Opinion

K-Con Building Systems, Inc. v. United States

  • 115 Fed. Cl. 558
  • 2014 U.S. Claims LEXIS 135
  • 2014 WL 1348155
Court
United States Court of Federal Claims
Filed
Apr 7, 2014
Status
Published
Author
Sweeney
On the bench
Margaret M. Sweeney
Cited by
3 cases
Authority
More cited than 46.8%

“The notice requirement contained in the contract’s changes and suspension of work clauses ... is flexible; and [the government] has not demonstrated that it was prejudiced by the timing of [the contractor’s] notice.” (citing Hoelr-Steffen Constr. Co. v. United States, 456 F.2d 760, 768 (Ct.C1.1972))

How later courts described this case

  • “The notice requirement contained in the contract’s changes and suspension of work clauses ... is flexible; and [the government] has not demonstrated that it was prejudiced by the timing of [the contractor’s] notice.” (citing Hoelr-Steffen Constr. Co. v. United States, 456 F.2d 760, 768 (Ct.C1.1972))

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

No. 05-981C

(Filed: April 7, 2014)

*************************************

K-CON BUILDING SYSTEMS, INC., *

* Cross-Motions for Summary Judgment;

Plaintiff, * Contract to Design and Build Prefabricated

* Building; Compulsory Counterclaim;

v. * Contract Disputes Act of 1978; Excusable

* Delay; Critical Path; Changes; Suspension

THE UNITED STATES, * of Work

*

Defendant. *

*************************************

William A. Scott, Charleston, SC, for plaintiff.

Daniel B. Volk, United States Department of Justice, Washington, DC, for defendant.

OPINION AND ORDER

SWEENEY, Judge

Plaintiff K-Con Building Systems, Inc. filed three suits in this court concerning its

contracts with the United States Coast Guard (“Coast Guard”) for the design and construction of

prefabricated metal buildings in Elizabeth City, North Carolina, St. Petersburg, Florida, and Port

Huron, Michigan. After the court issued summary judgment rulings in each case and held trial in

the Elizabeth City case, the parties engaged in settlement discussions. Those discussions

revealed several issues that required resolution prior to any settlement. Accordingly, the parties

have filed the relevant motions in all three cases.

In this case, which concerns the building in St. Petersburg, plaintiff moves for partial

summary judgment on the issue of liquidated damages, and defendant cross-moves for summary

judgment on all of plaintiff’s remaining claims. For the reasons set forth below, the court denies

both motions.

I. BACKGROUND

In April 2001, the United States General Services Administration (“GSA”) awarded

plaintiff a Federal Supply Schedule contract for Prefabricated Structures and Outdoor Smoking

Shelters.1 Subsequently, in the summer of 2003, the Coast Guard solicited a proposal from

plaintiff for the design and construction of a prefabricated structure to serve as a supply

warehouse in St. Petersburg. The Coast Guard divided the warehouse project into three

components: a base item and two options items. The base item consisted of the design and

construction of the warehouse, and included all site work, utilities, and parking. The option

items concerned the construction of additional facilities within the warehouse. The Coast Guard

awarded the contract to plaintiff on September 5, 2003, but due to funding issues, only the base

item was awarded. Along with other standard clauses, the contract contained clauses pertaining

to changes, differing site conditions, suspension of work, and liquidated damages. Of particular

interest in this case is the liquidated damages clause that provided for liquidated damages in the

amount of $564 for each day that plaintiff failed to complete the building beyond the

contractually specified completion date, which, on the date of contract award, was July 26, 2004.

A. Contract Performance

1. Design Submissions

The contract award triggered deadlines related to construction bonds, project schedules,

project meetings, the commencement of work, and the initial design submission. On October 15,

2003, after approving plaintiff’s bonds, the Coast Guard permitted plaintiff to begin work at the

job site. Shortly thereafter, on November 4, 2003, the Coast Guard conducted a delayed

postaward kickoff meeting with plaintiff. During the meeting, the participants discussed a

variety of issues related to the design documents that plaintiff would provide to the Coast Guard.

In addition, plaintiff informed the Coast Guard that its geotechnical firm had begun its site

investigation, and that it had hired both an architect and a firm to produce the site work and civil

work designs.

Pursuant to the contract specifications, plaintiff was required to present to the Coast

Guard a schedule that reflected plaintiff’s submission of the design in three phases (a “50%

design,” a “100% design,” and a “final design”). In the schedule it submitted to the Coast Guard

on November 7, 2003, plaintiff indicated that it had begun working, to an unspecified extent, on

the 50% design on October 16, 2003–the day it likely received the Coast Guard’s notice to

proceed–and planned to submit it to the Coast Guard around November 14, 2003. In that same

schedule, plaintiff indicated that it anticipated beginning construction on December 29, 2003,

1

The court derives many of the facts in this section from its November 30, 2012 Opinion

and Order, K-Con Bldg. Sys., Inc. v. United States, 107 Fed. Cl. 571 (2012). The balance of the

facts are derived from the appendices filed in conjunction with defendant’s current motion for

summary judgment (“Pl.’s 2nd App.” and “Def.’s 2nd App.”) and the appendices filed in

conjunction with the parties’ briefing on the original motions for summary judgment (“Pl.’s

App.,” “Pl.’s Supp’l App.,” and “Def.’s Supp’l App.”); citations to those documents are set out

in footnotes. Only the facts relevant to the parties’ present motions are included.

-2-

erecting the building beginning on March 22, 2004, and completing the project around May 27,

2004–two months before the contract completion date.

Plaintiff did not meet its self-imposed November 14, 2003 deadline for submitting the

50% design to the Coast Guard. Instead, it appears that plaintiff submitted the 50% design

shortly after December 10, 2003. In a January 6, 2004 letter, the Coast Guard noted several

issues with the design that required plaintiff’s attention before it could conduct its official

review. These issues included electronic files that did not comply with computer-aided-design

requirements, incomplete drawing sets, systems missing from the drawings, and missing

calculations for the foundation design. To address the Coast Guard’s comments, plaintiff was

required to have its designer redesign the foundation, which entailed making new calculations

and amending its drawings.

Plaintiff resubmitted a complete 50% design on February 2, 2004, and its foundation

calculations on February 3, 2004. The Coast Guard approved the design three days later.

Plaintiff then submitted its 100% design on February 25, 2004. In a cover letter to its review

comments, the Coast Guard noted that it “consider[ed] the design, especially the Structural

design, incomplete” and requested that plaintiff make corrections.

2. Construction Begins

Pursuant to the contract specifications, plaintiff could not begin construction until the

Coast Guard approved the final design. That approval occurred some time before April 6, 2004,

when plaintiff and the Coast Guard conducted a preconstruction conference. Plaintiff ultimately

began mobilizing for construction on May 1, 2004, with actual construction beginning during the

week of May 10, 2004.

Upon the commencement of construction, plaintiff began work on the building’s

foundation. According to an as-built schedule included with defendant’s expert’s report, plaintiff

performed its initial work on the foundation from May 13 to May 24, 2004; poured the footings

from May 24 to June 1, 2004; poured the walls from June 1 to June 11, 2004; and completed the

foundation from June 11 to June 26, 2004.2 The progression of work reflected in this as-built

schedule was a departure from what plaintiff had initially planned when it began construction.

As early as May 13, 2004, plaintiff had anticipated completing the foundation by June 1, 2004,

the date that it had scheduled an order for concrete to arrive on the job site.3

2

See Pl.’s App. 444. The record does not contain the documents from which defendant’s

expert took these dates, such as an updated progress schedule or daily construction reports.

However, defendant’s expert cites some supporting documents in several footnotes in the body of

his report. See id. at 434-35.

3

See Def.’s 2nd App. 1.

-3-

During a June 15, 2004 progress meeting, plaintiff and the Coast Guard discussed several

issues related to constructing the foundation, pouring the slab, and erecting the building.4 One

issue discussed was plaintiff’s late start on construction. Because of this late start, the Coast

Guard considered most remaining items on the project schedule as being on the critical path of

performance. Then, with respect to the foundation and slab, the Coast Guard expressed its

concern that plaintiff was “not following proper construction practices at the jobsite especially

regarding the building slab and foundation,” noting that its “[i]nspector had to reject two concrete

trucks last Friday (6/11/04) as they sat around the jobsite over two hours because [plaintiff] was

not ready to use the concrete in the trucks.”

