Opinion

Msc Industrial Direct Co., Inc. v. United States

  • 126 Fed. Cl. 525
  • 2016 WL 2609685
Court
United States Court of Federal Claims
Filed
May 6, 2016
Status
Published
Author
Bruggink
On the bench
Bruggink
Cited by
3 cases
Authority
More cited than 46.4%

“The considerations brought to bear when it is the agency’s own procurement needs that prompt corrective action are fundamentally different from a situation in which a competitor alleges that corrective action is warranted by potential prejudice to it.”

How later courts described this case

  • “The considerations brought to bear when it is the agency’s own procurement needs that prompt corrective action are fundamentally different from a situation in which a competitor alleges that corrective action is warranted by potential prejudice to it.”
  • “A discrepancy as significant as the delivery date is more than sufficient to warrant an amendment to the solicitation.”

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

No. 15-1409C

(Originally Filed: May 3, 2016)

(Re-Filed: May 6, 2016)1

********************

MSC INDUSTRIAL DIRECT CO., INC.

Plaintiff,

v. Bid Protest; Pre-Award;

Corrective Action;

Federal Supply Schedule;

THE UNITED STATES, Blanket Purchase

Agreement, FAR 8.405-

Defendant, 3; AbilityOne Program

and

W. W. GRAINGER, INC.

Defendant-Intervenor.

********************

Joseph P. Hornyak, McLean, VA, for plaintiff, with whom were

Gregory R. Hallmark, McLean, VA, and Denisse S. Velarde-Cubek, McLean,

VA, of counsel.

Jeffrey D. Klingman, Trial Attorney, Department of Justice, Civil

Division, Commercial Litigation Branch, Washington, DC, for defendant, with

whom were Benjamin C. Mizer, Principal Deputy Assistant Attorney General,

Robert E. Kirschman, Jr., Director, Douglas K. Mickle, Assistant Director, and

Alissa Schrider, Assistant General Counsel, Personal Property Division, Office

of General Counsel, General Services Administration, of counsel.

1

This opinion was originally filed under seal. The parties were directed to

confer and propose redactions. The court adopted the parties’ suggested

redactions, removed the information, and inserted brackets to replace the

redacted content. The opinion is now prepared for release.

Anne B. Perry, Washington, DC, for intervenor, with whom were

Jonathan S. Aronie, Washington, DC, David S. Gallacher, Washington, DC,

and Matthew W. Turetzky, Washington, DC, of counsel.

_______________

OPINION

_______________

BRUGGINK, Judge.

This is a post-award protest of a corrective action decision taken by the

General Services Administration (“GSA” or “the agency”) in response to a

Government Accountability Office (“GAO”) protest by W.W. Grainger, Inc.

(“Grainger”) following the award of two blanket purchase agreement (“BPA”)

modifications to MSC Industrial Direct Co., Inc. (“MSC”). Specifically, MSC

protests GSA’s decision to (1) terminate the awards of the BPA modifications

to MSC under Request for Quotations (“RFQ”) No. QS0A-4PL-150014; (2)

amend the RFQ to correct an asserted misstatement of a requirement; (3) invite

competitors to submit revised quotations; and (4) make a new award decision.

Pending are the parties’ cross-motions for judgment on the administrative

record pursuant to Rule 52.1 of the Rules of the Court of Federal Claims

(“RCFC”) and intervenor’s motion to dismiss pursuant to RCFC 12(b)(1) and

12(b)(6). The motions are fully briefed, and oral argument was held on April

29, 2016. As announced at the conclusion of oral argument, and for the reasons

set out herein, we deny plaintiff’s motion and grant defendant’s and

intervenor’s motions for judgment on the administrative record. Intervenor’s

motion to dismiss is denied as moot.

BACKGROUND

The GSA Office of General Supplies and Services (“GSS”) is

responsible for acquisition services and comprehensive supply chain

management. One of its divisions, Retail Operations, manages GSS’s fourth-

party logistics (“4PL”) solutions program. This program is designed to provide

supply solutions to client organizations.

The Federal Supply Schedule (“FSS”), also known as the GSA

Schedules Program or the Multiple Award Schedule Program (“MAS”),

provides federal agencies with a simplified process for obtaining commonly

used commercial supplies and services. GSA schedule contracts require all

2

contractors to publish an “Authorized Federal Supply Schedule Pricelist,”

which contains all supplies and services offered by a contractor. BPAs may be

established under FSS contracts “to fill repetitive needs for supplies or

services.” FAR 8.405-3(a)(1).

