Opinion

Hcic Enterprises, LLC v. United States

Court
United States Court of Federal Claims
Filed
Jul 9, 2020
Status
Published
On the bench
Elaine D. Kaplan
Cited by
0 cases
Authority
More cited than 12.1%

emphasizing also that “the grant or denial of an opportunity to amend is within the discretion of the [trial court]”

How later courts described this case

  • emphasizing also that “the grant or denial of an opportunity to amend is within the discretion of the [trial court]”

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

No. 18-1943C

(Filed: July 9, 2020)

)

HCIC ENTERPRISES, LLC, )

d/b/a HCI GENERAL CONTRACTORS, )

) Keywords: Motion to Amend; Futility;

Plaintiff, ) Bad Faith; Contracting Officer Final

) Decision

v. )

)

THE UNITED STATES, )

)

Defendant. )

)

)

Frank V. Reilly, Fort Lauderdale, FL, for Plaintiff.

Robert C. Bigler, Trial Attorney, Commercial Litigation, Civil Division, U.S. Department of

Justice, Washington, DC, for Defendant, with whom were Steven J. Gillingham, Assistant

Director, Robert E. Kirschman, Jr., Director, Joseph H. Hunt, Assistant Attorney General.

OPINION AND ORDER

KAPLAN, Judge.

Plaintiff HCIC Enterprises, LLC (“HCIC”) has filed a second motion to amend its

complaint. For the reasons set forth below, the motion is denied.

BACKGROUND

I. Relevant Facts 1

The Court’s prior opinions granting the government’s motion for partial summary

judgment and denying HCIC’s first motion to amend its complaint contain a comprehensive

discussion of the background of the present motion. See HCIC Enters., Inc. v. United States, 147

Fed. Cl. 118, 121–23 (2020); ECF No. 32 (order denying motion to amend complaint). To briefly

recapitulate, on April 20, 2016, the Federal Bureau of Prisons (“FBOP”) awarded HCIC a

contract worth $2,735,000 to replace roofs on some of the buildings at the Federal Correctional

Institute (“FCI”) in Estill, South Carolina. Def.’s Cross Mot. for Partial Summ. J. & Resp. to

1

The facts set forth in this section are drawn from the parties’ pleadings and documents

submitted in connection with the earlier motions filed in this case.

Pl.’s Mot. for Summ. J. App. (“Def.’s App.”) at 70, ECF No. 14-1 (February 14, 2019

Determination and Findings Authorizing Contract Termination for Default). Under the contract,

the repairs were to be completed within one year. The contracting officer (“CO”) issued a notice

to proceed on June 13, 2016, setting a completion date of June 13, 2017. Id.

The performance period was subsequently extended through four bi-lateral contract

modifications—first by fifty-five days, then twenty-five days, then 180 days, and finally by 193

days to September 6, 2018. See Initial Compl. Ex. C, at 10–11, ECF No. 1. 2 Despite the

extensions, HCIC failed to complete the work by September 5. Def.’s App. at 74. Instead, on

September 6, 2018, HCIC filed a claim for an equitable adjustment, requesting another extension

of the performance period, this time for 419 days, to October 30, 2019. See Initial Compl. Ex. C,

at 10–12. In its claim, HCIC stated that between December 20, 2017 and September 5, 2018 (the

period covered by the most recent modification of the contract) the project had incurred another

259 calendar days of delays which HCIC attributed to “the inability of the government to provide

adequate staff to escort the necessary HCI[C] crews required to complete the project in the time

allotted in the contract.” Id. at 11. HCIC requested $480,821.74 as compensation for additional

costs incurred. Id. at 12. It also requested an additional award of $777,854.48 to cover its costs

and profit for the additional 419 days it had requested to complete the project. Id.

The CO denied HCIC’s request for an equitable adjustment in a November 14, 2018

email. Id. Ex. D, at 19–20. He noted that the prior extensions “were executed as supplemental

agreements and agreed to bi-laterally.” Id. at 19. Those modifications, he explained, “[were]

considered complete equitable adjustments for each of the associated time periods.” Id. The CO

acknowledged that HCIC was entitled to compensation for twelve days of delay during the most

recent modification period “for time that FCI Estill could not accommodate the contractor” and

that those days “w[ould] not be calculated in the liquidated damages that are currently accruing.”

