IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Robert J. Cummins, d/b/a Bob :

Cummins Construction Company :

:

v. :

:

Bradford Sanitary Authority, : No. 1000 C.D. 2019

Appellant :

:

Robert J. Cummins, d/b/a :

Bob Cummins Construction Company, :

Appellant :

:

v. :

: No. 1009 C.D. 2019

Bradford Sanitary Authority : Submitted: May 15, 2020

BEFORE: HONORABLE P. KEVIN BROBSON, Judge

HONORABLE ANNE E. COVEY, Judge

HONORABLE BONNIE BRIGANCE LEADBETTER, Senior Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY

JUDGE COVEY FILED: June 8, 2020

Bradford Sanitary Authority (Authority) appeals from the McKean

County Common Pleas Court’s (trial court) June 27, 2019 order denying its Motion

for Post-Trial Relief (Authority Motion). Robert J. Cummins d/b/a Bob Cummins

Construction Company (Cummins) also appeals from the trial court’s June 27, 2019

order denying in part Cummins’ Motion to Mold the Verdict for Interest, Penalty

Interest and Attorney’s Fees (Cummins Motion). The Authority presents four issues

for this Court’s review: (1) whether the trial court erred by finding that the

Authority’s Contract 2013-2 General Construction (Contract) was ambiguous,

thereby allowing Cummins to introduce expert testimony; (2) whether the trial court

erred by finding that the Authority acted in bad faith; (3) whether the trial court erred

by allowing the jury to decide Cummins’ change order claims; and (4) whether the

trial court erred by denying the Authority a new trial. Cummins presents two issues

for this Court’s review: (1) whether the trial court erred by denying Cummins penalty

interest; and (2) whether the trial court abused its discretion by denying Cummins the

balance of its attorney’s fees. After review, we reverse the trial court’s June 27, 2019

order denying the Authority’s Motion, and vacate the trial court’s June 27, 2019 order

denying, in part, Cummins’ Motion.

Background

The Authority owns and operates a wastewater treatment plant (Plant) in

Foster Township, McKean County, that serves the City of Bradford and other nearby

communities. When the Authority sought to conduct Wastewater Treatment Plan

Upgrades (Project), it retained Gannett Fleming, Inc. (GF) to provide engineering and

construction management services. See Reproduced Record (R.R.) at 1152a. Part of

the Project required the construction of concrete tanks containing sequencing batch

reactors (SBR)1 to treat sewage and other wastewater at the Plant.

In 2013, the Authority issued an Invitation for Bids (IFB) from

contractors for the Project that included the Contract and documents attached thereto

1

“A[n SBR] is a type of bioreactor used to remove sludge and other organic matter from

sewage in order to produce clean water for discharge.” Amici Br. at 3. More specifically,

[a]n SBR sequentially conducts each phase of the treatment of

wastewater in a single tank: filling the tank with untreated wastewater

(fill stage); reacting the untreated wastewater with diffused oxygen

(aeration stage); allowing the reacted wastewater to settle so solids

can fall to the bottom of the tank (settle stage); decanting the treated

water out of the tank (decant stage).

Authority Br. at 11-12.

2

and incorporated therein (Contract Documents).2 The IFB included a Project Manual

containing, inter alia, Instructions to Bidders and the Contract.3 Section 11393 of the

Project Manual contained the specifications for the SBR and its ancillary structures,

equipment and controls (SBR Specifications). See R.R. at 148a-171a. The Authority

described that GF’s design and the SBR Specifications were based on

a continuous-flow SBR manufactured by ABJ Sanitaire . . .

with four separate SBRs installed in 4 adjacent, contiguous

tanks (Tanks 1-4) (thereby increasing the total volume of

wastewater that could be treated). Tanks 1 and 2 shared a

common ‘influent box’ where wastewater entered the SBR,

as did Tanks 3 and 4. ‘Influent’ is the untreated

wastewater, so the wastewater first entered the influent box.

Each tank had its own manual gate in the influent box, and

as designed the influent was to continuously and

intentionally flow over the gate, which generally remained

in the open position (unless a tank was being cleaned or

repaired). Influent entered the influent boxes through 20-

inch ductile iron influent pipes capable of supplying 13.88

million gallons per day (‘MGD’) of wastewater.

Authority Br. at 12 (record citations omitted); see also R.R. at 152a, 196a-198a.

GF’s drawings, included in the Contract Documents, were of the above-described

system. Notwithstanding, because the Project was competitively bid, in Section 1.05

2

“‘The statutory mandate of competitive bidding is grounded in sound public policy.’

Philips Bro[s.] Elec[.] Contractors, Inc. v. P[a.] T[pk.] Comm[’]n, 960 A.2d 941, 945 (Pa. Cmwlth.

2008). ‘[I]t is the taxpaying citizen who provides the necessary funds and whose interest must be

protected.’ Yohe [v. City of Lower Burrell,] 208 A.2d [847,] 850 [(Pa. 1965)].” Hanisco v. Twp. of

Warminster, 41 A.3d 116, 123 (Pa. Cmwlth. 2012).

The first round of bids were received in June 2013. However, the Project was rebid, and

rebids were received in September 2013. See R.R. at 632a-633a.

3

The Contract consisted of the documents set forth in Article 15.01 of the parties’

Agreement, see R.R. at 56a, and in Article 1.01.A.16 of the General Conditions (see R.R. at 317a),

which included, inter alia: Instructions to Bidders, Agreement, General Conditions, Supplementary

Conditions, Specifications, GF’s Contract Drawings, Addenda, Agreement Exhibits including the

Notice to Proceed and Cummins’ Bid, plus any Written Amendments, Work Change Directives and

Change Orders to be delivered on or after the Contract’s effective date (collectively, the Contract

Documents).

3

of the SBR Specifications, the Authority designated as “ACCEPTABLE

MANUFACTURERS”:

A. ABJ Sanitaire

B. Ashbrook Simon Hartley [(Ashbrook)]

C. Aqua Aerobics

R.R. at 152a.

Although the SBR Specifications authorized bidders to select Ashbrook

or Aqua Aerobics as acceptable manufacturers, Section 11.01.B of the Instructions to

Bidders (Section 11.01.B.3) stated:

1. Products named on the Contract Drawings, if any, and

products of manufacturers named first throughout the

Project Manual[,] constitute [GF’s] design.

2. Products of named manufacturers, other than the first

named manufacturer, appearing throughout the Project

Manual or on the Contract Drawings are accepted as

equal; however, the requirements of [Section] 6.03 of the

General Conditions regarding ‘equipment’ and

‘machinery’ shall apply.

3. If products of manufacturers other than those named first

differ from those named first in the Project Manual or on

the [Contract] Drawings to the extent that their proper

incorporation into the [work required by the Contract

Document (]Work[)4] requires changes to the structural,

piping, mechanical, electrical, instrumentation, or any

4

Section 1.01.A.42 of the General Conditions (DEFINED TERMS) defined “Work” as:

The entire completed construction, or the various separately

identifiable parts thereof required to be provided under the Contract

Documents. Work includes and is the result of performing or

providing all labor, services, and documentation necessary to produce

such construction, and furnishing, installing, and incorporating all

materials and equipment into such construction, all as required by the

Contract Documents.

R.R. at 320a.

4

other changes of whatsoever nature, the [c]ontractor

shall be responsible for such changes.

Section 11.01.B (R.R. at 137a).

