Opinion

US Ex Rel. Miller v. BILL HARBERT INTERN. CONST.

  • 608 F.3d 871
Court
Court of Appeals for the D.C. Circuit
Filed
Jun 22, 2010
Status
Published
On the bench
Sentelle, Chief Judge, Ginsburg and Tatel, Circuit Judges
Cited by
2 cases
Authority
More cited than 48.1%

concluding that the trial court did not abuse its discretion in admitting the testimony of an expert witness who had no direct knowledge of the facts of the case and had not examined the evidence, but instead testified generally about cartel economics

How later courts described this case

  • concluding that the trial court did not abuse its discretion in admitting the testimony of an expert witness who had no direct knowledge of the facts of the case and had not examined the evidence, but instead testified generally about cartel economics

Written by the judges who cited it.

The opinion

United States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued December 7, 2009 Decided June 22, 2010

Nos. 08-5390, 08-5391, 08-5392, 08-5393, 08-5394

UNITED STATES OF AMERICA EX REL. RICHARD F. MILLER AND

RICHARD F. MILLER,

APPELLEES

v.

BILL HARBERT INTERNATIONAL CONSTRUCTION, INC., ET AL.,

APPELLANTS

Appeals from the United States District Court

for the District of Columbia

(No. 1:95-cv-01231-RCL)

Alfred W. Putman, June Ann Sauntry, Barry Coburn,

Charles C. Murphy Jr., and Charles S. Leeper argued the

causes for appellants. With them on the briefs were Michael

R. Miner and Alicia Hickok. Bryan B. Lavine, Stephen P.

Murphy, and Brian P. Watt entered appearances.

Steve Frank, Attorney, U.S. Department of Justice, and

Paul R.Q. Wolfson argued the cause for appellees. With them

on the brief were Douglas N. Letter, Attorney, U.S.

Department of Justice, Keith V. Morgan, Assistant U.S.

Attorney, Robert B. Bell, Jennifer M. O’Connor, and Annie L.

2

Owens. R. Craig Lawrence, Assistant U.S. Attorney, and

Daniel S. Volchok entered appearances.

Before: SENTELLE, Chief Judge, GINSBURG and TATEL,

Circuit Judges.

Opinion for the Court filed PER CURIAM.

Separate opinion dissenting from Parts II.A.2 and II.G.4

filed by Circuit Judge TATEL.

TABLE OF CONTENTS

I. Background .......................................................................... 3

II. Analysis .............................................................................. 8

A.  Statute of Limitations ................................................ 8

1.  Relation Back Under the FCA ........................... 10

2.  Claims Concerning Contracts 07 and 29 ........... 13

3.  Claims Against BIE ........................................... 19

4.  Remaining Claims ............................................. 24

B.  Preemption ............................................................... 25

C.  Personal Jurisdiction over HUK .............................. 27

D.  Anderson’s Settlement ............................................. 29

E.  BHIC Stipulation ..................................................... 30

F.  Precluding BIE from Contesting Liability ............... 33

G.  Evidentiary Issues .................................................... 35

1.  BIE’s Guilty Plea ............................................... 36

2.  Expert Testimony on Cartels ............................. 40

3.  Ruggieri’s Testimony ........................................ 45

4.  Evidence of HII and HC’s Wealth ..................... 46

H.  Sufficiency of the Evidence ..................................... 50

1.  Overarching Conspiracy .................................... 51

2.  HUK’s Involvement in the Conspiracy ............. 55

3.  Damages ............................................................ 62

III. Conclusion ...................................................................... 66

3

PER CURIAM: In this False Claims Act case, the jury

found five companies and one individual liable for rigging the

bidding on three contracts in Egypt funded by the USAID.

Trebling the jury’s award, the district court imposed over $90

million in damages. The defendants appeal, challenging

several of the district court’s rulings, as well as the

sufficiency of the evidence adduced against them. For the

reasons set forth in this opinion, we conclude (1) that the

plaintiffs’ claims on two of the contracts are barred by the

applicable statute of limitations, and (2) that certain testimony

and evidence introduced at trial unfairly prejudiced three

defendants. In all other respects, we affirm.

I. Background

Following the 1978 Camp David Accords, the United

States agreed to provide economic assistance to Egypt

through the U.S. Agency for International Development

(USAID), including funding for improving sewer systems in

Cairo and Alexandria. The sewer projects were divided into

numerous construction contracts and put out for bidding by

contractors prequalified by the USAID.

In 1995, Richard Miller, then a Vice President of the J.A.

Jones Construction Company (Jones), the 40% partner in a

series of identical joint ventures that bid on three of the

projects, filed a complaint under the False Claims Act (FCA).

31 U.S.C. § 3729 et seq. Enacted during the Civil War, the

FCA penalizes knowingly submitting or conspiring to submit

false or fraudulent claims to the United States Government,

§ 3729(a)(1)(A), (C), and authorizes private enforcement

through qui tam actions, which give individuals knowing of

fraud a monetary incentive to come forward, § 3730(b). In

his complaint, Miller alleged that in the course of his

employment, he discovered that the defendants, other

4

contractors, and a variety of related corporate entities and

individuals were all members of a conspiracy to rig the

bidding on contracts in Egypt. This so-called Frankfurt Club

would meet to discuss upcoming contract bids in Frankfurt,

Germany, the home of the conspiracy’s leader, Jones’s parent

corporation, Holzmann, A.G. Miller’s complaint focused on

the bidding for one particular contract, Contract 20A, and

named Holzmann, Jones, Harbert International, Inc. (HII)—

Jones’s partner on the other side of the joint venture—and

several related corporations as defendants.

In accordance with the FCA, Miller filed his complaint

in camera, and the district court placed it under seal. A qui

tam relator suing under the FCA brings his case “in the name

of the Government,” § 3730(b)(1), and his initial complaint

remains under seal for sixty days. Before the expiration of

that period, the Government must (1) intervene and “proceed

with the action, in which case the action shall be conducted

by the Government,” § 3730(b)(4)(A); (2) “notify the court

that it declines to take over the action, in which case [the

relator has] the right to conduct the action,” § 3730(b)(4)(B);

or (3) petition the court for an extension of the seal period by

showing “good cause,” § 3730(b)(3). If the Government

decides to intervene, it typically does so by filing an amended

complaint.

In this case, soon after Miller filed his complaint, the

Government opened a criminal investigation into the alleged

conspiracy and, fearing that active civil litigation would

interfere with that investigation, filed successive motions to

keep Miller’s complaint sealed. In the meantime, the

Government prosecuted many of the participants in the Cairo

and Alexandria bid-rigging arrangements, obtaining guilty

pleas or convictions from at least five U.S. corporations or

individuals.

5

In February 2001, the Government allowed Miller’s

complaint to be unsealed and filed its own Complaint in

Intervention, taking over control of the case. The

Government’s complaint adopted the claims that Miller had

asserted on Contract 20A and added claims on two other

contracts, Contracts 29 and 07, which it characterized as part

of the same Frankfurt Club conspiracy. It charged all the

defendants with substantive FCA violations for each of the

three contracts and with participating in the overarching

conspiracy. Miller later amended his complaint to do the

same. In essence, Miller and the United States alleged that

prior to each contract, some or all of the bidders prequalified

by the USAID met in Frankfurt to discuss the bidding. At

these meetings or thereafter, the bidders reached an

agreement that all but one would either bid high or refrain

from bidding, and the winning bidder would pay these

cooperators a “loser’s fee.”

Contract 20A, the first of the three contracts and the only

one identified in Miller’s original complaint, covered

installation of large-diameter, underground sewer pipe in

densely populated Cairo neighborhoods. The plaintiffs

alleged that the joint venture between HII and Jones (Harbert-

Jones), one of three prequalified bidders, sought and received

commitments from the other two companies to either overbid

or not bid for the contract. Thanks to this agreement,

Harbert-Jones ultimately won the contract for $115 million,

subsequently paying the other two bidders $2.2 and $3

million for their cooperation. The plaintiffs further alleged

that in order to hide $10 million in excess profits, the joint

venture engaged in a sale/leaseback transaction with an

affiliated corporation.

Contract 29, the second contract, involved the

construction of a wastewater treatment plant near Cairo. In

6

this instance, Harbert-Jones allegedly met with the only other

prequalified bidder and agreed to lose the bid in exchange for

a $4 million loser’s fee.

The third contract, Contract 07, covered the construction

of sewers in Alexandria. Because this time Harbert-Jones

was apparently unable to reach a bid-rigging agreement with

all other qualified bidders, it entered into a bilateral

agreement with one other bidder. Under that deal, the party

that won the contract would compensate the other with a

loser’s fee. Although the record is unclear on this point, the

fee would have been either 1.5 million U.S. Dollars or 1.5

million German Deutschmarks.

As relevant here, the Government’s Complaint in

Intervention and Miller’s amended complaint named the

following defendants:

 Holzmann, see supra at 4;

 Jones, see supra at 3;

 HII, see supra at 4;

 Harbert Corporation (HC), HII’s parent corporation;

 Bilhar International Establishment (BIE), to which HII

assigned the contracts in question after bidding was

complete. (We hold, infra at 20, that the reference in

the original complaint to Harbert International

Establishment, Inc., was intended to refer to BIE);

 Harbert Construction Services (U.K.), Ltd. (HUK), a

corporation owned 49% by BIE and 51% by a private

7

individual that provided various financial services in

connection with the bidding;

 Bill Harbert International Construction, Inc. (BHIC), a

corporation which, though inactive at the time of

bidding, subsequently took partial ownership of BIE

and allegedly provided support for fraudulent billing

on inflated invoices as the ill-gotten contracts were

completed.

 Bill Harbert, President of HII and a senior executive at

other corporate defendants; and

 Roy Anderson, Vice President of HII and President of

BIE.

Five years of pleadings, motions, and discovery followed

Miller’s amended complaint and the Government’s

Complaint in Intervention. After declaring bankruptcy and

settling with the plaintiffs, Holzmann and Jones were each

dismissed from the case. Trial began in March 2007, and

following seven weeks of testimony, the jury found for the

plaintiffs on every count. This included conspiracy by all

defendants, as well as substantive violations by most

defendants with respect to most of the contracts. (For some

defendants’ involvement in some contracts, the district court

held that it lacked subject matter or personal jurisdiction. In

addition, at the conclusion of testimony, the court found all

claims against Bill Harbert were barred by the FCA’s statute

of limitations.)

The jury found that the United States suffered

approximately $34 million in damages from the defendants’

conduct. As required by the FCA, the district court trebled

these damages and added statutory penalties. See 31 U.S.C.

8

§ 3729(a). After subtracting amounts previously recovered by

the United States, it awarded $90.4 million in damages. The

defendants moved for judgment notwithstanding the jury’s

verdict on a variety of issues and sought a new trial on others.

Rejecting the defendants’ legal arguments and finding the

jury’s verdict amply supported by the evidence, the district

court denied all of the defendants’ motions in a 125-page

opinion. Miller v. Holzmann, 563 F. Supp. 2d 54 (D.D.C.

2008). This appeal followed.

II. Analysis

The defendants raise a number of issues. We first

address two threshold issues—whether the statute of

limitations bars any claims against the defendants and

whether the Foreign Assistance Act preempts the False

Claims Act. We next address personal jurisdiction over

HUK, the contradiction at trial of a stipulation regarding

BHIC’s existence, and the district court’s decision to preclude

BIE from contesting liability. Finally, we address the

defendants’ arguments concerning four evidentiary issues and

the sufficiency of the evidence.

A. Statute of Limitations

As relevant here, the FCA precludes a civil action filed

“more than 6 years after the date on which the violation . . . is

committed.” 31 U.S.C. § 3731(b)(1). The violations at issue

here occurred in the late 1980s and the 1990s. Miller filed his

initial complaint in 1995 alleging the defendants violated the

FCA in their dealings associated with Contract 20A. The

Government filed its Complaint in Intervention in 2001,

adopting Miller’s claims concerning Contract 20A and adding

its own claims concerning Contracts 07 and 29. In his Third

Amended Complaint, filed in 2006, Miller too added claims

concerning the latter contracts.

9

The defendants argue the statute of limitations bars all the

Government’s claims and bars Miller’s claims concerning

Contracts 07 and 29 because the events giving rise to those

claims occurred more than six years before the claims were

brought. The Government and Miller argue the claims relate

back to Miller’s initial complaint and therefore have the

benefit of the earlier filing date.1 BIE argues separately the

claims against it do not relate back because it was added as a

defendant after the statute of limitations had run.

The district court held the Government’s claims

concerning Contracts 07, 20A, and 29, as well as Miller’s

claims concerning Contracts 07 and 29, relate back to Miller’s

initial complaint. See 563 F. Supp. 2d at 139–42. We review

de novo whether “claims are barred by the statute of

limitations,” Jung v. Mundy, Holt & Mance, PC, 372 F.3d

429, 432 (D.C. Cir. 2004), and hold the statute of limitations

does not bar the Government’s claims concerning Contract

20A because they relate back to Miller’s timely filed

complaint but does bar all claims, both the Government’s and

Miller’s, concerning Contracts 07 and 29. The district court

also rejected BIE’s separate argument, as do we, because BIE

1

In a post-argument letter to the court, the Government

belatedly argues at least one claim concerning Contract 29 was

timely without regard to relation back because the underlying

events occurred less than six years before the Government filed its

Complaint in Intervention. Because the Government failed to raise

this point in the district court or in its briefs in this court, the point

is doubly forfeit and we do not consider it. See Bryant v. Gates,

532 F.3d 888, 898 (D.C. Cir. 2008). With the exception of the

arguments regarding recent decisions of the Supreme Court, the

same is true for the other arguments the parties raised in the various

post-argument letters. See id.; Fed. R. App. P. 28(j).

10

should have known within the required time it was an

intended defendant.

1. Relation Back Under the FCA

At the time of trial the FCA did not by its terms address

relation back, but the district court held the FCA nonetheless

implicitly permitted an otherwise untimely claim to relate

back under what is now Federal Rule of Civil Procedure

15(c)(1)(B). See 563 F. Supp. 2d at 139–40 n.137

(interpreting what was then Rule 15(c)(2)). In 2009, after trial

but before this appeal was briefed, the Congress amended the

FCA expressly to provide for relation back. The statute now

reads:

For statute of limitations purposes, any such Government

pleading shall relate back to the filing date of the

complaint of the person who originally brought the

action, to the extent that the claim of the Government

arises out of the conduct, transactions, or occurrences set

forth, or attempted to be set forth, in the prior complaint

of that person.

31 U.S.C. § 3731(c).

The statute as thus amended applies to this case on

appeal. Although most of the 2009 amendments to the FCA

apply only “to conduct on or after the date of enactment,” the

provision permitting relation back was made expressly

“appl[icable] to cases pending on the date of enactment.”

Fraud Enforcement and Recovery Act of 2009 (FERA), Pub.

L. No. 111-21, § 4(f)(2), 123 Stat. 1617, 1625 (emphasis

added).

The defendants’ arguments that the amended statute

cannot constitutionally be applied to this case are

11

unpersuasive. The Ex Post Facto Clause of the Constitution

applies only to penal legislation. See Calder v. Bull, 3 U.S. (3

Dall.) 386, 390–91, (1798) (opinion of Chase, J.); see also

Landgraf v. USI Film Prods., 511 U.S. 244, 266 n.19 (1994)

(citing Calder). The FCA is not penal. See Hudson v. United

States, 522 U.S. 93, 100–03 (overruling Court’s prior decision

that a civil FCA proceeding could be criminal under the

Double Jeopardy Clause). We need not address the

arguments concerning the Takings and the Due Process

Clauses of the Constitution because they were raised in only

two conclusory sentences. See Cablevision Sys. Corp. v.

