Opinion

United States v. United Technologies Corp.

  • 626 F.3d 313
  • 2010 U.S. App. LEXIS 23710
  • 2010 WL 4643244
Court
Court of Appeals for the Sixth Circuit
Filed
Nov 18, 2010
Status
Published
Author
Sutton
On the bench
Siler, Sutton, Cleland
Cited by
21 cases
Authority
More cited than 70.5%

finding false statements material but noting government is not entitled to damages if it received fair market value

How later courts described this case

  • finding false statements material but noting government is not entitled to damages if it received fair market value
  • “[The parties] do not dispute that the false statements were material to the government’s decision to enter into a contract with Pratt.... [A]n invoice, which itself does not contain a falsity, may supply the premise for a false claim if submitted in connection with a fraudulently obtained contract.”
  • “Hess establishes that an invoice, which itself does not contain a falsity, may supply the premise for a false claim if submitted in connection with a fraudulently obtained contract.”
  • “False statements underlying multi-year contracts generate a stream of related invoices and cause the government to pay all of the invoices related to the contract.”

Written by the judges who cited it.

The opinion

RECOMMENDED FOR FULL-TEXT PUBLICATION

Pursuant to Sixth Circuit Rule 206

File Name: 10a0357p.06

UNITED STATES COURT OF APPEALS

FOR THE SIXTH CIRCUIT

_________________

X

Plaintiff-Appellant/Cross-Appellee, -

UNITED STATES OF AMERICA,

-

-

-

Nos. 08-4256/4257

v.

,

>

-

Defendant-Appellee/Cross-Appellant. -

UNITED TECHNOLOGIES CORPORATION,

-

N

Appeal from the United States District Court

for the Southern District of Ohio at Dayton.

No. 99-00093—Thomas M. Rose, District Judge.

Argued: August 3, 2010

Decided and Filed: November 18, 2010

Before: SILER and SUTTON, Circuit Judges; CLELAND, District Judge.*

_________________

COUNSEL

ARGUED: Alan S. Gale, UNITED STATES DEPARTMENT OF JUSTICE,

Washington, D.C., for Appellant. Jeffrey A. Hall, BARTLIT BECK HERMAN

PALENCHAR & SCOTT LLP, Chicago, Illinois, for Appellee. ON BRIEF: Alan S.

Gale, UNITED STATES DEPARTMENT OF JUSTICE, Washington, D.C., for

Appellant. Jeffrey A. Hall, BARTLIT BECK HERMAN PALENCHAR & SCOTT

LLP, Chicago, Illinois, David C. Greer, BIESER, GREER & LANDIS LLP, Dayton,

Ohio, David Z. Bodenheimer, CROWELL & MORING LLP, Washington, D.C., for

Appellee.

*

The Honorable Robert H. Cleland, United States District Judge for the Eastern District of

Michigan, sitting by designation.

1

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 2

_________________

OPINION

_________________

SUTTON, Circuit Judge. Fighter jet engines propel planes faster than the speed

of sound, a sight that may be as exhilarating to watch as it must be to experience. Not

so the procurement process for awarding contracts to make jet engines.

In the early 1980s, the Air Force set up a bidding process to make fighter jet

engines. Attempting to win as many engine contracts as possible, United Technologies

manipulated its cost estimates to convince the Air Force to award the company a large

share of the work. After the Air Force discovered that United Technologies had played

with its numbers, the United States filed a lawsuit under the False Claims Act and

common law, seeking reimbursement for the fraud. The district court (1) ruled for the

government on liability under the False Claims Act but held that it had suffered no

damages and (2) ruled that the government’s administrative proceedings precluded it

from raising its common law claims. We affirm the liability determination but reverse

the district court’s damages determination and its claim-preclusion ruling.

I.

Pratt and Whitney is a division of United Technologies Corporation. For many

years, the United States Air Force relied exclusively on Pratt to provide it with F-15 and

F-16 fighter jet engines. In 1982, fearful of the risks of relying on just one company to

produce the engines, the Air Force conducted a fighter engine competition (FEC) for

future fighter jet engine contracts. Only Pratt and General Electric had the capacity to

manufacture the Air Force’s desired fighter jet engines and thus only the two companies

competed for the contract.

