Opinion

Precision Homes, Inc. v. The Metropolitan Government of Nashville and Davidson County

Court
Court of Appeals of Tennessee
Filed
Jun 6, 2019
Status
Published
On the bench
Judge Andy D. Bennett
Cited by
0 cases
Authority
More cited than 7.9%

The opinion

06/06/2019

IN THE COURT OF APPEALS OF TENNESSEE

AT NASHVILLE

April 4, 2019 Session

PRECISION HOMES, INC. V. THE METROPOLITAN

GOVERNMENT OF NASHVILLE AND DAVIDSON COUNTY

Appeal from the Chancery Court for Davidson County

No. 17-467-I Claudia Bonnyman, Chancellor

No. M2018-01322-COA-R3-CV

The owner of three lots located in a water quality buffer zone along the Cumberland

River filed a request for a variance to allow the owner to build a small house on each lot.

The Metropolitan Stormwater Management Committee denied the request for a variance,

and the chancery court affirmed the committee’s denial. We affirm the trial court’s

judgment in all respects.

Tenn. R. App. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed

ANDY D. BENNETT, J., delivered the opinion of the Court, in which RICHARD H. DINKINS

and W. NEAL MCBRAYER, JJ., joined.

Shawn Ray Henry, Nashville, Tennessee, for the appellant, Precision Homes, Inc.

Lora Barkenbus Fox and Catherine Jane Pham, Nashville, Tennessee, for the appellee,

Metropolitan Government of Nashville and Davidson County.

OPINION

FACTUAL AND PROCEDURAL BACKGROUND

In 1999, the Metropolitan Government of Nashville and Davidson County

(“Metro”) instituted stormwater regulations that created water quality buffers.1 Precision

Homes, Inc. (“Precision”) owns three vacant lots on Miami Avenue along the

Cumberland River and entirely within the Zone 1 water quality buffer. This water quality

buffer includes the floodway for the Cumberland River plus an additional 50 feet. Metro

1

“Buffer” is defined as “[a] vegetated area, including trees, shrubs and herbaceous vegetation, which

exists or is established to protect community water. Alteration of this natural area is strictly limited.”

Metro Stormwater Mgmt. Regs. App. B, Definitions.

Stormwater Mgmt. (“SWM”) Regs. § 6.9.2. Zone 1 is a “‘no disturb zone,’ where the

vegetation cannot be disturbed, removed or replanted unless a buffer restoration plan has

been approved” by the Metro Department of Water and Sewerage Services. Id.

Construction is not permitted in Zone 1 without a variance. SWM Regs. § 6.9.3. The

three lots, purchased by Precision in 2004, were inundated during the May 2010 flood.

On November 2, 2016, Precision submitted a request for a variance from the

stormwater regulations to the Stormwater Management Committee (“SWMC” or “the

Committee”) so that it could build an 800-square-foot one-bedroom house on each lot. In

its statement of hardship, Precision stated: “This lot is 100% within the floodway or the

zone 1 Stream Buffer and therefore the lot cannot be utilized without the requested

variance.”

The SWMC first met about Precision’s variance request at a public hearing on

December 1, 2016. The Committee voted to defer the matter to allow SWMC staff to

evaluate possible options for purchase of the properties or a land swap. At the SWMC’s

next meeting, on January 5, 2017, the staff reported that there was no money available to

purchase the lots and no possibility of a land swap. The Committee considered a motion

to approve Precision’s variance request, and the motion failed by a vote of four to two.

On March 2, 2017, the SWMC considered a request filed by Precision that the Committee

rehear its variance case. The SWMC voted to rehear the case. At its April 6, 2017

meeting, the SWMC reheard the variance request, and a motion to approve the variance

failed by a vote of three to three.

Precision filed a petition for writ of certiorari in the chancery court and, in an

order entered on June 27, 2018, the court affirmed the decision of the SWMC. The court

found that the “Committee’s decision was based on substantial and material evidence and

was not arbitrary and capricious.”

On appeal, Precision presents a number of arguments to support its position that

the trial court erred in affirming the decision of the SWMC, including challenges to the

reasoning applied by various board members. Metro asserts that the trial court correctly

determined that there was substantial and material evidence to support the Committee’s

decision to deny the variance. Precision also argues that it is entitled to its attorney fees

under the Equal Access to Justice Act.

STANDARD OF REVIEW

As this court has stated, “the only issue raised by a writ of common law certiorari

is whether the Board exceeded its jurisdiction or acted illegally, arbitrarily, or

fraudulently.” Hoover, Inc. v. Metro Bd. of Zoning Appeals, 924 S.W.2d 900, 904 (Tenn.

