EMERALD POINTE, LLC, )

)

Plaintiff-Appellant, )

)

vs. ) No. SD36725

)

TANEY COUNTY PLANNING ) Filed: April 8, 2021

COMMISSION and TANEY COUNTY )

BOARD OF ADJUSTMENT, )

)

Defendants-Respondents. )

APPEAL FROM THE CIRCUIT COURT OF TANEY COUNTY

Honorable Laura J. Johnson, Special Judge

REVERSED AND REMANDED

Emerald Pointe, LLC (“Emerald Pointe”) is the developer of Emerald Pointe

subdivision (the “subdivision”) located in Taney County. The Taney County Planning

Commission (the “Commission”) entered a stop work order (the “Stop Work Order”)

against Emerald Pointe when it began Phase 12 of the subdivision. Emerald Pointe filed

an appeal of the Commission’s issuance of the Stop Work Order to the Taney County

Board of Adjustment (the “Board”). After the Board denied Emerald Pointe’s appeal,

Emerald Pointe filed a Petition in the Circuit Court of Taney County pursuing relief

1

against the Commission, the Board, and their individual members. 1 After an evidentiary

hearing, the trial court affirmed the decision of the Board denying Emerald Pointe’s

appeal of the issuance of the Stop Work Order. 2 Emerald Pointe filed its timely Notice of

Appeal.

Emerald Pointe brings two points on appeal, including: (1) a contention that the

Board erred as a matter of law in (a) enforcing the grade requirements of its ordinance to

private property and (b) that the Board is estopped from imposing strict compliance with

the security requirements of the ordinance; and (2) that the Final Plat was overwhelming

evidence which supported the conclusion that the Taney County Subdivision Regulations

(“Subdivision Regulations”) and Taney County Road Standards (“Road Standards”) and

the grade requirements did not apply to the private roads in Phase 12, the plat was

approved in 2008, and it contains no reservations for security or grade requirements. 3

Because we find in favor of Emerald Pointe on Point I as a matter of law, we do not

address Point II. 4

1

The trial court dismissed the Petition; however, this Court reversed the judgment of dismissal and

remanded the case. Emerald Pointe, LLC v. Taney County Planning Commission, 578 S.W.3d 390

(Mo.App. S.D. 2019) (“Emerald Pointe I”).

2

At the hearing the individual defendants were dismissed without prejudice with the stipulation by the

Commission and the Board that they would not later challenge that the circuit court did not have all the

proper parties before it.

3

The issues are complicated by the fact that the Commission required, if necessary pursuant to section

64.825 RSMo Cum.Supp. 2004, a bond to enforce compliance with the road standards. There is no issue

that Emerald Pointe could provide a security bond if the grading requirements are not applicable to the

subdivision. The issuance of the security interest bond is only relevant to the underlying issue whether

Emerald Pointe must comply with the Road Standards. Therefore, we address that as the real issue in

contention between the Board and Emerald Pointe – do the road requirements apply to the subdivision.

4

Emerald Pointe contends in the alternative in Point I that the Board is estopped from imposing strict

compliance with the security requirements of section 64.825 and Article 8, Section 6. Because we agree

with Emerald Pointe’s first contention, we do not address the argument regarding estoppel.

2

FACTS

On December 20, 1993, the Commission issued a Division III permit to Emerald

Pointe’s original developer, Gary Snadon, to develop 604 acres in a hilly, wooded, rural

area of Taney County. Over the next 15 years, Emerald Pointe sought the Commission’s

approval for additional Division III permits. On May 19, 2008, the Commission issued a

Division III Permit #2008-0029 authorizing Emerald Pointe to plat fifty (50) acres more

or less into 160 residential lots, as Phase 12 of the subdivision. On September 17, 2008, 5

the Final Plat of Emerald Pointe Phase 12 was approved and signed by the Commission’s

Chairperson and the Planning Administrator, receiving the “Certificate of Approval by

the Commission.” The Commission approved and stated on the Final Plat “[t]his survey

does not violate the rules and regulations of the Taney County Development Guidance

Code.”

