In the United States Court of Federal Claims

Case Nos. 13-584 C, 13-585 C, 13-586 C

(Filed UNDER SEAL March 25, 2016)

REISSUED April 7, 2016

YANKEE ATOMIC ELECTRIC )

COMPANY, )

Plaintiff, ) Spent Nuclear Fuel Storage Cost;

v. ) Breach of Contract Damages; Cost of

) Corporation Existence; Termination of

THE UNITED STATES, ) Benefit Programs Costs; Property

Defendant, ) Transfer Costs.

MAINE YANKEE ATOMIC )

POWER COMPANY, )

Plaintiff, )

v. )

)

THE UNITED STATES, )

Defendant, )

CONNECTICUT YANKEE )

ATOMIC POWER COMPANY, )

Plaintiff, )

v. )

)

THE UNITED STATES, )

Defendant. )

Robert H. Stier, Jr., Pierce Atwood LLP, Portland, Maine, for plaintiffs.

Lucus A. Ritchie and Eric J. Wycoff, Pierce Atwood LLP, Portland, Maine, of

counsel.

Lisa L. Donahue, Commercial Litigation Branch, Civil Division, United

States Department of Justice, Washington, D.C., with whom appeared Benjamin C.

Mizer, Principal Deputy Assistant Attorney General, Robert E. Kirschman, Jr.,

Director, Allison Kidd-Miller, Assistant Director, for defendant. Kristin B. McGrory

and Heidi L. Osterhout, Trial Attorneys. Jane K. Taylor, Office of General Counsel,

United States Department of Energy, Washington, D.C., of counsel.

OPINION

Merow, Senior Judge

Yankee Atomic Electric Company (“Yankee Atomic”), Maine Yankee

Atomic Power Company (“Maine Yankee”), and Connecticut Yankee Atomic Power

Company (“Connecticut Yankee”) (collectively “plaintiffs”), filed complaints on

August 16, 2013, alleging the government’s breach of its contractual obligations

related to the removal of spent nuclear fuel (“SNF”) from plaintiffs’ facilities. See

Case No. 1:13-cv-584, Doc. 1; Case No. 1:13-cv-585, Doc. 1; Case No. 1:13-cv-

586, Doc. 1. The three cases have been consolidated for trial.1

This is the third round of litigation as a result of the government’s continuing

breach of the same agreements. In the first set of cases, the government’s liability

was established. See Yankee Atomic Elec. Co. v. United States, 73 Fed. Cl. 249

(2006). The parties, however, continue to disagree as to the damages each plaintiff

is entitled to recover. Plaintiffs now seek damages in an amount of approximately

$77.9 million, for costs incurred as a result of the government’s breach between

January 1, 2009 and December 31, 2012. See Doc. 39 at 6.

To resolve the dispute, trial was held on June 30 through July 1, 2015.

Following the submission of post-trial briefs, supplemental briefing was ordered to

clarify part of the legal framework for plaintiffs’ claims relating to costs associated

with administration of health and welfare benefits programs. See Doc. 44. Final

oral argument was held on Friday, February 19, 2016.

FINDINGS OF FACT

The government entered into nearly identical Standard Contracts with each of

the utilities in this case, under which the government, through the Department of

Energy (“DOE”), agreed to dispose of the utilities’ SNF. 2 At the time of trial, all

1

Because the cases often involve identical filings, unless otherwise noted, citations to the docket

refer to documents filed in Case No. 1:13-cv-584.

2

In Yankee Atomic Elec. Co. v. United States, 73 Fed. Cl. 249 (2006), the court wrote extensively

on the contracts between the utilities and the government and on the historical context in which

2

three utilities had been shut down, and currently each maintains its corporate

existence only due to the SNF stored at the sites as a result of the government’s

breach of its obligations to dispose of it. See Tr. at 16:18-17:8 (Norton). As a result

of this “steady-state” existence, plaintiffs’ claim:

[A]ll costs reasonably incurred by each Yankee to maintain its corporate

existence following the completion of decommissioning of its power

plant are related to the management of SNF/GTCC, and are recoverable

unless those costs would have also been incurred in the non-breach

world. After the date when the company would have gone out of

business in the non-breach world, there should be no set-off to the costs

actually incurred.

Doc. 39 at 6-7 (emphasis in original).

At the direction of the court, the parties have cooperated in an extensive audit

process, through which they evaluated the specific costs included in plaintiffs’

damages claim. See Docs. 12, 13. Although the government contends that plaintiffs

should recover none of the claimed damages for failure to establish a sufficient non-

breach world model, see Doc. 42 at 19-20, the government specifically objects only

to the following categories of damages: (1) the costs to plaintiffs of administering

their health and welfare plans, (2) the distribution of settlement proceeds from the

Stone & Webster Engineering Corporation (“SWEC”) litigation, (3) costs associated

with transfer of the property on which the nuclear plants were situated, and (4) the

legal and tax expenses related to the recovery of damages from the first round of this

litigation. The following facts are relevant to resolving these issues.

I. Plaintiffs’ Calculation of Damages

Each utility arrived at its amount of claimed damages by calculating the actual

costs incurred as a result of the government’s breach, less the costs that the utility

would have incurred in the non-breach world. See Tr. at 83:16-84:4 (Smith). The

starting point for these calculations are the storage facility costs, or “ISFSI

Operational Costs” for each utility during the claim period. See Doc. 39 at 11; Tr.

at 91:21-92:3 (Smith). The operational costs include: full and part-time employees,

security costs, contracted labor for temporary or special projects, taxes, insurance,

utility costs, materials and supplies, and other miscellaneous expenses. See Tr. at

the contracts came about. In the interest of focusing on the new issues before the court, the

discussion is not repeated in this opinion.

3

17:9-21:14 (Norton). These costs were not only deemed reasonable by plaintiffs’

own witness, see Tr. at 24:20-26:18 (Norton), but were also reviewed and allowed

by the Federal Energy Regulatory Commission (“FERC”), see Tr. at 99:11-19

(Smith). The specific figures are presented in Exhibits P3004A, P3005A, and

P3006A, each of which is accompanied by supporting details derived from the

utilities’ accounting system, invoices, purchase orders, and payroll information. See

Tr. at 95:7-95:18 (Smith).

For Connecticut Yankee and Yankee Atomic, the damages calculation

includes offsets for the utilities’ corporate existence into the instant claims period.

See Ex. P3004A, Ex. P3006A; Tr. at 92:23-93:24 (Smith). Absent the government’s

breach, plaintiffs contend, Connecticut Yankee and Yankee Atomic would have

been out of business by the end of 2010. See Tr. at 37:14-16 (Norton). No such

offset is included in Maine Yankee’s calculation of damages because in the non-

breach world, it allegedly would have been out of business at the end of 2008. See

Tr. at 29:1-2 (Norton); 122:7-124:5 (Smith).

