Opinion

Mw Builders, Inc. v. United States

  • 134 Fed. Cl. 469
Court
United States Court of Federal Claims
Filed
Oct 18, 2017
Status
Published
Author
Braden
On the bench
Susan G. Braden
Cited by
7 cases
Authority
More cited than 51.1%

The opinion

In the United States Court of Federal Claims

No. 13-1023 C

Filed: October 18, 2017

**************************************** Anti-Deficiency Act, 31 U.S.C. § 1350;

* Breach of Contract;

* Contract Disputes Act,

MW BUILDERS, INC. f/n/a * 41 U.S.C. §§ 7101–7109;

MW BUILDERS OF TEXAS, INC., * Counterclaims, 28 U.S.C. § 2508;

* False Claims Act, 31 U.S.C. §§ 3729–

Plaintiff, * 3733;

* Federal Acquisition Regulation,

v. * 48 C.F.R. §§ 52.211-12 (Liquidated

* Damages), 52.242-14 (Suspension of

* Work), 52.249-10 (Contract Default);

THE UNITED STATES, * Good Faith and Fair Dealing;

* Special Plea In Fraud, 28 U.S.C. § 2514;

Defendant. * Tucker Act Jurisdiction, 28 U.S.C. § 1491;

* Unreasonable Delay;

* Waiver.

****************************************

Paul Harvey Sanderford, Sanderford and Carroll, P.C., Temple, Texas, Counsel for Plaintiff.

Alexander Orlando Canizares, United States Department of Justice, Washington, D.C., Counsel

for the Government.

POST-TRIAL MEMORANDUM OPINION AND FINAL ORDER 1

This case concerns the United States Army Corps of Engineers (“Army Corps”) attempt to

shift its contractual responsibility to make arrangements for permanent electrical utility services

that MW Builders, Inc. (“MW Builders”) needed to build an Army Reserve Center in Sloan,

Nevada. This imposed unnecessary construction delay and costs on MW Builders that the

Contracting Officer (“CO”) refused to pay. When MW Builders filed a Complaint in the United

States Court of Federal Claims, the Government alleged that the contractor’s claim was fraudulent.

As discussed herein, the court has determined that the Army Corps breached a

September 10, 2010 Contract with MW Builders and violated the duty of good faith and fair

dealing for which $418,961.90 is awarded, as compensable delay damages, together with statutory

1

On September 29, 2017, the court forwarded a sealed copy of this Post-Trial Memorandum

Opinion And Final Order to the parties to provide them the opportunity to correct any

typographical or similar errors. The parties had until October 16, 2017 to submit suggested

corrections. On October 18, 2017, the court issued a final Post-Trial Memorandum Opinion And

Final Order that incorporated all appropriate corrections.

interest. The Government’s counterclaims for fraud are dismissed, but the Government’s

affirmative defense of waiver concerning one of MW Builders’ subcontractors’ alleged pass-

through claim is granted.

To facilitate review of this Post-Trial Memorandum Opinion And Final Order, the court

has provided the following outline.

I. RELEVANT FACTUAL BACKGROUND.

A. In 2008, The United States Army Corps Of Engineers Began Designing An Army

Reserve Center To Be Built In Sloan, Nevada.

B. On June 11, 2010, The United States Army Corps Of Engineers Issued Solicitation No.

W912QR-09-R-0104 Requesting Proposals For A Firm, Fixed-Price Contract To Build

The Army Reserve Center In Sloan, Nevada.

C. On September 10, 2010, The United States Army Corps Of Engineers Awarded Contract

No. W912QR-10-C-0078 To MW Builders, Inc.

D. On December 6, 2010, MW Builders, Inc. Entered Into A Subcontract With Bergelectric

Corporation To Provide An Electrical System.

E. In 2011, MW Builders, Inc. Executed A Third Party Authorization Form And Design

Approval Agreement With NV Energy.

F. In March 2012, MW Builders, Inc. And The United States Army Corps Of Engineers

Had A Dispute Over The Execution Of A Line Extension Agreement With NV Energy.

G. On April 6, 2012, MW Builders, Inc. Notified The United States Army Corps Of

Engineers That The Construction Schedule Would Be Delayed, Because The Line

Extension Agreement With NV Energy Was Not Executed.

H. On April 19, 2012, The United States Army Corps Of Engineers Began To Negotiate A

Line Extension Agreement With NV Energy.

I. On July 12, 2012, The United States Army Corps Of Engineers Signed A Line

Extension Agreement With NV Energy.

J. On December 27, 2012, MW Builders, Inc. Submitted A Certified Claim To The

Contracting Officer For Costs Incurred As A Result Of The United States Army Corps

Of Engineers’ Failure To Timely Execute A Line Extension Agreement With NV

Energy.

K. On June 10, 2013, The Contracting Officer Issued A Final Decision Denying MW

Builders, Inc.’s Monetary Claim, But Granting A Non-Compensable Time Extension Of

146 Days For MW Builders, Inc. To Complete Construction Of The Army Reserve

Center In Sloan, Nevada.

L. On December 13, 2013, The Completed Army Reserve Center in Sloan, Nevada Was

Accepted By The United States Army Corps Of Engineers.

II. PROCEDURAL HISTORY.

2

III. DISCUSSION.

A. Subject Matter Jurisdiction.

B. Standing.

C. Plaintiff’s Claims Against The Government.

1. The September 10, 2010 Contract Required The United States Army Corps Of

Engineers To Sign The Line Extension Agreement With NV Energy.

a. Plaintiff’s Argument.

b. The Government’s Response.

c. The Court’s Resolution.

i. The September 10, 2010 Contract Contains A Latent Ambiguity Regarding

Which Party Was Responsible For Signing The Line Extension Agreement

With NV Energy.

ii. Extrinsic Evidence Of Intent Demonstrates That The United States Army Corps

Of Engineers Was Responsible For Signing The Line Extension Agreement

With NV Energy.

2. The United States Army Corps Of Engineers Violated The Duty Of Good Faith And

Fair Dealing Causing An Unreasonable Delay To The Project.

a. Plaintiff’s Argument.

b. The Government’s Response.

c. Plaintiff’s Reply.

d. The Government’s Sur-Reply.

e. The Court’s Resolution.

i. The United States Army Corps Of Engineers Violated The Duty Of Good Faith

And Fair Dealing.

ii. The United States Army Corps Of Engineers’ Conduct Caused An

Unreasonable Delay.

D. The Government’s Affirmative Defense And Counterclaims.

1. The Government’s Affirmative Defense Of Waiver.

a. The Government’s Argument.

b. Plaintiff's Response.

c. The Court’s Resolution.

2. The Government’s Counterclaims.

a. Subject Matter Jurisdiction.

b. Standing.

c. The Government’s Argument.

d. Plaintiff’s Response.

e. The Government’s Reply.

f. The Court’s Resolution.

i. Regarding The Anti-Fraud Provision Of The Contract Disputes Act.

3

ii. Regarding The Special Plea In Fraud.

iii. Regarding The False Claims Act.

IV. CALCULATION OF DELAY CAUSED BY THE UNITED STATES ARMY CORPS OF

ENGINEERS’ BREACH AND DAMAGES.

A. The Parties’ Scheduling Experts.

1. Plaintiff’s Scheduling Experts.

a. Mr. Neil W. Miltonberger.

b. Mr. Denny Lee.

2. The Government’s Scheduling Expert, Mr. Stephen Weathers.

3. The Scheduling Experts’ Critiques.

B. Plaintiff’s Damages Claim.

1. Plaintiff’s Claimed Amount.

2. The Government’s Response.

3. The Court’s Determination.

a. Regarding The Amount Of Delay.

b. Regarding The Daily Jobsite Overhead Rate.

c. Regarding The Materials And Equipment Costs.

d. Regarding Home Office Overhead.

e. Regarding Profit.

f. Regarding The Bond Fee.

g. Calculation Of Damages.

V. CONCLUSION.

* * *

I. RELEVANT FACTUAL BACKGROUND. 2

A. In 2008, The United States Army Corps Of Engineers Began Designing An

Army Reserve Center To Be Built In Sloan, Nevada.

In 2008, the United States Army Corps of Engineers (the “Army Corps”) began designing

an Army Reserve Center in Sloan, Nevada (the “Project”) for use by the Army Reserve 63rd

2

The facts discussed herein were derived from evidence adduced at the trial held on May

4–6, 9 and 10, 2016 in Austin, Texas (TR at 1–1329), together with the parties’ Joint Stipulations

Of Fact (Jt. Stip. ¶¶ 1–32). The witnesses for each party are identified in Court Attachment A. At

trial, Plaintiff’s Exhibits (PX 4–684) were admitted into evidence. TR at 6–7. The Government’s

Exhibits (DX 1–273), together with 95 Joint Exhibits (JX 1–95) also were admitted into evidence.

TR at 9–10. The Government also moved into evidence two Rule of the United States Court of

Federal Claims (“RCFC”) 30(b)(6) depositions: i.e., the April 12, 2016 Deposition of David

Cimpl, Chief Financial Officer for MMC Corporation (4/12/16 Cimpl Dep.); and the March 10,

2016 Deposition of Daniel “Sparky” Campbell, MW Builders’ Operations Manager (3/10/16

4

Regional Support Command (“63rd RSC”). TR at 16–17 (Probst); TR at 971 (Miller). During the

“Design Phase,” the Army Corps retained Mason & Hanger, an architecture and engineering firm,

to design and prepare construction specifications. Jt. Stip. ¶ 8. Mr. Jonathan Miller also served as

Mason & Hanger’s Project Manager. TR at 970–71 (Miller). Several Army Corps employees also

were involved:

• Hans Probst, the Branch Chief of the Instruction Division of the Army Reserve

Program Louisville District, served as the Project Manager, TR 15 (Probst);

• Robert Caskie, an employee from the Army Corps’ Los Angeles District Office, served

as the Geographical Administrative Contracting Officer, TR 370 (Caskie);

• Johnny Ringstaff, an employee from the Army Corps’ Louisville District Office, served

as an Administrative Contracting Officer, TR at 1118 (Ringstaff); and

• Tara O’Leary, an Army Corps Design Project Engineer, managed the Army Corps’

design contract with Mason & Hanger, TR at 1144–45 (O’Leary).

The Sloan, Nevada site selected by the Army Corps did not have any existing electric

utilities. Jt. Stip. ¶ 5. Therefore, the local electrical utility, Nevada Power Company, doing

business as NV Energy (“NV Energy”), was required to design a new utility line that would

connect the Project with existing power lines. PX 4 at 2; see also JX 2 (4/28/09 Meeting Minutes

reporting that “[u]tility coordination is critical”).

Mason & Hanger was responsible for contacting NV Energy about utility design and, on

May 6, 2009, NV Energy provided Mason & Hanger with a draft “Design Initiation Agreement,”

together with a memorandum that listed all the steps necessary for NV Energy to provide electrical

power to the Project. DX 6 at 4. NV Energy’s May 6, 2009 draft Design Initiation Agreement

provided that, “[p]rior to going to construction, [the applicant must] sign one or more of the

following agreements: Line Extension Agreement (LEA); Large Profit Service Agreement (LPS

Agreement); Contribution In Aid of Construction Agreement (CIAC Agreement); Non-

Refundable Construction Agreement (NRCA).” DX 6 at 5.

On May 14, 2009, a Mason & Hanger employee forwarded the Design Initiation

Agreement and attached memorandum to Mark Cutler, an employee of the 63rd RSC. DX 6 at 2.

On May 15, 2009, Mr. Cutler forwarded the agreement to Ms. O’Leary, the Army Corps Design

Project Engineer for the Project, and stated that the Design Initiation Agreement should “be signed

by the [Army] Corps,” because it “has a look on it that whoever signs it should really have a

warrant or be a contracting officer.” DX 6 at 1. But, Ms. O’Leary declined to authorize a

representative of the Army Corps to sign the Design Initiation Agreement. DX 6 at 1.

Consequently, neither the 63rd RSC, Mason & Hanger, nor the Army Corps signed the Design

Initiation Agreement that NV Energy required before it would commence utility work on the

Project. JX 4. Instead, Ms. O’Leary suggested that the Army Corps “place that requirement on

the construction contractor.” DX 6 at 1.

Campbell Dep.). TR at 12–13. The court also admitted two Court Exhibits (CX 1–2) into

evidence. TR at 773, 969.

5

On July 15, 2009, the 63rd RSC, the Army Corps, and Mason & Hanger decided that the

solicitation should include a requirement that the winning bidder must sign the Design Initiation

Agreement with NV Energy. DX 8 at 1; see also TR at 978 (Miller). The Army Corps and Mason

& Hanger, however, did not include any express requirement about the “Line Extension

Agreement” in the solicitation.

B. On June 11, 2010, The United States Army Corps Of Engineers Issued

Solicitation No. W912QR-09-R-0104 Requesting Proposals For A Firm, Fixed-

Price Contract To Build The Army Reserve Center In Sloan, Nevada.

On June 11, 2010, the Army Corps issued Solicitation No. W912QR-09-R-0104 for a firm,

fixed-price contract to build a new 800-person Army Reserve Center in Sloan, Nevada for use of

the 63rd RSC. Jt. Stip. ¶¶ 1, 14.

C. On September 10, 2010, The United States Army Corps Of Engineers

Awarded Contract No. W912QR-10-C-0078 To MW Builders, Inc.

On September 10, 2010, the Army Corps awarded a contract to construct the Project to

MW Builders, based on a $23,661,000.00 bid (the “Contract”). Jt. Stip. ¶ 3. Under the terms of

the Contract, the completed Army Reserve Center would consist of: a training center (the “Training

Building”); an organizational maintenance shop building; a unit storage building; and a pump

house and tank. Jt. Stip. ¶ 2. In addition, the Contract required MW Builders to follow the Contract

specifications and design prepared by Mason & Hanger. Jt. Stip. ¶ 8.

Because the Project’s location in Sloan, Nevada did not have electric utilities, the Contract

required MW Builders to provide both “temporary power” 3 and “permanent power.” 4 DX 14; TR

at 426–27 (Matson). Contract Drawing ES-002, however, addressed the “Division of

Responsibility (Power):”

NV Energy is the electric utility serving this project. The contractor is responsible

for providing all electric infrastructure, equipment, and wiring for the project unless

specifically noted as provided by NV Energy in the Division of Responsibility.

Contractor shall contact NV Energy prior to bidding to verify that NV Energy will

provide everything noted [in the contract drawing table]. Contractor is responsible

for providing a complete and working electrical system, and shall include all costs

in this bid.

* * *

3

The term “temporary power” describes the electricity required to operate construction

tools and equipment during construction, and can be supplied by generators that construction

contractors bring onsite. TR at 426 (Matson).

4

The term “permanent power” refers to electrical facilities that remain a permanent part of

the building once construction is complete. TR at 427 (Matson).

6

The contractor will be required to sign a Design Initiation Agreement with NV

Energy and pay fees as shown in the bid schedule. The contractor shall contact NV

Energy and determine the scope and costs of this work prior to submitting a

proposal. The contractor’s proposal shall include all work and all costs associated

with providing electrical power for the project. Contractor is responsible for all

guidelines and requirements within [NV Energy’s] Electric Service Requirements,

which can be found on their website listed below.

The construction contractor shall obtain written documentation of all transactions

with NV Energy and provide them to the [Army Corps.]

DX 14.

The Contract also included Line Item 0006, “Nevada Energy Service Fee,” in the amount

of $590,160.00, that “includes the fee required by [NV Energy] to bring electric service to the

site.” Jt. Stip. ¶ 9.

In addition, the Contract required MW Builders to develop and update project schedules

using a “Critical Path Method” (“CPM”), 5 of an “appropriate level of detail,” and provide monthly

schedule updates to the Army Corps. Jt. Stip. ¶ 17. During the course of the Project, the Army

Corps hired a third-party scheduling consultant, Management Solutions, LLC (“Management

Solutions”), to review MW Builders’ CPM schedule updates and either approve them or make

suggestions. TR at 512–13 (Stone).

On November 9, 2010, the Army Corps issued a Notice To Proceed. DX 20. MW

Builders’ work was to be completed in 660 days, i.e., by August 30, 2012. Jt. Stip. ¶ 7.

D. On December 6, 2010, MW Builders, Inc. Entered Into A Subcontract With

Bergelectric Corporation To Provide An Electrical System.

On December 6, 2010, MW Builders entered into a $4,579,943.00 subcontract with

Bergelectric Corporation (“Bergelectric”) to “provide a complete Electrical System in accordance

with [the Contract] plans and specifications.” JX 9 at 2, 14. Bergelectric also was required to

provide temporary power for the site, prior to the installation of permanent power. JX 9 at 14.

Attached to the December 6, 2010 subcontract was a “Partial Waiver And Release,” under which

Bergelectric waived “any and all mechanic’s liens or other liens or any other claims on any bonds

or any other claims whatsoever in connection with this Contract and with the Realty . . . reserving,

however, all lien rights for materials and labor furnished or performed after said period[.]” JX 9

at 49. During performance, Bergelectric also was required to sign periodic partial waivers and

5

The Critical Path Method is a scheduling approach wherein the “logic” of a construction

schedule describes the interdependency of each construction activity. Miltonberger Direct at 6.

The term “critical path” refers to the continuous chain of activities that establishes the minimum

overall project duration. Miltonberger Direct at 6. Thus, a delay in any critical path activity will

extend the final completion date. Miltonberger Direct at 6–7. The term “float” refers to the amount

of time an activity may be delayed before affecting the critical path of the project. Miltonberger

Direct at 7.

7

submit them to MW Builders, together with applications for payment. DX 124 (4/15/12 waiver);

see also TR 672 (Campbell).

E. In 2011, MW Builders, Inc. Executed A Third Party Authorization Form

And Design Approval Agreement With NV Energy.

