Opinion

Sirius Federal, LLC v. United States

Court
United States Court of Federal Claims
Filed
Apr 14, 2021
Status
Published
On the bench
Edward H. Meyers
Cited by
0 cases
Authority
More cited than 15.3%

“A court reviewing a best value procurement agency action must be highly deferential, and the agency that made the determination in question is presumed to have acted in a reasonable and rational manner.”

How later courts described this case

  • “A court reviewing a best value procurement agency action must be highly deferential, and the agency that made the determination in question is presumed to have acted in a reasonable and rational manner.”
  • “To establish prejudice, [plaintiff] must show that there was a ‘substantial chance’ it would have received the contract award but for the alleged error in the procurement process.”
  • “We therefore construe the term ‘interested party’ in § 1491(b)(1) in accordance with the CICA.”
  • rejecting protest standing for a contract dispute over the close out method for an existing contract that plaintiff had performed on for more than ten years

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

Nos. 21-1030C, 21-1041C, 21-1043C & 21-1053C

Originally Filed: March 29, 2021

Re-issued: April 14, 20211

________________________________________

)

SIRIUS FEDERAL, LLC )

(f/k/a FORCE 3, LLC), )

CDW GOVERNMENT LLC, )

COUNTERTRADE PRODUCTS, INC., and )

BLUE TECH INC., )

)

Plaintiffs, )

)

v. )

)

THE UNITED STATES, )

)

Defendant, )

)

and )

)

TELOS CORPORATION, and )

RED RIVER TECHNOLOGY LLC, )

)

Defendant-Intervenors. )

________________________________________ )

David A. Edelstein, Asmar, Schor & McKenna, PLLC, Washington, D.C., for Plaintiff Sirius

Federal, LLC (f/k/a FORCE 3, LLC). Laurence Schor, of counsel.

David Y. Yang, K&L Gates LLP, Seattle, WA, for Plaintiff CDW Government LLC. Stuart B.

Nibley, Erica L. Bakies, Sarah F. Burgart, and Melody A. Alemansour, of counsel.

Scott F. Lane, Thompson Coburn LLP, St. Louis, MO, for Plaintiff CounterTrade Products, Inc.

Katherine S. Nucci and Jayna Marie Rust, of counsel.

Paul F. Khoury, Wiley Rein LLP, Washington, D.C., for Plaintiff Blue Tech Inc. Brian G.

Walsh, Cara L. Lasley, Sarah B. Hansen, and Adam R. Briscoe, of counsel.

1

The Court initially filed this opinion under seal so that the Parties could propose redactions.

The redactions are indicated by bracketed ellipses (“[ … ]”) below.

Reta E. Bezak, Trial Attorney, United States Department of Justice, Civil Division, Washington,

D.C., with whom were Brian M. Boynton, Acting Assistant Attorney General, Robert E.

Kirschman, Jr., Director, Patricia M. McCarthy, Assistant Director, Catharine Parnell and Bret

Vallacher, Trial Attorneys, and Jaron E. Chriss, General Services Administration, Office of the

General Counsel, Southeast Sunbelt Division, Senior Assistant Regional Counsel, of counsel.

C. Peter Dungan, Miles & Stockbridge P.C., Washington, D.C., for Defendant-Intervenor Telos

Corporation. Roger V. Abbott and Jarrod R. Carman, of counsel.

Gregory R. Hallmark, Holland & Knight LLP, Tysons, VA, for Defendant-Intervenor Red River

Technology LLC. Amy L. Fuentes and Kelsey M. Hayes, of counsel.

OPINION AND ORDER

MEYERS, Judge.

Pending before the Court in this multi-party consolidated protest are two motions for

preliminary injunctive relief and two motions to dismiss three of the Plaintiffs. The motions for

preliminary injunctive relief seek to prohibit the Government from issuing any orders against the

disputed Blanket Purchase Agreements while this action is pending. The motions to dismiss,

filed by the Defendant-Intervenors but not the Government, allege that three of the Plaintiffs lack

standing. For the reasons explained below, the pending motions are each denied.

I. Factual Background

A. The Solicitation.

On March 4, 2019, the United States, acting through the General Services

Administration, Federal Acquisition Service, Information Technology Category (“GSA” or the

“Government” or the “Agency”) issued RFQ No. 47QTCA-19-Q-0009 (the “RFQ”) for the “2nd

Generation Information Technology Blanket Purchase Agreement” program (“2GIT”). Sirius

Federal Compl. ¶¶ 1, 10; CDW-G Compl. ¶¶ 1, 10; CounterTrade Compl. ¶¶ 1, 13; Blue Tech

Compl. ¶¶ 1, 29. The RFQ contemplated the award of multiple firm-fixed-price BPAs under

FAR 8.405-3(b) with a five-year period of performance. RFQ § 4, D. Appx at 142; RFQ § 6, D.

Appx at 152. Under this procurement, GSA sought multiple award BPAs for IT “hardware and

software commodities, ancillary supplies and services as a follow on to the First Generation

Information Technology (1GIT) BPAs.” See RFQ § 2.1, D. Appx at 141. The RFQ anticipated

nine BPA awards, but GSA reserved the right to make additional awards at its discretion. RFQ §

15.1, D. Appx at 187-88.

The 2GIT BPAs “will contain attributes not found in other IT commodity acquisitions

solutions within the Federal Government” and will “decrease costs, reduce paperwork and save

time by eliminating the need for repetitive, individual purchases from the GSA Schedule

contract.” RFQ § 2.2, D. Appx at 142. 2GIT also incorporates security and supply chain risk

management procedures. See RFQ § 5, D. Appx at 145-46. Based upon these attributes, the

United States Air Force “has decided to make the 2GIT BPA a mandatory use vehicle for the

2

replacement of the NETCENTS-2 Products IDIQ contract,” which expired in 2019. RFQ § 2.2,

D. Appx at 142; see also CDW-G Compl. at 1.

The 2GIT RFQ describes the basis for awards as a tradeoff of non-price factors and price.

RFQ § 15.1, D. Appx at 187. The RFQ states that “[t]he Government will consider all non-price

and price factors in addition to a comparative consideration of price, special features, [and]

administrative costs to meet the Government’s needs . . . . All evaluation factors other than cost

or price, when combined, are significantly more important the cost or price.” Id. The

solicitation also notes that a goal of the multiple award BPAs is to provide a broad network of

original equipment manufacturers (“OEMs”). RFQ § 15.1, D. Appx at 187-88. The RFQ notes

that GSA may adjust the number of awardees in furtherance of the goal of broad OEM coverage.

RFQ § 15.1, D. Appx at 188.

The RFQ identifies four non-price factors: (1) breadth of OEMs (“BOEM”); (2) relevant

experience; (3) socioeconomic considerations; and (4) supply chain risk management (“SCRM”).

RFQ “Non-Price Factors”, D. Appx at 189. Quotes largely consist of self-scoring assessments

for each factor. The RFQ cautions that exaggerated self-scoring assessments could result in the

quoter’s elimination from further consideration. RFQ “Non Price Factors (e)”, D. Appx at189.

The price factor consists of a market basket evaluation in which quoters provide a quote

for each product in a market basket compiled by GSA. RFQ § 15.2.1, D. Appx at 190. The RFQ

warns that “[q]uoters must quote on each item in the market basket” and that “[q]uoters must

quote products that meet or exceed the minimum salient characteristics specified for each item

listed in the market basket.” Id. The RFQ also requires quoters to “submit documentation to

support their claim that each product they quoted meets the minimum salient characteristics

specified.” Id. The required supporting documentation included submission of specification

sheets on each OEM—that is, technical data sheets or product brochures that summarize “the

performance and other characteristics of a product in sufficient detail that allows the evaluation

team to understand what the product is and if the item meets or exceeds the Government[’]s

minimum salient characteristics of the item requested.” RFQ § 15.2.1, D. Appx at 191. If a

quoter does not include all items in the market basket or if its quoted items are deemed

technically unacceptable, the quoter will be eliminated and ineligible for award unless the

deficiency was cured. RFQ § 15.2.1.1.3, D. Appx at 193.