The Final Plat specifically states:

All streets as shown hereon are not dedicated to the public and shall be

private. Access along said road from public lake road #265-20 or Hill

Haven Road and Sercy Drive to the subdivision[] is hereby granted to all

existing and future lot owners. The county or local authorities shall

assume no responsibility for improvements or maintenance thereof. All

other easements are hereby dedicated to the public.

IN TESTIMONY WHEREOF, the undersigned manager has hereunto set

his hand this 15 day of July, 2008.

EMERALD POINTE, L.L.C.

___[signature of Gary Snadon]_____

Gary W. Snadon, Managing Member

....

NOTES:

5

The Final Plat was received, accepted and filed of record by the Recorder of Deeds, Taney County, on

September 18, 2008.

3

All lots have a 25’ building setback along all roads. All lot[s] have a 7.5’

sideyard setback and 10’ rear setback. All lots have a 15’ utility easement

along all roads. All lots are subject to setback lines and utility easements

by Taney County Planning Commission, Taney County, Missouri. No

access is permitted directly onto Hill Haven Road from the lots adjoining

said Hill Haven Road.

Restrictive Covenants are filed of record and are recorded in the records of

Taney County recorder’s office in [Document #116] Book [Slide J] at

Page [238].[ 6]

It is the twelfth and final phase that is at issue in this action. At the time that

Phase 12 was being implemented, all the necessary permits for construction were issued

and extended. Despite the permits and prior approval, the Commission caused a Stop

Work Order to be entered on September 21, 2016 by the Taney County Planning

Administrator. Although the initial reason for the issuance of the Stop Work Order was

for Emerald Pointe to provide a different form of security than had been provided in the

past, the underlying reason for the Stop Work Order was the Commission’s insistence

that Emerald Pointe comply with the Subdivision Regulations and Road Standards. The

Commission indicated that Section 3: Design Criteria and Standard, Section 3

Subsection 8 of the Road Standards addressing road grades had to be satisfied (those

standards required engineering construction plans and standards for high density streets).

Specifically, the Commission determined that the roads had to have a grade of fifteen

percent (15%) or less. Emerald Pointe maintained that the streets were private streets on

the approved Final Plat and that the local authorities assumed no responsibility for

improvement or maintenance of any of the roads at issue.

6

The Final Plat is labeled as document #116, then stamped twice (upper right and lower left) with a

slide/page stamp. One reads “Slide J, page 238” and the other “Slide J, page 237.”

4

Point I

In its first point, Emerald Pointe contends the denial of their appeal to the Board

was error because “Article 8, Section 6 of the Subdivision Regulations and grade

requirements of Road Standard Section 3 Subsection 8 do not apply as a matter of law to

private streets in a private, gated subdivision.” The Commission and Board contend that

all of the standards apply to all roads – including private roads – and the Stop Work

Order was valid to enforce the standards. Thus, the issue before the Board and on appeal

is whether the Road Standards regarding the grading of the roads, 7 as set forth in the

Subdivision Regulations, apply to the private roads as set forth in the Final Plat. Under

the facts before us, we agree that the road grading standards do not apply to the Final Plat

approved in 2008. 8

STANDARD OF REVIEW

We review the findings and decision of the Board, not the judgment of the circuit

court. Antioch Community Church v. Board of Zoning Adjustment of the City of

Kansas City, 543 S.W.3d 28, 33 (Mo. banc 2018); State ex rel. Teefey v. Board of

Zoning Adjustment of Kansas City, 24 S.W.3d 681, 684 (Mo. banc 2000). The scope of

judicial review is limited to a determination of whether the decision of the Board is

authorized by law and is supported by competent and substantial evidence upon the

7

The technical ability to enforce standards derive their authority from section 64.825 RSMo Cum.Supp.

