The opinion

Filed 9/19/16

IN THE SUPREME COURT OF CALIFORNIA

FRIENDS OF THE COLLEGE OF )

SAN MATEO GARDENS, )

)

Plaintiff and Respondent, )

) S214061

v. )

) Ct.App. 1/1 A135892

SAN MATEO COUNTY COMMUNITY )

COLLEGE DISTRICT et al., )

) San Mateo County

Defendants and Appellants. ) Super. Ct. No. CIV 508656

____________________________________)

To ensure that governmental agencies and the public are adequately

informed about the environmental impact of public decisions, the California

Environmental Quality Act (CEQA) (Pub. Resources Code, § 21000 et seq.)

requires a lead agency (id., § 21067) to prepare an environmental impact report

(EIR) before approving a new project that ―may have a significant effect on the

environment.‖ (Id., § 21151, subd. (a).) When changes are proposed to a project

for which an EIR has already been prepared, the agency must prepare a subsequent

or supplemental EIR only if the changes are ―[s]ubstantial‖ and require ―major

revisions‖ of the previous EIR. (Id., § 21166.) Guidelines promulgated by the

state Natural Resources Agency (Resources Agency) extend this subsequent

review framework to projects for which a negative declaration was initially

adopted, and no EIR prepared, because the agency had concluded the project

1

would have no potentially significant environmental effects. (Cal. Code Regs., tit.

14, § 15162; hereafter CEQA Guidelines.)

In this case, a community college district proposed a district-wide facilities

improvement plan that called for demolishing certain buildings and renovating

others. The district approved the plan after determining that it would have no

potentially significant, unmitigated effect on the environment. Years later, the

district proposed changes to the plan. The changes included a proposal to

demolish one building complex that had originally been slated for renovation, and

to renovate two other buildings that had originally been slated for demolition. The

district approved the changes after concluding they did not require the preparation

of a subsequent or supplemental EIR under Public Resources Code section 21166

(section 21166) and CEQA Guidelines section 15162. The Court of Appeal

invalidated the district‘s decision, finding it ―clear‖ as a matter of law that the

district‘s proposed demolition of the building complex was not merely a change to

its previously approved project, but a new project altogether. The court ruled that

the district‘s proposal was therefore subject to the initial environmental review

standards of Public Resources Code section 21151 (section 21151) rather than the

subsequent review standards of section 21166 and CEQA Guidelines section

15162.

We conclude that the Court of Appeal erred in its application of this new

project test. When an agency proposes changes to a previously approved project,

CEQA does not authorize courts to invalidate the agency‘s action based solely on

their own abstract evaluation of whether the agency‘s proposal is a new project,

rather than a modified version of an old one. Under the statutory scheme, the

agency‘s environmental review obligations depend on the effect of the proposed

changes on the decisionmaking process, rather than on any abstract

characterization of the project as ―new‖ or ―old.‖ An agency that proposes project

2

changes thus must determine whether the previous environmental document

retains any relevance in light of the proposed changes and, if so, whether major

revisions to the previous environmental document are nevertheless required due to

the involvement of new, previously unstudied significant environmental impacts.

These are determinations for the agency to make in the first instance, subject to

judicial review for substantial evidence.

I.

A.

―In CEQA, the Legislature sought to protect the environment by the

establishment of administrative procedures drafted to ‗[e]nsure that the long-term

protection of the environment shall be the guiding criterion in public decisions.‘ ‖

(No Oil, Inc. v. City of Los Angeles (1974) 13 Cal.3d 68, 74 (No Oil).) At the

―heart of CEQA‖ (CEQA Guidelines, § 15003, subd. (a)) is the requirement that

public agencies prepare an EIR for any ―project‖ that ―may have a significant

effect on the environment.‖ (§ 21151, subd. (a); see id., §§ 21080, subd. (a),

21100, subd. (a).) The purpose of the EIR is ―to provide public agencies and the

public in general with detailed information about the effect which a proposed

project is likely to have on the environment; to list ways in which the significant

effects of such a project might be minimized; and to indicate alternatives to such a

project.‖ (Pub. Resources Code, § 21061.) The EIR thus works to ―inform the

public and its responsible officials of the environmental consequences of their

decisions before they are made,‖ thereby protecting ― ‗not only the environment

but also informed self-government.‘ ‖ (Citizens of Goleta Valley v. Board of

Supervisors (1990) 52 Cal.3d 553, 564, quoting Laurel Heights Improvement

Assn. v. Regents of University of California (1988) 47 Cal.3d 376, 392 (Laurel

Heights).)

3

Under CEQA and its implementing guidelines, an agency generally

conducts an initial study to determine ―if the project may have a significant effect

on the environment.‖ (CEQA Guidelines, § 15063, subd. (a).) If there is

substantial evidence that the project may have a significant effect on the

environment, then the agency must prepare and certify an EIR before approving

the project. (No Oil, supra, 13 Cal.3d at p. 85; see also Pub. Resources Code,

§§ 21100 [state agencies], 21151 [local agencies].) On the other hand, no EIR is

required if the initial study reveals that ―there is no substantial evidence that the

project or any of its aspects may cause a significant effect on the environment.‖

(CEQA Guidelines, § 15063, subd. (b)(2).) The agency instead prepares a

negative declaration ―briefly describing the reasons that a proposed project . . .

will not have a significant effect on the environment and therefore does not require

the preparation of an EIR.‖ (Id., § 15371; see id., § 15070.) Even when an initial

study shows a project may have significant environmental effects, an EIR is not

always required. The public agency may instead prepare a mitigated negative

declaration (MND) if ―(1) revisions in the project plans . . . before the proposed

negative declaration and initial study are released for public review would avoid

the effects or mitigate the effects to a point where clearly no significant effect on

the environment would occur, and (2) there is no substantial evidence in light of

the whole record before the public agency that the project, as revised, may have a

significant effect on the environment.‖ (Pub. Resources Code, § 21064.5.)

For many projects, this is the end of the environmental review process. But

like all things in life, project plans are subject to change. When such changes

occur, section 21166 provides that ―no subsequent or supplemental environmental

impact report shall be required‖ unless at least one or more of the following

occurs: (1) ―[s]ubstantial changes are proposed in the project which will require

major revisions of the environmental impact report,‖ (2) there are ―[s]ubstantial

4

changes‖ to the project‘s circumstances that will require major revisions to the

EIR, or (3) new information becomes available. (§ 21166.)

