Opinion

C. Carulli & B. Carulli, h/w v. N. Versailles Twp. Sanitary Auth. v. Port Vue Plumbing, Inc.

Court
Commonwealth Court of Pennsylvania
Filed
Aug 13, 2019
Status
Published
On the bench
Fizzano Cannon, J. ~ Dissenting Opinion by McCullough, J.
Cited by
0 cases
Authority
More cited than 8.5%

stating whether a complaint is timely filed is a matter of law

How later courts described this case

  • stating whether a complaint is timely filed is a matter of law
  • concluding that a count for promissory estoppel, although technically a “quasi-contract” claim, was governed by the four-year SOL in section 5525(4) for breach of contract claims and, more importantly, was subjected to the discovery rule
  • stating that “the recipient of an allegedly fraudulent misrepresentation is under no duty to investigate its falsity in order to justifiably rely”
  • applying discovery rule in action that alleged authority’s charges for sewer tapping 22 fees violated Act and noting similarity of claim to that in Harleysville Homestead, Inc. v. Lower Salford Township Authority, 980 A.2d 749 (Pa. Cmwlth. 2009

Written by the judges who cited it.

The opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Carmen Carulli and Barbara :

Carulli, husband and wife :

:

v. :

:

North Versailles Township :

Sanitary Authority :

:

v. :

:

Port Vue Plumbing, Inc., : No. 751 C.D. 2017

Appellant : Argued: October 17, 2018

BEFORE: HONORABLE MARY HANNAH LEAVITT, President Judge

HONORABLE RENÉE COHN JUBELIRER, Judge

HONORABLE P. KEVIN BROBSON, Judge

HONORABLE PATRICIA A. McCULLOUGH, Judge

HONORABLE ANNE E. COVEY, Judge

HONORABLE CHRISTINE FIZZANO CANNON, Judge

HONORABLE ELLEN CEISLER, Judge

OPINION

BY JUDGE FIZZANO CANNON FILED: August 13, 2019

Port Vue Plumbing, Inc. (Port Vue) appeals a judgment of the

Allegheny County Court of Common Pleas (trial court) entered against Port Vue and

in favor of North Versailles Township Sanitary Authority (Authority), awarding

damages in the amount of $39,033.69 in a breach of contract action. In doing so, the

trial court rejected Port Vue’s claim that the four-year statute of limitations

applicable to contract actions barred the Authority from bringing its claim. The trial

court applied the discovery rule, reasoning that the Authority had no reason to know

of the breach until it received a complaint from residents alleging damage to their

residence approximately 10 years later. We vacate and remand.

I. Background

In December 2002, the Authority contracted with Port Vue to replace

terra cotta sewer pipes along Bevan Road in North Versailles Township. Port Vue

agreed to replace the pipes using the “pipe bursting” method, which bursts the

existing pipe while simultaneously pulling through a new pipe. Notes of Testimony

11/21/2016 (N.T.) at 75, Reproduced Record (R.R.) at 138a. The portion of sewer

line to be replaced stretched from manhole 755 to manhole 767. Port Vue also

contracted to excavate the new line to reconnect all residential sewer laterals to the

new line. In July 2003, Port Vue notified the Authority that it had completed work

on the project and requested final payment, which was approved by the Authority’s

engineer. Trial Court Opinion at 1.1 In accordance with the contract, the Authority

paid Port Vue for completion of the project. Id. at 1-2.

In March 2012, the Authority was notified that the basement of a house

along Bevan Road belonging to Carmen and Barbara Carulli (together, Carullis) had

flooded with raw sewage. Trial Court Opinion at 2. The Authority also discovered

that manhole 767 was surcharged2 to within several feet of its top. Id. The Authority

inspected the sewage lines with a camera and discovered that 112.71 lineal feet of

piping between manhole 766 and manhole 767 had not been replaced in accordance

with the contract. Id. The Authority requested that Port Vue replace the sewer line

1

Pagination supplied beginning after cover page.

2

A “[s]ewer surcharge refers to the overloading of the sewer beyond its design capacity

due to inflow and infiltration of water. A surcharging sewer often results in sewer overflow at

manholes and customers’ over flow relief gully[.]” Sewer Surcharge, The Local Government

Municipal and Knowledge Base, http://www.lgam.info/sewer-surcharge (last visited August 12,

2019).

2

between manhole 766 and manhole 767. Id. When Port Vue refused, the Authority

retained another contractor, State Pipe Services, to replace the old sewer line. Id.

In September 2012, the Carullis filed a complaint for damages against

the Authority. In response, on or about November 20, 2012, the Authority filed a

complaint to join Port Vue as an additional defendant arising from Port Vue’s

alleged failure to fulfill its obligations under the contract. Trial Court Opinion at 2.

The Carullis settled their claims, and the Authority and Port Vue proceeded to a non-

jury trial.

Before the trial court, Port Vue argued that the statute of limitations

bars the Authority’s claims. Trial Court Opinion at 2. The parties did not dispute

that Pennsylvania’s statute of limitations for a breach of contract claim of this nature

is four years. Id. (citing 42 Pa.C.S. § 5525(1)). The parties also did not dispute that

Port Vue was not made a party to the lawsuit until nearly 10 years after it completed

work on the project. Id. The Authority, however, claimed it was unaware that a

section of the project was unfinished until those pipes caused the damage to the

Carullis’ home, and therefore, the discovery rule tolled the running of the statute of

limitations. See id. at 2-3.

At trial, the Authority presented the testimony of Donald Glenn

(Glenn), an engineer from the Authority’s engineering firm, Glenn Engineering and

Associates Ltd. N.T. at 10-11, R.R. at 73a-74a. Glenn testified that he designed the

project for the Authority, which consisted of replacing the sewer lines, reconnecting

the house laterals to the new line and installing additional manholes. N.T. at 11,

R.R. at 74a. The project was to be completed in two phases. N.T. at 12, R.R. at 75a.

Phase 1 started at manhole 755 and ended at manhole 764. Id. Phase 2 started at

3

manhole 764 and ended at manhole 767. Id. Port Vue contracted to do the work for

both phases of the project. See N.T. at 13, R.R. at 76a.

Glenn testified that he was not at the site every day to inspect the work

in progress. His colleague, Joseph Dursa (Dursa), and the Authority’s

representative, Jack Gaffney (Gaffney), were on-site. When asked if an individual

could visibly inspect the new sewer line between manholes 764 and 767, Glenn

testified that “you can’t physically inspect” the pipe because there was no excavation

of the pipe line. N.T. at 25-26, R.R. at 88a-89a. Further, the Authority did not have

the physical equipment to do a camera inspection of the sewer line. N.T. at 59, R.R.

at 122a. Glenn testified that Port Vue forwarded an invoice to him representing that

the project had been completed, including bursting the entire line, and that based on

such representation, Glenn authorized payment in full to Port Vue. N.T. at 24-25,

R.R. at 87a-88a.

Glenn also testified about the incident that caused the damage to the

Carullis’ property. Glenn testified that after the incident, it was determined that the

pipe bursting had not been done for the entire length as specified in the contract.

N.T. at 27, R.R. at 90a. Glenn stated that this caused a backup in the sewer line and

a surcharge at manhole 767. Id. Glenn testified that, after the incident, the Authority

determined the line had collapsed using two methods: physical observation

(climbing down a ladder in the manhole and shining a flashlight up and down the

sewer) and inserting a camera. N.T. at 28-29, R.R. at 91a-92a. The inspection

revealed that the old terra cotta pipe had collapsed and that a new liner had never

been installed. N.T. at 27-29, R.R. at 90a-92a. Glenn testified that the backup in

the sewer line and the surcharge at manhole 767, and the resulting photographs from

the inspection, were the first indication that the sewer line had not been completed

4

all the way to manhole 767. See N.T. at 26-27, 31 & 81, R.R. at 89a-90a, 94a &

144a. Despite Port Vue’s assertions to the contrary, Glenn testified that he never

had a conversation with anyone at Port Vue, including owner Richard Perkoski

(Perkoski), about doing other work instead of replacing the sewer line between

manhole 764 and manhole 767. N.T. at 33, R.R. at 96a.

Glenn testified that under the contract, Port Vue was to furnish as-built

drawings. N.T. at 32, R.R. at 95a. He stated he did not personally request that Port

Vue submit as-built drawings after the contract was completed but that the request

“would have come from one of my other people at the office.” Id. Glenn testified

that, to his knowledge, Port Vue did not supply Glenn Engineering or the Authority

with as-built drawings. N.T. at 32-33, R.R. at 95a-96a.

Glenn also testified that after it was determined the terra cotta pipe

collapsed, he told Port Vue it had to complete the project, but it refused, so the

Authority contracted with, and paid, State Pipe Services to complete the work. N.T.

at 29 & 32, R.R. at 92a & 95a.

On cross-examination, Glenn stated that the contract defines the scope

of the work to be performed. N.T. at 36, R.R. at 99a. Glenn also acknowledged that

the terms of the contract provided that the engineer could inspect the contractor’s

work at any time. N.T. at 38, R.R. at 101a. Glenn also testified that Glenn

Engineering had assigned an inspector to the project, although not a full-time

inspector, and that Gaffney, who worked for the Authority, was also an inspector.

Id. Glenn acknowledged that the contract provided that the Authority’s engineer

was to perform a final inspection to determine whether the job was completed. Id.