2004. The Taney County Development Guidance Code (the “Code”), Subdivision Regulations and Road

Standards set forth the legal requirements for development.

8

The Commission and the Board contend that Emerald Pointe has not preserved this issue; however, it is

clear that from the issuance of the Stop Work Order and the appeal of that order that Emerald Pointe

notified the Commission that the imposition of the grading requirements contained in the Code, the

Subdivision Regulations, and Road Standards did not apply to private roads contained in a private, gated

community. That contention was and has been their defense to the Stop Work Order from the beginning.

The issue was preserved for the Board and for this Court.

5

whole record. Antioch, 543 S.W.3d at 33-34. This Court determines de novo whether a

decision is authorized by law as it is a legal question. Id.

In reviewing city ordinances, we apply the same general rules of construction as

are applicable to state statutes. State ex rel. Teefey, 24 S.W.3d at 684. The general rule

is to determine and give effect to the enacting legislative body’s intent of the ordinance.

Id. In an ordinance, the words contained therein should be given their plain and ordinary

meaning. Id. “Where two statutory provisions covering the same subject matter are

unambiguous standing separately, but are in conflict when examined together, a

reviewing court must attempt to harmonize them and give effect to both.” City of

Clinton v. Terra Foundation, Inc., 139 S.W.3d 186, 189 (Mo.App. W.D. 2004). The

general statute must yield to the more specific statute where harmonization is impossible.

Id.

Additionally, “‘zoning ordinances, being in derogation of common law property

rights, are to be strictly construed in favor of the property owner against the zoning

authority.’” State ex rel. Cushman Properties, LLC v. Board of Adjustment of City of

Branson, 453 S.W.3d 815, 818 (Mo.App. S.D. 2014) (quoting Rice v. Board of

Adjustment of Village of Bel-Ridge, 804 S.W.2d 821, 823 (Mo.App. E.D. 1991)). The

courts are to “‘give weight to the interpretation that, while still within the confines of the

term, is least restrictive upon the rights of the property owner to use the land as he

wishes[,]’” where a zoning ordinance is susceptible to more than one interpretation.

Coots v. J.A. Tobin Construction Co., 634 S.W.2d 249, 251-252 (Mo.App. W.D. 1982)

(quoting Frank’s Nursery Sales v. City of Roseville, 295 N.W.2d 604, 608-609(4)

(Minn. 1980)).

6

APPLICABLE CODE, SUBDIVISION REGULATIONS AND ROAD STANDARDS

We must look at the applicable Code, Subdivision Regulations and Road

Standards to determine and give effect to the enacting legislative body’s intent of the

ordinance.

The Subdivision Regulations contain the following definitions:

Article 2. DEFINITIONS, INTERPRETATION and STANDARDS

....

Section 9. Definitions

....

Plat – Final

The final plan or drawing and any accompanying required data or

information which is submitted to the Planning Administrator for final

approval of a proposed subdivision and recording with the County

Recorder of Deeds.

....

Public Improvements

Those things that are constructed, installed or performed on public land, or

on land that is to become public in the subdivision process, including but

not limited to street and alley pavement, curbs, storm drainage facilities,

sidewalks, sanitary sewers and water lines, and including the grading of

such land.

....

Street, Private

Street under private ownership, control and maintenance. Requires

covenants approved by the Planning Administrator to provide for

maintenance.

The Road Standards provide the following definitions:

SECTION 1

7

DEFINITIONS

....

26. Public Improvements. Those things that are constructed, installed,

or performed on public land, or on land that is to become public in the

subdivision process, including but not limited to street and alley pavement,

curbs, storm drainage facilities, sidewalks, and sanitary sewers, and

including the grading of such land.

....

35. Streets. A way for vehicular traffic, whether designated with the

suffix as a street, highway, thoroughfare, parkway, throughway, road,

avenue, boulevard, lane, place, or however otherwise designated.

Further, the Road Standards address the differences between “Private Improvements” and

“Gated Communities/Private Communities” for street construction in the following

sections:

SECTION 2

STREET REQUIREMENTS

....

