Opinion

AICI-Archirodon JV

Court
Armed Services Board of Contract Appeals
Filed
Jul 19, 2021
Status
Published
On the bench
Osterhout
Cited by
0 cases
Authority
More cited than 16.0%

“The mere existence of a scintilla of evidence in support of the [non-movant]’s position will be insufficient . . . .”

How later courts described this case

  • “The mere existence of a scintilla of evidence in support of the [non-movant]’s position will be insufficient . . . .”
  • “[I]f the primary intended beneficiary of a statute or regulation is the government, then a private party cannot complain about the government’s failure to comply with that statute or regulation, even if that party derives some incidental benefit from compliance with it.”

Written by the judges who cited it.

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- )

)

AICI-Archirodon JV ) ASBCA No. 62201

)

Under Contract No. W912ER-17-C-0014 )

APPEARANCES FOR THE APPELLANT: Scott M. Heimberg, Esq.

Thomas P. McLish, Esq.

Amanda B. Lowe, Esq.

Akin Gump Strauss Hauer & Feld LLP

Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.

Engineer Chief Trial Attorney

Rebecca L. Bockmann, Esq.

James D. Stephens, Esq.

Engineer Trial Attorneys

U.S. Army Engineer District, Middle East

Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE OSTERHOUT

ON THE PARTIES’ CROSS-MOTIONS FOR SUMMARY JUDGMENT

This appeal involves a contract to replace the Mina Salman Pier in Manama,

Bahrain. The contract required appellant to use United States-flagged vessels to transport

materials unless it applied for and was granted an exception to use a foreign-flag vessel.

The government moves for summary judgment, arguing that appellant failed to properly

request an exception and failed to follow the contract by using a foreign-flagged vessel. 1

Appellant cross-moves for summary judgment, alleging that it properly filed a request for

exception but the contracting officer failed to respond in a timely manner, and that no

harm occurred to the government. We grant the government’s motion, in part, regarding

appellant’s failure to properly request an exception and follow the requirements of the

1 The government also filed a motion in limine to exclude appellant’s expert testimony

and report. The government argued that the Board should shield the record

from the introduction of irrelevant, immaterial, or cumulative matters and that

the expert’s opinion included legal conclusions (gov’t mot. at 1, 14). Based on

this decision, the risk of appellant’s expert report being irrelevant, immaterial,

or cumulative is low. Further, the Board is capable of giving the report and

potential testimony the proper weight it deserves. Thus, the government’s

motion in limine is denied.

contract. We deny the government’s motion as to the amount. Similarly, we deny

appellant’s motion, in part, regarding entitlement but grant appellant’s motion, in part,

concerning the inability to determine the amount based on the record.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS

1. On September 25, 2017, the United States Army Corps of Engineers (USACE

or the government) awarded Contract No. W912ER-17-C-0014 (the contract) to

AICI-Archirodon JV (AAJV or appellant) to replace the Mina Salman Pier at Naval

Support Activity, Manama, Bahrain, at the firm-fixed-price of $48,148,000 (R4, tab 4

at 1-2).

2. The contract incorporated by reference Defense FAR Supplement (DFARS)

252.247-7023, TRANSPORTATION OF SUPPLIES BY SEA (APR 2014) (R4, tab 4

at 14). The clause stated, in part, “(b)(1) The Contractor shall use U.S.-flag vessels

when transporting any supplies by sea under this contract.” Further, the clause

allowed for exceptions to this requirement and provided a method by which the

contractor could request to use a foreign-flag vessel from the contracting officer (CO):

(c) The Contractor and its subcontractors may request that

the Contracting Officer authorize shipment in foreign-flag

vessels, or designate available U.S.-flag vessels, if the

Contractor or a subcontractor believes that—

(1) U.S.-flag vessels are not available for timely shipment;

(2) The freight charges are inordinately excessive or

unreasonable; or

(3) Freight charges are higher than charges to private

persons for transportation of like goods.

