Opinion

Southwinds Express Construction, LLC v. D.H. Griffin of Texas, Inc.

  • 513 S.W.3d 66
  • 2016 Tex. App. LEXIS 12217
  • 2016 WL 6775759
Court
Court of Appeals of Texas
Filed
Nov 15, 2016
Status
Published
On the bench
Thompson, Frost, Boyce, Wise
Cited by
26 cases
Authority
More cited than 3.3%

explaining that applying § 171.088(a)(3)(A) to circumstances like those in issue here would render portions of § 171.088(a)(4) “meaningless”

How later courts described this case

  • explaining that applying § 171.088(a)(3)(A) to circumstances like those in issue here would render portions of § 171.088(a)(4) “meaningless”
  • detailing argument made to arbitrator

Written by the judges who cited it.

The opinion

Affirmed and Majority and Concurring Opinions filed November 15, 2016.

In The

Fourteenth Court of Appeals

NO. 14-15-00610-CV

SOUTHWINDS EXPRESS CONSTRUCTION, LLC, Appellant

V.

D.H. GRIFFIN OF TEXAS, INC., Appellee

On Appeal from the 151st District Court

Harris County, Texas

Trial Court Cause No. 2015-22736

MAJORITY OPINION

Southwinds Express Construction, LLC challenges the trial court’s judgment

confirming an arbitration award in favor of D.H. Griffin of Texas, Inc. Southwinds

contends that the trial court erred in confirming the arbitrator’s award because

(1) the arbitration agreement between the parties did not cover the claims asserted

by Griffin; (2) even if the arbitration agreement between the parties covered

Griffin’s claims, mediation was a condition precedent to arbitration and did not

occur; and (3) the arbitrator’s award was tainted by manifest disregard for the law

and gross mistake in applying the law. We affirm.

BACKGROUND

The Lemoine Company contracted with Griffin in 2013 to serve as the

demolition subcontractor on a construction, renovation, and demolition project for

a hospital in Louisiana. Griffin, in turn, requested bids from Southwinds for the

removal of construction and demolition debris from the project site.

Southwinds proposed that it would perform (1) “concrete excavation and

haul off” for free; (2) brick haul-off for $40 per truckload; and (3) construction and

demolition (“C&D”) haul-off for $12 per cubic yard plus disposal fees. Griffin

accepted Southwinds’s proposal concerning concrete haul-off and brick haul-off,

but declined the proposed terms for C&D haul-off.

Griffin and Southwinds entered into a Subcontractor Agreement reflecting

their agreement on September 26, 2013. This agreement included a provision

requiring arbitration of “a claim” made by either party.

The arbitration provision in paragraph 3 of the Subcontractor Agreement

states as follows:

In the event that a claim is not resolved through the negotiations of the

parties, claim resolution will be resolved through mediation unless, in

the sole discretion of [Griffin], [Griffin] believes mediation would be

a useless exercise in which case [Griffin], unilaterally, may escalate

the claims process to binding arbitration at any time. If mediation

fails, both parties agree that the claim will be resolved pursuant to

binding arbitration. Any mediation or arbitration will be conducted

under the rules of the American Arbitration Association’s (“AAA”)

Construction Industry Dispute Resolution Procedures (including

Mediation and Arbitration Rules) in effect at the time of the execution

of this Agreement; provided, however, that where there is a conflict, if

any, between those rules and this Agreement, this Agreement governs.

2

This written agreement included an attached “Exhibit A” that identified the scope

of work under the agreement as follows:

Southwinds Express Construction LLC will remove and haul off

concrete slabs, foundations and parking at the [hospital] site in

Lafayette, Louisiana for No Charge. Southwinds Express

Construction LLC will haul brick and concrete generated from the

demolition operation for Forty Dollars ($40.00) per load.

Weeks later, Griffin and Southwinds orally agreed that Southwinds would perform

C&D haul-off for $9 per cubic yard including disposal fees.1

Southwinds performed C&D haul-off for Griffin until early 2014.

Southwinds contends it ceased working because Griffin’s payments were not

timely.

Griffin contends that Southwinds stopped paying landfill disposal fees in

November and December 2013, and that the landfill owner consequently barred

Southwinds from use of the landfill. Griffin contends that with no landfill

available for debris disposal, Southwinds abandoned work on the project and left

Griffin with landfill fee arrearages totaling $67,000. Griffin contends that it was

required to pay the landfill fees because the landfill operator threatened to place a

lien on the project property if the fees were not paid. Griffin also contends that it

1

To that end, Griffin sent Southwinds a second unexecuted Subcontractor Agreement

that was identical to the previously executed agreement except that the scope of work exhibit

included this addition: “Construction debris generated and hauled will be an all inclusive rate of

$9.00 per cubic yard (including transportation and disposal cost).” The second agreement was

dated October 14, 2013.

In the portion of the contract stating that Griffin would pay Southwinds for invoiced

amounts within 10 days after Griffin received payment from Lemoine, Southwinds interlineated

“except for trucking and dump fees which will be Net 14.” Similarly, Southwinds modified the

scope of work exhibit with the interlineation, “Payment terms will be Net 14.” Southwinds

executed the modified second agreement. The parties dispute whether Southwinds returned the

modified agreement to Griffin at that time, but it is undisputed that Griffin did not execute the

modified second agreement.