The RFQ allows for the use of Contractor Teaming Arrangements (“CTAs”). See RFQ §

10.10, D. Appx at 155. CTA Team Members, like their CTA Team Lead counterparts, are

required to have IT Schedule 70 contracts. Id. The RFQ requires CTAs to provide a copy of

their CTA agreements along with their quotes but does not otherwise place constraints on the

form or format of these agreements. D. Appx at 156. In the event a CTA is chosen for award,

the RFQ expressly addresses that CTA Team Members are not Subcontractors and summarizes

the key differences. See RFQ “CTAs versus Prime/Subcontractor Relationships”, D. Appx at

159 (stating among other differences that “Each team member has privity of contract with the

government and can interact directly with the government.”).

B. Procurement History.

3

GSA initially made awards under the RFQ in November 2019. See D. Appx 879.

Several unsuccessful bidders subsequently filed protests at the Government Accountability

Office (“GAO”) and, as a result, GSA took corrective action in December 2019. D. Appx 879.

In May 2020, the Agency again issued awards, and again numerous unsuccessful bidders filed

GAO protests, resulting in another corrective action. D. Appx 880-81.

On August 10, 2020, GSA issued Amendment 18 to the RFQ which, among other things,

changed the basis of award from Highest Rated Quoters with a Fair and Reasonable Price to a

best value tradeoff approach. D. Appx 881; see also D. Appx 187. Quoters were cautioned to

closely review the entire revised solicitation document. See, e.g., D. Appx 138, 186, 223

(“Quoters are expected to examine this entire revised BPA solicitation document. Failure to do

so will be at the Quoter’s own risk.”). Revised quotes were due on August 31, 2020. D. Appx

136. On August 18, 2020, the Agency issued Amendment 19 to update the BOEM self-scoring

assessment. D. Appx 256-57. GSA issued a final amendment, Amendment 20, on August 31,

2020 solely to extend the closing time for quotes an additional hour because of a short period of

submission portal inaccessibility. D. Appx 258.

GSA received 27 quotes in response to the revised solicitation. The 27 quotes were

submitted through CTA submissions—that is, numerous contractors entered into agreements

whereby the team members combined their capabilities to meet the procurement requirements.

See D. Appx155-59 (describing CTAs); see also D. Appx 886-87 (identifying the number of

team members participating in each quote). The solicitation did not preclude individual

companies from participating in more than one quote, and therefore many companies were

members of more than one team. See, e.g., D. Appx 981-84. CTA members, unlike

subcontractors, would be considered in privity with the Government for the work they were to

perform if their teams were chosen for award. D. Appx 159. CounterTrade submitted a quote as

team lead but was also a member of another team that obtained a BPA award, led by [ … ]. See

D. Appx 981; see also D. Appx 32-42. Sirius Federal (formerly known as Force 3, LLC) was a

member of [ … ] winning teams, D. Appx 982, and Blue Tech was a member of [ … ] winning

teams, D. Appx 981. CDW-G submitted a quote as a team lead but was not a member of any

winning team. D. Appx 886, 981.

GSA also engaged in two rounds of confer sessions with the quoters. D. Appx 901.

Relevant to CounterTrade’s Motion for Preliminary Injunction, on November 25, 2020, GSA

informed CounterTrade (in its position as team lead), via a Confer Session Notice, that some of

its items exceeded the minimum salient characteristics which [ … ]. See CounterTrade Compl.

¶¶ 38-39. The Confer Session Notice also provided CounterTrade the fair opportunity to revise

its quote. Id. at ¶ 43.

At the conclusion of the confer sessions, the Agency conducted evaluations of each factor

for each quote. Finally, the contracting team considered the evaluations and engaged in a best

value determination analysis that included a comparative evaluation of quoters’ non-price and

price quote features. D. Appx 945-77. GSA ultimately selected nine quoters for award. D.

Appx 975-76. GSA informed Plaintiffs of the award decision on February 18, 2021. Sirius

Federal Compl. ¶ 37; CDW-G Compl. ¶ 45; CounterTrade Compl. ¶ 46; Blue Tech Compl. ¶ 44.

4

II. Procedural Background.

On March 5, 2021, Sirius Federal, LLC (“Sirius Federal”) filed its bid protest with this

Court (“Sirius Federal Compl.”). ECF No. 1. On March 9, 2021, CDW Government LLC

(“CDW-G”) filed its related bid protest with this Court (“CDW-G Compl.”). Case No. 21-1041,

ECF No. 1. On March 10, 2021, CounterTrade Products, Inc. (“CounterTrade”) filed its related

bid protest with this court (“CounterTrade Compl.”). Case No. 21-1043, ECF No. 1. On March

11, 2021, Blue Tech Inc. (“Blue Tech”) filed its related bid protest with this Court (“Blue Tech

Compl.”). Case No. 21-1053, ECF No. 1. These four related bid protests were consolidated with

Sirius Federal as the lead case because they concern the same solicitation and contain factual and

legal commonalities. ECF No. 12, ECF No. 22, ECF No. 27. On March 9, 2021, CDW-G filed

its Motion for Preliminary Injunction and Memorandum in Support (“CDW-G Mot.”). Case No.

21-1041, ECF No. 5. On March 12, 2021, CounterTrade filed its Motion for Preliminary

Injunction, ECF No. 39, and Memorandum in Support, ECF No. 40 (“CounterTrade Mot.”).

Neither Sirius Federal nor Blue Tech sought preliminary Injunctive Relief. On March 17, 2021,

Defendant-Intervenor Telos Corporation (“Telos”) filed a Motion to Dismiss under Rule of the

United States Court of Federal Claims (“RCFC”) 12(b)(1) for lack of subject matter jurisdiction

(“Telos MTD”), ECF No. 52, and Defendant-Intervenor Red River Technology LLC (“Red

River”) filed a Motion to Dismiss under RCFC 12(b)(1) for lack of subject matter jurisdiction

(“Red River MTD”), ECF No. 55. Also on March 17, 2021, the Government filed its Response

to CDW-G’s and CounterTrade’s Preliminary Injunctions (“Def. Resp.”), ECF No. 53, and Red

River filed its Response to CDW-G’s and CounterTrade’s Preliminary Injunctions (“Red River

Resp.”), ECF No. 54. On March 19, 2021, CounterTrade filed its Reply in Support of its Motion

for Preliminary Injunction and Response to Defendant-Intervenors’ Motions to Dismiss

(“CounterTrade Reply” or “CounterTrade Resp.”). ECF No. 56. On March 19, 2021, Blue Tech

filed its Response to Defendant-Intervenors’ Motions to Dismiss (“Blue Tech Resp.”), ECF No.

57, and Sirius Federal filed its Response to Defendant-Intervenors’ Motions to Dismiss (“Sirius

Federal Resp.), ECF No. 58. Lastly, on March 19, 2021, CDW-G filed its Reply in Support of

its Motion for Preliminary Injunction (“CDW-G Reply”). ECF No. 59. Oral argument was

heard on both the Motions to Dismiss and Motions for Preliminary Injunction on March 22,

2021. These matters are now ripe for review.

III. Defendant-Intervenors’ Motions to Dismiss.

Given that some, but not all, of the numerous parties are subject to the motions to

dismiss, a quick summary about which parties bring or are subject to the pending motions is in

order before wading into the various arguments. Defendant-Intervenors Telos, ECF No. 52, and

Red River, ECF No. 55, move to dismiss the complaints of Plaintiff Sirius Federal (formerly

known as Force 3, LLC), CounterTrade, and Blue Tech for lack of standing under RCFC

12(b)(1). Because many of the arguments are common to multiple parties, the Court will refer to

Telos and Red River collectively as “Defendant-Intervenors” and to Sirius, Blue Tech, and

CounterTrade collectively as “Plaintiff-Awardees.” The motions to dismiss do not challenge

Plaintiff CDW-G’s standing. The Government does not move to dismiss any Plaintiff’s

complaint.

A. Standard of Review.

5

Whether this Court has jurisdiction to decide the merits of a case is a threshold matter.

See PODS, Inc. v. Porta Stor, Inc., 484 F.3d 1359, 1365 (Fed. Cir. 2007). The burden of proving

that the Court of Federal Claims has subject matter jurisdiction over a claim lies with the party

seeking to invoke its jurisdiction. Alder Terrace, Inc. v. United States, 161 F.3d 1372, 1377

(Fed. Cir. 1998). This burden must be established by a preponderance of evidence. Reynolds v.