In addition, the Coast Guard addressed plaintiff’s plan to alter its sequence of

construction. Initially, as reflected on the structural drawing included with its final design,

plaintiff planned to erect the building on the foundation after pouring the slab. But, due to a

concrete shortage arising from the large amount of construction occurring in central Florida,

plaintiff sought to reverse the sequence and pour the slab after erecting the building. Plaintiff

indicated that many contractors in the area were being forced “to implement [nontraditional]

construction sequences” due to the concrete shortage. Indeed, the Coast Guard acknowledged the

effect the concrete shortage would have on the project, remarking that the project might not be

completed by the July 26, 2004 contract completion date because the lead time for getting

concrete on site was three weeks, and no loads could be placed on the poured concrete until it set,

which typically took seven days or longer. Nevertheless, it concluded that the building could not

be erected without the slab in place, and therefore advised plaintiff that it was required to pour

the slab before erecting the building.

Further complicating matters, the Coast Guard also informed plaintiff during the progress

meeting that there was no space available on the job site to store the building before plaintiff was

ready to erect it, and that plaintiff would have one week in which to store and erect the building

once it arrived on site. Plaintiff had originally scheduled three weeks for this process.

Two days after the progress meeting, on June 17, 2004, plaintiff requested by letter an

extension of the contract completion date to August 26, 2004, to accommodate the concrete

shortage, explaining that it could not obtain the quantity of concrete it needed until July 9, 2004.

Plaintiff retracted this request one week later.5

The concrete shortage was not the only issue facing plaintiff during this period of time;

plaintiff was also encountering unexpected ground water during its work on the job site.

Pursuant to the contract specifications, plaintiff was to assume “[f]or bidding purposes” that the

4

See Pl.’s App. 264-66.

5

See Def.’s 2nd App. 5.

-4-

“depth of the groundwater table [was] four feet below grade or deeper.”6 In a June 18, 2004

letter, plaintiff notified the Coast Guard that it encountered ground water when it attempted to

install an underground storm line. It indicated that it would cost an additional $4,097 to remove

the water from the area using stone and a gas-operated pump, a process it called “dewatering,”

and accordingly requested an increase in the contract price. The Coast Guard provided two

responses to plaintiff’s request. First, Steve Allen, the Coast Guard’s project manager, advised

plaintiff in a June 18, 2004 electronic-mail message that the water plaintiff encountered was not a

differing site condition,7 explaining (footnote added):

The geotech report (dated 7/25/03) furnished by the Government as part of the

RFP noted that you would experience groundwater at elevation 3 (your report

dated 11/10/03 notes “seasonal high groundwater table will be encountered at a

depth of three feet below existing site grades”).8 Can’t tell from your photo what

elevation you’re experiencing ground water, but your company should have

allowed for dewatering in your bid if you are digging 3 feet below grade.

Then, in a June 21, 2004 letter, Cathy Broussard, the contracting officer, advised plaintiff that it

“should have known” that ground water existed because it was identified in the July 25, 2003

geotechnical report provided to plaintiff as part of the proposal request package.9

Despite these two responses from the Coast Guard, plaintiff resubmitted its request for a

contract modification on June 22, 2004,10 explaining:

The bid documents under Section 1.6 Geotechnical Design, subsection

1.6.3 state “depth of groundwater is four feet below grade or deeper.[”] Utilizing

this information we did not anticipate utilizing any dewatering or well pointing

system. Had we done so the bid price would have increased as much as Twenty

or Thirty Thousand Dollars.

The same holds true after our geotech report was completed.

In the best interest of the government, K Con, Inc. held the request for

modification with the knowledge that . . . dewatering the entire site would cost

6

Pl.’s App. 150.

7

See Def.’s 2nd App. 2.

8

Neither the July 25, 2003 geotechnical report nor plaintiff’s November 10, 2003 report

is part of the record before the court.

9

Def.’s 2nd App. 3.

10

See Pl.’s Supp’l App. 45.

-5-

considerably more than dewatering specific areas as per our request. Hence K

Con, Inc saved the government more than Twenty Thousand Dollars using this

approach.

In addition to the monetary compensation it previously sought, plaintiff requested a ten-day

contract extension. Mr. Allen responded to plaintiff’s request that same day, informing plaintiff

via electronic mail that the Coast Guard disagreed with plaintiff’s assessment of the situation.11

He noted that he received the following report from the Coast Guard’s on-site inspector:

The storm pipe and trench from the parking lot side and under the building

are basically dry. On the Air Field side which is the low point elevation wise.

[sic] The site contractor is using a sump pump to keep dry. There [are] currently

no well points (dewatering) being utilized. In talking with the Superintendent, no

well points (dewatering) [are] required nor planned. In regards to a claim, I

concur with your e-mail declining unforeseen site conditions. Although I have not

reviewed the Geotech report, the seasonal [high water] table was identified and

the scope of work as illustrated on sheet c102 indicated that the storm pipe work

would be below elevation 3'. In my opinion, a sump pump for a few days should

be incidental to the work. If we had had rain when the footing trenches were

open, a sump pump would also have been required to remove water prior to

concrete placement.

Mr. Allen stated his agreement that dewatering and well points were unnecessary and, therefore,

plaintiff was not incurring additional costs.

Approximately one week later, on July 1, 2004, plaintiff sent the Coast Guard a progress

schedule via electronic mail. As noted in the accompanying message, the schedule reflected a

planned completion date of August 26, 2004, which was one month after the contract completion

date. The Coast Guard acknowledged plaintiff’s submission and further noted that the new,

delayed completion date would result in the assessment of liquidated damages. Plaintiff

responded that it would “not accept responsibility for the delay” because the delay resulted from

the Coast Guard’s modification of plaintiff’s “construction method.” It specifically referred to

the request for a contract modification that it had submitted earlier in the day. In that request,

plaintiff sought an additional $5,100 and ten days for the removal of ground water it encountered

when installing the storm drainage pipe. Plaintiff also sought an additional $16,500 and thirty

days for not being permitted to erect the building before pouring the slab, not being permitted to

store and erect the building over the course of three weeks, and its inability to schedule concrete

with any certainty due to the concrete shortage. Thus, in total, plaintiff sought an additional

$24,100 and forty days for performing work under the contract.

11

See Pl.’s Supp’l App. 44.

-6-

As noted previously, plaintiff had informed the Coast Guard on June 19, 2004, that it had

scheduled a delivery of concrete for July 9, 2004. However, on July 6, 2004, the Coast Guard

informed plaintiff that it could not proceed with pouring the slab because the “workmanship and

quality of the footings, concrete work, [and] anchor bolts” were unacceptable. Later that day,

Luther Ramsey, plaintiff’s project manager, responded:12

This concrete was in place and visible the day we held an on site progress

meeting (June 15) attended by Mr. Allen, [the Coast Guard’s inspector, and

plaintiff]. I was aware of the finish appearance and planned to do cosmetic work

when the next pour was scheduled. It is not reasonable to notify us three weeks

later and 48 hours prior to a scheduled critical task that the work is unacceptable.

I have a pour scheduled for Friday at 5 AM. I am exploring all the options and

ramifications of this notice. I will correspond my findings tomorrow as soon as I

have the engineer[’s] response. If I have to cancel the pour due to this issue

[plaintiff] will be requesting a time extension due to same.

Indeed, in a November 2013 affidavit, Mr. Ramsey reiterated that the “alleged defective work”

noted by the Coast Guard “could be corrected or completed as the work progressed, was

insignificant, and did not require resubmittal and approval of any drawings.”13

Communications between plaintiff and the Coast Guard regarding the concrete work

continued. On July 8, 2004, the Coast Guard advised plaintiff that it would not authorize any

concrete pours until it had “received and approved” plaintiff’s “deviations for the slab and

concrete work.”14 That same day, plaintiff responded that the Coast Guard’s “late review of the

construction” made it “impossible to pour the slab on July 9,” indicated that it had rescheduled

the pour for July 16, 2004, “the next available day,” and advised that it would be requesting a

fourteen-day contract extension as a result of the delay.15 Between July 9 and July 16, 2004,

plaintiff’s concrete subcontractor repaired hairpins and columns, drilled holes, cut rebar for

control joints, and replaced expansion joints on columns.16 Ultimately, the Coast Guard

authorized the pouring of the slab on July 15, 2004.

12

Pl.’s Supp’l App. 50.

13

Pl.’s 2nd App. 103.

14

Def.’s 2nd App. 10.

15

Pl.’s Supp’l App. 13.

16

See Def.’s Supp’l App. 17-28.