3

had to hire third parties to complete the removal of construction and demolition

debris.

Griffin filed a demand for arbitration in March 2014. Southwinds objected

to the arbitrator’s jurisdiction, contending that the arbitration provision in the

written Subcontractor Agreement did not extend to any claims arising from the

subsequent oral agreement to provide C&D haul-off services. The arbitrator

overruled Southwinds’s objection.

A two-day arbitration hearing was held in January 2015. The arbitrator

issued an Award of Arbitration on March 12, 2015. In its award, the arbitrator

found that the oral agreement was a modification of the Subcontractor Agreement;

the oral agreement caused the C&D haul-off to be included within the scope of

work of the Subcontractor Agreement; and any claim relating to the C&D haul-off

therefore was a claim under the Subcontractor Agreement subject to the

Subcontractor Agreement’s arbitration provision.

Concluding she had jurisdiction to consider this dispute, the arbitrator

determined that Southwinds breached its agreement with Griffin. The arbitrator

awarded Griffin $42,251.20 in actual damages, $36,851.08 in attorney’s fees, and

$8,800 in arbitration fees and expenses; she also ordered Southwinds to release a

lien it had filed against the project.

Griffin sought to have the arbitration award confirmed in district court in

April 2015. After briefing and argument from the parties, the trial court signed a

final judgment confirming the arbitration award on June 16, 2015. Southwinds

appealed.

4

STANDARD OF REVIEW

We review a trial court’s decision to confirm or vacate an arbitration award

under a de novo standard of review. D.R. Horton–Tex., Ltd. v. Bernhard, 423

S.W.3d 532, 534 (Tex. App.—Houston [14th Dist.] 2014, pet. denied). “Review of

an arbitration award is ‘extraordinarily narrow.’” Amoco D.T. Co. v. Occidental

Petroleum Corp., 343 S.W.3d 837, 841 (Tex. App.—Houston [14th Dist.] 2011,

pet. denied) (quoting Statewide Remodeling, Inc. v. Williams, 244 S.W.3d 564, 568

(Tex. App.—Dallas 2008, no pet.)). We give an arbitration award great deference

and indulge every reasonable presumption in favor of the award and none against

it. CVN Grp., Inc. v. Delgado, 95 S.W.3d 234, 238 (Tex. 2002); Amoco D.T. Co.,

343 S.W.3d at 841.

ANALYSIS

I. Arbitrability of the C&D Claims

Southwinds contended below that the C&D haul-off claims were not

covered by a valid arbitration agreement because they were the subject of the

parties’ oral agreement — which, according to Southwinds, constituted a separate

agreement distinct from the original Subcontractor Agreement containing the

arbitration provision. Overruling Southwinds’s objection, the arbitrator

determined instead that (1) the oral agreement was a modification of the

Subcontractor Agreement; and (2) the C&D haul-off claims therefore fell within

the parties’ arbitration agreement.

After the arbitrator ruled in Griffin’s favor on the merits, Griffin filed an

action in district court seeking confirmation of the arbitrator’s award. Southwinds

moved to vacate the award, contending the arbitrator exceeded her power by

5

deciding matters outside the scope of her authority — namely, the C&D haul-off

claims.

In its final judgment confirming the arbitrator’s award, the trial court stated:

The Court is persuaded that the agreement between the parties

contemplated additional potential work such as the C&D work. Thus,

this work arose out of the agreement and, consequently, the arbitration

agreement contemplated additional work. Further, the issue of

whether there was, in fact, an enforceable oral agreement to do the

C&D work was for the arbitrator to decide, not this Court. The Court

will note, though, that the agreement between the parties does NOT

state that no subsequent oral agreements could be formed; only that no

oral representations prior to the written agreement existed or were

relied upon.

On appeal, Southwinds contends the trial court erred in determining that C&D

haul-off claims fell within the scope of the Subcontractor Agreement’s arbitration

provision. Griffin responds that the Subcontractor Agreement’s arbitration

provision governed at least a portion of the dispute between the parties; the

arbitration provision referenced that any arbitration would be conducted pursuant

to the American Arbitration Association (“AAA”) rules, which state that

determinations of arbitrability shall be made by the arbitrator; and the parties

therefore clearly and unmistakably agreed to submit the determination of

arbitrability of the C&D haul-off claims to the arbitrator rather than the trial court.

A. Who Determines Arbitrability?

Arbitration is a matter of contract. Howsam v. Dean Witter Reynolds, Inc.,

537 U.S. 79, 83 (2002).2 The question of arbitrability addresses which claims must

2

Because the substantive principles applicable to the analysis in this appeal are the same

under both the Federal Arbitration Act and the Texas Arbitration Act, we rely on cases

discussing both statutes. See Forest Oil Corp. v. McAllen, 268 S.W.3d 51, 56 n.10 (Tex. 2008);

Branch Law Firm L.L.P. v. Osborn, No. 14-14-00892-CV, 2016 WL 444867, at *3 n.3 (Tex.

App.—Houston [14th Dist.] Feb. 4, 2016, pet. denied).

6

be arbitrated. Leshin v. Oliva, No. 04-14-00657-CV, 2015 WL 4554333, at *5

(Tex. App.—San Antonio July 29, 2015, no pet.) (mem. op.); see also Saxa Inc. v.