Id. Finally, the CO observed that HCIC was out of time to complete the project as of the date of

his letter. Id. He advised HCIC that it had not provided information “that compels the

Government to believe that additional adjustments are necessary or appropriate.” Id. at 19–20.

He therefore denied HCIC’s request for a fifth extension of the deadline for completion of the

project. Id. at 20.

On February 13, 2019, two months after HCIC filed the present action, it requested that

the contract be terminated for convenience. Pl.’s Mot. for Leave to File 2d Am. Compl. Ex. B,

ECF No. 29-3 (email exchange from HCIC president to CO seeking contract termination).

Instead, the CO issued a “Determination and Findings Authorizing Contract Termination for

Default” on February 14, 2019. Def.’s App. at 70. FBOP’s Administering Contracting Officer

concurred in the recommended default termination, id. at 78, and the CO issued a Notice of

Termination for Default on April 30, 2019, id. at 67–68.

2

Many of Plaintiff’s exhibits are contained in the same document as the initial complaint. The

page numbers cited for these exhibits reflect the pagination assigned by the court’s electronic

filing system. See Initial Compl., ECF No. 1.

2

II. Prior Proceedings

HCIC filed the present action on December 19, 2018. ECF No. 1. In its initial complaint,

HCIC alleged that FBOP “breached the written agreement between the parties by failing to allow

access to the site during normal working hours except during emergencies . . . [,] by failing to

provide access to all roofs designated in the Statement of Work . . . [, and] by improperly

denying HCI[C]’s claim” submitted to the CO. Initial Compl. ¶¶ 9–10, 12. HCIC further alleged

that the CO’s denial of its request for an equitable adjustment was arbitrary and capricious

“because there was no evidence in the administrative record to show that HCI[C] is or was the

sole and proximate cause of the delayed completion date for the project.” Id. ¶ 14. It demanded

an award of $480,821.74 “plus additional damages as will be shown to have been incurred after

the date the claim was filed.” Id. ¶ 19.

On September 9, 2019, and before expiration of the discovery period, HCIC filed what it

later clarified was a motion for summary judgment pursuant to Rule 56 of the Rules of the Court

of Federal Claims (“RCFC”). See HCIC Enters., 147 Fed. Cl. at 123 (clarifying that HCIC

sought a motion for summary judgment notwithstanding that its motion was stylized as a motion

for judgment on the pleadings). The government filed a cross-motion for partial summary

judgment on October 7, 2019 in which it sought a ruling that HCIC’s breach claim was based on

a misinterpretation of the relevant provisions of the contract. Id.

The Court denied HCIC’s motion for summary judgment. Id. at 125. It observed that its

denial was based on HCIC’s failure to identify what undisputed facts supported its claim, and its

inability to “explain how the application of the legal standards it recite[d] entitle[d] it to

judgment as a matter of law.” Id. at 124.

Next, the Court addressed the government’s motion for summary judgment regarding the

interpretation of the contractual provisions upon which HCIC relied. It concluded that the

contractual provisions that promised HCIC would be granted “access” to the worksite and to the

roofs of the buildings at FCI Estill must be read in light of other provisions in the contract which

conditioned such access on compliance with security requirements. Id. at 125. These included the

requirement that workers be escorted “at all times, when entering the institution” and the

prohibition against workers “mov[ing] to other parts of the institution without an escort.” Id.

(quoting Def.’s App. at 55, 56). Under the contract, FBOP only committed to provide two

security escorts for the project. Id. (citing Def.’s App. at 52). As the Court observed, “[t]he

requirement that workers always be escorted when on the premises, coupled with FBOP’s

limited obligation to make only two escorts available for the project . . . meant that the crews

could only work on one roof at a time, with one escort on the roof and one on the ground.” Id. It

therefore granted the government’s cross-motion for partial summary judgment as to that issue of

contract interpretation. Id.

As noted above, one day before the Court issued its opinion on the cross-motions for

summary judgment, HCIC filed an eleventh-hour motion to amend its complaint to delete its

breach of contract claim. It sought to substitute an allegation that the CO’s denial of HCIC’s

requests for equitable adjustment and assessment of liquidated damages violated the

Administrative Procedure Act. See id. at 125–26; Pl.’s Proposed 1st Am. Compl. ¶¶ 110–121,

ECF No. 27-1. Before the government could file a response to HCIC’s first motion to amend,

3

HCIC filed the new one that is currently before the Court. Accordingly, the Court denied the first

motion to amend as moot. See ECF No. 32.

