Opinion

City of Cookeville v. Upper Cumberland Electric Membership Corp.

  • 484 F.3d 380
  • 2007 WL 1146456
Court
Court of Appeals for the Sixth Circuit
Filed
Apr 19, 2007
Status
Published
Author
Rogers
On the bench
Rogers, Griffin, Russell
Cited by
3 cases
Authority
More cited than 49.7%

The opinion

RECOMMENDED FOR FULL-TEXT PUBLICATION

Pursuant to Sixth Circuit Rule 206

File Name: 07a0138p.06

UNITED STATES COURT OF APPEALS

FOR THE SIXTH CIRCUIT

_________________

X

Plaintiff-Appellant, -

CITY OF COOKEVILLE, TENNESSEE,

-

-

-

Nos. 05-5886; 06-5363

v.

,

>

UPPER CUMBERLAND ELECTRIC MEMBERSHIP -

-

-

CORPORATION; HILDA G. LEGG; RURAL UTILITIES

-

SERVICES, an Agency of the Department of

-

Agriculture; DEPARTMENT OF AGRICULTURE;

-

SHELDON PETERSON, Governor; NATIONAL BANK

-

FOR COOPERATIVES; NATIONAL RURAL UTILITIES

COOPERATIVE, -

Defendants-Appellees. -

-

N

Appeal from the United States District Courts

for the Middle District of Tennessee at Cookeville and Nashville.

No. 02-00093—Thomas A. Wiseman, Jr., District Judge.

Argued: March 5, 2007

Decided and Filed: April 19, 2007

Before: ROGERS and GRIFFIN, Circuit Judges; RUSSELL, District Judge.*

_________________

COUNSEL

ARGUED: Andree Sophia Blumstein, SHERRARD & ROE, Nashville, Tennessee, for Appellant.

W. Brantley Phillips, Jr., BASS, BERRY & SIMS, Nashville, Tennessee, Frances M. Toole,

UNITED STATES DEPARTMENT OF JUSTICE, Washington, D.C., for Appellees. ON BRIEF:

Andree Sophia Blumstein, SHERRARD & ROE, Nashville, Tennessee, T. Michael O’Mara,

Cookeville, Tennessee, for Appellant. W. Brantley Phillips, Jr., John R. Lodge, Jr., Russell S.

Baldwin, BASS, BERRY & SIMS, Nashville, Tennessee, Frances M. Toole, UNITED STATES

DEPARTMENT OF JUSTICE, Washington, D.C., for Appellees.

*

The Honorable Thomas B. Russell, United States District Judge for the Western District of Kentucky, sitting

by designation.

1

Nos. 05-5886; 06-5363 City of Cookeville v. Upper Cumberland Page 2

Elec. Membership Corp., et al.

_________________

OPINION

_________________

ROGERS, Circuit Judge. In this case, we affirm the federal district court’s resolution of a

dispute over one element of the compensation that Tennessee law requires when a city annexes

territory and exercises its right to purchase electric utility property within the annexed territory. The

federal court had jurisdiction because a federal agency, the Rural Utilities Service (“RUS”), was a

party defendant. We reverse, however, a post-judgment order enjoining the city from providing

electric service in this annexed area pending resolution of the compensation dispute.

When a Tennessee municipality that owns and operates its own electric system annexes

territory in which an electric cooperative is providing electric services to customers, the municipality

has two choices of how to provide electric services to those customers under Tennessee law. See

City of South Fulton v. Hickman-Fulton Counties Rural Elec. Coop. Corp., 976 S.W.2d 86, 90

(Tenn. 1998). The municipality can either “grant such cooperative a franchise to serve the annexed

area” or, as the City of Cookeville chose to do here, “offer to purchase any electric distribution

properties and service rights within the annexed area owned by any electric cooperative.” Tenn.

Code Ann. § 6-51-112(a). The same Tennessee statute that requires this choice also provides a

formula for determining the amount of compensation that the municipality must offer the

cooperative. See Tenn. Code Ann. § 6-51-112(a)(2). As part of this compensation, the municipality

must offer “[a]n amount equal to the cost of constructing any necessary facilities to reintegrate the

system of the cooperative outside the annexed area after detaching the portion to be sold.” Tenn.

Code Ann. § 6-51-112(a)(2)(B).

Cookeville annexed nine areas in which the Upper Cumberland Electric Membership

Corporation (“UCEMC”) provided electric services. Cookeville sued UCEMC, originally in state

court, to condemn UCEMC’s facilities and electric service rights in the annexed areas. RUS was

later added as a defendant. Cookeville and UCEMC disagreed on the cost of

reintegration—Cookeville argued that the cost was approximately $127,000 whereas UCEMC

argued that the cost was $5.825 million. The district court agreed with UCEMC and ordered

Cookeville to pay the higher amount so that UCEMC could build a new substation and distribution

loop. Cookeville appealed. While that appeal was pending, Cookeville began building electric

facilities in the annexed areas and providing electric services to customers in those areas. UCEMC

sought and obtained an injunction from the district court enjoining Cookeville from building

facilities or providing service until it paid UCEMC the damages owed for the condemnation.