Sometime prior to December 2013, a number of Command Fleet

Readiness Centers (“COMFRC”) and DLA Aviation Fleet Readiness Centers

(“FRC”) requested the 4PL program. In order to provide supply services to the

FRCs, GSA Retail Operations issued an RFQ on December 9, 2013, for the

purpose of establishing multiple BPAs with existing MAS vendors to provide

and manage inventory within the FRCs.

On June 16, 2014, GSA established BPAs with four vendors: MSC,

Grainger, [ ], and [ ]. All four vendors have contracts pursuant to FSS

Schedule 51V, which covers hardware supply needs. The BPAs did not

authorize vendors to begin supplying products; instead, they provided that

GSA would issue a competitive RFQ and would award two BPA modifications

to the vendor(s) whose quotations represented the best value to the

government.

The BPAs contemplated that the awardee vendors would establish

physical storefronts for the purpose of stocking and managing industrial

product inventory for military FRCs. Vendors would also be required to fill in-

store “referral” orders of items from the vendor’s catalog which were not

currently stocked in the store and allow for on-line “referral” ordering. The

BPAs provided that “[d]elivery is required no later than 3 calendar days after

receipt of order.” Administrative Record (“AR”) 31. Further, the vendor was

to maintain a fill rate for in-store/online referral and web ordering of 95%. AR

43. This rate is “based upon the maximum time interval (in business days)

from the issuance of the order to the date that the order is delivered.” Id.

The modifications required vendors to “ensure that no item which is

essentially the same as an AbilityOne item be sold to a Government customer,”

and to delete “all items, terms and conditions not accepted by the Government,

including items Essentially-the-Same (“ETS”) as AbilityOne products” from

print and electronic catalogs. AR 123-24.2

2

The AbilityOne program is authorized by the Javits-Wagner-O’Day Act “to

(continued...)

3

RFQ QS0A-4PL-150014 was issued in February 2015.3 Its purpose was

to “acquire support for GSA [] end-to-end supply chain management

requirements (Issue Points) for the Distribution Centers and Supply Storage

Centers” for FRCs in Jacksonville, Florida (“FRCSE”), Oceana and Norfolk,

Virginia (“FRCMA”), Cherry Point, North Carolina (“FRCE”), and San Diego,

California (“FRCSW”). AR 284. The RFQ contemplated that two BPA

modifications would be awarded one for FRCSE, FRCMA, and FRCE, and

a second for FRCSW. The statement of work provided that the BPA holder

would supply the line of tools and industrial products for the FRCs’

Distribution Centers, Supply Storage locations, Master Tool Room

Warehouses, Safety Crib Warehouses, and Facilities Maintenance Warehouses.

Id. Unlike the BPA, the RFQ did not mention a three-calendar-day delivery

requirement for referral orders.

The evaluation was based on price and non-price factors. The non-price

factors, in order of importance, were: Specific Technical Expertise-Supply

Chain System Capability, Past Performance, and Local and Small Business

Utilization Plan. AR 297-98. These factors, when combined, were significantly

more important than price. Id. For the price evaluation, the RFQ instructed

BPA holders to quote prices for 548 commonly purchased items, called the

“market basket.” AR 296. The evaluation would involve a comparison of each

vendor’s proposed unit pricing for the market basket items. However, the

bidders were not expected to submit price quotations for all 548 items; thus,

only the common items submitted would be evaluated. The evaluation would

2

(...continued)

increase employment and training opportunities for persons who are blind or

have other severe disabilities through Government purchasing of commodities

and services from nonprofit agencies employing these persons.” 41 C.F.R. §

51-1.3 (2016). This program is administered by the Committee for Purchase

from People Who Are Blind or Severely Disabled. The Committee maintains

and publishes in the Federal Register a procurement list that includes items

which must be procured from “a qualified nonprofit agency for the blind or .

. . a qualified nonprofit agency for other severely disabled.” 41 U.S.C. §

8503(a)(1) (2012). Federal agencies intending to procure an item on the list

must purchase it from a qualified nonprofit agency, if available. § 8504(a).

3

The RFQ was amended several times during March 2015 prior to the initial

submission of proposals.

4

be “based on offered discount from BPA prices, including the weighted

average of the discounts proposed for the three sales volume tiers.” AR 111.