Although section 21166 does not, by its terms, address cases in which a

negative declaration or an MND, rather than an EIR, has been prepared, CEQA

Guidelines section 15162 provides that no subsequent EIR is required either

―[w]hen an EIR has [previously] been certified or [when] a negative declaration

[has previously been] adopted for a project,‖ unless there are substantial changes

to a project or its circumstances that will require major revisions to the existing

EIR or negative declaration. (CEQA Guidelines, § 15162, subd. (a), italics added;

see also § 21166.) ―If changes to a project or its circumstances occur or new

information becomes available after adoption of a negative declaration,‖ and if no

subsequent EIR is required, the agency ―shall determine whether to prepare a

subsequent negative declaration, an addendum, or no further documentation.‖

(CEQA Guidelines, § 15162, subd. (b).) CEQA Guidelines further provide that an

agency must prepare an addendum to a previously certified EIR ―if some changes

or additions are necessary but none of the conditions described in Section 15162

calling for preparation of a subsequent EIR have occurred.‖ (Id., § 15164, subd.

(a).) An addendum to an adopted negative declaration ―may be prepared if only

minor technical changes or additions are necessary or none of the conditions

described in Section 15162 calling for the preparation of a subsequent EIR or

negative declaration have occurred.‖ (Id., § 15164, subd. (b).)

B.

This case arises from a series of proposed facilities improvements to a

college campus in San Mateo County. In 2006, the San Mateo Community

College District and its Board of Trustees (collectively, District) adopted a

facilities master plan (Plan) proposing nearly $1 billion in new construction and

facilities renovations at the District‘s three college campuses. At the College of

5

San Mateo (College), the District‘s Plan included a proposal to demolish certain

buildings and renovate others. The buildings slated for renovation included the

College‘s ―Building 20 complex,‖ which includes a small cast-in-place concrete

classroom and lab structure, greenhouse, lath house, surrounding garden space,

and an interior courtyard.

In 2006, the District published an initial study and mitigated negative

declaration analyzing the physical environmental effects of implementing the

Plan‘s proposed improvements at the College, including the proposed

rehabilitation of the Building 20 complex. The MND stated that, with the

implementation of certain mitigation measures, the Plan would not have a

significant effect on the environment. In 2007, the District certified its initial

study and adopted the 2006 MND.

When the District later failed to obtain funding for the planned Building 20

complex renovations, it re-evaluated the proposed renovation. In May 2011, the

District issued a notice of determination, indicating that it would instead demolish,

rather than renovate, the ―complex and replace it with parking lot, accessibility,

and landscaping improvements.‖ The District also proposed to renovate two other

buildings, buildings 15 and 17, that had previously been slated for demolition.

The District concluded a subsequent or supplemental EIR was not required.

It instead addressed the change through an addendum to its 2006 initial study and

MND, concluding that ―the project changes would not result in a new or

substantially more severe impact than disclosed in the 2006 [initial study and

mitigated negative declaration]. Therefore, an addendum . . . is the appropriate

CEQA documentation.‖ (San Mateo County Community College Dist., CEQA

Addendum: Evaluation of Project Change to Building 20 Complex (May 2011)

p. 20.)

6

The newly proposed demolition of the Building 20 complex, and

particularly the demolition of the complex‘s associated gardens, proved

controversial. Certain members of the public, as well as a number of College

students and faculty, vocally criticized the demolition proposal at public hearings.

The District nevertheless approved demolition of the Building 20 complex in

accordance with the addendum.

Plaintiff Friends of the College of San Mateo Gardens filed suit challenging

the approval. The District thereafter rescinded its original addendum and issued a

revised addendum in August 2011. The revised addendum reiterated the original

addendum‘s conclusion but bolstered its analysis. On August 24, 2011, after

public comment and discussion, the revised addendum was adopted and

demolition of the Building 20 complex was reapproved. Plaintiff voluntarily

dismissed its prior suit and filed the present action, challenging the revised

addendum and the reapproval of the demolition. Plaintiff sought a peremptory

writ of mandate ordering the District to set aside its approval of the Building 20

complex demolition and to fully comply with CEQA, including preparing an

adequate EIR and adopting feasible alternatives and mitigation measures. The

trial court found that the demolition project was inconsistent with the previously

approved plan and that its impacts were not addressed in the 2006 mitigated

negative declaration. The trial court thus granted plaintiff‘s petition for a writ of

mandate, ordering the District to refrain from taking further action adversely

affecting the physical environment at the Building 20 complex pending the

District‘s full compliance with CEQA.

The Court of Appeal affirmed. Relying primarily on Save Our

Neighborhood v. Lishman (2006) 140 Cal.App.4th 1288 (Save Our

Neighborhood), the court concluded, as a threshold matter of law, that the

proposed building demolition was a new project, rather than a project

7

modification. The court accordingly concluded that the agency is required to

engage in an initial study of the project to determine whether an EIR is required

under section 21151.

In so holding, the Court of Appeal deepened a disagreement among the

appellate courts concerning the reasoning of Save Our Neighborhood, supra, 140

Cal.App.4th 1288. In Save Our Neighborhood, the Court of Appeal invalidated an

agency‘s approval of a proposed modification to a project that had previously been

approved via negative declaration. Although the original project and the proposed

modification involved ―the same land and . . . similar mixes of uses,‖ there were a

number of differences. (Id. at p. 1300 [the original project was a 106-unit motel

that included some 15,000 square feet of other retail uses; the purported

modification was a 102-unit hotel that did not include any separate retail uses and

was sponsored by a different developer than the original project].) The court held

that the agency had erroneously relied on the statutory and regulatory provisions

governing the preparation of subsequent or supplemental EIRs because the

proposal was not a modification at all but rather a ―new project altogether.‖ (Id. at

p. 1301.) The court concluded that whether the proposal constituted a ―new

project‖ was ―a threshold question‖ of law and rejected the agency‘s determination

to treat the proposal as a modification after reviewing that question de novo.

(Ibid.)