Army & Air Force Exch. Serv., 846 F.2d 746, 748 (Fed. Cir. 1988). When deciding a Rule

12(b)(1) Motion to Dismiss, the Court “must accept as true all undisputed facts asserted in the []

complaint and draw all reasonable inferences in favor of the [non-movant].” Acevedo v. United

States, 824 F.3d 1365, 1368 (Fed. Cir. 2016) (quoting Trusted Integration, Inc. v. United States,

659 F.3d 1159, 1163 (Fed. Cir. 2011).) Further, the Court “presumes that general allegations

embrace those specific facts that are necessary to support the claim.” Lujan v. Nat’l Wildlife

Fed’n, 497 U.S. 871, 889 (1990). When making its determination, the Court is allowed to

consider not only “the allegations in the complaint, [but] may also look to ‘matters incorporated

by reference or integral to the claim, items subject to judicial notice, [and] matters of public

record.’” A&D Auto Sales, Inc., v. United States, 748 F.3d 1142, 1147 (Fed. Cir. 2014) (quoting

5B Charles Alan Wright & Arthur R. Miller, Federal Practice and Procedure § 1357 (3d ed.

2004)); see Terry v. United States, 103 Fed. Cl. 645, 652 (2012) (collecting cases). If the Court

determines that it lacks subject matter jurisdiction, “the court must dismiss the action.” RCFC

12(h)(3).

B. The challenged Plaintiffs have established their standing.

The question presented is whether the Plaintiff-Awardees, which are members of teams

that won BPA awards in this procurement, have standing to pursue their protest actions

challenging the Government’s rejection of their quotes as team leads. According to Defendant-

Intervenors, the Plaintiff-Awardees status as CTA Team Members defeats their standing here.

Because “standing is a threshold jurisdictional question,” the Court is required to decide this

issue before proceeding to the merits. Myers Investigative & Sec. Servs., Inc. v. United States,

275 F.3d 1366, 1369 (2002) (citing Steel Co. v. Citizens for a Better Env’t, 523 U.S. 83, 102-04

(1998)).

The Tucker Act gives this Court “jurisdiction to render judgment on an action by an

interested party objecting to . . . the award of a contract . . . .” 28 U.S.C. § 1491(b)(1). “The

standing issue in this case is framed by 28 U.S.C. § 1491(b)(1), which we have found imposes

more stringent standing requirements than Article III.” Weeks Marine, Inc. v. United States, 575

F.3d 1352, 1359 (Fed. Cir. 2009). Because the Tucker Act does not define “interested party,” the

Federal Circuit has determined that the proper definition is found in the Competition in

Contracting Act (“CICA”). Am. Fed’n of Gov’t Emps., AFL–CIO v. United States, 258 F.3d

1294, 1302 (Fed. Cir. 2001) (“We therefore construe the term ‘interested party’ in § 1491(b)(1)

in accordance with the CICA.”); see also Eskridge & Assocs. v. United States, 955 F.3d 1339,

1344 (Fed. Cir. 2020); Sys. Application & Techs., Inc. v. United States, 691 F.3d 1374, 1382

(Fed. Cir. 2012). Applying the “interested party” definition from the CICA (31 U.S.C. §

3551(2)(A)), the Federal Circuit has limited standing under § 1491(b)(1) to “actual or

prospective bidders or offerors whose direct economic interest would be affected by the award of

the contract or by failure to award the contract.” Eskridge & Assocs., 955 F.3d 1339, 1344 (Fed.

6

Cir. 2020) (quoting Myers Investigative & Sec. Servs., Inc. v. United States, 275 F.3d 1366, 1370

(Fed. Cir. 2002)).

Because it is beyond dispute that Plaintiff-Awardees are actual bidders, the dispute

focuses on the second prong of the “interested party” definition—whether Plaintiff-Awardees’

“direct economic interest” would be affected by the Government’s failure to award the contract.

See Telos MTD at 6 (focusing on the “direct economic interest” prong); Red River MTD at 3

(same). What constitutes a sufficient “direct economic interest” for standing is dependent upon

the procedural posture of the protest at hand. Sys. Application & Techs., Inc., 691 F.3d at 1382

(“A protest will, by its nature, dictate the necessary factors for a ‘direct economic interest.’”)

(citation omitted). To satisfy the “direct economic interest” element, plaintiffs in post-award

protests must show they had a “substantial chance” of receiving the contract award. Info. Tech.

& Applications Corp. v. United States, 316 F.3d 1312, 1319 (Fed. Cir. 2003) (“To establish

prejudice, [plaintiff] must show that there was a ‘substantial chance’ it would have received the

contract award but for the alleged error in the procurement process.”) (citation omitted). Here,

Plaintiff-Awardees have alleged that but for the Government’s challenged errors in evaluating

theirs or other proposals, they would have a substantial chance of award. The Defendant-

Intervenors do not challenge any of this. Instead they argue that the Plaintiff-Awardees

automatically lack standing because they are members of CTA Teams that won BPA awards.

These arguments are not convincing.

First, the notion that awardees can never have bid protest standing has been soundly

rejected by this Court. As the Court held in National Air Cargo Group, Inc. v. United States,

126 Fed. Cl. 281, 295 (2016), “status as a contract awardee does not by itself deprive this court

of bid protest jurisdiction.” As another member of this Court recently explained, “an awardee

still has an ‘economic interest’ in ‘stopping the government from stepping outside stated

procurement terms in making further awards.” PAE-Parson Global Logistics Services, LLC v.

United States, 145 Fed. Cl. 194, 199 (2019) (quoting Nat’l Air Cargo Grp., 126 Fed. Cl. at 295);

see also Fluor Intercontinental, Inc. v. United States, 147 Fed. Cl. 309, 323-24 (2020) (finding

standing when awardees challenged awards of “more valuable IDIQ contracts to other offerors”).

Second, the motions to dismiss rely upon cases that hold the Court lacks protest

jurisdiction over cases challenging the plaintiff’s own contract award. Indeed many of these

cases addressed pre-award protests that challenged the terms of the procurement and held that the

plaintiff loses standing to maintain such a challenge upon award. See Telos MTD at 6

(collecting cases). But these cases do not support the argument here that Plaintiff-Awardees lack

standing to challenge the Government’s rejection of their quotes simply because they are

members of CTA Teams led by others that won awards. For example, MLS-Multinational

Logistic Services, Ltd v. United States, 143 Fed. Cl. 341 (2019), is a case in which a contract

awardee sought to change the terms of its existing contract through the protest process. Because

MLS did not allege any fault in the Government’s award decision, the court determined that the

protest was “more consistent with a pre-award protest seeking to change the terms of the

solicitation” and that an awardee performing under a contract did not have standing to bring a

pre-award protest. Id. at 370-75. Instead, the court noted that awardees must pursue a Contracts

Disputes Act (“CDA”) claim to challenge terms within their contract. Id. at 376. Here, Plaintiff-

Awardees are specifically alleging error in the Government’s evaluation and award decisions that

7

prevented them from obtaining separate awards. CounterTrade Resp. at 8 (“CounterTrade has

alleged violations of procurement law by GSA in making the BPA awards, and it has a

substantial chance of receiving a BPA award as a team lead if it is determined that such

violations occurred.”); Blue Tech Resp. at 7 (“But Blue Tech is not challenging the terms of its

own Team Member award. Rather, it is challenging the Agency’s failure to award it a BPA as a

Team Lead.”); Sirius Federal Resp. at 7. (“Sirius Federal is protesting a selection issue; its

Complaint is a ‘protest’ Complaint that ‘stem[s] from [its] status as offeror[], not

awardee[].’”)(internal citations omitted).

It is certainly true that MLS-Multinational Logistic “pointed out that ‘a number of

decisions by judges of the United States Court of Federal Claims’ support the proposition that

contract awardee’s lack standing to bring protests under this court’s bid protest jurisdiction and

are limited to raising claims under the court’s [CDA] jurisdiction.” Telos MTD at 6, ECF No. 52

(citing MLS-Multinational Logistic, 143 Fed. Cl. 341, 361-66 (2019) (collecting cases)). But

these cases are similarly distinguishable as cases that challenge terms of existing contracts rather

than challenging an award decision. See TransAtlantic Lines LLC v. United States, 126 Fed. Cl.

