Opinion

Voith Hydro, Inc. v. United States

Court
United States Court of Federal Claims
Filed
May 8, 2019
Status
Published
On the bench
Patricia E. Campbell-Smith
Cited by
0 cases
Authority
More cited than 7.6%

stating that “technical ratings . . . involve discretionary determinations of procurement officials that a court will not second guess”

How later courts described this case

  • stating that “technical ratings . . . involve discretionary determinations of procurement officials that a court will not second guess”
  • not discussing an argument abandoned by the plaintiff

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

No. 18-1907C

(E-Filed: May 8, 2019) 1

)

VOITH HYDRO, INC., )

)

Plaintiff, )

)

v. )

Post-Award Bid Protest;

)

Challenges to Technical Ratings,

THE UNITED STATES, )

Past Performance Ratings, and

)

Best Value Tradeoff Analysis;

Defendant, )

Motion to Strike Declaration of

)

Source Selection Authority.

and )

)

ALSTOM RENEWABLE US LLC, )

)

Intervenor-defendant. )

)

David T. Ralston, Jr., Washington, DC, for plaintiff. Frank S. Murray, Micah T. Zomer,

and Krista A. Nunez, of counsel.

Douglas G. Edelschick, Trial Attorney, with whom were Joseph H. Hunt, Assistant

Attorney General, Robert E. Kirschman, Jr., Director, Douglas K. Mickle, Assistant

Director, Commercial Litigation Branch, Civil Division, United States Department of

Justice, Washington, DC, for defendant. Theresa L. Hampson, United States Army Corps

of Engineers, Walla Walla, WA, of counsel.

1

This opinion was issued under seal on April 30, 2019. Pursuant to paragraph (6)

of the ordering language, the parties were invited to identify source selection, proprietary

or confidential material subject to deletion on the basis that the material was

protected/privileged. A small number of redactions were proposed by defendant and

intervenor-defendant. See ECF No. 94. Plaintiff did not agree with the legal basis for

these redactions, but also did not object “due to their limited scope and the relative

immateriality of the information sought to be redacted.” Id. at 2. The court accepts the

proposed redactions and notes the cooperation of counsel in this regard. Redactions are

indicated by brackets [ ].

Jonathan D. Shaffer, Tysons Corner, VA, for intervenor-defendant. Mary Pat Buckenmeyer and

Todd M. Garland, of counsel.

OPINION AND ORDER

CAMPBELL-SMITH, Judge.

This post-award bid protest is before the court on the parties’ cross-motions for

judgment on the administrative record (AR), brought pursuant to Rule 52.1 of the Rules

of the United States Court of Federal Claims (RCFC). 2 The court has reviewed the

complaint, ECF No. 1; the AR, ECF Nos. 23-31; the supplement to the AR, ECF No. 48;

plaintiff’s memorandum in support of its motion for judgment on the AR, ECF No. 55-1;

defendant’s cross-motion for judgment on the AR, ECF No. 69; intervenor-defendant’s

cross-motion for judgment on the AR, ECF No. 70; plaintiff’s response/reply brief, ECF

No. 76; defendant’s reply brief, ECF No. 81, and intervenor-defendant’s reply brief, ECF

No. 82. 3 Oral argument on the parties’ cross-motions for judgment on the AR was held

on April 10, 2019, addressing the topics set forth in the court’s order of April 4, 2019.

See ECF Nos. 88 (order), 91 (digital audio recording of oral argument held April 10,

2019).

In addition to the parties’ briefing of the merits of this bid protest, the court has

before it plaintiff’s motion to strike the declaration of Donna L. Street, the Source

Selection Authority (SSA) for the procurement at issue in this bid protest. See ECF No.

75. That motion has been fully briefed. See ECF No. 78 (defendant’s opposition); ECF

No. 79 (intervenor-defendant’s response); ECF No. 80 (plaintiff’s reply). For the reasons

set forth below, plaintiff’s motion for judgment on the AR is DENIED, and defendant’s

2

Plaintiff’s motion was defective under this rule, because it did not include a

statement of facts. See RCFC 52.1(c)(1). This defect, along with the length of plaintiff’s

brief, which, by the court’s leave, exceeded the limit set by this court’s rules by five

pages, permitted plaintiff to produce an extremely detailed and multi-faceted set of

challenges to the contract award. See ECF No. 53 (order). The court has considered all

of plaintiff’s arguments, but, due to the expedited litigation schedule to which the parties

and the court agreed, the court will only discuss plaintiff’s principal arguments here.

3

Additional context for this bid protest may be found in two prior decisions of this

court: (1) one addressing access to protected information in the record; and (2) another

addressing the scope of the administrative record. See Voith Hydro, Inc. v. United

States, 142 Fed. Cl. 233 (2019); Voith Hydro, Inc. v. United States, 141 Fed. Cl. 723

(2019).

2

and intervenor-defendant’s cross-motions for judgment on the AR are GRANTED.

Plaintiff’s motion to strike the declaration of Donna L. Street is DENIED.

I. Background

A. Overview

This bid protest challenges “the evaluation and award decision by the U.S. Army

Corps of Engineers, Walla Walla District [(USACE or agency)] under Request for

Proposals No. W912EF-17-R-0004 [(solicitation or RFP)], which sought proposals for

the design, supply and installation of new turbines in fourteen hydroelectric generator

units at the McNary Lock and Dam Powerhouse located on the Lower Columbia River.”

ECF No. 1 at 1. The protest filed here by Voith Hydro, Inc. (Voith) was preceded by

Voith’s post-award bid protest at the Government Accountability Office (GAO). Id. at 3.

That protest was dismissed as academic when the agency informed the GAO that it

intended to take corrective action to address concerns about the award raised in Voith’s

GAO protest. Id. at 5. Here, plaintiff argues that the agency’s decision to award the

contract to Alstom Renewable US LLC (Alstom), following the corrective action

undertaken by the agency, failed to correct significant evaluation errors committed by the

agency. Id. at 5-6, 35.

Voith’s challenge to the award to Alstom raises three general areas of concern. In

Count I of the complaint, plaintiff alleges that the evaluation of the offerors’ technical

proposals was flawed. Id. at 41-43. In Count II, plaintiff alleges that the agency’s past

performance evaluation was unreasonable, arbitrary and capricious. Id. at 43-45. In

Count III, Voith contends that the price realism analysis undertaken by the agency was

flawed. 4 Id. at 45-48. In Count IV, plaintiff contends that these evaluation errors

invalidate the agency’s determination that Alstom, not Voith, provided the best value

proposal in this procurement. Id. at 48.

B. Solicitation, as Amended 5

4

At oral argument, plaintiff’s counsel acknowledged that Voith’s challenge to the

agency’s price realism analysis is no longer being pursued. ECF No. 91 at minute 05:00.

5

Although the parties have referenced procurement planning documents that

predate the amended solicitation, the court has not found such references to be helpful.

The court must determine whether the proposals received in response to the finalized

version of the solicitation were evaluated pursuant to the evaluation scheme set forth in

the amended solicitation. Accordingly, the court will not discuss the acquisition plan of

January 24, 2017, the source selection plan (SSP) of April 13, 2017, or superseded

versions of various sections of the solicitation in this opinion.

3

1. RFP Provisions of Note

The solicitation issued on April 14, 2017. See ECF Nos. 23-4 at 387-1460, 23-5,

23-6, 23-7, 23-8, 23-9, 23-10, 23-11 at 1-8. Amendments 1-7 occurred between May 17,

2017, and December 12, 2017. See ECF No. 23-11 at 9-1064. The last two amendments

were received after initial proposals had been submitted and governed final proposal

revisions submitted by the offerors. Id. at 840-1062 (Amendment 6), 1063-64

(Amendment 7).

Of note, Amendment 6 contained an updated version of the bid schedule, which

described the pricing of adjustable and fixed blade turbines in the following manner:

The alternate bid tables provide [line items] to complete 8 additional

adjustable blade turbines beyond the base 6 in the event that the Government

chooses to install fewer than 8 fixed blade turbines. . . . The 8 additional

adjustable blade turbines would replace any number of the 8 fixed blade

turbines. . . . In the instance that additional adjustable blade turbines are

added, optional bid items for the supply and installation of additional

adjustable blade turbine components would be exercised, concurrent with a

modification to deduct the same number of fixed blade turbine component

bid items.

Id. at 842. In short, the base projection was for 6 adjustable blade turbines and 8 fixed

blade turbines, for a total of 14 turbines to be installed. The solicitation included,

however, line items for 22 turbines (6 base adjustable blade, 8 optional adjustable blade,

and 8 base fixed blade).

As part of Amendment 5, which issued before initial proposals were received, the

agency set forth a revision to the list of Federal Acquisition Regulation (FAR) provisions

which would govern the contract as to construction activities. 6 Id. at 799-831. Among

the identified contract provisions was FAR 52.217-7 (“Option for Increased Quantity –

Separately Priced Line Item (MAR 1989)”). ECF No. 23-11 at 808-17. The same FAR

provision, FAR 52.217-7, was included as well under the contract’s “supply” FAR

provisions, but the supply clause cross-referenced the construction clause and indicated

that the information included under the FAR 52.217-7 clause for construction also

governed the supply elements of this contract. ECF No. 23-4 at 495.

