Opinion

Caquelin v. United States

Court
United States Court of Federal Claims
Filed
Nov 6, 2018
Status
Published
Cited by
0 cases
Authority
More cited than 5.8%

“Government hardly could go on if to some extent values incident to property could not be diminished without paying for each such change in the general law.”

How later courts described this case

  • “Government hardly could go on if to some extent values incident to property could not be diminished without paying for each such change in the general law.”
  • “Th[is] traditional rule also avoids otherwise difficult line-drawing problems” with how much physical taking would be too much
  • “In Loretto, was possible for the landowner to act in a manner so as to avoid the taking . . . [because] a landlord could avoid the law’s requirements by ceasing to rent the building to tenants, but [] this did not make the cable company’s invasion of the property not permanent.”
  • The “triggering event for any takings claim under the Trails Act occurs when the NITU is issued.”

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

No. 14-37L

(Filed: November 6, 2018)

**********************************

NORMA CAQUELIN, ) Post-trial decision on remand in a rails-to-

) trails takings case; liability for a

Plaintiff, ) temporary taking arising upon issuance of

) a NITU by the Surface Transportation

v. ) Board

)

UNITED STATES, )

)

Defendant. )

)

)

**********************************

Thomas S. Stewart, Stewart, Wald & McCulley LLC, Kansas City, Missouri, for

plaintiff. With him at the trial and on the briefs was Elizabeth McCulley, Stewart, Wald &

McCulley LLC, Kansas City, Missouri. Also with him on the briefs were Steven M. Wald of

Stewart, Wald & McCulley LLC, St. Louis, Missouri, and J. Robert Sears, of Baker Sterchi

Cowden & Rice, L.L.C., St. Louis, Missouri.

Kristine S. Tardiff, Trial Attorney, Natural Resources Section, Environmental and

Natural Resources Division, United States Department of Justice, Concord, New Hampshire for

defendant. With her on the briefs was Jeffrey H. Wood, Acting Assistant Attorney General,

Environmental and Natural Resources Division, United States Department of Justice,

Washington, D.C.

OPINION AND ORDER

LETTOW, Senior Judge.

This rails-to-trails takings case is before the court after a trial held on remand from the

United States Court of Appeals for the Federal Circuit. The remand directed the court to develop

a factual record bearing on the government’s contention that a set of precedents in the court of

appeals should be overruled. See Caquelin v. United States, 697 Fed. Appx. 1016 (Fed. Cir.

2017) (“Caquelin II”), vacating 121 Fed. Cl. 658 (2015) (“Caquelin I”). The government had

argued on appeal that a recent decision of the Supreme Court, Arkansas Game & Fish Comm’n v.

United States, 568 U.S. 23 (2012), had undercut prior decisions by the Federal Circuit (and,

indeed, the Supreme Court) relating to the analysis of takings claims in the rails-to-trails context.

See Caquelin II, 697 Fed. Appx. at 1019 (“[E]n banc review may be warranted” because the

“Arkansas Game decision does raise questions about Ladd [v. United States, 630 F.3d 1015 (Fed.

Cir. 2010)],” and other earlier rails-to-trails decisions by the court of appeals.).

The case has its genesis in a Notice of Interim Trail Use (“NITU”) issued by the federal

Surface Transportation Board (“STB”), which authorized conversion of a portion of a railroad

line located in Hardin and Franklin Counties, Iowa and its attendant right-of-way into a public

recreational trail pursuant to Section 208 of the National Trails System Act Amendments of

1983, Pub. L. No. 98-11, § 208, 97 Stat. 42, 98 (“Trails Act”) (codified at 16 U.S.C. § 1247(d)).1

Plaintiffs, Kenneth Caquelin, now deceased,2 and his wife, Norma Caquelin, owned two parcels

of land adjacent to and under the railroad right-of-way on the date of the STB’s action.3 For one

parcel, the predecessor railroad had acquired its interest by a right of way deed, and for the other

parcel, the railroad had acquired its rights by condemnation. Stip. ¶ 1; Caquelin I, 121 Fed. Cl.

at 660. The successor railroad held easements limited to railroad purposes that were exceeded by

issuance of the NITU, rendering the government liable for taking plaintiffs’ property without just

compensation under the Fifth Amendment. See, e.g., Preseault I, 494 U.S. at 12-13 (holding that

the Tucker Act, 28 U.S.C. § 1491(a), provided a remedy for an alleged taking of a property

1

The original purpose of the Trails Act “was to preserve unused railroad rights-of-way by

converting them into recreational trails.” Barclay v. United States, 443 F.3d 1368, 1371 (Fed.

Cir. 2006) (citing Preseault v. Interstate Commerce Comm’n, 494 U.S. 1 (1990) (“Preseault I”)).

The Trails Act Amendments in 1983 added new provisions that created a “railbanking” system

that allowed rail carriers to transfer management of rail corridors to private or public entities for

interim management as public recreational trails while preserving the ability to reactivate the

abandoned rail corridors for potential future railroad use. 16 U.S.C. § 1247(d). A NITU serves

as the mechanism that bars the fee owners’ reversionary interest during the pendency of trail-use

negotiations. See Preseault I, 494 U.S. 8, 10; Barclay, 443 F.3d at 1374.

2

Mr. Caquelin died on July 24, 2017. Tr. 674:9-14; Corrected Stipulations of Fact for

Trial (“Stip.”) ¶ 5, ECF No. 51. On the date the NITU was issued, Mr. and Mrs. Caquelin held

the property as joint tenants with full right of survivorship, Stip. Ex. 4, and Mrs. Caquelin as the

surviving spouse succeeded to title upon her husband’s death, see id.

The transcript of the trial will be cited as “Tr. __.” The Stipulations incorporate

extensive documentary exhibits, and citations to those exhibits will appear as “Stip. Ex. ___.”

Defendant’s exhibits will be cited as “DX ___,” and plaintiff’s exhibits will be cited as “PX

___.”

3

Mrs. Caquelin is a widow in her 80s who was in ill health at the time of the trial and not

able to testify despite having been called by the parties to do so. Tr. 445:22 to 447:8, 671:10 to

674:19. The property at issue was purchased by Mrs. Caquelin’s great grandfather, William

Summer Nobles in 1892. Stip ¶ 2. Mrs. Caquelin’s family has owned the farmland since that

purchase. Stip. ¶ 2. In Mrs. Caquelin’s hands, the property thus qualifies as a “Century Farm” in

Iowa parlance. The house in which Mrs. Caquelin was born and raised abuts her farmland and

was viewed during the site visit. Tr. 672:22 to 673:9.

2

interest in land previously used as a railroad right-of-way that had been transferred to a public

entity for use as a public trail).4

FACTS5

The parties’ dispute concerns a 10.46-mile strip of land extending from milepost 201.46

near Ackley, Iowa, to milepost 191.0, outside Geneva, Iowa, upon which the North Central

Railway Association, Inc. (“North Central Railway”) previously acquired easements for railway

purposes through a series of mesne conveyances. Caquelin I, 121 Fed. Cl. at 660. A railroad

had been constructed by the Eldora Railroad and Coal Company in 1866 from approximately one

mile north of Eldora, Iowa, to Ackley, Iowa for the purpose of transporting coal from the Coal

Bank Hill area in the Iowa River valley near Eldora6 to a connection at Ackley with an east-west

railroad, then known as the Dubuque & Sioux City Railroad, which later became part of the

Illinois Central Railroad. Stip. Ex. 11 at STB000023. Between 1868 and 1870, the line was

extended north to Northwood, Iowa, and south to Marshalltown, Iowa, where it connected with

the Chicago & North Western Railroad. Id. A predecessor extending the rail line, the Central

Railroad of Iowa,7 acquired rights in one of the parcels at issue by a right-of-way deed, see

Caquelin I, 121 Fed. Cl. at 660 (citing Pls.’ Mem. in Support of Mot. for Partial Summ.

Judgment on Liability (“Pls.’ Mot.”), at 13 & Exs. A-2 (Maps of the Line) & J (Right of Way

Deed by Henry and Maria Ihde to Central Railroad of Iowa (filed Apr. 30, 1870)), and rights to

the second parcel by a condemnation, see id. (citing Pls.’ Mot. at Ex. K (Latham Condemnation,

Franklin County, Iowa (witnessed Aug. 31, 1870))). North Central Railway acquired property

rights in the rail corridor in 1989. See United States’ Cross-Mot. for Summ. Judgment & Mem.

in Support, and Opp’n to Pls.’ Mot. for Partial Summ. Judgment on Liability (“Def.’s Cross-

Mot.”) at 2-3, ECF No. 18. The rail corridor traverses a rural area of fertile agricultural land.

See id. at 2; see also Stip. Ex. 6 (Franklin County Assessor’s map of parcels). Indeed, the

segment of the rail corridor at issue in this case is comprised of Klinger silty clay loam and

4

The Taking Clause of the Fifth Amendment provides that “private property [shall not] be

taken for public use, without just compensation.” U.S. Const. amend. V.

5

The recitation of facts is drawn from the record of the trial held in Eldora, Iowa from

May 30, 2018 through June 1, 2018, stipulations of fact filed by the parties in advance of trial,

and uncontested facts developed during proceedings in 2015 related to the parties’ cross-motions

for partial summary judgment on liability.

