Opinion

Wayco Sand and Gravel v. DEP & P. Karnick

Court
Commonwealth Court of Pennsylvania
Filed
Jan 6, 2020
Status
Unpublished
On the bench
Wojcik, J.
Cited by
0 cases
Authority
More cited than 10.0%

holding that the owner of public water systems waived its right to challenge EHB’s finding that it had committed violations of the Pennsylvania Safe Drinking Water Act13 because it did not contest those violations in its post-hearing brief

How later courts described this case

  • holding that the owner of public water systems waived its right to challenge EHB’s finding that it had committed violations of the Pennsylvania Safe Drinking Water Act13 because it did not contest those violations in its post-hearing brief

Written by the judges who cited it.

The opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Wayco Sand and Gravel, :

:

Petitioner :

:

v. : No. 713 C.D. 2018

: Submitted: March 22, 2019

Department of Environmental :

Protection and Peter Karnick, :

:

Respondents :

BEFORE: HONORABLE RENÉE COHN JUBELIRER, Judge

HONORABLE ROBERT SIMPSON, Judge1

HONORABLE MICHAEL H. WOJCIK, Judge

OPINION NOT REPORTED

MEMORANDUM OPINION

BY JUDGE WOJCIK FILED: January 6, 2020

Wayco Sand and Gravel (Wayco) petitions for review of the order of

the Environmental Hearing Board (EHB) sustaining Peter Karnick’s (Landowner)

appeal from the Department of Environmental Protection’s (DEP) approval of the

Stage I and II bond release to Wayco for the permitted area of Landowner’s

property. We affirm.

Wayco is in the business of asphalt paving and conducts surface

mining of sand and gravel. In July 1994, Wayco was issued a noncoal surface

mining permit to conduct operations on a 7.6-acre portion of Landowner’s property

1

This matter was assigned to this panel before September 1, 2019, when Judge Simpson

assumed the status of senior judge and was decided before Judge Simpson's service on the Court

ended on December 31, 2019.

in Waymart, Pennsylvania, identified as Parcel 13 on Module 15 (the Site). See

Reproduced Record (R.R.) at 117, 120, 848-62. Mining support activities occurred

on the Site that included the processing of sand and gravel, but no mining or

extraction of minerals occurred there and there were no pits or highwalls on the

Site. The Site was previously mined for sand and gravel and was reclaimed before

Wayco and Landowner entered into a 10-year lease for Wayco to use it for

processing minerals that had been extracted from other sites.

As part of the processing operations, Wayco constructed several

ponds or impoundments on the Site, including two large silt or sedimentation

ponds or basins (silt ponds). See R.R. at 252-54, 890. There are drainage

problems associated with the continued presence of the silt ponds on the Site

affecting drainage patterns and preventing adequate drainage. See id. at 252-54.

Wayco’s attempts to improve the draining problems associated with its decision to

leave the silt ponds on the Site have not eliminated the drainage problems. See id.

at 261.

Section 17.1 of Module 17, relating to Post-mining Use and

Reclamation, states that “the present land use is forestland with a portion as

pastureland,” that the “[a]ffected areas will be restored to forestland,” and that the

“[Approximate Original Contour (AOC)2] will be restored during reclamation.”

2

Section 3 of the Noncoal Surface Mining Conservation and Reclamation Act (Act), Act

of December 19, 1984, P.L. 1093, as amended, 52 P.S. §3303, defines AOC as “[c]ontouring as

defined in this act” which, in turn, is defined as:

Reclamation of the land affected to [AOC] so that it closely

resembles the general surface configuration of the land prior to

mining and blends into and complements the drainage pattern of

the surrounding terrain with no highwall, spoil piles or depressions

to accumulate water and with adequate provisions for drainage.

(Footnote continued on next page…)

2

R.R. at 905. Section 17.2 states, “The [S]ite will be restored to AOC by regrading.

Positive drainage will be produced and forestland restored. Reclamation will

increase the amount of forestland on the permit area.” Id.

On November 26, 2014, DEP informed Landowner that Wayco had

applied for a Stage I and II bond release of liability on the permit and that an

inspection would be scheduled “to evaluate the adequacy of the reclamation work

performed.” R.R. at 919.3 On July 1, 2016, DEP sent Landowner a letter stating

(continued…)

See also Section 77.1 of DEP’s regulations, 25 Pa. Code §77.1 (same). Additionally, Section

77.1 of DEP’s regulations defines “reclamation” as “[a]ctions taken to reclaim the area affected

by surface mining activities as required by this chapter.” Id.

3

Section 77.242(a) of DEP’s regulations sets forth the procedure for seeking a Stage I

and II bond release stating, in relevant part:

(a) Release of bond. The permittee may file an application with

[DEP] for release of all or part of the bond liability applicable to a

permit or designated phase of a permit area after reclamation,

restoration and abatement work in a reclamation stage, as defined

in §77.243 (relating to criteria and schedule for release of bond),

has been completed on the permit area or designated phase of a

permit area, subject to the following conditions:

(1) Applications may be filed only at times or seasons that allow

[DEP] to properly evaluate the reclamation operations reported to

have been completed.