FCC, 597 F.3d 1306, 1312 (D.C. Cir. 2010) (“Federal courts

should not . . . decide [a] constitutional question unless it is

presented with the clarity needed for effective adjudication.”)

(brackets in original) (internal quotation marks omitted);

Cement Kiln Recycling Coalition v. EPA, 255 F.3d 855, 869

(D.C. Cir. 2001) (“A litigant does not properly raise an issue

by addressing it in a cursory fashion with only bare-bones

arguments.”) (internal quotation marks omitted).

The defendants argue the Congress did not intend that the

amendment reach cases in which the Government had already

intervened because it referred to “cases pending” rather than

to “all pending cases.” In Lindh v. Murphy, 521 U.S. 320

(1997), upon which the defendants rely, the Supreme Court

discussed in a footnote the use and omission of “all” and

“any” in statutory provisions. See id. at 328–29 n.4. There

the Court interpreted a retroactivity provision that on its face

applied only to one of several chapters in the statute. See id.

at 326–27 (quoting Antiterrorism and Effective Death Penalty

Act of 1996, Pub. L. No. 104-132, § 107, 110 Stat. 1214,

1226 (“Chapter 154 . . . shall apply to cases pending on or

after the date of enactment of this Act”)); see also Martin v.

Hadix, 527 U.S. 343, 356 (1999) (explicating Lindh). Unlike

the statute interpreted in Lindh, the clause in the FERA

12

specifying the effective date of the provision concerning

relation back is not limited in scope to a particular type of

case or subset of cases.

The defendants, citing the Supreme Court’s recent

decision in Carr v. United States, 560 U.S. __, No. 08-1301

(June 1, 2010), would also have us infer, from a temporal

sequence or choice of verb tense, that Congress intended to

limit the effect of the statute to cases in which the

Government has not yet intervened. We have no need to draw

inferences, however, when the statute is clear on its face. See

Robinson v. Shell Oil Co., 519 U.S. 337, 340 (1997) (“Our

first step in interpreting a statute is to determine whether the

language at issue has a plain and unambiguous meaning with

regard to the particular dispute in the case. Our inquiry must

cease if the statutory language is unambiguous and the

statutory scheme is coherent and consistent.”) (internal

quotation marks deleted). The amendment “applies to cases

pending on the date of enactment.” Pub. L. No. 111-21,

§ 4(f)(2), 123 Stat. 1617, 1625. Because this case was

pending on the date of enactment, the amendment applies.

Q.E.D.

The defendants urge us to adopt an “equitable doctrine of

relation back” and so not to allow the Government’s claims to

relate back in this case because it delayed filing its own

complaint and unsealing Miller’s complaint until several

years after the statute of limitations had run. We reject this

argument because the statute, as amended, permits both

relation back and—if good cause be shown—maintaining the

relator’s complaint under seal indefinitely beyond the sixty

days. See 31 U.S.C. § 3730(b)(3).

Although the Government may take advantage of the

relator’s filing date, the FCA still does limit the claims it may

13

add. Under the new provision, the Government’s complaint

can relate back to the original complaint only “to the extent

that the claim of the Government arises out of the conduct,

transactions, or occurrences set forth, or attempted to be set

forth, in the prior complaint.” 31 U.S.C. § 3731(c). The

defendants do not argue the scope of the Government’s claims

concerning Contract 20A impermissibly expands beyond that

of Miller’s. Accordingly we hold the Government’s claims

concerning Contract 20A are not barred by the statute of

limitations because they relate back to Miller’s original timely

complaint.

2. Claims Concerning Contracts 07 and 29

In contrast, the Government’s claims concerning

Contracts 07 and 29 do not meet that standard because they

have little to do with Miller’s claims concerning Contract

20A. As we noted in Meijer, Inc. v. Biovail Corp., 533 F.3d

857 (D.C. Cir. 2008), ordinarily “[t]he underlying question [in

analyzing relation back] is whether the original complaint

adequately notified the defendants of the basis for liability the

plaintiffs would later advance in the amended complaint.” Id.

at 866 (citing 6A Charles Alan Wright, Arthur R. Miller, &

Mary Kay Kane, Federal Practice & Procedure § 1497 (“if

the alteration of the original statement is so substantial that it

cannot be said that defendant was given adequate notice of the

conduct, transaction, or occurrence that forms the basis of the

claim . . . then the amendment will not relate back”)).

This focus upon notice is in tension with the requirement

that a complaint alleging a violation of the FCA be filed under

seal and not served “on the defendant until the court so

orders.” 31 U.S.C. § 3730(b)(2). We have not had occasion

to address this tension before because in no prior case in this

circuit had the Government kept the complaint under seal and

14

refrained from serving it on the defendant until after the

statute of limitations had run.2 The Second Circuit, however,

considered this tension when it held the FCA, before it was

amended, did not implicitly permit relation back: “The

secrecy required by § 3730(b) is incompatible with Rule

15(c)(2) [now 15(c)(1)(B)], because (as is well-settled) the

touchstone for relation back pursuant to [that] Rule[] is

notice.” United States v. Baylor Univ. Med. Ctr., 469 F.3d

263, 270 (2006).

Under the statute as amended to allow relation back, the

inquiry cannot be whether the defendant had actual notice of

the claim before the statute of limitations had run because the

FCA specifically requires that the complaint be filed under

seal. The timely filed private party’s complaint, however, still

limits the permissible scope of the Government’s later-filed

complaint because, as mentioned above, the statute requires

that in order to relate back a new claim must arise from the

same conduct, transactions, or occurrences as did the timely

complaint.

Cases concerning relation back under Rule 15, despite

their focus upon notice to the defendant, are useful in

analyzing relation back under the FCA because the standards

in the FCA and in Rule 15 are substantively identical. As we

have seen, the FCA allows relation back only “to the extent

that the claim of the Government arises out of the conduct,

transactions, or occurrences set forth, or attempted to be set

forth, in the prior complaint,” 31 U.S.C. § 3731(c); Rule

15(c)(1)(B) allows relation back only to the extent the new

2

Although the defendants were aware of the criminal

investigation involving the same conduct, they did not have notice

until 2001 of the precise allegations in the Government’s FCA

complaint.

15

pleading “asserts a claim or defense that arose out of the

conduct, transaction, or occurrence set out—or attempted to

be set out—in the original pleading.”

Relation back generally is improper when the new

pleading “asserts a new ground for relief supported by facts

that differ in both time and type from those the original

pleading set forth,” Mayle v. Felix, 545 U.S. 644, 650 (2005);

“attempts to introduce a new legal theory based on facts

different from those underlying the timely claims,” United

States v. Hicks, 283 F.3d 380, 388 (D.C. Cir. 2002); or,

although it “shares ‘some elements and some facts in

common’ with the original claim . . . its effect is ‘to fault [the

defendants] for conduct different from that identified in the

original complaint,’” Jones v. Bernanke, 557 F.3d 670, 674

(2009) (quoting Meijer, 533 F.3d at 866).

Courts have refused to relate back “amendments alleging

the separate publication of a libelous statement, the breach of

an independent contract, the infringement of a different

patent, or even a separate violation of the same statute.” 6A

Wright, Miller, & Kane, supra, § 1497 (footnotes deleted)

(collecting cases). For example, in United States ex rel.

Bledsoe v. Community Health Systems, 501 F.3d 493 (2007),

the Sixth Circuit applied the relation back provisions of Rule

15 in a qui tam case involving claims for reimbursement from

Medicare and Medicaid submitted under certain Current

Procedural Terminology (CPT) codes used for billing medical

services. The timely documents alleged improper billing

under Code 94799 for services related to “emergency room”

and “02 Equip./Daily” but the amended complaint also

alleged “improper[] billing . . . under that [same] code for a

‘call back’ charge for which no procedure is associated”; the

court held the latter allegation did not relate back because the

former allegation would not have “alert[ed]” the defendant

16

that billing related to call backs was involved. Id. at 518–19.

The timely documents also made “several allegations of

improper billing under CPT code 99201,” including

allegations concerning miscoding of supplies, but the

amended complaint added allegations of improper billing “for

cardiopulmonary resuscitation under [that] code”; again the

court held the latter allegations did not relate back because the

original documents would not have “alert[ed] [the]

[d]efendants . . . that cardiopulmonary resuscitation

procedures were involved.” Id. at 513, 518–19. Although in

each instance the allegations in the timely documents and in

the amended complaint addressed improper billing under the

same billing code, the court held the new allegations did not

relate back because they did not “arise from the same

conduct, transaction or occurrence” involved in the timely

complaint. Id. at 519.

In this case, all three contracts are similar only in that

each was funded by the USAID and required work related to

sewer systems in Egypt. The differences among them,

however, are significant. Based upon the allegations in the

complaint, the critical facts regarding each contract are the

work to be performed, who was prequalified to participate in

the bidding that was allegedly rigged, when the contract was

awarded, who won the contract, and the amount of the

winning bid. The following table summarizes these facts for

each contract and thus shows the important differences.

Contract Awarded Winning Project Prequalified Recipient

bid

20A 1988 $114.9 19 km of George A. Fuller Co., Harbert-

million underground Fru-Con Construction Jones 20A

sewer pipe in Co., and Harbert-Jones Joint

Cairo 20A Joint Venture Venture

29 1989 $114.9 Wastewater At least Sadelmi U.S.A. Sadelmi

17

million treatment and Harbert-Jones 29 U.S.A.

plant in Cairo Joint Venture

07 1990 $44.6 Sewer in Morrison-Knudsen, Harbert-

million Alexandria FruCon, Maclean Jones 07

Grove, Tidewater, and Joint

Harbert-Jones 07 Joint Venture

Venture

18

As reflected in the table, each contract required work to

be performed on a different project and was awarded in a

different year to a different winning bidder drawn from a

different pool of prequalified bidders. Allegations concerning

Contract 20A do not fairly encompass Contracts 07 or 29

because each contract is unique and no two involved the same

“conduct, transaction[], or occurrence[].”

Miller and the Government argue the use of the plural in

Miller’s complaint—“conspired to rig the bidding for

construction contracts paid for by the [USAID]” (emphasis

added)—together with the allegation there was a “club []

organized to control prices” and the contention that

“discovery in this case will reveal [] other AID contracts,”

broadened the scope of the complaint beyond Contract 20A.

As we held in Meijer, however, using the plural form does not

cause new allegations to relate back when, as here, the new

allegations do not involve “conduct, transactions, or

occurrences” common to the timely pleading. See 533 F.3d at

866. As in Meijer, our decision here is impelled by more than

the limited relevance of the plural form. Miller’s allegations

concerning any contracts beyond 20A were nothing more than

“‘naked assertion[s]’ devoid of ‘further factual

enhancement,’” viz., the existence of a price-fixing “club,”

and that discovery would reveal other rigged contracts.

Ashcroft v. Iqbal, 129 S. Ct. 1937, 1949 (2009) (quoting Bell

Atlantic Corp. v. Twombly, 550 U.S. 544, 557 (2007))

(brackets in original). Allowing such broad and vague

allegations to expand the range of permissible amendments

after the limitation period has run would circumvent the

statutory requirement in the FCA that the amendments

“arise[] out of the conduct, transactions, or occurrences” in

the original complaint, 31 U.S.C. § 3731(c); it would also, we

note, circumvent the recent teachings of Iqbal and Twombly

by allowing amendments to relate back to allegations that

19

were themselves nothing more than “naked assertions.” That

potential for abuse is avoided by the relation back provision in

the FCA, the amendment of which postdates Twombly,

cabining the scope of otherwise untimely amendments by

imposing the same “conduct, transactions, or occurrences”

requirement. 31 U.S.C. § 3731(c).

Turning to Miller’s claims concerning Contracts 07 and

29, we hold they are barred by the statute of limitations

because he added them after the limitation period had run.

Miller may not take advantage of the relation back provision

in the FCA, which applies only to the Government’s

pleadings. See id. If his claims are to relate back then they

must do so under Rule 15(c)(1)(B), which permits relation

back for claims “that arose out of the conduct, transaction, or

occurrence set out . . . in the original pleading.” We need not

decide whether Rule 15(c)(1)(B) applies to claims made by a

relator in litigation under the FCA because we have

determined the claims concerning Contracts 07 and 29 do not

meet that standard, which for our purposes is substantially the

same as the standard in the amended FCA.

3. Claims Against BIE

Prior to 2006 both Miller’s and the Government’s

complaints named Harbert International Establishment, Inc.

(HIE, Inc.) among the defendants; they did not name Bilhar

International Establishment (BIE). In amended complaints

filed in 2006, Miller and the Government replaced references

to “Harbert International Establishment, Inc.” with references

to “Bilhar International Establishment f/k/a Harbert

International Establishment.” The statute of limitations bars

all claims against BIE unless the amended complaints relate

back to a timely complaint. The district court held the

amended complaints relate back because BIE should have

20

known it was the intended defendant. Miller v. Holzmann,

2007 WL 778599, 2007 U.S. Dist. LEXIS 15598 (D.D.C.

Mar. 6, 2007). We agree with the district court.

(a) History of the Companies

A company called Harbert International Establishment

was formed in Liechtenstein in 1975. At all relevant times

Bill Harbert owned at least part of that company and at

various times BHIC and HII owned the remainder. In

September 1993 Harbert International Establishment changed

its name to Bilhar International Establishment. The next

month a new company was formed in Liechtenstein, also

called Harbert International Establishment. It acquired many

of the assets of BIE (formerly HIE), including both the name

Harbert International Establishment and that company’s

interest in Contract 20A. After transferring its assets to the

new HIE, the old HIE (by then BIE) ceased operating. In

1999 Bill Harbert’s son formed Harbert International

Establishment, Inc. in Alabama.

(b) Analysis

Rule 15(c)(1)(C), which for present purposes is

substantively the same as the version of then-Rule 15(c)(3)

applied by the district court, provides an amendment relates

back when:

the amendment changes the party or the naming of the

party against whom a claim is asserted . . . if, within the

[120 days] provided by Rule 4(m) for serving the

summons and complaint, the party to be brought in by

amendment:

(i) received such notice of the action that it will not be

prejudiced in defending on the merits; and

21

(ii) knew or should have known that the action would

have been brought against it, but for a mistake

concerning the proper party’s identity.

Fed. R. Civ. P. 15(c)(1)(C) (emphasis added).

Relation back under this provision “is most obviously

appropriate in cases [such as this] where the plaintiff has sued

a corporation but misnamed it.” Roberts v. Michaels, 219

F.3d 775, 778 (8th Cir. 2000). BIE does not claim the

misnaming prejudiced it and the plaintiffs do not dispute

BIE’s defense that it did not actually know it was the intended

defendant; the dispute between the parties is whether BIE

should have known it was the intended defendant.

The same attorney represented BIE, HIE, and HIE, Inc.

That attorney acknowledges she knew the plaintiffs had erred

in naming HIE, Inc., but as between her two other clients with

similar names she “felt that it was likely that the Government

had intended to sue Harbert International Establishment[,] . . .

not Bilhar International Establishment.”

In determining what BIE, in the person of its attorney,

knew or should have known, we consider the allegations in

Miller’s Second Amended Complaint3 as follows:

3

The parties agree this is the complaint to which BIE should

have referred in order to determine the identity of the intended

defendant. BIE states, “Similar allegations appear in the

government’s Complaint in Intervention,” and does not identify any

significant differences between the complaints for these purposes.