756 (2016) (rejecting protest standing for claim that the Government’s refusal to accept proposed

rates after the contract award was a violation of the Cargo Preference Act of 1904); ITility, LLC

v. United States, 124 Fed. Cl. 452 (2015) (rejecting protest standing when plaintiff challenged a

CPARS evaluation of it under a contract it was performing); Kellogg Brown & Root Services,

Inc. v. United States, 117 Fed. Cl. 764 (2014) (rejecting protest standing for a contract dispute

over the close out method for an existing contract that plaintiff had performed on for more than

ten years); Trailboss Enterprises, Inc. v. United States, 111 Fed. Cl. 338 (2013) (rejecting

standing when plaintiff alleged after contract formation that its pricing was no longer valid and

sought to enjoin the Airforce from “compelling” it to perform under the contract); Diversified

Maintenance Systems, Inc. v. United States, 103 Fed. Cl. 431 (2012) (rejecting protest standing

in a breach of contract case that plaintiff alleged fell under this Court’s jurisdiction because it

was “in connection with a procurement”); Outdoor Venture Corp. v. United States, 100 Fed. Cl.

146 (2011) (rejecting protest standing when plaintiff was awarded a contract and attempted to

protest the threatened termination of that contract for convenience). But none of the plaintiffs in

these cases asserted that a contract was improperly awarded or that a quoter was not awarded a

contract when they should have, as Plaintiff-Awardees allege here. These cases thus stand for

the uncontroverted proposition that a contractor may not circumvent the CDA by invoking this

Court’s protest jurisdiction. Plaintiff-Awardees are not attempting to do so here; indeed, there is

no provision of the CDA that allows a disappointed bidder to challenge the Government’s

evaluation of its proposal.

Finally, the Defendant-Intervenors argue that Plaintiff-Awardees cannot qualify as

“interested parties” because they have already received BPA awards as CTA Team Members.

Telos MTD at 7; Red River MTD at 3. Telos additionally maintains that “to the extent that

Plaintiff-Awardees are affected by the Agency’s decision not to provide them with additional

awards, the impact is too speculative to constitute a direct economic interest.” Telos MTD at 7.

Red River furthers this point by asserting, “[n]one [of the Plaintiff-Awardees] has a substantial

chance of becoming any more of an awardee than it already is.” Red River MTD at 3. This

argument rings hollow. Both Defendant-Intervenors moved to intervene in this case under

RCFC 24(a). According to Telos, it “invested substantial time and money in the preparation of

8

its proposal that led to the award protested in this action and, by intervening, Telos will be able

to protect its investment.” ECF No. 11 at 2. Similarly, “Red River seeks to intervene to protect

its interest in the Blanket Purchase Agreement (‘BPA’) awarded to Red River by the General

Services Administration (‘GSA’) . . . .” ECF No. 14 at 1. These arguments certainly appear to

be based on the awards to the Defendant-Intervenors as team leads rather than the award made to

[ … ], the lead of a team that both Defendant-Intervenors are members of. It is thus hard to

accept that Defendant-Intervenors can have a sufficient interest in defending their award as a

team lead while arguing that the Plaintiff-Awardees do not.

In any event, there are some significant differences in being awarded a contract as a team

lead and as a team member. It bears noting that the Defendant-Intervenors only submitted one

quote in response to the RFQ for which they each led teams. And the RFQ provides that “BPA

Holders/Team Leads” may add or remove members of their teams, meaning that team members

do not appear to have the assurance that they will retain their status as team members on teams

that they do not lead. RFQ § 10.13, D. Appx at 163. While the Defendant-Intervenors argue that

this provision applies to all team leads and team members, that interpretation fails to account for

the fact that changes will be made through a “BPA modification signed by the BPA Contracting

Officer.” Id. Because only the team lead is permitted to communicate with the BPA Contracting

Officer after award, RFQ § 10.10, D. Appx at 157, it does not follow that anyone other than the

team lead is able to remove other team members under the RFQ’s terms. Finally, the

Government itself understood that it was making nine awards under the RFQ. See D. Appx at

981 (listing the “nine awardees and their CTA Team members”) (emphasis added).

Because Plaintiff-Awardees meet the “substantial chance” standard constituting a “direct

economic interest,” they have standing to pursue their protests.

IV. Plaintiffs’ Motions for Preliminary Injunctive Relief.

“[A] party is entitled to a preliminary injunction if: (1) the party has a likelihood of

success on the merits; (2) the party will be irreparably harmed without injunctive relief; (3) the

balance of hardships favors the petitioning party; and (4) the public interest favors the grant of

injunctive relief.” Akal Security, Inc. v. United States, 87 Fed. Cl. 311, 317 (2009) (citing Erico

Int’l Corp. v. Vutec Corp., 516 F.3d 1350, 1353–54 (Fed. Cir. 2008)). “No single factor is

determinative, and ‘the weakness of the showing regarding one factor may be overborne by the

strength of the others.’” Id. (quoting FMC Corp. v. United States, 3 F.3d 424, 427 (Fed. Cir.

1993)). “Conversely, ‘the absence of an adequate showing with regard to any one factor may be

sufficient’ to deny preliminary injunctive relief.” Cashman Dredging & Marine Contracting

Co., LLC v. United States, 148 Fed. Cl. 58, 63 (2020) (quoting FMC, F.3d at 427). “Preliminary

injunctive relief is characterized as an extraordinary remedy.” Id. “Nevertheless, the decision to

award such relief is within the discretion of the court.” Id.

9

A. Neither CDW-G nor CounterTrade has established a likelihood of success on

the merits.

The first factor in deciding whether to grant preliminary injunctive relief concerns the

plaintiff’s likelihood of success on the merits. “‘[W]hen analyzing the likelihood of success

factor, the trial court, after considering all the evidence available at this early stage of the

litigation, must determine whether it is more likely than not that the challenger will be able to

prove at trial’ the validity of its claim.” Eskridge Rsch. Corp. v. United States, 92 Fed. Cl. 88, 97

(2010) (quoting Titan Tire Corp. v. Case New Holland, Inc., 566 F.3d 1372, 1379 (Fed. Cir.

2009)). In bid protest actions, a plaintiff’s success on the merits turns on whether the Court finds

that the procurement decision in dispute was “arbitrary, capricious, an abuse of discretion, or

otherwise not in accordance with law.” Akal Sec., 87 Fed. Cl. at 315 (citing 5 U.S.C. §

706(2)(A)).

1. CDW-G does not establish a likelihood of success.

CDW-G makes three arguments regarding its likelihood of success on the merits. First,

CDW-G contends that the Government “arbitrarily and capriciously evaluated the offerors’

quotes under the BOEM Factor by failing to hold offerors to the strict requirements for the

supporting documentation required under this factor.” CDW-G Mot. at 7. Second, CDW-G

asserts that the Government arbitrarily and capriciously evaluated the offerors’ submissions

under the Price Factor by improperly allowing end-of-life and/or products that failed to meet

minimum salient characteristics. Id. at 9. Third, CDW-G argues that the Government

improperly conducted the best-value tradeoff as required by the RFQ and “instead mechanically

tallied offerors’ scores to select BPA awardees.” Id. at 9-10. Each argument will be addressed

in turn.

a) CDW-G is unlikely to succeed in arguing that the Government

improperly evaluated offerors’ submissions under the BOEM Factor.

CDW-G asserts that the Government must have arbitrarily and capriciously failed to

adhere to the documentation requirements added to the RFQ in Amendments 18 & 19. Id. at 7.

According to CDW-G, the only way to meaningfully increase a quoter’s BOEM score was to add

new OEMs to a quote and provide the additional documentation. CDW-G Mot. at 7. Because

offerors only had 15 business days from August 10, 2020 to August 31, 2020 to provide brand

new OEM documentation required by Amendments 18 & 19, CDW-G concludes that “[i]t is

simply improbable that any offerors could have materially increased their scores” for the BOEM

Factor. Id. at 7-8.

