Opinion

Hanley Industries, Inc.

Court
Armed Services Board of Contract Appeals
Filed
Aug 12, 2014
Status
Published
On the bench
Paul
Cited by
0 cases
Authority
More cited than 33.2%

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- )

)

Hanley Industries, Inc. ) ASBCA No. 56584

)

Under Contract No. W52P1J-05-C-0076 )

APPEARANCE FOR THE APPELLANT: Ryan K. Manger, Esq.

Manger Law, LLC

St. Louis, MO

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq.

Army Chief Trial Attorney

Brian E. Bentley, Esq.

CPT Tudo N. Pham, JA

Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE PAUL

This is a timely appeal of a contracting officer's (CO's) decision terminating

appellant Hanley Industries, Inc.'s (Hanley's) supply contract for default. The Contract

Disputes Act of 1978, 41 U.S.C. §§ 7101-7109 is applicable. In a decision promulgated

on 29 November 2012, the Board denied the government's motion for summary

judgment. 13 BCA ii 35,195. Familiarity with that decision is presumed.

Subsequently, a five-day hearing was held in St. Louis, Missouri.

FINDINGS OF FACT

1. On 29 September 2005, the U.S. Army Sustainment Command (Army) issued

Contract No. W52P1J-05-C-0076 to Hanley to supply 37,718 MK45-1 Electric Primers

(R4, tab 1 at 1-3). The MK45 primer initiates the propelling charge for shells fired from

U.S. Naval warships (compl. and answer ii 2). 13 BCA ii 35,195 at 172,685. The

firm-fixed-price contract had a total contract amount of $1,870,812.80 with a unit price of

$49.60 for each of the primers. The negotiated contract included four option years with

unit prices as follows: FY06, $49.63; FY07 $51.30; FY08 $53.04; and FY09, $54.84.

(R4, tab 1 at 1-3)

2. The contract incorporated standard FAR and DF ARS clauses by reference,

including FAR 52.249-8, DEFAULT (FIXED-PRICE SUPPLY AND SERVICE) (APR 1984) (R4,

tab 1 at 36). The contract specifically provided that FAR and DFARS clauses which

were incorporated by reference, "the full text of which will be made available upon

request, [have] ... the same force and effect as if set forth in full text" (id. at 15).

3. The contract included, in full text, the Local 52.246-4506, STATEMENT OF

WORK FOR STATISTICAL PROCESS CONTROL (FEB 1999) clause, also known as SPC. That

clause described in great detail Hanley's responsibilities including its "commitment to

continuous process improvement." Various subsections of the clause set forth

requirements for, inter alia, "SPC Training," "Manufacturing Controls," "Determination

of SPC Use," "Process Stability and Capability," "Control Chart Policy,"

"Vendor/Subcontractor Purchase Controls," "SPC Audit System," "SPC Records," and

"Control of Process/Operation Parameters or Characteristics" (id. at 8-10).

4. Also included in the contract was the Local 52.209-4511, FIRST ARTICLE TEST

(GOVERNMENT TESTING) (MAY 1994) clause, which provided:

a. The first article shall consist of: ONE HUNDRED

THIRTY MK 45 MOD 1 PRIMERS AND 5 EACH OF

EVERY COMPONENTS PART AND SUBASSEMBLY

(LESS EXPLOSIVE COMPONENTS) PER MIL-P-18714

REV D, AMENDMENT 1 AND ADL 10001-2434755K;

which shall be examined and tested in accordance with

contract requirements, the item specification(s), the Quality

Assurance Provisions (QAPS) and drawings listed in the

Technical Data Package.

b. The first article shall be delivered to:

SEVENTY-FOUR COMPLETE MK 45 MOD 1 PRIMERS

TO: NAVAL SURFACE WARFARE CENTER,

DAHLGREN DIVISION, 17320 DAHLGREN ROAD,

DAHLGREN, VA 22446-5100/FITY [sic ]-SIX COMPLETE

PRIMERS AND FIVE EACH OF EVERY COMPONENT

PARTS AND SUBASSEMBLY (LESS EXPLOSIVE

COMPONENTS) TO: NAVAL SURF ACE WARF ARE

CENTER, IDIAN [sic] HEAD DIVISION, 101 STRAUSS

A VENUE, INDIAN HEAD, MD 20640. The first article

shall be delivered by the Contractor Free on Board (FOB)

destination except when transportation protective service or

transportation security is required by other provision of this

contract. If such is the case, the first article shall be delivered

FOB origin and shipped on Government Bill of Lading.

2

c. The first article shall be representative of items to

be manufactured using the same processes and procedures as

contract production. All parts and materials, including

packaging and packing, shall be obtained from the same

source of supply as will be used during regular production.

All components, subassemblies, and assemblies in the first

article sample shall have been produced by the Contractor

(including subcontractors) using the technical data package

provided by the Government.

d. Prior to delivery, each of the first article assemblies,

subassemblies, and components shall be inspected by the

Contractor for all contract, drawing, QAP and specification

requirements except for any environmental or destructive

tests indicated below: NIA. The Contractor shall provide to

the Contracting Officer at least 15 calendar days advance

notice of the schedule date for final inspection of the first

article. Those inspections which are of a destructive nature

shall be performed upon additional sample parts selected

from the same lot(s) or batch( es) from which the first article

as selected. Results of contractor inspections (including

supplier's and Vendor's inspection records when applicable)

shall be verified by the Government Quality Assurance

Representative (QAR). The QAR shall attach to the

contractor's inspection report a completed DD Form 1222.

One copy of the contractor's inspection report with the DD

Form 1222 shall be forwarded with the first article; two

copies shall be provided to the Contracting Officer. Upon

delivery to the Government, the first article may be subjected

to inspection for all contract, drawing, specification, and QAP

requirements.

e. Notwithstanding the provisions for waiver of first

article, an additional first article sample or portion thereof,

may be ordered by the Contracting Officer in writing when (i)

a major change is made to the technical data, (ii) whenever

there is a lapse in production for a period in excess of 90

days, or (iii) whenever a change occurs in the place of

performance, manufacturing process, material used, drawing,

specification or source supply. When conditions (i), (ii), or

(iii) above occurs, the Contractor shall notify the Contracting

3

Officer so that a determination can be made concerning the

need for an additional first article sample or portion thereof,

and instructions provided concerning the submission,

inspection and notification of results. Costs of the first article

testing resulting from production process change, change in

the place of performance, or material substitution shall be

borne by the Contractor.

f. Rejected first articles or portions thereof not

destroyed during inspection and testing will be held at the

government first article test site for a period of 30 days

following the date of notification of rejection, pending receipt

of instructions from the Contractor for the disposition of the

rejected material. The Contractor agrees that failure to

furnish such instructions within said 30 day period shall

constitute abandonment of said material by the Contractor

and shall confer upon the Government the right to destroy or

otherwise dispose of the rejected items at the discretion of the

Government without liability to the Contractor by reason of

such destruction or disposition.

(R4, tab 1at15-16)

5. In addition, the contract contained the Local 52.245-4537, ACCEPTANCE

INSPECTION EQUIPMENT (AIE) (FEB 2002) clause, which stated:

a. Acquisition, maintenance, and disposition of

Acceptance Inspection Equipment (AIE) shall be in

accordance with ANSl/NCSL Z540-1 or ISO 10012-1. AIE

shall be used to assure conformance of components and end

items to contract requirements. AIE shall include all types of

inspection, measuring, and test equipment whether

Government furnished, contractor designed, or commercially

acquired, along with the necessary specifications, and the

procedures for their use.

b. The Contractor shall provide all Acceptance

Inspection Equipment (AIE) necessary, except for the

Government Furnished Equipment (GFE) listed in paragraph

(g.8). The GFE shall be provided in accordance with the

Government Property clause of this contract. The Contractor is

responsible for contacting NSWC Corona at least 45 days in

4

advance of the date the GFE is required to schedule delivery.

Government furnished AIE shall not be used by the contractor

or his subcontractor in lieu of in-process or work gages.

c. Contractor AIE designs, specifications, and

procedures for Critical, Major, Special, and Minor

characteristics shall.be submitted to the Government for

review and approval in accordance with the Contract Data

Requirements List, DD Form 1423. All Contractor AIE

documentation requiring Government approval shall contain

sufficient information to permit evaluation of the AIE's

ability to test, verify or measure the characteristic or

parameter with the required accuracy and precision.

Contractor designed AIE requiring Government approval

shall be made either in accordance with the equipment

drawings specified in section C of contract

(Description/Specification Section), or in accordance with

any other design documentation provided that it is approved

by the Government. The Government will approve the AIE

documentation or provide requirements for approval within

45 days of receipt. The Contractor shall be responsible for

any delays resulting from late submission of AIE

documentation to the Government for approval, and any

delays resulting from the submission of inadequate or

incomplete AIE documentation.

d. The contractor must ensure that all AIE is approved

and available for use prior to First Article Submission, if First

Article is required, or prior to initiation of production under

this contract.

e. Resubmission of AIE design, specification, and

procedure documentation for approval on a follow-on

contract is not required provided inspection characteristic

parameters specified in the current technical data package and

the previously approved AIE documentation remain

unchanged. The contractor shall provide the contract number

and identify previously approved AIE documentation that

meets the above prerequisites.

5

f. The Government reserves the right to disapprove at

any time during the performance of this contract, use of any

AIE not meeting the requirements of the approved design,

specification, or procedure documentation.

g. Navy Special Interface Gage Requirements (NSIG)

1. The Navy Special Interface Gages listed under this

clause will be forwarded to the Contractor for joint use by the

Contract Administration Office (CAO) and the Contractor.

2. The Contractor may substitute contractor designed

and built AIE for the NSIG noted as applicable in paragraph

(g)(8). However, the designs require Government approval

and the contractor AIE hardware requires Government

certification. AIE designs shall be submitted in accordance

with paragraph (c). The contractor shall notify NSWC Corona

prior to submission of AIE for certification. Two copies of

each Government approved contractor AIE drawing shall

accompany the contractor AIE hardware sent to the

Government for certification. The Government shall perform

the contractor AIE certification, return the hardware and

provide notification of acceptance or rejection to the

Contractor within 45 days of receipt of the contractor AIE.

The contractor shall be responsible for any delays resulting

from late submission of documentation or hardware. The

Contractor shall also submit the calibration periods for each

contractor AIE for approval. The Government shall affix

Calibration stickers to the contractor AIE for Quality

Assurance Representative (QAR) identification.

3. The NSIGs are provided for verification of selected

interface dimensions and do not constitute sole acceptance

criteria of production items or relieve the Contractor of

meeting all drawing/specification requirements under the

contract.

4. Items that fail to be accepted by the applicable

NSIGS may be inspected by another means to determine

acceptance or rejection, provided the alternate inspection

method is acceptable to the government approval authority.

6

5. The Government shall not be responsible for

discrepancies or delays in production items resulting through

misuse, damage or excessive wear to the NSIGs.

6. Calibration and repair of the NSIGs shall only be

performed as authorized by the Naval Surface Warfare Center

(NSWC), Corona Division. Repair is at no cost to the

Contractor unless repair is required due to damage to the

gages resulting from Contractor fault or negligence.

Damaged, worn, or otherwise unserviceable NSIGs shall be

brought to the immediate attention of the CAO and NSWC

Corona. The Contractor shall not make any adjustments,

alterations or add permanent markings to NSIG hardware

unless specified by the NSIG operating instructions or

authorized by the Designated Technical Activity.

7. Within 45 days after final acceptance of all

production items, the NSIGs shall be shipped to NSWC,

Corona Division, ATTN: Receiving Officer, Bldg 575, Gage

Laboratory, 1999 Fourth St., Norco, CA 92860-1915.

The following specifications are applicable:

(i) Shipping, MIL-STD-2073, "DOD Standard Practice

for Military Packaging"

(ii) Marking, MIL-STD-129, "Marking for Shipment

and Storage".

8. The following NSIGs shall be provided and are

mandatory for use except as noted by an (x) for paragraph

(g.2) applicability.

7

Para.

g.2

applies Drawing Rev Char NSIG Qty Dimensions Weight Value

685477 N Ml05 6117015 3 l .75xl 21b $1,000

Pitch Dia. .7286

M106 6117009 3 1.75x3 2lb $1,500

o dia.006

M107 6117015 3 1.75xl 2lb $1,000

o dia.005

1275047 N Ml07 3030384 3 10x10x12 60lb $4,200

o dia.001

M108 3236972 3 3x5 5lb $2,000

o dia.002

MllO 3030939 3 3x3x3 2lb $190

Mill 3236972 3 3x5 $2,000

o dia.002

Ml21 3236972 3 3x5 5lb $2,000

o dia.005

M122 3236973 lx2.5 llb $200

o dia.005

Ml18 6117014 3 .75xl .12 llb $200

o dia.005

2434755 M Ml04 3030396 3 lxlx3 llb $200

.000 Min

M105 3030936 3 lxlx3 llb $200

.018MAX

(R4, tab 1at16-17)

6. Also contained in the contract was the Local 52.246-4506, STATISTICAL PROCESS

CONTROL (SPC) (FEB 2004) clause, which provided:

a. In addition to the quality requirements of the

technical data package, the Contractor shall implement

Statistical Process Control (SPC) in accordance with a

government accepted SPC Program Plan. Control chart

techniques shall be in accordance with the American National

Standards Institute (ANSI) Bl, B2 and B3. Alternate SPC

charting methods may be proposed and submitted to the

Government for review.