6

Mining was discontinued many years ago. The locality of the mine now is preserved in

name by the Coal Bank Hill Bridge, which traverses the Iowa River between Fallen Rock State

Preserve to the north and Pine Lake State Park to the south. The bridge is listed on the National

Register of Historic Places.

7

The Central Railroad of Iowa was succeeded by the Central Iowa Railway and

eventually became part of the Minneapolis and St. Louis Railway system.

3

Dinsdale silty clay loam (designated soil types 184 and 337B, respectively), DX22, which both

have a very high Corn Suitability Rating (“CSR”) of 95, DX 11; see also Tr. 246:20 to 248:5.8

Ms. Caquelin is a resident of Cedar Falls, Iowa, who acquired the two parcels, numbered

1219200016 and 1219200001, in Franklin County, Iowa, through inheritance from her

grandparents. Stip. ¶¶ 2-5 & Ex. 6 (map of parcels).9 Plaintiff alleges that under Iowa law, she

gained fee title up to the centerline of the rail corridor in question. Compl. ¶ 4; see also Pl.’s

Mot. at 1-2, Exs. G (Warranty Deed (May 11, 2007)), H (Summary of Parcels (Jan. 15, 2015)),

& I (Map of Parcels); Hr’g Tr. 5:21-25 (May 14, 2015).

On May 13, 2013, North Central Railway filed a Proposed Abandonment with the STB,10

including a verified notice of exemption pursuant to 49 C.F.R. § 1152.50, seeking to abandon the

railroad line on the grounds that “no local traffic [or overhead] has moved over the [l]ine for at

least two years.” Stip. Ex. 11 at STB000006, STB000009 (Notice of Exemption-Abandonment

Exemption (May 9, 2013)).11 Under STB’s regulations, the abandonment exception for the

8

CSR ratings extend from 00 (nonexistent) to 100 (perfect). By comparison, CSR ratings

for other good-to-excellent farmland that was at issue in another rails-to-trails case, located in the

same general area of Iowa, ranged from 56 to 97.5. See Sears v. United States, 132 Fed. Cl. 6,

16 (2017), aff’d, 726 Fed. Appx. 823 (Fed. Cir. 2018). For a more detailed description of CSR

ratings in Iowa, which are based on soil information generated by the United States Department

of Agriculture and adapted by Iowa State University to take account of variables pertinent to

land in the State, see Sears, 132 Fed. Cl. at 13-14 nn.11, 12.

9

In 1982, Mrs. Caquelin inherited a real estate contract from her mother Lois R. Hoffman.

Stip. ¶ 3; see also Stip. Ex. 1 (real estate contract between Lois R. Hoffman and Gary L. and

Joyce M. Fairbanks (Mar. 13, 1981)). At that point, she held legal title but not equitable title.

See Installment Land Contract, Black’s Law Dictionary (10th ed. 2014). That conditional

contract for sale was never fully implemented, and the equitable as well as legal title was fully

vested in Mrs. Caquelin in 1986. Stip. ¶ 4; see also Stip. Exs. 2, 3 (deeds recorded Dec. 29 and

30, 1986).

10

The STB has authority “to regulate the construction, operation, and abandonment of

most railroad lines in the United States.” Caldwell v. United States, 391 F.3d 1226, 1228 (Fed.

Cir. 2004).

11

49 C.F.R. § 1152.50 addresses abandonments and discontinuances of service and

trackage rights that are exempt from the generally applicable procedures outlined under 49

U.S.C. § 10903 and provides, in pertinent part:

An abandonment or discontinuance of service or trackage rights is exempt if the

carrier certifies that no local traffic has moved over the line for at least 2 years

and any overhead traffic on the line can be rerouted over other lines and that no

formal complaint filed by a user of rail service on the line (or a state or local

government entity acting on behalf of such user) regarding cessation of service

4

railroad line was scheduled to become effective July 5, 2013. See Stip. Ex. 11 at STB000074-75

(STB Notice (June 5, 2013)).

Shortly before the abandonment exception became effective, on June 24, 2013, the City

of Ackley and the Iowa National Heritage Foundation (collectively “the City”) filed a request for

issuance of a Public Use Condition under 49 U.S.C. § 10905 and a NITU under the Trails Act.

See Stip. ¶ 12.a & Ex. 11 at STB000066 (Pet. for Recons. (filed June 21, 2013 and entered June

24, 2013)); Hr’g Tr. 6:4-11 (May 14, 2015) (noting that “the railroad initially applied purely for

abandonment”).12 Several days later, on June 27, 2013, a letter from North Central Railway was

entered with the STB indicating its agreement with the requested public use condition and related

restrictions and its willingness to negotiate with the Iowa Trails Council regarding acquisition of

the railroad line. See Stip. ¶ 12.c; see also Stip. Ex. 11 at STB000073 (Letter to Chief, Section

of Administration, Office of Proceedings, STB from Counsel for North Central Railway (filed

June 24, 2013 and entered June 27, 2013)). On July 3, 2013, STB accordingly issued a NITU for

the railroad line. Stip. Ex. 11 at STB000077 (STB Decision and Notice of Interim Trail Use or

Abandonment (July 3, 2013)).13 The NITU provided a 180-day period during which the railroad

could negotiate with the potential trail group regarding “railbanking and interim trail use” of the

corridor. Id. at STB000080. After the 180-day period, absent an extension, the NITU would

expire by its own terms, at which point the railroad would be authorized to abandon the line. See

id. at STB000081.

over the line either is pending with the Board or any U.S. District Court or has

been decided in favor of the complainant within the 2-year period. The complaint

must allege (if pending), or prove (if decided) that the carrier has imposed an

illegal embargo or other unlawful impediment to service.

49 C.F.R. § 1152.50(b) (emphasis added).

12

49 U.S.C. § 10905 provides, in relevant part:

When the [STB] approves an application to abandon or discontinue . . . , the

[STB] shall find whether the rail properties that are involved in the proposed

abandonment or discontinuance are appropriate for use for public purposes,

including highways, other forms of mass transportation, conservation, energy

production or transmission, or recreation. If the [STB] finds that the rail

properties proposed to be abandoned are appropriate for public purposes and not

required for continued rail operations, the properties may be sold, leased,

exchanged, or otherwise disposed of only under conditions provided in the order

of the [STB].

49 U.S.C. § 10905.

13

Mr. and Mrs. Caquelin maintained ownership over the two parcels in question on that

date.

5

On October 15, 2013, the Iowa Trails Council filed a Trail Use Request with the STB,

and negotiations over a Trail Use Agreement ensued, contemplating that the rail corridor would

be used as a public recreational trail with railbanking for possible future activation as a railroad.

See Caquelin I, 121 Fed. Cl. at 662.14 No agreement was reached, however. On December 6,

2013, the Iowa National Heritage Foundation requested a 180-day extension to continue

negotiations, see Stip. Ex. 11 at STB000082 (Letter to Cynthia T. Brown, STB, from President,

Iowa Natural Heritage Foundation (Dec. 6, 2013)), but North Central Railway did not file a letter

indicating its consent, and on December 30, 2013, the NITU expired, see id.; see also Hr’g Tr.

12:7-15, 29:22 to 30:4 (May 14, 2015). On March 31, 2014, the railroad consummated

abandonment of its line and the STB’s regulatory jurisdiction ended. Stip. ¶ 12.f & Ex. 11 at

STB000085 (STB Decision (May 9, 2014)). On April 24, 2014, North Central Railway notified

the STB that it had exercised the authority to fully abandon the line. Id. ¶ 12.f & Ex. 11 at

STB000084 (Notice of Consummation (Apr. 24, 2014)).

On January 16, 2014, Mr. and Mrs. Caquelin filed suit in this court. Their complaint

alleged an uncompensated taking of their property in contravention of the Fifth Amendment.

Specifically, plaintiffs argued that cessation of railroad activities across the burdened property

effected an abandonment under Iowa law of the railroad-purposes easement, leading to a taking

when the STB forestalled plaintiffs from regaining use and possession of their property. Compl.

¶¶ 7-9. Plaintiffs averred the government’s action “diminish[ed] the value of the remaining

property[] and [engendered] delay damages based upon the delayed payment of compensation.”

Compl. ¶ 10. Plaintiffs requested damages equal to the “full fair market value of the property . . .

on the date it was [allegedly] taken, including severance damages and delay damages, and costs

and attorneys’ fees” in addition to “such further relief as [the] [c]ourt may deem just and proper.”

Compl. at 3.15

14

The complaint incorrectly lists the date as October 15, 2001. Compl. ¶ 6.

15

At trial, the parties conceded that the segment of the rail corridor at issue was limited to

the west half of the corridor south of milepost 191, an area of .359 acres. See PX 2 (Expert

Report of Dr. James B. Kliebenstein) at 7, 9; DX 18 (Expert Report of Gary Thien) at 7, 16; Tr.

204:15 to 207:18, 236:11 to 237:9, 511:4 to 516:20.

Mrs. Caquelin should have ownership of the west half of the corridor north of milepost

191 but for a cloud on title attributable to improper deeds transferring her interest to her neighbor

to the east, David Wohlford. The corridor north of milepost 191 was subject to a NITU issued

on October 23, 2001, Stip. Ex. 8 at STB000142, but no trail agreement was ever reached. The

railroad quitclaimed its right-of-way in the entirety of that part of the corridor to D.W.R.R., LLC

on October 21, 2002. Stip. Ex. 9 at US000033-34. D.W.R.R., LLC was controlled by Don

Wohlford, David Wohlford’s father. On December 18, 2003, D.W.R.R. LLC quitclaimed the

former railroad corridor north of milepost 191 to Mrs. Caquelin’s neighbor to the east, David

Wohlford. Stip. Ex. 10 at US 000039. This set of quitclaim deeds inappropriately encompassed

Mrs. Caquelin’s residual fee interest as well as that of Mr. Wohlford.