Cookeville appealed, and now the propriety of both the damage award and the injunction are before

this court. Cookeville also challenges the district court’s jurisdiction over the entire case and the

district court’s jurisdiction to enter the injunction while the first appeal was pending.

The district court properly exercised jurisdiction because a federal agency was a party. The

district court order requiring Cookeville to pay reintegration costs of $5.825 million was legally

proper and not clearly erroneous. The district court’s injunction, entered during the pendency of the

appeal from the district court’s compensation order, however, improperly expanded the scope of the

previous order. We therefore affirm in part and reverse in part.

I.

In 2000, Cookeville annexed five areas surrounding the city. In 2002, Cookeville annexed

four additional areas. With respect to each annexed area, Cookeville gave notice to UCEMC, an

electric cooperative serving customers in the annexed areas, as required by Tennessee law, but

Nos. 05-5886; 06-5363 City of Cookeville v. Upper Cumberland Page 3

Elec. Membership Corp., et al.

UCEMC refused to sell voluntarily any of its electric distribution properties or service rights in those

areas. See Tenn. Code Ann. § 6-51-112(a)(1) (requiring notice).

Removal and Denial of Motion to Remand

On July 31, 2001, Cookeville brought a civil action against UCEMC in Tennessee state court

in order to condemn UCEMC’s facilities and service rights. On August 14, 2002, Cookeville

amended its complaint and added RUS and National Rural Utilities Cooperative Finance

Corporation (“CFC”) as defendants. RUS is a federal agency. See 7 U.S.C. § 6942. RUS and CFC

each hold a security interest in all of UCEMC’s equipment and service rights within the annexed

areas. UCEMC, RUS, and CFC removed the case under 28 U.S.C. § 1442(a)(1) to the United States

District Court for the Middle District of Tennessee. Cookeville then filed a motion to remand in the

district court arguing that the district court lacked subject matter jurisdiction.

The district court denied Cookeville’s motion to remand. Tennessee ex rel. City of

Cookeville v. Upper Cumberland Elec. Membership Corp., 256 F. Supp. 2d 754, 758 (M.D. Tenn.

2003). Section 1442 states that “[t]he United States or any agency thereof or any officer (or any

person acting under that officer) of the United States or of any agency thereof, sued in an official

or individual capacity for any act under color of such office or on account of any right, title or

authority claimed under any Act of Congress for the apprehension or punishment of criminals or the

collection of the revenue” can remove a civil action to the district court. Courts have also required

as necessary for removal under this statute that the defendant assert a colorable federal defense.

Here, the district court held that “[c]learly, the RUS is an agency of the United States being sued for

acting under color of its office in this case.” Tennessee ex rel. City of Cookeville, 256 F. Supp. 2d

at 758. The court also held that defendants asserted the colorable federal defense of preemption

because they “adequately pled” such a defense and the defense was an issue the district court needed

to decide. Id.

Tennessee Statute

The crux of this case is what compensation Cookeville must pay to UCEMC for UCEMC’s

facilities and service rights in the annexed areas. Tennessee law provides the following formula for

determining the amount of compensation an annexing municipality must pay an electric cooperative:

The municipality shall offer to purchase the electric distribution properties of the

cooperative located within the annexed area, together with all of the cooperative’s

rights to serve within such area, for a cash consideration, which shall consist of:

(A) The present-day reproduction cost, new, of the facilities being

acquired, less depreciation computed on a straight-line basis; plus

(B) An amount equal to the cost of constructing any necessary

facilities to reintegrate the system of the cooperative outside the

annexed area after detaching the portion to be sold; plus

(C) An annual amount, payable each year for a period of ten

(10) years, equal to the sum of:

(i) Twenty-five percent (25%) of the revenues received from power

sales to consumers of electric power within the annexed area, except

consumers with large industrial power loads greater than three

hundred kilowatts (300kW), during the last twelve (12) months

preceding the date of the notice provided for in subdivision (a)(1);

and

Nos. 05-5886; 06-5363 City of Cookeville v. Upper Cumberland Page 4

Elec. Membership Corp., et al.

(ii) Fifty percent (50%) of the net revenues, which is gross power

sales revenues less wholesale cost of power including facilities rental

charge, received from power sales to consumers with large industrial

power loads greater than three hundred kilowatts (300kW) within the

annexed area during the last twelve (12) months preceding the date

of the notice provided for in subdivision (a)(1).

Tenn. Code Ann. § 6-51-112(a)(2). Cookeville and UCEMC agreed on the first and third elements

of the statutory formula. Cookeville agreed to pay UCEMC $1,136,325.25 for the present-day

reproduction cost, new, less depreciation of UCEMC’s electric distribution properties located in the

annexed areas. Cookeville also agreed to make ten annual payments to UCEMC of $276,330 to

comply with section 6-51-112(a)(2)(C).

Trial

Cookeville and UCEMC did not agree on the second element of the statutory formula: “the

cost of constructing any necessary facilities to reintegrate the system of the cooperative outside the

annexed area after detaching the portion to be sold.” See City of Cookeville v. Upper Cumberland

Elec. Membership Corp., 360 F. Supp. 2d 873, 879 (M.D. Tenn. 2005) (quoting Tenn. Code Ann.