(d) The Contractor must submit any request for use of

foreign-flag vessels in writing to the Contracting Officer

at least 45 days prior to the sailing date necessary to meet

its delivery schedules. The Contracting Officer will

process requests submitted after such date(s) as

expeditiously as possible, but the Contracting Officer’s

failure to grant approvals to meet the shipper’s sailing date

will not of itself constitute a compensable delay under this

or any other clause of this contract. Requests shall contain

at a minimum—

2

(1) Type, weight, and cube of cargo;

(2) Required shipping date;

(3) Special handling and discharge requirements;

(4) Loading and discharge points;

(5) Name of shipper and consignee;

(6) Prime contract number; and

(7) A documented description of efforts made to secure

U.S.-flag vessels, including points of contact (with names

and telephone numbers) with at least two U.S.-flag carriers

contacted. Copies of telephone notes, telegraphic and

facsimile message or letters will be sufficient for this

purpose.

(g) In the event there has been unauthorized use of foreign-flag

vessels in the performance of this contract, the Contracting

Officer is entitled to equitably adjust the contract, based on the

unauthorized use.

DFARS 252.247-7023. Before the exemption is issued, the CO “must, by regulation,

seek the advice of one of the military transport commands regarding the U.S.-flag vessel

availability.” The Navy’s Military Sealift Command (MSC) provides formal advice on

the availability of U.S.-flag vessels for voyage and time charters. MSC will then

“consult with the Maritime Administration (MARAD) to ensure that 100% U.S.-flag

service is not available and that U.S. flag vessels are being used to their fullest extent.”

(R4, tab 06A at 2) We find that the 45-day notice requirement is reasonable, given the

coordination with multiple governmental agencies in order to provide the CO the

necessary advice as to the availability of U.S. flag vessels or if the rates quoted to a

contractor are excessive or otherwise unreasonable.

3. By letter dated August 30, 2018, addressed to the CO’s representative

(COR), appellant formally requested to use a foreign-flag vessel to ship steel piles for

the project (R4, tab 6 at 1). Appellant proposed a shipping date range from

September 25, 2018 through October 15, 2018 (id. at 2). Appellant listed the required

information pursuant to DFARS 252.247-7023 (id. at 1-2). For item no. 7, appellant

included a list of requirements for the shipment but did not document a description of

efforts made to hire a U.S-flag vessel, did not provide points of contacts and telephone

numbers of at least two U.S-flag carriers contacted, and did not provide any copies of

3

notes or letters to demonstrate contact with U.S.-flag vessels (id. at 2). The

attachments contained emails discussing the availability of vessels but the ones

addressing U.S.-flag vessels were dated August 28, 2018, or later (id. at 6, 10-16;

see also app. supp. R4, tab 8A-1). The only quoted price for a U.S.-flag vessel that

appellant presented to the CO was $1,384,220 (R4, tab 2 at 4).

4. On September 9, 2018, the CO denied appellant’s request to use a foreign-flag

vessel. The CO stated that appellant failed to make the request 45 days prior to the

sailing date and that appellant only provided supporting documentation dated August 28,

2018, or later, which indicated to the CO that appellant did not make a reasonable effort

to find a U.S.-flag vessel in a reasonable time. (R4, tab 7)

5. On September 18, 2018, appellant responded that it was not feasible to

provide 45 days of notice and provided information about the foreign-flag vessel it had

scheduled to use (R4, tab 8). Appellant stated that it started looking for U.S.-flag

vessels in May 2018 and provided an email to demonstrate the search (id. at 21). The

May 2018 email asked for quotes but the only reference to U.S.-flag vessels was a

single parenthetical: “(if us flag is not available please quote for the standard)” (id.).

No other conversations about U.S.-flag vessels from May 2018 were provided.