(2) Within 60 days after filing the application for release, the

permittee shall submit proof of publication of the advertisement [of

the filing of the application in a newspaper of general circulation in

the locality of the permit area as] required by subsection (b).

25 Pa. Code §77.242(a).

(Footnote continued on next page…)

3

(continued…)

Section 77.243(b)(1), (2) and (c) sets forth the standards governing the bond release:

(b) For the purposes of this section the following apply:

(1) Reclamation Stage I shall be deemed to have been completed

when:

(i) The permittee completes backfilling, regrading and

drainage control in accordance with the approved

reclamation plan.

(ii) Topsoil has been replaced and revegetation has been

established in accordance with the approved reclamation

plan and the standards for the success of revegetation are

met.

(iii) The lands have been stabilized to prevent accelerated

erosion and sedimentation under Chapter 102 (relating to

erosion control).

(iv) The permittee has successfully completed mining and

reclamation operations in accordance with the approved

reclamation plan, so that the land is capable of supporting

post-mining land use approved under §77.653 (relating to

post-mining land use).

(v) The permittee has achieved compliance with the

requirements of the environmental acts, this chapter and the

conditions of the permits.

(2) Reclamation Stage II shall be deemed to be complete when

the applicable liability period under §77.204 (relating to period of

liability) has expired.

(c) [DEP] will not release a bond amount deposited . . . if the

release would reduce the total remaining amount of bond to an

amount which would be insufficient for [DEP] to complete

reclamation and to take measures that may be necessary to prevent

adverse effects upon the environment or public health, safety or

(Footnote continued on next page…)

4

that following a field inspection “to evaluate the adequacy of the reclamation work

performed and the success standards of the vegetation that has been planted,” DEP

intended to release the bond posted on the site based on its determination that “the

reclamation work performed and revegetation success of the [S]ite meets the

requirements contained in the mine permit and [DEP’s] rules and regulations[.]”

Id. at 921. On July 21, 2016, DEP released Wayco’s bond. Id. at 923.

On August 10, 2016, Landowner appealed DEP’s release of Wayco’s

bond alleging, inter alia, that the Site “was not reclaimed to where [h]e could use

it” because the “silt ponds are 5 to 8 [feet] deep with swamp grass and willows”

and that the “dams on the silt ponds are keeping [the] ponds from drying out.”

R.R. at 1. Landowner also asserted that DEP had not classified the Site as

“wetlands,” and that it is now overgrown “with swamp grass [and] weeds and it’s

to[o] rough to farm.” Id. In sum, Landowner stated, “All I want is [the] land

(continued…)

welfare under the environmental acts, the [A]ct, this chapter, the

terms and conditions of the permits and order of [DEP].

25 Pa. Code §77.243(b)(1) and (2), (c).

In turn, Section 77.204(a) states:

(a) Liability under bonds posted for a noncoal mining activity

shall continue for the duration of the mining activities and its

reclamation as provided in the act, this chapter and the conditions

of the permit for 5 years after completion of the mining and

reclamation of the area, unless released in whole or in part prior

thereto if [DEP] is satisfied that the reclamation covered by the

bond has been accomplished as required by the act.

25 Pa. Code §77.204(a).

5

reclaimed so [I] can use it again without getting stuck in [the] silt ponds [that]

Wayco created.” Id.

On September 13, 2016, DEP sent Landowner a letter that stated the

following, in relevant part:

On June 28, 2016, a field inspection was conducted at the

[S]ite to evaluate the adequacy of the reclamation work

performed and the success standards of the vegetation

that had been planted. You were present at the

inspection.

During this inspection you expressed concerns and/or

objections to: 1) grading[4] of the out slopes[5] of the

former sedimentation ponds; 2) stability of surface of the

former sedimentation ponds; 3) former sedimentation

ponds still holding water; 4) revegetation of the upper

area above the access road; 5) amount of rent payment

that Wayco was to pay you; and 6) verbal agreements

made with Wayco and you and that were not honored.

Your concerns are addressed below, respectively:

1. Grading of the out slopes of the former sedimentation

ponds:

[DEP] determined that Wayco graded the out slopes of

the former sedimentation ponds to approximately an 18°

slope, which is less than the 35° reclamation slope

required by the rules and regulations of [DEP] under 25

4

“Grade” is defined, inter alia, as “a rate of ascent or descent,” or the “deviation from a

level surface to a inclined plane stated as so many feet per mile . . . or as one foot rise or fall in

so many feet of horizontal distance . . . or as so much in a hundred feet or as a percentage of

horizontal distance.” Webster’s Third New International Dictionary 985 (1986).