6

On January 16, 2015, plaintiffs filed a motion for partial summary judgment on the issue

of liability. See Pls.’ Mot. On March 6, 2015, the government responded with a cross-motion

for partial summary judgment on the same issue. See Def.’s Cross-Mot. These motions were

thoroughly briefed and were argued at a hearing held on May 14, 2015. The court granted

plaintiff’s motion for summary judgment and denied defendant’s cross-motion for summary

judgment on June 17, 2015. Caquelin I, 121 Fed. Cl. at 658. In its opinion, the court concluded

that the government was liable to the Caquelins under the three-part analysis outlined by the

Federal Circuit in Preseault v. United States, 100 F.3d 1525 (Fed. Cir. 1996) (“Preseault II”).

See Caquelin I, 121 Fed. Cl. at 663-67. Following this decision, on November 18, 2015, the two

parties stipulated to the amount of just compensation, including principal and interest, of

$900.00. Stipulation as to Just Compensation (“First Stip.”) at 1, ECF No. 30. Judgment was

entered under Rule 54(b) of the Rules of the Court of Federal Claims (“RCFC”) on January 6,

2016. Judgment, ECF No. 32. A few months later, the government submitted a notice for appeal

to the Federal Circuit. Notice of Appeal, ECF No. 35. In the appeal, the government argued

“the 180-day blocking of reversion was not a categorical taking, but instead calls for a multi-

factor analysis . . . invok[ing] the general ‘regulatory takings’ framework set forth to govern

land-use restrictions in Penn Central . . . and the temporary-takings analysis set forth to govern

the repeated controlled floodings . . . at issue in Arkansas Game & Fish . . . .” Caquelin II, 697

Fed. Appx. at 1019 (citing Penn Central Transp. Co. v. City of New York, 438 U.S. 104, 124

(1978); Arkansas Game, 568 U.S. 38-40). At bottom, the government’s “principal argument is

that Ladd should be overruled en banc” by the Federal Circuit and replaced by a more ad-hoc

multi-factor analysis. Id.

In a short per curium opinion, the Federal Circuit vacated and remanded this court’s

decision to grant summary judgment in favor of the plaintiffs. The Federal Circuit opined that

“[e]n banc review may be warranted” since “Arkansas Game does raise questions about Ladd,”

and instructed this court to further develop the litigation record to determine “how the

government-advanced multi-factor analysis applies in this case, on the assumption that such an

analysis is the governing standard.” Caquelin II, 697 Fed. App. at 1019-20 (emphasis added).

The appellate court noted that “this panel cannot declare Ladd no longer to be good law based on

. . . Arkansas Game.” Id. at 1019. The Federal Circuit also requested this court to “discuss[]

what facts invoke which of the Supreme Court’s standards” in order to “focus the appellate

consideration of the issues raised by the government.” Id. at 1020. In short, this court was

charged with developing a conceptual framework followed by analysis of a factual record

bearing on the government’s proffered multifactor analysis approach.

Following this prime directive of the Federal Circuit, the court started the process of

developing the requested factual record. In preparation for the trial, on April 3, 2018, the parties

filed joint stipulations of fact. See Stipulations of Fact for Trial, ECF No. 48. This was followed

by revised stipulations of fact for trial that corrected some minor errors, filed May 10, 2018. See

Stip. A three-day trial was held in Eldora, Iowa from May 30, 2018 to June 1, 2018. At the trial,

the court heard from both fact and expert witnesses and conducted a site visit on the second day

of trial for the court to see and examine the land at issue and to hear testimony from witnesses

about the land on site.

7

After the trial, the court requested post-trial briefing by the parties to further hone the

factual record. Scheduling Order of June 11, 2018, ECF No. 61. Plaintiff filed her opening post-

trial brief on July 20, 2018. Pl.’s Post-Trial Br., ECF No. 66. The government filed its

responsive post-trial brief on August, 29, 2018. Def.’s Post-Trial Br., ECF No. 68. A reply brief

was filed by the plaintiff on September 11, 2018, Pl.’s Post-Trial Reply Br., ECF No. 69, and a

closing argument was held on September 19, 2018.

STANDARDS FOR DECISION

The Takings Clause of the Fifth Amendment provides that “private property [shall not]

be taken for public use, without just compensation.” U.S. Const. amend. V. The inquiry into

whether a compensable taking has occurred requires this court to resolve “a question of law

based on factual underpinnings.” Wyatt v. United States, 271 F.3d 1090, 1096 (Fed. Cir. 2001)

(citations omitted); see also Ruckelshaus v. Monsanto Co., 467 U.S. 986, 1005 (1984) (stating

that courts perform “an ‘ad hoc, factual’ inquiry” in analyzing whether a compensable taking has

occurred (quoting Kaiser Aetna v. United States, 444 U.S. 164, 175 (1979))). In this case, Mrs.

Caquelin, as plaintiff, bears the burden of proving the relevant factual underpinnings of her claim

against the United States, and must generally proffer “‘evidence which is more convincing than

the evidence which is offered in opposition to it.’” Jazz Photo Corp. v. United States, 439 F.3d

1344, 1350 (Fed. Cir. 2006) (quoting Hale v. Department of Transp., 772 F.2d 882, 885 (Fed.

Cir. 1985)).

To establish a viable takings claim, Mrs. Caquelin must prove two things. First, she must

establish that she had “a property interest for purposes of the Fifth Amendment.” Members of

the Peanut Quota Holders Ass’n v. United States, 421 F.3d 1323, 1330 (Fed. Cir. 2005) (citing

Conti v. United States, 291 F.3d 1334, 1339 (Fed. Cir. 2002); Wyatt, 271 F.3d at 1096 (“[O]nly

persons with a valid property interest at the time of the taking are entitled to compensation.”)).16

Second, Mrs. Caquelin must establish that the government’s actions “amounted to a compensable

taking of that property interest.” American Pelagic Fishing Co., L.P. v. United States, 379 F.3d

1363, 1372 (Fed. Cir. 2004).

ANALYSIS

The procedural posture of this case is unusual. The court is charged with developing a

factual record, accompanied by legal analysis, to enable the Federal Circuit to make an informed

decision regarding which analytical test should apply to temporary takings resulting from the

issuance of a NITU. To complete this task, the court will first comply with the court of appeals’

mandate to “discuss[] what facts invoke which of the Supreme Court’s standards,” Caquelin II,

697 Fed. Appx. at 1020, and develop a conceptual framework for takings analysis. After this

framework is established, the court will apply the factual record of this case to the Arkansas

Game multi-factor analysis as commanded. See id.

16

That Mrs. Caquelin has the requisite property interest in the pertinent segment of the

rail corridor is not disputed. See Caquelin I, 121 Fed. Cl. at 663-67.

8

I. Takings Principles

Generally, the government can take property by two means: physically or by regulation.

Both types of takings can be further divided into two categories: categorical and non-categorical.

Categorical takings deprive the owners of all economically viable use of their property. Non-

categorical takings, on the other hand, deprive the owner of some amount of the economic use of

their land, either through physical invasion or onerous regulation. Takings can be either

permanent or temporary in duration.

A. Physical Takings

1. Categorical physical takings.

a. Permanent categorical physical takings.

The classic takings case – indeed, the salient exemplar of a taking under the Takings

Clause of the Fifth Amendment – involves a categorical physical taking that is permanent in

duration. This situation is also the most straightforward to analyze. In these cases, the

government physically and permanently seizes possession of the entirety of a landowner’s

property for public use. See, e.g., 28 U.S.C. § 1358 (relating to “proceedings to condemn real

estate for the use of the United States or its departments or agencies”). Physical possession of

land occurs when the “owner [is] deprived of valuable property rights, even [if] title ha[s] not

formally passed.” Caldwell v. United States, 391 F.3d at 1235 (citing United States v. Dow, 357

U.S. 17, 23 (1958)). In permanent categorical physical taking cases, the taking itself is often

uncontested – the litigation instead typically focuses on “what compensation [is] just.” Hendler

v. United States, 952 F.2d 1364, 1371 (Fed. Cir. 1991). It does “no[t] matter how weighty the

asserted ‘public interests’ involved” are – the government must pay compensation for a

“permanent physical occupation.” Lucas v. South Carolina Coastal Council, 505 U.S. 1003,

1015, 1028 (1992) (citing Loretto v. Teleprompter Manhattan CATV Corp., 458 U.S. 419

(1982)).

b. Temporary categorical physical takings.

By contrast, a temporary categorical physical taking occurs when the government

physically seizes the entirety of a landowner’s property for public use, but returns it to the

original owner after a period of time. “[C]ompensation is mandated when a leasehold is taken

and the government occupies the property for its own purposes, even though that use is

temporary.” Tahoe-Sierra Pres. Council, Inc. v. Tahoe Reg’l Planning Agency, 535 U.S. 302,

321-23 (2002) (citing United States v. General Motors Corp., 323 U.S. 373 (1945)). When a

physical taking is categorical, courts look to the temporal element to determine the measure of

just compensation under the Fifth Amendment, not whether a claim arose at all. See Ladd, 630

F.3d at 1025; Yuba Nat. Res., Inc. v. United States, 821 F.2d 638, 641-42 (1987).