Because it received a better deal on the SBR system from Ashbrook than

from ABJ Sanitaire, Cummins proposed to install an Ashbrook SBR, which is a true

sequencing (rather than continuous-flow) SBR system, in which only one of the four

SBR tanks fills at a time. Cummins proposed to install automatic gates to control

influent flow into a tank, rather than manual gates or a separate pipe with a valve into

each tank. Cummins was the winning bidder.

On February 12, 2014, the Authority and Cummins executed the

Contract. On March 11, 2014, GF issued Cummins a Notice to Proceed. See R.R. at

284a. Pursuant to Section 1330 of the Project Manual (Submittal Procedures), see

R.R. at 1672a-1675a, Cummins submitted the Ashbrook product data and shop

drawings reflecting changes Ashbrook proposed to GF’s design to incorporate the

Ashbrook SBR. GF determined, based on Cummins’ and Ashbrook’s assurances

during the bid and submittal processes, that the proposed Ashbrook SBR would meet

the SBR Specifications with regard to hydraulic and organic capacity, in particular,

that it could handle up to 13.88 MGD of influent. After several meetings and some

changes, GF marked Cummins’ final SBR shop drawings “Reviewed,” R.R. at 640a,

3405a, and Cummins installed the Ashbrook SBR at the Plant.5

After the SBR was put into operation in 2015, the parties discovered an

influent overflow problem with the SBR system, which Cummins claimed was due to

the 20-inch influent piping being too small to accommodate the Ashbrook system’s

sequencing. The Authority/GF disputed that the piping size was the cause, and

claimed that the overflow resulted from the automatic gates not controlling the flow,

5

Cummins argues that GF reviewed and approved the drawings, but GF only marked them

“Reviewed.” R.R. at 640a, 3405a.

5

and that a different piping configuration was necessary to accommodate the

Ashbrook SBR. Notwithstanding, neither Cummins nor Ashbrook had previously

identified to GF a need to increase the size of the 20-inch influent pipes in GF’s

design or to reconfigure the piping for the Ashbrook SBR to deliver the contractual

13.88 MGD of wastewater.6 The parties disagreed on the solution and the cost

thereof.

On or about December 22, 2015, GF certified that the Project was

substantially complete – with the exception of the SBRs and two other items. See

R.R. at 273a-282a. However, because the Authority believed Cummins’ performance

was contrary to the Contract’s provisions relative to the SBRs and other Project

components, it denied certain of Cummins’ change orders and withheld Cummins’

final payment to correct or complete Cummins’ work.

On March 17, 2016, Cummins filed a complaint in the trial court against

the Authority, alleging that the Authority breached the Contract, and sought recovery

of the retainage ($259,920.00), and costs it incurred to perform extra work required

by the change orders ($393,523.00), plus interest, penalty interest and attorney’s fees.

Cummins amended its complaint on June 29, 2016. On July 28, 2016, the Authority

6

Cummins encouraged Ashbrook to submit a Technical Proposal to GF to be included as an

Acceptable Manufacturer for the Project. See R.R. at 706a, 4211a-4215a. In Ashbrook’s July 23,

2013 Technical Proposal, it represented:

Ashbrook proposes the elimination of the pre-react walls, as they are

not required for the Ashbrook SBR process proposed for this

[P]roject. Ashbrook will require the use of [four] (4) 20” electrically

actuated plug valves to feed/isolate each SBR basin in lieu of the

influent distribution splitter box and the [] weir gates shown in . . . the

[P]roject plans.

R.R. at 705a. Without GF’s input, Ashbrook changed its proposal to install automated influent

control gates in lieu of GF’s designed manual gates and, in advance of the rebids, Ashbrook sent its

modified Technical Proposal to the potential bidders. See R.R. at 3530a-3535a. As a result, the

above language was not included in Cummins’ rebid, or in its submittal after it won the Contract.

See R.R. at 706a, 4211a-4213a.

6

filed its answer and new matter to Cummins’ amended complaint, and

counterclaimed regarding various alleged defective or incomplete work, as well as

liquidated damages for delay. On August 29, 2016, Cummins filed its reply to the

Authority’s new matter and counterclaim. On November 14, 2016, the trial court

ordered the parties to complete discovery by January 30, 2017. The parties

conducted extensive discovery and exchanged expert reports.

On October 17, 2017, the parties filed competing motions for partial

summary judgment. The Authority asked the trial court to interpret, as a matter of

law, that the Contract made Cummins solely responsible for SBR overflows and

barred certain of Cummins’ requested change orders. See R.R. at 7a-563a. Cummins

requested that the trial court enter judgment in its favor, as a matter of law, on the

Authority’s SBR-related claims and counterclaims. See R.R. at 564a-1052a. The

parties opposed one another’s motions. See R.R. at 1227a-2554a. On February 28,

2018, the trial court denied both partial summary judgment motions, see R.R. at

2555a-2560a, stating: “[I]t is apparent that the facts alleged in each cannot both be

simultaneously true, and there is much doubt in the record about what facts exist.”

R.R. at 2556a.

On October 31, 2017, Cummins filed a second amended complaint to

include additional change order claims. See R.R. at 1053a-1149a. On November 8,

2017, the Authority filed an answer and new matter to Cummins’ second amended

complaint, and asserted counterclaims against Cummins for costs the Authority

incurred as a result of Cummins’ purported failure to correct SBR deficiencies that

allowed untreated wastewater to overflow the SBR gates. See R.R. at 1150a-1226a.

On February 15, 2019, the Authority filed two motions in limine in the

trial court. In the first, the Authority requested the trial court to preclude Cummins’

expert James D. Hannon (Hannon) of Hannon Engineering, P.C. from expressing

opinions regarding Cummins’ and GF’s contractual responsibilities that are contrary

7

to the Contract’s express terms. See R.R. at 2604a-2676a. In the second, the

Authority sought to have the trial court find Cummins responsible for identifying and

making changes necessary to incorporate the Ashbrook SBR into GF’s design

pursuant to Section 11.01.B.3. See R.R. at 2677a-2717a. Cummins opposed the

motions in limine. See R.R. at 2760a-2806a.

On March 7, 2019, the trial court partially granted the Authority’s

motion in limine to exclude Hannon’s opinions, stating that no expert shall give

opinions regarding legal issues. See R.R. at 2819a-2820a. On the same date, the trial

court deferred a ruling on the Authority’s motion in limine concerning Contract

interpretation, stating that “the [trial c]ourt is without sufficient evidence to consider

the contract as a whole, which is a factor the [trial c]ourt must weigh in determining

ambiguity.” See R.R. at 2817a. The trial court further ruled that the matter “may be

appropriately decided after a jury verdict through post-trial motions[.]” R.R. at

2818a.

The trial court conducted a jury trial from March 11 to 20, 2019. On

March 15, 2019, at the end of Cummins’ case-in-chief, the Authority moved for non-

suit, arguing: (1) the Contract required judgment in the Authority’s favor on all of

Cummins’ SBR-related claims because Cummins was solely responsible for

identifying, modifying, making, and paying for all changes necessary to incorporate

the Ashbrook SBR into GF’s design; (2) the jury should not be permitted to decide,

under the Commonwealth Procurement Code,7 Cummins’ bad faith claims related to

the Authority’s payments and the $260,000.00 it retained; and (3) certain of

Cummins’ extra work/change order claims were barred by the Contract’s express

terms. See R.R. at 4393a-4409a. Cummins opposed the motion. See R.R. at 4409a-

4418a. The trial court denied the Authority’s non-suit motion. See R.R. at 4418a.