In May 1983, the Air Force issued a request for proposal, seeking offers for the

contract. Each offer, the Air Force explained, should include three options: (1) a price

for one purchase order covering three years and three “not-to-exceed price options” for

the Air Force to make annual purchases for an additional three years; (2) a price for a

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 3

five-year purchase order with one not-to-exceed price option for the last year; and (3)

a price option for a one-year purchase order, firm fixed-price options for annual

purchases the second and third years and not-to-exceed price options for the last three

years. Appeals of United Techs. Corp., 04-1 BCA P 32556, 2004 WL 483216

(A.S.B.C.A. Feb. 27, 2004), finding #3 (Initial ASBCA Decision).

Faced with the prospect of losing some of its fighter jet engine contracts to GE,

Pratt prepared an offer that made it difficult for the Air Force to enter into dual-source

engine contracts with Pratt and GE. Pratt submitted its initial proposal in August 1983.

The Air Force reviewed the proposal, prepared some objections and met with Pratt to go

over its concerns. After the meeting, the Air Force gave Pratt a list of questions about

cost estimates for Pratt to answer in its final proposal. Pratt submitted its best and final

offer in December 1983.

As part of this final offer, Pratt submitted a document (Exhibit 3.8.1) that

explained the company’s cost estimates and responded to the Air Force’s questions.

Exhibit 3.8.1 contained three false statements, all designed to drive up the prices for

split-award contracts and to discourage the Air Force from splitting up the work. One:

Pratt said that it had used the most recent inflation forecasts to calculate the not-to-

exceed prices when it had used a different inflation index. Two: in preparing its cost

estimates, Pratt said that it had applied a “decrement factor”—an estimate of how much

the engine prices would decrease based on Pratt’s prior negotiations with engine-parts

suppliers—even though Pratt had not factored decrement data into the final offer. Three:

Pratt said that it had used the most current engine configurations to calculate its prices,

even though it had relied on an earlier engine model without accounting for engine

components that did not go into the updated engine. The method to the scheme was to

drive up the prices for split-award contracts, then provide a variation-in-quantity formula

to reduce prices if the Air Force awarded a greater percentage of the engines to Pratt.

Pratt does not dispute any of these facts.

Based on Pratt’s and GE’s proposals, and despite Pratt’s efforts to discourage the

Air Force from splitting the work, the Air Force chose to exercise a one-year, split-award

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 4

option for the first year of the FEC and executed the contract with Pratt and GE. The

contract allowed the Air Force to exercise 1-year, 3-year or 5-year options, the 1-year

option allowing the Air Force to determine its engine quantities for one year, the 3-year

option allowing the Air Force to determine its engine quantities for three years, and so

on. The contract breaks each year into FY and FEC terms, with FY85 for example

corresponding with FEC I and FY86 corresponding with FEC II. The contract obligated

the Air Force to purchase at least 25 engines from Pratt in FEC I, and at least 100

engines from Pratt for each of the remaining five years.

In February 1983, the Air Force briefed Congress on its decision to award engine

contracts to Pratt and GE on a competitive basis. After the hearings, Congress passed

the Defense Department Authorization Act for FY85, which prohibited the Air Force

from making a contract to purchase engines if the warranty price—which is to say the

costs the engine provider would have to pay the government if the engine

failed—exceeded 10 percent of the total contract price. See Pub. L. No. 98-525, 98 Stat.

2591 (1984).

Because Pratt’s warranties in the final offer exceeded the statutory cap, the Air

Force sent a letter to Pratt indicating that the Air Force would “review and consider any

update or revision to [Pratt’s] warranty offer.” Appx. at 618. The Air Force also

suggested that Pratt could use this opportunity to revise other terms and conditions of the

contract. Pratt responded with an offer to reduce its warranty prices in exchange for a

$17.22 million cap on its previously unlimited liability. Pratt also offered several other

improvements to the contract. The Air Force accepted the warranty modification and

incorporated it into the contract. The Air Force also accepted several other

modifications proposed by Pratt, including one that reduced the Air Force’s minimum

engine purchases. The Air Force exercised its option under these revised terms and

awarded 40 engines to Pratt and 120 engines to GE for FEC I.