Ct. App. 1996). Review by a court under the common law writ of certiorari is limited to

a determination of whether the municipal agency acted illegally, arbitrarily, fraudulently,

-2-

or in excess of its jurisdiction. McCallen v. City of Memphis, 786 S.W.2d 633, 638

(Tenn. 1990). In doing so, the court determines “whether there is any material evidence

that supports the action of the administrative agency.” Laidlaw Envtl. Servs. of Nashville,

Inc. v. Metro. Bd. of Health for Nashville & Davidson Cnty., 934 S.W.2d 40, 49 (Tenn.

Ct. App. 1996). Under the common law writ, “courts may not (1) inquire into the

intrinsic correctness of the lower tribunal’s decision, (2) reweigh the evidence, or (3)

substitute their judgment for that of the lower tribunal.” State ex rel. Moore & Assocs.,

Inc. v. West, 246 S.W.3d 569, 574 (Tenn. Ct. App. 2005) (citations omitted).

The issue of “[w]hether or not there is any material evidence to support the action

of the agency is a question of law to be decided by the reviewing court upon an

examination of the evidence introduced before the agency.” Massey v. Shelby Cnty. Ret.

Bd., 813 S.W.2d 462, 465 (Tenn. Ct. App. 1991) (citing Hoover Motor Express Co. v.

R.R. & Pub. Utils. Comm’n, 261 S.W.2d 233, 239 (Tenn. 1953)). With respect to

conclusions of fact, Judge Cantrell described the proper analysis for a reviewing court:

“‘The function of the reviewing court is limited to asking whether there was in the record

before the fact-finding body any evidence of a material or substantial nature from which

that body could have, by reasoning from that evidence, arrived at the conclusion of fact

which is being reviewed.’” Id. (quoting B. Cantrell, Review of Administrative Decisions

by Writ of Certiorari in Tennessee, 4 MEM. ST. U. L. REV. 19, 29-30 (1973)).

ANALYSIS

I. Legal standards for variance request under Metro stormwater regulations.

We begin with a discussion of the legal standards applicable to the SWMC’s

decision regarding Precision’s variance request. Metro’s stormwater management

regulations provide the following standards for granting a variance:

a. Variances shall only be issued upon a determination that the variance is

the minimum necessary, considering the flood hazard, to afford relief; and

in the instance of a historical building, a determination that the variance is

the minimum necessary so as not to destroy the historic character and

design of the building.

b. Variances shall only be issued upon (i) a showing of good and sufficient

cause, (ii) a determination that failure to grant the variance would result in

exceptional hardship, and (iii) a determination that the granting of a

variance will not result in increased flood heights, additional threats to

public safety or extraordinary public expense; create nuisance; cause fraud

on or victimization of the public; or conflict with existing local laws or

ordinances.

-3-

SWM Reg. § F1.1.2(4). The regulations further state that the SWMC “shall consider all

technical evaluations, all relevant factors, all standards specified in others sections of

these regulations,” and the following list of considerations:

a. The danger that materials may be swept by floodwaters or streams onto

other lands to the injury of others.

b. The danger to life and property due to flooding or erosion damage.

c. The susceptibility of the proposed facility and its contents to flood

damage and the effect of such damage on the individual owner.

d. The importance of the services provided by the proposed facility to the

community.

e. The necessity of the facility to a waterfront location, in the case of a

functionally dependent facility.

f. The availability of alternative locations, not subject to flooding or

erosion damage, for the proposed use.

g. The compatibility of the proposed use with existing and anticipated

development.

h. The relationship of the proposed use to the comprehensive plan and

master drainage plans for that area.

i. The safety of access to the property in times of flood for ordinary and

emergency vehicles.

j. The expected heights, velocity, duration, rate of rise, and sediment

transport of the floodwaters and the effects of wave action, if applicable,

expected at the site.

k. The costs of providing governmental services during and after flood

conditions including maintenance and repair of public utilities and facilities

such as sewer, gas, electrical, and water systems, and streets and bridges.

l. The following evaluation criteria will apply to appeals involving

modification of the buffer.

i. Modifications to the buffer area shall be the minimum necessary

to achieve a reasonable buildable area, as decided by the Committee. Other

requirements for building in the floodway shall still apply.

ii. Where possible, an area equal to the encroached area or

equivalent stormwater management practices shall be established elsewhere

on the lot or parcel in a way to maximize, or provide equivalent, storm

water quality enhancement and protection.

iii. Variances for reducing the no-disturbance buffer require a

written recommendation, positive or negative, from the Greenways

Commission.

iv. Redevelopment, as defined in Appendix B of this volume, within

intensely developed areas may be exempt from all or a portion of the

-4-

requirements of this subsection, provided feasible alternatives or BMPs[2] to

benefit storm water quality are applied.

