ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- )

)

Agility Logistics Services Company KSC ) ASBCA Nos. 57415, 57416, 57417

) 57418,57419,57420

) 57421,57422,57423

) 57424,57425,57426

) 57895,57896,57897

) 57898,57899,57900

) 57901,57902,57903

) 57904,57905,57906

) 57907

Under Contract No. DABVOl-04-D-0014 )

APPEARANCES FOR THE APPELLANT: Michael R. Charness, Esq.

Graham E. Eddy, Esq.

Erin N. Rankin, Esq.

Vinson & Elkins LLP

Washington, DC

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq.

Army Chief Trial Attorney

Robert B. Neill, Esq.

Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE DELMAN ON THE

GOVERNMENT'S MOTION TO DISMISS FOR LACK OF JURISDICTION

The government has filed a motion to dismiss these appeals for lack of

jurisdiction. Agility Logistics Services Company KSC (appellant or Agility) opposes the

motion, and contends that the Board has jurisdiction under the Contract Disputes Act

(CDA), 41 U.S.C. §§ 7101-7109, or under the ASBCA Charter.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. These appeals arise out of contracting officer (CO) decisions related to the

definitization of task orders (TOs) issued under an Indefinite Delivery/Indefinite Quantity

(ID/IQ) contract awarded to appellant 1 on 6 June 2004 by the Coalition Provisional

Authority (CPA) of Iraq. The CPA was created by coalition nation partners to be the

ruling authority in Iraq pending transfer of this authority to a newly constituted Iraqi

1

The contract was awarded to appellant under the name "Public Warehousing Company,

KSC" (amended compl. at 3 n.2).

government. MAC International FZE, ASBCA No. 56355, 10-2 BCA ~ 34,591 at

170,507 (MAC I).

2. The contract scope of work was to establish and operate two distribution center

warehouses and staging areas as part of a supply chain management system supporting

the reconstitution of Iraqi security forces, and for the reconstruction support of Iraq civil

infrastructure (R4, tab 1 at 5). The contract's Statement of Work (SOW) defined the

period of performance as a one-year base period with two one-year options (id. at 6).

3. The contract stated "All task orders issued hereunder are subject to the terms

and conditions of the basic contract. The basic contract shall take precedence in the event

of a conflict with any task orders." (R4, tab 1 at 59)

4. The contract's SOW provided in paragraph 1.2 as follows:

1.2 Executive Agency. The CPA is the current governing

authority in Iraq. The U.S. Army is the executive agent for

Program Management (PM) and contracting for CPA's Iraqi

reconstitution and reconstruction programs. The Program

Management Office [PMO] is a functional staff directorate of the

Coalition Provision[ al] Authority, reporting to the Administrator,

CPA. The [PMO] is CPA's PM and contracting activity.

(R4, tab 1 at 5-6)

5. Paragraph 1.3 of the contract's SOW provided as follows:

1.3 Contract Management. CPA's PMO contracting activity is

the contracting activity responsible for the SCMSDP Support

Contract. As the Contracting Activity for this contract, they have

the authority, through a duly appointed Procuring Contracting

Officer (PCO), to enter into, administer, and/or terminate this

contract and make related determinations and findings.

(R4, tab 1 at 6)

6. At page 68 of the contract, there began a section entitled:

CONTRACT PROCEDURES APPLICABLE TO VESTED

AND SEIZED IRAQI PROPERTY AND DEVELOPMENT

FUND FOR IRAQ [DFI]

This contract is entered into under the authority of the

Administrator as head of the Coalition Provisional Authority

2

(CPA), which is temporarily exercising governmental

authority in Iraq pursuant to the law and usages of war and

relevant United Nations Security Council Resolutions

including Resolution 1483 (2003) (Coalition)

(R4, tab 1 at 68) Insofar as pertinent, this section contained the following contract

provisions:

3. Assignment. The Contractor shall not assign, transfer, or

make any other disposition of this contract, or any part thereof,

without the prior written consent of the Contracting Officer.

4. Changes. Changes in the terms and conditions of this

contract may be made only by written agreement of the parties.