8

b. The SPC Program Plan developed by the contractor

shall consist of a general plan and a detailed plan. The plans

shall be structured as delineated on the Data Item Description

referenced in the DD Form 1423. The general and the

detailed plans shall be submitted to the government for

review per DD Form 1423 requirements. Notification by the

Government of acceptance or nonacceptance of the plans

shall be provided in accordance with the timeframes specified

on the DD Form 1423. Once a general plan for a facility has

been approved by this Command, the approval remains in

effect for subsequent contracts as long as the contractual

requirements remain substantially unchanged from contract to

contract. Therefore, resubmission of a previously accepted

general SPC plan is not required if current SPC contract

clause and Data Item Description (DID) requirements are

fulfilled. If this Command has previously accepted the

general SPC plan under essentially the same SPC contractual

requirements, so indicate by providing the Contracting

Officer with the following information:

Date of Acceptance _ _ _ _ _ __

Contract Number(s) _ _ _ _ __

c. The contractor is responsible for updating the

general plan to current SPC contractual requirements. If

errors or omissions are encountered in a previously accepted

SPC general plan, opportunities for improvement will be

identified by the Government, and corrective action shall be

accomplished by the contractor.

d. A milestone schedule will be submitted for those

facilities that do not have, or have never had, a fully

implemented SPC program and will not have a fully

operational SPC program once production is initiated. The

milestones shall provide a time-phased schedule of all efforts

planned relative to implementation of an SPC program

acceptable to the Government. A milestone schedule shall

include implementation start and complete dates for those

SPC subjects addressed in Part II of this clause. The

milestone schedule shall only include those actions that

cannot be accomplished prior to first article or the initiation

9

of production, if a first article is not required. Milestones

shall be developed for each commodity identified for SPC

application. Milestones shall be submitted through the

Government Quality Assurance Representative to the

Contracting Officer for review and acceptance. Any

deviations from the accepted milestones, to include

justification for such deviations, shall be resubmitted through

the same channels for review. The Government reserves the

right to disapprove any changes to the previously accepted

milestones. Notification by the Government of the

acceptance or non-acceptance of the milestones shall be

furnished to the Contractor by the Contracting Officer.

e. The Contractor shall review all process and

operation parameters for possible application of SPC

techniques. This review shall include processes and

operations under the control of the prime contractor and those

under the control of subcontractor or vendor facilities. A

written justification shall be included in the detailed plan for

each process and operation parameter that controls or

influences characteristics identified as critical, special, or

major which have been deemed impractical for the

application of SPC techniques. A pamphlet on application of

SPC for short production runs is available through the

Contracting Officer.

f. Statistical evidence in the form of control charts

shall be prepared and maintained for each process or

operation parameter identified in the detailed plan. These

charts shall identify all corrective actions taken on statistical

signal. During production runs, control charts shall be

maintained in such a manner to assure product is traceable to

the control charts. At the conclusion of the production run, a

collection of charts traceable to the product, shall be

maintained for a minimum of three years. The control charts

shall be provided to the Government for review at any time

upon request.

g. When the process or operation parameter under

control has demonstrated both stability and capability, the

Contractor may request, in writing, through Administrative

Contracting Officer (ACO) and Contracting Officer (CO)

10

channels to the Product Assurance and Test Directorate, that

acceptance inspection or testing performed in accordance

with contract requirements be reduced or eliminated. Upon

approval by the CO, acceptance shall then be based upon the

accepted SPC plan, procedures, practices and the control

charts.

h. The Government will not consider requests for

reduction or elimination of 100% acceptance inspection and

testing .. .if any one of the following conditions exists:

( 1) The existing process currently utilizes a fully

automated, cost effective, and sufficiently reliable method of

100% acceptance inspection or testing for an attribute-type

critical parameter or characteristic.

(2) The Contractor utilizes attribute SPC control chart

methods for the critical parameter or characteristic.

(3) The critical parameter or characteristic is a first

order, single point safety failure mode (nonconformance of

the critical parameter or characteristic in and of itself would

cause a catastrophic failure).

i. The Government will only consider reduction or

elimination of the 100% acceptance inspection or test

requirement for other critical parameters or characteristics if

either of the following conditions is met:

(1) The process is in a state of statistical control

utilizing variable control chart methods for the critical

parameter or characteristic under control and the process

performance index (Cpk) is at least 2.0. The Contractor shall

maintain objective quality evidence through periodic audits

that the process performance index is being maintained for

each production delivery.

(2) The critical parameter or characteristic is

conclusively shown to be completely controlled by one or

more process or operation parameters earlier in the process,

and those parameters are in a state of statistical control

utilizing variable data, and the product of the probability of

11

the conformance for each earlier parameter associated to the

critical characteristic is better than or equal to a value

equivalent to that provided by a Cpk of at least 2.0. The

Contractor shall maintain objective quality evidence through

periodic audits that the process performance indexes are

being maintained for each production delivery.

j. For characteristics other than critical, requests for

reduction or elimination of acceptance inspection and testing

shall be considered when the process performance index is

greater than or equal to a Cpk of 1.33 for variables data.

Requests shall be considered for attributes data when the

percent beyond the specification limits is less than or equal to

.003 (Cpk=l.33).

k. Process or operation parameters under reduced or

eliminated inspection or testing that undergo a break in

production less than 6 months in length, may continue to

operate under reduced or eliminated inspection or testing

provided there has been no degradation below a Cpk of 1.33

(2.0 for criticals). Any break in production greater than 6

months shall require resubmission of the request for reduction

or elimination of inspection or testing through the same

channels cited in paragraph (g) above.

1. Not used.

m. Immediately following a change to a process or

operation parameter under reduced or eliminated inspection,

the process capability (Cp) or process performance indexes

(Cpk) shall be recalculated and documented for variable data;

the grand average fraction defective shall be recalculated for

attribute data. If any of these values have deteriorated,

immediate notification shall be made to the Government

along with the associated documentation. Return to original

inspection and test requirements may be imposed as

stipulated in paragraph n below.

n. The Government reserves the right to withdraw

authorization to reduce or eliminate final acceptance

inspection or testing and direct the Contractor to return to

original contract inspection or test procedures at any

12

indication of loss of process control or deterioration of

quality.

(R4, tab 1 at 17-19)

7. In addition, the contract included the Local 52.246-4530, SUBMISSION OF

PRODUCTION LOT SAMPLES (GOVERNMENT TESTING) (MAY 1994) clause, which provided:

a. A lot acceptance test sample is required to be

submitted by the Contractor from each production lot

tendered to the Government for acceptance. This sample

shall consist of: ONE HUNDRED FIVE MK 45 MOD 1

PRIMERS PER MIL-P-18714 REV D, AMENDENT 1 AND

ADL 10001-2434755K. The sample units shall be delivered

by the Contractor Free on Board (FOB) destination, except

when transportation protective service of transportation

security is required by other provision of this contract. When

such is the case, the sample units shall be delivered FOB

origin and shipped to the test facility identified below on a

Government Bill of Lading for the following tests:

TEST

AS SPECIFIED IN TABL 1 OF MIL-P-18714 REV D

W/AMEND 1 DETAIL STRIP, BLACK POWDER AND

PACKING

REQUIREMENTS

RADIOGRAPHIC, ELECTRICAL RESISTANCE,

FUNCTIONAL, BALLISTIC

SAMPLE-

FORTY-NINEMK45MOD1 PRIMERS TONSWC

DAHLGREN AND FIFTY-SIX MK 45 MOD 1 PRIMERS

TO NSWC INDIAN HEAD

TEST FACILITY:

NAVAL SURFACE WARF ARE CENTER,

DAHLGREN DIVISION

13

17320 DAHLGREN ROAD

DAHLGREN, VA 22446-5100

NAVAL SURFACE WARFARE CENTER, INDIAN HEAD

DIVISION

101 STAUSS AVENUE

INDIAN HEAD, MD 20640

b. When the production lot sample consists of

components parts which require uploading at a Government

Load, Assemble, and Pack (LAP) facility, and a shipping

address is provided below, the contractor shall ship the

sample units as specified above directly to the LAP facility.

The LAP facility, upon completion of the uploading, will be

responsible for shipping the samples to the tests facility

indicated above in paragraph (a).

LAP FACILITY: NIA

c. The sample units shall be randomly selected from

the entire lot by or in the presence of the Government Quality

Assurance Representative. Unless otherwise specified, the

sample units are considered to be destructively tested and are

in addition to the units deliverable under the contract.

d. Prior to selection of the sample units, the lot shall

have been inspected to and meet all other requirements of the

contract. A sample shall not be submitted from a lot rejected

for nonconforrnance to the detailed requirements of the

specifications) and drawing(s) unless authorized by the

Contracting Officer.

e. Unless authorized by the Contracting Officer, the

lot from which the samples are drawn shall not be shipped

until official notification has been provided by the

Contracting Officer that the tested units have satisfactorily

met the established requirements. Final acceptance of the lot

shall not proceed until such notification has been provided.

f. If the production lot sample contains samples for

ballistic testing, the test samples shall be identified as such on

the outer packs and the applicable Ballistic Test Request

14

(BTR) number shall be stenciled on all outer packs and

included on all shipping documents.

g. The Contracting Officer shall by written notice to

the Contractor within 45 days after receipt of the sample units

by the government, approve, disapprove, or conditionally

approve the lot acceptance sample.

h. If the production lot sample fails to meet applicable

requirements, the Contractor may be required at the option of

the Government, to submit an additional production lot test

sample for test. When notified by the Government to submit

an additional production lot test sample, the Contractor shall

at no additional cost to the Government make any necessary

changes, modifications, or repairs and select another sample

for testing. The additional test sample shall be furnished to

the Government under the terms and conditions and within

the time specified in the notification. The Government shall

take action on this test sample within the time limit specified

in paragraph (g) above. All costs associated with the

additional testing shall be borne by the Contractor.

i. If a ballistic test sample fails to meet contractual

performance or functional requirements, the Contractor shall

reimburse the Government for transportation costs associated

with the failing sample, including the cost of transportation

protective service and transportation security requirements

when such security is required by other provision of this

contract. An exception to this requirement for reimbursement

of Government transportation costs will occur if the

Government determines that the functional test samples failed

to meet contractual performance requirements through no

fault of the contractor.

j. If the Contractor fails to deliver any production lot

test sample(s) for test within the time or times specified, or if

the Contracting Officer disapproves any production lot test

sample(s), the Contractor shall be deemed to have failed to

make delivery within the meaning of the Default clause of

this contract. Therefore, this contract may be subject to

termination for default. Failure of the Government in such an

event to terminate this contract for default shall not relieve

15

the contractor of the responsibility to meet the delivery

schedule for production quantities.

k. In the event the Contracting Officer does not

approve, conditionally approve, or disapprove the production

lot test sample(s) within the time specified in paragraph g

above, the Contracting Officer shall equitably adjust the

delivery or performance dates, or the contract price, or both,

and any other contractual provision affected by such delay in

accordance with the procedures provided in the Changes

clause. Failure to agree to any adjustment shall be a dispute

concerning a question of the fact within the meaning of the

clause of this contract entitled Disputes.

(R4, tab 1 at 19-20)

8. In addition, the contract contained the Local 52.246-4528, REWORK AND

REPAIR OF NONCONFORMING MATERIAL (MA y 1994) clause. It stated:

(a) Rework and Repair are defined as follows:

( 1) Rework - The reprocessing of nonconforming

material to make it conform completely to the drawings,

specifications or contract requirements.

(2) Repair - The reprocessing of nonconforming

material in accordance with approved written procedures and

operations to reduce, but not completely eliminate, the

nonconformance. The purpose of repair is to bring

nonconforming material into a usable condition. Repair is

distinguished from rework in that the item after repair still

does not completely conform to all of the applicable

drawings, specifications or contract requirements.

(b) Rework procedures along with the associated

inspection procedures shall be documented by the Contractor

and submitted to the Government Quality Assurance

Representative (QAR) for review prior to implementation.

Rework procedures are subject to the QAR's disapproval.

(c) Repair procedures shall be documented

by the Contractor and submitted on a Request for

16

Deviation/Waiver, DD Form 1694, to the Contracting Officer

for review and written approval prior to implementation.

( d) Whenever the Contractor submits a repair or

rework procedure for Government review, the submission

shall also include a description of the cause for the

nonconformance and a description of the action taken or to be

taken to prevent recurrence.

(e) The rework or repair procedure shall also contain a

provision for reinspection which will take precedence over the

Technical Data Package requirements and shall, in addition,

provide the Government assurance that the reworked or

repaired items have met reprocessing requirements.

(R4, tab 1 at21)

9. Also, the contract included the Local 52.246-4550, CRITICAL CHARACTERISTICS

(FEB 2004) clause. It provided:

(a) The contractor's processes shall be designed to

prevent the creation or occurrence of critical nonconformances.

The contractor shall establish, document and maintain specific

procedures, work and handling instructions and process controls

relating to any critical characteristics.

(b) The contractor shall assure his critical processes

are robust in design such that product and performance are

relatively insensitive to design and manufacturing parameters.

A robust design anticipates changes and problems. Robust

processes shall be designed to yield less than one

nonconformance in one million.

(c) An inspection/verification system shall be

employed that will verify the robustness of your critical

processes. Maximum use should be made of automated

inspection equipment to accomplish verification of product

quality. Mistake proofing techniques of your material

handling and inspection systems are encouraged.

