Opinion

Lockheed Martin Corporation v. United States

  • 124 Fed. Cl. 709
  • 2016 WL 765722
Court
United States Court of Federal Claims
Filed
Feb 19, 2016
Status
Published
Author
Lettow
On the bench
Charles F. Lettow
Cited by
9 cases
Authority
More cited than 57.8%

declining to preliminarily enjoin contract award when protestor did not establish a likelihood of success or irreparable harm

How later courts described this case

  • declining to preliminarily enjoin contract award when protestor did not establish a likelihood of success or irreparable harm
  • “[N]o one factor is dispositive.”
  • “[A] plaintiff may not show irreparable harm by claiming generically that the winner's transition into performance will give it advantages.”
  • “To the extent proposals differ, the government may rationally take different action regarding different proposals.”

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

No. 15-1536C

(Filed Under Seal: February 11, 2016)

(Reissued: February 19, 2016)

) Post-award bid protest; motion for

LOCKHEED MARTIN ) preliminary injunction; likelihood of

CORPORATION, ) success; discussions; FAR § 15.306; equal

) treatment; irreparable injury

Plaintiff, )

)

v. )

)

UNITED STATES, )

)

Defendant, )

and )

)

OSHKOSH DEFENSE, LLC, )

)

Defendant-Intervenor. )

)

Marcia G. Madsen, Mayer Brown LLP, Washington, D.C. for plaintiff. With her on the

briefs were David F. Dowd, Cameron S. Hamrick, Luke Levasseur, and Polly Myers, Mayer

Brown LLP, Washington, D.C. Of counsel was Maryann Surrick, Lockheed Martin Corporation,

Bethesda, Maryland.

William P. Rayel, Senior Trial Counsel, Commercial Litigation Branch, Civil Division,

United States Department of Justice, Washington, D.C., for defendant. With him on the briefs

were Benjamin C. Mizer, Principal Deputy Assistant Attorney General, Civil Division, United

States Department of Justice, Washington, D.C., and Robert E. Kirschman, Jr., Director, and

Douglas K. Mickle, Assistant Director, Commercial Litigation Branch, Civil Division, United

States Department of Justice, Washington, D.C.

Scott Arnold, Dickstein Shapiro LLP, Washington, D.C., for defendant-intervenor. With

him on the briefs were Harvey G. Sherzer, Justin A. Chiarodo, Stephanie M. Zechmann, and

Christian N. Curran, Dickstein Shapiro LLP, Washington, D.C.

OPINION AND ORDER 1

LETTOW, Judge.

The Army held a competition in three phases for a contract to design, develop prototypes

of, and ultimately manufacture and supply a new armored but agile all-terrain tactical vehicle to

be used in combat zones. Oshkosh Defense, LLC (“Oshkosh”) won the last phase of the

competition in August 2015, and it was awarded the manufacturing contract. Lockheed Martin

Corporation (“Lockheed”), a losing offeror, has filed suit seeking a court order that would

require the Army to reopen the competition and give Lockheed another chance. Lockheed

generally alleges that the Army violated procurement law by failing to credit Lockheed’s data

relating to performance of its proffered prototype, while unfairly crediting Oshkosh’s data

relating to its prototype under similar circumstances. The Army disputes these allegations and

avers that the performance of the vehicle Lockheed proposed was not as desirable as that

proposed by Oshkosh.

It may take time to resolve this case, especially given that the administrative record

reportedly is over 300,000 pages in length and numerous fact-intensive issues have been raised.

Because of that prospect, Lockheed has requested a preliminary injunction in the form of a stop-

work order, which would bar Oshkosh from doing work while this case is pending. This opinion

addresses Lockheed’s request. Unfortunately, the court must decide the pending motions

without having in hand all of the evidentiary materials in the Army’s procurement record.

Instead, for the purpose of resolving Lockheed’s motion, the parties have submitted excerpts of

the records of the procurement, along with some materials from aborted protest proceedings that

occurred before the Government Accountability Office (“GAO”).

After reviewing the available materials, the court has decided to deny Lockheed’s motion

for a preliminary injunction. The court concludes that Lockheed has not made a sufficiently

strong showing that it is likely to prevail on the merits of its protest or that it will be irreparably

harmed if Oshkosh conducts the initial work due under the awarded contract.

1

Because this opinion and order might have contained confidential or proprietary

information within the meaning of Rule 26(c)(1)(G) of the Rules of the Court of Federal Claims

(“RCFC”) and the protective order entered in this case, it was initially filed under seal. The

parties were requested to review this opinion and provide proposed redactions of any

confidential or proprietary information. The resulting redactions are shown by brackets

enclosing asterisks, i.e., “[***]”.

2

FACTS 2

A. The Army’s Three-Phase Plan to Develop a New Tactical Combat Vehicle

In 2007, the Army and Marine Corps began planning a program to develop a Joint Light

Tactical Vehicle (“JLTV”). PI-1155. 3 The JLTV would be light, mobile, and capable of airlift,

while still providing strong armor and heavy payload capacity. PI-1558. This vehicle would fill

a “critical capability gap” in the military’s combat transport assets. PI-1558. Currently, the

military has heavily armored vehicles that are difficult to maneuver off-road, and it has light

vehicles that lack strong armor and thus fail adequately to protect soldiers and marines from

explosives. PI-1558. The JLTV would fill this gap, being fast, relatively light, and well

armored. PI-1558.

The JLTV program has three phases, each of which has been covered by a separate

contract. PI-1155. In Phase One, three companies won contracts to design the JLTV. Phase

One lasted from 2007 until 2012. PI-1155. Lockheed and two other companies won this design

contract. PI-1155. Phase Two began in 2012 and lasted until 2014. PI-1155. The Army

awarded the Phase Two contracts to Lockheed, Oshkosh, and AM General, LLC. PI-1155. In

Phase Two, the three companies fabricated 22 JLTV prototypes. These prototype vehicles then

were extensively field-tested by the Army, being driven roughly 155,000 miles during those field

tests. PI-1155. In the tests, the Army collected data to be used during the Phase Three

competition. For Phase Three, only the Phase Two contractors were eligible to compete, and

only one could win. Phase Three involves production and deployment of the JLTV, which

would become operational by 2019. PI-1560.

In December 2014, the Army invited the three companies who had participated in Phase

Two to bid for Phase Three, and each submitted bids. PI-1156. The Army selected Oshkosh for

the final award on August 24, 2015. PI-1159. Lockheed filed protests of the Army’s decision

with GAO in September 2015. PI-1159. Toward the end of the GAO proceeding, the Army

located a substantial number of records of its evaluation of the competing offers which had not

previously been included in the record of the procurement as provided to GAO. When GAO

indicated that it would proceed to render a decision without considering the newly provided

materials, Lockheed filed suit in this court on December 16, 2015. The next day, Oshkosh

2

The recitation of facts is drawn from the evidentiary submissions of the parties, which

they represent have been drawn from the administrative record that will be filed with the court.

The court has conducted its preliminary analysis of the merits pursuant to the standards of 28

U.S.C. § 1491(b), RCFC 52.1(c), and Bannum, Inc. v. United States, 404 F.3d 1346, 1356 (Fed.

Cir. 2005) (noting that bid protest proceedings “provide for trial on a paper record, allowing fact-

finding by the trial court”).

3

The record excerpts provided by the parties during briefing were sequentially paginated,

beginning with those provided by plaintiff with its complaint. See Pl.’s Compl. for Declaratory

and Injunctive Relief Exs., ECF No. 17-1; Defs.’ Joint Supplemental App., ECF Nos. 27-1 and

27-2; Pl.’s Reply Exs., ECF No. 31-1. That sequential numbering scheme will be used in this

opinion preceded by “PI,” as “PI-__”.

3

intervened to defend the award. Mot. to Intervene, ECF No. 8. AM General did not intervene,

and it is not a party to this case.

B. During Phase Two, the Army Field Tests the Designs of the Contractors

The Phase Two contract required the winners to manufacture 22 prototype JLTVs and

turn them over to the government for testing. PI-1155. The contract provided performance

benchmarks, which each contractor sought to achieve during testing. For example, the vehicle

needed to start within [***] in temperatures ranging from [***] Fahrenheit, PI-357, accelerate

from [***] miles per hour in under [***], PI-360, ford [***] water, PI-376, and provide air

conditioning that could lower the crew compartment temperature from [***] Fahrenheit within

[***], PI-447. Most importantly for this case, the government also evaluated the rate at which

the vehicle’s functions became impaired or failed. This rate was determined by applying “failure

scoring criteria,” which focused particularly on “mission essential function” failures. PI-503,

506 to -07. 4 A failure was generally defined as an event “in which an item or part of an item

does not perform as specified.” PI-504. A failure could be classified as an essential function

failure (“EFF”), an operational mission failure (“OMF”), or a hardware mission failure (“HMF”).

PI-504.

“An EFF is an event that results in significant degradation of a [mission essential

function], yet the vehicle is still partially mission capable.” PI-504. In contrast, “[a]n OMF is an

event that results in the loss of a [m]ission [e]ssential [f]unction . . . that reduces its utility to the

point that it is deemed ineffective in its role on the battlefield. OMF[s] are failures that cause

immediate removal from service in an operational environment or that preclude a vehicle from

starting a mission on time.” PI-504. Finally, a HMF “is a subset of OMFs that are chargeable to

[the] contractor.” PI-504.