III. HCIC’s Proposed Amended Complaint

HCIC’s second proposed amended complaint includes five numbered counts. In Count I,

HCIC challenges the CO’s November 14, 2018 denial of its request for a 419-day extension of

the contract deadline and payment of costs incurred on the grounds that the CO’s decision was

“factually and legally flawed.” 2d Proposed Am. Compl. ¶¶ 218–30, ECF No. 29-1. In Count II,

HCIC challenges what it claims was the CO’s assessment of liquidated damages against it in his

November 14, 2018 letter, again on the grounds that the decision was “factually and legally

flawed.” Id. ¶¶ 231–45. In Count III, HCIC similarly contends that the CO’s February 14, 2019 3

decision to terminate the contract for default was “factually and legally flawed” and also that it

“was made in bad faith.” Id. ¶¶ 246–77. In Count IV, HCIC alleges that the claim the

government has apparently asserted against its performance bond is “based on false facts,” id.,

and that “[a]t the time FBOP filed its false bond claim, FBOP knew full well that HCIC should

not be held responsible for th[e] delays and costs because FBOP did not ‘provide access to all

roofs designated in the Statement of Work’” as the contract required, id. ¶ 265 (quoting Def.’s

App. at 54). Finally, in Count V (which is mis-numbered as a second Count IV), HCIC asserts

that it is entitled to rescind its previous waiver of a potential claim for $182,570.05 based on

additional costs allegedly accrued from September 15, 2017 to December 20, 2017. Id. ¶¶ 278–

89; Initial Compl. Ex. C, at 11. HCIC seeks a total of $1,833,455.49 “plus additional costs that

may be incurred during the pendency of these proceedings against FBOP.” 2d Proposed Am.

Compl. at 37.

DISCUSSION

RCFC 15(a)(2) provides that where, as here, a party can no longer amend its pleading “as

a matter of course,” it may do so “only with the opposing party’s written consent or the court’s

leave.” Although the Court should “freely give leave” to a party seeking to amend its pleading

“when justice so requires,” that principle is not unlimited. Id. “[F]utility of amendment,” among

other things, may justify denial of a motion to amend. Foman v. Davis, 371 U.S. 178, 182 (1962)

(emphasizing also that “the grant or denial of an opportunity to amend is within the discretion of

the [trial court]”).

For the reasons set forth below, the Court concludes that none of the claims set forth in

HCIC’s second proposed amended complaint would survive a motion to dismiss. Because the

proposed amendments of the complaint would be futile, HCIC’s motion to amend is denied.

I. Count I

As noted, in Count I of its proposed amended complaint, HCIC alleges that the CO’s

decision not to extend the contract a fifth time (for 419 days) and not to pay HCIC for costs it

incurred as a result of the most recent delays was “factually and legally flawed,” “was not based

3

Count III states that the decision to terminate was made on February 14, 2018, but this appears

to be a typographical error. See Def.’s App. at 70–78.

4

on a proper analysis of the facts,” and was “legally deficient.” Id. ¶ 224. Count I appears to be

based on the mistaken premise that this Court will be conducting a review of the CO’s decision

to determine whether it is arbitrary and capricious or contrary to law. Under the Contract

Disputes Act (“CDA”), however, the Court does not review the CO’s decision; it conducts de

novo review of the claims that were put before the CO. See Assurance Co. v. United States, 813

F.2d 1202, 1206 (Fed. Cir. 1987); see also 41 U.S.C. § 7104(b) (providing for “de novo” action

in the Court of Federal Claims). Put another way, “once an action is brought following a

contracting officer’s decision, the parties start in court or before the board with a clean slate.”

Wilner v. United States, 24 F.3d 1397, 1402 (Fed. Cir. 1994).

Further, Count I of the proposed amended complaint does not contain sufficient factual

allegations to support HCIC’s claim that FBOP breached the contract by not extending the

performance period a fifth time. As it did when it filed its claim with the CO, HCIC alleges its

performance was delayed because of government action, i.e., FBOP’s failure to supply HCIC

with more than two security escorts, which—in light of security requirements—prevented

HCIC’s crews from working on more than one roof at a time. See, e.g., 2d Proposed Am. Compl.