Section 13. Private Improvements:

1. Private improvements, if any, shown on the public improvement plans,

shall be clearly defined and marked as such. These improvements will

not be maintained by Taney County and, as such, an appropriate note

shall be included on the drawings.

Section 14. Gated Communities/Private Communities

1. Private streets in gated or private communities are encouraged to

construct their roadway infrastructure to the same design requirements

and specifications as public improvements. If these communities are

not built to these standards they may not be taken into the county

maintenance program.

The Board contends that Article 2, Section 2(A) of the Subdivision Regulations

negates any differences between public and private streets in the regulations:

8

Article 2. DEFINITIONS, INTERPRETATION and STANDARDS

....

Section 2. Conflict with Public and Private Provisions

A. Public Provisions

The regulations are not intended to interfere with, abrogate or annul

any other County Commission Order, rule or regulation, statute or

other provision of law. Where any provisions of these regulations

imposes restrictions, which differ from those imposed by any other

provision of these regulations or any other County Commission Order,

rule, or regulation or other provision of law, whichever provisions are

more restrictive or impose higher standards, shall control.

Further, the Board contends Article 8, Section 2 of the Subdivision Regulations applies.

Specifically:

ARTICLE 8. REQUIRED IMPROVEMENTS

....

Section 2. Streets

A. Unless otherwise approved by the Planning Commission, all

streets shall be public streets.

B. Public streets shall be designed and constructed in accordance with

the Taney County Road Standards

....

F. Private Streets

1. Private streets shall be permitted only with approval of the

Planning Commission.

2. Where private streets are permitted, the restrictive covenants

must contain provisions to assure maintenance of the streets,

sidewalks, and other common improvements. Restrictive

covenants must be approved by the Planning Administrator

and must be recorded with the final plat.

3. Only local streets may be designed as private streets.

9

4. Private streets shall be constructed in accordance with Taney

County Road Standards. Any private street located within the

ingress / egress / utility and drainage easement shall have the

same width as the right-of-way provided for local streets in the

Taney County Road Standards.

Article 8, Section 2 (emphasis added).

Appendix K of the Code (emphasis added) requires:

1. General Provisions

County road standards and requirements are defined and managed by

the Taney County Road and Bridge department. All construction must

adhere to the current published standards set for[th] in the Taney

County Road Standards.

The Road Standards provide in part:

SECTION 3

DESIGN CRITERIA AND STANDARDS

....

Section 8. Grade and Curves:

1. The minimum grade on curb and gutter streets shall be one-half

percent (1/2%). The maximum grade shall be eight percent (8%) on

arterials, twelve percent (12%) on collectors and fifteen percent (15%)

on local streets.

(Emphasis added.) The Road Standards define “Local Street” as:

SECTION 1

DEFINITIONS

....

19. Local Street. A street primarily providing direct access to abutting

property and designed to accommodate low-volume, low-speed traffic.

10

ANALYSIS

It is clear from reading the Subdivision Regulations and the Road Standards that

the legislative body in Taney County intended that there be such a thing as private roads

with different design requirements and specifications than public improvements.

Harmonizing Subdivision Regulations Article 8, Section 2(F) with Road Standards

Section 2, Subsections 13 and 14, given their plain and ordinary meaning, indicates that

Emerald Pointe’s private streets, located in a private gated community, do not mandate

the same design requirements and specifications as Public Improvements.

SUBDIVISION REGULATIONS

In the Subdivision Regulations, a differentiation is made between “Public

Improvements” and “Street, Private.” Public Improvements are defined as: “Those

things that are constructed, installed or performed on public land, or on land that is to

become public in the subdivision process, including but not limited to street and alley

pavement . . . .” The term “Street, Private” is defined as a “[s]treet under private

ownership, control and maintenance[,]” and maintenance is to be provided through

covenants approved by the Planning Administrator.

