Opinion

L3 Technologies, Inc.

Court
Armed Services Board of Contract Appeals
Filed
Mar 1, 2021
Status
Published
On the bench
Prouty
Cited by
0 cases
Authority
More cited than 15.1%

“When, during the course of litigation, it develops that the relief sought has been granted or that the questions originally in controversy between the parties are no longer at issue, the case should generally be dismissed.”

How later courts described this case

  • “When, during the course of litigation, it develops that the relief sought has been granted or that the questions originally in controversy between the parties are no longer at issue, the case should generally be dismissed.”
  • though the burden is “heavy,” a case may be dismissed as moot if the defendant can demonstrate that there is “no reasonable expectation that the wrong will be repeated.”
  • “It seems that KBR seeks a presumption that it is entitled to reimbursement simply because it incurred facilities costs. It is not.”

Written by the judges who cited it.

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - )

)

L3 Technologies, Inc. ) ASBCA Nos. 61811, 61813, 61814

)

Under Contract Nos. FA8620-06-G-4002 et al. )

APPEARANCES FOR THE APPELLANT: Karen L. Manos, Esq.

Erin N. Rankin, Esq.

Justin P. Accomando, Esq.

Gibson, Dunn & Crutcher LLP

Washington, DC

APPEARANCES FOR THE GOVERNMENT: Arthur M. Taylor, Esq.

DCMA Chief Trial Attorney

Amelia R. Lister-Sobotkin, Esq.

Trial Attorney

Defense Contract Management Agency

Chantilly, VA

MAJORITY 1 OPINION BY ADMINISTRATIVE JUDGE PROUTY

These three appeals, submitted by appellant, L3 Technologies, Inc. (L3), involve

government claims challenging both indirect and direct costs paid to L3 on several

government contracts for certain years. As the litigation progressed, the government

apparently thought better of its claims and withdrew them in toto and represented it

would make no further claims on the contract years in question. Consequently, the

government has moved for dismissal of these appeals on mootness grounds. L3 opposes,

seeking either summary judgment in its favor or that we deny the motion to dismiss and

keep the appeals live so that it can obtain a victory that, it believes, would preclude its

suffering similar government claims in other contract years. On the facts before us,

we grant the government’s motion and dismiss these appeals as moot. L3’s motion for

summary judgment is denied.

1 These appeals were originally considered by a five-judge division of the Board,

including Judge Kinner, who passed away while the matter was still under

deliberation. Because three of the remaining four judges concurred in this

opinion, there was no need to appoint a fifth judge to the division. Under the

Board’s internal rules, this decision is precedential.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

For the purposes of deciding the motions before us, we need not delve too deeply

into the merits of the underlying appeals, but need to understand their scope and the

limits of what they may accomplish.

I. What the Appeals are About

The first of these appeals, No. 61811, challenges a Contracting Officer’s Final

Decision (COFD) dated June 28, 2018, seeking repayment of $10,692,605 by L3 for

certain “other direct costs” and overhead that had been included in L3’s final indirect

cost rate proposals 2 for the fiscal years 2011, 2012, 2013, and 2014. See compl. ¶ 8. 3

The COFD followed a group of audit reports (one for each contract year) 4 by the Defense

Contract Audit Agency (DCAA), all issued on September 27, 2017, questioning

$14,337,524 of these already-paid costs (id. ¶ 9). These audit reports all utilized some

degree of statistical sampling of particular costs (e.g., individual instances of premium air

travel that the auditor felt were not justified), with results extrapolated across the board

for that cost (id. ¶¶ 12, 15, 20, 22; app. opp’n at 7-8, 10-11 5).

Appeal No. 61813 is an appeal of a far more modest government claim. There, the

June 29, 2018 COFD demanded the payment of $6,002 based upon a February 14, 2018

DCAA audit report that questioned the use of premium airfare for two L3 employees for

the years 2012-2015 (see R4, tab 4 at G000274, G000344-49).

And Appeal No. 61814 is another, even smaller, government claim, resting upon a

different COFD, though also issued on June 29, 2018, seeking $2,542 in premium airfare

incurred by an L3 employee in 2011. It rested upon the same February 14, 2018 DCAA

audit report that informed the COFD in Appeal No. 61813 (see R4, tab 4 at G000274,

G000352-58).

2 For an explanation of how indirect cost rate proposals work, we refer the reader to

Tech. Sys., Inc., ASBCA No. 59577, 17-1 BCA ¶ 36,631.

3 The only appeal for which a complaint was submitted (and it was submitted by the

government) is Appeal No. 61811.

4 These were numbered 9511-2011G10100001, 9511-2012G10100001, 9511-

2013G10100001, and 9511-2014G10100002 (compl. ¶ 9).

5 With the exception of its objection to certain language it deemed inflammatory and some

characterizations of the evidence, the government agrees with the facts presented in

L3’s brief in opposition to its motion to dismiss. See gov’t reply at 2-3. Thus,

much of the procedural history that we set forth here comes from L3’s brief since

both parties agree that it is accurate.

2

II. The Present Litigation and the Government’s Unequivocal Withdrawal of its

COFDs

These three appeals (all submitted to the Board the same day) were immediately

consolidated. L3 then requested that the Board order the government to file the

complaint in Appeal No. 61811, which we directed and the government accomplished. 6

The government’s complaint in Appeal No. 61811 seeks no declaratory or injunctive

relief, but merely explains the basis of its claim and demands payment consistent with the

COFD for the years covered by it. See compl. Discovery followed.

Ultimately, as admitted in a February 28, 2020 email from government counsel to

L3’s attorney, the government decided that it could not defend these appeals. See app.

opp’n, ex. 2. Thus, in a letter to L3’s Chief Financial Officer dated February 28, 2020,

the cognizant administrative contracting officer wrote:

I hereby unequivocally withdraw the Contracting Officer’s

Final Decisions (“COFDs”) and demands for payment dated

28 June 2018 (ASBCA No. 61811), signed by Gladys Broyles,

29 June 2018 (ASBCA No. 60813) signed by Cheryl L. Clark,

and 29 June 2018 (ASBCA No. 60814), signed by

Jennings L. Summers that have been appealed to the ASBCA

and assigned the respective docket numbers. A motion for

dismissal of those appeals will be filed by the assigned trial

attorney. The Government does not intend to re-assert the

costs at issue in those disputes.

(Gov’t mot., ex. 1) L3 makes no assertion that these COFDs may be re-imposed nor

that the government will re-assert its challenge to the costs at issue in those disputes.

We find, as a matter of fact, that the withdrawal of these claims is unequivocal.

III. Other Litigation Involving L3’s Contracts and DCAA Audits

As we will explain more below (and as noted in Judge Clarke’s dissent), L3

opposes the government’s request to dismiss these appeals because it contends it has been

here before. Many times. And without resolution. The dissenting opinion discusses this

at length and, although we come to a different conclusion regarding the legal

consequences, we agree that L3 has been to the Board quite often in recent years as a

consequence of COFDs stemming from incurred cost audits and that none of these

6 The government opposed L3’s motion to require it to file a complaint, stating in its

November 9, 2018 opposition, inter alia, that, L3 “is fully aware of the issues in

these appeals . . . . The disallowances are the results of an ongoing dispute that

has existed for several years and which is the subject of several other disputes

before the Board.” See app. opp’n at 12.

3

appeals has led to a decision on the merits. 7 This happened for appeals of audits of years

2006, 2007, 2008, 2009, and 2010. (App. opp’n at 4-10) Moreover, some of these prior

appeals involved audits which utilized statistical sampling as in the audit that is the basis

of Appeal No. 61811. See, e.g., app. opp’n at 6-7 (referring to the use of decrement for

audit of 2009 direct costs). Appeal Nos. 62123, 62267, and 62268, brought by L3

challenging the disallowance of other incurred costs by the government resting in part on

similar statistical extrapolation, remain pending before the Board, but stayed pending the

outcome of the present appeals. (App. opp’n 13-14)

DECISION

As will be discussed below, the government’s withdrawal of the COFDs moots

these appeals, which are premised upon them since there is simply no additional, legally

cognizable relief that this Board can afford L3. Moreover, neither exception to the

mootness doctrine asserted by L3 – voluntary cessation and capable of repetition yet

evading review – is applicable here.

I. The Mootness Doctrine: Generally, a Case is Moot When an Adjudicatory

Body May No Longer Provide Relief.

In the past, we have had no compunction against dismissing, as moot, appeals in

cases analogous to this one, where the CO has withdrawn COFDs asserting government

claims on incurred costs. In Combat Support Associates, ASBCA Nos. 58945, 58946,

16-1 BCA ¶ 36,288, a case involving incurred cost audits and government claims

disallowing costs already paid, we dismissed the appeal on government motion after the

government claims were withdrawn, writing:

Where a contracting officer unequivocally rescinds a

government claim and the final decision asserting that claim,

with no evidence that the action was taken in bad faith, there is

no longer any claim before the Board to adjudicate, and the

appeal is dismissed. KAMP Systems, Inc., ASBCA No. 54253,

09-2 BCA ¶ 34,196 at 168,995. In such circumstances, the

government’s voluntary action moots the appeal, cf. Teddy’s

Cool Treats, ASBCA No. 58384, 14-1 BCA ¶ 35,601

at 174,410 (dismissing appeal as moot where government

changed default termination to a notice termination), leaving

the Board without jurisdiction to entertain the appeal further.