5. Disputes. This contract is not subject to the Contract

Disputes Act of 1978, as amended (41 U.S. Code, Sections

601-613). Failure of the parties to this contract to reach

agreement on any request for equitable adjustment, claim,

appeal, or action arising under or relating to this contract shall be

a dispute to be resolved in accordance with the United States

Federal Acquisition Regulation Clause 52.233-1, Disputes,

which is incorporated herein by reference except that appeals

from final decisions of a Contracting Officer may only be

appealed to the U.S. Armed Services Board of Contract Appeals

(ASBCA). The decision of the ASBCA shall be final. The

contractor shall proceed diligently with performance of this

contract, pending final resolution of any dispute arising under the

contract.

29. Source of Funds. The obligation under this contract is

made with Iraqi Funds, as defined in CPA Memorandum

Number 4, dated 19 August 2003Y1 No funds, appropriated or

2

CPA Memorandum No. 4, the purpose of which was, inter alia, to establish procedures

for contracts for the benefit of the Iraqi people using Iraqi funds, defines "Iraqi

Funds" as including funds in the Development Fund for Iraq (gov't mot., ex. 4 at

1, 3).

3

other, of any Coalition country are or will be obligated under

this contract. [Emphasis added]£ 3l

32. Turn Over of Coalition Provisional Authority. The

contractor hereby recognizes that a transfer of authority (TOA)

from the [CPA] to the interim Iraqi Governing Council is

scheduled to take place June 30, 2004. Furthermore, the

contractor recognizes that upon the TOA on June 30, 2004, or

upon any later TOA date if delayed, the CPA is dissolved. The

CPA, US. Government or Coalition Government will not be

liable to the contractor for any performance undertaken after the

TOA. The contractor hereby waives any claims and rights it now

has or may have in the future against the CPA, U.S. Government

or Coalition Governments in connection with the contract. The

interim Iraqi Governing Council may but is not obligated to be

bound to the obligations of the CPA before the TOA with respect

to performance undertaken after the TOA. The interim Iraqi

Governing Council may but is not obligated to ratify all previous

actions taken by the CPA and agree to be bound with the same

force and effect as if the action had been undertaken [by] the

interim Iraqi Government. If the interim Iraqi Governing

Council undertakes any obligations under this contract, the CPA

recognizes the interim Iraqi Government as its successor in

interest with respect to any such obligations. All payments and

reimbursements previously made by the CPA to the contractor

and all other previous actions taken by the CPA under this

contract shall be considered to have discharged those parts of the

CPA's obligations under this contract. The contractor agrees that

the CPA, the U.S. Government, or any Coalition Government is

not obligated to pay or reimburse the contractor, or otherwise

give effect to, any costs, taxes, or other expenses, or any related

increases, directly or indirectly arising from the TOA. Nothing

herein shall be construed as a waiver of any rights the CPA, U.S.

Government or a Coalition Government may have against the

contractor.

(R4, tab I at 69, 72-73) (Emphasis added)

3

Modification No. P00003, dated 4 December 2004, deleted~ 29, Source of Funds

(R4, tab 4 ), but this modification took effect about six months after the contract

was awarded, and more than five months after the CPA was dissolved.

4

7. On 28 June 2004 the CPA issued CPA Order No. 100, which, inter alia,

revised CPA laws, regulations, orders and memoranda to facilitate the transfer of

authority to the new Iraqi Interim Government (IIG) (gov't mot., ex. 8, § 1 at 1). Insofar

as pertinent, this order amended CPA Memorandum No. 4 above, rescinding the Disputes

clause that provided for ASBCA jurisdiction over CPA contract disputes and provided, in

its stead, for disputes resolution in accordance with the laws of Iraq (id. § 6 at 19, 20).

This order was to be effective immediately prior to the transfer of authority from the CPA

to the IIG (id. § 7 at 21 ). It is undisputed that on or about 28 June 2004, the CPA was

dissolved, and sovereignty transferred from the CPA to the IIG. Pursuant to law, the IIG

obtained control of the DFI at that time. 4

Contract Administration

8. On 15 June 2004, the Minister of Finance of the IIG issued a Memorandum to

the Director, PMO, referencing "SUBJECT: Administration of [DFI]-Funded

Contracts." As of this date, the subject contract was funded with DFI funds (SOF ~ 6, see

clause~ 29). The Finance Minister, citing relevant CPA authority, provided the

following delegation of authority for the administration of contracts on behalf of the 110:

I hereby designate you [PMO] with responsibility to monitor and

confirm performance, certify and/or make payments and

otherwise administer contracts or grants funded with monies

from the [DFI] that:

(a) were entered into on or before June 30, 2004 by

the Coalition Provisional Authority or the

Multi-National Force-Iraq in accordance with

United Nations Security Council Resolution 1483

and implementing regulations;

(b) require the continued performance and/or payment

of money originating from the DFI past June 30,

2004;and

(c) are not the subject ofa fully-funded letter of credit

intended to otherwise ensure performance under

the contract or grant.

The [PMO] will provide as soon as practicable to the Ministry of

Finance a breakdown by Ministry of contracts to which the PMO

is a party.

4

See CPA Regulation No. 11 (app. opp'n, ex. 3), and CPA Memorandum No. 15

(gov't mot., ex. 5), both signed by the CPA Administrator on 18 June 2004.

5

The powers, privileges, rights and authorities granted to you

under this designation shall be exercised in coordination with

relevant officials from the [IIG] and consistent with U.N.

Security Council Resolution 1546 (2004 ), to satisfy outstanding

obligations against the DFI. This designation does not authorize

you to terminate, amend, or novate any contracts or grants

covered by this designation. However, if requested by the IIG,

you shall assist the IIG if it decides to terminate, amend or

novate any such contract.

The powers, privileges, rights, and authorities granted to you

under this designation may be further delegated. They shall

transfer to the Chief of Mission of the United States Embassy

Baghdad and the Commander of the Multi-National Force-I on

June 30, 2004, both of whom shall also have the authority to

delegate these powers, privileges, rights, and activities further.

I retain the right to terminate this designation in writing at any

time and for any reason whatsoever. You shall have the right to

do the same. In any event, this designation shall expire on

December 31, 2004 unless extended in writing by me or another

duly authorized official of the [IIG].£51

Nothing in this designation shall authorize the PMO, the MNF-1,

and/or its designees to enter into any contracts funded by the DFI

after June 30, 2004.

(Gov't mot., ex. 6) (Emphasis added)

9. We find that the IIG, as the new sovereign, assumed responsibility over the

DFI-funded contracts for which it delegated contract administration above. We find that

the subject contract, awarded 6 June 2004 and subject to DFI funds at the time of award,

was one of those contracts.

10. Based upon the above IIG memorandum, we also find that the authority to

administer these DFI-funded contracts, including the subject contract, was transferred

from the PMO to the Chief of Mission of the United States Embassy Baghdad and the

5

This designation/delegation of the IIG Finance Minister was extended through

31 December 2006 (gov't mot., ex. 7).

6

Commander of the Multi-National Force-I effective 30 June 2004. While earlier-issued

TOs under this contract were funded by Iraqi funds and later-issued TOs were funded by

U.S. appropriation (infra), there is no evidence showing that the IIG ever withdrew this

delegation of authority with respect to this contract. Consistent with this IIG

memorandum allowing for further delegation of contract administration authority, it

appears that contract administration was exercised through various components of the

Department of Defense (DoD) throughout the course of the contract (see below).

11. By National Security Presidential Directive dated 11 May 2004, the President

established a temporary organization within the DoD called the Project and Contracting

Office (PCO). The PCO was created, inter alia, to provide "acquisition and project

management support to the Chief of Mission." (App. opp'n, ex. 5 at 3) The Deputy

Secretary of Defense later ordered that the PCO be part of the Department of the Army

(id., ex. 6). The PCO was also identified in Block 6 of DD Form 115 5 as the "issuer"

under TOs 6 and 11 (SOF ii 15). Subsequently, the Joint Contracting Command/Iraq and

Afghanistan (JCC-I/A) was established, whose responsibilities also included contract

administration duties. See Kellogg Brown & Root Services, Inc., ASBCA No. 56256,

10-2 BCA i! 34,613 at 170,591. The JCC-I/A was also identified in Block 6 of DD Form

1155 as the "issuer" on a number ofTOs (SOF ii 15). It also appears that after

performance of the TOs, the Army Contracting Command, Rock Island Contracting

Center (ACC-RI) was involved with appellant's definitization proposals (SOF ii 16).