6

All citations are to the 2018 version of Title 48 of the Code of Federal

Regulations.

4

Another FAR provision incorporated into the solicitation language by full text

remained unchanged throughout the amendments of the solicitation: FAR 52.217-5,

Evaluation of Options (JUL 1990). This regulation states in its entirety:

Except when it is determined in accordance with FAR 17.206(b) not to be in

the Government’s best interests, the Government will evaluate offers for

award purposes by adding the total price for all options to the total price for

the basic requirement. Evaluation of options will not obligate the

Government to exercise the option(s).

ECF No. 23-4 at 475. The court now turns to the evaluation criteria set forth in

Amendment 3 of the solicitation.

2. Evaluation Scheme

This solicitation is for a fixed-price with economic price adjustment contract.

ECF No. 23-11 at 578; see also ECF No. 23-4 at 474. Award in this negotiated

procurement would made on a best value tradeoff basis. ECF No. 23-11 at 578, 580.

Four evaluation factors would be considered in the best value analysis, only three of

which are relevant to Voith’s protest: Technical, Past Performance and Price. Id. at 580.

The non-price factors, taken together, were significantly more important than the price

factor. Id. Technical and Past Performance were equal in importance. Id.

a. Technical, Factor I

There were five subfactors in Factor I, listed here in order of their importance:

(A) hydraulic design, modeling, and analysis experience; (B) technical work plan and

schedule; (C) turbine component design, manufacture, and installation experience;

(D) management and quality control; and (E) unit stator winding design, manufacture,

and installation experience. Id. Within the Technical factor, the agency would identify

“strengths, deficiencies, weaknesses, risks and uncertainties.” Id. at 585. The evaluation

of Factor I would produce one of the following ratings: Outstanding, Good, Acceptable,

Marginal, Unacceptable. Id.

b. Past Performance, Factor II

Voith challenges virtually every aspect of the Past Performance evaluation

conducted by the agency, so the court, with some alterations of formatting, reproduces

almost the entire evaluation section addressing Factor II here. Generally, there were

“three aspects to the past performance evaluation: Recency, Relevancy (including

context of data) and Quality (including general trends in contractor performance and

source of information).” Id. Further, the solicitation stated as follows:

The Government will focus its inquiries on the offeror’s (and major sub-

contractors’) record of performance as it relates to all solicitation

5

requirements, including price, schedule, performance and management of

sub-contractors. Major sub-contractors are defined as members of an

offeror’s overall team who are expected to perform ten (10) percent or more

of the proposed effort. Therefore, offerors are reminded to include the most

current and relevant past performance efforts (within the past fifteen years)

in their proposal. Absent any current and relevant past performance history

or when the performance record is so sparse that no meaningful confidence

assessment rating can be reasonably assigned, the offeror will be assigned an

"unknown confidence rating" and its proposal will not be evaluated either

favorably or unfavorably on past performance. The Government may use

data provided by the offeror in its proposal and data obtained from other

sources, including data in Government files or data obtained through

interviews with personnel familiar with the contractor and their current and

past performance under Federal, State or Local government or commercial

contracts for same or similar services as compared to the North American

Industry Classification System NAICS 237990, Other Heavy and Civil

Engineering Construction. Data submitted by the offeror or gathered from

other sources by the government in conducting performance risk assessments

shall not extend past fifteen years prior to the issue date of the RFP, but may

include performance data generated during the past fifteen years without

regard to the contract award date. [Contractor Performance Assessment

Report System] CPARS data is limited to the past 6 years. Offeror’s

should provide additional performance data for projects beyond 6yrs.

Offerors should submit all Government and/or commercial contract numbers

and descriptions for the prime offeror and each major sub-contractor in

performance or awarded during the past fifteen years, from the issue date of

this RFP, which are relevant to the efforts required by this RFP.

RECENCY; The Government will evaluate recency by examining the

offerors’ record of past performance and to assess the time period during

which the offeror’s past performance is considered relevant.

RELEVANCY: The Government will evaluate those aspects of an offeror’s

history of contract performance that would provide the most context and give

the greatest ability to measure whether the offeror will successfully satisfy

the current requirement. This evaluation will include all aspects of the

offeror’s execution of schedule, performance, customer support and

subcontracting plan for these projects and the offeror’s record of:

1) Conforming to specifications and standards of good workmanship;

2) Maintaining program execution within price; 3) Adherence to contract

schedules, including the administrative aspects of performance; 4) Ability to

resolve technical and manufacturing problems quickly and effectively;

6

5) Businesslike concern for the interest of its customers; 6) Establishing and

maintaining adequate management of sub-contractors; and 7) Compliance

with subcontracting plans submitted on previous projects.

ECF No. 23-11 at 585-86. The evaluation of relevancy, governed by the extent that the

present/past performance effort involved “the scope and magnitude of effort and

complexities this solicitation requires,” would produce one of the following ratings:

Very Relevant, Relevant, Somewhat Relevant, or Not Relevant. Id. at 586-87.

As for quality, the RFP contained the following information:

The third aspect of the past performance evaluation is to establish the overall

quality of the offeror’s past performance. The quality past performance

evaluation conducted gathers information from the offeror’s customers to

determine how well the offeror performed those past contracts. This quality

assessment will be reflected in the overall confidence assessment described

below.

Id. at 587.

Finally, another metric used to evaluate Past Performance was the Performance

Confidence Assessment (PCA). Id. Where recent and relevant performance information

was available, the PCA would show the level of the government’s “expectation that the

offeror will successfully perform the required effort.” Id. One of the following ratings

would be assigned in those circumstances: Substantial Confidence, Satisfactory

Confidence, Limited Confidence or No Confidence. Id. at 587-88. If, however, “no

recent/relevant performance record is available or the offeror’s performance record is so

sparse that no meaningful confidence assessment rating can be reasonably assigned,” a

Neutral Confidence rating would be the PCA for that offeror. Id. at 587. The Source

Selection Evaluation Board (SSEB) would determine a “single consensus performance

confidence assessment,” or PCA, for each offeror. Id.

c. Price, Factor IV

The most relevant statements in the solicitation regarding the evaluation of each

offeror’s price are as follows:

The Government will evaluate offers for award purposes by adding the total

price for all options to the total price for the base requirements. . . .

Evaluation of options will not obligate the Government to exercise the

option(s). The Government will evaluate offers for award purposes by

evaluating the prices proposed in the Bid Schedule. The offeror must provide

a price proposal by completing the Bid Schedule as instructed in Section

00100.

7

ECF No. 23-11 at 589. Price, although significantly less important than the combined

non-price evaluation factors, was part of an integrated tradeoff analysis to determine the

best value proposal:

The award will be made based on the best overall (i.e., best value-tradeoff)

proposal that is determined to be the most beneficial to the Government

based on an integrated assessment, with appropriate consideration given to

the four (4) evaluation factors: I. Technical, II. Past Performance, III. Small

Business Participation, and IV. Price.

Id. at 580.

As defendant notes, the number of Contract Line Item Numbers (CLINs) in the bid

schedule was greater than 250. ECF No. 69 at 11. By the court’s count, there were

approximately 275 CLINs in the finalized bid schedule, along with twenty-two “rate

schedule” items. See ECF No. 23-11 at 844-900. Of the CLINs in the bid schedule,

approximately 135 CLINs were specifically identified as optional, as set forth in the list

of optional CLINs in the contract clause incorporating FAR 52.217-7, Option for

Increased Quantity – Separately Priced Line Item (MAR 1989). See ECF No. 23-11 at

808-17.

C. Award to Alstom and Voith’s GAO Protest

Once the SSA reviewed the offerors’ final proposal revisions that had been

submitted after discussions, she determined that Alstom provided the best value proposal.

ECF No. 30-1 at 649-50. The award decision was posted on a government website on

March 21, 2018. Id. at 700. Voith was notified of Alstom’s contract award on the same

day, and the agency held an oral debriefing for Voith on March 28, 2018. ECF No. 31-1

at 76-77, 113-36.

Voith filed its protest with the GAO on April 9, 2018; the agency issued a stop

work notice to Alstom on April 10, 2018. Id. at 158-256. During the course of Voith’s

protest at the GAO, the agency informed the GAO, on July 3, 2018, that the USACE

intended to take corrective action. ECF No. 31-3 at 209-10. The agency intended to

reevaluate the proposals in the competitive range in a variety of ways. Id. at 209. Most

pertinent here, (1) the Source Selection Advisory Council (SSAC) would conduct a new

Technical, Factor I, evaluation of proposals; (2) the SSA would reassess past

performance data so that the agency could reevaluate Past Performance, Factor II; and

(3) the agency would “perform a new comparative analysis and a new best value

determination that comports to the solicitation requirements.” Id. at 209-10. On July 9,

2018, the GAO dismissed Voith’s protest as academic. Id. at 211-12.