But CDW-G’s premise is flawed. First, quoters had two months’ notice of the additional

documentation requirements. As the Government explains, a draft of Amendment 18 that

included the additional documentation requirements was sent to quoters on July 1, 2020. Def.

Resp. at 12-13 (citing D. Appx at 131-32). When the Government sent a second draft of

Amendment 18 to quoters on July 23, 2020, the Government advised quoters “use this time

before quotes are officially due in response to the official Amendment 0018 to solidify any

changes necessary to their Schedule contracts, fix any Letter of Supply issues, obtain new pricing

as necessary, [and] begin completing Attachment B – Breadth of OEMS – AMD 18 that is

10

attached to this email.” Id. at 13 (citing D. Appx at 134). CDW-G appears to concede this point

in its Reply but insists that the lack of documentation confirming that all BOEM documentation

is valid means that the Government ignored the requirement. CDW-G Reply at 6-7. This turns

the analysis on its head because the Court assumes the Government acted in compliance with the

law unless shown otherwise. E.g., Impresa Construzioni Geom. Domenico Garufi v. United

States, 238 F.3d 1324, 1338 (Fed. Cir. 2001) (“[I]n determining whether to require an

explanation, the agency decision is entitled to a presumption of regularity. Because of that

presumption of regularity, the agency should not be required to provide an explanation unless

that presumption has been rebutted by record evidence suggesting that the agency decision is

arbitrary and capricious. The litigant challenging that presumption necessarily bears a heavy

burden.”) (internal citations omitted).

Second, the Government points out that there was not a 15-day, or even a two-month,

period in which quoters were able to establish relationships with new OEMs. The CTA Teams

submitted their quotes for the second round of evaluation on May 6, 2019. Def. Resp. at 12

(citing CDW-G Compl. ¶¶ 14, 19 & D. Appx at 44-46). Thus, CTA Teams had from May 6,

2019 until August 31, 2020 to establish new relationships and add OEMs to their proposal.

CDW-G fails to explain why this was insufficient time to establish new OEM relationships.

Finally, and most importantly, CTA Teams could also add OEM coverage to their quotes

by [ … ], which would increase their BOEM scores. Def. Resp. at 13 (comparing D. Appx at 48-

49 with 886-87). Indeed, this is what several CTA Teams did, including the Defendant-

Intervenors. Id. CDW-G’s only response to these facts is by taking issue with the possibility

that [ … ] could increase the score, noting that six offerors [ … ] and their BOEM Factor scores

decreased. CDW-G’s Reply at 7. This does nothing to change the fact that awardees did

increase their scores through [ … ].

Accordingly, the Court finds that CWD-G has not shown that it is likely to succeed on

the merits on the theory that the Government arbitrarily and capriciously disregarded the

requirements of the RFQ relating to the BOEM Factor.

b) CDW-G is unlikely to succeed in arguing that the government

arbitrarily and capriciously evaluated the offerors’ submissions under the

price factor.

CDW-G’s next argues (in a total of two paragraphs) that the Government must have

disregarded the RFQ’s requirements “because the average price of awardees is unrealistic as

compared to the requirements.” CDW-G Mot. at 9. According to CDW-G, the only way that

awardees could quote such low prices was to bid “prohibited end-of-life or discontinued products

or for products that do not meet the minimum specifications required by the RFQ.” CDW-G

Mot. at 9. Here too, CDW-G argues that the Government failed to document how it assessed

quotes to determine if prohibited end-of-life products were included. In CDW-G’s terms,

the [Defendant’s] Appendix wholly fails to describe how the

Government conducted its end-of-life and discontinued product

analysis. There is simply no articulated process for assessing end

of life, such as whether the Government researched each part

11

number, consulted the Letters of Supply, reviewed technical

documentation in light of requirements, etc. There is no support

for, and the Government has not cited to anything purporting to be,

the process by which it conducted its end-of-life and discontinued

product analysis.

CDW-G Reply at 8-9.

CDW-G’s argument fails. The RFQ provides that “Quoters shall not quote products that

are end of life. The decision as to whether the Quoter’s quoted product is an end of life item

rests solely with the procurement evaluation team.” D. Appx at 190. While CDW-G argues that

there is no explanation of how the Government conducted this analysis, the Government’s

Appendix does make clear that the GSA did conduct this analysis. In fact, when GSA found an

end of life product, GSA identified it and brought it to the attention of the quoter. When

evaluating one of the quotes, GSA determined that “[w]hile the quoted item itself meets the

minimum salient characteristics, the item quoted is discontinued/end of life.” D. Appx at 726.

Upon identifying this end of life product, the GSA brought it to the quoter’s attention, and a

different product was substituted in that quoters final quote. Id. at 727. Based on the record

before the Court, it does not appear that the GSA’s consideration of the end of life issue was

arbitrary or capricious simply because the GSA did not specifically state that each product was

not an end of life product.

c) CDW-G is unlikely to succeed in arguing that the government

failed to conduct the best-value tradeoff as contemplated in the RFQ.

CDW-G’s final argument is that the Government failed to conduct a best-value tradeoff

as required under the RFQ because the Government “improperly applied a mechanically rote

exercise aimed only at reviewing the overall evaluated scores of offerors to determine the list of

awardees, without actually conducting the tradeoff of price and non-price factors it was required

to perform.” CDW-G Mot. at 10. While CDW-G acknowledges that the Government discussed

the merits of the awardees at the various phases of the best-value tradeoff, it purportedly “wholly

failed to consider the merits of CDW-G’s proposal and instead irrationally relied solely on the

mechanical application of point values.” CDW-G’s Reply at 11. While CDW-G clearly believes

a more detailed analysis should have been documented, that is not the issue for the Court to

decide. The issue for the Court is whether what the GSA did was rational. It was.

Before turning to the merits of CDW-G’s argument, the Federal Circuit’s precedent

makes clear that this Court is to provide the deference to the Agency’s best value tradeoff. E.g.,

Med. Dev. Int’l, Inc. v. United States, 89 Fed. Cl. 691, 702 (2009) (“A court reviewing a best

value procurement agency action must be highly deferential, and the agency that made the

determination in question is presumed to have acted in a reasonable and rational manner.”)

(citing Advanced Data Concepts, Inc. v. United States, 216 F.3d 1054, 1057 (Fed. Cir. 2000)

(additional citation omitted); see also Galen Med. Assocs., Inc. v. United States, 369 F.3d 1324,

1330 (Fed. Cir. 2004) (“Additionally, as the contract was to be awarded based on ‘best value,’

the contracting officer had even greater discretion than if the contract were to have been awarded

on the basis of cost alone.”) (citation omitted).

12

As explained above, the best value trade off, which spans thirty pages of the decision

document, proceeded in six phases. In the first phase, the Agency identified the four quoters that

were rated in the top nine for their technical scores and were within the nine lowest-priced

quotes. D. Appx at 952-56. Given that the Agency was planning for nine awards, this

combination would appear to rationally identify the candidates likely to be the most beneficial

quotes for the Government. CDW-G argues that the analysis was flawed, however, because the

decision refers to the unsuccessful quoters in the collective, without mention of CDW-G

specifically. CDW-G Reply at 12-14 (citing Revised Award Decision Document, Tradeoff

Analysis Process Explained, D. Appx at 952 (“Red River is number three in price as compared to

sixteen quoters in this tradeoff analysis.”); id. at 953 (“New Tech is ranked number seven in

points and nine in price.”); id. (“New Tech is number seven in price as compared to sixteen

quoters in this tradeoff analysis.”); id. at 954 (“These four quotes were both the top nine

evaluated quotes in terms of price and the top nine in terms of non-price factors proving them to

be the best value total solution for the Government.”)). Given that each of the four potential

awardees from Phase I—Red River Technology, LLC, New Tech Solutions, World Wide

Technology, LLC, and Govplace, Inc.—was higher rated technically and lower priced than

CDW-G, it is hard to imagine what trade off was necessary here. In any event, the GSA

explained what made these proposals technically superior. For example, regarding Red River,

the Government states:

One of the key components in Red River[‘]s quote is their vast

breadth of OEMs coverage for the 275 “named OEMs” in the

Breadth of OEMs self scoring assessment. Red River can cover [

… ] of 21 of the mandatory OEMs listed in RFQ section 15.1(a)

and 15.2.7 of the RFQ. Of the top tier OEMs (Tier 1, Tier 2, Tier

3, Tier 4, Tier 5, and Tier 7 OEMs having points values of 150 or

more) listed within the Attachment B – Breadth of OEMs Self

Scoring Assessment, Red River has the ability to supply [ … ] out

of 50 of those OEMs products.