7

62 Pa.C.S. §§ 101-2311.

8

Also, after Cummins’ case-in-chief, and before commencement of the

Authority’s case-in-chief, the trial court denied the Authority’s motion in limine

concerning Contract interpretation, stating that the Contract, particularly Section

11.01.B.3 applicable to the SBR, was ambiguous as a matter of law. See R.R. at

2865a-2867a. The trial court explained:

[] [The Authority] contends that [Section 11.01.B.3] is plain

in its meaning and that a contractor is responsible for any

and all changes to incorporate a contractor’s item selections

in [GF’s] design. [Cummins] responds that while the

contractor may suggest changes in its bid to afford the

greatest savings to [the Authority], [GF] is ultimately

responsible for ensuring that the project design is a

functioning whole, at least in theory. Furthermore,

[Cummins] contends that a contractor is bound to construct

according to [GF’s] design and has no discretion absent

[GF’s] or [the Authority’s] approval.

[] After considering the whole contract and recognizing the

context of how public projects are bid and executed in

practice, including how this project specifically transpired,

it is apparent to the [trial c]ourt that a contractor’s work is

greatly informed, if not dictated, by the project engineer’s

design. Moreover, there is no apparent contract clause or

mechanism that allows for a contractor to re-design how a

portion of the project should be constructed (or for a

contractor to construct sua sponte) to address a needed

design change, even if a contractor identified design

changes necessary to incorporate alternate equipment or

items, as chosen by the contractor, that are in contradiction

with the project engineer’s basis of design. In light of these

findings of fact surrounding the [C]ontract, the [trial c]ourt

must determine that the [C]ontract is susceptible to more

than one reasonable interpretation.

R.R. at 2866a-2867a. The Authority renewed its non-suit motion at the close of all of

the evidence, which the trial court again denied. See R.R. at 5310a. Accordingly, the

trial court permitted the jury to decide Cummins’ contract-based claims. See R.R. at

5310a.

9

Over the Authority’s objection, the trial court instructed the jury that it

could interpret Section 11.01.B.3, explaining:

[Cummins] and the [Authority] disagree about the meaning

of some of [the] words and terms in the [C]ontract. Each

party must prove that its interpretation is correct. When

deciding which interpretation is correct, you should

consider the following. The parties intent at the time they

entered into the [C]ontract. The [C]ontract as a whole, so

all parts make sense when read together. The parties’

words and conduct after they entered into the [C]ontract.

The words’ plain and ordinary meaning unless you find that

the parties intended the words to have another meaning, or

if they are technical words, the meaning used by people in

that trade or business. Whether the parties intended to

exclude other similar items. Whether specific words or

terms control general words or terms.

....

If and only if you cannot determine what the parties

intended the disputed words or terms to mean based upon

the above considerations, then you may consider which

party drafted the [C]ontract and interpret the language

against that perianal [sic]. Again, this rule should be your

last resort in determining which party’s interpretation of the

[C]ontract is correct. Notwithstanding, when a contract is

clear and unequivocal, its meaning must be determined by

its contents alone. The fundamental rule in interpreting the

meaning of a [C]ontract is to ascertain and to give effect to

the intent of the [C]ontract of the parties.

See R.R. at 5413a-5415a.

On March 21, 2019, the jury rendered a verdict in favor of Cummins in

the amount of $488,243.24, consisting of the Contract balance that the Authority

withheld, along with a number of Cummins’ change order claims. See R.R. at 2868a-

2876a. The jury also found that the Authority acted in bad faith in retaining the

Contract balance. See R.R. at 2869a. In addition, the jury found against the

Authority on 19 of its 20 counterclaims. See R.R. at 2873a-2874a.

10

Facts

On March 29, 2019, Cummins filed the Cummins Motion, therein

seeking to have the trial court award the following additional amounts: (1) regular

interest in the amount of $112,548.00; (2) penalty interest in the amount of

$88,372.00; (3) attorney’s fees and costs in the amount of $449,107.55; and (4)

litigation expenses in the amount of $35,464.87. See R.R. at 2877a-2900a, 3056a-

3264a. The Authority opposed Cummins’ Motion. See R.R. at 2989a-3005a.

On April 1, 2019, the Authority filed the Authority Motion, see R.R. at

2901a-2988a, seeking judgment in its favor and against Cummins, claiming that the

trial court improperly determined that the Contract was ambiguous and erred by

allowing the jury to interpret the Contract provisions. See R.R. at 2946a-2960a. The

Authority also asserted that the trial court erred by permitting the jury to decide

Cummins’ bad faith claim, see R.R. at 2960a-2965a, and extra work/change order

claim. See R.R. at 2967a-2983a. Cummins opposed the Authority’s Motion. See

R.R. at 3006a-3055a.

On June 27, 2019, relative to Cummins’ Motion, the trial court entered

judgment upon the verdict for the amounts the jury awarded to Cummins, and

awarded regular interest and some of Cummins’ requested attorney’s fees, but denied

Cummins’ request for penalty interest. See Authority Br. App. B. By separate June

27, 2019 order, the trial court denied the Authority’s Motion.8 See Authority Br.

App. A.

On July 23, 2019, the Authority appealed to this Court.9 See Pa.

Cmwlth. No. 1000 C.D. 2019. On July 25, 2019, Cummins filed a cross-appeal in

this Court. See Pa. Cmwlth. No. 1009 C.D. 2019. On July 29 and August 5, 2019,

8

Notably, the trial court’s order did not address the challenged change orders.

9

Also, on July 23, 2019, the McKean County Prothonotary issued a Notice of Entry of

Judgment against the Authority in the amount of $857,743.14. See R.R. at 5468a.

11

respectively, the trial court directed the parties to file Statements of Errors

Complained of on Appeal pursuant to Pennsylvania Rule of Appellate Procedure

(Rule) 1925(b) (1925(b) Statement). On August 16 and 23, 2019, respectively, the

parties filed their Rule 1925(b) Statements. See R.R. at 5469a-5480a. On October

15, 2019, the trial court issued its opinion pursuant to Rule 1925(a) (1925(a)

Opinion). See R.R. at 5481a-5527a. On October 21, 2019, this Court consolidated

the appeals.10 On January 3, 2020, the American Council of Engineering Companies

of Pennsylvania and GF filed an Amici Curiae brief.

Discussion

1. Authority’s Motion

In its Motion, the Authority sought judgment notwithstanding the verdict

(JNOV) or a new trial based on the trial court’s interpretation that the Contract was

ambiguous.

a. SBR

The Authority argued that the trial court should have determined as a

matter of law that the Contract placed sole responsibility on Cummins for defective

system performance related to Cummins’ Ashbrook SBR and, by failing to do so, the

trial court erred by allowing the jury to interpret the Contract language based on

extrinsic evidence.

“Under [this Court’s] applicable standard of review, we will reverse a

trial court’s denial of a motion for JNOV or a new trial only if we find an abuse of

discretion or an error of law that controlled the outcome of the case.” Walnut St.

Assocs., Inc. v. Brokerage Concepts, Inc., 982 A.2d 94, 97 (Pa. Super. 2009), aff’d,

10

The Authority is the designated appellant.

12

20 A.3d 468 (Pa. 2011). The crux of the Authority’s appeal is that the trial court

improperly determined that the Contract was ambiguous. “[T]he question of whether

a contract is ambiguous is a question of law.” Kripp v. Kripp, 849 A.2d 1159, 1164

n.5 (Pa. 2004); see also PBS Coals, Inc. v. Dep’t of Transp., 206 A.3d 1201 (Pa.

Cmwlth. 2019).11 “When, as here, the issue raised on appeal presents a question of

law, [this Court’s] standard of review is de novo and our scope of review is plenary.”