5

“Slope” is defined, inter alia, as “ground whose surface forms an angle with the plane

of the horizon : a natural or artificial incline (as a hillside or terrace)” or the “upward or

downward slant or inclination : degree or extent of deviation from the horizontal or

perpendicular.” Webster’s Third New International Dictionary 2145 (1986).

6

Pa. Code §77.594.[6] The grading is also consistent with

the [AOC] of the surrounding landscape.

2. Stability of surface of the former sedimentation

ponds:

[DEP] determined that Wayco stabilized the surface of

the former sedimentation ponds by digging two drainage

ditches from each pond and filling the drainage ditches

with rock to ensure that no water would be retained by

the former sedimentation ponds. The trenching was

initiated in June 2013 and was completed by October

2013. Once this trenching was completed, material was

pushed from the out slopes of the ponds to cover and

stabilize the surface of the ponds. Since October 2013,

[DEP] has been monitoring and evaluating the stability of

the former sedimentation ponds. After this length of time

monitoring and evaluating the stability of the former

sedimentation ponds, [DEP] determined that the former

sedimentation ponds are stabilized. In addition, [DEP]

has driven its vehicle on the reclaimed areas, including

the former sedimentation ponds, without sinking in or

getting stuck.

3. Former sedimentation ponds still holding water:

Wayco dug two drainage ditches from each

sedimentation pond and filled the drainage ditches with

rock to ensure that no water would be retained by the

6

Section 77.594(2) of DEP’s regulations provides, in pertinent part, “If terracing is

approved for post-mining reclamation, the final overall slope shall be 35° or less unless

otherwise approved under subparagraph (v).” 25 Pa. Code §77.594(2). In turn, Section 3 of the

Act defines “terracing” as follows:

Grading where the steepest contour of the highwall is not greater

than 35[°] from the horizontal, with the table portion of the restored

area a flat terrace without depressions to hold water and with

adequate provision for drainage, unless otherwise approved by

[DEP].

52 P.S. §3303.

7

former sedimentation ponds. Since October 2013, [DEP]

has been monitoring and evaluating the stability of the

former sedimentation ponds. After this length of time

monitoring and evaluating the stability of the former

sedimentation ponds, [DEP] determined that the former

sedimentation [ponds] are stabilized.

4. Revegetation of the upper area above the access road:

Wayco revegetated the upper area above the access road

as directed by [DEP] in July 2015, to address your

concerns. Although, at the time, this upper area met

[DEP] standards for successful revegetation under 25

Pa. Code §77.618.[7]

R.R. at 925-26.

7

Section 77.618(b)(1), (2) and (3) of DEP’s regulations states:

(1) The standards for successful revegetation shall be determined

by ground cover.

(2) The approved standard shall be the percent ground cover of

the vegetation which exists on the proposed area to be affected by

surface mining activities. [DEP] will not approve less than a

minimum of 70% ground cover of permanent plant species with

not more than 1% of the area having less than 30% ground cover

with no single or contiguous area having less than 30% ground

cover exceeding 3000 square feet. When woody species are

planted in mixture with herbaceous species, these standards shall

be met and a minimum of 400 woody plants per acre shall be

established unless alternate plans are approved or required by

[DEP]. On slopes greater than 20[°], the minimum number of

woody plants shall be 600 per acre.

(3) The percent of ground cover of the mined area shall meet the

standards of paragraph (2) to qualify for Reclamation Stage I and

Reclamation Stage II approval.

25 Pa. Code §618(b)(1), (2) and (3).

8

With respect to Landowner’s concerns regarding the amount of rent

that Wayco was to pay and the verbal agreements with Wayco that were not

honored, DEP explained that it “has no authority to enforce any lease agreement

and/or rent or royalty payment between the landowner and the permittee,” and “no

authority to enforce any verbal agreements that were discussed between the

landowner and the permittee.” R.R. at 926. As a result, DEP again notified

Landowner “that the bond for the permitted site was eligible for release” and that

“[t]he issued bond release materials [were] available for review at [its] Pottsville

District Office.” Id. at 927.

On October 11, 2016, Landowner appealed DEP’s decision to EHB,

summarizing his objection to the bond release as follows:

I had leased the property to Wayco Inc. for the purpose

of processing the sand and gravel. [It] operated the[]

plant there for 15 years with the agreement that [it]

would reclaim the property to an “as good or better”

condition than what it was. [It] built two large silt ponds

which held the[] waste material. The dams for these

ponds are still present, along with all of the waste

material. These dams are too steep to drive farm

equipment on, and during wet seasons, you cannot drive

onto the waste-filled ponds. I am not asking for Wayco

to remove all of the waste material, but to simply grade

the dams down to an even slope, allow the waste material

to dry out, and allow my property to be useful again.

This farm has been in the family for close to 100 years,

and I just would like it to be put back into a condition

that would make it suitable for future generations.