(d) Previous Practices/Special Characteristics. As a

result of previous practices, the governments technical data

17

may refer to Critical (not annotated with I or II) and Special

characteristics. Characteristics classified as Critical (not

annotated with a I or II) shall be subject to all requirements

herein associated with Critical (I) characteristics and level I

Critical nonconformances. Unless otherwise stated in Section

C, characteristics classified as Special shall be subject to all

requirements herein associated with Critical (II) and Level

(II) Critical nonconformances.

( e) Contractor Identified Critical Characteristics List

(CICCL). Not including critical characteristics defined in the

governments technical data (drawings, specifications, etc.),

the contractor shall identify and document all material,

component, subassembly and assembly characteristics whose

nonconformances may result in hazardous or unsafe

conditions for individuals using, maintaining or depending

upon the product. All additional critical characteristics

identified by the contractor shall comply with the critical

characteristic requirements of the technical data package,

supplemented herein. The contractors additional critical

characteristics shall be classified as Critical (I) or Critical (II),

and shall be reviewed and approved by the procuring activity

prior to manufacturing (Dl-SAFT-80970A). The following

definitions are provided.

Level I critical nonconformance. A nonconformance of a

critical characteristic that judgment and experience indicate

would result in hazardous or unsafe conditions for individuals

using, maintaining or depending upon the product; or a

nonconformance that judgment and experience indicate

would prevent performance of the tactical function of a

weapon system or major end item.

The following (as a minimum) are classified as Level I

critical nonconformances:

( 1) A nonconformance that will result in a hazardous or

unsafe condition (often referred to as a single point failure).

(2) A nonconformance that will remove or degrade a

safety feature (such as those in a safe and arm device or

fuzing system).

18

(3) A nonconformance that will result in violation of

mandatory safety policies or standards.

Level II critical nonconformance: A nonconformance of a

critical characteristic, other than Level I. This includes the

nonconformance of a characteristic that judgment and

experience indicate may, depending upon the degree of

variance from the design requirement, the presence of other

nonconformances or procedural errors:

( 1) result in a hazardous or unsafe conditions [sic] for

individuals using, maintaining or depending upon the product, or

(2) prevent performance of the tactical function of a

major end item.

( f) In the event that a Critical nonconformance is found

anywhere in the production process, the contractor, as part of

his quality system, shall have procedures in place to ensure:

( 1) The nonconformance is positively identified and

segregated so that there is no possibility of the item

inadvertently reentering the production process. This control

shall be accomplished without affecting or impairing

subsequent defect analysis.

(2) The operation that produced the defective

component or assembly and any other operations

incorporating that component or assembly are immediately

stopped.

(3) The government is immediately notified of the

critical nonconformance (telephonically and electronic mail.)

(Dl-SAFT-80970A).

(4) Any suspect material (material in process that may

contain the same defect) is identified, segregated and

suspended from any further processing.

( 5) An investigation is conducted to determine the

cause of the deficiency and required corrective actions. A

19

report of this investigation shall be submitted to the

government (DI-SAFT-80970A). The use of the DID report

shall not delay notification to the government.

(6) A request to restart manufacturing or to use any

suspect material associated with the critical nonconformance is

submitted to the government (DI-SAFT-80970A). Restart of

production shall not occur until the investigations are complete

or upon authorization from the procuring contracting officer.

All objective evidence of the investigations to date shall be

available for review at the time of restart. Suspect materiel

found to be nonconforming shall not be used without

Government approval.

(g) The contractor may develop alternative plans and

provisions relative to government or contractor identified

Critical level (I) and Critical Level (II) characteristics. The

provisions shall be submitted to the government for advanced

approval and shall address the following:

(1) Complete explanation of potential failure mode(s)

together with supporting historical and statistical data.

(2) Pre-established plan of action (POA) to be taken

when a critical nonconformance occurs and a description of

controls to ensure there is no possibility of the nonconforming

item inadvertently entering the production process.

(3) Means of tracking nonconformance rate,

investigative results and corrective actions taken.

(4) Method to immediately verify that a produced

critical nonconformance is consistent with the identified

failure mode(s) and does not exceed the historical

nonconformance rate. The contractor can resume production

without specific government approval based upon the

pre-approved alternate plans and provisions for Critical

(I) characteristics and level (I) Critical nonconformances and

Critical (II) characteristics and level (II) Critical

nonconformances.

20

(h) If a critical nonconformance is discovered during

further processing or loading, the original manufacturer who

introduced the critical nonconformance shall bear

responsibility for the nonconformance.

(i) The Government Quality Assurance Representative

will perform the surveillance actions necessary to ensure

compliance with this clause.

(R4, tab 1 at 22-23)

10. The version of the contract contained at tab 1 of the Rule 4 file contains the

full text of the CRITICAL CHARACTERISTIC clause. The document at tab 1 contains the

CO's electronic signature but is not signed by the contractor. (R4, tab 1 at 1) A virtually

identical copy of the contract appears at tab 313 of the Supplemental Rule 4 file. This

copy is manually signed by both parties and incorporates the clause by reference. (R4,

tab 313 at 1, 22) In addition, a copy of the solicitation, which was also signed by the

contractor, included the full text of the clause (R4, tab 255 at 1, 21-22).

11. The contract also included DFARS 252.223-7007, SAFEGUARDING SENSITIVE

CONVENTIONAL ARMS, AMMUNITION, AND EXPLOSIVES (SEP 1999), which provided:

(a) Definition. "Arms, ammunition, and explosives

(AA&E)," as used in this clause, means those items within

the scope (chapter 1, paragraph B) ofDoD 5100.76-M,

Physical Security of Sensitive Conventional Arms,

Ammunition, and Explosives.

(b) The requirements ofDoD 5100.76-M apply to the

following items of AA&E being developed, produced,

manufactured, or purchased for the Government, or provided

to the Contractor as Government-furnished property under

this contract:

NOMENCLATURE

1390-00-877-5245

NATIONAL STOCK NUMBER

primer, Electric

SENSITIVITY/CATEGORY

IV

21

(c) The Contractor shall comply with the requirements

ofDoD 5100.76-M, as specified in the statement of work.

The edition ofDoD 5100.76-M in effect on the date of

issuance of the solicitation for this contract shall apply.

(d) The Contractor shall allow representatives of the

Defense Security Service (DSS), and representatives of other

appropriate offices of the Government, access at all reasonable

times into its facilities and those of its subcontractors, for the

purpose of performing surveys, inspections, and investigations

necessary to review compliance with the physical security

standards applicable to this contract.

(e) The Contractor shall notify the cognizant DSS

field office of any subcontract involving AA&E within

10 days after award of the subcontract.

(f) The Contractor shall ensure that the requirements

of this clause are included in all subcontracts, at every tier

(1) For the development, production,

manufacture, or purchase of AA&E; or

(2) When AA&E will be provided to the

subcontractor as Government-furnished property.

(g) Nothing in this clause shall relieve the Contractor

of its responsibility for complying with applicable Federal,

state, and local laws, ordinances, codes, and regulations

(including requirements for obtaining licenses and permits) in

connection with the performance of this contract.

(R4, tab 1 at 40)

12. The Security Statement of Work (SSW) outlined the physical security

requirements ofDoD 5100.76-M which were referenced in DFARS 252.223-7007. It

was attached to the contract as Attachment 9. It required that the "command will make a

Suitability Determination of structural adequacy on production and storage facilities used

by the contractor." It also stated that the "contractor shall implement a control system

that ensures accountability and control of storage structure locks and keys." Moreover,

the SSW required that "[d]uring periods when the production line is unattended, the

22

contractor shall remove sensitive A&E [ammunition and explosives] to approved storage

areas or protect the production line." (R4, tab 1 at 46, 50-51)

13. The contract also contained an extensive Automated Data List (ADL) which set

forth various technical requirements (R4, tab 1 at 62-76). Included was military

specification MIL-T-15119A which governed the round, seamless alloy steel tubing to be

used in the production of the primers (id. at 65). Paragraph 4.3 of the specification stated:

"A lot shall consist of homogeneous tubing produced from the same heat and the same heat

treatment" (R4, tab 2 at 93). Dr. Christopher Ramsay, appellant's expert witness, defined a

"heat lot" as "that original batch of steel that comes out of the electric arc furnace" (tr.

21194-95). His testimony was corroborated by Mr. Jerry Hahin, a U.S. Navy engineer, who

testified that a "heat lot" was "basically one steel billet that is sent through the heat treater

at a steel mill." For purposes of this contract, Mr. Hahin further distinguished a "heat lot"

from a "production lot." Here, a production lot was a lot of finished primers. He also

confirmed that the specification required that there be only one heat lot per production lot.

(Tr. 3/152-53) Paragraph 6.1 of the specification was titled "Intended use" and provided:

"The seamless alloy steel tubing covered by this specification is manufactured into primer

tubes subjected by explosive charges to high internal gas pressures of short duration."

Paragraph 3. 7 stated: "The tubing shall not break or permanently increase in diameter

more than 0.003 inch when subjected to the hydrostatic test of 4.9." The latter paragraph

described this test in some detail:

All tubing shall be subjected to the minimum hydrostatic

pressure specified in the contract or purchase order (see 6.2).

The test shall be performed on tubing lengths up to 12 feet.

The outside diameter of each test length shall be gaged in the

same location before and after application of the specified

pressure. Failure of the tubing to meet the requirements of

3.7 shall be cause for rejection of the lot.

Paragraph 6.2 required that the "[p]rocurement documents," inter alia, "should specify" the

"[h]ydrostati[c] test pressure (see 4.9 and 6.3)." Paragraph 6.3 of the specification detailed

the "[h]ydrostati[c] test fiber stress" in these terms:

It is intended that the tubes covered by this specification be

subjected by the hydrostatic pressure test to a fiber stress no

greater than 75,000 pounds per square inch as calculated from

the following formula:

bz + az

s=p b2

-a 2

23

S = Fiber stress in pounds per square inch

P =Hydrostatic test pressure in pounds per square inch

a= Outside radius of the tube in inches

b =Inside radius of the tube in inches.

(R4, tab 2 at 92-95)

14. With respect to quality control, Hanley was also required to comply with

ISO 9001-2000 (R4, tab 1 at 20-21 ). However, it submitted a quality control program

pursuant to MIL-Q-9858A which Mr. Hahin found "to be adequate as a reasonable

alternative to ISO 900[1-]2000 for this contract" (tr. 3/212). 1 Paragraph 1.2 of

MIL-Q-9858A stated:

This specification requires the establishment of a quality

program by the contractor to assure compliance with the

requirements of the contract. The program and procedures

used to implement this specification shall be developed by the

contractor. The quality program, including procedures,

processes and product shall be documented and shall be

subject to review by the Government Representative. The

quality program is subject to the disapproval of the

Government Representative whenever the contractor's

procedures do not accomplish their objectives. The

Government at its option, may furnish written notice of the

acceptability of contractor's quality program.

In addition, paragraph 3 .4 of the specification provided:

The contractor shall maintain and use any records or data

essential to the economical and effective operation of his

quality program. These records shall be available for review

by the Government Representative and copies of individual

records shall be furnished him upon request. Records are

considered one of the principal forms of objective evidence of

quality. The quality program shall assure that records are

complete and reliable. Inspection and testing records shall, as

a minimum, indicate the nature of the observations together

1

Paragraph 1.5 ofMIL-Q-9858A stated in part: "ISO 9001 and ANSI/ASQC Q9001 are

alternative model quality system requirements to this specification" (R4, tab 4 at 1).

24

with the number of observations made and the number and

type of deficiencies found. Also, records for monitoring work

performance and for inspection and testing shall indicate the

acceptability of work or products and the action taken in

connection with deficiencies. The quality program shall

provide for the analysis and use of records as a basis for

management action.

(R4, tab 4 at 112-14)

15. Pursuant to MIL-Q-9858A, Hanley forwarded a Quality Assurance Program to

the government in January 2004. The manual was approved in March 2004. (R4, tab 316

at 1) Hanley stated the purpose of the manual in these terms:

The QA Program Manual is designed to assure

adequate controls throughout all areas of contract

performance. Hanley will insure all supplies and services

under contract, regardless where manufactured or performed,

shall be controlled at all points necessary for conformance to

contractual requirements. This program will provide for the

prevention and ready detection of discrepancies and for

timely and positive corrective action. Hanley will document

evidence of quality conformance and make such

documentation available to the Government representative.

This program will delegate authority, responsibility,

and accountability for decisions affecting quality in clear and

precise manner, which assures the proper functioning of the

quality program. By delegating, Hanley intends to promote

prevention or early detection of quality failures to reduce

correctives action costs.

Additionally, Hanley will collaborate and coordinate

closely with DOD contract and administrative personnel to

ensure contract compliance.

(Id. at 5)

16. Paragraph 5.2 of the manual was entitled "PURCHASING DATA." It stated:

Prior to the issuance of any Hanley purchase order for

services or materials a Hanley "Purchase Order Request"

form will be completed defining the article or services to be

procured. The QA Manager examines and approves all

25

purchase orders to insure that they define the articles or

services to be procured. All Purchase Order Request [sic]

may include the following items:

1) The applicable Government contract number, name

and address of the subcontractor and the consignee.

2) A clear, concise description of the supplies or

services ordered.

3) Specification numbers, drawing numbers and

revisions, and process requirements.

4) Packaging, shipping and preservation requirements.

5) Classification of defects or other inspection

requirements.

6) Requirements for qualification or other

Government or contractor approval.

7) Provisions for direct shipment from the

subcontractor's or vendor's plant to Government.

8) Contractor or Government source inspection

requirements.

Document changes will be controlled by procedures

outlined in Chapter 4, section 4.1 Drawings, Documentation

and Changes.