DFD Architecture Inc., 312 S.W.3d 224, 229 (Tex. App.—Dallas 2010, pet.

denied) (questions of arbitrability include “whether the parties agreed to arbitrate

and whether a claim or dispute is encompassed in the agreement to arbitrate”).

When there is an undisputed arbitration provision in an agreement between

the parties, we ordinarily look to the arbitration provision’s language to determine

whether the parties “clearly and unmistakably” intended for the arbitrator to

determine arbitrability or instead left that decision to the trial court. See Howsam,

537 U.S. at 83; First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938, 944 (1995).

This case presents a different circumstance in which a subsequent oral agreement

governs some of the claims. Griffin contends the arbitration provision applies to

all claims at issue because the oral agreement modified the Subcontractor

Agreement containing the arbitration provision. Southwinds contends the written

contract’s arbitration provision does not apply to the C&D haul-off claims because

the oral agreement governing C&D haul-off was wholly independent.

Southwinds therefore challenges the existence of an agreement to arbitrate

the C&D haul-off claims. As the Supreme Court of Texas has explained:

[W]here the very existence of an agreement is challenged, ordering

arbitration could result in an arbitrator deciding that no agreement was

ever formed. Such an outcome would be a statement that the

arbitrator never had any authority to decide the issue. . . . We

therefore conclude that where a party attacks the very existence of an

agreement, as opposed to its continued validity or enforcement, the

courts must first resolve that dispute.

In re Morgan Stanley & Co., 293 S.W.3d 182, 189 (Tex. 2009) (quoting Will–Drill

Res., Inc. v. Samson Res. Co., 352 F.3d 211, 219 (5th Cir. 2003)) (emphasis in

original).

7

In Texas La Fiesta Auto Sales, LLC v. Belk, 349 S.W.3d 872 (Tex. App.—

Houston [14th Dist.] 2011, no pet.), we considered the situation in which a valid

arbitration agreement was acknowledged to exist but was alleged to have merged

into a later arbitration agreement with different terms. Id. at 879-80. The

appellants contended that, once it was determined a valid arbitration agreement

existed, any issue concerning merger should have been decided by the arbitrator.

Id. at 880. We concluded that the issue of whether the subsequent contract’s

arbitration provision superseded the initial arbitration agreement was a question for

the trial court. Id. Explaining our conclusion, we noted that “it is the trial court’s

duty to determine whether a later agreement between the parties revokes an

arbitration clause, because the court must determine the threshold issue of whether

a valid arbitration agreement exists.” Id. at 881.

In Valero Energy Corp. v. Teco Pipeline Co., 2 S.W.3d 576 (Tex. App.—

Houston [14th Dist.] 1999, no pet.), we considered a party’s argument that “its

claims are not based on the Operating Agreement, which contains an arbitration

clause, but rather, arise out of a separate unwritten partnership agreement, which

was created as a result of the sale of the 50% undivided interest in the pipeline.”

Id. at 584. The party argued that, because its claims were related to the separate

partnership, those claims were not subject to the Operating Agreement’s arbitration

provision. Id. Although we did not make an explicit statement to this effect, our

de novo review of the issue indicates that we reviewed an issue decided by the trial

court rather than the arbitrator. See id. at 584-86.

These cases inform our analysis here. Similar to the argument advanced in

Valero, Southwinds contends the C&D haul-off claims arise from a separate

agreement. Consistent with Valero, we conclude that the arbitrability of the C&D

haul-off claim is a matter for trial court determination because those claims

8

allegedly stem from a separate agreement. See id. We reach this conclusion

because, as we stated in Texas La Fiesta, the trial court must determine the

threshold issue of whether a valid arbitration agreement exists under circumstances

like those present here. See Texas La Fiesta, 349 S.W.3d at 881; see also In re

Bath Junkie Franchise, Inc., 246 S.W.3d 356, 364 (Tex. App.—Beaumont 2008,

orig. proceeding) (whether a later agreement between the parties operated as a

novation of an earlier contract containing an arbitration provision was a question

for the trial court, not the arbitrator). Accordingly, we conclude that the question

of whether the C&D haul-off claims were governed by a valid arbitration

agreement was one for the trial court, not the arbitrator.

When, as in this case, the arbitrator determines arbitrability even though it is

a question for the trial court, we ordinarily would remand for the trial court to

consider the issue. See, e.g., Leshin, 2015 WL 4554333, at *8 (“Whether Leshin

was a party to the arbitration agreement under some legal theory is a question of

arbitrability, which is for the trial court to determine. Therefore, we reverse the

trial court’s judgment confirming the arbitration award and remand . . . for the trial

court to consider the arbitrability issue and determine whether there is any legal

theory that would allow the trial court to compel Leshin, in his individual capacity,

to arbitrate and be bound by any ensuing award.”); Elgohary v. Herrera, 405

S.W.3d 785, 793-94 (Tex. App.—Houston [1st Dist.] 2013, no pet.) (remanding for

trial court to consider arbitrability). Because the trial court already has made an

independent determination that the claims were arbitrable, we review the trial

court’s determination for error. See, e.g., Roe v. Ladymon, 318 S.W.3d 502, 518

(Tex. App.—Dallas 2010, no pet.) (reviewing trial court’s independent

determination of arbitrability de novo).