Finally, all three utilities include “agreed-to-reductions” in the damages

calculus. Through the audit process, the parties agreed to the modification of certain

costs in the government’s favor. See Tr. at 92:6-20 (Smith).

In accordance with this methodology, the specific figures for each plaintiff are

as follows:

Connecticut Yankee

ISFSI Operational Costs: $36,585,702

Offset for Minimal Corporate Continuation: ($2,213,299)

Agreed-to Reductions: ($1,444,809)

Total: $32,927,594

Maine Yankee

ISFSI Operational Costs: $25,278,882

Agreed-to Reductions: ($239,083)

Total: $25,039,799

Yankee Atomic

ISFSI Operational Costs: $22,841,715

Offset for Minimal Corporate Continuation: ($1,669,886)

Agreed-to Reductions: ($1,235,177)

Total: $19,936,652

4

See Doc. 39 at 13-14; Exs. P3004A, P3004B, P3004C (Connecticut Yankee);

P3005A, P3005B (Maine Yankee); P3006A, P3006B, P3006C (Yankee Atomic).

II. Corporate Existence Dates in the Non-Breach World

A central assumption of plaintiffs’ damages claims is that they are entitled to

recover the full amount of costs incurred after the date on which each utility would

have gone out of business in the non-breach world. Essentially, plaintiffs argue that

at some point during this claim period, the liability not only for fuel storage, but also

for corporate existence costs, shifts entirely to the government. See Tr. at 38:5-9

(Norton). As noted above, plaintiffs contend that the government is no longer

entitled to any offsets for Maine Yankee at the end of 2008, and for Connecticut

Yankee and Yankee Atomic at the end of 2010.

To establish that these assumptions are appropriate, plaintiffs rely on the

experience and testimony of several executive officers, including Mr. Wayne

Norton, who serves as President and Chief Executive Officer of Yankee Atomic and

Connecticut Yankee and Chief Nuclear Officer for Maine Yankee, see Tr. at 9:13-

16 (Norton); Mr. Todd Smith, the Director of Operations for all three utilities, see

Tr. at 77:24-78:7 (Smith); and Ms. Carla Pizzella who serves as the Vice President,

Chief Financial Officer and treasurer for all three utilities, as well as assistant

secretary for Connecticut Yankee and assistant clerk for Yankee Atomic, see Tr. at

184:2-4 (Pizzella).

In determining the dates on which the utilities would have been out of business

in the non-breach world, the utilities first assumed that decommissioning would have

occurred on the same date in the non-breach world as it did in the real world. See

Tr. at 26:19-28:1 (Norton). Maine Yankee completed physical decommissioning in

2004, and limited the scope of its license to accommodate only fuel storage in 2005.

See Tr. at 28:10-20 (Norton). Both Connecticut Yankee and Yankee Atomic were

decommissioned in 2007, and plaintiffs assumed they would have terminated their

licenses at approximately the same time. See Tr. at 34:10-15, 35:23-36:4 (Norton).

The utilities then “estimated the period of time it would take to terminate our

benefits programs, disposition our assets and liabilities, including our property, and

then ultimately submit to the respective states—Maine, Massachusetts, and

Connecticut—our cessation of existence and termination of our corporations under

the appropriate filings with the state.” Tr. at 28:2-8 (Norton). Mr. Norton, Ms.

Pizzella, and Mr. Smith, three individuals who were intimately involved with critical

5

aspects of the businesses, collaborated as a team to arrive at these estimates. See Tr.

at 47:7-52:23, 63:14-64:22 (Norton).

Their estimates and assumptions, although necessarily hypothetical due to the

government’s breach of the Standard Contracts, were not untethered from real world

experience. Many of the activities required to shut down the utilities overlap with

tasks actually performed by the companies in the course of downsizing to the current

steady-state of operations. Mr. Norton described the process of downsizing the

companies in his testimony:

[I]t’s a series of regulatory changes; it’s a series of programmatic and

process changes; it’s a series of physical changes at the facility; it’s

winding down staffing; it’s terminating union agreements; it’s

unwinding assets and liabilities; and getting to the point where you can,

in our case, store spent nuclear fuel at a facility that has a reduced

license and a reduced organizational structure to support fuel storage

until it’s removed.

Tr. at 16:10-17 (Norton). Ms. Pizzella has managed the termination of three pension

plans and two 401(k) plans for plaintiffs. See Tr. at 194:17-25. Pension plans are

not health and welfare benefit plans, but pension plans are more complicated to

terminate due to governing federal regulations that do not apply to the plans at issue

here. See Tr. at 195:1-196:25 (Pizzella). In addition, Maine Yankee and Connecticut

Yankee have actually gone through the process of dispositioning property that is

unencumbered by the presence of spent nuclear fuel. See Tr. at 324:16-23

(Richardson) (describing Connecticut Yankee’s property disposition); Tr. at 337:11-

342:1 (Richardson) (describing Maine Yankee’s property disposition).

Mr. Norton and Mr. Smith estimated that it would take an additional three

years, or until the end of 2008, for Maine Yankee to complete these activities and

wind up corporate existence. See Tr. at 29:1-2 (Norton), Tr. at 122:7-124:5 (Smith).

After conducting a similar analysis for Connecticut Yankee and Yankee Atomic, Mr.

Norton and Mr. Smith determined that both utilities would have been out of business

in the non-breach world by the end of 2010. See Tr. at 34:10-36:14 (Norton); Tr. at

124:13-25, 147:21-148:8, 152:25-153:5 (Smith).

The government takes issue with the authority that Mr. Norton, Ms. Pizzella,

and Mr. Smith have to determine the actions and time periods that would have been

necessary in order to terminate the corporate existence of the utilities, claiming that

their testimony lacked specificity and that the witnesses lacked expertise in winding

6

down corporations. See Doc. 42 at 14-18. The court disagrees. In the court’s view,

Mr. Norton, Ms. Pizzella, and Mr. Smith were all credible witnesses and are each

well-positioned to understand and testify to the details of the businesses involved in

this case. Their testimony provides a solid foundation for the court’s conclusion

regarding the dates on which each utility would have been out of business in the non-

breach world.

The court finds that, absent the government’s breach, Maine Yankee would

have been out of business by the end of 2008, while Connecticut Yankee and Yankee

Atomic would have been out of business by the end of 2010.

III. Defendant’s Specific Challenges

Apart from its position that plaintiffs should recover no damages due to their

alleged failure to present a plausible non-breach world model, the government takes

issue with four specific categories of claimed damages.

A. Benefits Program Administration Costs

Plaintiffs provide post-retirement health and welfare benefits plans to eligible

employees. See Tr. at 185:22-25 (Pizzella). The plans include medical, dental, and

life insurance benefits. See Tr. at 186:17-187:5 (Pizzella). The plans are funded

through utility rates and maintained in a Voluntary Employees’ Beneficiary

Association Fund for Retiree Welfare, or a VEBA trust account. See Tr. at 188:15-

190:7 (Pizzella). In the course of administering these plans, plaintiffs incur costs for

legal and actuarial services. See Tr. at 190:8-191:15 (Pizzella).