Both MSC and Grainger submitted quotations in response to the RFQ

on March 11, 2015. MSC’s quotation provided that it is able to deliver orders

anywhere in the contiguous 48 United States within three business days after

receipt of order. Grainger’s quotation stated that it can “provide 24-48 hour

shipment times on most referral orders” and that “items requested for pick-up

that are not immediately available at the On-Site location will be shipped for

next day pick-up from the supporting [distribution center].” AR 459, 468.

The quotations were evaluated during March and April 2015. Grainger

and MSC were given the same ratings for all of the non-price factors. AR 950-

60. During the price evaluation, it was determined that MSC’s price was

approximately 23% lower than Grainger’s price. AR 961-66. The contracting

officer therefore determined that MSC’s quotation represented the best value

to the government. AR 966. On May 4, 2015, GSA awarded the BPA

modifications to MSC. The contracting officer subsequently notified Grainger

of the award decision and informed Grainger that MSC’s price was

approximately 23% lower than Grainger’s. AR 972.

On May 13, 2015, Grainger filed a protest at GAO, challenging GSA’s

award of the BPA modifications to MSC on grounds not relevant to the current

protest. On June 16, 2015, Grainger’s counsel contacted GSA to point out a

discrepancy between the BPA’s three-calendar-day delivery requirement and

MSC’s quotation providing that it could deliver orders within three business

days after receipt of order. Subsequently, the contracting officer reviewed the

BPA and the Memorandum of Agreements with the FRCs and discovered that

the FRCs do not receive deliveries on weekends or federal holidays. AR 11.

She therefore determined that the BPAs incorrectly stated the Government’s

delivery requirement in terms of calendar days. Id. The agency further found

that “the distinction between three ‘calendar’ days and three ‘business’ days

could significantly impact shipping costs, [which] likely impacted the BPA

Holders’ price quotations,[] includ[ing] shipping price.” AR 569. GSA thus

decided that it was necessary to take corrective action to modify the BPA to

include the Government’s actual delivery requirement. Id.; AR 11.

GSA cancelled MSC’s BPA modifications on June 18, 2015 and

announced that it would be taking corrective action due to a “flaw in the

procurement.” AR 554. GAO therefore dismissed Grainger’s protest as

5

academic. AR 986. On July 2, 2015, MSC protested at GAO the decision to

take corrective action, alleging that GSA’s decision was improper because

Grainger was not prejudiced by the misstated delivery requirement. AR 575.

On July 16, 2015, while MSC’s GAO protest was still pending, GSA

issued an amended RFQ that reflected a three-business-day delivery

requirement for referral orders. AR 326. The instructions accompanying the

amended RFQ provided that

[n]o changes to your price quotation are anticipated. However,

should your [Final Quotation Revisions (“FRQ”)] include price

changes, those changes will be evaluated only to the extent that

they are supported by a clear demonstration that the change in

offered price from your previous price quotation is directly

related to the BPA amendment regarding shipping and delivery

requirements or this RFQ amendment regarding the inventory

and inspection requirements.

AR 329. The agency, in effect, was trying to minimize the potential for

prejudice which might result from reopening the RFQ by limiting changes to

those triggered by the error.

On July 30, 2015, Grainger protested the corrective action, arguing that,

due to the passage of time, vendors should be allowed to update proposed

products to reflect current availability and pricing. AR 620-21. Grainger

submitted its revised quotation the next day, indicating that its list of Schedule

51V products had changed significantly since its initial quotation in March

2015, but that given the limitation imposed by the amended RFQ, those

changes were not reflected in its revised quotation.

The contracting officer subsequently discovered that between April and

July 2015, Grainger had, indeed, made numerous decreases to its Schedule

51V contract prices as well and had deleted a number of items from its

Schedule 51V item list. AR 725; 1201-08. Accordingly, she determined that

further corrective action was necessary to allow BPA holders to update their

revised quotations based on changes to their Schedule 51V prices. AR 725.

Without this corrective action, she determined, the revisions as they currently

stood would “inadvertently result in an invalid price evaluation and would

produce misleading results.” Id. GSA therefore issued another amended RFQ,

allowing BPA holders to update their revised quotations “to reflect any price

6

changes based on the amended BPA and RFQ shipping and delivery

requirements, as well as any revisions necessitated by changes make to the

BPA holders’ underlying GSA Schedule Contract.” AR 648. GAO thereupon

dismissed Grainger’s protest as academic. AR 988.