Glenn acknowledged that he certified that the work had been completed even though

neither he nor anyone from his office did any type of inspection. N.T. at 53, R.R. at

5

116a. Glenn also reconfirmed that the Authority had determined that a portion of

the line was not bursted when the Authority looked into manhole 767. N.T. at 56a,

R.R. at 119a. Glenn also conceded that the work could have been visually inspected

at any time without the aid of any type of camera, although he stated “[i]t would take

of lot of effort to do that,” explaining that “[y]ou would have to climb down, get a

flashlight, [and] shine it[.]” Id. Glenn stated he “had no idea” whether that was done

at any time between Port Vue completing its work in 2003 and when the backup

incident occurred in 2012, “but obviously not.” Id.

The Authority also presented Dursa’s testimony; Dursa was a project

representative from Glenn Engineering who inspected the work performed by Port

Vue. N.T. at 103, R.R. at 166a. He explained that, at the beginning of the

construction period, Port Vue laid out the new sections of pipe and fused the pipes

together so that they could be pulled through the old terra cotta pipe during the

bursting process. N.T. at 105, R.R. at 168a. Dursa explained that during the

installation of the pipe,

[y]ou really can’t view [the actual bursting of the line], but

you can just see the machines working, and it’s pulling the

pipe through that they had on site already put together

behind the area [that] was dug out.

N.T. at 104, R.R. at 167a.

Dursa stated that in January 2003, when he arrived at the site, the

machine that was used for pipe bursting had stopped working in the vicinity of

manhole 766. See N.T. at 105, R.R. at 168a. He understood that Port Vue was

evaluating the problem and attempting to get the machine working again. N.T. at

105-06, R.R. at 168a-69a. Thereafter, Dursa went on vacation, and upon his return,

the equipment was no longer at the same location. N.T. at 107, R.R. at 170a. Dursa

6

testified that he never spoke to Perkoski about not completing the line replacement

to manhole 767 and, instead, doing other work. N.T. at 108 & 110-11, R.R. at 171a

& 173a-74a. On cross-examination, Dursa stated that he reviewed the contract

documents before he started his inspections and that he had the contract documents

on site, although he did not “have a copy on me[.]” N.T at 116-17, R.R. at 179a-

80a. He acknowledged that he understood what Port Vue was supposed to do. N.T.

at 119, R.R. at 182a.

John McDonald (McDonald) also testified for the Authority.

McDonald was a foreman for State Pipe Services, which replaced the broken sewer

line in 2012. N.T. at 85, R.R. at 148a. Initially, State Pipe Services performed a

pre-inspection of the site using a camera. N.T. at 86, R.R. at 149a. After determining

that the old terra cotta pipe had not been completely replaced, State Pipe Services

continued the pipe bursting process to the top of manhole 767, thereby completing

the project. N.T. at 88, R.R. at 151a.

Gaffney, a former foreman for the Authority at the time of the project,

also testified for the Authority. N.T. at 191-92, R.R. at 254a-55a. Gaffney testified

that he was instructed by the office manager and the Board of the Authority to check

in daily if there was going to be any problems but it was not his position to inspect

anything, and he did not, nor was he at the site daily. N.T. at 192-93, R.R. at 255a-

56a. He confirmed that he never had a conversation with Perkoski about not

completing the bursting of the line between manholes 766 and 767. N.T. at 193,

R.R. at 256a. Regarding the visual inspection of a new sewer line, Gaffney

explained:

If it’s an open cut, in other words, if they excavate and put

the pipe in, both the engineer and myself if I’m in the area,

7

make sure that it’s cemented out correctly with stone,

make sure that there’s good flow on it.

However, if the inspectors work by themselves, you don’t

go down into a sewer by yourself. It’s a safety issue. By

[Occupational Safety and Health Administration]

standard, there should be three people on site.

I have never been there where it’s just myself and/or Joe

[Dursa]. So we don’t make it a habit or standard to go

down any sewers, manholes themselves because of safety

issues.

N.T. at 199-200, R.R. at 262a-63a.

In its case, Port Vue called its President, Perkoski. N.T. at 127-28, R.R.

at 190a-91a. Perkoski testified that throughout the duration of the project, his

communications had been with Glenn Engineering. N.T. at 129-30, R.R. at 192a-

93a. Perkoski explained that during phase 2 of the project, from manhole 764 to

manhole 767, his workers encountered problems connecting some of the homes to

the new sewer line. See N.T. at 140-41, R.R. at 203a-04a. They had to enter the

basements of these houses, cut the basement floors to find the sewer, install a new

eight-inch pipe, and then clean up the basements. N.T. at 141, R.R. at 204a. This

work exceeded the scope of the work set forth in Port Vue’s contract with the

Authority. Id. Perkoski testified that Glenn Engineering was aware of this extra

work and agreed that it would be “traded for the other pipe bursting,” which was

scheduled to be done for a payment of $14,000. N.T. at 143, R.R. at 206a. Perkoski

explained:

[t]he remaining pipe bursting that had to be done, which

amounted to, if you looking [sic] at the schedule,

[$]14,000, and I did eight houses or seven houses, and it

had to cost me five to eight thousand at that time.

8

So I did $35,000 worth of work for $14,000, because

[Glenn] is a friend of [mine].

N.T. at 143-44, R.R. 206a-07a.3

When asked if he completed the 112 feet of sewer line between

manholes 766 and 767, Perkoski stated:

No. I guess if that’s what we say, but that’s what we

figured that we were going to get extras for the inside, and

they didn’t have the money for the inside. So we said,

okay, we’ll leave that existing sewer in and take that

money and apply it to each house.

N.T. at 156, R.R. at 219a. When questioned as to whether Port Vue ever supplied

the Authority or Glenn with as-built drawings after Port Vue completed the project,

Perkoski stated:

A. Yeah, I drew it with Joe [Dursa] and them on the job

the way it was. They knew the way it was. That’s how

these come up and they’re still wrong.

Q. Did you bring a copy of the as-builts with you?

A. No. We draw it on paper up at the job.

Q. You took a piece of paper at the site and said, This is

what I did?

A. Well, they could see what I did, but then they put it

wrong. It ain’t even right on here.

Q. Well, they couldn’t see that you did not complete the

121 feet that was underground.

A. Well, we agreed to eliminate it to save money.

3

On cross-examination, Perkoski explained how he arrived at the $14,000 figure. He stated

that he decided that “wherever we were at that time, we left that pipe bursting go and said we’ll

apply that money to bursting these people’s houses.” N.T. at 189, R.R. at 252a.

9

N.T. at 165, R.R. at 228a. Perkoski acknowledged that the payment application that

his company submitted to the Authority indicated that Port Vue had completed 100%

of the bursting of the lines from manhole 764 to manhole 767. N.T. at 171, R.R. at

234a.

Following the one-day trial, the trial court entered a verdict in favor of

the Authority and awarded it $39,033.69 in damages. Trial Court Opinion at 6. The

trial court concluded that “the discovery rule applie[d] to toll the statute of

limitations until March of 2012 when the Authority became aware that [Port Vue]

failed to complete the work as required by the contract.” Id. at 4. The trial court

also concluded that a 2008 consent order signed by the Authority in a separate case

did not bar the instant case. Id. at 4-5. Finally, the trial court rejected Port Vue’s

argument that it could only be held liable for the cost of the work it did not complete

in the original contract, which was $14,351.00. Id. at 5. Port Vue sought post-trial

relief, which was denied. R.R. at 61a. The present appeal followed.

II. Arguments and Analysis

On appeal,4 Port Vue raises three arguments. First, it contends that the

four-year statute of limitations applicable to breach of contract claims bars the

Authority’s claims. Second, Port Vue contends that a 2008 consent order between

the parties released it from any future claims related to the project. Third, Port Vue

contends that the amount of damages awarded to the Authority exceeded what it

would have been paid under the contract and, therefore, exceeded those allowed by

law.

4

“When reviewing a non-jury verdict, our standard of review is limited to determining

whether the competent evidence supports the trial court’s findings of fact and whether the trial

court committed an error of law.” E. Coast Paving & Sealcoating, Inc. v. N. Allegheny Sch. Dist.,

111 A.3d 220, 225 n.8 (Pa. Cmwlth. 2015). “This Court must treat the trial court’s findings of fact

the same as this Court would treat a jury’s findings of fact.” Id. “This Court views the evidence

in the light most favorable to the party that prevailed before the trial court.” Id.

10

In response, the Authority argues that the trial court did not err or abuse

its discretion in concluding that the Authority’s claim was not barred by the statute

of limitations. Next, the Authority argues that this matter is not barred by the consent

order because that order involved a separate nucleus of facts and did not release Port

Vue from the present claim. Finally, the Authority responds that the trial court did

not award damages in excess of those allowed by law because the Authority is

entitled to compensation for all damages resulting from Port Vue’s failure to fulfill

the contract.

This case was originally argued before a panel of three judges of this

Court. Subsequently, the Court issued an order directing the parties to file

supplemental briefs addressing: (1) “[w]hether a sewer authority may invoke the

doctrine of nullum tempus occurit Regi [“time does not run against the king”] to

defeat an otherwise applicable statute of limitations defense . . .” and whether the

Authority “acted in its governmental capacity to enforce an obligation imposed by

law[]”; and (2) “[w]hether the statute of limitations begins to run upon occurrence

of a breach of contract or upon the discovery of the breach in all types of contracts.”

Cmwlth. Ct. Order 8/7/18. The matter was then argued before the Court en banc.

We will begin by addressing Port Vue’s argument that the consent order

bars this action because it released Port Vue from any future claims related to the

project.