7 In a significant number of these appeals, however, the matters were settled with the

consent of L3 and not over its objections. See app. opp’n at 4 (appeal of COFD

for 2006 costs settled by parties shortly before hearing), app. opp’n at 5 (appeal of

COFDs for 2007 costs settled by parties), app. opp’n at 7 (appeal of COFDs for

some 2009 costs settled by parties), app. opp’n at 9-10 (appeal of COFDs for other

2009 costs and 2010 costs settled by parties).

4

See Lasmer Indus., Inc., ASBCA No. 56411, 10-2 BCA

¶ 34,491 at 170,123.

16-1 BCA ¶ 36,288 at 176,974; see also Advanced Powder Solutions, ASBCA No. 61818,

19-1 BCA ¶ 37,425, aff’d 831 Fed. Appx. 501 (Fed. Cir. 2020) (dismissing appeal

because, without claim, the Board had no jurisdiction).

We ruled similarly in Quimba Software, Inc., ASBCA No. 59197, 19-1 BCA

¶ 37,350, rejecting Quimba’s complaints that the government had wrongfully compelled

it to expend resources defending against a claim that had no basis, (allegedly) being

brought after the expiration of the statute of limitations. See Quimba Software, 19-1

BCA at 181,613. Indeed, L3, itself, had a previous set of its appeals of government

incurred cost claims dismissed over its objection upon the government’s withdrawal of

the COFD’s in question. 8 See L-3 Communications Integrated Sys., L.P., ASBCA

Nos. 60431, 60432, 16-1 BCA ¶ 36,362.

The basis for such mootness dismissals is the constitutional requirement for a case

or controversy. 9 “Simply stated, a case is moot when the issues presented are no longer

‘live’ or the parties lack a legally cognizable interest in the outcome.” Powell v.

McCormack, 395 U.S. 486, 496 (1969). As the Federal Circuit summarized in Ferring

B.V. v. Watson Labs., Inc.-Fla., 764 F.3d 1382 (Fed. Cir. 2014), “[a] case becomes moot

when interim relief or events have eradicated the effects of a defendant’s act or omission,

and there is no reasonable expectation that the alleged violation will recur.” 764 F.3d

at 1391 (citing County of Los Angeles v. Davis, 440 U.S. 625, 631 (1979)); see also

Chapman Law Firm Co. v. Greenleaf Constr. Co., 490 F.3d 934, 939 (Fed. Cir. 2007)

(“When, during the course of litigation, it develops that the relief sought has been granted

or that the questions originally in controversy between the parties are no longer at issue,

the case should generally be dismissed.”).

It should be clear that this “legally cognizable interest” in the outcome is tied not

merely to the conduct being challenged by the lawsuit, but the relief or remedy available

through continued litigation. The Supreme Court recognized this in Powell v.

McCormack when discussing one of its earlier opinions holding a matter moot: “[The

earlier case] stands . . . for the proposition that, where one claim has become moot and

the pleadings are insufficient to determine whether the plaintiff is entitled to another

remedy, the action should be dismissed as moot.” 395 U.S. at 499. Put another way,

even if a litigant remains harmed by the actions of the other party after that party has

8 This was one of the sets of appeals of which L3 complains above.

9 L3 argues that, to the extent that these decisions rested upon the notion that withdrawal

of the COFD’s divested the Board of jurisdiction by the fact that there was no

longer a COFD to appeal, they were contrary to Board precedent holding that

withdrawal of COFDs does not divest the Board of jurisdiction. See app. opp’n

at 26-30. We rest our opinion here upon the mootness doctrine, which is centered

upon the case-or-controversy requirement, not the lack of a COFD to appeal.

5

changed its behavior to remove the basis of the pending suit, if the court is no longer able

to provide a remedy to that remaining harm, the case is moot. As the Supreme Court

noted in Spencer v. Kemna, a case remains viable only if “throughout the litigation,

the plaintiff ‘must have suffered, or be threatened with, an actual injury traceable to the

defendant and likely to be redressed by a favorable judicial decision.’” 523 U.S. 1, 7

(1998) (quoting Lewis v. Cont’l Bank Corp., 494 U.S. 472, 477 (1990)). The

implications of this straightforward explanation of the law, it will be seen, are significant.

II. On Their Faces, These Appeals Are Moot

Simply speaking, the COFDs appealed here no longer exist – they have been

withdrawn. Moreover, the government has unequivocally stated that it will never again

challenge the incurred price proposals for the contract years at issue. Therefore,

seemingly, there is no relief we may grant and the appeals should be dismissed. This is

very much like the circumstances we saw in Combat Support Associates, Quimba, and

the previous 2016 L3 decision. Thus, if there weren’t more to it, we could comfortably

grant the government’s motion based upon our precedent.

III. The Voluntary Cessation Doctrine Is Inapplicable Here Because The Harm

Being Appealed Is Unlikely To Recur

But there is somewhat more to it: L3 argues that the two exceptions to the

mootness doctrine preclude dismissal. The first of these, “voluntary cessation,” is where

L3 makes its primary argument. See app. opp’n at 21-32. L3 quotes the Supreme Court

as holding that, “[i]t is well settled that ‘a defendant’s voluntary cessation of a challenged

practice does not deprive a federal court of its power to determine the legality of the

practice.’ ‘[I]f it did, the courts would be compelled to leave “[t]he defendant … free to

return to his old ways.’” (App. opp’n at 18; citing to Friends of the Earth, Inc. v.

Laidlaw Envtl. Servs., Inc., 528 U.S. 167, 189 (2000) (internal citations omitted)

However, as L3 rightly concedes, it is not that voluntary cessation could never support a

dismissal for mootness, just that the party seeking dismissal must also demonstrate that

the objected to actions will not recur. Hence, in County of Los Angeles, the Supreme

Court explained that the voluntary cessation doctrine would not apply if: “it can be said

with assurance that ‘there is no reasonable expectation . . .’ that the alleged violation will

recur, and (2) interim relief or events have completely and irrevocably eradicated the

effects of the alleged violation.’” 440 U.S. at 631 (citations omitted); see also United

States v. W.T. Grant Co., 345 U.S. 629, 633 (1953) (though the burden is “heavy,” a case

may be dismissed as moot if the defendant can demonstrate that there is “no reasonable

expectation that the wrong will be repeated.”).

The motion here turns on the question of what “wrong” is at issue. The

government argues that the wrong at issue is delimited by the COFDs being appealed:

the government’s rejection of cost submissions for particular contract years, which the

government asserts it will never again reject. No argument is made by L3 that these will

6

ever return. If the government is correct (and it is), the voluntary cessation doctrine does

not apply because there is no reasonable expectation that the wrong will be repeated.

L3 appears to see the wrong(s) that may be repeated as the government’s

challenges to L3’s corporate travel policy and its use of its statistical means of

challenging its incurred cost submissions. See, e.g., app. opp’n at 20. If those were the

wrongs that these appeals could legally eliminate, we would agree that the voluntary

cessation doctrine might require our denial of the government’s motion. They aren’t.

These appeals do NOT seek a declaratory judgment or injunctive relief finding

L3’s corporate travel policy appropriate or preventing the statistical sampling

methodology which L3 finds so objectionable. 10 Thus, if we refused to dismiss the

appeals, and if L3 were to obtain a complete legal victory on the merits, the remedy that

L3 would obtain would be no more than it is already getting by the withdrawal of the

COFDs: it would no longer be obliged to repay the government the costs set forth in

the three withdrawn COFDs. L3 and the dissent appear to be laboring under the

mistaken notion that winning on the merits here would, per se, decide the propriety of

L3’s travel policies once and for all and prevent the future use of DCAA’s statistical

sampling and extrapolation methodologies in other audits, but there is no basis for such

a belief. After all, entitlement to a decision on an appeal is not the same thing as

entitlement to binding precedent, generalized beyond the years of a particular dispute,

upon the issues of interest to a particular party. 11 To be sure, a victory on the merits

would be satisfying to L3 and present a rhetorical cudgel to use against DCAA in the

future – perhaps even to persuasive effect – but the only thing certain that it would do

for L3 would be to provide relief for the years at issue and that is already being given. 12

That is why we have placed so much emphasis on the “legally cognizable relief” part of

the mootness definitions, for it defines the arena in which the mootness analysis and,

necessarily, its exceptions apply. The 10th Circuit Court of Appeals came to a similar

conclusion in Chihuahuan Grasslands Alliance v. Kempthorne, 545 F.3d 884 (10th Cir.

2008), a case in which the plaintiffs fought a motion to dismiss on mootness grounds by

arguing that the court was presented with a case of both voluntary cessation, and

10 Given the fact that, at L3’s demand, the government filed the complaint here, this is

hardly surprising. But even if L3 had filed the complaint, itself, we are not so

certain that its appeal of the government’s claims would have entitled it to seek such

relief – a matter which we need not address as it remains hypothetical, just as the

possibility of a claim seeking a contractual interpretation finding L3’s travel policies

to be appropriate or barring the use of DCAA’s statistical modeling would be.

11 To state the obvious, the law provides a way for a litigant to get that binding precedent:

declaratory or injunctive relief. If a party wants it, it must explicitly seek it, rather

than hoping to obtain it as an incidental consequence of its monetary claims.

