Opinion

Brookshire Katy Drainage District v. the Lily Gardens, LLC, Richard E. Fluecker and Kenneth B. Luedecke

Court
Texas Court of Appeals, 1st District (Houston)
Filed
Feb 25, 2011
Status
Published
Cited by
0 cases
Authority
More cited than 42.2%

The opinion

Opinion issued February 25, 2011

In The

Court

of Appeals

For The

First

District of Texas

————————————

NO. 01-07-00431-CV

———————————

Brookshire Katy Drainage District , Appellant

V.

The Lily Gardens, LLC, Richard E. Flueckiger and

Kenneth B. Luedecke , Appellees

On Appeal from the 9th District Court

Waller County, Texas

Trial Court Case No. 06-08-18415

CONCURRING OPINION ON DENIAL OF EN BANC CONSIDERATION

This case is about a picturesque cover placed over an

existing bridge on private land. Long

ago, appellant, Brookshire Katy Drainage District (“the District”), constructed

a drainage canal across the land pursuant to an express easement with prior

landowners. Around that time, the

District built the bridge across the canal.

Appellees, Lily Gardens, LLC, Richard E. Flueckiger, and Kenneth B.

Leudeck (“the Landowners”), who operate an outdoor-venue business on the land,

placed the cover on the bridge in the belief that it enhances their business. The District brought this action to compel

the Landowners to remove the cover from the bridge. The district court and a panel of this Court

have both ruled in favor of the Landowners, determining that the cover may

remain.

The History of the

Bridge and Cover

In 1962, the District obtained an easement for a drainage

ditch approximately 10 feet deep that runs across the entire width of the

property. The ditch divides the front

portion from the back part of the property.

To allow ingress and egress from the back portion of the property that

is otherwise inaccessible due to the ditch, the District built the bridge over

30 years ago. The bridge has never

affected drainage in any way. In 2004,

the Landowners purchased this property with the intention of beautifying it for

use as a facility to host weddings. To

beautify the bridge, the Landowners constructed a cover that is 24 feet long

and 20 feet wide. The cover consists of

a triangular-shaped roof and two sides, which conceal the unattractive steel guardrails

that support the bridge. A large vehicle

can travel over the bridge and under the cover without any impediment such as

walls or doors. The lowest portion of

the bridge cover is approximately 10 feet above the ground, and no portion extends

below the bridge.

In October 2006, a voluminous amount of rain besieged the

land in one of the wettest months in recorded history, but the waters flowed

unimpeded by the bridge cover. The prior

owner of the land said that in the past 25 years, he never saw the level of the

water rise above the banks of the ditch, even during Tropical Storm

Allison. The Landowners’ engineer expert

opined that the bridge cover would have “no real effect” on the drainage

waters.

The Terms of the

Private Easement

This lawsuit is not about easements granted to public

utilities in general because this easement was the product of a private

contract between the District and prior landowners. Rather, this lawsuit is about a particular

bridge cover and whether it violates the particular contractual and legal

rights of an easement holder, the District.

Under the parties’ contract, the District has the right to “abate other

obstruction, upon said canal right of way, that may injure, endanger, or

interfere with the construction, operation, maintenance and repair of said

drainage canal.” Under the law, the

District has the right to reasonable use and enjoyment of its easement right,

and the Landowners must not engage in any activity that interferes with that right. See Still v. Eastman Chem. Co. , 170

S.W.3d 851, 854 (Tex. App.—Texarkana 2005, no pet.) (citing Harris County v.

S. Pac. Transp. Co ., 457 S.W.2d 336, 340 (Tex. Civ. App.—Houston [1st

Dist.] 1970, no writ)).

The Landowners do not deny that the contract prohibits them

from activities that may interfere with the District’s use of the drainage

canal, nor that the law prohibits them from interfering with the District’s use

and enjoyment of its easement rights.

What the Landowners dispute is whether the bridge cover in issue

actually may or does interfere with these rights. Because the District put forth no evidence of

such interference or the potential for such interference, we affirmed the trial

court’s judgment in favor of the Landowners.

Although it concedes that the cover does not currently

interfere with its reasonable use and enjoyment of the easement, the District asserts

that in the future, the cover might create a drainage problem or might make it

difficult to remove the culverts, which are metal pipes inside the canal,

because the bridge cover might interfere with access. The District, however, presented no evidence

showing how the cover—as compared to the bridge—might interfere in any way with

the District’s ability to construct, operate, maintain, or repair the drainage

canal. The cover simply made what was

already there prettier.

The examples given in the amicus briefs concerning how the

cover might interfere with the easement in the future illustrate the

evidentiary failure that occurred here.