22

Allegation Comment

(1) BHIC “controls and BHIC owned 79% of BIE but

operates” the defendant. none of HIE.

(2) The defendant is “a This allegation does not advance

Liechtenstein corporation the inquiry because both HIE

which, upon information and BIE were organized in

and belief, has as its Liechtenstein and neither has its

principal place of business principal place of business in

Birmingham, Alabama.” Alabama.

(3) The defendant “holds a 49 This allegation applied, at one

percent share” of HUK. time or another, to both BIE and

HIE. By the time the complaint

was filed BIE had sold its 49%

interest in HUK to HIE.

(4) Bill Harbert was Chairman This allegation applied equally

and Roy Anderson was to BIE and to HIE.

President of the defendant.

(5) “In 1991, as a consequence The same paragraph describes

of a reorganization of the HII as managing the 20A Joint

Harbert entities, Contract Venture, suggesting the

20A was assigned to referenced assignment of

Harbert International Contract 20A came from HII.

Establishment, which is The paragraph better describes

owned and controlled by BIE. As stated above, BHIC

[BHIC], and these owned the majority of BIE, not

companies began of HIE. The assignment of

participating directly in the Contract 20A did not change in

conspiracy.” 1991. In 1989 HII assigned it to

BIE, which was then known as

HIE. In 1993, after the new

company was created and

named HIE, BIE reassigned

Contract 20A to the new HIE.

23

Of these five allegations, Nos. 2 and 4 are of no help in

identifying the correct defendant because they favor neither

HIE nor BIE. Of the three allegations that better describe one

company than they do the other, only one more accurately

applies to HIE: At the time of the complaint, HIE owned 49%

of HUK. Allegations 1 and 5 indicate BIE was the intended

defendant: BHIC, not HIE, owned the majority of BIE, and

HII assigned part of its interest in Contract 20A to the

company that, at the time, was named HIE and was owned

primarily by BHIC. Thereafter the assignee participated in

the conspiracy. This latter datum, which unlike the others

reaches the intended defendant’s substantive involvement in

the bid rigging, should have led counsel to the conclusion that

BIE was the intended defendant.

This discussion undoubtedly seems obscure to anyone

unfamiliar with the various companies in the Harbert group of

companies. When an attorney for several of these companies,

however, receives a complaint she knows mistakenly names

as the defendant one company in the group, and she

represents two other companies in the group with names

similar to that of the named defendant, it should be obvious

that she needs to consider the history and corporate structure

of both companies and to determine which company is the

intended defendant.

BIE argues the Government and Miller could have

determined the correct name because the relevant parts of the

structure of the Harbert complex were disclosed in certain

financial documents of which they had copies. The

appropriate inquiry under Rule 15, however, is what the

intended defendant “should have known.” Fed. R. Civ. P.

15(c)(1)(C)(ii). After this case had been submitted the

Supreme Court clarified the issue in Krupski v. Costa

Crociere S.p.A., 560 U.S. __, No. 09-337 (June 7, 2010). In

24

Krupski the plaintiff sued Costa Cruise Lines N.V. instead of

the related company Costa Crociere S.p.A.4 Although the

plaintiff could have determined the correct identity of the

intended defendant, the Court explained,

Rule 15(c)(1)(C)(ii) asks what the prospective defendants

knew or should have known during the Rule 4(m) period,

not what the plaintiff knew or should have known. . . .

That a plaintiff knows of a party’s existence does not

preclude her from making a mistake with respect to that

party’s identity.

Id. at __, slip op. at 8–9.

BIE argues for the first time in a footnote in its brief on

appeal that the 120-day period in Rule 4(m), referred to in

Rule 15(c)(1)(C), started to run when the suit was filed in

1995 rather than when the complaint was unsealed in 2001.

We do not ordinarily consider an argument made for the first

time on appeal. In any event, as we stated in Hutchins v.

District of Columbia, 188 F.3d 531, 539 n.3 (D.C. Cir. 1999)

(en banc), “[w]e need not consider cursory arguments made

only in a footnote.”

4. Remaining Claims

To summarize, the only claims left standing are Miller’s

claims concerning Contract 20A, as originally pleaded and

subsequently amended, and the Government’s claims

concerning the same contract, which relate back to Miller’s

claims for purposes of the statute of limitations. All the

4

Crociera means cruise in Italian. See Krupski, 560 U.S. at

__, slip op. at 17.

25

Government’s and Miller’s claims concerning Contracts 07

and 29 are time barred.

B. Preemption

BIE, HUK, and BHIC alone argue this case should have

been dismissed because the Foreign Assistance Act (FAA), 22

U.S.C. § 2151 et seq., preempts the False Claims Act. The

district court rejected this argument in Miller v. Holzmann,

2007 WL 710134 at *11, 2007 U.S. Dist. LEXIS 16105 at

*35–36 (D.D.C. Mar. 6, 2007). We address the question of

preemption de novo, Bldg. & Constr. Trades Dep’t, AFL-CIO

v. Allbaugh, 295 F.3d 28, 32 (D.C. Cir. 2002), and affirm.

The FAA, which governs how the United States provides

aid to foreign countries, includes its own false claim

provision. That provision authorizes the President to bring a

suit on behalf of the United States, but does not authorize a

private party to bring a qui tam action. See 22 U.S.C.

§ 2399b(b). In contrast, the FCA allows a private party, in

addition to the Attorney General, to bring a civil suit. See 31

U.S.C. § 3730(a), (b).

The defendants argue the qui tam provision of the FCA

conflicts with the lack of such a provision in the FAA because

“a precisely drawn, detailed statute pre-empts more general

remedies.” Brown v. Gen. Servs. Admin., 425 U.S. 820, 834

(1976). They assert “[a]llowing a qui tam relator the right to

file an action against foreign aid contractors . . . would

effectively nullify the FAA’s more restrictive [remedial]

provision.” With this argument they suggest that, for fraud

involving foreign aid, the false claim provision in the FAA,

enacted in 1968, implicitly displaced the qui tam provision in

the FCA, which has been around in some form since 1863.

See Act of March 2, 1863, ch. 67, § 4, 12 Stat. at 698, Rev.

Stat. § 3491.

26

“[W]hen two statutes are capable of co-existence, it is the

duty of the courts, absent a clearly expressed congressional

intention to the contrary, to regard each as effective.” Morton

v. Mancari, 417 U.S. 535, 551 (1974). The FCA and the FAA

are surely capable of co-existence. In a case involving

foreign aid, such as this one, the Government could bring suit

under either the FCA or the FAA. Indeed, the FCA expressly

contemplates the possibility the Government will have a

choice of remedy. See 31 U.S.C. § 3730(c)(5) (“the

Government may elect to pursue its claim through any

alternate remedy available to the Government”). A choice

does not create a conflict, let alone an “irreconcilable

conflict.” See United States v. Batchelder, 442 U.S. 114, 118,

122 (1979) (“overlapping statutes” with “partial redundancy”

“fully capable of coexisting”); cf. EC Term of Years Trust v.

United States, 550 U.S. 429, 435 (2007) (nine-month

limitations period for a claim under specific statute conflicts

with four-year period provided by a more general statute).

Finally, the Government need not face the prospect posed

by the defendants of a private plaintiff in a qui tam case

somehow interfering in a case brought by the Government

under the FAA. The FCA requires the private plaintiff to

present his claim to the Government before it is served on the

defendant. The Government may “proceed with the action,

. . . dismiss the action notwithstanding the objections of [the

relator], . . . settle the action . . . notwithstanding the

objections of [the relator],” or keep the complaint under seal

during an investigation. 31 U.S.C. §§ 3730(b), (c). Indeed,

the FCA specifically authorizes the Government to restrict the

relator’s involvement, such as by limiting his discovery, if his

involvement otherwise “would interfere with the

Government’s investigation or [with] a prosecution of a

criminal or civil matter arising out of the same facts.”

§ 3730(c)(4).

27

In sum, although the false claims provisions of the FAA

and the FCA do overlap, the two statutes are fully capable of

coexisting. Therefore, the FAA does not preempt the FCA.

C. Personal Jurisdiction over HUK

HUK challenges the district court’s assertion of personal

jurisdiction over it. Miller v. Holzmann, 2007 WL 778568,

2007 U.S. Dist. LEXIS 15599 (D.D.C. Mar. 6, 2007); United

States ex rel. Miller v. Bill Harbert Int’l Constr., Inc., 501 F.

Supp. 2d 51, 53 & n.3 (D.D.C. 2007). Reviewing the district

court’s assertion of personal jurisdiction de novo, McAninch

v. Wintermute, 491 F.3d 759, 765 (8th Cir. 2007); see also FC

Inv. Group LC v. IFX Markets, Ltd., 529 F.3d 1087, 1091

(D.C. Cir. 2008) (reviewing dismissal), we hold HUK had

sufficient contacts with the United States to subject the

company to the jurisdiction of its courts.

A court may exercise personal jurisdiction over a

defendant not present within the forum if the defendant has

“certain minimum contacts with [that forum] such that the

maintenance of the suit does not offend traditional notions of

fair play and substantial justice.” Int’l Shoe Co. v.

Washington, 326 U.S. 310, 316 (1945) (internal quotation

marks deleted). The exercise of personal jurisdiction “must

have a basis in some act by which the defendant purposefully

avails itself of the privilege of conducting activities within the

forum State, thus invoking the benefits and protections of its

laws.” Asahi Metal Indus. Co. v. Superior Ct. of Cal., 480

U.S. 102, 109 (1987) (internal quotation marks omitted).

Personal jurisdiction is proper where the defendant has

“purposefully directed his activities at residents of the forum

and the litigation results from alleged injuries that arise out of

or relate to those activities.” Burger King Corp. v. Rudzewicz,

471 U.S. 462, 472 (1985) (internal quotation marks omitted).

28

HUK argues against personal jurisdiction based upon our

decision in Creighton Ltd. v. Gov’t of State of Qatar, 181 F.3d

118 (1999). There we held the Government of “Qatar lacks

the minimum contacts with the United States that would make

it amenable to suit here” even though it had “entered into a

contract with a company based in the United States.” Id. at

127–28. The contract had been “offered, accepted, and

performed in Qatar.” Id. at 128. In addition, the “contract

was made subject to the laws of Qatar, payment was made in

Qatari riyals to Creighton’s bank account in Qatar, and the

alleged breach occurred in Qatar.” Id. HUK’s contacts with

the United States were a good deal more substantial than

those of Qatar.

At all relevant times HUK was, not surprisingly, based in

the United Kingdom. It had no office, bank account, real

property, or employees in the United States. It was not a

party to Contract 20A, nor was it a member of the joint

venture that bid for that contract. On the other hand, HUK

was intimately involved with the Harbert-Jones Joint Venture

bid for Contract 20A. From 1985 to 1988, fully 50% of

HUK’s work was on the preparation of the bid for Contract

20A and one of its employees signed the tender. HUK knew

that the United States Government was funding the contract

and that all payments to HUK for work done in connection

with the contract were funded by payments from the United

States Government via bank accounts in the United States

belonging to one of the other Harbert companies. In addition,

the district court found, and HUK does not dispute, the

following facts: HUK “was created by American citizens,

acting as agents for . . . American corporations, for the

specific purpose of providing services to companies that were

bidding on projects that were going to be funded by agencies

of the United States.” Miller v. Holzmann, 2007 WL 39371 at

29

*7–8, 2007 U.S. Dist. LEXIS 501, *25–26 (D.D.C. Jan. 8,

2007).

Considering these facts, we conclude “the defendant’s

conduct and connection with the forum State are such that he

should reasonably anticipate being haled into court there.”

World-Wide Volkswagen Corp. v. Woodson, 444 U.S. 286,

297 (1980); see McGee v. Int’l Life Ins. Co., 355 U.S. 220,

223 (1957) (personal jurisdiction over Texas company proper

in California court “based on a contract which had substantial

connection with” that state). Accordingly, we hold HUK’s

contacts with the United States were sufficient to give the

district court personal jurisdiction over it.

D. Anderson’s Settlement

For a time Anderson and the Government tried to settle

the Government’s case against him. He argues they reached

an agreement and have an enforceable settlement; the

Government argues the settlement was never made final and

should not be enforced.

The district court dismissed “all of the relator’s claims on

all contracts against defendant Anderson, and all of the

Government’s claims but one claim on contract 29 against

defendant Anderson . . . as untimely under the FCA’s statute

of limitations.” United States ex rel. Miller v. Bill Harbert

Int’l Constr., Inc., 505 F. Supp. 2d 1, 19 (D.D.C. 2007). At

trial Anderson was found liable for $149,615.20 on that one

claim. 501 F. Supp. 2d 51, 58 (D.D.C. 2007).

Anderson joined the other defendants’ argument that the

statute of limitations bars all claims concerning Contract 29.

Having agreed with the defendants on that point, we have no

need to reach Anderson’s alternative argument that the

30

Government and he entered into a final and binding

settlement agreement.

E. BHIC Stipulation

Prior to trial, the parties jointly stipulated that BHIC “did

not exist at the time Contracts 20A, 29, [or] 07 were bid or

entered into.” This stipulation simplified the more complex,

but mostly irrelevant, circumstances surrounding the

formation of BHIC. In 1986, an entity named BLH

Enterprises, Inc. was formed but had no employees or

operations for six years. In December 1991, BLH changed its

name to Bill Harbert International Construction, Inc. Then, in

1992, more than a year after Harbert-Jones entered into the

last contract, BHIC acquired employees and began operations.

At that point, BHIC also became the majority owner of BIE

and provided support services such as administrative

accounting to that company.

During trial, the Government introduced evidence that

the defendants argue contradicted the joint stipulation of fact

that BHIC did not exist at the time companies were bidding

on and entering into the relevant contracts. The evidence

introduced was a document submitted by BHIC in 1992 for

prequalification to bid on another contract not at issue in this

case. That document included the information about BLH’s

formation and its subsequent name change, indicating that

BHIC had, in fact, existed when Harbert-Jones and other

companies bid on and entered into Contracts 20A, 29, and 07.

The Government emphasized this contradiction with the joint

stipulation, asking Alf Hill, the project manager for Contract

20A, to read aloud the part of the document explaining

BHIC’s history. The Government then asked, “So according

to this document which was submitted to the Government,

BHIC existed since 1986, right?” The project manager

31

replied, “Yes.” Over BHIC’s objection that the witness had

not seen the document before and that the document had not

been authenticated, the district court allowed the document to

be submitted into evidence and refused to strike the testimony

relating to BHIC’s date of incorporation. In closing

arguments, the Government pointed back to that document,

saying “Why are we suing BHIC? . . . Take a look at that

document.” The Government further clarified its point later

in its closing argument, saying, “BHIC was in existence at the

time Bill Harbert, Roy Anderson, and Tommy Kitchens were

doing what they were doing rigging the bids, dealing with the

profits on Contract[s] 20A, 07 and 29.”

After trial, BHIC argued in support of a new trial that this

evidence was contrary to the stipulation, prejudicial, and

undermined the credibility of BHIC counsel, who relied in

opening statements on the joint stipulation. The district court

denied BHIC’s motion for a new trial, and clarified its

reasoning for allowing the Government to introduce the

evidence that BHIC had incorporated in 1986:

[P]laintiffs did not stipulate that neither BHIC nor any

predecessor company existed ‘at the time Contracts 20A,

29, 07 were bid or entered into.’ Plaintiffs did not seek to

disprove the stipulated fact that BHIC did not exist prior

to 1992. Rather, they sought to prove that BHIC, by its

own admission, is a direct outgrowth of any entity that

did exist when the bid-rigging occurred.