§ 6-51-112(a)(2)(B)). At a bench trial in November of 2004, each side presented testimony of an

expert who had produced a “reintegration” plan. Cookeville’s expert, Thomas M. Barnes, testified

about the report that he prepared. In the report, Barnes stated that to reintegrate UCEMC’s system,

UCEMC would only need to construct facilities in one of the annexed areas and would incur “costs

related to coordination of the facility transfer” and “a restocking charge of metering equipment” in

all of the annexed areas. Barnes estimated the total reintegration costs to be $127,282.64. Prior to

the annexations, Cookeville and UCEMC shared a Cookeville-owned substation in West Cookeville

(“West Substation”), and Barnes’ plan anticipated that UCEMC would continue to use that

substation.

UCEMC’s expert, Robert C. Dew, Jr., testified about the report that he prepared. In his

report, Dew concluded that UCEMC needed a new substation and distribution loop built. Dew

estimated that this would cost $5.825 million. Dew’s plan anticipated that UCEMC would no longer

use the West Substation after the annexations. At trial, Dew testified that the new substation was

needed to “have the same operational flexibility, same capacity, same reliability, and better

efficiency” as compared to UCEMC’s system prior to the annexation. Dew testified that after

Cookeville removes UCEMC’s former customers, UCEMC will be left with extra line that continues

through the annexed areas without serving any customers, resulting1 in increased costs from

maintaining the line and losing electricity due to resistance in that line.

District Court Decision

The district court agreed with UCEMC and found that the disputed second part of the

formula equaled $5.825 million. City of Cookeville, 360 F. Supp. 2d at 879.2 In coming to that

conclusion, the court first noted that “[t]here was some argument at trial as to whether [the statutory]

1

When a current is run through an electrical line with resistance, some of the electrical energy is converted to

heat and lost. The longer the line, the more resistance between the substation and the consumer, and thus the more

electricity lost.

2

The district court first held that the proposed condemnation did not frustrate the purpose of the Rural

Electrification Act (“REAct”). City of Cookeville, 360 F. Supp. 2d at 875-78. Neither party challenges this part of the

court’s ruling.

Nos. 05-5886; 06-5363 City of Cookeville v. Upper Cumberland Page 5

Elec. Membership Corp., et al.

definition meant the cost of returning the system to running as well as it had before or whether it

meant the cost of making the system adequate for operation.” Id. The court concluded that

“reintegration costs are those costs associated with returning the system to running as well as [it]

had before the condemnation—no extra inefficiencies and no extra costs related to the system.” Id.

The district court found “that reintegration costs equal the cost of a new substation and the cost of

restoring UCEMC’s distribution loop with the new substation.” Id. This was because the

condemnations otherwise “would lead to inefficient electric distribution” for UCEMC due to the loss

of electricity along lines no longer serving UCEMC customers and due to the maintenance of those

lines. Id.3

Overall, the district court found that UCEMC’s condemnation damages totaled “a single

payment of $6,961,325.25 and 10 annual payments of $276,330.00 per year.” Id.

Motions to Alter or Amend and Appeal

Cookeville and UCEMC moved to alter or amend the court’s order. The issues presented

in the motions involved how and when Cookeville was to pay UCEMC, whether UCEMC would

be allowed to petition the court for additional reintegration costs if the cost of building the substation

and distribution loop exceeded $5.825 million, and whether Cookeville was condemning feeder lines

associated with Cookeville’s West Substation. The district court denied the motions of Cookeville

and UCEMC as to the means and timing of payment because there was “no good reason that the

parties should not be able to come to a resolution of how to execute the judgment.” The court also

held that $5.825 million was the maximum amount Cookeville had to pay and that if the “actual

costs are less than that amount, the remaining amount shall revert to or remain with” Cookeville.

Finally, the court held that Cookeville did not condemn the feeder lines, which remained UCEMC’s

property.

Both parties appealed. UCEMC later voluntarily dismissed its cross-appeal.

Injunction

While the appeal (No. 05-5886) was pending, Cookeville began constructing electric

distribution facilities inside some of the annexed areas. Cookeville admits that it installed street

lighting and other electric facilities in the annexed areas, but maintains that none of those facilities

serviced UCEMC’s pre-annexation customers. Cookeville explained that it has only “begun to serve

new customers, i.e., customers who had moved into the annexed areas (into the City of Cookeville)

after the annexation and who had not previously been UCEMC customers.”

On December 2, 2005, defendants filed with the district court a joint motion for injunctive

relief and costs. Defendants moved for an order compelling Cookeville to “immediately transfer to

UCEMC all electric service currently being provided by [Cookeville] within UCEMC’s exclusive

service territory,” enjoining Cookeville “from constructing electric distribution facilities and/or

servicing customers within UCEMC’s exclusive service territory,” and requiring Cookeville “to pay

all reasonable costs and attorneys’ fees incurred by [d]efendants in connection with bringing” the

motion. Cookeville responded by arguing that the district court lacked jurisdiction to issue an

3

The district court also made a number of rulings not challenged on appeal. The district court refused to include

as reintegration costs the cost of power lines within the annexed areas because no evidence was presented at trial

regarding those costs. Id. The court also refused to make an upward adjustment sought by UCEMC in the amount of

over $3.1 million for “lost revenue from [supposedly] low cost/high profit customers [in the annexed areas].” Id. & n.5.