(R4, tab 316 at 20) Ms. Cheryl Nielsen, the CO for the contract, testified that item 6,

"Requirements for qualification or other Government or contractor approval" required that

quality clauses relating to Acceptance and Inspection Equipment (AIE), Statistical Process

Control (SPC), and First Article Testing (FAT), would be included in purchase orders. In

addition, item 8 required that "Contractor or Government source inspection requirements"

were to be included in purchase orders as well. This alerted subcontractors that

government inspectors could be required to conduct inspections at their facilities.

(Tr. 5/13, 32-34) Ms. Nielsen's testimony was corroborated in part by paragraph 7.1 of

Hanley's manual which provided:

26

When Government source inspection is required, under

authorization of the Government Representative the purchase

order shall contain the following statement:

"Government inspection is required prior to shipment

from your plant. When material is ready for inspection

notify, if practical, ten (10) days in advance, the Government

Representative who normally services your plant."

When under authorization of the Government

Representative, copies of the subcontract are to be furnished

directly by the subcontractor to the Government

Representative at his facility rather than through Government

channels, the purchase order shall contain the following

statement:

"On receipt of this order, promptly furnish a copy to

the Government Representative who normally services your

plant, or, if none, to the nearest Government Inspection

Office in your locality. In the event the Representative or

office cannot be located, our purchasing agent should be

notified immediately."

Government inspection shall not constitute acceptance

nor shall it in any way replace contractor inspection or

otherwise relieve the contractor of his responsibility to

furnish an acceptable end item.

All applicable purchasing documents will be provided

to the Government Representative at the supplier's plant upon

request.

(R4, tab 316 at 28)2 Ms. Teresa S. Johnson, the government's product quality manager,

testified that, despite the contract's various quality control provisions, Hanley failed to

2

In addition, MIL-P-18714D, paragraph 4.1 stated: "Unless otherwise specified in the

contract or purchase order (see 6.2), the contractor is responsible for the

performance of all inspection requirements (examinations and tests) specified

herein. Except as otherwise specified in the contract or purchase order, the

contractor may use his own or any other facilities suitable for the performance of

the inspection requirements specified herein, unless disapproved by the

Government. The Government reserves the right to perform any of the inspections

27

I

l "push down" these requirements to its subcontractors. This resulted in various problems.

(Tr. 4/126-27, 141-42)

17. Pursuant to the requirements of DoD 5100.76-M (see finding 12), the

Defense Security Service (DSS) conducted a pre-award survey "to evaluate the

protection afforded items of AA&E [Arms, Ammunition and Explosives]." DSS

concluded that the two buildings proposed by Hanley as manufacturing sites for the

primers were non-compliant. They had been built to an unknown standard, did not have

the required "high security locks and hasps on the access doors," and lacked compliant

key and locks procedures. In addition, privately owned vehicles were parked within

100 feet of the buildings. (R4, tab 289) 3

18. On 9 December 2005, the CO informed Hanley that, inter alia, the deficiencies

listed by DSS were endangering its "ability to perform this contract" (R4, tab 297). In a

response of 20 December 2005, Hanley's president, Mr. T. Gaynor Blake, stated that

Hanley had selected a different building within which to manufacture the primers and that

any "deficiencies that are identified will be corrected or brought up to current

requirements." He concluded that approval [by DSS] "will be requested upon completion

and prior to use under this contract." (R4, tab 296) On 21 December 2005, the CO replied

to Hanley's letter. Ms. Nielsen outlined the various inspections which DSS would have to

conduct in order to approve use of the newly proposed building (R4, tab 298). On

16 February 2006, Ms. Darlene Jones, DCMA's administrative contracting officer (ACO),

informed Hanley that its new site plan could not be approved "due to lack of detailed

information regarding the proposed loading, assembly and packaging operations being

performed" in its proposed building. She listed seven items "that were missing or not

clearly stated." (R4, tab 299) Later that month, DCMA personnel conducted a site visit to

review Hanley's "facility site plan and the set-up of the Mk 45 Primer Manufacturing

operation." DCMA concluded "that very little progress was being made towards finalizing

the site plan on the day of the visit." It made four "observations" regarding deficiencies

and noted that "proper installation of all production equipment could not be verified" due

to the building's renovation not being completed. (R4, tab 300) On 8 March 2006, the

Army informed Hanley that its proposed use of military security locks manufactured by

H.O. Boehme, Inc., did not comply with the requirements ofDoD 5100.76-M. It noted that

the regulation required use of high security locks. (R4, tab 306) On 17 April 2006, the

Army informed Hanley that it had satisfactorily addressed the various deficiencies cited by

DSS and that the Army was issuing "a favorable suitability determination" (R4, tab 302).

set forth in this specification where such inspections are deemed necessary to

ensure supplies and services conform to prescribed requirements." (R4, tab 3 at 5)

3

DSS also noted that Hanley's facility had not previously been involved with the

requirements ofDoD 5100.76-M (R4, tab 289).

·~

28

j

I

There is no persuasive evidence demonstrating that government officials overreached in

their efforts to require Hanley to comply with the requirements of DoD 5100. 76-M.

19. At the hearing, Mr. Blake, Hanley's president, generally described the

production process for the MK.45-1 primer as follows:

There are three subassemblies that go together at the final

assembly. So I'll talk about each of the subassemblies

separately.

This is the primer stock or head stock. This part gets

a[n] insulator pressed into here, and it's staked in. If you

know what staking is, it's where you take a metal punch and

push into the metal, and it squeezes metal and it grips the

insulator that goes in there. Then that insulator is drilled,

that's subassembly.

Course before you can do that, of course you have to

purchase the parts and they have to all go through your

receiving inspection.

This is the tube and this tube is still open. This tube is

made from the 12 foot length of tubing that we talked about

earlier.l41 And these holes are cross drilled in it. And there's

a counterbore on this end, smooth on the inside, it's threaded

on the outside and there's a groove on the inside of this end.

We buy that tube, it goes through receiving inspection

and we put the paper liner in it, which you can see showing

through the holes. And then we fill all these holes with

purple laquer [sic] and that's going to seal them against

moisture. Then that subassembly is set aside.

Well no, I'm sorry I missed this, the brass plug gets

pressed into there. And you can see it won't go in there

without a tremendous amount of a force. So that becomes

this subassembly then. The heart of the Mk45 gun primer is

the igniter. And the igniter is an assemblage of brass and

4

The 12 foot long tubes were eventually cut into 2-foot lengths, the size of the completed

primers (tr. 3/100-01).

29

plastic parts. That assembly, that parts pressed together and

then it gets a fillet of red epoxy to seal it.

And then it gets slotted with a jeweler's saw. Into that

slot we put a wire and we solder it in the left, right and the

center. Such as there are two bridge wires on this unit.

That's for redundancy if one of them would fail that there

would still be another one that would do the job. That's

assembled into this cup with a spacer and some black powder

and it's got a closure foil on the top, and it's crimped. So that

makes that subassembly.

At the final assembly then the igniter is put into the

head stock and there's some sealant put in there. And then

the tube is screwed onto the head stock and tightened up to a

specified torque. And that crushes the igniter and makes a

seal, that's the next step.

Then this is filled with black powder according to

weight, which it comes up to about this full, somewhere in

here. Then there's a paper cup pushed in and that paper cup

then you pour varnish into here, which is going to seal around

the edges of that cup.

You invert it let the excess varnish drip out, you let it

dry. And then you put in another cup very similar to this one

you put into the end, and seal that with varnish. Then it's

ready for final inspection and testing.

(Tr. 1151-53) Mr. Blake also testified that it did not manufacture any of the components;

instead, it purchased all of them from various suppliers (tr. 1/53-54). Moreover, the

government was aware of this fact, as it was stated in Hanley's proposal (R4, tab 256 at 3;

tr. 1/54-55).

20. Much of the tubing which Hanley used in the FAT and the first production lot

was purchased from Propellex, the prior contractor for the primers, and had been

purchased by Propellex from Plymouth tubing. The tubes had been prepared for storage

with oil and had been stored by Propellex in a closed warehouse for approximately a

decade. All of the tubes had been hydrostatically tested and some of them had been

drilled. (Tr. 217-8) Hanley also purchased several pieces of old production equipment

from Propellex (tr. 1171).

30

21. Regarding the production and machinery of the tubing, Mr. Blake testified:

The tubing comes from the mill with a certification of the

chemistry of the steel. And the heat treating and the physical

properties of the steel. Just like you purchase anything,

there'll be a certification on it.

So this tube then is 12 feet long and the first operation

is to centerless grind it. Tubes these days are relatively

straight and smooth but they have to be exceptionally straight

and smooth to be able to go through the process. They go

through what's called a Swiss machine. And if this tube had

any bulges or irregularities in it, it would not feed properly

through the Swiss machine.

So this centerless grinding operation is not required by

the Government. It's a step that we did in order to improve

the quality of the part.

(Tr. 1/55-56) Hanley thus expended time and energy on a process which it admitted was

not required by the contract.

22. In December 2005, Hanley purchased additional Plymouth tubing from Gormac

(R4, tab 315). Unlike the tubing which it had purchased from Propellex, this tubing had to

undergo the entire machining process which Mr. Blake described in these terms:

So the tubing came in and Gormac had that tubing shipped to

their supplier, which was Banner. Banner is a very large

machining operation in that area and their only, well I say

only, I don't know their only business. They're known for

their centerless grinding, that's their specialty.

So we bought the tubing, had it shipped to Banner for

Gormac. Gormac had it centerless ground and then the tube

went to Gormac where it was hydrostatically tested. It's

tested in 12 foot lengths, in a machine with a calibrated gauge

that gives it 18,000 PSI, to ensure that no tube fails.

After the hydrostatic test the part would then go to

Gormac' s Swiss machine. And it would feed into the

31

machine. Does everybody know what a lathe is, it turns the

metal horizontally.

You feed it into the machine and the machine would

then drill the holes and put the counterbore in the end, thread

this end and cut off this end. The part is essentially done, then

it goes to plating which will make the diameter just a little bit

larger. The plating does have a measurable thickness.

Then after inspection steps it would be, there's a cap

that goes on the thread. I thought I had it here, but there's a

plastic cap that goes on the thread to protect it during

shipping and then it comes to Hanley.

(Tr. 1/57-58)

23. Pursuant to Local 52.209-4511 which was included in the contract (finding 4),

Hanley was required to produce a first article for testing (FAT). The first article comprised

130 primers, as well as "5 EACH OF EVERY COMPONENT PART AND

SUBASSEMBLY (LESS EXPLOSIVE COMPONENTS)" (id.). Ms. Teresa S. Johnson,

the Army's product quality manager, was involved in Hanley's two FATs (tr. 4/125-26,

129). The first FAT was conducted in August 2006, and the second FAT took place in

December 2006 (R4, tab 321; tr. 5/177-78). There were several issues with respect to

Hanley's first FAT, according to Ms. Johnson. There were "some failures of the primer

tube." In addition, there were "some gauges that...were either not available or we had to go

and get them calibrated." Finally, there were parts that were "not clearly marked" (see

finding 5; tr. 4/130). With respect to the primer tubing, Ms. Johnson testified:

I remember that I checked that part myself. I also remember

that in the tubes, the holes has [sic] to be straight across from

the other side and you have to put a pin through it, whatever

gauge identified. But the primer tubes that I looked at the

first day the pin wouldn't go through the holes.

(Tr. 4/130-31) Ms. Johnson testified further regarding Hanley's deficiencies:

Instead of failing Hanley because we had been working

together and trying to get through with this, we allowed

Hanley to provide us with five original, ten was [sic] the from

a new producer they had to identify they were going to go to a

new producer. They gave us ten tubes and the agreement was

they would give us ten tubes at the point of introducing the

32

tube and all the assembly up to completion. However we

would allow them to keep the ballistics samples that they had

built up with the original and that they would use these tubes.

And when they got those ready, when we would come back

and look at it and they would not use the tubes that they had

already produced for production for the first first [sic] article.

(Tr. 4/131)

24. Ms. Johnson's testimony regarding Hanley's FAT deficiencies was

corroborated by a letter forwarded to the contractor by the CO, Ms. Nielsen, on

10 August 2006:

Reference Contract W52PlJ-05-C-0076, First Article

Testing (FAT) for the Electric, Primer MK45-l on 1 Aug

2006.

After reviewing the results of your FAT, there are

areas of concern that need to be addressed prior to the return

of the team for the completion of the First Article test. The

following comments are recommended for your use to assist

Hanley Industries in completing the FAT:

1. Request Hanley post work instructions at the site

where the work is to be performed.

2. Develop Inspection Instructions. (Gage usage,

number of samples, identify what characteristic is being

checked, and directions on how to perform the inspection,

etc)[.]

3. Ensure all characteristics are listed on data sheets.

Example MlOl and Ml02 are missing from PN 2847020.

4. Clarify CofC's.

5. Request Hanley position all gages that will be used

in production where they will he used during the process.

Ensure non-necessary gages are not included.

i

I

I

j

33

l

6. Ensure correct gages are called out on the

inspection sheets. Example PN 1275047Ml10 Hanley sheet

calls out 3236973, contract calls out 3030939.

7. Verify receipt of or request Gage 3030396.

8. Obtain AIE approval for characteristics not

inspected/listed at FAT.

9. Submit and get approval for Gage modifications

and additions including those for checking radius. If gages

are modified, change drawing to reflect the modification and

add a revision level to the drawing or a dash number to

indicate a change. Document change in calibration system.

