Opinion

Podrez Enterprise, LLC

Court
Armed Services Board of Contract Appeals
Filed
Jul 2, 2019
Status
Published
On the bench
Shackleford
Cited by
0 cases
Authority
More cited than 8.3%

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- )

)

Podrez Enterprise, LLC ) ASBCA No. 61971

)

Under Contract No. W911S2-18-P-1546 )

APPEARANCE FOR THE APPELLANT: Ms. Tara J. Powell

Executive Administrator

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq.

Army Chief Trial Attorney

MAJ Wayne T. Branom III, JA

Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD

This is an appeal from a contracting officer's final decision terminating the

captioned contract for cause. Appellant has elected Rule 12.2, Expedited Procedure,

and the parties have elected to submit the appeal on the record without a hearing,

pursuant to Board Rule 11. A decision under Board Rule 12.2 shall have no value as

precedent, and in the absence of fraud, shall be final and conclusive and may not be

appealed or set aside. The government filed a Rule 11 brief and no further briefing

was made by either party. In addition to the government's Rule 11 brief, the record

consists of the government's Rule 4 file as supplemented and the pleadings, including

documents attached to appellant's complaint. For the reasons stated below, the appeal

is denied.

SUMMARY FINDINGS OF FACT

1. In early August 2018, Request for Quotations (RFQ) No. H00DLRCFR003l

was issued by Fort Hood for 220 Railcar Spanners described as follows:

Part# RS 20 24 084 18 STUB Q8372, Rail Spanner with

2" high Stub Toe 24" wide/ 84" long/ 4" thick Rated:

20,000lbs per single spanner (40,000lbs per pair) Improved

"kicker plate" utilizing tubes instead of angles Stub Toe

increases lifespan Items must meet the requirements listed

above no variations will be accepted!

(Compl., attach. A) Moreover, the RFQ provided that any award would be subject to

certain commercial item terms and conditions, including, among others, FAR 52.211-6,

I

BRAND NAME OR EQUAL and FAR 52.212-4, CONTRACT TERMS AND CONDITIONS-

COMMERCIAL ITEMS. (Id.)

2. On or about August 22, 2018 appellant, Podrez Enterprise, LLC (Podrez or

appellant) responded to the RFQ, specifically referencing that the procurement was brand

name or equal, and that no variations were acceptable (R4, tab 2 at 1, 3). The quote was

for a quantity of 220 at $566.50 each for a total quote of $124,630.00 (id. at 2).

3. The quote further iterated the description of the product upon which it was

quoting, as follows:

Seller Line Item Details:

Manufacturer: Podrez Enterprise

Part Number: CSTMRS

Description: Spanner - MANUFACTURED FROM

HIGH-STRENGTH, LIGHTWEIGHT ALUMINUM -

Non-skid 2" wide traction cleat self-cleaning surface with

5 serrated teeth - Extra large beam spacing for heavy chain

and tie-downs-2" HIGH STUB TOE-24" W x 84" L x

4" thick-RATED 20,000 LBS PER SPANNER/40,000

LBS PER PAIR-KICKER PLATE UTILIZES TUBES

INSTEAD OF ANGLE - STUB TOE INCREASES

LIFESPAN 100% MADE IN USA SMALL BUSINEES

THE BERRY AMENDMENT ACT COMPLAINT [sic]

BUY AMERICAN ACT COMPLIANT SHIPPING= FOB

DESTINATION CONUS -

Said description was substantially similar to the language contained in the RFQ (R4,

tab 2 at 3).

4. On August 24, 2018, the government awarded to Podrez Contract

No. W911S2-18-P-1546 (R4, tab 6 at 1). The contract incorporated by reference

FAR 52.212-4, CONTRACT TERMS AND CONDITIONS -COMMERCIAL ITEMS (JAN 2017)

which stated in pertinent part:

(m) Termination/or cause. The Government may

terminate this contract, or any part hereof, for cause in the

event of any default by the Contractor, or if the Contractor

fails to comply with any contract terms and conditions, or

fails to provide the Government, upon request, with

adequate assurances of future performance. In the event of

termination for cause, the Government shall not be liable

to the Contractor for any amount for supplies or services

2

not accepted, and the Contractor shall be liable to the

Government for any and all rights and remedies provided

by law. If it is determined that the Government improperly

terminated this contract for default, such termination shall

be deemed a termination for convenience.

