joint powers agency of the San Gabriel and

Lower Los Angeles Rivers and Mountains Conservancy and the

Los Angeles County Flood Control District. Defendant is the lead

agency responsible for preparing an EIR under CEQA. The

Angeles National Forest is responsible for preparing an

environmental impact statement under the National

Environmental Policy Act. A joint statement was prepared under

the direction of both lead agencies to satisfy their respective

requirements.

2 The EIR further states: “The purpose and need for the

project is to: [¶] • Provide recreation facilities and

infrastructure that are high quality, well-maintained, safe, and

accessible to visitors. [¶] • Shift and concentrate recreational

use to certain areas in order to minimize adverse effects over a

4

“include the development of new picnic areas, pedestrian trails,

river access points and upgrades to existing facilities,

improvements to paved and unpaved roadways, parking

improvements, restrooms and refuse disposal improvements,

restoration of riparian and upland vegetation communities . . .

and implementation of a Forest Closure Order to prohibit

overnight camping.”

After public scoping meetings in November 2016, a draft

EIR was prepared and circulated in November 2017 for public

comments.

2. The Draft EIR

We describe the draft EIR as it relates to the parking

reduction, the focus of defendant’s appeal. Additional facts

relevant to plaintiff’s claims concerning project alternatives and

land use conflicts are included in our legal discussion of those

claims.

a. Existing parking conditions

The draft EIR described the existing limited number of

designated parking spaces and the widespread practice of

parking in undesignated areas.

broader area. [¶] • Promote stewardship of public land by

providing quality and sustainable recreation opportunities that

result in increased visitor satisfaction. [¶] • Allow for better

management of the recreation resources in the forest. [¶]

• Improve riparian habitat conditions in certain areas and make

progress toward enhancing stream habitat conditions by

restoring vegetation, minimizing invasive plants and noxious

weed presence, and developing management strategies to

regulate access.”

5

“Currently, designated parking (paved area with

delineations) within the project site consists of 15 parking spaces

at the Oaks Picnic Area and 33 parking spaces at the East Fork

Day Use Parking trailhead. The remainder of the parking occurs

in undesignated areas along the shoulders and any wide spot

along the side of the road. During busy summer weekends,

almost all available designated and undesignated parking spots

are used. During the 2013–2014 seasons, the WCA measured the

average use during the weekends between Memorial Day and

Labor Day was 273 vehicles per survey day. There are an

estimated 417 total parking spaces available, both designated

and undesignated, in the project area (Blue Green Consulting,

2017). This is a rough estimate based on aerial photography and

does not include parking that would be prohibited by current

signage. The estimate also does not take into account the

addition of parking spaces located at the old fire station site, and

the removal of spaces located at the East Fork Day Use Parking

Trailhead to accommodate new facilities. [¶] Parking capacity in

undesignated areas will fluctuate depending on how visitors park

and the type of vehicles they arrive in. Some parking efficiencies

are achieved in undesignated areas when groups arrive in

multiple cars and double or triple park. On major summer

holiday weekends (Memorial Day, Independence Day, and Labor

Day) parking capacity in the project site is reached early in the

day.”

b. The proposal to formalize parking spaces and

prevent parking in undesignated areas

The draft EIR proposed “to formalize parking spaces by

adding features such as pavement, stripes, and signage.

Undesignated parking areas would be blocked with boulders and

6

‘no parking signage’ would be installed.” The draft EIR described

the proposed “parking spaces available” (as relevant here) this

way:

“Once fully implemented, the maximum parking available

. . . will be 270 car spaces and 3 bus spaces. During the 2013–

2014 seasons the WCA measured the average use during the

weekends between Memorial Day and Labor Day was

273 vehicles per survey day. With the reduction in parking there

would be an impact to the number of visitors able to park in the

project site. [¶] The displacement that does occur would likely

lead to increased use at other areas with similar amenities within

the region. It is assumed that displaced visitors would be

dispersed across the region as they find substitute activities.”

The draft EIR further explained the changes, separately for

the lower canyon and the upper canyon.3 In the lower canyon,

“[i]n current conditions, there are 15 designated parking spaces

available. WCA field observations found that on average over the

summer weekends, the vehicle count for this area was

131 parked cars. With implementation of [the project], this

would change to 169 designated spaces available.” In the upper

canyon, “[i]n current conditions, there are 33 designated parking

spaces available. WCA field observations found that on average

3 The lower canyon includes “the Confluence Area, Junction

Area and Oaks Picnic Area to the south project boundary.” The

upper canyon is “the area north of the Cattle Canyon Bridge to

the northern project boundary and includes the East Fork

Trailhead Parking, East Fork Scenic Overlook, Coyote Flat, and

Heaton Flat areas.”

7

over the summer weekends, the vehicle count for this area was

142 parked cars. With implementation of [the project], this

would change to 101 designated spaces available.”

In both locations, “[d]uring peak use hours, some visitors

will not be able to find a place to park and will likely either find a

substitute activity or location to participate in their desired

activity.”

c. Environmental consequences

The draft EIR found the project’s impact on recreation was

less than significant. Specifically:

“The project would not increase the use of existing

neighborhood and regional parks or other recreational facilities

such that substantial physical deterioration of the facility would

occur or be accelerated.” The draft EIR cited the most recent

National Visitor Use Monitoring (NVUM) survey that found more

than half the responding people said if they were unable to visit

the national forest, they would travel elsewhere in the region to

participate in their desired activity.4 The draft EIR also found

4 The draft EIR explained: “Based on 2011 NVUM studies

for the [Angeles National Forest], 52 percent of survey

respondents indicated that they would travel somewhere else to

participate in their main activity if they were unable to visit the

national forest. From that group of respondents, 51 percent of

them would be willing to travel up to 25 miles to participate in

the activity and an additional 31 percent would be willing to

travel up to 50 miles to participate in their primary activity.