One amici contends that the cover might prevent a backhoe from moving

onto the bridge and reaching down into the culverts to remove debris. It also states that equipment might need to

be located on the bridge in order to replace existing culverts. However, the District presented no evidence

of this. Had an expert provided an affidavit

averring to the reasonable possibility that these things might occur, the trial

court and the panel of this Court likely would have ruled in its favor. Instead, the evidence shows the cover is

above ground level and has never affected the drainage canal in any way despite

heavy rain. No mention of the possible

need for heavy equipment is in evidence.

Although the use of the word “may” in the contract indicates a low

standard, proof is still required. Even

had the District established that this easement is forward looking due to the

use of the word “may,” the evidence would remain deficient to show how the

cover might reasonably affect the easement in the future.

Furthermore, the parties could have negotiated a contract that

precluded construction of any structure on or near the easement. Cf. Pan

Am. Gas Co. v. Lobit , 450 S.W.2d 877, 880 (Tex. Civ. App.—Houston [1st

Dist.] 1969, writ ref’d n.r.e.) (pipeline easement provided that subservient

estate owner could not build or construct any obstruction, building or other

structure over or on right-of-way); Okan

Pipeline Co. v. Eiland , 394

S.W.2d 548, 550 (Tex. Civ. App.—Eastland 1965, writ ref’d n.r.e.) (gasoline

easement prohibited constructing “any obstruction, building, engineering works,

or other structure over said pipe line”).

This particular contract does not absolutely disallow structures;

rather, the plain language of the contract implicitly allows structures as long

as they may not interfere with the canal.

No-Evidence Review

In her dissent from denial of en banc review, Justice Keyes

objects to the application of the no-evidence standard, rather than the

traditional summary judgment standard, in review of this appeal. It is well-established in this Court that,

when a party moves for both traditional and no-evidence summary judgment, we

first review the trial court’s summary judgment under the no-evidence standard

of Texas Rule of Civil Procedure 166a(i). [1] Justice Keyes recognizes this practice, but

argues that the practice is problematic in instances where the issue is a “pure

question of law.” Without commenting on

the merits of Justice Keyes’s analysis, I respectfully disagree that the case

at bar presents “purely legal issues.”

As demonstrated above, this case necessarily depends on a determination

of whether the bridge cover in issue hinders or may hinder the District’s use

of its easement. This is necessarily a

fact-specific inquiry subject to the presentation of evidence by the parties.

In fact, while the original opinion in this case, which

Justice Keyes endorses, ostensibly applied a traditional summary judgment

standard, it too looked to the District’s evidence to determine the issue of

whether the bridge cover may impede the District’s use of the easement. The pivotal distinction between the opinion

issued on rehearing and the original opinion is not found in interpretation of

the contract or easement law, but in the determination of whether the testimony

in Raymond Dollins’s affidavit constitutes competent evidence that the bridge

cover may interfere with the District’s maintenance and operation of the

drainage system.

Finally, Justice Keyes asserts that “[t]he problem with

granting a no-evidence summary judgment on a purely legal issue is, as the

court in the Cone case acknowledged,

that, even if a motion for summary judgment is presented as a no-evidence

motion, the law must be construed before it can be determined what the elements

of the applicable law are as to which the non-movant must produce proof.” I

respectfully disagree that this approach is problematic in this case, nor do I

read Cone as identifying a “problem”

rather than merely observing common practice.

See Cone v. Fagadau Energy Corp. ,

68 S.W.3d 147 , 156 n.4 (Tex. App.—Eastland 2001, pet. denied) (“ the

court must determine the law which is applicable to the case with respect to

any no-evidence motion for summary judgment in order to determine if the

summary judgment evidence raises a genuine issue of material fact. The fact that a dispute exists with respect to

the applicable law does not prevent the court from performing its function of

analyzing the non-movant’s evidence to determine if it raises a fact issue.”).

Courts are routinely, if not always, put to the task of determining

legal issues in deciding no-evidence motions for summary judgment. To decide whether a plaintiff has put forth

evidence of the elements of a tort, the court must necessarily determine what

those elements are. Granting summary

judgment on the basis of a failure to present evidence of an element that the

law does not impose is error. See,

e.g., Moreno v. Quintana , 324 S.W.3d 124, 136-37 (Tex.

App.—El Paso 2010, pet. denied) (reversing no-evidence summary judgment where

movant alleged no evidence of malice but malice was not element of non-movant’s

claim); Villarreal v. Wells Fargo Brokerage Services, LLC , 315 S.W.3d

109, 127 (Tex. App.—Houston [1st Dist.] 2010, no pet.) (reversing no-evidence

summary judgment where only element identified by movants as entitling them to

summary judgment was not element of claim on which summary judgment was

granted); Baker v. City of Robinson , 305 S.W.3d 783, 793 (Tex. App.—Waco

2009, pet. denied) (sustaining error with respect to traditional and

no-evidence summary judgment on statutory fraud claim on basis of absence of

intent to deceive because intent to deceive is element of common law fraud but

not statutory fraud claim pled). The primary

distinction between traditional and no-evidence motions for summary judgment is

not whether the court must decide legal issues to rule on the motion—both

motions require the court to act as arbiter of the law—but, rather, whether the

legal issues in the case dictate the outcome without regard to any evidentiary

issue.