12. On 24 July 2004, the PCO issued an internal memorandum providing its

understanding of its authority under the 15 June 2004 memorandum (SOF ii 8) from the

IIG Finance Minister above. The memorandum stated as follows:

In accordance with the Ministry of Finance's letter dated

15 June 2004, the Contracting Activity will continue to monitor

and confirm performance, certify and/or make payments, and

otherwise administer contracts or grants financed by

Development Fund for Iraq (DFI) and awarded under the former

Coalition Provisional Authority (CPA). The delegation letter

does not grant us the authority to award, terminate, amend, or

novate any contracts or grants under that delegation.

(App. opp'n, ex. 4) (Emphasis added) This memorandum reflects the PCO's

understanding that it was acting on behalf of the IIG under these contracts, not on

behalf of the United States.

The Relevant TOs

13. This contract was performed through the issuance of 20 TOs. Each of the

13 TOs at issue in these appeals was undefinitized at the time of award. (Amended

Compl. ii 13)

7

14. The TOs were issued by use of DD Form 1155. The CPA was identified in

Block 6 as "issuer" for TOs 1, 2, and 3. The CPA issued TOs 1 and 2 on 17 June 2004,

both of which were funded by DFI, and neither of which is at issue in these appeals. The

CPA also issued TO 3 on 19 June 2004. (App. opp'n, exs. 7, 8; R4, tab 87)

15. As for the other TOs, the PCO was identified in Block 6 as "issuer" under

TOs 6 and 11 (R4, tabs 250, 454 ). The CPA was identified in Block 6 as "issuer" under

TOs 9 and 10 (R4, tabs 345, 411). The JCC-1/A was identified in Block 6 as "issuer"

under TOs 12, 14, 15, 16, 17, 18, 19, and 20 (R4, tabs 479, 499, 511, 528, 544, 562, 574,

594 ). Under a number of these TOs, the issuer granted performance time extensions.

16. Each TO remained undefinitized at the end of the performance period, and

Agility submitted several rounds of definitization proposals to the government through

March 2009 (amended compl. ,-i 141). At the request of ACC-RI in March 2009, the

Defense Contract Audit Agency audited Agility's proposals and issued audit reports.

The parties engaged in discussions to negotiate the definitization of the TOs.

(Id. iii! 145-52)

Claims and Appeals

17. On 23 September 2010, the CO issued 13 final decisions, unilaterally

definitizing TOs 3, 6, 9, 10, 11, 12, 14, 15, 16, 17, 18, 19, and 20 (amended compl.

ii 153) and claiming from appellant a total of $80,830,305.62 (id. ii 208). Each CO

decision included the CDA language pertaining to a contractor's right to appeal.

18. On 5 November 2010, Agility timely filed notices of appeal to the Board,

appealing twelve of the thirteen decisions, excluding the CO decision on TO 16

(Bd. corr., ASBCA Nos. 57415-57426). The Board assigned a docket number to each

appealed decision, ASBCA Nos. 57415 through 57426.

19. On 19 April 2011, Agility submitted a certified claim to the CO in the amount

of $47,196,205.98 plus interest, seeking unpaid costs and fees owed to Agility for its

work under each of the 13 TOs (Bd. corr., ASBCA Nos. 57895-57907, amended NOA,

19 December 2011, ex. 1). The CO issued a final decision denying Agility's claim on

15 December 2011 (id., ex. 2) This CO decision also included the CDA language

pertaining to a contractor's right to appeal, and Agility timely filed a notice of appeal to

the Board. The Board assigned a docket number to each of the 13 TOs, ASBCA

Nos. 57895-57907.

20. On 8 July 2011, the government notified Agility that the government's

monetary claim was "being loaded into the Treasury Offset Program for collection"

(app. opp'n, ex. 13). By 14 September 2011, the Defense Finance and Accounting

Service had set-off over $11 million in payments from an Agility contract with the U.S.

8

Government against the government's claims on the TOs (id., ex. 14). By 21 September

2012, payments due to Agility had been offset by over $16 million (id., ex. 15). As far as

the record shows, there are no appeals before us with respect to these specific matters.