Save Our Neighborhood was criticized in Mani Brothers Real Estate Group

v. City of Los Angeles (2007) 153 Cal.App.4th 1385, 1400 (Mani Brothers). In

Mani Brothers, the agency certified an EIR for an original project consisting of

―five buildings with . . . offices, a 550- to 770-room hotel, retail facilities, and an

optional cultural center.‖ (Id. at p. 1389.) Fifteen years later, the project‘s

developer proposed to revise the project, including by ―reduc[ing] much of the

[o]riginal [p]roject‘s office and retail space, and eliminat[ing] the optional culture

8

use component, while maintaining the hotel component and adding residential

components,‖ which increased the overall size of the project from ―approximately

2.7 million square feet to a maximum of just over 3.2 million square feet.‖ (Id. at

p. 1391.) The Mani Brothers court affirmed the agency‘s determination that the

proposal was a modification of an existing project and found the agency‘s

conclusion that no supplemental EIR was required to be supported by substantial

evidence. (Id. at pp. 1398–1399.) The court distinguished Save Our

Neighborhood, supra, 140 Cal.App.4th 1288, on the ground that it ―involved an

addendum to a previously certified negative declaration and not . . . an addendum

to a previously certified EIR.‖ (Mani Brothers, at p. 1400.) But the court also

opined that, even if it were not distinguishable, Save Our Neighborhood‘s

―fundamental analysis is flawed.‖ (Mani Brothers, at p. 1400.) The court

explained that Save Our Neighborhood‘s threshold ― ‗new project‘ test . . .

inappropriately bypassed otherwise applicable statutory and regulatory

provisions,‖ and ―undermine[d] the deference due the agency.‖ (Mani Brothers, at

pp. 1400–1401; see also Pub. Resources Code, § 21083.1.)

The Court of Appeal in this case acknowledged the disagreement between

Save Our Neighborhood and Mani Brothers. It concluded, however, that ―in the

narrow circumstances of the present case, where it is clear from the record that the

nature of the project has fundamentally and qualitatively changed to the point

where the new proposal is actually a new project altogether,‖ the approach

adopted in Save Our Neighborhood ―is both workable and sound.‖1 Here, the

1 Shortly after issuing its decision in this case, the same division of the Court

of Appeal issued a decision in which it declined to apply the Save Our

Neighborhood new project test to review a city‘s determination that changes to a

previously approved project did not require a supplemental or subsequent EIR.

(Latinos Unidos de Napa v. City of Napa (2013) 221 Cal.App.4th 192, 201–202.)

(Footnote continued on next page.)

9

court observed, the District‘s 2011 addendum ―changes ‗renovation‘ of the

Building 20 complex to ‗demolition‘ of the complex‘s buildings and a substantial

portion of the gardens.‖ The court concluded: ―[A]t least under the

straightforward facts of the present case we can decide, as a matter of law, that the

demolition project is a ‗new project.‘ ‖

The Court of Appeal acknowledged the District‘s argument that the

proposal to demolish the Building 20 complex is only one component of the

District‘s project, which, as revised, now proposes to renovate two buildings that

had previously been slated for demolition. Relying on Sierra Club v. County of

Sonoma (1992) 6 Cal.App.4th 1307 (Sierra Club), however, the Court of Appeal

concluded that when an agency initially adopts a broad, large-scale environmental

document — such as the 2006 MND here — that addresses the ―environmental

effects of a complex long-term management plan‖ (id. at p. 1316), a court can find

a material alteration regarding a particular site or activity covered by that plan to

be a new project triggering environmental review under section 21151.

II.

Once a project has been subject to environmental review and received

approval, section 21166 and CEQA Guidelines section 15162 limit the

circumstances under which a subsequent or supplemental EIR must be prepared.

These limitations are designed to balance CEQA‘s central purpose of promoting

consideration of the environmental consequences of public decisions with interests

(Footnote continued from previous page.)

Explaining that ― ‗a court should tread with extraordinary care before reversing a

local agency‘s determination about the environmental impact of changes to a

project,‘ ‖ the court instead ―elect[ed] to evaluate the City‘s decision to proceed

under section 21166 using the substantial evidence test.‖ (Id. at p. 202.)

10

in finality and efficiency. (See Bowman v. City of Petaluma (1986) 185

Cal.App.3d 1065, 1074 (Bowman).) Thus, as both Save Our Neighborhood and

Mani Brothers explained: ―The purpose behind the requirement of a subsequent

or supplemental EIR or negative declaration is to explore environmental impacts

not considered in the original environmental document. . . . The event of a change

in a project is not an occasion to revisit environmental concerns laid to rest in the

original analysis. Only changed circumstances . . . are at issue.‖ (Save Our

Neighborhood, supra, 140 Cal.App.4th at p. 1296; accord, Mani Brothers, supra,

153 Cal.App.4th at pp. 1398–1399.)

Consistent with these principles, section 21166 and CEQA Guidelines

section 15162 provide that an agency that proposes changes to a previously

approved project must determine whether the changes are ―[s]ubstantial‖ and ―will

require major revisions of the previous EIR or negative declaration due to the

involvement of new significant environmental effects or a substantial increase in

the severity of previously identified significant effects.‖ (CEQA Guidelines,

§ 15162, subd. (a)(1).) If the proposed changes meet that standard, then a

subsequent or supplemental EIR is required.

Drawing on the reasoning of Save Our Neighborhood, plaintiff argues that

implicit in the statutory and regulatory scheme is a threshold inquiry that

determines whether the subsequent review provisions properly apply in the first

place. Because section 21166 and CEQA Guidelines section 15162 both refer to

substantial changes to ―a project‖ — and not, as the Save Our Neighborhood court

observed, changes to ―a new project proposed for a site where a similar project

was previously approved‖ — a court reviewing an agency‘s proposed approval of

project changes must first satisfy itself that the project remains the same project as

before, rather than an entirely new project, before proceeding to evaluate whether

the changes call for a subsequent or supplemental EIR under CEQA‘s subsequent

11

review provisions. (Save Our Neighborhood, supra, 140 Cal.App.4th at p. 1297.)

Plaintiff further argues that whether an agency‘s proposal qualifies as a new

project is a question of law for courts to decide based on their independent

judgment. The premise of plaintiff‘s argument is sound, but its conclusions are

not.

Plaintiff is correct that the subsequent review provisions can apply only if

the project has been subject to initial review; they can have no application if the

agency has proposed a new project that has not previously been subject to review.