10. Ensure all gages are calibrated and have a current

sticker. Ensure calibration records are available. When

calibrating gages, document gage dimensions being checked

and calibration standard[.]

11. Ensure gage identification is not duplicated for

two or more gages. Example PN 685475 there were two

gages #685475-1, one was incorrectly marked. Had .7489

diam stenciled on the side.

Reference a new supplier of the primer tube:

12. Have available for inspection the 10+ primer tubes

and associated data at the component level from the new

supplier as agreed.

13. Have available for inspection all assemblies and

sub assemblies and associated data containing the primer tube

as agreed.

14. Ensure all certs are available for the new primer

tube with emphasis on hydrostatic testing cert as agreed.

In reference to the new supplier of the primer stock

insulator drawing number 451563.

34

15. Have available for inspection the primer stock

insulator and associated data at the component level from the

new supplier.

16. Have available for inspection all assemblies and

sub assemblies and associated data containing the primer

stock insulator.

17. Ensure all certs are available for the new primer

stock insulator.

In lieu of failing your FAT test, the Government and

Hanley Industries agreed that FAT Testing should be delayed

to allow Hanley Industries additional time to correct the items

listed above. Therefore, this delay in FAT testing is not due

to any fault of the Government and the Government is not

responsible for any additional costs that are derived from this

delay. The test samples that are being sent out to NSWC,

Dahlgren Division, for testing are at Hanley's risk. The

Government assumes no responsibility if these samples fail

their first article test. If the FA testing being conducted at

Hanley Industries or NSWC, Dahlgren Division, fails for any

reason, a new FAT test will be required at Hanley' s cost.

Also, Hanley Industries needs to provide this office the

date when the Government can complete FA testing on the

identified areas of concern.

Thank you for your cooperation in this matter. Please

reply to the above comments NL T 24 August 2006.

(R4, tab 321)

25. The references by both Ms. Wilson and Ms. Johnson to a "new supplier"

referred to the fact that the Army concluded that, during inspection of the FAT tubing, the

pin would not go through the holes because of rust. This apparently resulted from the fact

the Propellex tubes had sat in storage for approximately a decade. (Tr. 4/133-34)

Accordingly, the Army determined that Hanley should seek a new supplier for the second

iteration of the FAT. Hanley complied and purchased new tubing directly from Plymouth

(id.). These tubes passed the second iteration of the FAT in December 2006 and

accordingly, were approved for production (tr. 1196, 5/179-80; finding 22).

35

26. It was only much later that the Army surmised that Hanley used the rejected

Propellex tubing in its production lots. Ms. Johnson, accompanied by other government

employees, traveled to Gormac' s facilities. Their trip report stated, in part:

Gormac claimed that 8800 pieces were delivered to them

from Hanley in various states and stages. These pieces were

primer tubes which Gormac "reworked."

The delivered primer tubes were cut to length with holes

already cut out. Some of the pieces required cleaning and

additional work, however; all the pieces received machining

of threads. These pieces were not hydrostatically tested by

Gormac.

(R4, tab 159 at 2) The only identified tubing which had been previously hydrostatically

tested and required cleaning and rework was the lot which Hanley had purchased from

Propellex and which had been rejected by the government in the first iteration of the FAT.

Setting aside the fact that the Propellex tubes had been rejected, the only way Hanley

could use the tubes in a production lot was to comply with the rework requirements of

FAR 52.246-4528, REWORK AND REPAIR OF NONCONFORMING MATERIAL (MAY 1994).

(Findings 8, 20, 22; tr. 4/134-35) Based upon these facts, the Board concludes that Hanley

used the reworked and rejected tubes which it had purchased from Propellex in its

production lots. 5

27. Hanley did not deliver the primers comprising production lot 1 in a timely

manner. Therefore, through a series of contractual modifications, culminating in

modification No. P00005, the Army extended the delivery date for production lot 1 to 2

February 2007 (R4, tab 1 at 4, tab 7 at 130, 132, tab 9 at 143, 145, tab 10 at 152).

Modification No. P00005 provided:

SECTION A - SUPPLEMENTAL INFORMATION

1. The purpose of this modification is the following:

a. Extend the contract Delivery Schedule as depicted

in Section B of this modification.

b. Increase the contract progress payment limitation

for allowable contract incurred costs.

5

There is no record evidence demonstrating that Hanley complied with the rework clause

with respect to the Propellex tubing (findings 8, 24).

36

j

2. The Delivery Schedule is hereby revised IAW the

Contractors [sic] proposed delivery schedule dated

November 7, 2006, which is incorporated into Section B of

this contract.

3. Clause HS6002, FAR 52.242-4506 Progress Payment

Limitation Incurred Costs, for the limitation of the Progress

Payment percentage for incurred allowable costs is changed

from I 0% to 20%.

4. As consideration for this extension/progress payment

percentage increase, the contractor offer [sic] to extend the

period of performance for exercising the evaluated option for

Fiscal year 2006 by 6 months. This extended FY06 option

period is from September 29, 2006 to March 28, 2007 and the

unit price for FY06 Evaluated Option remains as initially

quoted in the basic contract.

5. In consideration for this extension/progress payment

percentage increase agreed to herein as complete equitable

adjustment for these contract adjustments, the contractor

hereby releases the Government from any and all liability

under this contract for further equitable adjustments

attributable to such facts or circumstances giving rise to those

contract adjustments.

6. All other terms and conditions of this contract remain

unchanged and in effect.

(/d.at151)

28. Through Modification No. P00005, the Army, in return for consideration from

Hanley, increased the progress payment percentage (R4, tab I 0). An issue later arose as to

whether the CO had stopped progress payments. In an email forwarded to the Army on

26 September 2007, Mr. Blake went so as far to state: "Cheryl [Nielsen] had previously

stopped our progress pay." He went on to write: "I CANNOT OVEREMPHASIZE THE

IMPORTANCE OF THIS MATTER." (Ex. A-13 at 1) However, Ms. Nielsen testified

that she had never stopped Hanley's progress payments. In addition, she stated: "I

wouldn't say that it's a stopping of progress payments like they were due to get a progress

payment, as much as it was [sic] they weren't showing progress to get a payment"

(tr. 5/137-39). Based upon the number of modifications to this contract which extended

delivery dates, the Board concludes that whatever problems Hanley allegedly encountered

37

J

in receiving progress payments on this contract resulted from its own inability to make

progress rather them from any unilateral actions on the Army's part.

29. On 30 April 2007, the Army executed bilateral Modification No. P00006

which extended the delivery date for production lot 1 for a fourth time to 12 October 2007

and also extended the delivery date for production lot 2 to 12 January 2008 (R4, tab 11 at

158). 6 In addition, it exercised the options for periods two and three (id. at 157). Also, the

modification incorporated three letters by reference which approved the FAT, and

conditionally approved both Hanley's SPC plan and its AIE. Finally, it incorporated

various requests for deviation (RFDs) and automated data list (ADL) into the basic

contract (id.).

30. On 2 August 2007, the Army executed Modification No. P00007 which

extended the delivery date for production lot 1 to 11 November 2007 and the delivery date

for production lot 2 to 11February2008 (R4, tab 12 at 189, 191). Because of various

problems with production lot 1, it was not accepted by the government until January 2008

(tr. 2/8-9).

31. On 19 November 2007, Mr. Larry Harris, the Defense Contract Management

Agency (DCMA) quality assurance representative (QAR) forwarded to Hanley Corrective

Action Request (CAR) 0076-002, which stated:

1) Reference: MIL-P-18714 D, Paragraph 4.7.1

"Radiographic". The primer shall be subjected to a

radiographic inspection in accordance with MIL-STD-453.

The primer shall be mounted in the VERTICAL position with

the primer stock up ...

It has come to our attention that Hanley Industries

radiographed the primers of Lot 001 in a HORIZONTAL

position.

2) Reference: MIL-STD-41 OE-Para 4.2 "Personnel"

Paragraph 4.2. Personnel Qualification and Paragraph 5,

Detailed Requirements. Paragraph 5 .1.3 Level II individuals

shall have the skills and knowledge to set up and calibrate

equipment, conduct tests ... evaluate and document results in

accordance with procedures approved by the appropriate

Level III...

6

The original delivery date for production Lot 2, as set forth in the contract, was

26 November 2006 (R4, tab 1 at 4).

38

Hanley Industries does not have X-Ray personnel qualified to

Level II.

Please address all of the questions, A thru E, in the block

above. [Ellipses in original]

(R4, tab 278) One of the purposes of the X-ray procedure referenced in the CAR was the

assessment of black powder levels. Accordingly, the CO wrote the following letter to

Hanley on 30 November 2007:

In conjunction with Corrective Action Request

0076-002 it has been determined that Lot l is now suspect of

having low black powder weights. As a result, prior to

Government acceptance of this lot, Hanley will need to l 00%

x-ray the lot to determine sufficient black powder is present

in each primer at no additional cost to the Government. An

x-ray and measurement of the black powder column height

can provide objective evidence that the primers have the

correct amount of black powder. Any primers that show a

discrepant amount of black powder present must be removed

from the lot. If Hanley choses [sic] not to conduct the x-ray

screening proposed above, the Government will not accept

the lot.

In order to complete this effort, Hanley is required to

submit an X-ray screening procedure to be reviewed

and approved by the Government. Enclosed are

suggested procedures for reference to help Hanley formulate

the x-ray screening procedures. The procedures are only

suggestions and it is Hanley's responsibility to formulate new

work plans and submit screening procedures to include

timeline to finish screening process to the Government for

approval.

Request screening procedure to be submitted to the

Government no later than 4 December 2007.

(R4, tab 279)

32. On 29 November 2007, Mr. Harris rejected lot l through another CAR. He

stated:

39

Deficiencies: Out of tolerance powder charge weights.

1) Reference: Drawing 2434755, Characteristic M107, class

2 black powder charge shall be 50.5-53.1 grams

Hanley Industries Variable Control Charts sample

measurements of Lot 001 indicate that there are four primers

in Lot 001 with low weights (50.2, 50.2, 50.1, 50.1).

Additionally, there is one measurement in Hanley's records

that has been recorded over "white-out" and another

recording that was originally recorded as 53.3 and then

"marked over" to show 51.3. There are no explanations in

your official records to indicate why those recordings were

changed.

Major Characteristics are to be accepted on 1 and rejected on

2 nonconpliances.

Lot 001 is rejected.

(R4, tab 281) As of 26 December 2007, Mr. Hahin, the Navy's project engineer, did not

consider this issue to be closed (R4, tab 284).

33. On 19 January 2008, Hanley forwarded an RFD to the government in which

it requested approval to add Roberts Automatic Products, Inc., as a vendor for the primer

stock. 7 On 22 January 2008, Mr. Hahin responded as follows:

This RFD will be considered, however, I wan [sic] to remind

Hanley that each lot of primers is to be homogeneous in

accordance with MIL-P-18714, paragraph 4.5 .1. Therefore,

this deviation will only be considered if this new primer stock

manufacturer is used for the entire lot 2 quantity.

(R4, tab 21 at 246-48) In another letter of that date, Mr. Hahin informed Hanley that its

RFD was not acceptable in its current form. He suggested a number of corrections. (R4,

tab 24 at 267)

7

The primer stock was a steel part distinguishable from the tubing itself (tr. 3/155-56).

40

I

34. Prior to this time period, Hanley had also concluded that Plymouth would no

longer be a reliable supplier of the tubes themselves because it had raised its prices.

Accordingly, Hanley resolved to purchase tubes for future production lots from another

firm called Webco. It issued a purchase order to Webco's agent, Steel Trading Co., Inc.,

for 164,000 linear feet of tubing on 31 May 2007 (R4, tab 328). Just as it would later do

with respect to the primer stock, Hanley was required to seek approval of its new tubing

vendor through the mechanism of an RFD. However, even though it placed the Webco

tubes into production, Hanley did not make such a request (tr. 1157, 4/136, 5/27).

35. On 28 January 2008, Mr. Harris, the QAR, issued another CAR for

Hanley's failure "to have required SPC data from vendors for each lot of component

parts, and not conducting in-process SPC." He added:

A recent inquiry about Lot-002 in-process SPC and SPC data

from vendors indicates a repeat of major deficiencies in

Hanley's SPC program. Specifically, contractor personnel

were not fully aware that their SPC Detailed Plan required

variable or attribute data (Xbar & R or P. Charts) from their

vendors for 15 components. In addition, Hanley was required

to perform in-process charting on eight component parts, and

the primer during manufacture.

Mr. Harris requested that Hanley respond to the CAR by 5 February 2008. It did not

respond in a timely fashion. (R4, tabs 52, 286; tr. 4/141; finding 6)

36. On 1 February 2008, the CO executed unilateral Modification No. POOO 10

which, in conjunction with Hanley's revised delivery schedule spreadsheet, established a

new delivery date for production lot 2 of 22 April 2008 (R4, tabs 4 7, 48). Despite

several extensions, Hanley never met this revised date (tr. 5/21).

37. On 5 February 2008, Hanley informed the government that four primer

tubes had failed the spin gage test (R4, tab 53; finding 5). On 6 February 2008,

Mr. Hahin responded to an inquiry from the CO by stating that this was a critical

failure. He also stated that "Hanley in general do [sic] not seem to grasp the

seriousness of critical defects." (R4, tab 56) Later that day, the CO forward an email

to Hanley in which she stated:

This failure is considered a critical failure in accordance with

the terms of your contract. As such, Hanley shall follow the

requirements of the Critical Characteristics Clause of the

contract. Hanley must cease production from the point of

failure. Hanley shall investigate the cause of the failure and

41

prepare a failure analysis and corrective action for

Government review and approval. Upon Government

approval of the failure analysis and corrective action, the

Government will provide Hanley approval to restart

production in writing.