-7-

On July 26, 2004, plaintiff submitted to the Coast Guard another request to modify the

contract, seeking an additional seventy-one days and $34,300.17 Plaintiff broke down this request

into several components. First, it sought additional time and compensation for the delays that

were the subject of its July 1, 2004 modification request: it sought thirty days and $19,000

related to the sequence of construction, the storage of the building, and the concrete shortage; and

ten days and $5,100 related to the removal of ground water. Second, it requested an additional

twelve days and $8,000 related to the commencement of construction, explaining (footnote

added):

K-Con is a Design/Build firm in which construction starts after the 35% design

approval. This duration was originally proposed and budgeted but K-Con was

unable to start construction until 100% design approval was made.18 This is not

the proposed Design/Build method nor was it budgeted. This delay[] occurred

between 16 October 2003 and 05 February 2004.

Third, it sought an additional fourteen days for the concrete placement delay, explaining that it

was forced to reschedule the concrete placement because the Coast Guard’s inspector, who was

“aware of the first concrete placement on 15 June 2004[,] did not notify [it] until three weeks

later and 48 hours prior to a known scheduled critical task that the work was unacceptable.”

Finally, it requested an additional five days and $2,200 for encountering previously unknown

conditions during the excavation of utilities.

The Coast Guard denied all but plaintiff’s last request in a July 28, 2004 letter signed by

Ms. Broussard.19 With respect to the Coast Guard’s refusal to allow plaintiff to erect the building

before pouring the slab, Ms. Broussard noted that plaintiff’s proposal was a deviation from the

approved drawings. Thus, she indicated, to change the order of construction, plaintiff should

have revised the drawings, obtained approval from its designer of record, and submitted the

designer’s approval to the Coast Guard. Next, concerning plaintiff’s removal of ground water,

Ms. Broussard indicated that the Coast Guard’s position had not changed because the July 25,

2003 geotechnical report indicated that “water could be expected at approximately -4 feet below

grade.” Then, addressing plaintiff’s contentions regarding it being unable to begin construction

before a 100% design was approved, Ms. Broussard remarked that the prerequisites for

commencing construction were clearly set forth in the contract specifications, explaining

(footnote added):

17

See Pl.’s Supp’l App. 33-35.

18

Although plaintiff refers to a “100% design approval,” the contract specifications

indicated that construction could not begin until the final design was approved.

19

See Pl.’s Supp’l App. 54-55.

-8-

[The contract specifications] clearly identified submittals, their review processes,

and the requirement that construction could not begin until the final design had

been reviewed and approved. Your proposal was . . . based on these contract

requirements. In addition, our telephone conference of 21 August 2003 . . .

discussed [sic] various aspects of the contract requirements including design

submittals. My records do not indicate any specific concerns with our submittal

requirements. A follow-up letter dated 29 August 2003 . . . did not list submittals

as one of the exceptions to the proposal.20

With respect to plaintiff’s inability to pour the slab on July 9, 2004, Ms. Broussard noted that the

Coast Guard expressed concern about the quality of the foundation during the June 15, 2004 site

visit and that two concrete trucks were rejected on June 11, 2004, because they sat too long

waiting for plaintiff to be ready for the pour. Finally, Ms. Broussard requested additional

information regarding the previously unknown water pipes plaintiff encountered during utility

excavation.

Plaintiff, in turn, responded to the Coast Guard in an August 9, 2004 letter.21 Of

particular note, it addressed Ms. Broussard’s comments regarding its inability to commence

construction during the design process:

[The Coast Guard] states that our proposal was based upon the contract

requirements when in fact the opposite is true. Our proposal was in lieu of the

unreasonable and costly specifications that would result in a price nearest to the

next bidder. Additionally we have no record of a telephone conference . . . on 21

August 2003. Therefore our request for 12 additional days and $8,000.00 in

extended overhead for design still remains.

Plaintiff also provided Ms. Broussard with the following “‘new’ information” regarding its

dewatering claim: “To meet the negotiated pricing K-Con did not include continuous

de-watering of the entire site. Understanding [the Coast Guard] would recognize a tremendous

savings in de-watering only when conditions required it. [sic]” In addition, plaintiff provided

information related to the unexpected water pipes it encountered during construction.

Ms. Broussard responded to this latest letter from plaintiff on August 11, 2004.22 With

respect to the proposal-versus-contract issue, she wrote:

20

The August 29, 2003 letter is not in the record before the court.

21

See Pl.’s Supp’l App. 56-57.

22

See Pl.’s Supp’l App. 98-99.

-9-

Your letter of 15 August 2003 . . . outlined your proposal and highlighted the

exceptions to the contract document. Receipt of this document triggered our

telephone conference call . . . on 21 August 2003. As stated previously, this

conversation reviewed [sic] the specification requirements and K-Con’s

assumptions in the proposal. We specifically discussed topographic, permitting

requirements, paving, grading, and your desire to use concrete in lieu of asphalt.

We also discussed the silt fence, telecommunication, GF Cable, Sheet A101

plumbing and sanitary lines, sprinkler system requirements and . . . design

submittals. Your . . . letter dated 29 August 2003 . . . specifically states “The

work performed and price herein will be in accordance with the drawings and

specifications provide[d] by [the Coast Guard], with the exception of those items

excluded and/or clarified below:” Three exceptions were listed: Asphalt, Fiber

Optic Cable and Plumbing Stub-ups. As stated in my letter of 28 July 2004, [the

contract specifications] clearly identified submittals, their review processes, and

the requirement that construction could not begin until the final design had been

reviewed and approved. Your proposal should have been based on these contract

requirements.

Ms. Broussard also addressed plaintiff’s “new” information concerning its dewatering claim:

As previously stated in my letter[s] of 21 June 2004 and 28 July 2004, you were

given a copy of the Geotech report dated 25 July 2003 in your Request for

Proposal package. It specifically stated water could be expected at approximately

-4 feet below grade. Since you have not provided any new information, our

position remains unchanged.

Finally, Ms. Broussard granted plaintiff’s request for additional compensation related to the

unexpected water pipes. The parties executed a contract modification on August 23, 2004,

increasing the contract price by $4,500 (to a total of $539,430), but leaving the contract

completion date unchanged.

While plaintiff was pursuing its contract modification requests with the Coast Guard,

work was continuing on the job site. The building was delivered on July 14, 2004, and plaintiff

began to erect the building on August 9, 2004.

3. Hurricane Season

Unfortunately for both plaintiff and the Coast Guard, construction was hindered by four

hurricanes that affected central Florida during the summer of 2004. The first

hurricane–Hurricane Charley–affected the job site in August 2004. The parties executed a

contract modification on August 18, 2004, extending the contract completion date by fifteen

days–to August 10, 2004–for “unusually high rainfall during the month of July and Hurricane

Charley” and releasing the government from “from any and all liability under the contract for

-10-

further equitable adjustments attributable to such facts [or] circumstances giving rise to the

proposal for adjustment . . . .”

As of September 1, 2004, plaintiff anticipated completing the project by September 17,

2004. However, plaintiff’s plans were stymied by two additional hurricanes–Frances and Ivan.

According to Mr. Allen (footnote added):23

From 9/01/04 to 9/20/04 (counting weekends), Kcon weathered two

Hurricanes (Frances and Ivan). Frances (on 9/5) had mandatory evacuation of

[the] St Pete area on 9/2 and 9/3 plus[] all Labor Day weekend had rain (5 days

total).24 Hurricane Ivan struck the panhandle of Florida on 9/15, but did not

impact the St Pete area, although prior to Ivan’s potential arrival the site had to be

readied if Ivan struck. During the remaining period, 2 days of rain occurred over

the September average of 0.25" [per] day.

This narrative is consistent with plaintiff’s daily construction reports, which reflect that work was

not being performed due to Hurricane Frances; that Hurricane Frances caused “minor flooding in

trenches” on the job site; that work was affected by Hurricane Ivan; and that it rained during

portions of September 8, September 9, and September 16, 2004.25 On September 21, 2004, the

parties executed a contract modification, extending the contract completion date by sixteen

days–to August 27, 2004–for “unusually high rainfall during the month of August and

Hurricane[]s Frances and Ivan” and releasing the government from “from any and all liability

under the contract for further equitable adjustments attributable to such facts [or] circumstances

giving rise to the proposal for adjustment . . . .”

In addition to documenting the effects of Hurricanes Frances and Ivan, plaintiff’s daily

construction reports for September 2004 reflected the difficulties plaintiff was experiencing with

excessive ground water at the job site.26 On September 20, 2004, plaintiff noted: “During the

digging for the trench box, we had to dig past the footer and encountered a great deal of water

which created problems and began undermining the footers under the building foundation.” The

following day, plaintiff further reported:

[W]e have been working on the trench drain for 5 days. There was a problem

with excessive water and while digging the hole for the trench drain box, it was

23

Pl.’s App. 301.