Emerald Pointe has private ownership over the streets in Phase 12 as they were

dedicated in the Final Plat as private streets with the county and local authorities

assuming no responsibility for the improvements or maintenance. The restrictive

covenants pertinent to Phase 12 were set forth and filed with the Recorder of Deeds in the

Final Plat. Every street in Phase 12 is identified by name and location on the Final Plat

and the words “Private” are delineated after each name. All streets in Phase 12 of the

Final Plat were specifically dedicated as “private” streets. These streets were not

11

constructed on public land nor on land that was to become public. Section 64.825 and

Article 8, Section 6 of the Subdivision Regulations did not require security for

improvements such as “private streets” that were not within the definition of “Public

Improvements” under the Subdivision Regulations.

ROAD STANDARDS

In support of the Subdivision Regulations, the Road Standards dovetail with the

definition of “Public Improvements” as “[t]hose things that are constructed, installed, or

performed on public land, or on land that is to become public in the subdivision

process[.]” These definitions in the Road Standards express the intent that improvements

are to be classified as either public or private.

Further, the Road Standards define “Private Improvements” and “Gated

Communities/Private Communities.” The Road Standards specify that Private

Improvements must be “clearly defined and marked as such” and would not be

maintained by Taney County. The Road Standards state the “[p]rivate streets in gated or

private communities are encouraged to construct their roadway infrastructure to the same

design requirements and specifications as public improvements.” (Emphasis added.)

Clearly, the Subdivision Regulations contemplated that there would be private roads in

the planning of Taney County plats and roads. The consequence of roads not being in

conformance with the Road Standards is spelled out as “they may not be taken into the

county maintenance program.”

Article 8, Section 2(F)(4) of the Subdivision Regulations, which is cited by

Respondents as supporting its position, requires that “[p]rivate streets shall be constructed

in accordance with Taney County Road Standards.” That statement simply refers back to

12

the Road Standards. The Road Standards provide for public improvements and private

improvements. Persons constructing private streets in gated or private communities are

only “encouraged” to construct their roadway infrastructure to the same design

requirements and specifications as public improvements. Thus, the option of allowing

private streets is set out in every provision of the Subdivision Regulations and the Road

Standards.

CONCLUSION

Taney County had the statutory authority to enact the Code, Subdivision

Regulations, and Road Standards. They did so. When Emerald Pointe came into

existence in 1993 as a subdivision and requested a permit for Phase 12 in 2008, Emerald

Pointe was in conformance with the Road Standards and Subdivision Regulations for

Taney County. At that time, the Commission was fully aware of the terrain of the

property and yet approved a plat which called for “private streets” in Phase 12. The Road

Standards create an exception to their public standards with the language, “unless

otherwise approved by the Planning Commission, all streets shall be public streets.” The

Commission approved Emerald Pointe’s private streets.

Because Emerald Pointe was given the authority to develop Phase 12 of the initial

plat, the Commission did not have the authority to enter the Stop Work Order in 2016.

The Board’s contention eight years after its initial approval of Phase 12, that there is no

difference between private roads and public roads, is not consistent with the Road

Standards and Subdivision Regulations. The designations regarding private and public

streets would have no meaning if we construe the Road Standards and Subdivision

Regulations in the manner suggested by Respondents. Thus, the fifteen percent (15%) or

13

less grade requirement of the Road Standards and any additional road specifications at

issue here are not required for Phase 12 of Emerald Pointe. The Board’s decision to

affirm the Commission’s Stop Work Order’s grading requirements for Phase 12 is not

authorized by law.

Emerald Pointe’s Point I is granted. For the foregoing reasons, we reverse the

judgment of the circuit court with directions that the cause be remanded back to the

Board with directions that the Board grant Emerald Pointe’s appeal of the Commission’s

Stop Work Order.

Nancy Steffen Rahmeyer, P.J. – Opinion Author

Jeffrey W. Bates, J. – Concurs

William W. Francis, Jr., J. – Concurs

14