9

B. Were the C&D Claims Arbitrable?

Both the arbitrator and the trial court determined that the C&D haul-off

claims were governed by the Subcontractor Agreement’s arbitration provision.

Despite the uniformity of result, our determination that it was the trial court’s

prerogative to resolve the question of arbitrability is important because it

determines the applicable standard of review. See id. at 511. As the court

succinctly summarized in Ladymon:

The parties to this appeal disagree about a preliminary—but critical—

question of law: who has the primary power to decide whether

Ladymon is required to arbitrate—the arbitrator or a court? The

answer determines the applicable standard of review: if the question is

primarily for the arbitrator to decide, courts will review the

arbitrator’s determination of that issue with great deference, but if the

question is primarily for the court to decide, courts will review the

question independently or de novo.

Id.; see also McReynolds v. Elston, 222 S.W.3d 731, 740 (Tex. App.—Houston

[14th Dist.] 2007, no pet.) (“Determining whether a claim falls within the scope of

an arbitration agreement involves the trial court’s legal interpretation of the

agreement, and we review such interpretations de novo.”). Accordingly, we

review de novo the trial court’s determination that the Subcontractor Agreement’s

arbitration provision governed the C&D haul-off claims. See, e.g., In re

Guggenheim Corp. Funding, LLC, 380 S.W.3d 879, 886 (Tex. App.—Houston

[14th Dist.] 2012, orig. proceeding) (“[A] determination of the scope of an

unambiguous arbitration clause is a matter of contract interpretation and a question

of law for the trial court.”).

Griffin contends that the oral agreement modified the Subcontractor

Agreement, leaving intact the Subcontractor Agreement’s arbitration provision and

extending its reach to encompass the C&D haul-off claims.

10

The trial court stated in its final judgment that “the agreement between the

parties contemplated additional potential work such as the C&D work,” and that

the C&D haul-off work “arose out of the agreement” and therefore was governed

by the arbitration provision. The trial court appears to have concluded that,

regardless of whether the oral agreement modified the Subcontractor Agreement or

was a stand-alone agreement, the C&D haul-off claims nevertheless arose out of

the Subcontractor Agreement and therefore were subject to the arbitration

provision. The trial court further noted that whether the oral agreement was

actually enforceable was for the arbitrator to decide, suggesting that the oral

agreement’s validity was a separate inquiry from arbitrability. We agree with the

trial court.

Claims generally are arbitrable when the facts alleged “touch matters” that

are covered by, have a “significant relationship” to, are “inextricably enmeshed”

with, or are “factually intertwined” with the contract that contains the arbitration

provision. AutoNation USA Corp. v. Leroy, 105 S.W.3d 190, 195 (Tex. App.—

Houston [14th Dist.] 2003, no pet.); In re Bath Junkie Franchise, Inc., 246 S.W.3d

at 366; see also Branch Law Firm L.L.P. v. Osborn, No. 14-14-00892-CV, 2016

WL 444867, at *12 (Tex. App.—Houston [14th Dist.] Feb. 4, 2016, pet. denied)

(“Where, as here, the contract includes a broad arbitration clause, we consider

whether the facts alleged are sufficiently intertwined with the contract and thus

arbitrable.”); Ascendant Anesthesia PLLC v. Abazi, 348 S.W.3d 454, 462 (Tex.

App.—Dallas 2011, no pet.) (recognizing that claims may become arbitrable when

factually intertwined with arbitrable claims). “To be within the scope of an

arbitration provision, the allegations need only be factually intertwined with

arbitrable claims or otherwise touch upon the subject matter of the agreement

containing the arbitration provision.” In re Prudential Sec. Inc., 159 S.W.3d 279,

11

283 (Tex. App.—Houston [14th Dist.] 2005, orig. proceeding). We resolve any

doubt about the “scope of arbitrable issues” in favor of arbitration. Green Tree

Fin. Corp. v. Bazzle, 539 U.S. 444, 452 (2003); Valero, 2 S.W.3d at 590.

Here, we agree with the trial court that the Subcontractor Agreement

contemplated additional work. The Subcontractor Agreement stated that Griffin

could “at any time require deviation from” the Subcontractor Agreement, including

material changes to the scope of work, by providing authorization to Southwinds.3

Additionally, the Subcontractor Agreement’s broad arbitration provision

covered “a claim by [Southwinds] against [Griffin]” and “a claim [filed by Griffin]

against [Southwinds].” The parties did not limit the arbitration provision’s scope

to claims arising out of the Subcontractor Agreement or to claims related to the

Subcontractor Agreement. The parties placed no limitation on the nature of the

claims between them that fell within the arbitration provision. Because of the

broad nature of this arbitration provision, we consider whether the C&D haul-off

claims are sufficiently intertwined with the Subcontractor Agreement to be

arbitrable. See Branch Law Firm L.L.P., 2016 WL 444867, at *12. The C&D

haul-off claims involved the same construction project and the same essential type

of work being performed; they differed only in the type of debris removed.

Accordingly, we conclude the C&D haul-off claims had a significant relationship

to, and were factually intertwined with, the Subcontractor Agreement.

3

Although the Subcontractor Agreement required modifications to the scope of work to

be in writing, Texas courts have allowed parties to orally modify contracts with such provisions.