The Consequences of This Decision

The terms of this private contract do not absolutely disallow

structures. They limit only those

obstructions that may injure, endanger, or interfere with the construction,

operation, maintenance and repair of the drainage canal. That some construction can coexist with a

free flowing drainage canal is evident from the District’s own bridge, which

sits above the easement without obstruction or interference. This decision is case specific. We examine the facts in light of the existing

bridge and the absence of any summary judgment evidence explaining how the

cover might affect the easement beyond any effect by the bridge.

This case does not

meet the en banc standard for review. See Tex.

R. App. P. 41.2(c). Nothing is

extraordinary about this case, there are no consequences beyond the particular

interpretation of this private contract, and this decision does not conflict

with any other. See id. Despite the dire

consequences predicted by government entities, this case comes down to one

government entity’s evidentiary failure in one case—nothing more. This Court’s holding does not diminish the

rights of public entities to abate obstructions that the evidence demonstrates

in reasonable likelihood may impair or impede the use of the easement. For these reasons, I concur in the denial of

en banc consideration and submit that the petition for review should be

denied. See id. ; Tex. R. App. P.

56.1(a).

Conclusion

I concur with the denial of en banc

consideration.

Elsa Alcala

Justice

A majority of the justices of the Court

voted to overrule the motion for en banc reconsideration.

En banc court consists of Justices

Jennings, Keyes, Alcala, Higley, Bland, Sharp, Massengale, Brown, and

Wilson. Chief Justice Radack not participating.

Justice Alcala, concurring in the denial

of en banc reconsideration.

Justice Massengale, concurring in the

denial of en banc reconsideration.

Justice Jennings, dissenting from the

denial of en banc reconsideration, joined by Justice Keyes.

Justice Keyes, dissenting from the

denial of en banc reconsideration, joined by Justice Jennings.

Justice Wilson, dissenting from the

denial of en banc reconsideration.

[1] E.g., Aspenwood

Apartment Corp. v. Coinmach, Inc. , No. 01-08-00636-CV, 2011 WL

478546, at *5 (Tex. App.—Houston [1st Dist.] Feb. 10, 2011, no. pet. h.)

(citing Ford Motor Co. v. Ridgway , 135 S.W.3d 598, 600 (Tex. 2004)); Coburn

v. Toys “R” Us-Delaware, Inc. , No. 01-09-00871-CV, 2011 WL 345936 , at *2

(Tex. App.—Houston [1st Dist.] Feb. 3, 2011, no. pet. h.) (mem. op.); Bosch

v. Cedar Vill. Townhomes Homeowners Ass’n, Inc. , No. 01-09-00654-CV, 2011

WL 346317 , at *2 (Tex. App.—Houston [1st Dist.] Feb. 3, 2011, no. pet. h.)

(mem. op.); Samuel v. Wal-Mart Stores, Inc. , No. 01-08-00702-CV, 2010 WL 2788879 , at *2 (Tex. App.—Houston

[1st Dist.] July 15, 2010, pet. denied) (memo op.); Maurer v. 8539, Inc. , No. 01-09-00709, 2010 WL 5395713 (Tex.

App.—Houston [1st Dist.] Dec. 30, 2010, no pet.) (mem. op.); Allen &

Martha Lewis Revocable Trust v. Perales , No. 01-09-00140-CV, 2010 WL 3212125 ,

at *5 (Tex. App.—Houston [1st Dist.] Aug. 12, 2010) (mem. op.) decision

clarified on denial of reh'g, No. 01-09-00140-CV, 2010 WL 4056513 (Tex.

App.—Houston [1st Dist.] Oct. 14, 2010, no pet.); Clark v. Wells Fargo Bank,

N.A. , No. 01-08-00887-CV, 2010 WL 2306418 , at *4 (Tex. App.—Houston [1st

Dist.] June 10, 2010, no pet.) (mem. op.); Blevins v. Andrews , No 01-08-00598-CV,

2010 WL 1611382 , at *3 (Tex. App.—Houston [1st Dist.] Apr. 22, 2010, no pet.)

(mem. op.); Dixon Fin. Servs., Ltd. v. Chang , 325 S.W.3d 668 , 676 n.5 (Tex.

App.—Houston [1st Dist.] 2010, pet. denied).