DECISION

Our jurisdiction under the CDA is predicated upon a contract made by an

"executive agency" of the United States as defined by the CDA, 41 U.S.C. §§ 7101(8),

7102(a). It is undisputed that this contract was awarded to appellant by the CPA. We

have held that the CPA, created by a coalition of nation states, is not a federal executive

agency for purposes of CDAjurisdiction. MAC International FZE, ASBCA No. 56355,

13 BCA iJ 35,299 (MAC JI); MAC I, 10-2 BCA iJ 34,591.

Given our lack of CDA jurisdiction over a contract awarded by the CPA,

appellant, as proponent of our statutory jurisdiction, must show that this contract was

novated, transferred or assigned to a executive agency over which we have CDA

jurisdiction. Appellant has not met this burden.

There is no evidence of record showing that the CPA or its successor IIG novated,

transferred or assigned this CPA contract to the DoD or to any federal executive agency

of the DoD. "A novation is a substituted contract that includes as a party one who was

neither the obligor nor the obligee of the original duty." RESTATEMENT (SECOND) OF

CONTRACTS,§ 280 (1981). Appellant contends that upon dissolution of the CPA, the

U.S. Army or DoD became the new "obligor" under this contract and its TOs. However

the "Assent of the obligee of the original duty and of the obligor of the new duty is always

necessary." Id., cmt. c (emphasis added). There is no document in evidence showing that

the purported obligor of this new duty, the Army/DoD, assented to assume the contract

obligations of the CPA or its successor under this contract. To the contrary, the subject

contract made clear that the United States had no intention of assuming any such contract

obligations after the transfer of authority from the CPA: "The ... U.S. Government...will

not be liable to the contractor for any performance undertaken after the TOA" (SOF ii 6,

clause 32).

The necessity for such evidence is particularly important because of the general

immunity of the United States from suit. Whether the United States has waived this

immunity and subjected itself to suit by assuming these contractual duties must not be

lightly presumed.

Pursuant to the memorandum of the IIG Finance Minster above, the IIG delegated

authority to administer this and similar contracts to the Chief of Mission of the U.S

Embassy and the Commander of the Multi-National Force-I, effective 30 June 2004,

which contract administration duties were later performed by various U.S. Army

components (SOF iii! 8, 9 10). Accordingly, the United States acted as a contract

9

administrator and not as a contracting party under these contracts. This fact was

recognized by the PCO in its memorandum dated 24 July 2004 (SOF ~ 12).

Appellant argues that the U.S. Army exceeded its authority as an agent for

contract administration during performance of this contract and its aftermath. However

assuming, arguendo, that appellant's contention is valid, a "rogue agent" does not a

"principal" make. In the final analysis, no novation of this contract from the CPA or

from the IIG to any DoD component has been shown.

We are not persuaded that the Army's execution of a TO, or the Army's

"issuance" ofa TO per Block 6 of the DD Form 1155, was tantamount to a novation,

placing the U.S. Army in contract privity with appellant for purposes of CDA

jurisdiction. We rejected a similar argument in MAC 11, 13 BCA ~ 35,299 at 173,277-78.

Indeed, it is readily apparent that the name appearing in Block 6 had little, real

significance. For example, the "CPA" was identified in Block 6 as issuer under TOs

9 and 10 (SOF ~ 15), notwithstanding the CPA had been dissolved many months earlier.

Nor are we persuaded that the use of U.S. appropriated funds for a TO made for

contract privity. We also rejected this argument in MAC II, 13 BCA ~ 35,299 at

173,277-78:

The contract under which the DOs now before us were

issued was a contract between the CPA, an international entity,

and MAC. The U.S. government was never a party to the

contract nor to any of the DOs. The U.S. government's role in

the contracting process (through the CPA Contracting Activity,

PCO and JCC-I/A) was solely as the specific delegate of the

CPA until its dissolution on 28 June 2004 and, after the

dissolution of the CPA, by specific delegation by the IIG. MAC

argues that the 16 DOs now at issue were U.S. government

contracts and that, after dissolution of the CPA, they were

obligations of the U.S. government and did not transfer to the

IIG. However, the DOs issued under the CPA contract, to which

the U.S. government was never a party, obligated the same

contracting party as the contract itself: the CPA and, by virtue of

CPA Order Number 100, any successor entities such as the

IIG ....