Finally, the court declined to make a downward adjustment sought by Cookeville for defendants’ purported “delay in

complying with the Tennessee law related to condemnations.” Id. & n.6.

Nos. 05-5886; 06-5363 City of Cookeville v. Upper Cumberland Page 6

Elec. Membership Corp., et al.

injunction because the notice of appeal filed in appeal No. 05-5886 transferred jurisdiction to the

court of appeals, and that even if the district court had jurisdiction, it should not issue an injunction

because post-annexation, a municipality has the right to provide electric service, not an electric

cooperative.

On January 6, 2006, the district court granted defendants’ motion for injunctive relief and

costs. The court concluded that Cookeville was

unlawfully constructing new electric distribution facilities and providing electric

services to customers within one or more of the nine annexation areas at issue in this

case; that such annexation areas [were] within the statutorily-assigned exclusive

service territory of [UCEMC]; and that while [Cookeville had] sued to condemn

UCEMC’s exclusive service rights associated with these annexations areas, it ha[d]

not yet paid the condemnation damages awarded and [wa]s not entitled to the use and

benefit of such exclusive service rights until UCEMC ha[d] been fully compensated

....

Accordingly, the district court held that Cookeville’s actions constituted “an unlawful interference

with UCEMC’s exclusive service rights to the nine annexation areas.” The district court ordered

Cookeville to “transfer to UCEMC within 30 days . . . all electric service customers within any of

the nine annexation areas that are currently being served by” Cookeville. Furthermore, the court

enjoined Cookeville from providing electric service to customers within the annexed areas until

appeal No. 05-5886 is resolved and Cookeville pays in full “the ultimate damage award to UCEMC,

including reintegration costs, . . . or until otherwise ordered” by the district court. Finally, the court

ordered Cookeville to pay defendants’ reasonable costs and attorneys’ fees associated with the

injunction motion because it found that Cookeville’s actions were “not undertaken in good faith, and

that said interference continued despite reasonable efforts by [d]efendants to avoid needless

additional litigation.” Cookeville filed a timely notice of appeal of this order (No. 06-5363).

II.

We affirm the district court’s order in appeal No. 05-5886. Defendants properly removed

the case to the district court and the district court’s decision on the merits awarding reintegration

costs of $5.285 million to UCEMC was not clearly erroneous. However, we vacate the district

court’s injunction in appeal No. 06-5363. The district court did not have jurisdiction to issue the

injunction because the injunction sought to expand the district court’s previous order.

1. Removal Jurisdiction

Defendants properly removed this action to federal court.4 A civil action may be removed

to the federal district court if the action is brought against

4

As a preliminary matter, RUS argues that this court cannot entertain the issue of removal jurisdiction because

Cookeville failed to raise this issue in its notice of appeal. This contention lacks merit. Federal subject matter

jurisdiction can of course be challenged at any stage of the litigation, and jurisdiction cannot be created by waiver. See

Ohio v. Doe, 433 F.3d 502, 505-06 (6th Cir. 2006); Alongi v. Ford Motor Co., 386 F.3d 716, 728 (6th Cir. 2004); Fed.

Nat’l Mortgage Ass’n v. LeCrone, 868 F.2d 190, 192 n.3 (6th Cir. 1989). In any event, Cookeville appealed from the

final order of the district court and this court consequently may consider any earlier errors to which Cookeville objected.

Where a party indicates in its notice of appeal that it appeals from the district court’s final order, this court considers any

alleged errors that occurred prior to the final order. United States v. Sandles, 469 F.3d 508, 518 n.6 (6th Cir. 2006).

Here, Cookeville’s notice of appeal stated that it appealed “from the final order of the District Court.” Therefore, we

may consider the removal issue.

Nos. 05-5886; 06-5363 City of Cookeville v. Upper Cumberland Page 7

Elec. Membership Corp., et al.

[t]he United States or any agency thereof or any officer (or any person acting under

that officer) of the United States or of any agency thereof, sued in an official or

individual capacity for any act under color of such office or on account of any right,

title or authority claimed under any Act of Congress for the apprehension or

punishment of criminals or the collection of the revenue.

28 U.S.C. § 1442(a)(1). In the context of federal officer removal, the Supreme Court has held that

the officer “must both raise a colorable federal defense and establish that the suit is ‘for a[n] act

under color of office.’” Jefferson County v. Acker, 527 U.S. 423, 431 (1999) (quoting 28 U.S.C.

§ 1442(a)(1)) (citation omitted; emphasis and alteration in Acker).