D. Second Award Decision in Favor of Alstom’s Proposal

8

The USACE again awarded the contract to Alstom on November 16, 2018, and

notified Voith of the award on the same day. ECF No. 31-5 at 6-11. To be clear, it is

that November 16, 2018 award to Alstom that is the subject of plaintiff’s bid protest

here. 7 The following documents contain the support for the agency’s second award to

Alstom: (1) the SSEB’s revised Final Evaluation Report, addressing actions taken during

August 14-25, 2017, January 16-19, 2018, July 16-20, 2018, and October 4-5, 2018, see

ECF No. 31-4 at 17-171; (2) the SSAC’s revised report, containing the original report of

February 21, 2018, as revised on October 23, 2018, see id. at 172-211; (3) the SSA’s

Source Selection Decision Document (SSDD), dated November 16, 2018, see id. at

212-83; ECF No. 31-5 at 1-5; and (4) underlying documents from the offerors’ final

proposal revisions and other underlying documents in the agency’s files, scattered

throughout the AR. The court reserves a more detailed discussion of documents

contained in the AR for its analysis of plaintiff’s challenges to the agency’s evaluation of

the Technical and Past Performance factors, and Voith’s challenge to the SSA’s best

value determination in favor of Alstom’s proposal.

II. Bid Protest Standard of Review

A. Arbitrary and Capricious Standard

As the United States Court of Appeals for the Federal Circuit has stated, “the

proper standard to be applied in bid protest cases is provided by 5 U.S.C. § 706(2)(A)

[(2012)]: a reviewing court shall set aside the agency action if it is ‘arbitrary, capricious,

an abuse of discretion, or otherwise not in accordance with law.’” Banknote Corp. of

Am. v. United States, 365 F.3d 1345, 1350-51 (Fed. Cir. 2004) (citing Advanced Data

Concepts, Inc. v. United States, 216 F.3d 1054, 1057-58 (Fed. Cir. 2000)). Under this

standard, a procurement decision may be set aside if it lacked a rational basis or if the

agency’s decision-making involved a clear and prejudicial violation of statute, regulation

or procedure. Emery Worldwide Airlines, Inc. v. United States, 264 F.3d 1071, 1085-86

(Fed. Cir. 2001) (citing Impresa Construzioni Geom. Domenico Garufi v. United States,

238 F.3d 1324, 1332-33 (Fed. Cir. 2001)). “The arbitrary and capricious standard

applicable [in bid protests] is highly deferential.” Advanced Data Concepts, 216 F.3d at

1058.

De minimis errors in the procurement process do not justify relief. Grumman Data

Sys. Corp. v. Dalton, 88 F.3d 990, 1000 (Fed. Cir. 1996) (citing Andersen Consulting v.

7

The court has considered all of the evidence to which plaintiff has pointed

regarding the evaluation of proposals before the agency undertook its corrective action.

None of that evidence convinces the court that it should alter its focus from the

documents in the administrative record which are directly relevant to the revised

evaluation of proposals that occurred after Voith’s GAO protest was dismissed as

academic.

9

United States, 959 F.2d 929, 932-33, 935 (Fed. Cir. 1992)). The bid protest plaintiff

bears the burden of proving that a significant error marred the procurement in question.

Id. (citing CACI Field Servs., Inc. v. United States, 854 F.2d 464, 466 (Fed. Cir. 1988)).

Examples of arbitrary and capricious agency action include “when the agency ‘entirely

failed to consider an important aspect of the problem, offered an explanation for its

decision that runs counter to the evidence before the agency, or [the decision] is so

implausible that it could not be ascribed to a difference in view or the product of agency

expertise.’” Ala. Aircraft Indus., Inc.-Birmingham v. United States, 586 F.3d 1372, 1375

(Fed. Cir. 2009) (quoting Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co.,

463 U.S. 29, 43 (1983) (Motor Vehicle Manufacturers)) (alteration in original). The

court will, however, “uphold a decision of less than ideal clarity if the agency’s path may

reasonably be discerned.” Bowman Transp., Inc. v. Arkansas-Best Freight Sys., Inc., 419

U.S. 281, 286 (1974) (citation omitted).

“‘If the court finds a reasonable basis for the agency’s action, the court should stay

its hand even though it might, as an original proposition, have reached a different

conclusion as to the proper administration and application of the procurement

regulations.’” Honeywell, Inc. v. United States, 870 F.2d 644, 648 (Fed. Cir. 1989)

(quoting M. Steinthal & Co. v. Seamans, 455 F.2d 1289, 1301 (D.C. Cir. 1971)).

B. Permanent Injunctive Relief

As the Federal Circuit has held:

In deciding whether a permanent injunction should issue, a court

considers: (1) whether, as it must, the plaintiff has succeeded on the merits

of the case; (2) whether the plaintiff will suffer irreparable harm if the court

withholds injunctive relief; (3) whether the balance of hardships to the

respective parties favors the grant of injunctive relief; and (4) whether it is in

the public interest to grant injunctive relief.

PGBA, LLC v. United States, 389 F.3d 1219, 1228-29 (Fed. Cir. 2004) (citing Amoco

Prod. Co. v. Vill. of Gambell, Alaska, 480 U.S. 531, 546 n.12 (1987)).

III. Analysis

Voith’s protest can be divided into three principal topic areas: Technical

evaluation, Past Performance evaluation and best value analysis, with some natural

overlap between the first two topics and the weighing of all evaluation criteria to

determine the proposal providing the best value to the USACE. Voith’s three main

sub-topics regarding the agency’s Technical evaluation are summarized by plaintiff as the

agency’s failure to consider Voith’s advantages, and Alstom’s disadvantages, in these

areas:

10

1. Voith’s Advantage in Demonstrating the Ability to Achieve

Acceptable Performance Without Costly Optional Draft Tube

Modifications[;]

2. Voith’s Recognition, and Alstom’s Failure to Recognize, the Need for

a 292-Inch Diameter Adjustable-Blade Design[; and the]

3. SSA’s Failure to Consider the Operational and Power Generation

Benefits of Voith’s Better-Performing Design[.]

ECF No. 55-1 at 2.

There is a similar division of Voith’s challenge to the agency’s Past Performance

evaluation, in this instance into four sub-topics. Each of the following sub-topics is cited

as evidence that the agency’s evaluation rating for Past Performance (and in particular,

the PCA) was “Irrational, Contrary to the Underlying Evaluation Record, the Result of

Disparate Treatment, and Performed Contrary to the Solicitation and Source Selection

Plan [(SSP)] Terms”:

1. The SSAC and SSA Irrationally Failed to Acknowledge Unfavorable

Alstom Performance Information Documented in the Evaluation

Record[;]

2. The SSA’s PCA Analysis Constituted Impermissible Disparate

Treatment by Failing to Pursue or Obtain Performance Feedback for

Alstom Projects Identified in Its Proposal as Most Relevant to the

McNary Effort[;]

3. The SSA’s PCA Violated the Solicitation Evaluation Criteria[; and]

4. The Agency Violated the SSP and Solicitation Terms Reserving

Exclusive Responsibility for Assigning PCA Ratings to the SSEB[.]

Id. at 2-3.

Lastly, Voith’s challenge to the SSA’s best value analysis could be divided into

two main sub-topics. First, according to Voith, the USACE failed to consider the

economic value of certain advantages in Voith’s proposal, especially the cost of “draft

tube modifications,” and the value of Voith’s “ability to meet or exceed hydraulic

performance requirements for output, efficiency, and operational flexibility.” Id. at

48-49. Second, Voith asserts that the agency improperly used an illusory price to

measure the additional costs of Voith’s superior proposal. Id. at 45-48. Plaintiff

contends that these flaws in the best value analysis rendered the award decision irrational

and contrary to regulation. Id. at 45.

11

For each of the evaluation areas criticized in this protest, Technical and Past

Performance, the court will begin with a review of the evaluation ratings assigned to

Alstom and Voith. The court will consider the findings of the SSEB, the SSAC, and the

SSA, as set forth in the finalized SSEB and SSAC reports and the SSDD of November

16, 2018. The court will then address the parties’ arguments regarding the alleged

evaluation flaws identified in Voith’s sub-topics.

For the SSA’s best value tradeoff analysis, the court’s inquiry is more

straightforward and poses three questions. First, did the SSA adhere to the solicitation’s

evaluation criteria when she failed, in plaintiff’s view, to acknowledge the value of

certain Voith “advantages”? Second, did the evaluated prices used by the SSA in her best

value tradeoff analysis comport with the evaluation scheme set forth in the solicitation?

And if the answer to these two questions is yes, because the SSA’s best value tradeoff

analysis was consistent with the evaluation scheme set forth in the solicitation, the court

must answer a third question: is plaintiff’s challenge to the SSA’s best value tradeoff

analysis timely?