Brown and Richter noted the following about visitors to the lower

canyon area[:] ‘relatively high numbers of visitors reside in zip

codes located along the I-605 corridor, then fanning out across

eastern Los Angeles County (south of the 60 freeway) into

downtown Los Angeles, and then the south/southeastern parts of

8

the project “would not include recreational facilities or require

the construction or expansion of recreational facilities which

might have an adverse physical effect on the environment.” The

draft EIR concluded: “The potential for substantial physical

deterioration of other recreational facilities in the region as a

result of the project would be minimized through implementation

of PDM [project design measures] REC-1 and PDM-REC 2.

Impacts would be less than significant.” These project design

measures included avoiding construction during weekends and

major holidays to reduce the likelihood of displacement of the

recreating public, and a public notification plan to inform the

public of possible area closures and other available recreation

opportunities.

In comparing the proposed project with the “no project”

alternative, the draft EIR stated: “[O]peration of the project

would result in a reduction in parking, thus potentially impacting

the number of visitors able to drive single-occupancy vehicles to

the project site. This could potentially result in a slight increased

use in other recreational facilities or areas with similar amenities

within the region, but it is assumed that this would be dispersed

Los Angeles County’ (Brown and Richter p. 5). Brown and

Richter’s study indicated that visits to the upper canyon area

generally are from a larger geographic area. The project site is

located approximately 16 miles or half hour drive from the

Interstate 210 the closest freeway. It is assumed that visitors to

the project site would likely drive to another location to

participate in their desired activity if they were unable to

participate in their activity within the project site.”

9

across the region as individuals find substitute activities. . . .

Project implementation would result in concentrated recreational

use centered around the river access points (as opposed to

existing dispersed recreation throughout the river). Crosswalks,

designated parking spaces, river access points, and designated

picnic areas would provide a safer environment for visitor

access.”

In concluding the project was the environmentally superior

alternative, the draft EIR stated the project’s concentration of

recreational uses around planned river access points would

“reduc[e] human impacts (i.e., erosion, water quality, trash,

habitat trampling) to the environment. Placement of restrooms,

parking areas, and trash bins would reduce impacts of visitors to

the area compared to existing conditions. In addition,

operational effects of the project would promote utilization of

formal trailheads, designated parking lots, crosswalks, and

closure of informal trails. [The project] would improve access and

safety of recreational users, while managing sustainable

recreation.”

3. The Final EIR: Responses to Comments

The final EIR in Appendix J contains defendant’s response

to every comment on environmental issues raised during the

public review period. Appendix J includes “master responses” on

several issues, including traffic and parking, and project

alternatives. The master responses “are intended to provide

comprehensive discussion in response to select sets of issues that

received multiple comments. They are intended to provide

clarification and refinement of information presented” in the

draft EIR.

10

In the traffic and parking category, commenters asked for

clarification of the baseline parking condition and expressed

opinions regarding the reduction in the number of parking

spaces; the need for a traffic/parking study; reliance on the

2014 Brown and Richter survey to estimate the average use of

273 vehicles in the project area, which some people considered

outdated; and limitations to public access.

Defendant’s response reiterated the existing parking

conditions as described in the draft EIR (48 designated and

369 undesignated spaces), and stated that “[d]uring busy summer

weekends, almost all available designated and undesignated

parking spots along the road shoulders—some of which are

unsafe and many of which occur in areas that are currently

signed as ‘no parking’—are used.” Defendant noted that parking

capacity in undesignated areas “will fluctuate depending on how

visitors park (i.e., perpendicular, parallel, or double or triple

park) and the type of vehicles they arrive in.”5

Defendant acknowledged that the number of current

parking spaces “was determined using aerial photographs from

one peak day in 2014,” and “[s]ince this only captures one peak

day, it is possible for actual peak day visitorship to be greater

5 Defendant observed the Brown and Richter 2014 survey

(measuring average use during summer weekends and finding

273 vehicles per survey day) was, at the time of the EIR notice of

preparation, “the best available science/information and most

relevant data collected in the project area specifically for this

project,” and “was provided to various commenters and will be

made public[ly] available.”

11

than 417 on certain days.” The data showed “the demand to

access the area is considerably greater than the designated

parking currently available,” and the project is “designed to

accommodate as much of this demand as is feasible while at the

same time ensuring public safety and protection of the natural

environment.” Defendant’s response expressly acknowledged (as

was evident from the draft EIR) that “this is a reduction in

parking space availability compared to the existing condition

when considering the use of undesignated parking spaces. As a

result, there would be an impact to the number of visitor vehicles

able to safely park on the project site.”

Defendant emphasized the project will have over five times

more designated spaces, and is designed to accommodate shuttle

service. “Undesignated parking spaces can create traffic safety

hazards (including for emergency access) and increase roadside

erosion. [The project] balances the need for more parking while

recognizing the recreational area’s carrying capacity and

emphasizing public safety. Group activities for private events

and ventures will be encouraged to provide shuttles from off-site

locations.” Further, the more formalized designated parking

spaces “would serve to improve the overall circulation in the area

by directing vehicles, including shuttle/bus vehicles to specific

areas. The overall safety of vehicular and pedestrian circulation

would be improved.” The response concluded that: “It is

recognized that this number of designated parking spaces will not

accommodate maximum demands during peak season/days,

which is not the intent of this project. However, the proposed

project improves the existing condition, while also protecting

public safety and the environment.”

12

4. WCA’s Certification of the Project

On October 25, 2018, defendant’s board held a public

hearing and certified the final EIR for the project. Some board

members commented on the parking issues. Ms. Chico said, “I’m

not familiar with the parking area. I didn’t realize, in listening to

public comment, that there is no designated official parking and I

can’t imagine the chaos that goes when people are trying to park.

[¶] So I appreciate trying to organize it and create these

designated parking areas.”