All three plaintiffs claim that their respective benefits plans would have been

terminated before or during the instant claims period—Maine Yankee at the end of

2006, see Tr. at 197:5-9 (Pizzella), and Connecticut Yankee and Yankee Atomic at

the end of 2008 (with minimal costs into 2009), see Tr. at 197:10-16, 201:21-202:24,

205:21-206:16 (Pizzella). As a result, the argument goes, all costs associated with

administering the plans after those dates are recoverable. See Doc. 39 at 24.

Plaintiffs claim the following amounts: Maine Yankee, $456,633;

Connecticut Yankee, $375,845; and Yankee Atomic, $295,580; for a total of

$1,128,058. See Ex. P3012.

Plaintiffs had the option to terminate the benefits plans in one of three ways,

and the complete discretion to choose between them. See Tr. at 197:24-198:7,

7

199:15-17 (Pizzella). Plaintiffs could have: (1) terminated the plans without making

any payments to beneficiaries, see Tr. at 198:5-7 (Pizzella); (2) made a lump-sum

payment from the trust, divided equally among beneficiaries, see Tr. at 198:9-17

(Pizzella); or (3) sold the obligation to pay benefits to a third party administrator, see

Tr. at 198:18-19 (Pizzella).

The damages that plaintiffs claim in this case are administrative costs paid out

of the utilities’ operating budgets, not drawn from the corpus of the VEBA trust. See

Tr. at 191:9-15 (Pizzella). According to plaintiffs, however, all costs associated with

terminating the benefits plans under any of the three available methods would come

from the trust assets. Tr. at 207:1-10, 236:15-237:9 (Pizzella). As a result, plaintiffs

take the position that the non-breach world model need not include any offset for

future administration costs, regardless of the method of termination. See Doc. 43 at

19; Tr. at 236:17-237:9, 207:1-10 (Pizzella).

At trial, because they insisted it did not make any accounting difference,

plaintiffs refused to choose which method of termination they would have pursued

in the non-breach world. See Tr. at 199:18-200:11; 207:1-10; 236:15-237:9

(Pizzella). In post-trial briefing, however, plaintiffs stated that they would have been

most likely to choose the lump-sum payment to beneficiaries. See Doc. 45 at 11.

Ms. Pizzella testified that if the plan obligations were transferred to a third party, the

costs of future administration would be included in the purchase price, which would

be paid out of the trust assets. See Tr. at 207:1-10; 236:15-237:9 (Pizzella). But

plaintiffs have admittedly engaged in no cost analysis for the lump-sum payment

option. See Tr. at 242:7-11 (Pizzella).

The government agrees that plaintiffs retain discretion as to the method of

termination, and do not seriously challenge the dates on which plaintiffs claim the

plans would have been terminated in the non-breach world. See Doc. 42 at 24-33.

It disagrees, though, that administration costs that are currently paid out of the

operating budget could be paid from the corpus of the trust in the event of

termination. For instance, the government’s expert Mr. Larry Johnson, testified that

if plaintiffs sold the plan obligations to a third party, they would have been required

to make a lump-sum payment from their operating budgets to cover future

administrative costs that were “economically equivalent” to the costs incurred in the

breach world. See Tr. at 406:4-407:9 (Johnson).

Proceeding from this assumption, the government insists that in order to

demonstrate a plausible non-breach world scenario, plaintiffs are required to elect

between the three methods of termination and account for offsets of any

8

administration costs. See Doc. 42 at 29. Because plaintiffs refused to do so, the

government contends, they have failed to prove their damages. See id.

B. SWEC Proceeds

Because the government failed to perform under the Standard Contract, Maine

Yankee contracted with Stone and Webster Engineering Corporation (“SWEC”) to

build dry storage facilities and perform decommissioning activities. SWEC failed

to perform and went bankrupt. Maine Yankee recovered damages from SWEC’s

insurer and as part of a settlement with SWEC’s bankruptcy estate. The recovered

funds were allocated between Maine Yankee’s decommissioning effort and as an

offset to the government’s damages for construction of dry storage facilities.3

Although the court addressed the allocation issue in the second round of this

litigation, it has resurfaced now because Maine Yankee received an additional

$1,421,000 from the settlement during the instant claim period. See Tr. at 207:23-

208:13 (Pizzella). The funds resulted from the resolution of coverage issues with

SWEC’s insurer. See Tr. at 38:25-39:17 (Norton). Of the total amount received,

Maine Yankee allocated 90% as an offset to its claim against the government, and

attributed the remaining 10%, or $142,100, to its decommissioning costs. See Tr. at

208:14-21 (Pizzella).

Maine Yankee decided to use the 90/10 allocation in accordance with an Offer

of Settlement, approved by FERC, which provided for the proper division of any

additional payments received from the SWEC bankruptcy in excess of $1 million.

See Tr. at 207:23-210:19 (Pizzella). The agreement stated, in relevant part:

To the extent that Maine Yankee receives more than $1 million in such

additional payments on [the SWEC bankruptcy proceeding], on or after

such execution date, the Parties agree that Maine Yankee will be

permitted to receive 10% of the amount so received over $1 million as

an additional Incentive Budget payment. Maine Yankee may withdraw

any such additional Incentive Budget payment from the

decommissioning trust as a valid decommissioning expense, and

distribute to Maine Yankee’s owners.

3

The court’s opinion in the second round of this litigation explained Maine Yankee’s recovery

and its allocation in more detail than is necessary to repeat here. See Yankee Atomic Elec. Co. v.

United States, 113 Fed. Cl. 323 (2013).

9

Ex. P3010 at 10.

The government objects to this allocation, claiming that the entire amount of

additional funds should be set off from Maine Yankee’s claim. See Doc. 42 at 37;

Tr. at 395:17-21 (Johnson). This position is based on the government’s view that

such an offset is mandated by this court’s previous opinion on the allocation issue.

See id.

C. Property Transfer Costs

In 2007, Connecticut Yankee and Yankee Atomic hired a consulting firm,

Vita Nuova, to assist the utilities in navigating the process of dispositioning their

properties. See Tr. at 315:2 (Richardson). According to Ms. Elaine Richardson,

Vita Nuova’s Vice President, the company “specialize[s] in redevelopment,

redevelopment planning and consulting services related to . . . lands that are

complicated by either environmental conditions or other challenges, be it legal or

regulatory, that may impact the ability to sell a property.” Tr. at 287:23-288:6

(Richardson). Over the government’s objection, the court qualified Ms. Richardson

as an expert in the “disposal of challenged real estate.” Tr. at 306:14.