See, e.g., Double Diamond, Inc. v. Hilco Elec. Coop., Inc., 127 S.W.3d 260, 267 (Tex. App.—

Waco 2003, no pet.) (“A written agreement not required by law to be in writing may be modified

by a later oral agreement, even though it provides that it can be modified only in writing.”); see

also Chopra & Assocs., PA v. U.S. Imaging, Inc., No. 14-13-01099-CV, 2014 WL 7204868, at

*4 n.2 (Tex. App.—Houston [14th Dist.] Dec. 18, 2014, no pet.) (mem. op.) (recognizing “that

courts have allowed parties to modify an agreement orally despite a no-oral-modification

clause”). Moreover, Griffin attempted to authorize the modifications in writing by providing

Southwinds with the revised subcontractor agreement.

12

Considering that the contract contemplated additions to the scope of work

such as the C&D haul-off, and considering that the asserted claims had a

significant relationship with and were factually intertwined with the contractual

responsibilities identified in the Subcontractor Agreement, the trial court correctly

determined that the C&D haul-off claims were governed by that agreement’s broad

arbitration provision.4 See In re Bath Junkie Franchise, Inc., 246 S.W.3d at 366-

67 (noting that, “[w]ithout the parties’ relationship that arose from the Franchise

Agreement, Hygiene and Bath Junkie would not have entered into the Termination

Agreement,” and concluding that the claims involving the Termination Agreement

arose out of and related to the Franchise Agreement and were “within the scope of

the claims the parties agreed to submit to arbitration” under the Franchise

Agreement); Gerwell v. Moran, 10 S.W.3d 28, 32-33 (Tex. App.—San Antonio

1999, no pet.) (where parties entered into an original agreement and a subsequent

agreement, with an arbitration provision contained only in the original agreement,

claims based on the subsequent agreement were arbitrable where arbitration

provision was broad and subsequent agreement was contemplated by original

agreement).

We also note that neither the FAA nor Texas law requires arbitration

provisions to be signed if they are in writing and agreed to by the parties. In re

AdvancePCS Health L.P., 172 S.W.3d 603, 606 (Tex. 2005) (orig. proceeding).

An agreement is enforceable when the parties agree on all essential terms. T.O.

Stanley Boot Co. v. Bank of El Paso, 847 S.W.2d 218, 221 (Tex. 1992); Mabon

Ltd. v. Afri-Carib Enters., Inc., 29 S.W.3d 291, 300 (Tex. App.—Houston [14th

4

This case does not involve enforcement of an arbitration agreement against a non-

signatory; rather, this case involves a determination that a valid arbitration agreement signed by

both parties covers claims arising from a separate oral agreement covering factually intertwined

issues.

13

Dist.] 2000, no pet.). Whether an agreement contains all essential terms to be an

enforceable contract is a question of law. See Southern v. Goetting, 353 S.W.3d

295, 300 (Tex. App.—El Paso 2011, pet. denied); America’s Favorite Chicken Co.

v. Samaras, 929 S.W.2d 617, 622 (Tex. App.—San Antonio 1996, writ denied). A

party’s signature on a contract is “strong evidence” that the party unconditionally

assented to its terms. In re Citgo Petroleum Corp., 248 S.W.3d 769, 774 (Tex.

App.—Beaumont 2008, orig. proceeding).

The parties here agree that, after they executed the Subcontractor

Agreement, they mutually agreed that Southwinds would perform C&D haul-off

services for $9 per cubic yard. To that end, Griffin sent Southwinds a new

contract. The contract was identical to the original Subcontractor Agreement

except that it included one additional sentence in the “Scope of Work” exhibit

stating that Southwinds would perform C&D haul-off services at $9 per cubic yard.

As with the original Subcontractor Agreement, the proposed agreement contained

an arbitration provision. Southwinds interlineated two modifications to the

payment terms for “trucking and dump fees,” signed the agreement, and alleges

that it returned the agreement to Griffin. Southwinds acknowledges that it

performed the C&D haul-off work pursuant to the second agreement.

Accordingly, the only contractual term the parties dispute addressed whether

payment was to be made (1) within 14 days of invoice; or (2) after Lemoine paid

Griffin.

Based on this record, these payment terms were not essential to the

agreement. See, e.g., Eastman Gas Co. v. Goodrich Petroleum Co., 456 S.W.3d

319, 329 (Tex. App.—Texarkana 2015, pet. denied) (concluding that “the manner

of payment and the amount and rate of interest [were] not essential terms” in that

instance and the agreement was therefore enforceable). The parties agreed on all

14

material terms and agreed to be bound by the arbitration provision. See Hardin

Constr. Grp., Inc. v. Strictly Painting, Inc., 945 S.W.2d 308, 313 (Tex. App.—San

Antonio 1997, no writ) (where subcontractor never signed agreement provided by

general contractor based on objection to single non-essential term but parties

otherwise performed under the terms of the agreement, “the only reasonable

conclusion that [the trial court] could have reached was that [the subcontractor]

agreed to be bound by all the terms of the subcontract except the [non-essential

term],” and that the parties therefore agreed to arbitrate under the arbitration

provision in the agreement).

Finally, after having relied on the second written agreement in asserting its

counterclaim during the arbitration proceeding, Southwinds cannot argue

convincingly that the arbitration provision in that agreement is unenforceable. See

In re Citgo Petroleum Corp., 248 S.W.3d at 775 (“Having affirmatively used the

“Dispute Resolution Agreement” to support a claim based on the same injury,

Rose’s challenge to the existence of the agreement based solely on the lack of a

signature for Pat Tank is not persuasive.”).