(R4, tab 6 at 4) The description of the items in the contract was the same as the

specifications returned with appellant's quote (R4, tab 6 at 3). The contract required

appellant to deliver the rail spanners to Fort Hood, TX by September 24, 2018 (R4,

tab 6 at 3-4 ).

5. Appellant failed to meet the September 24, 2018 due date and on

October 22, 2018, the contracting officer (CO) threatened to terminate the contract for

cause due to non-delivery (R4, tab 7 at 4). Thereafter the CO granted appellant's

request to extend the due date to December 3, 2018 (R4, tab 8 at 1).

6. The 220 rail spanners were delivered to Fort Hood in two partial shipments

on December 3 (165 units) and 6 (55 units), 2018 (R4, tab 23 at 4). David Slaughter,

Plans and Operations Chief of the Logistics Readiness Center at Fort Hood, and a prior

maintenance technician and manager of technicians, stated in a sworn declaration:

3. [In early December 2018] we examined the first pallet

load of spanners .... Our initial impression was of

disappointment, due to the apparent poor quality of

workmanship. Welds were not smooth and pure and the

thickness of bracing materials seemed shy of

specifications. Our Quality Control team and certified

welders were called... to make a preliminary assessment.

4. While waiting for the maintenance personnel, we

removed one spanner from the pallet and placed it on the

ground: I stepped on the middle if the spanner and moved

up and down without jumping and the spanner flexed

significantly, convincing all of us, that if it flexed that

much with 200 pounds, it would not support 2,000 pounds.

5. [The maintenance personnel] confirmed the poor

welding craftsmanship and further pointed out the many

areas of inferior welding.

(R4, tab 57, Slaughter decl. ,r,r 3-5)

3

7. Rex Wheeler, a maintenance supervisor at Fort Hood, set forth in a sworn

declaration his significant experience in the field and was tasked, along with his senior

welder, to complete an inspection of the spanners on December 4, 2018. They

submitted a report on December 6, 2018, which concluded that the spanners did not

meet the contract specifications. More specifically, they found:

a. There were several instances where the measurements

did not meet the specifications required.

b. Some of the metal products used did not meet the

specifications. For example square tubing should have

been used for the main support beams and kicker plate.

However, the vendor fabricated the main support beams

from flat sheet folded into channel and then welded flat

sheet to box the channel in. The kicker plate was

fabricated from aluminum angle instead of square tubing.

These two instances of noncompliance dramatically affect

the structural integrity of the spanner and affect the

spanners' ability to safely support the load requested.

c. During the inspection it was noted that there were

several instances where the welding work was not in

compliance with current industry standards. The welding

used in the assembly process was not standardized on each

spanner. Some did not have enough welding applied to

make the product structurally sound. There were welds

that lacked penetration which affects structural integrity.

There were welds that had too much penetration that

caused holes to be burnt into the structure or caused a

thinning of material, both of which can affect the structural

integrity of the spanner.

d. Overall the spanners did not meet the specifications

outlined and therefore were deemed unsafe to use.

Because of the concern for safety we did not attempt to put

the spanners under any load.

(R4, tab 58, Wheeler decl. ,r,r 3.a-d)

8. The Army completed an inspection report consisting of numerous detailed

photographs with a key to demonstrate how the items delivered did not conform to the

specifications and drawings in the contract (R4, tab 10; see also gov't br. proposed

finding of fact 16).

II

4

I

9. On December 17, 2018, the government rejected the shipment of spanners

for the reasons set forth as follows:

The 220 rail spanners did not meet the dimensions called

for [in] the solicitation; the spanners were only 23 9/ 16

inches wide but the solicitation called for 24 inches. The

aluminum tubing was not 4 inche[s] high but only 3 1/2

inches high. The material was not properly assembled in

accordance with the solicitation, welds were poorly struck,

incomplete welds, and missing welds were prevalent

throughout all spanners.

(R4, tab 11 at 2) The full inspection report including photographs and keys were

provided to Podrez on December 19, 2018 (R4, tab 12 at 2). We find that the items

were not in conformance with the contract specifications.

10. On January 7, 2019, the CO issued a show cause to appellant why the

contract should not be terminated for cause due to appellant's failure to deliver

spanners that conformed to the contract. Podrez was given 10 days to explain why its

failure to deliver was without fault, or else the contract would be terminated for cause.