Ms. Richardson acted as project manager for both utilities. See Tr. at 314:4-

6; 320:12-15 (Richardson). The work Vita Nuova performed for the utilities

involved: (1) reuse assessments to consider the relevant challenges of each parcel

and options for disposition, see Tr. at 312:21-319:5, 326:15-331:21 (Richardson);

(2) efforts to identify interested purchasers, see Tr. at 319:6-320:19, 332:1-333:22

(Richardson); and (3) assisting with negotiations and purchase and sale agreements,

see Tr. at 322:6-22 (Richardson).

Based on the assessments and subsequent efforts to sell the property, Ms.

Richardson expressed the opinion that had the government performed under the

Standard Contracts, both Connecticut Yankee and Yankee Atomic could have

dispositioned the subject properties by the end of 2009. See Tr. at 325:7-23; 335: 3-

24 (Richardson). Although Vita Nuova did not perform the same services for Maine

Yankee, based on a review of the assessments and efforts to sell the property made

by a different company, Ms. Richardson concluded that Maine Yankee would have

been able to disposition all of its property in the non-breach world by the end of

2006. See Tr. at 343:7-344:19 (Richardson).

Vita Nuova charged $124,186 for the work performed with respect to the

Connecticut Yankee property between 2009 and 2012. See Tr. at 346:11-14

10

(Richardson); Ex. P3020; Tr. at 156:13-21 (Smith). The company charged Yankee

Atomic $198,237 for services performed in the same time period. See Tr. at 349:2-

5 (Richardson); Ex. P3020; Tr. at 156:13-21 (Smith).

Plaintiffs asked Ms. Richardson to provide an estimate of the fees that would

have been charged in the non-breach world, where the presence of spent nuclear fuel

would not have been one of the challenges with the property. See Tr. at 346:15-20

(Richardson). In order to determine the portion of work attributable to the presence

of spent nuclear fuel, Ms. Richardson personally reviewed the invoices and back up

documentation associated with each project. See Tr. at 346:12-348:20, 349:2-351:16

(Richardson). After her detailed review, and using her personal knowledge of the

projects as project manager, Ms. Richardson concluded that approximately 40% of

the work for Connecticut Yankee was related to the presence of spent fuel, see Tr.

at 348:24-349:1 (Richardson), while 20% of the work for Yankee Atomic was

related to the fuel, see Tr. at 349:13-15 (Richardson). Ms. Richardson testified that

her estimates were different for each company because in arriving at her conclusions

she took into account the specific, unique challenges at each property. See Tr. at

349:16-351:16 (Richardson).

Applying Ms. Richardson’s percentages to the total invoiced amount for each

company results in a claim for damages in an amount of $89,321—$49,674 from

Connecticut Yankee, and $39,647 from Yankee Atomic. See Ex. P3020.4

The government does not claim that the Vita Nuova costs were not incurred,

but rather, that plaintiffs should not recover these fees because Ms. Richardson’s

method for determining the percentage of the work attributable to the presence of

spent nuclear fuel was unreliable. See Doc. 42 at 40-45.

D. Legal and Tax Expenses Related to Phase I Damages

The final category of damages to which the government specifically objects

is plaintiffs’ claims to recover legal and tax expenses that they incurred as a result

of receiving a payment for damages awarded in the first round of this litigation. See

Doc. 39 at 38-39. During the instant claim period, plaintiffs received large payments

as a result of the first judgments in this case. See Tr. at 211:9-12 (Pizzella).

4

Plaintiffs’ Ex. P3020 actually reflects an amount of $39,648 for property transfer costs incurred

by Yankee Atomic. After reviewing the figures, and independently applying Ms. Richardson’s

percentages to the total costs incurred, it appears to the court that the correct figure is $39,647, and

the discrepancy is likely the result of a rounding error.

11

Ms. Pizzella testified that upon receipt of “[a]ny large cash stream . . . we have

to do a rate filing and a financial analysis to show to FERC our funding needs and

our ability to return the money to our wholesale customers.” Tr. at 211:17-24

(Pizzella). In addition to expenses related to meeting the regulatory requirements,

plaintiffs engaged tax consultants in order to understand the tax implications of

receiving such large sums of money. See Tr. at 211:25-212:14 (Pizzella).

Plaintiffs incurred a total of $30,227 in sorting out the legal and tax

implications of receiving funds from the first round judgments, divided between the

companies as follows: Maine Yankee, $10,500; Connecticut Yankee, $13,727; and

Yankee Atomic $6,000. See P3013 (the parties agreed during trial to exclude the

category of “travel expenses” reflected on this exhibit, see Tr. at 214:13-14). Ms.

Pizzella testified that these expenses are reasonable based on her experience with the

providers on similar, unrelated matters. See Tr. at 214:2-4 (Pizzella).

The government objects to plaintiffs’ recovery of these expenses because it

argues that the costs are legally unrecoverable costs of litigation. See Doc. 42 at 45-

46.

CONCLUSIONS OF LAW

As this court has often noted, traditional contract principles govern spent

nuclear fuel disputes. At the most basic level, the appropriate remedy for the

government’s breach “is damages sufficient to place the injured party in as good a

position as it would have been had the breaching party fully performed.” Indiana

Michigan Power Co. v. United States, 422 F.3d 1369, 1373 (Fed. Cir. 2005)

(citations omitted). Specifically, “[d]amages for a breach of contract are recoverable

where: (1) the damages were reasonably foreseeable by the breaching party at the

time of contracting; (2) the breach is a substantial causal factor in the damages; and

(3) the damages are shown with reasonable certainty.” Id. (citing Energy Capital

Corp. v. United States, 302 F.3d 1314, 1320 (Fed. Cir. 2002)).

To establish that damages were reasonably foreseeable, “a plaintiff must show

that the type of damages are foreseeable as well as the fact of damage.” See Vermont

Yankee Nuclear Power Corp. v. Entergy Nuclear Vermont Yankee, 683 F.3d 1330,

1344 (Fed. Cir. 2012). As the Federal Circuit has explained:

Although this does not require “actual foresight” that the breach will

cause a “specific injury or a particular amount in money[,] . . . the injury

actually suffered [still] must be one of a kind that the defendant had

12

reason to foresee and of an amount that is not beyond the bounds of

reasonable prediction.”

Id. (citing Joseph M. Perillo, 11 Corbin on Contracts § 56.7 at 108 (rev. ed. 2005)

(emphasis added)).

It is then plaintiffs’ burden to demonstrate that the government’s breach was

a “substantial causal factor” in the damages they seek to recover. Indiana Michigan,

422 F.3d at 1373. See Yankee Atomic Elec. Co., 536 F.3d at 1273, and Yankee

Atomic Elec. Co. v. United States, 113 Fed. Cl. 323, 332 (2013) (noting that both the

“substantial causal factor” test and the “but-for” test are both acceptable standards

for determining causation, and choosing to apply the former). To do this, the

plaintiff must submit a “comparison between the breach and non-breach worlds.”