Appellant also advised “the delivery of piles is on the critical path and any further

delay will negatively affect the Project completion date.” Thus, appellant indicated

that it was going to proceed with the steel piles transport using a foreign-flagged

vessel. (R4, tab 8)

6. On September 20, 2018, the COR responded that the government received

appellant’s letter stating the intention to use a foreign-flag vessel without approval.

The COR also referenced the contract requirement to use U.S.-flag vessels and cited

DFARS 252.247-7023. Additionally, the COR informed appellant that because the

request was disapproved due to lack of timeliness and insufficient supporting

documentation, the CO could equitably adjust the contract if a foreign-flag vessel was

used. Finally, the COR reminded appellant that these requirements also applied to

subcontractors. The COR included a full-text version of the clause as an attachment.

(R4, tab 9 at 1-2)

7. On September 21, 2018, the CO supplemented the COR’s September 20, 2018

letter, informing appellant that while appellant’s intent to proceed with a foreign-flag

vessel was in violation of the contract and that insufficient evidence was provided to

substantiate the request, the CO would submit the request through the appropriate

channels. The CO stated, “[u]nless and until approved, any shipment not using a U.S.

4

flagged vessel is an unauthorized shipment and any goods included in that shipment may

be rejected by the Government or the contract otherwise adjusted to account for the

non-compliance with the requirement, as indicated in serial letter C-0021.” (R4, tab 10)

8. On October 10, 2018, appellant shipped the piles via a foreign-flag vessel

(compl. at 5).

9. On November 9, 2018, the CO sent appellant a letter stating that she had

forwarded appellant’s request but that MSC would not consider the request because

appellant proceeded with a non-U.S.-flag vessel before MSC made a decision. The

CO notified appellant that the decision to use a foreign-flag vessel violated the

contract and that the government would “take authorized and appropriate action in

response to the violation.” (R4, tab 11)

10. On December 12, 2018, the CO informed appellant that she would

equitably adjust the contract for the difference in price between the cost of shipping

via the U.S.-flag vessel appellant quoted and the foreign-flag vessel appellant used.

The CO asked appellant to respond no later than December 21, 2018. (R4, tab 12)

11. On December 19, 2018, appellant responded that it had to ship with a

foreign-flag vessel because of time constraints on the contract and because a U.S.-flag

vessel was five times the cost of the foreign-flag vessel (R4, tab 13 at 1-2).

12. On April 9, 2019, the CO sent appellant a letter stating that the government

planned to reduce the amount of the contract by $1,384,220 to reflect the price of the

U.S.-flag vessel quoted in appellant’s August 30, 2018 request (R4, tab 14 at 2).

However, the CO offered to decrease the reduction to the difference between that

quote and the price appellant paid for the foreign-flag vessel—$1,107,376—if

appellant signed and returned an attached modification by April 15, 2019 (id. at 3).

13. On April 13, 2019, appellant responded and asked the CO to reconsider the

downward adjustment, and did not sign the modification (R4, tab 15 at 1-3).

14. On April 16, 2019, the CO issued unilateral Modification No. P00009

which decreased the price of the contract by $1,384,220, which was the subject matter

of appellant’s claim and appeal. In the modification, the CO stated, “[t]he adjusted

price reflects the cost represented by AICI/Archirodon JV to ship these specific

materials in accordance with DFARS 252.247-2023, a total of $1,384,220. The

Government has elected not to increase the adjustment by assessing penalties or

applying the contractor’s indirect rates.” (R4, tab 5 at 1-2)

5

DECISION

The Parties’ Contentions

The government argued that appellant failed to comply with the contract by

using a foreign-flag vessel without authorization, and thus the government was entitled

to equitably adjust the contract price by the amount appellant saved by violating the

contract (gov’t mot. at 1). Appellant argued that it properly requested approval to use

a foreign-flag vessel, that the government’s CO failed to respond to its request in a

timely manner, and that the government was not harmed as a result of appellant’s use

of a foreign-flag vessel. Thus, according to appellant, reduction of the contract price

was inappropriate. (App. mot. at 3)

Standard of Review

Summary judgment is proper when there are no genuine issues of material fact

and the movant is entitled to judgment as a matter of law. Celotex Corp. v. Catrett,

477 U.S. 317, 322 (1986); Mingus Constructors, Inc. v. United States, 812 F.2d 1387,

1390 (Fed. Cir. 1987). A fact is material if it may affect the outcome of the decision.

Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-49 (1986). The movant bears the

burden of establishing the absence of any genuine issue of material fact. Celotex,

477 U.S. at 322. Regardless of the type of claim being raised, the applicable

substantive law determines which facts are material and thus preclude an entry of

summary judgment. Liberty Lobby, 477 U.S. at 248. Such facts must be viewed in the

light most favorable to the non-moving party. Id. at 255; C. Sanchez and Son, Inc. v.

United States, 6 F.3d 1539, 1541 (Fed. Cir. 1993). However, the non-movant must set

forth specific facts demonstrating the existence of a genuine issue of material fact;

mere conclusory statements and bare assertions are inadequate. Mingus, 812 F.2d

at 1390-91; Liberty Lobby, 477 U.S. at 252 (“The mere existence of a scintilla of

evidence in support of the [non-movant]’s position will be insufficient . . . .”). Our

responsibility is not “‘to weigh the evidence and determine the truth of the matter,’

but rather to ascertain whether material facts are disputed and whether there exists any

genuine issue for trial.” Holmes & Narver Constructors, Inc., ASBCA Nos. 52429,

52551, 02-1 BCA ¶ 31,849 at 157,393 (quoting Liberty Lobby, 477 U.S. at 249).

Appellant Failed to Comply with Contract’s Unambiguous Terms

The government argued that appellant violated DFARS 252.247-7023’s

unambiguous terms by shipping the steel piles via foreign-flag vessel (gov’t mot. at 35).

A contract is ambiguous if it is reasonably susceptible to more than one interpretation.

Edward R. Marden Corp. v. United States, 803 F.2d 701, 705 (Fed. Cir. 1986). The

Board must look to the plain language of the contract to determine if it is ambiguous.

American Int’l Contractors, Inc., ASBCA Nos. 60948, 61166, 18-1 BCA ¶ 37,061

6

at 180,411. If the contract’s terms are clear and unambiguous, they must be given their

plain and ordinary meaning. Alaska Lumber & Pulp Co. v. Madigan, 2 F.3d 389,

392 (Fed. Cir. 1993). The Board may not use extrinsic evidence to “introduce an

ambiguity where none exists.” Interwest Constr. v. Brown, 29 F.3d 611, 615 (Fed. Cir.

1994); see also American Int’l Contractors, 18-1 BCA ¶ 37,061 at 180,411.

Here, the contract incorporated DFARS 252.247-7023. The plain language of

the clause required that appellant “use U.S.-flag vessels when transporting any

supplies by sea under this contract.” The clause provided exceptions to this

requirement—including both lack of availability of U.S.-flag vessels and excessive

costs—with proper authorization from the CO. The clause also explicitly entitled the

CO to “equitably adjust the contract, based on the unauthorized use” if a foreign-flag

vessel was used without prior approval. (SOF ¶ 2)

The clause required a contractor to submit a written request to the CO at least

45 days prior to the shipping date before using a foreign-flag vessel (SOF ¶ 2). On

August 30, 2018, appellant submitted such a request, which the CO denied on

September 9, 2018 (SOF ¶¶ 3-4). After appellant subsequently notified the CO of its

intention to use a foreign-flag vessel without approval, the CO informed appellant that

“[u]nless and until approved, any shipment not using a U.S. flagged vessel is an

unauthorized shipment and any goods included in that shipment may be rejected by the

Government or the contract otherwise adjusted to account for the non-compliance with

the requirement . . . .” (SOF ¶ 7). Moreover, DFARS 252.247-7023(d) provided that

“the Contracting Officer’s failure to grant approvals to meet the shipper’s sailing date

will not of itself constitute a compensable delay under this or any other clause of this

contract” (SOF ¶ 2). It is therefore undisputed that when appellant shipped the steel

piles on October 10, 2018, via a foreign-flag vessel (SOF ¶ 8), it did so without the

CO’s authorization, and thus violated the terms of the contract.