SWM Reg. § F1.1.2(1).

The regulations do not define “good and sufficient cause” or “exceptional

hardship,” the legal standards upon which the variance decision is to be based. Precision

and Metro offer differing interpretations of these terms. We begin by noting that, in its

variance request, Precision asked for “permission to construct a single family residence in

the Zone 1 floodway buffer for the Cumberland River.” Thus, Precision asked for a

modification in its use of the buffer, not for a modification in the size of the buffer area.

In discussing the relevant legal standards, Precision emphasizes two provisions in

the SWM regulations applicable to modifications to the buffer area. Section 6.9.3 of the

SWM regulations states, in pertinent part: “When the application of the buffer area

would result in the extreme loss of buildable area, modifications to the width of the buffer

area may be allowed through the Stormwater Management Committee appeals process.”

We do not consider this section applicable because Precision has not requested a

modification “to the width of the buffer area.” Precision also cites section F1.1.2(1)(l)(ii)

of the SWM regulations, one of the criteria found under subsection (l) of the variance

considerations (set out above), which concerns “modification of the buffer.” This

criterion provides that, “[w]here possible, an area equal to the encroached area or

equivalent stormwater management practices shall be established elsewhere on the lot or

parcel in a way to maximize, or provide equivalent, storm water quality enhancement and

protection.” We, likewise, do not consider this provision applicable to the present case

because Precision’s variance request does not involve a modification to the water quality

buffer area.

Next, Precision argues that this is a “situation where reasonable use of the land

cannot be made with strict adherence to the zoning regulations.” Because several of the

cases cited by Precision in support of this argument involved the rezoning of property

rather than requests for variances3 from the zoning ordinance, we do not consider them

instructive here. See Campbell v. Nance, 555 S.W.2d 407 (Tenn. Ct. App. 1976);

Bayside Warehouse Co. v. City of Memphis, 470 S.W.2d 375 (Tenn. Ct. App. 1971). In

Metropolitan Historical Commission v. Colony Associates Joint Venture, 1988 WL

109234, at *6 (Tenn. Ct. App. Oct. 19, 1988), another case cited by Precision, the board

of zoning appeals granted a variance to allow for the construction of a 21-story

2

“BMPs” are Best Management Practices. Metro Stormwater Mgmt. Regs. App. B., Acronyms.

3

As this court has explained, “[a] variance is an authorization to construct or maintain a building or

structure or to establish or maintain a use of land that is otherwise prohibited by the zoning ordinance.”

Hunter v. Metro. Bd. of Zoning Appeals, No. M2002-00752-COA-R3-CV, 2004 WL 315060, at *6 (Tenn.

Ct. App. Feb. 17, 2004).

-5-

commercial building in downtown Nashville. The Metropolitan Historical Commission

filed a petition for writ of certiorari, and the trial court affirmed the decision of the board

of zoning appeals. Colony, 1988 WL 109234, at *7. On appeal, this court determined

that, read together, state law and the zoning ordinance required proof “that a particular

hardship (as distinguished from a mere inconvenience or diminution of financial return)

is imposed upon the owner by (1) size (2) shape or (3) topographical conditions of the

property.” Id. at *9. The owner asserted only that the architect’s design did not conform

to the zoning law and that “a change in the designed configuration would be required to

comply with the law.” Id. The only hardship identified by the board of zoning appeals

was “frontage on four streets.” Id. at *10. This court concluded that “[t]he inability to

pursue one of a great number of alternates is not a “‘hardship.’” Id. Finding that the

board’s decision was not supported “by any evidence of any ground of variance included

in the statute or local code,” the court reversed the trial court’s decision.4 Id. at *12.

The Colony case does not provide support for Precision’s theory because it did not

involve a property owner who was unable to make use of its property without a variance.

In McClurkan v. Board of Zoning Appeals for Metropolitan Government of

Nashville & Davidson County, 565 S.W.2d 495, 496 (Tenn. Ct. App. 1977), owner #1

sold her property to owner #2. Owner #1 had applied for and been granted a permit to

continue using the property as a four-family apartment dwelling after it was zoned for

one- and two-family dwellings. McClurkan, 565 S.W.2d at 496. The permit stated that,

when owner #1 ceased to live there, the property would revert to a “lawful use.” Id.