Although the parties assume that the Jefferson County v. Acker officer removal test applies

to federal agency removal as well, the text and legislative history of § 1442(a)(1) demonstrate that

any federal agency sued can always remove under § 1442(a)(1) because the “sued” clause in that

provision applies only to federal officers.5

The text of § 1442(a)(1), is best read to mean that the three entities that can remove are

(1) the United States; (2) any agency thereof; or (3) any officer of the United States or of any agency

thereof, sued in an official or individual capacity for any act under color of such office. A possible

different reading—assumed by the parties in this appeal—is that the three entities that can remove

are (1) the United States; (2) any agency thereof; or (3) any officer of the United States or of any

agency thereof; and that each of these entities must be sued in an official or individual capacity for

an act under color of such office. Although the latter reading is supported by the placement of a

comma directly preceding the word “sued” (suggesting that everything after the comma (i.e., the

“sued” clause) applies to each element of the list before the comma: the United States, any agency

thereof, or any officer of the United States or any agency thereof), that reading does not make sense

because the United States and federal agencies are not “sued in an official or individual capacity”

and are not sued for an “act under color of such office.” Indeed, distinguished scholars of federal

jurisdiction have questioned whether amended § 1442(a)(1) should “be read to permit the United

States to remove only when it is ‘sued in an official or individual capacity for any act under color

of such office’—perhaps a null set and surely a peculiar category.” See Richard H. Fallon, Jr.,

Daniel J. Meltzer & David L. Shapiro, Hart and Wechsler’s The Federal Courts And The Federal

System 910 (5th ed. 2003). Moreover, the Supreme Court rejected an interpretation of an earlier

version of the statute that would have applied a similar “sued” clause to agencies because under that

interpretation, the statute “read[] very awkwardly” because “[a]n agency would not normally be

described as exercising authority ‘under color’ of an ‘office.’” Int’l Primate Prot. League v. Adm’rs

of Tulane Educ. Fund, 500 U.S. 72, 80 (1991). Our independent reading of the text of § 1442(a)(1)

is thus that a federal agency defendant may remove without more.

5

The removal statute, § 1442(a)(1), is broad and allows for removal when its elements are met “regardless of

whether the suit could originally have been brought in a federal court.” Willingham v. Morgan, 395 U.S. 402, 406

(1969). But as the Ninth Circuit reasoned in a case involving prior exclusive jurisdiction, State Eng’r of Nev. v. S. Fork

Band of Te-Moak Tribe, 339 F.3d 804, 809 (9th Cir. 2003), “[§] 1442 is not a trump. If there are specific jurisdictional

bars elsewhere that prevent the district court from asserting jurisdiction, the general removal provision cannot overcome

the jurisdictional defect.” See also Nebraska ex rel. Dep’t of Soc. Servs. v. Bentson, 146 F.3d 676, 678-79 (9th Cir.

1998) (express deprivation of subject matter jurisdiction under 26 U.S.C. § 6305). Indeed, the legislative history of the

1996 amendment to § 1442 indicates that one purpose of giving agencies the power to remove was to “fulfill[] Congress’

intent that questions concerning the exercise of Federal authority, the scope of Federal immunity and Federal-State

conflicts be adjudicated in Federal court.” S. Rep. No. 104-366, at 31 (1996), reprinted in 1996 U.S.C.C.A.N. 4202,

4210-11. Cookeville does not identify any preclusive rule that would have divested the district court of jurisdiction after

removal.

Nos. 05-5886; 06-5363 City of Cookeville v. Upper Cumberland Page 8

Elec. Membership Corp., et al.

The legislative history provides compelling confirmation of this reading.6 The addition of

“The United States or any agency thereof” was the result of a 1996 amendment that sought to

reverse an earlier Supreme Court decision. In International Primate Protection League, 500 U.S.

at 79-82, the Supreme Court held that the pre-1996 version of § 1442 permitted only federal officers,

not federal agencies, to remove suits to federal courts. The pre-1996 version stated that, “Any

officer of the United States or any agency thereof, or person acting under him, for any act under

color of such office or on account of any right, title or authority claimed under any Act of Congress

for the apprehension or punishment of criminals or the collection of the revenue” could remove a

civil action to district court. Congress responded by replacing the beginning of the section (up to

the phrase “or on account of”) with the current language at issue. See S. Rep. No. 104-366, at 6-7,

30-31 (1996), reprinted in 1996 U.S.C.C.A.N. 4202, 4202, 4210-11. This effectively added the

United States and “any agency thereof” as parties that could remove cases to district court. Id. at

31 (noting that the amendment “legislatively reverses the Supreme Court’s decision in International

Primate Protection League”).

The Senate Report supports a reading that § 1442(a)(1) as amended permits a federal agency

to remove to federal district court without limitation. The Senate Report in multiple places separates

the “sued” clause from reference to an agency and includes that clause only with reference to

officers. For example, the Senate Report notes that the amended statute “allows civil actions . . .

against Federal agencies as well as those against Federal officers sued in either an individual or

official capacity to be removed to Federal district court.” Id. at 30. The Senate Report goes on to

state that the amendment “clarifies that suits against Federal agencies, as well as those against

Federal officers sued in either an individual or official capacity, may be removed to Federal district

court.” Id. at 31. The Report, therefore, demonstrates that the “sued” clause applies only to federal

officers and not to federal agencies. Such a reading is consistent with the “clear command from both

Congress and the Supreme Court” that § 1442 is to be interpreted “broadly in favor of removal.”

Durham v. Lockheed Martin Corp., 445 F.3d 1247, 1252 (9th Cir. 2006). RUS therefore properly

removed the action to the district court under § 1442(a)(1) because RUS is a federal agency.