A. Technical

1. Evaluation Results

a. Alstom

The five-member SSEB (reduced from six original members by a retirement)

came to consensus on most of the ratings for Alstom on Technical, Factor I, but a

minority report expressed the views of two of the five SSEB members. ECF No. 31-4 at

24, 28, 170-71. The SSEB minority expressed no concerns regarding Alstom’s proposal

on Technical subfactors (C) and (E), which were “Turbine component design,

manufacture, and installation experience” and “Unit stator winding design, manufacture,

and installation experience.” Id. at 170-71. The SSEB minority did comment however,

on their perception of risks related to Technical subfactors (A), (B) and (D), which were

“Hydraulic design, modeling, and analysis experience,” “Technical work plan and

schedule,” and “Management and quality control.” Id. These views led the SSEB

minority to conclude that Alstom’s performance risk on Factor I was low to moderate,

and that Alstom should have received a Good rating, not an Outstanding rating, on the

Technical evaluation. Id. at 170.

The SSEB majority disagreed, and awarded Alstom an Outstanding rating on

Factor I. Id. at 24. The entire SSEB unanimously found that Alstom’s ratings on the five

Technical subfactors, (A) through (E), were, respectively, Outstanding, Good,

Outstanding, Good, and Outstanding. Id. at 24, 28-29, 170. The entire SSEB reached

consensus regarding Alstom’s strengths (32), weaknesses (5), and uncertainties (2) for

the Technical subfactors. Id. at 29-43.

12

The SSAC conducted an “independent review of the Source Selection Evaluation

Board (SSEB) evaluation results and ratings assigned,” as well as a “comparative

analysis of each proposal . . . document[ing] the risks in each proposal.” Id. at 176. The

SSAC’s report’s goal was to offer “recommendations to the Source Selection Authority

(SSA) for consideration in making an ultimate selection decision on the best value for the

Government.” Id. There were five SSAC members. Id. at 177.

The SSAC acknowledged the minority report from the SSEB which concluded

that Alstom’s proposal posed a higher performance risk than Voith’s proposal. Id. at 180.

The SSAC, however, sided with the SSEB majority, and found that Alstom’s Outstanding

rating for Technical, Factor I, was justified due to a low risk of unsuccessful

performance. Id. The SSAC then reviewed each of the Technical subfactors and created

a list of “advantages and disadvantages” that the SSAC found in the proposals before it.

Id. at 181-88.

The SSAC concurred with the Outstanding ratings on Technical subfactors (A),

(C), and (E), awarded to both Alstom and Voith by the SSEB. Id. at 181, 185, 187. The

SSAC also concurred with the ratings given by the SSEB for subfactor (D), which were

Good for Alstom and Outstanding for Voith. Id. at 185. For Technical subfactor (B), the

SSAC again concurred with the ratings given by the SSEB for this subfactor (Good for

Alstom and Outstanding for Voith). Id. at 182. The SSAC characterized one of the

weaknesses that the SSEB had assigned in the Technical subfactor (B) to Alstom as a

“slight disadvantage,” related to Alstom’s “performance curves.” Id. at 184.

The remainder of the SSAC’s comparative analysis regarding Technical, Factor I,

was devoted to the topic of the performance risk of Alstom’s and Voith’s proposals. Id.

at 204-11. For example, the SSAC calculated the potential costs, measured in dollars and

in schedule delays, of the remaining weaknesses, after final proposal revisions, in each

proposal. Id. at 206-07. The SSAC’s performance risk analysis was also summarized in

narrative form. Id. at 207-08.

The SSA produced a Source Selection Decision Document (SSDD) on November

16, 2018. See ECF No. 31-4 at 212-83; ECF No. 31-5 at 1-5. As to Alstom’s rating for

Technical, Factor I, the SSA agreed with the SSAC and the majority of the SSEB that the

rating for Alstom should be Outstanding on this factor. ECF No. 31-4 at 228. The SSA’s

review of Alstom’s strengths, weaknesses and uncertainties in the Technical subfactors

largely tracked those discussed in the SSEB’s report, with minor deviations. Id. at

228-41.

Much like the SSAC, the SSA performed a comparative analysis of the proposals

for Technical, Factor I, “[b]ased on the strengths and weaknesses identified previously

in” the SSDD. Id. at 272-74. For Technical subfactor (A), Alstom had a “slight

disadvantage.” Id. at 272. For Technical subfactor (B), Alstom merited a Good rating,

whereas Voith merited an Outstanding rating. Id.; ECF No. 31-5 at 3. For Technical

13

subfactor (C), the SSA mentioned both that Voith had a slight advantage in one respect,

but that generally “neither ha[d] an advantage.” ECF No. 31-4 at 274. For Technical

subfactor (D), the SSA noted that Voith had an advantage. Id. Finally, for Technical

subfactor (E), the SSA determined that Alstom had a slight advantage. Id.

The SSA concurred with the SSAC’s risk analysis of the proposals. In the SSA’s

view, when all of the remaining weaknesses in the proposals were considered, these

“would present low risk to the execution of the contract and will not have a significant

cost or schedule impact over the life of this contract.” ECF No. 31-5 at 2. The SSA

concluded that Voith had “an advantage under Factor I, technical for their relevant

project experience.” Id. at 3. The SSA also found that Voith had “an overall advantage”

on the non-price evaluation factors. Id. at 4.

b. Voith

The five-member SSEB came to consensus on all of the ratings for Voith on

Technical, Factor I. ECF No. 31-4 at 57. The SSEB awarded Voith an Outstanding

rating on Factor I. Id. The entire SSEB unanimously found that Voith’s ratings on the

five Technical subfactors, (A) through (E), were, respectively, Outstanding, Outstanding,

Outstanding, Outstanding, and Outstanding. Id. The entire SSEB reached consensus

regarding Voith’s strengths (49), weaknesses (0), and uncertainties (1) for the Technical

subfactors. Id. at 58-69.

The SSAC report did not mention any notable differences between its view, and

the SSEB’s view, of the ratings for Voith on the Technical subfactors, (A) through (E), or

for the overall Technical rating for Voith of Outstanding. Id. at 180-88, 210. Just as was

the case for Alstom, the SSAC measured the performance risk of the remaining

weaknesses in Voith’s proposal in dollars and schedule delays. Id. at 204-09. The SSAC

noted that Alstom’s remaining weaknesses, in all evaluation criteria combined, were

greater in number than those of Voith, and might “translate to cost and schedule

impacts.” Id. at 208.

The SSA’s comparative analysis of the proposals on Technical, Factor I, has been

largely summarized earlier in this opinion section. As to Voith’s Factor I ratings, the

SSA agreed with the SSAC and the unanimous SSEB that Voith was Outstanding on the

factor overall, and Outstanding on subfactors (A) through (E). ECF No. 31-5 at 3. The

SSA’s review of Voith’s strengths, weaknesses and uncertainties in the Technical

subfactors tracked those discussed in the SSEB’s report in every respect. ECF No. 31-4

at 241-53.

2. Evaluation Errors Alleged by Voith

a. Draft Tube Modifications

14

Plaintiff defines a draft tube as “the conduit at the exit of a turbine through which

the water discharged from the turbine is carried away.” ECF No. 55-1 at 13. Both

offerors were required to price draft tube modifications at the McNary hydroelectric

facility in a number of optional CLINs. See, e.g., ECF No. 69 at 24-25 (citing the CLINs

that include draft tube modifications). According to plaintiff, the SSA failed to recognize

that Voith’s design would not need draft tube modifications, whereas Alstom’s design

would. See ECF No. 55-1 at 15 (“In sharp contrast to Alstom’s ‘draft tube modifications

required’ design, Voith proposed mature, detailed runner designs, backed by modeling

results indicating that Voith’s designs can readily achieve and even exceed the specified

performance targets with the existing McNary draft tubes.”). According to plaintiff,

“[t]he SSA’s failure to take this striking Voith proposal advantage into account was

irrational.” Id. at 18 (citing Motor Vehicle Manufacturers, 463 U.S. at 43).

The parties have thoroughly examined and parsed the solicitation, Voith’s and

Alstom’s final proposal revisions, documentation of the agency’s evaluation of those

proposals, and documents that were produced at the GAO before the agency decided to

take corrective action in this procurement. See ECF No. 55-1 at 13-20 & nn.1-3; ECF

No. 69 at 24-25 & n.2; ECF No. 70 at 30-37; ECF No. 76 at 11-12 & nn.6-7, 21-26; ECF

No. 81 at 5; ECF No. 82 at 11-14. After consideration of all of these portions of the

administrative record, the court finds that the SSA could rationally conclude that both

Voith’s and Alstom’s proposals were likely to require draft tube modifications.

Indeed, the USACE expert who consulted with the SSAC conveyed this opinion to

the SSAC before the SSAC made its final recommendation to the SSA. See ECF No.