For example, in Kimball Laundry Co. v. United States, 338 U.S. 1 (1949), the

government seized plaintiff’s laundry facility during World War II to provide laundry and dry

9

cleaning services to the armed forces. The Supreme Court found the taking to be categorical, as

the government possessed the entirety of plaintiff’s property. Id. at 3. But it was ultimately

temporary, as the government returned the property after the war ended. Id. at 3-4. Thus, the

principal disagreement in Kimball Laundry was over how compensation should be calculated,

not whether a taking occurred. See id. at 6 (stating that “the question of compensation for the

temporary taking of petitioner’s land, plant, and equipment” was at issue.).

Similarly, United States v. Pewee Coal Co. also involved a temporary categorical taking

during World War II. 341 U.S. 114 (1951). In Pewee Coal, the government seized control of

various coal mines across the country in 1943 to circumvent a nationwide strike of miners. Id. at

115. A mine was returned to the original owners after five and one-half months of government

occupation, and the operators of the mine sued for compensation. Id. The Court found the

seizure of the mine to be “‘in as complete a sense as if the [g]overnment held full title and

ownership.’” Id. at 116 (citing United States v. United Mine Workers, 330 U.S. 258 (1947)).

Much like Kimball Laundry, the majority of the opinion was devoted to detailing how much

compensation the mine owners were entitled to for the taking period, rather than if a taking had

occurred at all. Id. at 116-17.

In sum, when the government physically seizes the entirety of a plaintiff’s property, it is a

categorical taking. Whether the government exercises permanent or temporary control is only

relevant for the calculation of compensation, not whether a taking occurred. See, e.g., General

Motors, 323 U.S. at 378 (“Governmental action short of acquisition of title or occupancy has

been held, if its effects are so complete as to deprive the owner of all or most of his interest . . . ,

to amount to a [T]aking.”).

2. Non-categorical physical takings.

Non-categorical physical takings also require proper compensation under the Takings

Clause of the Fifth Amendment. See, e.g., Loretto, 458 U.S. at 419. A non-categorical physical

taking occurs when the government occupies part of an owner’s property in some manner. The

physical invasion could be as small as a single cable box, see id., or as large as multiple wells,

see Hendler, 952 F.2d 1364, 1375-78. And like categorical physical takings, non-categorical

physical takings can be permanent or temporary in duration.

a. Permanent non-categorical physical takings.

Permanent, non-categorical physical takings are treated analytically the same as

categorical physical takings, except for the calculation of damages. The Supreme Court has

consistently drawn a bright line that any permanent physical invasion of property, no matter how

negligible, constitutes a taking. See Loretto, 458 U.S. at 436 (“Th[is] traditional rule also avoids

otherwise difficult line-drawing problems” with how much physical taking would be too much);

United States v. Causby, 328 U.S. 256, 261-65 (1946) (holding that repeated flights by

government planes through the plaintiffs’ airspace constituted a permanent non-categorical

physical taking); Hendler 952 F.2d at 1375-78 (finding government-drilled wells on a plaintiff’s

property constituted a permanent non-categorical physical taking that required compensation).

10

When physically, and permanently, taking a part of property, “the government does not simply

take a single ‘strand’ from the ‘bundle’ of property rights: it chops through the bundle, taking a

slice of every strand. . . . it effectively destroys each of these rights.” Loretto, 458 U.S. at 435

(emphasis in original).

The seminal case of this type in the Supreme Court is Causby. The plaintiffs in Causby

were farmers who sued the government for “frequent and regular flights of army and navy

aircraft over [plaintiffs’] land at low altitudes” that injured chickens and forced them to close the

farm. 328 U.S. at 258. Despite the fact that the “enjoyment and use of the land [was] not

completely destroyed,” the Court found a physical taking because “the use of the airspace

immediately above the land [] limit[ed] the utility of the land and cause[d] a diminution in its

value.” Id. at 262. And, “the fact that [the government planes] do[] not occupy [the land] in a

physical sense – by the erection of buildings and the like – is not material. As we have said, the

flight of airplanes [in this case] . . . is as much an appropriation of the use of the land as a more

conventional entry upon it.” Id. at 265. The Court in Causby effectively recognized the

existence of a non-categorical physical taking, i.e., one that does not completely deprive the

owner of all economic value, but is of a permanent nature.

In Loretto, Court formally recognized the principle that any permanent physical invasion

of property constitutes a taking, no matter how “minimal [the] economic impact on the owner.”

458 U.S. at 434-35. The Court in Loretto found a non-categorical permanent physical taking

from the imposition of cable boxes on the plaintiffs’ property – despite the small impact on the

property’s value. See id. at 434, 441-42. “Once the fact of occupation is shown, of course, a

court should consider the extent of the occupation as one relevant factor in determining the

compensation due. For that reason, moreover, there is less need to consider the extent of the

occupation in determining whether there is a taking in the first instance.” Id. at 437 (emphasis in

original).

Public easements being imposed on a landowner can also constitute permanent non-

categorical physical takings. See Kaiser Aetna v. United States, 444 U.S. 164, 179-80 (1979)

(citing Causby, 328 U.S. at 265; Portsmouth Harbor Land & Hotel Co. v. United States, 260

U.S. 327 (1922)). In Kaiser Aetna, the Court held that “even if the [g]overnment physically

invades only an easement in property, it must nonetheless pay just compensation.” Id. at 180.

Similarly, in Nollan v. California Coastal Comm’n, 483 U.S. 825, 831 (1991), Justice Scalia

wrote, “[t]o say that the appropriation of a public easement across a landowner’s premises does

not constitute the taking of a property interest but rather . . . ‘a mere restriction on its use,’ . . . is

to use words in a manner that deprives them of all their ordinary meaning.” Id. The right to

exclude others is “one of the most essential sticks in the bundle of rights that are commonly

characterized as property.” Id. (quoting Loretto, 458 U.S. at 433).

The Federal Circuit followed a similar path in recognizing permanent non-categorical

physical takings. See, e.g., Hendler, 952 F.2d at 1375-78. In Hendler, the Federal Circuit found

ground wells drilled by the government on the plaintiffs’ property to monitor pollution

constituted a permanent non-categorical physical taking. See 952 F.2d at 1375-77. The wells

were permanent because “[y]ears have passed since the [g]overnment installed the first wells . . .

11

[which are] 100 feet deep, lined with plastic and stainless steel, and surrounded by gravel and

cement.” Id. at 1376. The government’s order also authorized state and federal officials to have

continuing access to the property. Id. at 1374. Recognizing that on a long enough timeline,

every government action could be considered “temporary,”17 the court noted “[a]ll takings are

‘temporary,’ in the sense that the government can always change its mind at a later time.” Id. at

1376. The court drew a distinction between “governmental activities which involve an

occupancy that is transient and relatively inconsequential,” such as the “parked truck of the

lunchtime visitor,” and the more “permanent” nature of the embedded wells. Id. at 1376-77.

The court noted that “the concept of permanent physical occupation does not require that in

every instance the occupation be exclusive, or continuous and uninterrupted.” Id. at 1377.

Rather, indefiniteness means permanency. Id. at 1376.

The Federal Circuit provided additional guidance on distinguishing between temporary

and permanent non-categorical physical takings in Otay Mesa Prop., L.P. v. United States, 670

F.3d 1358, 1363 (Fed. Cir. 2012). The court concluded that takings are considered permanent

even if the landowner could take “specified action” to terminate the taking. 670 F.3d at 1368-69

(“In Loretto, was possible for the landowner to act in a manner so as to avoid the taking . . .

[because] a landlord could avoid the law’s requirements by ceasing to rent the building to

tenants, but [] this did not make the cable company’s invasion of the property not permanent.”)

(citing Loretto, 458 U.S. at 421, 438-39). In Otay Mesa, the government installed roads, a tented

structure, and underground sensors outside a previously-granted twenty-foot-wide easement on

property in California adjacent to the border with Mexico. 670 F.3d at 1360-61. The Federal

Circuit concluded that the taking by the government was permanent, even though the plaintiff in

Otay Mesa could have “decide[d] to develop the entirety of its property, thereby terminating the

sensor easement.” Id. at 1368. Arbitrary end dates are similarly unpersuasive in finding whether

an easement was temporary or permanent in nature. Id. at 1368. “[O]nly such activities [like]

abandonment of the easement by the Border Patrol . . . can end the easement.” Id.

b. Temporary non-categorical physical takings.

Ordinarily, temporary governmental action will give rise to a taking if permanent action

of the same character would constitute a taking. See Arkansas Game, 568 U.S. at 26-27, 32-34;

First English Evangelical Lutheran Church of Glendale v. County of Los Angeles, 482 U.S. 304,

318-20 (1987). That is true for non-categorical as well as categorical physical takings, but

temporary non-categorical physical takings have to be differentiated from torts. See Ridge Line,

Inc. v. United States, 346 F.3d 1346, 1355 (Fed. Cir. 2003). That line-drawing exercise can be

significant with government-induced flooding, see, e.g., Arkansas Game, 568 U.S. at 36,

although “[t]here is thus no solid grounding in precedent for setting flooding apart from all other

government intrusions on property,” id.