The CO’s Denial of Appellant’s Request to use a Foreign-Flag Vessel was Proper

Since the undisputed facts show that appellant violated the contract by shipping

the steel piles via a foreign-flag vessel without the CO’s approval, our decision turns

on whether the CO’s denial of appellant’s request to use a foreign-flag vessel was

proper. Appellant contended that the CO should have granted its request to use a

foreign-flag vessel because no suitable U.S.-flag vessel was available to transport the

steel piles at a reasonable cost at the time it needed to ship them (app. mot. at 14-16).

However, as the government argued, even if the CO erred in denying appellant’s

request, appellant must prove that her decision amounted to an abuse of discretion in

order for its claim to have merit. See Empire Energy Management Systems, Inc.,

ASBCA No. 46741, 03-1 BCA ¶ 32,079 at 158,553. When reviewing a CO’s

discretionary action, the Board may not substitute its own judgment for that of the CO;

rather, the Board may only review the decision to determine whether the CO’s action

7

amounts to an abuse of discretion or is otherwise arbitrary and capricious. Id. This

assessment requires an evaluation of four factors: (1) whether the CO acted in bad

faith; (2) whether the CO had a reasonable, contract-related basis for the decision;

(3) whether the CO overreached the amount of discretion accorded to her; and

(4) whether the CO violated any relevant statutes and/or regulations so as to render the

decision arbitrary and capricious. Id.; Raytheon Co., ASBCA No. 57743 et al.,

17-1 BCA ¶ 36,724 at 178,854.

The first question is whether the CO acted in bad faith. Government officials

are strongly presumed to carry out their duties in good faith; every contract imposes

upon each party a covenant of good faith and fair dealing in its performance and

enforcement. Metcalf Constr. Co. v. United States, 742 F.3d 984, 990 (Fed. Cir.

2014). However, this implicit duty “cannot expand a party’s contractual duties beyond

those in the express contract or create duties inconsistent with the contract’s

provisions.” Id. at 991 (quoting Precision Pine & Timber, Inc. v. United States,

596 F.3d 817, 831 (Fed. Cir. 2010)). The proper inquiry regarding the duty of good

faith and fair dealing “boils down to questions of ‘reasonableness’ of the government’s

actions.” Relyant, LLC, ASBCA No. 59809, 18-1 BCA ¶ 35,085 at 180,539, aff’d on

recon. 18-1 BCA ¶ 37,146. Appellant has not presented any evidence that the CO, nor

any other government representative, acted unreasonably.

Regarding the second factor, appellant must establish that the CO did not have a

reasonable, contract-related basis for denying appellant’s request to use a foreign-flag

vessel. Raytheon, 17-1 BCA ¶ 36,724 at 178,854. Appellant alleged that its August 30,

2018 request to use a foreign-flag vessel was proper under DFARS 252.247-7023 (app.

mot. at 7-8). DFARS 252.247-7023 required that a contractor requesting to use a

foreign-flag vessel submit to the CO, among other items, “[a] documented description of

efforts made to secure U.S.-flag vessels, including points of contact (with names and

telephone numbers) with at least two U.S.-flag carriers contacted” (SOF ¶ 2). While

appellant included a list of requirements for the shipment with its request, it failed to

provide a description of any efforts made to hire a U.S-flag vessel, points of contacts or

telephone numbers of at least two U.S-flag carriers it contacted, and copies of notes or

letters to demonstrate contact with U.S.-flag vessels (SOF ¶ 3). Furthermore, the clause

required that the contractor submit its request at least 45 days before its proposed

shipping date (SOF ¶ 2). Appellant submitted its request just 26 days before

September 25, 2018—the earliest of its proposed shipping dates (see SOF ¶ 3).