31-3 at 171 (stating that “each offeror will need some sort of draft tube modification to

achieve an acceptable design”); ECF No. 31-4 at 183-84, 273 (commenting on the

expert’s opinion as to the “water passageway geometries at McNary”). The court notes,

too, that the agency’s solicitation sought offers that would incorporate design changes

during the collaboration between the USACE and the contractor. See ECF No. 70 at 30

(“The RFP provides for a design-supply-install contract, not proposals for a fixed design

and build only. The RFP demanded an extensive iterative design phase.”). In these

circumstances, the court does not find that the SSA’s evaluation of Voith’s proposal, or

of Voith’s costs for draft tube modifications, was irrational, arbitrary or capricious.

Voith also argues that the SSAC and the SSA erroneously characterized Voith’s

proposal as being founded on its Ice Harbor design, while at the same time concluding

that Alstom’s proposal was founded on the existing water passageways at the McNary

facility. ECF No. 55-1 at 18-19 (citing ECF No. 31-4 at 182, 273). As defendant and

intervenor-defendant have noted, however, the statement in the SSAC’s final report is

supported by a passage in Voith’s final proposal revision. See ECF No. 69 at 25 (citing

ECF No. 29-3 at 47-48); ECF No. 70 at 36 (citing ECF No. 29-3 at 47). The court has

compared this passage in Voith’s proposal, ECF No. 29-3 at 47-48, with other pages of

Voith’s proposal that plaintiff points to as proof that the SSAC and the SSA committed a

15

factual error, ECF No. 29-2 at 267; ECF No. 29-3 at 50, 60, 76; see also ECF No. 55-1 at

15 n.1; ECF No. 76 at 24.

The record is subject to a variety of interpretations, but the SSAC was correct to

note that Voith referenced its Ice Harbor project and used the terms “baseline” and

“baseline model” when doing so. ECF No. 29-3 at 47-48. The court finds that plaintiff

has not shown that the SSAC or the SSA committed a factual error in the description of

Voith’s and Alstom’s proposals. Nor has plaintiff shown that the reference to Ice Harbor

was the source of any significant, prejudicial evaluation error. Plaintiff’s challenge to the

draft tube modifications aspect of the agency’s evaluation of proposals on Technical,

Factor I, fails to show that the agency’s award decision was irrational, arbitrary or

capricious.

b. Adjustable Blade Diameter

Plaintiff argues that the SSA did not take into account a clear advantage of Voith’s

proposal, which, in plaintiff’s view, reflected a better understanding of the adjustable

blade design that would reduce fish mortality at McNary to acceptable levels. ECF No.

55-1 at 20-21. Voith’s optimal fish-friendly design is referred to by plaintiff as the

“292-inch, six-blade adjustable blade runner.” Id. at 20. In plaintiff’s view, Alstom’s

proposal was inferior due to its reliance on a 280-inch adjustable blade runner. Id. at 22

(noting Alstom’s focus on a 280-inch, as opposed to a 292-inch, adjustable blade design

in its proposal). These adjustable blade “runners” are also referred to by plaintiff as

“Kaplan (adjustable-blade) turbine runners.” See ECF No. 76 at 26. Plaintiff’s argument

in this regard, with its emphasis on the distinction between 292-inch adjustable blades

and 280-inch adjustable blades, states that

it was irrational for the SSA to have ignored in her tradeoff analysis and

best-value determination the comparative advantage of Voith’s proposed

Kaplan runner design, as compared to Alstom’s, with respect to the lower

risk of unsuccessful performance and lower likelihood of schedule impact

from additional design iterations.

Id. at 28.

Defendant notes that Voith was awarded more strengths than Alstom for

Technical, Factor I. ECF No. 69 at 26. Indeed, Voith received a higher rating on

Technical subfactor (B), and more strengths within this subfactor, which includes turbine

runner configurations. ECF No. 31-4 at 24, 33, 60-61. The record shows that Voith was

awarded a strength related to its reliance on a 292-inch adjustable blade design. Id. at 61.

The SSA mentioned this strength in the SSDD as well. Id. at 244. The court concludes

that the SSA did take the advantage cited by Voith into account. Plaintiff’s challenge to

this aspect of the evaluation is, in the court’s view, a mere disagreement with the

agency’s highly discretionary technical evaluation of proposals. See, e.g., E.W. Bliss Co.

16

v. United States, 77 F.3d 445, 449 (Fed. Cir. 1996) (stating that “technical ratings . . .

involve discretionary determinations of procurement officials that a court will not second

guess”) (citations omitted).

In a related argument, plaintiff argues that the agency erred when it failed to factor

in all of the costs that would flow from Alstom changing from a 280-inch design to a

292-inch design for the Kaplan turbine runners. ECF No. 55-1 at 24-25. Defendant notes

that the SSA discussed this performance risk in the SSDD in the context of a price

realism analysis of Alstom’s proposal. ECF No. 69 at 27 (citing ECF No. 31-4 at 268).

The SSAC also factored in performance risks flowing from the costs of Alstom’s

potential redesign of turbine runners, in general. See ECF No. 31-4 at 206-08.

The SSA agreed with the SSAC as to the performance risks in Alstom’s proposal.

ECF No. 31-5 at 2. The SSA found that the performance risk for both Voith’s and

Alstom’s proposals was low, and that these proposals’ weaknesses would “not have a

significant cost or schedule impact over the life of the contract.” Id. Based on the record

before the court, the SSA’s consideration of the costs of Alstom’s potential redesign of its

adjustable blade runners has not been shown to be irrational, arbitrary or capricious. This

protest ground, too, is unavailing.

c. Output, Efficiency and Operation Flexibility

Plaintiff states that the SSA erred when she did not take into account the fact that

Voith’s designs “exceeded the performance targets for efficiency and power output” at

McNary, and offered operational flexibility. ECF No. 55-1 at 25-26. Indeed, plaintiff

asserts that the net present value of these advantages in Voith’s proposal was “roughly

$65 million.” Id. at 26. In plaintiff’s reply brief, Voith argues that the SSA irrationally

failed to consider these advantages in her tradeoff analysis, despite having noted various

strengths in Voith’s proposal in an earlier section of the SSDD. ECF No. 76 at 28-29.

Plaintiff places specific emphasis on the SSA’s discussion of Technical subfactor (B). Id.

The court agrees with plaintiff that the SSA never identified advantages in Voith’s

proposal worth roughly $65 million in net present value in the SSDD. But the court also

agrees with defendant that the SSA rationally considered Voith’s advantages in

Technical, Factor I, and that the SSDD is neither incomplete nor defective in this regard.

ECF No. 69 at 29. Moreover, the court agrees with Alstom that the weight given to

Voith’s strengths in Technical, Factor I, has not been shown to be irrational, and that the

SSA’s consideration of Voith’s proposal under this evaluation factor was “in accordance

with the RFP factors.” ECF No. 70 at 39. The court concludes, therefore, that the SSA’s

consideration of Voith’s performance efficiencies survives the arbitrary and capricious

standard of review applicable here. As to plaintiff’s critique of the SSA’s best value

tradeoff analysis, alleging that the SSA irrationally ignored the quantifiable value of

Voith’s performance efficiency advantages, the court addresses that topic in the best

value tradeoff section of this opinion.

17

B. Past Performance

1. Evaluation Results

It is helpful to remember that: (1) a Past Performance evaluation was completed

before the initial award to Alstom and before the corrective action was undertaken by the

agency; (2) additional Past Performance information became available to the evaluators

once the corrective action was undertaken by the agency; and (3) the agency produced a

final Past Performance evaluation. This opinion section will focus on the results of the

agency’s final evaluation of Past Performance, Factor II, of the parties’ proposals. The

process for evaluating Past Performance will be discussed below under the headings

devoted to Voith’s challenges to the agency’s Past Performance evaluation.

a. Alstom

Some of the principal Past Performance ratings by the agency are summarized

here. The SSEB compiled data from Past Performance Questionnaires (PPQs), and based

on this raw data, the SSAC found that Alstom had the following percentages of customer

ratings: Marginal (0%), Satisfactory (12.2%), Very Good (52.8%) and Excellent (35%),

with a combined percentage for Very Good/Excellent ratings of 87.8%. ECF No. 31-4 at

192; see also ECF No. 30-1 at 203. The “most recent and most relevant” CPARS reports

available for Alstom were summarized by the SSAC as providing the following

combined Very Good/Excellent customer ratings: 32.4%, 42.5%, 46.2% and 65%. ECF

No. 31-4 at 194-95.

The SSAC, relying on the SSEB’s findings, concluded that neither Alstom nor

Voith had deficiencies in Past Performance, Factor II. Id. at 197. The SSAC, again

relying on the SSEB’s findings, concluded that Alstom had 3 strengths, 4 weaknesses and

1 uncertainty in Past Performance. Id. Agreeing with the SSEB, the SSAC concluded

that Alstom’s Past Performance data was Relevant. Id. at 200. Disagreeing with the

SSEB, the SSAC rated Alstom on the PCA metric as providing Substantial Confidence.