The Army’s field tests counted the mean miles driven between EFFs and the mean miles

driven between HMFs. In particular, the vehicle needed to be able to demonstrate 3800 mean

miles between hardware mission failures (“MMBHMF”). PI-427.

1. The contractors’ Phase Two demonstrated failure rates.

During the Phase Two contract, both Oshkosh’s and Lockheed’s prototypes failed to

demonstrate 3800 MMBHMF. PI-212. Each contractor could make changes or “fixes” to its

prototype vehicles during the field tests. Lockheed’s vehicles were tested three separate times,

demonstrating [***] MMBHMF and showing [***] during the three field tests. PI-113. In

contrast, Oshkosh’s vehicles demonstrated [***] MMBHMF and showed improvement over the

tests. PI-128. Of relevance, however, during this testing, Oshkosh’s [***] experienced an EFF.

PI-597.

4

Mission essential functions reflect essential or highly desirable performance

characteristics. As an example, mission essential functions included “mobility,” which meant

“[t]he capability to provide forward and rearward motion, day and night, over varying terrains

and environments specified [elsewhere in the RFP]. Included in this essential function is the

capability to start, stop, and maneuver the vehicle.” PI-503.

4

2. Each contractor presents changes at an Army assessment conference.

After field testing, the government held an “assessment conference,” during which each

contractor proposed or implemented “fixes” to their prototype vehicles. PI-115, -129. With

these fixes, one could calculate an “assessed MMBHMF.” PI-115, -129.

The effect of a proposed fix was calculated by applying three “fix effectiveness factors”

(“FEF”). PI-115. The factors were: (1) understanding the root cause of the failure; (2) certainty

of improvement; and (3) test results to verify the effectiveness of the corrective action. PI-115;

Compl. ¶ 33. Each of these fixes was rated from 0.0 to 0.9 in increments of 0.3 such that the

maximum fix score was 0.9. PI-115; Compl. ¶ 33. This rating would then be applied against the

number of failures, resulting in an “assessed reliability” score. PI-115; Compl. ¶ 33.

An assessment conference fix to a contractor’s design could be either proposed or

implemented. A proposed change was just that – a proposal. But if a change had been actually

implemented during Phase Two testing, then it would have been on the vehicle for any remaining

portion of the field tests, allowing the change to receive potential credit under FEF (3) – test

results. Hr’g Tr. 131:23-25, 132:1-4 (Jan. 20, 2016); 5 see also Pl.’s Notice of Citation, ECF No.

35. For example, Oshkosh experienced [***] types of HMFs. Pl.’s Notice of Citation at 3-4. Of

these, Oshkosh implemented changes to address [***] of these failures, allowing the changed

vehicles to drive for tens of thousands of (and in some cases over one hundred thousand)

additional testing miles after the change had been implemented. Id. 6

After the assessment conference, the government’s “assessed MMBHMF” for

Lockheed’s vehicle was [***] and that for Oshkosh was [***]. PI-115, -129.

C. The Army Issues a RFP for Phase Three, Establishing the Rules of the Competition

The competition for Phase Three began in December 2014 with the Army’s Request for

Proposals (“RFP”). PI-1156. The offerors from Phase Two were each invited to bid, and each

had an opportunity to improve upon their design to offer an even better vehicle than that tested in

Phase Two. PI-1156 to -57.

1. The RFP establishes a best-value procurement based on three factors.

Pursuant to the RFP, the government would award the contract to the company offering

the “best value.” PI-101 (RFP § M.1.1). Value would be determined using a tradeoff process

between three factors: Primary Technical; Total Evaluated Cost/Price (“TEC/P” or “price”); and

5

The date of the hearing will be omitted from further citations to the hearing transcript.

6

Lockheed points out that [***] of Oshkosh’s Phase Two changes were tested for [***]

miles; [***] were tested for [***] of the field testing’s total miles; and [***]% of changes were

tested for [***]% or less of those miles. Pl.’s Notice of Citation at 1.

5

Small Business Participation. PI-101 (RFP § M.1.1). These three factors were not equally

weighted. Instead, Primary Technical was the most important factor; price was second most

important; and Small Business Participation was least important. PI-101. Primary Technical

referred to the ability of the offeror to meet the government’s performance requirements for the

vehicle. PI-104 (RFP § M.4.1). Thus, for example, the requirement that a vehicle demonstrate

3800 MMBHMF was a Primary Technical requirement.

In addition, the Primary Technical and Small Business Participation factors combined

were “significantly more important” than the price factor. PI-101 (RFP § M.1.1). This meant

that price was not dispositive, and the RFP stated that “th[e procurement] determination may

result in award to other than the [o]fferor with the lowest TEC/P.” PI-102. Although the RFP

established that price was not controlling, it also explained that a scenario existed in which price

could be controlling, i.e., “when proposals are otherwise considered approximately equal in non-

TEC/P factors.” PI-102 (RFP § M.3.1(a)).

2. The Primary Technical factor explained.

Pursuant to the Primary Technical factor, the Army would “assess” the “risk that the

[o]fferor[’]s JLTV will [not] achieve the [g]overnment’s defined threshold performance levels

for [25 different purchase descriptions listed in the RFP’s Attachment 0061]. Each P[urchase]

D[escription] requirement identified in Attachment 0061 is weighted equally and will be

evaluated as such.” PI-104 (RFP § 4.1). Attachment 0061 listed these 25 purchase descriptions

by a “PDFOV” number. The 25 purchase descriptions called for a variety of performance

requirements. For example, one required that the JLTV “be capable of ascending [***],” PI-359

(PDFOV-7478), while another required the JLTV to “be capable of entering and exiting [a

variety of different warships].” PI-395 (PDFOV-8452). A risk assessment for a purchase

description would be based on an adjectival rating scale of very low, low, moderate, high, and

unacceptable risk. PI-1007 (providing definitions for each adjectival rating category).

Of the 25 purchase descriptions, two are relevant to this case. First, PDFOV-2909

provided that the “JLTV shall demonstrate at a minimum, a point estimate of 3,800 Mean Miles

Between Hardware Mission Failure (MMBHMF).” PI-427. This PDFOV was termed

“Reliability.” PI-427. Second, PDFOV-2918 provided that the “JLTV shall demonstrate the

operational availability (Ao) of 95%.” PI-428. PDFOV-2918 was called “Operational

Availability,” and was determined by multiplying MMBHMF by other stated factors. PI-428.

Thus Operational Availability was linked to MMBHMF, meaning that an error in the MMBHMF

calculation could cause an error in the Operational Availability calculation.

Pursuant to Section M.4.1 of the RFP, the government would assess the risk that an

offeror would fail to meet these standards by analyzing Army testing data from Phase Two and

data submitted by the offerors. PI-104. The RFP explained:

Government test data which establishes conformance to the proposed

design configuration represents the most credible form of substantiating

data. Therefore, any substantiating data for a design configuration which

meaningfully varies from the offered design configuration may be considered

6

less credible. The greater the extent to which the [o]fferor[’]s proposed design

configuration meaningfully varies from the originally tested configuration or

testing conducted under different conditions, the greater the probability that

the [g]overnment may discount the relevance of the test data as substantiating

information.

PI-104 (emphasis added). In effect, this meant that the data from Phase Two, including the

“assessed MMBHMF” scores, would be the “most credible form” of data. PI-104. Offerors

could also submit non-government data, including data generated by the offerors themselves.

However, non-governmental data would be considered “less credible.” PI-104. Meaningful

variation was also not binary, but rather a matter of degree. Greater meaningful variation meant

“greater probability” that the government would discount the Phase Two data. This created an

incentive for offerors to propose designs that did not “meaningfully var[y]” from the Phase Two

design, because they would otherwise need to provide sufficient data for the Army to conclude

that the design would still meet the government’s purchase-description requirements.

In addition, RFP § 4.1.2 permitted offerors to propose performance that exceeded the

minimum thresholds set by the purchase descriptions. PI-104. Performance beyond threshold

level would be accepted if it was backed by credible substantiating data. If so, then the RFP

provided that the Army “may” assess the offer at a “reduced risk” of meeting the purchase-

description requirements. But if the proposed beyond-threshold performance was not backed by

credible substantiating data, then pursuant to RFP § M.4.1.5 it could be disqualified from the

competition. PI-104.

3. How MMBHMF affected the price calculation.

Price would be determined by a formula set out in RFP § 4.2. PI-104. One factor in this

formula was “life cycle cost,” which predicted repair costs over the life of a vehicle. Included in

“life cycle cost” was each offeror’s “proposed” MMBHMF score under PDFOV-2909, since a

vehicle with fewer failures would need fewer repairs. PI-106 (RFP § M.4.2.3); see also PI-524

(attachment to RFP showing the life cycle cost formula). Of crucial importance, the life cycle

credit was not based on an offeror’s demonstrated or even assessed MMBHMF. Instead, it was

based only on the MMBHMF “proposed” in the final offer. PI-106.