On March 15, 2011, NV Energy informed MW Builders that “the [Project] Owner shall

complete a NV Energy Consultant/Third Party [Contact] Authorization Form before any activity

will be provided to deliver electric service to the [P]roject site.” DX 37 at 30. On that date, an

Army Corps representative signed a Third Party Authorization Form, indicating that MW Builders

was the “sole contact” between NV Energy and the Army Corps, but MW Builders did not have

authority to negotiate contract changes on behalf of the Army Corps. 6 PX 15. The Third Party

Authorization Form designated the Army Corps as the “Customer/Legal Owner” of the Project. 7

PX 15.

On March 29, 2011, NV Energy also was provided with a “Project Information Sheet,”

wherein MW Builders provided a description of the Project to assist NV Energy’s utility design

and listed the Army Corps as the “Customer/Legal Owner.” PX 567 at 4.

On April 15, 2011, NV Energy sent MW Builders a draft “Design Initiation Agreement.”

DX 37 at 3. This document authorized NV Energy to design a utility system to bring permanent

power to the Project. TR at 1027–28 (Creveling). The draft Design Initiation Agreement listed

the “US Army Corps of Engineers” as the “Applicant” for permanent power. DX 37 at 14. A

timeline titled, “Milestones And NPC Durations For Typical New Business Projects,” also was

included stating that, generally it took NV Energy 20 weeks before it could begin providing

permanent power, but it could take as long as 88 weeks, i.e., 616 days, depending on how long it

took to secure the necessary approvals and perform other preliminary design steps, such as site

inspection. DX 37 at 19.

On April 27, 2011, Michael Marti, then MW Builders’ Project Manager, 8 signed the Design

Initiation Agreement and returned it to NV Energy, as required by Contract Drawing ES-002. JX

19 at 10. On or about April 28, 2011, MW Builders hired Richard Rial of STF, Inc., as a consultant

to help coordinate with NV Energy. Jt. Stip. ¶ 12.

6

The unsigned version of the Third Party Authorization Form initially provided that MW

Builders would have the authority to “communicate and authorize all change requests.” JX 14 at

11. In the signed version “and authorize” was crossed out. PX 15.

7

The Project’s eventual owner and end-user was to be the 63rd RSC. But, the 63rd RSC

deferred to the Army Corps with respect to the Third Party Authorization Form, because the Army

Corps was “the construction agent/property holder until construction completion/beneficial

occupancy.” DX 37 at 30.

8

Mr. Marti managed the Project for MW Builders from December 2010 until November

2011. TR at 219–20 (Marti).

8

On July 25, 2011, Mr. Marti also executed the “Design Approval Agreement,” by which

MW Builders approved NV Energy’s preliminary design for the Project’s permanent power.

TR at 213 (Marti). The Design Approval Agreement stated that the “Applicant” for permanent

power was the “US Army Corps of Engineers.” JX 21 at 1.

After executing the Design Approval Agreement, MW Builders began the work necessary

to connect the Project site to the electric grid. TR at 213 (Marti). 9 The closest hookup to the grid

was an NV Energy-owned utility pole located outside of the Project site at the intersection of

Arville Street and Ray Way (the “Arville Hub”). PX 471. To connect to the Arville Hub, MW

Builders was required to build an underground “offsite ductbank” across privately owned land, but

Contract Drawing CD-100 showed an easement running from the Project site to the Arville Hub

across this property. PX 471; see also PX 267 (“The contract drawings identify a corridor down

the Arville alignment for the construction contractor to install underground ductbanks for both

comm[unications] and power.”). Once the ductbank work was completed, NV Energy was

required to “pull” a utility line from the Arville Hub to the Project site. PX 267. Subsequently,

however, the parties discovered that there were no easements that allowed MW Builders to

construct ductbanks and manholes along the route to the Arville Hub. PX 267. Thereafter, NV

Energy and the telephone company informed the Army Corps that they would not install their lines

without an easement in the underground ductbanks. PX 267.

On or about August 9, 2011, MW Builders informed the Army Corps that their part of the

electrical work could not continue without the required easements. PX 477 at GOV_00012196.

On September 14, 2011, MW Builders sent a letter informing the Army Corps that their failure to

secure the easements, which was their responsibility under the Contract, and was delaying MW

Builders’ work. JX 26. On September 22, 2011, Mr. Caskie, the Army Corps’ Geographical

Administrative Contracting Officer, sent an email to Mr. Probst, the Army Corps’ Project

Manager, to inform him that Army Corps made a “big goof” in not securing the easements, because

it was “prohibited from awarding a contract wherein [its] real estate interests [were] not covered”

and “the design should never have required work on lands that the Government does not have the

right to access.” PX 267. On October 29, 2011, MW Builders sent the Army Corps a Request for

Information (“RFI”) concerning the offsite ductbank easement. PX 481.

On December 5, 2011, MW Builders also sent another letter to the Army Corps,

complaining that “delays in the delivery of permanent power” could affect completion of the

Project. JX 31 at 1. MW Builders attributed these delays to the Army Corps’ failure to secure

utility easements, prior to the start of the construction. JX 31 at 1. Specifically, NV Energy

required an offsite easement to continue the underground electrical work and an “Access To

Equipment Agreement,” signed by the Project owner, to allow NV Energy employees to monitor

the equipment on site. JX 31 at 1. MW Builders warned that, unless permanent power was in

place by May 21, 2012, it could not complete the Project by August 30, 2012. JX 31 at 1.

9

In the interim, temporary power was supplied by onsite generators. TR at 687–88

(Campbell).

9

On February 9, 2012, an NV Energy representative sent an email to the Army Corps

requesting that a senior Army official sign the Access To Equipment Agreement. PX 18.

It took until February 28, 2012, for an Army Corps representative to respond to MW

Builders’ July 9, 2011 email and September 2011 follow up requesting that a senior Army official

sign the Access To Equipment Agreement. PX 18. On March 16, 2012, an Army Reserve Major

General signed a letter authorizing NV Energy to enter the Project site. JX 49.

F. In March 2012, MW Builders, Inc. And The United States Army Corps Of

Engineers Had A Dispute Over The Execution Of A Line Extension

Agreement With NV Energy.

To provide permanent power, NV Energy also required a signed “Line Extension

Agreement” (also called a “Rule 9 Agreement”). PX 4 at GOV_0010874 (“Prior to going to

construction, [the applicant must] sign one or more of the following agreements: Line Extension

Agreement (LEA)[.]”); DX 221 at 7 (providing that NV Energy “shall deliver the Rule 9

Agreement and final cost estimate to Applicant”); see also TR at 38–39 (Probst). 10 The Line

Extension Agreement governed the terms of payment. TR at 473 (Rial) (“A Line Extension

Agreement is the contract between the utility and the owner on how the money is to be collected,

the breakdown on the money, and then, also, how the moneys will be refunded[.]”). Typically, a

Line Extension Agreement had a term of five years and was executed by the utility and the owner

of the project, not the construction contractor. TR at 469–70 (Rial), 584 (Risse); see also TR at

1077–78 (Finley) (same). But, NV Energy’s Utility Electric Service Rule No. 9, governing Line

Extension Agreements between NV Energy and commercial customers, did not expressly require

that the owner of the property sign the Line Extension Agreement. DX 270; see also TR at 631

(Risse) (“I don’t think [Rule No. 9] required the ultimate end user to have to sign [the Line

Extension Agreement.”).

At trial, Katherine Creveling, NV Energy’s Senior Project Coordinator, testified that she

remembered preparing an initial draft of a Line Extension Agreement with the understanding that

MW Builders would sign the agreement, not a government agency. TR at 1001, 1004–05

(Creveling). Although Ms. Creveling was unable to locate a copy of the draft Line Extension

Agreement in this case, she remembered that an initial draft Line Extension Agreement was

rejected by MW Builders, because MW Builders was not the “applicant” for permanent power.

TR at 1005–06 (Creveling).

On March 13, 2012, Mr. Probst, the Army Corps Project Manager assigned to the Project,

hosted a conference call that included representatives of: the 63rd RSC; MW Builders; NV Energy;

and Mason & Hanger. JX 44 at 1 (3/13/12 email summary of conference call). During the

conference call, it was agreed that, by March 16, 2012, NV Energy “will have sent draft contract

for review to 63[rd] RSC (Jeffrey Reed[s])[11] and [the] contract will be executed between NV

10

The December 5, 2011 letter sent by MW Builders about permanent power delays did

not discuss the Line Extension Agreement. JX 31.

11

Mr. Jeffrey Reeds was an attorney that represented the 63rd RSC. TR at 71 (Probst).

10

Energy and 63[rd] RSC such that staging of equipment can start on or about 19 March 2012.” JX

44 at 1. At trial, NV Energy’s in-house attorney, Ms. Rebeca Risse, testified that the “draft

contract” identified in this email was the draft Line Extension Agreement to be signed by the 63rd

RSC. TR at 583 (Risse). During the March 13, 2012 telephone conference, the participants also

agreed that permanent power would be available at the Project site by April 9, 2012. JX 44 at 1.

On March 13, 2012, Mr. Rial also sent an email to Mr. Probst, wherein he explained that

NVE is in the process of preparing [the] Line Extension Contract for service to the

site. On today’s phone call some of the contact information changed. I made a

note that you wanted the contract in the name of “United States Army Reserve, 63d

Regional Support Command.” It was originally submitted to NV Energy as the

Army [Corps] of Engineers.

JX 45 at 2.

On March 14, 2012, Ms. Creveling sent an email to the 63rd RSC with a “Government

Line Extension Agreement.” JX 47 at 1. The Line Extension Agreement provided:

• the Agreement term was five years (PX 449(r) ¶ 14.1);

• the 63rd RSC would make a partially-refundable advance payment of $143,495.00

(PX 449(r) ¶ 1.3);

• the refundable portion (“the Allowance”) of the 63rd RSC’s advance payment

would be reduced via an “Allowance True-Up,” if the 63rd RSC’s demand for

electricity decreased within the 18 months after the Agreement was signed (PX

449(r) ¶ 3.5); and

• the Agreement would be governed by and construed, in accordance with the Nevada

law, and all actions beyond the scope of the Nevada Utility Commission’s

jurisdiction were to be filed, in either Nevada state court or in federal district court.

(PX 449(r) ¶ 13.4).

On that same date, “uncertainty” arose as to whether or not a representative of the 63rd RSC would

sign the Line Extension Agreement. TR at 81–82 (Probst). Mr. Probst opined via email to other

Army Corps officials that: “I anticipate [the Army Corps] will become involved in the review and

possibly signature on the contract with NV Energy depending [on] what the nature of the document

is.” JX 46 at 1–2.

11

Later in the day, Ronald L. Musgrave, an Army Corps Contracting Officer’s

Representative, 12 responded that

I really don’t know why MW cannot sign the contract as they a[re] paying the fee 13

and the cost for service until it is acceptable, but I don’t want to introduce another

issue in this process by asking [NV Energy] if that is acceptable. We did issue a

document naming MW as our proxy. Maybe Rich Rial can go through the backdoor

and get an answer.

PX 501 at GOV_00005390.

That evening, however, Mr. Musgrave reported that

MW’s agent, Rich Rial, has spoken with [NV Energy] and they stated MW cannot

sign the contract on behalf of the [Army] Corp[s] or [the Army] Reserve[s’ 63rd

RSC]. They say it is a 5 year contract and the end user needs to be a signatory. As

of now the contract being prepared by NV [Energy] is on hold until they get a

commitment as to whom will sign and the name to be shown on the contract.

JX 46 at 1.

On March 19, 2012, Mr. Probst hosted a second conference call with the Army Corps and

NV Energy. PX 60A. MW Builders, however, was not invited to participate. TR at 84–85

(Probst). During this conference, the participants “determined that each party will tentatively

consider an arrangement whereby the [Army Corps’] Construction Contractor–MW Builders may

enter the agreement with NV Energy since this supports the typical means [the Army Corps]

obtains electric serv[ice] for new projects and has provisions in the [Army Corps]-MW Builders

Construction Contract.” PX 60A. On that same date, MW Builders provided NV Energy with a

renewed “Project Information Sheet.” DX 88A. Unlike the earlier March 19, 2012 Project

Information Sheet, the March 20, 2012 version stated that the “Customer/Legal

Owner/Responsible Party on Contracts” was MW Builders, not the Army Corps. DX 88A.

On March 20, 2012, Mr. Musgrave learned that NV Energy “ha[d] issues with the

contract,” particularly with respect to the Line Extension Agreement’s five year term and

indemnification provision. PX 60B.

On March 21, 2012, MW Builders informed the Army Corps that it would not sign the Line

Extension Agreement, because it “flatly” exceeded the scope of the September 10, 2010 Contract,

unless the Contracting Officer (the “CO”) ordered it to do so. PX 528. On that same date, Mr.

Probst also hosted another telephone conference with NV Energy, but again excluded MW

12

Although Mr. Musgrave was located in Las Vegas, Nevada during the Project, his

primary responsibility was to “keep the [C]ontracting [O]fficer informed of what was going on”

and answer any of MW Builders’ requests for information. TR at 1038 (Musgrave).

13

The September 10, 2010 Contract required MW Builders to pay NV Energy a

$590,160.00 Service Fee. Jt. Stip. ¶ 9.

12

Builders. PX 60C. During that conference, the participants agreed to procure a letter from a

“competent contracting authority of US Army Corps of Engineers . . . confirm[ing] that the [Army

Corps] construction contract with . . . MW Builders requires MW Builders to provide a complete

and working electric system to serve the Army Reserve Center at Sloan Road.” PX 60C.

On March 22, 2012, Mr. Musgrave informed Mr. Probst that MW Builders still “will not

move forward without [a] directive from the [Army] Corps,” and suggested that the Army Corps

not engage in a “letter writing campaign regarding interpretation” with MW Builders, but instead

recommended that the Army Corps should “[m]ake them do it and let the chips fall where they

may.” PX 27.

On March 26, 2012, Mr. Probst hosted a third telephone conference that included MW

Builders, wherein the participants discussed obtaining a letter from the CO to NV Energy, to

explain MW Builders’ responsibilities regarding electrical power. DX 109 at 2. The issue of who

would sign the Line Extension Agreement was not resolved, but the permanent power delivery

date remained as April 9, 2012. TR at 185 (Probst); DX 109 at 2.

On March 28, 2012, Ms. Creveling, the NV Energy Senior Project Coordinator, sent an

email to the Army Corps stating that “I have not received the letter that states MW Builders can

sign the LEA [i.e., the Line Extension Agreement] contract yet.” PX 504. Johnny Ringstaff, an

Army Corps Administrative Contracting Officer, responded that “I am holding the letter since we

are not in a position to sign the agreement. Our contractor has taken exception to some of the

agreement. Once that it is resolved we will send the letter.” PX 504.

On March 29, 2012, MW Builders’ Operations Manager Greg Herriott, sent an email to

Mr. Ringstaff, reiterating that MW Builders remained opposed to signing the Line Extension

Agreement, because “[i]t appears that this Agreement is intended to be signed by the end user, as

it obligates the Applicant to a 5 year term of service . . . with the Utility and puts the Applicant at

risk of additional costs after the 18 month ‘Allowance true-up[.]’” DX 102 at 1. Mr. Herriott also

stated that the Line Extension Agreement permitted multiple signatories and suggested that MW

Builders could potentially sign the Line Extension Agreement along with either the Army Corps

or the 63rd RSC, provided that “certain language could be modified to limit MW’s responsibilities

after project completion and acceptance by the Government.” DX 102 at 1.

On April 2, 2012, Mr. Ringstaff provided Ms. Creveling with a letter, signed by the CO,

stating that MW Builders was: responsible for providing a “complete and working electric

system;” required to follow NV Energy’s guidelines; and responsible for paying the “fee required

by [NV] Energy to bring electric service to the site.” PX 502 at GOV_00005419. The April 2,

2012 CO letter, however, did not state that MW Builders was obligated to sign the Line Extension

Agreement or that MW Builders was authorized to sign it. PX 502 at GOV_00005419. On that

same date, Ms. Creveling responded that she had received the letter, but was “under the impression

from our meeting . . . that some things still need to be ironed out between MW Builders and the

Army before I can start my contract.” DX 109 at 1.

13

G. On April 6, 2012, MW Builders, Inc. Notified The United States Army Corps

Of Engineers That The Construction Schedule Would Be Delayed, Because

The Line Extension Agreement With NV Energy Was Not Executed.

On April 6, 2012, MW Builders sent a “Notice Of Potential Delay” to inform the Army

Corps of a “delay to the project schedule due to a lack of permanent power at the projected site

referenced above.” JX 58. Although MW Builders completed the “primary duct bank and installed

electrical switchgear in accordance with the Contract Documents and Nevada Energy

requirements,” there was still no permanent power at the site, because “the Line Extension

Agreement between the Government and Nevada Energy [was] not yet in place, subsequently

delaying permanent power installation and startup.” JX 58. Once the site had permanent power,

however, MW Builders still needed “additional time and compensation” to make up the time it

was unable to work, because of the delay caused by the Army Corps’ failure to sign the Line

Extension Agreement. JX 58.

H. On April 19, 2012, The United States Army Corps Of Engineers Began To

Negotiate A Line Extension Agreement With NV Energy.

On April 19, 2012, the Army Corps’ counsel, Mr. Kevin M. Finley, sent an email to Ms.

Creveling questioning the terms of the Line Extension Agreement. JX 60. Mr. Finley also shared

his concerns with NV Energy’s in-house counsel, Ms. Rebecca Risse. TR at 1066, 1073 (Finley).

On April 26, 2012, Mr. Finley also sent an email to Ms. Risse, to begin contract negotiations about

the Line Extension Agreement and summarized the issues, as follows:

The current Agreement is drafted for the end user to sign (the [Army] Reserve[‘s

63rd RSC]), however, it involves issues related to both construction, for which the

[Army] Corps is responsible, and operation, for which the [63rd RSC is]

responsible.