Id.

Comparing the Past Performance of these two offerors, the SSAC concluded that

“Alstom has a slight performance confidence advantage over Voith with regard to

successful performance for the McNary Turbine Replacement project.” ECF No. 31-4 at

200. The SSA largely concurred with the SSAC, noted two additional strengths for

Alstom, and also removed the single uncertainty regarding Alstom’s Past Performance.

Id. at 253-59, 278-82. The SSA’s rating for Alstom for Past Performance, Factor II, was

Relevant/Substantial Confidence. ECF No. 31-5 at 3. The SSA, in her integrated

analysis of all of the evaluation factors, found that “Alstom ha[d] an advantage over

Voith” in Past Performance. Id. at 4.

b. Voith

18

Some of the principal Past Performance ratings by the agency are summarized

here. The SSEB compiled data from PPQs, and based on this raw data, the SSAC found

that Voith had the following percentages of customer ratings: Marginal (0.6%),

Satisfactory (11.8%), Very Good (38.2%) and Excellent (49.4%), with a combined

percentage for Very Good/Excellent ratings of 87.6%. ECF No. 31-4 at 192; see also

ECF No. 30-1 at 230. The “most recent and most relevant” CPARS reports available for

Voith were summarized by the SSAC as providing the following combined Very

Good/Excellent customer ratings: 32%, 31.3%, 45.1% and 25.8%. ECF No. 31-4 at

194-95.

The SSAC, relying on the SSEB’s findings, concluded that neither Alstom nor

Voith had deficiencies in Past Performance, Factor II. Id. at 197. The SSAC, again

relying on the SSEB’s findings, concluded that Voith had 5 strengths, 5 weaknesses and 0

uncertainties in Past Performance. Id. Agreeing with the SSEB, the SSAC concluded

that Voith’s Past Performance data was Very Relevant. Id. at 198. Disagreeing with the

SSEB, the SSAC rated Voith on the PCA metric as providing Satisfactory Confidence.

Id.

Comparing the Past Performance of these two offerors, the SSAC concluded that

“Alstom has a slight performance confidence advantage over Voith with regard to

successful performance for the McNary Turbine Replacement project.” ECF No. 31-4 at

200. The SSA largely concurred with the SSAC, and did not change any of the strengths

or weaknesses for Voith in Past Performance. Id. at 259-64, 276-77, 279-82. The SSA’s

rating for Voith for Past Performance, Factor II, was Very Relevant/Satisfactory

Confidence. ECF No. 31-5 at 3. The SSA, in her integrated analysis of all of the

evaluation factors, found that “Alstom ha[d] an advantage over Voith for” Past

Performance. Id. at 4.

2. Evaluation Errors Alleged by Voith

a. Unfavorable Alstom Past Performance Information

Voith contends that three types of negative Past Performance information were

irrationally ignored by the SSAC and the SSA. First, according to Voith, the agency

obtained customer feedback from [ ] during a telephone interview that was unfavorable

to Alstom. ECF No. 55-1 at 28-32. Second, plaintiff argues that the fact that one of

Alstom’s customers, [ ], refused to provide feedback during a telephone interview was

“even more damning.” Id. at 32-33. Third, again according to Voith, the SSAC and the

SSA mischaracterized the overall tone of the [ ] project CPARS, the most recent CPARS

considered by the agency for Alstom. Id. at 33-36.

More generally, Voith contends that evidence of the Past Performance evaluation

deliberations of the agency before the GAO protest, when compared to the final Past

Performance evaluation by the SSAC and the SSA, shows that the SSAC and the SSA

19

irrationally ignored negative information in a way that incorrectly improved Alstom’s

Past Performance ratings. See id. at 28 (“Essentially, both entities created a new set of

‘alternate facts,’ at odds with the underlying evaluation record, to avoid acknowledging

that the adverse Alstom performance information they had previously ignored actually

contradicted their narrative of Alstom’s superior recent/relevant performance, which they

had used to reverse the SSEB’s consensus-assigned PCA ratings, to Alstom’s benefit and

to Voith’s prejudice.”). Both defendant and Alstom contend that the SSA’s Past

Performance ratings for Alstom were rational and supported by the record. The court

must agree.

First, as defendant notes, the phone interviews with [ ] and [ ] were given little

weight by the SSAC, as the phone interviews with Alstom’s customers “‘were limited in

detail and not highly informative and therefore were not considered a substantial source

of past performance information.’” ECF No. 69 at 30 (quoting ECF No. 31-4 at 199).

The court has carefully reviewed the notes describing the phone interview results, ECF

No. 31-4 at 161; ECF No. 31-5 at 115-17, along with the consideration of these phone

interview records by the SSA and the SSAC, ECF No. 31-4 at 199-200, 282, and defers

to the agency’s rational consideration of that customer feedback. As for the SSAC’s

consideration of the [ ] CPARS, the court agrees with Alstom that the SSAC’s

categorization of that report as including “‘both positive and negative comments’” was

rational. ECF No. 70 at 45 (quoting ECF No. 31-4 at 278); see also ECF No. 31-4 at 199;

ECF No. 48-1 at 31-34). In addition, the court has reviewed the documentation

describing the CPARS for Alstom in the record, ECF No. 31-4 at 45-47; ECF No. 48-1 at

31-34, and defers to the SSA’s rational analysis of those CPARS, ECF No. 31-4 at 281.

Finally, the court addresses plaintiff’s contention that the agency changed facts to

conform with its intent to award to Alstom. Plaintiff has clarified that Voith does not

accuse the SSA of bias or bad faith. ECF No. 76 at 30 n.12. Instead, plaintiff urges the

court to consider the SSA’s final Past Performance evaluation of proposals with

“appropriate skepticism” because the evaluation is an example of a post hoc

rationalization for a contract award. See id. (citing Centerra Grp., LLC v. United States,

138 Fed. Cl. 407, 420 (2018)).

Factually, this case is distinguishable from Centerra. Here, the SSDD is a

contemporaneous award decision document produced in conformance with proper

reevaluation procedures, whereas in Centerra the agency held improper discussions with

the awardee after requesting a remand to reevaluate proposals. Id. at 410, 416-19 &

nn.5-6. In contrast with the “outlier” facts in Centerra, id. at 416 n.6, the record before

the court in this case supports the rationality of the SSA’s Past Performance evaluation of

Alstom’s proposal, and a presumption of regularity attaches to her analysis. Info. Tech.

& Applications Corp. v. United States, 316 F.3d 1312, 1323 n.2 (Fed. Cir. 2003) (citing

Impresa, 238 F.3d at 1338). Because the administrative record does not show that the

20

SSA irrationally ignored negative feedback as she rated Alstom’s Past Performance, this

protest ground is unavailing.

b. Disparate Treatment, Failure to Seek Out Information

Briefly summarized, plaintiff contends that the agency’s Past Performance

evaluation evidenced disparate treatment, because Alstom’s Canadian projects were

subjected to a less probing analysis than were Voith’s American projects. 8 See ECF No.

55-1 at 36-39. In support of this protest ground, Voith suggests that the agency should

have aggressively pursued additional customer feedback regarding Alstom’s Canadian

projects. Id. at 37 (“The absence of PPQs or CPARS reports for these Canadian projects

Alstom had identified as most relevant to McNary made it incumbent upon the agency

evaluators to obtain feedback from those customers directly, to ensure that both Voith

and Alstom were being treated equally by both being rated on the Past Performance

factor based on a full and complete record of feedback from the customers of the projects

they had self-identified as relevant.”). Defendant and Alstom disagree.

Defendant correctly contends that the agency had sufficient data to perform a

rational evaluation of Alstom’s Past Performance. ECF No. 69 at 31. The government

also notes that Voith’s American projects, and Voith’s robust Past Performance data,

contributed to Voith’s higher rating on the Relevancy aspect of the Past Performance

evaluation. Id. at 31-32. Alstom correctly contends that there was no requirement in the

solicitation that compelled the agency to redouble its data-gathering activities for

Canadian projects. ECF No. 70 at 47. Having considered all of the parties’ arguments in

this regard, plaintiff has not shown that the agency’s data-gathering activities for

Canadian projects evinced disparate treatment. Even though Voith’s projects supplied

the agency with more robust feedback from CPARS, for example, see ECF No. 31-4 at

196, the record shows that the offerors were treated “fairly and impartially,” even though

they were not treated exactly the same, see 48 C.F.R. § 1.102-2(c)(3) (2018).

c. PCA Not in Accordance with Evaluation Scheme

Plaintiff’s “not in accordance with the evaluation scheme” argument is a two-part

challenge to the SSA’s Past Performance evaluation of proposals, focused largely on

8

In its reply brief, plaintiff raises a new disparate treatment argument, contending

that the SSA employed a “far-more-forgiving” standard for balancing negative customer

feedback with positive customer feedback in her evaluation of Alstom’s proposal. ECF

No. 76 at 31, 36. This argument is untimely and waived. See, e.g., Arakaki v. United

States, 62 Fed. Cl. 244, 246 n.9 (2004) (“The court will not consider arguments that were

presented for the first time in a reply brief or after briefing was complete.” (citing

Novosteel SA v. United States, 284 F.3d 1261, 1274 (Fed. Cir. 2002); Cubic Def. Sys.,

Inc. v. United States, 45 Fed. Cl. 450, 467 (1999))).