This created an incentive for offerors to propose a high MMBHMF. The higher the

proposed score, the cheaper the proposal would look under the Army’s price evaluation.

However, RFP § M.4.1.5 prevented offerors from proposing an unrealistically high MMBHMF.

PI-104. As described above, if offerors could not support their MMBHMF claims with credible

substantiating data, then the offer could be disqualified.

7

D. Lockheed and Oshkosh Make Initial Offers in Early 2015

1. Lockheed’s initial offer.

In its initial offer, Lockheed stepped up its MMBHMF from [***], assessed during Phase

Two, to a proposed MMBHMF of [***]. PI-525. Lockheed conceded that it had not yet met this

performance standard, but said that it “has committed to achieving” MMBHMF based on future

testing and “ongoing RGT design improvements” after award. PI-525 [***]. 7 Lockheed later

explained that its [***] proposal was also based on [***]. PI-862. Lockheed expressly noted

that it was proposing [***] in the RFP. PI-525.

Lockheed’s offer was premised upon inclusion of a variety of design changes, including

changes to [***]. PI-114; see also PI-866 (acknowledging changes to many of these systems).

Lockheed initially did not provide information relating the effect of these changes to its

prototype tested during Phase Two, which could have shown the government the extent to which

the design improved upon and varied from that tested in Phase Two. PI-114.

2. Oshkosh’s initial offer.

Oshkosh proposed a vehicle with [***] MMBHMF, which roughly matched Oshkosh’s

assessed MMBHMF from Phase Two field testing. PI-129. Oshkosh also proposed [***] design

changes, including changes to [***]. PI-129; see also PI-220, -589, -843 ([***]). Its

submissions included substantiating data and information showing the government how

Oshkosh’s proposed design was revised from its Phase Two prototype design. PI-130.

E. The Army Corresponds with Lockheed and Holds Discussions

On April 16, 2015, the Army sent notices to Lockheed raising questions about its

proposal. PI-8543 to -56. First, the Army said Lockheed’s “proposal does not explain the extent

of the variances and the impact of such variances between the As-Tested [Phase Two] design and

the proposed design. The [o]fferor did not provide accurate traceability for the RAM[‘Reliability

Availability Maintenance’]-related Corrective Actions, defining how the [Phase Two] tested

configuration transitions to the proposed design configuration and the impact to RAM at the

7

“RQT” or “Reliability Qualification Testing” is to be conducted post-award as part of

Phase Three. PI-54 (RFP § 6.2.4.2.1.2). The Reliability Qualification Testing is to be conducted

by the government whereas post-award Reliability Growth Testing is to be conducted by the

Phase Three awardee. See PI-148 (Lockheed offer document proposing “RGT”). Oshkosh also

proposed to do its own growth testing post-award, see PI-273, but its offered performance did

not rely on growth post-award to meet solicitation requirements. The Failure Definition and

Scoring Criteria (“FDSC”) contemplate that “Reliability Growth Testing (RGT)” could occur,

and that the FDSC criteria would apply. PI-501 (noting that failure scoring occurs during

Reliability Growth Testing, Reliability Availability Maintaining Testing, and “other reliability

testing”). But the court can discern no RFP provision requiring any Reliability Growth Testing.

In sum, it appears RGT is an optional exercise the contractor receiving the Phase Three award

might undertake.

8

system level.” PI-854. Second, the Army indicated to Lockheed that it had not provided

sufficient data to substantiate its proposal. In particular, “the offeror did not provide

substantiating data to support the proposed [fix effectiveness factor] claims and threshold

MMBHMF.” PI-856.

Lockheed responded to the Army on April 20 with performance and testing data, but it

continued to rely on future growth and design changes. See PI-858. A few days later, on April

24, the Army sent Lockheed another notice saying that Lockheed’s submission of data on April

20 was deemed insufficient. PI-857 to -58. The Army advised that Lockheed’s “proposed

configuration meaningfully varies from the as tested [Phase Two] configuration. This

appreciably reduces the relevance [of] the Government Assessment Conference and the final

assessed MMBHMF.” PI-858. The government identified four specific concerns:

“[Lockheed] . . . [first] has not justified the relevance and validity of [***] used to support

MMBHMF claims[, second,] has not identified apparent non[-]RAM related configuration

changes[, third,] has not substantiated apparent non[-]RAM related configuration changes and

associated impacts to reliability,” and fourth, Lockheed’s proposed MMBHMF of [***] “is

considered an[] unsubstantiated technical commitment, per section M.4.1.5. As such . . .

[Lockheed’s] proposal is in jeopardy of being rejected.” PI-858. 8

Lockheed promptly responded. PI-860. Lockheed noted that Phase Two and Phase

Three used different scoring criteria for failures. PI-862; see also PI-894 (explaining Lockheed’s

understanding that the scoring criteria had changed between Phase Two and Phase Three).

Applying Phase Three standards to the data collected in Phase Two, Lockheed believed it had a

“start point” MMBHMF of [***]. PI-864. With this number as a baseline, Lockheed predicted

there would be “new modes that will surface during [Lockheed’s planned] [***]. PI-864

(emphasis added). Taking that [***] into account, Lockheed reiterated its prediction of an

average FEF factor of [***]. PI-864. On the basis of these yet-to-be-achieved changes and

predictions, Lockheed would contractually commit to [***] MMBHMF. PI-864.

Lockheed acknowledged that it had made [***] design changes, but averred that each had

been analyzed for MMBHMF impact. PI-865. Based on a [***] Lockheed estimated that the

[***]. PI-865. This [***]. PI-865 to -66 (listing reasons). Lockheed acknowledged making

changes regarding [***]. PI-866. Lockheed’s response explained that it would continue to make

“design improvements configuration changes,” and that based on future design changes and

testing, it would achieve [***] MMBHMF. PI-866.

The Army sent Lockheed a further notice on May 7, 2015 saying that the company still

had not applied the FEF and reliability standards correctly, and that the proposed [***]

MMBHMF was still unsubstantiated and consequently at risk of disqualification. PI-890 to -91.

Lockheed responded with additional data, restating its position that based on the scoring criteria

in Phase Three (which differed from Phase Two) and based on [***], Lockheed estimated a

“start-point” MMBHMF of [***]. PI-895. It stood by its proposal to grow MMBHMF in the

future.

8

“Non-RAM” changes refer to design changes made after Phase Two. Hr’g Tr. 35:18-25.

9

Army evaluators held an internal meeting on May 19, 2015 at which they discussed

Lockheed’s proposal. PI-184. Notes from the meeting show that the evaluators were concerned

that (1) Lockheed had not “substantiate[d] the design changes” and was relying on Phase Two

data even though the design meaningfully varied; (2) Lockheed proposed to make future design

changes; and (3) that Lockheed’s [***] MMBHMF was unsubstantiated. PI-184. The evaluators

also said “[u]p to this point, the main message has been a lack of substantiating data, leading

L[ockheed] to provid[e] more data. Need to address the fact that a number lower than the

proposed reliability can be substantiated. L[ockheed] is providing well above the reliability

performance that can be substantiated.” PI-184.

The next day, May 20, 2015, representatives of Lockheed and the government had a

detailed oral discussion. PI-170 to -82. The Army began by advising Lockheed of problems

with its proposal: “I’d like to state upfront that the [g]overnment still assesses threshold

performance for PDFOV-2909 as appreciably increased risk and the proposed value as an

unsubstantiated technical commitment.” PI-171. The government further told Lockheed that

because of “the complexity of the components and subsystems that were addressed with

corrective actions, combined with the quantity of design changes impacting [mission essential

function] and . . . related components, we believe that the design meaningfully varies from the

[Phase Two] as tested configuration.” PI-171 (emphasis added). The government added that it

“does not view the [***] [MMBHMF assessed in Phase Two] as still[ ] being relevant.” PI-173.

Although the Army did not give Lockheed a list of every change that needed supporting

data, or which meaningfully varied, the Army provided an example of one such change: “For

example the [***] . . . experienced multiple issues during [Phase Two] Reliability Testing [but

received a FEF of [***] during Phase Two based on proposed solutions] . . . . Within the

proposed design, the [***] was changed from that which was presented within [Phase Two]. . . .

Therefore, the system meaningfully varies and the achieved [Phase Two] [***] FEF is

invalidated[.] Data identifying & substantiating the projected FEF was not provided; this should

come in the form of the three components that make up a FEF – Root Cause, Certainty, and Test

Results.” PI-171 to -72.

Later, Lockheed representatives asked, “Do[] the RFP and subsequent contract include or

contemplate reliability growth prior to starting [post-award] Government Reliability

Qualification Testing ([post-award] RQT)?” PI-174. Although the RFP required substantiating

data, PI-104, Lockheed apparently wanted to rely on predicted future growth. The government

explained that “[a] growth curve does not substantiate the performance of a particular design.”

PI-175.