Mr. Uranga said: “So I see here that—or what I saw and I

heard from the consultants . . . , they did a traffic study and they

did a parking study and they have even made some

recommendations about some additional parking that will be

provided along the trail to provide greater access to people who

want to reach the river, and even making improvements in terms

of providing greater access to the river by giving stairs.” “So in

that respect, I don’t see why we would want to stop the project

from moving forward, when it’s only one issue that’s involved

here. We’re talking about a multimillion-dollar project that

involves more access and my question, my issue is access. [¶]

And what this project has done and what the consultants have

brought forward is actually an enhancement to access for people

to enjoy the Emerald Necklace.” Board member Mendelsohn

said, “I just feel that I have not had adequate time to truly review

all of this, to review the responses.”

The consultants made a further presentation of the master

responses to the public comments, including the master response

on traffic and parking. The discussion turned to “the Jones

letter,” principally to the impact on Mr. Jones’s commercial

ventures such as bungee jumping at his property on the “Bridge

13

To Nowhere” near the project site.6 Ms. Chico observed, “It’s

unfortunate that Mr. Jones wasn’t clear in his comments that it

was because of a business interest.”

The board then voted 4 to 1 to certify the EIR

(Ms. Mendelsohn voting no).

5. The Writ Petition Proceedings

On November 28, 2018, plaintiff petitioned for a writ of

mandate directing defendant to set aside its approval of the

project.

The trial court granted plaintiff’s petition in part,

concluding: “The project creates (or exacerbates) a parking

shortage and, without adequate analysis and evidence of how

that shortage would materialize, it cannot be said that the

project’s parking impacts, direct or secondary, are insignificant.”

First, the trial court found deficits in the draft EIR’s

“parking baseline determinations.” The court found there was no

substantial evidence to support defendant’s determination the

maximum number of parking spaces at the site was 417, because

the aerial photography on which its consultant relied was not in

the record. While plaintiff likewise could not substantiate its

claim that the actual maximum number was 473 (as the report it

relied on was also missing from the record), the court concluded

defendant’s error was prejudicial.

6 Mr. Jones’s comments also included a statement that the

East Fork Scenic Trail “would eliminate at least 75 much-needed

legal roadside parking spaces in the East Fork Scenic Overlook

area.” Defendant’s response, in addition to referring to the

master response, was that “[i]t is unclear where these 75 legal

parking spaces were derived since the entire project site

currently has 48 designated parking spaces.”

14

The trial court also found it “alarming” that defendant did

not disclose “the particular maximum number of parking spaces

available in each area.” (The court observed that “parking does

not presumably distribute evenly throughout the Project Site,”

and “[i]f the reduction in parking spaces occurs

disproportionately in one popular area of the Project Site, e.g.,

the East Fork Scenic Overlook where a trailhead is located, then

this logically could have a significant impact on parking in that

area and create downstream recreational effects. The EIR

provides no reasonable explanation for not presenting this vital

baseline information.”)7

In addition, the trial court found the Brown study—finding

the average number of parked vehicles was 273—did not support

the proposed project’s 270 parking spaces. This was because the

Brown survey was done between 2:30 p.m. and 6:30 p.m., rather

than at peak demand hours earlier in the day.8

Then the court turned to the parking reduction, and agreed

with plaintiff the EIR failed to serve its informational role. While

7 The draft EIR stated that “[p]arking within the project site

generally concentrates around the Oaks Picnic Area and the East

Fork Day Use Parking Area [at the trailhead]. As these locations

reach capacity visitors will expand out to surrounding

undesignated parking areas.”

8 The draft EIR acknowledged that “parking capacity in the

project site is reached early in the day,” so the court agreed with

plaintiff that an actual vehicle count should have measured

parking at peak demand hours. The court concluded: “Thus, no

reasonable inference supports the conclusion that a study

performed after peak hours would accurately reflect the average

number of vehicles at the Project Site.”

15

defendant disclosed the parking reduction, the court found

defendant relied on “unreliable and/or inaccurate parking

baseline determinations to assess the significance of the Project’s

impacts on parking. More accurate parking baseline

determinations could lead WCA to conclude that the Project’s

parking impacts are significant and require mitigation.” The

court cited Taxpayers for Accountable School Bond Spending v.

San Diego Unified School Dist. (2013) 215 Cal.App.4th 1013,

1051 (Taxpayers) for the proposition that a parked car has a

physical impact on the environment around it that could

constitute a significant effect on the environment, and so “the

Project’s parking reduction could constitute a significant effect on

the environment.”

The court rejected plaintiff’s other contentions, denying the

petition as to all other elements of the project. Judgment was

entered and a writ of mandate issued on November 14, 2019,

ordering defendant to articulate and substantiate an adequate

parking baseline for the project, and to reassess the significance

of the impacts resulting from the project’s parking reduction.

These appeals followed.

In a postjudgment order, the court awarded plaintiff

$154,000 in attorney fees under the private attorney general

doctrine (Code Civ. Proc., § 1021.5). Defendant appealed from

that order, and we consolidated the appeals for purposes of

argument and decision.

16

DISCUSSION

We describe the applicable law, then discuss the parking

issue raised in defendant’s appeal, and conclude with the

remaining issues raised in plaintiff’s appeal.

1. CEQA Principles and the Standard of Review

A comprehensive discussion of CEQA and the purposes and

role of an EIR appears in Laurel Heights Improvement Assn. v.

Regents of University of California (1988) 47 Cal.3d 376, 390–393

(Laurel Heights). Suffice it to say that, before approving a

project, the lead agency—here, WCA—must find either that the

project’s significant environmental effects identified in the EIR

have been avoided or mitigated, or that unmitigated effects are

outweighed by the project’s benefits. (Id. at p. 391, citing

§§ 21002, 21002.1 & 21081.) “If CEQA is scrupulously followed,

the public will know the basis on which its responsible officials

either approve or reject environmentally significant action, and

the public, being duly informed, can respond accordingly to action

with which it disagrees.” (Laurel Heights, at p. 392.)