Walnut St. Assocs., Inc., 982 A.2d at 97. “Thus, ‘we need not defer to the

conclusions of the trial court and are free to draw our own inferences.’” PBS Coals,

Inc., 206 A.3d at 1210 (quoting Sw. Energy Prod. Co. v. Forest Res., LLC, 83 A.3d

177, 187 (Pa. Super. 2013)).

The Pennsylvania Supreme Court has explained:

It is [] well established that under the law of contracts, in

interpreting an agreement, the court must ascertain the

intent of the parties.

In cases of a written contract, the intent of the parties is the

writing itself. If left undefined, the words of a contract are

to be given their ordinary meaning. When the terms of a

contract are clear and unambiguous, the intent of the parties

is to be ascertained from the document itself. When,

however, an ambiguity exists, parole evidence is admissible

to explain or clarify or resolve the ambiguity, irrespective of

whether the ambiguity is patent, created by the language of

the instrument, or latent, created by extrinsic or collateral

circumstances. A contract is ambiguous if it is reasonably

susceptible of different constructions and capable of being

understood in more than one sense. While unambiguous

contracts are interpreted by the court as a matter of law,

ambiguous writings are interpreted by the finder of fact.

Kripp, 849 A.2d at 1163 (citations omitted). “The fact that the parties do not agree

upon the proper interpretation does not necessarily render the contract ambiguous.”

11

Appeal granted in part, 218 A.3d 373 (Pa. 2019) (Table).

13

Parshall v. Parshall, 560 A.2d 207, 211 (Pa. Super. 1989) (quoting Vogel v. Berkley,

511 A.2d 878, 881 (Pa. Super. 1986)).

Here, the trial court concluded that the “[C]ontract was ambiguous[,]”

Trial Ct. June 27, 2019 Op. at 2 (R.R. at 5495a), based on “the [C]ontract clause most

exemplary of the dispute,”12 Trial Ct. June 27, 2019 Op. at 4 (R.R. at 5497a), Section

11.01.B.3, which stated:

If products of manufacturers other than those named first

differ from those named first in the Project Manual or on

the [Contract] Drawings to the extent that their proper

incorporation into the Work requires changes to the

structural, piping, mechanical, electrical,

instrumentation, or any other changes of whatsoever

nature, the [c]ontractor shall be responsible for such

changes.

Section 11.01.B.3 (R.R. at 137a). The parties do not dispute that ABJ Sanitaire was a

manufacturer “named first in the Project Manual or on the [Contract] Drawings[,]” and

that Ashbrook was a manufacturer “other than [the one] named first in the Project

Manual or on the [Contract] Drawings.” Id. (emphasis added). Therefore, Section

11.01.B.3 mandated that “to the extent that incorporation [of the Ashbrook SBR] into

[GF’s design] require[d] changes to the structur[e], piping, mechanic[s] . . . or any other

changes whatsoever, [Cummins] shall be responsible for such changes.” Id.

The parties also agree that changes were necessary to incorporate the

Ashbrook SBR into GF’s design because there were fundamental flow differences

between the Ashbrook system and the ABJ Sanitaire system. Cummins presented

12

Although the trial court added that Section 11.01.B.3 was “not the only [Contract] clause

in dispute,” Trial Ct. Op. at 4 (R.R. at 5497a), it was the only Contract clause the trial court

analyzed in reaching its conclusion that the entire Contract was ambiguous. In its 1925(a) Opinion,

the trial court stated: “[Section] 11.01.B.3 was the exemplary clause and was discussed in great

detail in the [trial c]ourt’s previous [o]rders[,] eliminating the need for reiteration [in the 1925(a)

Opinion].” Trial Ct. 1925(a) Op. at 4-5 (R.R. at 5484a-5485a). Accordingly, this Court’s review is

likewise limited herein to Section 11.01.B.3.

14

changes to GF in the shop drawing submittal process and GF reviewed them. The

dispute arose after the overflow problem. The parties disagreed about whether GF or

Cummins was responsible for identifying that the 20-inch influent pipe in GF’s

design was undersized for the Ashbrook system. The Authority interpreted Section

11.01.B.3 to mean that Cummins was required to identify, make and pay for all changes

necessary to incorporate the Ashbrook SBR into GF’s design. Cummins interpreted

Section 11.01.B.3 such that, although it was required to make and pay for changes

necessary to incorporate its Ashbrook SBR, it was not liable for the overflow issues or

the fix because GF was responsible during the shop drawing submittal process to ensure

that the SBR system worked as a functioning whole, regardless of which SBR

manufacturer was used.

Because this Court’s review of whether the trial court erred turns on

whether Section 11.01.B.3 is ambiguous, we must first examine the Contract to interpret

the parties’ intent.13 The Contract consisted, inter alia, of the following Contract

Documents: Instructions to Bidders, the Agreement, General Conditions, Contract

Drawings, and SBR Specifications. See Section 15.01 of the Agreement (CONTRACT

DOCUMENTS) (R.R. at 56a), Section 1.01.A.16 of the General Conditions (DEFINED

TERMS/CONTRACT DOCUMENTS) (R.R. at 317a).

According to the Contract, as part of the bid process, Cummins made

assurances that it carefully reviewed and understood the Work, including GF’s basis

of design as incorporated into GF’s Contract Drawings and the SBR Specifications.14

13

For clarity, this Court replaced Contract references to “OWNER” with “the Authority,”

references to “ENGINEER” with “GF,” and references to “CONTRACTOR” with “Cummins.”

14

Section 1.01.A.42 of the General Conditions (DEFINED TERMS) defined “Specifications”

as

[t]hat part of the Contract Documents consisting of written technical

descriptions of materials, equipment, systems, standards, and

workmanship as applied to the Work, and certain administrative

details applicable thereto. The arrangement, style and format of the

15

Section 11.01.B.1 of the Instructions to Bidders explained: “Products named on the

Contract Drawings, if any, and products of manufacturers named first throughout

the Project Manual[,] constitute [GF’s] design.” R.R. at 137a (emphasis added).

Generally, Section 1.01 of the SBR Specifications summarized that “[t]he work

specified . . . consists of providing the [SBR] equipment in the reinforced concrete

SBR tanks and all ancillary equipment and controls.” R.R. at 148a (emphasis

added). Again, Section 1.03 of the SBR Specifications detailed the system

description based on the ABJ Sanitaire SBR. See R.R. at 148a-150a. In Section 1.05

of the SBR Specifications, the Authority designated as “ACCEPTABLE

MANUFACTURERS”:15

A. ABJ Sanitaire

B. [Ashbrook]

C. Aqua Aerobics

Specifications is solely for convenience; and does not constitute

segregation of the Work for subcontracts, products, or labor, nor does

it control the extent of Work to be performed by any trade.

R.R. at 319a.

15

Section 1.02.A.1 of the General Conditions (TERMINOLOGY) declared:

Whenever in the Contract Documents the terms ‘as allowed,’ ‘as

approved,’ or terms of like effect or import are used, or the adjectives

‘reasonable,’ ‘suitable,’ ‘acceptable,’ ‘proper,’ ‘satisfactory,’ or

adjectives of like effect or import are used to describe an action or

determination of [GF] as to the Work, it is intended that such action

or determination will be solely to evaluate, in general, the

completed Work for compliance with the requirements of and

information in the Contract Documents and conformance with

the design concept of the completed [P]roject as a functioning

whole as shown or indicated in the Contract Documents. The use

of any such term or adjective does not create any duty or authority

by [GF] to supervise or direct the performance of the Work or

any duty or authority to undertake responsibility contrary to . . .

any other provision of the Contract Documents.