We recognize that other courts of appeals have suggested that a federal agency may also have

to assert a colorable federal defense. See City of Jacksonville v. Dep’t of the Navy, 348 F.3d 1307,

1313 n.2 (11th Cir. 2003) (“We recognize that it remains to be decided whether the requirement of

a federal defense also applies to removal by the United States or one of its agencies.”); Parker v.

Della Rocco, 252 F.3d 663, 665 n.2 (2d Cir. 2001) (expressly not deciding whether a colorable

federal defense is required for agency removal); United States v. Todd, 245 F.3d 691, 693 (8th Cir.

2001) (finding that the United States had asserted a colorable federal defense for removal under

§ 1442 rather than rejecting the need for one). The requirement of a colorable federal defense,

however, is not only not supported by the statutory language, but also is not necessary to ensure the

constitutionality of § 1442(a) under Article III of the Constitution. Article III, section72 extends the

federal judicial power “to Controversies to which the United States shall be a Party.” This case is

thus different from Mesa v. California, 489 U.S. 121, 136-37 (1989), in which the Supreme Court

rejected the government’s argument that a federal defense is not required for officer removal. The

Mesa Court reasoned that an interpretation of § 1442 requiring such a defense ensures Article III

6

We are mindful of the limited utility and reliability of legislative history. In this regard, “the authoritative

statement is the statutory text, not the legislative history or any other extrinsic material.” Exxon Mobil Corp. v.

Allapattah Servs., Inc., 545 U.S. 546, 568 (2005).

7

This constitutional language of course does not lift the sovereign immunity of the United States. In this case,

however, the federal agency consented to jurisdiction so that, as agreed by RUS counsel at oral argument, there is no

sovereign immunity issue in this case. Cf. Lapides v. Bd. of Regents of Univ. Sys. of Ga., 535 U.S. 613, 616 (2002)

(holding that State waives Eleventh Amendment immunity when it removes to federal court).

Nos. 05-5886; 06-5363 City of Cookeville v. Upper Cumberland Page 9

Elec. Membership Corp., et al.

jurisdiction by virtue of the case’s “arising under” federal law. Id. No such interpretation is

required where the United States is a party.

But even if a colorable federal defense were required, RUS fulfilled this requirement by

asserting the defense of preemption. Defendants argued that federal law preempted Cookeville’s

proposed condemnation of UCEMC’s facilities because the condemnation frustrated the purposes

of the Rural Electrification Act of 1936 (“REAct”), 7 U.S.C. §§ 901-950bb (as amended). City of

Cookeville, 360 F. Supp. 2d at 875. The district court noted that this was an issue of first impression

in the Sixth Circuit, and that other courts had split on the issue. Id. at 875. Compare Pub. Util. Dist.

No. 1 of Pend Oreille City v. United States, 417 F.2d 200 (9th Cir. 1969) (disregard of federal

interest precluded condemnation under state law), Pub. Util. Dist. No. 1 of Franklin County v. Big

Bend Elec. Coop., Inc., 618 F.2d 601 (9th Cir. 1980) (condemnation under state law not permitted

after disapproval by the Rural Electrification Administration), City of Morgan City v. S. La. Elec.

Coop. Ass’n, 31 F.3d 319 (5th Cir. 1994) (state-law condemnation preempted by REAct), with City

of Stilwell v. Ozarks Rural Elec. Coop. Corp., 79 F.3d 1038, 1043-46 (10th Cir. 1996) (REAct does

not preempt Oklahoma condemnation statute), Tlingit-Haida Reg’l Elec. Auth. v. Alaska, 15 P.3d

754, 766-68 (Alaska 2001) (similar). Although the district court ultimately sided with Cookeville

and held that the REAct did not preempt Tennessee law permitting the condemnations (a decision

defendants do not challenge on appeal), this does not mean that the defense was not colorable. For

instance, in Acker, 527 U.S. at 431, the Supreme Court concluded that defendants presented a

colorable federal defense of intergovernmental tax immunity even though the Court ultimately

rejected that defense. See also Magnin v. Teledyne Cont’l Motors, 91 F.3d 1424, 1427 (11th Cir.

1996) (“[A colorable federal defense] need only be plausible; its ultimate validity is not to be

determined at the time of removal.”). Here, where the federal defense was an issue of first

impression in this court and had previously found success in other circuits, one would be hard

pressed to say that the defense was not colorable. Therefore, RUS properly removed the action to

the district court even if assertion of a colorable federal defense were required for agency removal

under § 1442(a)(1).

2. Reintegration Costs

The district court did not clearly err by holding that Cookeville must pay to build UCEMC

a new substation and distribution loop. Tennessee law requires as part of the compensation that an

annexing municipality must pay to an electric cooperative “[a]n amount equal to the cost of

constructing any necessary facilities to reintegrate the system of the cooperative outside the annexed

area after detaching the portion to be sold.” Tenn. Code Ann. § 6-51-112(a)(2)(B). Cookeville

argues that the district court erred by awarding reintegration compensation of $5.825 million for two

reasons: (1) the district court applied an incorrect legal standard by requiring financial efficiency

even though the statute requires only engineering efficiency; and (2) even if the district court applied

the correct legal standard, UCEMC’s reintegration plan, which the district court adopted, does not

comply with that standard. This court reviews the district court’s conclusions of law de novo and

findings of fact for clear error. Overton Distribs., Inc. v. Heritage Bank, 340 F.3d 361, 365-66 (6th

Cir. 2003).