In an action to set aside an agency’s decision under CEQA,

the court’s inquiry extends only to whether there was a

prejudicial abuse of discretion. Abuse of discretion occurs if the

agency has not proceeded in a manner required by law, or if its

decision is not supported by substantial evidence. The court

passes only upon the EIR’s sufficiency as an informative

document, not upon the correctness of its environmental

conclusions. (Laurel Heights, supra, 47 Cal.3d at p. 392.)

CEQA Guidelines, which implement the provisions of

CEQA, “define ‘substantial evidence’ as ‘enough relevant

information and reasonable inferences from this information that

a fair argument can be made to support a conclusion, even

17

though other conclusions might also be reached.’ ” (Laurel

Heights, supra, 47 Cal.3d at p. 393, quoting CEQA Guidelines,

§ 15384, subd. (a).) Courts “should afford great weight to the

Guidelines except when a provision is clearly unauthorized or

erroneous under CEQA.” (Laurel Heights, at p. 391, fn. 2.)9

Laurel Heights cautions that a court may not set aside an

agency’s approval of an EIR on the ground that an opposite

conclusion would have been equally or more reasonable. (Laurel

Heights, supra, 47 Cal.3d at p. 393.) CEQA’s purpose is to compel

government to make decisions with environmental consequences

in mind, but CEQA “ ‘does not, indeed cannot, guarantee that

these decisions will always be those which favor environmental

considerations.’ ” (Laurel Heights, at p. 393.) Technical

perfection in an EIR “ ‘ “is not required; the courts have looked

not for an exhaustive analysis but for adequacy, completeness

and a good-faith effort at full disclosure.” ’ ” (California Native

Plant Society v. City of Santa Cruz (2009) 177 Cal.App.4th 957,

979.)

The appellate court’s inquiry is the same as that of the trial

court. The appellate court reviews the administrative record

independently to determine whether defendant complied with

CEQA or made determinations that were not supported by

substantial evidence. (Planning & Conservation League v.

Department of Water Resources (2000) 83 Cal.App.4th 892, 912;

see also § 21168.) “The burden of showing that the EIR is

9 All references to “Guidelines” are to the current CEQA

Guidelines (Cal. Code Regs., tit. 14, § 15000 et seq.).

18

inadequate is on the party challenging the EIR.” (Pfeiffer v. City

of Sunnyvale City Council (2011) 200 Cal.App.4th 1552, 1562.)

2. The Parking Issue (Defendant’s Cross-appeal)

Plaintiff’s opening brief tells us that “the centerpiece of the

project” is an “intentional reduction in parking” devised by

defendant’s staff to “severely constrain the public’s access to the

[San Gabriel Mountains National] Monument and force them to

recreate elsewhere.” The draft EIR, plaintiff says, “glossed over”

this plan and “misled” most of the public “into believing that the

project was going to increase existing parking instead of

decreasing it.”

That is not true. The notion that the “centerpiece” of the

project is an intentional reduction in parking is utterly absurd.

Nor does the draft EIR—quoted at length above—“gloss over” the

reduction in parking. The draft EIR clearly informs the decision-

maker and the public that the project reduces parking—according

to defendant, from 417 designated and undesignated spots to

270 designated spots (and according to plaintiff, from 473 rather

than 417). As explained below, we consider unimportant the

discrepancy between 417 versus 473 spots in the context of this

case.

We likewise reject plaintiff’s other assertions of CEQA

violations related to the reduction in parking. In our view, the

nature of this project, the applicable law, and the information

disclosed in the draft EIR support the conclusions that defendant

proceeded as required by law, and the EIR is sufficient as an

informative document. Defendant disclosed the reduction in

parking, and properly found the proposed project “would have

less than significant impacts on recreation.” That is all it was

required to do.

19

We find it strange that plaintiff attacks the EIR for not

converting more wilderness open space to parking or,

alternatively, for not continuing to permit parking in fragile

natural areas that have become degraded by erosion, trash, and

habitat trampling. Since when was environmental protection

focused on promoting and expanding parking in protected

wilderness monuments? Plainly, reducing and formalizing

parking spaces in the San Gabriel River and adjacent canyon

recreation areas will protect and restore the environment.

Plaintiff has identified no adverse physical impact on the

environment that results from the reduction in parking, much

less a “potentially substantial, adverse change in any of the

physical conditions within the area affected by the project.”

(Guidelines, § 15382.) Nor has plaintiff proffered evidence of any

secondary adverse environmental effects of reduced parking, such

as on traffic or air quality at the project site.

We agree with the principle stated in San Franciscans

Upholding the Downtown Plan v. City & County of San Francisco

(2002) 102 Cal.App.4th 656 (San Franciscans): “The social

inconvenience of having to hunt for scarce parking spaces is not

an environmental impact; the secondary effect of scarce parking

on traffic and air quality is. Under CEQA, a project’s social

impacts need not be treated as significant impacts on the

environment. An EIR need only address the secondary physical

impacts that could be triggered by a social impact.” (San

Franciscans, at p. 697, citing Guidelines, § 15131, subd. (a).)

San Franciscans involved a massive redevelopment project

in downtown San Francisco to provide office, retail, hotel,

entertainment, and restaurant space in place of abandoned

buildings that had been vacant and deteriorating for a decade.

20

(San Franciscans, supra, 102 Cal.App.4th at pp. 666, 669–670.)

Among other things, the plaintiffs contended the project would

have significant impacts “in the form of increased gridlock and

traffic pressure and the demand for at least 1,250 new parking

spaces,” and failed to identify or propose any mitigating measures

for those impacts. (Id. at pp. 695–696.) The project was located

at a transit hub; the EIR pointed out that providing additional

off-street parking would have the adverse environmental impact

of attracting more cars to the area, in conflict with the city’s

policy of encouraging use of public transit. (Id. at pp. 696–697.)

San Franciscans found the EIR “correctly concluded that

‘[p]arking shortfalls relative to demand are not considered

significant environmental impacts in the urban context of San

Francisco. Parking deficits are an inconvenience to drivers, but

not a significant physical impact on the environment.’ ” (San

Franciscans, supra, 102 Cal.App.4th at p. 697.) The EIR fulfilled

its purpose “by identifying ways in which the secondary

environmental impacts resulting from the projected parking

deficits could be mitigated.” (Ibid.)