To update and potentially improve the terms of the contract, as required under

federal law, see A.S.P.R. § 1-1505(c)(iii), (d)(2), (f)(2), the Air Force began a “call for

improvement” process, Initial ASBCA Decision, finding # 33. Before the Air Force

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 5

exercised its option for FEC II, it sent a letter to Pratt asking if Pratt had any updates or

improvements to its option prices. The Air Force repeated this process for FEC III, IV,

V and VI. Before exercising its options for each year, the Air Force sent a letter to Pratt

offering the company an opportunity to “update and improve the terms and conditions”

of “options under [Contract F33657-84-C-2014].” Appx. at 680 (FEC III), 692 (FEC

IV), 708 (FEC V), 734 (FEC VI). The Air Force indicated that it would consider each

improvement individually, requiring Pratt to offer each revision on a “stand alone basis.”

E.g., Appx. at 682 (FEC III), 694 (FEC IV), 713 (FEC V), 736 (FEC VI). The Air Force

also explained that it did not “intend to and will not conduct an additional formal

competition,” disclaiming any suggestion that Pratt should treat the letter as “a request

for proposal.” E.g., Appx. at 681 (FEC III), 694 (FEC IV), 711–12 (FEC V), 735–36

(FEC VI).

Pratt responded with updated options for each FEC cycle. Pratt offered

improvements on its engine prices, its warranty prices and other contract provisions. In

each year, the Air Force accepted Pratt’s improvements, modified the contract and

exercised its options under the revised contract terms. Due to these improvements, the

Air Force awarded Pratt an increasing percentage of the engines after FEC I.

As the six-year jet engine contract drew to a close, the Air Force began an audit

of the FEC program, which uncovered handwritten notes by a Pratt executive detailing

the company’s plans to play with the numbers to win a sole-source contract. The Air

Force looked into the matter but eventually closed the investigation.

In 1997, a Department of Justice auditor investigated the engine contracts and

noticed Pratt’s false statements in its best and final offer. In response, the United States

launched two proceedings against Pratt: an administrative action and a federal-court

lawsuit. In 2001, it sought a contract price reduction before the Armed Services Board

of Contract Appeals, arguing that Pratt had furnished defective cost or pricing

data—Pratt’s final offer and other preparatory work—in violation of the Truth in

Negotiations Act. 10 U.S.C. § 2306(f). The Board held that Pratt’s final offer was not

cost or pricing data within the meaning of the Truth in Negotiations Act, that Pratt’s

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 6

preparatory work constituted “cost or pricing data” under the Act and that Pratt’s failure

to disclose its preparatory work violated the Act. The Board, however, did not reduce

the contract price because it determined that Pratt’s understatements in its cost estimates

offset its overstatements.

Pratt moved for reconsideration. The Board changed its mind in part, concluding

that the Air Force had not relied on Pratt’s cost or pricing data to determine the

reasonableness of Pratt’s offers, an affirmative defense under the Truth in Negotiations

Act. ASBCA Reconsideration, 05-1 BCA P 32860, 2005 WL 147601 (A.S.B.C.A. Jan.

19, 2005). The Air Force appealed, and the Federal Circuit affirmed. Wynne v. United

Techs. Corp., 463 F.3d 1261 (Fed. Cir. 2006).

In March 1999, the government filed a lawsuit against Pratt in federal district

court for violations of the False Claims Act and for relief under three common law

theories: breach of contract, payment by mistake and unjust enrichment. Because the

False Claims Act has a 10-year statute of limitations, 31 U.S.C. § 3731(b)(2), the United

States sought to recover only for False Claims Act violations after March 1989, which

included the last three years of the contract.

For reasons that the record does not fully explain, the bench trial did not begin

until October 2004. The trial lasted through December 2004, and the court heard closing

arguments in April 2005. In August 2008, the court issued its decision, finding Pratt

liable for 709 violations of the False Claims Act, a number that corresponds to the

number of invoices that Pratt submitted under the contract after March 3, 1989. The

court concluded that, despite the calls for improvements process, “the Government had

the legal right to award the entire multi-year contract to Pratt and to have the contract

performed based upon Pratt’s [final offer].” R.397 at 18. At the same time, however,

the court found that the government suffered no damages because Pratt’s price

reductions offset any cost overstatements in its final offer. It separately held that claim

preclusion barred the government from bringing its common law contract claims because

it litigated or could have litigated those claims before the Board of Contract Appeals.