Miller v. Holzmann, 563 F. Supp. 2d 54, 104 n.61 (D.D.C.

2008).

Even if the stipulation is read so narrowly, the

Government violated it. The Government elicited testimony

and claimed in closing argument that BHIC itself existed

since 1986, not that a BHIC predecessor existed since then.

32

Not only that, but the evidence establishes BLH was not in

fact a predecessor to BHIC, but actually the same company.

The only difference was a change in name. The document

introduced by the Government included the articles of

incorporation for BLH and the amendment to those articles

that change its name to BHIC. The evidence did not seek to

prove BHIC was an “outgrowth” of another entity. It

established that BHIC existed at the time of the contract

bidding.

Stipulations of fact bind the court and parties. Gander v.

Livoti, 250 F.3d 606, 609 (8th Cir. 2001); see also

Verkouteren v. District of Columbia, 346 F.2d 842, 844 n.2

(D.C. Cir. 1965). This is their very purpose, their “vital

feature.” 9 Wigmore, Evidence § 2590 (Chadbourn rev.

1981). Once a stipulation of fact is made, “the one party need

offer no evidence to prove it and the other is not allowed to

disprove it.” Id. § 2588. When the Government claimed that

BHIC existed since 1986, it directly contradicted the joint

stipulation that BHIC did not exist until after the bidding for

the three contracts.

The contradictory statements constitute substantial

prejudice to BHIC. In his opening argument, BHIC’s counsel

emphasized the stipulated fact, saying, “[I]f you remember

those key events, the last of those was in May 1991, more

than a year before BHIC begins its operations in July of 1992.

The plaintiffs do not and will not contest that BHIC did not

even come into existence, it didn’t even exist at the time that

Contracts 20A, 29 and 07 were bid and entered into.” We

agree with BHIC that allowing the Government to contradict

the stipulation called into question the credibility of BHIC’s

counsel, severely impeding counsel’s ability to effectively

advocate for his client. The district court recognized this

problem, but stated that it had “confidence that after hearing

33

testimony concerning the complex corporate restructuring

from which most of these defendants emerged, the jury was

able to appreciate the distinction between plaintiffs’ argument

[that BLH ultimately became BHIC] and the stipulated fact.”

563 F. Supp. 2d at 104 n.61. But we do not immediately see

what distinction separates the Government’s assertion that

“BHIC existed since 1986,” and the stipulated fact that

“BHIC did not exist at the time Contracts 20A, 29, 07 were

bid or entered into.” We therefore cannot conclude that the

jury made such a distinction. The district court abused its

discretion when it allowed the Government to contradict the

stipulation and thereby undermine BHIC’s defense. We

remand for a new trial for BHIC.

F. Precluding BIE from Contesting Liability

The district court held that BIE was estopped from

contesting liability under the FCA as to Contracts 20A and 29

because of its guilty plea in a separate criminal proceeding.

United States ex rel. Miller v. Bill Harbert Int’l Constr., Inc.,

2007 WL 851857, 2007 U.S. Dist. LEXIS 17667 (D.D.C.

Mar. 14, 2007). In February 2002, BIE pleaded guilty to an

indictment charging violations of the Sherman Act, 15 U.S.C.

§ 1, by its involvement in the bid-rigging conspiracy from

1988 to 1996. BIE contends that it was error to preclude it,

based on the doctrine of collateral estoppel, from contesting

liability under the FCA because a Sherman Act conspiracy

does not require an overt act, while an FCA conspiracy does.

Therefore, BIE argues, it might have been able to show that

although it was guilty of a Sherman Act violation, it was not

liable under the FCA. As BIE sees it, because collateral

estoppel affects only issues that were actually litigated and

necessarily decided in the first action, Jack Faucett Assocs. v.

Am. Tel. & Tel. Co., 744 F.2d 118, 125 (D.C. Cir. 1984),

issues relating to the overt acts necessary for the FCA

34

conspiracy were not precluded by the guilty plea in the

Sherman Act prosecution, which did not require the proof of

such acts. The district court disagreed, reasoning that the

overt acts BIE admitted in its guilty plea and accompanying

memorandum were essential to its Sherman Act plea because

they supplied the factual basis for the plea. Miller v.

Holzmann, 563 F. Supp. 2d 54, 80–81 (D.D.C. 2008). The

district court reasoned that the preclusive effects of a guilty

plea in a prior criminal proceeding extend not only to the

essential elements of the crime charged, but also to the facts

admitted in the accompanying Rule 11 proceeding. As the

court explained, Rule 11 “mandates that before entering

judgment on a guilty plea, a court must ‘mak[e] such inquiry

as shall satisfy it that there is a factual basis for the plea.’” Id.

at 79 (quoting Fed. R. Crim. P. 11(f) (brackets in the district

court opinion)). Thus, because the facts admitted in the Rule

11 proceeding are essential to the entry of judgment, it is

consistent with the underpinnings of the collateral estoppel

doctrine that a defendant should be precluded from

relitigating those facts as well as those related to the essential

elements of the crime. Therefore, the court concluded that

having admitted liability with respect to Contracts 20A and 29

in the previous proceeding, BIE was properly precluded from

contesting its liability for conspiracy with respect to those

contracts. Id. at 81.

We need not ultimately decide this issue. The district

court relied not only on collateral estoppel, but also on the

equitable doctrine of judicial estoppel, which states that if a

party successfully assumes a certain legal position in one

proceeding, “he may not thereafter, simply because his

interests have changed, assume a contrary position.” Id. at 81

n.14 (quoting Davis v. Wakelee, 156 U.S. 680, 689 (1895)).

As applied to BIE’s circumstances, the court found that BIE

was advancing a position contrary to the one the criminal

35

court relied on when it accepted BIE’s guilty plea, and that

judicial estoppel was therefore appropriate. Id.

Before this court, BIE has not asserted any error in this

alternative reason for estopping BIE. Because BIE has

forfeited the argument that the judicial estoppel was

erroneous, we need go no further in our analysis. Even if we

were to reject the district court’s reasoning on the collateral

estoppel theory, we would nonetheless affirm its ruling

precluding BIE from contesting liability. See Kauthar SDN

BHD v. Sternberg, 149 F.3d 659 (7th Cir. 1998) (“in

situations in which there is one or more alternative holdings

on an issue, . . . failure to address one of the holdings results

in a waiver of any claim of error with respect to the court’s

decision on that issue”).

G. Evidentiary Issues

The defendants argue the district court committed

reversible error in four evidentiary rulings: (1) admitting into

evidence against all defendants BIE’s prior guilty plea;

(2) allowing the Government to present expert testimony on

the economics of generic cartels; (3) allowing Luigi Ruggieri,

an officer of the company that received Contract 29, to testify

about his subordinate’s meeting with Peter Schmidt, a

Holzmann executive in Frankfurt; and (4) permitting the

Government to question a witness about the wealth of HII,

HC, and a related management company that was not a

defendant in this case. We review for abuse of discretion the

district court’s decisions to admit evidence. United States v.

Watson, 409 F.3d 458, 462 (D.C. Cir. 2005). However, to the

extent the defendants argue the district court misinterpreted

the Federal Rules of Evidence, we review those

interpretations de novo. United States v. Gewin, 471 F.3d

197, 200 (D.C. Cir. 2006). Applying those standards, we hold

36

that the district court did not err in the first two decisions. We

also hold that Ruggieri’s testimony was irrelevant to the

remaining Contract 20A claims, and therefore that claim is

moot. We do, however, hold that allowing the Government to

elicit evidence of HII and HC’s wealth constituted an abuse of

discretion. Therefore, claims against HII and HC must be

remanded for new trial.

1. BIE’s Guilty Plea

As explained above, see supra at 33, BIE pleaded guilty

to violating the Sherman Act, 15 U.S.C. § 1, by engaging in

the bid-rigging conspiracy. Pursuant to Rule 11 of the

Federal Rules of Criminal Procedure, BIE also submitted a

memorandum describing the conspiracy and BIE’s role. This

guilty plea and accompanying memorandum explained that

BIE and others rigged bids by “submitting bids on USAID-

funded Contracts 20A, 29 and 07” and “making payments to

co-conspirators who agreed to not compete for USAID-

funded contracts 20A and 08 pursuant to the bid-rigging

conspiracy.” Pl. Ex. 562A, at Joint App’x Pl. Exs. 568–69

(Joint Rule 11 Memorandum, United States v. Bill Harbert

Int’l, No. 01–00302 (N.D. Ala. Feb. 4, 2002), as redacted).

When the Government sought to introduce evidence of

BIE’s guilty plea in the district court, the defendants argued

that admitting the guilty plea and accompanying Rule 11

memorandum into evidence would improperly impute BIE’s

involvement to the remaining defendants. The district court

disagreed, concluding that the plea and accompanying

memorandum were evidence of the factual admissions

therein, and were therefore “relevant pieces of evidence that

are admissible against all defendants.” United States ex rel.

Miller v. Bill Harbert Int’l Constr., Inc., Civ. No. 95-1231,

slip op. at 4 (D.D.C. Mar. 21, 2007) (Mem. Op. & Order Den.

37

Mot. to Sever). Of course, the plaintiffs would “still bear the

burden of establishing a link between the ‘others’ who BIE

allegedly conspired with, and specific defendants in this

case.” Id. at 4 n.3. The court therefore allowed the

Government to use the plea in its opening statement and again

at the end of its case-in-chief, when counsel read the text of

the memorandum to the jury.

The defendants contend that this use of BIE’s guilty plea

should have been excluded as hearsay. They dispute the

plaintiffs’ contention that it is admissible under the hearsay

exception set forth in Federal Rule of Evidence 803(22).

They further argue that the danger of unfair prejudice

substantially outweighed its probative value. See Fed. R.

Evid. 403. We disagree.

Rule 803(22) permits a judge to admit “[e]vidence of a

final judgment, entered after a trial or upon a plea of guilty

. . . to prove any fact essential to sustain the judgment, but not

including, when offered by the Government in a criminal

prosecution for purposes other than impeachment, judgments

against persons other than the accused.” First, we note that

the exception to Rule 803(22)—the clause beginning “but not

including”—does not apply. Because this case is not a

criminal prosecution, the rule does not preclude introduction

of the plea documents as evidence of the judgment “against

persons other than the accused” (i.e., the other defendants) for

reasons other than impeachment. That is, because this is a

civil case, BIE’s guilty plea may be admitted under Rule

803(22) against all the defendants as long as the plea was

admitted “to prove any fact essential to sustain the judgment.”

The defendants argue the guilty plea was not admitted to

establish any fact. Instead, they assert, BIE’s guilty plea was

submitted only as evidence of the legal conclusion that BIE

38

was guilty of conspiracy. But the Rule 11 memorandum

clearly states more than the bare conclusion that BIE was

guilty. Instead, it asserts the several facts already mentioned:

that BIE and others submitted bids and made payments as part

of a bid-rigging conspiracy involving Contracts 20A, 29, and

07. Each of those facts is essential to sustain the legal

conclusion of BIE’s guilt under Section 1 of the Sherman Act,

and therefore fell within the scope of the rule. Other facts that

were not essential to that conclusion—such as specific

references to the defendants—were redacted by the district

court. See United States ex rel. Miller v. Bill Harbert Int’l

Constr., Inc., 2007 WL 842079, 2007 U.S. Dist. LEXIS

18560, at 3 (D.D.C. Mar. 16, 2007). We hold therefore that

the district court properly interpreted the scope of Rule

803(22) and properly admitted BIE’s guilty plea and Rule 11

memorandum under that rule.

Nor was the admission of BIE’s guilty plea improper

under Rule 403. Rule 403 states that relevant evidence may

be excluded if, inter alia, the evidence’s “probative value is

substantially outweighed by the danger of unfair prejudice,

confusion of the issues, or misleading the jury.” Fed. R. Evid.

403. But to quote the district court, “properly admitted but

potentially incriminating evidence does not equate to unfairly

prejudicial evidence that must be excluded.” United States ex

rel. Miller v. Bill Harbert Int’l Constr., Inc., Civ. No. 95-

1231, slip op. at 4–5 (D.D.C. March 21, 2007) (Mem. Op. &

Order Den. Mot. to Sever). In assessing prejudice and

probativeness, the district court, not this court, “is in the best

position to perform this subjective balancing.” United States

v. Cassell, 292 F.3d 788, 795–96 (D.C. Cir. 2002) (quoting

United States v. Washington, 969 F.2d 1073, 1081 (D.C. Cir.

1992)). We are therefore “extremely wary of second-

guessing” the district court, United States v. Law, 528 F.3d

888, 898 (D.C. Cir. 2008) (quoting Henderson v. George

39

Wash. Univ., 449 F.3d 127, 133 (D.C. Cir. 2006)), and review

its decision “only for ‘grave abuse,’” Cassell, 292 F.3d at 796

(quoting Washington, 969 F.2d at 1081).

BIE’s guilty plea did carry with it the potential to cause

prejudice or confuse the jury—it might have presumed that

the “co-conspirators” referred to in the plea were the other

defendants in the case. The district court recognized that

potential, acknowledging that the “documents pose certain

problems insofar as they refer to other parties who are

defendants here,” United States ex rel. Miller v. Bill Harbert

Int’l Constr., Inc., 2007 WL 842079, 2007 U.S. Dist. LEXIS

18560, at 3 (D.D.C. March 16, 2007), and that a jury might

assume the other parties were also guilty under BIE’s plea just

because the case caption listed them. Therefore, the court

struck any names other than BIE’s in the case caption and

elsewhere on the document. See id. With that redaction, the

court held that “the recitation of facts admitted to by BIE is

highly probative, and, under these conditions [of redaction],

poses relatively little risk of undue prejudice.” Id. at 3–4.

The court further mitigated the potential problem by twice

instructing the jury that “[t]he fact that BIE pleaded guilty

may not in any respect be considered against any other

defendants, nor may any inference be drawn against them by

reason of BIE’s plea of guilty.” Given these protective

measures against undue prejudice, the district court clearly

did not abuse its discretion in admitting against all defendants

the evidence of BIE’s guilty plea.

HII separately argues the guilty plea was particularly

prejudicial to it because the Government implied in its

opening statement that HII was trying to avoid responsibility.

According to HII, this implication would look particularly

reprehensible when juxtaposed with BIE’s guilty plea. The

jury, HII asserts, might have seen the guilty plea as evidence

40

of BIE “taking responsibility” while HII avoided doing the

same. Again, we disagree. HII’s argument rests on a short

passage from the Government’s opening statement, in which

counsel argued that “just because [HII] assigned [the

contracts] out to Harbert International Establishment, they

don’t assign away their responsibilities.” As the plaintiffs

argue, that brief comment did not suggest that HII had been

implicated in the earlier criminal case against BIE, but instead

noted only “that HII did not escape liability for its own

actions when it assigned Contracts 20A and 07 to BIE.”

Thus, the Government’s comment does not disturb our

holding that the district court did not abuse its discretion in

admitting against all defendants the evidence of BIE’s guilty

plea.

2. Expert Testimony on Cartels

Preston McAfee, a professor of economics and business

strategy at California Institute of Technology, testified for the

Government as an expert witness on how bid-rigging cartels

work. McAfee had no direct knowledge of the facts in this

case, and testified that he had not examined the evidence to

conclude whether there actually was any bid rigging in this

case. Instead, he testified about “how auction and bidding

work, how collusion in auctions work[s], and the incentives

that are created for seeking cost-reducing technologies.” For

example, he explained that an economically rational member

of a cartel must factor into its calculation of costs the risks

associated with bid rigging (i.e., being found out and

prosecuted). The cartel member’s bid must be higher than

that of a competitive bidder in order to cover those costs.