In this context, the Supreme Court employed six interrelated factors in Arkansas Game to

help determine if a temporary non-categorical physical taking occurred. 568 U.S. at 38-39.

17

This echoes the famous economist John Maynard Keynes, who famously stated “[i]n

the long run we are all dead.”

12

Those factors were “time,” “inten[t],” “forseeab[ility],” “character of the land,” “reasonable

investment-backed expectations,” and “severity of the interference.” Id. Arkansas Game

involved the flooding and destruction of forest land caused by the Army Corps of Engineers

through its operations of a dam during the period 1993 through 2000. Id. at 28. Those

operations deviated from planned water-release rates to benefit farmers and recreational users.

Id. at 27. Water was stored behind the Corps’ dam from September to December, but was

released above historical norms during the ensuing tree-growing season, id. at 28, saturating soil

and weakening root systems of trees to the point the trees were destroyed, id. at 30. The Corps

eventually ceased the deviations and returned to more normal water flows. Id. at 28. The Court

found that the flooding could constitute a taking. Id. at 38-40.

Some of the factors employed in Arkansas Game have origins in accepted takings

jurisprudence. For example, “inten[t]” seems to correlate with authorized government action,

although that may not always be factually the case. Additionally, “character of the land” and

“reasonable investment-backed expectations” have roots in regulatory takings jurisprudence,

although “character of the land,” Arkansas Game, 568 U.S. at 39 (emphasis added), is a reversal

from the focus in regulatory takings on “character of the government action,” Penn Central, 438

U.S. at 124 (emphasis added). Contrastingly, factors relating to tort concepts, i.e.,

“forseeab[ility]” and “severity of the interference” were employed in Arkansas Game.18 Finally,

“time” concerns the duration of the temporary interference.

On the other hand, if landowners suffered “an incidental or consequential injury . . .

caused, for example, by improvident conduct on the part of the government in managing its

property,” such landowners may have to look to tort law. See Ridge Line, 346 F.3d at 1356. In

applying the distinction between a foreseeable injury and a merely incidental injury, the Federal

Circuit requires plaintiffs to demonstrate that their injury was “the likely result of the

[government’s] act, not that the act was the likely cause of the injury.” Cary, 552 F.3d at 1377

(citing Moden, 404 F.3d at 1343) (emphasis added).19

18

In this respect, it is not necessary to show that the government specifically intended to

invade and injure the property. Rather, the standard allows recovery based on injuries that are

the direct, natural, predictable, or probable result of governmental action (i.e., foreseeable). See

Cary v. United States, 552 F.3d 1373, 1377 (Fed. Cir. 2009); see also Ridge Line, 346 F.3d at

1356. That is, a court can infer governmental action for an invasion of a property interest where

the plaintiff proves that “the government should have predicted or foreseen the resulting injury.”

Cary, 552 F.3d at 1377 (quoting Moden v. United States, 404 F.3d 1335, 1343 (Fed. Cir. 2005)).

19

Foreseeability can be critical in governmental flooding cases. See, e.g., Arkansas

Game, 568 U.S. at 23; Cary, 552 F.3d at 1373; Moden, 404 F.3d at 1335; Ridge Line, 346 F.3d at

1346; Cotton Land Co. v. United States, 109 Ct. Cl. 816 (1948). In governmental flooding cases,

liability can turn on whether the taking was predictable or whether an intervening cause broke

the chain of causation. See Arkansas Game & Fish Comm’n v. United States, 87 Fed. Cl. 594,

621-24 (2009), rev’d, 637 F.3d 1366 (Fed. Cir. 2011), rev’d & remanded, 568 U.S. 23, aff’d on

remand, 736 F.3d 1364 (Fed. Cir. 2013). Predictability focuses on the end-result, i.e., whether

the flooding should have been foreseen based on information available to the government at the

13

B. Regulatory Takings

Justice Holmes articulated the basic standard for regulatory takings in Pennsylvania Coal

Co. v. Mahon, 260 U.S. 393, 414-15 (1922): “while property may be regulated to a certain

extent, if regulation goes too far it will be recognized as a taking.” By this general formulation,

Justice Holmes endeavored to balance the legitimate, regulatory needs of the state with the

reasonable expectations of property owners. Id. at 413-15 (“Government hardly could go on if to

some extent values incident to property could not be diminished without paying for each such

change in the general law.”). Following Pennsylvania Coal, courts have struggled to define a

“set formula” for determining how much regulation is too much. See Lucas, 505 U.S. at 1015.

In doing so, courts have engaged in “essentially ad hoc, factual inquires.” Id. (citing Penn

Central, 438 U.S. at 124). Over the years, the Court has recognized two types of regulatory

takings – categorical and non-categorical. See id. at 1014-1020.

1. Categorical regulatory takings.

A categorical regulatory taking occurs when a “regulation denies all economically

beneficial or productive use of land . . . for the common good.” Lucas, 505 U.S. at 1015-16, 19

(citing Agins v. City of Tiburon, 447 U.S. 255, 260 (1980), abrogated by Lingle v. Chevron

U.S.A. Inc., 544 U.S. 528 (2005); Nollan, 483 U.S. at 834; Keystone Bituminous Coal Ass’n v.

DeBenedictis, 480 U.S. 470, 495 (1987); Hodel v. Virginia Surface Mining & Reclamation

Ass’n., 452 U.S. 264, 295-96 (1981)) (emphasis added). As the Court observed in Lucas, the

“total deprivation of beneficial use is, from the landowner’s point of view, the equivalent of a

physical appropriation.” Id. at 1017 (citations omitted). And like a categorical physical taking,

courts do not need to run through the “case-specific inquiry into the public interest advanced in

support of the restraint” to determine if the taking is compensable. Id. at 1015.

In Lucas, the regulation at issue prevented the development of certain coastal lots in

South Carolina. 505 U.S. at 1006-07. Plaintiff, owner of two coastal lots on a barrier island, was

prevented from building on or developing the two pieces of land. Id. After the South Carolina

trial court found that the land was effectively rendered economically valueless, the Supreme

Court held that the regulation would constitute a categorical regulatory taking. Id. at 1030-32.

Cases subsequent to Lucas have considered that a categorical regulatory taking is

“limited to the ‘extraordinary circumstance when no productive or economically beneficial use

of land is permitted.’” Tahoe-Sierra, 535 U.S. at 330 (quoting Lucas, 535 U.S. at 1017)

(emphasis in original); see also Lost Tree Village Corp. v. United States, 787 F.3d 1111, 1116

(Fed. Cir. 2015) (“[A] Lucas [categorical regulatory] taking is rare.”). Indeed, even a 93%

time of action. Id. at 621-23. Relatedly, intervening causes might “break the ‘chain of

causation’ between the governmental action and plaintiff’s injury.” Id. at 615, 623-24 (citing

Cary, 552 F.3d at 1380.

14

reduction in land value is not enough to meet the Lucas standard for a categorical regulatory

taking. Palazzolo v. Rhode Island, 533 U.S. 606, 616 (2001).

In Lost Tree, the Federal Circuit addressed noneconomic attributes. See Lost Tree, 787

F.3d at 1111. In that case, the Army Corps of Engineers denied a wetland fill permit to the

plaintiffs to build on waterfront property. Id. at 1114. The land’s value decreased by 99.4% due

to the government action. Id. The government argued that since there was some (even if token)

property value remaining (regardless of its source), the taking was not categorical and should

instead be analyzed through the Penn Central lens. Id. at 1116. The Federal Circuit disagreed,

holding that a purely nominal noneconomic residual value would not forestall a categorical

regulatory taking. Id. at 1117.

2. Non-categorical regulatory takings.

If a regulation does not “den[y] all economically beneficial or productive use of land,”

courts turn to a “complex of factors,” Palazzolo, 533 U.S. at 617, which together guide what is

“essentially [an] ad hoc, factual inquir[y],” Penn Central, 438 U.S. at 124. Penn Central listed

three factors to be considered in determining if a non-categorical taking occurred: (1) “[t]he

economic impact of the regulation on the claimant”; (2) “the extent to which the regulation has

interfered with distinct investment backed expectations;” and (3) “the character of the

government action.” Id. “Each of these factors are considered in terms of the ‘parcel as a

whole.’” Seiber v. United States, 364 F.3d 1356, 1370 (Fed. Cir. 2004) (quoting Penn Central,

438 U.S. at 130-31). Although these factors provide “important guideposts . . . [, t]he Takings

Clause requires careful examination and weighing of all the relevant circumstances.” Palazzolo,

533 U.S. at 634, 636 (O’Connor, J., concurring); see also Tahoe–Sierra, 535 U.S. at 321

(Whether a taking has occurred “depends upon the particular circumstances of the case.”); Yee v.

City of Escondido, 503 U.S. 519, 523 (1992) (Regulatory takings claims “entail[ ] complex

factual assessments.”).

A non-categorical taking does not require a complete economic loss; rather, a partial but

substantial temporary taking may be compensable. Palazzolo, 533 U.S. at 617; Cienega

Gardens v. United States, 331 F.3d 1319, 1343, 1345 (Fed. Cir. 2003).