12 Moreover, if “case or controversy” has any meaning at all, merely symbolic wins, with

no formal legal consequence, no matter how helpful to a party, are not what courts

are for. See, e.g., Massachusetts v. E.P.A., 549 U.S. 497, 547 (2007) (Roberts, CJ,

dissenting).

7

“capable of repetition yet evading review” (which we address below). The Court of

Appeals held that, for purposes of mootness determination, it was proper to “rely on the

claims and requests for relief in the Complaint” and not the broader issues that the

plaintiffs later wished to address. 545 F.3d at 892-93. Such are the circumstances here.

IV. The Dismissed Appeals Are Not an Injury Capable of Repetition, Yet

Evading Review

If the voluntary cessation doctrine may be thought of as preventing one of the

interested parties from pulling the rug out from under the other, “capable of repetition,

yet evading review” is the circumstance where the very nature of the alleged wrong

precludes judicial review because its duration is too short, but the controversy is expected

to return. It was first enunciated in S. Pac. Terminal Co. v. ICC, 219 U.S. 498 (1911),

and has been part of jurisprudence ever since, recently discussed in a procurement

context by the Supreme Court in Kingdomware Technologies, Inc. v. United States,

136 S. Ct. 1969 (2016). As summed up in Kingdomware:

[T]his Court’s precedents recognize an exception to the

mootness doctrine for a controversy that is “‘capable of

repetition, yet evading review.’” Spencer v. Kemna, 523 U.S.

1, 17, 118 S.Ct. 978, 140 L.Ed.2d 43 (1998). That exception

applies “only in exceptional situations,” where (1) “the

challenged action [is] in its duration too short to be fully

litigated prior to cessation or expiration,” and (2) “there [is] a

reasonable expectation that the same complaining party [will]

be subject to the same action again.” Ibid. (internal quotation

marks omitted; brackets in original).

136 S. Ct. 1976. But this is not the kind of case for which this exception applies.

First, nominally, there would be ample time for the matter to be reviewed by the Board or

the Court of Federal Clams. Cost allowability determinations, like the ones at issue here,

are not the type of actions that end after a given period time; rather, they have no

expiration date and are simply about who is entitled to a certain amount of money.

Moreover, L3 obtained its full remedy: full review was, in fact, available and the

only reason that a judicial decision wasn’t issued was because it was not necessary.

To the extent that L3 attempts to argue that the government’s actions are what

made the duration too short to afford review (see app. opp’n at 32-33), thus placing this

matter into the capable of repetition yet evading review rubric, it has made the logical

fallacy known as a category error. For under this approach, all instances of voluntary

cessation would fall within the capable of repetition yet evading review classification and

there would be no point in the separate analysis. It is more consistent with the legal

paradigm of mootness exceptions to review the government’s actions here under the

voluntary cessation umbrella. Moreover, as discussed above, the unavailability of a

8

legally cognizable remedy deprives us of a case or controversy, leaving no basis to apply

the second exception, even if it were otherwise proper to do so.

CONCLUSION

Because these appeals are moot, they are dismissed. This action makes L3’s

motion for summary judgment, itself, moot, since we no longer possess jurisdiction over

these appeals, and we deny it as such.

Dated: March 1, 2021

J. REID PROUTY

Administrative Judge

Vice Chairman

Armed Services Board

of Contract Appeals

I concur I concur

RICHARD SHACKLEFORD ELIZABETH WITWER

Administrative Judge Administrative Judge

Acting Chairman Armed Services Board

Armed Services Board of Contract Appeals

of Contract Appeals

I dissent (see separate opinion)

CRAIG S. CLARKE

Administrative Judge

Armed Services Board

of Contract Appeals

9

DISSENTING OPINION BY ADMINISTRATIVE JUDGE CLARKE

I respectfully dissent because I believe the mootness exception applies. The

majority decision subjects L3 (and other contractors) to the unfortunate chain of events

discussed below until DCAA and DCMA resolve whatever their differences are. I wrote

the original decision with which my colleagues disagree. I have attached my original

decision as my dissent. 13

In these appeals of government claims, the contracting officer unequivocally

withdrew the supporting final decisions stating the claims would not be asserted again

rendering the appeals moot. I find that the final decisions are moot. For the first time,

the Board should allow a moot case to proceed based on the exception to mootness

doctrine. After resolving the mootness matter, I interpret FAR 31.201-3, Determining

reasonableness, to properly allocate the burden of proof. Finally, I would deny L3’s

motion, which I deem to be a motion for summary judgment, because of material

disputed facts concerning allowability of L3’s costs. The Board has jurisdiction pursuant

to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-9.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

Relevant FAR Clauses

1. Two FAR clauses 14 play an important role in the Defense Contract Audit

Agency (DCAA) Audits:

FAR 31.201-2, Determining allowability.

(a) A cost is allowable only when the cost complies with all

of the following requirements:

(1) Reasonableness.

(2) Allocability.

(3) Standards promulgated by the CAS Board, if

applicable, otherwise, generally accepted accounting

principles and practices appropriate to the

circumstances.

(4) Terms of the contract.

13 I attempted to resolve the change from “we” to “I” in adapting my decision to a dissent

but may not have been totally successful.

14 I do not list FAR 31.201-4, Allocability, because there is no disagreement over the fact

these costs are allocable to L3’s contracts.

10

(5) Any limitations set forth in this subpart.

And:

FAR 31.201-3, Determining reasonableness.

(a) A cost is reasonable if, in its nature and amount, it does

not exceed that which would be incurred by a prudent

person in the conduct of competitive business.

Reasonableness of specific costs must be examined with

particular care in connection with firms or their separate

divisions that may not be subject to effective competitive

restraints. No presumption of reasonableness shall be

attached to the incurrence of costs by a contractor. If an

initial review of the facts results in a challenge of a

specific cost by the contracting officer or the contracting

officer’s representative, the burden of proof shall be upon

the contractor to establish that such cost is reasonable.

(b) What is reasonable depends upon a variety of

considerations and circumstances, including-

(1) Whether it is the type of cost generally recognized as

ordinary and necessary for the conduct of the

contractor’s business or the contract performance;

(2) Generally accepted sound business practices,

arm’s-length bargaining, and Federal and State laws

and regulations;

(3) The contractor’s responsibilities to the Government,

other customers, the owners of the business,

employees, and the public at large; and

(4) Any significant deviations from the contractor’s

established practices.

DCAA Audit Methodology 15

2. The method DCAA uses to conduct its audits depends on the volume of cost

data. In a few situations the volume of cost data may be small enough that DCAA can

15 I readily admit that the audit reports, expert reports and briefs do not afford a complete

understanding of DCAA’s procedures to include Dollar Unit Sampling (DUS),

11

conduct a 100% audit. In most situations the data is voluminous making 100% audit

impossible. In these situations DCAA must use statistical analysis to perform its audits

and reach its conclusions. DCAA has an in-house developed statistical tool called

“EZ-Quant” that it uses to select a sample based on DCAA’s size criteria and then

conducts a 100% audit of the sample to determine the questioned costs in the sample.

DCAA then “extrapolates” the questioned costs in the sample to the remaining costs to

arrive at its conclusions on total unallowable costs (app. opp’n at 10-11, 15-16, 24)16. At

times DCAA will question the accuracy EZ-Quant results and resort to a sample based on

auditor judgmental selection (app. opp’n at 11). DCAA discusses its methodology in its

opposition, here is an example:

DCAA auditor Cynitra Kennard, under the supervision of

Mr. North, audited L3’s shelter differential costs for

2011-2014, and selected a sample of transactions using

EZ-Quant. Ms. Kennard testified that she used EZ-Quant

again to audit shelter differential costs for 2015-2016.

Kennard Dep. at 28:12-18. The 2015-2016 audit report

confirms that DCAA used statistical sampling methodology

to select a sample and extrapolate questioned costs. Ex. 25

at 55. For 2017, Ms. Kennard likewise used EZ-Quant and

statistical sampling to extrapolate questioned costs for L3’s

off-site living allowances. Id. at 26:20-22; Ex. 26 at 43-44.

Ms. Kennard also testified that she used EZ-Quant to select

the sample transactions from the shelter differential account

for the 2018 ICP audit, which is ongoing. Kennard Dep. at

26:3-17.

(App. opp’n at 16)

The DCAA Audits

3. These claims were audited by DCAA resulting in Audit Reports for L3’s

Mission Integration Division (MID), dated September 27, 2017, and Platform Integration

Division (PID), dated February 14, 2018. The audit report for MID are 9511-

2011G10100001, 9511-2012G10100001, 9511-2013G10100001 and 9511-

2014G10100002 for L3’s fiscal years 2011 to 2014 (R4, tab 2). The audit report for PID

are 9511-2011W10100001, 9511-2012W10100001, 9511-2013W10100001 for L3’s

fiscal years 2011 to 2013 (R4, tab 3).

4. In the audit reports for MID, DCAA questioned the following costs:

Physical Unit Sampling (PUS), and judgmental selection, but I have sufficient

detail required for our decision.

16 I rely on L3’s Statement of Facts because DCMA generally agrees with L3’s facts

except for certain characterizations (gov’t resp. at 2-3).

12

• $56,285 of the contractor’s claimed CFY 2011-2014 Indirect Labor costs.