McAfee also explained what could be inferred from the

assumption that a cartel existed. For example, he testified that

if a cartel existed, one could infer that members of the cartel

must be able to successfully influence the bidding process if

41

they are to succeed in the object of the conspiracy—that is,

rigging the bids. But the individual who prepares the bid need

not know about the cartel, as long as that person is

“influenced by somebody who knows about the cartel.” In

sum, the professor explained that “[c]artels are formed . . . to

subvert competition and increase prices” and testified how a

cartel member achieves that purpose.

Rule 702 of the Federal Rules of Evidence provides that

“[i]f scientific, technical, or other specialized knowledge will

assist the trier of fact to understand the evidence or to

determine a fact in issue, a witness qualified as an expert by

knowledge, skill, experience, training, or education, may

testify thereto in the form of an opinion or otherwise.” Fed.

R. Evid. 702. However, not all scientific testimony is created

equal; some expert opinions are more helpful or more valid

than others. Recognizing this fact, in 1993, the Supreme

Court in Daubert v. Merrell Dow Pharmaceuticals, Inc., 509

U.S. 579 (1993), held that trial judges must act as gatekeepers

to exclude unreliable expert testimony. Under Daubert and

the Court’s further clarification in Kumho Tire Co. v.

Carmichael, 526 U.S. 137 (1999), testimony admitted under

Rule 702 must be both reliable and relevant. Id. at 152. In

2000, the Supreme Court amended Rule 702 to reflect the

Daubert line of cases, outlining general standards that the trial

court must use to assess the reliability and relevance of

testimony. An expert witness may therefore testify only “if

(1) the testimony is based upon sufficient facts or data, (2) the

testimony is the product of reliable principles and methods,

and (3) the witness has applied the principles and methods

reliably to the facts of the case.” Fed. R. Evid. 702.

The defendants moved in limine to exclude McAfee’s

testimony, arguing the testimony did not meet the standards of

Rule 702 because it was too broad, too generic, and based too

42

heavily on assumptions rather than analysis of the actual

evidence. They argued that McAfee’s testimony was not

related to the facts of the case. Instead, McAfee simply

assumed that a cartel actually existed between the defendants

and other companies in order to make his testimony relevant.

The defendants also stressed that McAfee had not tried to

determine whether a cartel existed in this case, even though

there are economics-based strategies to identify whether bids

are in fact collusive. Because of these weaknesses, McAfee’s

testimony would not assist the jury in understanding the

evidence as required by Rule 702.

The district court denied the motions, and reaffirmed and

explained its decision when it denied motions for a new trial.

In its opinion denying a new trial, the court explicitly held

that McAfee’s testimony satisfied the requirements of

Daubert and Rule 702. Miller v. Holzmann, 563 F. Supp. 2d

54, 96 (D.D.C. 2008). Quoting the advisory committee’s note

to Rule 702, the court stated that in some cases an expert may

give valuable testimony to the factfinder by explaining

general principles “without ever attempting to apply these

principles to the specific facts of the case.” Id. at 90 (quoting

Fed. R. Evid. 702 advisory committee’s note) (emphasis

omitted). According to the advisory committee’s note, “[f]or

this kind of generalized testimony, Rule 702 simply requires

that: (1) the expert be qualified; (2) the testimony address a

subject matter on which the factfinder can be assisted by an

expert; (3) the testimony be reliable; and (4) the testimony

‘fit’ the facts of the case.” Fed. R. Evid. 702 advisory

committee’s note. The district court initially held that

McAfee was a qualified expert. 563 F. Supp. 2d at 92 & n.40;

see also id. at 96 (listing McAfee’s credentials as evidence

that he was “well-qualified to testify on generally-accepted

economics principles”). The court then proceeded to analyze

McAfee’s testimony under the rest of the advisory

43

committee’s note’s rubric, first assessing relevance (addressed

by the second and fourth criteria), then reliability (addressed

by the third).

First, the district court held McAfee’s testimony to be

relevant. The testimony addressed a subject matter

appropriate for expert testimony—the second criterion under

the Rule 702 advisory committee’s note—because McAfee

explained complex processes and economic theory such as the

federal government’s procurement process, auction

incentives, and the effect of collusion on auctions. Id. at 92.

These topics “are precisely the sort of specialized, technical

matter concerning which a lay jury may benefit from a

qualified expert’s tutelage.” Id. The testimony also “‘fit’ the

facts of the case” as required by the fourth criterion. The

defendants argued that the assumptions on which McAfee

based his testimony were not based in the facts of the case,

and therefore did not “fit.” But the district court disagreed.

The court pointed out that, contrary to the defendants’

assertions, “McAfee never assumed that a cartel existed in

this case.” Id. at 94. Instead, McAfee made it clear he was

describing generic circumstances, “leaving the jury to

determine which scenario best ‘fit’ the facts in this case.” Id.;

see also id. at 94 n.45 (holding that McAfee’s testimony also

did not create unfair prejudice under Rule 403 because he

“repeatedly” explained he was not familiar with the facts, and

that he did not know whether collusion occurred here). His

testimony, while not derived from the facts in the case, was

sufficiently connected to the facts to be relevant and helpful to

the jury. Id. at 95.

Last, the district court turned to the third criterion—

reliability—noting that “the law grants a district court the

same broad latitude when it decides how to determine

reliability as it enjoys in respect to its ultimate reliability

44

determination.” Id. at 95 (quoting Kumho, 526 U.S. at 141–

42). Citing Daubert’s observations about how to determine

whether expert testimony is reliable—from whether a theory

has been subjected to peer review, to its potential rate of error,

to whether a theory is generally accepted in the relevant

field—the court determined that McAfee’s testimony was

reliable. Id. at 96. McAfee has published over twenty peer-

reviewed articles on his theories about the nature of auctions

and bidding. His testimony on economics “embodied basic

principles” that are “taught in undergraduate economics

courses” and “generally accepted in the field of economics.”

Id. Therefore, concluded the district court, McAfee’s

testimony satisfied the reliability criterion.

As the preceding summary of the court’s reasoning

demonstrates, the district court thoroughly and thoughtfully

analyzed the application of Rule 702 to McAfee’s testimony.

We also note that district courts have “broad discretion in

determining whether to admit or exclude expert testimony.”

United States v. Gatling, 96 F.3d 1511, 1523 (D.C. Cir. 1996).

The court clearly did not abuse that discretion.

The defendants also argue that McAfee’s testimony

should have been excluded under Rule 403 because the

professor used “highly charged terms” such as “cartel

member” and “colluders,” and even once made an analogy to

bank robbers. As Daubert explained, Rule 403 exclusion

based on unfair prejudice is particularly important in the case

of expert evidence, which “can be both powerful and quite

misleading because of the difficulty in evaluating it.” 509

U.S. at 595 (quoting Jack B. Weinstein, Rule 702 of the

Federal Rules of Evidence Is Sound; It Should Not Be

Amended, 138 F.R.D. 631, 632 (1991)). But, as explained

above, see supra at 38, the district court is best able to apply

the balancing test of Rule 403 and determine whether

45

evidence’s potential for undue prejudice substantially

outweighs its probative value. This is true for expert

testimony as well as for other types of evidence. Mindful,

therefore, of our responsibility not to second-guess the district

court’s application of the Rule 403 balancing test, we

conclude the district court did not improperly apply the rule

here. McAfee used terms descriptive of the theories he

explained, but he also repeatedly emphasized that he was not

applying the terms to the facts in this case or these defendants.

The district court did not abuse its discretion when it

determined that McAfee’s use of terms like “cartel members”

and “colluders” did not make his testimony’s potential for

undue prejudice substantially outweigh its probative value.

Indeed, it is difficult to conceive of expert testimony relevant

to the issues of this case in which the witness would not

employ terms like “cartel members” and “colluders.” We

note that Rule 403 provides the exclusion of evidence if its

“probative value is substantially outweighed by the danger of

unfair prejudice,” not simply “prejudice.” In some sense, any

evidence that is probative might be arguably prejudicial. That

is, the purpose of offering evidence is to influence the

decision of the jury. We can hardly say that the district court

abused its discretion by admitting expert testimony that used

terms entirely relevant to the issues at trial.

3. Ruggieri’s Testimony

Luigi Ruggieri was an officer of Asea Brown Boveri

Ltd., the parent company of Sadelmi U.S.A., Inc. (SUSA), the

company that received Contract 29. Over the objection of the

defendants, the district court allowed Ruggieri to testify about

a conversation he had with his subordinate, Giovanni

Greselin, about a meeting between Greselin and Peter

Schmidt, the Holzmann executive who hosted the conspiracy

meetings in Frankfurt. In his testimony, Ruggieri stated that

46

Schmidt met with Greselin and a “gentleman from Harbert” in

Frankfurt. There, Schmidt proposed to Greselin that they

agree on which of their companies would bid lower for

Contract 29, with compensation going to the losing bidder.

Ruggieri also testified, without objection from the defendants,

to his personal involvement in the conspiracy. He said that he

saw, then shredded, a document signed by Greselin outlining

the bid rigging between Harbert-Jones and SUSA. Ruggieri

then authorized Greselin to go ahead with the agreement and

pay Harbert-Jones a loser’s fee in cash.

Ruggieri’s testimony dealt only with the bid rigging of

Contract 29. We have already dismissed all the claims

against the defendants regarding Contract 29 for violation of

the statute of limitations. See supra at 24–25. The defendants

do not argue that the part of Ruggieri’s testimony to which

they object—his testimony about the conversation between

Greselin and Schmidt—tainted the jury’s consideration of the

remaining claims under Contract 20A or provided the only

link between any one of the defendants and the conspiracy

involving 20A. Therefore the defendants’ arguments

regarding the admissibility of Ruggieri’s testimony under Fed.

R. Evid. 801(d)(2)(E) are moot. We need not address them

here.

4. Evidence of HII and HC’s Wealth

Raymond Harbert is Bill Harbert’s nephew and CEO of

Harbert Management Company, a company formed in 1993

(after most of the underlying events in this case) that manages

assets for third parties, including HC. When Raymond

Harbert testified, Miller’s counsel asked him about the assets

of HII, HC, and Harbert Management Company. From the

exchange, counsel elicited that HII currently owns or is

associated with seven or eight power plants in California,

47

owns various cash assets, and makes approximately $40 to

$50 million in annual revenues. Raymond Harbert also

confirmed that between approximately 1990 and 1993, HII

sold somewhere between $250 million and $500 million in

assets, including selling its 50% ownership in BIE. Raymond

Harbert also testified that HC was a holding company with

assets in the form of stock in subsidiary companies, and that

Harbert Management Company currently manages over $100

million in assets for HC. He also testified that Harbert

Management Company manages assets for other Harbert

entities, including individuals of the Harbert family, for a total

of around $9 billion in assets. In its closing, the Government

recalled this testimony and juxtaposed the wealth of all the

Harbert companies with the relative poverty of those in

countries benefitting from projects funded by the USAID,

saying that the excess money the Government paid to the

conspirators “could have [been] used for less fortunate people

in other countries.”

Counsel for HII and HC objected to this testimony on the

grounds that information about the companies’ wealth was

both irrelevant and prejudicial, and reiterate this argument on

appeal. We agree. To be admitted, evidence must be

relevant. Fed. R. Evid. 402. That is, the evidence must have

a “tendency to make the existence of any fact that is of

consequence to the determination of the action more probable

or less probable than it would be without the evidence.” Fed.

R. Evid. 401. None of Raymond Harbert’s testimony

described above satisfies this definition. No fact concerning

the present size and scope of Harbert Management Company

was of consequence to the determination of the action. The

present size and scope of Harbert Management Company, a

company that was not a defendant and manages assets for

many non-defendants, including Raymond Harbert, his

mother, and other members of the Harbert family, had nothing

48

to do with the liability of any of the defendants or the measure

of damages. Indeed, the district court recognized this

irrelevance in its opinion denying a new trial, though it

deemed the irrelevant evidence not prejudicial. 563 F. Supp.

2d at 111 n.73. However, arguments to the jury about a

defendant’s wealth are grounds for new trial. Koufakis v.

Carvel, 425 F.2d 892, 902 (2d Cir. 1970) (“Remarks . . .

which can be taken as suggesting that the defendant should

respond in damages because he is rich and the plaintiff is

poor, are grounds for a new trial.”) (citing Washington

Annapolis Hotel Co. v. Riddle, 171 F.2d 732, 740 (D.C. Cir.

1948) (“A mistrial should have been declared on account of

these remarks [suggesting that the defendant should respond

in damages because it was rich and the plaintiff poor].”)).

Nor was evidence of the wealth of HII and of HC

relevant. The district court said the testimony concerning HII

and HC was properly admitted because it could help the jury

decide whether one company was the alter ego of the other, a

theory presented by the Government as a way to implicate HC

in the conspiracy. 563 F. Supp. 2d at 111. “Under the alter

ego theory, the court may ignore the existence of the

corporate form whenever an individual so dominates an

organization ‘as in reality to negate its separate personality.’”

Founding Church of Scientology of Wash., D.C., Inc. v.

Webster, 802 F.2d 1448, 1452 (D.C. Cir. 1986) (quoting

Quinn v. Butz, 510 F.2d 743, 758 (D.C. Cir. 1975)). Applied

to this case, HII would be the alter ego of HC: if the jury had

decided HII was part of the conspiracy, and that it was the

alter ego of HC, the jury could have found HC liable for the

conspiracy even if there was no direct evidence that HC had

itself joined the conspiracy. But the evidence described above

does not help establish whether HII was the alter ego of HC.

Instead, Raymond Harbert testified only as to how much

money HII made from selling assets in the 1990s, how much

49

money HII makes now, and how many assets HC now has.

Under Rule 401’s terms, the evidence made it no “more

probable or less probable” that one corporation was the alter

ego of the other. The only way the information could have

affected the jury was to prejudice it.

The Government and Miller argue before us that all the

testimony at issue was nonetheless admissible because the

counsel for HII and HC brought up the subject of its wealth

first, and in any case “the amount of wealth evidence elicited

and referred to at trial was not large and was not significant

enough” to warrant a new trial. We disagree on both points.

First, the plaintiffs cite only two references to support their

“But they started it!” argument: counsel’s opening and closing

statements.5 Neither reference is convincing. The first time

HII and HC’s counsel referenced the corporations’ money

was to point out Miller’s monetary interest in the case. This

is a perfectly acceptable point for counsel to make. Cf. United

States v. Smith, 232 F.3d 236, 242 (D.C. Cir. 2000)

(“Routinely, defense counsel cross-examines government

witness about an informant’s bias—whether it be a plea

5

In a footnote, the plaintiffs also cite two other statements to

support their assertion that HII and HC brought up their wealth

“throughout trial.” The first reference only obliquely touches on

those companies’ wealth when counsel asked Miller about wealthy

corporations in general. Nothing was said about HII or HC in

particular. The second reference is even less pertinent. There,

counsel asked a witness if she thought John Harbert, Bill Harbert’s

nephew who was also involved in the Harbert companies, ever “felt

that he needed to investigate or look over the shoulder of Mr. Bill

Harbert.” In response, the witness testified the two might have been

a little suspicious of each other and recalled that John Harbert spent

a lot of money on his hunting dogs. Whatever insight that

testimony gave into the relationship between those two men, it had

nothing to do with HII and HC’s wealth.