21

Alstom’s Past Performance, not Voith’s Past Performance. See ECF No. 55-1 at 39-42.

The first allegation is that the SSA improperly resolved an uncertainty in favor of Alstom

based on a letter from Alstom, when such uncertainties should only be resolved through

additional favorable customer feedback. Id. at 39-40. The second allegation is that

because Past Performance data considered by the agency must be recent, the SSA’s

reliance on data for Alstom that was no longer recent invalidated the SSA’s PCA for

Alstom. Id. at 40-42. The court addresses each of these arguments in turn.

Defendant argues that the SSA’s decision to remove the uncertainty regarding

Alstom’s Past Performance was rational, supported by the record, and not contrary to the

evaluation criteria in the solicitation. ECF No. 69 at 32. Further, defendant states that

“Voith does not (and cannot) point to any provision of the RFP that would have required

the Corps to disregard Alstom’s entire record of past performance and a written assurance

that Alstom’s ‘management team’ remained ‘the same’ after its ownership changed.” Id.

(citing ECF No. 31-4 at 247-50). The court agrees with defendant’s assessment that the

SSA could rationally remove the uncertainty for Alstom’s Past Performance, based on the

letter cited, and not violate the evaluation scheme set forth in the solicitation. Plaintiff

did not address defendant’s argument in its reply brief. Thus, plaintiff’s challenge to the

removal of the uncertainty in Alstom’s Past Performance evaluation does not persuade.

The court turns to plaintiff’s argument that the agency did not obtain “recent”

information, as required by the solicitation, to evaluate Alstom’s Past Performance after

Voith’s GAO protest was dismissed. One of Alstom’s principal arguments in this regard

is that the offerors were required to include recent Past Performance information with

their proposals, but those same RFP provisions did not require the agency to continuously

update Past Performance information as the result of protest delays. See ECF No. 70 at

49-50; ECF No. 82 at 18-19. The court finds that the agency complied with the

requirements imposed on it under the solicitation, and that any challenge plaintiff now

wishes to interpose concerning this requirement is untimely.

The court further finds that the agency’s Past Performance evaluation comported

with the FAR and binding precedent requiring that an agency conduct rational

evaluations of proposals. Moreover, the court agrees with the government that the

solicitation did not require a different analysis of trends in Past Performance than the one

the agency conducted here. See ECF No. 81 at 8-9. For all of the above reasons,

plaintiff’s argument that the SSA’s PCA was not in accordance with the RFP’s evaluation

scheme is unavailing.

d. SSEB’s Role in Determining PCA “Usurped”

As stated in one of the subheadings in plaintiff’s opening brief, Voith alleges that

“[t]he Agency Violated the SSP and Solicitation Terms Reserving Exclusive

Responsibility for Assigning PCA Ratings to the SSEB.” ECF No. 55-1 at 42.

Defendant responded to this argument with a thorough analysis of the roles of the SSEB,

22

the SSAC and the SSA, as set forth in relevant record documents and the FAR. ECF No.

69 at 33-34. When plaintiff did not respond to the government’s analysis of the roles of

the SSAC and the SSA, defendant argued, in its reply brief, that this specific challenge to

the Past Performance evaluation had been abandoned. ECF No. 81 at 9.

The court also reads plaintiff’s reply brief as evincing an abandonment of this

protest ground. However, at oral argument, plaintiff responded to the court’s inquiry as

to the status of this particular protest ground, insisting that the argument had not been

abandoned, and, indeed, that this argument did not constitute a separate protest ground at

all. ECF No. 91 at minutes 05:00-17:00. Plaintiff’s counsel also asserted that the

language the court quoted from plaintiff’s brief failed to capture the essence of plaintiff’s

contentions regarding the role of the SSEB in formulating the PCA for each proposal.

As the court understands the colloquy at oral argument, plaintiff does not contend

that the SSA usurped the role of the SSEB in finalizing the PCA ratings. Instead, Voith

contends that the changes that the SSAC made to the PCA ratings determined by the

SSEB constitute evidence of disparate treatment, an irrational evaluation, and conduct not

in accordance with the SSP. In the court’s view, this reframing of Voith’s challenge to

the agency’s PCA ratings does not assist plaintiff.

As to the argument contained in the text of plaintiff’s motion, which asserts that

the RFP did not allow the SSAC to modify the SSEB’s PCA for the proposals being

evaluated, see ECF No. 55-1 at 42-43 (stating that “[t]he SSAC . . . violat[ed] the express

terms of the Solicitation, which stated explicitly that the PCA ratings would be assigned

by the SSEB, and no other body”), the court deems that position to have been abandoned,

and thus, plaintiff’s abandoned argument requires no further consideration by the court,

see, e.g., Beauchamp Constr. Co. v. United States, 14 Cl. Ct. 430, 435 (1988) (not

discussing an argument abandoned by the plaintiff). Even if this argument were not

abandoned, the court agrees with defendant that both the SSAC and the SSA could

rationally modify the PCAs assigned by the SSEB, and could do so without violating the

terms of the solicitation.

And as to the “evidence of disparate treatment and irrationality” argument plaintiff

raises, the record does not support a finding that the SSAC and the SSA acted

irrationally, arbitrarily or capriciously when these evaluators changed the PCAs for Voith

and Alstom. As Alstom notes, “the SSAC thoroughly explained its reasons for its

comparative assessment and concerns regarding some SSEB ratings,” and the SSA’s

analysis in this regard was similarly grounded in rational decision-making and supported

by the record. See ECF No. 70 at 51 (citing ECF No. 31-4 at 197-201, 280-82). The

court concludes that plaintiff has not shown that the modification of the PCAs for Voith

and Alstom by the SSAC and the SSA was either irrational or improper.

C. Best Value Tradeoff

23

1. SSA’s Alleged Failure to Value Voith’s Advantages

Plaintiff argues that the SSA irrationally ignored the costs of the draft tube

modifications required by Alstom’s proposal. ECF No. 55-1 at 48-49. As the court noted

earlier in this opinion, it was not irrational for the SSA to expect that both Voith’s and

Alstom’s proposals were likely to require draft tube modifications. It was rational, then,

for the SSA to not include the “tens of millions of dollars in cost” for Alstom’s draft tube

modifications in her best value tradeoff analysis. Id. at 49. More importantly, plaintiff

has not shown how the SSA’s best value analysis, which did not specifically mention or

account for the cost of Alstom’s draft tube modifications, violated the evaluation scheme

set forth in the solicitation.

Turning to the advantages in Voith’s proposal that may be described as

performance efficiencies, plaintiff argues that the SSA’s best value analysis ignored this

“tremendous economic benefit” to the agency and its customers. ECF No. 55-1 at 49.

Defendant argues that the benefits quantified by Voith are incorporated into the SSDD in

the SSA’s discussion of the strengths in Voith’s Technical proposal. ECF No. 69 at 29.

Thus, as Alstom points out, the SSA properly accounted for Voith’s performance

efficiencies in her best value analysis. See ECF No. 70 at 54 (“[T]he SSA reasonably

considered the various strengths and weaknesses in the offerors[’] proposals as part of the

comparative analysis, tradeoff, and best value determination.”) (citing ECF No. 31-5 at

2-5). Plaintiff has not shown that the SSA’s best value analysis, which did not recognize

the specific economic benefits identified by Voith as flowing from the performance

efficiencies in its proposal, was either irrational or contrary to the evaluation scheme set

forth in the solicitation.

2. SSA’s Use of “Illusory” Prices in the Best Value Tradeoff

According to Voith, the SSA “weigh[ed] Voith’s technical superiority against a

cost differential the agency itself had admitted, in its own documented price analysis,

would be impossible to realize.” ECF No. 55-1 at 8. Voith concludes, therefore, that the

SSA’s best value tradeoff analysis did not properly weigh the additional cost for the

Corps to obtain the technical advantages in Voith’s proposal. See ECF No. 76 at 41

(citing 48 C.F.R. § 15.101-1(c) (2018)). Both plaintiff and Alstom submitted additional

authority on this topic, and the parties’ presentations at oral argument covered this topic

in detail. The key to the resolution of this challenge to the tradeoff analysis lies in the

solicitation.

There is no dispute that Price, Factor IV, required that the agency total all of the

CLINs in each proposal, for both base and optional items. ECF No. 23-11 at 589.

Plaintiff notes this solicitation requirement, but then states that the best value tradeoff,

performed by the SSA in accordance with the solicitation’s terms, violated the FAR.