• $5,539,395 of the contractor's claimed CFY 2011-2014 Outside Services

costs.

• $4,359,465 of the contractor’s claimed CFY 2011-2014 Employee

Relocation costs.

• $67,153 of the contractor’s claimed CFY 2011-2014 Settlement to Cost

Center costs.

• $178,270 of the contractor’s claimed CFY 2011-2014 Indirect Travel

Airfare costs.

• $137,975 of the contractor’s claimed CFY 2011 L3 Corporate Allocation

costs.

• $288,719 of CFY 2014 Corporate Home Office Allocation costs.

• $791,170 of the contractor’s claimed CFY 2011 Home Office Allocation

costs.

• $14,337,524 of the contractor’s claimed Direct Costs. Exhibit C identifies

the questioned amounts by account.

(R4, tab 2 at 4) DCAA provided additional detail in Exhibit A (Indirect costs),

Schedule A-07 (R4, tab 2 at 20-45), and Exhibit C (Direct costs), Schedule C-05 (R4,

tab 2 at 80-100). At the end of the audit DCAA offered to provide more information,

“Due to the voluminous nature of the calculations related to these questioned costs,

additional information will be provided upon request” (R4, tab 2 at 100).

5. In the audit reports for PID, DCAA questioned the following costs:

• $297,177 ($267,113 + $30,064) of the contractor’s claimed CFYs 20112013

Indirect Travel – Airfare costs.

• $128,246 of the contractor’s claimed CFYs 2011-2013 Bonus Costs which

are included in the claimed Fringe Expenses.

• $37,511 of the contractor’s claimed CFY 2011 Workers Compensation

Fringe Costs.

• $82,429 of the contractor’s claimed Direct Costs.

13

(R4, tab 3 at 6) DCAA provided supporting detail in Exhibit A, indirect costs 2011-2013

(id. at 12); Schedule A-01, air travel and marketing, G&A and engineering for 2011 (id.

at 16-18); Schedule A-02, engineering air travel for 2011 (id. at 21); Schedule A-03,

fringe for 2011 (id. at 22-25); Schedule A-04, G&A air travel for 2012 (id. at 26);

Schedule A-05, engineering air travel for 2012 (id. at 27); Schedule A-06, fringe for 2012

(id. at 28); Schedule A-07, G&A air travel for 2013 (id. at 29); Schedule A-08,

engineering airfare for 2013 (id. at 30); Schedule A-09, fringe air travel for 2013 (id.

at 31); Exhibit B, penalties for 2011 to 2013 (id. at 32-44); and Exhibit C, direct costs air

travel for 2011 to 2013 (id. at 45-47).

DCMA Contracting Officer Final Decisions17

6. According to the Board’s docketing notice (R4, tab 4 at 1) the following

ASBCA Nos. are associated with the following government claims:

ASBCA No. Claim

61810 Government claim for $347,915

61811 Government claim for $10,692,605

61812 Government claim for $572,318

61813 Government claim for $6,002

61814 Government claim for $2,542

ASBCA No. 61810 was settled and dismissed with prejudice. ASBCA No. 61812

was dismissed without prejudice for lack of jurisdiction leaving ASBCA Nos. 61811,

61813 and 61814 active in this appeal.

7. On June 28, 2018, Ms. Gladys Broyles, Defense Contract Management Agency

(DCMA) Administrative Contracting Officer (ACO), issued a Contracting Officer’s Final

Decision (COFD) demanding payment of $10,692,605 based on DCAA Audit Report

Nos. 9511-2011G10100001, 9511-2012G10100001, 9511-2013G10100001,

9511-2014G10100002, dated September 27, 2017 (R4, tab 4 at 28). Based on the

docketing notice this COFD relates to ASBCA No. 61811. ACO Broyles broke down her

decision into six unallowable direct cost amounts:

ODC Travel Air $1,335,924

ODC Hotel $443,368

ODC Meals $210,771

ODC Shelter Differential $7,602,056

ODC Other $1,100,486

G&A $1,722,601

17 At this point it is difficult, but also unnecessary, to trace the dollar amounts in the

audits directly to the amounts in the final decisions.

14

(R4, tab 4 at 30-31) ACO Broyles provided the rational for her finding in six notes

associated with each of the six amounts disallowed (id. at 31-40). ACO Broyles

repeatedly relied on FAR 31.201-3(a) to place the burden to prove challenged costs are

reasonable on L3 (id. at 31-38).

8. On June 29, 2018, ACO Cheryl Clark issued a COFD demanding payment of

$6,002 based on DCAA Audit Report No. 9511-2011W10100001 (R4, tab 4 at 71). Based

on the docketing notice this COFD relates to ASBCA No. 61813. ACO Clark explained

the $6,002 as follows, “This pertains to contract number FA8620-10-G-3023-1118

regarding the travel expenses of Frank Franklin and Mark Cross from January 1, 2012 to

January 12, 2015 outlined in document numbers 19003022785 and 1900303999” (id.).

ACO Clark further explained, “Under FAR 31.201-3(a) if the contracting officer

challenges the specific costs . . . ‘the burden of proof shall be upon the contractor to

establish that such cost is reasonable.’ As a result, in order to establish reasonableness, L3

PIO has the burden of justifying the need for premium airfare under FAR 3 l-205-46(b) to

include FAR 3 l.205(46)(a)(7)” (id. at 73).

9. On June 29, 2018, ACO Jennings L. Summers issued a COFD demanding

payment of $2,542 based on DCAA Audit Report No. 9511-2011W10100001 (R4, tab 4

at 79). Based on the docketing notice this COFD relates to ASBCA No. 61814. ACO

Summers explained that the disallowed amount related to air travel by Mr. Bays. ACO

Summers further explained, “Given the above, under FAR 31.201-3(a), I cannot find that

a reasonably prudent person would incur the cost of business class airfare for air travel of

three hours. The return coach airfare trip supports my position. As a result, under

31.201-3(a) the burden of proof is on L3 to establish reasonableness fell to L3” (Id.

at 81).

L3 Appeals

10. L3 appealed the COFDs to the Board (app. opp’n at 11 ¶ 22).

DCMA Withdraws the COFDs and Moves for Dismissal

11. On February 28, 2020 DCMA ACO Charles A. McGlothen withdrew the

COFDs:

I hereby unequivocally withdraw the Contracting Officer’s Final

Decisions (“COFDs”) and demands for payment dated 28 June 2018

(ASBCA No. 61811), signed by Gladys Broyles, 29 June 2018

(ASBCA No.60813) signed by Cheryl L. Clark, and 29 June 2018

(ASBCA No.60814), signed by Jennings L. Summers that have been

appealed to the ASBCA and assigned the respective docket numbers.

A motion for dismissal of those appeals will be filed by the assigned

trial attorney. The Government does not intend to re-assert the costs

at issue in those disputes.

15

(Gov’t mot., ex. 1) DCMA filed a Motion to Dismiss on the same day, February 28,

2020 (gov’t mot.).

Other Audit Disputes

12. In its opposition to DCMA’s motion to dismiss, L3 summarizes similar audit

disputes between L3 and DCAA/DCMA from 2006 through 2018. These disputes all

followed a similar path: DCAA conducts Audits challenging costs, DCMA issues

COFDs implementing the DCAA Audits and demanding repayment of the challenged

costs, L3 appeals the COFDs to the Board and DCMA either withdraws the COFDs or

the parties settle for a nuisance amount resulting in dismissal of the appeals with

prejudice (app. opp’n ¶¶ 3-5 (2006), 6-8 (2007), 9-12 (2008), 13-15 (2009) and 16-19

(2010). The disputes involved in this decision followed a similar path but remain

unresolved (app. opp’n ¶¶ 20-22 (CYs 2011 to 2014)). There are several similar appeals

that have been stayed pending resolution of the appeals in ASBCA Nos. 61811, 61813

and 61814 (app. opp’n ¶¶ 27-28, 33 (CYs 2011 to 2016)).

13. In its opposition, L3 makes the point that this cycle of DCAA Audit using

statistical analysis and extrapolation, DCMA COFDs, appeal and withdrawal of the

COFDs is seen from 1006 through 2018:

As described above, DCMA ACOs have issued COFDs

disallowing L3’s airfare costs year after year since 2006 and

then subsequently withdrew the claims or settled for nuisance

amounts. This dispute has continued with DCAA’s 2015-2016

and 2017 audit reports.

(App. opp’n at 16) And:

However, it is clear that DCAA continues to question the

same types of costs for the same reasons, and DCAA also

continues to use the same purported statistical sampling

methods.

(App. opp’n at 15) And:

During those depositions, several of the auditors who were

involved in subsequent audits of ICPs (i.e., the 2015, 2016,

2017, and 2018 ICPs) admitted that DCAA employed

statistical sampling to extrapolate and question costs in those

subsequent audits.

(App. opp’n at 15) And:

16

As of the date of this filing, DCMA has not issued a COFD

sustaining the costs questioned in those reports. However, it

is clear that DCAA continues to question the same types of

costs for the same reasons, and DCAA also continues to use

the same purported statistical sampling methods.

(App. opp’n at 15)

Expert Witnesses

14. Each party employed an expert and submitted an expert report. Neither party

objected to the expert status of the other party’s expert, therefore, I find both witnesses

qualify as experts in statistical analysis.