R.R. at 321a (emphasis added).

16

R.R. at 152a. However, Section 1.04.D of the SBR Specifications cautioned: “The

naming of a manufacturer in this Specification Section is not an indication that

the manufacturer’s standard equipment is acceptable in lieu of the specified

component features. Naming is only an indication that the manufacturer may

have the capability of engineering and supplying a system as specified.” R.R. at

151a (emphasis added).

Section 1.01 of the Agreement (WORK) represented: “[Cummins] shall

complete all Work as specified or indicated in the Contract Documents. The

Work is generally described as follows: “[Cummins] shall at its sole expense furnish

all labor, . . . materials, supplies, equipment, . . . and all things necessary or proper

for, and to perform all work necessary or incidental to, and perform all other

obligations imposed by this Contract for [the Project].”16 R.R. at 50a (emphasis

added).

16

Section 1.02 of the General Conditions (TERMINOLOGY) declared:

D. Furnish, Install, Perform, and Provide:

1. The word ‘furnish,’ when used in connection with

services, materials, or equipment, shall mean to supply and

deliver said services, materials, equipment to the Site . . .

ready for use or installation.

2. The word ‘install,’ when used in connection with services,

materials, or equipment, shall mean to put into use including

all necessary hook-ups, connections, and testing; and/or

place in final position said services, materials, or equipment

complete and ready for its intended use.

3. The words ‘perform’ or ‘provide,’ when used in

connection with services, materials, or equipment, shall

mean to furnish and install said services, materials, or

equipment complete and ready for its intended use.

4. When ‘furnish,’ ‘install,’ ‘perform,’ or ‘provide’ is not

used in connection with services, materials, or equipment in

a context clearly requiring an obligation of [Cummins],

‘provide’ is implied.

17

Section 3.01 of the General Conditions (INTENT) declared, in relevant

part:

A. The Contract Documents are complementary; what is

called for by one is as binding as if called for by all.

B. It is the intent of the Contract Documents to describe

a functionally complete Project or part thereof, to be

constructed in accordance with the Contract

Documents.

1. Any labor, documentation, services, materials

or equipment that may reasonably be inferred

from the Contract Documents, or from prevailing

custom or trade usage as being required[17] to

produce the intended result, shall be provided,

whether or not specifically called for, at no

increase in the Contract [p]rice.

....

D. [Cummins] acknowledges that the Contract

Drawings and Specifications are intended only to show

the intent of the completed Project. [Cummins]

E. Unless stated otherwise in the Contract Documents, words or

phrases which have a well-known technical or construction

industry or trade meaning are used in the Contract Documents in

accordance with such recognized meaning.

R.R. at 321a-322a.

17

Section 9.10.I of the General Conditions (LIMITATIONS ON THE ENGINEER’S AUTHORITY

AND RESPONSIBILITIES) declares:

The words ‘required’, ‘prescribed’, ‘directed’, or ‘ordered’ by

[GF] or words of like import where used in these Contract Documents

shall have the meaning only of interpreting the Contract Documents,

directing notice to or attention of the materials, and finished results

for conformity to and compliance with the Contract Drawings; and or

not intended or implied as any directions, instructions, or

superintendence of [Cummins’] methods of construction; or use

of equipment, . . . ; or acceptance of liability therefore [sic]; by

[the Authority] or [GF].

R.R. at 369a.

18

represents that it is qualified to construct the Work as

depicted in the Contract Documents; and to determine its

own means, methods, techniques, sequences, and

procedures. To the extent that means, methods,

techniques, sequences, and procedures are identified in the

Contract Documents; [Cummins] is required to

independently evaluate those means, methods,

techniques, sequences, and procedures for the purpose

of determining whether the means, methods, techniques,

sequences, and procedures depicted in the Contract

Documents are adequate to construct the Work.

[Cummins] further represents that it has based its bid upon

its own determination of the appropriate means, methods,

techniques, sequences, and procedures required to construct

the Contract Work.

R.R. at 324a-325a (emphasis added).

Accordingly, Section 4.06.A. of the Instructions to Bidders

(EXAMINATION OF BIDDING DOCUMENTS AND THE SITE) also stated, in pertinent part:

Before submitting a Bid, it is the responsibility of each

Bidder to do the following:

1. Examine and carefully study the Bidding

Documents,[18] including any Addenda and the other related

data identified in the Bidding Documents.

....

4. Determine the means and methods the Bidder proposes to

use to construct the Work consistent with the Contract

Documents.

....

9. Correlate the information known to the Bidder,

information and observations obtained from visits to the

Site, reports and drawings identified in the Bidding

Documents, and all additional examinations, investigations,

18

According to Section 1.01.A.5 of the General Conditions (DEFINED TERMS), the Bidding

Documents consisted of: “The Bidding Requirements, proposed Contract Documents current at the

time of the Bid, Resource Drawings, and all Addenda issued prior to opening of Bids.” R.R. at

316a (emphasis added).

19

explorations, tests, studies, and data with the Bidding

Documents.

....

11. Promptly give [GF] written notice of all conflicts,

errors, ambiguities, or discrepancies that the Bidder

discovers in the Bidding Documents; and confirm that the

written resolution thereof by [GF] is acceptable to Bidder.

12. Determine that the Bidding Documents are generally

sufficient to indicate and convey an understanding of all

terms and conditions for the performance of the Work.

R.R. at 132a-133a (emphasis added); see also Section 4.10.A of the Instructions to

Bidders (ADEQUACY OF BIDDING DOCUMENTS), R.R. at 134a. Section 7.01 of the

Instructions to Bidders (QUESTIONS, INTERPRETATIONS, AND CLARIFICATIONS)

reiterated that “[a]ll questions about the meaning or intent of the Bidding Documents

shall be submitted to [GF] in writing . . . .” R.R. at 135a.

By signing the Agreement, Cummins repeated its understanding.

Section 7.01 of the Agreement (CONTRACTOR REPRESENTATIONS) provided, in

relevant part:

In order to induce [the Authority] to enter into this

Agreement[,] [Cummins] makes the following

representations:

A. [Cummins] has examined and carefully studied

the Contract Documents and the other related data

identified in the Bidding Documents.

....

G. [Cummins] has correlated the information known to

[Cummins], information and observations obtain[ed] from

visits to the Site, reports and drawings identified in the

Contract Documents, and all additional examinations,

investigations, explorations, tests, studies, and data with the

Contract Documents.

20

H. [Cummins] has given [GF] written notice of all

conflicts, errors, ambiguities, or discrepancies that

[Cummins] has discovered in the Contract Documents, and

the written resolution thereof by [GF] is acceptable to

[Cummins].

I. The Contract Documents are generally sufficient to

indicate and convey [an] understanding of all terms and

conditions for performance and furnishing of the Work.

R.R. at 54a (emphasis added).

Moreover, Section 2.05.A.1 of the General Conditions (BEFORE

STARTING CONSTRUCTION) (General Conditions (BEFORE)), required: “Before

undertaking each part of the Work, [Cummins] shall carefully study and compare

the Contract Documents and check and verify pertinent figures therein and

apply all field measurements.” R.R. at 323a (emphasis added). Section 2.05.C of

the General Conditions (BEFORE) repeated: “[Cummins] shall promptly report in

writing to [GF] any conflict, error, ambiguity, or discrepancy which [Cummins] may

discover; and shall obtain a written interpretation or clarification from [GF] before

proceeding with the Work affected thereby.” R.R. at 323a.