[T]he existence of our jurisdiction is not changed by the fact that

the 16 DOs at issue in the remainder of the appeal contained

U.S. government appropriated fund cites. [Citations omitted]

10

Appellant cites AmerescoSolutions, Inc., ASBCA Nos. 56824, 56867, 11-1 BCA

~ 34,705 (Ameresco), for the proposition that the Board has CDAjurisdiction over a TO

issued by a DoD component under an ID/IQ contract. We believe the facts of Ameresco

are distinguishable.

In Ameresco, the ID/IQ contract provided for various federal agencies, including

DoD components, to enter into delivery orders with the contractor to obtain energy

savings services. On the other hand, this CPA contract, awarded with Iraqi funds, did not

provide for DoD components to enter into any delivery orders with the contractor to

obtain any services (SOF ~ 13 ). Also, this CPA contract provided that the basic contract

shall take precedence in the event of conflict with the TOs; in Ameresco it was the

delivery orders that were granted precedence.

We believe that neither Ameresco nor any of the other cases cited by appellant

compels a conclusion supporting our jurisdiction under the CDA under the circumstances

presented here. We conclude that we lack jurisdiction over this CPA contract and its TOs

under the CDA.

The ASBCA Charter

The ASBCA was created by the DoD by Charter. Part 1, paragraph 1 of the

Charter, provides as follows:

1. There is created the Armed Services Board of Contract

Appeals which is hereby designated as the authorized

representative of the Secretary of Defense, the Secretary of the

Army, the Secretary of the Navy and the Secretary of the Air

Force, in hearing, considering and determining appeals by

contractors from decisions of contracting officers or their

authorized representatives or other authorities on disputed

questions. These appeals may be taken (a) pursuant to the

Contract Disputes Act of 1978 (41 U.S.C. Section 7101-7109),

(b) pursuant to the provisions of contracts requiring the decision

by the Secretary of Defense or by a Secretary of a Military

Department or their duly authorized representative, or

(c) pursuant to the provisions of any directive whereby the

Secretary of Defense or the Secretary of a Military Department

or their authorized representative has granted a right of appeal

not contained in the contract on any matter consistent with the

contract appeals procedure. The Board may determine contract

disputes for other departments and agencies by agreement as

permitted by law. The Board shall operate under general policies

established or approved by the Under Secretary of Defense for

Acquisition, Technology and Logistics and may perform other

11

duties as directed not inconsistent with the Contract Disputes Act

of 1978.

48 C.F .R., Ch. 2, Appx. A, Part 1 (2007).

Appellant contends, alternatively, that we have jurisdiction over these appeals

under the ASBCA Charter, pursuant to the Disputes provision of the CPA contract

requiring decision of disputes by the ASBCA (SOF ~ 6). We disagree. Consistent with

CPA Order No. 100 and its amendment of CPA Memorandum No. 4 (SOF ~ 7), we

believe that the CPA intended to eliminate ASBCA jurisdiction over contract disputes

effective on the date of transfer of authority to the IIG. Appellant argues that this change

applied to new or prospective contracts only, but this contention is not supported by the

record.

However, even if CPA Order No. 100 did not have the effect of removing the

original Disputes clause from this contract, it is nevertheless clear that parties to a

contract may not by agreement confer jurisdiction on a tribunal where jurisdiction

otherwise does not exist. There is nothing in our DoD Charter that confers jurisdiction on

this Board over disputes under this contract with the CPA. The Board did not have any

agreement with the CPA or with the nation states that created it to hear CPA contract

appeals, nor has appellant shown any DoD directive that would otherwise grant

jurisdiction to the Board over such appeals. Nor has appellant shown that the CPA was a

DoD organization or that any DoD contract was involved here. We rejected similar

arguments in MAC I, 10-2 BCA ~ 34,591at170,518-19.

The cases cited by appellant in its opposition papers are distinguishable. They

involve our jurisdiction over appeals under contracts between contractors and DoD

non-appropriated fund instrumentalities under which the parties consented to our

jurisdiction. These facts do not pertain here.

In view of the foregoing, we conclude that we do not have jurisdiction of these

appeals under the ASBCA Charter.