24

In 2004, Labor Day weekend spanned from Saturday, September 4 through Monday,

September 6.

25

See Def.’s Supp’l App. 99-100, 102, 104-06, 108, 119.

26

See Def.’s Supp’l App. 105-06, 108, 119, 124, 126.

-11-

undermining the footers on the foundation of the building, so we used sheet piling

to prevent the undermining, put rock on the bottom of the trench drain, and used a

pump in a bucket to keep the water draining out.

On September 22, 2004, as a result of these difficulties, plaintiff submitted to the Coast Guard

another request for a contract modification for dewatering,27 seeking $3,800 and a seven-day

contract extension and explaining:

During the course of installing the trench drain sump K Con, Inc

encountered ground water. In order to complete this task K Con, Inc notified the

government of the problem via daily reports, and then proceeded with a

dewatering and shoring process in order to maintain a scheduled concrete

delivery. The task was critical to our overall construction schedule. This

condition is due to excessive rain in the area which has caused the water table to

rise.

The Coast Guard denied plaintiff’s request on September 27, 2004,28 stating (all errors in the

original):

2. The Geotech reports in your contract indicated groundwater could be expected

at -4' below grade. You have not provided documentation that indicates they were

encountering groundwater above -4' below grade.

3. Your designer of record’s C202 drawing detail (“Grate Inlet & Sump Pump

Detail”). The existing grade to match is at 7', detail C202 indicates that the sump

trench finished grade at 3.83' or (based on finished grade at 7') it is -3.17' below

grade or only a few inches above the -4' elevation that groundwater is expected to

be encountered. Some water will seep or appear into the bottom of the trench.

You should have expected some water removal when trenching so close to the

expected groundwater elevation.

4. Dewatering normally requires digging a hole (well points) in the ground, put a

barrel or similar with holes in it, near the trench, allow water to accumulate in the

barrel, then a pump is used to remove the water from the barrel and the water is

discharged far away via piping. Providing a pump to remove a small amount of

water in a trench due to rain from stopping concrete pours or men working is a

normal practice in Florida due to the rainy conditions encountered there.

27

See Pl.’s Supp’l App. 101.

28

See Pl.’s Supp’l App. 104.

-12-

5. Our inspector reports show a “3" pump on site and used for 1 day. No

dewatering well points installed.” As per your design drawings C103, note 2 that

reads:

“Although no dewatering activities are anticipated, all dewatering shall be

directed to a temporary pond area, adequately sized to contain the

dewatering flow with minimum discharge directed to the area of natural

discharge. The temporary dewatering pond shall be surrounded by

properly installed siltation screen with double siltation screen located at

the temporary dewatering pond discharge area.”

A fourth hurricane–Hurricane Jeanne–affected work on the job site in late September

2004, but the record before the court lacks any evidence that plaintiff sought any compensation

from the Coast Guard related to it.

4. Completion of the Building

On November 4, 2004, Mr. Allen scheduled a final inspection of the project for

November 10, 2004. Another inspection occurred on December 1, 2004, at which time the Coast

Guard accepted beneficial occupancy of the building.

On February 3, 2005, the Coast Guard assessed liquidated damages against plaintiff by

unilaterally amending the contract to reduce the contract price. Before that date, the contract

completion date had been extended, for reasons unrelated to the issues in the present motions,

from August 27, 2004, to September 2, 2004. Based on its December 1, 2004 acceptance of the

building, the Coast Guard assessed ninety days of liquidated damages, which, at $564 per day,

totaled $50,760. It therefore reduced the contract price to $488,670, depriving plaintiff of the

$52,260 that it would have been paid had the Coast Guard not assessed liquidated damages.

B. Procedural History

Plaintiff submitted a claim to Ms. Broussard on July 28, 2005, seeking the payment of

$51,260 that it alleges was wrongfully withheld by the Coast Guard as liquidated damages, plus

interest. Specifically, plaintiff contended:

The assessment of liquidated damages is not appropriate because [it] was not the

sole cause of any alleged delays, any alleged delays by [it were] concurrent with

delays caused by the government, the government failed to issue extensions to the

completion date as a result of changes to the contract by the government, and the

liquidated damages are an impermissible penalty.

It requested a final decision on its claim, but also noted that “the assessment of liquidated

damages is a claim by the government.” Ms. Broussard issued her decision on plaintiff’s claim

on August 22, 2005. After acknowledging plaintiff’s request for the remission of liquidated

-13-

damages and noting that plaintiff had not completed work by the September 2, 2004 contract

completion date, Ms. Broussard determined that plaintiff had not provided any information

demonstrating why it was “not responsible for the delay,” and that the Coast Guard was “not

aware of any event or occurrence that would excuse [plaintiff’s] late performance.” She

therefore denied the claim.

Less than one month later, plaintiff filed a complaint in the United States Court of Federal

Claims (“Court of Federal Claims”) challenging Ms. Broussard’s decision. It alleged that during

contract performance, “the Coast Guard changed and modified the contract in[,] among other

ways, by failing to properly review and approve drawings [it] submitted . . . , and by directing [it]

to perform additional work that was not required by the Contract.” It also alleged that “[t]he

Coast Guard failed to extend the Contract as a result of its actions, or inactions, and as required

by the Contract because of the changes to the work directed by the Coast Guard.” For these

reasons, plaintiff sought the remission of $50,760 in liquidated damages retained by the Coast

Guard.

On December 15, 2006, plaintiff submitted a second claim to Ms. Broussard, seeking

payment of $34,300 and an eighty-eight-day contract extension for additional work performed at

the Coast Guard’s direction, indicating that its claim was based on the contentions set forth in its

July 26, 2004 letter and other, unidentified “correspondence during the contract.” In her January

16, 2007 letter denying plaintiff’s claims, Ms. Broussard addressed each contention set forth in

plaintiff’s July 26, 2004 letter, but did not address any contentions that may have been set forth

in other correspondence. Shortly thereafter, plaintiff filed an unopposed motion to amend its

complaint to add the allegations it presented to Ms. Broussard in its December 15, 2006 claim

letter. Specifically, plaintiff sought to amend its complaint to assert a claim for a $34,300

increase in the contract price and an eighty-eight-day contract extension, alleging that despite Ms.

Broussard’s rejection of its claim, it was “entitled to additional compensation and an extension to

the contract as a result of changes directed by the Coast Guard.” The court granted plaintiff’s

unopposed motion and plaintiff thereafter filed its amended complaint.

After discovery, plaintiff moved for summary judgment on two issues: whether the

contract’s liquidated damages rate constituted a penalty and whether it was entitled to the

remission of some of the retained liquidated damages due to excusable delays. On the latter

issue, plaintiff argued that it was entitled to the remission of sixty-seven days of liquidated

damages: thirty-two days for the Coast Guard’s delay in convening the postaward kickoff

meeting; eleven days for being required to change the design of the building’s foundation; and

twenty-four days to compensate for the impact of Hurricanes Charley, Frances, Ivan, and Jeanne.

Defendant cross-moved for summary judgment on these same issues, contending that the

liquidated damages rate was not a penalty and that plaintiff was not entitled to the remission of

sixty-seven days of liquidated damages for the reasons plaintiff cited. Defendant also moved for

summary judgment with respect to what it referred to as the remaining twenty-three days of

liquidated damages that plaintiff sought to recover.