Our construction contract was set up for the contractor to handle this by including

a line item with MW Builders that provides an allowance in sufficient amount to

cover the ‘Nevada Energy Service Fee.’ It was done that way to try to avoid this

very situation of meeting both utility requirements and Government requirements.

The Corps did execute a third party authorization form to allow our contractor to

coordinate and exchange of information related to the design and I think that has

worked and Nevada Energy is satisfied with the design.

We also furnished a letter to Ms. Creveling dated 27 March 2012 explaining the

Contractor’s requirements under his contract with the Government. I believe

[b]ased on this [NV Energy] is willing to accept the Contractor’s signature on the

Agreement. However, the Contractor is having problem[s] with par. 14.1 (5 year

term of service and par. 3.5 (18 month allowance true up).

This has become a critical path item on our construction contract and we are looking

for a path forward.

14

The first request would be to modify the agreement in such a way that either the

contractor or the Corps can sign it[.]

JX 61 at 1–2. In the alternative, Mr. Finley requested that the Army Corps sign an agreement that

governed construction and the 63rd RSC sign an agreement that governed operations, after

construction was completed. JX 61 at 2.

At trial, Ms. Risse testified that she did not read Mr. Finley’s April 26, 2012 email, until

the following week and “didn’t really understand why [Mr. Finley] was making these various

requests,” because she thought “we were having the contractor [i.e., MW Builders] sign” the Line

Extension Agreement, based on the March 21, 2012 conference call. TR at 607–09 (Risse). In

her opinion, the email also was “strange,” because it appeared that Mr. Finley was attempting to

negotiate a contract on behalf of MW Builders, which was not his client. TR at 608–09 (Risse).

On April 30, 2012, Mr. Finley sent a follow-up email, because Ms. Risse did not respond to his

first one. JX 61 at 1.

On May 2, 2012, MW Builders again reiterated that it would not sign the Line Extension

Agreement. PX 31. On May 15, 2012, Mr. Probst arranged a telephone call between Ms. Risse

and Mr. Finley. DX 127. Thereafter, Ms. Risse and Mr. Finley began renegotiating the terms of

the Line Extension Agreement via email. JX 68 (email chain running from 5/17/12 to 6/8/12).

On May 23, 2012, MW Builders sent another letter to the Army Corps, entitled “Permanent

Power Delay,” emphasizing that the “lack of permanent power to the jobsite continues to have

significant cost and schedule impacts,” i.e., MW Builders was required to “build the entire project

with temporary power;” MW Builders was unable to start up and test equipment; and MW Builders

was unable to “install building finishes which require conditioned air in the buildings.” PX 44.

MW Builders attributed the permanent power delay to “the Government’s failure to timely acquire

the onsite and offsite easements and execute the necessary agreements with the electric utility

provider (Nevada Energy)[.]” PX 44. MW Builders also stated that it “fulfilled its contractual

obligations as relates to the power,” but NV Energy still would not “give[] a final price or begin

work until the Government execute[d] the Line Extension Agreement.” PX 44. MW Builders

advised the Army Corps that it had no alternative but to request the additional costs incurred as a

result of the delay. PX 44.

On May 25, 2012, Mr. Finley resumed email negotiations with Ms. Risse, requesting that

the Line Extension Agreement be modified, so that its terms were enforceable and consistent with

federal law. JX 68 at 4–5. Negotiations continued over the next four weeks. PX 500. On May

29, 2012, Mr. Finley told Ms. Risse: “I would just like to get there sooner than later because we

are looking at having to bring in generators so that construction can continue. That is a costly

proposition that we would like to avoid.” JX 68 at 4. Mr. Finley also explained that “I think the

main issue is indemnity (limitations of damages)” and asked Ms. Risse to provide him with a

“sample” agreement that NV Energy previously entered into with a military customer. JX 68 at 4.

On June 4, 2012, Mr. Finley sent another email to Ms. Risse, wherein he stated that “I haven’t

received any reply to my [emails] of May 25 or May 29[.]” JX 68 at 3. On June 7, 2012, Ms.

Risse responded, opposing Mr. Finley’s proposed change to the enforceability provision. JX 68

at 3.

15

On June 15, 2012, Ms. Risse sent another email to Mr. Finley, describing his proposed

changes, but complained: “NV Energy has already compromised by agreeing that the

government’s contractor can be the applicant instead of the [g]overnment.” DX 143 at 2. Ms.

Risse also questioned why Mr. Finley wanted to change the Line Extension Agreement’s choice

of law provision, “given that NV Energy’s counterparty isn’t the federal government but rather the

government’s contractor.” DX 143 at 2.

On June 18, 2012, Mr. Finley responded:

Now, I am confused. I was under the impression that NV Energy would not accept

the contractor and was even balking at accepting the Corps of Engineers versus the

Reserves (the end user). What I have been trying to draft is an agreement between

the [Army] Corps and NV Energy. We seem to be working toward different goals.

DX 143 at 1. On that same date, Ms. Risse replied that she too was confused, because her

understanding was that the Line Extension Agreement was to be between NV Energy and MW

Builders. PX 500 at GOV_00005315. So, on June 20, 2012, Ms. Risse sent an email to MW

Builders’ in-house counsel, Harold Mitts, stating that, “[i]t was NV Energy’s understanding that

MW Builders was going to sign” the Line Extension Agreement. JX 72 at 1.

On June 21, 2012, Mr. Finley and Ms. Risse arranged for a telephone conference call with

Mr. Mitts. JX 75 at 1. At trial, Ms. Risse testified that it was only after this call that she actually

understood that MW Builders was not signing the Line Extension Agreement. TR at 597–98

(Risse). Thereafter, Ms. Risse resumed negotiations with Mr. Finley. JX 75 at 1 (6/21/12 email

from Ms. Risse to Mr. Finley with proposed changes to Line Extension Agreement); see also TR

at 598–99 (Risse). Negotiations continued from June 21, 2012 until July 7, 2012, during which

“drafts were exchanged quickly,” because the parties were no longer confused as to who was

actually signing the agreement. TR at 598–600, 626 (Risse). 14 While Mr. Finley and Ms. Risse

were negotiating the Line Extension Agreement, Mr. Probst initiated discussion with other Army

Corps officials about the pragmatic impact of the delay:

Requirement is for an electric utility line extension with Nevada Energy for

permanent primary power to the project site. Project is experiencing delay and

additional cost, a condition that is frustrating [the Army Corps’] customer [the 63rd

RSC. The Army Corps’] contract requires the contractor to provide a complete and

working electrical system. The contractor has refused to sign the NV Energy Line

Extension Agreement (LEA) claiming the conditions contained therein are meant

for the owner, [i.e., the Government.] NV Energy advises that the . . . approved

LEA is required and if not signed, NV energy will not provide the line extension.

NV energy has advised contractor can act on behalf of the owner ([the Army

Corps]) and have accepted [a CO] letter to that effect. The contractor continues to

object to signing the LEA and after investigation into the [Army Corps/MW

Builders] construction contract, [the CO] is unwilling to direct the contractor to

14

Ms. Risse testified that “once we understood that it was going to be the Government who

signed it, I thought it went pretty quickly—extremely quickly.” TR at 633 (Risse).

16

sign the NV Energy LEA as the [CO] feels the terms are not enforceable and would

expose the Government to a potential Request for Equitable Adjustment (REA) and

a contract ratification if an REA was upheld.

PX 294 (emphasis added).

On July 7, 2012, Ms. Risse sent a draft Line Extension Agreement to Mr. Finley. JX 83 at

1. At trial, Ms. Risse testified that the parties “[came] to an agreement on all of the terms” by that

date. TR at 600 (Risse).

I. On July 12, 2012, The United States Army Corps Of Engineers Signed A

Line Extension Agreement With NV Energy.

On July 12, 2012, the Army Corps signed the Line Extension Agreement. Jt. Stip. ¶ 25.

On July 17, 2012, MW Builders paid NV Energy’s service fee. Jt. Stip. ¶ 26. On July 23, 2012,

NV Energy signed the Line Extension Agreement. Jt. Stip. ¶ 25.

On September 19, 2012, the Army Corps was notified that MW Builders was preparing to

submit a claim for costs 15 incurred by the Army Corps’ failure to sign the Line Extension

Agreement. DX 181 at 1.

By September 26, 2012, NV Energy was supplying permanent power to all buildings at the

Project, except the pump house. Jt. Stip. ¶ 27. On October 12, 2012, MW Builders informed its

subcontractors that the Project had permanent power and directed them to “return to the project

and complete all remaining work immediately.” JX 85.

In early October 2012, MW Builders began to install climate sensitive materials, including

Acoustic Ceiling Tiles (“ACT”) and Vinyl Composition Tiles (“VCT”), inside the Training

Building. PX 343 at 3. This work could not have been performed without permanent power,

required for the Training Building’s heating, ventilation, and air conditioning (“HVAC”) system

to function. PX 343 at 3. 16

15

During the Project, MW Builders’ Accounting Department used a cost accounting

computer system known as “COMET.” 4/12/16 Cimpl Dep. at 17–18. COMET created “job cost

summaries” and prepared monthly financial statements submitted to MW Builders’ parent

corporation, MMC Corporation (“MMC”). 4/12/16 Cimpl. Dep. at 10–16, 18, 82–83. Job cost

summaries were used to track costs and compare them to budget estimates. TR at 1167–68

(Campbell). On April 12, 2016, the Government deposed David Cimpl, the Chief Financial

Officer of MMC Corporation, about MMC’s and MW Builders’ accounting methods. 4/12/16

Cimpl Dep. at 10. On May 4, 2016, the court admitted this deposition into evidence. ECF No. 97.

16

But, the pump house did not have permanent power on October 12, 2012, requiring MW

Builders to install “a temporary generator to supply power to the Pump House pumping system”

to continue work. JX 85. NV Energy did not provide power to the pump house until January 7,

2013. DX 218 at 3.

17

J. On December 27, 2012, MW Builders, Inc. Submitted A Certified Claim To

The Contracting Officer For Costs Incurred As A Result Of The United States

Army Corps Of Engineers’ Failure To Timely Execute A Line Extension

Agreement With NV Energy.

On December 27, 2012, MW Builders submitted a certified claim to the CO requesting a

169-day time extension and $2,139,215.00 for “costs incurred” by MW Builders as a result of

delay caused by “the Government’s failure to execute the required ‘Line Extension Agreement’

with Nevada Energy . . . by the date required to allow [NV Energy] to bring power to the jobsite

as scheduled.” JX 88 at 1–2. MW Builders again stated that it was not responsible for signing the

Line Extension Agreement. JX 88 at 1. MW Builders’ claim included ten subcontractor claims

in the amount of $985,874.00, including Bergelectric’s claim for $296,300.00. JX 88 at 3. MW

Builders’ claim itemized: (1) $181,678.00 for “Material & Equipment” costs; (2) $14,716.00 for

tax reimbursement; (3) $19,639.00 for overhead; (4) $17,283.00 for general contractor’s profit; (5)

$687,999.00 for “Jobsite Overhead Costs;” 17 (6) $192,998.00 for “Home Office Overhead;” (7)

$16,381.00 for insurance reimbursement; and (8) a $22,647.00 bond fee. JX 88 at 3. In submitting

the certified claim, MW Builders’ President, Jason Evelyn, represented that

this claim is made in good faith; that the supporting data are accurate and complete

to the best of my knowledge and belief; that the amount requested accurately

reflects the contract adjustment for which the Contractor believes the Government

is liable; and that I am duly authorized to certify the claim on behalf of the

Contractor.

JX 88 at 1; see also 41 U.S.C. § 7103(b). 18

17

The jobsite overhead costs were derived by multiplying a “daily cost rate” of $4,071.00

by 169 days. JX 88 at 3 (Claims Worksheet); TR at 1178–80 (Campbell). The “daily cost rate”

was ascertained, based upon a five-page work sheet (the “General Conditions Worksheet”) that

MW Builders submitted together with the certified claim; no other underlying documentation was

submitted to support the daily cost rate for jobsite overhead. JX 88 at 6–10 (Claims Worksheet);

see also TR at 1175, 1178–80 (Campbell).

18

Section 7103(b) of the Contract Disputes Act (“CDA”) provides that:

(1) Requirement generally.–For claims of more than $100,000 made by a

contractor, the contractor shall certify that–

(A) the claim is made in good faith;

(B) the supporting data are accurate and complete to the best of the

contractor's knowledge and belief;

18

The General Conditions Worksheet was prepared by MW Builders’ Operations Manager

Mr. Daniel “Sparky” Campbell in November 2012; the December 27, 2012 claim letter was

prepared by Mr. Greg Herriott, an MW Builders employee and Operations Manager. TR at 1171–

72, 1174 (Campbell).

On January 3, 2013, MW Builders submitted a request to the Army Corps for

reimbursement of the fee MW Builders paid to NV Energy. DX 200 at 2.

On May 15, 2013, MW Builders submitted a revised certified claim (“Amended Certified

Claim”) to the CO, wherein MW Builders again stated that it was not required to sign the Line

Extension Agreement, because certain provisions about the conveyance of property rights could

only be provided by the Project site owner. JX 89 at 1–2. MW Builders added that the “[t]he

failure of the Government to timely execute the Line Extension [A]greement implicated the

Government[’]s general duty to cooperate and to do nothing that unreasonably hinders the

contractor’s performance.” JX 89 at 2. MW Builders also revised and increased the claim amount

to $2,562,049.00, but did not change any of the estimated costs. JX 89 at 2.

(C) the amount requested accurately reflects the contract adjustment for

which the contractor believes the Federal Government is liable; and

(D) the certifier is authorized to certify the claim on behalf of the

contractor.

(2) Who may execute certification.–The certification required by paragraph (1)

may be executed by an individual authorized to bind the contractor with respect to

the claim.

(3) Failure to certify or defective certification.–A contracting officer is not

obligated to render a final decision on a claim of more than $100,000 that is not

certified in accordance with paragraph (1) if, within 60 days after receipt of the

claim, the contracting officer notifies the contractor in writing of the reasons why

any attempted certification was found to be defective. A defect in the certification

of a claim does not deprive a court or an agency board of jurisdiction over the

claim. Prior to the entry of a final judgment by a court or a decision by an agency

board, the court or agency board shall require a defective certification to be

corrected.

41 U.S.C. § 7103(b).

19

K. On June 10, 2013, The Contracting Officer Issued A Final Decision Denying

MW Builders, Inc.’s Monetary Claim, But Granting A Non-Compensable

Time Extension Of 146 Days For MW Builders, Inc. To Complete

Construction Of The Army Reserve Center In Sloan, Nevada.

On June 10, 2013, the Army Corps CO issued a final decision denying MW Builders’ claim

for both the company and its subcontractors, but granted a non-compensable time extension of 146

days. DX 218 at 4. Therein, the CO also found that, although significant delay incurred as a result

of difficulties surrounding the execution of the Line Extension Agreement, it “was beyond the

control of the Contractor or the Government,” and therefore was “excusable, but not

compensable,” pursuant to the Federal Acquisition Regulation (“FAR”). DX 218 at 1–3;

52.249-10.

With respect to the apportionment of responsibility, although Contract Drawing ES-002

“places much of the responsibility of arranging for power to the site on the Contractor,” it “does

not specifically place responsibility of the Line Extension Agreement on the Contractor.” DX 218

at 4. As such, NV Energy’s delay in providing electrical power to the Project “was beyond the

Contractor’s control.” 19 DX 218 at 4. Therefore, the Army Corps was not entitled to assess

liquidated damages 20 against MW Builders for the 146 days of delay that occurred between March

14, 2012, when NV Energy first sent the Government a proposed Line Extension Agreement, and

July 12, 2012, when the Army Corps signed the agreement. DX 218 at 3. And, MW Builders was

not entitled to recover costs incurred in connection with the delay by the Army Corps, because the

entirety of the delay was attributable to NV Energy, a “third party over whom the Government had

no control.” DX 218 at 4.

L. On December 13, 2013, The Completed Army Reserve Center in Sloan,

Nevada Was Accepted By The United States Army Corps Of Engineers.

On December 13, 2013, the Army Reserve accepted the completed Project from MW

Builders. DX 225. The Project’s original completion date was August 30, 2012. Jt. Stip. ¶ 7.

During the course of the Project, however, the parties made 85 contract changes and extended the

completion date by 413 days, extending the contract completion date to October 17, 2013.

DX 241.

19

The FAR provision governing contractor default for fixed-price construction contracts

provides: “[t]he Contractor’s right to proceed shall not be terminated nor the Contractor charged

with damages under this clause, if . . . [t]he delay in completing the work arises from unforeseeable

causes beyond the control and without the fault or negligence of the Contractor.” 48 C.F.R.

§ 52.249-10(b)(1).

20

The FAR provision governing liquidated damages in construction contracts provides:

“[i]f the Contractor fails to complete the work within the time specified in the contract, the

Contractor shall pay liquidated damages to the Government[.]” 48 C.F.R. § 52.211-12.

20

II. PROCEDURAL HISTORY.

On December 27, 2013, MW Builders filed a Complaint (“Compl.”) in the United States

Court of Federal Claims: Count One alleged that the Army Corps breached its duty to cooperate;

Count Two alleged that the Army Corps caused an unreasonable delay; and Count Three alleged

that the Contracting Officer improperly classified the delay as “non-compensable.” ECF No. 1.

As a result, MW Builders alleged that it was owed “a compensable time extension of at least 169

days,” as well as $2,562,094.00 in damages. ECF No. 1.

On May 13, 2014, the Government filed an Answer. ECF No. 8.

On July 7, 2014, the parties filed a Joint Preliminary Status Report. ECF No. 9. On July

17, 2014, the court issued a Scheduling Order allowing fact discovery to proceed from July 16,

2014 until July 15, 2015. ECF No. 10. On July 24, 2014, the Government filed an Unopposed

Motion For Entry Of A Discovery Order Concerning Materials As To Which Privileges May Be

Asserted, that the court granted the same day. ECF Nos. 11–12.

