Opinion

Friends of the Motherhouse v. City of Portland

  • 152 A.3d 159
  • 2016 ME 178
  • 2016 Me. LEXIS 201
Court
Supreme Judicial Court of Maine
Filed
Dec 8, 2016
Status
Published
Cited by
0 cases
Authority
More cited than 3.3%

The opinion

MAINE SUPREME JUDICIAL COURT Reporter of Decisions

Decision: 2016 ME 178

Docket: Cum-16-225

Argued: November 10, 2016

Decided: December 8, 2016

Panel: SAUFLEY, C.J., and ALEXANDER, MEAD, GORMAN, JABAR, HJELM, and HUMPHREY, JJ.

FRIENDS OF THE MOTHERHOUSE et al.

v.

CITY OF PORTLAND et al.

MEAD, J.

[¶1] Friends of the Motherhouse, a nonprofit corporation, and Raymond

Foote and Barbara Weed (collectively “Friends”) appeal from a summary

judgment entered by the Superior Court (Cumberland County, Warren, J.) in

favor of the defendant City of Portland and intervenors Sea Coast at Baxter

Woods Associates, LLC, and Motherhouse Associates LP (intervenors

collectively “Sea Coast”). The court entered judgment on Friends’ complaint

seeking a declaration that the Portland City Council’s rezoning of a parcel

owned by Sea Coast was invalid. We conclude that the Council acted within its

broad legislative authority and affirm the judgment.

2

I. FACTS AND PROCEDURE

[¶2] Although the facts, drawn from the summary judgment record, are

taken in the light most favorable to Friends, see Sullivan v. St. Joseph’s Rehab. &

Residence, 2016 ME 107, ¶ 2, 143 A.3d 1283, in this case Friends admitted the

statement of material facts filed by Sea Coast in its entirety.

[¶3] Sea Coast has a purchase and sale agreement to buy a 17.5-acre

parcel located on Stevens Avenue in Portland (the property) that is the site of a

private high school; St. Catherine’s Hall, which is used as a residence by retired

Sisters of Mercy; and the vacant St. Joseph’s Convent, known as the

“Motherhouse.” Sea Coast intends to give the high school a twenty-five-year

lease, retain St. Catherine’s Hall’s current use, develop the Motherhouse into a

multifamily dwelling consisting of eighty-eight affordable and market-rate

senior housing units, and develop the surrounding grounds into a retirement

community consisting of additional dwelling units and assisted living facilities.

[¶4] On March 4, 2015, Sea Coast requested a zoning amendment that,

after some revision, sought to have a 13.5-acre portion of the property that did

not include the high school and St. Catherine’s Hall rezoned from R-5 residential

to R-5A residential. As described in Portland’s comprehensive plan, “[t]he

3

permitted residential uses in the R-5a1 zone are very similar to those in the

R-5 zone, except that multiplexes are not allowed. The other significant

difference is that PRUDs [planned residential unit developments] may be

developed at a higher density.”

[¶5] On May 12, after notice and a public hearing, the Planning Board

voted unanimously to recommend that the Council approve a zoning map

amendment rezoning the Sea Coast property as proposed, and approve

amendments to the text of the zoning ordinance having general applicability

concerning the R-5A zone. The Planning Board’s report to the Council

contained an explicit finding that the amendments were consistent with

Portland’s comprehensive plan.

[¶6] The Council held a public hearing and voted to adopt the text

amendments, while tabling the proposed map amendment. Sea Coast then

reduced the portion of the property to be rezoned as R-5A to 7.51 acres, in the

process reducing the number of potential housing units on the property by

eighty-five. The Council unanimously approved the revised map amendment

on July 6, rezoning the 7.51-acre portion of the property to R-5A.

1 The comprehensive plan designates the zone as “R-5a”; the zoning ordinance, Planning Board,

City Council, and Superior Court designate the zone as “R-5A.” We will use “R-5A” throughout the

remainder of this opinion.

4

[¶7] Following the Council’s rezoning action, Sea Coast applied to the

Planning Board for a four-lot subdivision of the entire property, as well as a

subdivision in the Motherhouse consisting of sixty-six affordable and

twenty-two market-rate senior housing units. The Planning Board approved

the application on August 11, 2015. No appeal from that action has been taken.

[¶8] On October 23, 2015, Friends filed a two-count complaint for

declaratory judgment in the Superior Court seeking to invalidate the Council’s

rezoning action. The complaint asserted that the comprehensive plan required

that R-5A zones be created only by contractual or conditional rezoning, and that

the map and textual amendments were “substantively inconsistent with the

Comprehensive Plan’s goals and policies for the Deering Center/Stevens

Avenue neighborhood.”

[¶9] Sea Coast moved for summary judgment and the City joined in the

motion. In a judgment dated April 19, 2016, the court concluded that

the zoning code and map amendments at issue are “in basic

harmony” with Portland’s Comprehensive Plan . . . and . . . the

rezoning of 7.51 acres of the St. Joseph’s convent site to R-5A did

not have to be accomplished by conditional or contract zoning.

Accordingly, Intervenors are entitled to summary judgment

granting declaratory relief to that effect.

Friends appealed.

5

II. DISCUSSION

[¶10] We review the entry of a summary judgment de novo, and will

“affirm the grant of summary judgment if the record reflects that there is no

genuine issue of material fact and the movant is entitled to a judgment as a

matter of law.” Remmel v. City of Portland, 2014 ME 114, ¶ 11, 102 A.3d 1168

(quotation marks omitted). In Remmel we set out the standards of review

applicable to this case, in which we are again called upon to review a zoning

decision of the Portland City Council:

Our review of the City Council’s action must respect that zoning is

a legislative act and must give deference to the legislative body.