In Section 6.20 of the General Conditions (CONTRACTOR’S REVIEW OF

CONTRACT DOCUMENTS), Cummins again agreed:

A. Submission of a Bid and/or execution of the

Agreement by [Cummins] is a representation that

[Cummins] has thoroughly reviewed and evaluated the

Contract Documents to determine whether [Cummins]

needs clarification of the Contract Documents or

additional interpretation of the intent of the Contract

Documents to determine its Bid, and that it has requested

any needed clarification prior to submitting its [B]id.

B. [Cummins] represents that it has the knowledge,

skill, and expertise to perform the Work; that it

understands that it must make reasonable inferences to

determine portions of the Work not shown in the

Contract Documents that would be required for a

proper and complete Project, and it has included all costs

21

for such inferences in its Bid; and, that [Cummins] is not

relying on representations the Contract Documents or

by [the Authority] or [GF] for the purpose of

determining the cost, means, methods, sequences, or

procedures of performing the Work.

R.R. at 359a-360a (emphasis added).

By bidding with the Ashbrook SBR and entering into the Contract,

Cummins also understood and guaranteed its work in accordance with the Contract

Documents. Article 6 of the General Conditions (CONTRACTOR RESPONSIBILITIES), in

Section 6.01.A thereof directed that “[Cummins] shall be solely responsible for the

means, methods, techniques, sequences, and procedures of construction[,]” and

“[Cummins] shall be responsible to see that the completed Work complies

accurately with the Contract Documents.” R.R. at 341a (emphasis added).

According to Section 6.03.A: “Unless otherwise specified in the General

Requirements, [Cummins] shall provide and assume full responsibility for all

services, materials, equipment, labor . . . and all other facilities and incidentals

necessary for the performance, testing, start up, and completion of the Work.”

R.R. at 341a (emphasis added). By Section 6.19.A of the General Conditions

(CONTRACTOR’S GENERAL WARRANTY AND GUARANTEE), Cummins “warrant[ed]

and guarantee[d] to [the Authority] and [GF] . . . that all Work, materials,

equipment, and other Contract performances shall be in accordance with the

Contract Documents . . . .” R.R. at 358a (emphasis added).

In Section 10.01 of the Agreement (CONTRACTOR SHALL GUARANTEE

THE WORK), Cummins agreed:

[Cummins] shall guarantee its work, material and

equipment and the other Contract performances, and

shall remedy, without cost to [the Authority], any

defects which may develop therein during a period of one

(1) year from the date of the [Authority’s] acceptance of the

Certificate of Substantial Completion issued by [GF].

22

R.R. at 55a (emphasis added).

Finally, under the Contract, GF’s review of Cummins’ shop drawings

did not shift liability for the Ashbrook system’s functionality to GF. Notably, Section

1.01.A.17.a of the General Conditions declared: “Shop drawings and other

[Cummins’] submittals are not Contract Documents as so defined.” R.R. at 317a

(emphasis added); see also Section 1.01.A.40 of the General Conditions (R.R. at 319a).

Section 6.17.B.2 of the General Conditions (SUBMITTALS) provided:

The data shown in [Cummins’] [s]hop [d]rawings shall be

complete with respect to quantities, dimensions,

specified performance and design criteria, materials and

similar data to show [GF] the services, materials and

equipment [Cummins] proposes to provide, and to enable

[GF] to review the information for the limited purposes

set forth in Subparagraph 6.17.F.

R.R. at 356a (emphasis added). According to Section 6.17.E.2 of the General

Conditions, “[b]efore submitting each [s]hop [d]rawing, . . . [Cummins] shall have

determined and verified . . . [a]ll . . . quantities, dimensions, specified

performance criteria, installation requirements, materials, . . . and similar

information with respect thereto[,]” R.R. at 356a (emphasis added), “shall have

reviewed and coordinated each [s]hop [d]rawing . . . or other submittal . . . with

the requirements of the Work and the Contract Documents[,]” and shall have

supplied written verification that it satisfied those obligations. R.R. at 357a

(emphasis added).

Section 6.17.E.4.a of the General Conditions further specifies that, “[a]t

the time of each submittal, [Cummins] shall give [GF] specific written notice if

any [s]hop [d]rawing . . . or other submittal [] deviates from the requirements of

the Contract Documents,” which notice is separate from the submittal, plus

“[Cummins] shall cause a specific notation to be made on each [s]hop [d]rawing .

23

. . or other submittal.” R.R. at 357a (emphasis added). Notwithstanding, according

to Section 6.17.E.5:

[Cummins’] obligations are not changed by an approval

of any [s]hop [d]rawing or other submittal.

a. If [Cummins] intends that a change to the

Contract be made by any information in a [s]hop

[d]rawing, it shall affirmatively state that the [s]hop

[d]rawing depicts a change in the Work, and submit a

written notice in accordance with the procedure in

Subparagraph 6.17.E.4.

b. Notations, marks, or other comments by [GF] on a

submittal . . . do not change the Contract Documents.

R.R. at 357a (emphasis added).

Regarding GF’s review of shop drawings and submittals, Section 6.17.F

of the General Conditions prescribed that, even if GF had “approved” Cummins’

shop drawings:

1. [GF’s] review and approval of [s]hop [d]rawings .

. . and other submittals will be only for general

conformance to the information given in the Contract

Documents and compatibility with the design concept of

the completed Project as a functioning whole as

indicated by the Contract Documents.

....

b. [GF’s] review and approval shall not extend to

the means, methods, techniques, sequences, or

procedures of construction . . . .

c. The review and approval of a separate item as

such will not indicate approval of the assembly in

which the item functions.

2. [GF’s] review and approval of [s]hop [d]rawings

or other submittals shall not relieve [Cummins] from

responsibility for any variation from the requirements

of the Contract Documents.

24

R.R. at 357a-358a (emphasis added).

Section 6.19.C of the General Conditions (CONTRACTOR’S GENERAL

WARRANTY AND GUARANTEE) stated:

[Cummins’] obligation to perform and complete the

Work in accordance with the Contract Documents shall

be absolute; none of the following shall constitute an

acceptance of Work, materials, equipment, or other

Contract performances that are not in accordance with

the Contract Documents, or a release of [Cummins’]

warranty or guarantee or obligation to perform the Work in

accordance with the Contract Documents:

1. Observations by [GF].

2. Recommendation by [GF] or payment by [the

Authority] of any progress or final payment.

3. The issuance of a [C]ertificate of Substantial

Completion by [GF] or any payment related thereto by [the

Authority].

....

6. Any review and approval of a [s]hop [d]rawing or

[s]ample submittal, or the issuance of a notice of

acceptability by [GF].

R.R. at 359a (emphasis added).

Consequently, if Ashbrook failed to take into account the hydraulics and

the influent piping size for the SBR system, the Contract made Cummins responsible

therefor. Section 6.06.D of the General Conditions (CONCERNING SUPPLIERS AND

OTHERS), specified: “[Cummins] shall be fully responsible to [the Authority] and

[GF] for all acts and omissions of the . . . [s]uppliers, and other individuals or

entities performing or furnishing any of the Work just as [Cummins] is responsible

for [its] acts and omissions.” R.R. at 348a (emphasis added).

According to Section 9.10.C of the General Conditions (LIMITATIONS ON

THE ENGINEER’S AUTHORITY AND RESPONSIBILITIES), “[GF] will not be responsible

25

for [Cummins’] failure to perform the Work in accordance with the Contract

Documents.” R.R. at 368a (emphasis added). Section 9.10.D thereof stated: “[GF]

shall not be responsible for the acts or omissions of [Cummins], or of any . . .