-14-

After reviewing the briefs and evidence submitted in support of the cross-motions for

summary judgment, the court invited supplemental briefs from the parties concerning whether, as

required by the Contract Disputes Act of 1978 (“CDA”), 41 U.S.C. §§ 601-613 (2000),29 plaintiff

had submitted a claim to Ms. Broussard that adequately informed her that it was seeking the

remission of liquidated damages as the result of the purported delays described in its motion for

partial summary judgment.30 Defendant responded to the court’s invitation by moving to dismiss

the bulk of plaintiff’s claims–plaintiff’s requests for the remission of liquidated damages, an

eighty-eight-day time extension, and a $34,300 increase in the contract price–for lack of

jurisdiction pursuant to Rule 12(b)(1) of the Rules of the United States Court of Federal Claims

(“RCFC”).31

In its November 30, 2012 Opinion and Order, the court first addressed the jurisdictional

issues. It held that it possessed jurisdiction over plaintiff’s claim for the remission of liquidated

damages because “plaintiff set forth a valid CDA claim for the remission of liquidated damages

in its July 28, 2005 claim letter, the basis of which is found in the formal requests for time

extensions that it submitted to the contracting officer during contract performance.” K-Con

Bldg. Sys., Inc., 107 Fed. Cl. at 571. In a footnote, the court noted that the record before it

included formal requests for time extensions in correspondence dated June 17, 2004; June 22,

2004; July 1, 2004; July 26, 2004; August 16, 2004; September 9, 2004; and September 22,

2004.32 Id. at 589 n.15. The court then concluded that it possessed jurisdiction to consider the

monetary claim set forth in plaintiff’s December 15, 2006 claim letter. Id. at 593. Next, turning

to plaintiff’s motion for summary judgment, the court concluded that the liquidated damages rate

was not an unenforceable penalty, and that for various reasons, plaintiff could not obtain the

remission of liquidated damages for the sixty-seven days of delay specified in its motion for

partial summary judgment. Id. at 594-601. Then, addressing defendant’s motion for summary

judgment, the court held that plaintiff was “not entitled to the remission of liquidated damages

for any delays incurred related to the sequence of construction.” Id. at 604. Finally, the court

explained that plaintiff still had viable claims before the court: “Remaining viable are plaintiff’s

29

All citations to the CDA are to the version of the statute in effect on the date that the

Coast Guard placed its order with plaintiff. Congress has since recodified title forty-one of the

United States Code, revising and renumbering the provisions of the CDA. See Pub. L. No. 111-

350, §§ 7101-7109, 124 Stat. 3677, 3816-26 (2011).

30

Defendant had not, prior to the court’s request for supplemental briefs, challenged the

court’s jurisdiction.

31

The only claim not subject to defendant’s motion was plaintiff’s contention that the

liquidated damages assessed by the Coast Guard constituted an unenforceable penalty.

32

At the time that it issued its November 30, 2012 Opinion and Order, the court was not

in possession of any evidence that plaintiff had retracted the request contained in its June 17,

2004 letter.

-15-

claim for the remission of liquidated damages for excusable delays not addressed in this Opinion

and Order and plaintiff’s claim for a $34,300 increase in the contract price.” Id. at 605.

As noted above, this is one of three breach-of-contract cases before the court involving

plaintiff and the Coast Guard. The court issued a summary judgment ruling in the Elizabeth City

case in January 2011, K-Con Bldg. Sys., Inc. v. United States, 97 Fed. Cl. 41 (2011), which was

followed by a two-week trial in December 2011. After trial, it was necessary for the court to rule

on plaintiff’s motion for sanctions. K-Con Bldg. Sys., Inc. v. United States, 106 Fed. Cl. 652

(2011). In addition, the court issued a summary judgment ruling in the Port Huron case in

August 2011, K-Con Bldg. Sys., Inc. v. United States, 100 Fed. Cl. 8 (2011). After the court

issued its summary judgment ruling in this case, the parties engaged in settlement discussions

through the court’s alternative dispute resolution program. Those discussions revealed several

issues that required resolution prior to any settlement, leading the parties to file the relevant

motions in each case. In this case, plaintiff filed a second motion for partial summary judgment

limited to the issue of whether defendant was required to file a counterclaim for liquidated

damages. Defendant filed a cross-motion for summary judgment, seeking the dismissal of all of

plaintiff’s remaining claims. The parties have completed briefing on the motions and, finding

oral argument unnecessary, the court is prepared to rule.

II. DISCUSSION

A. Motions for Summary Judgment

Both parties move for summary judgment pursuant to RCFC 56. Summary judgment is

appropriate when there is no genuine issue of material fact and the moving party is entitled to a

judgment as a matter of law. RCFC 56(a); Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986).

A fact is material if it “might affect the outcome of the suit under the governing law.” Anderson

v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). An issue is genuine if it “may reasonably be

resolved in favor of either party.” Id. at 250.

The moving party bears the initial burden of demonstrating the absence of any genuine

issue of material fact. Celotex Corp., 477 U.S. at 323. The nonmoving party then bears the

burden of showing that there are genuine issues of material fact for trial. Id. at 324. Both parties

may carry their burden by “citing to particular parts of materials in the record, including

depositions, documents, electronically stored information, affidavits or declarations, stipulations

(including those made for purposes of the motion only), admissions, interrogatory answers, or

other materials” or by “showing that the materials cited do not establish the absence or presence

of a genuine dispute, or that an adverse party cannot produce admissible evidence to support the

fact.” RCFC 56(c)(1).

The court must view the inferences to be drawn from the underlying facts in the light

most favorable to the nonmoving party. Matsushita Elec. Ind. Co. v. Zenith Radio Corp., 475

U.S. 574, 587 (1986). However, the court must not weigh the evidence or make findings of fact.

See Anderson, 477 U.S. at 249 (“[A]t the summary judgment stage the judge’s function is not

-16-

himself to weigh the evidence and determine the truth of the matter but to determine whether

there is a genuine issue for trial.”); Contessa Food Prods., Inc. v. Conagra, Inc., 282 F.3d 1370,

1376 (Fed. Cir. 2002) (“On summary judgment, the question is not the ‘weight’ of the evidence,

but instead the presence of a genuine issue of material fact . . . .”), abrogated on other grounds by

Egyptian Goddess, Inc. v. Swish, Inc., 543 F.3d 665 (Fed. Cir. 2008) (en banc); Ford Motor Co.

v. United States, 157 F.3d 849, 854 (Fed. Cir. 1998) (“Due to the nature of the proceeding, courts

do not make findings of fact on summary judgment.”); Mansfield v. United States, 71 Fed. Cl.

687, 693 (2006) (“[T]he Court may neither make credibility determinations nor weigh the

evidence and seek to determine the truth of the matter. Further, summary judgment is

inappropriate if the factual record is insufficient to allow the Court to determine the salient legal

issues.”). Entry of summary judgment is mandated against a party who fails to establish “an

element essential to that party’s case, and on which that party will bear the burden of proof at

trial.” Celotex Corp., 477 U.S. at 322. However, if neither party meets this burden on the filing

of cross-motions for summary judgment, then the court must deny both motions. See, e.g., Canal

66 P’ship v. United States, 87 Fed. Cl. 722, 723 (2009); Dick Pac./GHEMM, JV v. United

States, 87 Fed. Cl. 113, 126 (2009).

B. Plaintiff’s Motion for Partial Summary Judgment

In its motion for partial summary judgment, plaintiff contends that defendant’s failure to

file a counterclaim asserting its right to liquidated damages requires the court to grant it summary

judgment on its claim for the remission of liquidated damages. Plaintiff is mistaken.

As noted above, the Coast Guard asserted a right to liquidated damages for plaintiff’s

failure to complete the project by the contract completion date and then assessed liquidated

damages against plaintiff by unilaterally modifying the contract to reduce the total contract price.

Plaintiff subsequently submitted a claim to the contracting officer seeking the remission of the

liquidated damages in the Coast Guard’s possession, which the contracting officer denied. In

such circumstances, there is both a government claim against plaintiff for liquidated damages and

a claim by plaintiff against the government for the remission of retained liquidated damages. See

K-Con Bldg. Sys., Inc., 107 Fed. Cl. at 587-88 (citing Sun Eagle Corp. v. United States, 13 Cl.

Ct. 465, 480-82 (1991)). And, there is both a final decision on the government’s claim for

liquidated damages, see Placeway Constr. Corp. v. United States, 920 F.2d 903, 906 (Fed. Cir.

1990) (holding that the contracting officer “effectively made a final decision on the government

claim” for set off by declining to pay the contractor the balance due on the contract), and a final

decision on plaintiff’s claim for the remission of liquidated damages.

There is no question that the only way that plaintiff could recover the liquidated damages

retained by the Coast Guard was by appealing one or both of the contracting officer’s final

decisions. See 41 U.S.C. §§ 606, 609. The Coast Guard, on the other hand, had no reason to

pursue its claim for liquidated damages any further because it already possessed all of the

liquidated damages to which it asserted entitlement. It would only have been necessary for

defendant to file a counterclaim had the remaining contract balance been less than the total

amount of assessed liquidated damages (and had the defendant wished to recover the funds that it

-17-

was unable to retain). See, e.g., K-Con Bldg. Sys., Inc., 100 Fed. Cl. at 19 (“Defendant filed a

counterclaim . . . seeking the balance of liquidated damages . . . .”); K-Con Bldg. Sys., Inc., 97

Fed. Cl. at 49 (same). Indeed, this was the situation in many of the cases cited by plaintiff in

support of its contention that the government must file a counterclaim to recover liquidated

damages from a contractor. See Metcalf Constr. Co. v. United States, 102 Fed. Cl. 334, 368-69

(2011) (noting that the government sought, in its counterclaim, liquidated damages in an amount

greater than what it retained from the contract price), rev’d, 742 F.3d 984 (Fed. Cir. 2014); M.