A. Consent Order

By way of background, in 2005, two property owners along Bevan

Road, William Roney and Gina Buzzard, filed suit against multiple parties including

Port Vue and the Authority, following land subsidence events behind their homes in

2002 and 2003 related to the sewer line replacement. See Trial Court Opinion at 4-

11

5; Consent Order ¶¶ 1 & 3, R.R. at 23a-24a. The lawsuit was resolved by a

settlement agreement, wherein the Authority agreed to release Port Vue from any

claim or cause of action related to the litigation. See R.R. at 23a-24a. Port Vue

contends that, “[b]ut for the contract between [it] and the Authority to perform pipe

bursting on the hillside below Bevan Road [it] would not have been involved in the

above litigation.” Port Vue’s Brief at 13.

“In Pennsylvania, a consent decree in an equity action is not considered

a legal determination by the courts but is an agreement between the parties.” Penn

Township v. Watts, 618 A.2d 1244, 1247 (Pa. Cmwlth. 1992). “‘It is in essence a

contract binding the parties thereto.’” Cecil Township v. Klements, 821 A.2d 670,

674 (Pa. Cmwlth. 2003) (quoting Commonwealth v. Rozman, 309 A.2d 197 (Pa.

Cmwlth. 1973)).

The consent order provided that the parties to the agreement, including

Port Vue and the Authority, agreed to release and discharge one another from all

claims or damages “arising from the slide or land subsidence occurring behind the

Roney and Buzzard residences in 2002 and 2003 and including, but not limited to,

any claim or cause of action arising out of, or related to, these consolidated litigation

matters and it is so ORDERED.” Consent Order ¶ 5, R.R. at 24a-25a. Based on this

language, the trial court concluded that the release did not apply to the instant case.

Trial Court Opinion at 5. We agree.

The Carullis’ claim arose because the sewer line between manholes 766

and 767 was not replaced. The 2008 consent order was limited to actions and claims

arising from the slide or land subsidence occurring behind the Roney and Buzzard

residences. The Carullis were not parties in the prior litigation and did not claim any

harm from the 2002 and 2003 land subsidence events behind the Roney and Buzzard

12

residences. Thus, the language of the release does not bar the Authority’s breach of

contract claim against Port Vue arising from the sewer line not being replaced.

Although Port Vue may not have been involved in the prior litigation but for its

contract with the Authority, the order released all claims and actions arising from or

related to the 2002 and 2003 slide or land subsidence behind the Roney and Buzzard

residences. Accordingly, we agree with the trial court that the 2008 consent order

does not bar the Authority from bringing its claims against Port Vue in this matter.

B. Statute of Limitations

With respect to the statute of limitations, Port Vue argues that the

Authority’s claim is barred because the statute of limitations began to run upon the

occurrence of the breach. In response, the Authority argues that it is not subject to

any statute of limitations under the doctrine of nullum tempus. The Authority also

asserts that its claim is not time-barred under the “discovery rule” and that the statute

of limitations does not begin until the Authority, exercising reasonable diligence,

could have discovered the injury, which it claims was when the damage to the

Carullis’ basement occurred. Additionally, and in the alternative, the Authority

argues that even if it is subject to a statute of limitations defense, Port Vue is

estopped from asserting such a defense due to fraudulent concealment.

(i) Nullum Tempus

We begin with the doctrine of nullum tempus. “The doctrine of nullum

tempus permits a government agency ‘to circumvent the applicable statute of

limitations.’” Allegheny Intermediate Unit v. E. Allegheny Sch. Dist., 203 A.3d 371,

378 (Pa. Cmwlth. 2019) (quoting Duquesne Light Co. v. Woodland Hills Sch. Dist.,

700 A.2d 1038, 1051 (Pa. Cmwlth. 1997)), petition for allowance of appeal denied,

(Pa., No. 52 WAL 2019, July 24, 2019). “Under the nullum tempus doctrine, statutes

13

of limitations do not apply to actions brought by the state and its agencies, unless the

statute of limitation expressly provides that it limits the government’s right to sue.”

Township of Salem v. Miller Penn Dev., LLC, 142 A.3d 912, 918 (Pa. Cmwlth.

2016). The four-year statute of limitations for contract actions does not expressly

provide that it applies to actions brought by government entities. See 42 Pa.C.S. §

5525. Therefore, the statute of limitations cannot bar this action if nullum tempus

applies. See Township of Salem, 142 A.3d at 918.

“The nullum tempus doctrine does not apply to all suits by local

governments, but does extend to local governments where they are enforcing strictly

public rights.” Township of Salem, 142 A.3d at 918. “For the nullum tempus

doctrine to exempt a municipality from the statute of limitations, the municipality’s

claims must both 1) accrue to the municipality in its governmental capacity and 2)

seek to enforce an obligation imposed by law, as distinguished from one arising out

of a voluntary agreement.”5 Id. “An action involving a local government contract

or agreement is brought in the local government’s governmental capacity and seeks

5

We note that Port Vue first asserts that the doctrine of nullum tempus does not apply

because the Authority is not a Commonwealth party. Port Vue’s Supplemental Brief at 1-2. We

note that the Authority does not argue that it is a Commonwealth party and does not dispute that

this two-prong test is the appropriate test to apply to determine whether nullum tempus applies.

See Authority’s Supplemental Brief at 1-2. For purposes of nullum tempus, we conclude that the

Authority cannot be construed as being a Commonwealth party. See Se. Pa. Transp. Auth. v. Union

Switch & Signal, Inc., 637 A.2d 662, 666 (Pa. Cmwlth. 1994) (stating, “[w]hile authorities may be

considered an ‘instrumentality of the Commonwealth’, that does not mean that they are

automatically considered to be ‘the Commonwealth’ for all purposes”). In Northampton County

Area Community College v. Dow Chemical, U.S.A., 566 A.2d 591, 596 (Pa. Super. 1989), aff’d,

598 A.2d 1288 (Pa. 1991), the Superior Court held that community colleges cannot be construed

as Commonwealth parties “because the legislature did not create them but merely authorized their

creation by means of an enabling statute[.]” Likewise here, the legislature, via the Municipality

Authorities Act (Act), 53 Pa.C.S. §§ 5601-5623, authorized the creation of municipal authorities,

but it is the municipality that creates authorities. See 53 Pa.C.S. § 5603 (concerning method of

incorporation); Se. Pa. Transp. Auth., 637 A.2d at 664 (stating, “authorities owe their existence to

the various units of government and their governing boards are appointed by those entities”).

14

to enforce obligations imposed by law where the contract is one that the local

government entity was required to enter into as part of its public duties.” Id. “The

requirement that the action be brought in the local government’s governmental

capacity and seek to enforce obligations imposed by law is likewise satisfied and

nullum tempus applies where the parties’ rights are governed by statute, even though

the local government was not required to enter into the contract.” Id. Thus, for

nullum tempus to apply, “the right sought to be enforced must be strictly public, as

well as imposed by law.” Duquesne Light Co., 700 A.2d at 1051.

In Township of Salem, this Court applied the doctrine of nullum tempus.

In that case, the township brought suit against the subdivision developer for

breaching the parties’ agreement for site improvements and to recover damages for

the cost of making the street repairs. Township of Salem, 142 A.3d at 916. In

concluding that the township’s action was not barred by the statute of limitations

because of nullum tempus, this Court stated:

the [d]eveloper’s [a]greement] and fixing [the street]

involve the [t]ownship’s duties to its residents. Ensuring

the adequate construction of streets is a purely public

purpose within a municipality’s obligations to its citizens,

not a mere voluntary contractual undertaking. Pocono

Township [v. Hall], 561 A.2d [53,] 56 [(Pa. Cmwlth.

1989)]. Indeed, Section 509 of the [Pennsylvania

Municipalities Planning Code6 (MPC)] imposes a duty on

municipalities to require that developers complete public

improvements in accordance with [subdivision and land

development ordinance] requirements. 53 P.S. §10509;

Stivala Investments, Inc. v. South Abington Township

Board of Supervisors, 815 A.2d 1, 5 (Pa. Cmwlth. 2003).

6

Act of July 31, 1968, P.L. 805, as amended, 53 P.S. §§ 10101–11202.

15

Moreover, the parties’ rights in this action are governed by

statute. Section 511 of the MPC imposes on developers the

cost of correcting improperly installed improvements. 53

P.S. §10511; Stivala Investments, 815 A.2d at 4; Safford

v. Board of Commissioners, Annville Township, 35 Pa.

Cmwlth. 631, 387 A.2d 177, 182 (1978).

Township of Salem, 142 A.3d at 918-19.

Similarly, this Court held that the doctrine of nullum tempus applied in

Delaware County v. First Union Corporation, 929 A.2d 1258 (Pa. Cmwlth. 2007),

wherein the county brought suit against banks that were the depositories for bonds

issued by the county. The banks did not return unclaimed funds within two years to

the county as required by the Local Government Unit Debt Act (Debt Act),7 but

rather, after another five years, escheated the unclaimed funds to the Commonwealth

pursuant to section 1301.3 of the act commonly known as the Unclaimed Property

Act.8 Id. at 1260. This Court held that nullum tempus applied, because while the

county had the discretion to decide whether to issue the bonds, once the bonds were

issued, the parties’ rights were controlled by statute, i.e., the Debt Act. Id. at 1262.

In contrast, in Altoona Area School District v. Campbell, 618 A.2d 1129

(Pa. Cmwlth. 1992), this Court held that a school district could not invoke the

doctrine of nullum tempus to defeat the statute of limitations in an action for breach

of contract and on the related performance bond concerning the construction of a

public library. Id. at 1134. We noted that although the school district was authorized

7

53 Pa.C.S. §§ 8001-8049.

8

Act of April 9, 1929, P.L. 343, as amended, added by Section 5 of the Act of December

9, 1982, P.L. 1057, 72 P.S. § 1301.3.