San Franciscans involved an urban setting, whereas this

case involves a wilderness setting, but the same principle applies

in both cases. Parking deficits are always inconvenient for

drivers, but they do not always cause a significant adverse

physical impact on the environment. Plaintiff does not discuss

San Franciscans, and relies (as did the trial court) on the

Taxpayers case. Taxpayers rejected the proposition that a

parking shortage “can never constitute a primary physical impact

on the environment.” (Taxpayers, supra, 215 Cal.App.4th at

p. 1051.) We agree that in some circumstances, parking deficits

can have a significant adverse impact on the environment.

21

The project in Taxpayers was for the installation of new

stadium field lighting and other improvements at a high school,

allowing evening sporting events that would attract visitors to a

bedroom community where the residents already had to deal with

problems caused by illegal parking on the narrow streets during

daytime events. (Taxpayers, supra, 215 Cal.App.4th at pp. 1021,

1023, 1047.) The school district approved the project, and the

trial court dismissed the plaintiff’s CEQA cause of action. (Id. at

pp. 1023–1024.) The Court of Appeal concluded there was

“substantial evidence to support a fair argument that the Project

may have a significant impact on parking and thus the

environment,” so an EIR was required. (Id. at pp. 1053, 1054.)

The evidence included letters from many residents expressing

concerns the project would adversely affect the availability of

street parking in a neighborhood “landlocked by canyons” with

narrow streets, with parked cars during school events illegally

blocking driveways, crosswalks, and so on. (Id. at pp. 1047,

1053–1054.) The court found the school district “did not have

sufficient information relating to the Project’s impact on parking

and therefore could not adequately consider the potential

significance of the Project’s impact on parking.” (Id. at p. 1054.)

Taxpayers rejected the school district’s reliance on San

Franciscans, disagreeing “with the broad statement made in [San

Franciscans] that a parking shortage is merely a social

inconvenience and can never constitute a primary physical

impact on the environment. [C]ars and other vehicles are

physical objects that occupy space when driven and when parked.

Therefore, whenever vehicles are driven or parked, they

naturally must have some impact on the physical environment.

The fact that a vehicle’s impact may be only temporary (e.g., only

22

so long as the vehicle remains parked) does not preclude it from

having a physical impact on the environment around it.

Therefore, as a general rule, we believe CEQA considers a

project’s impact on parking of vehicles to be a physical impact

that could constitute a significant effect on the environment.”

(Taxpayers, supra, 215 Cal.App.4th at p. 1051.)

It seems clear from both San Franciscans and Taxpayers

that “the circumstances of [the] case” (Taxpayers, supra,

215 Cal.App.4th at p. 1052) are determinative. The project in

San Franciscans would attract crowds downtown without

providing parking for the people who might prefer to drive, but

the parking deficits would have the environmentally desirable

effect of increasing reliance on mass transit. In contrast, the

project in Taxpayers would attract out-of-area evening crowds to

a suburban neighborhood with narrow streets where residents

would have a hard time finding parking when they returned

home at the end of the day. This project in the Angeles National

Forest would better manage the heavy recreational use by

designating parking near picnic areas, restrooms and trash bins,

and also protect the wilderness from further erosion and other

damage caused by vehicles parking throughout the site, and by

people leaving behind their trash and polluting the water in

areas not designated for parking. The parking reduction here

may have an adverse social impact for those who must recreate

elsewhere, but it will prevent further adverse physical impacts on

the environment.

The CEQA Guidelines in Appendix G list more than

20 potential environmental factors that may affect a project’s

environmental review. Parking availability has not been on the

list since 2009. The California Natural Resources Agency

23

explained the deletion of the question related to parking

adequacy from Appendix G, in a statement of reasons for

amendments to the CEQA Guidelines on greenhouse gas

emissions: “The Natural Resources Agency is aware of no

authority requiring an analysis of parking adequacy as part of a

project’s environmental review. Rather, the Agency concurs with

the court in the San Franciscans case that inadequate parking is

a social impact that may, depending on the project and its

setting, result in secondary effects. Consistent with existing

CEQA Guidelines section 15131(a), deletion of the parking

adequacy question from Appendix G checklist will ensure that

[‘]the focus of the analysis shall be on the physical changes.’

Specifically, the Appendix G checklist contains questions asking

about possible project impacts to air quality and traffic.”10 The

agency’s statement lends further credence to the point that

parking as an environmental factor is dependent “on the project

and its setting.” 11

10 The agency concluded: “In sum, nothing in the CEQA

statute, or cases interpreting that statute, require an analysis of

parking demand. Further, parking supply is not a reasonable

proxy for direct physical impacts associated with a project

because parking supply may in some circumstances adversely

affect air quality and traffic while in other circumstances, it may

create air quality and traffic benefits. Thus, maintaining the

parking question in the general Appendix G checklist is not

necessary to effectuate the purposes of the CEQA statute.”

11 Since 2014, CEQA has expressly provided that parking

impacts are not significant in certain urban contexts. (§ 21099,

subd. (d)(1) [“Aesthetic and parking impacts of a residential,

mixed-use residential, or employment center project on an infill

site within a transit priority area shall not be considered

24

Plaintiff’s other arguments are colored by plaintiff’s

repeated formulation of the issue as “impacts on parking” rather

than impacts of reduced parking on the environment.

Much of plaintiff’s brief is devoted to an attempt to show

defendant “concealed the Project’s impacts on parking by

subtracting disclosures of this fact” from the EIR. The trial court

correctly rejected this claim, finding the draft EIR disclosed the

parking reduction and analyzed it, also observing the reduction

“is implicit throughout the Recreation Section.”