Lockheed then asked, “[I]f the government does not recognize reliability growth prior to

Government RQT, what is the [g]overnment’s basis for providing offerors such large TEC/P

incentives?” PI-175. This question appears to address the life cycle credit, by which a high

MMBHMF number could reduce the government’s evaluated price. The government’s

representative reiterated that Lockheed could not rely on future growth or design changes:

As we understand it, L[ockheed]’s RGT significantly influences the proposed

value [***]. Through RGT, the design will evolve and may derive

10

a configuration that varies from the proposed design. In essence, L[ockheed]

is asking the [g]overnment to accept and evaluate a design that is different

from what is being proposed. Nowhere within the RFP is it stated that we

will evaluate a design other than what is explicitly being proposed. It doesn’t

appear that RGT concludes prior to the [g]overnment taking ownership of

the design, [so] it is unclear how L[ockheed] is planning to implement RGT

corrective actions to accomplish [the] proposed reliability claim.

PI-175 to -76.

Toward the end of this discussion, Lockheed asked about whether it needed to provide

more substantiating data. One Lockheed representative asked, “Did we provide enough

substantiating data for the [***] [post-Phase Two] changes?” PI-177. To this, the Army

responded that “the [g]overnment is still evaluating data to verify the [g]overnment’s position on

the [***] [post-Phase Two] changes.” PI-177. Another Lockheed representative then said

“[Lockheed’s] understanding is that the [g]overnment wants data for every change.” PI-177. In

response, the government said: “Yes, think of every change is a change is a change.” PI-177.

After these discussions on May 20, Lockheed submitted a revised response to the

government’s notice dated May 7. PI-896 to -913. In this revised response, Lockheed [***] its

proposed MMBHMF to [***]. PI-899. Lockheed explained that its decision “is largely based on

the [g]overnment’s decision to [***].” PI-899. Lockheed acknowledged that its previous

proposals had “forecast[] design improvements and/or changes” and that the government wanted

an “evaluation of only the proposed [Phase Three] design at the time of proposal evaluation.”

PI-900 (emphasis in original). Lockheed also explained that it had re-analyzed the FEFs

pursuant to the government’s instructions. PI-900.

F. The Army Evaluates Lockheed’s and Oshkosh’s Final Offers

1. Lockheed.

A source selection evaluator described the history of communications with Lockheed,

observing that Lockheed originally failed to explain “the extent of the variances and the impact

of such variances between the [Phase Two] as-tested configuration and the proposed design are

still unknown.” PI-114 to -15. Later submissions from Lockheed traced the changes, which the

Army then understood. PI-116. The evaluator concluded Lockheed’s design meaningfully

varied, based on the “complexity of the components and subsystems that were addressed

. . . combined with the quantity of design changes.” PI-114. This included changes to [***]. PI-

114. The evaluator also noted that certain changes “have the potential to cause a Mission

Essential Function (MEF) failure and therefore meaningfully vary from [Phase Two] test

configuration.” PI-114.

Because of the meaningful variation, the MMBHMF assessed in Phase Two was “not

relevant,” and the evaluator needed to look at non-government data. PI-115 (“This risk can only

be addressed with substantiating data.”). Lockheed provided data and engineering narratives to

support its proposal, but these offeror-supplied data were deemed “less credible.” PI-117.

11

Nonetheless, Lockheed’s data were considered sufficient to substantiate its [***] MMBHMF

[***] threshold of 3800, meaning its proposed MMBHMF [***] was not an unsubstantiated

technical commitment. PI-118. But because this [***] performance was not “well-supported,” it

did not reduce Lockheed’s overall risk assessment. PI-118. The evaluator accordingly rated

Lockheed a “high” risk of not meeting PDFOV-2909’s 3800 MMBHMF figure. PI-118.

Likewise, the evaluator concluded Lockheed was at a “moderate” risk of meeting PDFOV-

2918’s Operational Availability requirements, in part because the proposed MMBHMF [***]

and because Lockheed had failed to fully substantiate its changes. PI-125 to -26.

2. Oshkosh.

The evaluator found that Oshkosh’s design did not meaningfully vary from Phase Two.

PI-129. The evaluator said that Oshkosh’s final design included [***] corrective actions that

were implemented during Phase Two testing and “remain constant within the proposed design.”

PI-129. [***] other corrective actions had not been implemented during Phase Two but were

deemed to “minimally vary,” although they did “reduce the relevance” of Phase Two data. PI-

129.

Next, the evaluator said that Oshkosh had made [***] other “design changes,” but that

these were “not related to [Phase Two] HMFs.” PI-129. Of these, [***] “address manufacturing

efficiencies and supplier changes. As these changes are the same form, fit and function; these

changes do not meaningfully vary from the [Phase Two] as-tested configuration . . . [and

therefore] have no impact on the relevance of [Phase Two government] test data.” PI-129. The

remaining [***] changes “address requirement changes and reliability enhancements. Some

changes are paper only, an accounting exercise, to address B[ill of ]M[aterials] issues. The

remaining changes were reviewed for impact to Mission Essential Functions (MEF) and were

determined not to meaningfully vary from the [Phase Two] as-tested configuration. Therefore,

relevance of [Phase Two] test data is not impacted.” PI-129.

Although Oshkosh’s final design did vary somewhat from its Phase Two design, “the

impact of such variances” were “understood” by the evaluator. PI-129. The changes were

deemed to have a “slight impact” on the “relevance” of government data from Phase Two, which

correspondingly only “slightly increase[d]” the risk assessment. PI-129. Oshkosh provided

other data, including engineering analyses, which the evaluator considered “less credible” but

which still substantiated Oshkosh’s claims. PI-130. In light of these data, and the fact that

government data from Phase Two remained relevant, the evaluator rated Oshkosh a “low” risk of

failing to meet PDFOV-2909, Reliability. PI-131. For similar reasons, Oshkosh was rated a

“very low” risk of failing to meet PDFOV-2918, Operational Availability. PI-135.

G. The Army Selects Oshkosh for Award

After reviewing the evaluator’s materials, the Source Selection Authority (“SSA”), David

G. Bassett, drafted a Source Selection Document that selected Oshkosh for award and explained

his reasoning. PI-1004 to -14. Beginning with the Primary Technical factor’s 25 purchase

descriptions, the SSA noted that Oshkosh was rated a “low” risk in thirteen categories and a

“very low” risk in twelve categories. PI-1011. This summary included Oshkosh’s rating of

12

“low” for PDFOV-2909 and “very low” for PDFOV-2918. PI-1010. Given these results, the

SSA agreed with prior evaluators that Oshkosh’s overall Primary Technical risk rating was

“low.” PI-1011.

Lockheed contrastingly had received one “high,” five “moderate,” twelve “low,” and

seven “very low” risk ratings. PI-1010. Lockheed’s “high” rating was for PDFOV-2909,

Reliability. On this point, however, the SSA disagreed with the prior evaluators. PI-1011. The

SSA “gave greater technical credibility to the likely effectiveness of the design changes

proposed” based on his “reviewing the specific design changes and their description of the

substantiating data with the [evaluation] team.” PI-1012. Thus the SSA gave Lockheed a

“moderate” rating for PDFOV-2909, bringing Lockheed’s score to six “moderate,” twelve “low,”

and seven “very low.” PI-1012. Overall, the SSA assigned Lockheed a “moderate” Primary

Technical risk rating. PI-1012.

On the price factor, the SSA noted that Lockheed’s evaluated contract price was $[***]

billion. Lockheed had received a life cycle cost credit of $[***]; a “TDP” (i.e., Technical Data

Package) Adjustment of $[***]; 9 a “Tier 1 Adjustment” of $[***]; and a “Secondary Technical

Adjustment” of $[***]. PI-1012. This brought Lockheed’s TEC/P to $3.087 billion. PI-1013.

Oshkosh’s evaluated contract price was $5.587 billion. PI-1012. It received a life cycle

cost credit of $1.527 billion; a TDP Adjustment of $511 million; a “Tier 1 Adjustment” of $229

million; and a “Secondary Technical Adjustment” of $622 million. PI-1012. This brought

Oshkosh’s TEC/P to $2.689 billion. PI-1013. Thus Oshkosh’s TEC/P was roughly $398 million

less than Lockheed.

Overall, the SSA found Oshkosh offered the “best value.” PI-1014. 10 Regarding Primary

Technical, the SSA noted that Lockheed received a “moderate” overall risk score, while Oshkosh

received a “low” risk score. PI-1014. Although the individual ratings appeared to be similar, the

SSA wrote that “the proposals were not as close as this might imply as [Oshkosh] is assessed as

Low Risk or Very Low Risk for all 25 requirements whereas . . . [Lockheed has] a number of

Moderate Risk ratings[.]” PI-1014. “The [Oshkosh] proposal met or exceeded requirements,

and was supported by the most credible substantiating data supporting a low risk Primary

Technical rating.” PI-1014. Although Lockheed had the best small business participation, the

SSA noted that this is “the least important factor” under the RFP, and that it “is significantly

offset by the [Oshkosh] proposal’s superiority in the two most important factors of Primary

Technical and TEC/P.” PI-1014.

9

The Technical Data Package Adjustment represents the value of a government option to

purchase additional rights to data and intellectual property regarding the JLTV. See PI-94 (RFP

§ 6.4.2.3).