(R4, tab 57) Correspondence between the government's engineers demonstrated

that the gage failure was related to Hanky's SPC deficiencies. In an email of

4 February 2008, Mr. Wuorinen, the government's product quality manager, stated:

Mr. Harris said that the vendor's lot of primer stock will

probably be rejected for failure of the inner threads to accept

the go gage. The present CAR did cite failure to have the

suppliers provide SPC charts with each shipment. SPC would

have detected this attribute defect, and if managed as

required, corrective actions implemented to immediately

address the probable cause (s) to prevent further defective

product.

(R4, tab 51)

38. On 6 February 2006, representatives of the government and Hanley met to

discuss a variety of contractual issues. Hanley, inter alia, requested a two-week

extension until 20 February 2008 to submit its revised SPC plan. (R4, tab 66 at 390)

39. On 11 February 2008, Hanley responded to the CO's email regarding the ring

gage failure. It concluded: "The source of rejection is an oversize NOGO thread ring

gage." (R4, tab 71 at 410) On 13 February 2008, Hanley proposed using certified gages

from its supplier, Gormac, so that it could proceed with production (R4, tab 75 at 442). In

response to an additional request from the government's engineers, Hanley responded that

the root cause of the failure was that the "ring gage had become worn during the

inspection process" (R4, tabs 77, 81 at 11). Further correspondence between the parties on

this issue resulted in Hanley submitting a calibration certificate for the gages (R4,

tabs 84-87).

40. On 14 February 2008, the CO wrote to Hanley to approve a conditional restart

of production lot 2. She concluded by stating: "It should be noted that any delay to the

current contract delivery schedule as a result of the information contained/reported on the

42

referenced Failure Analysis is considered to be the responsibility of Hanley Industries,

Inc." (R4, tab 94) 8

41. As of 27 February 2008, Hanley still had not submitted either a revised SPC

plan or an updated AIE list despite several missed deadlines (R4, tabs 100, 131).

42. On 26 February 2008, Hanley informed the government that "high pressure

testing at Gormac has caused [one] tube to rupture" (R4, tab 101). On that same day,

the government responded as follows:

This is considered a critical per the Critical Characteristic

clause of your contract. Therefore Hanley must complete a

Failure Analysis and Corrective Action Report for

Government approval before Hanley can utilize any Gormac

tubes in their process. If the tubes that failed are of the same

heat of steel as tubes Hanley is currently using in production,

Hanley must immediately cease use of those tubes until

Government approval of failure analysis and corrective action

report.

(R4, tab 111)

43. On 27 February 2008, the contract specialist, Ms. Crosson, requested

"Government personnel to visit Gormac on Tuesday 4 March 2008." She also requested

"participation of Hanley personnel to accompany the Government to Gormac for the visit."

(R4, tab 114) On 28 February 2008, Hanley informed the government: "Gormac is

expecting your visit. Hanley will not be sending a representative." (R4, tab 121)

44. Despite the fact that government representatives were traveling to Gormac to

investigate the circumstances regarding the burst tube, Hanley informed the government

on 29 February 2008 that the ruptured tube was being forwarded to Hanley's shop for

evaluation (R4, tab 127). On 3 March 2008, Mr. Wuorinen forwarded the following email

to Hanley:

Please confirm ifthat tube is at Gormac or at your plant as

soon as possible. We should have been informed about your

plans to ship the tube last Tuesday. Now we have six team

members going to Gormac today who will [be] conducting an

8

The CO also instructed Hanley "to identify the previous portion of lot 2 as a separate

sublot" (id).

43

investigation. I was not able to participate in this visit due to

training all week.

If it is at your facility, I recommend that any tests conducted

do not destroy the site of the defect. It is extremely important

to assure that the tube is not altered to the extent that it would

significantly impede the Government's evaluation of your

root cause analysis.

What tests do you plan on conducting on the tube?

Spectrographic, atomic adsorption, scanning electron

microsopicity (SEM), wet chemistry?

(R4, tab 133) On that same day, Hanley responded that the tube was scheduled to arrive

at its shop "this morning" (R4, tab 134). The tube was inspected on 4 March 2008, and

Hanley submitted its inspection report to the government on 5 March 2008. Hanley also

stated that it had forwarded the tube to St. Louis Testing Laboratories for "Scanning

Electron Microscope (SEM) analysis." (R4, tab 146)

45. During their visit to Gormac's plant on 4 and 5 March 2008, governmental

representatives learned, for the first time, that Hanley "had switched its steel tube vendor

from Plymouth to WEBCO" (tr. 4/136). Although Hanley had issued a purchase order to

Webco in May 2007 and had received tubes from the new supplier in the January to

February 2008 timeframe, it never informed the government of this fact (finding 34;

tr. 3/116). Moreover, Plymouth Steel-not Webco-was the tube vendor for the first and

the second FATs which had been approved by the government (tr. 2/5, 4/135; findings

22, 25). In addition, Plymouth Steel was also the vendor for production lot 1 which had

been accepted by the government in January 2008 (tr. 2/5; finding 30).

46. Also during their visit to Gormac on 4 and 5 March 2008, the government's

representatives discovered that Gormac was not conducting hydrostatic testing in

accordance with the contract's requirements. On 17 March 2008, the CO forwarded the

following email to Hanley:

Your source may have assured you that the hydrostatic tester

was used on every tube, however, the issue lies with the fact

that Gormac is not conducting the test in accordance with

MIL-T-15119A. According to MIL-T-15119A, the dimensional

portion of the hydrostatic test must also be completed on 100%

of the tubes to satisfy the requirement that there be no more than

.003 inches of permanent deformation. Gormac has only been

conducting the dimensional portion of the test on 1 out of every

44

10 pieces. I have attached a copy of the record they provided

the Government team at the approved visit for the dimensional

test. This will be explained in our response to your restart

request.

(Finding 13; R4, tab 161 at 169) Gormac's "Hydrotest Record," which the CO attached

to her email, confirmed that it had measured only "1 pc each 10 pcs" (R4, tab 161 at

170).

47. During their visit, the government's representatives also concluded that

Gormac was reworking tubes although Hanley had not sought permission to do so

pursuant to the contract's requirements (finding 8; tr. 41148-49). Finally, in violation of

the contract's terms, the government's engineers were unable to inspect Gormac's

hydrostatic testing machine which had been rented and returned to the vendor by Gormac

(finding 5; tr. 4/146).

48. All of the tubes forwarded to Gormac had been subjected to centerless

grinding by another of Hanley's vendors, even though this was not a contractual

requirement (finding 21). A byproduct of this process was that the heat lot stamps

engraved on the 12-foot sections of tubing by the steel mill were erased (tr. 41145). Thus,

the government's engineers were unable to confirm that each production lot was

comprised of only one heat lot, as required by the contract (finding 13). In a situation

where there was only one tube vendor, this might not have been a problem. But here

both Plymouth and Webco had provided tubes to Hanley, and there was no way to

differentiate the various heat lots (tr. 4/162).

49. Hanley's closure report for production lot 2 demonstrated that the problem

was even more serious than it first appeared. Hanley stated that the tubes comprising

production lot 2 contained four heat lots. (R4, tab 206 at 90) Mr. Hahin, the government

engineer, testified that his analysis of Hanley's closure report revealed that there might

even have been a fifth heat lot in production lot 2 (tr. 31163-64).

50. The loss of traceability of the various heat lots was so severe that Dr. Ramsay,

Hanley's expert, could not discern from which of the lots the tube which burst on

26 February 2008 had originated (tr. 2/199-200). On 10 March 2008, St. Louis Testing

Laboratories forwarded their report to Hanley. They concluded:

This analysis suggests that the subject failure condition was

due to the presence of a lap that had split open during

subsequent mechanical operations. The presence of cold

working, rough textured fracture surface (with scale), and an

45

angled fracture along the exterior and interior surfaces of the

tube supports this conclusion.

Laps are surface defects, which appear as seams and are

caused by the folding over of hot metal fins that are rolled

into the metal surface. The condition can become elongated

during subsequent forming operations.

This analysis indicates the linear discontinuity observed on

the exterior surface of the tube was due to mechanical

gouging of the surface. The presence of a cold worked

depression in the location of the discontinuity supports this

conclusion.

(R4, tab 150 at 89)

51. On 11 March 2008, Hanley submitted its CAR for the tube failure

(R4, tabs 154-57). It concluded that it had complied with the requirements of

MIL-T-15119A and that the tubes conformed to specifications. It requested the

CO's permission to restart production on 12 March 2008. (R4, tab 154 at 121)

52. On 17 March 2008, Hanley wrote to the CO:

In our recent phone call you stated that only 10% of tubes

were hydrostatically tested by Gormac. Please check your

source. Gormac assures us that EVERY tube is and has been

hydrostatically tested.

(R4, tab 160) As we have found, the CO rejected this response (finding 46). 9

53. On 19 March 2008, the DCMA QAR, Mr. Conover forwarded a CAR to

Hanley in which he set forth several deficiencies as follows:

Contract Requirements:

1. 150-9000-2000 Paragraph 7.4.2, Purchasing Information

2. MIL-P-18714D, Primer, Electric, Mark 45 Mod 1,

Paragraph 4.5.1, Lot formation. Production must consist of

9

Obviously, Hanley's testing costs would have been lower since Gormac was testing

only 10 percent of the tubes (tr. 41148).

46

not more than 20,000 homogeneous primers plus those

required for inspection ... and only one tubing heat treat lot.

3. MIL-T-15119A, Tubing, Round, Seamless Alloy Steel,

Para 4.3, "A lot shall consist of homogeneous tubing

produced from the same heat and the same heat treatment."

4. ED-STD-183A, (invoked by MIL-T-15119A Para 3.8)

Deficiencies:

1. Hanley Industries Issued purchase order #6082 to

Gormac for the processing of Primer Tube PN 685475.

The lot formation requirements and restrictions of

MIL-P-18714D were not incorporated into the applicable

purchase order nor was the required homogeneity of the

lots maintained. There was no heat lot tracking/control at

Gormac, nor was Gormac aware that only one heat lot

was allowed per primer lot, required to maintain

homogeneous lots. Lot 002 contains 1,800 sections of

12' tubes from 2 different heat lots, 3 7 pieces from heat

lot 06N83 and 1526 from heat lot 540325. Thus,

homogeneity was not maintained as required.

Requirement: MIL-P-18714D, paragraph 4.1

Responsibility for Inspection.

Deficiency: P.O. to Banner and Gormac requires

delegation statement for Government source inspection

(GSI). Request the clause stated below be included in all

purchase orders from Hanley regarding this contract and

any other P.O. requiring GSI.

When Government inspection is required, the contractor

shall add to his purchasing document the following

statement: "Government inspection is required prior to

shipment from your plant. Upon receipt of this order,

promptly notify the Government Representative who

normally services your plant so that appropriate planning

for Government inspection can be accomplished."

47

Requirements:

1. MIL-T-15119A, Paragraph 3.7, Hydrostatic Test.

"The tubing shall not break or permanently increase in

diameter more than 0.003 inch when subjected to the

hydrostatic test of 4.9."

2. MIL-T-15119A, Paragraph 4.9, "The outside diameter

of each test length shall be gaged in the same location

before [and] after application of the specified pressure."

Deficiency:

Gormac only measured 1 out 10 ( 10%) of the tubes for an

increase of .003 inch after the hydrostatic test instead of

the required 100%.

Requirements:

1. IS0-9000-2000 Paragraph 7.4.2, Purchasing

Information

2. MIL-T-1519A, Paragraph 3.7, Hydrostatic test (Cl)

3. Contract W52PIJ-05-C-0076, Section E-10,

Critical Characteristics

Deficiency: The hydrostatic pressure test is a critical

characteristic, inspected and tested at the subcontract

level, and was not identified as such in the purchase order

with Gormac. In addition, the applicable requirements of

Section E-10 for controlling critical characteristics were

not incorporated into the purchase order.

(R4, tab 173 at 208-09)

54. On 19 March 2008, the CO approved a conditional restart of the primer

production. She wrote:

48

a. Hanley Industries Ruptured Tube Corrective Action

Report, dated March 11, 2008.

b. Government visit to Gormac on March 4-5, 2008.

On February 26, 2008, Hanley informed the

Government they experienced failure on a critical

characteristic during high pressure testing which caused

a tube to rupture at Gormac while producing Lot 2. This

occurance [sic] is classified as a critical characteristic

per MIL-T-15119A. As a result and in accordance with the

Critical Characteristics Clause, E-10, Far Clause 52.246-4550

per contract W52PIJ-05-C-0076, production was

stopped/discontinued at both Hanley and Gormac on February

26, 2008.

The Government has completed the necessary

technical review of MK-45, Primer Tube 685475 Root Cause

and Corrective Action Report and has determined that the

report is insufficient in identifying root cause and subsequent

corrective action. Notwithstanding the deficient failure

analysis, the Government is hereby allowing Hanley to restart

production upon completion of the following conditions:

1. Reject and segregate ALL tubes that have been

manufactured by Webco tubing - Primer tubes and Primers.