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 7

Both parties filed appeals—Pratt with respect to the liability ruling and the government

with respect to the damages and claim-preclusion rulings.

II.

As to liability, the district court concluded that Pratt violated two provisions of

the False Claims Act: §§ 3729(a)(1) and 3729(a)(2) of Title 31. (In 2009, Congress

amended 31 U.S.C. § 3729, Pub. L. No. 111-21, § 4. In this opinion, all references to

§ 3729 are to the earlier version.) Section 3729(a)(1) prohibits an individual from

“knowingly present[ing] or caus[ing] to be presented, to an officer or employee of the

United States Government . . . a false or fraudulent claim for payment or approval.”

31 U.S.C. § 3729(a)(1). Section 3729(a)(2) prohibits “knowingly mak[ing], us[ing], or

caus[ing] to be made or used, a false record or statement to get a false or fraudulent

claim paid . . . .” 31 U.S.C. § 3729(a)(2) (2006). The Act defines a “claim” as “any

request or demand, whether under a contract or otherwise, for money or property . . . .”

31 U.S.C. § 3729(c) (2006).

Under the Act, a “false or fraudulent claim” includes a false statement that is

material to the government’s decision to pay a claim. See United States ex rel. A+

Homecare, Inc. v. Medshares Mgmt. Grp. Inc., 400 F.3d 428, 442–43 (6th Cir. 2005).

The parties do not dispute that Pratt’s best and final offer may provide the basis for

liability under the Act. They do not dispute that Pratt’s final offer contained three false

statements. They do not dispute that those false statements were material to the

government’s decision to enter into a contract with Pratt. And they do not dispute that,

in the abstract, an invoice submitted in connection with a contract premised on a false

statement amounts to a “claim” under the Act—a “request . . . under a contract . . . for

money.” 31 U.S.C. § 3729(c) (2006).

That leaves the possibility that liability does not exist when the relevant invoices

are sent in connection with a multi-year contract like this one, as opposed to a single-

year or one-time contract. That distinction, however, does not change things. See

United States ex rel. Marcus v. Hess, 317 U.S. 537, 542–44 (1943); Harrison v.

Westinghouse Savannah River Co., 176 F.3d 776, 785–88 (4th Cir. 1999). Hess

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 8

establishes that an invoice, which itself does not contain a falsity, may supply the

premise for a false claim if submitted in connection with a fraudulently obtained

contract. 317 U.S. at 542–44. Why? The invoices “caused the government to pay

claims . . . under contracts found to have been executed as the result of . . . fraudulent

bidding.” Id. at 543. One variety of fraud is a knowingly false statement that has the

“natural tendency to influence, or is capable of influencing” a government decision

maker to pay the related invoice. A+ Homecare, 400 F.3d at 445. False statements

underlying multi-year contracts generate a stream of related invoices and cause the

government to pay all of the invoices related to the contract.

That is just what happened here. In its request for proposal, the Air Force asked

that all proposals include cost estimates with fully supported cost data. After Pratt

submitted its initial proposal, the Air Force asked Pratt why it failed to apply

decrements. The Air Force met with Pratt before the company submitted its final offer

and asked it to explain the cost estimates. Exhibit 3.8.1 addressed the Air Force’s

questions. On this record, Pratt’s false statements had the potential to influence the

government’s decision to sign the contract and thus to pay the invoices under it. See A+

Homecare, 400 F.3d at 445.

None of this matters, Pratt submits, because it made the best and final offer well

before March 3, 1989, when the statute-of-limitations window closed on its initial

interactions with the government and above all well before several non-fraudulent

modifications to the contract. All that leaves, Pratt urges, are invoices submitted after

March 1989, which did not themselves contain falsities and which were connected to six

separate one-year fighter jet engine contracts with the Air Force after it modified the

original contract through the calls for improvements process.

But it is not that easy to separate the original contract from the modifications to

it. The original contract set price windows for six years and obligated the Air Force to

purchase a minimum number of engines in each of these six years. Not surprisingly, as

a result, all of the documentation through FEC VI refers to the same contract—F33657-

84-C-2014—the one arising from the false statements in the best and final offer. In

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 9

soliciting revisions, moreover, the Air Force indicated it would consider each revision

on a “stand alone basis,” not that it would reconsider the entire contract. E.g., Appx. at

682 (FEC III), 694 (FEC IV), 713 (FEC V), 736 (FEC VI). The government recorded

the new terms as contract modifications, not as new freestanding contracts.