16

to build libraries under section 418 of The Library Code,9 it was not mandated to do

so. Id. at 1132. Therefore, we reasoned that the school district was not obligated by

law to enter into a contract to construct the library, but rather, entered into the

contract voluntarily as it was authorized to do under The Library Code. Id. at 1132-

33. Accordingly, we concluded that the school district was not seeking to enforce

strictly public rights, and therefore, nullum tempus did not apply. Id. at 1134.

Here, Port Vue argues that nullum tempus does not apply because there

is no statutory duty or obligation to provide sewer service. The Authority, on the

other hand, argues that it was created pursuant to the Municipality Authorities Act

(Act) for the sole purpose of extending the public right of sewer services to

Township residents, and the Authority is the governmental arm through which the

Township acts in its governmental capacity. Authority’s Supplemental Brief at 2.

Further, the Authority argues that once a sewer service exists, the Authority has a

duty, or legal obligation, to continue to provide those services and keep them in good

repair. Id. at 3.

The Act defines an authority as “[a] body politic and corporate created

under this chapter[.]” 53 Pa.C.S. § 5602. The Act authorizes the creation of an

authority for:

(a) Scope of projects permitted.—Every authority

incorporated under this chapter shall be a body corporate

and politic and shall be for the purposes of financing

working capital; acquiring, holding, constructing,

financing, improving, maintaining and operating, owning

or leasing, either in the capacity of lessor or lessee,

9

Act of June 14, 1961, P.L. 324, as amended, formerly 24 P.S. § 4418, repealed by Act of

November 1, 2012, P.L. 1683.

17

projects of the following kind and character and providing

financing for insurance reserves:

...

(5) Sewers, sewer systems or parts thereof.

53 Pa.C.S. § 5607(a)(5). Further, the Act states that an authority “may exercise all

powers necessary or convenient for the carrying out of the[se] purposes . . . .” 53

Pa.C.S. § 5607(d) (emphasis added).

Thus, the Act only authorizes the creation of the Authority for the

purpose of, inter alia, improving and maintaining sewers or sewer system projects;

the Act does not mandate such. The Authority argues, however, that this is of no

consequence; rather, the Authority contends that it is mandated to continue the

provision of such services and that this mandate is important and what distinguishes

this case from Altoona. Authority’s Supplemental Brief at 2-3. The Authority

argues that once it undertakes a sewer system, it has a duty to maintain it. While we

agree with the Authority that once it undertakes a sewer system, it has a duty to

maintain it, there is no statutory duty. The Act does not control the terms of any

contract between a contractor and an authority relating to the sewer or sewer system

or the maintenance thereof. Rather, the duty the Authority forwards is no different

than the common law duty of care. This duty is unlike the statutory duty in Township

of Salem, where the parties’ contractual terms were governed by the township’s

subdivision and land development ordinance, and unlike Delaware County, where

the Debt Act governed the parties’ rights. Thus, the Authority’s claims do not accrue

to it in its governmental capacity and do not seek to enforce an obligation imposed

by law. In sum, unlike the case of Township of Salem and similar to the case of

Altoona, here, the parties’ obligations are not imposed by statutory law but are

dictated solely by the actual terms of the contract. Accordingly, the doctrine of

18

nullum tempus does not apply, and therefore, the statute of limitations applies to this

action.

(ii) Whether the statute of limitations begins

to run upon the occurrence of the breach

or upon the discovery of the injury

Port Vue argues that the statute of limitations begins to run upon the

occurrence of the breach. The Authority, on the other hand, argues the discovery

rule applies, pursuant to which the statute of limitations does not begin to run until

a party, using reasonable diligence, discovers the breach. Authority’s Supplemental

Brief at 4-5. The trial court applied the discovery rule.

The Supreme Court of the United States observed:

Statutes of limitation are vital to the welfare of society and

are favored in the law. They are found and approved in all

systems of enlightened jurisprudence. They promote

repose by giving security and stability to human affairs.

An important public policy lies at their foundation. They

stimulate to activity and punish negligence. While time is

constantly destroying the evidence of rights, they supply

its place by a presumption which renders proof

unnecessary. Mere delay, extending to the limit

prescribed, is itself a conclusive bar.

Wood v. Carpenter, 101 U.S. 135, 139 (1879).

In Pennsylvania, our courts have noted that, generally, “[s]tatutes of

limitations ‘are designed to effectuate three purposes: (1) preservation of evidence;

(2) the right of potential defendants to repose; and (3) administrative efficiency and

convenience.’” Lesoon v. Metro. Life Ins. Co., 898 A.2d 620, 626-27 (Pa. Super.

2006) (quoting Kingston Coal Co. v. Felton Mining Co., 690 A.2d 284, 288 (Pa.

Super. 1987)). “Whether a complaint is timely filed within the limitations period is

19

a matter of law for the court to determine.” Crouse v. Cyclops Indus., 745 A.2d 606,

611 (Pa. 2000).

Section 5502 of the Judicial Code sets forth the method of computing

periods of limitation and provides:

The time within which a matter must be commenced under

this chapter shall be computed, except as otherwise

provided by subsection (b) or by any other provision of

this chapter, from the time the cause of action accrued, the

criminal offense was committed or the right of appeal

arose.

42 Pa.C.S. § 5502(a) (emphasis added). Our Supreme Court has stated, “[i]n

construing this language for general contract purposes, we have adopted the view of

a majority of jurisdictions that it is the accrual of the right of action that starts a

limitations period to run.” Erie Ins. Exch. v. Bristol, 174 A.3d 578, 585 (Pa. 2017).

Our Supreme Court noted that this view is “in accord with the law across the

country[,]” which provides:

Unless a statute provides otherwise, the statute of

limitations begins to run at the time when a complete

cause or right of action accrues or arises, which occurs as

soon as the right to institute and maintain a suit arises.

The general rule, as embodied in most statutes, is that,

unless a statute specifically provides otherwise, as, for

example, a statute specifically providing that the statute of

limitations shall run from a particular event which may

precede the time where the liability actually arises, the

statute of limitations begins to run at the time when a

complete cause or right of action accrues or arises, and

only at such time, that is, as soon as the right to institute

and maintain a suit arises, or when there is a demand

capable of present enforcement. An action may accrue at

20

the time of a wrongful act, although the limitations period

does not always begin on the date the wrong is committed.

54 C.J.S. Limitations of Actions, § 81 (footnotes and case

citations omitted.)

Erie Ins. Exch., 174 A.3d at 585-86 (citing Ctr. Concrete Co. v. AGI, Inc., 559 A.2d

516, 518-19 (Pa. 1989)) (emphasis in original).10 “In general, for a claim based upon

contract, the cause of action accrues and the statute of limitations begins to run on

the date that the contract is breached.” GAI Consultants, Inc. v. Homestead Borough,

120 A.3d 417, 423-24 (Pa. Cmwlth. 2015) (citing McGaffic v. City of New Castle,

973 A.2d 1047, 1052 (Pa. Cmwlth. 2009)). Therefore, applying contract principles

to the Authority’s breach of contract claim at issue here, the statute of limitations

would begin to run when the Authority’s cause of action accrued, i.e., when Port

Vue breached its duty under the agreement. The trial court, however, applied the

discovery rule. We therefore consider whether grounds exist to deviate from the

general rule concerning the statute of limitations in a breach of contract action and

whether the application of the discovery rule to such breach of contract claim is

appropriate.

With respect to the statute of limitations and the discovery rule, our

Supreme Court has stated:

10

In Erie Insurance Exchange, our Supreme Court considered when the statute of

limitations begins to run when an insurer is alleged to have breached its duty under an insurance

contract involving a claim for uninsured motorist coverage. Erie Ins. Exch., 174 A.3d at 579. The

case did not involve the discovery rule. Nonetheless, the relevance of this decision to the case

before us is that our Supreme Court emphasized that the controlling law for determining when the

limitations period begins to run for a breach of contract action is when the cause of action accrued.

Id. at 585-86. Further, the Court concluded that because there was no compelling public policy

ground or legislative intent in the related motor vehicle statute, there was no reason to create a

special rule for when the statute of limitations begins to run in an uninsured motorist case. Id. at

589.

21

As a matter of general rule, a party asserting a cause

of action is under a duty to use all reasonable diligence to

be properly informed of the facts and circumstances upon

which a potential right of recovery is based and to institute

suit within the prescribed statutory period. . . . Thus, the

statute of limitations begins to run as soon as the right to

institute and maintain a suit arises; lack of knowledge,

mistake or misunderstanding do not toll the running of the

statute of limitations . . . ; even though a person may not

discover his injury until it is too late to take advantage of

the appropriate remedy, this is incident to a law arbitrarily

making legal remedies contingent on mere lapse of time.

Once the prescribed statutory period has expired, the party

is barred from bringing suit unless it is established that an

exception to the general rule applies which acts to toll the

running of the statute.

The “discovery rule” is such an exception, and arises from

the inability of the injured, despite the exercise of due

diligence, to know of the injury or its cause. . . . The salient

point giving rise to the equitable application of the

exception of the discovery rule is the inability, despite the

exercise of diligence by the plaintiff, to know of the injury.

Pocono Int’l Raceway, Inc. v. Pocono Produce, Inc., 468 A.2d 468, 471 (Pa. 1983)

(emphasis in original) (citations omitted). The discovery rule is a “judicially created

device[.]” Gustine Uniontown Assocs., Ltd. v. Anthony Crane Rental, Inc., 842 A.2d

334, 334 n.8 (Pa. 2004) (Gustine I).