MSC subsequently filed a supplement to its then-pending protest with

GAO, challenging GSA’s second corrective action. MSC argued that the

second corrective action was without reasonable basis and would result in

competitive prejudice to MSC. AR 715-20. MSC and Grainger submitted their

revised quotations on August 19, 2015, prior to resolution of the protest. In its

revised quotation, MSC opted not to revise its prices. AR 1150.

On October 9, 2015, GAO denied MSC’s protest. Regarding the first

corrective action, GAO noted that, “where an agency discovers that a

solicitation overstates its needs, the proper remedy generally is the revision of

the solicitation to reflect the agency’s actual needs,” and found that it was

“within the agency’s discretion to decide there was a reasonable possibility

that the flaw in the solicitation resulted in prejudice to Grainger.” AR 983.

With respect to the second corrective action, GAO also found that it was

within the agency’s discretion. AR 984.

MSC filed this protest on November 20, 2015. On December 3, 2015,

we stayed the case pending an award decision by GSA regarding the revised

quotations submitted on August 19, 2015. In February 2016, GSA determined

that Grainger’s quotation offered the best value to the government and

awarded the BPA modifications to Grainger. We lifted the stay, and the parties

filed their cross-motions for judgment on the administrative record.

DISCUSSION

Pursuant to the Tucker Act, this court has jurisdiction to “render

judgment on an action by an interested party objecting to a solicitation by a

Federal Agency for bids or proposals for a proposed contract or to a proposed

award . . . or any alleged violation of statute or regulation in connection with

a procurement or a proposed procurement.” 28 U.S.C. § 1491(b)(1) (2012).

MSC is an “interested party” because it is a prospective bidder “whose direct

economic interest would be affected” by the award of the BPA modifications

to Grainger. Am. Fed’n of Gov’t Emps., ALF-CIO v. United States, 258 F.3d

1294, 1302 (Fed. Cir. 2001).

7

Our review is limited to the existing administrative record generated in

connection with the procurement at issue. See RCFC 52.1. We review the

administrative record pursuant to the standards set forth in section 706 of the

Administrative Procedure Act (“APA”), 5 U.S.C. § 706(2)(A) (2012). 28

U.S.C. § 1491(b)(4). Thus, we may set aside an agency’s decision only if it is

“arbitrary, capricious, an abuse of discretion, or otherwise not in accordance

with the law.” Banknote Corp. of America, Inc. v. United States, 365 F.3d

1345, 1350 (Fed. Cir. 2004). We note that, in the case at bar, much of the

administrative record consists, in large measure, of explanations for corrective

actions undertaken in response to and during the pendency of the parties’

multiple GAO protests. Because the explanations of the corrective actions are

thus inextricably linked to the GAO protests, we have no reservations about

treating them as contemporaneous documents rather than as part of an after-

the-fact narrative.

The protestor bears the burden of establishing that the agency’s decision

lacked a rational basis or was otherwise in violation of applicable law or

regulation. See Impresa Construzioni Geom. Domenico Garufi v. United

States, 238 F.3d 1324, 1332 (Fed. Cir. 2001). Additionally, plaintiff must show

prejudice, meaning that, had it not been for the error in the procurement

process, there is a reasonable likelihood that the challenger would have been

awarded the contract. Data Gen. Corp. v Johnson, 78 F.3d 1556, 1562 (Fed.

Cir. 1996).

Plaintiff asks this court to determine that both of GSA’s corrective

actions were arbitrary and capricious and requests that this court issue a

permanent injunction requiring GSA to terminate the BPA modification

awards to Grainger.

First, plaintiff argues that GSA’s initial corrective action was

unreasonable because there was no real possibility that Grainger or any other

competitor was prejudiced by the BPA’s misstatement of the delivery

requirement. According to plaintiff, corrective action is unreasonable where

the agency has not identified a clear defect in the procurement, when it is in

response to a non-prejudicial error, or where it does not specifically target the

identified defect in the procurement.

Plaintiff contends that the supposed error, MSC’s noncompliance with

the solicitation’s three-calendar-day delivery requirement for referral orders,

was not actually an error because there was not in fact a three-calendar-day

8

delivery requirement. While the BPA used language stating the requirement

in those terms, the RFQ did not. Instead, the RFQ expressly stated that the

vendor’s “fill rate” for referral orders would be its percentage of on-time

deliveries calculated in terms of business days. Moreover, the FRCs do not

accept deliveries on weekends or holidays and therefore there was no basis for

competitors to believe that the solicitation required delivery in three calendar

days.