C. The July 3, 2013 NITU Issued Regarding Mrs. Caquelin’s Land

Mrs. Caquelin’s reversionary property interest was blocked by the STB’s imposition of

the NITU pending consideration of authorizing a trail for public use. See Stip. ¶¶ 12-14. “In the

bundle of rights we call property, one of the most valued is the right to sole and exclusive

possession – the right to exclude strangers, or for that matter friends, but especially the

government.” Hendler, 952 F.2d at 1374-75 (Fed. Cir. 1991) (citing Nollan, 483 U.S. at 831;

Loretto, 458 U.S. at 426) (internal citations omitted) (emphasis in original). Here, Mrs. Caquelin

was prevented from using her land for any purpose for the duration of the NITU. See Stip. Ex.

11 at STB000077-81. It makes no difference that the NITU did not ultimately result in trail use

of the railroad corridor. The court therefore determines that the NITU issued regarding Mrs.

Caquelin’s property represents a categorical physical taking, albeit a temporary one. In these

15

circumstances, the principles identified and applied in Pewee Coal, Kimball Laundry, and

General Motors would govern the takings analysis, and the Arkansas Game factors would be

inapplicable.

Nonetheless, as instructed by the Federal Circuit’s mandate, the court will proceed to

apply the factors identified in Arkansas Game to the factual record established by the trial held

on remand.

II. Multi-Factor Analysis

The court here is charged with an atypical task. The Federal Circuit specifically

instructed this court to determine “how the government-advanced multi-factor analysis applies in

this case, on the assumption that such an analysis is the governing standard.” Caquelin II, 697

Fed. Appx. at 1020. Thus, the court is to act in a supporting role – teeing up the problem for the

Federal Circuit to determine if en banc review is necessary to examine the Ladd precedent and

the earlier decisions by the Federal Circuit that provided antecedents for Ladd. As mandated, the

court will address the six factors from Arkansas Game in turn.

Factor 1: Time and Duration of the Taking

In Arkansas Game, the Supreme Court advised that “time is indeed a factor in

determining the existence vel non of a compensable taking.” Arkansas Game, 568 U.S. at 38-39

(citing Loretto, 458 U.S. at 435, n.12; Tahoe-Sierra, 535 U.S. at 342; National Bd. of YMCA v.

United States, 395 U.S. 85, 93 (1969) (finding the brief occupation of a building by the United

States military during a riot in Panama did not constitute a taking because the building was

already under attack)). Other temporary takings cases provide additional instruction as to how

time factors into the overall calculus. See First English, 482 U.S. at 318 (“‘[T]emporary’ takings

which, as here, deny a landowner all use of his property, are not different in kind from permanent

takings, for which the Constitution clearly requires compensation.”); Tahoe-Sierra, 535 U.S. at

322 (“[C]ompensation is mandated when a leasehold is taken and the government occupies the

property for its own purposes, even though that use is temporary.”); Yuba, 821 F.2d at 641-42

(“[T]emporary reversible takings should be analyzed in the same constitutional framework

applied to permanent irreversible takings.”).

For this case, the duration and time of the taking is undisputed and uncontroversial. The

taking began on the date the STB issued the NITU and blocked Mrs. Caquelin’s reversionary

interest in the property, i.e., on July 3, 2013, and ended when the NITU expired, i.e., on

December 30, 2013, for a total period of 180 days. See Stip. Ex. 11 at STB000077, 80-81. The

duration factors into the calculation of just compensation for Mrs. Caquelin, rather than into the

existence vel non of a taking. See First English, 482 U.S. at 318-19; Yuba, 821 F.2d at 641-42.

When the STB first issued the NITU and blocked Mrs. Caquelin’s reversionary interest in the

land at issue, it was indeterminate how long the taking would last. Stip. Ex. 11 at STB000080.

As a factual matter, near the end of the six-month period of the NITU, the Iowa Heritage Council

sought a 180-day extension to continue negotiations for a trial, Stip. Ex. 11 at STB000082, but

no extension was granted, see supra, at 6.

16

The government, in its post-trial brief, emphasizes that the NITU “was in place for only

180 days,” and that “there was no extraordinary delay in the regulatory abandonment

proceeding.” Def.’s Br. at 46-47; see also id. at 41-50. But as discussed previously, the NITU

deprived Mrs. Caquelin of all use of the land at issue during the time it was in effect. See Stip.

Ex. 11 at STB000077; see also Caldwell, 391 F.3d at 1235 (The “triggering event for any takings

claim under the Trails Act occurs when the NITU is issued.”). It does not matter for the takings

analysis that the NITU was “only” in place for 180 days or that it was resolved without an

“extraordinary delay.” The time is relevant only to the calculation of damages. See Yuba, 821

F.2d at 641-42. What matters is on July 3, 2013, the government acted in a way that completely

deprived Mrs. Caquelin the use of her property for what was then an unspecified amount of time.

See Stip. Ex 11 at STB000077-81.

The court concludes that the time factor weighs in favor of finding a taking of Mrs.

Caquelin’s property. See Banks v. United States, 138 Fed. Cl. 141, 150 (2018) (citing Kimball

Laundry, 338 U.S. 1) (additional citations omitted); see also Balagna v. United States, 138 Fed.

Cl. 398, 403 (2018) (“[A]pplication of the Arkansas Game factors would not be likely to yield a

result different from that reached under controlling precedent.”) (internal citation omitted). Mrs.

Caquelin was not deprived of her land by the mere “parked truck of the lunchtime visitor.”

Hendler, 952 F.2d at 1376. Rather, the NITU denied Ms. Caquelin useable time to reclaim the

plot of land for the next planting season and also delayed her ability to harvest the valuable

timber on the segment.

Factor 2: Degree to Which the Invasion was Intended

The next factor the Supreme Court lists as “relevant to the takings inquiry,” is the “degree

to which the invasion is intended.” Arkansas Game, 568 U.S. at 39. This factor cannot be

disputed. The STB issued the NITU with intent to block Ms. Caquelin from any use of the

corridor segment while a potential trail use was being negotiated. See Caldwell, 391 F.3d at

1233-34 (“[G]overnment action . . . operates to . . . preclude the vesting of [the] reversionary

interest.”); Banks, 138 Fed. Cl. at 150 (“There was no inadvertence here.”). The rails-to-trails

program was specifically amended to prevent the railroad from abandoning the property and to

block the owner’s reversionary interest. See Preseault I, 494 U.S. at 8 (“By deeming interim

trail use to be like discontinuance rather than abandonment, . . . Congress prevented property

interests from reverting under state law.”) (citing S. Rep. No 98-1, p.9 (1983)). The very

purpose of the Act is to effectuate a taking to preserve the option for interim trail use and

railbanking. Id.

Factor 3: The Foreseeable Result of Authorized Government Action

In related vein, Arkansas Game referred to consideration of whether the revision was “the

foreseeable result of authorized government action.” Arkansas Game, 568 U.S. at 39 (citing

John Horstmann Co. v. United States, 257 U.S. 138, 146 (1921) (no takings liability when the

government action, an increase of water in a lake due to an irrigation project in Nevada, was not

foreseeable); Ridge Line, 346 F.3d at 1355-56 (requiring plaintiffs in a flooding case to establish

17

that “the effects [plaintiff] experienced were the predictable result of the government’s action”);

In re Chicago, Milwaukee, St. Paul & Pac. R. Co., 799 F.2d 317, 325-26 (7th Cir. 1986)

(discussing how “[a]ccidental unintended injuries inflicted by governmental actors are treated as

torts, not takings.”)).

In Moden, 404 F.3d at 1343, the Federal Circuit held that “[a]n inverse condemnation

plaintiff must prove that the government should have predicted or foreseen the resulting injury,”

and also that there were no intervening causes that might relieve the government of liability. See

also Cary, 552 F.3d at 1379 (“Wherever there is an authorized action, the causation prong is

satisfied for any injury which is the direct, natural, and probable result of that action.”). At

bottom, this factor “merely inquires into whether the ‘invasion’ is the foreseeable result of

government action.” Banks, 138 Fed. Cl. at 150 (citing Arkansas Game, 568 U.S. at 39).

Here, the result of the NITU was foreseeable, as the very point of a NITU is to prevent a

landowner’s reversionary interest from taking effect so the trail negotiating process can take

place. See Preseault I, 494 U.S. at 7-9. No preternatural clairvoyance is needed in this case to

predict that the outcome of the government action is the deprivation of Mrs. Caquelin’s property

interest. See id.; see also Stip. Ex. 9 at STB000077-81. It does not matter that there was no

“physical presence of federal or third party actors.” Banks, 138 Fed. Cl. at 150. In the words of

Judge Bruggink, the fact that a NITU results in an owner’s losing the rights to use their own land

“requires no great foresight to anticipate.” Id. And, no intervening cause that might relieve the

government of liability is present here.20

Therefore, the court finds that the deprivation of property was a predictable and

foreseeable consequence of issuing the NITU. None of the predictability or foreseeability issues

present in inverse-condemnation flooding cases is present here.

Factor 4: Character of the Land at Issue

The fourth factor spelled out by the Supreme Court in Arkansas Game is the “character of

the land at issue.” 568 U.S. at 39 (citing Palazzolo, 533 U.S. at 618). In Arkansas Game, the

Court noted that the trial court “found the [a]rea had not been exposed to flooding comparable to

the 1990’s accumulations in any other time span either prior to or after the construction of the

[d]am.” Id. In the eyes of the Court, the lack of prior comparable flooding made it more likely

that a taking occurred – as the owners of the property had no forewarning of the potential for

floodwaters to inundate their land. See id.