R.R. at 8.

Before EHB, DEP Surface Mine Conservation Inspector Gary Harper

was qualified as an expert in noncoal surface mining reclamation. R.R. at 112.

With respect to the reclamation of the Site, he testified that Section 77.592 of

9

DEP’s regulations “covers [AOC],” and that “AOC means you are approximating

what was there to begin with [a]nd if you can look at it and it seems to blend in

[with] the landscape . . . and it looks a lot like the original landscape . . . it’s

reclaimed to AOC.” R.R. at 107-08. Harper stated that the steepest slope at the

Site in April 2012, after the first regrading was 30°, but that the average slope after

a subsequent regrading was around 12° to 16° in October 2012, with one slope

measuring 18.75°. Id. at 144-45, 147-48, 151. He testified that Wayco’s permit

provides that the Site should be returned to AOC and that the permit also allows

35° terracing based on the applicable DEP regulations. Id. at 170-71. He stated

that the Site was reclaimed to AOC except where Landowner asked for a terrace

“by his barn,” that terracing could include AOC and those portions of the Site that

were terraced, and that Wayco was permitted to terrace the Site and indicated

terracing on a completion report. Id. at 174-175, 176, 177-78.

Harper conceded that a soil test was required by one of the modules,

but that Wayco did not submit one and that Module 15 stated that “the [S]ite will

be reclaimed to AOC.” R.R. at 182-83, 185. He acknowledged that the permit

states that the Site had slopes ranging from 12% at the highest elevations to 1% at

the lowest and estimated that the final average slope was 8° or 9°, but that DEP did

not measure the final slopes after reclamation. Id. at 186, 188. Harper also

acknowledged that he did not know whether DEP applied a 35° terracing or an

AOC standard when it approved the bond release and that the 35° standard applies

to AOC, but he did not know where that could be found in the regulations. Id. at

196-97, 312.

EHB also qualified DEP Surface Mine Conservation Inspection

Supervisor Gary Latsha as an expert in noncoal surface mining reclamation. R.R.

10

at 207.8 Regarding the reclamation of the Site, Latsha testified that it was

reclaimed to AOC even though the Completion Report indicates that there was a

35° terrace reclamation. Id. at 207-08. He stated that Module 15 states that the

entire Site would be reclaimed to AOC and that Module 17 states that AOC would

be restored through regrading, the reduction of positive drainage, and the

restoration of forestland. Id. at 208-09, 210-11. He testified that although the Site

was reclaimed to AOC, any terracing that was done occurred at the south end of

the Site and that soil reports should have been submitted, but they were not. Id. at

216, 222.

Latsha conceded that he had no knowledge of the specifics of a DEP

October 18, 2012 Inspection Report, which recommended that the dams at the Site

be torn down to 8 to 10 feet and that the land be regraded over the silt ponds even

though the report was sent to his attention. R.R. at 224-26. He testified that he

generally agreed that the slopes on the Site should be cut down, that he did not

recall a specific number, and that Wayco cut down the slopes even though DEP did

not require it to do so. Id. at 225, 227. He stated that DEP would not allow slopes

in excess of 35° and that 35° slopes “also applied to [AOC],” but that he did not

“necessarily know that it applies to [AOC] because [they were] trying to . . . blend

the area into the surrounding area” so that “[t]here may be parts that are a little

steeper” and “parts that are shallower.” Id. at 239.

8

EHB also qualified Jeff Weinberger, a Wayco employee working in engineering,

estimating, and permit managing, as an expert professional engineer in noncoal mining

reclamation. R.R. at 320-21. He testified, in relevant part, that the Site was returned to the 70%

minimum permanent plant species revegetation standard, and the 30% non-revegetation standard,

of property other than cropland as provided in Section 77.618(b) of DEP’s regulations, 25

Pa. Code §77.618(b).

11

Based on Landowner’s, Harper’s, and Latsha’s testimony, and the

related exhibits, EHB found that “[t]he problem with reclamation on the Site in

achieving AOC was excess material in the form of silt ponds,” and “[t]he silt ponds

on the Site grew over time as Wayco processed more materials from more sites

where minerals were extracted” so that “[a]s more materials were processed in the

silt ponds, more processing waste was left on the Site.” R.R. at 1177. EHB found

that “[w]hen Wayco mined the adjoining Andrews property, [it] placed excess

material on the Site, and the final reclamation of the Site had to account for that

excess material,” so “[a] terrace was done on a part of the Site and AOC was done

on the rest of it.” Id. EHB found that “[d]espite Wayco’s efforts to regrade the silt

ponds and to reduce the final slopes of the edges of the silt ponds, the silt ponds

remain in place on the Site,” and that “they still contain substantial amounts of silt

and other waste materials from Wayco’s long term processing operations on the

Site.” Id. at 1178.