But plaintiff‘s approach would assign to courts the authority — indeed, the

obligation — to determine whether an agency‘s proposal qualifies as a new

project, in the absence of any standards to govern the inquiry. Plaintiff does not

suggest any standards, nor do the cases on which it relies. The Save Our

Neighborhood court simply asserted that the modified project proposal at issue

was a new project, pointing out that while the ―projects‖ at issue involved the

―same land‖ and a ―similar mix[] of uses,‖ they ―ha[d] different proponents and

there [was] no suggestion the latter project utilized any of the drawings or other

materials connected with the earlier project . . .‖ (Save Our Neighborhood, supra,

140 Cal.App.4th at p. 1300). The court neither purported to give any content to

the determination whether a proposal counts as a new project, nor did it explain

why the distinctions it identified make any difference for purposes of CEQA,

whose aim is simply to ―compel government . . . to make decisions with

environmental consequences in mind.‖ (Bozung v. Local Agency Formation Com.

(1975) 13 Cal.3d 263, 283.) The Court of Appeal in this case likewise offered no

standards to guide the inquiry, simply declaring it ―clear‖ that the proposal at issue

constituted a ―new project.‖

In the absence of any benchmark for measuring the newness of a given

project, the new project test plaintiff urges would inevitably invite arbitrary

12

results. As the Court of Appeal in Mani Brothers observed, to ask whether an

agency proposal constitutes a ― ‗new project‘ ‖ in the abstract ―does not provide an

objective or useful framework. Drastic changes to a project might be viewed by

some as transforming the project to a new project, while others may characterize

the same drastic changes in a project as resulting in a dramatically modified

project. Such labeling entails no specific guidelines and simply is not helpful to

our analysis.‖ (Mani Brothers, supra, 153 Cal.App.4th at p. 1400.)

What is more, to ask whether proposed agency action constitutes a new

project, purely in the abstract, misses the reason why the characterization matters

in the first place. The central purpose of CEQA is to ensure that agencies and the

public are adequately informed of the environmental effects of proposed agency

action. The subsequent review provisions, as Save Our Neighborhood recognized,

are accordingly designed to ensure that an agency that proposes changes to a

previously approved project ―explore[s] environmental impacts not considered in

the original environmental document.‖ (Save Our Neighborhood, supra, 140

Cal.App.4th at p. 1296.) This assumes that at least some of the environmental

impacts of the modified project were considered in the original environmental

document, such that the original document retains some relevance to the ongoing

decisionmaking process. A decision to proceed under CEQA‘s subsequent review

provisions must thus necessarily rest on a determination — whether implicit or

explicit — that the original environmental document retains some informational

value. If the proposed changes render the previous environmental document

wholly irrelevant to the decisionmaking process, then it is only logical that the

agency start from the beginning under section 21151 by conducting an initial study

to determine whether the project may have substantial effects on the environment.

It follows that, for purposes of determining whether an agency may proceed

under CEQA‘s subsequent review provisions, the question is not whether an

13

agency‘s proposed changes render a project new in an abstract sense. Nor does

the inquiry turn on the identity of the project proponent, the provenance of the

drawings, or other matters unrelated to the environmental consequences associated

with the project. (Cf. Save Our Neighborhood, supra, 140 Cal.App.4th at

p. 1300.) Rather, under CEQA, when there is a change in plans, circumstances, or

available information after a project has received initial approval, the agency‘s

environmental review obligations ―turn[] on the value of the new information to

the still pending decisionmaking process.‖ (Marsh v. Oregon Natural Resources

Council (1989) 490 U.S. 360, 374 (Marsh).)2 If the original environmental

document retains some informational value despite the proposed changes, then the

agency proceeds to decide under CEQA‘s subsequent review provisions whether

project changes will require major revisions to the original environmental

document because of the involvement of new, previously unconsidered significant

environmental effects. 3

2 In this respect, CEQA resembles the federal statute on which it was

modeled. (See Marsh, supra, 490 U.S. at p. 374 [agencies employ a ― ‗rule of

reason‘ ‖ in determining whether to issue a supplemental environmental impact

statement under the National Environmental Policy Act of 1969, 42 U.S.C. § 4321

et seq.]; Citizens of Goleta Valley v. Board of Supervisors, supra, 52 Cal.3d 553,

565, fn. 4 [―CEQA was modeled on the National Environmental Policy Act

(NEPA)‖ and ― ‗we have consistently treated judicial and administrative

interpretation of the latter enactment as persuasive authority in interpreting

CEQA.‘ ‖].)

3 As a practical matter, if proposed modifications have rendered the prior

environmental review wholly irrelevant to the ongoing decisionmaking process,

and if the modifications create potentially significant environmental impacts, the

two inquiries will yield substantially the same result: the agency must prepare an

EIR. Although CEQA distinguishes ―subsequent EIRs‖ (§ 21166) from initial

EIRs (see § 21151), both types of EIRs are subject to the same general procedural

and substantive requirements. (See generally Pub. Resources Code, § 21061

[defining environmental impact report]; see also id., §§ 21100, 21100.1

(Footnote continued on next page.)

14

This understanding of the relevant statutory framework supplies the

benchmark missing from the Court of Appeal‘s application of the new project test

in this case. It also exposes the court‘s error in treating the new project inquiry as

a question for the court‘s independent determination under a de novo standard.

Plaintiff, seeking to defend the court‘s chosen standard of review, likens the new

project inquiry to the inquiry whether a particular activity qualifies as a project

within the meaning of CEQA. (See Save Our Neighborhood, supra, 140

Cal.App.4th at p. 1297; cf. Save Tara v. City of West Hollywood (2008) 45 Cal.4th

116, 131; Muzzy Ranch Co. v. Solano County Airport Land Use Com. (2007) 41

Cal.4th 372, 382; Fullerton Joint Union High School Dist. v. State Bd. of

Education (1982) 32 Cal.3d 779, 795–798.) The comparison fails. Whether a

proposed activity is a project within the meaning of CEQA is, as we have

recognized, a predominantly legal question, for it depends on whether ―undisputed

data in the record on appeal‖ satisfy the detailed statutory definition of the term

―project.‖ (Muzzy Ranch Co., supra, 41 Cal.4th at p. 382, citing Pub. Resources

Code, § 21065 [defining ―project‖ as ―an activity which may cause either a direct

physical change in the environment, or a reasonably foreseeable indirect physical

change in the environment‖].) But whether an initial environmental document

remains relevant despite changed plans or circumstances — like the question

whether an initial environmental document requires major revisions due to

changed plans or circumstances — is a predominantly factual question. It is thus a

question for the agency to answer in the first instance, drawing on its particular

(Footnote continued from previous page.)