D. Appx at 952; see also D. Appx. 953 (similarly discussing the OEM coverage of the other

phase one awardees).

CDW-G fails to identify anything that requires the Government to specifically compare

each proposal to each other when proposals being considered are both higher rated technically

and lower priced than CDW-G’s. Indeed, “[i]t is well settled that the government is only

required to make a ‘cost/technical tradeoff . . . where one proposal is rated higher technically

than another, but the other is lower in cost.’” Indus. Property Mgmt., Inc. v. United States, 59

Fed. Cl. 318, 324 (2004) (quoting State Mgmt. Servs., Inc., B-255,528 Comp. Gen., 1995 WL

19600 at *5) (additional citations omitted) (alteration in original).

CWD-G next argues that the remaining five rounds of trade off suffered from the same

flaw. CDW-G Reply at 12. As an example, CDW-G attacks the GSA’s decision to award a

BPA to DH Technologies, which is higher rated technically but slightly more expensive than

CDW-G. See D. Appx at 961. CDW-G quotes the Government’s conclusion and points to all

the references to technical scores:

13

In summary, despite identical scores for the socioeconomic factor

for all quoters in this tradeoff analysis and a slightly lower relevant

experience score than PCMG, Telos, M2 Technology, CDW

Government, FCN, Connection (GovConnection), and Iron Bow,

there was a vast difference in the Breadth of OEMs score for DH

Technologies quote as compared to the remaining quoters in this

tradeoff analysis. DH Technologies has a vast Breadth of OEMs

coverage with a total of 267 Letters of Supply. These differences in

DH Technologies’ quote as compared to the remaining quoters was

significant to the agency particularly their Breadth of products as

the Breadth of OEMs Factor accounts for 87% of all points

based non-price factor points available. DH Technologies

lowered their initial BPA price by 51.22% from $329,434.75 to

160,692.67. Despite their $160,692.67 BPA price making them the

11th lowest quote of the twelve quotes in this tradeoff decision (or

16th lowest price quote out of all quoters), DH Technologies

quote provides better value to the Government relative to the

overall objective of the acquisition.

Id. at 12-13 (quoting D. Appx at 963-64) (emphasis added in CDW-G Reply).

Relatedly, CDW-G further underscores that, after indicating above that DH Technologies

received a higher BOEM Factor score, “[i]nstead of discussing how the DH Technologies’

BOEM scope was of greater benefit to the Government than other offerors’ BOEM scopes, the

Government focused solely on the fact that DH Technologies had a higher BOEM score:”

DH Technologies has greater technical merit for the non-price

factors than the other ten quoters (PCMG, Telos, Force 3, M2

Technology, CDW Government, FCN, Connection (Gov

Connection), MicroTechnologies, Iron Bow, Integration

Technologies Group) in this tradeoff analysis. DH technologies

vast breadth of products aligns with the fundamental scope of the

2GIT acquisition. Their Breadth of products combined with their

relative experience merits its higher price. There is a greater

benefit to the Government to make an award to DH Technologies

at a higher price as DH Technologies quote demonstrates qualities

important to GSA and its customers regarding breadth of original

equipment manufacturers, relevant experience [which was lower

than other offerors, including CDW-G], and socioeconomic

makeup [which was identical to all other offerors in this tradeoff

analysis]. The Government has determined that there is minimal to

no increased risk in awarding to DH technologies at a higher price.

DH Technologies’ quote did not contain any finding[s] that have

not been cured or adequately addressed through confer sessions or

points deductions. DH Technologies’ quoted price of $160,692.67

was determined fair and reasonable.

14

Id. at 13-14 (quoting D. Appx at 964) (emphasis added in CDW-G Reply).

The Court is unpersuaded by CDW-G’s arguments here as well. While the GSA was

certainly free to add even more detail to the 30 pages it spent explaining its best value trade off,

that was not required. Here, the GSA made clear in the RFQ that “The GSA evaluation team will

total the points scoring for evaluation non-price Factors 1, 2, and 3 for all the Quoters. The

Government will then select the potential awardees based upon an assessment and tradeoffs of

non-price factors and price. The amount of total points for non-price Factors 1, 2, and 3 will be

considered as part of the tradeoff analysis.” RFQ § 15.2.5.2, D. Appx at 201 (emphasis added).

To the extent CDW-G complains that it is the total points that the GSA considered for the OEM

factor rather than a granular analysis of each specific OEM is foreclosed by the RFQ.

Moreover, the RFQ explicitly puts quoters on notice that the Breadth of OEM would be

the most significant technical factor for award. First, the Government explained that “[a]ll

evaluation factors other than cost or price, when combined, are significantly more important than

cost or price.” RFQ § 15.1(a), D. Appx at 187. Second, the Government made clear that the

most important non-price factor is the Breadth of OEMs Factor, stating:

In addition to the Breadth of OEMs Factor making up 87% of the

total possible points available for all points-based non-price

factors, as the quotes became more equal with regard to the

Relevant Experience and Socioeconomic Factors, the more

controlling the Breadth of OEMs Factor became in the tradeoff

determination. For this reason, most of the emphasis in the below

tradeoff analysis will be placed on Breadth of Original Equipment

Manufacturers as well as price.

D. Appx at 950 (emphasis added). When viewed under these criteria, the GSA’s explanation of

why DH Technologies’ quote was more beneficial to the Government than CDW-G’s is

sufficient. DH Technologies offered the broadest OEM coverage, which the GSA found to be “a

vast difference” between its proposal and the others. D. Appx at 963. Finally, it is important

that the price difference was minimal here – CDW-G’s evaluated price was [ … ], while DH

Technologies’ evaluated price was [ … ]. D. Appx at 961. Given the greater significance of the

non-price factors, it was rational for the GSA to find that the “vast difference” in DH

Technologies’ technical quote justified the small increase in evaluated price. While CDW-G

does not address the remaining trade off decisions, they are similarly documented. See D. Appx

at 959-60 (explaining that Sterling Computers’ proposal was superior on technical factors,

particularly breadth of OEM, and only slightly higher priced at $161,215.07); D. Appx at 967

(explaining that PCMG’s greater breadth of OEM offerings justified the slightly higher price of

$160,012.31); D. Appx at 970-71 (explaining that Telos’s higher rated proposal and lower price

justified award); D. Appx at 973-74 (explaining that M2’s slightly higher rated and less

expensive proposal was more beneficial to the Government).

d) The Court will not consider CDW-G’s argument raised for the first

time in its reply that the record does not indicate a required comparative

analysis.

15

Finally, CDW-G introduces a new argument in its Reply that there is no record of the

Government’s “comparative analysis of each item quoted in the market basket” as required under

the RFQ. CDW-G Reply at 9-10. “Raising [an] issue for the first time in a reply brief does not

suffice; reply briefs reply to arguments made in the response brief—they do not provide the

moving party with a new opportunity to present yet another issue for the court’s consideration.”

Eden Isle Marina, Inc. v. United States, 89 Fed. Cl. 480, 507 n.25 (2009) (quoting Novosteel SA

v. United States, 284 F.3d 1261, 1274 (Fed. Cir. 2002)) (emphasis in original); see also RCFC

5.4(a)(2)(E) (requiring the “first brief or memorandum” to contain “a clear statement of the

argument, setting forth the points of fact and law being presented and the authorities relied

upon”) (emphasis added). This Court, like other courts, considers any argument raised for the

first time in a reply brief to be waived. E.g., 2M Research Servs., LLC v. United States, 148 Fed.