EHB summarized Landowner’s argument on appeal as “Wayco never

returned his property to its [AOC] and instead employed terracing in its

reclamation efforts, in addition to leaving behind sedimentation ponds lacking in

proper drainage.” R.R. at 1179. With respect to DEP’s and Wayco’s claims on

appeal, EHB characterized them as the “telling of two stories,” initially asserting

that terracing, including a 35° final slope requirement, was an alternative to AOC,

and then later conflating the separate and distinct AOC and terracing statutory and

regulatory standards for reclamation in the proceedings. Id. at 1183, 1187.9

9

As EHB explained:

It is apparent to [EHB] that Wayco and [DEP] had

something of an epiphany following [EHB’s] explanation of the

(Footnote continued on next page…)

12

EHB determined that, “[i]n general, Sections 77.592 and 77.593

provide for reclamation to return a site to [AOC] unless [DEP] approves alternative

reclamation to contouring. 25 Pa. Code §§77.592-593.” R.R. at 1182 (footnote

omitted). However, “[i]f there is sufficient material to achieve AOC, and no

alternative is approved under Section 77.593, Section 77.594(1) requires that the

final slopes approximate the general nature of pre-mining topography. 52 P.S.

§3303; 25 Pa. Code §77.594(1).” Id. at 1182-83.

Quoting Section 77.1 of DEP’s regulations, EHB explained that

“AOC is defined as ‘[r]eclamation of land affected to approximate original contour

so that it closely resembles the general surface configuration of the land prior to

mining and blends into and complements the drainage pattern of the surrounding

terrain with no highwall, spoil piles or depressions to accumulate water and with

adequate provision for drainage.’ 25 Pa. Code §77.1.” R.R. at 1205. Quoting

Section 77.591 of DEP’s regulations, EHB noted that “‘[a]reas disturbed . . . shall

be reclaimed by contouring, except terracing may be utilized if the operator

(continued…)

regulatory requirements governing the terracing alternative to

AOC and the related 35[°] final slope requirement. At the hearing,

[DEP] and Wayco more or less abandoned their joint position that

the mining permit allowed the terracing alternative for the

reclamation of the Site and the availability of the 35[°] final slope

requirement. [DEP] and Wayco shifted their positions at the

hearing and only asserted that the final reclamation of

[Landowner’s] property met the applicable AOC requirement. The

complete record before [EHB] establishes that this belated

argument was not the reason that [DEP] and Wayco gave

[Landowner] when [DEP] granted Wayco’s application for bond

release in 201[6].

R.R. at 1185 (footnote omitted).

13

demonstrates that the operation has extracted quantities of minerals so that

contouring cannot be achieved with the remaining overburden and waste material.’

25 Pa. Code §77.591.” Id. at 1204.

EHB stated that the only “two situations where an alternative form of

reclamation to [AOC] may be used” are “where the applicant demonstrates ‘that

the proposed operation will be carried out over a substantial period of time and that

the volume of mineral to be removed is large compared to the overburden to

restore the area to [AOC],’” pursuant to Section 77.593(1) of DEP’s regulations,

and where the foregoing requirements “are not met and the applicant ‘demonstrates

that the operation will either restore the land affected to a condition capable of

supporting the uses it was capable of supporting prior to mining or to a higher or

better use,’” under Section 77.593(2). R.R. at 1204-05.

EHB concluded that “AOC was the correct reclamation standard to

apply to the Site, because the site was never mined and used only for processing

operations by [Wayco]. 25 Pa. Code §77.591,” and that “[t]he 35[°] final slope

requirement is a requirement related to the terracing alternative to AOC and it is

not part of the AOC reclamation standard. 25 Pa. Code §§77.592-594.” R.R. at

1205. EHB also concluded that “Wayco’s reclamation of [Landowner’s] property

did not meet the AOC reclamation standard. 52 P.S. §3303; 25 Pa. Code §77.1[10]”;

10

In this regard, EHB “[did] not find the testimony of [DEP’s] and Wayco’s multiple

expert witnesses that Wayco’s reclamation of the Site achieved AOC to be credible.” R.R. at

1199. Specifically, EHB explained:

Regardless of the fact that [Landowner] did not present expert

witnesses, we find that the testimony of the multiple expert

witnesses proffered by [DEP] and [Wayco] was not credible and

leaves us unconvinced as to the legal basis for [DEP’s] approval of

Stage I and II bond release. The expert witness testimony was

(Footnote continued on next page…)

14

“[t]he terracing alternative to AOC and the related 35[°] final slope requirement is

not applicable to the reclamation of [Landowner’s] property because no mineral

extraction occurred on [Landowner’s] property and there were sufficient materials

to achieve AOC. 25 Pa. Code §§77.591-594”; and “[n]either of the two situations

where an alternative form of reclamation to AOC applies in this appeal. 25

Pa. Code §77.593.” Id.