After buying the property, owner #2 applied for a variance, and the board of zoning

appeals denied the application. Id. He filed a writ of certiorari, and the trial court

affirmed the board’s decision. Id. This court cited the state statute authorizing municipal

boards of zoning appeals to grant variances where, due to the unusual characteristics of

the property at the time of the enactment of the zoning regulations, or due to “exceptional

topographic conditions or other extraordinary and exceptional situation or condition of

such piece of property,” the regulations would “impose ‘peculiar and exceptional

practical difficulties . . . or undue hardship upon the owner . . . .’” Id. at 497 (citing prior

version of Tenn. Code Ann. § 13-7-207(3)). The court went on to state that both the state

statute and the local zoning ordinance “clearly contemplate that a variance is not a

‘personal license given to a landowner.’” Id. Rather, “it is the peculiar circumstances of

the land that must be the primary consideration, rather than any hardship personal to or

created by an owner of it.” Id. Applying these principles to the facts of that case, the

court determined that owner #2 was not entitled to a variance based on a hardship created

by an owner of the property and that “the case for a variance here is made even weaker

by a lack of any evidence of hardship other than pecuniary loss, which has been held

insufficient by itself to justify a variance.” Id. (citing Houston v. Memphis & Shelby

Cnty. Bd. of Adjustment, 488 S.W.2d 387, 389 (Tenn. Ct. App. 1972)); see also

4

We decline to rely upon the general zoning principles and cases from other states cited in the Colony

opinion to the extent they were unnecessary to the resolution of the dispute before the court.

-6-

Hillsboro-W. End Neighborhood Ass’n, Inc. v. Metro. Bd. of Zoning Appeals, No. 01A01-

9406-CH-00282, 1995 WL 79224, at *2-3 (Tenn. Ct. App. Feb. 24, 1995) (finding no

material evidence to support board’s grant of variance “[b]ecause there are no facts

establishing a hardship to the defendant created by the peculiar characteristics of the

land”).

We do not have any cases interpreting Metro’s SWM regulations. The caselaw,

on variances in other zoning contexts discussed above provides some persuasive

authority. Those cases considered the governing statutes and ordinances and concluded

that the board’s granting of a variance must be based upon hardship related primarily to

the circumstances of the land rather than to the personal circumstances of the property

owner.

Metro argues that the SWM regulations “align with the standards contained in

FEMA’s[5] regulations on the National Flood Insurance Program, codified at 44 C.F.R. §

60.6.” We agree with Precision that the FEMA variance provisions cited by Metro do not

apply to the present case.6 The variance provision (44 C.F.R. § 60.6(a)(3)) in these

federal regulations, however, is essentially the same as the variance provision (§

F1.1.2(4)(b)) in Metro’s stormwater regulations. Both provisions require a showing of

“good and sufficient cause” and a determination that failure to grant the variance will

result in “exceptional hardship” to the applicant. In this circumstance, where the parties

have cited no other source to define these terms, we will consider the authority offered by

Metro as to FEMA’s interpretation of the terms.

According to FEMA, a variance request based on “good and sufficient cause”

“deals solely with the unique site-specific physical characteristics of the property,

subdivision lot, or land parcel in question.” Variances and the National Flood Insurance

Program, FLOODPLAIN MGMT. BULLETIN § 3.3.3 (FEMA July 2014). FEMA further

states:

A “good and sufficient” cause for a variance occurs when a parcel of land

possesses physical characteristics so unusual that complying with NFIP[7]

regulations in a local ordinance would create an exceptional hardship

related to the property, the surrounding property owners, or the community

5

“FEMA” stands for “Federal Emergency Management Agency.”

6

The federal regulations provide, in pertinent part, that “[v]ariances may be issued by a community for

new construction and substantial improvements to be erected on a lot of one-half acre or less in size

contiguous to and surrounded by lots with existing structures constructed below the base flood level . . . .”

44 C.F.R. § 60.6(a)(2). Precision’s project is not below the base flood level and does not fit within this

description. In fact, federal regulations do not require water quality buffers.

7

“NFIP” stands for “National Flood Insurance Program.” 44 C.F.R. § 206.251(d).

-7-

in general. In addition, the unusual physical characteristics must be unique

to that property and not be shared by adjacent parcels or be typical of other

lots in the community.

Id. FEMA explains that a determination of “good and sufficient cause” should never be

based upon “the personal difficulties of the owner or inhabitants” and that “the financial

hardship of the property owner is never a ‘good and sufficient’ cause for granting a

variance.” Id.

As to the requirement that denial of the variance would result in “exceptional

hardship,” FEMA offers the following interpretation:

The hardship that would result from failure to grant a requested

variance must be exceptional, unusual, and specific to the property

involved, not the personal circumstances of the applicant. When

determining whether an applicant has established an exceptional hardship

sufficient to justify a variance, the local variance appeal board or other

governing body must weigh the applicant’s hardship against the

community-wide flood damage prevention requirements.

. . . This applies even if the alternative means of construction are

more expensive or complicated than building the structure with a variance,

or if they require the property owner to use the parcel differently than

originally intended or build the home elsewhere.