The trial court properly determined that the C&D haul-off claims were

arbitrable.5

5

Southwinds additionally argues that the trial court erred by failing to vacate the

arbitrator’s award under the Texas Arbitration Act. Southwinds identified two statutory grounds

for vacatur of the award. First, it argued that the award should be vacated because there was no

valid agreement to arbitrate. See Tex. Civ. Prac. & Rem. Code Ann. § 171.088(a)(4) (Vernon

2011). Second, it argued that the arbitration award should be vacated because the arbitrator

exceeded her power by deciding matters outside the scope of her authority, specifically

contending that the arbitrator exceeded her authority “by essentially dispensing her own justice

in deciding the C&D removal matters without an agreement to arbitrate these matters.” See id. §

171.088(a)(3)(A).

Having concluded that a valid and enforceable arbitration agreement covered all claims,

including the C&D haul-off claims, we reject Southwinds’s argument that the trial court failed to

properly apply the statutory vacatur grounds.

15

II. Mediation as a Condition Precedent to Arbitration

Southwinds next contends that the trial court erred in determining that

mediation was not a condition precedent to arbitration.6

The Subcontractor Agreement provides:

In the event that a claim is not resolved through the negotiations of the

parties, claim resolution will be resolved through mediation unless, in

the sole discretion of [Griffin], [Griffin] believes mediation would be

a useless exercise in which case [Griffin], unilaterally, may escalate

the claims process to binding arbitration at any time. If mediation

fails, both parties agree that the claim will be resolved pursuant to

binding arbitration.

Southwinds argues that Griffin’s “bilateral promise to adhere to a specific [dispute

resolution] process is illusory and unenforceable” because Griffin “at its own

option or whim . . . can stop the dispute resolution process and escalate it” by

skipping mediation and going straight to arbitration. According to Southwinds,

“[T]he Subcontractor Agreement does not equally bind both parties to the same

dispute resolution procedure” because “Griffin’s promise to adhere to the dispute

resolution procedure is totally optional to it, but not Southwinds.” Southwinds

asserts as follows: “If enforced as written, [the arbitration provision] deprives

Southwinds of a valuable right to resolve disputes through mediation.”

Southwinds contends that, after the Subcontractor Agreement is reformed to

remove Griffin’s supposedly illusory promise, the agreement requires arbitration of

claims only if the claims are first mediated unsuccessfully. Because mediation did

not occur, Southwinds contends that arbitration was improper due to the failure to

satisfy a condition precedent.

6

In its final judgment, the trial court stated that “the Court is not persuaded that the

mediation clause was a condition precedent to arbitration.”

16

A. Who Determines Whether an Arbitration Provision is Illusory?

Before reaching the merits of Southwinds’s contention, we first must address

whether the trial court or the arbitrator decides whether the arbitration provision is

illusory and unenforceable. We agree with Southwinds that this determination is

the trial court’s to make, but we rely on a different basis than the one Southwinds

urges.

Generally, “[o]nce it is determined . . . that the parties are obligated to

submit to arbitration, ‘procedural’ questions which grow out of the dispute and

bear on its final disposition should be left to the arbitrator.” Valero, 2 S.W.3d at

583 (quoting John Wiley & Sons, Inc. v. Livingston, 376 U.S. 543, 557 (1964)). In

Valero, we concluded that the arbitrator decided whether conditions precedent to

arbitration were satisfied. Id. at 584.

Southwinds relies on Amir v. International Bank of Commerce, 419 S.W.3d

687 (Tex. App.—Houston [1st Dist.] 2013, no pet.), to argue that this case falls

within an exception to the general rule.

Amir acknowledged that, “[t]ypically, questions of whether prerequisites to

arbitration have been fulfilled are left to the arbitrators to resolve.” Id. at 692. The

court went on to observe as follows:

If, however, there is clearly established proof that a strictly procedural

requirement has not been met and that procedural requirement

precludes arbitration, a court can deny a motion to compel arbitration

on this ground. This is a narrow exception. As an example, a trial

court cannot compel arbitration when the provision requires the

parties to mediate before arbitration. To do so would frustrate the

parties’ original intent clearly expressed in the agreement.

Id. (internal citations omitted); see also In re Igloo Prods. Corp., 238 S.W.3d 574,

579-81 (Tex. App.—Houston [14th Dist.] 2007, orig. proceeding [mand. denied])

17

(where neither party suggested that arbitration agreement was ambiguous or that

condition precedent had been satisfied, issue was really a “‘gateway dispute’ as to

whether the arbitration agreement covers a particular kind of controversy” for the

trial court to decide).

Under Amir and In re Igloo, a trial court decides the gateway issue of

whether arbitration can be compelled in light of a condition precedent when there

is no factual dispute about whether the condition precedent has been satisfied. In

those circumstances the trial court can make this determination as a matter of law.