Yankee Atomic, 536 F.3d at 1273. The plaintiff bears the burden of proving “the

extent to which his incurred costs differ from the costs he would have incurred in

the non-breach world.” Energy Nw. v. United States, 641 F.3d 1300, 1306 (Fed. Cir.

2011).

And, although damages must be “shown with reasonable certainty,” they need

not be “ascertainable with absolute exactness or mathematical precision,” but

“recovery for speculative damages is precluded.” Indiana Michigan, 422 F.3d at

1373 (citations omitted). Enough evidence to allow the court to make “a fair and

reasonable approximation” is required. Bluebonnet Sav. Bank v. United States, 266

F.3d 1348, 1355 (Fed. Cir. 2001) (citations omitted).

In this round of litigation, plaintiffs have alleged entitlement to damages in

the amount of $77.9 million. See Doc. 39 at 6. Those damages fall into five

categories: (1) operational costs not specifically contested at trial, (2) the costs to

plaintiffs of administering their health and welfare plans, (3) the proper allocation of

settlement proceeds from the SWEC litigation, (4) costs associated with transfer of

the property on which the nuclear plants were situated, and (5) the legal and tax

expenses related to damages recovered in the first round of this litigation.

I. Operational Costs Not Specifically Contested At Trial

The government has put forth no argument or evidence that plaintiffs did not

incur the claimed expenses, beyond what may have been resolved as part of the audit

process. Rather, it raises objections to the legal sufficiency of plaintiffs’ proof with

regard to the non-breach world models presented at trial. See Doc. 42 at 14-24.

13

As a starting point, plaintiffs may only recover costs caused by the

government’s breach if those costs would not have been incurred in the non-breach

world. See Indiana Michigan, 422 F.3d at 1373 (“The remedy for breach of contract

is damages sufficient to place the injured party in as good a position as it would have

been in had the breaching party fully performed.”). In order to prove those damages,

a plaintiff must “submit a hypothetical model establishing what its costs would have

been in the absence of a breach,” and bears the burden of proving “the extent to

which his incurred costs differ from the costs he would have incurred in the

nonbreach world.” Energy Nw., 641 F.3d at 1305-06.

Plaintiffs have submitted non-breach world models to support their damages

claims, which the government argues are insufficient. See Exs. P3004B, P3006B.

First, the government attacks the dates on which plaintiffs claim each utility

would have been out of business, a critical piece of the non-breach world models,

arguing that plaintiffs engaged in “no specific analysis” of the issue and simply made

unsupported assumptions of what the dates would have been. Doc. 42 at 14. As

explained in the court’s findings of fact, the court disagrees. Plaintiffs actually

engaged in much of the activity required to shut down the plants in the course of

down-sizing to the steady-state existence. Furthermore, plaintiffs’ witnesses are

well-positioned to fill in the blanks that were created by the government’s failure to

perform.

The government then argues that even if the court agrees with the plaintiffs’

termination dates, plaintiffs cannot recover any actual costs because they “offered

no foundation or support for their non-breach scenario (in the form of estimated

offsets to their actual costs) at trial.” Doc. 42 at 20. It claims that plaintiffs were

entirely unable to estimate non-breach world costs without the help of outside

counsel. See id. at 20-21. Plaintiffs did consult an attorney with regard to some non-

breach world costs, and the government characterizes that attorney as the “lynchpin”

of the plaintiffs’ claims. Id. The government argues that because the attorney did

not testify, the models have insufficient foundation. See id.

The government’s position is an unsupported exaggeration of outside

counsel’s role in the non-breach world analysis. As Mr. Smith testified at trial, the

attorney was only consulted after the non-breach world model had been prepared.

See Tr. at 123:5-124:5, 173:21-176:2 (Smith). The government presents this fact as

a craven attempt on plaintiffs’ part “apparently to infuse the model with some

credibility,” but fails to explain how its characterization of the attorney as the

14

“lynchpin” of the model squares with the fact that he had no hand in creating it. Doc.

42 at 21.

Although not framed precisely in terms of the applicable legal standard, the

heart of the government’s argument seems to be that the plaintiffs have failed to

prove damages to a reasonable certainty. See Indiana Michigan, 422 F.3d at 1373

(noting that damages need not be “ascertainable with absolute exactness or

mathematical precision,” but “recovery for speculative damages is precluded”)

(citations omitted). Stated differently, the government implies that plaintiffs have

failed to provide enough evidence to allow the court to make “a fair and reasonable

approximation” of damages. Bluebonnet Sav. Bank v. United States, 266 F.3d 1348,

1355 (Fed. Cir. 2001) (citations omitted). The government claims that neither Ms.

Pizzella, Ms. Richardson, Mr. Norton, nor Mr. Smith gave reliable testimony. Doc.

42 at 15-17. As a result, the government claims, that “[p]laintiffs’ complete failure

to elicit qualified evidence at trial makes it impossible for them to support their non-

breach financial scenario.” Id. at 19.

Contrary to the government’s contention, plaintiffs provided not only detailed

documentation of their non-breach world models, but also a detailed explanation of

how they arrived at the figures included in those models. Mr. Smith testified that

the non-breach world models used in this case were extensions of the models

presented in the second round cases. See Tr. at 99:24-100:14 (Smith). The initial

models were designed by starting with actual operating budgets for each company

in the years after completing decommissioning. See id. Mr. Smith, Mr. Norton, and

Ms. Pizzella then evaluated each line in the budgets and made a determination as to

whether a similar activity would have been required in the non-breach world. See

id.; Tr. at 62:15-64:22 (Norton), 105:15-106:2 (Smith). The models were later

refined through discussions with the government. See Tr. at 114:13-19 (Smith),

282:21-284:2 (Pizzella).

The difference in this round of litigation, of course, is that plaintiffs have

established that all three utilities would have been out of business either prior to or

during the instant claims period. The proposed offsets for costs that the utilities

would have incurred in the non-breach world are, therefore, different. Because

Maine Yankee would have been out of business by the end of 2008, it makes no

offset to costs incurred in this claims period. See Tr. at 28:24-34:2 (Norton), 122:7-

124:5 (Smith). For both Connecticut Yankee and Yankee Atomic, plaintiffs offset

their damages claims for operating expenses through the time each utility would

have been out of business, at the end of 2010. See Tr. at 34:10-36:14 (Norton),

124:13-25, 147:21-148:8, 152:25-153:5 (Smith). Mr. Smith provided detailed

15

explanations of the costs and assumptions built into the models. See Tr. at 124:13-

127:23, 130:24-133:10, 147:21-155:22 (Smith).

The court found plaintiffs’ witnesses credible and believes that they presented

the best information possible in the non-breach world models. The government is

admonished to remember that its own failure to perform is the principle reason that

the plaintiffs are able to present non-breach world costs only with reasonable

certainty, rather than with absolute certainty.