Id. at § 3.3.4.

Overall, the FEMA guidance is similar to the Tennessee caselaw in that the

emphasis is on the peculiar characteristics of the property itself and not upon the personal

circumstances of the property owner.

II. Application of standards to Precision’s variance request.

As a reviewing court, we must determine “whether there is any material evidence

that supports the action of the administrative agency.” Laidlaw, 934 S.W.2d at 49. The

threshold standard that a variance must meet is the following:

Variances shall only be issued upon (i) a showing of good and sufficient

cause, (ii) a determination that failure to grant the variance would result in

exceptional hardship, and (iii) a determination that the granting of a

variance will not result in increased flood heights, additional threats to

public safety or extraordinary public expense; create nuisance; cause fraud

-8-

on or victimization of the public; or conflict with existing local laws or

ordinances.

SWM Reg. § F1.1.2(4)(b). Precision appealed an adverse decision of the Department of

Water Services “that no construction can occur on this lot without approval of a variance

from the Stormwater [Management] Committee.” Precision’s statement of hardship

provides in full: “This lot is 100% within the floodway or the zone 1 Stream Buffer and

therefore the lot cannot be utilized without the required variance.” Similarly, at the April

6, 2017 hearing before the Committee, Precision stated: “So the exceptional hardship

that would result if this variance is not granted is the inability to construct a home,

period.”

Does the fact that no construction can occur on these lots without a variance

constitute exceptional hardship and/or good and sufficient cause? Under the standards

discussed above, we conclude that there is nothing unusual or exceptional about

Precision’s property; rather, the lots are located in Zone 1, where construction is not

permitted, and Precision did not submit evidence sufficient to overcome the “extreme

hardship” threshold necessary to justify a variance from the requirements of the Zone 1

restrictions.

As set forth above, there are also numerous “considerations” appropriate for the

Committee to take into account in making its determination. See SWM Reg. § F1.1.2(1).

A variance shall not be issued, however, without a determination that exceptional

hardship would otherwise result.

We will proceed to examine Precision’s objections to the individual votes cast in

favor of the Committee’s decision to deny the variance.

A. Vote of Committee Member Debra Grimes.

Precision makes two arguments regarding the vote of Committee Member Grimes:

(1) that her vote was “arbitrary and illegal” because it was based on criteria not

authorized by the ordinance and because she voted to deny the variance despite

concluding that Precision met the legal requirements; and (2) that her reasoning was not

supported by material evidence.

As to the first argument, Precision cites the legal proposition that “a board member

can not vote to deny an application when the board member believes the applicant has

met the necessary zoning requirements. “ Hoover, 924 S.W.2d at 905. In Hoover, a case

involving a conditional use permit, the court stated that, if a board member based his or

her “decision to deny the permit on something other than whether [the applicant] had met

the required conditions,” that “decision is arbitrary under the laws of Tennessee.” Id. at

905-06. In the present case, Precision cites the following testimony as a basis for

-9-

asserting that Ms. Grimes reached the conclusion that Precision met the legal

requirements for a variance yet voted against granting it a variance:

They’ve met the criteria as outlined by their attorney, and met the right—

the ordinances. So although I think it’s a great goal, I don’t know how we

can be the one to stand in—to hold that mind, I guess.

According to Precision, “it is illegal for her to conclude that Precision Homes met the

ordinance requirements for a water quality variance and then deny the application for a

reason other than the ordinance criteria.”

Although the isolated quotation relied upon by Precision seems to lend support to

its argument, it is important to view the entirety of Ms. Grimes’s pertinent testimony:

MS. DEBRA GRIMES: I’ve been kind of waffling back and forth,

really trying to decide which way I would vote on this. And—because I

think that the thought that Metro is moving that direction to try to recapture

the riverfront makes a lot of sense. And I would love to see that happen.

But we can’t hold that flag when Planning approved it, because

that’s a Metro committee as well. And if Metro is unwilling to buy it as the

client said, you know, that really puts their—what they’re saying they want

into play.

And so for us to try to hold up the flag and fight the battle for them

when they’re not—not everybody is fighting the same battle—I guess it just

makes it hard for me to say that would be a reason to deny this, which they

certainly are doing the mitigation that’s needed. They’ve met the criteria as

outlined by their attorney, and met the right—the ordinances. So although I

think it’s a great goal, I don’t know how we can be the one to stand in—to

hold that mind, I guess.

CHAIRPERSON WAGNER: All right. Thank you, Ms. Grimes.

MS. PAULA KEE [Metro Water Services]: I guess I wanted to

provide a little clarification. I think you mentioned Planning approved it.

That—they got no variance from the Board of Zoning Appeals for front

setback.