(R4, tab 27 at 1)

11. Appellant responded to the show cause on January 10, 2019 claiming it was

unaware of a drawing upon which the rejection of the goods was based in part, when

in fact appellant had referred to said drawing in its own quote responding to the RFQ

(R4, tab 33 at 5).

12. Nevertheless, on January 15, 2019, the CO attempted to rectify the

situation by allowing appellant to retrieve the nonconforming items and bring them

into conformance, granting an additional 30 days from retrieval to effect conformance

(R4, tab 37 at 1; tab 59, Brown decl. ,-i 7).

13. By February 4, 2019, the items had not been picked up from Fort Hood and

the CO gave appellant until 1400 on February 7, 2019 to provide a time line for

retrieval or else the contract would be terminated for cause (R4, tab 41 at 1). Rather

than provide said timeline, appellant advised that if the contract were terminated they

would "dispute it and have it reversed and then file a claim for TERMINATION FOR

CONVENIENCE" (R4, tab 42 at 1).

14. Thereafter the CO, on February 8, 2019, issued a final decision terminating

the contract for cause and on February 11, 2019 modified the contract accordingly

(R4, tabs 43-45, 4 7).

5

15. Appellant timely appealed the termination for cause to the Board which we

docketed as ASBCA No. 61971. Only the termination for cause is at issue here.

DECISION

A termination for default is a drastic sanction which should be imposed (or

sustained) only for good grounds and on solid evidence. Lisbon Contractors, Inc. v.

United States, 828 F.2d 759, 765 (Fed. Cir. 1987) (quoting JD. Hedin Constr. Co. v.

United States, 408 F .2d 424, 431 (Ct. Cl. 1969)). Though this is an appeal brought by

Podrez, because a termination for default is essentially a government claim, the

government bears the initial burden of proving "by a preponderance of the evidence that

a termination for default was justified." Keystone Capital Services, ASBCA No. 56565,

09-1 BCA, 34,130 at 168,753 (citing Lisbon Contractors, 828 F.2d at 765). "If the

government establishes a prima facie case justifying the termination, the burden shifts to

the contractor to prove the default was excusable." Truck/a Services, Inc., ASBCA

Nos. 57564, 57752, 17-1 BCA, 36,638 at 178,445 (citingADTConstr. Grp., Inc.,

ASBCA No. 55358, 13 BCA, 35,307 at 173,312).

Based upon the evidence of record we find that the spanners did not comply

with the contract, that appellant failed to take corrective action when given the

opportunity to do so and that it has provided no reason for its failure to perform in

accordance with the contract (findings 9, 13). Appellant has presented no evidence

that the spanners were in compliance with the contract.

Appellant filed a document entitled "Affirmative Statement of Disputed Facts"

on April 8, 2019. This document does not include any additional evidence in support

of its case. It merely makes conclusory statements about the government's case and

states that it disputes said statements and wants documents in support of them. Those

documents in support of the government's decision to terminate for cause are in the

Rule 4 file submitted by the government and clearly support the termination action.

The "Conclusion" of the appellant's affirmative statement is quoted in full as follows

because that is the most cogent argument it makes in this record:

The goods delivered by appellant conformed to the

specifications of the contract. No intended use was

provided by the Government. Appellant did not agree to

the corrective action plan offered by the Government and

believes the actions to be an abuse of discretion. The

appellant advised the Government that the specifications

provided by the government were defective, improper, and

invalid. The appellant completed the contract under the

terms of the contract. Appellant believed the actions taken

6

by the Government were coercive; the Government refused

to consider any corrective action plans proposed by

appellant. Appellant believes the actions taken by the

contracting officer violated the Government's implied duty

of good faith and fair dealing, as a result, terminated the

contact improperly.

Unfortunately for appellant, there is no evidence in this record to support those

conclusions. Accordingly the termination for cause was proper and fully supported by

the record.

CONCLUSION

The appeal is denied.

Dated: July 2, 2019

RICHARD SHACKLEFORD

Administrative Judge

Vice Chairman

Armed Services Board

of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA No. 61971, Appeal of Podrez

Enterprise, LLC, rendered in conformance with the Board's Charter.

Dated:

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

7

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.