50

agreement, a financial arrangement, or both.”); 3 Federal Jury

Practice and Instructions § 101.43 (5th ed.) (jury instruction

stating that, in assessing the credibility of a witness, jury may

consider whether the witness has any bias or prejudice). It is

unrelated to the testimony later elicited by the plaintiffs about

the various Harbert companies’ wealth. Even less convincing

is the plaintiffs’ reliance on counsel’s closing statements,

which of course came after the plaintiffs had already elicited

Raymond Harbert’s testimony.

As for the argument that there was not enough prejudice

to warrant a new trial, again we disagree. Evidence need not

be reinforced and reiterated again and again for it to be

prejudicial enough to warrant a new trial. Here, it is enough

that there were several inappropriate references to multiple

different companies’ wealth, especially given that the

Government’s counsel emphasized the wealth of the Harbert

companies in his closing statement and insinuated that the

money would be in better hands if it were taken from the

defendants. We therefore vacate the judgments with respect

to HII and HC and remand for a new trial for those two

defendants.

H. Sufficiency of the Evidence

Finally, the defendants argue that the evidence was

insufficient to support the jury verdict. Given our resolution

of the foregoing issues, however, we need address only the

arguments made by HUK and BIE. See Part II.D (claims

against Anderson, which were limited to Contract 29, are

time-barred); Part II.E (Government’s contradiction of

stipulation regarding BHIC requires new trial); Part II.G.4

(evidence of HII and HC’s wealth requires new trial).

The jury found HUK liable for conspiracy, as well as for

substantive FCA violations with respect to Contract 20A. To

51

hold HUK liable for conspiracy, the jury must have found (1)

that an agreement existed to have false or fraudulent claims

allowed or paid by the United States; (2) that HUK willfully

joined that agreement, either at the conspiracy’s inception or

afterwards; and (3) that one or more conspirators knowingly

committed one or more overt acts in furtherance of the object

of the conspiracy. See Miller v. Holzmann, 563 F. Supp. 2d

54, 114 n.83 (D.D.C. 2008); see also, e.g., Halberstam v.

Welch, 705 F.2d 472, 478 (D.C. Cir. 1983) (describing the

elements of common law civil conspiracy). HUK challenges

all three findings. Although estopped from challenging its

liability, see Part II.F, BIE joins HUK in contending that the

jury erred in its calculation of damages.

The district court denied the defendants’ motion for

judgment as a matter of law with respect to the sufficiency of

the evidence. Although we review that decision de novo, we

“do not . . . lightly disturb a jury verdict.” McGill v. Muñoz,

203 F.3d 843, 845 (D.C. Cir. 2000). We “draw all reasonable

inferences in favor of the nonmoving party and . . . may not

make credibility determinations or weigh the evidence.”

Reeves v. Sanderson Plumbing Prods., Inc., 530 U.S. 133,

150 (2000). We “disregard all evidence favorable to the

moving party [here, the defendants] that the jury is not

required to believe,” id. at 151, and will reverse a jury’s

decision “only if the evidence and all reasonable inferences

that can be drawn therefrom are so one-sided that reasonable

men and women could not have reached a verdict in

plaintiff[s’] favor.” McGill, 204 F.3d at 845 (internal

quotation marks omitted).

1. Overarching Conspiracy

The plaintiffs alleged and the jury found an overarching

conspiracy spanning Contracts 20A, 29, and 07. HUK

52

contends that the evidence does not support this finding and

that we must therefore reverse both the conspiracy and

substantive verdicts against it. We must reverse the

conspiracy verdict, HUK urges, because record evidence

shows only that Peter Schmidt “was involved in three separate

and distinct episodes of discussing bid-rigging.” Citing

Kotteakos v. United States, 328 U.S. 750, 774 (1946), the

defendants also argue that we must reverse the substantive

verdict because the overarching conspiracy theory created

“dangers of transference of guilt from one [defendant] to

another.” In other words, HUK argues, the jury may well

have relied on its conspiracy verdict to hold HUK liable for

substantive FCA violations based on the actions of its co-

conspirators. See Halberstam, 705 F.2d at 481.

As we explained in United States v. Tarantino, 846 F.2d

1384, 1393 (D.C. Cir. 1988), a jury must consider three

factors to determine whether potentially connected conduct

constitutes an overarching conspiracy: (1) “whether the

conspirators share[d] a common goal”; (2) “the degree of

dependence inherent in the conspiracy”; and (3) “the overlap

of participants” between the arguably separate schemes.

Pointing out that Tarantino involved a drug conspiracy, HUK

argues that this framework is inapplicable, or at least more

demanding, where, as here, the conspiracy is of a commercial

nature. But we have repeatedly applied this three-part inquiry

to non-drug conspiracies without altering its contours. See,

e.g., United States v. Hemphill, 514 F.3d 1350, 1363–64 (D.C.

Cir. 2008) (single conspiracy to steal from Washington

Teachers Union); United States v. Gatling, 96 F.3d 1511,

1520 (D.C. Cir. 1996) (single conspiracy to commit bribery in

connection with illegal issuance of section 8 housing

subsidies); cf. United States v. Anderson, 326 F.3d 1319,

1327–28 (11th Cir. 2003) (applying this three-part framework

and upholding a jury finding of an overarching conspiracy in

53

Anderson’s criminal case on the same facts as in the case

before us). To apply that test to the overarching conspiracy

the jury found in this case, we must consider testimony and

evidence regarding the bidding on each contract even though,

as explained in Part II.A.2, Contracts 29 and 07, by

themselves, cannot give rise to substantive liability against

any defendant. Cf. Hemphill, 514 F.3d at 1363–64

(considering evidence relating to multiple schemes as proof of

one overarching conspiracy).

In assessing the first factor—whether defendants

involved in allegedly conspiratorial conduct shared a common

goal—“a conspiracy’s purpose should not be defined in too

narrow or specific terms.” Gatling, 96 F.3d at 1520. Thus,

we have found “obtaining money in exchange for

[government] subsidies,” id., and “steal[ing] money from [a]

union,” Hemphill, 514 F.3d at 1364, to be sufficiently specific

common purposes. Reviewing the evidence, the district court

determined that the jury could have reasonably found an

overarching conspiracy with a common purpose of “limiting

competition” in bidding on projects in Egypt funded by the

USAID. Miller, 563 F. Supp. 2d at 138–139 & n.131. We

agree.

The jury heard testimony revealing just such a common

purpose, including for example Anderson’s statement that all

prequalified contractors working in Egypt were part of a

“Frankfurt Club” that “set up” the bids on Egyptian contracts.

John Ollis, Vice President of Holzmann, inferred from

Anderson’s comments that “the jobs that we were bidding,

there had been some kind of arrangements made among the

bidders to collaborate on how much would be bid. In the

vernacular, bid-rigging.” The defendants contend that even if

the other participants shared the common goal of limiting

competition in Egypt, “Schmidt had a separate goal—pursing

54

Holzmann’s interests in Europe.” In support, they point to

testimony that Schmidt offered to make a trade with SUSA, a

prequalified bidder on Contract 29, under which SUSA would

win that contract in exchange for Harbert-Jones winning a

later contract in Europe. During the second Contract 29

meeting, however, Schmidt abandoned this plan, and in any

event, Schmidt’s fleeting desire to use the conspiracy to

accomplish an additional goal is insufficient to undermine the

jury’s finding of a common purpose across all three contracts.

The second factor, interdependence, requires that each

defendant’s actions “facilitate the endeavors of other alleged

coconspirators or facilitate the venture as a whole.” United

States v. Carnagie, 533 F.3d 1231, 1238 (10th Cir. 2008)

(internal quotation marks omitted); see also Tarantino, 846

F.2d at 1392–93. We have upheld a jury’s finding of

interdependence where “the assistance one branch of a

conspiracy provides to another is fairly minimal” and where

“given the overlap in participation and timing . . . accusations

relating to one of the schemes could trigger an investigation

that would lead to exposure” of the others. Gatling, 96 F.3d

at 1522. This standard is clearly satisfied here. For one thing,

a written bid-rigging agreement between Holzmann and

Archirodon (Fuller’s parent company) regarding Contract

20A expressly contemplated future collusion on Contract 29.

Similarly, a SUSA manager testified that Schmidt offered

SUSA a deal in which “the loser” on Contract 29 would bid

high on that contract and “the winner” would compensate “the

loser” “in kind,” by bidding high on another “contract[] to be

bid in Egypt similar to [Contract 29].” The jury could also

have reasonably inferred interdependence from financial

statements for the “Harbert-Jones Egypt Joint Venture,”

which included Contract 20A, Contract 07, and other projects.

55

The third factor—overlap among participants—is “less

significant” than the others, requiring “only that the main

conspirators work with all the participants.” Hemphill, 514

F.3d at 1363 (citing United States v. Mathis, 216 F.3d 18, 23–

24 (D.C. Cir. 2000)). Again, record evidence satisfies this

standard. The defendants concede that Schmidt, on behalf of

Jones and its parent company, Holzmann, was involved in all

three contracts. The jury also heard evidence (1) that another

prequalified bidder, Fru-Con (through its parent company,

Bilfinger & Berger), received payoffs for cooperating on

Contracts 20A and 07; (2) that BIE admitted conspiring to rig

bids on Contracts 20A and 29; and (3) that Anderson

participated in meetings on Contracts 20A and 07, may well

have participated in a meeting on Contract 29, and had

authority over all three contracts. Thus, the jury could have

reasonably concluded that Schmidt and possibly Anderson

worked with all participants and that BIE and HII (through

Anderson) were directly involved in rigging bids on multiple

contracts. The defendants respond that with the exception of

Schmidt and Anderson, each individual met with competitors

to discuss but one contract. True enough, but because the

conspiracy was between corporations, the identity of the

individuals representing those corporations at bid-rigging

meetings is irrelevant. In sum, then, sufficient evidence

supports the jury’s finding of an overarching conspiracy.

2. HUK’s Involvement in the Conspiracy

Even if a reasonable jury could have found an

overarching conspiracy, HUK insists that the evidence is

insufficient to show that it willfully joined that conspiracy. In

evaluating this argument, we note that “in most civil

conspiracy cases,” the jury “ha[s] to infer an agreement from

indirect evidence.” Halberstam, 705 F.2d at 486. A jury may

infer that a defendant willfully joined the conspiracy if he

56

understood the scheme’s “essential nature and general scope.”

Hobson v. Wilson, 737 F.2d 1, 52 (D.C. Cir. 1984) (internal

quotation marks omitted), overruled in part on other grounds

by Leatherman v. Tarrant County Narcotics Intelligence &

Coordination Unit, 507 U.S. 163 (1993). Under basic

principles of agency law, corporate defendants are charged

with constructive knowledge of all material facts that their

agents and officers learn in the scope of their employment.

See 2 William Fletcher, Cyclopedia of the Law of

Corporations § 790 (2010); see also BCCI Holdings

(Luxembourg), S.A. v. Clifford, 964 F. Supp. 468, 478 (D.D.C.

1997). Thus, to uphold the jury’s finding that HUK joined the

conspiracy, we must be sure that the record contains sufficient

evidence for the jury to have reasonably found that (1) an

HUK employee, officer, or director knowingly joined the

conspiracy and (2) in so doing, acted within the scope of his

HUK duties.

At trial, the plaintiffs presented testimony and evidence

that revealed HUK’s involvement in bidding on Contract

20A. In April 1988, the USAID and an Egyptian government

agency called the Cairo Wastewater Organization solicited

bids on Contract 20A from three prequalified contractors:

George A. Fuller Co. (Fuller); Fru-Con Construction

Company; and the Harbert-Jones 20A Joint Venture.

A month later, Schmidt invited a group of prequalified

contractors to meet in Frankfurt. Schmidt suggested that the

others bid high on Contract 20A in exchange for a payoff.

Although no agreement was reached at that meeting, several

weeks later Schmidt and an executive of Bilfinger & Berger

(B&B) (Fru-Con’s parent company) agreed that Fru-Con

would submit a high bid in exchange for a payoff equivalent

to 2–3% of the contract value.

57

The Harbert-Jones joint venture convened a bid

reconciliation meeting in June. Jones’s estimator, Carl Nagel,

proposed that Harbert-Jones bid $95.2 million. Ian Young,

HUK’s lead estimator, represented Harbert at the meeting,

where the Harbert team suggested to the Jones team that they

include more conservative estimates. Based in part on these

suggestions, the two sides initially agreed to bid $103 million.

After Anderson arrived at the meeting and once additional

“philosophy changes,” including more expensive methods of

construction, were incorporated into the bid, the joint proposal

increased to $130 million. Shortly thereafter, Harbert-Jones

submitted a $125 million bid, which Young signed.

On August 3, the final day to submit bids, Schmidt and

an officer of Fuller’s parent, Archirodon, signed a written

agreement stipulating that Fuller would refrain from bidding

on Contract 20A in exchange for Archirodon receiving either

5% of the contract value or 3% and a subcontract. In

addition, Holzmann committed to “caus[ing]” Harbert-Jones

to “reciprocate” by helping Fuller obtain another contract of

similar value from the USAID, such as Contract 29. On the

same day, Young directed that the Harbert-Jones bid be

increased by 3.5%, to $129 million.

The bids were opened the next day. Fru-Con had bid

$152 million, Harbert-Jones had bid $129 million, and Fuller

had not bid at all. Although the lower of the bids, Harbert-

Jones’s was substantially higher than the project’s consultant

had expected. As a result, the Cairo Wastewater Organization

and the USAID opted to scale down the contract and solicit

re-bids.

In December, Anderson, Schmidt, and Archirodon

representatives met to discuss the new round of bidding. In a

handwritten addendum to the August agreement, they agreed

58

that Fuller would receive a subcontract worth at least $2.5

million plus $500,000 cash. Later that month, Fru-Con bid

$139 million for the scaled-down version of Contract 20A,

and Harbert-Jones bid $115 million. Harbert-Jones won the

contract, eventually submitting 33 invoices totaling over $107

million.

In January 1990, Schmidt, Anderson, and a representative

from Archirodon negotiated a payment schedule for the

agreed-upon $3 million payoff. Holzmann made payments to

Archirodon over the next year. Testimony and other evidence

suggest that Harbert-Jones funneled money for these payoffs

through HUK. For example, Holzmann billed HUK for

services it never requested nor received, and HUK paid those

invoices.

According to HUK, this evidence is insufficient to

support the jury’s finding that the company agreed to join the

overarching conspiracy. We disagree. The jury could have

reasonably concluded that Ian Young, HUK’s lead estimator,

knowingly joined the conspiracy on behalf of HUK.

Specifically, Young’s interactions with Roy Anderson, his

behavior at the Harbert-Jones bid-reconciliation meeting, and

his involvement in increasing the bid on the same day that

Schmidt secured Archirodon’s no-bid promise all suggest he

knowingly joined the conspiracy while acting within the

scope of his employment for HUK.

The jury had reason to believe that Anderson knew of the

conspiracy by the time of the June 1988 bid-reconciliation

meeting. Specifically, it heard testimony and viewed

evidence that Anderson was the Vice President of HII, the

60% partner in the joint venture; that he was the “lead man”

on the Egypt jobs; that he held powers of attorney from the

President of HII, Bill Harbert, authorizing him “without

59

reservation” to represent HII in the bidding; and that he may

have been present at the May 1988 meeting in which Schmidt

proposed the bid-rigging scheme, see Miller, 563 F. Supp. 2d

at 116 n.87 (“In light of Anderson’s explicit status as HII’s

point-man in Europe for international contracting and his

attendance at the December 1988 renegotiation with Fuller, it

would be reasonable to infer that if a HII representative

attended the May meeting, it would have been Anderson.”).

