Opinion

Johnson Lasky Kindelin Architects, Inc v. United States

Court
United States Court of Federal Claims
Filed
Jan 29, 2021
Status
Published
On the bench
Matthew H. Solomson
Cited by
0 cases
Authority
More cited than 14.8%

The opinion

In the United States Court of Federal Claims

No. 19-1520C

(Filed: January 29, 2021)

)

JOHNSON LASKY KINDELIN )

ARCHITECTS, INC., for the benefit of )

IMEG CORP., f/k/a KJWW )

ENGINEERING )

)

Plaintiff, )

)

)

v.

)

)

THE UNITED STATES,

)

)

Defendant. )

OPINION AND ORDER

The Court once again must decide whether it has jurisdiction – pursuant to the

Tucker Act, 28 U.S.C. § 1491(a), and the Contract Disputes Act (“CDA”), 41 U.S.C.

§§ 7101–7109 – to decide a case predicated upon a government claim contained in a

contracting officer’s final decision finding that two, unrelated contractors are jointly

liable for the same injury and sum certain arising from alleged breaches of their

respective, independent contracts. For the reasons discussed below, and based upon

the Court’s previous decision in Johnson Lasky Kindelin Architects, Inc. v. United States

(“JLK I”), No. 19-1419C, -- Fed. Cl. --, 2020 WL 7649972 (Dec. 23, 2020), the Court

dismisses this case for lack of jurisdiction.

I. Factual Background

Plaintiff Johnson Lasky Kindelin Architects, Inc. (“JLK”) filed two separate

complaints against Defendant, the United States of America, acting by and through the

General Services Administration (“GSA”). Both cases involve the same underlying

contract. This Court dismissed the first matter in JLK I. This decision addresses JLK’s

second case against the government.

In 2010, GSA retained JLK to provide professional design services as the

architect-engineer supporting the relocation of existing National Labor Relations Board

(“NLRB”) office space. JLK I, 2020 WL 7649972, at *1 (Dec. 23, 2020). GSA separately

contracted with Master Design Build, LLC (“MDB”) to provide the necessary

construction services for the relocation of the NLRB office space. Id.

In JLK I, the claim at issue involved a supplemental air conditioning unit, which

JLK designed for the NLRB space and MDB installed. Id. Ultimately, a condenser

fluid pipe in the newly installed cooling system malfunctioned and caused extensive

damage to parts of the NLRB space, as well as portions of the United States

Bankruptcy Court on the sixth and seventh floors of the building in which the NLRB

space was located. Id. at *2. GSA retained Bailey Edward, an independent architecture

and engineer consulting firm, to investigate the cause of the condenser fluid piping

system failure. Id. Following that investigation, Bailey Edward issued a report, in

which the firm concluded that “that the leak resulted due to the confluence of several

factors,” including issues with JLK’s design and MDB’s installation failures. Id. Bailey

Edward, however, “determined that it could not assign fault to JLK to the exclusion of

MDB (or the government) . . . .” Id.

After reviewing Bailey Edward’s report, the cognizant contracting officer issued

a single contracting officer’s final decision (“COFD”) to both JLK and MDB for

$1,938,866.86, claiming that both companies were jointly and severally liable to GSA

for that amount. Id. at *3. While the COFD acknowledged that the design and

construction services were provided separately by JLK and MDB under different

contracts, the contracting officer nevertheless concluded that JLK and MDB were

jointly and severally liable for the resulting damages and, accordingly, instructed them

to collectively reimburse GSA. Id. In essence, the contracting officer issued a COFD

finding two, unrelated contractors – JLK and MDB – jointly and severally liable for the

same sum certain arising from independent breaches of their respective contracts with

GSA. Id. at *1. It is this COFD upon which JLK’s first claim and complaint were

predicated and that this Court ultimately dismissed in JLK I.

The above-captioned case raises a similar issue. As part of JLK’s prime contract

with GSA, JLK hired a subcontractor, IMEG Corp. (“IMEG”), to provide design services

for the installation of a fire alarm system. ECF No. 1 (“Compl.”) ¶ 9. After GSA

determined that certain conduit connections for the fire alarm system were not

furnished and installed per project specifications, MDB charged GSA $48,795.54 to

complete the additional work. Id. at ¶¶ 15, 16. On October 2, 2018, the same

contracting officer who had issued the COFD in JLK I issued another COFD, this time

finding that JLK and MDB were jointly liable for the $48,795.54 MDB charged to GSA

for the conduit work.1 Id. at ¶¶ 17, 18. The COFD at issue here uses identical language