While this factor is ostensibly similar to one from Penn Central, a key difference exists

between the test for non-categorical regulatory takings in Penn Central and the inquiry detailed

by the Supreme Court in Arkansas Game. In Penn Central, the focus is on the character of the

20

The government’s post-trial brief does not address this factor except for a cursory

acknowledgement. See Def.’s Br. at 34. Instead, the government attempts to shoehorn the non-

categorical regulatory taking test from Penn Central into the current analysis. See id. at 34-67.

18

governmental action. See Penn Central, 438 U.S. at 123. But in Arkansas Game, the Supreme

Court reverses the inquiry and directs courts to look to the “character of the land at issue.” See

Arkansas Game, 568 U.S. at 39 (emphasis added). When viewed in the government flooding

context, and in conjunction with the other Arkansas Game factors, this change in the focus of the

inquiry is cogent and instructive. The Penn Central factors are designed to determine if a non-

categorical regulatory taking occurred, Penn Central, 438 U.S. at 124, or, in the words of Mr.

Justice Holmes, whether a governmental regulation “goes too far,” Pennsylvania Coal, 260 U.S.

at 415. Arkansas Game, by contrast, points courts to determine whether a taking (as opposed to

a tort) occurred by looking at the nature of the underlying land, i.e., was it prone to repeated

flooding or especially susceptible to flooding. 568 U.S. at 39. This factor, much like factors 2

and 3, seems specifically identified to be deployed in a governmental flooding context.

The character of the land at issue in this case is largely undisputed. The plot of land here

is a 0.359 acre segment located adjacent to farmland in Franklin County, Iowa, measuring 313

linear feet in length from the location of the Milepost 191 marker extending to the southeastern

corner of the Caquelin property, and fifty feet in width extending from the westerly line of the

railroad corridor to the center line. Stip. ¶¶ 19-20 & Ex. 15 at US000288-89; see also Caquelin

I, 121 Fed. Cl. at 660-61. At the time of the taking, the bucolic segment of land was covered

with trees and residual ballast. Because of the ballast, the remainder of the plot was “a couple of

feet lower than the rail[bed].” See Tr. 71:18 to 72:7, 91:7 to 93:25 (testimony of Mr. Abbas).21

After a rain, the area could be briefly “wet” because of the slightly elevated railbed, but it is not

“wetland,” and reclamation of the corridor plus tiling could put the land into productive use. Tr.

71:18 to 72:7, 91:7 to 93:25 (Abbas). Dr. Kliebenstein, an expert who testified on behalf of Mrs.

Caquelin, emphasized that the CSR of the soil involved is 95, indicating the soil is extremely

productive for the growing of corn and other crops. Id. at 208:5-14, 218:24 to 222:1, 225:1-11,

277:7 to 278:4. The court therefore determines this factor also weighs in favor of finding a

taking.22

21

Mr. Abbas farms Mrs. Caquelin’s land under a leasehold. TR. 63:2-25.

22

“Whether the plaintiffs’ property was commercial, farm, or undeveloped land, the

United States has no right to simply block control of the surface . . . .” Banks, 138 Fed. Cl. at

150. In a case of this type, character of the land is only relevant for determining compensation,

rather than liability. See id. It is antagonistic to long-standing takings principles that a plaintiff

would be required to demonstrate the various productive characteristics of his or her land in

order to prove liability when faced with a categorical physical or regulatory taking. See, e.g.,

Loretto, 458 U.S. 434-35; Tahoe-Sierra, 535 U.S. at 323-24; Horne v. Department of

Agriculture, ___ U.S. ___, ___, 135 S. Ct. 2419, 2428-2430 (2015) (“[O]nce there is a taking, as

in the case of a physical appropriation, any payment from the Government in connection with

that action goes, at most, to the question of just compensation.”) (citing Suitum v. Tahoe Reg’l

Planning Agency, 520 U.S. 725, 747-48 (1997)). Indeed, the government would still be liable

for taking entirely unproductive land with little value – even if the compensation ultimately paid

was nominal. Correspondingly, the fact that the corridor segment is relatively small does not

affect liability, although it bears directly on compensation. See Loretto, 458 U.S. at 434-36.

19

Factor 5: Reasonable Investment-Backed Expectations

The fifth factor identified by the Supreme Court is “the owner’s ‘reasonable investment-

backed expectations’ regarding the land’s use.” Arkansas Game, 568 U.S. at 39 (citing

Palazzolo, 533 U.S. at 618 (detailing the difference between a categorical regulatory taking

where “a regulation has deprived a landowner of ‘all economically beneficial use’ of the

property” and a non-categorical regulatory taking, when a regulation “defeated the reasonable

investment-backed expectations of the landowners to the extent that a taking has occurred.”)).

This factor has its roots in Penn Central, where the Court stated it was necessary to determine

the “extent to which the [governmental action] has interfered with distinct investment-backed

expectations” when examining a non-categorical regulatory taking. 438 U.S. at 124 (citation

omitted). And unlike the fourth factor of Arkansas Game, there is no reversal of the inquiry.

Other cases provide additional guidance regarding how the court should interpret

“reasonable investment-backed expectations.” See Ruckelhaus, 467 U.S. at 1006-07 (finding

that reasonable investment-backed expectations “must be more than a ‘unilateral expectation or

abstract need’”) (quoting Webb’s Fabulous Pharmacies, Inc. v. Beckwith, 499 U.S. 155, 161

(1980)); see also Love Terminal Partners, L.P. v. United States, 889 F.3d 1331, 1345 (Fed. Cir.

2018) (“The reasonable, investment-backed expectation analysis is designed to account for

property owners’ expectation that the regulatory regime in existence at the time of their

acquisition will remain in place, and that new, more restrictive legislation or regulations will not

be adopted.”); Cienega Gardens, 331 F.3d at1345-46 (“This factor also incorporates an objective

test – to support a claim for a regulatory taking, an investment-backed expectation must be

‘reasonable.’”); but see Palm Beach Isles Assoc. v. United States, 231 F.3d 1354, 1364 (Fed. Cir.

2000) (“[I]n accord with Lucas, and not inconsistent with any prior holdings of this court, when a

regulatory taking, properly determined to be ‘categorical,’ is found to have occurred, the

property owner is entitled to a recovery without regard to consideration of investment-backed

expectations. In such a case, ‘reasonable investment-backed expectations’ are not a proper part

of the analysis, just as they are not in physical takings cases.”) (emphasis added).

Dr. Kliebenstein testified that the land at issue could be reclaimed as high quality

farmland and put into very productive use. See Tr. 208:5-14; 218:24 to 222:1; 225:1-11; 277:7:7

to 278:4. According to Dr. Kliebenstein, the cost to reclaim the land would be approximately

$1,120, Tr. 249:1 to 250:6, with a potential “$3 and $3.50 return for every dollar of investment,”

Tr. 251:2 to 252:14.

In early July 2013, with the issuance of the NITU, Mrs. Caquelin was denied the

opportunity to prepare the land for productive use during the next planting season. See Tr. 802:8

to 807:13; Pl.’s Br. at 58-59. Mr. Abbas, who farms the land on a cash-rent basis, Tr. 72:15 to

73:9,23 has been active in enhancing the productivity of the land by tiling and otherwise

23

In 2012 and 2013, Mr. Abbas paid $18,000 to farm Mrs. Caquelin’s property. Stip. Ex.

14 at PLT00020. In 2014 and 2015, the rent was raised to $25,000. Id. at PLT000019. But rent

20

improving it, Tr. 73:21 to 76:9. He had discussed potential tiling of the corridor segment at issue

with the principal of a firm that had performed other reclamation work in the area. Tr. 80:14 to

81:8, 91:20 to 92:7. Plaintiff’s experts, Mr. Matthews and Dr. Kliebenstein, had also discussed

the cost of reclamation with this local contractor. See PX 1 (Matthews Expert Report) at 11; PX

2 (Kliebenstein Expert Report) at 13; Tr. 249:1 to 250:6, 322:2-23. Therefore, Mrs. Caquelin

contends that additional rental income should be considered in her reasonable investment-backed

expectations, if such a test were to apply. See Pl.’s Br. at 58-59.

The government, on the other hand, claims that due to the timing of the NITU and the

unreclaimed nature of the property, Mrs. Caquelin could not have any reasonable investment-

backed expectations. See Def.’s Br. at 29, 50-55; see also Tr. 811:1 to 813:14. Its argument

emphasizes the fact that the timing of the NITU precluded Mrs. Caquelin from gaining any farm

rental income from the unreclaimed plot in 2013, the year the NITU was issued. See Def.’s Br.

at 62-65. The government acknowledges that Mrs. Caquelin could have started the reclamation

process after the NITU expired in December 2013. See Tr. 801:15 to 802:3.24

The government further argues that Mrs. Caquelin did not have any reasonable

investment backed expectations, as she “acquired her interest in the adjacent farmland by

inheritance” with the railroad’s easement still present on the property, and she could not have

known when or if that easement would be abandoned. See Def.’s Br. at 50-55; see also Tr.

786:19 to 788:23. In addition, the government contends that Mrs. Caquelin “had no actual or

objectively reasonable expectations about the use of the 0.359-acre segment of the railroad

corridor at the time she acquired her interest in the adjacent property” or “at the time of the

government’s action.” Def.’s Br. at 51.