[information to be included], 21104, 21153 [consultation requirements], 21091–

21092 [public notice and comment].)

15

expertise. (Center for Biological Diversity v. Department of Fish & Wildlife

(2015) 62 Cal.4th 204, 215.) A court‘s task on review is then to decide whether

the agency‘s determination is supported by substantial evidence; the court‘s job

― ‗ ―is not to weigh conflicting evidence and determine who has the better

argument.‖ ‘ ‖ (Ibid.)

We expect occasions when a court finds no substantial evidence to support

an agency‘s decision to proceed under CEQA‘s subsequent review provisions will

be rare, and rightly so; ―a court should tread with extraordinary care‖ before

reversing an agency‘s determination, whether implicit or explicit, that its initial

environmental document retains some relevance to the decisionmaking process.

(Moss v. County of Humboldt (2008) 162 Cal.App.4th 1041, 1052, fn. 6.)4 But

this is only the first step. Once a court determines that substantial evidence

supports an agency‘s decision to proceed under CEQA‘s subsequent review

provisions (see § 21166; CEQA Guidelines, § 15162), the next — and critical —

step is to determine whether the agency has properly determined how to comply

with its obligations under those provisions. In particular, where, as here, the

agency has determined that project changes will not require ―major revisions‖ to

its initial environmental document, such that no subsequent or supplemental EIR is

required, the reviewing court must then proceed to ask whether substantial

evidence supports that determination. As explained below, judicial review must

reflect the exacting standard that an agency must apply when changes are made to

a project that has been approved via a negative declaration.

4 As noted, an agency‘s decision to proceed under CEQA‘s subsequent

review provisions necessarily incorporates an implicit conclusion that the original

environmental document retains at least some degree of relevance. Nothing in the

statute requires the agency to make an explicit finding to that effect.

16

III.

Perhaps anticipating our disagreement with the Court of Appeal‘s

formulation and application of Save Our Neighborhood‘s new project test,

plaintiff asks us to affirm the judgment below on the alternative ground that

CEQA‘s subsequent review provision, section 21166, applies only to projects for

which an initial EIR was prepared. Plaintiff urges us to hold that CEQA

Guidelines section 15162 is invalid to the extent that it extends the section 21166

subsequent review framework to projects that were initially approved via negative

declaration, like the campus improvement project at issue in this case.5

The Resources Agency, as the ―agency with primary responsibility for

statewide implementation of CEQA,‖ promulgated CEQA Guidelines section

15162 in accordance with its statutory obligation to establish guidelines for

CEQA‘s implementation. (California Building Industry Assn. v. Bay Area Air

Quality Management Dist. (2015) 62 Cal.4th 369, 378; see Pub. Resources Code,

§ 21083.) These Guidelines, we have said, are ―central to the statutory scheme‖;

they ―serve to make the CEQA process tractable for those who must administer it,

those who must comply with it, and ultimately, those members of the public who

must live with its consequences.‖ (California Building Industry Assn., supra, 62

Cal.4th at pp. 384–385.) Although we have ―not [yet] decided . . . whether the

Guidelines are regulatory mandates or only aids to interpreting CEQA‖ (Laurel

5 Plaintiff did not raise this issue in its response to the petition for review,

and indeed conceded in its opening brief that the ―point has not been at issue in

this case.‖ At oral argument, however, both parties focused on this issue rather

than on the issue on which we had granted review. Concluding that a full response

to the issue presented requires resolution of plaintiff‘s claim that CEQA

Guidelines section 15162 is invalid as applied to projects initially approved by

negative declaration, we solicited supplemental briefing from the parties and the

Resources Agency to address it.

17

Heights, supra, 47 Cal.3d at p. 391, fn. 2), we have nevertheless concluded that

the Guidelines are owed deference insofar as they reflect the agency‘s specialized

knowledge and expertise and were adopted through a process of notice and public

comment under the California Administrative Procedure Act. (California Building

Industry Assn., supra, 62 Cal.4th at pp. 381, 389–390.) Thus, we afford the

Guidelines ―great weight‖ unless a provision is ―clearly unauthorized or erroneous

under the statute.‖ (Id. at p. 381.)

Plaintiff argues that CEQA Guidelines section 15162 is clearly erroneous

because section 21166 is, by its terms, limited to projects for which an EIR has

been prepared. Plaintiff argues that the omission of any reference to negative

declarations reflects a legislative intent to exclude projects initially approved via

negative declaration from the subsequent review framework of section 21166, and

instead to require a new round of initial study each time changes are proposed in

project plans or circumstances. We disagree.

To begin with, the omission of any reference to negative declarations in

section 21166 is less revealing than plaintiff suggests. At the time section 21166

was enacted in 1972, no provision of CEQA referred to negative declarations; the

category of negative declarations originated with the Resources Agency‘s

promulgation of the first set of CEQA implementation guidelines the following

year. (See No Oil, supra, 13 Cal.3d at p. 74 and fn. 2, citing former Cal. Admin.

Code, tit. 14, § 15083 [adopted 1973].) The Legislature subsequently ratified this

innovation in 1976, when it amended CEQA to direct the Resources Agency to

―include objectives and criteria for . . . the preparation of environmental impact

reports and negative declarations.‖ (Pub. Resources Code, § 21083, subd. (a), as

amended by Stats. 2004, ch. 689, § 1, p. 5239, italics added.) Because, at the time

of section 21166‘s enactment, EIRs were the only type of environmental document

expressly referenced by CEQA‘s text, the Legislature could not have used the

18

phrase ―environmental impact report‖ in section 21166 with any specific intent to

exclude negative declarations from its scope.

Plaintiff directs our attention to the Legislature‘s 1977 amendments to

CEQA in Assembly Bill No. 884 (AB 884), which, among other things, amended

section 21166 to add a provision for the preparation of subsequent or supplemental

EIRs based on the discovery of new information. (See Stats. 1977, ch. 1200, § 16,

p. 4003.) Plaintiff observes that while the Legislature did not amend section

21166 to add a reference to negative declarations, it did add two statutory

provisions that do specifically refer to negative declarations. (See Pub. Resources

Code, § 21080.1 [―The lead agency shall be responsible for determining whether

an environmental impact report [or] a negative declaration . . . shall be required for

any project which is subject to [CEQA]. That determination shall be final and

conclusive on all persons . . . unless challenged as provided in Section 21167.‖];

id., § 21080.3, subd. (a) [―Prior to determining whether a negative declaration or

environmental impact report is required for a project, the lead agency shall consult

with all responsible agencies . . . .‖].) Plaintiff argues that the Legislature‘s failure

to add a similar reference to section 21166 demonstrates its intent to limit section

21166‘s reach to projects initially approved via EIR, and to treat any and all

changes to projects initially approved via negative declaration as though they were

entirely new projects for purposes of section 21151 review.