10

As for small business participation, Lockheed was rated “outstanding” and Oshkosh

was rated “good.” PI-1009.

13

H. Lockheed Protests at GAO and This Court

The government debriefed Lockheed on September 2, 2015, and six days later Lockheed

filed a protest with GAO, triggering an automatic stay of Oshkosh’s performance of the contract.

PI-1159. On November 18, 2015, GAO held a hearing and took testimony from government

officers, who also submitted declarations. Compl. ¶ 15. According to Lockheed, on October 9

and 14, 2015, the government had told Lockheed that no evaluator notes existed. Compl. ¶¶ 107,

108. Weeks later, however, the government notified GAO that it had located more documents,

and on December 4, 2015, GAO directed the government to disclose them. Compl. ¶¶ 112, 113.

GAO nonetheless informed the parties that it would not consider these new documents in

rendering its decision, which was statutorily required to be issued within a few days after GAO’s

order to the government to disclose the newly identified records relating to the procurement.

Compl. ¶ 114. Because GAO would not consider the documents in rendering its decision,

Lockheed filed a protest in this court on December 16, 2015, and GAO dismissed the protest

before it. Compl. ¶ 11. At that point, the automatic stay of performance of the Army’s award to

Oshkosh terminated.

In this court, Lockheed filed a motion for preliminary injunction. See Pl.’s Mot. for a

Preliminary Injunction (“Pl.’s Mot.”), ECF No. 10. At an initial status conference on December

18, 2015, the government informed the court that it could not file the administrative record until

February 2016. See Order of December 18, 2015, ECF No. 13. Lockheed opted to proceed with

the motion for a preliminary injunction despite not having a complete record of the procurement.

The briefing by the parties regarding this motion has drawn upon selected portions of the record.

The parties have submitted excerpts from the solicitation, the parties’ offers, the parties’

responses to evaluation notices, government correspondence (including notes and evaluations),

declarations provided by government officials to GAO, and transcripts of testimony adduced at

the GAO hearing.

JURISDICTION

The Court of Federal Claims has jurisdiction to “render judgment on an action by an

interested party objecting to a solicitation by a Federal agency for bids or proposals for a

proposed contract or to a proposed award or the award of a contract or any alleged violation of

statute or regulation in connection with a procurement or a proposed procurement.” 28 U.S.C.

§ 1491(b)(1), added by the Administrative Dispute Resolution Act, Pub. L. No. 104-320, § 12,

110 Stat. 3870, 3874 (Oct. 19, 1996); see also Systems Application & Techs., Inc. v. United

States, 691 F.3d 1374, 1380-81 (Fed. Cir. 2012). Accordingly, the court has jurisdiction over

this post-award bid protest.

STANDARDS FOR DECISION

A. Preliminary Injunction

To obtain the extraordinary relief of a preliminary injunction, the court considers four

factors: (1) likelihood of success on the merits; (2) irreparable harm to the protestor if an

injunction is not granted; (3) whether the balance of hardships tips in the movant’s favor; and (4)

14

the public interest. FMC Corp. v. United States, 3 F.3d 424, 427 (Fed. Cir. 1993). Although no

one factor is dispositive, a protestor must establish the first two factors, likelihood of success on

the merits and irreparable harm, before a preliminary injunction can be granted. See Per Aarsleff

A/S v. United States, 123 Fed. Cl. 147, 156-57 (2015) (citing Altana Pharma AG v. Teva Pharm.

USA, Inc., 566 F.3d 999, 1005 (Fed. Cir. 2009)).

B. Standard for Review of a Procurement Action

The Administrative Procedure Act (“APA”), specifically 5 U.S.C. § 706, governs the

court’s review of an agency’s contract award. 28 U.S.C. § 1491(b)(4) (“In any action under this

subsection, the courts shall review the agency’s decision pursuant to the standards set forth in

section 706 of title 5.”). “Section 706 of the APA provides, in relevant part, that a ‘reviewing

court shall . . . hold unlawful and set aside agency action, findings, and conclusions found to

be . . . arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.’”

Centech Grp., Inc. v. United States, 554 F.3d 1029, 1037 (Fed. Cir. 2009) (alterations in

original). Accordingly, the court may set aside a procurement action if “(1) the procurement

official’s decision lacked a rational basis; or (2) the procurement procedure involved a violation

of regulation or procedure.” Impresa Construzioni Geom. Domenico Garufi v. United States,

238 F.3d 1324, 1332 (Fed. Cir. 2001).

When challenging the rationality of an award under the first Impresa ground, “the

disappointed bidder bears a heavy burden.” Centech, 554 F.3d at 1037 (quoting Impresa, 238

F.3d at 1332-33). As a practical matter, this burden can be particularly difficult to meet when

challenging a negotiated procurement for best value because such procurements inherently entail

exercise of a contracting officer’s discretion. See Galen Med. Assocs., Inc. v. United States, 369

F.3d 1324, 1330 (Fed. Cir. 2004). Thus, de minimis errors in the procurement process do not

justify relief. Grumman Data Sys. Corp. v. Dalton, 88 F.3d 990, 1000 (Fed. Cir. 1996).

Notably, “[c]ourts have found an agency’s decision to be arbitrary and capricious when the

agency ‘entirely failed to consider an important aspect of the problem, offered an explanation for

its decision that runs counter to the evidence before the agency, or [the decision] is so

implausible that it could not be ascribed to a difference in view or the product of agency

expertise.’” Alabama Aircraft Indus., Inc. – Birmingham v. United States, 586 F.3d 1372, 1375

(Fed. Cir. 2009) (quoting Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S.

29, 43 (1983)).

In particular, an agency’s procurement action is arbitrary and capricious if it treats

offerors unevenly. See PGBA, LLC v. United States, 60 Fed. Cl. 196, 207 (2004), aff’d, 389 F.3d

1219 (Fed. Cir. 2004); see also CliniComp Int’l, Inc. v. United States, 117 Fed. Cl. 722, 741

(2014) (collecting cases). The agency “must . . . evaluat[e] proposals evenhandedly against

common requirements,” CW Gov’t Travel, Inc. v. United States, 110 Fed. Cl. 462, 490 (2013),

and must “consistently apply the evaluation factors listed in the solicitation,” TLT Constr. Corp.

v. United States, 50 Fed. Cl. 212, 216 (2001). However, evenhanded and fair treatment does not

necessarily mean indistinguishable consideration. See FAR § 1.102-2(c)(3) (“All contractors and

prospective contractors shall be treated fairly and impartially but need not be treated the same.”).

15

To the extent proposals differ, the government may rationally take different action regarding

different proposals.

Turning to the second Impresa ground, “the disappointed bidder must show ‘a clear and

prejudicial violation of applicable statutes or regulations.’” Cyios Corp. v. United States, 122

Fed. Cl. 726, 737 (2015) (quoting Impresa, 238 F.3d at 1332-33).

Under either Impresa ground, the court should review an agency’s procurement record

existing at the time of decision. Axiom Res. Mgmt., Inc. v. United States, 564 F.3d 1374, 1379-

80 (Fed. Cir. 2009) (citing Camp v. Pitts, 411 U.S. 138, 142 (1973)). Because the standard of

review under the APA requires the court to analyze the agency’s reasoning in light of the facts

and circumstances before it, supplementation of the record with new evidence could frustrate this

standard. Id. at 1380. Accordingly, “supplementation of the record should be limited to cases in

which ‘the omission of extra-record evidence precludes effective judicial review.’” Id. (quoting

Murakami v. United States, 46 Fed. Cl. 731, 735 (2000), aff’d, 398 F.3d 1342 (Fed. Cir. 2005)).

Among other things, supplementation may be appropriate in instances where there is a gap in the

administrative record. Midwest Tube Fabricators, Inc. v. United States, 104 Fed. Cl. 568, 573

(2012). Also, the Federal Circuit’s recent decision in Glenn Defense Marine (Asia), PTE Ltd. v.

United States, 720 F.3d 901, 911 n.8 (Fed. Cir. 2013), elaborates on required elements of the

record. In Glenn Defense, the Federal Circuit observed that pursuant to 31 U.S.C. § 3556, “all of

the materials submitted to GAO are part of the administrative record before the Court of Federal

Claims.” Id. Accordingly, materials generated in proceedings at GAO must be submitted to, and

are part of the record in this court, but any “post-hoc rationalizations” in those materials are

critically and skeptically evaluated. See Citizens to Preserve Overton Park, Inc. v. Volpe, 401

U.S. 402, 420-21 (1971), abrogated in part by Califano v. Sanders, 430 U.S. 99, 105 (1977); Co-

Steel Raritan, Inc. v. International Trade Comm’n, 357 F.3d 1294, 1314 (Fed. Cir. 2004); PGBA,

60 Fed. Cl. at 204.

ANALYSIS

A. Likelihood of Success on the Merits

Lockheed makes two principal arguments that the Army erred in selecting Oshkosh.

First, it asserts the Army misled Lockheed during the discussions held on May 20, 2015. Hr’g

Tr. at 139:7-8 (“So the problematical misleading discussion is on May 20th.”); Pl.’s Mot. at 24-

26. Second, Lockheed argues that the Army treated Lockheed worse than Oshkosh for no

rational reason, in particular by refusing to credit certain Lockheed data while crediting Oshkosh

data under similar circumstances. Pl.’s Mot. at 22, 26-37.