Pratt demurs, pointing to language in the government’s letters about “canceling”

and “superseding” the original contract. But when read in context, this language cancels

contract clauses or attachments, not the entire contract. See, e.g., Appx. at 1131–32

(FEC IV), 1213–14 (FEC VI). Confirming the point, the language appears in a section

outlining “enhancement[s]” to be “incorporat[ed]” into the fighter-jet engine contract,

Appx. at 1123 (FEC IV), or is listed as one of several “changes” to the original contract,

Appx. at 1212 (FEC VI).

The nature of the revisions points in the same direction. They arose from the

calls for improvements process, a federally mandated opportunity to facilitate further

price competition between Pratt and GE. The Air Force designed the process to benefit

itself—to seek “improvements” to the contract from the government’s perspective, an

opportunity to sweeten a deal that happened only because the Air Force entered into the

contract based on fraud in the first place. The Air Force never issued a new request for

proposal; it sought only improvements from parties to the existing jet engine contracts.

Also unavailing is Pratt’s reliance on Allison Engine Co. v. United States ex rel.

Sanders, 553 U.S. 662 (2008). Construing a prior version of § 3729(a)(2), Allison

Engine held that a plaintiff must prove that a defendant intended to use a false record to

get the government to pay a claim. Id. at 665. In response, Congress amended the False

Claims Act, retroactive to claims pending in June 2008, providing that a claimant no

longer has to prove that a defendant intended to get a false claim paid. See Fraud and

Enforcement Recovery Act of 2009, Pub. L. No. 111-21, 123 Stat. 1617 (2009). Even

if the Allison Engine standard for liability under § 3729(a)(2) applies to Pratt, a point we

need not decide, the government satisfied it. Pratt intended the government to pay the

fraudulent invoices that it submitted directly to the government, while Allison Engine

had no such intent when it submitted invoices to a contractor, not the government.

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 10

Allison Engine, 553 U.S. at 666, 671–72. Even if that were not the case, moreover, Pratt

still violated § 3729(a)(1), a provision not at issue in Allison Engine, by submitting

fraudulent invoices to the government.

Pratt separately invokes a procurement regulation obligating the Air Force to

solicit cost or pricing data if the Air Force modifies a contract by over $500,000.

A.S.P.R. § 3-807.3. The regulation makes an exception if the price is “based on

adequate price competition.” Id. Because the Air Force never solicited cost or pricing

data during the calls for improvements process, Pratt claims that the Air Force must have

based the contract prices on adequate price competition rather than on Pratt’s final offer

or cost or pricing data. Yet the link missing in this chain of reasoning—why all of this

releases Pratt from liability—is never explained, and we think it is inexplicable. The

False Claims Act makes an individual liable for presenting a fraudulent claim to the

government regardless of whether the government decides to pay the claim based on

price competition. 31 U.S.C. § 3729(a)(1); see A+ Homecare, 400 F.3d at 443–44. And

under § 3729(a)(2), a false statement must be “material” to the government’s decision

to pay, meaning that it must have the objective, natural tendency to influence a

government decision maker. Liability does not depend on whether the government

relied in fact on the false statement to pay out the claim. A+ Homecare, 400 F.3d at 445.

The False Claims Act, unlike the Truth in Negotiations Act, does not contain an

affirmative defense if the government does not rely on a false statement. Cf. 10 U.S.C.

§ 2306a(e)(2). The regulation thus does not alter the material reality under the False

Claims Act—that Pratt’s false statements had the natural tendency to influence the Air

Force to enter into this six-year contract—and at most goes to the government’s

damages, not Pratt’s liability.

III.

The government says that the district court erred in concluding that Pratt’s

conduct caused no damages. Under the False Claims Act, the government may recover

“actual damages,” the difference between what it paid and what it should have paid for

the goods. United States v. Bornstein, 423 U.S. 303, 317 n.13 (1976); United States ex

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 11

rel. Roby v. Boeing Co., 302 F.3d 637, 646 (6th Cir. 2002); United States ex rel.