(continued…)

clearly self-serving statements that ignored key facts and was

based on a fundamental misunderstanding of AOC requirements.

Id. at 1200.

Rather, EHB determined that

[Landowner’s] testimony regarding the state of his property prior

to Wayco’s processing operations on the Site as compared with the

state of his property after Wayco left to be compelling. Put

another way, [Landowner] convinced [EHB] that his property was

not returned to AOC, which is what [DEP] and Wayco insisted had

been done. [Landowner] described the still present silt ponds on

his property, which had not existed prior to Wayco’s use of the

Site for processing operations: “[T]he biggest concern is the silt in

the silt pond [. . .]. I’d say maybe it’s eight, ten, or maybe even

deeper feet deep. And I see no way that they can ever be dried out

unless they got exposed to the air.” [R.R. at 253]. According to

[Landowner’s] testimony, the silt ponds are unsafe due to being

steep and saturated. [Id. at 253-254]. Further, [Landowner] “kind

of figured if a guy uses your property for 15 years, he could put it

back where it was” and this was not done, as water is trapped in

the silt ponds and the silt is still in them. [Id. at 256, 261]. Taken

together, [EHB] finds these statements to be compelling support

for Wayco having failed to return the Site to AOC.

Id. at 1200-01 (footnote omitted).

15

As a result, EHB concluded that “[t]he requirements of Stage I and

Stage II bond release, found in Section 243, subsection (b)(1) and (2), of Chapter

77 were not met because backfilling and regrading were not done in accordance

with the law,” so that “[DEP’s] approval of the Stage I and II bond release was

unreasonable, an abuse of discretion, and not in accordance with the facts or law.”

R.R. at 1205-06. Accordingly, EHB issued an order sustaining Landowner’s

appeal and vacating DEP’s approval of Wayco’s application for bond release. Id.

at 1207. Wayco then filed the instant appeal.11

11

As this Court has explained:

Our appellate review of [EHB’s] adjudications is limited to

determining whether [EHB] committed an error of law, violated

constitutional rights, or whether its material findings of fact are

supported by substantial evidence. On issues of law, our standard

of review is de novo and our scope of review is plenary.

In determining whether substantial evidence of record

exists to support a material factual finding, we view the record in

the light most favorable to the prevailing party below, giving that

party the benefit of all reasonable inferences that can be drawn

from the record evidence. Substantial evidence is such “relevant

evidence upon which a reasonable mind could base a conclusion.”

Resolution of evidentiary conflict, witness credibility, and

evidentiary weight are matters committed to the discretion of

[EHB]. “It is irrelevant whether the record contains evidence that

would support contrary findings. Our critical inquiry is whether

the findings are supported by substantial evidence.”

EQT Production Company v. Department of Environmental Protection, 193 A.3d 1137, 1148-49

(Pa. Cmwlth. 2018) (citations omitted).

16

I.

On appeal,12 Wayco first claims that EHB erred in permitting

Landowner’s son to participate in the hearings as legal counsel because he is not a

licensed attorney. Wayco also asserts that Landowner may not object to the bond

release because he failed to exhaust his administrative remedies with respect to the

issuance of the initial permit. However, Wayco failed to preserve these issues for

our review by not raising them in its post-hearing brief filed with EHB. See R.R.

at 1123. See also Section 1021.131(c) of EHB’s regulations, 25 Pa. Code

§1021.131(c) (“An issue which is not argued in a post[-]hearing brief may be

waived.”); Pa. R.A.P. 1551(a) (“No question shall be heard or considered by the

court which was not raised before the government unit[.]”); Wilbar Realty, Inc. v.

Department of Environmental Resources, 663 A.2d 857, 861 (Pa. Cmwlth. 1995)

(holding that the owner of public water systems waived its right to challenge

EHB’s finding that it had committed violations of the Pennsylvania Safe Drinking

Water Act13 because it did not contest those violations in its post-hearing brief).

II.

Wayco next claims that EHB erred in overruling its hearsay objection

to Landowner’s admission of a letter from the Soil Conservation District and in

considering the contents of the letter for the truth of the matters asserted therein.

R.R. at 86.14 However, our review of EHB’s Adjudication filed in support of its

12

We consolidate and reorder Wayco’s claims on appeal in the interest of clarity.

13

Act of May 1, 1984, P.L. 43, 35 P.S. §§721.1–721.17.

14

“Although not bound by the technical rules of evidence, [EHB] generally adheres to

the Pennsylvania Rules of Evidence in its formal proceedings. See 25 Pa. Code §1021.123(a)

(Footnote continued on next page…)

17

order sustaining Landowner’s appeal of DEP’s approval of the bond release

demonstrates that the letter was not relied upon by EHB in disposing of the appeal,

see R.R. at 1163-1206, and Wayco does not direct this Court to the portion of the

Adjudication in which EHB erroneously relied upon the letter. As a result, any

purported error in this regard is harmless15 and will not serve as a basis upon which

this Court will disturb EHB’s order in this matter. Likewise, EHB did not commit

reversible error by failing to exclude testimony by Landowner with respect to a

purported oral lease as Wayco does not direct this Court to the portion of the

Adjudication in which EHB relied on this testimony so that any purported error in

this regard is also harmless.