Although neither party presents a foreseeability analysis for the general

operational expenses, the court notes that the record supports a finding that the

claimed costs were sufficiently foreseeable to justify recovery. In order to recover,

plaintiffs must demonstrate that both the type and amount of damages sought were

reasonably foreseeable at the time of contracting. See Vermont Yankee Nuclear

Power Corp. v. Entergy Nuclear Vermont Yankee, 683 F.3d 1330, 1344 (Fed. Cir.

2012).

The actual costs at issue here are storage facility operational costs incurred by

each utility during the claims period. See Doc. 39 at 11; Tr. at 91:21-92:3 (Smith).

As the court has previously noted, dry storage construction and maintenance were

reasonably foreseeable in the event of the government’s breach. Yankee Atomic, 73

Fed. Cl. at 267 (concluding that “absent DOE performance the need to spend

substantial sums for additional at-reactor storage was reasonably foreseeable at the

time of contracting”); id. at 288 (“The court finds that substantial SNF . . . dry storage

costs were reasonably foreseeable to DOE, the breaching party at the time of

contracting.”); Yankee Atomic, 94 Fed. Cl. at 710-711 (holding that “[i]n [the] non-

breach world, the Yankees’ dry storage costs would have been zero because dry

storage would not have been built,” and noting that the Federal Circuit affirmed the

“reasonableness and foreseeability” of the dry storage costs in Yankee Atomic, 536

F.3d 1268). Furthermore, the rather extreme expense of maintaining spent nuclear

fuel storage is entirely logical. See Yankee Atomic, 113 Fed. Cl. at 346 (noting that

“[n]uclear fuel storage is inherently a sensitive and expensive endeavor”) (citing

Yankee Atomic, 73 Fed. Cl. at 253 (stating that the disposal of SNF poses a “severe

potential health hazard” with “complex technical problems”) (citations omitted); id.

at 251 (noting that domestic utilities were required to enter into the Standard

Contracts at issue here due in part to the highly-regulated nature of the nuclear

industry, and that DOE agreed to accept the fuel “in return for payment of substantial

fees” by the utilities)).

16

This case presents a new foreseeability issue—whether it was reasonably

foreseeable at the time of contracting that plaintiffs would incur damages for

corporate existence in the event that the utilities were forced to remain in business

as a result of the government’s continuing breach. A finding that such damages were

reasonably foreseeable is a logical and only incremental extension of the court’s

previous holdings, and is fully supported by the evidence. The claims are based on

dry storage operational costs, which the court has already found to be reasonably

foreseeable. And even the language of the Standard Contracts contemplates that the

utilities would, at some point, cease producing spent nuclear fuel for the government

to dispose of. See, e.g., Ex. P3001 at 8 (“The services to be provided by DOE under

this contract shall begin, after commencement of facility operations, not later than

January 31, 1998 and shall continue until such time as all SNF and/or HLW from

the civilian nuclear power reactors . . . has been disposed of.”).

Subject to analysis of the government’s specific objections, plaintiffs are

entitled to recover damages for operational expenses in all three cases.

II. Benefits Administration Costs

Plaintiffs seek to recover all costs associated with administration of their

health and welfare benefits plans that were incurred beyond the dates on which each

plan would have been terminated in the non-breach world. See Doc. 39 at 24. Maine

Yankee asserts that it would have terminated its plan by the end of 2006, see Tr. at

197:5-9 (Pizzella), while both Connecticut Yankee and Yankee Atomic assert that

their respective plans would have been terminated in 2008, with some residual costs

incurred in 2009, see Tr. at 197:10-16, 201:21-202:24, 205:21-206:16 (Pizzella).

As the court previously explained, plaintiffs have complete discretion to

terminate these plans in one of three ways. Plaintiffs could have: (1) terminated the

plans without making any payments to beneficiaries, see Tr. at 198:5-7 (Pizzella);

(2) made a lump-sum payment from the trust, divided equally among beneficiaries,

see Tr. at 198:9-17 (Pizzella); or (3) sold the obligation to pay benefits to a third

party administrator, see Tr. at 198:17-18 (Pizzella).

At trial, plaintiffs refused to take a position as to which method of termination

they would have selected in the non-breach world. See Tr. at 200:7-11 (Pizzella).

Plaintiffs claim that any costs associated with effectuating the terminations would

come from the trust assets rather than the utilities’ operating budgets, thus not

requiring any offset in the non-breach world models that support plaintiffs’ damages

claims in this case. See Doc. 43 at 19; Tr. at 207:1-10, 236:15-237:9 (Pizzella). Ms.

17

Pizzella testified to this fact based on her experience transitioning pension

obligations to third parties, and did not cite any basis for her assumption that funding

administrative costs would work the same way for health and welfare benefits. See

Tr. at 236:15-237:9 (Pizzella). At oral argument, plaintiffs conceded that Ms.

Pizzella’s testimony was the only evidence in the record to support this assumption.

See Oral Arg. Recording, at 1:14:45PM-1:14:55PM (Feb. 19, 2016).

The government presented expert testimony that contradicted Ms. Pizzella’s

position. Mr. Larry Johnson testified that if plaintiffs sold the plan obligations to a

third party, they would have been required to make a lump-sum payment from their

operating budgets to cover future administrative costs that were “economically

equivalent” to the costs incurred in the breach world. See Tr. at 376:19-25, 429:5-

18 (Johnson). On the basis of this testimony, the government argues that in order to

demonstrate a plausible non-breach world scenario, plaintiffs are required to elect

between the three methods of termination and account for offsets of any

administration costs. See Doc. 42 at 29. Because plaintiffs refused to do so, the

government contends, they have failed to prove their damages. See id.

Neither party is entirely correct on this point. Contrary to the government’s

argument, the court would have no reason to require plaintiffs to select between the

methods of termination if, in fact, plaintiffs had proven that any costs associated with

any of the three methods would have come from the trust funds as opposed to the

utilities’ operating budgets. The problem for plaintiffs’ case is that they did not

present sufficient evidence on this point. Plaintiffs performed no financial analysis

on either of the first two options. See Tr. at 198:3-9 (Pizzella) (stating that plaintiffs

would not have chosen to terminate the plans without payment to employees); Tr. at

242:7-11 (Pizzella) (admitting that no analysis was done with regard to the cost of

the lump sum payment option). And with regard to the possibility of transferring

the obligation to a third party, the court is left with nothing more than competing

testimony from Ms. Pizzella and Mr. Johnson on which to base its decision. Both

Ms. Pizzella and Mr. Johnson were credible witnesses, but neither possesses

expertise in the area of terminating or transferring health and welfare benefits plans.

As such, the evidence is in equipoise, and plaintiffs have failed to carry their burden.

Plaintiffs are not entitled to recover the costs of health and welfare benefits

administration.