"Implied-In-Fact" Contract to Definitize TOs

Alternatively, appellant contends that there exists an "implied-in-fact" contract

between Agility and ACC-RI to definitize the TOs over which we may exercise

jurisdiction under the CDA (app. opp'n at 24-25), citing the conduct of the parties in the

negotiation of the definitization of the TOs. This "implied-in-fact" contract claim is not

identified in appellant's claim letter dated 19 April 2011, and raises separate and distinct

facts from those supporting appellant's claim of privity through, among other things, the

execution, issuance and the funding of the TOs. As a prerequisite to our jurisdiction, a

contractor claim must be presented first to the CO for decision, 41 U.S.C. § 7103(a)(l).

Accordingly, we are without jurisdiction over this "implied-in-fact" contract claim.

12

Assuming, arguendo, that this "implied-in-fact" contract claim was somehow

indirectly raised in appellant's claim letter of 19 April 2011, we are still without

jurisdiction for the following reason. Appellant's claim posits an implied-in-fact

agreement by the government to provide definitization services. It is well settled

however that the CDA does not extend to contracts that provide government services to a

contractor; rather, the CDA extends to the government's procurement of services/ram a

contractor. Laudes Corp. v. United States, 86 Fed. Cl. 152, 161 (2009). Appellant has

failed to show such a procurement here. Appellant also has not persuaded us that our

DoD Charter provides for our jurisdiction over any "implied-in-fact" contracts of this

nature.

For reasons stated, we are without jurisdiction over appellant's "implied-in-fact"

contract claim.

Appellant's Request for Stay

Alternatively, appellant requests an indefinite stay to allow it to take additional

discovery on the jurisdictional issue.

When the government raised the jurisdictional issue by letter to the Board dated

3 July 2013, citing MAC II, appellant responded by letter dated 9 July 2013. Appellant

did not seek a stay for additional discovery at that time. Rather, it argued forcefully

against the government's position on jurisdiction, distinguishing MAC II, and provided

evidence in support. Not only did appellant fail to seek a stay, it requested "that the

Board expedite review of the jurisdiction issue, so that the parties can continue

[settlement] negotiations, and enter into a Mediation Agreement." (Bd. corr., ASBCA

Nos. 57415-57426)

On 25 July 2013, the Board convened a conference to set a briefing schedule on

the jurisdictional issue, and issued an Order on Briefing dated 29 July 2013. Again,

appellant did not object to setting a firm briefing schedule, nor did it seek a stay of the

proceedings for additional discovery.

On both of the above occasions, appellant did not assert that it needed additional

discovery to assert or defend its position. Appellant's comprehensive treatment of

jurisdiction in its motion papers also belies its current position.

We believe that appellant's request in its motion papers for an indefinite stay of

proceedings for additional discovery is untimely and unreasonable. We deny appellant's

request.

13

Appellant's Request for Substantive Board Orders

Alternatively, appellant requests that if we determine we are without jurisdiction,

the Board should issue orders to the government to withdraw its claims and pay appellant

all withheld funds. Appellant's request is self-contradictory. A tribunal without

jurisdiction of an action may not issue any substantive orders to the parties with respect

to matters related to the action. Once we determine we are without jurisdiction, we must

dismiss the appeals. See Johns-Manville Corp. v. United States, 893 F.2d 324, 327

(Fed. Cir. 1989).

CONCLUSION

For reasons stated herein, we lack jurisdiction over these appeals. The

government's motion to dismiss is granted, and the appeals are dismissed.

Dated: 9 December 2014

Administrative Judge

Armed Services Board

of Contract Appeals

I concur I concur

~

Administrative Judge

RICHARD SHACKLEFORD

Administrative Judge

Acting Chairman Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

14

I certify that the foregoing is a true copy of the Opinion and Decision of the Armed

Services Board of Contract Appeals in ASBCA Nos. 57415, 57416, 57417, 57418, 57419,

57420,57421,57422, 57423, 57424,57425,57426, 57895, 57896, 57897, 57898,57899,

57900, 57901, 57902, 57903, 57904, 57905, 57906, 57907, Appeals of Agility Logistics

Services Company KSC, rendered in conformance with the Board's Charter.

Dated:

JEFFREY D. GARDIN

Recorder, Armed Services

Board of Contract Appeals

15