2. Per referenced b. Gormac's current procedures

indicate that Hydrostatic Testing is being conducted on 100%

of the material. The procedure discusses using a snap gage

set to .765 to measure the tube for distortion of the O.D. after

hydro-testing per MIL-T-l 5119A, however, it fails to address

whether a measurement was taken of the tube prior to

hydro-testing in order to determine if max .003 distortion was

not exceeded. Therefore, these procedures shall be revised

and provided to the Government for approval to reflect that

beginning measurement of the tube is being recorded prior to

hydrostatic testing. Also, all Acceptance Inspection

Equipment (AIE) being utilized at Gormac shall be submitted

to the Government for review and approval.

49

3. Only material obtained from the qualified tube

vendor that was approved at First Article (FAT) can be

utilized in production. If Hanley wishes to submit Webco or

any other vendor as a source of supply for tubing for

Government approval, Hanley shall submit a request for a

"modified" FAT to qualify a new vendor(s). Please note,

however, that the recent rupture makes Webco a questionable

source of tubing. Therefore, a detailed root cause analysis

would be required in addition to FAT request in order for the

Government to consider Webco as a qualified source.

4. Only tubing that is certified to MIL-T-15119A,

TABLE I, paragraphs 3.7 and 4.9 can be utilized in

production. Hanley's qualified tubing vendor(s) must supply

the proper certification.

5. Hanley shall revise all their procedures to ensure

that flowdown of applicable quality contractual requirements

are included in subcontractor purchase orders. This shall be

validated by DCMA QAR.

It should be noted that any delay to the current contract

delivery schedule as a result of the critical failure is

considered to be the responsibility of Hanley Industries, Inc.

As a result of this authorization to resume production,

it is requested that Hanley provide necessary delivery

schedule revisions to include their offer of consideration to

the Government for any delays.

(R4, tab 169 at 195-96) The CO, Ms. Nielsen, testified that she was not required to issue

a conditional restart in this instance. She testified further "I was trying to do what I could

to help Hanley keep moving and making progress." (Tr. 5/49)

55. On 26 March 2008, Hanley forwarded to the government a "Root Cause and

Corrective Action Report" in which it concluded:

All the investigation, evaluation data and reports

provided show only one 12 foot section of tubing is

non-conforming. Whole Lot is not non-conforming[.]

50

Webco has provided the steel per AMS-T-6736 which has the

same chemical composition as the MIL-T-1511-9A. No

requirement for pressure testing.

Material is Non Destruct Tested: Electric tested to

ASTM A450 or A1016 & applicable test method

E309 or E426 per certification[.]

Gormac has 100% pressure tested the tubes prior to

just prior [sic] to going into production (found only 1

ruptured 12 foot section of non-conforming tube was

removed from being placed in use).

Saint Louis Testing report stated embrittlement is not

the cause of the rupture of the tube.

All processing at Hanley Industries has been per

procedure.

All final assemblies have passed manufacturing and

x-ray processing as deliverable product[.] Please review the

previously submitted documentation for approval.

This is a also [sic] request to restart production at

Hanley Industries[.]

If at all possible list Effectivity date for 3/26/08 for

this request[.]

(R4, tab 172 at 206)

56. On 7 April 2008, the CO informed Hanley in writing that its CAR was

insufficient and that "the entire lot of Webco tubing is considered rejected." She

indicated that the government might consider accepting the rejected lot if Hanley

successfully complied with these requirements:

1. Prepare a fault tree/root cause analysis of the

critical failure and identify what has been done or will be

done to investigate the various possible causes of the

failure ....

2. Provide documentation of Traceability of all Heat

Lots in Lot 2 ....

3. Provide documentation that all tubes were

Hydrostatic tested in accordance with MIL-T-15119A and

met all the requirements ....

51

4. In addition to the above mentioned requirements for

the existing tubes, to qualify Webco as a supplier will require

a Modified FAT ....

5. Also, in order to accept the tube stock from Webco

in lot 2, Hanley will need to submit two Requests for

Deviation.

(R4, tab 180 at 1-3) 10

57. On 23 April 2008, Hanley stated it intended to use Webco as its tube vendor.

The government responded that Hanley would have to qualify Webco through a full FAT.

(R4, tab 187 at 251) Hanley never met this requirement (tr. 5/52). On 29 April 2008,

Hanley submitted two RFDs to the government: one related to the certification of a

different type of steel; the other sought to allow multiple heat lots of tubes in production

lot 2 (R4, tab 192 at 266-67).

58. On 2 June 2008, the CO forwarded a show cause notice to Hanley. She

stated:

Since you have failed to perform Contract

W52PIJ-05-C-0076 within the time required by its terms,

or cure the conditions endangering performance under

Contract W52PIJ-05-C-0076 as described to you in the

Government's letter date[d] 19 March 2008, the Government

is considering terminating the contract under the provisions

for default of this contract. Pending final decision in this

matter, it will be necessary to determine whether your failure

to perform arose from causes beyond your control and

without fault or negligence on your part. Accordingly, you

are given the opportunity to present, in writing, any facts

bearing on the question to Ms. Cheryl Nielsen; HQ, ASC,

ATTN: AMSAS-ACA- M; 1 Rock Island Arsenal; Rock

Island, IL 61299-6500, within ten (10) days after receipt of

this notice. Your failure to present any excuses within this

time may be considered as an admission that none exist.

Your attention is invited to the respective rights of Hanley

Industries, Inc. and the Government and the liabilities that

10

At the hearing, the CO testified that Hanley never complied with items 2 and 3

(tr. 5/56-57).

I

J

52

may be invoked if a decision is made to terminate for default

in accordance with clause 52.249-8, Default.

Effective 22 April 2008 subject contract's delivery

schedule became delinquent due to a critical failure that

occurred on 26 February 2008. Hanley's inability to provide

a realistic schedule is directly tied to their inability to meet

the conditions of production restart as follows:

a. Hydrostatic Test the primer tubes in accordance with

TDP requirement MlL-T-15119A which requires

measurement to be taken prior to Hydrostatic Testing.

b. Government approval on Acceptance Inspection

Equipment (AIE) utilized at Hanley's subcontractor

Gonnac in accordance with FAR clause 52.245-4537,

Acceptance Inspection Equipment (AIE) and CDRL

A009.

c. Government approval on a FAT plan to qualify a new

vendor for steel tubing in accordance with CDRL

AOlO. Only material obtained from the qualified steel

tube vendor that was approved by First Article Testing

(FAT) can be utilized in production. Hanley

purchased tubes without the Government's knowledge

from an unqualified vendor that produced the critical

failure. Hanley failed to use steel tubing that is

certified to MIL-T-15119A in production.

d. Revise procurement procedures to ensure that

flowdown of applicable quality contractual

requirements are included in subcontractor purchase

orders in accordance with FAR clause 52.246-4550,

Higher-Level Contract Quality Requirement, ISO

9001-2000.

Any assistance given to you on this contract or any

acceptance by the Government of delinquent goods or

services will be solely for the purpose of mitigating damages,

and it is not the intention of the Government to condone any

delinquency or to waive any rights the Government has under

the contract.

53

If Hanley Industries, Inc. fails to provide any response

satisfactory to the Government within ten (10) days of the

date of this letter, the Government reserves the right to assert

its rights under this contract to include terminating the

contract for default in accordance with FAR clause 52.249-8.

(R4, tab 264)

59. Hanley responded to the show cause notice on 14 June 2008. With respect to

"a"; the hydrostatic testing, Hanley stated:

The government's letter of 4/7/08 address [sic] this topic is

paraphrased as follows:

Provide documentation that all tubes were Hydrostatic

tested in accordance with MIL-T-15119 or tube stock

that has not been machined will need to be Hydrostatic

tested and the DCMA representative to verify, and all

tube stock that has been processed into tubes checked

to insure not expanded beyond. 003 or provide

documentation that all tube stock and/or primer tubes

that the outer diameter could not have experienced a

permanent deformation ofgreater than . 003" [.]

Hanley submitted documentation in support of the

third option on 5/27/08. The documentation showed

statistically that there was less tha[ n] 1 in a million

possibility that a tube had swelled more than .003."

The use of statistics to evaluate a characteristic is well

understood and used extensively in quality

determinations by the Government. Hanley provided

an explanation that we thought was suitable for

persons with a passing understanding of statistical

methods. Attached is documentation and calculations

providing engineering evidence that the .003

requirement is met and tubes at Hanley Industries have

been measured with Government [oversight] and meet

the drawing requirements. Ifthere is need of a more

detailed explanation, we would be happy to provide it.

Hanley requests that the Government clarify in what

way the documentation was insufficient. (Reference

Master Restart Index Items 11-14).

54

Regarding "b"; the AIE requirements, Hanley asserted:

Hanley submitted documentation in support of the AIE

requirement on 5/27/08. Hanley requests that the

Government clarify in what way the documentation was

insufficient. (Reference Master Restart Index Item 60)

As for "c"; the FAT plan to qualify Webco as a new vendor, Hanley stated in part:

In regards the use of tubing from Plymouth, Hanley was made

to understand the critical nature of the need. We understand

our Navy needs top quality Mk45 gun primers immediately.

We have governed our actions accordingly and attempted to

get production restarted as soon as possible. Obtaining

material from Plymouth (vendor #1) will introduce a delay of

many weeks. Perhaps we should not have assumed that the

Government wanted quick delivery. Please note that all the

tubing needed for Lot 3 has already been produced by Webco,

and that production can begin immediately when the

Government is satisfied with the provided documentation.

Hanley did purchase tubing from a vendor that had not been

prequalified by the Government, and we apologize for that.

This, however, in no way was related to the critical failure.

The process for qualifying a new vendor requires the

examination of 5 tubes with QAR oversight. The tubes, had

they been submitted in advance of use on Lot 2, would have

passed. In fact, we could have presented 10,000 tubes to the

QAR, and each would have passed. Please note that the

vendor for Lot 1, Plymouth, is not immune to having tubes

burst. Hanley has interviewed the retired Government QAR

who had oversight at Propellex when the previous

Mk45s were manufactured. He confirms that there was

an occasional tube burst, and that burst tubes were discarded,

with production continuing. In addition please note that

Plymouth Tube declines to quote tubing to MIL-T-[15119A].

In addition, it is our understanding that the only significant

difference between the AMS-T-6736A specification and the

MIL-T-[ 15119A] specification is the Hydrostatic testing.

With the accomplishment of the Hydrotest, MIL-T-[15119A]

requirements have been met.

55

If the government insists, we will order tubing from

Plymouth. The tubing will take many weeks longer to get,

cost more, will still be subject to rare hydrostatic test

failures and will not be certified by the manufacturer to

MIL-T-15119A. Hanley requests clear direction on this

question, as the government's requirement for prompt

delivery seems to be at odds with the Governments [sic]

desire to use Plymouth tubing, without achieving any

demonstrated improvement in quality.

Hanley submitted documentation in support of the Webco

FAT requirement on 5/27/08. Hanley requests that the

Government clarify in what way the documentation was

insufficient. (Reference Master Restart Index Items 14-16)

With respect to "d"; Revising procurement procedure to reflect flowdown of applicable

quality requirements, Hanley asserted:

Procurement procedures have been revised and submitted to

the Government QAR. Hanley requests that the Government

clarify in what way the documentation was insufficient.

Concerning the reference to the delivery schedule, Hanley has

pointed out a critical issue that must be resolved. Since a heat

lot of tubing may extend over several lots of Primers, and the

failure of one tube calls into question the entire heat lot, does

the government intend that every tube for the entire contract

be Hydrostatically tested before machining begins on any

tube? Otherwise a burst tube in Lot 8 could reject Lot 4 from

a year earlier. When the tube burst issue first came up, I

asked why not just throw the bad tube away and continue

production. The answer was that a burst tube could indicate

hydrogen embrittlement that could affect the entire heat. We

promptly sent samples to St. Louis Test Labs where the

definitive answer was given that there was no hydrogen

embrittlement. In response to further government questions,

further metallurgical testing was conducted. The test results

concluded that the failure was an anomaly. This information

was submitted to the government 5/5/08, and is apparently

still under review.

56

In consultations with Webco we have educated ourselves

about the methods of Non Destructive Testing (NOT) suitable

for tubing. There are two types, Eddy Current and Ultrasonic,

neither [of] which is a requirement of the contract. Eddy

Current is suitable for finding flaws of some types, but not of

the type that was encountered in Lot 2. Ultrasonic is suited

for the type of flaw that was encountered; however it cannot

be used on such a small tube as we are using. Webco and

Hanley have developed a plan by which the tubing can be

ultrasonically tested before being drawn down to the final

diameter. This testing is available as an option from the

vendor, starting with Lot 4, and the government may want to

consider including this testing in the specification.

In effect, Hanley provided the CO with little new information, preferring to recycle

arguments and data which it had already forwarded to the government. (R4, tab 243)

60. On 16 July 2008, the CO forwarded to Hanley her determination to terminate

its contract for default. She wrote, in pertinent part:

Reference:

a. Contract No. W52P1J-05-C-0076

b. Letter. HQ, Army Sustainment Command, subject:

Show Cause letter, dated 02 June 2008.

c. Letter, Hanley Industries, Inc. not dated, received

electronically June 13, 2008 Re: Show Cause Notice;

Contract Number W52P1J-05-C-0076

d. Request for Deviation (RFD) for Primer, Electric

MK 45 MODI, RFD No. 0076-D-0023, dated 02 May 2008,

Procuring Activity Number R08U7038 entitled: Material

Certification Change for Lot 2 Primer Tubes (enclosure)

The Government has reviewed Hanley Industries, Inc.

response to the Government's Show Cause letter, which was

provided in the Hanley Industries letter in reference c. above.