III.

Wayco next claims that EHB erred in determining that Landowner

sustained his burden of proof in establishing that the Site was not returned to AOC

as required by the statutory and regulatory standards for reclamation of the Site

prior to the Stage I and II bond release of liability on the permits. Specifically,

Wayco contends that Landowner was required to present expert testimony in order

to sustain his burden of proof in this regard.

(continued…)

[(“[EHB] is not bound by technical rules of evidence and relevant and material evidence of

reasonable probative value is admissible. [EHB] generally applies the Pennsylvania Rules of

Evidence.”)].” EQT Production Company, 193 A.3d at 1154.

15

To constitute reversible error, an administrative evidentiary ruling must not only be

erroneous, but also harmful or prejudicial to the complaining party. An order of an

administrative agency will not be disturbed based on harmless error. Lock v. City of

Philadelphia, 895 A.2d 660, 669 (Pa. Cmwlth. 2006); Pennsylvania Game Commission v.

Bowman, 474 A.2d 383, 390 (Pa. Cmwlth. 1984).

18

Section 1021.122(c)(2) of EHB’s regulations states, in relevant part,

that “[a] party appealing an action of [DEP] shall have the burden of proof . . .

[w]hen a party who is not the recipient of an action by [DEP] protests the action.”

25 Pa. Code §1021.122(c)(2). Thus, Wayco is correct that Landowner bore the

initial burden of proof with respect to whether Wayco returned the Site to AOC

before DEP could properly approve the Stage I and Stage II bond release.

However, Wayco is not correct that Landowner was required to

present expert testimony in this regard. Pa. R.E. 701 states:

If a witness is not testifying as an expert, testimony in

the form of an opinion is limited to one that is:

(a) rationally based on the witness’s perception;

(b) helpful to clearly understanding the witness’s

testimony or to determining a fact in issue; and

(c) not based on scientific, technical, or other

specialized knowledge within the scope of Rule 702.

As outlined above, EHB found “[Landowner’s] testimony regarding

the state of his property prior to Wayco’s processing operations on the Site as

compared with the state of his property after Wayco left to be compelling.” R.R. at

1200 (citation omitted). EHB also found that “[Landowner] described the still

present silt ponds on his property, which had not existed prior to Wayco’s use of

the Site for processing operations[,]” and that “[a]ccording to [Landowner’s]

testimony, the silt ponds are unsafe due to being steep and saturated.” Id. at 1200,

1201 (citations omitted). EHB further found that “[Landowner] ‘kind of figured if

[Wayco] uses your property for 15 years, [it] could put it back where it was’ and

this was not done as water is trapped in the silt ponds and the silt is still in them.”

Id. at 1201 (citations omitted). EHB concluded, “Taken together, [EHB] finds

19

these statements to be compelling support for Wayco having failed to return the

Site to AOC.” Id.

Clearly, the foregoing lay opinion testimony is based on Landowner’s

perception of the Site both before and after Wayco began its operations; is helpful

to EHB in determining whether the Site was returned to AOC, as defined in the

statute and regulations, following Wayco’s purported reclamation of the Site; and

is not based on scientific, technical, or other specialized knowledge within the

scope of Pa. R.E. 702. Thus, this lay testimony regarding Landowner’s perception

of the condition of his property both before and after Wayco commenced

operations on his property, and the absence and presence of silt ponds and the

retention of water therein, is competent evidence upon which EHB could rely in

determining whether Wayco’s reclamation of the property returned it to AOC as

required by the statute and the regulations.

As one commentator has explained:

Considerable discretion is given the trial court in

determining whether the lay opinion testimony will aid

the jury in reaching a just result. A witness should be

permitted to testify in the form of opinions, conclusions,

or observations that he or she draws through their senses.

This will include such things as: the appearance of

persons or things, identity, the manner of conduct,

competency of a person, feeling, sound, size, weight,

distance, and an endless number of things that cannot be

described factually in words apart from inferences.

***

Whatever was left of the rule precluding the use of

lay witness opinion testimony on the ultimate issue has

been eliminated by the codification of the Pennsylvania

Rules of Evidence. The “Comment” to Pa. R.E. 701

indicates that the intent of the Rule is to eliminate the

20

rule prohibiting lay witness testimony on the ultimate

issue, and Pa. R.E. 704 provides that opinion testimony is

not objectionable because it embraces an ultimate issue.

Robert Berkley Harper, Handbook of Pennsylvania Evidence, §701[B] at 347-38

(2001) (citation omitted). See also Commonwealth v. Berry, 172 A.3d 1, 4 (Pa.