Maropakis Carpentry, Inc. v. United States, 84 Fed. Cl. 182, 184 (2008) (“These allegations were

met with . . . a four-paragraph counterclaim, in the amount of $59,514, representing the unpaid

balance of the assessed liquidated damages.”), aff’d, 609 F.3d 1323 (Fed. Cir. 2010); Roxco, Ltd.

v. United States, 77 Fed. Cl. 138, 140 (2007) (noting that the remaining contract balance was

insufficient to cover all of the assessed liquidated damages, and that the government sought in its

counterclaim all of the liquidated damages assessed); Mega Constr. Co. v. United States, 29 Fed.

Cl. 396, 487 (1993) (explaining that the government sought, in its counterclaim, reprocurement

costs and liquidated damages in an amount greater than the remaining contract balance).

That defendant was not required to assert a counterclaim for liquidated damages is

entirely consistent with RCFC 13, contrary to plaintiff’s contention. RCFC 13 addresses, in part,

compulsory counterclaims, and provides:

A pleading must state as a counterclaim any claim that–at the time of its

service–the pleader has against an opposing party if the claim:

(A) arises out of the transaction or occurrence that is the subject matter of

the opposing party’s claim; and

(B) does not require adding another party over whom the court cannot

acquire jurisdiction.

RCFC 13(a)(1) (emphasis added). At the time defendant served its answer, it did not have an

outstanding claim against plaintiff; the Coast Guard’s claim had already been resolved to its

satisfaction, as reflected by its possession of all of the funds to which it claimed entitlement.

Therefore, defendant was not required to assert a counterclaim.

Moreover, even if defendant was required to assert a counterclaim for liquidated

damages, plaintiff could not obtain the relief it seeks–judgment on its claim for the remission of

retained liquidated damages. Rather, the consequence of a defendant’s failure to assert a

compulsory counterclaim is that the defendant “waive[s] its right to bring the counterclaim and is

forever barred from asserting that claim in future litigation.” Polymer Indus. Prods. Co. v.

Bridgestone/Firestone, Inc., 347 F.3d 935, 938-39 (Fed. Cir. 2003) (citing Vivid Techs., Inc. v.

Am. Sci. & Eng’g, Inc., 200 F.3d 795, 801-02 (Fed. Cir. 1999)); accord Nasalok Coating Corp. v.

Nylok Corp., 522 F.3d 1320, 1324 (Fed. Cir. 2008) (citing Baker v. Gold Seal Liquors, Inc., 417

U.S. 467, 469 n.1 (1974); Restatement (Second) of Judgments § 22(2) (1982)). This

consequence to the defendant does not affect a plaintiff’s obligation to prove its affirmative

-18-

claims. Accordingly, plaintiff is not entitled to summary judgment on its claim for the remission

of retained liquidated damages.

C. Defendant’s Cross-Motion for Summary Judgment

In its cross-motion for summary judgment, defendant addresses all of the claims asserted

by plaintiff that it believes remain viable after the court’s November 30, 2012 Opinion and

Order. From defendant’s point of view, the surviving claims are (1) plaintiff’s claim of

excusable delay asserted in its July 28, 2005 claim letter and more specifically described in its

earlier formal requests for time extensions submitted to the Coast Guard, and (2) plaintiff’s

request for a $32,100 increase in the contract price asserted in its December 15, 2006 claim letter

and premised on its July 26, 2004 letter to the Coast Guard.33 More specifically, defendant

identifies plaintiff’s unresolved time extension requests as:

• an up-to-one-month extension due, in part, to concrete shortages, as set forth

in plaintiff’s July 1, 2004, and July 26, 2004 letters;

• a ten-day extension due to plaintiff encountering unexpected ground water

when installing a storm drainage pipe, as set forth in plaintiff’s June 22, 2004,

July 1, 2004, and July 26, 2004 letters;

• a twelve-day extension due to plaintiff’s inability to proceed with construction

before the submission of a 100% design, as set forth in plaintiff’s July 26,

2004 letter;

• a fourteen-day extension due to delays related to concrete placement, as set

forth in plaintiff’s July 26, 2004 letter;34 and

33

Plaintiff actually requested a price increase of $34,300; however, $2,200 of its

request–the portion related to the unexpected conditions encountered when excavating utilities–

was granted in a contract modification.

34

Defendant contends that plaintiff’s concrete placement claim was part of plaintiff’s

construction sequence claim, which the court rejected in its November 30, 2012 Opinion and

Order. The court disagrees. In its construction sequence claim, plaintiff alleged that it could

have completed the building earlier than it did had the Coast Guard allowed it to erect the

building prior to pouring the slab. In contrast, in its concrete placement claim, plaintiff contends

that it could have completed the building earlier than it did had the Coast Guard not withheld for

three weeks its opinion that plaintiff’s prior concrete work was unacceptable. These are two

distinct claims, requiring separate proofs.

-19-

• a seven-day extension due to plaintiff encountering unexpected ground water

when installing the trench drain sump, as set forth in plaintiff’s September 22,

2004 letter.

And, defendant avers that plaintiff’s request for a contract price increase includes:

• $8,000 for extended overhead related to plaintiff’s inability to proceed with

construction before the submission of a 100% design;

• up to $19,000 for extended overhead pertaining to the concrete shortage; and

• $5,100 for dewatering during plaintiff’s installation of a storm drainage pipe

in June 2004.

Based on the record before the court, defendant’s characterization of plaintiff’s remaining

claims is accurate.35 The record does not include any formal requests by plaintiff to the

contracting officer for time extensions other than those enumerated above. And, because the

only contract price increase sought by plaintiff in its amended complaint is the one it described in

its December 15, 2005 claim letter, any other request for a price increase that may be included in

the record is not properly before the court.36 In sum, in considering defendant’s cross-motion for

35

Plaintiff’s contention that the record contains evidence of a viable claim concerning

the thickness of a concrete slab that it was required to remove lacks merit. While the evidence in

the record demonstrates that plaintiff advised the Coast Guard of the issue, Pl.’s Supp’l App. 78-

79, and that the excessive slab thickness had “impacted” it, id. at 79, there is no evidence that

plaintiff actually requested an increase in the contract price or a time extension to compensate it

for the additional work that was required. In other words, plaintiff never submitted a claim to the

contracting officer, as required by the CDA. See 41 U.S.C. § 605(a); Reflectone, Inc. v. Dalton,

60 F.3d 1572, 1576 (Fed. Cir. 1995) (en banc) (holding that “the [Federal Acquisition Regulation

(“FAR”)] requires a ‘claim’ to be a written demand seeking a sum certain . . . as a matter of

right”). Such a claim is a jurisdictional prerequisite to pursuing the allegations in the Court of

Federal Claims. England v. Swanson Grp., Inc., 353 F.3d 1375, 1379 (Fed. Cir. 2004).

36

For example, while plaintiff’s September 22, 2004 request for a $3,800 price increase

related to its installation of the trench drain sump appears to qualify as a CDA claim, see 41

U.S.C. § 605(a); Reflectone, Inc., 60 F.3d at 1576, and Ms. Broussard’s rejection of that request

appears to qualify as a contracting officer’s decision, see 41 U.S.C. § 605(a), (c); Alliant

Techsys., Inc. v. United States, 178 F.3d 1260, 1268 (Fed. Cir. 1999) (“A letter can be a final

decision under the CDA even if it lacks the standard language announcing that it constitutes a

final decision.”); Placeway Constr. Corp., 920 F.2d at 907 (“The decision is no less final because

it failed to include boilerplate language usually present for the protection of the contractor.”),

plaintiff did not appeal that decision to the court. A proper appeal is a jurisdictional prerequisite.

See Scott Timber Co. v. United States, 333 F.3d 1358, 1365-66 (Fed. Cir. 2003) (noting that the

-20-

summary judgment, the court treats the claims set forth above as plaintiff’s sole remaining

claims.

1. Commencement of Construction

In the first of its remaining claims, plaintiff seeks a twelve-day time extension and $8,000

for being unable to begin construction until the Coast Guard’s approval of a 100% design.

Defendant articulates several reasons why plaintiff cannot recover for this delay. Two of the

reasons are premised on plaintiff’s contention, in its July 26, 2008 letter, that it typically is

permitted to proceed with construction upon the approval of a 35% design, and that the proposal

it submitted to the Coast Guard was consistent with this typical practice. Specifically, defendant

contends that plaintiff’s project schedules never included the submission of a 35% design and

that the contract did not contain a 35% design requirement. As plaintiff asserts, defendant’s

focus on its reference to a 35% design is misplaced. In its July 26, 2004 letter, plaintiff did not

argue that it should have been permitted to submit a 35% design; rather, it contended that it

should have been able to begin construction before the Coast Guard approved a 100% design.