1JLK, as a prime contractor, is responsible for the actions of its subcontractors. See Todd Const.,

L.P. v. United States, 656 F.3d 1306, 1316 (Fed. Cir. 2011) (“[A] contractor is responsible for the

-2-

as the COFD in JLK I, with the agency claiming a sum certain from the same parties and

under the same contracts at issue in JLK I, once again invoking a tort theory of joint

liability.2

II. Procedural History

On October 1, 2019, JLK, for the benefit of IMEG, filed suit in this Court, alleging

that the COFD for $48,795.54 was unreasonable and erroneous, or in the alternative,

incomplete. Compl. at 7. JLK also filed a notice of directly related case, informing the

Court that the instant case involved the same contracts as those at issue in JLK I, which

had been filed several weeks prior. ECF No. 2. On January 9, 2020, GSA filed an

answer and counterclaim, requesting that the Court enter judgment in GSA’s favor in

the amount of $48,795.54 and dismiss JLK’s claim. ECF No. 14. JLK filed an answer to

GSA’s counterclaim on January 30, 2020. ECF No. 15. The case was reassigned to the

undersigned Judge on February 5, 2020. ECF Nos. 16, 17.

On March 19, 2020, the parties filed a joint preliminary status report requesting

that further proceedings be stayed “in light of enforcement proceedings that the

General Service Administration (GSA) will bring against Master Design Build, LLC

(MDB) for the exact same debt – $48,795.54 – that is at issue in this litigation.” See ECF

unexcused performance failures of its subcontractors.”). This claim, brought by JLK on behalf

of IMEG, is a sponsored (or “pass-through”) claim. See Montano Elec. Contractor v. United States,

114 Fed. Cl. 675, 680 (2014) (“Even absent privity of contract, a subcontractor's claims may be

brought against the government if the prime contractor brings the suit on behalf of the

subcontractor—as a pass-through or sponsored claim.”), aff'd, 610 F. App'x 987 (Fed. Cir. 2015);

see also Compl. ¶ 10 (“In August of 2019 . . . JLK transferred its appellate rights against the GSA

to IMEG, effectively, sponsoring any de facto claims which could be incurred by IMEG in

relating to this matter.”).

2 In particular, the contracting officer determined as follows:

JLK & MDB [a]re jointly liable because: 1) MDB/their sub did not

provide the submittal initially that clarified what

conduit/connection components were for the fire alarm system and

what were for the remainder of the electrical systems installation;

2) JLK/their MEP sub did not clarify this further in their review of

the submittals, to assure that the installation of the fire alarm

system followed the specifications.

Compl. at ¶ 18. Moreover, according to the second COFD, because “both JLK and MDB have

both provided design and construction services, respectively, on numerous projects for GSA,

they both were totally familiar with the all of the GSA requirements of a fire alarm system

installation; simply put, this oversight on both of their parts should not have occurred in the

first place.” Id.

-3-

No. 18 at 2. Those planned collection proceedings are based on the fact that “the final

decision finding MDB liable for $48,796.54 is conclusive and binding against MDB,”

because MDB “failed to either appeal [the COFD] to the Civilian Board of Contract

Appeals (CBCA) within 90 days of the decision or appeal the final decision to this Court

within a year of that decision.” Id. The government acknowledged that “the collection

of MDB’s debt by GSA would moot this litigation,” and thus requested that this case be

stayed while it “diligently pursue[d] the collection of that debt against MDB.” Id.

On December 23, 2020, this Court entered an Order and Opinion in JLK I,

dismissing that case, as noted above, for lack of subject matter jurisdiction. JLK I, 2020

WL 7649972, at *1 (Dec. 23, 2020). In that opinion, the Court held that the COFD at issue

was invalid because it invoked joint and several liability, a tort theory of damages, to

claim the same sum certain from both JLK and MDB for the alleged breach of their

respective, independent contracts with GSA. Id. at *11 (“This Court lacks jurisdiction to

decide this case because both the government’s Counterclaim and the predicate COFD

constitute a ‘damages [claim] . . . sounding in tort.’” (quoting 28 U.S.C. § 1491(a)(1))).

Additionally, the Court noted that “the government’s approach . . . provides this Court

– and more importantly, JLK – with no assurances, no procedural method, and no

substantive rule to ensure that the government will not seek a double recovery via two

separate judgments in two separate fora.” Id. at *22.

In light of the similarities between the COFD at issue in JLK I and this case, this

Court ordered the government to show cause as to why this matter should not be

governed by the result in JLK I, and, thus, dismissed for lack of jurisdiction. ECF No.