18

III. SWEC Proceeds

During the instant claims period, Maine Yankee received final proceeds from

the SWEC bankruptcy proceedings in an amount of $1,421,000. See Tr. at 207:23-

208:13 (Pizzella). The parties disagree, as they did in the previous round of

litigation, regarding how these funds should be allocated between Maine Yankee’s

decommissiong effort and as an offset to the government’s damages for construction

of dry storage facilities.

Plaintiffs have allocated 90% of the funds as an offset to its claim against the

government, and attributed the remaining 10%, or $142,100, to its decommissioning

costs. See Tr. at 208:14-21 (Pizzella). As noted above, Maine Yankee decided to

use the 90/10 allocation in accordance with an Offer of Settlement, approved by

FERC, which provided for the proper division of any additional payments received

from the SWEC bankruptcy in excess of $1 million. See Tr. at 207:23-210:19

(Pizzella). The agreement stated, in relevant part:

To the extent that Maine Yankee receives more than $1 million in such

additional payments on [the SWEC bankruptcy proceeding], on or after

such execution date, the Parties agree that Maine Yankee will be

permitted to receive 10% of the amount so received over $1 million as

an additional Incentive Budget payment. Maine Yankee may withdraw

any such additional Incentive Budget payment from the

decommissioning trust as a valid decommissioning expense, and

distribute to Maine Yankee’s owners.

Ex. P3010 at 10.

The government objects to this allocation, claiming that the entire amount of

additional funds should be set off from plaintiff’s claim. See Doc. 42 at 37; Tr. at

395:17-21 (Johnson). This position is based on the government’s view that such an

offset is mandated by this court’s previous opinion on the allocation issue. See id.

The government claims that the court “adopted the cap methodology” advocated by

Maine Yankee in the second round of this litigation. Doc. 42 at 36.

The government has misread the court’s previous opinion. Rather than adopt

Maine Yankee’s methodology, the court simply held plaintiff to its proposed offset

because the government’s own logic would have resulted in an even smaller offset

than plaintiff was willing to give. See Yankee Atomic Elec. Co., 113 Fed. Cl. at 339

(“Because [the figure resulting from the method of calculation presented by the

19

government] is well-below the $5.4 million that Maine Yankee has already

allocated, the court denies the government’s claim to an additional credit. The court

will, however, hold Maine Yankee to its $5.4 million figure.”).

The FERC settlement agreement expressly allows Maine Yankee to allocate

10% of any additional recovery, or $142,100 in this case, as a decommissioning

expense. The government has presented no argument or evidence that the agreement

is invalid or otherwise does not apply in the current circumstances, beyond its

incorrect argument with regard to the court’s previous opinion. As such, the court

finds that Maine Yankee’s decision to allocate 90% of the SWEC proceeds as an

offset to its claim for damages is proper.

IV. Property Transfer Costs

Connecticut Yankee and Yankee Atomic hired Vita Nuova, a consulting firm

that specializes in dealing with challenged properties, to assist the utilities in

dispositioning their land. The work Vita Nuova performed for the utilities included:

(1) reuse assessments to consider the relevant challenges of each parcel and options

for disposition, see Tr. at 312:21-319:5, 326:15-331:21 (Richardson); (2) efforts to

identify interested purchasers, see Tr. at 319:6-320:19, 332:1-333:22 (Richardson);

and (3) assisting with negotiations and purchase and sale agreements, see Tr. at

322:6-22 (Richardson). For these services, Vita Nuova charged Connecticut Yankee

$124,186, and charged Yankee Atomic $198,237. See Ex. P3020.

Ms. Elaine Richardson, Vita Nuova’s Vice President, served as project

manager on both accounts. See Tr. at 287:22-288:6, 314:6-320:12-15 (Richardson).

At trial, the court qualified her as an expert in dispositioning challenged properties.

See Tr. at 306:8-16 (Richardson). On the basis of her expertise, she testified with

regard to the time it would have taken in the non-breach world to disposition

property that is now complicated by the presence of dry storage facilities. See Tr. at

324:24-325:23, 335:3-337:10 (Richardson).

Ms. Richardson also testified at trial that the actual cost of Vita Nuova’s

services was higher than it would have been in the non-breach world due to the

presence of spent nuclear fuel on the sites. Specifically, she concluded that

approximately 40% of the work for Connecticut Yankee was related to the presence

of spent fuel, see Tr. at 348:24-349:1 (Richardson), while 20% of the work for

Yankee Atomic was related to the fuel, see Tr. at 349:13-15 (Richardson). Plaintiffs

now seek to recover this difference as part of their breach damages.

20

In coming to these percentages, Ms. Richardson personally reviewed the

invoices and back up documentation associated with each project. See Tr. at 346:12-

348:20, 349:2-351:16 (Richardson). She testified that the percentages were different

for each company because in arriving at her conclusions she took into account the

specific, unique challenges at each property. See Tr. at 349:16-351:16 (Richardson).

Ms. Richardson did not produce documentation of her review process or any sort of

work papers to support her conclusions. Rather, her estimates were based on her

personal knowledge of the projects.

At trial, the government objected to her testimony on this point, and the court

heard the evidence as an offer of proof. See Tr. at 303:4-8. The government does

not take issue with costs incurred, but argues that Ms. Richardson’s methodology

for arriving at these estimates is unreliable, and therefore, that plaintiffs cannot

recover. See Doc. 42 at 40-45. In addition, according to the government, Ms.

Richardson’s testimony is inadmissible because “specialized expertise is necessary

to determine what Vita Nuova costs were attributable to the presence of spent fuel,”

and she was not qualified as an expert on this issue. See id. at 44.

As an initial matter, the court sees no reason that expert testimony would be

required to apportion Vita Nuova’s invoices. Under Federal Rule of Evidence 701,

lay opinion testimony is sufficient so long as the opinion is:

(a) rationally based on the witness’s perception;

(b) helpful to clearly understanding the witness’s testimony or to

determining a fact in issue; and

(c) not based on scientific, technical, or other specialized knowledge

within the scope of Rule 702.

By way of explication, the Advisory Committee noted that most courts do not require

expert testimony on financial matters relating to a business’s value or expected

profits, so long as the offered testimony is based on “particularized knowledge that

the witness has by virtue of his or her position in the business.” Fed. R. Evid. 701,

Advisory Committee Notes, 2000 Amendments (citing Lightning Lube, Inc. v. Witco

Corp. 4 F.3d 1153 (3d Cir. 1993) (finding no abuse of discretion in permitting the

plaintiff’s owner to give lay opinion testimony as to damages, as it was based on his

knowledge and participation in the day-to-day affairs of the business).

The government claims that expert testimony is required under these

circumstances because Ms. Richardson did more than simply add numbers. See Doc.