Plaintiff next contends defendant did not properly disclose

“baseline parking conditions.”12 Plaintiff contends, and the trial

court agreed, there is no evidence in the record supporting

defendant’s determination that the maximum number of parking

spaces currently at the project site is 417.

Plaintiff relied on the Sugden recreation report (which

formed the basis for the draft EIR recreation section) to assert to

significant impacts on the environment.”].) See also Covina

Residents for Responsible Development v. City of Covina (2018)

21 Cal.App.5th 712, 728 (“the Legislature endorsed the approach

of . . . San Franciscans for urban infill projects near transit

hubs . . . . While secondary parking impacts caused by ensuing

traffic congestion (‘air quality, noise, safety, or any other impact

associated with transportation’) must be addressed, parking

impacts, in and of themselves, are exempted from CEQA review

for these projects,” quoting § 21099, subd. (b)(3)).

12 “An EIR must include a description of the physical

environmental conditions in the vicinity of the project. This

environmental setting will normally constitute the baseline

physical conditions by which a lead agency determines whether

an impact is significant.” (Guidelines, § 15125, subd. (a).)

25

the trial court that the actual maximum number of parking

spaces is 473. But, as the trial court pointed out, there is no

evidence in the record supporting the Sugden number either.

Both estimates (417 and 473) were based on aerial photography

missing from the record.

We find it immaterial whether the maximum number of

parking spaces is currently 417, or 473, or some number in

between. Plaintiff insists the EIR “failed to provide a true

baseline for the Project’s impacts on parking.” But again, it is not

the project’s “impacts on parking” that matter; it is the impact of

the project’s reduced parking on the environment that matters.

Whether that reduction is 203 fewer spaces (473 to 270) or

147 fewer spaces (417 to 270) has no impact on the environment

unless the 57–space difference would result in significant

deterioration of other recreational facilities in the area. Given

the large regional area, the number of facilities available (eight,

see post), and the small difference in the estimates, it would be

irrational to conclude there would be any significant

deterioration of those other facilities.

The EIR identifies eight “major recreation facilities with

similar activities” located within approximately 25 driving miles

to the project site. Plaintiff challenges the EIR’s assumption that

reduced parking would likely lead to increased use at other

recreation areas in the region. The trial court also criticized the

“undue assumption that the parking reduction would lead to

increased use of other areas with similar amenities within the

region.” The trial court referred to the National Visitor Use

Monitoring survey for the Angeles National Forest, described in

footnote 4, ante. The court concluded the survey was of “dubious

value,” because it is “unclear” on whether those visitors who “had

26

already traveled to [the San Gabriel Mountains] to recreate

would immediately ‘travel somewhere else to participate in their

main activity.’ ” Further, the survey “does not account for the

48% of other visitors who presumably would still attempt to

recreate at” the project site.

We do not agree that visitors who cannot find a place to

park “presumably would still attempt to recreate” at the site, or

that they must be “account[ed] for.” Plaintiff says people will not

“just turn around and go elsewhere” when there is no place to

park, and instead “will circle and idle, hoping to catch a space

being vacated before someone else does.” Certainly, some people

may do so, but plaintiff’s claim this will become herd behavior at

the site is unsubstantiated speculation. (See Guidelines, § 15384,

subd. (a) [“Argument, speculation, [or] unsubstantiated opinion

or narrative . . . does not constitute substantial evidence.”].)

On the contrary, it was reasonable for defendant to assume

that a potential secondary effect of a reduction in parking in a

wilderness area is that visitors who cannot park there would go

elsewhere, and that demand on alternative recreational areas

could potentially have a physical impact on those facilities.

Appendix G of the CEQA Guidelines suggests analysis of that

very question, and the draft EIR addressed it—concluding there

would be no substantial physical deterioration (or acceleration of

deterioration), because displaced visitors would be dispersed

across a large region. That is a rational conclusion, and plaintiff

offers no rational basis for a contrary conclusion.

3. Plaintiff’s Appeal

Plaintiff contends the EIR’s analysis of alternatives to the

project violated CEQA, and in addition the EIR failed to analyze

27

the project’s alleged conflicts with certain land use policies.

These contentions have no merit.

a. The Alternatives Issue

i. The law

The principles governing analysis of alternatives to a

project are described in In re Bay-Delta etc. (2008) 43 Cal.4th

1143 (Bay-Delta). “CEQA requires that an EIR, in addition to

analyzing the environmental effects of a proposed project, also

consider and analyze project alternatives that would reduce

adverse environmental impacts. [Citations.] The CEQA

Guidelines state that an EIR must ‘describe a range of reasonable

alternatives to the project . . . which would feasibly attain most of

the basic objectives of the project but would avoid or substantially

lessen any of the significant effects of the project . . . .’ ” (Id. at

p. 1163, quoting Guidelines, § 15126.6, subd. (a).) “An EIR need

not consider every conceivable alternative to a project or

alternatives that are infeasible.” (Bay-Delta, at p. 1163.)

“ ‘There is no ironclad rule governing the nature or scope of

the alternatives to be discussed other than the rule of reason.’ ”

(Bay-Delta, supra, 43 Cal.4th at p. 1163, quoting Guidelines,

§ 15126.6, subd. (a).) “The rule of reason ‘requires the EIR to set

forth only those alternatives necessary to permit a reasoned

choice’ and to ‘examine in detail only the ones that the lead

agency determines could feasibly attain most of the basic

objectives of the project.’ ” (Bay-Delta, at p. 1163, quoting

Guidelines, § 15126.6, subd. (f).)

ii. The draft EIR

Here, the draft EIR fully analyzed only two alternatives:

the project and “no project.” (The Guidelines (§ 15126.6,

subd. (e)(1)) require evaluation of a “no project” alternative.) The

28

draft EIR explained how defendant arrived at these two

alternatives.