According to plaintiff, the record shows that GSA did not even attempt

to investigate whether the difference between a three-business-day and a three-

calendar-day delivery requirement had an impact on pricing. Plaintiff contends

that it could not have had a meaningful impact because the requirement only

applies to referral orders, which are a small portion of the overall cost of

supplying items. Further, plaintiff argues that the record shows that Grainger

was not prejudiced by the misstated requirement because it did not change its

pricing at all in response to the amendment to the RFQ, and any subsequent

changes were solely the result of changes to its underlying Schedule 51V

pricing.

Plaintiff also challenges GSA’s decision to take corrective action a

second time by allowing Grainger and other vendors to make pricing changes.

This was unreasonable, plaintiff argues, because it was not targeted at the

concern that justified the initial corrective action. Plaintiff argues that any

changes in the vendors’ Schedule 51V pricing would automatically be

incorporated during performance and thus it was unnecessary to allow pricing

changes to the quotations. In addition, Grainger was given the opportunity for

an unfair advantage by being told that its initial price was 23% higher than that

of MSC.

Plaintiff also has an alternative argument directed at the award decision

itself. It contends that the award was arbitrary and capricious for three reasons:

(1) the agency should have realized that Grainger’s manipulation of the market

basket rendered the price evaluation methodology flawed; (2) Grainger’s

quotation is noncompliant with the delivery requirement; and (3) Grainger’s

quotation is noncompliant with the AbilityOne requirements.

As to the first reason, that Grainger’s manipulation of the market basket

rendered the price evaluation methodology flawed, plaintiff contends that the

evaluated price figures based on the RFQ’s market basket are intended to be

representative prices. Most products available for sale through the vendors’

9

Schedule 51V catalog are not included in the market basket; the idea is that the

market basket items will reasonably reflect the ultimate cost to the

government. According to plaintiff, it should have been clear to GSA that

Grainger manipulated the market basket pricing scheme by selectively

reducing the prices of the highest costing items in its revised quotation, thus

rendering the evaluation methodology flawed because it did not reasonably

reflect the costs to the government.

In support of the second reason, that Grainger’s quotation is

noncompliant with the delivery requirement, plaintiff argues that Grainger’s

quotation is ambiguous as to whether it will meet the delivery requirement

because Grainger’s quotation refers to an erroneous requirement of five to

seven day delivery. Because GSA clearly views the delivery requirement as

material, plaintiff argues, the agency acted arbitrarily and capriciously in

awarding the BPA modifications to Grainger on the basis of a noncompliant

quotation.

For the third reason, plaintiff argues that Grainger’s quotation is

noncompliant with the AbilityOne requirements because it quoted at least nine

items that are essentially the same products as those on the AbilityOne

procurement list.

Lastly, plaintiff argues that it satisfies the other requirements for a

permanent injunction it would suffer irreparable harm in the form of loss of

sales if a permanent injunction were not entered, the public interest favors

issuing a permanent injunction, and the balance of hardships tips in its favor.

In response, defendant argues that the agency did not act unreasonably

in initiating the first corrective action because MSC’s quotation did not

conform to the delivery requirement. Even if it did conform, defendant argues,

the agency was within its rights in initiating the corrective action because it is

undisputed that the original RFQ did not reflect its actual needs. Moreover,

defendant contends, MSC offers no support for its argument that the delivery

requirement was immaterial; rather, at the time, the agency had reason to

believe that the changed requirement could have had a significant impact on

vendors’ proposed pricing.

As to the second corrective action, defendant argues that the agency’s

decision was rational given that the vendors’ underlying Schedule 51V pricing

had changed extensively. Moreover, defendant disagrees that this corrective

10

action resulted in any competitive advantage to Grainger because both parties

were given the opportunity to change their pricing.

Defendant also disputes plaintiff’s arguments for why the agency acted

unreasonably in awarding the BPA modifications to Grainger. First, defendant

argues that the contention that Grainger manipulated the pricing scheme is

completely speculative. Next, defendant contends that Grainger’s quote

actually did comply with the delivery requirement it stated that Grainger can

provide 24-48 hour shipment times on referral orders, and next day pickup for

on-site pickup referral orders. Lastly, defendant points out that MSC has failed

to show that it was prejudiced by the inclusion of any essentially-the-same

items as AbilityOne items in Grainger’s market basket.