The jury also heard evidence suggesting that Anderson could

have passed his knowledge along to Young: Colin Towsey,

the Managing Director of HUK, testified that Anderson and

Young “had interactions . . . with respect to the bidding on

Contract 20A,” and “had discussions about what the

estimating work would be.”

In addition, the jury could have reasonably inferred that

Young knew of the conspiracy based on evidence that he

sought to increase the bid at the Harbert-Jones bid

reconciliation meeting. Nagel, Jones’s estimator, testified that

although Jones’s pre-meeting proposal was $95.2 million,

Young’s “arm twist[ing]” “pressured” the Jones team to

include more expensive methods of construction, thus

significantly increasing the bid, first to $103 million and later,

after Anderson’s arrival, to $130 million. Nagel testified that

he thought that even the $103 million figure was “inflated.”

According to Nagel, the Jones team deferred to Young

because Harbert was the majority owner of the joint venture,

giving Harbert “the hammer” in the negotiations. Similarly,

Young’s August 3 order to increase the bid by 3.5%—the

same day Schmidt secured a no-bid agreement from

Archirodon—could also lead a reasonable jury to conclude

that he knew about the bid rigging. Reinforcing these

inferences, the plaintiffs’ expert explained that in order to

make collusive agreements profitable, managers must exert

influence on the prices their companies set.

60

HUK challenges this view of the evidence, arguing that

an innocent explanation supports Young’s actions and that

“[c]onduct that is as consistent with other equally plausible

explanations as with illegal conspiracy, without more, does

not support an inference of conspiracy.” See Matsushita Elec.

Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986);

Monsanto Co. v. Spray-Rite Serv. Corp., 465 U.S. 752, 768

(1984). According to HUK, at the bid-reconciliation meeting

Young simply believed that more conservative construction

techniques should be used. This explanation is bolstered,

HUK tells us, by Nagel’s statement on cross-examination that

reasonable and experienced estimators could disagree about

the need for such methods. Similarly, HUK contends that

Young’s August 3 order to increase the bid by 3.5% was

completely innocent—the letter was one of two prepared in

advance to deal with volatile steel prices. As the district court

observed, however, these arguments largely ignore the

standard of review for sufficiency challenges: “In essence,

HUK merely posits that another—in its opinion, better—

explanation of the facts exists. But at this stage in the

litigation, the relevant question is whether the view adopted

by the jury in reaching its verdict was at all reasonable.”

Miller, 563 F. Supp. 2d at 121 n.98 (citing Anderson v.

Liberty Lobby, Inc., 477 U.S. 242, 251 (1986)). Here the jury

had sufficient evidence to conclude that Young’s efforts to

increase the bid were motivated by knowledge of a bid-

rigging conspiracy. Moreover, in crediting the plaintiffs’

version of the facts over HUK’s more innocent explanation,

the jury would have had no need to speculate, as HUK claims

it did. Testimony regarding Young’s interactions with

Anderson, the existence of a bid-rigging agreement between

Harbert-Jones and Fru-Con, the timing of Young’s actions,

and the expert testimony about collusive agreements all

support the jury’s inference that Young knowingly joined the

conspiracy. Cf. Matsushita, 475 U.S. at 596–97 (where

61

plaintiffs fail to show that defendants had any plausible

motive to engage in conspiracy, conduct consistent with other,

equally plausible explanations does not give rise to an

inference of conspiracy).

Sufficient evidence also supports the jury’s finding that

Young acquired knowledge of the conspiracy while acting

within the scope of his employment for HUK. Not only was

Young an HUK employee when Contract 20A was bid, but in

his testimony, Colin Towsey, HUK’s Managing Director,

revealed that Young worked on the bid as part of his HUK

employment. HUK counters that Towsey’s testimony

suggests that during the relevant period Young was actually

working for BIE, HUK’s 49% owner. But Towsey’s

testimony establishes only that HUK “provide[d] some

engineering and estimating support” to BIE. Towsey never

said that Young worked primarily or exclusively for BIE; in

fact, Towsey indicated that Young worked in HUK’s London

office during this time, that he remained on HUK’s payroll,

and that “[h]e was certainly the head of [HUK’s] estimating

team” in connection with Contract 20A. Thus, based on

Towsey’s testimony the jury could have reasonably found that

Young learned of the conspiracy and contributed to it in his

capacity as an HUK employee. In sum, then, Young’s actions

provided sufficient evidence for the jury to conclude that

HUK knowingly joined the conspiracy.

HUK next challenges the jury’s finding that it committed

substantive FCA violations, i.e., that it “knowingly

present[ed], or cause[d] to be presented, a false or fraudulent

claim” and “knowingly ma[de], use[d], or cause[d] to be

made or used, a false record or statement material to a false or

fraudulent claim” with respect to Contract 20A. 31 U.S.C.

§ 3729(a). We have no need to address this argument.

Because the jury had sufficient evidence to find that HUK

62

conspired to submit false bids, supra at 58, HUK was liable

for its co-conspirators’ foreseeable actions in support of the

conspiracy. See, e.g., Halberstam, 705 F.2d at 481. And as

explained in Part II.G.1, BIE’s admission that it both

conspired to and did submit false claims with respect to

Contract 20A was properly admitted against all of the

defendants. That admission thus provides sufficient evidence

for the jury to have found HUK liable for false claims

submitted on Contract 20A. We therefore turn to the

defendants’ challenges to the jury’s calculation of damages.

3. Damages

As the parties agree, the measure of damages is the

difference between what the United States paid and what it

would have paid had there been no bid-rigging agreement.

Because the plaintiffs’ claims on Contracts 29 and 07 are

barred by the statute of limitations, see Part II.A.2, we need

consider damages only as to Contract 20A. After being

instructed on the proper standard, the jury awarded damages

of $29.9 million on that contract. HUK and BIE challenge the

award on two independent grounds. First, they contend that

the plaintiffs presented insufficient evidence to support the

jury’s finding. Second, they argue that the district court

permitted the plaintiffs to argue an improper damages theory

to the jury and that this error requires a new trial.

Regarding the sufficiency of the evidence, the defendants

assert that “plaintiffs failed altogether to prove that USAID

incurred [any] loss” from the bid rigging on Contract 20A.

This claim rests on the contention that no defendant attended

the bid-rigging meetings led by Schmidt on behalf of

Holzmann—indeed, that no defendant even knew about the

meetings—and that Harbert-Jones therefore could not have

raised its bid based on Schmidt’s agreements with the other

63

Contract 20A bidders. Our earlier discussion explains why

this argument fails: a reasonable jury could have concluded

that Anderson and Young, representing the Harbert side of the

Harbert-Jones venture, knew about the bid-rigging plan when

they attended the venture’s June 1988 bid-reconciliation

meeting and that, based on that knowledge, they aggressively

advocated a higher bid.

Moreover, the jury heard substantial evidence that the

payment Harbert-Jones ultimately received for its work on

Contract 20A was well above what it could have obtained

through a competitive bidding process. Although the joint

venture’s bid rose and fell several times between the June

1988 bid reconciliation meeting and the final award of the

contract, in the end, executives at Jones described their profits

as “exorbitantly wonderful.” Indeed, the plaintiffs’ expert

testified that Harbert-Jones reaped profits of 52%; other

witnesses testified that the norm for construction jobs of this

type is 7 to 15%. The plaintiffs’ expert also detailed several

complicated financial transactions that BIE undertook to hide

$25 million of this profit. Contrary to the defendants’

argument, it required no speculation for the jury to conclude

that the defendants overcharged on Contract 20A.

As to the amount of the award, the defendants argue that

even if the plaintiffs successfully proved some degree of bid

inflation, “there is no correlation between the $29,920,000

jury award and any of the various amounts plaintiffs urged the

jury to assess.” When considering a sufficiency of the

evidence challenge to a jury’s damages award, “[o]ur inquiry

ends once we are satisfied that the award is within a

reasonable range and that the jury did not engage in

speculation or other improper activity.” Carter v. Duncan-

Huggins, Ltd., 727 F.2d 1225, 1239 (D.C. Cir. 1984).

Especially in a case like this, “[w]here the jury finds a

64

particular quantum of damages and the trial judge refuses to

disturb its findings,” we must be “certain indeed that the

award is contrary to all reason” before reversing the jury and

the district court. Id. (internal quotation marks omitted). And

in determining what constitutes a “reasonable range” for the

jury’s award, we make allowances for the fact that the

defendants’ own misconduct has foreclosed any exact

calculation of what a competitive bid would have been on

Contract 20A. See Bigelow v. RKO Radio Pictures, Inc., 327

U.S. 251, 264 (1946) (“[W]here the defendant by his own

wrong has prevented a more precise computation, the jury

may not render a verdict based on speculation or guesswork[,]

[b]ut [it] may make a just and reasonable estimate of the

damage based on relevant data.”).

At trial, the plaintiffs suggested several methods for

estimating the extent of the bid inflation on Contract 20A.

We highlight two, each of which demonstrates that the jury’s

award falls “within a reasonable range.” Carter, 727 F.2d at

1239.

First, the plaintiffs urged the jury to begin with the

defendants’ actual final costs on Contract 20A of $52 million,

and then add a generous 25% profit margin (as described

above, the jury heard testimony that profit on a contract like

20A would normally have been 7 to 15%), thus yielding a

final bid of $65 million. Since Harbert-Jones ultimately

submitted invoices totaling $107 million, this calculation

suggested damages of $42 million ($107 million minus $65

million), comfortably above the jury’s actual $29.9 million

award.

Alternatively, the plaintiffs suggested that the jury could

estimate the competitive bid amount for the final Contract

20A specification by starting with either of two “free of

65

influence” estimates for the original, larger version of the

contract, and then discounting whichever estimate it chose for

the subsequent scope of work changes. The two estimates the

plaintiffs suggested as a baseline were: (1) $95 million, the

bid proposal prepared by Jones before its June 1988

reconciliation meeting with the Harbert side of the venture,

and (2) $80 million, the bid amount apparently considered by

Fuller before deciding not to bid on Contract 20A.

Proportionately reduced for the subsequent changes to

Contract 20A that led Harbert-Jones to lower its bid from

$129 to $115 million (an 11% reduction), these estimates

suggest that the competitive bid amount on the final contract

would have been between $71 and $85 million, indicating

damages of $22 to $36 million. The jury’s actual award—

$29.9 million—falls squarely within this range. The jury’s

award thus easily survives our deferential standard of review.

Finally, the defendants argue that the district court

allowed the plaintiffs to present an improper damages theory

to the jury. Specifically, they contend that by allowing the

plaintiffs’ counsel to refer occasionally to the proper measure

of damages as what the Government “should” have paid

rather than what it “would” have paid absent the bid rigging,

the district court allowed the plaintiffs to suggest that the jury

calculate damages by disgorging the defendants’ Contract

20A profits. Cf. United States ex rel. Harrison v.

Westinghouse Savanna River Co., 352 F.3d 908, 923 (4th Cir.

2003) (finding disgorgement of all government payments on a

fraudulently obtained contract to be an inappropriate remedy

under the FCA). “[W]here a jury was permitted to consider

an improper standard of damages,” the defendants argue, “the

reviewing court must reverse unless it can be assured that the

verdict was not based on [the] erroneous standard.” In its

post-trial order, however, the district court pointed out that its

jury instructions set out the proper damages standard and

66

found that these instructions “eliminated any confusion

engendered by plaintiffs’ counsel[].” 563 F. Supp. 2d at 108

n.68.

Reviewing the district court’s denial of a new trial for

abuse of discretion, we find none. To begin with, we doubt

very much that the few offhand references to what the

Government “should have paid” could have misled the jury.

As the plaintiffs point out, “what the Government ‘should

have paid’ can readily be understood as what the Government

ought to have paid on the contracts absent Defendants’

wrongdoing.” Indeed, in describing the proper measure of

damages in his closing argument, the plaintiffs’ counsel used

the phrase “should have paid” in just this way: “[T]he

measure of the damage will be . . . that difference between

what [the Government] paid and what [it] should have paid if

the bidding had not been rigged and the competition had been

free, robust, and vibrant.” But even if these scattered “should

have paid” references may have confused the jury, we agree

with the district court that its instructions eliminated any

prejudice. The court explained to the jurors that “the measure

of damages to the United States is the difference between

what the United States paid and what it would have paid had

there been no bid-rigging agreement.” As the district court

was entitled to presume that the jurors “follow[ed] the

instructions they [were] given,” United States v. Mouling, 557

F.3d 658, 665 (D.C. Cir. 2009), its denial of the defendants’

motion for a new trial was well within its discretion.

III. Conclusion

For the foregoing reasons we (1) vacate the judgment of

the district court, pursuant to the statute of limitations, with

respect to the claims concerning Contracts 07 and 29; (2)

vacate the judgment against the defendants HII, HC, and

67

BHIC and remand the matter for a new trial because the

district court erred in admitting testimony about the wealth of

HII and HC and statements contrary to the stipulation about

BHIC’s existence; and (3) affirm the judgment with respect to

the claims concerning Contract 20A against the remaining

defendants, namely BIE and HUK.

So ordered.

TATEL, Circuit Judge, dissenting from Parts II.A.2 and

II.G.4: In Part II.A.2 the court finds the Government‘s claims

on Contracts 29 and 07 barred by the False Claims Act‘s

statute of limitations, and in Part II.G.4 it rules that testimony

and evidence regarding the defendants‘ wealth was so

prejudicial as to require a new trial for HII and HC. I

respectfully dissent from both rulings.

I.

Under the False Claims Act (FCA) as recently amended,

the Government‘s complaint in intervention inherits the filing

date of the qui tam relator‘s complaint that initiated the action

―to the extent that the claim of the Government arises out of

the conduct, transactions, or occurrences set forth, or

attempted to be set forth, in the prior complaint.‖ 31 U.S.C.

§ 3731(c). In this case, the ―conduct, transactions, or

occurrences set forth, or attempted to be set forth‖ in Richard

Miller‘s 1995 complaint involved a Frankfurt-based

conspiracy to rig bidding for multiple USAID contracts in

Egypt. This court denies relation back of much of the

Government‘s complaint in intervention because two

contracts the Government alleges were part of that

conspiracy, Contracts 29 and 07, were not mentioned in

Miller‘s original complaint. Yet in the very first sentence in

which Miller described the conduct at issue, he left no doubt

that he was accusing the defendants of fraud spanning more

than one USAID project: ―Defendants conspired to rig the

bidding for construction contracts paid for by the United

States Agency for International Development.‖ Miller

Compl. ¶ 1 (emphasis added). Emphasizing that he was

alleging fraud involving more than one contract, he continued,

―The particular transaction about which most is known is

Contract 20A.‖ Id. (emphasis added). After detailing the bid

rigging on Contract 20A, id. ¶¶ 1, 15–30, Miller again made

clear that the conspiracy he was alleging was not limited to

that particular contract: ―Plaintiff has received information

2

that there was a ‗club‘ in Frankfurt, Germany of contractors

qualified to perform AID contracts in Egypt; the club was

organized to control prices in what should have been full and

open competition for AID contracts.‖ Id. at ¶ 33. Indeed,

Miller predicted that discovery would uncover additional

rigged contracts: ―Upon information and belief, discovery in

this case will reveal that other AID contracts in Egypt were

subject to similar and related collusive agreements on price

that resulted in the submission of other false or fraudulent

claims to the U.S. Government.‖ Id. Finally, in the

complaint‘s formal counts, Miller neither mentioned Contract

20A nor limited his claim for damages to the allegedly false

claims on that contract (estimated earlier in the complaint at

$40 million). Instead, he ―incorporate[d] the allegations of‖

the preceding paragraphs by reference, id. ¶¶ 34, 37, including

the allegation of ―other false or fraudulent claims‖ arising

from ―other AID contracts in Egypt,‖ id. at ¶ 33, and sought

―actual damages in an amount to be proven at trial,‖ id. ¶¶

36, 39.