See generally Amir, 419 S.W.3d at 692; In re Igloo, 238 S.W.3d at 579-81; see

also, e.g., Omoruyi v. Grocers Supply Co., No. 14-09-00151-CV, 2010 WL

1992585, at *8 (Tex. App.—Houston [14th Dist.] May 20, 2010, no pet.) (mem.

op.) (noting that courts, including this court in In re Igloo, have recognized an

exception to the general rule that arbitrators resolve questions of procedural

arbitrability — such as satisfaction of conditions precedent to arbitration — when

“the issues are factually undisputed”).

Amir addresses situations in which “there is clearly established proof that a

strictly procedural requirement has not been met and that procedural requirement

precludes arbitration” — such as, the court notes, where the parties’ agreement

clearly requires the parties to mediate before arbitration. See Amir, 419 S.W.3d at

692. In re Igloo involved an arbitration provision restricted to “disputes that

cannot first be resolved through [Igloo’s] internal dispute resolution procedures or

mediation.” See In re Igloo, 238 S.W.3d at 581. It was undisputed that no

mediation had occurred. See id.

This case, in contrast, involves an arbitration provision that expressly allows

Griffin unilaterally to “escalate the claims process to binding arbitration at any

time.” Thus, this case does not fall within the “narrow exception” under which the

18

agreement unambiguously requires mediation as a condition precedent to

arbitration. See id.; cf. In re Pisces Foods, L.L.C., 228 S.W.3d 349, 351, 353 (Tex.

App.—Austin 2007, orig. proceeding) (employment agreement requiring both

employee and employer to follow multi-step dispute resolution program —

including mediation — before arbitrating raised “no question of fact with respect

to the mediation prerequisite,” and “expressly require[d] mediation as a

precondition for requesting arbitration”).

Southwinds is correct that the determination here was for the trial court to

make, but not for the reason it advances. Southwinds contends that we must (1)

determine that Griffin’s option to avoid mediation makes the arbitration provision

illusory; and then (2) read the option out of the agreement. After removing the

option, Southwinds argues that mediation is a condition precedent to arbitration.

Because Griffin indisputably did not mediate before arbitrating, Southwinds

contends that this case falls within the “narrow exception” described above so the

trial court can decide a strictly procedural requirement was not met.

Southwinds flips the order in which we must proceed. Contrary to

Southwinds’s assertion, the threshold question is not whether a condition precedent

was satisfied. Instead, the threshold question is whether an arbitration provision

allowing one contracting party to skip mediation before arbitrating is illusory and

unenforceable. A decision on the arbitration provision’s enforceability comes

before a decision on whether the arbitration provision imposes a condition

precedent.

When Southwinds asserts that Griffin’s option to skip mediation makes the

arbitration provision illusory, Southwinds attacks the arbitration provision itself as

being unenforceable as drafted. This unenforceability challenge was the trial

court’s to decide. See In re Labatt Food Serv., L.P., 279 S.W.3d 640, 643 (Tex.

19

2009) (orig. proceeding) (whether there is a valid and enforceable agreement to

arbitrate is a legal question subject to de novo review); Perry Homes v. Cull, 258

S.W.3d 580, 589 (Tex. 2008) (“[A]rbitrators generally must decide defenses that

apply to the whole contract, while courts decide defenses relating solely to the

arbitration clause.”); Omoruyi, 2010 WL 1992585, at *8 (“[Q]uestions of

substantive arbitrability, such as whether an arbitration agreement is enforceable or

whether the matter at hand falls within the scope of the agreement, are matters for

a court to determine.”).

B. Did Griffin’s Option Not to Mediate Before Arbitrating Make the

Arbitration Provision Illusory and Unenforceable?

In reaching its conclusion that mediation was not a condition precedent to

arbitration, the trial court necessarily concluded that Griffin’s unilateral option to

bypass mediation before arbitrating did not make the arbitration provision illusory

and unenforceable. We agree.

“An arbitration clause is not illusory unless one party can avoid its promise

to arbitrate by amending the provision or terminating it altogether.” In re 24R,

Inc., 324 S.W.3d 564, 567 (Tex. 2010) (orig. proceeding). The mere fact that an

arbitration provision is one-sided does not make it illusory. Royston, Rayzor,

Vickery, & Williams, LLP v. Lopez, 467 S.W.3d 494, 505 (Tex. 2015); NACE Int’l

v. Johnson, 01-15-00529-CV, 2016 WL 4486158, at *3 (Tex. App.—Houston [1st

Dist.] Aug. 25, 2016, no pet.) (mem. op. on reh’g).

The arbitration agreement in NACE provided that disputes would be

resolved through arbitration but allowed NACE the unilateral right to pursue

litigation if it was unsatisfied by the arbitration result. NACE Int’l, 2016 WL

4486158, at *1. The other party maintained that the arbitration agreement was

illusory “because NACE effectively never agreed to submit itself to binding

20

arbitration when it reserved the right to pursue litigation if a ‘satisfactory

settlement’ is not reached by the arbitration process.” Id. at *3. The court

concluded that, “[b]ecause both NACE and Appellees must first arbitrate all claims

and neither can avoid that promise by amending or terminating the arbitration

clause, the arbitration agreement is not illusory.” Id. at *4.