The presence of walnut trees on the segment complicates the equation of reasonable

investment-backed expectations. David Matthews, an expert appraiser, testified at trial that one

of the walnut trees by itself was worth “several thousand dollars” in his estimation. Tr. 365:6-

23, 368:3 to 370:8, 370:18 to 373:1. The court also observed the walnut trees on its site visit to

the property. Tr. 461:22-25 to 462:6, 462:24 to 463:6.25

was reduced back to $20,700 for 2016 and 2017. Id. at PLT000018. For 2018, the rent was

further reduced to $19,200. Id. at PLT00017.

24

Another lengthy argument made by the government is that the July 3, 2013 issuance

date of the NITU precluded the planting of soybeans on the corridor segment in 2013. See Def.’s

Br. at 61-65; see also Tr. at 547:19 to 548:5, 550:10 to 551:15, 555:8 to 557:13, 795:1 to 802:23.

This argument misses the point – it is irrelevant if Mrs. Caquelin would have been able to

reclaim the plot of land for productive use in 2013. What is relevant is that Mrs. Caquelin would

have been able to start the reclamation process for the next planting season. See Tr. 796:8-19.

As the court pointed out in closing argument, any “prudent landowner” would have used the time

from July 3rd onward to clear the property to “prepare it for planting the next season.” Id.

25

The segment at issue is wooded and fairly flat. Tr. 222:2 to 224:22. The larger trees

are growing at and near the fenceline that separated the railroad corridor from Mrs. Caqulin’s

21

To the court, these trees signify an additional component of Mrs. Caquelin’s investment-

backed expectations independent of rental income from farming purposes. This undercuts the

government’s argument that STB’s “interference . . . had no measurable economic impact.” E.g.,

Def.’s Br. at 54. The government’s argument seems to be myopically focused on the economic

viability of growing crops on the taken property during 2013, after the July 3, 2013 NITU

issuance date. See id. at 62-67. Mr. Thien, an appraiser testifying as an expert on behalf of the

government, was asked to provide a value for the entirety of the parcels owned by Ms. Caquelin

and also to evaluate whether those was any loss of revenue or rent during the period of July 3

through December 30, 2013. Tr. 497:24 to 498:9. Despite the exhaustive exposition of Mr.

Thien’s methodology and his ultimate conclusion regarding the viability of farming the plot,

neither the government in its brief, nor Mr. Thien in his testimony, addressed the impact of the

walnut trees on the cost to reclaim Mrs. Caquelin’s property or on the value of the segment at

issue. See generally Def.’s Br. at 59-68; see also Tr. 641:12 to 644:24, 645:21 to 647:7, 647:18

to 649:2, 656:17 to 658:4. Correlatively, Mr. Thein did not consider the extent to which

reclamation would provide a positive recovery to Mrs. Caquelin through the enhanced value of

the segment.

Therefore, the court finds factor 5 cuts in favor of a taking. When the NITU was

imposed on Mrs. Caquelin’s property on July 3, 2013, it denied her the opportunity to perform

the economically viable action of reclaiming the land and putting it to productive agricultural

use. Moreover, the presence of the harvestable walnut trees on the property would have covered

the cost of reclamation, and this circumstance also bears on objectively reasonable investment-

backed expectations.

Factor 6: Severity of the Interference

For the last factor, the Supreme Court in Arkansas Game details that the “[s]everity of the

interference figures in the calculus as well.” 568 U.S. at 39 (citing Portsmouth Harbor, 260 U.S.

at 329-30 (“[W]hile a single act may not be enough, a continuance of them in sufficient number

and for a sufficient time may prove [a taking]. Every successive trespass adds to the force of the

evidence.”)). In Portsmouth Harbor, the Court held the repeated firing of military guns over the

plaintiff’s beach resort could constitute a taking if the firings were numerous enough. 260 U.S.

at 329-30. This fact pattern has a similarity to Causby, where repeated overflights of

governmental aircraft over a farm constituted a taking. 328 U.S. at 258, 265.

farmland to the west. Tr. 224:15-20. The larger trees included at least one walnut that could be

harvested as part of the reclamation work, and sold to a veneer company. Tr. 368:4-22, 461:22

to 462:23. The price obtainable for the large walnut, apart from the other walnuts and

hardwoods, Tr. 368:4 (conservatively, $2,000), would exceed the estimated reclamation cost. Tr.

82:5-25, 114:10 to 115:7, 249:3 to 250:6 (approximately $1,120); PX 1 at 11. Walnut trees are

prized for their high quality wood and “bring premium prices, and have since the 1700s, with

single trees bringing up to $20,000.” Craig Wallin, Growing Walnut Trees for Profit, Profitable

Plants Digest, https://www.profitableplantsdigest.com/growing-walnut-trees-for-profit/ (last

accessed Nov. 5, 2018).

22

In a rail-to-trails case, however, this factor is less relevant. See Banks, 138 Fed. Cl. at

150. In rails-to-trails cases, the NITU acts as a complete interference to the plaintiff’s use and

enjoyment of their land. The segment here would have reverted to Mrs. Caquelin but for the

issuance of the NITU. She was unable to harvest the valuable walnut trees, prepare the land for

the next planting season, or exercise any other of her rights in the “bundle of sticks” that are

inherent to landownership. “None of the rails to trails case precedent[s] with respect to liability

has required an additional showing by landowners of what they would have done with the land if

they could access it.” Id.

For this factor, the court therefore finds the interference to be complete, i.e., as severe as

possible. The court also notes that this factor is redundant in a categorical takings analysis. If

the taking is categorical, see supra Part I, the taking of the property is complete and the duration

of the taking is only relevant regarding compensation. Consequently, any categorical taking

would also necessarily result in a 100% interference in the use of land, the severest possible

level.

III. SYNOPSIS

After addressing the Arkansas Game factors in the context of the facts of this case, the

court concludes that a taking occurred when the STB issued a NITU that blocked Mrs.

Caquelin’s reversionary interest in the land. The STB’s action delayed Mrs. Caquelin’s

reversion by 180 days. For that, the government owes just compensation, even if the amount is

underwhelming in the circumstances. See Loretto, 458 U.S. at 434-35; see also First Stip. (“The

parties have stipulated, based on the Court’s liability decision, that the principal and interest of

just compensation due to Plaintiffs Norma E. and Kenneth Caquelin is $900.00.”). The taking

was foreseeable, manifestly intended as a taking, and not mitigated by the character of the land

or Mrs. Caquelin’s reasonable investment-backed expectations. See also Banks, 138 Fed. Cl. at

150 (finding the same outcome with another NITU); Balagna, 138 Fed. Cl. at 403 (same).

Additionally, notwithstanding the foregoing takings analysis, if for whatever reason the

court of appeals should conclude that no taking occurred, a tort claim under the Federal Torts

Claim Act, 28 U.S.C. § 1346, would become applicable, but such a claim might actually

establish that a taking was more appropriate. That Act provides that:

“[D]istrict courts . . . shall have exclusive jurisdiction of civil actions or

claims against the United States . . . for injury or loss of property . . . caused

by the . . . wrongful act or omission of any employee of the [g]overnment

. . . , under circumstances where the United States, if a private person,

would be liable to the claimant in accordance with the law of the place

where the act or omission occurred.” 28 U.S.C. § 1346(b)(1).

At issue in a tort claim would be the precepts set out in Chapter 7 of the

Restatement (Second) of Torts (Am. Law Inst. 1965) (entitled “Invasions of the

Interest in the Exclusive Possession of Land and its Physical Condition (‘Trespass on

23

Land’).”). Under the Restatement, “a person who is in possession” is someone who

“has the right against all persons to immediate occupancy of land, if no other person is

in possession.” Id. § 157(c). With the abandonment by the railroad of its rail line, its

easement was extinguished and Mrs. Caquelin was entitled to occupancy of her

portion of the said corridor. “Liability for intentional intrusions on land” is covered by

Section 158 of the Restatement (heading, capitals omitted), excepting “[c]onduct

which would otherwise constitute a trespass if it is privileged.” Id., § 158 cmt. e. A

privilege “may be given by law because of the purpose for which the actor acts or

refrains from acting.” Id. The STB’s authorization to enter a NITU in anticipation of

trail use and rail-banking may constitute such a privilege.26 If so, the authorized

action presumptively would give rise to a taking.

CONCLUSION

For the reasons stated, the government is liable for a taking of plaintiff’s property on July

3, 2013, upon issuance of the NITU. In accord with the remand, the court concludes that final

judgment for the stipulated amount of principal and interest, $900.00, shall be entered under

RCFC 54(b) because there is no just reason for further delay. The clerk shall issue judgment

consistent with this disposition.

The court will address attorneys’ fees and expenses under the Uniform Relocation

Assistance and Real Property Acquisition Policies Act, 42 U.S.C. § 4654 (c), after the judgment

entered under RCFC 54(b) has become final as defined in 28 U.S.C. § 2412(d)(2)(G). See RCFC

54(d)(2)(B)

It is so ORDERED.

s/ Charles F. Lettow

Charles F. Lettow

Senior Judge

26

Restatement (Second) of Torts § 163 pertains to “intended intrusions causing no harm.”

Id. (heading, capitals omitted). As the Restatement explains, “[t]he wrong for which a remedy is

given under the rule stated in this Section consists of an interference with the possessor’s interest

in excluding others from the land.” Id., § 163 cmt. d.

24

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.