Plaintiff here places more weight on the 1977 amendments than they can

bear. Given that the Guidelines had already authorized the use of negative

declarations without express statutory authorization — a development the

Legislature had ratified the previous year — the Legislature simply may not have

perceived a need to add an express reference to negative declarations in section

21166. But in any event, when the 1977 amendments did refer to negative

declarations, it was in order to affirm that a lead agency‘s decision to proceed by

19

negative declaration is entitled to the same degree of finality as a decision to

proceed by EIR. (Pub. Resources Code, § 21080.1.) In light of that provision,

plaintiff‘s reading of the 1977 amendments — as implicitly requiring agencies to

start the environmental review process over each time there is a change in plans or

circumstances, no matter how minor — is an unlikely one.

Ultimately, plaintiff‘s argument simply highlights a gap in CEQA‘s

statutory structure. No provision of CEQA directly addresses the subsequent

environmental review obligations for projects that were initially approved via

negative declaration. CEQA authorizes the Resources Agency to fill such gaps

in the statutory scheme, so long as it does so in a manner consistent with the

statute. (See Pub. Resources Code, §§ 21082–21083; City of Santa Ana v. City

of Garden Grove (1979) 100 Cal.App.3d 521, 529 [the CEQA ―statute

empowers [the] administrative agency to exercise a judgment of high order in

implementing legislative policy‖].) And in the year following the 1977

amendments, the Resources Agency filled that gap by extending the predecessor

to CEQA Guidelines section 15162 to projects initially approved by negative

declaration. (See former Cal. Admin. Code, tit. 14, § 15067 [adopted 1978].)

Limiting agencies‘ postapproval review obligations for projects that were

initially approved via negative declaration is wholly consistent with a statutory

scheme in which negative declarations, no less than EIRs, are entitled to a

presumption of finality once adopted. (See Pub. Resources Code, § 21080.1, subd.

(a).) As explained in Benton v. Board of Supervisors (1991) 226 Cal.App.3d

1467, 1479–1480 (Benton): ―In a case in which an initial EIR has been certified,

section 21166 comes into play precisely because in-depth review of the project has

already occurred, the time for challenging the sufficiency of the original CEQA

document has long since expired, and the question before the agency is whether

circumstances have changed enough to justify repeating a substantial portion of

20

the process. [Citations.] These same principles apply with even greater force in a

case such as this,‖ in which the project ―initially raised so few environmental

questions that an EIR was not required, but a negative declaration was found to

satisfy the environmental review requirements of CEQA.‖ The alternative that

plaintiff proposes — which would restart the CEQA process every time plans or

circumstances change, or whenever new information comes to light — ―would

render agency decisionmaking intractable, always awaiting updated information

only to find the new information outdated by the time a decision is made.‖

(Marsh, supra, 490 U.S. at p. 373; see also Laurel Heights, supra, 47 Cal.3d at

p. 396 [noting the original environmental review process includes consideration of

reasonably foreseeable future expansions to the project, and that subsequent EIRs

are necessary when evaluating future action not considered in the initial review].)

The Resources Agency did not act unreasonably in concluding that the statutory

scheme calls for some limitations on postapproval environmental review of

projects initially approved via negative declaration.

Plaintiff‘s stronger arguments do not concern the Guidelines‘ limitations of

postapproval environmental review as such, but instead focus on the substance of

the limitations the Guidelines prescribe. As plaintiff points out, when an agency

initially proposes a project, an EIR is required ―whenever it can be fairly argued

on the basis of substantial evidence that [a] project may have significant

environmental impact.‖ (No Oil, supra, 13 Cal.3d at p. 75; see Pub. Resources

Code, § 21082.2, subd. (a) [requiring an EIR when a project ―may‖ have a

significant effect on the environment]; accord, § 21151, subd. (a).) Thus, when a

reviewing court evaluates an agency‘s initial determination whether to proceed

with an EIR, the court‘s function is ―to determine whether substantial evidence

supported the agency‘s conclusion as to whether the prescribed ‗fair argument‘

could be made. If there was substantial evidence that the proposed project might

21

have a significant environmental impact, evidence to the contrary is not sufficient

to support a decision to dispense with preparation of an EIR . . . because it could

be ‗fairly argued‘ that the project might have a significant environmental impact.‖

(Friends of “B” Street v. City of Hayward (1980) 106 Cal.App.3d 988, 1002; see

Bowman, supra, 185 Cal.App.3d at p. 1073 [― ‗fair argument‘ ‖ test is a question

of law, permitting the court‘s independent analysis of the sufficiency of the

evidence].) By contrast, when an agency proposes changes to a previously

approved project, CEQA Guidelines section 15162 generally prohibits the agency

from requiring a subsequent or supplemental EIR unless the agency determines,

―on the basis of substantial evidence in the light of the whole record,‖ that

―[s]ubstantial changes . . . will require major revisions of the previous EIR or

negative declaration due to the involvement of new significant environmental

effects or a substantial increase in the severity of previously identified significant

effects.‖ (CEQA Guidelines, § 15162, subd. (a).) Plaintiff argues that application

of this substantial evidence standard to projects initially approved via negative

declaration creates a loophole in the statutory scheme, allowing agencies to evade

their obligation to prepare an EIR based on the more demanding ―fair argument‖

standard, so long as the potential environmental effects of the project are caused

by changes in the project after a negative declaration had been approved.