19. On January 15, 2021, the government responded to the Court’s order, conceding

that, based on the Court’s reasoning and subsequent holding in JLK I, the government

was not aware of any basis on which to distinguish the instant case. ECF No. 20 at 1–2.

The government acknowledged that

[t]he COFD from which plaintiff appeals in this case – like the

COFD in JLK I – found that JLK and MDB are jointly and

severally liable for the loss at issue. Because, according to

JLK I, joint and several liability is a tort concept, this Court

would not possess jurisdiction to entertain this litigation . . . .

Id. at 2. Thus, the government ultimately agreed that JLK I requires the dismissal of this

case for lack of subject matter jurisdiction. Id.

-4-

III. The COFD At Issue In This Case Suffers From The Same Defects As The

COFD In JLK I And Thus This Court Lacks Jurisdiction

Pursuant to Rule 12(h)(3) of the Court of Federal Claims (“RCFC”), “[i]f the court

determines at any time that it lacks subject-matter jurisdiction, the court must dismiss

the action.” A court’s “[s]ubject-matter jurisdiction may be challenged at any time by

the parties, or by the court sua sponte.” Folden v. United States, 379 F.3d 1344, 1354 (Fed.

Cir. 2004) (citations omitted). As acknowledged by the government in its response to

this Court’s order to show cause, the predicate COFDs in both JLK I and the instant case

use nearly identical language, which the Court previously held invokes a tort theory of

recovery, rendering the COFD invalid and the case outside of this court’s jurisdiction.

ECF No. 20 at 2. The government thus further agreed that the rationale in JLK I requires

the dismissal of this case for lack of jurisdiction. 3 Id. The Court concurs with the

government’s assessment.

We write further only to emphasize that the hypothetical situation with which

we were concerned in JLK I has actually materialized in this case. Because MDB failed

to appeal the COFD at issue here, MDB is liable to the government for the full amount

of $48,795.54 at issue in this case. In essence, then, the government already has held

another contractor liable for the same sum certain that it seeks to recover from JLK in

this case. In JLK I, we expressed that precise concern – i.e., that there is no mechanism

to ensure that the government would not “seek a double recovery via two separate

judgments in two separate fora.” JLK I, 2020 WL 7649972, at *22 (Dec. 23, 2020). Here,

the government seeks to do just that: despite the fact that it already has declared the

judgment against MDB to be “conclusive and binding,” the government is still pursuing

the identical sum certain for the same injury, but under a different contact and from a

different contractor in the matter before us. The Court in JLK I determined that no

contract language or theory of damages permitted the government to take such an

approach.

The fact that the Court has granted the government’s request to stay this case

pending any collection action against MDB does not cure the problem. In that regard,

the government itself repeatedly has admitted that it cannot collect the same sum

certain from both JLK and MDB. Specifically, in the government’s request to stay this

case, the government acknowledged that “the collection of MDB’s debt by GSA would

moot this litigation” because it seeks to recover from MDB “the exact same debt –

$48,795.54 – that is at issue in this litigation.” See ECF No. 18 at 2 (emphasis added).

The government conceded the identical point in JLK I, recognizing that should JLK

tender the entire amount due to GSA pursuant to the COFD at issue in that matter,

3 To be clear, the government does not concede that JLK I was correctly decided.

-5-

MDB’s pending CBCA appeal of that first COFD would be moot “because there would

be nothing left for the CBCA to adjudicate.” JLK I, 2020 WL 7649972, at *18 n.14 (Dec.

23, 2020). The government, however, has not directed the Court to any authority

demonstrating that our jurisdiction to decide a contract case may turn on the

collectability of a judgment against another company on another contract. Indeed, as

this Court noted in JLK I, the possibility of that situation – which, again, apparently has

materialized in this case – provides further evidence that the COFD’s claim of joint

liability is grounded in a tort theory of liability, and, thus, is not within this Court’s

CDA jurisdiction. Id. at *23. (“In the Court's view, the fact that neither the Court nor

the CBCA can preclude the government from a double recovery at a minimum suggests

that the government's approach to this matter is erroneous.”).

For the above reasons, as well as those explained in JLK I, the COFD at issue in

this case is invalid, as it improperly relies upon a tort theory of recovery, and thus this

Court lacks subject-matter jurisdiction to decide this case. Accordingly, both the

Plaintiff’s Complaint and the government’s Counterclaim are DISMISSED, without

prejudice, pursuant to RCFC 12(h)(3).

IT IS SO ORDERED.

s/Matthew H. Solomson

Matthew H. Solomson

Judge

-6-

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.