On January 12, 2015, the Government filed a Motion To Compel Production Of

Documents. ECF No. 13. That motion requested the court to order MW Builders to respond to

the Government’s First Set Of Document Requests. ECF No. 13 at 1. The court convened

telephone status conferences on January 26, 2015 and March 23, 2015. During the March 23, 2015

Status Conference, the Government voluntarily withdrew the January 12, 2015 Motion To Compel.

See ECF No. 14.

On July 14, 2015, the parties filed a Joint Status Report And Joint Motion To Enlarge The

Discovery Period until October 30, 2015. ECF No. 15. That same date, the court granted the

parties’ July 14, 2015 Motion. ECF No. 16.

On September 2, 2015, the parties filed a Status Report And Second Joint Motion To

Enlarge The Discovery Period until January 13, 2016. ECF No. 17. On September 9, 2015, the

parties filed a Joint Motion For Scheduling Order, including with a proposed schedule. ECF No.

18. On September 10, 2015, the court issued an Order adopting the parties’ proposed schedule.

ECF No. 20.

On December 30, 2015, the Government filed a Status Report And Consent Request For

Status Conference Regarding Productions Of Documents And Trial Issues. ECF No. 23.

On January 6, 2016, the court convened a telephone status conference. On January 8, 2016,

the parties filed a Joint Motion For Scheduling Order. ECF No. 24. The same date, the court

entered that Order. ECF No. 25. On January 29, 2016, the Government filed a Motion In Limine

To Exclude Testimony Of Witnesses Not Properly Disclosed. 21 ECF No. 26.

On February 17, 2016, the Government filed a Motion For Leave To Amend Its Answer

To Assert Counterclaims And Affirmative Defenses, together with a proposed Amended Answer

21

The Government moved to exclude the expert testimony of: Eric Stone, of MW Builders,

Inc.; Justin Knippel, of Bergelectric Corporation; and Larry Campbell, of Desert Fire Protection,

L.P., as they were listed on MW Builders, Inc.’s Designation Of Experts as “non-retained experts.”

21

(“Gov’t Amend. Answer”). ECF No. 27. The February 17, 2016 Amended Answer asserted

counterclaims, based on: the Special Plea In Fraud, 28 U.S.C. § 2514; the anti-fraud provision of

the Contract Disputes Act, 41 U.S.C. § 7103(c)(2); and the False Claims Act, 31 U.S.C. §§ 3729–

3733. ECF No. 27 at 1. The Amended Answer also asserted the affirmative defenses of accord

and satisfaction, and waiver. ECF No. 27 at 1.

On February 22, 2016, MW Builders filed a Response To Defendant’s Motion In Limine.

ECF No. 29. On February 23, 2016, the court convened a telephone status conference. That same

date, the Government filed a Status Report that detailed ongoing discussions with MW Builders to

resolve the Government’s January 29, 2016 Motion In Limine and requested that the court order

MW Builders to produce any remaining waivers or releases. ECF No. 30 at 5. The Government

also requested the court’s leave to take a deposition of one of MW Builders’ non-retained expert

witnesses, pursuant to Rule of the United States Court of Federal Claims (“RCFC”) 30(b)(6). ECF

No. 30 at 5. On February 23, 2016, MW Builders filed a Status Report Noting The Parties’

Agreement Pertaining To The Matters Subject To The Status Conference Scheduled For February

23, 2016. ECF No. 31.

On March 2, 2016, the Government filed a Status Report Regarding Plaintiff’s Expert

Disclosure. ECF No. 32. That same date, MW Builders filed a Status Report Regarding Plaintiff’s

Expert Disclosure. ECF No. 33. On March 4, 2016, the Government filed a Status Report,

indicating that the parties reached an agreement and the Government was withdrawing the January

29, 2016 Motion In Limine. ECF No. 34.

On March 7, 2016, MW Builders filed a Response To Defendant’s February 17, 2016

Motion To Amend. ECF No. 35. On March 15, 2016, the Government filed a Reply. ECF No.

36. That same date, MW Builders filed a Sur-Response To Defendant’s Motion (ECF No. 37),

and the Government filed a Response To Plaintiff’s Sur-Response (ECF No. 38). On that date, the

court issued an order granting the Government’s February 17, 2016 Motion To Amend. ECF No.

39.

On March 24, 2016, MW Builders filed: a Motion To Dismiss Defendant’s Counterclaims,

Pursuant To Rule 12(b)(6), And Alternative Answer To Defendant’s Counterclaims (ECF No. 42);

a Motion For Leave To Supplement Its Expert Report, Initial Exhibit List, And Initial Witness List

To Respond To The Government’s Late-Filed Fraud Counterclaim (ECF No. 43); and a Motion

For Authorization Of Service Of Subpoenas More Than 100 Miles From The Place Of Trial (ECF

No. 44); and a Request For A Status Conference (ECF No. 45).

On March 25, 2016, the Government filed Responses To MW Builders’ March 24, 2016

Motion For Authorization Of Service Of Subpoenas and March 24, 2016 Motion To Supplement.

ECF Nos. 46–47. The Government also included a Cross-Motion In Limine To Deny Introduction

Of Late Produced Documents At Trial. ECF No. 47. That same date, MW Builders filed a Reply.

ECF No. 48.

On March 28, 2016, MW Builders filed a Reply to the Government’s March 25, 2016

Response And Cross-Motion In Limine. ECF No. 49. On March 29, 2016, the Government filed

a Reply In Support Of The Cross-Motion In Limine. ECF No. 50.

22

On March 29, 2016, the Government filed a Motion For Extension Of Time To Serve

Responses To Plaintiff’s Interrogatories And Document Requests And For Leave To Take

Deposition. ECF No. 51. That same date, the court issued an Order granting MW Builders’ March

24, 2016 Motion For Leave To Supplement and denying the Government’s March 25, 2016 Cross-

Motion In Limine. ECF No. 52.

On March 31, 2016, the Government filed a Status Report Regarding Motion For Extension

Of Time And For Leave To Take Deposition, explaining it was withdrawing the March 29, 2016

request for an extension of time to respond to MW Builders’ interrogatories, but still was seeking

leave to take a RCFC 30(b)(6) deposition of an unnamed fact witness. ECF No. 54. On April 5,

2016, the court issued a Scheduling Order that provided additional deadlines for discovery

production. ECF No. 59. On April 8, 2016, MW Builders filed a Pre-Trial Submission that

detailed MW Builders’ proposed findings of fact, proposed conclusions of law, witness list, exhibit

list, and preliminary objections. ECF No. 62. On April 12, 2016, MW Builders filed a

Supplemental Disclosure Regarding Its Pre-Trial Filings that included an exhibit MW Builders

inadvertently omitted from the April 8, 2016 Pre-Trial Submission. ECF No. 63.

On April 14, 2016, the Government filed a Status Report And Request For Status

Conference to resolve a dispute regarding the trial schedule. ECF No. 64. On April 15, 2016,

MW Builders filed a Response to the Government’s April 14, 2016 Status Report. ECF No. 65.

On April 18, 2016, MW Builders filed the written direct testimony of Mr. Neil W.

Miltonberger (“Miltonberger Direct”) and attachments (“Miltonberger Direct Atts. 1–6.5”),

together with the written direct testimony of Mr. Denny Lee (“Lee Direct”) and a Second

Supplemental Designation of Experts. ECF No. 68. On April 19, 2016, the Government filed

Proposed Findings Of Fact And Conclusions Of Law. ECF No. 76.

On April 22, 2016, the Government filed a Motion In Limine To Preclude Privileged Trial

Testimony Of Attorney Witnesses (ECF No. 78) and a Motion In Limine To Admit Into Evidence

Plaintiff’s Binding Admissions (ECF No. 79). On that same date, MW Builders filed a Motion In

Limine (ECF No. 80) to exclude the expert testimony of Mr. Stephen Weathers and a Motion In

Limine Regarding Any Evidence That Supports The Government’s Fraud Allegations (ECF No.

81).

On April 25, 2016, the Government filed a Motion Regarding Procedural Matters At Trial,

requesting that the court enter a proposed order governing witness disclosure. ECF No. 82. The

Government also filed a Response to MW Builders’ April 22, 2016 Motion To Exclude Expert

Testimony. ECF No. 83. On that same date, MW Builders filed a Response to the Government’s

April 22, 2016 Motion To Exclude Privileged Testimony (ECF No. 84), as well as a Response to

the Government’s April 22, 2017 Motion To Admit Plaintiff’s Binding Admissions (ECF No. 85).

On April 26, 2016, the parties filed a Joint Stipulations Of Trial And Pre-Trial Procedure.

ECF No. 86. MW Builders also filed a Response to the Government’s April 25, 2016 Motion

Regarding Procedural Matters. ECF No. 87. On that same date, the Government filed a Response

to MW Builders’ April 22, 2016 Motion To Exclude Evidence Related To Fraud Claims. ECF

No. 88. On that date, the Government also filed the Written Direct Testimony of Mr. Stephen

Weathers, together with seven tabs (“Weathers Direct Tabs A–G”). ECF No. 89.

23

On April 27, 2016, the court issued an Order denying both of the Government’s April 22,

2016 Motions In Limine, and both of MW Builders’ April 22, 2016 Motions In Limine. ECF No.

90. The court also denied the Government’s April 25, 2016 Motion Regarding Procedural Matters,

as moot. On the same date, the Government filed a Revised Exhibit List. ECF No. 91. On April

28, 2016, MW Builders filed a Third Supplemental Exhibit List. ECF No. 92. On the same date,

the parties filed a Joint Stipulations Of Fact. ECF No. 93.

On May 2, 2016, MW Builders filed a Fourth Amended Exhibit List. ECF No. 94. On the

same date, the Government filed a Response to MW Builders’ April 28, 2016 Third Supplemental

Exhibit List and May 2, 2016 Fourth Amended Exhibit List. ECF No. 95.

A trial took place from May 4, 2016 to May 10, 2016 in Austin, Texas. TR at 1–1329. On

May 9, 2016, and at the request of the court, the Government filed the Updated Written Direct

Testimony of Mr. Stephen Weathers (“Weathers Rev. Direct”). ECF No. 96. At the close of trial,

the court left the record open to allow both parties’ experts to file supplemental damages testimony,

if they wished to do so. TR at 1314.

On May 27, 2016, the Government filed an Unopposed Motion To Admit Into Evidence

Deposition Exhibits, i.e., the depositions of Mr. David Cimpl and Mr. Daniel Campbell. ECF No.

97.

On June 14, 2016, the court granted the Government’s May 27, 2016 Motion and issued a

Scheduling Order setting a deadline of August 1, 2016 for MW Builders to file a Post-Trial

Proposed Findings of Fact And Memorandum Of Law. ECF No. 108 at 1. The Order also set a

deadline of September 1, 2016 for the Government to file the same. ECF No. 108 at 1.

On July 13, 2016, MW Builders filed an Unopposed Motion For Leave To Extend Post-

Trial Briefing Deadlines to August 15, 2016 and for the Government’s extension to September 15,

2016. ECF No. 110. On July 14, 2016, the court granted MW Builders’ July 13, 2016 Motion.

On August 4, 2016, the Government filed a Response to MW Builders’ March 24, 2016

Motion To Dismiss Counterclaims. ECF No. 111. On August 17, 2016, MW Builders filed a

Motion To Enter Additional Evidence, i.e., Mr. Neil Miltonberger’s Supplemental Expert Report.

ECF No. 114. On August 18, 2016, the parties filed a Joint Motion For Entry Of Order On Trial

Exhibits. ECF No. 115. On August 19, 2016, MW Builders filed its Post-Trial Proposed Findings

Of Fact And Memorandum Of Law (“Pl. Post Tr. Br.”). ECF No. 116.

On August 26, 2016, MW Builders filed a Motion To Enter PX 679, PX 680, and PX 681

into evidence. ECF No. 118. The August 26, 2016 Motion asserted that the Government waived

any objections to these exhibits at trial and failed to show how it would be prejudiced by their

admission. ECF No. 118 at 2–6.

On September 2, 2016, the Government filed Responses To MW Builders’ August 26,

2016 Motion (ECF No. 120) and MW Builders’ August 17, 2016 Motion To Enter Additional

Evidence (ECF No. 121). On September 9, 2016, MW Builders filed a Reply In Support Of The

August 17, 2016 Motion To Enter Additional Evidence. ECF No. 122.

On December 8, 2016, after receiving 80 days of extensions, the Government filed its

Proposed Findings Of Fact And Conclusions Of Law (“Gov’t Post Tr. Br.”). ECF No. 127.

24

On December 19, 2016, MW Builders filed a Motion For Leave To File Additional Post-

Trial Briefing in response to the Government’s December 8, 2016 Post-Trial Brief. ECF No. 128.

On December 21, 2016, the Government also filed a Response To MW Builders’ December 19,

2016 Motion. ECF No. 129. On the same date, the court granted MW Builders’ December 19,

2016 Motion. ECF No. 130. On January 30, 2017, MW Builders filed a Reply To The

Government’s December 8, 2016 Proposed Findings Of Fact And Conclusions Of Law (“Pl. Post

Tr. Reply Br.”). ECF No. 131.

On February 28, 2017, the Government filed a Motion For Leave To File A Reply Brief.

ECF No. 132. On March 21, 2017, the court issued an Order granting the Government’s February

28, 2017 Motion. ECF No. 133. On March 31, 2017, the Government filed a Reply To Plaintiff’s

January 30, 2017 Brief (“Gov’t Post Tr. Reply Br.”). ECF No. 134.

On June 9, 2017, the court issued an Order granting MW Builders’ August 17, 2016 Motion

To Enter Additional Evidence and MW Builders’ August 26, 2016 Motion For Leave To File

Plaintiff’s Exhibits PX 679–81. ECF No. 135. The June 9, 2017 Order also permitted the

Government to file a Rebuttal Report prepared by the Government’s expert, Mr. Stephen Weathers

(“Weathers Rebuttal”). ECF No. 135.

III. DISCUSSION.

A. Subject Matter Jurisdiction.

The United States Court of Federal Claims has jurisdiction, under the Tucker Act, to

adjudicate any claim arising under the Contract Disputes Act (“CDA”), 41 U.S.C. §§ 7101–7109,

and that has been submitted to a CO for a final decision. See 28 U.S.C. § 1491(a)(2) ( “The Court

of Federal Claims shall have jurisdiction to render judgment upon any claim by or against, or

dispute with, a contractor arising under section 7104(b)(1) of title 41 . . . on which a decision of

the contracting officer has been issued[.]”); see also 41 U.S.C. § 7104(b)(1) (“[I]n lieu of appealing

the decision of a [CO] . . . to an agency board, a contractor may bring an action directly on the

claim in the United States Court of Federal Claims.”).

The term “claim” is defined “as a written demand or written assertion by one of the

contracting parties seeking, as a matter of right, the payment of money in a sum certain, the

adjustment or interpretation of contract terms, or other relief arising under or relating to this

contract.” 48 C.F.R. § 52.233–1. Although a CDA claim need not be submitted in any particular

form or use any particular wording, it must contain “a clear and unequivocal statement that gives

the contracting officer adequate notice of the basis and amount of the claim.” Contract Cleaning

Maint., Inc. v. United States, 811 F.2d 586, 592 (Fed. Cir. 1987). The CDA also requires that the

claim indicate to the CO that the contractor is requesting a “final” decision. James M. Ellett

Constr. Co. v. United States, 93 F.3d 1537, 1543 (Fed. Cir. 1996).

25

A claim “arises under” the CDA if it is based on,

any express or implied contract . . . made by an executive agency for—(1) the

procurement of property, other than real property in being; (2) the procurement of

services; (3) the procurement of construction, alteration, repair, or maintenance of

real property; or (4) the disposal of personal property.

41 U.S.C. § 7102(a).

In this case, the December 27, 2013 Complaint includes three CDA claims: Count One

alleges that the Government breached the duties to cooperate and not hinder; Count Two alleges

that the Government caused unreasonable delay; and Count Three alleges that the CO improperly

classified the delay as non-compensable delay. Compl. ¶¶ 22–36. MW Builders requested the

same relief for all three Counts; i.e., $2,562,049.00 in damages and a 169-day extension of time.

Compl. ¶¶ a–d.

MW Builders’ August 19, 2016 Post-Trial Proposed Findings Of Fact And Memorandum

Of Law characterizes Count One as “primarily rest[ing] on the implied duty of good faith and fair

dealing.” Pl. Post Tr. Br. at 6. The Government responds that the court does not have jurisdiction

over any claim arising from a breach of the implied duty of good faith and fair dealing, because

“[t]here is no mention of good faith” in MW Builders’ May 15, 2013 Amended Certified Claim.

Gov’t Post Tr. Br. at 105 (citing England v. The Swanson Grp., Inc., 353 F.3d 1375, 1379 (Fed.

Cir. 2004) (“[J]urisdiction over an appeal of a contracting officer's decision is lacking unless the

contractor's claim is first presented to the contracting officer and that officer renders a final

decision on the claim.”). MW Builders replies that the duty not to hinder and the duty to cooperate

are both aspects of the implied duty of good faith and fair dealing and MW Builders’ May 15,

2013 Amended Certified Claim put the Government on notice that MW Builders alleged a

violation of that duty. Gov’t Post Tr. Br. at 32 n. 145. In addition, the May 15, 2013 Amended

Certified Claim stated that “[t]he failure of the Government to timely execute the Line Extension

[A]greement implicated the Government[’]s general duty to cooperate and to do nothing that

unreasonably hinders the contractor’s performance.” JX 89 at 2. Therefore, the court construes

Count One to allege a breach of the September 10, 2010 Contract and a violation of the duty of

good faith and fair dealing. Regarding the latter, the United States Court of Appeals for the Federal

Circuit has held that “[b]oth the duty not to hinder and the duty to cooperate are aspects of the

implied duty of good faith and fair dealing.” Metcalf Constr. Co. v. United States, 742 F.3d 984,

991 (Fed. Cir. 2014) (emphasis added) (quoting Precision Pine & Timber, Inc. v. United States,

596 F.3d 817, 820 n.1 (Fed. Cir. 2010)). It also has held that the United States Court of Federal

Claims may adjudicate a claim, if it arises from the “same operative facts” and requests “essentially

the same relief,” as a claim presented to the CO, even if the complaint at issue alleges a “slightly

different legal theory.” Scott Timber Co. v. United States, 333 F.3d 1358, 1365 (Fed. Cir. 2003).