¶¶ 56, 58 (“FBOP will not allow HCIC to start work on The General Housing Unit # 2 Building

for security reasons . . . because FBOP will only provide 2 security escorts at a time.”); id. ¶¶ 39,

41 (“FBOP did not provide additional escorts as HCI[C] had requested . . . [and] did not allow

HCIC to work on more than one building at a time.”); id. ¶¶ 87, 89 (“FBOP will not allow HCIC

to start work on The General Housing Unit # 3 Building for security reasons . . . because FBOP

will only provide 2 security escorts at a time.”); id. ¶¶ 119, 121 (making identical allegations

relating to the general housing building #4); id. ¶ 152 (same with regard to the camp core

building); id. ¶¶ 181, 183 (same with regard to the outside warehouse garage and powerhouse

storage building). But this Court has already ruled that FBOP was within its rights under the

contract to supply only two escorts to HCIC, and to enforce security requirements that limited

HCIC’s crews to working on only one roof at a time.

HCIC acknowledges in its reply brief that “the proposed amended complaint . . . [is]

based upon the same operative facts as the original claim.” HCIC Reply to Def.’s Objs. to Pl.’s

2d Mot. for Leave to File[] Its Proposed Am. Compl. (“HCIC’s Reply”) at 4, ECF No. 34. It also

recognizes that the Court determined in its earlier decision that, “[a]s a matter of law . . . FBOP

was within its contractual rights to delay the project under the circumstances of this case.” Id. at

3. Nonetheless, HCIC asserts, its proposed amended complaint alleges “an alternative theory of

recovery,” i.e., “that FBOP was not within its contractual rights to deny the claim.” Id. at 4. But

HCIC does not explain the basis for this assertion. And to the extent that its “alternative theory”

concerns the merits of the CO’s reasoning when he denied the claim, its allegations fail to state a

claim because the Court’s review, as noted above, is de novo. Id. The Court concludes, therefore,

that Count I of HCIC’s proposed amended complaint fails to state a plausible claim for relief,

would not withstand a motion to dismiss, and is therefore futile. See Ashcroft v. Iqbal, 556 U.S.

662, 679 (2009) (citing Bell Atl. Corp. v. Twombly, 550 U.S. 544, 556 (2007)) (“[O]nly a

complaint that states a plausible claim for relief survives a motion to dismiss.”); Meyer Grp.,

Ltd. v. United States, 115 Fed. Cl. 645, 650 (2014) (citing Shoshone Indian Tribe v. United

States, 71 Fed. Cl. 172, 176 (2006)) (“An amendment is futile where it ‘would not withstand a

motion to dismiss.’”).

5

II. Count II

In Count II, HCIC seeks to amend its complaint to include a challenge to the

government’s alleged assessment of liquidated damages in the amount of $421,768. 2d Proposed

Am. Compl. ¶¶ 233, 245. This claim is not ripe, however, because the government has not

assessed liquidated damages against HCIC. The CO merely stated in denying HCIC’s claim that

such damages continued to accrue. See Initial Compl. Ex. D, at 19 (stating only that “liquidated

damages [] are currently accruing”). He did not make a demand for payment. Since there is

nothing for the Court to review at this time regarding liquidated damages, amendment of the

complaint to include Count II would be futile.

III. Counts III and IV

In Count III, HCIC alleges that FBOP’s decision to terminate the contract for default was

made in bad faith. 2d Proposed Am. Compl. at 31. Relatedly, in Count IV, HCIC alleges that the

government used “false facts” to support its claim against HCIC’s performance bond because

FBOP knew that it had not provided access to all roofs designated in the Statement of Work as

the contract required. Id.

HCIC’s proposed amended complaint does not include sufficient facts to support its

claim that the government terminated the contract for default in bad faith. The Federal Circuit

and its predecessor court, the Court of Claims, “have long upheld the principle that government

officials are presumed to discharge their duties in good faith.” Road & Highway Builders, LLC

v. United States, 702 F.3d 1365, 1368 (Fed. Cir. 2012) (citing Am–Pro Protective Agency v.