Cl. 99, 110 (2020) (“Arguments raised for the first time in a reply brief are not properly before

this court.”) (quoting United States v. Ford Motor Co., 463 F.3d 1267, 1276 (Fed. Cir. 2006));

Tetra Tech Amt v. United States, 128 Fed. Cl. 169, 184 (2016) (“[I]t is ‘well established that

arguments not raised in the opening brief are waived.’”) (quoting SmithKline Beecham Corp. v.

Apotex Corp., 439 F.3d 1312, 1319 (Fed. Cir. 2006)) (additional citations omitted).

While it is true that CDW-G did not have access to the Agency’s decision document until

the Government filed its Response to the preliminary injunction motions, CDW-G’s argument is

based on the presumption that the Administrative Record is devoid of any documentation of the

Agency’s analysis, which is unsupportable at this stage. What we do know at this stage is that

the evaluation team:

1. “[C]onducted an independent analysis of the individual items quoted by each

quoter to determine if the prices quoted for each item was at or below their

schedule prices”;

2. “[C]onducted a price analysis and made a determination as to whether each item

quoted was determined fair and reasonable (independent of prices quoted by

other quoters)”;

3. “[C]onducted a [sic] analysis to determine whether discounts in each Quoters

Attachment E - Market Basket - AMD 18 mirror the discounts quoted in

Attachment F - Discount Rates - AMD 18”; and

4. “In accordance with RFQ section 15.2.1.1.2, the evaluation team also utilized

other tools (i.e. standard deviation calculations, GSA’s Price Point PLUS Portal

(4P Tool), which is a GSA developed market research tool that provides multiple

data points to assist GSA contracting staff in determining whether fair and

reasonable pricing has been obtained, etc.) in determining price reasonableness.”

D. Appx at 922 (emphasis added). This recitation makes clear that an analysis of each item was

performed. Once we have the Administrative Record, CDW-G may argue whether the record

sufficiently documents such analyses in its motion for judgment on the administrative record and

for permanent injunctive relief.

2. CounterTrade does not establish a likelihood of success on the merits.

16

CounterTrade’s protest rests largely upon a dispute over what the RFQ required quoters

to propose as an Advanced Secure Web Gateway (“Gateway”). The Gateway, which is a

mandatory component for the price evaluation, is a computer network security device that

“controls web traffic” by processing all the data coming into and going out of a computer

network. CounterTrade Mot. at 16. As part of this processing, the Gateway “filter[s], strip[s],

block[s] or replace[s] web content to mitigate risks and prevent data loss.” Id. Much of

CounterTrade’s protest depends on whether quoters were permitted to include a “cold spare”

version of the Gateway that is only functional as a backup unit. While there is some dispute as to

what specific differences exist between the “cold spare” and primary devices, it is not disputed

that the cold spares lack any licenses and “are utilized as backup units.” D. Appx at 116

(discussing different versions of the ASG-S400-30 Gateway).

The central question, therefore, is what the minimum characteristics were for the

Gateway under the RFQ. If CounterTrade is correct that only the more expensive version of the

Gateway meets the RFQ’s minimum requirements, then GSA erred in awarding BPAs to quoters

offering the cold standby devices. See, e.g., Centech Grp., Inc. v. United States, 554 F.3d 1029,

1038 (Fed. Cir. 2009) (“[A] proposal that fails to conform to the material terms and conditions of

the solicitation should be considered unacceptable and a contract award based on such an

unacceptable proposal violates the procurement statutes and regulations.’”) (quoting E.W. Bliss

Co. v. United States, 77 F.3d 445, 448 (Fed. Cir. 1996)) (alteration in original). Under the RFQ,

the minimum salient requirements for the Gateway are:

***DEVICE ONLY***

Physical: Disk Drives= capable of supporting 6TB SAS; Boot Device= capable of

supporting 16GB SSD (redundant); RAM= capable of supporting 32GB;

Onboard Ports= capable of supporting (2) 10/100/1000Base-T capable w/bypass,

(2) 10/100/1000Base-T (non-bypass); 10/100Base-T, BMC Management Port

Optional NICs= capable of supporting 1GbE Fiber, 10Gb Base-T, or 10Gb Fiber;

Chassis= 1 RU

Available slots= 1 Full height/1 half height; (2) Power supplies= min 350W,

redundant, hot swappable

Integrated Threat Protection

D. Appx at 250. CounterTrade makes several arguments that the RFQ requires the licensed

version of the Gateway.

First, CounterTrade argues that the cold standby device is merely a “backup component

for the specified Advanced Secure Web Gateway Device.” CounterTrade Mot. at 16; see also D.

Appx at 116 (recognizing that cold standby machines are “not functional without

configuration”). And as a backup component, according to CounterTrade, the cold standby

cannot be purchased without the primary gateway device and is typically only permitted for use

by OEMs and system licenses when the primary device is not functioning. Id. at 16-17. Thus,

the price listed for the cold standby is not an accurate reflection of the cost of purchasing a

functioning device. True enough. But that is only a problem if the GSA were seeking a

functional configuration through the price evaluation. It was not. The purpose of the price

comparison was to compare prices for a sampling of devices. According to the RFQ: “A market

basket evaluation approach will be utilized in evaluating price for this acquisition. The market

basket includes a sample of products most frequently purchased based on historical data.” RFQ

§ 15.2.1, D. Appx at 190.

17

Second, CounterTrade argues that the minimum salient characteristics require the

necessary software for the Gateway to have “Integrated Threat Protection” as required by the

RFQ. This, according to CounterTrade, “requires that the device be functional and have

software to detect and isolate threats. A cold standby does not satisfy this requirement.”

CounterTrade Reply at 4. The Government, however, argues that “[t]he only difference between

the ‘cold standby’ parts and the part that CounterTrade proposed is that licenses are pre-installed

onto the version that CounterTrade proposed but have yet to be installed onto the cold standby

devices.” Def.’s Resp. at 19-20. Both CounterTrade and the Government rely solely on

statements appearing on the same page of the GSA’s evaluation.

According to CounterTrade, when the GSA recognized that the cold standby “is not

functional without configuration,” D. Appx at 116, that necessarily means that it does not have

any software installed on it at all. CounterTrade Reply at 10. The Government, however, relies

on the same discussion to conclude that “[t]he only difference between the ‘cold standby’ parts

and the part that CounterTrade proposed is that licenses are pre-installed onto the version that

CounterTrade proposed but have yet to be installed onto the cold standby devices.” Def.’s Resp.

at 19-20 (citing D. Appx at 116). But there is nothing about the GSA’s recognition that the cold

standby is not functional without configuration that compels the conclusion that there is no

software at all installed on the device. Instead, it could just as easily mean that the device will

not work until licenses are installed, as the Government asserts. Indeed, as the Government

points out, the RFQ specifically states that quote is for the “***DEVICE ONLY***.” The

Government added “device only” to the RFQ in Amendment 18 because quoters were offering a

wide variety of Gateways ranging from cold standby to versions licensed for many users and the

GSA wanted to clarify what it was seeking. Def. Resp. at 21-22. There is nothing irrational

about the GSA’s determination that the cold standby satisfied the RFQ’s requirements.

Third, CounterTrade argues that quoters could not have complied with requirements to

provide documentation showing that a cold standby satisfied all the RFQ’s minimum salient

characteristics. CounterTrade Mot. at 17. CounterTrade observes that all “[q]uoters were

obligated to include sufficient supporting detail to evidence that the specific part they proposed

satisfied the RFQ’s minimum salient characteristics.” Id. As such, CounterTrade maintains that

the “awardees simply could not have provided the requisite supporting documentation to confirm

that the part number they proposed (which has a “CS” at the end designating the device as only a

“cold standby”) actually complies with the RFQ requirements.” Id. And that the Government

did not provide the specification sheets in its Appendix with the cold standby part number

confirms that none were submitted. CounterTrade Reply at 9-10. Therefore, according to

CounterTrade, “the awardees’ failure to provide the required documentation to demonstrate that

their cold standby units met all RFQ requirements . . . render[s] the award decision as improper

and unlawful.” Id. at 10.

The Court is not persuaded. Because, as explained above, the cold standby appears to

satisfy all RFQ minimum requirements, there is no reason to conclude that documentation of a

cold standby Gateway was insufficient to show that it met all RFQ requirements. Moreover, to

the extent CounterTrade argues that the lack of any documentation in the Government’s

Appendix establishes that no quoter included such documentation presumes that the

Administrative Record lacks any such documentation, which is not supportable at this time.