Nos. 05-5886; 06-5363 City of Cookeville v. Upper Cumberland Page 10

Elec. Membership Corp., et al.

a. Legal Standard

The district court applied a legal standard that is consistent with Tennessee law.8 The district

court interpreted reintegration costs under the Tennessee statute to mean “those costs associated with

returning the system to running as well as [it] had before the condemnation—no extra inefficiencies

and no extra costs related to the system.” City of Cookeville, 360 F. Supp. 2d at 879. The Tennessee

statute does not define “reintegrate” but the dictionary definition of “reintegrate” is “to restore to

unity after disintegration.” Webster’s Third New International Dictionary 1915 (3d ed. 2002). The

structure of section 6-51-112(a)(2) suggests that the reintegration costs are those necessary to place

the system in the same state of integration that it was in prior to the condemnation. Section 6-51-

112(a)(2)(A) provides for replacement costs for any facilities acquired by the municipality whereas

section 6-51-112(a)(2)(B) then provides for the cost of constructing “necessary facilities to

reintegrate the system of the cooperative.” This scheme suggests that the reintegration costs are

those necessary to reconnect the replaced facilities into the cooperative’s existing electrical system.

To bring the system back to “unity” would involve placing the system in as integrated a condition

as existed prior to the annexation.

Cookeville argues that this standard was incorrect because it read into the statute “an

additional requirement that cost inefficiencies, not just engineering disruptions, be compensated as

part of the reintegration element of the statutory formula.” The distinction Cookeville asks this court

to draw between engineering and economic efficiency is largely semantic. It is not clear how an

engineering 9inefficiency would not be costly, or how any increased cost would not be caused by

engineering. Cookeville refers to no authority for such a distinction in the statute, legislative

history, case law, or any other source. There is nothing in the statute that purports to limit

reintegration costs only to “engineering” efficiency. The statute instead seeks to place the electric

cooperative in the same position it was prior to the municipality’s condemnation of its facilities.10

b. Factual Findings

The district court’s determination of the amount of reintegration costs was largely factual

in nature, and the district court did not clearly err in its findings.

First, the district court did not clearly err by rejecting Cookeville’s proposed reintegration

plan. The question under the statute is what “necessary facilities” must be built in order to

“reintegrate” UCEMC’s distribution system. The district court agreed with UCEMC that

Cookeville’s reintegration plan, which involved maintaining UCEMC’s use of the West Substation,

created inefficiencies because UCEMC would incur extra costs in maintaining several miles of extra

power lines leading to UCEMC’s first customers and from losing electricity along those extra lines.

See City of Cookeville, 360 F. Supp. 2d at 879. This finding is not clearly erroneous because there

was adequate support in the record, in particular, the report and testimony of UCEMC’s expert,

8

Defendants first argue that Cookeville should either be estopped from making this argument because

Cookeville endorsed the same legal test at trial or should be deemed to have waived this argument because Cookeville

failed to object or suggest another legal standard at trial. Cookeville proposed a reintegration plan that included

inefficiencies and argued that this plan was consistent with the statute. Therefore, Cookeville neither is estopped from

making, nor has forfeited, this argument on appeal.

9

Indeed, the district court rejected an adjustment for loss of high paying customers. See supra n.3.

10

As an alternative basis for upholding the district court’s legal standard, defendants argue that Tennessee law

permits the district court to modify the statutory formula for compensation. Because the district court applied a standard

consistent with the statute, we do not need to reach this alternative argument.

Nos. 05-5886; 06-5363 City of Cookeville v. Upper Cumberland Page 11

Elec. Membership Corp., et al.

Dew, for the fact that Cookeville’s reintegration plan failed to account for inefficiencies added to

UCEMC’s electric distribution network.

The district court also did not clearly err by accepting UCEMC’s reintegration plan.

Arguably, UCEMC’s reintegration plan results in a distribution system even more efficient than

UCEMC previously had. In his report, Dew noted that UCEMC’s plan “assumes that UCEMC’s

post-annexation Putnam County distribution system should operate at least as efficiently and as

reliably as it does in its current configuration” (emphasis added). At trial, Dew stated that in

formulating the UCEMC plan, he determined that the plan “had to have the same . . . operational

flexibility, the same capacity, the same reliability[, and h]opefully, improved efficiency” (emphasis

added). But once the district court concluded that Cookeville’s plan did not meet the minimum

required by Tennessee Code section 6-51-112(a)(2)(B), the district court was left only with

UCEMC’s plan, which did meet the minimum requirements of the statute. Cookeville did not

propose an alternative plan—for example, a cost-shifting arrangement where UCEMC would

continue to use the West Substation but Cookeville would compensate UCEMC for cost

inefficiencies.11 The district court’s finding that UCEMC’s plan was required was therefore not

clearly erroneous. When left with the choice between two plans—one that was below the required

minimum and one that was arguably above that minimum—the district court did not clearly err by

requiring the only option that complied with the statute. Therefore, we affirm the district court’s

order requiring Cookeville to pay UCEMC up to $5.285 million in reintegration costs to construct

a new substation and distribution loop.