In addition, “[t]his standard . . . does not require rigid adherence to the exact language or structure

of the original administrative CDA Claim.” Id. Therefore, the fact that MW Builders’ certified

claim did not use the words “good faith” does not divest the court of jurisdiction to adjudicate this

claim. See Transamerica Ins. v. United States, 973 F.2d 1572, 1578 (Fed. Cir. 1992) (“[C]ertain

magic words need not be used and . . . the intent of the claim governs.”).

26

For these reasons, the court has determined that it has jurisdiction to adjudicate the claims

alleged in Count One of the December 27, 2013 Complaint.

Count Two of the December 27, 2013 Complaint alleges that the Army Corps’ improper

actions caused an “unreasonable delay.” Compl. ¶ 28–32. The May 15, 2013 Amended Certified

Claim alleges that the Government “unreasonably hinder[ed] the contractor’s performance” and

that, “for reasons not totally known to MW Builders, the Line Extension Agreement went unsigned

for 6 months after MW Builders presented it to the Government for execution[.]” JX 89 at 2. As

such, Count Two of the Complaint arises from the “same operative facts” as those presented in the

May 15, 2013 Amended Certified Claim. See Scott Timber Co., 333 F.3d at 1365.

For these reasons, the court has also determined that it has jurisdiction to adjudicate the

claims alleged in Count Two of the December 27, 2013 Complaint.

Count Three alleges the CO’s decision improperly classified the cause of the delay. The

court considers this Count to be redundant. Therefore, the discussion of MW Builders’ claims will

concern only the legal injuries alleged in Counts One and Two.

B. Standing.

The United States Supreme Court has held that “the question of standing is whether the

litigant is entitled to have the court decide the merits of the dispute or of particular issues.”

Warth v. Seldin, 422 U.S. 490, 498 (1975). Standing must be determined “as of the commencement

of suit[.]” Rothe Dev. Corp. v. Dep’t of Def., 413 F.3d 1327, 1334 (Fed. Cir. 2005) (quoting

Lujan v. Defs. of Wildlife, 504 U.S. 555, 570 n.5, (1992)). “The party invoking federal jurisdiction

bears the burden of establishing [standing].” Lujan, 504 U.S. at 561. The United States Supreme

Court held in Friends of the Earth, Inc. v. Laidlaw Envtl. Servs., Inc., 528 U.S. 167 (2000) that, to

establish standing,

a plaintiff must show (1) it has suffered an “injury in fact” that is (a) concrete and

particularized and (b) actual or imminent, not conjectural or hypothetical; (2) the

injury is fairly traceable to the challenged action of the defendant; and (3) it is

likely, as opposed to merely speculative, that the injury will be redressed by a

favorable decision.

Id. at 180–81.

In addition, “[t]o have standing to sue the sovereign on a contract claim, a plaintiff must

be in privity of contract with the United States.” Anderson v. United States, 344 F.3d 1343, 1351

(Fed. Cir. 2003). In other words, the contract in issue must be between the plaintiff and the

Government. See Ransom v. United States, 900 F.2d 242, 244 (Fed. Cir. 1990) (“To maintain a

cause of action pursuant to the Tucker Act that is based on a contract, the contract must be between

the plaintiff and the [G]overnment.”).

It is undisputed that MW Builders was in privity of contract with the Government. Compl.

¶ 4 (“MW Builders and the Government, acting by and through [the Army Corps], are parties to a

firm, fixed price Contract No. W912 QR-10-C-0078 . . . for the construction of a new Army

Reserve Center in Las Vegas, Nevada[.]”). The December 27, 2013 Complaint also alleges that

27

MW Builders incurred financial injury that is concrete, particularized, and fairly traceable to the

Army Corps’ actions. And, any financial injury established by MW Builders can be addressed by

a monetary award.

For these reasons, the court has determined that MW Builders has standing to seek an

adjudication of the claims alleged in Count One and Count Two of the December 27, 2013

Complaint.

C. Plaintiff’s Claims Against The Government.

Count One of the December 27, 2013 Complaint alleges that the Army Corps violated the

duty of good faith and fair dealing and Count Two alleges that the Government caused an

unreasonable delay. Compl. ¶¶ 22–31. The gravamen of the December 27, 2013 Complaint is:

(1) the September 10, 2010 Contract required the Army Corps to sign the Line Extension

Agreement with NV Energy; (2) the Army Corps failed to secure easements, as required by the

September 10, 2010 Contract, and did not sign the Line Extension Agreement in a timely manner,

thereby breaching the September 10, 2010 Contract; and (3) the Army Corps eventually changed

its position, but nevertheless violated the duty of good faith and fair dealing in its discussions with

NV Energy that substantially delayed MW Builders’ work on the Project.

1. The September 10, 2010 Contract Required The United States Army

Corps Of Engineers To Sign The Line Extension Agreement With NV

Energy.

a. Plaintiff’s Argument.

The parties agree that the September 10, 2010 Contract was ambiguous as to which party

was required to sign the Line Extension Agreement with NV Energy. Pl. Post Tr. Br. at 7; see also

TR at 104 (Government’s counsel conceding that the September 10, 2010 Contract was ambiguous

as to the Line Extension Agreement). Therefore, the court must look to extrinsic evidence of the

parties’ intent as to which party was responsible for signing the Line Extension Agreement. Pl.

Post Tr. Br. at 7–8 (citing D’Andrea Bros. LLC v. United States, 96 Fed. Cl. 205, 219 (Fed. Cl.

2010)).

Prior to issuing the Solicitation, the Army Corps, Mason & Hanger, and the 63rd RSC,

began to work on the “Design Phase” of the Project. TR at 16, 27, 159 (Probst). During the Design

Phase, each of these entities refused to sign NV Energy’s Design Initiation Agreement. PX 45 at

GOV_17874–75. As a result, Mason & Hanger, sua sponte, amended Contract Drawing ES-002

to require the construction contractor to sign the Design Initiation Agreement. Pl. Post Tr. Br. at

31–32. Thereafter, in a May 6, 2009 memorandum, NV Energy, the utility, advised all concerned

that a signed Line Extension Agreement was required before permanent power would be provided

and nothing in Contract Drawing ES-002 changed that obligation. PX 4; see also DX 6 at 4 (5/6/09

Memorandum).

At trial, the witnesses agreed that Line Extension Agreements and similar types of contracts

typically are formed between utilities and the owners/end users of new construction, not between

utilities and the contractor. Pl. Post Tr. Br. at 8–12. For example, Robert Caskie, an Army Corps

28

employee, openly hostile to MW Builders’ claim, 22 confirmed this was a standard industry

practice. TR at 403–05 (Caskie). In addition, Mr. Kevin Finley, the Army Corps attorney who

negotiated the final Line Extension Agreement between the Army Corps and NV Energy, testified

that NV Energy’s “typical way of doing business” was for the end-user to sign the Line Extension

Agreement. TR 1077–78 (Finley). MW Builders’ conduct throughout the performance of the

contract also evidences its understanding, consistent with industry practice, that the September 10,

2010 Contract assigned responsibility for signing the Line Extension Agreement to the Army

Corps or Army Reserve. Pl. Post. Tr. Br. at 12–16. The Contract only required MW Builders to

“coordinate” with NV Energy, provide specific information about power needs, and sign the

Design Initiation Agreement. TR at 335–36 (Herriott). As such, when MW Builders received the

Line Extension Agreement, it “immediately” recognized that Agreement was the responsibility of

the end-user. TR at 355 (Herriott), 451 (Matson). For this reason, beginning in March 2012, MW

Builders first advised and then actively and continually complained that the Army Corps’ failure

to execute this Agreement interfered with and delayed progress on the Project. PX 528.

All of this evidence demonstrates that the parties did not intend the Contract to require MW

Builders to negotiate, sign, or be responsible for the Line Extension Agreement. Pl. Post Tr. Br.

at 37. MW Builders adds that the plain language of the Contract requires only that MW Builders:

(1) build the Project in such a way as to meet NV Energy’s Technical Requirements; and (2) sign

the Design Initiation Agreement. Pl. Post Tr. Br. at 40 (citing PX 422 at 3). There is no express

requirement that MW Builders sign a Line Extension Agreement. Pl. Post Tr. Br. at 40 (citing PX

422 at 3). Nor can the Contract reasonably be read as requiring MW Builders to sign the Line

Extension Agreement, because the term was for five years, i.e., 1,826 days; the term of the

construction Contract was only 660 days. Compare PX 449 ¶ 14.1 (“This [Line Extension]

Agreement . . . will continue for a term of five (5) years[.]”), with PX 52 at GOV_12823 (“The

Contract shall . . . complete [performance] within 660 calendar days[.]”).

In addition, the canon of expressio unius est exclusio alterius, i.e., “the expression of one

thing is the exclusion of the other,” is relevant, because the September 10, 2010 Contract required

that MW Builders sign a Design Initiation Agreement, but does not mention the Line Extension

Agreement. Pl. Post Tr. Br. at 46–47; see also Design & Prod., Inc. v. United States, 18 Cl. Ct.

168, 198–99 (Fed. Cl. 1989) (determining that a theater construction contract that expressly

required installation of seats implicitly did not require construction of interior walls, under the

doctrine of expressio unius est exclusio alterius). Likewise, it is well established that government

contracts that contain latent ambiguities are construed against the Government. See SIPCO Servs.

& Marine, Inc. v. United States, 41 Fed. Cl. 196, 215–16 (Fed. Cl. 1998) (determining that

contractor’s reasonable interpretation of latently ambiguous contract should be construed against

the Government). Therefore, MW Builders reasonably interpreted the latent ambiguity in the

22

Mr. Caskie explained that, when he worked as a CO, he regularly saw contractors file

“frivolous claims.” TR at 410–11 (Caskie). According to Mr. Caskie, MW Builders also had

multiple issues on the site, but chose to use the issues related to permanent power “to their

advantage to support their attempt to get back moneys” they lost on the project. TR at 418–19

(Caskie).

29

September 10, 2010 Contract concerning the Line Extension Agreement, not to require assumption

of that responsibility. Pl. Post Tr. Br. at 49.

Finally, the Government’s argument about the Line Extension Agreement is “riddled with

myopic inconsistency.” Pl. Post Tr. Br. at 16. Initially, the Army Corps decided the 63rd RSC

was required to sign the Agreement; after the 63rd RSC refused, the Army Corps attempted to

convince MW Builders to sign the document. Pl. Post Tr. Br. at 16. After MW Builders refused,

the Army Corps considered having multiple signers, before stepping up to the plate and signing

the Agreement. Pl Post Tr. Br. at 16. The fact that the Army Corps’ position shifted so many

times evidences that the Army Corps was well aware that MW Builders was not required to sign

the Line Extension Agreement. Pl. Post Tr. Br. at 19, 28–29. As MW Builders argued, “how a

party applies a contract during the performance period of a contract is evidence of how a party

interprets the contract,” and “how a party interprets a contract is good evidence of what that party

intended that contract to mean.” Pl. Post Tr. Br. at 28–29.

b. The Government’s Response.

The Government responds that MW Builders offered “no evidence” at trial that the

September 10, 2010 Contract required the Army Corps to sign the Line Extension Agreement.

Gov’t Post Tr. Br. at 108. The plain language did not impose any permanent power-related

obligations on the Government. Gov’t Post Tr. Br. at 108. In fact, Contract Drawing ES-002

expressly required MW Builders to provide a “complete and working electrical system” at the

Project, i.e., MW Builders needed to ensure that NV Energy would extend a line to the Project.

Gov’t Post Tr. Br. at 110.

The Government agrees that the September 10, 2010 Contract is ambiguous, but the

extrinsic evidence shows that the parties intended MW Builders to be responsible for the Line

Extension Agreement. Gov’t Post Tr. Br. at 110–11. This is so, because MW Builders was

required to provide a complete and working electrical system and doing so required the execution

of a Line Extension Agreement. Gov’t Post Tr. Br. at 111. And, multiple witnesses testified that

they had no knowledge about the Line Extension Agreement during the Design Phase. Gov’t Post

Tr. Br. at 111–12.

In addition, the course of performance supports a finding that MW Builders was required

to execute the Line Extension Agreement, because Contract Drawing ES-002 required MW

Builders to coordinate with NV Energy and, pursuant to that obligation, MW Builders signed the

Design Initiation and Design Approval Agreements with NV Energy. Gov’t Post Tr. Br. at 113.

For this reason, the Army Corps executed an “NV Energy Consultant/Third Party Contact

Authorization Form,” authorizing MW Builders to be NV Energy’s “sole contact” with respect to

the Project work. Gov’t Post Tr. Br. at 113; see also DX 30 (3/29/11 Contact Authorization Form).

Although MW Builders argues that Line Extension Agreements typically are signed by owners,

and not by construction contractors, that does not mean all such agreements need to be signed by

property owners. Gov’t Post Tr. Br. at 114.

Moreover, interpreting the Contract to require that the Government was responsible for

entering the Line Extension Agreement would render the September 10, 2010 Contract invalid

under the Anti-Deficiency Act, 31 U.S.C. § 1350. Gov’t Post Tr. Br. at 116. Under that Act, the

30

Government cannot lawfully enter into obligations for which there is no appropriation from

Congress. Since the Line Extension Agreement includes open-ended provisions regarding future

events, the Government could not sign the agreement without violating that Act. Gov’t Post Tr.

Br. at 116–17.

c. The Court’s Resolution.

i. The September 10, 2010 Contract Contains A Latent

Ambiguity Regarding Which Party Was Responsible For

Signing The Line Extension Agreement With NV

Energy.

Contract interpretation is a question of law. See NVT Techs., Inc. v. United States, 370

F.3d 1153, 1159 (Fed. Cir. 2004). In interpreting a contract, the court begins with the language of

the agreement. Id. (“Contract interpretation begins with the language of the agreement.”); see

also C. Sanchez & Son, Inc. v. United States, 6 F.3d 1539, 1543 (Fed. Cir. 1993) (“A contract is

read in accordance with its express terms and the plain meaning thereof.”). “When the contract’s

language is unambiguous it must be given its ‘plain and ordinary’ meaning and the court may not

look to extrinsic evidence to interpret its provision.” TEG-Paradigm Envtl. Inc. v. United States,

465 F.3d 1329, 1338 (Fed. Cir. 2006) (quoting Coast Fed. Bank, FSB v. United States, 323 F.3d

1035, 1040 (Fed. Cir. 2003)). If a contractual provision is susceptible to more than one reasonable

interpretation and is ambiguous, the court should consult extrinsic evidence to determine the

parties’ intent. See Edward R. Marden Corp. v. United States, 803 F.2d 701, 705 (Fed. Cir. 1986)

(“It is a generally accepted rule . . . that if a contract is reasonably susceptible of more than one

interpretation, it is ambiguous.”); see also Metro. Area Transit, Inc. v. Nicholson, 463 F.3d 1256,

1260 (Fed. Cir. 2006) (“Having found the contract ambiguous, we may appropriately look to

extrinsic evidence to aid in our interpretation of the contract.”).

When contract language is ambiguous, the court must determine whether “that ambiguity

was patent so as to impose a duty to seek clarification, or only latent.” Interwest Constr. v. Brown,

29 F.3d 611, 614 (Fed. Cir. 1994); see also Newsom v. United States, 676 F.2d 647, 649 (Ct. Cl.

1982) (“If a patent ambiguity is found in a contract, the contractor has a duty to inquire of the

contracting officer the true meaning of the contract before submitting a bid.”). Whether an

ambiguity is patent or latent is a question of law. See Grumman Data Sys. Corp. v. Dalton, 88

F.3d 990, 997 (Fed. Cir. 1996). When the ambiguity is patent, United States Court of Appeals for

the Federal Circuit precedent requires a departure from the ordinary rule of contra proferentem,

under which ambiguities in government contracts are construed against the drafter, i.e., the

Government. See Metric Constructors, Inc. v. NASA, 169 F.3d 747, 751 (Fed. Cir. 1999) (“The

doctrine of patent ambiguity is an exception to the general rule of contra proferentem which

construes an ambiguity against the drafter[.]”).

A patent ambiguity has been defined as “an obvious omission, inconsistency, or

discrepancy of significance.” Beacon Constr. Co. v. United States, 314 F.2d 501, 504 (Ct. Cl.

31

1963). 23 In contrast, a latent ambiguity is “neither glaring nor substantial nor patently obvious”

on the face of the contract document. See Grumman Data Sys. Corp., 88 F.3d at 997 (quoting

Cmty. Heating & Plumbing Co. v. Kelso, 987 F.2d 1575, 1579 (Fed. Cir. 1993) (explaining that

latent ambiguities arise in the “grey area between the point . . . at which a document requires more

exacting language and that at which additional detail will add nothing but worthless

surplusage[]”)). Therefore, a latent ambiguity usually is not apparent unless there is a dispute. See

Latent Ambiguity, BLACK’S LAW DICTIONARY (10th ed. 2014) (“An ambiguity that does not readily

appear in the language of a document, but instead arises from a collateral matter once the

document's terms are applied or executed”).