“The discovery rule . . . was first used in the limited area of medical

malpractice and soon spread to other tort fields.” 33 A.L.R.5th 1 (originally

published in 1995); see, e.g., Gleason v. Borough of Moosic, 15 A.3d 479 (Pa. 2011)

(applying discovery rule in action alleging negligent road construction); Hidden

Creek, L.P. v. Lower Salford Twp. Auth., 129 A.3d 602 (Pa. Cmwlth. 2015)

(applying discovery rule in action that alleged authority’s charges for sewer tapping

22

fees violated Act and noting similarity of claim to that in Harleysville Homestead,

Inc. v. Lower Salford Township Authority, 980 A.2d 749 (Pa. Cmwlth. 2009), a claim

that was held to sound in tort); Garvey v. Rosanelli, 601 A.2d 1334 (Pa. Cmwlth.

1992) (applying discovery rule in negligence action alleging latent defects in

residential construction).

Pennsylvania courts have also considered the application of the

discovery rule to non-tort actions. See, e.g., Altoona, 618 A.2d at 1135 (Pa. Cmwlth.

1992) (stating that Section 5523 of Judicial Code, 42 Pa.C.S. § 5523, is a statute of

limitations and, therefore, cause of action on performance bond brought pursuant to

that section is subject to discovery rule)11; Amodeo v. Ryan Homes, Inc., 595 A.2d

1232 (Pa. Super. 1991) (holding that discovery rule applied to breach of implied

11

In Altoona, this Court held that a school district’s claims against the contractor and surety

based on the performance bond raised genuine issues of fact as to when the statute of limitations

began to run, and that because Section 5523 of the Judicial Code— which states that an action

upon any payment or performance bond must be commenced within one year— is a statute of

limitations, rather than a statute of repose, the claim was subject to the discovery rule. Altoona

Area Sch. Dist., 618 A.2d at 1135. That case does not mandate applying the discovery rule here,

as it is distinguishable given the role of the entity seeking to enforce the performance bond. An

action asserting a claim based on a performance bond is not a breach of contract action per se and

is sui generis. A performance bond is “[a] bond given by a surety to ensure the timely performance

of [the terms of] a contract.” Performance Bond, Black’s Law Dictionary 1319 (10th ed. 2014).

Under a performance bond, a third party, usually known as a surety, agrees to guarantee the

completion of a construction contract. See id. The contractor purchases the performance bond

from the surety to ensure the contractor’s performance of the construction contract for the benefit

of the named obligee (e.g., the property owner who is a party to the underlying construction

contract), which in Altoona was the school district. See Philip L. Bruner & Patrick J. O’Connor,

Jr., 4A Bruner & O’Connor on Construction Law § 12:32 (June 2018) (stating that purpose of

performance bond is to protect named obligee against contractor’s default in completion of

underlying contract). Notably, the obligee, the entity seeking to enforce the performance bond, is

not involved in the creation/procurement of the performance bond and does not provide

consideration (or payment) for the performance bond. In other words, that entity is essentially a

third-party beneficiary and is not a negotiating party at arms’ length. When determining liability

of the surety under the performance bond, the terms of the bond instrument control, not the

underlying contractor agreement. 20 Standard Pa. Practice 2d § 108:18 (June 2019).

23

warranty of habitability claims involving defective construction). The Pennsylvania

Superior Court has stated, “[t]he discovery rule in Pennsylvania applies to all causes

of action, including breach of contract.” Morgan v. Petroleum Prods. Equip. Co.,

92 A.3d 823, 828 (Pa. Super. 2014) (citing Sadtler v. Jackson-Cross Co., 587 A.2d

727, 731 (Pa. Super. 1991)) and applying discovery rule to breach of contract claim);

Sadtler (applying discovery rule to breach of contract case in which purchasers of

real estate brought suit against their appraiser).12 Compare Gustine Uniontown

Assocs., Ltd., ex rel. Gustine Uniontown, Inc. v. Anthony Crane Rental, Inc., 892

A.2d 830, 836 (Pa. Super. 2006) (Gustine II) (holding that contract language, which

stated that “applicable statute of limitations shall commence to run” not later than

the date of substantial completion, precluded application of discovery rule).

Our Supreme Court, however, has not pronounced the applicability of

the discovery rule to a breach of contract action based on an express written contract

negotiated at arms’ length. In Crouse, our Supreme Court affirmed the Superior

Court’s application of the discovery rule to a claim based on promissory estoppel, a

doctrine which, while sounding in contract law, “makes otherwise unenforceable

agreements binding,” id. at 610, and, thus, is not based on an express written

negotiated term.13 Notably, in his concurring and dissenting opinion, Justice Saylor

stated:

12

Although the plaintiffs in Sadtler alleged negligent performance of an agreement to

appraise real estate, the Superior Court held that the action was a breach of contract action because

the appraiser owed no duties to the plaintiffs except those imposed by the appraisal agreement.

Sadtler, 587 A.2d at 731.

13

“For example, the doctrine allows a party to enforce a promise that is not supported by

consideration.” Peluso v. Kistner, 970 A.2d 530, 532 (Pa. Cmwlth. 2009) (citing Crouse, 745 A.2d

at 610). Promissory estoppel is also referred to as detrimental reliance. Id.

24

I also question whether the discovery rule should apply to

a claim based upon promissory estoppel. Although the

discovery rule, which evolved in the tort context, has been

applied by Pennsylvania courts in some discrete categories

of cases involving contractual or quasi-contractual claims,

see, e.g., Amodeo v. Ryan Homes, Inc., 407 Pa. Super. 448,

453-54, 595 A.2d 1232, 1235 [1991] (stating that “the

discovery rule does apply to cases involving defective

construction”), its use has not been adopted on a

wholesale basis in this area, and, notably, other

jurisdictions are divided as to its applicability. Compare

Morris v. Fauver, 153 N.J. 80, 707 A.2d 958, 972

(1998)(“the rationale for employing the discovery rule in

tort- or fraud-type actions . . . does not carry over to most

contract actions, and therefore, the discovery rule has not

been applied in such suits”); CLL Assoc[s.] Ltd. v.

Arrowhead Pacific Corp., 174 Wis.2d 604, 497 N.W.2d

115, 117 (1993)(“[i]n the context of general contract law,

public policy favors the current rule that the contract

statute of limitations begins to run at the time of breach”),

with Heron Financial Corp. v. United States Testing Co.,

926 S.W.2d 329, 332 (Tex. App. 1996)(“a discovery rule

analysis applies to both tort and contract actions alike”).

Crouse, 745 A.2d at 613 n.1 (Saylor, J., concurring and dissenting) (emphasis

added).

Subsequent to Justice Saylor’s statement above, this Court issued an

unreported decision in Ruddy v. Mt. Penn Borough Municipal Authority (Pa.

Cmwlth., Nos. 1120 C.D. 2013 & 1200 C.D. 2013, filed May 6, 2014), in which we

applied the discovery rule to a claim for unjust enrichment. In doing so, however,

the Court noted, among other things, that the situation was not one “where the

damages were based on an actual contract, but instead, on the quasi-contractual and

equitable doctrine of unjust enrichment.” Id., slip op. at 6.

25

As pointed out by Justice Saylor in Crouse, states are split as to the

applicability of the discovery rule in breach of contract actions. For example, in

Wisconsin, the discovery rule does not apply to actions for breach of contract. CLL

Assocs. Ltd. The Wisconsin Supreme Court stated that although it applies the

discovery rule to tort cases, it would not extend the doctrine to breach of contract

actions because, “unlike in tort law, the need to protect defendants from stale or

fraudulent claims outweighs any injustice caused by barring rights of action prior to

discovery.” Id. at 118. In so holding, the court relied on two critical differences

between tort and contract claims. Id. The first stemmed from the availability of

liability insurance in tort law, whereas, “[i]n contrast, contract law, which deals

primarily with the enforcement of private promises, has nothing comparable to

liability insurance.” Id. The second difference was that, unlike a potential tort

claimant, “a contract claimant often has a significant amount of control over its risk

of loss.” Id. The court noted, for example that the parties had choices regarding

what materials to use, inspections, warranties, price adjustments, etc., and that such

“increased ability of potential contract claimants to protect themselves in the first

instance lessens the need to provide them an opportunity for legal redress.”14 Id.

Likewise, in New York, the discovery rule does not apply to breach of

contract actions because

[the state’s] statutes of limitation serve the same objectives

of finality, certainty and predictability that New York’s

contract law endorses. Statutes of limitation not only save

14

The Wisconsin Supreme Court noted that, to the extent its holding “creates unjust results

in specific situations not now before this court, i.e.[,] in the consumer context where contracting

consumers have limited bargaining power, the legislature, with its greater resources for weighing

policy, is best equipped to enact specific ameliorative laws.” CLL Assocs. Ltd., 497 N.W.2d at

119.

26

litigants from defending stale claims, but also “express[ ]

a societal interest or public policy of giving repose to

human affairs” . . . . And we have repeatedly “rejected

accrual dates which cannot be ascertained with any degree

of certainty, in favor of a bright line approach” . . . .

Accordingly, New York does not apply the “discovery”

rule to statutes of limitations in contract actions . . . .

Rather, the “statutory period of limitations begins to run

from the time when liability for wrong has arisen even

though the injured party may be ignorant of the existence

of the wrong or injury” . . . . This is so even though the

result may at times be “harsh and manifestly unfair, and

creates an obvious injustice” because a contrary rule

“would be entirely dependent on the subjective equitable

variations of different [j]udges and courts instead of the

objective, reliable, predictable and relatively definitive

rules that have long governed this aspect of commercial

repose” . . . . Indeed, “[t]o extend the highly exceptional

discovery notion to general breach of contract actions

would effectively eviscerate the [s]tatute of [l]imitations

in this commercial dispute arena” . . . .