Judicial review of a . . . rezoning decision is ultimately limited to

determining whether the City Council could rationally have

adopted the [new] zone in light of the evidence presented to it, the

various policies articulated in the comprehensive plan, and the

mandate of [the applicable statute].

. . . .

By statute, zoning ordinances and subsequent rezoning actions

must be “pursuant to and consistent with a comprehensive plan

adopted by the municipal legislative body.” 30-A M.R.S. § 4352(2)

[(2015)]. When considering whether a rezoning action is

“consistent with” a city’s comprehensive plan, a court must

determine whether the City Council could have, from the evidence

before it, found that the rezoning was in basic harmony with the

comprehensive plan. The challenger bears the burden of proving

that the amendment is inconsistent with the comprehensive plan.

A zoning or rezoning action need not perfectly fulfill the goals of a

comprehensive plan; it may be in basic harmony with the plan so

6

long as it strikes a reasonable balance among the municipality's

various zoning goals or overlaps considerably with the plan. In

addition, a comprehensive plan is considered as a whole; a

municipality may conclude that a rezoning action is consistent with

a comprehensive plan when it is in harmony with some provisions

of the plan, even if the action appears inconsistent with other

provisions of the plan.

Id. ¶¶ 1, 12-14 (alterations, citations and quotation marks omitted); see also

Golder v. City of Saco, 2012 ME 76, ¶ 11, 45 A.3d 697. We review the Council’s

factual determinations for clear error. Remmel, 2014 ME 114, ¶ 21 n.5,

102 A.3d 1168.

[¶11] The evidence before the Council included the Planning Board’s

report. In that report, the Planning Board found that the Sea Coast project was

consistent with the purpose of the R-5A zone as set out in the comprehensive

plan, which is

[t]o provide for moderate-density residential development in

off-peninsula sections that can provide a unique residential living

experience with a high degree of natural site amenities; and to

provide areas of the city in the general proximity of the peninsula

that have the ability for adequate municipal services, including

traffic corridors with adequate traffic capacity, that can

appropriately accommodate a more intensive use of land than

other lower-density zoned land and be compatible with

surrounding neighborhoods; and to increase affordable housing

opportunities in off-peninsula locations by providing a moderate

density zone.

7

The Planning Board additionally identified “[g]oals and policies” stated in the

comprehensive plan that it found to be relevant to the Sea Coast proposal,

including several focusing on the need for an adequate housing supply for the

City’s residents in general, and for senior citizens at all income levels in

particular.

[¶12] Given the portions of the comprehensive plan identified by the

Planning Board and considered by the Council, and applying Remmel and the

deference to the Council’s decision that it requires, 2014 ME 114, ¶ 12,

102 A.3d 1168, Friends did not meet its burden to prove that the Council’s

action rezoning part of the Motherhouse property to allow the development of

senior housing—while retaining the high school and St. Catherine’s Hall in their

original zone—was not “in basic harmony with the comprehensive plan.”

Id. ¶ 13 (quotation marks omitted).

[¶13] Friends’ argument that the amendments are inconsistent with the

comprehensive plan because the Council did not employ conditional or contract

zoning is not persuasive. The comprehensive plan does not specify a particular

method for rezoning a property as R-5A, and says nothing about conditional or

contract zoning at all in the section defining the R-5A zone. It says only that

8

“[t]he R-5a is applied though rezoning when a site and development proposal

meets the intent of this zoning classification.”

[¶14] The zoning ordinance—not the comprehensive plan—formerly

required conditional or contract zoning in order to create an R-5A zone

containing a planned residential unit development, but the Council chose to

follow the recommendation of the Planning Board and changed the ordinance

to eliminate that requirement. As the Planning Board noted, the

comprehensive plan explicitly allows such a change in providing that

“[p]otential text amendments will be considered to update the residential zones

in conformance with the recommendations of [the comprehensive plan].”

“[B]asic harmony with the comprehensive plan,” not harmony with the former

zoning ordinance, is the test that we apply when reviewing the Council’s zoning

decision. Remmel, 2014 ME 114, ¶¶ 13-14, 102 A.3d 1168 (quotation marks

omitted). Because that test is satisfied in this case, the court did not err in

finding that Sea Coast was entitled to judgment as a matter of law.

[¶15] Having concluded that summary judgment was appropriately

granted, we do not reach the alternative argument advanced by Sea Coast and

the City that even if the Council’s rezoning action conflicted with the

9

comprehensive plan, the Planning Board’s approval of Sea Coast’s subdivision

application remains valid because Friends did not appeal from that action.

The entry is:

Judgment affirmed.

On the briefs:

David A. Lourie, Esq., Cape Elizabeth, for appellants Friends of the

Motherhouse, Raymond Foote, and Barbara Weed

Danielle P. West-Chuhta, Esq., City of Portland, Portland, for appellee City

of Portland

Natalie L. Burns, Esq., and Mark A. Bower, Esq., Jensen Baird Gardner &

Henry, Portland, for appellees Motherhouse Associates LP and Sea Coast

at Baxter Woods Associates

At oral argument:

David A. Lourie, Esq., for appellants Friends of the Motherhouse,

Raymond Foote, and Barbara Weed

Danielle P. West-Chuhta, Esq., for appellee City of Portland

Natalie L. Burns, Esq., for appellees Motherhouse Associates LP and Sea

Coast at Baxter Woods Associates

Cumberland County Superior Court docket number CV-2015-480

FOR CLERK REFERENCE ONLY