ECF No. 55-1 at 46. According to plaintiff, because the evaluated price of Voith’s

proposal was “artificially” disconnected from the actual expenses of contract

24

performance, the SSA’s tradeoff decision was illogical and precluded by the FAR. See

id. (“While the Solicitation required the agency to evaluate offerors’ relative standing on

the unscored Price factor using this artificially inflated ‘evaluated price,’ the FAR’s

tradeoff procedure precludes the SSA from weighing the benefits of a superior technical

proposal against added costs the Government well knows it can never, and will never,

incur in the best-value tradeoff.”).

While the court agrees that a number of the CLINs in Voith’s proposal were

deductive, in that certain optional CLINs would cause the cancellation of base CLINs,

this is precisely the scheme that the agency presented to the offerors in the solicitation.

When the SSA used the proposals’ evaluated prices determined by Price, Factor IV, in

her tradeoff analysis, the SSA adhered to the evaluation scheme that was disclosed to the

offerors. Thus, the approach used in the SSA’s tradeoff analysis, as a whole, conformed

with the RFP.

3. Voith’s Challenge to the Best Value Tradeoff Is Untimely

The court agrees with defendant and Alstom that plaintiff’s critique of the

evaluated price mechanism set forth in the solicitation, as that evaluated price is carried

through in the tradeoff analysis, is not timely asserted. ECF No. 69 at 35; ECF No. 70 at

53. The proper time to have challenged the evaluated price methodology was pre-award,

not post-award. This type of challenge must be brought before proposals are received by

the agency. See Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308, 1313 (Fed. Cir.

2007) (“We also hold that a party who has the opportunity to object to the terms of a

government solicitation containing a patent error and fails to do so prior to the close of

the bidding process waives its ability to raise the same objection subsequently in a bid

protest action in the Court of Federal Claims.”). Under Blue & Gold Fleet, plaintiff’s

attempt to change the evaluation scheme of this procurement, post-award, is untimely.

The parties found a great deal of commentary in GAO decisions as to the

timeliness of challenges to the rationality and propriety of an agency’s price evaluation.

See ECF Nos. 89-90. None of these GAO decisions sustained a protest of a tradeoff

analysis which incorporated an illusory evaluated price calculated pursuant to the terms

of a solicitation. In contrast, one of the GAO decisions cited by plaintiff specifically

found that a challenge to a price evaluation scheme was untimely because it was brought

after award. See Trinity Ship Mgmt., LLC, B-416167, B-416167.2, 2018 CPD ¶ 214,

2018 WL 3101249, at *7 (Comp. Gen. June 19, 2018) (rejecting a post-award challenge

to an “expressly stated” price evaluation scheme as untimely). When this court and the

GAO have considered post-award challenges to the prices used in a best value tradeoff

analysis, those challenges have been found to be untimely if the offeror was on notice of

the evaluation scheme. See, e.g., Ocean Ships, Inc. v. United States, 115 Fed. Cl. 577,

592 (2014) (citing Blue & Gold Fleet, 492 F.3d at 1313); Am. Corr. Healthcare, Inc.,

B-415123.3, B-415123.4, B-415123.5, 2018 CPD ¶ 85, 2018 WL 1536745, at *5 (Comp.

Gen. Jan. 2, 2018) (stating that if the protestor “believed this pricing evaluation scheme

25

to be inadequate, it should have protested this alleged solicitation impropriety before the

closing time for receipt of proposals”).

Even if plaintiff’s challenge to the use of the proposals’ evaluated prices in the

best value tradeoff decision were timely, plaintiff has not established that a FAR violation

occurred here. Voith relies on two provisions, FAR 15.101-1 and FAR 15.308, which

describe a tradeoff analysis component--the “additional cost” of the higher priced

proposal. ECF No. 55-1 at 45. In FAR 15.101-1(c), the relevant phrase is “[t]he

perceived benefits of the higher priced proposal shall merit the additional cost.” In FAR

15.308, the relevant phrase is “documentation [of the source selection decision] shall

include the rationale for any business judgments and tradeoffs made or relied on by the

SSA, including benefits associated with additional costs.” Neither of these provisions

directly address the question of whether an illusory evaluated price is an impermissible

measure of the additional cost of the higher priced proposal. Nor do any of the GAO

decisions cited by plaintiff rely on these FAR provisions to invalidate a best value

tradeoff analysis. See ECF No. 90.

Defendant and Alstom argue that the FAR provisions cited by plaintiff actually

support the SSA’s best value tradeoff analysis, because these provisions require that the

tradeoff be based on the evaluation criteria set forth in the solicitation. ECF No. 69 at

35-36; ECF No. 70 at 53. The court agrees that the SSA’s best value tradeoff analysis

has not been shown to violate these FAR provisions. Further, even if plaintiff’s challenge

to the tradeoff analysis were timely, the court has found no legal authority that would

permit this court to enjoin an award decision where the proposals’ prices were evaluated

pursuant to the methodology set forth in the solicitation, and those evaluated prices were

then used in the agency’s best value tradeoff analysis. 9 For all of these reasons, the

SSA’s best value award to Alstom survives review.

D. Permanent Injunctive Relief Not Warranted

Plaintiff has not succeeded on the merits of its protest. “Because proving success

on the merits is a necessary element for a permanent injunction,” no injunctive relief is

9

The GAO has noted that the evaluation of the offerors’ prices in certain

procurements is not always an exact science. See MAR, a Div. of Oasis Sys., LLC,

B-414810.5, 2018 CPD ¶ 266, 2018 WL 3868896, at *5 (Comp. Gen. July 26, 2018). If

the evaluated prices did not distort the price differences between the offerors, it is

difficult to establish that the disappointed offeror was prejudiced by unrealistic evaluated

prices, even in a best value tradeoff procurement. Id. at *6. Here, the SSA’s use of the

evaluated prices for Voith and Alstom in her best value tradeoff analysis has not been

shown to have distorted the price differential between these proposals.

26

warranted in this case. Dell Fed. Sys., L.P. v. United States, 906 F.3d 982, 999 & n.13

(Fed. Cir. 2018). This protest must be dismissed.

E. Plaintiff’s Motion to Strike

Finally, the court addresses plaintiff’s motion to strike the declaration of the SSA,

Donna L. Street. ECF No. 75. Plaintiff requests that the SSA’s declaration be stricken,

or, alternatively, that the court “attribute no weight to the Street Declaration.” Id. at 1.

Both defendant and Alstom oppose plaintiff’s motion. See ECF Nos. 78-79. The dispute

focuses on the purposes for which the declaration was submitted by defendant, and

whether the court’s consideration of that document is justified under this court’s caselaw

and the FAR.

In essence, the Street declaration, prepared after this litigation was well underway,

discusses the price premium Ms. Street would not have been willing to pay for the

“overall advantage for Voith in the combined non-price factors.” ECF No. 69-1 at 2.

The price premium for Voith’s proposal discussed in the SSA’s contemporaneous SSDD

was $267,161,904. See id. at 1 (citing ECF No. 31-5 at 4). The other price premiums the

SSA would not have been willing to pay, according to her newly crafted declaration, are

$148,928,550, or anything over $50,000,000. Id. at 2 (citing ECF No. 31-5 at 40). For

its consideration of the merits of this protest, the court does not view the post hoc

rationalization provided in the Street declaration to be relevant. See, e.g., Sys. Eng’g

Int’l, Inc., B-402754, 2010 CPD ¶ 167, 2010 WL 2861120, at *4 n.3 (Comp. Gen. July

20, 2010) (stating that when a “contracting officer’s analysis is not reflected anywhere in

the contemporaneous record[,] we give little weight to this post-hoc analysis”).

Whether the court should consider the Street declaration for any sort of prejudice

inquiry is a moot question, because the court, under the deferential standard of review

applicable here, has found no error in the agency’s contract award. Similarly, because

plaintiff has not prevailed on the merits in this protest, the potential use of the Street

declaration for the fashioning of equitable relief is also a moot inquiry. There is,

therefore, no need to consider the Street declaration in this litigation. Plaintiff’s motion

to strike the declaration of Ms. Donna L. Street is DENIED, even though the court

accords no weight to the content of that document.

IV. Conclusion

Accordingly,

(1) Plaintiff’s motion for judgment on the AR, ECF No. 55, is DENIED;

(2) Defendant’s cross-motion for judgment on the AR, ECF No. 69, is

GRANTED;

27

(3) Intervenor-defendant’s cross-motion for judgment on the AR, ECF

No. 70, is GRANTED;

(4) Plaintiff’s motion to strike the declaration of Donna L. Street, ECF

No. 75, is DENIED;

(5) The clerk’s office is directed to ENTER final judgment for defendant

and intervenor-defendant, DISMISSING plaintiff’s complaint, with

prejudice; and,

(6) On or before May 17, 2019, the parties shall CONFER and FILE a

proposed redacted version of this opinion, with any competition-

sensitive or otherwise protectable information blacked out.

IT IS SO ORDERED.

s/Patricia E. Campbell-Smith

PATRICIA E. CAMPBELL-SMITH

Judge

28