A series of planning workshops were held in 2014 and 2015

to solicit input from an advisory committee. The committee

included conservation and environmental organizations,

regulatory agency staff, United States Forest Service technical

experts, and WCA consultants. A consultant prepared three

design concepts based on input from the first two workshops,

each with a particular focus (public access, river path, and low

impact development). The intent of the alternatives was “to

demonstrate a range of design interventions that could meet the

project objectives.” The three design concepts were presented at

a third planning workshop.

The project design that developed is a “hybridized design

alternative” that “includes components from each of the three

concepts initially developed by BlueGreen [the consultant] as a

preferred design to meet the project objectives. In [contrast] to

the Public Access and River Path Design Alternative,

recreational use is concentrated. In differentiating from the Low

Impact Development Design Alternative, there is a higher

emphasis on recreational facilities and infrastructure. An

administrative site type modification was added to prioritize day

use recreation to further meet the project objectives.”

The draft EIR explains that alternatives “were assessed for

their ability to reasonably achieve the purpose and need and

reduce environmental impacts.” (See fn. 2, ante, recounting the

stated purpose and need.) “Based on the screening criteria,”

defendant selected Alternative 1 (the project) and Alternative 2

(no action) for detailed analysis in the EIR.

29

The EIR also describes “alternatives considered but

eliminated from full analysis.” This consisted of a “forest closure

alternative” suggested by the California Department of Fish and

Wildlife. This alternative would have closed “all or a portion of

the project site to adequately protect biological resources during

the breeding season of the Santa Ana sucker (March 1 through

August 1).” The draft EIR describes the reasons for eliminating

this alternative from full analysis, including that recreation use

would be restricted during the time of year when most use

currently occurs.

iii. Plaintiff’s contentions

Plaintiff contends CEQA, the Guidelines, and Supreme

Court case law require an EIR to analyze more than the “no

project” alternative. That is not correct.

Plaintiff’s first argument is that CEQA and the Guidelines

consistently use the plural (“alternatives”) rather than the

singular. This point is unconvincing, given the rule of reason

required by the Guidelines and confirmed by the Supreme Court,

telling us the EIR must “ ‘set forth only those alternatives

necessary to permit a reasoned choice’ ” and that “ ‘could feasibly

attain most of the basic objectives of the project.’ ” (Bay-Delta,

supra, 43 Cal.4th at p. 1163; see also Citizens of Goleta Valley v.

Board of Supervisors (1990) 52 Cal.3d 553, 566 “[[e]ach case must

be evaluated on its facts,” and CEQA establishes “no categorical

legal imperative as to the scope of alternatives to be analyzed in

an EIR”].)

Two courts have rejected the contention that an EIR must,

as a matter of law, analyze more alternatives than the no project

alternative. The court in San Franciscans for Livable

Neighborhoods v. City and County of San Francisco (2018)

30

26 Cal.App.5th 596 stated: “To the extent [the plaintiff] would

have us conclude, as a matter of law, that consideration in the

EIR only of a proposed project and a no project alternative is

inadequate, we reject that contention. As explained in Mount

Shasta Bioregional Ecology Center v. County of Siskiyou (2012)

210 Cal.App.4th 184 (Mount Shasta), in response to a similar

claim, ‘there is no rule specifying a particular number of

alternatives that must be included. “CEQA establishes no

categorical legal imperative as to the scope of alternatives to be

analyzed in an EIR. Each case must be evaluated on its facts,

which in turn must be reviewed in light of the statutory

purpose.” ’ ” (Id. at p. 633, quoting Mount Shasta, supra, at

p. 199.)

Plaintiff claims Mount Shasta is an “outlier,” and relegates

San Franciscans for Livable Neighborhoods to a footnote. But

there are no precedents that disagree with the principle stated in

those cases, and we agree with both of them.

Plaintiff then argues that, even if analysis of only a “no

project” alternative is permissible, it is not permissible under the

specific facts of this case. That contention has no merit either.

Plaintiff tells us, correctly, that “public agencies should not

approve projects as proposed if there are feasible alternatives or

feasible mitigation measures available which would substantially

lessen the significant environmental effects of such projects.”

(§ 21002.) Then plaintiff asserts the record shows defendant

“was presented with several feasible alternatives to the Project”

that defendant should have analyzed in the EIR. These consist of

5 one-sentence alternatives listed in the comments from

Mr. Jones, owner of the Bridge to Nowhere, whose vested interest

31

in the impact of the project on his business was noted by

defendant’s board member Ms. Chico.

Mr. Jones’s suggested alternatives were: “1. Increasing

public access to a dispersed area of the Monument; [¶]

2. Preserving natural resources through a combination of

enforcement and public education about high impact behaviors,

and encouraging low impact behaviors; [¶] 3. Providing greater

public access with increased public parking in the East Fork

Overlook area [parking for the Bridge to Nowhere is in this area];

[¶] 4. Funding through government appropriations and

philanthropic sources for the upkeep of improvements rather

than construction of new improvements, and a cost-benefit

analysis of same; and [¶] 5. Providing for parking replacement

during construction, and placing the parking phase last to

minimize the parking impacts during construction of other

improvements.”

From Mr. Jones’s perspective, these alternatives are fine

ideas that would help grow his business, save taxpayer dollars,

and use park rangers and education to reduce environmental

impacts. But CEQA “ ‘does not require that an agency consider

specific alternatives that are proposed by members of the public

or other outside agencies.’ ” (South of Market Community Action

Network v. City and County of San Francisco (2019)

33 Cal.App.5th 321, 345 (South of Market).) “Rather, [an agency

is] responsible for selecting a range of project alternatives that

could feasibly accomplish most of the basic objectives of the

project and could avoid or lessen one or more of its significant

impacts.” (Ibid.) As we have already said, the necessary range is

governed by a rule of reason “ ‘that requires the EIR to set forth

32

only those alternatives necessary to permit a reasoned choice.’ ”

(Ibid.)