Intervenor’s cross-motion makes much the same argument as defendant,

but Grainger further seeks dismissal of plaintiff’s challenge to the agency’s

price evaluation as untimely, arguing that it should have been challenged prior

to the due date for receipt of proposals.4

GSA’s Decision to Take Corrective Action

We find that the agency was well within its rights in taking both

corrective actions. As to the first, MSC is in a weak position to argue that it

was prejudiced by the agency’s decision to re-solicit. Its quotation could have

been rejected as materially non-compliant with the delivery term. Instead, the

agency determined that the use of three “business” days was sufficient. The

problem, of course, was that Grainger and at least one other bidder offered to

comply with the “calendar” day requirement. A discrepancy as significant as

the delivery date is more than sufficient to warrant an amendment to the

solicitation. See FAR 15.206(a) (2015); see also EP Prods., Inc. v. United

States, 63 Fed. Cl. 220, 224-25 (2004) (“Amendments under this provision

may also be appropriate ‘to avoid award decisions not based on the agency’s

most current view of its needs.’”).

We disagree with MSC’s contention that the agency should have

undertaken a careful forensic inquiry into whether the mistake it made in

stating the delivery requirement could have had enough impact on Grainger’s

4

Grainger’s motion to dismiss additionally contends that plaintiff’s protest of

Grainger’s AbilityOne compliance is an unprotestable matter of contract

administration.

11

pricing to make up the difference in the two bidders’ pricing. The agency

considered the problem and, not unreasonably, found that “the distinction

between three ‘calendar’ days and three ‘business’ days could significantly

impact shipping costs, [which] likely impacted the BPA Holders’ price

quotations,[] includ[ing] shipping price.”5 AR 569. It was not required to go

further and speculate from its own knowledge base how the vendors would

have reacted to a different RFQ. It is important to note, in any event, that the

agency initially limited the vendors to submitting new prices only to the extent

they could demonstrate prejudice, i.e., that the original bid factored in tighter

delivery times. The way the corrective action was crafted initially thus

accounts for the very concern which plaintiff now asserts. In fact, Grainger’s

response to the first corrective action, while made under protest, did not result

in altered pricing.

Validity of the second corrective action is closely linked to the first. If

the delay triggered by the first corrective action was understandable, as we find

that it was, the factual groundwork was laid for Grainger’s request for the

decision to reopen pricing more broadly, due to the hundreds of thousands of

changes to its Schedule 51V pricing. The agency, in doing price comparisons,

had to cope with four moving targets: both Grainger’s and MSC’s FSS price

list, the items of overlap within the “market basket,” and the list of AbilityOne

products. The first two and the last item it had no control over, and the agency

knew that all three routinely changed over time. The third variable, the market

basket items, it had only limited control over. It did not know which items both

bidders would provide price quotations for. The net result is that comparison

of quoted prices inevitably ran the risk of some degree of imprecision. But

what was known for certain was that the longer the lapse of time after the

quotes were initially received (March 2015), the more likelihood that price

comparisons would not accurately reflect actual costs in the future. The agency

was confronted in August 2015 with Grainger’s evidence of its changes to

hundreds of thousands of prices and the deletion of 53,000 items. Concern

5

The considerations brought to bear when it is the agency’s own procurement

needs that prompt corrective action are fundamentally different from a

situation in which a competitor alleges that corrective action is warranted by

potential prejudice to it. Thus the cases plaintiff cites are not apt. See, e.g.,

Amazon Web Servs., Inc. v. United States, 113 Fed. Cl. 102, 111 (2013). Nor

is this a circumstance in which there is a complete failure to offer a rationale

for taking corrective action. See WHR Group, Inc. v. United States, 115 Fed.

Cl. 386, 398 (2014).

12

about whether the prices were so stale that they would not afford a proper price

comparison and thus the best value to the government was not irrational.

The fact that the delay associated with the first corrective action turned

out to be unnecessary, while ironic under the circumstances, is irrelevant. The

contracting officer cannot be faulted for not consulting a crystal ball. Once the

first corrective action had become part of the procurement history, it was not

irrational to permit comprehensive price re-submissions in order to protect the

government’s interests. Accordingly, we deny plaintiff’s challenge to the

validity of either corrective action.

