The opinion

IToke, J.

It has been repeatedly held in the State that the beneficiaries of an indemnity contract ordinarily can recover though not named therein, “when it appears by express stipulation or by fair and reasonable intendment that their rights and interests were being provided for.”

Supply Co. v. Lumber Co.,

160 N. C., 428 ;

Withers v. Poe,

167 N. C., 372 ;

Voorhees v. Porter,

134 N. C., 591 ;

Town of Gastonia v. Engineering Co.,

131 N. C., 363 , and

Gorrell v. Water Co.,

124 N. C.,

*587

328. And so stated the principle has been fully approved in the more recent cases of

Lumber Co. v. Johnson,

177 N. C., 44 -47;

Crumpler v. Hines,

174 N. C., 283 ;

McCausland v. Construction Co.,

172 N. C., 708 -711. Speaking more minutely to some of the cases, and the question directly decided therein it is said in

McCausland v. Construction Co., supra:

“In case of building contracts with bonds guaranteeing the performance on the part of the contractor, it is held that in determining the question of the sureties’ liability to third persons, the contract and bond shall be construed together.

Mfg. Co. v. Andrews,

165 N. C., 285 , and recoveries on the part of claimants of that character, usually laborers and material men, not expressly named, are sustained where it appears that the guarantee bond, in express terms, provides for liability to such persons, as in

Morton v. Water Co., supra; Gorrell v. Water Co., supra,

or when there is stipulation that claims of this kind shall be paid by the contractor, the case presented in

Supply Co. v. Lumber Co., supra,

and

Gastonia v. Engineering Co.,

an application of the principle approved by many authoritative decisions elsewhere.

Knight & Jillson Co. v. Arthur Castle,

172 Ind., 97 ; reported also in 42 L. R. A., U. S., 573, with note by the editor.

Ocho v. Carnahan Co.,

42 Ind. App., 157 ;

Brown v. Markland,

22 Ind. App., 652 ;

Jordan v. Kavanaugh,

63 Iowa, 152 , and cases cited in note to

Cleveland Roofing Co. v. Gaspard,

Anno. Cases, 1916 A, 39 vol., pp. 745-758, or where the language of the instrument is sufficiently ambiguous to permit of construction, and the terms of the obligation and the attendant facts and circumstances, relevant and permissible in their proper interpretation, show by fair and reasonable intendment that claimants of that character are to be provided for; an instance presented in

Shoaf v. Ins. Co.,

127 N. C., 308 , and the cases of

Voorhees v. Porter

and

Withers v. Poe

may be referred in part to same position.”

The instant case is well nigh exactly similar to that of

Supply Co. v. Lumber Co., supra,

and considering the present contract and bond in view of these authorities, and the principles they approve and illustrate, we are of opinion that they clearly extend to the claim of plaintiff, and that liability therefor has been properly adjudged against the surety.

In

McGausland’s

case the surety was relieved, but that was because the bond in that case, as affected by the contract and other circumstances pertinent to its true construction, appeared to be one in strictness of indemnity toward the owner, and in which the interests of third persons, materialmen, or others, were in no way contemplated or provided for.

We

find no error in the record, and the judgment for plaintiff is affirmed.

No error.