1. Meaningful discussions.

FAR § 15.306(d) governs “discussions” between the agency and offerors. Discussions

“are tailored to each offeror’s proposal” and “are undertaken with the intent of allowing

the offeror to revise its proposal” so the government may “obtain the best value.” FAR

§ 15.306(d)(1), (2). Pursuant to this regulation, contracting officers “must, subject to paragraphs

(d)(5) and (e) of this section . . . indicate to, or discuss with, each offeror still being considered

16

for award, deficiencies, significant weaknesses, and adverse past performance information to

which the offeror has not yet had an opportunity to respond.” FAR § 15.306(d)(3). In doing so,

the contracting officer must not “engage in conduct” that “favors one offeror over another.”

FAR § 15.306(e)(1). Beyond that, the FAR imposes few other constraints on discussions.

Instead, “[t]he scope and extent of discussions are a matter of contracting officer judgment,” and

“the contracting officer is not required to discuss every area where the proposal could be

improved.” FAR § 15.306(d)(3).

Restated, discussions must be “meaningful” and not “misleading.” See, e.g., CEdge

Software Consultants, LLC v. United States, 117 Fed. Cl. 419, 434-35 (2014). “For discussions

to be meaningful, they must ‘generally lead offerors into the areas of their proposals requiring

amplification or correction, which means that discussions should be as specific as practical

considerations permit.’” Id. at 434 (quoting Advanced Data Concepts, Inc. v. United States, 43

Fed. Cl. 410, 422 (1999), aff’d, 216 F.3d 1054 (Fed. Cir. 2000)). Misleading discussions occur

when the agency provides “materially disparate information to bidders on matters that could

easily affect their decisions about important aspects of the final competing offers that the agency

will be comparing.” Raytheon Co. v. United States, 809 F.3d 590, 596 (Fed. Cir. 2015).

Applying these principles here, by May 20, 2015, the government believed Lockheed’s

proposal had several “deficiencies” or “weaknesses” within the meaning of FAR

§ 15.306(d)(3). 11 Those were that Lockheed’s [***] MMBHMF proposal was unsubstantiated,

its design meaningfully varied, and it had failed to submit enough data to satisfy the Army’s

evaluators. The government had communicated these problems to Lockheed through a series of

notices in April and early May 2015. PI-853 to -866. And during the May 20 discussion, the

government reiterated those concerns. The Army explained that it “assesses threshold

performance for PDFOV-2909 as appreciably increased risk and the proposed value as an

unsubstantiated technical commitment.” PI-171. The government then told Lockheed that it

considered Lockheed’s design to meaningfully vary from that tested in Phase Two because of the

“complexity” of systems changes “combined with the quantity of design changes.” PI-171. The

government asked Lockheed to explain the changes and provide data for them. PI-171.

Although the government did not give Lockheed a list of changes requiring substantiating data,

the government did give Lockheed an example of such a change: [***]. PI-171. Thus the

government “generally le[d] [Lockheed] into the areas of [its] proposal requiring amplification or

correction.” See CEdge, 117 Fed. Cl. at 434.

Lockheed makes four arguments that the discussions were unsound. First, Lockheed

contends that the government misled it by saying “a change is a change is a change,” which

implied that every design change needed supporting data. Hr’g Tr. 67:19-24, 68:16-22 (arguing

that because Lockheed did not know what changes mattered, the company “ha[d] no choice but

to substantiate every change”). But that contention overstates the Army’s commentary. The

government’s statement that a “change is a change” came at the end of a lengthy conversation, in

which the government indicated its reluctance to fully credit the reliability data from Phase Two

because of the scope of Lockheed’s changes. Standing alone, the “change is a change” statement

might have been ambiguous. But in the context of the [***] example and the government’s

11

FAR § 15.001 defines “deficiency” and “weakness.”

17

commentary about “complexity” and “quantity” of changes, the government properly led

Lockheed into the area requiring elaboration or correction.

Second, Lockheed argues that the notes of a meeting of Army evaluators on May 19

show the Army did not need more data and thus prove that the Army’s requests for more data

were misleading. Pl.’s Mot. at 24-25. As evidence to support this contention, Lockheed points

to several lines in the evaluator’s notes of the internal meeting on May 19 that state “[u]p to this

point, the main message has been lack of substantiating data, leading L[ockheed] to providing

more data. Need to address the fact that a number lower than the proposed reliability can be

substantiated. L[ockheed] is well above the reliability performance that can be substantiated.”

PI-184 (cited in Pl.’s Mot. at 25). These notes do not, however, indicate that the data issue was

closed. Rather, they reflect the Army evaluators’ continuing concern about establishing a well-

supported reliability figure. PI-184.

Third, Lockheed says that the government failed to disclose its internal assessment of

Lockheed’s design’s MMBHMF value. Pl.’s Mot. at 24. On May 6, Lockheed sent an e-mail to the

government asking “[w]hat is the [g]overnment’s assessed value of Lockheed Martin’s reliability

against the PDFOV-2909 3800 MMBHMF threshold value?” PI-155. The government replied on

May 7, explaining that pursuant to RFP § M.4.1, the government was not assessing MMBHMF

values, but was instead assessing the risk that an offeror would meet 3800 MMBHMF. PI-154.

Lockheed asserts that a chart in the record belies that reply. The Army chart appears to assess

MMBHMF values for Lockheed, based on its proposal. PI-166. Beneath this chart is the number

“[***].” PI-166. In Lockheed’s view, this “[***]” figure must be the government’s assessed

MMBHMF value for Lockheed, which means that the government incorrectly represented in the

May 7 e-mail that the government was not making calculations. Pl.’s Mot. at 24. Nonetheless, the

government properly explained to Lockheed that the RFP required an assessment of the risk an

offer would not meet threshold MMBHMF, not a precise or particular MMBHMF assessment. PI-

154. The fact that a government employee may have calculated an assessed MMBHMF for

Lockheed does not show that was the government’s authoritative position, nor that the calculation

supplanted the government’s decision process under the RFP. Moreover, Lockheed does not

explain what it would have done differently had it known this information before the significant

discussions on May 20.

Finally, Lockheed argues that the discussion on May 20 caused Lockheed to [***]

proposal and to instead submit its [***] proposal, which [***]. Pl.’s Mot. at 22. But this

discussion did not cause Lockheed to [***]. Lockheed explained the [***]. PI-899. Although

the government told Lockheed its [***] MMBHMF was unsubstantiated, that does not mean

Lockheed had to [***]. It could have substantiated [***], or any other figure.

The court finds that the discussions with Lockheed were likely meaningful and not

misleading. 12 The Army explained its concerns to Lockheed, it noted the unsubstantiated

12

Lockheed also argues that the government failed to tell Lockheed that its design

changes were not “understood,” citing a draft evaluation where the word “understood” is deleted

as evidence that the government did not fully apprehend the effect of Lockheed’s changes. Pl.’s

Mot. at 26. But this argument does not show that the government failed to have meaningful

18

technical commitment, and it advised Lockheed that it could not rely on future design changes.

It also explained what changes varied and needed supporting data. Thus the Army likely

fulfilled its responsibilities under FAR § 15.306.

2. Unequal treatment.

Lockheed contends that: (i) it was similarly situated to Oshkosh yet was required to

submit more data; (ii) the Army failed to apply a consistent standard when assessing meaningful

variation; and (iii) the Army failed to analyze Oshkosh’s changes for meaningful variation,

permitting Oshkosh to rely on Phase Two data despite the fact that Oshkosh made serious design

changes. Pl.’s Mot. at 24, 26-34. These arguments essentially turn on whose proffered design

differed more from the prototypes evaluated in the Phase Two testing. Accordingly, the question

of whether the Army fairly asked Lockheed and not Oshkosh for more data depends on whether

the evaluators fairly applied the “meaningful variation” standard to both offerors.

Pursuant to RFP § M.4.1, “any substantiating data for a design configuration which

meaningfully varies from the offered design configuration may be considered less credible.” PI-

104. Thus if a proposed design did not meaningfully vary from the prototype design tested by

the government in Phase Two, the offeror could rely on government test data to substantiate

performance claims. The phrase “meaningfully varies” was not defined in the RFP. Hr’g Tr. at

82:6-7 (government’s counsel stating this point), 132:16-20 (plaintiff’s counsel stating same).

“Meaningful variation” is a broad term, and Lockheed does not focus on how it should be

interpreted but instead argues that the evaluators applied the concept inconsistently. Pl.’s Mot. at

26-32. Lockheed asserts that for its proposal, the Army found meaningful variation if a change

created the “potential for a HMF.” Pl.’s Mot. at 27. As evidence of this, Lockheed cites an

evaluator’s comment that “L[ockheed] is modifying [***]. These design changes have the

potential to cause a Mission Essential Function (MEF) failure and therefore meaningfully vary

from [Phase Two] test configuration.” Id. (quoting PI-114). Lockheed asserts that for Oshkosh,

the Army applied a more lenient standard, asking whether Oshkosh’s changes related to “form,

fit and function” or whether they were “likely” to cause a HMF. Pl.’s Mot. at 30-31 (quoting an

Army evaluation at PI-129).