From the face of Miller‘s complaint, it is thus clear that

the ―conduct, transactions, or occurrences set forth, or

attempted to be set forth‖ encompassed bid-rigging not just on

Contract 20A (identified by Miller in his original complaint)

but also on Contracts 29 and 07 (later added by the

Government in its complaint in intervention). The

Government‘s claims on Contracts 29 and 07 ―arise[] out of‖

the Frankfurt-based bid rigging conspiracy originally alleged

by Miller—indeed, the ―collusive agreements‖ on these

contracts were precisely what Miller predicted discovery

would unearth. Id. ¶ 33. For this reason, the Government‘s

claims relate back to Miller‘s original complaint and are

therefore not barred by the FCA‘s statute of limitations. As

we have said, ―an amendment offered for the purpose of

adding to or amplifying the facts already alleged in support of

3

a particular claim may relate back.‖ United States v. Hicks,

283 F.3d 380, 388 (D.C. Cir. 2002).

According to the court, ―[a]llegations concerning

Contract 20A do not fairly encompass Contracts 07 or 29

because each contract is unique.‖ Ct. Op. at 18. In support, it

says that ―each contract required work to be performed on a

different project and was awarded in a different year to a

different winning bidder drawn from a different pool of

prequalified bidders.‖ Id. This misses the point. Of course

the three contracts were different. As is typical in

government contracting, USAID and the Egyptian

government divided the sewer improvements into multiple

contracts signed on different dates. What matters for relation

back purposes is that the three contracts were all part of the

―conduct,‖ i.e., the Frankfurt-based bid-rigging conspiracy,

alleged in Miller‘s original complaint.

The three contracts, moreover, are not nearly as different

as the court suggests. Although each contract was awarded to

a ―different winning bidder,‖ id., the winners on Contracts

20A and 07 were identical in structure—each was owned 60%

by HII and 40% by Jones—and the defendants‘ financial

statements treated them as a single entity, the ―Harbert-Jones

Egypt Joint Venture.‖ Indeed, had Holzmann not agreed that

Harbert-Jones would overbid the contract in exchange for a

$4 million loser‘s fee from its competitor, HII and Jones

might have won Contract 29 as well. Moreover, while it is

true that the pool of bidders varied among contracts, there

were important overlaps: HII and Jones, through their joint

ventures, were prequalified to bid on all three, and Fru-Con

was prequalified for Contracts 20A and 07. Indeed, ―Fru-Con

(through its parent company, Bilfinger & Berger), received

payoffs for cooperating on Contracts 20A and 07,‖ Ct. Op. at

55. In addition, Fuller, which was prequalified for Contract

4

20A, also submitted prequalification information on Contract

29 but was ultimately found ineligible. And when Fuller‘s

parent corporation and Holzmann rigged the bidding on

Contract 20A, they signed an agreement ―expressly

contemplat[ing] future collusion on Contract 29.‖ Id. at 54.

The court relies on Meijer, Inc. v. Biovail Corp., 533 F.3d

857 (D.C. Cir. 2008), but that case is very different from this

one. There, a group of wholesale drug purchasers alleged that

Biovail, a drug manufacturer, misused a patent it owned to

keep ―generic versions‖ of one of its brand name drugs off the

market. The complaint named one particular generic

competitor, developed by a company called Andrx, that

Biovail had blocked. Id. at 866. In their amended complaint,

the plaintiffs alleged for the first time that Biovail, along with

its exclusive distributor, Forest Laboratories, also violated the

antitrust laws through their ―decision not to sell their own

generic.‖ Id. (emphasis added). We disallowed relation back

of this new allegation even though the original complaint

accused the defendants of blocking ―generic versions‖ of the

drug. Id. (emphasis added). According to my colleagues,

Miller‘s use of the plural—―Defendants conspired to rig the

bidding for construction contracts,‖ Miller Compl. ¶ 1—

likewise cannot support relation back of the Government‘s

subsequent allegations.

Our decision in Meijer, however, rested on the fact that

―the whole thrust of the amendments [was] to fault both

Biovail and Forest . . . for conduct different from that

identified in the original complaint.‖ Meijer, 533 F.3d at 866.

As we interpreted the plaintiffs‘ original complaint, it alleged

that Biovail, acting alone through misuse of its patent, was

―bent upon preventing the FDA from granting final approval

of the generic drug proposed by Andrx (and perhaps others).‖

Id. The plaintiffs‘ amended complaint, however, differed in

5

two important respects. First, it added claims against Forest,

―alleg[ing] for the first time that Biovail and Forest

unlawfully conspired to extend their lawful monopoly.‖ Id.

Second, it alleged an entirely different means of unlawful

monopolization, i.e., that Biovail and Forest ―planned

preemptively to introduce their own generic Diltiazem HCl,

and that they unlawfully abandoned that plan.‖ Id. Thus, our

decision in Meijer flowed from the well established principle

that ―an amendment . . . that attempts to introduce a new legal

theory based on facts different from those underlying the

timely claims may not‖ relate back. Hicks, 283 F.3d at 388.

Here by contrast the Government‘s theory of liability on

Contracts 29 and 07 is identical to that first pleaded by Miller,

namely that the defendants entered into a Frankfurt-based

conspiracy to rig the bidding on USAID contracts in Egypt,

and that through that conspiracy, the defendants rigged the

bidding not just on Contract 20A, but also on Contracts 29

and 07. Indeed, in Meijer we suggested that relation back

may well have been appropriate had the plaintiffs there—like

the Government here—simply added additional examples of

the unlawful conduct alleged in the original complaint. 533

F.3d at 866 (describing plaintiffs‘ original allegations

regarding ―generic versions‖ of Biovail‘s drug as

encompassing ―the generic drug proposed by Andrx (and

perhaps others)‖ (emphasis added)).

My colleagues also rely on Bell Atlantic Corp. v.

Twombly, 550 U.S. 544, 557 (2007), and Ashcroft v. Iqbal,

129 S. Ct. 1937 (2009), in which the Supreme Court held that

to survive a motion to dismiss, a complaint must provide

more than ―‗naked assertion[s]‘ devoid of ‗further factual

enhancement.‘‖ Id. at 1949 (quoting Twombly, 550 U.S. at

557). Characterizing Miller‘s conspiracy allegation as such

an assertion, the court concludes that it cannot support

6

relation back of the Government‘s claims on Contracts 29 and

07. This argument suffers from two fundamental defects. To

begin with, the defendants raised it neither here nor in the

district court, and as we have repeatedly said, ―appellate

courts do not sit as self-directed boards of legal inquiry and

research, but essentially as arbiters of legal questions

presented and argued by the parties before them.‖ Carducci

v. Regan, 714 F.2d 171, 177 (D.C. Cir. 1983). Second, and

setting aside the fact that the allegations in Miller‘s original

complaint, which identified the conspiracy as based in

Frankfurt, described the scope of its operations (USAID

contracts in Egypt), and detailed its bid-rigging on Contract

20A, are a far cry from the ―naked assertions‖ that doomed

the complaints in Twombly and Iqbal, those two cases have no

applicability to the question before us. In Twombly and Iqbal

the Supreme Court interpreted Federal Rule of Civil

Procedure 8(a)(2), which sets the standard that a complaint

must satisfy to survive a motion to dismiss. Nothing in either

case even hints that the Supreme Court intended Rule 8(a)‘s

standards to apply to relation back, which is governed by the

entirely different language of Rule 15(c), now incorporated

into the FCA. In fact, my colleagues‘ invocation of Twombly

and Iqbal contradicts the FCA‘s plain text, which provides

that claims relate back not only to ―conduct, transactions, or

occurrences set forth,‖ in an earlier complaint, but also to

―conduct, transactions, or occurrences . . . attempted to be set

forth.‖ 31 U.S.C. § 3731(c) (emphasis added); cf. Krupski v.

Costa Crociere S.p.A., 560 U.S. __, No. 09-337, slip op. at 13

(June 7, 2010) (emphasizing, with respect to relation back of

parties, that Rule 15 ―plainly sets forth an exclusive list of

requirements for relation back,‖ and ―mandates relation back

once the Rule‘s requirements are satisfied‖ (emphasis

added)). Indeed, two other circuits have expressly held, in

language we have cited with approval, that an ―amended

claim arises from the same conduct and occurrences upon

7

which the original claim was based,‖ and therefore relates

back, even if (unlike here) ―the original claim contained

insufficient facts to support it.‖ Dean v. United States, 278

F.3d 1218, 1222 (11th Cir. 2002); see also id. (―One purpose

of an amended claim is to fill in facts missing from the

original claim.‖); United States v. Thomas, 221 F.3d 430, 436

(3d Cir. 2000) (an amendment that ―seeks to correct a

pleading deficiency by expanding the facts but not the claims

alleged‖ in an earlier filing ―would clearly fall within Rule

15(c)‖); Hicks, 283 F.3d at 388 (quoting Dean and Thomas).

In FCA cases, the time for defendants to file Iqbal motions,

and thus to ensure that Rule 8(a)‘s pleading standards are not

―circumvent[ed],‖ Ct. Op. 18, is when the relator‘s complaint

is unsealed. And where, as here, the Government files a

complaint in intervention and the relator an amended

complaint, it is those two complaints, not the relator‘s initial,

sealed complaint, that are tested against the Iqbal standard.

When Miller filed his 1995 complaint, he knew that

contracts other than 20A were involved in the Frankfurt Club

conspiracy. Congress added the relation back provision to the

FCA precisely for situations like this—to allow ―a complete

and thorough investigation of the merits of a qui tam relators‘

allegations.‖ S. Rep. No. 110-507, at 28–29 (2008) (report on

the False Claims Correction Act of 2008, a FERA

predecessor). By interpreting Miller‘s complaint as limited to

the one contract he was able to identify by number when he

first filed, and by applying Twombly and Iqbal to Miller‘s

original, sealed complaint, this court deprives the Government

of the fruits of just such an investigation and frustrates

congressional intent.

II.

After the jury returned its verdict, HII and HC sought a

new trial, arguing that the plaintiffs‘ counsel‘s questioning of

8

one witness, together with his closing argument, introduced

unfairly prejudicial evidence about the defendants‘ wealth.

The district court found that much of the wealth evidence was

relevant and that in any event, it was not so prejudicial as to

require a new trial. Miller v. Holzmann, 563 F. Supp. 2d 54,

110–13; see Fed. R. Civ. P. 61 (all trial errors are harmless

unless they affect ―substantial rights‖). This court now finds

that the district court abused its discretion in failing to order a

new trial for HII and HC. I cannot agree. Faced with ―only a

cold record,‖ Edwards v. Sears, Roebuck & Co., 512 F.2d

276, 281 (5th Cir. 1975), I would defer to the judgment of the

experienced district judge who conducted this seven-week

trial and observed the witnesses.

The plaintiffs‘ counsel elicited information from

Raymond Harbert about the assets and structure of HII, HC,

and non-party Harbert Management Company. The district

court found this testimony—at least with respect to HII and

HC—relevant to the Government‘s alter ego theory, i.e., its

argument that as HII‘s parent, HC completely controlled HII

and ignored its separate corporate existence, making it

responsible for HII‘s actions. The district court grounded its

relevance finding in circuit precedent establishing that the

undercapitalization of a subsidiary corporation may suggest

the existence of just such an improper relationship. Miller,

563 F. Supp. 2d at 111 (discussing Labadie Coal Co. v. Black,

672 F.2d 92 (D.C. Cir. 1982)). In other words, according to

the district court, Raymond Harbert‘s testimony was relevant

because it could have suggested to the jury that adherence to

the corporate form might have permitted HC ―to evade the

impact of a judgment against an inadequately capitalized

HII.‖ Id.

Having found some of Raymond Harbert‘s testimony

relevant, the district court applied Federal Rule of Evidence

9

403, asking whether the testimony presented a risk of unfair

prejudice that substantially outweighed its probative value.

Although recognizing that ―knowledge that a defendant has

the resources to pay a judgment may increase jurors‘ comfort

level in making a large damages award,‖ the district court

found that ―a bare handful of remarks in the course of a

seven-week trial‖ fell short of ―creat[ing] such unfair

prejudice as to substantially outweigh the significant

probative value‖ of the evidence. Id. at 112. A new trial was

unnecessary, the district court explained, because ―plaintiffs

here never even approached the sort of egregious misconduct

and overt pandering that have compelled reversal or a new

trial in other cases.‖ Id.

With little explanation, this court now rejects the district

court‘s relevance analysis. Ct. Op. at 48–49. More troubling,

the court disregards the district court‘s determination of

prejudice. But even if, as this court finds, much of the wealth

testimony was in fact irrelevant, we owe substantial deference

to the district court‘s determination that the testimony was not

so prejudicial as to ―affect . . . substantial rights.‖ Fed. R.

Civ. P. 61. Indeed, because we have long recognized that the

district court‘s proximity to the trial places it in a far better

position to determine prejudice, ―[w]e review a trial court's

evidentiary rulings for abuse of discretion . . . [and] [e]ven if

we find error, we will not reverse an otherwise valid judgment

unless appellant demonstrates that such error affected her

‗substantial rights.‘‖ Whitbeck v. Vital Signs, Inc., 159 F.3d

1369, 1372 (D.C. Cir. 1998) (citations omitted).

Given that the trial lasted for seven weeks, that the

evidence was hardly close, and that the court points to only

one series of questions and a single comment in which the

defendants‘ wealth was raised, I cannot say that the district

court abused its discretion in refusing to order a new trial.

10

See, e.g., United States v. Mejia, 597 F.3d 1329, 1342 (D.C.

Cir. 2010) (―embellishment‖ in prosecutor‘s closing argument

did not require a new trial ―where the statement was isolated

and the case was not close‖). Although my colleagues may

well be correct that ―[e]vidence need not be reinforced and

reiterated again and again for it to be prejudicial enough to

warrant a new trial,‖ Ct. Op. at 50, such limited evidence does

tend to suggest limited prejudice. Cf. Koufakis v. Carvel, 425

F.2d 892, 901–05 (2d Cir. 1970) (district court‘s refusal to

order a new trial constituted an abuse of discretion where

counsel made inappropriate comments ―[t]hroughout his

presentation at trial and in summation,‖ including ―many

references‖ likening defendant to a Mafia boss; engaged in

―repeated name-calling, such as referring to [defendant] . . . as

‗liar,‘ ‗faker,‘ ‗phony,‘ and ‗perjurious‘‖; and made it a

―theme[]‖ throughout trial ―that the case was one which pitted

a ‗little‘ and virtuous man of modest resources against a

powerful and unscrupulous man with untold wealth.‖).

Because the district court was in a far better position than we

to weigh the evidence and determine its effect on substantial

rights, I would defer to its judgment.

III.

For the foregoing reasons, I would affirm the district

court‘s ruling that the Government‘s claims on Contracts 29

and 07 relate back to Miller‘s 1995 complaint, as well as its

finding that the plaintiffs‘ references to wealth do not require

a new trial. And because I agree with the remainder of the

district court‘s rulings, substantially for the reasons given, I

would affirm as to all three contracts and, except for BHIC,

see Ct. Op. at 30–33, as to all defendants.