15. L3’s expert is Mr. Lynford Graham. In his expert report Mr. Graham explains

that he was hired by L3 “to comment on the applications of statistical sampling in the

Defense Contract Audit Agency (DCAA) claims of questioned costs as stated in the

2 audit reports at issue in the appeals of L3 Technologies, Inc. (L3), ASBCA Nos. 61810,

61811, 61813, 61814” (app. opp’n, ex. 22 at 4-5). Mr. Graham concludes that DCAA’s

methods using Dollar Unit Sampling (DUS), Physical Unit Sampling (PUS), DCAA’s

sample size selection, and DCAA’s “EZ-Quant” software used by the DCAA to apply

statistical techniques all result in unreliable results (id. at 5-6). Specifically, DCAA’s

methods and software used “for the purpose of estimating questioned costs are not

supportable” (id. at 6). Attached to Mr. Graham’s report is Appendix A: Summary of

Sampling Applications in L3 Technology Audits (id. at 46). The table indicates that

sampling was used for six out of eight costs. By way of explanation I look at employee

relocation costs. According to the table, DUS sampling was used on a “population” of

$7,822,914 using a sample of 89 resulting in disallowing $4,359,456 18 (id.).

16. DCMA’s expert is Mr. Ali Arab. 19 In his rebuttal report Mr. Arab starts out

by distinguishing DCAA audits, “The audits performed by DCAA are significantly

different than financial audits. The purpose of an incurred cost audit (the subject of the

L3 ASBCA cases) is to provide an opinion on the contractor’s certified assertion that the

incurred cost submission does not contain unallowable costs” (app. opp’n, ex. 23 at 6).

He further explained:

My report is focused on DCAA’s sampling program as used

in the L3 audits. It is important to note that DCAA

questioned a total of $26.2 million; of which $5.6 million

(21.4 percent) was based on statistical sampling projections.

18 The table is not completely self-explanatory and the numbers may be a little off

because the table is a bit illegible but it serves its purpose for this decision.

19 DCMA produced Mr. Arab’s expert rebuttal report but expressed its intention not enter

it into evidence (gov’t resp. at 22).

17

The remaining $20.6 million is based on methods outside of

the use of statistical sampling.

(Id. at 7) Mr. Arab found that the sample sizes used by DCAA were based on 80% not

90% confidence level and were therefore smaller than DCAA desired. DCAA’s use of

DUS sample size planning procedure also contributed to a small sample size (id. at 8).

He explained that when DCAA used statistical samples to calculate questioned costs, the

DCAA audit reports present the point estimate as the most likely amount of the true

questioned costs in the audit universe under review (id. at 11-12). Mr. Arab conducted an

in-depth review of EZ-Quant and did not identify any issues or concerns (id. at 15).

17. Mr. Arab explained that Audit Report No. 09511-2011G10100001, dated

September 27, 2017, used statistical sampling for 21.8 percent of the total questioned

costs while the remaining questioned costs were from reviewing individual transitions

using judgmental selection (id. at 15-16). None of the questioned costs in Audit Report

No. 09511-2011W10100001, dated February 14, 2018, resulted from projections of

statistical samples. All costs questioned were from review of each transaction using

judgmental selection. (Id. at 16) Mr. Arab also attached a table at the end of his expert

report presenting DCAA’s methods of arriving at its questioned coasts (id. at 22).

DCAA TOP Note

18. On January 17, 2020, DCAA, apparently relying on Mr. Arab’s findings,

issued a “TOP Note” that changed the sample size for Dollar Unit Sampling:

Dollar Unit Sampling (DUS): DCAA's sampling program is

intended to use a two-sided limit at the 90 percent confidence

level. However, our evaluation determined that the AICP A

Table we have used to determine minimum sample sizes is

'based on a one-sided confidence limit. Consequently, the

sample sizes correspond to a two-sided limit at the 80 percent

confidence level; not the two-sided limit at the 90 percent

confidence level we had instructed.

Using a lower confidence level results in sample sizes that are

smaller than desired which impacts the confidence we have in

the point estimate. As a result, our sample sizes will increase.

To address this issue, when performing a DUS sample, please

use the chart below to determine minimum sample sizes.

(Chart omitted).

(App. opp’n, ex. 24 at 2) DCAA also changed the sample size for Physical Unit

Sampling:

18

Physical Unit Sampling (PUS): Prior to this Top Note,

DCAA used the DUS sample size planning procedure for a

physical unit sample. We determined this methodology is not

justifiable as the underlying theory for these two methods are

quite different. Consequently, the sample sizes determined

for PUS using this approach may potentially be smaller than

required for a statistically valid sample. To address this issue,

when performing a PUS sample, please use the EZ Quant

sample sizer to determine the appropriate sample size. The

Table is no longer valid for PUS. Enclosure 1 provides

details on how to use the EZ Quant Sample Sizer.

(Id. at 3)

DECISION

Procedural Background

After L3 appealed DCMA’s COFDs (SOF ¶ 10), ACO Charles A. McGlothen

issued a February 28, 2020 letter “unequivocally” withdrawing COFDs for Appeal

Nos. 61811, 61813 and 61814. The ACO stated, “The Government does not intend to re-

assert the costs at issue in those disputes” (SOF ¶ 11). Also on February 28, 2020,

DCMA filed with the Board a Motion to Dismiss ASBCA Nos. 61811, 61813 and 61814

as moot (id.).

Rather than accepting dismissal, L3 chose to fight. On March 4, 2020 L3 filed its

Opposition to Government’s Motion to Dismiss and Cross-Motion for a Decision

Sustaining the Appeals (app. opp’n). On April 16, 2020 DCMA filed its Response to

Appellant’s Opposition and Cross-Motion arguing that the appeals were moot (gov’t

resp.). On May 18, 2020, L3 filed its Reply in Support of its Opposition to the

Government’s Motion to Dismiss and Cross-Motion for a Decision Sustaining the

Appeals (app. reply). I view L3’s Cross-Motion for a Decision Sustaining the Appeals as

a Motion for Summary Judgment.

The details of above procedural posture is a little confusing. However, the “big

picture” is that first I must decide if the appeals are moot and if so, does the mootness

exception apply? If the exception applies, I address L3’cross motion that I deem a

Motion for Summary Judgment. As explained below, I find the appeals are moot but the

mootness exception applies and I deny L3’s motion. Therefore, L3 may continue to

pursue its appeals and (1) challenge DCAA’s statistical audit procedures and

extrapolation of costs found to be unallowable and (2) prove the reasonableness of the

alleged unallowable costs.

19

Positions of the Parties

DCMA believes that the appeals should be dismissed as moot based on the

unequivocal withdrawal of the final decisions and promise not to reassert the claims

(gov’t mot. at 1). DCMA opposes L3’s argument that the appeal remains “live” because

there is no possibility that DCMA will reassert the claim (gov’t resp. at 2, 4, 15, 20, 23).

L3 sums up what it wants as follows:

More importantly, the appeals are not moot because the issues

presented in the appeals remain live: L3 seeks a decision on

the merits to resolve the issues presented in these appeals—

the continuing dispute over the correct interpretation of

various FAR sections related to L3’s incurred costs and

DCAA’s use of purported “statistical” sampling to extrapolate

questioned costs—which remain live despite the withdrawal

of the COFDs.

(App. opp’n at 24) L3 argues that DCAA’s statistical sampling and “extrapolation” of

questioned costs is flawed. L3 argues, “EZ-Quant is DCAA’s fundamentally flawed

statistical sampling software application” (app. opp’n. at 16).

Next L3 raises the issue of the correct interpretation of various FAR sections

related to L3’s incurred costs. Central to L3’s position is the allocation of burden of

proof. L3 contends that since these are government claims, DCMA has the burden of

proof. L3 reasons that since DCMA abandoned its claims, L3 is entitled to judgment on

the merits due to DCMA’s failure to prove its case.

ASBCA Nos. 61811, 61813 and 61814 are Moot

The Board has many decisions dismissing appeals as moot. One of the latest is

Quimba Software, Inc., ASBCA No. 59197, 19-1 BCA ¶ 37350:

In seeking dismissal of the appeal on the ground of mootness,

the government argues that the ACO granted all the relief that

Quimba sought by voluntarily rescinding the demand for

repayment of indirect costs paid through provisional billing

rates and stating that it does not intend to issue another

decision disallowing the same costs (gov’t mot. at 3-5; see

statement 7).

Quimba opposes the dismissal. Quimba's main argument is

that, while the final audit report was issued in 2008, the

government waited until December 2013, after expiration of

20

the Contract Disputes Act statute of limitations, 41 U.S.C.

§7103(a)(4)(A), to issue the final decision.

....

We reject Quimba's argument and dismiss the appeal as moot.

(Id. at 181,613) In Beechcraft Defense Co., ASBCA No. 61550, 18-1 BCA

¶ 37,069 we wrote:

Where a contracting officer unequivocally rescinds a final

decision asserting a government claim, there is no longer any

claim before the Board to adjudicate, and the Board has

dismissed the appeal as moot. URS Federal Support Services,

Inc., ASBCA No. 60364, 17-1 BCA ¶36,587 at 178,204;

Combat Support Associates, ASBCA Nos. 58945, 58946, 16-1

BCA ¶36,288 at 176,973. Accordingly, the appeal is

dismissed as moot.