The reason that the September 10, 2010 Contract is ambiguous as to which party was

required to sign the Line Extension Agreement, is because the language of Contract Drawing ES-

002 is subject to more than one reasonable interpretation. As MW Builders argues, it is reasonable

to read Contract Drawing ES-002 as not requiring MW Builders to sign the Line Extension

Agreement, because there is no express instruction requiring MW Builders to sign it. TR at 104;

see also Gov’t Post Tr. Br. at 110 (“Contract Drawing ES-002 does not expressly say which party

was to execute the Line Extension Agreement; the drawing itself does not refer to a ‘Line

Extension Agreement.’ In that respect, it is ambiguous.”)

Contract Drawing ES-002 begins by stating that the “Contractor is responsible for

providing all electric infrastructure, equipment, and wiring for the Project unless specifically noted

as provided by NV Energy in the division of responsibility.” DX 14. But, this requirement speaks

only to physical construction requirements. The “Division of Responsibility (Power)” table that

accompanies the text lists a number of physical items to be constructed, e.g., a “transformer,” a

“transformer pad,” a “primary duct bank,” and a “secondary duct bank;” it does not discuss the

execution of documents. DX 14. Next, Contract Drawing ES-002 states that the “Contractor shall

contact NV Energy prior to bidding to verify that NV Energy will provide everything noted in the

table below.” DX 14. This clause also unambiguously concerns only the physical construction

requirements, reflected in the Division of Responsibility table. The sentence immediately

following, however, provides that “Contractor is responsible for providing a complete and working

electrical system, and shall include all costs in this bid.” DX 14. It is here that ambiguity arises,

because “complete and working electrical system” can be read as requiring more than just building

the physical items listed in the Division of Responsibility table. But, this ambiguity is “latent,”

because nothing “obviously [is] omitted” from the surrounding language and it is not inconsistent

with the surrounding sentences. “All costs,” reasonably could be interpreted as relating to all costs

incurred by MW Builders’ to facilitate the installation of electrical power, e.g., building the ducts

and paying the fee associated with the Design Initiation Agreement. In any event, the issue of

responsibility for signing the Line Extension Agreement did not arise until March 19, 2012, when

the Army Corps changed its view that the responsibility was the 63rd RSC’s and instead insisted

that MW Builders was responsible for signing this document. Compare JX 44 at 1 (3/13/12

conference call summary, wherein parties agreed that the Line Extension Agreement “will be

executed between NV Energy and 63D RSC such that staging of equipment can start on or about

19 March 2012”), with PX 60A (3/19/12 conference call summary, wherein Army Corps

23

The United States Court of Appeals for the Federal Circuit has held that United States

Court of Claims decisions issued prior to September 30, 1982, are binding precedent.

See S. Corp. v. United States, 690 F.2d 1368, 1369 (Fed. Cir. 1982).

32

announced intention to “consider an arrangement whereby . . . MW Builders may enter the

agreement with NV Energy”).

Contract Drawing ES-002 also provides that “The electrical distribution system shown on

the plans is the preliminary layout discussed with NV Energy during the project design and may

not match the final design required by NV Energy. Electrical manholes are not shown, but shall

be provided per NV Energy requirements. The electrical design must be coordinated with the

communications design provided[.]” DX 14 at 1. This language also does not require MW

Builders to enter into any contracts with NV Energy. Although the Government placed

considerable emphasis on the term “coordinate,” as the court observed during trial: “[c]oordinate

doesn’t mean to enter into a contract.” TR at 414. The term “coordinate,” in this context, means

that the electrical work had to be coordinated with the telecommunications work performed, in

accordance with the communications design. DX 14 at 1. 24

The next sentence appears to require MW Builders to enter into a contract with NV Energy:

“The contractor will be required to sign a Design Initiation Agreement with NV Energy and pay

fees as shown in the bid schedule.” DX 14 at 1. This language, however, refers to the fact that

MW Builders was responsible to sign that specific contract. The fact that there was no mention

of the Line Extension Agreement was not necessarily an “obvious omission.” See Beacon Constr.,

314 F.2d at 504. Instead, “when parties list specific items, without any more general or inclusive

term, they intend to exclude similar items, even though they are similar to those listed.” 2 E.

ALLEN FARNSWORTH, FARNSWORTH ON CONTRACTS § 7.11 at 293–94 (3d ed. 2004) (emphasis

added). In this case, Contract Drawing ES-002 required MW Builders only to sign one specific

type of agreement with NV Energy, but did not require MW Builders to enter into “contracts” with

NV Energy. Therefore, a reasonable construction contractor could read Contract Drawing ES-002

as requiring MW Builders only to sign the Design Initiation Agreement. To require MW Builders

to sign more than just the Design Initiation Agreement, the Army Corps could have required MW

Builders to “enter into any agreements necessary for the provision of permanent power” or

otherwise be required to “contract with” NV Energy to provide such power. Instead, Contract

Drawing ES-002 requires that “[t]he contractor shall contact NV Energy and determine the scope

and costs of this work prior to submitting a proposal. The contractor’s proposal shall include all

work and all costs associated with providing electrical power for the project.” DX 14 at 1

(emphasis added). This, however, was not a directive to MW Builders to sign the Line Extension

Agreement.

Contract Drawing ES-002 expressly requires MW Builders to provide “all electric

infrastructure, equipment, and wiring for the Project.” DX 14 at 2. Contract Drawing ES-002 also

requires MW Builders to provide “a complete and working electrical system.” DX 14 at 2. In

addition, Contract Drawing ES-002 requires the contractor to “contact” NV Energy and “obtain

written documentation of all transactions with NV Energy and provide them to the [Army Corps].”

DX 14 at 2. But, this contractual provision could be interpreted to require MW Builders to serve

as a middleman between the Army Corps and NV Energy. Contract Drawing ES-002 further

24

Contract Drawing ES-002 also included a “Division of Responsibility (Embarq),” that

governed the telecommunications aspect of the Project; telecommunications were to be provided

by Embarq, a utility company. DX 14 at 1.

33

provides that “The contractor is responsible for all guidelines and requirements within Nevada

Power Company’s [i.e., NV Energy’s] Electric Service Requirements, which can be found on their

website below.” DX 14 at 2. But, this sentence requires MW Builders to abide by the “Electrical

Service Requirements,” found at the website: a 432 page document consisting of technical

requirements related to construction, including, “how deep power lines need to be buried.” TR at

459 (Matson); see also PX 680. The term “Line Extension Agreement” does not appear anywhere

in this document. PX 680.

For these reasons, the court has determined that the September 10, 2010 Contract is

ambiguous as to which party was responsible for signing the Line Extension Agreement, but that

ambiguity was latent.

ii. Extrinsic Evidence Of Intent Demonstrates That The

United States Army Corps Of Engineers Was

Responsible For Signing The Line Extension Agreement

With NV Energy.

Because there was a latent ambiguity in the September 10, 2010 Contract as to which party

was required to sign the Line Extension Agreement, the rule of contra proferentem applies,

meaning that any ambiguity may be construed against the Army Corps. That rule, however, is one

“of last resort” and should be applied only if the ambiguity cannot be reconciled after “looking to

the circumstances attending the transaction and the circumstances under which [the parties]

executed the contract.” See Gardiner, Kamya & Assocs., P.C. v. Jackson, 467 F.3d 1348, 1352

(Fed. Cir. 2006) (quoting Chris Berg, Inc. v. United States, 455 F.2d 1037, 1044 (Ct. Cl. 1972)).

Therefore, “before resorting to the doctrine of contra proferentem, [the court] ‘may appropriately

look to extrinsic evidence’” to aid in the interpretation of the contract. See Gardiner, 467 F.3d at

1352 (quoting Metro. Area Transit, Inc., 463 F.3d at 1260).

As a threshold matter, the Government argues that there is “no evidence” that the Army

Corps was “specifically aware of the Line Extension Agreement prior to Contract award.” Gov’t

Post Tr. Br. at 110. The trial testimony about the pre-award “Design Phase” of the contract

supports this assertion: Army Corps and Mason & Hanger witnesses testified that, during the

Design Phase, they were concerned with the Design Initiation Agreement and not with the Line

Extension Agreement. TR at 16–17 (Probst); TR at 975–78 (Miller). In addition, although the

May 9, 2009 letter attached to the draft Design Initiation Agreement mentioned a “Line Extension

Agreement,” it was in the context of requiring the applicant for permanent power to “sign one or

more of the following agreements: Line Extension Agreement (LEA); Large Project Service

Agreement (LPS Agreement); Contribution in Aid of Construction Agreement (CIAC

Agreement); Non-Refundable Construction Agreement (NRCA).” DX 6 at 5. Consequently, it

appears that the Army Corps was not aware of the significance of the Line Extension Agreement

before awarding the September 10, 2010 Contract to MW Builders. But, any assertion that the

Army Corps was not aware of the Line Extension Agreement, and nevertheless intentionally

bargained for MW Builders to sign that Line Extension Agreement, is logically inconsistent. In

other words, the Army Corps cannot insist on a requirement, if it was not aware the requirement

existed. Recognizing the flaw in its reasoning, the Government next argues that since the

September 10, 2010 Contract did not expressly require the Army Corps to sign the Line Extension

Agreement, that obligation fell on MW Builders. Gov’t Post Tr. Br. at 108–09. This argument is

34

not supported by any evidence and ignores the fact that the Army Corps was aware of industry

practice. See, e.g., Jowett, Inc. v. United States, 234 F.3d 1365, 1369 (Fed. Cir. 2000) (explaining

that the court may look to industry practice where a “term with an accepted industry meaning [was]

omitted from the contract”). In this case, both NV Energy and Army Corps witnesses testified that

it was industry practice for building owners of new construction (“end users”) to execute Line

Extension Agreements. Ms. Risse, the NV Energy in-house attorney responsible for negotiating

Line Extension Agreements, 25 testified that NV Energy typically required “the ultimate end user

to be the counterparty,” because “there are ongoing obligation[s] that survive the termination of

the contract, and it’s a five year contract.” TR at 584 (Risse). Likewise, Mr. Finley, the Army

Corps attorney responsible for negotiating the Line Extension Agreement, testified that NV

Energy’s “typical way of doing business” was for the “end user” to enter into the Agreement, and

it was for that reason that NV Energy originally drafted the Line Extension Agreement for the 63rd

RSC to sign. TR at 1078 (Finley).

It is true that Ms. Creveling, another NV Energy employee, testified that NV Energy once

entered into a Line Extension Agreement with a contractor, instead of the Government end-user,

but this occurred on a “much smaller” project. 26 TR at 1013–14 (Creveling). And, the testimony

of other witnesses confirmed that situation was an exception, not the rule. TR at 343 (Herriott).

Moreover, Mr. Rial, a twenty-three-year veteran of NV Energy who now provides consulting

services for companies contracting with NV Energy, testified that he could not remember a

situation where a contractor signed the Line Extension Agreement. TR at 462, 469–70 (Rial).

This makes sense, because the Line Extension Agreement governs utility payments for at least a

five-year term—long after the construction contractor’s work is over. TR at 473 (Rial) (“A Line

Extension Agreement is the contract between the utility and the owner on how the money is to be

collected, the breakdown on the money, and then, also, how the moneys will be refunded[.]”).

The bottom line is the Army Corps could have contracted to depart from ordinary industry

practice by expressly placing the obligation to enter into a utility contract on the contractor. 27 But,

the Army Corps did not do so and apparently was not aware of the fact that NV Energy would

require a signed Line Extension Agreement from the Project’s end-user. Under these

circumstances, the court declines to supply an omitted term that departs from ordinary industry

practice, without evidence of pre-contract intent to include such a term. Instead, the court has

determined that the parties agreed to follow the typical industry practice with respect to the Line

25

Ms. Risse was responsible for “tak[ing] the lead” on contract negotiations during the ten

years she was employed by NV Energy. TR at 578–80. Ms. Risse negotiated the July 12, 2012

Line Extension Agreement executed between the Army Corps and NV Energy in this case. TR at

599–600 (Risse).

26

Ms. Creveling was unable to find any past projects of similar scope to this Project where

the Line Extension Agreement was executed by the contractor, instead of the end user. TR at 1014

(Creveling).

27

In fact, the Army Corps did seek to contract out of industry practice in a subsequent

solicitation, by including a provision that “[t]he Contractor must also sign the Line Extension

Agreement provided by Nevada Energy.” PX 274 at GOV_00049373.

35

Extension Agreement, placing that contractual obligation on the Army Corps in its capacity as

Project Manager and agent for the 63rd RSC by virtue of its signature on the September 10, 2010

Contract. 28

The parties’ performance also evidences that there was no agreement that MW Builders

was required to sign the Line Extension Agreement. Prior to any controversy regarding the Line

Extension Agreement, the Army Corps restricted MW Builders’ ability to negotiate contract

changes on behalf of the Army Corps, by modifying the terms of NV Energy’s Third Party

Authorization Form. Compare JX 14 at 11 (Unsigned and undated Third Party Authorization

Form draft, providing that MW Builders would have authority to “communicate and authorize all

change requests”), with PX 15 (3/29/11 Third Party Authorization Form, including Government

modifications, deleting “and authorize”). Other paperwork filled out by MW Builders identified

the Army Corps as the “Customer/Legal Owner” of the Project. PX 15 (3/29/11 Third Party

Authorization Form); PX 567 (3/29/11 Project Information Sheet). Similarly, on the April 27,

2011 Design Initiation Agreement, the Army Corps was identified as the “Applicant” for

permanent power. JX 19 at 10.

In addition, when NV Energy sent the Line Extension Agreement to MW Builders and the

Army Corps, all parties held a March 13, 2012 conference call together with the 63rd RSC and

concluded that the Agreement should be signed by the 63rd RSC. JX 44 at 1 (“The contract will

be executed between NV Energy and 63D RSC such that staging of equipment can start on or

about 19 March 2012.”). The fact that the Army Corps first took the Line Extension Agreement

to the 63rd RSC is inconsistent with the Army Corps’ later claim that MW Builders was

responsible for entering into the Line Extension Agreement. TR at 1077 (Finley). It was only

after the 63rd RSC refused to sign the Line Extension Agreement that the Army Corps took the

position that it was MW Builders’ responsibility. PX 501 at GOV_00005389 (Mr. Musgrave’s

email that: “I really don’t know why MW cannot sign the contract as they a[re] paying the fee and

the cost for service until it is acceptable.”). 29

In any event, the Army Corps changed its position as to which party was obligated to sign

the Line Extension Agreement and the CO never issued a directive ordering MW Builders to sign

it. PX 528; TR at 1132 (Ringstaff) (“[i]f the contractor feels that something is out of the scope

and [the Army Corps] feel[s] like it is in scope, we can direct them to do the work.”). And, as Mr.

Probst explained in his June 29, 2012 email, the CO refused to take this step, because doing so

“would expose the Government to a potential Request for Equitable Adjustment (REA) and a

contract ratification if an REA was upheld.” PX 294. In short, the Army Corps refused to order

MW Builders to sign the Line Extension Agreement, because it was cognizant that doing so would

entitle MW Builders to a Request for Equitable Adjustment. Therefore, the extrinsic evidence

28

The Army Corps was the owner of the property while the Project was under construction,

and was designated as “the construction agent/property holder until construction completion/

beneficial occupancy.” DX 37 at 30.

29

Mr. Musgrave subsequently advised that the Army Corps should “[m]ake them [i.e., MW

Builders] do it and let the chips fall where they may.” PX 27.

36

demonstrates that the parties did not intend for MW Builders to sign the Line Extension Agreement

with NV Energy, but instead agreed to follow the industry practice of having the end user sign.

Finally, the Government argues that the September 10, 2010 Contract could not have

placed responsibility for the Line Extension Agreement on the federal government, because it

would be unenforceable under the Anti-Deficiency Act. Gov’t Post Tr. Br. at 116 (citing 31 U.S.C.

§ 1350 (imposing criminal sanctions for knowingly spending funds in excess of those appropriated

by Congress)). It is true that certain sections of the Line Extension Agreement obligated payments

that were not in sum certain for future years and the Anti-Deficiency Act only allows spending

that is authorized by Congress. JX 72 at 5 (Draft Line Extension Agreement providing that

applicant’s refund could be reduced via an “Allowance True-Up”). The Army Corps, however,

removed those provisions prior to finally executing the July 23, 2012 Line Extension Agreement

with NV Energy. Compare JX 72 at 5 (6/20/12 draft Line Extension Agreement providing for a

potential reduction of an Applicant’s refund via an “Allowance True-Up”), with JX 94 at 125

(7/23/12 executed Line Extension Agreement intentionally omitting “Allowance True-Up”

provisions). Therefore, the fact that the draft Line Extension Agreement included language to

which Army Corps could not have agreed, is irrelevant since the September 10, 2010 Contract did

not include any terms contrary to the Anti-Deficiency Act.

For these reasons, the court has determined that the Army Corps was obligated to sign the

Line Extension Agreement and breached the September 10, 2010 Contract by failing to do so in a

timely manner.

2. The United States Army Corps Of Engineers Violated The Duty Of

Good Faith And Fair Dealing Causing An Unreasonable Delay To The

Project.

a. Plaintiff’s Argument.

MW Builders argues that the duties to cooperate and not to hinder are two “sub-duties” of

the broader duty of good faith and fair dealing. Pl. Post. Tr. Br. at 107. In this case, MW Builders

had a reasonable expectation that the Army Corps would not hinder or interfere with MW Builders’

Project Schedule. Pl. Post. Tr. Br. at 108.

The Army Corps first unreasonably failed to secure necessary easements, despite

representing in the September 10, 2010 Contract that offsite property rights would be available to

MW Builders so permanent power could be connected to the Project site. Pl. Post Tr. Br. at 111.