But Planning’s comment was: “Planning will not have further

comments for these cases. The previous comments from Stormwater

provide an effective premise for not granting a variance for any of these lots

along Miami.”

MS. DEBRA GRIMES: That’s it. Thank you.

In context, Ms. Grimes’s statements indicate that she had not yet decided how she

was going to vote. At the time of the above statement, she thought that Precision had met

the criteria of the ordinance—according to its attorney—but she was still gathering

- 10 -

information and had not yet made up her mind. Although the Committee discussion after

Ms. Grimes’s comments did not pertain to the points she raised, there was additional

discussion about adding a condition and Ms. Grimes had time to consider her vote; when

it was time to vote, she voted against approving the variance. We reject Precision’s

assertion that Ms. Grimes’s vote was arbitrary and illegal.

Precision’s argument that Ms. Grimes’s vote was not supported by material

evidence is based upon the same theory as its first argument, namely that Ms. Grimes

found that Precision met all the requirements for a variance. Because we have rejected

that theory, we likewise reject Precision’s second argument and conclude that Ms.

Grimes’s vote is supported by material evidence.

B. Vote of Committee Member Dodd Galbreath.

Precision makes two arguments regarding the vote of Committee Member

Galbreath: (1) that his vote was “arbitrary and illegal” because “he misapplied and

misrepresented the legal requirements for a buffer variance” and (2) that his reasoning

was not supported by material evidence.

Precision’s “arbitrary and illegal” argument is based upon its assumption that Mr.

Galbreath “required Precision Homes to conduct a ‘metric-for-metric’ replacement of a

‘native forest.’” As discussed above, however, the provisions of subsection (l) of the

variance considerations included in Metro’s stormwater regulations do not directly apply

to Precision’s variance request. See SWM Reg. § F1.1.2(1)(l)(ii). Moreover, in its brief,

Metro acknowledges that the stormwater regulations do not require “metric-for-metric”

replacement, an approach discussed by Mr. Galbreath in some of his comments at the

hearing. Even Mr. Galbreath seemed to admit as much at the hearing.8

8

Committee Member Galbreath stated:

But you know, the—we have never had—and—and I’ve argued for this, and this

is probably an administrative procedures issue that needs to be addressed. And I think a

Zone 1 decision like this probably warrants this kind of discussion. And unfortunately

it—it’s not resolvable today.

But we have—we have never proven that the mitigation provides a metric-for

metric replacement; they—they don’t have any quantifiable evidence of that today. And

I know from a scientific standpoint that it is impossible to put a building on that site and

mitigate the water quality and the water quantity benefits of—of a riparian buffer, metric-

for-metric. It’s—it’s impossible.

....

And Metro policy is moving towards a native riparian buffer on these sites. And

I don’t think we’re setting a good precedent if we make it easy for someone to make that

harder for Metro to do. I—I just—I think that’s what’s at stake here, more than just

giving someone a little bit of a change to get FEMA to approve something that is

surrounded by a flood risk.

- 11 -

Mr. Galbreath identified numerous other bases to explain his vote. He inquired

and received an affirmative answer from counsel for Precision that the property was

“within the area that flooded during the 2010 flood.” Thus, Precision admitted that the

lots would “flood during flood events above 100-year storm events.” See SWM Reg. §

F1.1.2(1)(b),(i), and (k) (variance considerations of danger to life and property, safety of

access, and costs due to flooding of property). Later in the hearing, Mr. Galbreath

discussed the fact that the properties at issue involved both floodplain and buffer

regulations and the underlying policy concerns:

The—we’ve got two issues on the table, the floodplain regulations

and the buffer regulations. So we haven’t talked about the buffer

regulations yet. The Zone 1 variance applies as well. So—so I’ll—I’ll

kind of back up from both before I—and—and—and talk more broadly

about what I think is Metro policy here.

....

So if—if we step back and look at this area we see Metro policy—to

me—being applied in a very clear way that has not been applied in the

areas where we have approved variances in the past.

In this particular area, Metro is consistently acquiring properties

along the riverfront that were developed, they were in the progress of being

development [sic], and that had development potential. So clearly Metro

policy is focusing on discouraging development on these parcels.

What makes this case challenging is we’ve got a site that’s in a gray

area on the flood side of the question, but we’ve got a clear Zone 1

delineation. It’s rare that we approve variances in Zone 1, so that doesn’t

make it a slam-dunk in terms of—of an approval of a variance.

And we have this very clear Metro policy intent of not encouraging

and facilitating development in these areas. We also don’t have the same

type of density surrounding the riverfront property where we have granted

variances in the past, like we did for the downtown parcel that was in the

Zone 1.

There were adjacent properties that were already there. That

represents a Metro policy focus for that site of allowing more development

in areas that we’d rather not develop. But this site clearly has a different

kind of policy focus.