(Id. at 180,431) I find that DCMA’s February 28, 2020 “unequivocal” withdrawal of

COFDs in ASBCA Nos. 61811, 61813 and 61814 and promise not to “re-assert the costs

at issue in those disputes” (SOF ¶ 11) renders these appeals moot.

The Exception to Mootness20

At the risk of stating the obvious, this repetitive cycle of DCAA Audits

challenging costs, DCMA COFDs demanding repayment of the challenged costs, L3’s

ASBCA appeals and DCMA’s dismissals without reaching the merits is untenable

(SOF ¶¶ 12-13).21 The root cause of why DCMA first adopts DCAA’s audit results and

then abandons the audits after an appeal is filed is unclear.

20 The majority seems to focus on “voluntary cessation” not the mootness exception.

21 This situation is apparently not limited to L3. Quimba Software, Inc., ASBCA

No. 59197, 19-1 BCA ¶ 37350; Advanced Powder Solutions, Inc., ASBCA

No. 61818, 19-1 BCA ¶ 37425; Northrop Grumman Corp., ASBCA No. 61771,

2019 WL 5089236; Northrop Grumman Corp., ASBCA No. 61345, 2019 WL

4908683; L3 Communications Integrated Systems, L.P., ASBCA No. 60431, 16-1

BCA ¶ 36362; Sygnetics, Inc., ASBCA No. 60357, 18-1 BCA ¶ 37160;

Flightsafety International Inc., ASBCA No. 60415, 2018 WL 7200012; Combat

Support Associates, ASBCA No. 58945, 16-1 BCA ¶ 36288; Beechcraft Defense

Co., ASBCA No. 61550, 18-1 BCA ¶ 37069; York International Corp.-York Navy

Systems, ASBCA No. 60561, 2016 WL 3565932; Autonomous Solutions, Inc.,

ASBCA No. 59131, 2014 WL 518988.

21

I start with the Supreme Court’s discussion of the exception to mootness in

Weinstein v. Bradford, 96 S.Ct. 347 (1975). In Weinstein v. Bradford the Supreme Court

did not apply the exception to mootness doctrine but did discuss it in the process of

reaching its decision:

In Sosna v. Iowa, 419 U.S. 393, 95 S.Ct. 553, 42 L.Ed.2d 532

(1975), we reviewed in some detail the historical

developments of the mootness doctrine in this Court.

Southern Pacific Terminal Co. v. ICC, 219 U.S. 498, 31 S.Ct.

279, 55 L.Ed. 310 (1911), was the first case to enunciate the

“capable of repetition, yet evading review” branch of the law

of mootness. There it was held that because of the short

duration of the Interstate Commerce Commission order

challenged, it was virtually impossible to litigate the validity

of the order prior to its expiration. Because of this fact, and

the additional fact that the same party would in all probability

be subject to the same kind of order in the future, review was

allowed even though the order in question had expired by its

own terms.

Sosna decided that in the absence of a class action, the

“capable of repetition, yet evading review” doctrine was

limited to the situation where two elements combined: (1) the

challenged action was in its duration too short to be fully

litigated prior to its cessation or expiration, and (2) there was

a reasonable expectation that the same complaining party

would be subjected to the same action again.

(Id. 348-49)

I found no ASBCA decisions applying this exception to mootness, but I did find

one decision acknowledging its existence. In Combat Support Associates, ASBCA

No. 58945, 16-1 BCA ¶ 36288 we stated:

We disagree with CSA that we are confronted with a dispute

that is “capable of repetition, yet evading review.” A case is

moot when the issues presented are no longer “live” or the

parties lack a legally cognizable interest in the outcome.

Humane Society of the United States v. Clinton, 236 F.3d

1320, 1331 (Fed. Cir. 2001). However, a claim is not moot if

that action is capable of repetition, yet evading review. Id.

To qualify for this exception, the challenged action must meet

two conditions. Id. First, the action must in its duration be

too short to be fully litigated prior to its cessation or

expiration. Id. Second, there must be a reasonable likelihood

22

that the party will again suffer the injury that gave rise to the

suit. Id.

(Id. at 176,974) I conclude from Combat Support Associates that there is no impediment

to the Board’s reliance on the mootness exception in the right circumstances. If there was

ever the “right circumstance,” this is it.

DCMA’s Position

DCMA opposes the application of the “exception” to mootness as follows:

There is no unlawful activity or wrongful behavior. Second,

the exception applies when the wrongful behavior is capable

of repetition. While it is clear that the Government will

continue to determine the allowability of airfare costs in

future incurred cost submissions for both L3 and other

contractors and may continue to utilize statistical sampling in

estimating the amount of those unallowable costs, the

Government’s future practice will not affect L3’s entitlement

to the costs originally questioned in the Government claims at

issue in these appeals.[ 22]

(Gov’t resp. at 6-7) I disagree with DCMA’s inference that the mootness exception

requires “unlawful activity or wrongful behavior” or that DCMA’s “future practice will

not affect L3’s entitlement to the costs originally questioned.” The cases highlighted

below do not involve unlawful activity or wrongful behavior. DCMA’s arguments

against the mootness exception are unpersuasive.

Examples Where the Exception Applied

L3 cited a number of Supreme Court and Federal Circuit cases and I selected

three, in addition to Weinstein v. Bradford (Southern Pacific Terminal Co. v. ICC, 219

U.S. 498, 31 S.Ct. 279, 55 L.Ed. 310 (1911)), to help us understand the exception. In

Kingdomware Technologies v. United States, 136 S.Ct. 1969 (2016) a veteran-owned

small business brought a 2012 bid protest claim seeking declaratory and injunctive relief

against Department of Veterans Affairs (VA) alleging that the Department failed to

comply with the statutory Rule of Two generally requiring the Department to set aside

contracts for veteran-owned small businesses. By 2014 the contracts in question had

been fully completed and the cases were moot. After reciting the elements of the

mootness exception discussed above in Weinstein v. Bradford (Southern Pacific Terminal

Co.), the Supreme Court in Kingdomware held the exception applied:

22 This may be true, but every time a contractor must go through this audit, final decision,

appeal, dismissal fiasco it must incur litigation costs the government does not

reimburse. Settlement is even worse because the contractor is required to pay.

23

Here, no live controversy in the ordinary sense remains

because no court is now capable of granting the relief

petitioner seeks. When Kingdomware filed this suit four

years ago, it sought a permanent injunction and declaratory

relief with respect to a particular procurement. The services

at issue in that procurement were completed in May 2013.

And the two earlier procurements, which Kingdomware had

also protested, were complete in September 2012. See decl.

of Corydon Ford Heard III ¶¶ 6–8. As a result, no court can

enjoin further performance of those services or solicit new

bids for the performance of those services. And declaratory

relief would have no effect here with respect to the present

procurements because the services have already been

rendered.

....

That exception applies to these short-term contracts. First,

the procurements were fully performed in less than two years

after they were awarded. We have previously held that a

period of two years is too short to complete judicial review of

the lawfulness of the procurement. See Southern Pacific

Terminal Co. v. ICC, 219 U.S. 498, 514–516, 31 S.Ct. 279,

55 L.Ed. 310 (1911). Second, it is reasonable to expect that

the Department will refuse to apply the Rule of Two in a

future procurement for the kind of services provided by

Kingdomware. If Kingdomware's interpretation of § 8127(d)

is correct, then the Department must use restricted

competition rather than procure on the open market. And

Kingdomware, which has been awarded many previous

contracts, has shown a reasonable likelihood that it would be

awarded a future contract if its interpretation of § 8127(d)

prevails. See decl. of Corydon Ford Heard III ¶¶ 11–15

(explaining that the company continues to bid on similar

contracts). Thus, we have jurisdiction because the same legal

issue in this case is likely to recur in future controversies

between the same parties in circumstances where the period

of contract performance is too short to allow full judicial

review before performance is complete. Our interpretation of

§ 8127(d)'s requirements in this case will govern the

Department's future contracting

(Id. at 1975-76) In Humane Society v. Clinton, 236 F.3d 1320 (Fed. Cir.),

wildlife and animal protection organizations sued the President and

24

Secretary of Commerce seeking to compel them to renew action against

Italy under High Seas Driftnet Fisheries Enforcement Act. At the time of

the Federal Circuit’s decision Italy had stopped widespread driftnet fishing

and the case was technically moot. However, the Federal circuit held that

the exception to mootness applied because a claim is not moot if that action

is capable of repetition, yet evading review:

In a memorandum date-stamped April 28, 1997, concerning

“Procedural steps under the High Seas Driftnet Fisheries

Enforcement Act,” government attorneys recognized that the

Driftnet Act did not explicitly address the situation if Italy

was to continue or resume large-scale driftnet fishing after the

Secretary's certification that driftnet fishing had ceased. The

memorandum stated that it was possible to read the Act to

require a new identification of Italy under § 1826a(b)(1)(B)

and a second round of consultations under § 1826a(b)(2)

before the Secretary could prohibit the importation of fish

products from Italy. The memorandum also noted that such a

process would appear to be incompatible with the purpose of

the statute and could result in an annual cycle of agreements

that appear to be adequate on paper but prove to be

ineffectual in practice.