GSA’s Decision to Award the BPA Modifications to Grainger

We come now to MSC’s separate contention that the agency’s decision

to award the BPA modifications to Grainger was arbitrary and capricious. As

to the first element in this line of argument that the agency should have

deduced that Grainger was manipulating the procurement by targeting price

changes on its FSS price schedule to market basket items counsel conceded

at oral argument that there is little daylight between this argument and its

challenges to the corrective actions. In effect, the argument is that, even if the

second corrective action was warranted in principle, as applied, it should have

been obvious that the agency was being duped. As Grainger argues in its

motion to dismiss, however, the opportunity for such manipulation, if it

existed, should have been apparent before MSC submitted its final revised

quotation, and, in any event, was an opportunity that MSC could have taken

advantage of. The evaluation methodology has remained unchanged since the

initial RFQ. The “as applied” challenge comes too late. A contractor who has

the opportunity to object to the terms of a solicitation but fails to do so prior

to the close of the bidding process waives its right to later object in this court.

Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308, 1313 (Fed. Cir.

2007).

In any event, we do not find support for the argument that Grainger

manipulated the market basket by selectively reducing the prices of its highest

priced items. While some of the market basket items were repriced, under the

circumstances, that is not surprising. During April and July 2015, Grainger

deleted approximately 53,000 products from its catalog, and reduced prices for

approximately 700,000 items. While the 548 items in the common market

basket were known to the bidders, they could not be certain which ones would

be common to all bidders and thus made the point of price comparison.

13

Next, we disagree that Grainger’s quotation was noncompliant with the

delivery requirement. Although Grainger’s proposal mentions its “ability to

meet the 5 to 7 day delivery requirement,” id. at 469, this is plainly an

irrelevant mistake. Elsewhere it clearly indicated its intent to meet the RFQ’s

actual requirement that orders be acknowledged within 24 hours of receipt and

shipped within one business day of acknowledgment using three-business-day

delivery. Id. at 12; 159-162. Grainger’s proposal contained numerous

indications that it intended to deliver referral orders within three business days.

See AR 451 (referencing one day delivery ability for FRCSE); 452

(referencing same and next day delivery ability for FRCE);453 (referencing

two day delivery ability for FRCMA); 454 (referencing same and next day

delivery ability for FRCSW); 459 (indicating next day pickup for referral

orders).

Finally, we believe that Grainger’s proposal complied with the

solicitation’s AbilityOne requirements. The BPAs simply stated that the

vendors were to “ensure that no item when is essentially the same as an

AbilityOne item be sold to a Government customer.” AR 1053 (emphasis

added). Thus the requirement refers to the items sold, not the items quoted.

Nowhere does the solicitation prohibit a vendor from quoting items that are

essentially the same as AbilityOne items. This is particularly understandable

in light of the fact that the vendors’ quotations were simply meant to be a

representative sample of the cost to the government rather than an exact list of

items to be sold. Accordingly, there was nothing unreasonable about the

agency’s decision to award the BPA modifications to a vendor, even if it

quoted items essentially the same as AbilityOne items. The AbilityOne list

changes over time, and whether an item offered by the vendors here was truly

the same as one on the AbilityOne list would be nuanced. Requiring that purge

prior to actual purchases would be a waste of time.

CONCLUSION

Because we find that the agency’s decisions to take corrective action

and to award the BPA modifications to Grainger were reasonable, we deny

plaintiff’s motion for judgment on the administrative record, and we grant

defendant’s and intervenor’s motion for judgment on the administrative record.

14

Grainger’s motion to dismiss is denied as moot.6 The clerk is directed to enter

judgment accordingly. No costs.

s/Eric G. Bruggink

ERIC G. BRUGGINK

Senior Judge

6

While the motion arguably implicates jurisdictional considerations, even if

the motion to dismiss were granted, not all of plaintiff’s arguments would be

dismissed. Moreover, as we explain in the text, it is not clear that the argument

concerning the agency’s failure to police Grainger’s alleged manipulation of

it opportunity to re-price its FSS list is really distinct from its other arguments,

which were timely preserved. Even if MSC’s arguments are more properly

deemed to fail a jurisdictional test, in the context of a bid protest, we assume

Grainger has no objection to MSC being hung for a sheep as opposed to a

lamb.

15

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.