Compton v. Midwest Specialities, Inc., 142 F.3d 296, 304 (6th Cir. 1998). In a case

covering as many years and involving as many complicated procurement regulations as

this one, it should not come as a surprise that the district court encountered several

difficult damages calculations. And, as a result, it perhaps also should not come as a

surprise that hindsight allows us to identify a few mistakes, some of which require a new

calculation by the trial court.

First, the district court subtracted the full amount of Pratt’s warranty price

reductions from the court’s estimate of the government’s damages without calculating

the value of the new warranties. In its best and final offer, Pratt offered to give the

government engine warranties without a cap on Pratt’s liability to the government.

When Pratt later reduced the warranty prices, as part of the calls for improvement

process, it capped its liability at 300% of the warranty price or $17.22 million. While

the government paid less for the engine warranties, it also got something less in

return—far less insurance for engines gone awry. Nothing in the court’s opinion shows

that it accounted for this reality. To calculate the difference between what the

government paid and what it should have paid, see Roby, 302 F.3d at 646, the court must

account for the diminished value of the new warranties.

None of this is necessary, Pratt counters, because the government gave up

nothing by agreeing to a liability cap—that the value to the government of an unlimited

warranty was no different from a warranty capped at $17.22 million. That is hardly self-

evident, and indeed nothing in the record supports the notion that $17.22 million

encompasses all damages that a faulty fighter-jet engine might cause or all repairs that

such an engine might need.

Second, the district court incorrectly subtracted the government’s total savings

from the final offer prices to calculate damages. The district court reduced the

government’s damages for FEC III, IV and V by the amount Pratt reduced its prices over

the course of the entire contract, meaning that it compared FEC VI prices to the original

contract prices. But in FEC III, IV and V, the government did not pay FEC VI prices

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 12

because those revisions had not yet occurred. The district court should calculate the

difference between what the government paid each year—FEC III, IV and V—and what

it should have paid each year. It should not subtract the price reductions the government

won for FEC VI when it determines whether the government suffered any damages

during FEC III, IV and V.

Third, we are not confident that the district court applied the correct damages

standard for the years under review. The district court calculated the difference between

the 1984 contract prices and what the government paid for FEC III–VI. But, as noted,

the district court should have calculated the difference between what the government

paid and what it should have paid for what it received. Neither party maintains that the

1984 contract prices represent the fair market value of the goods the government

received or that the government should have paid those prices. The court, to the

contrary, found that the FEC I prices turned on false claims. On remand, the district

court should calculate what the government eventually paid each year during FEC III,

IV, V and VI, what it should have paid each year based on what the government

received, then take the difference between the two. If the court concludes that Pratt’s

prices during FEC III, IV, V and VI represent the fair market value of the fighter jet

engine contract—or were below fair market value—the government is not entitled to

damages.

IV.

After a final judgment on the merits, a party cannot relitigate claims it brought

in the first proceeding, and it cannot litigate any claim it could have raised in the first

proceeding. Mitchell v. Chapman, 343 F.3d 811, 819 (6th Cir. 2003). The district court

concluded that claim preclusion barred the government from pursuing its common law

claims in this case. We disagree.

The district court first concluded that the government litigated Count III—the

contract claim—before the Board of Contract Appeals and therefore cannot have a

second bite at the apple. Count III alleges that Pratt breached its contractual obligation

“to provide accurate, complete and current cost or pricing data . . . and failed to adjust

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 13

its [Alternate Fighter Engine] Contract prices to reflect the impact and effect on those

prices.” R.334 at 25. The Board decided, however, only whether Pratt had violated the

Truth in Negotiations Act, not whether Pratt had breached its contractual obligations or

overstated its prices. The decision left open the possibility that Pratt’s false statements

were actionable on other grounds, including breach of contract. See Initial ASBCA

Decision, Conclusion of Law III. The factual premises of this case and the Board’s case

also differ. Before the Board the government argued that Pratt’s failure to provide its

preparatory work was a violation of the Truth in Negotiations Act, but we are not

concerned with Pratt’s preparatory work here, only its final offer. The government thus

did not litigate Count III before the Board, leaving us to decide whether Count III, like

Counts IV and V, could have been litigated before the Board, not whether it was.