Super. 2017) (“[Two police officers] gave permissible lay opinion testimony

regarding their observations of the blood droplets while inside [the defendant’s]

home during their conversation with [his wife]. The trial court’s determination is

consistent with the holding in [Commonwealth v. Glover, 401 A.2d 779, 782 (Pa.

Super. 1979) (citations omitted), that ‘[a] lay witness may testify that a certain

substance appeared to be blood without having to subject the substance to chemical

analysis.’]”).

Because Landowner sustained his initial burden of proof in this regard

through the foregoing lay opinion testimony, the burden then shifted to Wayco to

demonstrate that it had returned the Site to AOC through the reclamation process

before the Stage I and II bond release could occur under the relevant DEP

regulations. See, e.g., 77 Pa. Code §77.242(a) (“The permittee may file an

application with [DEP] for release of all or part of the bond liability applicable to a

permit or designated phase of a permit area after reclamation . . . as defined in

§77.243 (relating to criteria and schedule for release of bond), has been completed

on the permit area[.]”). See also 25 Pa. Code §77.204(a), which states:

(a) Liability under bonds posted for a noncoal mining

activity shall continue for the duration of the mining

activities and its reclamation as provided in the act, this

chapter and the conditions of the permit for [five] years

after completion of the mining and reclamation of the

area, unless released in whole or in part prior thereto if

[DEP] is satisfied that the reclamation covered by the

bond has been accomplished as required by the act.

21

As outlined above, EHB specifically rejected as not credible the

evidence that was presented in support of the bond release. See R.R. at 1200

(“[W]e find that the testimony of the multiple expert witnesses proffered by [DEP]

and [Wayco] was not credible and leaves us unconvinced as to the legal basis for

[DEP’s] approval of Stage I and II bond release. The expert witness testimony was

clearly self-serving statements that ignored key facts and was based on a

fundamental misunderstanding of AOC requirements.”). Moreover, EHB’s

determination in this regard is patently not subject to our review on appeal. EQT

Production Company, 193 A.3d at 1148-49. As a result, we will not accede to

Wayco’s request to reconsider EHB’s review of the substantial record evidence

supporting its Adjudication reversing DEP’s decision.16

IV.

Finally, Wayco claims that EHB erred in overruling Wayco’s

objections that Landowner’s arguments against the bond release were barred by the

statute of limitations in Section 1021.52 of EHB’s regulations 17 because

16

Based on our disposition of this claim, we need not address Wayco’s additional claims

regarding the other criteria applicable to a bond release because its failure to return the Site to

AOC through the reclamation process is a sufficient basis alone to deny the bond release. See

R.R. at 1205 (“The requirements of Stage I and II bond release, found in Section 243, subsection

(b)(1) and (2) of Chapter 77 were not met because backfilling and regrading were not done in

accordance with the law. 25 Pa. Code §77.243(b)(1)-(2).”).

17

25 Pa. Code §1021.52. Section 1021.52(a)(2)(ii) states, in relevant part, that

“jurisdiction of [EHB] will not attach to an appeal from an action of [DEP] unless the appeal is

in writing and is filed with [EHB] as follows[:] . . . Any other person aggrieved by an action of

[DEP] shall file its appeal with [EHB] within . . . [t]hirty days after actual notice of the action if a

notice of the action is not published in the Pennsylvania Bulletin.” 25 Pa. Code

§1021.52(a)(2)(ii).

22

Landowner did not file his objections within 30 days of DEP’s issuance of the

permit in 1994. However, as outlined above, the actions that triggered the instant

proceedings were DEP’s approval of Wayco’s request for both Stage I and II bond

release on July 21, 2016, and September 13, 2016, respectively. R.R. at 923, 925-

27. Landowner appealed these DEP decisions to EHB18 on August 10, 2016, and

October 11, 2016, respectively. Id. at 1-4, 5-9. Thus, Wayco’s allegation of error

in this regard is based on the false premise that Landowner is appealing DEP’s

1994 permit grant. To the contrary, the instant proceedings are clearly

Landowner’s appeals of DEP’s approval of the Stage I and II bond release, which

were clearly timely filed under Section 1021.52(a)(2)(ii) of EHB’s regulations.

Accordingly, EHB’s order is affirmed.

MICHAEL H. WOJCIK, Judge

18

EHB sua sponte consolidated the appeals. R.R. at 1178.

23

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Wayco Sand and Gravel, :

:

Petitioner :

:

v. : No. 713 C.D. 2018

:

Department of Environmental :

Protection and Peter Karnick, :

:

Respondents :

ORDER

AND NOW, this 6th day of January, 2020, the order of the

Environmental Hearing Board dated April 24, 2018, is AFFIRMED.

__________________________________

MICHAEL H. WOJCIK, Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.