Plaintiff‘s argument would have force if the Guidelines did, in fact, create

such a loophole. But the substantial evidence test referred to in the Guidelines

does not, as plaintiff supposes, refer to substantial evidence that the project, as

modified, will necessarily have significant environmental effects. It instead refers

to substantial evidence that the proposed modifications will involve ―[s]ubstantial

changes‖ that ―require major revisions of the previous EIR or negative declaration

due to the involvement‖ of new or significantly more severe environmental

effects. (CEQA Guidelines, § 15162, subd. (a); see id., § 15384 [defining

22

―substantial evidence‖].) The distinction is important here, because whether

―major revisions‖ will be required as a result of project changes necessarily

depends on the nature of the original environmental document. A negative

declaration is permitted when ―there is no substantial evidence that the project or

any of its aspects may cause a significant effect on the environment‖ (CEQA

Guidelines, § 15063, subd. (b)(2), italics added; see also Pub. Resources Code,

§§ 21151, 21064.5), whereas an EIR is required when a project and project

alternatives may have significant effects (id., § 21002.1, subd. (a)). When there is

a proposal to modify a project originally approved through EIR, no ―major

revision‖ to the initial EIR is required if the initial EIR already adequately

addresses any additional environmental effects that may be caused by the

proposed modification. In contrast, when a project is initially approved by

negative declaration, a ―major revision‖ to the initial negative declaration will

necessarily be required if the proposed modification may produce a significant

environmental effect that had not previously been studied. (CEQA Guidelines,

§ 15162.) Indeed, if the project modification introduces previously unstudied and

potentially significant environmental effects that cannot be avoided or mitigated

through further revisions to the project plans, then the appropriate environmental

document would no longer be a negative declaration at all, but an EIR.6

6 We recognize that language in the appellate cases might be read as applying

a different rule. In Benton, supra, 226 Cal.App.3d 1467, for example, the Court of

Appeal considered whether a proposal to relocate a winery that had previously

been approved via negative declaration required the preparation of a subsequent or

supplemental EIR. Benton held that, under CEQA Guidelines section 15162, the

question whether a subsequent or supplemental EIR was required depended on the

effect of the proposed relocation; the changes were not an occasion to reopen the

original environmental review of the winery project. (Benton, at pp. 1482–1484.)

As the Court of Appeal in Abatti v. Imperial Irrigation Dist. (2012) 205

Cal.App.4th 650 later observed, ―the central premise of Benton [is] that it makes

(Footnote continued on next page.)

23

In short, the substantial evidence standard prescribed by CEQA Guidelines

section 15162 requires an agency to prepare an EIR whenever there is substantial

evidence that the changes to a project for which a negative declaration was

previously approved might have a significant environmental impact not previously

considered in connection with the project as originally approved, and courts must

enforce that standard. (See Friends of “B” Street v. City of Hayward, supra, 106

Cal.App.3d at p. 1002.) It therefore does not permit agencies to avoid their

obligation to prepare subsequent or supplemental EIRs to address new, and

previously unstudied, potentially significant environmental effects. So

understood, CEQA Guidelines section 15162 constitutes a valid gap-filling

(Footnote continued from previous page.)

little sense to set a lower threshold for further environmental review of a project

that is determined not to have a significant effect on the environment than section

21166 sets for a project that may have significant effects on the environment.‖

(Abatti, at p. 673 [agreeing with the ―central premise‖ of Benton].) Benton‘s

longstanding interpretation has been followed by courts and the Resources Agency

and is a correct statement of the law insofar as it recognizes that negative

declarations, like EIRs, are entitled to a presumption of finality; it would, as

Benton says, be ―absurd‖ to require agencies to restart the entire process of

environmental review from scratch each time the agency proposes any change, no

matter how minor, simply because the project was previously approved by

negative declaration. (Benton, supra, 226 Cal.App.3d at p. 1480.) But Benton

went on to conclude that no subsequent or supplemental EIR was required in that

case because, among other things, substantial evidence supported the agency‘s

conclusion that ―[t]he environmental impacts of the modification were not

significant . . . .‖ (Id. at p. 1483.) As seen, however, the inquiry prescribed by the

Guidelines is not whether the environmental impacts of the modification are

significant, but whether the modification requires major revisions to the negative

declaration because of the involvement of new, potentially significant

environmental effects that had not previously been considered in connection with

the earlier environmental study.

24

measure as applied to projects initially approved via negative declaration,

including the project at issue in this case.

IV.

Finally, plaintiff contends that both section 21166 and CEQA Guidelines

section 15162 are inapplicable because the District‘s initially approved project is

akin to a plan, a phased project, or a program rather than a simple project. Relying

on Sierra Club, supra, 6 Cal.App.4th 1307, plaintiff argues that the District‘s

proposed changes to the plans for the Building 20 complex should therefore be

treated as a new site-specific project that triggers new environmental review under

CEQA‘s provisions for so-called ―tiered‖ EIRs. (See Pub. Resources Code,

§§ 21068.5, 21094.) The Court of Appeal appeared to accept this argument as

further support for its conclusion that the project changes at issue may be

considered a new project under a de novo standard of review. The argument also

fails, however, because the tiering provisions — and therefore Sierra Club, supra,

6 Cal.App.4th 1307 (involving a tiered EIR) — have no direct application here.

Unlike ―[p]roject EIR[s],‖ which ―examine[] the environmental impacts of

a specific development project‖ (CEQA Guidelines, § 15161), the CEQA

provisions governing tiered EIRs ―permit[] the environmental analysis for long-

term, multipart projects to be ‗tiered,‘ so that the broad overall impacts analyzed in

an EIR at the first-tier programmatic level need not be reassessed as each of the

project‘s subsequent, narrower phases is approved.‖ (Vineyard Area Citizens for

Responsible Growth, Inc. v. City of Rancho Cordova (2007) 40 Cal.4th 412, 429

(Vineyard Area Citizens); see CEQA Guidelines, § 15152 [― ‗Tiering‘ refers to

using the analysis of general matters contained in a broader EIR (such as one

prepared for a general plan or policy statement) with later EIRs and negative

declarations on narrower projects; incorporating by reference the general

25

discussions from the broader EIR; and concentrating the later EIR or negative

declaration solely on the issues specific to the later project.‖].)

―The standard for determining whether to engage in additional CEQA

review for subsequent projects under a tiered EIR is more relaxed than the

prohibition against additional review imposed by Public Resources Code section

21166 for project EIR‘s.‖ (Friends of Mammoth v. Town of Mammoth Lakes

Redevelopment Agency (2000) 82 Cal.App.4th 511, 528.) For project EIRs, of

course, a subsequent or supplemental impact report is required in the event there

are substantial changes to the project or its circumstances, or in the event of

material new and previously unavailable information. (Ibid., citing § 21166.) In

contrast, when a tiered EIR has been prepared, review of a subsequent project

proposal is more searching. If the subsequent project is consistent with the

program or plan for which the EIR was certified, then ―CEQA requires a lead

agency to prepare an initial study to determine if the later project may cause

significant environmental effects not examined in the first tier EIR.‖ (Ibid., citing

Pub. Resources Code, § 21094, subds. (a), (c).) ―If the subsequent project is not

consistent with the program or plan, it is treated as a new project and must be fully

analyzed in a project—or another tiered EIR if it may have a significant effect on

the environment.‖ (Friends of Mammoth, at pp. 528–529.)