Moreover, appellant informed the CO on September 18, 2018, that it was proceeding with

the shipment using a foreign flag vessel, in clear violation of the contract (SOF ¶ 5).

Because appellant’s August 30 request did not include all of the required information

under DFARS 252.247-7032(d), was not timely submitted, and was subsequently

rendered obsolete by its unilateral action, we conclude that appellant has failed to

demonstrate that the CO lacked a valid, contract-related basis for denying the request.

8

Turning to the third element, we must consider the amount of discretion vested

in the CO under the contract. Raytheon, 17-1 BCA ¶ 36,724 at 178,854. Under the

terms of the contract, the CO was the only person with the authority to approve or

deny a request from appellant to use a foreign-flag vessel (SOF ¶ 2). Using this

authority, the CO denied appellant’s initial request to use a foreign-flag vessel to ship

the steel piles, and reaffirmed her denial when appellant informed her it intended to

proceed with using a foreign-flag vessel anyway (SOF ¶¶ 4, 6). Appellant presented

no evidence alleging that the CO exceeded her authority in doing so.

Finally, the Board must determine whether the CO violated any relevant statutes

or regulations that would render her denial of appellant’s request arbitrary and capricious.

Raytheon, 17-1 BCA ¶ 36,724 at 178,854. In order for a contractor to successfully bring

a claim against the government for violating a regulation, that regulation must exist for

the benefit of the contractor—not the government. Parsons Evergreene, LLC, ASBCA

No. 61784, 18-1 BCA ¶ 37,135 at 180,725 (citing Freightliner Corp. v. Caldera,

225 F.3d 1361, 1365 (Fed. Cir. 2000); Cessna Aircraft Co. v. Dalton, 126 F.3d 1442,

1451 (Fed. Cir. 1997); Rough Diamond Co. v. United States, 351 F.2d 636,

640-42 (Ct. Cl. 1965)). Therefore, even if the CO violated a regulation, a contractor does

not have a cause of action against the government if the regulation exists for the

government’s benefit. See Cessna, 126 F.3d at 1451. While a regulation may benefit

both the government and the contractor in practice, “the operative test is not that

application of the regulation merely be to the benefit of the contractor in the particular

controversy for which it is bringing suit, but that the contractor has been an intended

beneficiary all along.” Parsons Evergreene, 18-1 BCA ¶ 37,135 at 180,725; see also

Freightliner, 225 F.3d at 1366; Cessna, 126 F.3d at 1451-52 (“[I]f the primary intended

beneficiary of a statute or regulation is the government, then a private party cannot

complain about the government’s failure to comply with that statute or regulation, even if

that party derives some incidental benefit from compliance with it.”).

Appellant pointed to only one relevant regulation in its argument:

DFARS 252.247-7023. Appellant alleged that the CO violated DFARS 252.247-

7023(d)—which requires the CO to process a request to use a foreign-flag vessel “as

expeditiously as possible”—by failing to timely authorize its shipment via a foreign-flag

vessel. (App. mot. at 7-14) However, as the government pointed out, the legislative

history behind DFARS 252.247-7023 indicated that the intended beneficiary is the

government (through its interest in a strong U.S. flag commercial merchant marine)2—

not contractors. DFARS 247.5, OCEAN TRANSPORTATION BY U.S.-FLAG

VESSELS (OCT 2010), implemented the Cargo Preference Act of 1904 (10 U.S.C.

2 As put forward by MARAD “history has tought us that. . .the reservation of certain

cargoes to U.S.-flag ships, is necessary for our national defense and a key driver

of domestic and foreign commerce.” Maritime.dot.gov/ports/cargo-preference,

last visited June 29, 2021.