We can assume that, if a plaintiff was to challenge the

Secretary's certification that a nation had ceased driftnet

fishing and brought forth adequate evidence of persistent

proscribed driftnet fishing, the Secretary would likely identify

that nation again. Because of that re-identification, the

challenge to the Secretary's prior certification would almost

always be moot under the Government's theory. Thus, the

question of the propriety of the Secretary's certification would

escape judicial review. Even the Government's attorneys

recognized that an ineffectual cycle of repetitious events

could occur. We conclude that the purpose of the Act is

better effectuated by holding that the question, whether the

Secretary's certification that a nation has ceased driftnet

fishing is in accord with law, is not rendered moot by a later

re-listing or re-identification of that nation.

(Id. 1331-32) In Federal Election Commission v. Wisconsin Right to Life, Inc., 551 U.S.

449 (2007) a nonprofit ideological advocacy corporation sued Federal Election

Commission (FEC), seeking declaration that “electioneering communications” provisions

of Bipartisan Campaign Reform Act (BCRA) violated First Amendment. Supreme Court

ruled the dispute was not mooted by passing of the election cycle:

25

As the District Court concluded, however, these cases fit

comfortably within the established exception to mootness for

disputes capable of repetition, yet evading review. (Citations

omitted). The exception applies where “(1) the challenged

action is in its duration too short to be fully litigated prior to

cessation or expiration, and (2) there is a reasonable

expectation that the same complaining party will be subject to

the same action again.” (Citations omitted). Both

circumstances are present here.

As the District Court found, it would be “entirely

unreasonable ... to expect that [WRTL] could have obtained

complete judicial review of its claims in time for it to air its

ads” during the BCRA blackout periods. (Citation omitted)

The FEC contends that the 2–year window between elections

provides ample time for parties to litigate their rights before

each BCRA blackout period. But groups like WRTL cannot

predict what issues will be matters of public concern during a

future blackout period. In these cases, WRTL had no way of

knowing well in advance that it would want to run ads on

judicial filibusters during the BCRA blackout period. In any

event, despite BCRA's command that the cases be expedited

“to the greatest possible extent,” § 403(a)(4), 116 Stat. 113,

note following (Citation omitted), two BCRA blackout

periods have come and gone during the pendency of this

action. “[A] decision allowing the desired expenditures

would be an empty gesture unless it afforded appellants

sufficient opportunity prior to the election date to

communicate their views effectively.” (Citations omitted)

3 The second prong of the “capable of repetition” exception

requires a “ ‘reasonable expectation’ ” or a “ ‘demonstrated

probability’ ” that “the same controversy will recur involving

the same complaining party.” (Citation omitted) Our cases

find the same controversy sufficiently likely to recur when a

party has a reasonable expectation that it “will again be

subjected to the alleged illegality,” (citation omitted) or “will

be subject to the threat of prosecution” under the challenged

law (citations omited). The FEC argues that in order to prove

likely recurrence of the same controversy, WRTL must

establish that it will run ads in the future sharing all “the

characteristics that the district court deemed legally relevant.”

Brief for Appellant FEC 23.

26

The FEC asks for too much. We have recognized that the “

‘capable of repetition, yet evading review’ doctrine, in the

context of election cases, is appropriate when there are ‘as

applied’ challenges as well as in the more typical case

involving only facial attacks.” (Citation omitted) Requiring

repetition of every “legally relevant” characteristic of an as-

applied challenge—down to the last detail—would effectively

overrule this statement by making this exception unavailable

for virtually all as-applied challenges. History repeats itself,

but not at the level of specificity demanded by the FEC.

Here, WRTL credibly claimed that it planned on running “

‘materially similar’ ” future targeted broadcast ads

mentioning a candidate within the blackout period, (citation

omitted) and there is no reason to believe that the FEC will

“refrain from prosecuting violations” of BCRA, (citation

omitted). Under the circumstances, particularly where WRTL

sought another preliminary injunction based on an ad it

planned to run during the 2006 blackout period, (citation

omitted) we hold that there exists a reasonable expectation

that the same controversy involving the same party will recur.

We have jurisdiction to decide these cases.

(Id. at 462-64)

Each of these cases apply the elements needed to establish the “capable of

repetition, yet evading review” doctrine which are (1) the challenged action was in its

duration too short to be fully litigated prior to its cessation or expiration, and (2) there

was a reasonable expectation that the same complaining party would be subjected to the

same action again.” Weinstein v. Bradford, 96 S.Ct. 347, 348-349. I studied the Supreme

Court’s and Federal Circuit’s application of the exception to mootness in these four

situations. Southern Pacific Terminal (cited in Weinstein v. Bradford) is the first case in

which the Supreme Court applied the mootness exception because of “the short duration

of the Interstate Commerce Commission order challenged, it was virtually impossible to

litigate the validity of the order prior to its expiration.” In Kingdomware Technologies it

was the short terms of the contracts meaning they were complete before the courts could

resolve the case; in Humane Society it was the “Secretary's certification that a nation has

ceased driftnet fishing”; in Wisconsin Right to Life it was the short duration of BCRA

[Bipartisan Campaign Reform Act] blackout periods. I want to highlight a significant

difference between these cases and L3’s situation. In the cases cited above the “short

duration” element of the exception was satisfied by something outside the control of

government entity arguing that the case was moot and the exception did not apply. Just

the opposite in L3’s case. It was DCMA that withdrew the final decisions cutting short

the appeals. It was DCMA that set up the “capable of repetition, yet evading review”

situation. DCMA withdraws the COFDs to moot the appeals and then argues that the

exception does not apply. This is unfair and makes for an even more compelling reason

27

to apply the exception. As the Federal Circuit wrote in Humane Society, finding the case

moot would lead to an “ineffectual cycle of repetitious events. . . .” The same is true in

L3, dismissal of these appeals as moot perpetuates the “ineffectual cycle” already seen

between 2006 and 2018 of DCAA audits finding unallowable costs prompting DCMA

final decisions demanding repayment, L3 appealing to the ASBCA and ultimately

DCMA abandoning the DCAA audits leaving L3 without resolution of its defenses. I

conclude from the above that the first element of the mootness exception, “the challenged

action was in its duration too short to be fully litigated prior to its cessation or expiration”

is satisfied.

The record establishes that L3 has endured this cycle of audit, final decision,

appeal and dismissal for at least twelve years with no end in sight (SOF ¶¶ 12-13).

Therefore, the second element of the mootness exception “a reasonable expectation that

the same complaining party would be subjected to the same action again” is satisfied.

The Mootness Exception Applies in ASBCA Nos. 61811, 61813 and 61814

I would apply the mootness exception and this case would continue. L3 is entitled

to present its arguments to the Board. DCAA/DCMA are likewise entitled to defend the

audits. This does not mean that L3 will prevail, it just gives L3 a chance to make its case.

I move on to L3’s motion for summary judgment.

Legal Standard for Summary Judgment

Summary judgment is properly granted only where there is no genuine issue of

material fact and the movant is entitled to judgment as a matter of law. The moving party

bears the burden of establishing the absence of any genuine issue of material fact and all

significant doubt over factual issues must be resolved in favor of the party opposing

summary judgment. Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390

(Fed. Cir. 1987) (citations omitted). In the course of the Board's evaluation of a motion

for summary judgment, our role is not “‘to weigh the evidence and determine the truth of

the matter,’ but rather to ascertain whether material facts are disputed and whether there

exists any genuine issue for trial.” Holmes & Narver Constructors, Inc., ASBCA

Nos. 52429, 52551, 02-1 BCA ¶ 31,849 at 157,393 (quoting Anderson v. Liberty Lobby,

Inc., 477 U.S. 242, 249 (1986)). A material fact is one which may make a difference in

the outcome of the case. Liberty Lobby, 477 U.S. at 249. The opposing party must assert

facts sufficient to show a dispute as to a material fact of an element of the argument for

reformation or breach. New Iraq Ahd Co., ASBCA No. 59304, 15-1 BCA ¶ 35,849

at 175,291-92 (citing Mingus, 812 F.2d at 1390-91) (“To ward off summary judgment,

the non-moving party must do more than make mere allegations; it must assert facts

sufficient to show a dispute of material fact.”); see Lee's Ford Dock. Inc., ASBCA

No. 59041. 16-1 BCA ¶ 36.298 at 177,010.

28

L3’s Articulation of the Burden of Proof

L3 discusses burden of proof several times:

A decision sustaining these appeals is appropriate in

accordance with Board Rule 17 (or in the alternative, Board

Rule 7(c)) and binding precedent of the Board because the

Government has plainly indicated an intention not to continue

the defense of the appeals and has failed to meet its burden of

proving the costs disallowed by the COFDs are unallowable.

(App. opp’n at 3) L3 repeats this argument later in its opposition:

A decision sustaining these appeals is appropriate in

accordance with Board Rule 17, or in the alternative Board

Rule 7(c), and binding precedent of the Board because the

Government has plainly indicated an intention not to continue

the prosecution or defense of the appeals and has not met its

burden of proving the costs disallowed in the COFDs are

unallowable.

(Id. at 34) And:

The facts in these appeals are analogous to those in Centron.

The Government has essentially conceded that it cannot—or

at least has no intent of trying to—meet its burden of proving

the Government’s cost disallowance claims asserted in the

COFDs.