ACE Sec. Corp. v. DB Structured Prods., Inc., 36 N.E.3d 623, 627-28 (N.Y. 2015)

(internal citations omitted).

Similarly, in holding that the discovery rule did not apply to a breach

of contract action for failure to follow payment provisions of a contract, the New

Jersey Supreme Court explained:

[a]lthough it seems “inequitable that an injured person,

unaware that he has a cause of action, should be denied his

day in court solely because of his ignorance, if he is

otherwise blameless,” it may also be “unjust, however, to

compel a person to defend a law suit long after the alleged

injury has occurred, when memories have faded, witnesses

have died and evidence has been lost.” . . .

27

Although some negligence or malpractice actions involve

inherently undiscoverable types of injuries, most contract

actions presume that the parties to a contract know the

terms of their agreement and a breach is generally obvious

and detectable with any reasonable diligence. Because

the discovery rule imposes on plaintiffs an affirmative

duty to use reasonable diligence to investigate a potential

cause of action, and thus bars from recovery plaintiffs who

had “reason to know” of their injuries, the discovery rule

generally does not apply to contract actions.

County of Morris v. Fauver, 707 A.2d 958, 972-73 (N.J. 1998) (emphasis added)

(citations omitted).

Where the discovery rule has been applied in other jurisdictions, courts

have done so because it would be unjust to deprive plaintiffs of a cause of action

before they are aware of an injury. For example, in California:

the discovery rule applies to unique breach of contract

cases when: 1) “[t]he injury or the act causing the injury,

or both, have been difficult for the plaintiff to detect”; 2)

“the defendant has been in a far superior position to

comprehend the act and the injury”; or 3) “the defendant

had reason to believe the plaintiff remained ignorant [that]

he had been wronged.” [April Enters., Inc. v. KTTV and

Metromedia, Inc., 195 Cal.Rptr. 421, 436 (Cal. Ct. App.

1983)]. The rationale underlying application of the

discovery rule is that “plaintiffs should not suffer where

circumstances prevent them from knowing they have been

harmed . . . [and] defendants should not be allowed to

knowingly profit from their injuree’s ignorance.” Id.

El Pollo Loco, Inc. v. Hashim, 316 F.3d 1032, 1039 (9th Cir. 2003).

In Arizona, the Supreme Court held that the discovery rule can apply to

breach of contract actions because “the important inquiry in applying the discovery

28

rule is whether the plaintiff’s injury or the conduct causing the injury is difficult for

plaintiff to detect, not whether the action sounds in contract or in tort.” Gust,

Rosenfeld & Henderson v. Prudential Ins. Co. of Am., 898 P.2d 964, 968 (Ariz.

1995).

One commentator in discussing the discovery rule and computing a

limitations period from “when a cause of action accrues” noted the division, i.e., the

statutory period may begin either when the defendant commits the wrong or when

the plaintiff is injured. Marc M. Schneier, Esq., 28 No. 2 Constr. Litig. Rep. 10 (Feb.

2007). He explained:

This division is fundamental to the distinction between

contract and tort: a contract action may be brought

immediately upon breach, whereas a tort action cannot be

brought until the plaintiff suffers appreciable injury. The

reason for this distinction is that, immediately upon

material breach, a contract plaintiff is entitled to at least

nominal damages; however, a negligent defendant is liable

to no one until he or she causes injury. See 18 Samuel

Williston, Williston on Contracts § 2021A at 698 (3d ed.

1978); 51 Am.Jur.2d Limitations of Actions §§ 160 & 167

(2000) (contract and tort, respectively); and 54 C.J.S.

Limitations of Actions §§ 163 & 193 (2005) (contract and

tort, respectively); accord, Travis Pruitt & Assocs., P. C.

v. Bowling, 238 Ga.App. 225, 518 S.E.2d 453 (1999), 20

CLR 340 (1999).

Schneier, 28 No. 2 Constr. Litig. Rep. 10.

This distinction is significant. In a breach of contract action such as

here, the injury is the failure to perform or, in other words, the breach. See Freedom

Oil Works Co. v. Williams, 152 A. 741, 743 (Pa. 1930) (holding that where defendant

admitted there was a breach of contract, plaintiffs were entitled at least to nominal

29

damages); Wolfe v. Allstate Prop. & Cas. Ins. Co., 790 F.3d 487, 497 (3d Cir. 2015)

(stating, “[u]nder Pennsylvania law, if a plaintiff is able to prove a breach of contract

but can show no damages flowing from the breach, the plaintiff is nonetheless

entitled to recover nominal damages”).

In sum, we are faced with the binding precedent of this Commonwealth

wherein the discovery rule has been extended from the tort context to breach of

implied warranty actions and quasi-contractual matters of promissory estoppel and

unjust enrichment. See supra pp. 22-25. However, our Supreme Court has neither

expressed a blanket prohibition nor has it applied the discovery rule— a judicially

created doctrine— to a breach of contract action where a party is seeking to enforce

an express written contract that the party negotiated. Further, although the Superior

Court has applied the discovery rule to a breach of contract action, its decisions are

not controlling authority for this Court. Additionally, as noted by Justice Saylor,

other jurisdictions are split on the application of the discovery rule in a breach of

contract action.

We are mindful that the controlling law for determining when the

limitations period begins to run for a breach of contract action is when the cause of

action accrued, i.e., upon the occurrence of the breach. See 42 Pa.C.S. § 5502(a);

Erie Ins. Exch., 174 A.3d at 585-86; GAI Consultants, 120 A.3d at 423-24. Further,

we are mindful that the discovery rule is a judicially created doctrine with equitable

application. The Authority has not forwarded any compelling inequities as a reason

to create a special rule as to when the statute of limitations begins to run in a breach

of contract action based on an express written negotiated contract. The mere fact

that a municipality is involved is not a sufficiently compelling ground. Because our

Supreme Court has not extended the discovery rule, a judicially created equitable

30

doctrine, to the arena of breach of contract actions involving express written

negotiated contracts,15 we decline to do so.

In declining to extend the discovery rule to breach of contract actions

based on an express written negotiated contract in the absence of precedent from our

Supreme Court, we note that the parties to a contract are not without recourse and,

thus, equity does not demand a contrary result. As the Wisconsin Supreme Court

reasoned when it refused to apply the discovery rule to a breach of contract action,

“a contract claimant often has a significant amount of control over its risk of loss.”

CLL Assocs. Ltd., 497 N.W.2d at 118.

The parties here had choices over the material to use and the inspection

procedures, and they specified those in the agreement.16 See Bid, Div. IX,

15

We note the case of Gustine I in which the owners of a shopping mall sued the

architectural contractor, as well as others, for, inter alia, breach of contract, asserting claims arising

out of a written construction contract. Gustine I, 842 A.2d at 338-39. Notably, the only issue

before our Supreme Court was whether the breach of contract claim was subject to the Judicial

Code’s four-year or six-year statute of limitations period. Id. at 338. Although the appellants, in

arguing for a longer limitations period, stated that Pennsylvania recognizes the discovery rule in

breach of contract actions, id. at 344, the Court did not mention whether the appellants cited any

authority in support of such claim, and the Court’s note appended to that statement only cites

Crouse relative to the discovery rule. See id. at 344 n.8. As discussed, supra, Crouse asserted a

claim based on the quasi-contractual theory of promissory estoppel, not a breach of contract claim

based on a written contract.

In Gustine I, on remand to the Superior Court, the court held that the contract language

(stating that the “applicable statute of limitations shall commence to run” not later than the date of

substantial completion) precluded application of the discovery rule. Gustine II, 892 A.2d at 836.

16

The agreement states that the “Contract Documents form the Contract for construction.”

Div. II, Information to Bidders, art. I- Definitions (.14), R.R. at 303a. The “Contract Documents”

consist of the following:

the Owner-Contractor Articles of Agreement, The Contract

Provisions, Information to Bidders, Legal Section, Proposal and

Bidding Sheets, Scope of Work, Statement of Bidders

Qualifications, Engineering Specifications (General and Detail),

Plans as defined in the Scope of Work, Schedule of Drawings, and

31

Engineering Specifications, R.R. at 408a-85a. For example, the contract provided

that the engineer would be the Authority’s representative during construction until

final payment is due. Bid, Div. VI, Contract Provisions, art. 1, § 1.01(.2); R.R. at

353a. The contract further provided that the engineer would visit the site at

appropriate intervals to become familiar with the progress and quality of work. Id.

at § 1.01(.4); R.R. at 353a. The contract further required Port Vue to have copies of

the contract documents and an additional set of plans at the work site for use by the

engineer and the Authority, and provided for observation of the work at all times by

the engineer and the Authority. Id. at § 1.01(.4-.5); R.R. at 353a; see also Bid, Div.

VI, Contract Provisions, art. 3, § 3.11(.1); R.R. at 366a.

We recognize that despite Glenn’s acknowledgement that the work

could have been visually inspected at any time by climbing down the manhole with

a flashlight, N.T. at 56, R.R. at 119a, the trial court found that “technology for video

inspection of the work was not readily available at the time and physical inspection

of the work after it was completed was not possible due to the subsurface nature of

the project.” Trial Court Opinion at 4. However, parties to a contract have choices

over inspection procedures and can negotiate those in advance. That was done here

using various procedures that were available to the parties at the time. Indeed, the

bid specifications for the project set forth documents that Port Vue would be

responsible for providing upon completion of the project and expressly required,

among other things:

shall include the Public Advertisement, Addenda (if any), Change

Orders, as issued, Notice of Award, Notice to Proceed, all Bonds

and Insurance as defined elsewhere, and the Federal Guideline

Requirements, if applicable.