42 at 44. To support this position, the government cites several cases. First, the

21

government points to In re MarketXT Holdings Corp., No. 1:04-12078 (ALG), 2011

WL 1422012 (Bankr. S.D.N.Y. Jan. 7, 2011). In that case, the Bankruptcy Court for

the Southern District of New York excluded lay testimony that related to “the state

of the securities markets, the state of the day-trading industry, customs and practices

within the day-trading industry, and the alleged potential profitability of the MTG,

measured by its own characteristics and by comparison with the performance of

allegedly similar groups.” See id., at *1. The court reasoned that the proposed

testimony should be excluded because it was not an opinion based on actual business

performance within the witness’s own perception, but was based on a series of

complex assumptions relating to financial market performance. See id., at *5, *6.

The government also cites LifeWise Master Funding v. Telebank, 374 F.3d

917, 929 (10th Cir. 2004) and Bank of China, New York Branch v. NBM LLC, 359

F.3d 171 (2d Cir. 2004). In LifeWise, the appellate court held that the company’s

Chief Executive Officer was improperly allowed to testify as to lost profits because

his testimony was not based simply on his personal knowledge of the company’s

operations, but instead involved “rolling averages, S-curves, and compound growth

rates that appear to be an amalgam of logic, hope, and economic jargon.” LifeWise,

374 F.3d at 930. And continuing with the common thread that only testimony based

on personal knowledge is permitted, the appellate court in Bank of China, disallowed

a witness’s testimony because it was “not based entirely on [the company

employee’s] perceptions,” but also required reference to his “experience and

specialized knowledge in international banking.” Bank of China, 359 F.3d at 181.

The testimony regarding complex projections and specialized knowledge of

financial markets and banking involved in the cases highlighted by the government

bears no resemblance to Ms. Richardson’s testimony here. Her opinion was rooted

not only in her particularized knowledge of Vita Nuova’s work and billing practices,

but in her significant personal involvement with the specific projects she was asked

to review. Ms. Richardson considered actual invoices, for work actually performed,

on projects managed by her, to draw her conclusions regarding what portion of that

work was required as a result of the presence of spent nuclear fuel. Her testimony

on this issue is admissible under Rule 701 as lay opinion.

The government also attacks the reliability of her methods—whether she is

considered a lay or an expert witness. See Doc. 42 at 42-43. Had the court concluded

that expert testimony was required on this point, plaintiffs would have been required

to demonstrate that Ms. Richardson’s methods were reliable. See Fed. R. Evid. 702

(requiring that “(c) the testimony is the product of reliable principles and methods;

and (d) the expert has reliably applied the principles and methods to the facts of the

22

case”). Because her testimony is acceptable as a lay opinion, however, the

government’s criticism of her approach goes to the weight of the evidence, not its

admissibility.

The court found Ms. Richardson to be a diligent and credible witness. She has

worked with Vita Nuova for nearly 20 years, see Tr. at 287:21 (Richardson), and as

the company’s Vice President is undoubtedly familiar with their billing practices.

She personally managed the projects at issue, and therefore, was well-positioned to

evaluate the extent to which the presence of spent fuel affected each billable activity.

The government’s position that Ms. Richardson’s evaluation required expertise

evinces an overly-complicated view of a relatively straightforward task. The court

admits Ms. Richardson’s testimony as sufficient to carry plaintiff’s burden.

Applying Ms. Richardson’s percentages to the total invoiced amount for each

company, Connecticut Yankee is entitled to recover $49,674 for property transfer

costs, and Yankee Atomic is entitled to recover $39,647.

V. Legal and Tax Expenses Related to Phase I Damages Award

During the instant claims period, plaintiffs received a large payment from the

government pursuant to the judgments in the first round of this litigation. See Tr. at

211:9-12 (Pizzella). As a result of that income, plaintiffs incurred legal and tax

expenses in an amount of $30,227 that they now seek to recover. Ms. Pizzella

testified that, based on her experience with procuring similar services, these

expenses are reasonable. See Tr. at 214:2-4 (Pizzella). The government does not

contest the fact that the costs were incurred, or that they are reasonable, but argues

that they should be categorized as legally unrecoverable costs of litigation. See Doc.

42 at 45-46.

“It is well settled that in the absence of specific statutory authority, expenses

incurred in litigation, whether legal, accounting, secretarial, or other, are not

awardable as such.” Kania v. United States, 650 F.2d 264, 269 (Ct. Cl. 1981)

(citations omitted). The costs claimed by plaintiffs, however, were not “incurred in

litigation,” within the plain meaning of that phrase. Ms. Pizzella testified that upon

receipt of “[a]ny large cash stream . . . we have to do a rate filing and a financial

analysis to show to FERC our funding needs and our ability to return the money to

our wholesale customers.” Tr. at 211:17-24 (Pizzella). In addition to expenses

related to meeting the regulatory requirements, plaintiffs engaged tax consultants in

order to understand the tax implications of receiving such large sums of money. See

Tr. at 211:25-212:14 (Pizzella). Plaintiffs do not seek to recover on invoices from

23

their attorneys in the first round of litigation. And the services at issue were not

performed in furtherance of plaintiffs’ positions related to any round of this

litigation.

Furthermore, these costs were foreseeable in the event of the government’s

breach. Ms. Pizzella testified: “Any fund stream I receive, I have to analyze it from

a tax stand point, from a regulatory standpoint. That’s what this is. This is, to me,

normal business activities [sic] that we undertake.” See Tr. at 213:7-214:4 (Pizzella).

The nature of these expenses, as ordinary and expected in the course of business,

demonstrates that the parties should have foreseen them as a consequence of a breach

at the time of contracting.

Plaintiffs’ are entitled to recover $30,227, divided between the companies as

follows: Maine Yankee, $10,500; Connecticut Yankee, $13,727; and Yankee

Atomic $6,000.

CONCLUSION

Based on the foregoing analysis, the court awards the plaintiffs the following

damages:

Yankee Atomic

Damages not specifically contested at trial: $19,595,425

Property transfer costs: $39,647

Legal and tax expenses: $6,000

Total recovery: $19,641,072

Maine Yankee

Damages not specifically contested at trial: $24,430,566

SWEC proceeds: $142,100

Legal and tax expenses: $10,500

Total recovery: $24,583,166

24

Connecticut Yankee

Damages not specifically contested at trial: $32,488,348

Property transfer costs: $49,674

Legal and tax expenses: $13,727

Total recovery: $32,551,749

All pending motions are DENIED as moot.

The court has filed this opinion under seal in the event that information

contained herein remains sensitive. The parties are directed to submit any proposed

redactions within fourteen days of the date of this opinion.

The clerk is directed to enter final judgment in favor of Yankee Atomic in an

amount of $19,641,072, final judgment in favor of Maine Yankee in an amount of

$24,583,166, and final judgment in favor of Connecticut Yankee in an amount of

$32,551,749.

SO ORDERED.

s/ James F. Merow

James F. Merow

Senior Judge

25