Sections F1.1.2(g) and (h) direct the SWMC to consider, in making a variance

determination, “[t]he compatibility of the proposed use with existing and anticipated

development” and “[t]he relationship of the proposed use to the comprehensive plan.”

Mr. Galbreath mentioned that building more houses would result in the necessity

of rescuing more families in a flood. See SWM Reg. § F1.1.2.(1)(b),(i), and (k). He also

commented:

- 12 -

There were all kinds of red flags that preceded this investment.

There were all kind of red flags that—that are asking for not moving

forward with this variance by virtue of all these parcels being purchased by

virtue of—of the—the ordinance, demand development in floodways. This

one is just too close to the risk. And I—I think we’d be making a major

mistake by approving this variance. And that’s—that’s my position.

He further justified his position against the variance by explaining the importance of

maintaining the buffer:

Okay. I—I—I need to provide my colleague with—with an

academic paper about how riparian trees, which are water hungry trees,

consume water quantity as well as clean water and filtered water. For

example, an oak tree on—on an upland will consume 109 gallons of water a

day. So—so we actually get water removed from floods by riparian trees.

That’s—that’s been documented.

A Zone 1 buffer is the last line of defense for a stream. It is a critical

zone for keeping the banks stable, and it’s a critical zone for being the last

filtering water gets. And it’s a critical zone for pulling the last water out of

a–last bit of water out of a flood that makes flood peaks a little bit smaller.

So I’d—I’d—I wouldn’t be making this point as—as—as fervent as

I am if it weren’t such a highly vulnerable, high-risk area that Metro

Council has identified as a high priority area—or it wouldn’t be identified

as—as a Zone 1 buffer. So—and—and that’s—I think I’ve said all I need

to say.

Contrary to Precision’s assertion, Mr. Galbreath did not misapply the regulations

regarding mitigation. He expressed his views regarding the appropriate standards and

acknowledged that “it’s not resolvable today.” Mr. Galbreath provided a number of

reasons to support his opposition to Precision’s variance request, and we conclude that

his vote was not arbitrary or illegal.

As to Precision’s second argument, that Mr. Galbreath’s reasoning was not

supported by material evidence, Precision asserts that Mr. Galbreath’s opposition was

based upon only two reasons: that the lots were “too close to the risk” and that

Precision’s water quality mitigation efforts were insufficient. We have already rejected

the latter argument above. (Furthermore, Mr. Galbreath’s opposition to the variance

request was supported by more than two reasons, as discussed above.)

We will now address Precision’s objection to Mr. Galbreath’s “too close to the

risk” reasoning. Mr. Galbreath expressed a concern regarding whether allowing

Precision to build the houses could cause increased financial risk to Metro taxpayers:

- 13 -

And—and—and I don’t think what my good friend, the—the

engineer I highly respect, Roy is saying—I don’t think Roy is saying we

should allow a variance here to increase the liability to the taxpayer. I—I—

I don’t think he’s saying we should allow a house to be built here so the

taxpayers has [sic] to come in here and buy a higher value, easily-at-risk

flood damaged property when it’s the investor who decided to take on the

risk and not the taxpayer.

And if we’re going to help the investor raise the risk to the taxpayer,

I just don’t think that’s good policy. I—I don’t think that’s consistent with

Davidson County’s political culture to increase risk to the taxpayer and cost

the taxpayers more money by adding value that’s not there, that we don’t

have to approve, that we’re not obligated to approve.

Metro Council stated years ago that—that these buffers have value.

And we’re going to regulate them and we’re not going to allow

development on them unless a panel of—of the applicant’s peers find that a

variance is warranted. And if—if this were any other site I would be

looking for ways to help the investor recoup their investment.

The evidence showed that, after the 2010 flood, which was classified as a 500-year flood

event, Metro participated in a grant program that allowed it to purchase homes that were

“substantially damaged” (more than 50% damaged) as well as adjacent lots owned by the

same homeowners. Mr. Galbreath’s taxpayer liability concern is consistent with the

provision in section F1.1.2(4) of the stormwater regulations stating that a variance shall

be issued only upon a determination that the variance will not result in “extraordinary

public expense.”

Precision asserts that its proposed houses would not present a risk to taxpayers

because, unlike the houses that were substantially damaged in the 2010 flood, the

proposed homes would be built several feet above the 500-year flood line. Precision

argues that, “Because the first floor is elevated 4 feet above the 2010 flood level, these

homes would be ‘out of harm’s way,’ not subject to substantial damage, and

consequently unqualified for a similar buy-out program.” Yet, as Metro staff pointed out

at the hearing, there had been a number of catastrophic weather events across the country

during the past year, so they did not consider the fact that property was “even inches or a

foot above the 100-year flood elevation” to mean that there was no flood risk.