Div. II, Information to Bidders, art. 1, Definitions (.15), R.R. at 304a.

32

“Record” or “As-Built” Drawings

01. The Contractor shall be responsible for supplying a

clean and legible set of final drawings clearly showing the

final position of all equipment or materials used in

construction of the project. This set of drawings must be

turned over to the Engineer and approved by the Owner

before the final payment is released on the project. This

drawing must be on the same data set as the existing

drawing and a CAD.dwg file of the manholes supplied.

Bid, Div. V, Scope of Work, Part 4.00, § 4.04(.01); R.R. at 345a. The contract also

provided for the engineer to conduct reviews to determine final completion. Bid,

Div. VI, Contract Provisions, art. 1, § 1.06(.2); R.R. at 356a. Port Vue also agreed

under the contract to make repairs for a period of 18 months after the date of

completion and to deliver a bond to the Authority to ensure completion. Bid, Div.

VI, Contract Provisions, art. 3, § 3.06(.14); R.R. at 364a; see id. at § 3.18(.2); R.R.

at 370a. The Authority does not argue, nor does it point to any contract provision,

that purportedly provides for a statute of limitations period longer than the four years

allowed by law upon the occurrence of a breach. This “increased ability of potential

contract claimants to protect themselves in the first instance lessens the need to

provide them an opportunity for legal redress.” CLL Assocs. Ltd., 497 N.W.2d at

118. Further, from a practical equitable perspective, to apply the discovery rule to

the situation here would leave contractors with prolonged and open-ended liability

and an unwillingness to contract with municipalities given an open-ended exposure

period.

Because we decline to extend the discovery rule to this breach of

contract action based on an express written negotiated contract in the absence of

Pennsylvania Supreme Court precedent doing so, we conclude that the trial court

erred as a matter of law in applying the discovery rule to the Authority’s breach of

33

contract claim and, therefore, in concluding that the complaint was timely. See

Crouse, 745 A.2d at 611 (stating whether a complaint is timely filed is a matter of

law). Nonetheless, we must address the Authority’s alternative argument that Port

Vue is estopped from asserting the statute of limitations as a defense under the

doctrine of fraudulent concealment.

(iii) Fraudulent concealment

The discovery rule is distinct from the issue of whether a

party is equitably estopped from invoking the statute of

limitations. Fine v. Checcio, 582 Pa. 253, 870 A.2d 850

(2005). The discovery rule operates to toll the statute of

limitations during the period the plaintiff’s injury or its

cause was neither known nor reasonably knowable to the

plaintiff. Id. The separate doctrine of fraudulent

concealment tolls the statute based on an estoppel theory

and provides that a defendant may not invoke the statute

of limitations if through either intentional or unintentional

fraud or concealment, the defendant causes the plaintiff to

relax his vigilance or deviate from his duty of inquiry into

the facts. Id. Thus, the former doctrine involves a

plaintiff’s lack of knowledge and the latter doctrine

pertains to a defendant’s conduct after the cause of action

arose.

Gustine II, 892 A.2d at 835 n.2.

The doctrine of fraudulent concealment is rooted in equity. 4 West’s

Pa. Prac., Torts: Law and Advocacy § 17.6 (November 2018) (citing Nesbitt v. Erie

Coach Co., 204 A.2d 473, 476 (Pa. 1964)). Our Supreme Court has explained that

“[t]he doctrine does not require fraud in the strictest sense encompassing an intent

to deceive, but rather, fraud in the broadest sense, which includes an unintentional

deception.” Fine, 870 A.2d at 860 (citing Deemer v. Weaver, 187 A. 215 (Pa. 1936)).

“The plaintiff has the burden of proving fraudulent concealment by clear, precise,

34

and convincing evidence.” Id. “Mistake, misunderstanding or lack of knowledge in

themselves do not toll the running of the statute of limitations.” Id. at 857. “While

it is for the court to determine whether an estoppel results from established facts, it

is for the jury [or judge sitting as the factfinder] to say whether the remarks that are

alleged to constitute the fraud or concealment were made.” Id. at 860 (citing Nesbitt,

204 A.2d at 476).

The trial court never addressed the Authority’s argument regarding

fraudulent concealment, presumably because it was not necessary to do so given the

trial court’s determination that the discovery rule applied to toll the statute of

limitations.17 Our ruling, however, makes it necessary to reach this issue. Because

factual determinations are necessary, we must remand this matter to the trial court

to address this issue.

Accordingly, we vacate the trial court’s order and remand the matter to

the trial court to issue a new decision determining whether Port Vue is estopped from

asserting the statute of limitations as a defense to the Authority’s claim under the

doctrine of fraudulent concealment.18

__________________________________

CHRISTINE FIZZANO CANNON, Judge

17

We note the Authority raised the issue of fraudulent concealment before the trial court.

See Authority’s Complaint ¶ 18, 20; Authority’s Brief in Opposition of Port Vue’s Motion for

Post-Trial Relief, R.R. at 53a-54a.

18

Because of our disposition, we do not reach the issue of whether the damages awarded

to the Authority exceeded those allowed by law.

35

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Carmen Carulli and Barbara :

Carulli, husband and wife :

:

v. :

:

North Versailles Township :

Sanitary Authority :

:

v. :

:

Port Vue Plumbing, Inc., : No. 751 C.D. 2017

Appellant :

ORDER

AND NOW, this 13th day of August, 2019, the order of the Allegheny

County Court of Common Pleas (trial court) is VACATED and the matter is

REMANDED to the trial court to issue a new decision in accordance with the

foregoing opinion.

Jurisdiction relinquished.

__________________________________

CHRISTINE FIZZANO CANNON, Judge

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Carmen Carulli and Barbara Carulli, :

husband and wife :

:

v. :

:

North Versailles Township Sanitary :

Authority :

: No. 751 C.D. 2017

v. :

: Argued: October 17, 2018

Port Vue Plumbing, Inc., :

Appellant :

BEFORE: HONORABLE MARY HANNAH LEAVITT, President Judge

HONORABLE RENÉE COHN JUBELIRER, Judge

HONORABLE P. KEVIN BROBSON, Judge

HONORABLE PATRICIA A. McCULLOUGH, Judge

HONORABLE ANNE E. COVEY, Judge

HONORABLE CHRISTINE FIZZANO CANNON, Judge

HONORABLE ELLEN CEISLER, Judge

DISSENTING OPINION

BY JUDGE McCULLOUGH FILED: August 13, 2019

I dissent respectfully, yet earnestly, from the Majority’s conclusions

that the Allegheny County Court of Common Pleas (trial court) erred in applying

the discovery rule—or, more precisely, that the discovery rule does not apply in

this case—and that a remand is required in order for the trial court to address the

issue of whether the statute of limitations (SOL) was tolled under the doctrine of

fraudulent concealment. To me, both of these conclusions are unnecessary and

unwarranted.

First, in my view, a remand to the trial court would be entirely

redundant because the trial court already issued the factual findings necessary for

this Court to readily conclude that Port Vue Plumbing, Inc. (PVP) engaged in

conduct that amounted to fraudulent concealment. Specifically, as found by the

trial court, PVP made an affirmative misrepresentation to North Versailles

Township Sanitary Authority (Authority) that it performed the contract and

replaced the sewer lines, and the Authority relied on that misrepresentation and

was unable to discover the non-performance through the exercise of reasonable

diligence.1 Under long-standing precedent, these facts are sufficient to establish

1

In its opinion, the trial court found and determined that the SOL was tolled until the

point in time in which,

The Authority became aware that PVP failed to complete the work

as required by the contract. PVP contracted with the Authority to

complete the entire project. On all occasions PVP represented to

the Authority that all work required under the contract was

completed. The Authority relied on PVP’s representation that all

work had been completed because technology for video inspection

of the work was not readily available at the time and physical

inspection of the work after it was completed was not possible due

to the subsurface nature of the project. Testimony was provided at

trial that conducting a video inspection of a newly installed sewer

line was not a standard practice at the time. Without such special

equipment, inspection of the site was limited to surface conditions

and there was no indication that PVP had not completed the work

or that there was a problem with the work. PVP was fully

qualified to complete the work, had performed work for the

Authority on prior occasions, and continually informed

representatives of the Authority that the work was being

completed. In light of the circumstances, it was reasonable for the

Authority to rely on the representations of PVP that all work had

been completed.

There was nothing to put the Authority on notice that the work

may not have been completed until [the date on which] the

(Footnote continued on next page…)

PAM – 2

fraudulent concealment and toll the applicable SOL as a matter of law. See, e.g.,

Nesbitt v. Erie Coach Co., 204 A.2d 473, 477 (Pa. 1964) (concluding that the SOL

was tolled via fraudulent concealment where “the agents of the defendant misled

the plaintiff into believing” that a set a circumstances existed and “lulled her into a

sense of false security”); cf. Toy v. Metropolitan Life Ins. Co., 928 A.2d 186, 207

(Pa. 2007) (stating that “the recipient of an allegedly fraudulent misrepresentation

is under no duty to investigate its falsity in order to justifiably rely”).2

Second, while fraudulent concealment requires a showing of at least

unintentional deception, Nesbitt, 204 A.2d at 477, be it a misrepresentation or

concealment, on the part of a defendant, the discovery rule does not. Instead, as

the Majority acknowledges, the discovery rule is a distinct legal principle that

focuses upon a plaintiff’s lack of knowledge with respect to his/her injury or its

cause. See Fine v. Checcio, 870 A.2d 850, 857-61 (Pa. 2005); Nesbitt, 204 A.2d

(continued…)

Authority was notified that the basement of a house along Bevan

Road was flooded with raw sewage. Upon such occurrence, the

Authority acted with reasonable diligence to inspect the line and it

was then that the Authority discovered the failure of PVP to

complete the work. For the aforementioned reasons, the

Authority's claims are not time barred.