United States, 281 F.3d 1234, 1239 (Fed. Cir. 2002)). And “it is ‘well-established . . . that a high

burden must be carried to overcome this presumption,’ amounting to clear and convincing

evidence to the contrary.” Id. (quoting Am-Pro Protective Agency, 281 F.3d at 1239–40).

“Moreover, a challenger seeking to prove that a government official acted in bad faith in the

discharge of his or her duties must show a ‘specific intent to injure the plaintiff’ by clear and

convincing evidence.” Id. (quoting Am–Pro Protective Agency, 281 F.3d at 1240).

HCIC’s allegations do not approach these thresholds. It alleges that “FBOP terminated

the contract . . . because the contracting officer intended to file his false claim on HCIC’s

performance bond . . . to force HCIC and/or HCIC’s surety to pay costs and liquidated damages.”

2d Proposed Am. Compl. ¶¶ 258–59. But there is no factual predicate for this claim which would

permit the Court to find—by clear and convincing evidence no less—that the presumption of

good faith has been rebutted. In fact, HCIC’s underlying theory that the agency terminated the

contract so that it could file a claim against the performance bond using “false facts” is

inherently implausible, given the fact that FBOP repeatedly agreed to extend the contractual

deadline. Moreover, the assertion that FBOP is relying upon “false facts” in making a claim on

the performance bond seems to be grounded in its contention—which the Court has rejected—

that FBOP was contractually obligated to provide it with more than two security escorts.

To the extent that HCIC is pressing a separate claim in Count IV regarding the merits of

FBOP’s claim on its performance bond, it lacks standing to do so. The performance bond is

based on a contract between the government and a third party. Therefore, amendment of the

complaint to add Counts III and IV would be futile.

6

IV. Count V

In the final count of the proposed amended complaint, HCIC claims it is entitled to

rescind a previous waiver of damages in the amount of $182,570.05 covering delays and costs

during the period from September 15, 2017 through December 20, 2017. 2d Proposed Am.

Compl. at 35; Initial Compl. Ex. C, at 11. The Court lacks jurisdiction over this claim because it

was never presented to the CO.

Under the CDA, the Court of Federal Claims has jurisdiction over actions filed within

twelve months of a contracting officer’s decision on a claim. 41 U.S.C. § 7104(b). The court of

appeals has held that this Court’s exercise of jurisdiction “requires both a valid claim and a

contracting officer’s final decision on that claim.” M. Maropakis Carpentry, Inc. v. United

States, 609 F.3d 1323, 1327 (Fed. Cir. 2010) (citing James M. Ellett Constr. Co. v. United States,

93 F.3d 1537, 1541–42 (Fed.Cir.1996)); see also Securiforce Int’l Am., LLC v. United States,

879 F.3d 1354, 1359 (Fed. Cir. 2018).

In this case, HCIC submitted a claim to the CO on September 6, 2018. Initial Compl. Ex.

C, at 10. It did not ask to rescind its previous waiver of damages covering delays from

September 15, 2017 through December 20, 2017, or state that it was entitled to an additional

$182,570.05 for that period of time. Id. at 10–12. Instead, it requested an additional 419 days to

complete the work and sought: 1) $480,821.74 representing costs, overhead, and profit for the

delay period from December 20, 2017 through September 5, 2018, and 2) $777,854.48 in costs,

overhead, and profit to cover the period from September 6, 2018 through October 30, 2019. Id. at

11–12. Because HCIC never filed a claim seeking to rescind its waiver of damages for the

September 15, 2017 through December 20, 2017 period, its proposed amendment of its

complaint would be futile.

CONCLUSION

For the foregoing reasons, HCIC’s second motion to amend the complaint is DENIED.

The Court hereby orders HCIC to show cause by Friday, July 24, 2020 why its original

complaint should not be dismissed for failure to state a claim in light of the Court’s opinion

granting the government’s motion for partial summary judgment. See Baptichon v. United

States, 144 Fed. Cl. 676, 683 (2019) (citing Anaheim Gardens v. United States, 444 F.3d 1309,

1315 (Fed. Cir. 2006)) (“[T]he court may dismiss a complaint sua sponte for failure to state a

claim upon which relief can be granted if ‘the pleadings sufficiently evince a basis for that

action.’”).

IT IS SO ORDERED.

s/ Elaine D. Kaplan

ELAINE D. KAPLAN

Judge

7