Overall, we cannot agree with Precision’s assertion that Committee Member

Galbreath’s reasoning for his vote was not supported by any material evidence. As

outlined above, Mr. Galbreath set forth a number of reasons to support his vote and,

except as pointed out with respect to the mitigation regulations that do not apply here, the

reasons dovetail with the applicable stormwater regulations.

- 14 -

C. Vote of Committee Chair Lance Wagner.

Precision’s final argument challenging the denial of its variance request is that

Chairman Wagner’s reasoning was not supported by material evidence. Precision asserts

that Mr. Wagner gave two reasons for his vote—the safety of first responders and

concern over loss of the water quality buffer—and that there is no material evidence to

support those reasons.

We begin with an examination of the relevant statements made by Chairman

Wagner at the hearings.9 He expressed concern about the safety of first responders in the

event of flooding:

I always have a concern about life, health and safety on these

measures, too, because I—I—I remember some efforts to pull people from

houses, and some life, health and safety issues during the 2010 flood.

So Miami Avenue, if I’m not mistaken, dead-ends to the east of

these sites. And during the 2010 Flood, I’m pretty sure it was mostly cut

off. And I’m—I’m pretty sure it was mostly cut off. And I’m—I’m just

looking to Roger or anyone else to kind of verify that.

But I am a little scared that: Are we creating a life, health and safety

issue by these being developed with residential houses?

....

I think the difference between these properties and the properties on the

other side of the road is that there will be three more families to rescue

during a flood. That’s—that’s the difference.

The safety of first responders is a valid consideration under section F1.1.2(1)(i) of the

stormwater regulations.

After the vote, Chairman Wagner expanded upon the reasons for his vote against

the variance:

I am not—I have a hard time divorcing the flooding issue, here

because I—is it—it is very prone to flooding. And I think more

development out here will be a sequius [sic] for first responders. I think it

will increase the risk for Metro to come up there and provide services out

there in a flood scenario.

And as I said before, it would have helped me if at least FEMA had

weighed in above us and said, “Hey, you know, we agree this area is

outside the floodway and the floodplain.” You know, staff has—has

9

As Precision points out, Chairman Wagner made some of his statements at the hearing on January 5,

2017, and others at the final hearing on April 6, 2017.

- 15 -

weighed in and said they’re not in complete agreement with it being outside

the floodplain because of the—the FEMA map saying so.

And I—I understand the—the elevations, and I’ve seen that. To me,

the clarification on that would be to get FEMA to agree with that. And so

that would have been, you know, my standpoint of a good—to have that to

fall back on.

But right now I see this as burdening the taxpayers and burdening

the city with more development in the area that doesn’t need to be

developed due to the flood risks.

And then the loss of the Zone 1—Zone 1 buffer is also a secondary

concern of mine. So I think you’ve done a fairly good job of establishing

how you would—how you would make up for a water quality loss, but I

don’t—I don’t—it would be enough on its own for me. But with the—the

flooding issues behind it, that pulls me to the no side.

These concerns are consistent with sections F1.1.2(4) and F1.1.2(1)(i) and (k) of Metro’s

regulations.

Precision objects to the concern regarding first responders. There was testimony

that, at the height of the 2010 flood, water in the area was “midway up [the witness’s] leg

[in] the deepest part” and that the police did not allow cars into the neighborhood.

Precision argues that there was no evidence that knee-deep water would present a risk to

first responders sufficient to deny its variance request. The burden of proof was on

Precision, however, to justify its entitlement to the variance. The safety of first

responders and the additional costs of rescuing residents living in the proposed homes

were valid considerations for the Committee under the regulations.10

As to Chairman Wagner’s comments about mitigation, we agree with Precision

that his comments suggest that, if that were his only concern, he may have been willing to

grant the variance. Nevertheless, Chairman Wagner’s concerns regarding first responders

and public expense provide material evidence for his vote.

We conclude that the Stormwater Management Committee’s decision is supported

by material evidence and affirm the decision of the trial court. We, therefore, deny

Precision’s request for attorney fees.

10

Precision also cites the Committee’s decision to grant a variance for a seven-story multifamily building

in another area. In reviewing the trial court’s determination, we limit our analysis to the case at hand.

We note, however, the previous discussion concerning the appropriateness of the Committee’s

consideration of Metro policy concerning development in a particular area.

- 16 -

CONCLUSION

The judgment of the trial court is affirmed, and this matter is remanded with costs

of appeal assessed against the appellant, Precision Homes, Inc., for which execution may

issue if necessary.

________________________________

ANDY D. BENNETT, JUDGE

- 17 -