Trial court op. at 4. Notably, although the trial court did not use the words “fraudulent

concealment” in its opinion, the trial court clearly applied the doctrine in theory.

2

See also Amodeo v. Ryan Homes, Inc., 595 A.2d 1232, 1236-37 (Pa. Super. 1991)

(concluding that principles of estoppel prevent a party from raising a SOL defense where the

party agrees to perform a repair, represents to the other party that the repair was performed, and

the other party relied upon the representation); Via Net v. TIG Insurance Co., 211 S.W.3d 310,

313 (Tex. 2006) (“Due diligence may include asking a contract partner for information needed to

verify contractual performance. If a contracting party responds to such a request with false

information, accrual may be delayed for fraudulent concealment.”).

PAM – 3

at 476-77; Gustine Uniontown Associates, Ltd. v. Anthony Crane Rental, Inc., 892

A.2d 830, 835 n.2 (Pa. Super. 2006). Since this matter can be disposed based

solely upon the doctrine of fraudulent concealment, I believe that the Majority

should refrain from addressing and deciding the broader issue of whether the

discovery rule should apply to breach of contract claims in the context of this

particular case where a misrepresentation is present. I find that such judicial

restraint is absolutely imperative considering the body of case law from our

Supreme Court, which, at the very least, strongly suggests that, as a matter of

statutory construction, the discovery rule is implied or read into the term “accrued”

in section 5502(a) of the Judicial Code, 42 Pa.C.S. §5502(a), and applies to each

and every SOL listed in subchapter B of Chapter 55 of the Judicial Code, 42

Pa.C.S. §§5521-38, necessarily including the SOL in section 5525(8) for contract

actions based on an express written agreement, 42 Pa.C.S. §5525(8).3 See

Pastierik v. Duquesne Light Co., 526 A.2d 323, 325 (Pa. 1987) (holding that

“application of the discovery rule” occurs when there are “[s]tatutory references to

. . . the accrual of a ‘cause of action’” because these claims “are subject to judicial

interpretation as to the degree of knowledge a plaintiff must possess before the

statute will start to run”); see also Wilson v. El Daief, 964 A.2d 354, 363 (Pa.

2009) (“[T]he discovery rule . . . is now appropriately regarded as an application of

statutory construction arising out of the interpretation of the concept of the

‘accrual’ of causes of action. See 42 Pa.C.S. §5502(a).”); Fine, 870 A.2d at 857-58

3

Section 5502 contains the heading, “Method of computing periods of limitation

generally,” and states in relevant part: “The time within which a matter must be commenced

under this chapter shall be computed . . . from the time the cause of action accrued . . . .” 42

Pa.C.S. §5502(a) (emphasis added). Undoubtedly, the four-year limitation period in section

5525 of the Judicial Code for actions sounding in contract is part of Chapter 55.

PAM – 4

(reiterating that section 5502(a) provides “that limitations periods are computed

from the time the cause of action accrued” and emphasizing that even if a cause of

action “has accrued and the prescribed statutory period has run,” the discovery rule

is an “exception[] that act[s] to toll the running of a statute of limitations,” and that

“the salient point giving rise to its application is the inability of the injured, despite

the exercise of reasonable diligence, to know that he is injured and by what

cause”); Crouse v. Cyclops Industries, 745 A.2d 606 (Pa. 2000) (concluding that a

count for promissory estoppel, although technically a “quasi-contract” claim, was

governed by the four-year SOL in section 5525(4) for breach of contract claims

and, more importantly, was subjected to the discovery rule).

Moreover, following the above precedent from our Supreme Court,

the Superior Court has concluded definitively that “[t]he discovery rule in

Pennsylvania applies to all causes of action, including breach of contract.”

Morgan v. Petroleum Products Equipment Co., 92 A.3d 823, 828 (Pa. Super.

2014); see, e.g., Levenson v. Souser, 557 A.2d 1081, 1086-87 (Pa. Super. 1989) (en

banc) (concluding that where the cause of action “does not fix a definite event as

the beginning of the limitations period” and is instead subjected to section 5502(a)

and the concept of “accrual” enunciated therein, the discovery rule applies

“because the accrual of the cause of action is not fixed as one definitively

established event and the existence of the cause of action may not be reasonably

ascertainable within the limitations period”). Likewise, in cases concerning

alleged breaches of express oral and written contracts, federal district courts have

held that “Pennsylvania recognizes a discovery rule in breach of contract cases.”

Creghan v. Procura Management, Inc., 91 F. Supp. 3d 631, 649 (E.D. Pa. 2015);

accord Slamon v. Carrizo (Marcellus) LLC (M.D. Pa., No. 3:16-CV-2187, filed

PAM – 5

September 5, 2017) (unreported), 2017 U.S. Dist. LEXIS 143242, at *31.

Ultimately, this case law, although not binding, should provide this Court with

additional cause for concern, prompting hesitation and reluctance to decide an

issue that need not be decided and “to tread lightly in our examination.” In re

Tribune Media Co., 799 F.3d 272, 276 (3d Cir. 2015).

The Majority says that “[o]ur Supreme Court, however, has not

pronounced the applicability of the discovery rule to a breach of contract action

based on an express written contract negotiated at arms’ length.” Slip op. at 24.

However, the Majority has not cited one case where a court has concluded that the

discovery rule does not apply to any of the causes of action in subchapter B of

Chapter 55 of the Judicial Code. Absent such authority, and in light of the

Pennsylvania case law discussed above, I cannot find persuasive value in the

foreign jurisdictions that the Majority relies upon to reach its conclusion and must

consider these cases to be of little to no value because they appear to be

inconsistent with the law of our state.

Rather, on balance, I find that the foreign jurisdictions that have

concluded that the discovery rule applies in breach of contract actions represents a

more considered and reasoned judgment on the issue—one that is in harmony with

Pennsylvania Supreme Court precedent and the spirit of Pennsylvania law. Under

this approach, the discovery rule would apply to an alleged breach of a written

contract “in situations where the breach is ‘inherently undiscoverable,’ ‘inherently

unknowable,’ or ‘difficult to detect,’” Individual Healthcare Specialists, Inc. v.

BlueCross BlueShield of Tennessee, Inc., 566 S.W.3d 671, 711-12 & n.43 (Tenn.

2019), but would not apply in cases where the plaintiff fails to exercise due

diligence, specifically “cases where the plaintiff’s injury is open and obvious.”

PAM – 6

Gust, Rosenfeld & Henderson v. Prudential Insurance Co. of America, 898 P.2d

964, 967 (Ariz. 1995). Indeed, our Supreme Court has stressed that “[t]he salient

point giving rise to the equitable application of the exception of the discovery rule

is the inability, despite the exercise of diligence by the plaintiff, to know of the

injury,” Pocono International Raceway, Inc., v. Pocono Produce Inc., 468 A.2d

468, 471 (Pa. 1983), and “[t]he rationale behind the discovery rule is that it is

unjust to deprive a plaintiff of a cause of action before the plaintiff has a

reasonable basis for believing that a claim exists.” Gust, 898 P.2d at 967. In my

view, the underlying reasons supporting the discovery rule are not diminished in

any way based upon the status of a suit being labeled a contract claim, for the

discovery rule “relates more to the circumstances under which a legal duty is

breached and less to the nature of the cause of action.” Id. As the Arizona

Supreme Court explained:

In fact, we find little to distinguish tort and contract such

that the discovery rule should properly apply to one but

not to the other. The difference between tort and contract

liability has become an increasingly difficult distinction

to make. But insofar as tort and contract are

distinguishable, [the defendant’s] arguments do not

persuade us. We have said that the statute of limitations

serves to protect defendants and courts from stale claims

where plaintiffs have slept on their rights. However

whether a tort victim or contract claimant, a blamelessly

uninformed plaintiff cannot be said to have slept on his

rights. Furthermore, the problems associated with stale

litigation (e.g., failing memory, unavailable witnesses)

are no more acute in contract claims than they are in tort.

And in either case, the requirement that parties exercise

reasonable diligence safeguards against cases where a

plaintiff has truly allowed his claim to become stale. We

also reject the suggestion that application of the

discovery rule to contract cases would eviscerate the

statute of limitations in commercial disputes. The

PAM – 7

discovery rule has applied uniformly in tort cases for

some time, and we do not believe that the statute of

limitations has ceased to serve its purpose in tort cases.

Id. at 968-69 (internal citations and quotation marks omitted).

Therefore, I believe that the Majority lacks sufficient justification to

create a special exception for written contracts—an exception that, apparently for

the first time in the history of Pennsylvania law, exempts application of the

discovery rule from a cause of action listed in subchapter B of Chapter 55 of the

Judicial Code. In the end, though, I would decline to reach the issue of whether the

discovery rule applies to actions founded upon an express written contract and

would conclude that, under the doctrine of fraudulent concealment, the Authority’s

claim is not barred by the SOL.

Hence, I respectfully dissent.

________________________________

PATRICIA A. McCULLOUGH, Judge

PAM – 8

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.