In addition, the Contract Drawings provided by the Army Corps indicated that MW Builders would

be able to build offsite ductbanks at the intersection of Arville Street and Ray Way (the “Arville

Hub”), and then work with NV Energy to “pull” a utility wire to the Project site. Pl. Post Tr. Br.

at 61 (citing PX 267). Although the Contract Drawings suggested that MW Builders would be

able to perform construction work in this area, MW Builders subsequently learned that the Army

Corps failed to secure the necessary easements for MW Builders to construct the necessary offsite

ductbanks. Pl. Post Tr. Br. at 62 (citing JX 26). MW Builders raised this issue with the Army

Corps in July 2011, but the Army Corps did not resolve the issue until March 2012. Pl. Post Tr.

Br. at 67. In fact, the Army Corps recognized that failure to secure the easements was a “big goof”

and, under ordinary circumstances, the Army Corps would work to secure the necessary easements

37

before opening up a project to bidding. Pl. Post Tr. Br. at 63 (citing PX 239); see also TR at 378–

79 (Caskie) (“I wouldn’t have let the bids be open if I knew there [were] real estate issues[.]”).

Therefore, the Army Corps acted unreasonably when it took months to resolve the easements issue,

despite knowing of its critical importance. Pl. Post Tr. Br. at 111.

NV Energy also needed to inspect MW Builders’ ductbank work before pulling a wire to

connect the Project site to the utility grid. Pl. Post Tr. Br. at 65 (citing PX 453, JX 26). This

required permission from the Army Corps so NV Energy provided both with an “Access To

Equipment Agreement” in September 2011. Pl. Post Tr. Br. at 67 (citing PX 18). But, the Army

Corps decided that it could not agree to several provisions in the Access To Equipment Agreement.

PX 18 (2/28/12 email regarding Access To Equipment Agreement). The Army Corps, however,

did not inform MW Builders and NV Energy of its disagreement with those provisions until

February 28, 2012, i.e., several months after first receiving that Agreement. PX 18. Although

none of this delay directly affected MW Builders’ critical path, the Army Corps’ failure to secure

the necessary easements and extended negotiations about NV Energy’s Access To Equipment

Agreement narrowed the window within which a Line Extension Agreement could be executed,

without pushing tasks onto the critical path that would delay the Project. Pl. Post Tr. Br. at 70.

Consequently, when the Army Corps later failed to sign the Line Extension Agreement in a timely

manner, the resulting delay had a considerably greater impact on the Project’s completion date

than it otherwise would have had. Pl. Post Tr. Br. at 70.

Most importantly, during the March 13, 2012 conference call, when the Line Extension

Agreement was first discussed with NV Energy and MW Builders present, the Army Corps stated

that the 63rd RSC would sign the Line Extension Agreement. Pl. Post Tr. Br. at 74 (citing JX 44).

But, the Army Corps changed its position and later insisted that MW Builders was responsible for

signing the Line Extension Agreement. Pl. Post Tr. Br. at 76–77 (citing PX 501, at GOV_5390).

The Army Corps’ bad faith is also evidenced by the fact that on March 19, 2012, the Army Corps

purposely excluded MW Builders from a second conference call with NV Energy, when it

explained the Army Corps intended to make MW Builders sign the Line Extension Agreement.

Pl. Post Tr. Br. at 77 (citing TR at 85 (Probst)).

MW Builders, however, was completely candid as it informed the Army Corps on

numerous occasions that it would not sign the Line Extension Agreement. Pl. Post Tr. Br. at 78–

84 (citing TR at 182 (Musgrave), 198 (Probst); PX 528; JX 58). Nevertheless, on April 26, 2012,

the Army Corps made misleading and confusing statements to NV Energy, to make it appear that

MW Builders would be the counterparty to the Line Extension Agreement. Pl. Post Tr. Br. at 85

(citing JX 61). And so, negotiations dragged on. Pl. Post Tr. Br. at 85–86. It was not until June

21, 2012, that Ms. Risse, NV Energy’s Representative, was clearly informed that the Army Corps,

instead of MW Builders, would sign the Line Extension Agreement. Pl. Post Tr. Br. at 89 (citing

TR at 597 (Risse)).

The “contemporaneous project schedules [also] establish the duration and causation” of the

“critical path” delay caused by the Army Corps’ violation of the duty of good faith and fair dealing.

Pl. Post Tr. Br. at 93. MW Builders began work by creating an initial “baseline schedule.” TR at

509–10 (Stone). As the Project progressed, MW Builders’ schedule was updated on a monthly

basis and was reviewed by Management Solutions, the third party scheduling consultant retained

by the Army Corps. TR at 512 (Stone). The February 2012 updated critical path schedule showed

38

that the Project would be completed 27 days ahead of schedule. PX 336. By the March 2012

Update, however, the lack of permanent power caused a delay and the updated schedule showed a

completion date that was ten days late. TR at 517–18 (Stone). Nevertheless, the Army Corps

continued to decline to sign the Line Extension Agreement and MW Builders’ Schedule Updates

continued to show delay. Pl. Post Tr. Br. at 96–97. By the April 2012 Update, the anticipated

delay reached 52 days and, by May 2012, the delay increased to 86 days. Compare PX 338 at 1

(April 2012 Update), with PX 339 at 2 (May 2012 Update). Management Solutions’ review of the

April 2012 Schedule Update identified several changes and the Army Corps was asked whether it

agreed “with the changes such as the change in original duration of Nevada energy-

wire/transformer/es, added activities, and logic changes?” 30 PX 348 at 3. By the June 2012

Update, the delay was 121 days, because various work activities required permanent power,

including air conditioning. PX 340 at 1 (June 2012 Update). Subsequently, the Army Corps

approved those changes to the underlying logic. PX 348; TR at 1063–64. Although the

Government’s damages expert, Mr. Weathers, did not agree with that decision (CX 2), the fact is

that the Army Corps approved them. Pl. Post Tr. Br. at 99. By the July 2012 Update, the delay

increased to 140 days, because there was “little available work left within [the Training Building]

due to lack of permanent power and as a result many subcontractors have demobilized.” PX 341

at 1–2 (July 2012 Update). By the October 2012 Update, the delay increased to 170 calendar days.

PX 344 at 1 (October 2012 Update).

MW Builders’ scheduling expert, Mr. Miltonberger, also estimated that the Project was

delayed a total of 413 days that could be divided into three “windows” or time periods.

Miltonberger Direct at 3–5. “Window 2” concerns 170 days of delay and is the subject of this

case. 31 Of that amount, Mr. Miltonberger opines that 140 days resulted from the Army Corps’

delay in signing the Line Extension Agreement. Miltonberger Direct at 4.

b. The Government’s Response.

The Government responds that MW Builders did not meet the “heightened burden” to

establish a breach of the implied covenant of good faith and fair dealing by evidencing “specific

intent to injure.” Gov’t Post Tr. Br. at 100, 105 (citing Austin v. United States, 118 Fed. Cl. 776,

790 (Fed. Cl. 2014)). Government officials are presumed to act in good faith. Gov’t Post Tr. Br.

at 100–01 (citing Schism v. United States, 316 F.3d 1259, 1302 (Fed. Cir. 2002)). Specifically,

there is no evidence that the Army Corps acted with animus towards MW Builders or otherwise

intentionally targeted MW Builders and Mr. Probst and Mr. Finley acted in good faith. Gov’t Post

30

Management Solutions regularly approved of MW Builders’ subsequent Schedule

Updates and represented to the Army Corps that the “level of detail in the schedule is admirable”

(PX 350), and MW Builders’ schedules were “well managed . . . and contain[ed] adequate detail

to manage the project.” PX 351. These statements undercut Mr. Weathers’ testimony that MW

Builders’ schedule was not sufficiently detailed. Pl. Post Tr. Br. at 99.

31

Window 1 concerns 20 days of Critical Path Delay and was resolved by a Contract

Modification executed between MW Builders and the Army Corps. Miltonberger Direct at 3.

Window 3 concerns 223 days of Critical Path Delay, but also was resolved by a Contract

Modification executed between MW Builders and the Army Corps. Miltonberger Direct at 3.

39

Tr. Br. at 105–06. Therefore, the Army Corps did not unreasonably delay negotiations surrounding

the Line Extension Agreement, but acted “reasonably and diligently,” and in good faith.

Gov’t Post Tr. Br. at 117–18.

It was NV Energy, a third party over which the Army Corps had no control, that insisted

on provisions that the Army Corps could not agree to by signing the Line Extension Agreement.

Gov’t Post Tr. Br. at 118. The Army Corps’ attorney, Mr. Finley, worked diligently with NV

Energy’s attorney, Ms. Risse, to resolve the Army Corps’ legitimate concerns regarding the Anti-

Deficiency Act, venue, and the law that would govern any future disputes. Gov’t Post Tr. Br. at

32 (citing DX 143). Although MW Builders argues that Ms. Risse’s confusion was

“understandable,” because Mr. Finley appeared to be negotiating on behalf of three separate parties

(MW Builders, the 63rd RSC, and the Army Corps), she should have been tipped off by the

“telling” fact that MW Builders’ lawyers were not included in the email conversation. Gov’t Post

Tr. Br. at 120. The Army Corps had “no incentive” to cause confusion as to which party was to

sign the Line Extension Agreement. Gov’t Post Tr. Br. at 121. In any event, the Army Corps and

NV Energy were able to resolve their dispute “very quickly,” after Ms. Risse’s confusion was

resolved. Gov’t Post Tr. Br. at 121.

To establish a breach of the duty to cooperate, MW Builders must establish that the delay

was the fault of the Army Corps. Gov’t Post Tr. Br. at 99. In this case, MW Builders assumed the

risk of any delay caused by problems with NV Energy, because MW Builders contracted to provide

“a complete and working electrical system.” Gov’t Post Tr. Br. at 107 (citing DX 14 at 1).

Therefore, MW Builders should be barred from recovery, because it caused the delay. Gov’t Post

Tr. Br. at 121. This is so, because Contract Drawing ES-002 obligated MW Builders to contact

NV Energy about its permanent power requirements, but MW Builders did not inform the Army

Corps about the Line Extension Agreement until March 14, 2012. Gov’t Post Tr. Br. at 122.

In addition, “to properly demonstrate delay[,] . . . the [Critical Path Method] schedule must

be kept current to reflect any delays as they occur.” Gov’t Post Tr. Br. at 123 (quoting PCL Constr.

Servs., Inc. v. United States, 47 Fed. Cl. 745, 801 (Fed. Cl. 2000). In this case, MW Builders’

schedules did not reflect a potential permanent power delay until March 28, 2012. Gov’t Post Tr.

Br. at 124 (citing DX 72 at 4). “This assumption was based upon ignorance and nothing more.”

Gov’t Post Tr. Br. at 124. At trial, MW Builders’ Scheduling Engineer, Mr. Stone, testified that

he could have incorporated the logic changes made in the March 2012 Schedule Update, if he had

been aware of the permanent power issue. Gov’t Post Tr. Br. at 124 (citing TR at 565 (Stone)).

Therefore, if “MW Builders had managed the project in a diligent manner, it would have identified

the Line Extension Agreement as a potential problem in 2011, if not sooner.” Gov’t Post Tr. Br.

at 124. Mr. Rial, the consultant employed by MW Builders to assist with NV Energy, testified

that he informed MW Builders about the Line Extension Agreement in July 2011. Gov’t Post Tr.

Br. at 124–25; see also TR at 484–85 (Rial). Therefore, to avoid a critical path delay, the Line

Extension Agreement needed to be signed at least “nine weeks before” May 3, 2012, i.e., by March

1, 2012. Gov’t Post Tr. Br. at 125; see also TR at 892 (Miltonberger). But, the Army Corps did

not receive the Line Extension Agreement until March 14, 2012. Gov’t Post Tr. Br. at 125.

As for MW Builders’ arguments about easement delays and how they “pushed the Line

Extension Agreement onto the critical path,” they “are based solely on speculation and not on any

evidence.” Gov’t Post Tr. Br. at 127–28. In any event, the easement delays were not solely caused

40

by the Government. Nor was all of the delay the fault of the Army Corps. Gov’t Post Tr. Br. at

127–28. Since any such delay was “concurrent or intertwined,” MW Builders did not meet its

burden of separating the delays it caused from those that may have been caused by the Army Corps.

Gov’t Post Tr. Br. at 129 (citing Blinderman Constr. v. United Sates, 695 F.2d 552, 559 (Fed. Cir.

1982). Therefore, the court should dismiss MW Builders’ claim. Gov’t Post Tr. Br. at 129.

c. Plaintiff’s Reply.

MW Builders replies that Metcalf Construction Co. v. United States, 742 F.3d 984 (Fed.

Cir. 2014), does not require a plaintiff to show bad faith or targeting by a federal government

official to establish a breach of the implied duty of cooperation, which is part of the duty of good

faith and fair dealing. Pl. Post Tr. Reply Br. at 29 (citing Metcalf, 742 F.3d at 994). Instead, the

relevant standard is whether the Government willfully or negligently interfered with a contractor’s

performance and reasonable expectations. Pl. Post Tr. Reply Br. at 32 (citing Malone v. United

States, 849 F.2d 1441, 1445 (Fed. Cir. 1988) (“[S]ubterfuges and evasions violate the obligation

of good faith, as does lack of diligence and interference with or failure to cooperate in the other

party’s performance”) (internal citations and quotations omitted)). Therefore, the Government’s

argument that MW Builders needs to establish that it was intentionally “targeted” by the Army

Corps is not correct as a matter of law. Pl. Post Tr. Reply Br. at 30.

With respect to easements, MW Builders replies that the Army Corps’ delay in securing

the easements consumed Project “float” time, i.e., the time between when an activity is first

scheduled to occur and the last date the activity can be completed. Pl. Post Tr. Reply Br. at 34.

As the Government’s expert testified, securing the easements was a “predecessor activity” to the

Line Extension Agreement. TR at 1312 (Weathers). Therefore, the Army Corps’ delay in securing

those easements lengthened the delay initially caused by the Army Corps. Pl. Reply at 36–37.

With respect to the Government’s argument that any delay connected to the Line Extension

Agreement was attributed to Ms. Risse’s “confusion,” it was the Army Corps that misled and

misrepresented that MW Builders was going to sign the Line Extension Agreement when it cut out

MW Builders from participating in telephone conferences with Ms. Risse. Pl. Reply at 42; TR at

85 (Probst).

With respect to MW Builders’ schedules, they were accurate and described as “well

managed and sufficiently detailed” by Management Solutions, the consultant hired by the Army

Corps, in contrast with the Government’s retained scheduling expert, Mr. Weathers, who opined

that the schedules lacked sufficient detail. “[C]ontemporaneous project records[, however,] are

more credible than the opinions of witnesses who contradict those records years later during trial

testimony.” Pl. Reply at 46.

With respect to the Government’s contention that MW Builders should have advised the

Army Corps of the Line Extension Agreement earlier, there is no evidence that doing so would

have changed anything. Pl. Reply at 47. As the Government’s expert conceded, securing the

easements was a predicate condition that had to be accomplished before the Line Extension

Agreement could be signed. Pl. Reply at 47 (citing TR at 1312 (Weathers)).

41

Finally, the Government’s assertion that MW Builders failed to apportion delay is “flatly

wrong,” because MW Builders’ expert performed an apportionment analysis and concluded that

140 days of delay could be attributed to a single cause, i.e., the Army Corps’ failure to execute the

Line Extension Agreement in a timely fashion. Pl. Reply at 44 (citing Miltonberger Direct at 11–

18).

d. The Government’s Sur-Reply.

The Government concedes that its argument that evidence of “bad faith” was required to

establish a breach of the duty to cooperate was “too broad,” but there is no evidence that the Army

Corps breached the implied duty of good faith and fair dealing, because it worked hard to resolve

the issue when it became aware of the Line Extension Agreement in March 2012. Gov’t Reply at

8–9. It was MW Builders’ fault that the Government did not learn about that agreement until

March 2012. Gov’t Reply at 9. As such, the delay was caused by NV Energy and MW Builders,

not the Army Corps. Gov’t Reply at 10. In addition, no critical path delay was caused by the

easement issue. Gov’t Reply at 9.

e. The Court’s Resolution.

i. The United States Army Corps Of Engineers Violated

The Duty Of Good Faith And Fair Dealing.

The duty of good faith and fair dealing includes “the duty not to interfere with the other

party’s performance and not to act so as to destroy the reasonable expectations of the other party

regarding the fruits of the contract.” Centex Corp. v. United States, 395 F.3d 1283, 1304 (Fed.

Cir. 2005). “Both the duty not to hinder and the duty to cooperate are aspects of the implied duty

of good faith and fair dealing.” Metcalf, 742 F.3d at 991 (quoting Precision Pine & Timber v.

United States, 596 F.3d 817, 820 n.1 (Fed. Cir. 2010)). Although it “is rarely possible to anticipate

in contract language every possible action or omission by a party that undermines the bargain,”

the terms of the contract and the “nature of that bargain” inform the reasonable expectations of the

parties. See Metcalf, 742 F.3d at 991. Therefore, “the implied duty of good faith and fair dealing

cannot . . . create duties inconsistent with the contract’s provisions.” Precision Pine, 596 F.3d at

831.

The United States Court of Appeals for the Federal Circuit has held that the Government

may violate the implied duty of good faith and fair dealing without “specifically targeting,” but

nevertheless deprive the contractor of the fruits of the contract. See Metcalf, 742 F.3d at 994. In

addition, the Government may violate that duty when its acts or omissions are “inconsistent with

the contract’s purpose and deprive the other party of the contemplated value.” Id. at 991. For

example, an unreasonable “lack of diligence” may violate the implied duty of good faith and fair

dealing. Id. at 991 (quoting Malone, 849 F.2d at 1445). A party also may violate the duty of good

faith and fair dealing by engaging in “subterfuges and evasions.” See Malone, 849 F.2d at 1445;

see also RESTATEMENT (SECOND) OF CONTRACTS § 205 cmt. d (AM. LAW INST. 1981)

(“Subterfuges and evasions violate the obligation of good faith in performance even though the

actor believes his conduct to be justified.”).