The arbitration provision in this case provided that the parties would mediate

all disputes unless Griffin in its sole discretion believed that mediation would be

useless, in which case Griffin could escalate directly to arbitration. The agreement

did not allow Griffin to avoid arbitration; nor did it allow Griffin to litigate an

unsatisfactory arbitration result. We conclude that Griffin’s ability to unilaterally

bypass mediation in favor of arbitration did not render the arbitration provision

illusory. See id. at *4; Cleveland Constr., Inc. v. Levco Constr., Inc., 359 S.W.3d

843, 853-54 (Tex. App.—Houston [1st Dist.] 2012, pet. dism’d) (party’s promise

to arbitrate claims “at [its] option” did not make arbitration provision illusory); see

also In re Palm Harbor Homes, Inc., 195 S.W.3d 672, 678 (Tex. 2006) (orig.

proceeding) (rejecting argument that arbitration agreement was substantively

unconscionable because it bound homebuyers to arbitrate with the manufacturer

but did not bind the manufacturer to arbitrate with homebuyers).

Having concluded that the arbitration provision was not illusory, we further

agree with the trial court’s conclusion that, under the plain language of the parties’

agreement allowing Griffin the option to bypass mediation, mediation was not a

condition precedent to arbitration for Griffin. Cf. In re Pisces Foods, 228 S.W.3d

at 351 (mediation was a condition precedent where employment agreement

required mediation before arbitration and provided that the company was “also

mutually bound to use this program for any covered claim”).

21

III. Manifest Disregard and Gross Mistake

In its final issue, Southwinds argues that the arbitration award should be

vacated because it is tainted by manifest disregard of the law and gross mistake in

applying the law. Southwinds contends that the arbitrator manifestly disregarded

the law and made a gross mistake of law in deciding matters that were not covered

by a valid arbitration agreement.

Under the Texas Arbitration Act, “[u]nless grounds are offered for vacating,

modifying, or correcting an award under Section 171.088 or 171.091, the court, on

application of a party, shall confirm the award.” Tex. Civ. Prac. & Rem. Code

Ann. § 171.087 (Vernon 2011); see also Hoskins v. Hoskins, No. 15-0046, 2016

WL 2993929, at *4 (Tex. May 20, 2016) (“The statutory text could not be plainer:

the trial court ‘shall confirm’ an award unless vacatur is required under one of the

enumerated grounds in section 171.088.”). As the Supreme Court of Texas

explained in Hoskins: “[T]he [Texas Arbitration Act] leaves no room for courts to

expand on those grounds, which do not include an arbitrator’s manifest disregard

of the law.” Hoskins, 2016 WL 2993929, at *4. Neither is gross mistake a

statutory ground for vacating, modifying, or correcting an award under the Texas

Arbitration Act. Casa Del Mar Ass’n, Inc. v. Williams & Thomas, L.P., 476

S.W.3d 96, 100 (Tex. App.—Houston [14th Dist.] 2015, no pet.); see also Tex.

Civ. Prac. & Rem. Code Ann. §§ 171.088, .091 (Vernon 2011).

Likewise, neither gross mistake nor manifest disregard of the law is a basis

for vacating an arbitration award under the Federal Arbitration Act. See 9 U.S.C. §

10 (2012) (no mention of gross mistake or manifest disregard in grounds for

vacating an arbitration award under the Federal Arbitration Act); Hall St. Assocs.,

L.L.C. v. Mattel, Inc., 552 U.S. 576, 578 (2008) (holding that grounds stated in the

22

Federal Arbitration Act for vacating an arbitration award are exclusive); Casa Del

Mar Assoc., 476 S.W.3d at 99-100.

Accordingly, regardless of whether the Texas Arbitration Act or the Federal

Arbitration Act applied in this case, the trial court properly confirmed the

arbitrator’s award. See Citigroup Glob. Mkts., Inc. v. Bacon, 562 F.3d 349, 358

(5th Cir. 2009) (arbitration awards under the FAA may be vacated only under

statutory grounds, which do not include manifest disregard); Hoskins, 2016 WL

2993929, at *5 (“[T]he TAA mandates that, unless a statutory vacatur ground is

offered, the court shall confirm the award.”) (emphasis in original); Casa Del Mar

Assoc., 476 S.W.3d at 99-101; Ancor Holdings, LLC v. Peterson, Goldman &

Villani, Inc., 294 S.W.3d 818, 829 (Tex. App.—Dallas 2009, no pet.) (manifest

disregard and gross mistake are not grounds for vacatur under the FAA).

Additionally, because we have concluded above that a valid and enforceable

arbitration agreement covered all claims, including the C&D haul-off claims,

Southwinds’s argument that there was no valid arbitration agreement cannot form

the basis for any manifest disregard of the law or gross mistake in applying the law

on the part of the arbitrator.7

7

Southwinds also contends, without any supporting argument or case law, that the

arbitrator manifestly disregarded the law and made a gross mistake of law “in awarding attorney

fees and incidental damages under the contracts without any evidence.” As discussed above,

neither manifest disregard nor gross mistake are grounds for vacatur under either the Texas

Arbitration Act or the Federal Arbitration Act.

23

CONCLUSION

Having concluded that a valid and enforceable arbitration agreement existed

covering all claims between the parties and that Southwinds failed to demonstrate

any meritorious grounds for vacatur of the arbitrator’s award, we conclude that the

trial court properly confirmed the award. We affirm the trial court’s judgment.

/s/ William J. Boyce

Justice

Panel consists of Chief Justice Frost and Justices Boyce and Wise. (Frost, C.J.,

concurring).

24

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.