The court’s role is to determine whether the evaluators were evenhanded in applying the

meaningful-variation standard. See PGBA, 60 Fed. Cl. at 207 (holding that “uneven treatment

goes against the standard of equality and fair-play that is a necessary underpinning of the federal

government’s procurement process”). Under the APA standard of review, the court does not

merely address the evaluator’s explanation. The phrases used by the evaluator cannot mask or

supplant the facts. See State Farm, 463 U.S. at 43 (requiring an agency to “examine the relevant

data” and “articulate a satisfactory explanation”). The evaluator’s comments about

“complexity,” “potential” HMFs or “form, fit and function” are not conclusive. Instead, the

court looks to the evidence before the evaluator, asking whether the agency “entirely failed to

consider an important aspect of the problem, offered an explanation for its decision that runs

discussions with Lockheed. The government in fact did convey its misgivings about Lockheed’s

proposal, as detailed supra, at 8-11, and it received information that allowed it to continue to

consider Lockheed for possible award.

19

counter to the evidence before the agency, or [the decision] is so implausible that it could not be

ascribed to a difference in view or the product of agency expertise.” Id.

The evaluator explained that Lockheed’s Phase Three proposal meaningfully varied

because as a matter of fact it had a “quantity of complex” changes from its Phase Two design.

PI-115 (“[T]he quantity of complex C[orrective]A[ction]s results in a design that meaningfully

varies from the [Phase Two] as-tested configuration and decreases the relevance of the [Phase

Two government] test data.”). The evaluator reiterated this point on a number of occasions,

saying, for example, that the “complexity of the components and subsystems that were addressed

with [Corrective Actions], combined with the quantity of design changes, results in a proposed

design that meaningfully varies from [the Phase Two] test configuration.” PI-114.

The evidence before the evaluator supports her finding that Lockheed made complex

changes. Lockheed redesigned [***]. PI-915 to -16. This redesign included a change from

[***]. PI-916. Lockheed also redesigned [***]. PI-925 to -27; see also PI-211 (explaining

these functions). Next, Lockheed made changes to the [***], PI-937 to -39, [***], PI-958 to -60,

and the [***], PI-961 to -65. Lockheed redesigned the [***], including the [***]. PI-944 to -55.

In due course, for all of these changes, Lockheed submitted data to support them. PI-915 to -71.

The evaluator took all this into account in her analysis and concluded that these changes

resulted in meaningful variation, which reduced the relevance of Phase Two data. PI-114

(identifying changes to the [***]). The absence of Phase Two testing data for a vehicle

reflecting these changes was critically important because, pursuant to RFP § M.4.1 the evaluator

considered Lockheed’s supporting data to have less credibility than that established during the

Phase Two testing regime. PI-114 to -16. Given the number of changes Lockheed made to

vehicle components, the court cannot discount the evaluator’s findings that these changes were

complex as a matter of fact, which findings supported her conclusion that they “meaningfully

var[ied]” under the RFP. The court cannot say the evaluator “offered an explanation for its

decision that runs counter to the evidence.” State Farm, 463 U.S. at 43.

The evaluator did not use the phrase “quantity of complex changes” when discussing

Oshkosh’s proposed design. But that does not mean that the evaluator’s analysis of Oshkosh’s

proposed design was inconsistent with the analysis she applied to Lockheed. The evaluator

explained that Oshkosh’s changes did not meaningfully vary because as a matter of fact the

changes addressed “manufacturing efficiencies” and were “the same form, fit and function.”

PI-129; see also PI-562 to -82. The government and Oshkosh argue that Oshkosh’s Phase

Three changes were not as meaningful as those proposed by Lockheed, because Oshkosh

replaced parts with similar but proven parts and did not redesign systems. See generally PI-220,

-299, -842-843.

Lockheed disagrees, saying the record shows Oshkosh made three significant design

changes that should have drawn more scrutiny from the Army. First, Lockheed points out that

Oshkosh changed a [***] in its proposed design. Pl.’s Mot. at 33 (citing PI-843). If this part

failed, a HMF “would” occur, PI-299, and so Lockheed argues this change is significant. Pl.’s

Mot. at 33. But the record shows that the [***] was tested on a JLTV during Phase Two and

experienced no failures. PI-842. Second, Lockheed argues that Oshkosh changed its [***]

20

which is a system that provides [***]. Pl.’s Mot. at 34 (citing PI-577). Lockheed says this

change should have drawn scrutiny. Pl.’s Mot. at 34. But evidence before the evaluator shows

Oshkosh’s change was to [***]. PI-220. Given this evidence, the court cannot say it runs

counter to the evaluator’s conclusion that the change was not meaningful.

Third, Lockheed argues that Oshkosh changed its [***] without drawing scrutiny. Pl.’s

Reply Br. in Support of Pl.’s Mot. (“Pl.’s Reply”) at 28, ECF No. 31. The [***] is a [***]

component, and during Phase Two, Oshkosh’s [***] which was scored as an EFF. PI-589 to -90.

Although aspects of this change were apparently presented during the Phase Two assessment

conference, held at the end of the Phase Two testing, this change by Oshkosh was not actually

tested on a prototype vehicle during Phase Two. Oshkosh’s change to the [***] in large measure

involved replacing [***], eliminating some [***] disparities in Oshkosh’s system. PI-589.

Oshkosh provided data to support this change. PI-591. It is difficult for the court to analyze the

significance of the change in Oshkosh’s [***], given the relative absence of details in the record

before the court. Although the evaluator seemingly credited Oshkosh with a system that was

effectively tested during Phase Two, that assessment appears incorrect. And, the RFP’s

attachments indicate that a total failure of this system would result in a HMF. Given that

Oshkosh changed some [***] in the system, this change may be similar in magnitude to

Lockheed’s changes to the [***]. But overall, a [***] change to Oshkosh’s [***] is likely not as

meaningful as Lockheed’s redesign of a number of systems, including the [***].

In summary, the limited record before the court suggests that the evaluator focused on

whether Lockheed’s and Oshkosh’s Phase Three designs varied from their Phase Two designs in

meaningful ways. The issue is whether the record supports the evaluator’s conclusion that

Lockheed made more changes to important systems, reducing the relevance of Phase Two test

data. The record before the court generally supports the evaluator in that regard. 13

Because the evaluator found Lockheed’s design meaningfully varied from that field

tested during Phase Two, the court cannot say the Army unfairly demanded more substantiating

data from Lockheed than Oshkosh. Lockheed’s initial proposal did not submit new data to

support its reliability claims. This meant the Army had to ask for substantiating data. In

response, Lockheed submitted data to support its changes, but the Army ultimately relied on the

degree of change from the prototypes tested in Phase Two to conclude that Lockheed’s data did

not deserve full credit. PI-117; see also PI-118 (observing that Lockheed’s changes “decrease[d]

the relevance of [g]overnment [Phase Two] data”). In contrast, Oshkosh made fewer changes to

important systems. For the changes it did make, it submitted data up front, meaning the Army

did not have to ask for more. The Army ultimately concluded that Oshkosh’s changes in fact

caused a “slight impact to the relevance of [Phase Two] test data” for Oshkosh. PI-129; see also

PI-1011 (noting Oshkosh “generally” relied on government test data). But because those

changes were more limited, the impact was only “slight.”

13

As Lockheed points out, Oshkosh also made “changes to the [***].” Pl.’s Mot. at 12

(quoting PI-298). Oshkosh provided data relating to these changes, PI-562 to -82, and Lockheed

does not seriously contest the Army’s decision to consider them not to be meaningful.

21

Based on the limited record here, the court finds it likely that the Army treated

Lockheed and Oshkosh fairly. 14 To the extent the Army treated Lockheed differently, it acted

rationally because Lockheed’s proposal raised issues that Oshkosh’s did not. See Chenega

Mgmt., LLC v. United States, 96 Fed. Cl. 556, 586 (2010) (finding agency acted rationally when

it refused to engage in clarifications with plaintiff, because plaintiff’s ratings were “significantly

inferior” to other offerors).

3. Adjectival rating.

Lockheed argues the Army erred by assigning it an overall risk rating of “moderate.”

Pl.’s Mot. at 35. For the 25 purchase-description requirements, Lockheed ultimately received six

“moderate,” twelve “low,” and seven “very low” scores. PI-1010. The RFP required these

factors to be “weighted equally.” PI-104 (RFP § M.4.1). Thus, in Lockheed’s view, these scores

should average out to a “low” overall risk rating, not “moderate” as the Army found. Pl.’s Mot.

at 35-37. As an example, Lockheed says that if one assumes a “very low” is worth four points, a

“low” is worth three, a “moderate” is worth two, a “high” is worth one, and an “unacceptable” is

worth zero, then Lockheed’s average score was greater than three, proving Lockheed deserved

an overall low-risk rating. Pl.’s Mot. at 36 n.5. 15

Lockheed’s argument assumes a quantitative analysis, rather than qualitative. Although

an Army chart in the record suggests some point values may have been internally assigned to the

risk categories, see Pl.’s Reply at 13 (citing PI-1585 (in turn showing a chart that appears to

average risk scores)), this does not reinforce Lockheed’s assumption that the risk categories

would be scored zero to four. Even though the RFP said the 25 requirements were equally

weighted, and even assuming the Army did a numerical averaging, any weights for the risk

categories have not been disclosed. In that respect, the contracting officer has broad discretion

when assigning adjectival ratings. See Wackenhut Servs., Inc. v. United States, 85 Fed. Cl. 273,

293 (2008) (giving deference to evaluator’s assignment of adjectival ratings).