This last point bears repeating: the claim that plaintiff presented to Ms. Broussard was

that the Coast Guard prevented it from beginning construction prior to the approval of a 100%

design. However, plaintiff has refined its claim and now argues, in its response to defendant’s

cross-motion for summary judgment, that the Coast Guard delayed the design process by not

complying with the review procedures and deadlines set forth in the contract specifications. This

argument is appreciably different from the claim it presented to Ms. Broussard, and there is no

evidence in the record before the court that plaintiff formally requested a contract modification

from the Coast Guard based on the Coast Guard’s purported noncompliance with the submittal

review procedures described in the contract. Because plaintiff’s current position was not

presented to the Coast Guard, as required under the CDA, the court must disregard it.37 See

Contract Cleaning Maint., Inc. v. United States, 811 F.2d 586, 592 (Fed. Cir. 1987) (holding that

contractor’s appeal must “arise from the same operative facts” and seek “essentially the same

relief” as the claim submitted to the contracting officer, and remarking that this requirement is

jurisdictional in nature); James M. Ellett Constr. Co. v. United States, 93 F.3d 1537, 1541 (Fed.

Cir. 1996) (“The CDA grants the court jurisdiction over actions brought on claims within twelve

months of a contracting officer’s final decision.”).

37

Indeed, to the extent that plaintiff is attempting to use a legal memorandum to assert

facts not in the record, it cannot be permitted to do so. See Enzo Biochem, Inc. v. Gen-Probe,

Inc., 424 F.3d 1276, 1284 (Fed. Cir. 2005) (“Attorney argument is no substitute for evidence.”);

Mel Williamson, Inc. v. United States, 229 Ct. Cl. 846, 848 (1982) (“Argument is not fact.”);

Del., Lackawanna & W. R.R. Co. v. United States, 54 Ct. Cl. 35, 41-42 (1919) (“The court can

not accept asseverations of counsel, as to facts, made in argument, whether denied or conceded

by the other side at the bar, without any stipulation duly filed or other evidence . . . .”).

-21-

a contractor must provide the contracting officer with “adequate notice of the basis and amount

of the claim”).

Plaintiff is therefore left with the claim it actually presented in its July 26, 2008 letter.

Defendant argues that this claim is not viable because plaintiff failed to notify the Coast Guard of

the purported delay in a timely manner. The court rejects this argument. The notice requirement

contained in the contract’s changes and suspension of work clauses, see FAR 52.242-14; FAR

52.243-4, is flexible; and defendant has not demonstrated that it was prejudiced by the timing of

plaintiff’s notice. See Hoel-Steffen Constr. Co. v. United States, 456 F.2d 760, 767-68 (Ct. Cl.

1972) (“To adopt [a] severe and narrow application of the notice requirements . . . would be out

of tune with the language and purpose of the notice provisions, as well as with this court’s

wholesome concern that notice provisions in contract-adjustment clauses not be applied too

technically and illiberally where the Government is quite aware of the operative facts.”); Calfon

Constr., Inc. v. United States, 18 Cl. Ct. 426, 438-39 (1989) (“If the contracting officials have

knowledge of the facts or problems that form the basis of a claim and are able to perform

necessary fact-finding and decisionmaking, the Government is not prejudiced by the contractor’s

failure to submit a precise claim at the time a constructive change occurs.” (citing Shepherd v.

United States, 113 F. Supp. 648, 653 (Ct. Cl. 1953); G.M. Shupe Inc. v. United States, 5 Cl. Ct.

662, 727 (1984))), aff’d on other grounds, 923 F.2d 872 (Fed. Cir. 1990) (unpublished table

decision). Indeed, the fact that Ms. Broussard responded to the merits of plaintiff’s claim is

evidence that the Coast Guard was not prejudiced by the timing of plaintiff’s notice.

Defendant’s sole remaining argument pertains to the critical path of contract performance.

To recover for an excusable delay, the alleged cause of the delay “must delay the overall contract

completion; i.e., it must affect the critical path of performance.”38 Sauer Inc. v. Danzig, 224 F.3d

38

The United States Court of Claims described the critical path concept in the following

manner:

[T]he critical path method is an efficient way of organizing and scheduling a

complex project which consists of numerous interrelated separate small projects.

Each subproject is identified and classified as to the duration and precedence of

the work. (E.g., one could not carpet an area until the flooring is down and the

flooring cannot be completed until the underlying electrical and telephone

conduits are installed.) The data is then analyzed, usually by computer, to

determine the most efficient schedule for the entire project. Many subprojects

may be performed at any time within a given period without any effect on the

completion of the entire project. However, some items of work are given no

leeway and must be performed on schedule; otherwise, the entire project will be

delayed. These latter items of work are on the “critical path.” A delay, or

acceleration, of work along the critical path will affect the entire project.

Haney v. United States, 676 F.2d 584, 595 (Ct. Cl. 1982); accord Wilner v. United States, 24

-22-

1340, 1345 (Fed. Cir. 2000). Defendant contends that plaintiff’s claim is not viable because

plaintiff’s expert concluded that the purported delay was not on the critical path. Defendant’s

representation is accurate, but fails to take into account the basis of plaintiff’s expert’s

conclusion. Plaintiff’s expert considered whether the Coast Guard’s review of plaintiff’s 50%

and 100% designs complied with the deadlines provided in the contract specifications and

concluded that the documentation to which he had access did not support a compensable delay,

but noted that his conclusion could change if further investigation revealed additional facts. See

Pl.’s App. 410-11. In light of its expert’s explanation, plaintiff responds to defendant’s argument

by citing defendant’s expert, who concluded that there were critical delays associated with the

submission and review of the 50% and 100% designs submitted by plaintiff. See id. at 431-33.

However, as noted above, these analyses have no bearing on plaintiff’s claim that the Coast

Guard prevented it from beginning construction prior to the approval of a 100% design.

Plaintiff’s claim does not concern the Coast Guard’s purported delays in reviewing and

approving its designs; rather, it concerns whether the Coast Guard should have permitted plaintiff

to begin construction at an earlier phase in the design process. According to the evidence in the

record, plaintiff premised the claim it presented to Ms. Broussard on the contents of its proposal,

which, it contends, was approved by the Coast Guard when Ms. Broussard executed the contract.

See Pl.’s Supp’l App. 56; see also Pl.’s App. 101 (“Your offer . . . including any additions or

changes which are set forth herein is accepted as to items.”). However, the court is unable to

evaluate plaintiff’s claim because plaintiff’s proposal is not a part of the record. And even if it

could evaluate the claim without reviewing plaintiff’s proposal, the record contains conflicting

evidence concerning the proposal’s contents. Compare Pl.’s Supp’l App. 54 (“Your proposal

was . . . based on these contract requirements. . . . My records do not indicate any specific

concerns with our submittal requirements. A follow-up letter . . . did not list submittals as one of

the exceptions to the proposal.”), with id. at 56 (“[The Coast Guard] states that our proposal was

based upon the contract requirements when in fact the opposite is true. Our proposal was in lieu

of the unreasonable and costly specifications . . . .”). Due to the existence of conflicting evidence

in the record concerning plaintiff’s claim, the court concludes that there exists a genuine issue of

material fact as to whether the Coast Guard improperly prevented plaintiff from beginning

construction prior to the approval of a 100% design.

2. Concrete Shortage and Placement

In addition to seeking a contract modification for its inability to begin construction during

the design phase of the project, plaintiff seeks additional time and money for delays associated

with the area-wide concrete shortage and its placement of concrete at the job site. In particular,

plaintiff seeks an up-to-one-month time extension and up to $19,000 related to the concrete

shortage, and a fourteen-day time extension related to concrete placement. The facts relevant to

these claims are intertwined; plaintiff contends that the Coast Guard delayed advising it about

unacceptable concrete work despite being aware that the concrete shortage constrained plaintiff’s

F.3d 1397, 1399 n.5 (Fed. Cir. 1994) (en banc).

-23-

ability to schedule concrete pours on short notice. Due to the inextricable nature of the claims,

the court addresses them together.