18

Finally, CounterTrade points to the consideration of Blue Tech’s quote as showing that

the GSA failed to consider the specific part numbers being offered and “only looked at the

characteristics of the broader model series (SG S400-20), as opposed to the characteristics of the

part number actually proposed (SG-S400-20-SRP).” CounterTrade Reply at 11. But, as

CounterTrade recognizes, the GSA rejected Blue Tech’s quote. With regard to other quotes, the

GSA clearly recognized the specific part numbers offered. See, e.g., D. Appx at 706

(recognizing the changed Gateway part number in an accepted proposal). There is no indication

in the limited record before the Court that the GSA improperly reviewed documentation in

proposals it did not reject. Finally, the Court is not able to determine at this stage whether Blue

Tech’s documentation is sufficient, particularly considering Blue Tech’s arguments that the RFQ

only requires a device that is “capable of supporting” certain size hard drives and memory. See

Blue Tech Compl. ¶¶ 21, 48.

Because neither movant has shown a likelihood of success on the merits, this factor

weighs against granting injunctive relief.

B. CDW-G and CounterTrade establish irreparable harm.

To obtain injunctive relief, CDW-G and CounterTrade must show that they would not

“have an adequate remedy at law absent an injunction.” Std. Commc’ns, Inc. v. United States,

101 Fed. Cl. 723, 744 (2011) (citation omitted). Here, CDW-G and CounterTrade claim

irreparable harm in the form of lost profits from work that they will not be able to compete for.

CDW-G Mot. at 11-12; CDW-G Reply at 15-18; CounterTrade Mot. at 19-21; CounterTrade

Reply at 12-13. Here it appears that the Government is waiting to issue numerous orders against

the BPAs and intends to do so without limitation during the pendency of this litigation (likely

through mid-June). See Contracting Officer’s Decl. ¶ 9, ECF No. 53-3 (stating that the “Air

Force and federal agency customers have delayed millions in infrastructure investments awaiting

the 2GIT BPA awards.”).

To the extent that CDW-G and/or CounterTrade prevail at the end of the case, there is

nothing the Court can do to remedy the lost opportunity to compete for this work and the lost

profits associated with their lost opportunity. Indeed, there is no adequate remedy for this harm

available at law because the only monetary relief the Court could award is bid preparation costs.

E.g., 28 U.S.C. § 1491(b)(2) (“To afford relief in such an action, the courts may award any relief

that the court considers proper . . . except that any monetary relief shall be limited to bid

preparation and proposal costs.”); see also Bean Dredging Corp. v. United States, 22 Cl. Ct. 519,

524 (1991) (finding irreparable harm “because plaintiffs could recover only bid preparation

costs, not lost profits, through an action at law”).

Therefore, this factor weighs in favor of granting injunctive relief.

C. The balance of the harms weighs against injunctive relief.

The third factor in determining whether to grant a preliminary injunction is that the

balance of hardships favors the petitioning party, i.e. the plaintiff’s hardship outweighs the

hardship to the Government and to third parties. E.g., Akal Sec., Inc. v. United States, 87 Fed.

Cl. 311, 320 (2009). In considering this factor, the Court must “give due regard to the interests

19

of national defense and national security.” 28 U.S.C. § 1491(b)(3). Where national security

issues are implicated, “the fact that a delay in the conduct of this procurement would raise

national defense concerns clearly places the weight of the balance-of-harms factor on

defendant’s side of the scale.” Aero Corp., S.A. v. United States, 38 Fed. Cl. 237, 241-42 (1997).

Here, the Government relies on the Contracting Officer’s declaration, which sets forth

several national security concerns regarding delays in the 2GIT awards. Def’s Resp. at 25-27; id.

Ex. 1 (“C.O. Declaration”) (ECF No. 53-3). The harm to the Government from a preliminary

injunction is that “[p]recluding ordering under the 2GIT BPA will erode the Air Force, and other

Federal Agencies, FY21 Information Technology implementation of crucial supply chain risk

management controls and modernization strategy objectives to specifically address counterfeit

and malicious software threats in the commercial Information Technology supplier base [and] . .

. hamper government agencies from procuring products that will decrease the risk of compromise

and exploitation by threat actors to federal agencies.” Id. ¶ 5.

As CDW-G and CounterTrade correctly note, however, every device and service offered

through the 2GIT quotes are already available to the Government. Since November 2019, the

Government has been able to obtain every device and service available under 2GIT through other

contract vehicles. See, e.g., CounterTrade Mot. at 22 (explaining that “government agencies can

continue to obtain the exact same products and services from numerous other GWACs, or from

individual orders/competitions through the GSA Schedule 70 contracts, i.e., purchasing through

“eBuy” or “GSA Advantage”). While this may be true, it does not fully obviate the national

security concerns here. As a GAO report titled “Federal Agencies Need to Take Urgent Action

to Manage Supply Chain Risks,” Rep. No. GAO-21-171, found that many agencies failed to

implement foundational practices for managing supply chain risks. This RFQ is intended to

address many of the GAO’s major findings and provides “[t]he only known approved Secure

Supply Chain Risk Management (SCRM) mandated vehicle for the Air Force to use to procure

all Air Force Network-related Information Technology products . . . .” C. O. Declaration ¶ 4.

While other contracts also have some form of supply chain risk management, see CounterTrade

Reply at 15, the Court cannot say that those vehicles provide the same level of security for the

Government. Indeed, the Contracting Officer does point to this procurement as “the only known

available procurement vehicle providing verification of SCRM compliant IT products for federal

agencies.” C.O. Declaration ¶ 13.

The relative harm to CDW-G and CounterTrade—the potential lost profit on work

awarded during the short period of this litigation—does not outweigh the security risk to the

Government. Therefore, this factor weighs against awarding injunctive relief.

D. The Public Interest Weighs Against Injunctive Relief.

The fourth and final factor in determining whether to grant a preliminary injunction is

whether the public interest favors such relief. “There is no dispute that ‘the public interest in

honest, open, and fair competition in the procurement process is compromised whenever an

agency abuses its discretion in evaluating a contractor’s bid.’” Torres Advanced Enter. Sols.,

LLC v. United States, 133 Fed. Cl. 496, 534, redacted opinion issued, 135 Fed. Cl. 1 (2017)

(citation omitted). “However ‘there is a countervailing public interest in minimizing disruption

[to the agency].’” Akal Sec., Inc., 87 Fed. Cl. at 321 (quoting Heritage of Am., LLC, 77 Fed. Cl.

20

66, 78 (2007)); see also Aero Corp., S.A. v. United States, 38 Fed. Cl. 237, 242 (1997) (“[A]

procuring agency should be able to conduct procurements without excessive judicial

infringement upon the agency’s discretion.”). Given that CDW-G and CounterTrade are unlikely

to succeed on the merits of their protests, as explained above, coupled with the national security

interests expressed by the Government, the Court finds that the public interest does not favor

granting them a preliminary injunctive relief. As such, this fourth factor weighs in favor of the

Government.

The Court has evaluated the requisite four factors in determining whether to grant a

preliminary injunction. In the end, although CDW-G and CounterTrade will likely suffer some

degree of irreparable harm regarding work awarded during the litigation that they may not

compete for, that one factor does not overcome the remaining factors in this case. The lack of

likelihood of success coupled with the national security interests articulated by the Government

weigh heavily against granting injunctive relief.

Conclusion

For the foregoing reasons:

1. Defendant-Intervenor Telos Corporation’s Motion to Dismiss, ECF No. 52, is

DENIED;

2. Defendant-Intervenor Red River Technology, LLC’s Motion to Dismiss, ECF No. 55,

is DENIED;

3. Plaintiff CDW Government LLC’s Motion for Preliminary Injunctive Relief, Case

No. 21-1041 ECF No. 5, is DENIED; and

4. Plaintiff CounterTrade Products, Inc.’s Motion for Preliminary Injunctive Relief, ECF

Nos. 39 & 40, is DENIED.

IT IS SO ORDERED.

s/ Edward H. Meyers

Edward H. Meyers

Judge

21

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.