3. Injunction

The district court, however, erred by issuing the injunction in appeal No. 06-5363 because

the injunction expanded the district court’s previous order on appeal in No. 05-5886 instead of

merely enforcing it. “As a general rule the filing of a notice of appeal divests the district court of

jurisdiction and transfers jurisdiction to the court of appeals.” Cochran v. Birkel, 651 F.2d 1219,

1221 (6th Cir. 1981). “Although a district court may not alter or enlarge the scope of its judgment

pending appeal, it does retain jurisdiction to enforce the judgment.” NLRB v. Cincinnati Bronze,

Inc., 829 F.2d 585, 588 (6th Cir. 1987). This court draws a “crucial distinction between expansion

and enforcement of judgments.” Am. Town Ctr. v. Hall 83 Assocs., 912 F.2d 104, 110 (6th Cir.

1990) (emphasis in original). Here, in the injunction order, the district court decided two legal

issues that it had not decided previously, and expanded significantly the scope of its previous order

on appeal.

First, the district court decided that UCEMC enjoyed exclusive service rights in the annexed

areas. In its order appealed in No. 05-5886, the district court merely decided the amount Cookeville

was required to pay UCEMC in reintegration costs for annexing areas where UCEMC provided

electric service. Whether UCEMC enjoyed exclusive service rights in those areas after Cookeville’s

annexation was not at issue. Thus, when the district court later enjoined Cookeville from

“interfering” with UCEMC’s exclusive service rights by providing electric service to new customers

in the annexed areas, the district court was deciding an issue of law that went beyond the scope of

the court’s initial order that was on appeal at the time of the injunction, and granting relief beyond

the scope of the earlier order.

11

We do not suggest that such a proposal would itself be consistent with the statute. The statute defines

reintegration costs as “[a]n amount equal to the cost of constructing any necessary facilities,” Tenn. Code Ann. § 6-51-

112(a)(2)(B) (emphasis added), and thus might not include payments that are not for constructing facilities, but are

instead meant to compensate the electric cooperative for cost inefficiencies.

Nos. 05-5886; 06-5363 City of Cookeville v. Upper Cumberland Page 12

Elec. Membership Corp., et al.

Second, the district court decided that Cookeville was required to compensate UCEMC prior

to taking UCEMC’s property.12 In denying UCEMC’s motion to alter or amend the earlier order

with respect to the timing of the payments, the district court refused to determine the means and

timing of Cookeville’s payments to UCEMC because there was “no good reason that the parties

should not be able to come to a resolution of how to execute the judgment.” The court also noted

that the $5.825 million awarded to UCEMC was “a maximum amount for reintegration damages”

and that “[i]n the event that actual costs are less than that amount, the remaining amount shall revert

to or remain with” Cookeville. While that decision was on appeal to this court, the district court

issued its injunction, which determined that Cookeville “is not entitled to the use and benefit of

[UCEMC’s] exclusive service rights until UCEMC has been fully compensated.” This decision

expanded the district court’s earlier judgment, which explicitly declined to determine the timing of

Cookeville’s payments. Nowhere in the earlier order did the district court require Cookeville to

compensate UCEMC prior to condemning UCEMC’s property or building electric distribution

facilities in the annexed areas. Also, the earlier order suggested that Cookeville might pay less than

the $5.825 million owed by indicating that if the costs were lower than estimated, the savings might

“remain” with Cookeville. Thus, the earlier order left open the question of whether Cookeville was

required to compensate UCEMC prior to condemnation. Therefore, by requiring Cookeville to pay

UCEMC prior to providing electric service within the annexed areas, the district court improperly

expanded an order on appeal to this court and thus exceeded its jurisdiction.

III.

For the foregoing reasons, we AFFIRM the district court’s order challenged in appeal No.

05-5886 and REVERSE the district court’s injunction order challenged in appeal No. 06-5363.

12

In addition, it appears that the district court erred on the merits in entering the injunction. Under Tennessee

law, a municipality may condemn private property prior to paying compensation. In Zirkle v. City of Kingston, 396

S.W.2d 356, 360-62 (Tenn. 1965), the Supreme Court of Tennessee held that a municipality could take control of private

water and sewer lines on annexed property notwithstanding the fact that the municipality had not paid just compensation

to the owner of the lines prior to taking control of them. See also White v. Nashville & N.W. R. Co., 54 Tenn. (7 Heisk.)

518 (1872) (“[I]t is the approved opinion that property in this country when taken for public use need not be paid for

before being taken.”); cf. Ruckelshaus v. Monsanto Co., 467 U.S. 986, 1016 (1984) (“The Fifth Amendment does not

require that compensation precede the taking.”). UCEMC points to a Tennessee statute that prohibits the taking of

property until damages are paid. See Tenn. Code. Ann. § 29-16-122. However, the Zirkle court referred to similar

language in a prior version of this statute, but nonetheless the court held that the municipality could still condemn the

water and sewer lines prior to paying compensation because an injunction was not an appropriate remedy where the

property owner could later sue for damages. 396 S.W.2d at 360-62. Therefore, it is doubtful that the district court could

have enjoined Cookeville from encroaching on UCEMC’s service rights prior to paying compensation, even if it had

jurisdiction.