The district court concluded that the administrative litigation barred the

government’s common law claims because the government could have litigated those

claims before the Board. But prior litigation precludes a claim only if the initial tribunal

had jurisdiction over the claim. Rawe v. Liberty Mut. Fire Ins. Co., 462 F.3d 521,

529–30 (6th Cir. 2006). According to all relevant precedent at the time the government

filed its administrative claims, the Board did not have jurisdiction over these common

law claims. Because these precedents directed the government not to bring these claims

before the Board, the government is not precluded from litigating the claims before the

district court.

The Board derives its authority from the Contract Disputes Act of 1978, which

sets up an administrative dispute resolution process for government contracts. 41 U.S.C.

§ 607. The Board may hear appeals only from a “decision” of a “contracting officer.”

Id. §§ 606, 607(d). Contracting officers may hear claims “relating to a contract.” Id.

§ 605(a). Yet the Contract Disputes Act does not authorize “any agency head to settle,

compromise, pay, or otherwise adjust any claim involving fraud.” Id. (emphasis added).

Because agency heads do not have the authority to resolve “any claim involving

fraud,” fraud-related claims (such as the False Claims Act claims here) are excluded

from the Contract Dispute Act’s dispute resolution process and, by extension, from the

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 14

Board’s jurisdiction. The same, we think, goes for the government’s common law

claims—breach of contract, payment by mistake and unjust enrichment—which in

essence are alternative pleadings to its fraud claims under the False Claims Act.

The government’s entire case, including its common law claims, “arises from

Pratt’s knowing false certifications, non-disclosures, and active concealments” during

the negotiation and performance of the jet engine contract. R.334 ¶ 2. It may be the

case, to be sure, that not every contract or unjust enrichment claim involves fraud. But

to describe these allegations is to show that they involve fraud. The complaint describes

“Pratt’s [alleged] fraud,” id. ¶ 4, “Pratt’s [alleged] fraudulent” behaviors, id. at 18, and

Pratt’s alleged knowingly false representations and active concealment of material facts,

see, e.g., id. ¶¶ 2, 30, 30E, 35, 36, 37, 45, the last of which amount to fraud by another

name, see A+ Homecare, 400 F.3d at 443–44; Restatement (Second) of Torts § 525. No

less important than the labels we put on the government’s claims is the reality that all of

the claims are premised on the same set of facts. See R.334 ¶¶ 2, 59, 60, 63, 68. To

resolve the one set of claims (the common law claims) requires the resolution of the

other (the False Claims Act fraud claim), and the Contracts Disputes Act does not allow

the agency to make that determination.

That, however, by itself does not prove the government is right. The more

difficult question is whether the Contract Disputes Act allows contracting officers (and

therefore the Board of Contract Appeals) to hear claims involving fraud. The Contract

Disputes Act prohibits only an “agency head” from settling claims involving fraud,

41 U.S.C. § 605(a) (emphasis added), but there is no similar restriction on contracting

officers’ ability to do so. Congress defined “contracting officer” and “agency head” to

refer to different individuals. 41 U.S.C. § 601(1), (3). The decision of the contracting

officer, not the agency head, forms the basis for the Board’s appellate jurisdiction, id.

§§ 606, 607(d), which means that, if a contracting officer could issue a decision on a

claim involving fraud, the Board could have heard the government’s common law

claims. (No carve out to the Board’s jurisdiction exists. Id. §§ 606, 607(d).)

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 15

While we may have to resolve whether contracting officers can issue decisions

on claims involving fraud at some point, this case does not require it. All available

precedent at the time, it turns out, directed the government not to bring its common law

claims before the Board of Contract Appeals. The initial litigation began before the

Board, whose decisions the Federal Circuit directly reviews. By the time the

government moved for a contract price reduction before the Board, the Federal Circuit

had already ruled that “Congress did not intend fraud claims by the government to be

included in the dispute process outlined by section 605(a).” Martin J. Simko Constr.,

Inc. v. United States, 852 F.2d 540, 545 (Fed. Cir. 1988). The Board by then also had

concluded that Congress excluded fraud-related claims from the jurisdiction of

contracting officers and the Board. See Appeal of Comada Corp., 83-2 BCA P 16681,

1983 WL 13084 (A.S.B.C.A. June 20, 1983). But see Appeal of Dry Roof Corp., 88-3

BCA P 21096, 1988 WL 97213 (A.S.B.C.A. Aug. 9, 1988) (suggesting the Board has

not definitively answered the question). Indeed, every court that has considered the

issue has determined that contracting officers and administrative boards do not have

jurisdiction over claims involving fraud. See, e.g., United States v. Hardrives, Inc., No.