Defendant argues that plaintiff cannot recover for any of the purported concrete-related

delays because (1) plaintiff was not ready to pour the slab on June 1, 2004, when the concrete

was scheduled to arrive on the job site; (2) the Coast Guard, on July 8, 2004, identified problems

with the existing concrete work, and therefore prevented plaintiff from proceeding with pouring

the slab until the problems were resolved; (3) plaintiff did not reschedule the concrete pour for

the slab until July 16, 2004; and (4) there is no evidence that the concrete shortage affected the

critical path of performance. In response, plaintiff asserts that the Coast Guard’s failure to advise

it regarding the problems with the existing concrete work for three weeks forced it to reschedule

the concrete delivery for the slab from July 9, 2004, to July 16, 2004, which, due to the concrete

shortage, was the earliest date for which sufficient concrete was available. Plaintiff further

contends that all of the concrete issues were on the critical path, noting that its expert failed to

address the concrete shortage only because he addressed a separate, concurrent delay on the

critical path, i.e., the purported construction sequence delay.

A review of the record submitted by the parties reveals that there is conflicting evidence

regarding whether the Coast Guard delayed plaintiff’s completion of the foundation by not

identifying its concerns regarding plaintiff’s concrete work until three weeks after that work had

been in place, even though it was aware of the area-wide concrete shortage. Thus, there is a

genuine issue of material fact for trial.

3. Dewatering

Plaintiff’s final two remaining claims concern its dewatering activities. Plaintiff seeks a

ten-day time extension and $5,100 for removing the ground water it encountered while installing

a storm drainage pipe in June 2004, and a seven-day time extension for removing the ground

water it encountered while installing a trench drain sump in September 2004. Defendant offers

several reasons why plaintiff is not entitled to recover on its dewatering claims. The court

addresses these reasons in turn.

First, defendant argues that plaintiff cannot obtain a contract modification under either

claim because all of the dewatering performed by plaintiff was foreseeable. As defendant notes,

federal procurement law provides that the government cannot assess liquidated damages against a

contractor for a failure to timely complete work under a contract if “[t]he delay in completing the

work arises from unforeseeable causes,” such as acts of the government, that are “beyond the

control and without the fault or negligence of the Contractor.” FAR 52.249-10(b)(1). In support

of its contention that the ground water encountered by plaintiff was a foreseeable condition,

defendant relies chiefly on the contents of the Coast Guard’s correspondence with plaintiff noting

that plaintiff should have been aware of the existence of ground water at a certain depth because

it was identified in the July 25, 2003 geotechnical report provided to plaintiff before plaintiff

submitted its proposal. Problematically, however, the correspondence contains conflicting

information regarding the precise depth identified in the July 25, 2003 geotechnical report: some

-24-

correspondence cites a depth of three feet, see Def.’s 2nd App. 2, while other correspondence

cites a depth of four feet, see Pl.’s Supp’l App. 54, 99, 104; cf. Pl.’s App. 150 (indicating, in the

contract specifications, a ground water depth of four feet below grade). The one-foot difference

is important, because it appears that plaintiff’s work on the storm drainage pipe may have

occurred at depths between three and four feet, and plaintiff’s work on the trench drain sump

actually occurred at depths between three and four feet. See Pl.’s Supp’l App. 44 (noting that a

drawing included with the contract specifications reflected that work on the storm drainage pipe

would occur at a depth of greater than three feet); id. at 104 (noting that plaintiff’s drawings

reflected that the trench drain sump was installed at a depth between three and four feet). The

court is unable to ascertain the actual depth of ground water identified in the July 25, 2003

geotechnical report because that report is not in the record. Accordingly, the court cannot

conclude that plaintiff encountering ground water at a particular depth was foreseeable.39

In a second, related argument, defendant contends that plaintiff cannot recover for

dewatering specific areas because it foresaw the need to remove water from the job site from the

outset. Defendant relies upon unspecified documents in the record in support of its contention.

The court’s review of the relevant documents in the record–i.e., those pertaining to plaintiff’s

dewatering claims–reveals that it was plaintiff’s position that it had reviewed the documents

provided by the Coast Guard in conjunction with the Coast Guard’s request for a proposal,

ascertained that those documents noted the existence of ground water at a depth of four feet

below grade, determined that its work would be performed above that depth, and therefore

prepared its proposal with the assumption that dewatering would be unnecessary. In the absence

of citations to documents in the record that contradict this interpretation, the court cannot accept

defendant’s argument.

Third, defendant contends, with respect to the September 2004 dewatering claim, that

plaintiff cannot obtain a time extension because its claim is based on excessive rain, and plaintiff

has already been compensated for the unusually high rainfall that occurred in August 2004.

Defendant accurately quotes plaintiff’s statement from its September 22, 2004 claim letter that it

encountered ground water because excessive rain caused the water table to rise. However, the

court disagrees that the evidence in the record demonstrates that the September 21, 2004 contract

modification that extended the contract completion date by sixteen days for “unusually high

rainfall during the month of August and Hurricane[]s Frances and Ivan” compensated plaintiff

for dewatering. First, the contract modification, by its express terms, only covered excessive

rainfall during the month of August and, indeed, only rainfall that occurred before August 18,

2004, the date the parties executed the contract modification. Thus, it is possible that the

“unusually high rainfall” described in the contract modification is not related to the rising of the

39

It bears noting that plaintiff’s June 2004 dewatering claim may also be cognizable

under the contract’s differing site conditions clause, FAR 52.236-2, which does not require

plaintiff to demonstrate that the differing site condition was foreseeable. Rather, plaintiff must

show that the conditions on the job site differed materially from the conditions described in the

contract. Id.

-25-

water table that affected plaintiff’s installation of the trench drain sump in mid-September 2004.

Second, the contract modification does not expressly indicate that the delays associated with

Hurricanes Frances and Ivan were due to “excessive” rain, i.e., rain that caused total rainfall for

September to exceed the threshold for compensation. Indeed, the evidence in the record

indicates that at least some of the impact of the two hurricanes related to demobilization and

mobilization activities. See Pl.’s App. 301; Def.’s Supp’l App. 99-100, 104-05, 112. Based on

the evidence in the record, the court cannot conclude that plaintiff released its September 2004

dewatering claim by executing the September 21, 2004 contract modification.

Fourth, defendant notes that neither party’s expert placed the September 2004 dewatering

claim on the critical path of performance. Plaintiff acknowledges this fact, but asserts that

because its expert stated that he did not place the water and sewer work on the critical path due to

the existence of other, concurrent, critical delays, the trench drain sump work should be treated as

if it were on the critical path. Plaintiff’s expert specifically provided:

The site water and sewer experience[d] approximately two months of

delay (67 calendar days) due to existing waterlines, ductbank, hurricanes, rain, and

late approvals. The delay was concurrent with the aforementioned delays so no

time can be asked for unless the full time for the other issues [is] not granted. . . .

This issue can be explored further if other time is not granted.

Pl.’s App. 413. Although it is unclear to the court whether the installation of the trench drain

sump was part of the water and sewer work referenced by plaintiff’s expert, his statement is

sufficient to raise a factual issue regarding whether the dewatering necessary to install the trench

drain sump was on the critical path.

Fifth, defendant implies that plaintiff cannot obtain a ten-day extension of time under its

June 2004 dewatering claim because its expert only assigned one day of critical delay to the

claim. As plaintiff notes, defendant’s expert assigned two days of critical delay to this claim.

See id. at 434-35. Accordingly, the precise duration of the delay remains in dispute.

Finally, defendant asserts that plaintiff’s claim for $5,100 is not supported by plaintiff’s

job cost ledger. Defendant correctly notes that plaintiff must establish that it incurred the

claimed expenses in order to recover them. However, defendant did not submit any evidence in

support of its assertion that the job cost ledger did not support plaintiff’s claim, whether that

evidence consists of the portion of the job cost ledger that should have included the expenses

plaintiff incurred for dewatering or an affidavit describing the lack of evidence supporting

plaintiff’s claim for expenses. See RCFC 56(c)(1) (requiring citation to materials in the record).

Defendant’s assertion of a fact in a legal memorandum is insufficient to carry its burden under

RCFC 56. See Enzo Biochem, Inc., 424 F.3d at 1284; Mel Williamson, Inc., 229 Ct. Cl. at 848;

Del., Lackawanna & W. R.R. Co., 54 Ct. Cl. at 41-42.

In sum, the court concludes that there are genuine issues of material fact with respect to

both of plaintiff’s dewatering claims.

-26-

III. CONCLUSION

As set forth above, the court DENIES plaintiff’s motion for partial summary judgment,

and DENIES defendant’s cross-motion for summary judgment. By no later than Monday,

April 28, 2014, the parties shall file a joint status report suggesting further proceedings.

IT IS SO ORDERED.

s/ Margaret M. Sweeney

MARGARET M. SWEENEY

Judge

-27-