In Sierra Club, on which plaintiff relies, a county approved a project

through a program EIR, a type of tiered EIR where the agency first analyzes

―general matters contained in a broader [initial] EIR . . . with later EIRs and

negative declarations [analyzing] narrow projects.‖ (CEQA Guidelines, § 15152,

subd. (a); see id., § 15168.) The Sierra Club court concluded that when a program

EIR is employed, if a later proposal is not ―either the same as or within the scope

of the project . . . described in the program EIR,‖ then review of the proposal is

not governed by section 21166‘s deferential substantial evidence standard. (Sierra

26

Club, supra, 6 Cal.App.4th at p. 1321, citing CEQA Guidelines, § 15168, subd.

(c)(5).) Instead, under Public Resources Code section 21094, the agency is

required to apply a more exacting standard to determine whether the later project

might cause significant environmental effects that were not fully examined in the

initial program EIR. (Sierra Club, at p. 1321; Pub. Resources Code, § 21094,

subd. (c).)

Unlike the program EIR at issue in Sierra Club, the 2006 initial study and

MND were not a tiered EIR. The District‘s 2006 initial study and MND did not

purport ―to defer analysis of certain details of later phases of long-term linked or

complex projects until those phases are up for approval.‖ (Vineyard Area Citizens,

supra, 40 Cal.4th at p. 431.) The District‘s initial environmental review

documents instead expressly concluded that ―all potential impacts‖ of the entire

project — including every building on the campus — had ―been mitigated to a

point where no significant impacts would occur, and there is no substantial

evidence the project would have a significant effect on the environment.‖ (San

Mateo County Community College Dist., Proposed Mitigated Negative

Declaration (Dec. 20, 2006) p. 2; see also San Mateo County Community College

Dist., Initial Study and Mitigated Negative Declaration for Facility Improvements

at College of San Mateo (Dec. 2006) p. 2 [describing the project and various

encompassed improvements, including those related to the Building 20 complex].)

To now entertain the argument that the 2006 MND should be treated as a tiered

EIR would disregard the substance of the District‘s conclusions in order to permit

plaintiff to raise an untimely challenge as to the adequacy of the MND, as well as

the District‘s decision to proceed by MND in the first place.

V.

Our conclusion today does not end this case. Plaintiff argues that even if

the proposed changes to the earlier-approved project do not render it a new project

27

altogether, the District abused its discretion in approving the Building 20 complex

demolition based on the 2006 MND and the 2011 addendum. Plaintiff also argues

that CEQA Guidelines sections 15162 through 15164 improperly authorize lead

agencies to approve certain proposed project modifications through the use of

addenda without public comment, rather than requiring the issuance of a

subsequent or supplemental EIR or negative declaration. The Court of Appeal did

not address these questions, nor are they fairly encompassed by the question on

which we granted review, and we accordingly express no view on them.

VI.

We reverse the judgment of the Court of Appeal and remand for further

proceedings consistent with this opinion.

KRUGER, J.

WE CONCUR:

CANTIL-SAKAUYE, C. J.

WERDEGAR, J.

CHIN, J.

CORRIGAN, J.

LIU, J.

CUÉLLAR, J.

28

See next page for addresses and telephone numbers for counsel who argued in Supreme Court.

Name of Opinion Friends of College of San Mateo Gardens v. San Mateo Co. Community College

__________________________________________________________________________________

Unpublished Opinion XXX NP opn. filed 9/26/13, 1st Dist., Div. 1

Original Appeal

Original Proceeding

Review Granted

Rehearing Granted

__________________________________________________________________________________

Opinion No. S214061

Date Filed: September 19, 2016

__________________________________________________________________________________

Court: Superior

County: San Mateo

Judge: Clifford Cretan

__________________________________________________________________________________

Counsel:

Eugene Whitlock, County Counsel; Remy Moose Manley, James G. Moose, Sabrina V. Teller and John T.

Wheat for Defendants and Appellants.

Cox, Castle & Nicholson, Andrew B. Sabey and Linda C. Klein for California Building Industry

Association, Building Industry Association of the Bay Area and California Business Properties Association

as Amici Curiae on behalf of Defendants and Appellants.

Michael W. Graf for High Sierra Rural Alliance as Amicus Curiae on behalf of Defendants and Appellants.

Downey Brand, Christian L. Marsh, Andrea P. Clark and Amanda M. Pearson for League of California

Cities, California State Association of Counties and Association of California Water Agencies as Amici

Curiae on behalf of Defendants and Appellants.

Charles F. Robinson, Kelly L. Drumm; Holland & Knight, Amanda Monchamp and Joanna Meldrum for

The Regents of the University of California as Amicus Curiae on behalf of Defendants and Appellants.

Brandt-Hawley Law Group and Susan Brandt-Hawley for Plaintiff and Respondent.

Chatten-Brown & Carstens, Jan Chatten-Brown , Amy Minteer and Josh Chatten-Brown for California

Preservation Foundation as Amicus Curiae on behalf of Plaintiff and Respondent.

Law Office of Sara Hedgpeth-Harris, Inc., and Sara Hedgpeth-Harris for Association of Irritated Residents,

Madera Oversight Coalition, Revive the San Joaquin and Sierra Club as Amici Curiae on behalf of Plaintiff

and Respondent.

Kamala D. Harris, Attorney General, Robert W. Byrne, Assistant Attorney General, Tracy L. Winsor and

Jeffrey P. Reusch, Deputy Attorneys General, for California Natural Resources Agency and Governor‘s

Office of Planning and Research as Amici Curiae.

Counsel who argued in Supreme Court (not intended for publication with opinion):

Sabrina V. Teller

Remy Moose Manley

555 Capitol Mall, Suite 800

Sacramento, CA 95814

(916) 443-2745

Susan Brandt-Hawley

Brandt-Hawley Law Group

P.O. Box 1659

Glen Ellen, CA 95442

(707) 938-3900