92-15224, 1993 WL 385498, at *7 n.10 (9th Cir. Sept. 30, 1993); United States ex rel.

Rille v. Sun Microsystems, Inc., No. 4:04CV00986, 2008 WL 4756170, at *5 n.66 (E.D.

Ark. Oct. 28, 2008); United States v. United Techs. Corp., No. 5:92-CV-375, 1996 WL

653620, at *2 (D. Conn. Oct. 11, 1996) (listing district court opinions). In addition to

this precedent, a Federal Acquisition Regulation says that contracting officers cannot

hear claims involving fraud. See 48 C.F.R. § 33.210.

Under these circumstances, we cannot say that the government should have

brought its common law claims before the Board. See Browning v. Levy, 283 F.3d 761,

772–73 (6th Cir. 2002). A plaintiff who relies on the initial tribunal’s decisions on

jurisdiction conserves judicial resources, serving one of the goals of claim preclusion.

See Charles Alan Wright et al., Federal Practice & Procedure § 4415 (3d ed. 2010). If

we were to apply claim preclusion based on a disagreement with the Federal Circuit’s

view of the Board’s jurisdiction, that would force litigants to raise their fraud claims

before the contracting officer and seek rehearing en banc in the Federal Circuit or

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 16

certiorari at the Supreme Court. Otherwise, the contracting officer and the Board would

reject the claims based on one jurisdictional view, and we could reject them based on the

other. While the government might have opted to urge the Federal Circuit to rethink its

decision in Martin Simko, we will not punish it for choosing not to do so.

Pratt insists that the Contract Disputes Act covers claims “relating to a contract,”

41 U.S.C. § 605(a), and because the government’s claims relate to the jet engine contract

they fall within the Board’s jurisdiction. That may be true, but this ignores the carve out

in § 605(a) for claims “involving fraud.”

Pratt adds that the government’s argument amounts to a “collateral attack” on the

Board’s jurisdiction. But that assumes the Board had jurisdiction over the government’s

common law claims, assumes that the Board asserted jurisdiction over those claims and

assumes that the government wishes to attack collaterally an adverse ruling on those

claims. Pratt’s argument fails at the first assumption, and the rest of the assumptions

collapse with it. The government did not raise these claims before the Board; otherwise

we would be talking about issue, as opposed to claim, preclusion. The Board, it may be

true, considered and rejected the government’s argument that the information contained

in Pratt’s final offer constituted cost or pricing data under the Truth in Negotiations Act.

But the Board made clear that it “express[ed] no opinion” on whether purported defects

in the final offer could be remedied under “other contract clauses, procurement

regulations or statutes.” Initial ASBCA Decision, Conclusion of Law III. Neither the

Board nor the Federal Circuit exercised jurisdiction over the government’s common law

claims, leaving nothing for the government to attack, collaterally or otherwise. See

Charles Alan Wright et al., Federal Practice & Procedure § 4413 (3d ed. 2010).

At the end of the day, we acknowledge, this claim-preclusion ruling may matter

little to Pratt or the government. If the government recovers False Claims Act damages,

there may be nothing left for it to recover on its common law claims. If the district court

concludes that the government suffered no damages, it is doubtful that it could recover

on its common law claims, which as shown amount to alternative ways of seeking relief

on the same facts.

Nos. 08-4256/4257 United States v. United Technologies Corp. Page 17

Finally, at places in its brief, Pratt raises an issue-preclusion defense with respect

to some of these questions. Because the district court ruled that the litigation before the

Board precluded the government from litigating its common law claims, however, it had

no reason to consider the defense. The district court should address the defense in the

first instance.

V.

We affirm the district court’s liability determination, reverse its damages

calculation, remand for a recalculation of damages, reverse its claim-preclusion ruling

and remand for further proceedings.