Most importantly, this adjectival rating appears to be a guide, not a dispositive

consideration, for the agency, as the Army’s RFP does not say that any particular ratings require

any particular results. The rating itself is less important than the rationale behind it. Thus

“[c]ourts should look beyond the adjectival ratings because proposals awarded the same

adjectival ratings are not necessarily equal in quality.” Blackwater Lodge & Training Ctr., Inc.

v. United States, 86 Fed. Cl. 488, 514 (2009). Whatever overall rating the Army chose here, the

record shows that the Army considered Oshkosh’s proposal to be technically less risky across the

25 factors, a fact the SSA discussed in his final selection decision. See PI-1014 (stating that

14

In reaching this result, the court does not rely on the parties’ citations to GAO

testimony or declarations developed in the GAO proceeding. The GAO materials cited by the

parties largely consist of “post hoc” rationalizations, which the court must view critically, and

they do not appear to affect the outcome in any material way. See Overton Park, 401 U.S. at

420-21; Co-Steel Raritan, 357 F.3d at 1316; PGBA, 60 Fed. Cl. at 204.

15

Lockheed has not challenged the government’s ratings for any of the 25 categories

other than Reliability and Operational Availability.

22

although the overall risk rating for Oshkosh was low and that for Lockheed was moderate, “the

proposals were not as close as this might imply as [Oshkosh] is assessed as Low Risk or Very

Low Risk for all 25 requirements whereas . . . [Lockheed has] a number of Moderate Risk

ratings.”). Oshkosh received thirteen “low,” twelve “very low,” and no “moderate” ratings. It

thus demonstrated lower risk than Lockheed, which had six “moderate ratings.” Given these

differences, it is difficult for the court to say the contracting officer acted arbitrarily.

4. Prejudice.

The court may grant relief in a bid protest only if the plaintiff demonstrates it was

prejudiced by the government’s action. See Information Tech. & Applications Corp. v. United

States, 316 F.3d 1312, 1319 (Fed. Cir. 2003); see also 5 U.S.C. § 706 (last sentence) (requiring

the court to take “due account” of “the rule of prejudicial error”). To be prejudiced, a protestor

must have had a substantial chance of receiving the award but for the government’s error. Id.

Here, the Army selected Oshkosh after weighing which offeror would provide the “best

value” to the government. The Primary Technical factor weighed more than price, which

weighed more than Small Business Participation. Against this Primary Technical standard, the

SSA found that Oshkosh had better risk scores, as detailed above. The SSA also found that

Oshkosh was cheaper by nearly $400 million. PI-1009. As for small business participation,

Lockheed was rated “outstanding” while Oshkosh was rated “good.” PI-1009. Accordingly, the

SSA selected Oshkosh because it had the best Primary Technical rating and the lowest price. PI-

1014. Although Lockheed had better small business participation, this was the weakest factor

and did not outweigh the other two.

Lockheed argues it was prejudiced because “[h]ad Lockheed Martin been properly

evaluated with respect to Reliability and not been misled, it would have made a substantially

different MMBHMF proposal. If Lockheed Martin had made such a proposal – or Oshkosh’s

proposal had been given equivalent scrutiny – a different, more favorable [life cycle cost]

adjustment would have resulted in an award to Lockheed Martin.” Pl.’s Mot. at 37.

The court is not persuaded. Even with adjustments to the Reliability and Operational

Availability elements, Oshkosh would still be technically superior. And, the RFP provided that

the Primary Technical factor weighed “more” than price, unless non-price factors were

approximately equal, PI-101, and that “this determination may result in award to other than the

[o]fferor with the lowest TEC/P.” PI-102.

Therefore, to establish prejudice Lockheed cannot only show that the technical evaluation

was flawed. It must also show that flaws affected the price calculation enough to make price

almost determinative. Cf. Weston Solutions, Inc. v. United States, 95 Fed. Cl. 311, 327 (2010)

(finding prejudice when, but for an error in the technical evaluation, plaintiff and the awardee

could have been technically equal, allowing the government to use non-technical factors as the

tie-breaker), aff’d, 440 Fed. Appx. 426 (Fed. Cir. 2011). Lockheed has not done so at this point.

There is no evidence in the record showing what alternative life cycle credit might have been

given. See Industrial Property Mgmt., Inc. v. United States, 59 Fed. Cl. 318, 324 (2004) (finding

that when offerors were technically equal, plaintiff did not have substantial chance of award

23

when his bid was 20% more expensive than the winner); see also CMI Mgmt., Inc. v. United

States, 115 Fed. Cl. 276, 298 (2014) (finding no prejudice on alleged error in rating of a

subfactor, because “even if the court were to find that [plaintiff’s] rating for Subfactor Four as

Acceptable rather than Good was ill-founded, . . . this subfactor would have no material bearing

on [plaintiff’s] overall rating of Acceptable.”).

Analytically also, on the merits, Lockheed has not yet satisfactorily addressed the

changes it made to its MMBHMF figures during the discussions. Lockheed ultimately proposed

a MMBHMF of [***]. Although in its reply brief Lockheed suggests that it could have

substantiated a MMBHMF of [***] but the government prevented it from doing so, Pl.’s Reply

at 9, that suggestion has limited support in the record. Lockheed’s final offer explained that the

[***] figure “is largely based on the government’s decision to not recognize any significant

value for continued reliability growth activities that occur after contract award, even though a

contractor has a contractor commitment to meet the proposed value.” PI-899. That concession

diminishes Lockheed’s overall posture and the likelihood that it could show prejudice.

B. Irreparable Harm

In the context of a preliminary injunction, a protestor can prove irreparable injury by

showing that an injunction is necessary to preserve the plaintiff’s remedies should it succeed on

the merits. Eskridge Research Corp. v. United States, 92 Fed. Cl. 88, 98 (2010) (citing Qingdao

Taifa Grp. Co. v. United States, 581 F.3d 1375, 1379-80 (Fed. Cir. 2009)). But in general, a

plaintiff may not show irreparable harm by claiming generically that the winner’s transition into

performance will give it advantages. See IBM Corp. v. United States, 118 Fed. Cl. 677, 684

(2014) (finding no irreparable harm from winner’s beginning performance).

Lockheed makes two arguments that it will be irreparably harmed without a preliminary

stop-work order. First, Lockheed asserts that without temporary relief, this court may be unable

to provide a remedy if Lockheed later prevails on the merits. See Pl.’s Reply at 33. All agree

that Oshkosh will perform largely preparatory work in the coming months, thus limiting potential

termination costs. See Def.-Interv.’s Opp’n at 39 n.8 (quoting a declaration from a Vice

President of Oshkosh explaining that “termination costs would be very modest relative to the

value of this procurement, and would not preclude an effective remedy”); Def.’s Opp’n at 35,

ECF No. 26 (“The amount of work to be performed over the next several months is very small

relative to the overall contract.”); Pl.’s Mot. at 39 (“[T]here is no urgency here.”). Given the

proportionately small commitment of resources compared to the overall value of this contract,

Oshkosh’s continuing performance would not prevent this court from giving Lockheed an

appropriate remedy should Lockheed ultimately prevail. See Turner Constr. Co. v. United

States, 645 F.3d 1377, 1388 (Fed. Cir. 2011) (noting that the Court of Federal Claims “has broad

equitable powers to fashion an appropriate remedy”).

Second, Lockheed argues that “Oshkosh may be well into performance when this matter

is resolved. Oshkosh may have the opportunity to further develop, change, and refine its solution

under [g]overnment funding and testing before any corrective action, which will adversely affect

Lockheed Martin’s prospects in any re-competition ordered by the [c]ourt.” Pl.’s Mot. at 38.

The only evidence of this harm cited by Lockheed is a chart, drafted by Oshkosh during the

24

competition, showing that Oshkosh will [***] post-award to test its own vehicles. Hr’g Tr.

142:6-12 (citing PI-273 to show that Oshkosh will conduct reliability testing). This does not

show how Lockheed will be harmed.

C. Remaining Factors

Because Lockheed has failed to establish a likelihood of success on the merits and

irreparable harm, the court cannot grant a preliminary injunction. See Altana Pharma, 566 F.3d

at 1005. Accordingly, the court need not consider the remaining factors pertinent to preliminary

injunctive relief.

CONCLUSION

Plaintiff’s motion for a preliminary injunction is DENIED. On or before February 24,

2016, the court requests that the parties submit a joint status report addressing further

proceedings in this action.

It is so ORDERED.

s/ Charles F. Lettow

Charles F. Lettow

Judge

25