[s]upplier, or any other individual or entity performing the Work.”19 R.R. at

368a (emphasis added).

Contrary to Cummins’ position, the Authority’s naming of Ashbrook as an

additional manufacturer did not make the Ashbrook SBR interchangeable with the ABJ

Sanitaire SBR around which the Project was designed. Nor did the Contract Documents

make any tacit guarantee that the Ashbrook SBR would fit and function without design

changes. Rather, this Court has explained:

It is well settled that where the government orders a

structure to be built, and in so doing prepares the

project’s specifications prescribing the character,

dimension, and location of the construction work,

the government implicitly warrants, nothing else

appearing, that if the specifications are complied

with, satisfactory performance will result.

If [a] court finds the cause of faulty construction to

be a deficiency in a design specification the

government would bear the risk, and consequently

be liable for reasonable costs incurred by the

plaintiff. Defective design specifications may

entitle a contractor to an equitable adjustment of the

contract for the reparative work required to build a

satisfactory end-product.

In fact, Section 9.10.H General Conditions (LIMITATIONS ON THE ENGINEER’S AUTHORITY

19

AND RESPONSIBILITIES) provided:

[GF] makes no representations or warranties to [Cummins], or [its] . .

. [s]uppliers . . . regarding the completeness, accuracy, the suitability

of any means or methods shown, or fitness of use of the plans,

estimates and Contract Documents; or that the Work can be

performed or constructed using normal and reasonable construction

methods.

R.R. at 368a.

26

But not all contract specifications are design

specifications - some are merely performance

specifications:

Design specifications explicitly state how the

contract is to be performed and permit no

deviations. Performance specifications, on the

other hand, specify the results to be obtained,

and leave it to the contractor to determine how

to achieve those results.

The government does not implicitly warrant

performance specifications for complete accuracy

or adequacy. Typical performance type

specifications set forth an objective or standard to

be achieved, and the successful bidder is expected

to exercise his ingenuity in achieving that objective

or standard of performance, selecting the means

and assuming a corresponding responsibility for

that selection.

A.G. Cullen Constr., Inc. v. State Sys. of Higher Educ., 898 A.2d 1145, 1157 (Pa.

Cmwlth. 2006) (bold emphasis added), disapproved of on other grounds by A. Scott

Enters., Inc. v. City of Allentown, 142 A.3d 779 (Pa. 2016) (quoting George Sollitt

Constr. Co. v. United States, 64 Fed. Cl. 229, 296-97 (2005) (emphasis added)

(citations and quotations omitted)).

This Court expounded:

In order to differentiate between design and performance

specifications, courts examine the level of discretion that

exists within a given specification; ‘discretion serves as the

touchstone for assessing the extent of implied warranty and

intended liability.’ Conner Bros. Constr. Co., Inc. v.

U[.]S[.], 65 Fed. Cl. 657, 685 (2005). A contractor

claiming a particular specification is ‘design’ rather than

‘performance’ must establish the specification ‘do[es] not

permit meaningful discretion . . . and the defective

specification [is] the cause of [the] injury.’ Id.

Of particular import here, the mere identification of a

product or manufacturer does not create a design

specification. Where a government agency identifies a

27

particular product or manufacturer by name, but

permits substitution of ‘an approved equal,’ such a

specification is ‘performance’ in nature and, as a result,

carries no implied warranty. See W.G. Yates & Sons

Constr. Co., Inc. v. United States, 53 Fed. Cl. 83 (2002);

Florida Bd. of Regents v. Mycon Corp., 651 So.2d 149 (Fla.

Dist. Ct. App. 1995). See also Philip L. Bruner and Patrick

J. O’Connor, Jr., 3 Bruner & O’Connor on Constr[.] Law §

9:93 (2005).

A.G. Cullen Constr., Inc., 898 A.2d at 1157 (emphasis added).

“A contract is not ambiguous if the court can determine its meaning

without any guide other than a knowledge of the simple facts on which, from the

nature of language in general, its meaning depends[.]” State Highway & Bridge Auth.

v. E. J. Albrecht Co., 430 A.2d 328, 330 (Pa. Cmwlth. 1981) (quoting 8 P.L.E.

Contracts § 146 (1971)). Here, based solely on the Contract language, the meaning

of Section 11.01.B.3 is clear. Because Cummins’ bid offered an SBR other than that

for which GF prepared the Contract Drawings, Cummins was at all times solely

responsible for incorporating the Ashbrook SBR as specified in the Contract

Documents. In that context, Section 11.01.B.3 mandated: “[T]o the extent that [the

Ashbrook SBR’s] proper incorporation into the Work require[d] changes to the

structural, piping, mechanical, electrical, instrumentation, or any other changes of

whatsoever nature, [Cummins was] responsible for” exercising its (or Ashbrook’s)

ingenuity anticipating and identifying changes necessary to make the Ashbrook SBR

and the connecting systems work as required by the Contract Documents, designing

or at the very least making GF aware of such changes and/or working with GF to

incorporate them, and ultimately guaranteeing an operational SBR system in

accordance with the Contract Documents, all at Cummins’ expense. Section

11.01.B.3 (R.R. at 137a) (emphasis added). The Contract expressly shifted to the

contractor the responsibility and risk for “changes of whatsoever nature,” Section

28

11.01.B.3, for a contractor to incorporate a different SBR and/or equipment into GF’s

design.20 Thus, this Court concludes that Section 11.01.B.3 is not ambiguous.

To the extent that Section 11.01.B.3 was “the [C]ontract clause most

exemplary of the dispute,” Trial Ct. June 27, 2019 Op. at 4 (R.R. at 5497a), and this

Court has ruled, based upon its extensive review of the Contract Documents, that

Section 11.01.B.3 is not ambiguous, the trial court erred by concluding that the entire

Contract was ambiguous. The trial court should have determined as a matter of law,

before allowing Cummins to proceed with its case-in-chief and relying on Cummins’

evidence to reach its conclusion, that the Contract placed sole responsibility on

Cummins for defective system performance related to its Ashbrook SBR.21 By

failing to do so, the trial court erred by allowing the jury to interpret the Contract

language based on extrinsic evidence. Accordingly, the trial court’s June 27, 2019

order denying the Authority’s Motion must be reversed.

b. Change Orders/Extra Work

The Authority also argues that the trial court erred as a matter of law and

abused its discretion by allowing the jury to decide Cummins’ claims for certain

20

Otherwise, the Authority and, by extension, the public would have borne the cost to have

GF design in advance for at least three potential SBRs and the myriad of configurations and

connectivity that a bidder may have included in its bid. Because the Contract did not expressly

prohibit bids proposing SBRs other than the ABJ Sanitaire, Ashbrook and Aqua Aerobics, based on

Cummins’ logic, the Authority would have to have paid GF to design the system to accommodate

the configuration and operability of every potential SBR system. Cummins’ interpretation was not

intended in the Contract, and is against public policy, as it would not protect taxpayer funds.

Hanisco.

21

In light of this Court’s holding that Section 11.01.B.3 is unambiguous, the Authority’s

interpretation of Section 11.01.B.3 was reasonable. Therefore, the Authority’s withholding of the

Contract balance due to its belief that Cummins was contractually responsible for the gate

overflows was not in bad faith. Accordingly, this Court need not further analyze that issue in this

appeal.

29

change orders when those claims were barred by the Contract terms and undisputed

evidence.