Further, “[c]ourts will defer to an agency’s selection of

alternatives unless the petitioners (1) demonstrate that the

chosen alternatives are ‘ “ ‘manifestly unreasonable and . . . do

not contribute to a reasonable range of alternatives,’ ” ’ and

(2) submit evidence showing the rejected alternative was both

‘feasible’ and ‘adequate,’ because it was capable of attaining most

of the basic objectives of the project.” (South of Market, supra,

33 Cal.App.5th at p. 345.)

Here, the project’s intent is “to provide recreational

improvements and ecological restoration,” focusing “on reducing

impacts along the most heavily used section of the river.”

Plaintiff has not shown it is “manifestly unreasonable” to analyze

only the project and the “no project” alternative. Nor has

plaintiff submitted any evidence, or even any argument, to show

that the “alternatives” it suggests “were capable of attaining most

of the basic objectives of the project.” (South of Market, supra,

33 Cal.App.5th at p. 345.) Nor has plaintiff explained how any of

the alternatives would “avoid or lessen one or more of [the

project’s] significant impacts.” (Ibid.) As the WCA board found,

no significant impacts were identified that could not be avoided

or reduced to a less than significant level.

The trial court put it this way: “WCA undertook extensive

[pre-draft EIR] initiatives to adequately design a Project that

would meet its stewardship and recreational goals. WCA

analyzed environmental effects caused by the Project and

concluded that none were significant. WCA then analyzed the

Project and the no project alternative in detail. Under these

circumstances, in particular the nature of the Project and its

33

demonstrably small effect on the environment, the Court agrees

with WCA that consideration of other project alternatives was

unnecessary.”

“[I]t is [the plaintiff’s] burden to demonstrate inadequacy of

the EIR. [A plaintiff] must therefore show the agency failed to

satisfy its burden of identifying and analyzing one or more

potentially feasible alternatives.” (Mount Shasta, supra,

210 Cal.App.4th at p. 199; see ibid. [“Absent a showing that the

EIR failed to include a particular alternative that was potentially

feasible or that, under the circumstances presented, including

only the Project and the ‘No Project’ alternatives did not amount

to a reasonable range of alternatives, plaintiffs’ challenge to the

alternatives analysis fails.”].) That is the case here.

b. Consistency with land use plans

Appendix G of the CEQA Guidelines contains this question:

“Would the project . . . [c]ause a significant environmental impact

due to a conflict with any land use plan, policy, or regulation

adopted for the purpose of avoiding or mitigating an

environmental effect?”

The draft EIR’s discussion of land use and planning covers

both the Angeles National Forest Land Management Plan (LMP)

and President Obama’s designation of the national monument

(proclamation 9194). The draft EIR states that the planning

effort for the project was concurrent with the monument plan and

was “consistent with both the existing [Angeles National Forest]

LMP and the Monument Plan direction.”

Plaintiff contends that, to the contrary, there are “glaring

land use conflicts.” The project’s “drastic reduction in public

parking is at loggerheads with Proclamation 9194’s unambiguous

objective to facilitate the ever-growing ranks of Angelinos [sic] in

34

recreating in the San Gabriel Mountains National Monument.”

The trial court rejected this claim, and we do, too.

Proclamation 9194, after an extensive description of the

San Gabriel Mountains and their history (including that the

lands “provide invaluable backcountry opportunities for the

rapidly expanding nearby communities and also provide habitat

for iconic and endangered species”), states it is in the public

interest “to preserve and protect the objects of scientific and

historic interest at the San Gabriel Mountains.” The president

therefore proclaimed “the objects identified above that are

situated upon” lands owned by the United States to be the

national monument, “for the purpose of preserving those objects.”

It repeatedly requires “the proper care and management of the

objects protected by this proclamation.” It requires a

management plan for the monument that “shall provide for

protection and interpretation of the scientific and historic objects

identified above and for continued public access to those objects,

consistent with their protection.”

We find the project is entirely consistent with the policies

enunciated in the proclamation. Plaintiff elevates public access

for recreation above all other objectives of the proclamation.

Certainly, the proclamation calls “for continued public access to

those objects,” but “consistent with their protection.” Plaintiff

completely ignores the latter phrase.

As the trial court pointed out, the project proposes “to

protect and restore the existing multi-use areas for public

enjoyment” by developing “new picnic areas, pedestrian trails,

river access points and upgrades to existing facilities,

improvements to paved and unpaved roadways, and restoration

of riparian and upland vegetation communities of the [river] and

35

Cattle Canyon Creek.” These improvements comport with the

objective of continued public access, consistent with the

protection of the wilderness being accessed, and they further as

well the overall objective “to preserve and protect the objects of

scientific and historic interest at the San Gabriel Mountains.”

Plaintiff also contends the project is inconsistent with the

Angeles National Forest LMP because it limits recreational use,

while the LMP calls for implementation of other management

actions (such as conservation education) before direct action

limiting visitor use. Defendant responded to plaintiff’s claim in

the final EIR, pointing out that “one of the purposes of the project

is to ‘provide recreation facilities and infrastructure that are high

quality, well-maintained, safe, and accessible to visitors.’ ”

Defendant concluded the project “does not restrict public access to

the Monument; rather, it provides for both new and improved

recreation facilities and amenities to visitors.”

The trial court found no inconsistency between the project

and the LMP, observing: “[Plaintiff] points to no evidence that

the Project would actually eliminate recreational use of the

Project Site. To the contrary, the Project’s features are designed

‘to protect and restore the existing multi-use areas for public

enjoyment’ by implementing sustainability actions. Overall, the

Project is consistent with and furthers this LMP policy.”

We agree with the trial court’s assessment.

4. The Attorney Fee Award

Our disposition of the parties’ appeals on the merits

compels reversal of the trial court’s award of attorney fees to

plaintiff.

36

DISPOSITION

The judgment granting a peremptory writ of mandate is

reversed and the cause is remanded with directions to enter a

new judgment denying the petition for writ of mandate in its

entirety. The order awarding attorney fees is reversed.

Defendant shall recover its costs on appeal.

GRIMES, Acting P. J.

WE CONCUR:

STRATTON, J.

WILEY, J.

37

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.