The Government has also reviewed and considered all

information and matters relevant to the Show Cause. As a

result of this review, it is the determination of the Contracting

57

j

Officer that the above referenced contract is hereby

terminated for default, pursuant to the Default Clause

52.249-8 of the contract. The reasons therefore and further

instructions in regard to the Default action are set forth below.

I. Review and Relevant Facts.

As a result of this review, the following is the

Government's response to the assertions in referenced c.

letter. The assertions of Hanley Industries are shown in the

bold print, followed by the Government position:

a. Primer Tubes met the .003 requirement and

measured with Government oversight and meet the

drawing requirements. Hanley Industries has not provided

objective evidence that all tubes were Hydrostatic tested in

accordance with MIL-T-15119A (OS) and met all the

requirements nor provided the Government revised work

procedures to ensure Hydrostatic Test would be performed on

new material in accordance with MIL-T-15119A. This would

include providing objective evidence that all tubes met the

expansion requirement ofMIL-T-5119A that none of the

tubes expand more than 0.003 inches after hydrostatic testing.

Hanley cites their outer diameter maximum after grinding is

0.763 +/- 0.001 and their lower specification limit after

grinding at 0.762. Contractor has not provided any objective

evidence that proves all tubes met the 0.762 limit (100%

inspection data not provided), and a maximum growth after

testing of 0.765. The snap gage at Gormac was set at 0.765.

Hanley did not test/inspect in accordance with paragraph 4.9

ofMIL-T-15119A. An unknown quantity oftubes could

have been less than 0.762; therefore, the data presented is not

acceptable. It has not been shown that tubes comply with the

0.003 requirement ofMIL-T-15l19A paragraph 3.7. Banner

provided data demonstrating conformance with the diameter

specification .763 +/- .001. This data was not taken with

approved procedures using approved AIE. To date Hanley

has not provided the Government revised work procedures to

ensure Hydrostatic Test would be performed on new material

in accordance with MIL-T-15119 A which is a condition for

restart of production.

58

b. Revised Acceptance Inspection Equipment (AIE)

has been submitted for Government approval. The

Government has reviewed Hanley's AIE submission dated

May 28, 2008 and it only provided Gormac's work

instructions (procedures) and make and model of the

equipment Gormac used during the investigation of the

ruptured tube. It failed to specifically identify all equipment

used to perform and verify the hydrostatic test requirement as

specified in MIL-T-15119A, as well as provide a detailed

procedure and log sheet for this characteristic. Hanley also

failed to submit AIE approval for two hydrostatic test

machines used at Gormac.

c. Hanley did purchase tubes from vendor that had

not been pre-qualified by the Government, however, in no

way was related to the critical failure. Government disagrees

with Hanley's assertion that changing the vendor was not

related to the critical failure. Hanley purchased tubes without

the Government's knowledge from an unqualified vendor that

produced the critical failure. The purchased steel tubing used

in production was not certified to MIL-T-l 5 l l 9A. Hanley has

not qualified Webco or any other steel supplier via the First

Article Test (FAT) process per FAR Clause 52.209-4511, First

Article Test (Government Testing).

d. Hanley has revised procurement procedures to

ensure flowdown of applicable quality contractual

requirements. DCMA QAR issued a Level II

Corrective Action Report (CAR) 0076-006 in violation of

MIL-Q-9858, paragraph 5.2 Purchasing Data. Even though

Hanley has provided revised procedures that appear to be

adequate, to date, Hanley has not provided corrected purchase

orders for Government verification.

e. Lot 002 can be submitted by Hanley 2 weeks

after restart approval. The Government provided Hanley

conditional restart to utilize new material. To date, Hanley

has not provided a revised delivery schedule. Hanley's

assertion that they can deliver 2 weeks after restart is

contingent upon obtaining Government approval to use

material purchased from Webco. Per letter dated April 7,

59

2008, the Government stipulated the conditions that Hanley

would need to meet in order to gain Government approval to

use material utilized in Lot 002 from Webco as follows:

( 1) Prepare root cause analysis of critical failure[.]

(2) Provide documentation of traceability of all Heat

Lots in Lot 002[.]

(3) Provide documentation that all tubes were

Hydrostatic tested in accordance with contract which requires

diametrical measurements to be taken b~fore and after

Hydrostatic Testing.

(4) Qualify Webco as a supplier via a modified First

Article Test[.]

(5) Submit Requests for Deviation to get approval for

the steel purchased to AMS-T-6736 in lieu of contract

requirement ofMIL-T-15119A and to allow the use of

multiple heat lots within Lot 002 of primers.

Hanley has failed to provide the required objective evidence

needed to gain Government approval to use the Webco

material for the following reasons:

a. Hanley's corrective action report provided in

response to the critical failure involving Webco tubing was

insufficient in identifying root cause and subsequent

corrective action. The root cause analysis failed to investigate

the supplier or foundry that produced the steel billets. Hanley

has not thoroughly evaluated the foundry processes therefore,

root cause analysis of the non-metallic inclusion is

incomplete. As result of this omission, Hanley has failed [to

provide] adequate root cause and corrective action for the

critical failure.

b. Hanley has failed to adhere to sampling

requirements ofMIL-T-15119A (OS); MIL-P-18714D,

paragraph 4.5.1 Lot Formation; and MIL-Q-9858A paragraph

3 .4 Records, as Lot 002 contains up to four known heats of

primer tubes (two Webco heat lots and two Plymouth heat

lots) and Hanley is unable to provide objective evidence to

determine/distinguish the heat lots of the entire quantity of

primer tubes in Lot 002.

60

j

c. As stated in paragraph la. above, Hanley Industries

has not provided objective evidence that all tubes were

Hydrostatic tested in accordance with MIL-T-15119A (OS)

and met all the requirements.

d. Hanley failed to qualify Webco as a supplier.

e. The RFD to obtain Government approval for steel

purchased to an alternative specification (0076-D-0023Rl)

is disapproved (see enclosure) as none of the proposed

alternative specifications would meet the required mechanical

properties required. Hanley has not submitted an official

copy of the RFD to allow use of multiple heat lots to the

Government.

As a result ofHanley's continued persistence on restarting

production with Webco material, Hanley's inability to provide

a realistic schedule is directly tied to their failure to meet the

conditions of production restart and makes them incapable of

meeting their proposed delivery of 2 weeks after restart.

Included in their response, Hanley also posed the

following question to the Government:

"Since a heat lot of tubing may extend over several

lots of Primers and the failure of one tube calls into

question the entire heat lot, does the Government intend

that every tube for the entire contract be Hydrostatically

tested before machining begins on any tube?"

The Government does not dictate production processes. The

requirements for hydrostatic testing is [sic] provided in

MIL-T-15119A, paragraph 3.7 Hydrostatic Test Cl, (Cl

designation means that this requirement is critical defect 1

and therefore must be 100% inspected) and paragraph 4.9

Hydrostatic Test. It is Hanley's responsibility to develop the

process for meeting these specification requirements.

II. Government Termination Decision

Based upon Hanley Industries failure to show the

Government reasonable cause not to terminate their contract

61

for default, this letter is a Notice of Termination of Contract

Number W52PIJ-05-C-0076 awarded September 29, 2005 to

Hanley Industries, Inc., for the remaining quantity of 84,630

MK.45 Electric Primers for a total dollar amount

$4,327,743.76. The Government exercises its right under

contract clause 52.249-8 Default (Fixed-Priced Supply and

Service) of the aforementioned contract. The act of failing to

deliver in accordance with the contract schedule, provide

supplies that conform to the TDP, use of approved vendors,

and to meet the criterion for quality in the subject contract

which is a failure to meet the following provisions in Hanley

Industries contract:

a. Higher Level Contract Quality Requirement

(Government Specified) 52.246-4550 (Feb 2004)

b. MIL-T-15119A(OS) dated October 20, 1976

c. Drawings/Specifications (Government Specified)

52.210-4501(March1988); TDP for the MK-45 Electric

Primer, 2434755K

d. Statement of Work for Statistical Process Control

(Government Specified) 52.246-4506 (Feb 1999)

e. First Article Test (Government Test) (Government

Specified) 52.209-4511(May1994)

f. Acceptance Inspection Equipment (AIE)

(Government Specified) 52.245-4537 (Feb 2002)

g. Contract Data Requirements List (CDRL) AOlO

Test/Inspection Reports, First Article Inspection & Test,

Identification Number DI-NDTI-80809B

h. MIL-P-18714D, 24 January 1994

i. Section B Delivery Schedule - Modification POOO 10

j. MIL-Q-9858A dated March 15, 2004

Hanley Industrie' s [sic] failure to meet the criteria listed

above violated the terms of their contract and thereby

constitutes the default.

(R4, tab 249)

61. This timely appeal followed.

62

DECISION

The law in this area is well settled. A default termination is "a drastic sanction

which should be imposed ... only for good grounds and on solid evidence." J.D.

Hedin Construction Co. v. United States, 408 F.2d 424, 431 (Ct. Cl. 1969) (citations

omitted). Accordingly, the government bears the burden of proving that the

termination was justified. If the government establishes a prima facie case in this

regard, the burden of production-or going forward-shifts to the contractor. Lisbon

Contractors, Inc. v. United States, 828 F.2d 759, 764-65 (Fed. Cir. 1987); New Era

Contract Sales, Inc., ASBCA No. 56661 et al., 11-1BCAif34,738 at 171,022. Here,

the government has met its burden.

Initially, the Board notes that Hanley failed to meet the delivery date of 22 April

2008 for production lot 2 which was set forth in Modification No. POOOlO (finding 36).

The government had previously extended the delivery dates for both the FAT and

production lot 1 multiple times (findings 23, 27-30). Similarly, the government had

extended, on several occasions, the delivery date for production lot 2 from 28 November

2006 to 22 April 2008 (findings 29, 30, 36).

Although, as executed, Modification No. POOO 10 was unilateral, the revised delivery

date was contained in a spreadsheet which Hanley itself prepared and which was forwarded

to the CO for incorporation into the modification (finding 36). Because the revised

delivery date was proposed by Hanley in its spreadsheet, it was "both reasonable and

specific from the standpoint of the performance capabilities of the contractor." McDonnell

Douglas Corp. v. United States, 323 F.3d 1006, 1019 (Fed. Cir. 2003).

The CO gave Hanley more than adequate notice of the reasons underlying the

default termination. On 19 March 2008, she approved a conditional restart of the

primer production even though she was under no contractual obligation to do so. The

CO referred to gaps in Hanley's hydrostatic testing procedures. In addition, she

stressed that Webco was not an approved tube supplier and that Hanley needed to pass a

modified FAT ifit desired to use Webco's tubes. (Finding 54) Hanley did not comply

with these requirements in its CAR of 26 March 2008 (findings 55-56). On 7 April

2008, the CO informed Hanley that its report was insufficient. She rejected the Webco

tubing, but once again, stated the prerequisite conditions for its acceptance. These

included preparing a root cause analysis of the critical tube failure, providing

documentation of traceability of all heat lots in production lot 2, and qualifying Webco

as a vendor through a modified FAT. (Finding 56) In a response of23 April 2008,

Hanley simply stated that it intended to use Webco as a tube supplier (finding 57).

On 2 June 2008, the CO replied by issuing a show cause letter in which she stated that

Hanley had failed to "cure the conditions endangering performance" under the contract.

She, once again, referred to the need for a modified FAT, government approval of

63

Hanley's AIE for hydrostatic testing, the need for appropriate hydrostatic testing, and

the flowdown of adequate quality requirements to subcontractors. The CO gave Hanley

10 days to cure these deficiencies. (Finding 58) On 14 June 2008, Hanley responded to

the cure notice, for the most part, by referring to information which it had previously

forwarded to the CO and which she had already deemed to be inadequate (finding 59).

Accordingly, the CO acted reasonably in terminating the contract for default on 16 July

2008 (finding 60).

Hanley makes a host of arguments designed to show that the default was improper.

Initially, we simply note that its repeated references to other contracts performed either

by itself or by other contractors are misguided. Testimony regarding other contracts is

simply irrelevant to the issues of contractual performance raised by the termination of

this contract.

The Board also disagrees with Hanley' s contention that the CO acted

unreasonably by declining to accept Webco as an alternate vendor (app. br. at 59-63).

Hanley never complied with the reasonable steps set forth by the CO to qualify Webco.

Further, the CO was acting responsibly when she demanded strict compliance with

contractual specifications. Mission Valve and Pump Co., ASBCA Nos. 13552, 13821,

69-2 BCA iJ 8010 at 37,243.

We also reject Hanley's belated argument that its difficulties were the result of the

government's defective technical data package (app. br. at 65). This issue was not raised

during contractual performance. The Board also notes that Hanley successfully

completed production of the FAT and lot 1, using the package at issue.

Hanley's argument that the CO acted in bad faith is also unfounded (app. br. at

66-68). As we have concluded, the CO acted reasonably in defaulting the contract after

Hanley failed to cure it deficiencies. Further, the record contains no evidence of bias

against Hanley by any government official. See Am-Pro Protective Agency, Inc. v.

United States, 281F.3d1234, 1240 (Fed. Cir. 2002).

We have carefully reviewed Hanley's other contentions and reject them.

64

CONCLUSION

The appeal is denied.

Dated: 12 August 2014

MICHAEL T. PAUL

Administrative Judge

Armed Services Board

of Contract Appeals

I concur I concur

~~~Apd --

Administrative Judge Administrative Judge

Acting Chairman Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA No. 56584, Appeal of Hanley

Industries, Inc., rendered in conformance with the Board's Charter.

Dated:

JEFFREY D. GARDIN

Recorder, Armed Services

Board of Contract Appeals

65

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.