9

§ 2631) and directed the inclusion of DFARS 252.247-7023 in contracts with the

Department of Defense. DFARS 247.572 “Policy” stipulates:

(a) In accordance with 10 U.S.C. 2631(a), DoD contractors

shall transport supplies, as defined in the clause

at 252.247–7023, Transportation of Supplies by Sea,

exclusively on U.S.-flag vessels unless—

(1) Those vessels are not available;

(2) The proposed charges to the Government are higher

than charges to private persons for the transportation of

like goods; or

(3) The proposed freight charges are excessive or

unreasonable.

DFARS 247.572.

The Cargo Preference Act, which requires the use of U.S.-flag vessels to

transport supplies bought for or purchased by the military or defense agencies, was

enacted to promote the U.S. merchant marine industry over lower-cost foreign

competition—not to benefit contractors. See 10 U.S.C. § 2631. Thus, the fact that

some of DFARS 252.247-7023’s provisions—including the requirement that the CO

process requests to use foreign-flag vessels “as expeditiously as possible”—may

incidentally benefit appellant does not change the fact that the government is the

regulation’s intended beneficiary. Cessna, 126 F.3d at 1451-52. Accordingly, even if

appellant could prove that the CO violated DFARS 252.247-7023 by failing to timely

authorize the request, it would still not be entitled to recovery under this theory.

See id. at 1451; Parsons Evergreene, 18-1 BCA ¶ 37,135 at 180,725.

Appellant failed to meet its burden of demonstrating that the CO abused her

discretion in rejecting appellant’s request to use a foreign-flag vessel or by failing to

authorize its request in a timely manner. Accordingly, as a matter of law the

government is entitled to adjust the contract price. See Empire Energy, 03-1 BCA

¶ 32,079 at 158,553.

Argument That Non-Compliance was Harmless is Irrelevant

Appellant further asserted that the government “suffered no harm” (app. mot.

at 16-18) from its non-compliance. However, we agree with the government that this

argument ultimately fails because the Board’s primary consideration when

10

determining equitable adjustment is the change in the contractor’s cost of performance,

not damages to the government. Federal Boiler Co., ASBCA No. 40314, 94-1 BCA

¶ 26,381 at 131,217.

Deduction Amount

“We have held that, when a contractor performs in a less costly manner than

required by the contract, the Government is entitled to realize these savings; the change

in cost of performance to the contractor, and not damages to the Government, is the

basis of adjustment (even when the contractor’s bid did not anticipate incurrence of the

costs).” Federal Boiler, 94-1 BCA ¶ 26,381 at 131,217 (citing Davis Constructors,

Inc., ASBCA No. 40630, 91-1 BCA ¶ 23,394 at 117,391-92; Bruce Andersen Co.,

ASBCA Nos. 29412, 32247, 89-2 BCA ¶ 21,872 at 110,037). Here, instead of

deducting the changed amount of the cost of performance to the contractor, the

government reduced the contract by $1,384,220, the full amount of the quote for the

U.S. flag ship (SOF ¶ 14). The pleadings and the record before us do not demonstrate

the proper deduction amount. Thus, we cannot decide quantum at this time.

CONCLUSION

We grant the government’s motion for summary judgment for entitlement but

deny it as to quantum. Similarly, we deny appellant’s motion for summary judgment

concerning entitlement but grant appellant’s motion to the extent that we cannot decide

quantum based upon the record as we have it before us. Thus, the matter is returned to

the parties to determine quantum in accordance with this decision.

Dated: July 19, 2021

HEIDI L. OSTERHOUT

Administrative Judge

Armed Services Board

of Contract Appeals

(Signatures continued)

11

I concur I concur

RICHARD SHACKLEFORD OWEN C. WILSON

Administrative Judge Administrative Judge

Acting Chairman Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA No. 62201, Appeal of

AICI-Archirodon JV, rendered in conformance with the Board’s Charter.

Dated: July 19, 2021

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

12

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.