In its Motion, the Authority claimed:

12. For the same reason, the [trial c]ourt erred in failing to

enter judgment on liability for [the Authority] on [the

Authority’s] own SBR-related claims. Because [Section]

11.01[.]B imposed sole contractual responsibility on

[Cummins], [Cummins] was liable for [the Authority’s]

SBR-related damages.

13. In addition, the [trial c]ourt erred as a matter of law in

permitting the jury to decide [Cummins’] extra work claims

relating to survey and control (No. 1), re-routing the sewer

line (No. 3), removal and replacement of the roof of the UV

plant to install the UV equipment (No. 19), and topsoil (No.

58) because the Contract Documents barred those claims

based on [Cummins’] prior execution of change orders.

(Ex. D-2 at pp. 186-187) ([Project Manual (]PM[)],

[General Conditions (]GC[)], 00700-64/65 at Art. 12.01(E),

(F))[.]

14. The [trial c]ourt erred as a matter of law in allowing the

jury to decide [Cummins’] extra work claim related to

communication (No. 30) as [Cummins] bore sole

contractual responsibility for the work described in the

claim. (Ex. P-3) (Agreement, Art. 1.01, 4.04(A), (B), 9.01);

(Ex. D-2) (PM, GC, 00700 at Art. 6.01(A); GC, 00700 at

Art. 6.03(A); GC, 00700 at Art. 6.06(E); GC, 00700 at Art.

6.13(A), (D), (E); GC, 00700 at Art. 6.19(C); GC, 00700 at

Art. 7.02(A); GC, 00700 at Art. 8.08(A))[.]

15. The [trial c]ourt erred as a matter of law in allowing the

jury to decide [Cummins’] extra work claims relating to

painting (Nos. 111-115) and additional painting because the

contract required [Cummins] to paint the exposed interior

concrete and masonry walls in Headworks No. 2 and

because [Cummins’] execution of change orders relating to

painting pipes barred [Cummins’] request for additional

compensation. (Ex. P-3) (Agreement, Art. 1.01(A)); (Ex.

D-2) (PM, § 01311 [] ¶1.03(D)(2)(g); § 09900 [] ¶¶1.09(B),

2.02(E)(1), (2), 3.02(J), 3.09(B), (C); GC, 00700 at Art.

3.01(A); GC, 00700 at Art. 12.01(E), (F))[.]

30

16. The [trial c]ourt erred as a matter of law in failing to

enter judgment for [the Authority] and in allowing the jury

to decide [Cummins’] extra work claim relating to

[Cummins’] pump entering the bar screen in Headworks

No. 1 (No. 41) because the Contract imposed sole liability

on [Cummins] for [Cummins’] use of its own equipment

and any damage associated with that use. (Ex. P-3)

(Agreement, Art. 9.01); (Ex. D-2) (PM, GC, 00700 at Art.

6.13(A), (D), (E); GC, 00700 at Art. 6.21(A))[.]

17. The [trial c]ourt erred as a matter of law in failing to

enter judgment for [the Authority] and in allowing the jury

to decide [Cummins’] extra work claim relating to the SBR

blower repair costs (Nos. 109, 116, 119, 120, 121) because

the Contract Documents imposed all liability on [Cummins]

for damage to equipment and because [Cummins] already

paid for that damage. (Ex. D-2) (PM, GC, 00700 at Art.

6.11(A), (B)(1)(a); GC, 00700 at Art. 10.05(A)(1), (F); GC,

00700 at Art. 12.01(G); § 01660 [] ¶¶1.02(A), 1.07)[.]

18. The [trial c]ourt erred as a matter of law in failing to

enter judgment for [the Authority] and in allowing the jury

to decide [Cummins’] claim for consequential damages

based on the sale of Florida real estate. [The Authority]

filed a pretrial motion in limine to preclude that evidence

and also sought judgment in its Nonsuit Motions.

[Cummins] argued that it was entitled to several hundred

thousand dollars, which sale was necessary (according to

Bob Cummins) as a result of the failure to release the

Contract balance. The jury initially awarded $75,000 on the

verdict sheet and then changed its verdict to $0. However,

that evidence reinforced [Cummins’] claim to the jury that

he was severely harmed by the non-release of the contract

balance and affected the outcome on both the bad faith

claim and the extra work claims, as evidenced by the jury’s

initial award of consequential damages. The evidence also

did not support a finding that [the Authority’s] withholding

of the Contract balance was the factual cause of the sale

inasmuch as [Cummins] acknowledged that he had another

major financial hardship relating to the East Branch Dam

project and purchasing equipment for his newly-formed

concrete company.

Authority Motion at 5-6 (R.R. at 2906a-2907a).

31

The trial court did not specifically address or mention its interpretation

of any Contract change order or extra work provisions or any ambiguity related

thereto in its June 27, 2019 order denying the Authority’s Motion. In its 1925(a)

Opinion, the trial court merely stated:

[The Authority’s] Twelfth, Thirteenth, Fourteenth, Fifteenth,

Sixteenth, Seventeenth, and Eighteenth points of appeal are

again all based upon contract interpretation. [This trial c]ourt

has ruled that the [C]ontract was ambiguous and it can

reasonably be inferred from the [j]ury’s verdict that [it]

agreed. [The Authority’s] arguments must now fail as they

have before.

Trial Ct. 1925(a) Op. at 9 (R.R. at 5489a). Because the trial court’s only basis for

denying the Authority’s Motion relative to the change order and extra work claims was

that the Contract was ambiguous, and this Court has ruled that the Contract was not

ambiguous, the trial court’s June 27, 2019 order denying the Authority’s Motion must

be reversed.

2. Cummins’ Motion

In light of this Court’s ruling that the trial court erred by denying the

Authority’s Motion, and allowing the matter to proceed to a jury trial on the basis of

contract ambiguity, the trial court’s order granting in part and denying in part Cummins’

Motion to mold the jury’s verdict for interest, penalty interest and attorney’s fees is

moot and must be vacated.

Conclusion

Based on the foregoing, the trial court’s June 27, 2019 order denying the

Authority’s Motion seeking JNOV or a new trial is reversed, and this matter is

remanded for the trial court to determine whether, in light of this Court’s ruling, any

issues remain. If there remain no outstanding issues, then the trial court is to grant

32

the Authority’s Motion for JNOV; however, if there are outstanding issues, then the

trial court is to grant the Authority’s Motion for a new trial. The trial court’s June 27,

2019 order denying in part Cummins’ Motion is vacated.

___________________________

ANNE E. COVEY, Judge

33

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Robert J. Cummins, d/b/a Bob :

Cummins Construction Company :

:

v. :

:

Bradford Sanitary Authority, : No. 1000 C.D. 2019

Appellant :

:

Robert J. Cummins, d/b/a Bob :

Cummins Construction Company, :

Appellant :

:

v. :

: No. 1009 C.D. 2019

Bradford Sanitary Authority :

ORDER

AND NOW, this 8th day of June, 2020, the McKean County Common

Pleas Court’s (trial court) June 27, 2019 order denying the Bradford Sanitary

Authority’s (Authority) Motion for Post-trial Relief is REVERSED, and this matter is

REMANDED to the trial court to determine whether, in light of this Court’s ruling,

the Authority shall be granted a judgment notwithstanding the verdict or a new trial.

The trial court’s June 27, 2019 order denying in part Robert J. Cummins

d/b/a Bob Cummins Construction Company’s Motion to Mold the Verdict for

Interest, Penalty Interest and Attorney’s Fees is VACATED.

Jurisdiction is relinquished.

___________________________

ANNE E. COVEY, Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.