42

The Line Extension Agreement was first discussed during a March 13, 2012 conference

call that included NV Energy and MW Builders, wherein the participants agreed that the “contract

will be executed between NV Energy and 63D RSC.” JX 44 at 1. It was only after the 63rd RSC

refused to sign the Line Extension Agreement on March 14, 2012, that the Army Corps tried to

obtain MW Builders’ signature, at the suggestion of Mr. Musgrave, an Army Corps Contracting

Officer’s Representative. PX 501 at GOV_00005389. On March 19, 2012, the Army Corps

convened a conference call with NV Energy, in part “to determine a strategy so that MW Builders

would sign the Line Extension Agreement.” TR at 85 (Probst). But, the Army Corps excluded

MW Builders from that telephone conference. TR at 84–85 (Probst). Ms. Risse, NV Energy’s

attorney, present during the March 19, 2012 telephone conference, testified that NV Energy

“wouldn’t have been asked to consider” having MW Builders sign the Line Extension Agreement,

“if MW Builders wasn’t on board with it.” TR at 590–91 (Risse).

On March 21, 2012, MW Builders informed the Army Corps that it would not sign the Line

Extension Agreement, without a directive from the CO. PX 528. Nevertheless, the Army Corps

proceeded to convene a second telephone conference with NV Energy that again excluded MW

Builders. PX 60C. After this second call, NV Energy’s attorney, Ms. Risse, “thought [her] work

was done[,] unless MW Builders came back and had concerns that we needed to discuss and

change the extension agreement if necessary.” TR at 609 (Risse). The purpose of the Army Corps’

conduct was to convince NV Energy that MW Builders would sign the Line Extension Agreement.

At the same time the Army Corps made these representations to NV Energy, it knew that MW

Builders would not sign the Line Extension Agreement, without a letter from the CO directing

them to do so.32 PX 27 (3/22/12 email stating that MW Builders “will not move forward without

[a] directive from the [Army] Corps”). And, on April 6, 2012, MW Builders sent a letter notifying

the Army Corps that the Project could potentially be delayed, because “the Line Extension

Agreement between the Government and Nevada Energy [was] not yet in place, subsequently

delaying permanent power installation and startup.” JX 58.

On April 26, 2012, the Army Corps first contacted Ms. Risse to begin negotiating the Line

Extension Agreement, because the critical path was being affected. JX 61 at 1–2. Ms. Risse

testified that she found the April 26, 2012 email confusing and “strange,” because it appeared to

suggest that MW Builders was going to sign the Line Extension Agreement (as suggested during

the conference calls in March), but also listed various complaints that the Army Corps and 63rd

RSC had with the Line Extension Agreement. TR at 608–09 (Risse). Moreover, Mr. Finley

appeared to be negotiating terms on the behalf of MW Builders, who was not his client. TR at

608–09 (Risse).

By May 23, 2012, confusion about who was to sign the Agreement continued and was

causing delay on the Project. JX 68. On June 15, 2012, Ms. Risse sent an email to Mr. Finley,

stating that “NV Energy has already compromised by agreeing that the [G]overnment’s contractor

can be the applicant instead of the [G]overnment.” DX 143 at 2. Three days later, Mr. Finley

responded that “What I have been trying to draft is an agreement between the [Army] Corps and

NV Energy. We seem to be working toward different goals.” DX 143 at 1. On June 21, 2012,

32

The CO did not do so, because it would potentially expose the Army Corps to a Request

for Equitable Adjustment. PX 294.

43

Mr. Finley and Ms. Risse had a telephone conference with MW Builders’ attorney, Mr. Mitts,

where the Army Corps agreed that MW Builders was not responsible for signing the Line

Extension Agreement. JX 75 at 1. Thereafter, “drafts were exchanged quickly” and the Army

Corps signed the Line Extension Agreement on July 12, 2012. TR at 626 (Risse); see also

Jt. Stip. ¶ 25.

Regarding the Government attempt to fault Ms. Risse for the uncertainty about the Line

Extension Agreement, no such evidence was proffered to excuse the Army Corps’ conduct of not

being candid with NV Energy about MW Builders’ refusal to sign the Line Extension

Agreement—and to exclude MW Builders’ lawyers from those discussions. The fact that the Line

Extension Agreement issue ultimately was quickly resolved evidences that it was the Army Corps

that was responsible for the uncertainty and delay caused by the Army Corps’ failure to sign the

Line Extension Agreement in a timely manner.

Likewise, the Government’s attempt to shift the blame for lack of the permanent power—

citing the fact that MW Builders did not raise the issue of the Line Extension Agreement until

March 2012, when it was “too late[:] only weeks before permanent power was due”—belies the

record. (Gov’t Post Tr. Br. at 123). Securing easements was a necessary predicate to providing

permanent power to the Project site, that was not addressed by the Army Corps until February 6,

2012. PX 4 (the “[P]roject will not be released for construction scheduling until after all of the

necessary property rights have been provided to NV Energy.”); Jt. Stip. ¶ 21. In fact, the Army

Corps did not even provide an “access letter” to NV Energy until March 16, 2012. Jt. Stip. ¶ 23.

Based on this record, the Army Corps’ conduct regarding the Line Extension Agreement

implicated the duty to not interfere with the other party’s performance, the duty not to hinder, and

the duty to cooperate. Although the September 10, 2010 Contract assigned some electric utility

obligations to MW Builders, no specific party was directed to sign the Line Extension Agreement,

because all the parties were aware of industry practice. Therefore, MW Builders entered into the

bargain with a “reasonable expectation” that the Army Corps was obligated to make arrangements

with respect to the Line Extension Agreement. See Centex Corp., 395 F.3d at 1304 (“The covenant

of good faith and fair dealing . . . include[s] the duty not to interfere with the other party’s

performance and not to act so as to destroy the reasonable expectations of the other party regarding

the fruits of the contract.”). The Army Corps, however, attempted to impose that obligation on

MW Builders by misleading, dilatory, and bad faith conduct. See Metcalf, 742 F.3d at 991.

The Government is correct that the United States Court of Appeals for the Federal Circuit

has held that a Government agency did not violate the duty of good faith and fair dealing with

respect to the contract when it failed to cooperate with a separate, unrelated third party. See

Precision Pine, 697 F.3d at 830. In that case, the United States Forest Service failed to cooperate

with the Fish and Wildlife Service with respect to consultations required under the Endangered

Species Act (“ESA”). Id. But, the “plain language” of the Precision Pine contract stated that its

“provisions [could] be modified, suspended, or even canceled to comply with the ESA.” Id. at

830–31. The September 10, 2010 Contract contains no such reservation. Nevertheless, the Army

Corps represented and continued to represent to NV Energy that MW Builders could or would sign

the Line Extension Agreement, although the Army Corps knew that was not the case. This

evidences that the Army Corps acted in bad faith.

44

For these reasons, the court has determined that the Army Corps violated the duty of good

faith and fair dealing. Metcalf, 742 F.3d at 991.

ii. The United States Army Corps Of Engineers’ Conduct

Caused An Unreasonable Delay.

The United States Court of Appeals for the Federal Circuit also has held that a contactor

may recover for an unreasonable delay, if the Government is “the sole proximate cause of the

contractor’s additional loss, and the contractor would not have been delayed for any other reason

during that period.” Triax-Pacific v. Stone, 958 F.2d 351, 354 (Fed. Cir. 1992); see also Essex

Electro Eng’rs, Inc. v. Danzig, 224 F.3d 1283, 1295 (Fed. Cir. 2000) (“A contractor seeking to

prove the government’s liability for a delay must establish the extent of the delay, the contractor’s

harm resulting from the delay, and the causal link between the government’s wrongful act and the

delay.”). In addition, any Government-caused delay must be “unnecessary or unreasonable in

duration.” P.R. Burke Corp. v. United States, 277 F.3d 1346, 1360 (Fed. Cir. 2002). As a result,

the contractor may not recover, if there is a concurrent delay caused by the contractor or some

other third party. See Triax-Pacific, 958 F.2d at 354 (holding that a contractor could not recover

where a delay was caused, in part, by the contractor’s failure to timely complete prior projects).

But, a contractor may recover when other factors contribute to the delay, provided that there is

proof of a “clear apportionment of the delay and the expense attributable to each party.” T. Brown

Constructors, Inc. v. Pena, 132 F.3d 724, 734 (Fed. Cir. 1997) (quoting Coath & Goss, Inc. v.

United States, 101 Ct. Cl. 702, 714–15 (Ct. Cl. 1944)).

In this case, the Government argues that MW Builders is barred from recovery, because it

failed to apportion the delay caused by the Army’s conduct with respect to the Line Extension

Agreement. Gov’t Reply at 7–8. The trial record, however, reflects that the delay was solely

caused by the Army Corps. As such, MW Builders was not required to provide a “clear

apportionment of the delay and the expense attributable to each party,” because there was only one

party at fault: the Army Corps. See T. Brown, 132 F.3d at 734. 33

The Government next argues that MW Builders’ contemporaneous Critical Path Method

schedules are not accurate and do not support a finding of unreasonable delay. The United States

Court of Federal Claims determined in Blinderman Construction Co. v. United States, 39 Fed. Cl.

529 (Fed. Cl. 1997), aff’d 178 F.3d 1307 (Fed. Cir. 1998), that a contractor may not recover

damages, even though it established that the Government caused an unreasonable delay, where the

contractor did not demonstrate that the delay affected the critical path and the schedules submitted

were not updated in a timely manner, to reflect the delay. Id. at 584–85.

MW Builders’ contemporaneous schedule updates, however, evidence that the permanent

power delay affected the critical path and that delay continued to accumulate:

33

In T. Brown, our appellate court observed that where multiple causes of a delay exist,

apportionment of the delay is required, if either party is to recover. See 132 F.3d at 734. But,

apportionment is not required where the delay results from a single cause. Id.

45

• The February 22, 2012 Schedule Update was the last schedule update issued before

the parties convened a telephone conference to discuss the Line Extension

Agreement. PX 336 at 1. In that update, MW Builders projected a Project

completion date of September 19, 2012. PX 336 at 1.

• The March 30, 2012 Schedule Update was issued after MW Builders and the Army

Corps disagreed about which party was responsible for signing the Line Extension

Agreement. PX 337 at 1. In that schedule update, MW Builders advised that “[w]e

are beginning to forecast a delay [in the critical path] to the overall completion date

of the project due to a lack of permanent power,” particularly because air

conditioning was required in the Training Building to conduct temperature and

moisture sensitive activities, including the installation of Acoustic Ceiling Tiles and

Vinyl Composition Tiles. PX 337 at 1–2. Therefore, permanent power or

generator-provided temporary power, 34 was needed. PX 337 at 2. For the project

not to be delayed, the schedule reflected that permanent power was required by

May 4, 2012. PX 337 at 2.

• The April 26, 2012 Schedule Update reflected that MW Builders needed air

conditioning by May 4, 2012 to comply with the critical path schedule. PX 338 at

3. MW Builders assumed that it would take 7 days to pay NV Energy’s service fee

and NV Energy would need 14 days to procure materials after the Line Extension

Agreement was assigned. PX 338 at 7. Thereafter, NV Energy needed 30 work-

days (42 calendar days) to complete the work required to provide electrical power.

PX 338 at 7. As a result, MW Builders projected a “negative float” of 52 days,

unless power was supplied on or before May 4, 2012. PX 338 at 7. Therefore, the

Project’s completion date was adjusted from September 19, 2012 to November 10,

2012. PX 327.

• The May 28, 2012 Schedule Update continued to reflect that MW Builders was

experiencing delay caused by lack of permanent power. PX 339 at 1. Because

neither permanent power nor sufficient temporary power was available for the air

conditioning system, MW Builders was unable to begin work on the temperature

sensitive critical path activities. PX 339 at 1. Therefore, MW Builders projected a

“negative float” of 86 days. PX 339 at 3. The job completion date was revised to

January 9, 2013. PX 328. 35

34

Generators were present at the Project site, but they were “half the size” needed to

provide sufficient power to the Training Building. JX 64 at 1. In a May 11, 2012 email, Mr.

Probst, the Army Corps Project Manager, suggested to Mr. Musgrave, an Army Corps Contracting

Officer’s Representative, that the Army Corps could mitigate delay by renting a larger generator

so work could commence. JX 64 at 1. But, no additional generator power was provided during

the time the Line Extension Agreement was being negotiated.

35

This adjustment was required to account for the fact that no work took place in December

2012 during Government holidays. PX 328 at MWB-008687.

46

• The July 9, 2012 Schedule Update reflected that the Army Corps was “getting

close” to reaching a Line Extension Agreement with NV Energy, but no

construction was advised by the Army Corps, and “negative float’ had increased to

121 calendar days. PX 340 at 1. MW Builders also advised that “[t]here is a little

available work left within the building due to a lack of permanent power and as a

result many subcontractors have de-mobilized.” PX 340 at 2. The job completion

date was revised to February 6, 2013. PX 329.

• The October 15, 2012 Schedule Update was the first issued after the Line Extension

Agreement was signed on July 23, 2012 and permanent power was available on

September 26, 2012. PX 343 at 1. Therein, it was reported that the Project incurred

165 days of “negative float,” due to delays to critical path activities requiring

conditioned air. PX 343 at 1.

By the time the Line Extension Agreement was executed on July 23, 2012, MW Builders’

contemporaneous Schedule Updates showed a 140-day delay to the critical path; i.e., the difference

between the original completion date of September 19, 2012, and the adjusted completion date of

February 6, 2013. Therefore, unlike the contractor in Blinderman Construction Co., MW Builders

proffered critical path schedules, as they existed before, during, and after the delay. In addition,

MW Builders proffered contemporaneous evidence that the delay in securing power affected

critical path activities, particularly the temperature sensitive indoor construction work in the

Training Building.

Nevertheless, the Government argues that, even if the delay was attributable to the Army

Corps, it was “reasonable in duration.” Gov’t Reply at 10. The Army Corps, however, was the

sole cause the delay, because it failed to obtain the necessary easements, unreasonably attempted

to shift responsibility for executing the Line Extension Agreement to MW Builders, engaged in

misleading discussions with NV Energy and failed to cooperate with MW Builders, causing a 116

day delay. See P.R. Burke, 277 F.3d at 1360 (Government-caused delay is unreasonable, if it is

“unnecessary or unreasonable in duration”) (emphasis added).

For these reasons, the court has determined that the Government violated the duty of good

faith and fair dealing, and caused an unreasonable delay to the Project.

D. The Government’s Affirmative Defense And Counterclaims.

1. The Government’s Affirmative Defense Of Waiver.

The Government’s February 17, 2016 Amended Answer asserted the following affirmative

defenses: (1) MW Builders’ claims are barred, in whole, or, in part, by accord and satisfaction;

(2) MW Builders’ claims are barred, in whole, or, in part, by waiver; and (3) the pass-through

claims of MW Builders’ subcontractors are barred, in whole, or, in part, by waiver. Gov’t Amend.

Answer ¶¶ 39–41. The Government’s December 8, 2016 Proposed Findings Of Fact And

47

Conclusions Of Law, however, presented only an argument relating to the waiver of one of MW

Builders’ subcontractors, Bergelectric. Gov’t Post Tr. Br. at 95. 36

a. The Government’s Argument.

The Government argues that any pass-through claim from Bergelectric is waived. Gov’t

Post Tr. Br. at 98. Under the December 6, 2010 subcontract, Bergelectric was required to sign a

periodic form release, as a condition of payment from MW Builders. JX 9 at 2 (12/6/2010). The

language in the form releases signed by Bergelectric unambiguously waived any claims against

MW Builders and, therefore, against the Government. Gov’t Post Tr. Br. at 97 (citing DX 124 at

2 (4/15/12 Bergelectric Waiver)). Because the language in the releases was unambiguous, the

court must consider their plain meaning, instead of extrinsic evidence of the parties’ course of

dealings or oral testimony. Gov’t Post Tr. Br. at 97.

Assuming arguendo that the court may consider extrinsic evidence, Bergelectric’s claims

still are waived. Gov’t Post Tr. Br. at 97. MW Builders required its subcontractors to sign a

release to protect MW Builders from liability. TR at 715 (Campbell). The Government contends

that MW Builders was aware of the need to modify the scope of the release, if Bergelectric intended

to preserve any pass-through claims, but MW Builders did not do so. Gov’t Post Tr. Br. at 98.

The testimony of Justin Knippel, Bergelectric’s Regional Manager for Las Vegas and Phoenix,

was irrelevant, because he was not the company representative who signed the releases. Gov’t

Post Tr. Br. at 97 (citing TR at 774–75 (Knippel)). Likewise, Mr. Campbell’s testimony is

irrelevant, because he was not a Bergelectric representative and had no personal knowledge about

Bergelectric’s intent, when it signed the releases. Gov’t Post Tr. Br. at 98 (citing TR at 717

(Campbell)).

b. Plaintiff’s Response.

MW Builders required Bergelectric to sign a standard form release to receive payment, but

neither party intended the releases to waive any claim arising from the permanent power delay.

Pl. Post Tr. Br. at 128. Instead, these releases were a contractual prerequisite to Bergelectric

getting paid each month. Pl. Post Tr. Br. at 128. The conduct of the parties after Bergelectric

signed the releases also shows that the parties did not intend for Bergelectric to waive any claims,

e.g., Bergelectric filing a Complaint against MW Builders in the United States District Court for

the Western District of Texas on November 26, 2014; executing an agreement to toll the statute of

limitations on Bergelectric’s claims; and passing Bergelectric’s claims through to the Government

in this suit. Pl. Post Tr. Br. at 128–31. And, as Messrs. Knippel, Campbell, and Sawyer testified

at trial, the parties never intended to waive any claims Bergelectric may have against the

Government. TR at 672–73 (Campbell), 776 (Knippel), 812–13 (Sawyer). Since the standardized

for

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.