(Id. at 35) And:

To the extent the Board considers a default judgment

sustaining the appeals a “sanction” under Rule 16—rather

than the natural result of failing to defend the appeals or meet

the Government’s burden of proving the cost disallowance

claims asserted in the COFDs—it is one that is “necessary to

the just and expeditious conduct of the appeal” under Rule 16

and an entirely “appropriate action” under Rule 17.

(Id. at 36)

FAR 31.201-3, Allocates the Burden of Proof to L3

It is true that these are government claims and the government bears an initial

burden but that burden is not as claimed by L3. As I explain below the government’s

29

burden is to challenge specific costs claimed by the contractor. In their briefs, neither L3

nor DCMA consider FAR 31.201-3, Determining reasonableness and how it operates to

place the burden of proof on L3. Our interpretation is consistent with that of DCMA’s

COFDs (SOF ¶¶ 7-9).

FAR Part 31, Contract Cost Principles and Procedures, defines what costs are and

are not allowable providing the standards applied by DCAA in its audits (SOF ¶¶ 4-5)

and DCMA in its final decisions (SOF ¶¶ 7-9). As explained in Boeing North American,

Inc. v. Roche, 298 F.3d 1274 (Fed. Cir. 2002), this Board is also obligated to follow

FAR Part 31:

Although a cost may be allocable to a contract, the cost is not

necessarily allowable. We have agreed with the general

proposition that “costs may be assignable and allocable under

CAS, but not allowable under [FAR].” United States v.

Boeing Co., 802 F.2d 1390, 1394 (Fed.Cir.1986). [Footnote

omitted] And the FAR makes clear that “[w]hile the total cost

of a contract includes all costs properly allocable to the

contract, the allowable costs to the Government are limited to

those allocable costs which are allowable pursuant to [FAR]

Part 31 and applicable agency supplements.” FAR § 31.201–

1(b) (2001).

(Id. at 1280)

FAR 31.201-2, Determining allowability lists five elements required to determine

if a cost is allowable (SOF ¶ 1). One of the five elements is reasonableness defined by

FAR 31.201-3 Determining reasonableness, which includes the following language in

FAR 31.201-3(a):

No presumption of reasonableness shall be attached to the

incurrence of costs by a contractor. If an initial review of the

facts results in a challenge of a specific cost by the

contracting officer or the contracting officer’s representative,

the burden of proof shall be upon the contractor to establish

that such cost is reasonable.

(SOF ¶ 1) (Emphasis added)

When interpreting a procurement regulation, “we seek an interpretation consistent

with the plain terms provided; it is not our prerogative to insert additional words or

phrases to alter an otherwise plain and clear meaning.” Raytheon Company, ASBCA

No. 57576 et al., 15-1 BCA ¶36,043 at 176,050. The language to be interpreted, quoted

and italicized above, is, “If an initial review of the facts results in a challenge of a

specific cost by the contracting officer or the contracting officer's representative, the

30

burden of proof shall be upon the contractor to establish that such cost is reasonable.”

This language is unambiguous and has only one reasonable interpretation. It requires two

actions by the government: (1) it must perform an “initial review of the facts,” and (2)

that review results in a “challenge” to “specific cost[s]” by a contracting officer or

contracting officer’s representative. If the government meets this initial burden, “the

burden of proof shall be upon the contractor to establish that such cost is reasonable.”

DCMA employed this interpretation in its COFDs (SOF ¶¶ 7-9).

We interpreted FAR 31.201-3(a) in Kellogg Brown & Root, ASBCA, No. 58081,

17-1 BCA ¶ 36,595, where we recognized that contesting reasonableness “is significant

because it shifts the burden of proof” to the contractor (id. at 178,240). We went on to

hold that a general (blanket) assertion that all costs are unreasonable is insufficient to

require the contractor to do more to prove reasonableness (id. at 178,250). I do not have

such a blanket objection before me in these appeals. We have DCAA audits that

challenge specific costs identified as unallowable and DCMA COFDs demanding

repayment of those unallowable costs (SOF ¶¶ 7-9).

In North American Landscaping, Construction and Dredge, Co. (NALCO)

ASBCA No. 60235, 18-1 BCA ¶ 37116 a separate concurring decision included the

following footnote No. 29:

The Federal Acquisition Regulation (FAR) has, on other

occasions, permitted a CO's suspicions to trigger a

requirement that a contractor provide more substantiation for

certain costs. For example, in FAR 31.201-3, all that is

necessary to impose upon a contractor the burden of proof of

demonstrating a particular cost to be reasonable is the CO's

“challenge” of that cost after “an initial review of the facts.”

FAR 31.201-3(a). Like the DFARS clause we have discussed

above, this FAR provision does not go into detail about what

is sufficient for the CO to bring such a challenge.

NALCO, 18-1 BCA ¶ 37116 at 180,659 n.29 (emphasis added). This footnote, although

dicta, presents the interpretation of FAR 31.201-3(a) I followed in this case.

In Parsons Evergreene, LLC, ASBCA No. 58634, 18-1 BCA ¶ 37137, the trial

judge employed the same interpretation of FAR 31.201-3(a) I discussed above that was

applied in Kellogg Brown & Root, 17-1 BCA ¶ 36,595. Parsons, 18-1 BCA ¶ 37137

at 180,790. A concurring opinion took issue with the trial judge’s conclusion that a

blanket challenge to costs that failed to challenge specific costs was insufficient to

require the contractor to do more to prove reasonableness. The concurring opinion

concluded, “There was no requirement nor need to follow FAR 31.201 to evaluate this

claim and thus, we concur in the result but not the analysis” Parsons, 18-1 BCA ¶ 37137

at 180,821. Again, I am not faced with such a blanket challenge in this case.

31

In BAE Systems San Francisco Ship Repair, ASBCA No. 58809, 14-1 BCA ¶

35642, citing the Federal Circuit, we held that where the government has challenged

specific costs, the contractor has the burden of proof to prove the costs it claims are

reasonable:

Interpreting FAR 31.201 -3(a), the Federal Circuit recently

affirmed that the contractor has the burden of proof, unaided

by a presumption of reasonableness, to establish that the costs

it incurred were reasonable. Kellogg Brown & Root Services,

Inc. v. United States, 728 F.3d 1348, 1363 (Fed. Cir. 2013)

(“It seems that KBR seeks a presumption that it is entitled to

reimbursement simply because it incurred facilities costs. It

is not.”). This Board has long so held. See Northrop

Worldwide Aircraft Services, Inc., ASBCA Nos. 45216,

45877, 98-1 BCA ¶ 29,654 at 146,934 (citing Northrop

Worldwide Aircraft Services, Inc., ASBCA No. 47442, 97-1

BCA ¶ 28,885).

(Id. at 174,534)

L3’s repeated contention that the government has the burden to prove the costs

challenged by DCAA and DCMA are unallowable is simply wrong. DCAA’s audits and

DCMA’s COFDs satisfy the government’s initial burden to conduct an initial review and

contracting officer challenge of specific costs. Accordingly, pursuant to FAR 31.201-3(a),

“the burden of proof shall be upon the contractor [L3] to establish that such cost is

reasonable” (SOF ¶ 1).

Disputed Material Facts Exist

Thus far I have spent all of my time on the mootness exception and interpreting

FAR 31.201-3(a) as it relates to the burden of proof. Such interpretation is a question of

law. States Roofing Corp. v. Winter, 587 F.3d 1364 at 1368 (Fed. Cir. 2009). Questions

of law are susceptible of resolution by summary judgment. Dixie Construction Company,

Inc., ASBCA No. 56880, 10-1 BCA ¶ 34,422 at 169,917. Although I resolved the

interpretation / burden of proof questions of law issues, I cannot resolve L3’s motion.

Placing the burden of proof of allowability on L3 just clears the way for the parties to

litigate the underlying factual matters in view of the proper allocation of burden of proof.

DCAA and DCMA contend that the audit challenged costs are unallowable. L3 contends

that the statistical analysis used in the DCAA audits is flawed 23 and the audit challenged

costs are allowable. Whether costs are allowable is a question of fact. Martin Marietta

23 I note that DCMA’s expert, Mr. Arab, identified an error in DCAA’s statistical analysis

(sample size) that DCAA agreed with and implemented a change (SOF ¶¶ 16-18).

I do not know if that cured the problem complained of by L3 or not, but L3 is

entitled to proceed.

32

Corp., ASBCA No. 15313, 71-1 BCA ¶ 8644 (Disputes as to whether certain kinds of

incurred costs (e.g. interest, donations, independent R&D, etc.) are allowable under the

contract are disputes concerning a question of fact arising under the contract provisions . .

. .). Accordingly, I have disputed material facts that cannot be resolved by summary

judgment.

L3 is not Entitled to Summary Judgment that its Challenged Costs are Allowable

Because the question of allowability of discrete costs involves disputed material

facts, I would deny L3’s motion and allow the litigation to proceed.

CONCLUSION

Based on the above, I would deny DCMA’s motion to dismiss for mootness and

L3’s motion asking the Board to decide that its challenged costs are allowable. I would

allow the appeals to proceed.

Dated: March 1, 2021

CRAIG S. CLARKE

Administrative Judge

Armed Services Board

of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA Nos. 61811, 61813, 61814,

Appeals of L3 Technologies, Inc., rendered in conformance with the Board’s Charter.

Dated: March 2, 2021

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

33

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.