Opinion

Southeast Development Partners, LLC v. St. Johns County, Florida

Court
Court of Appeals for the Eleventh Circuit
Filed
Aug 7, 2026
Status
Unpublished
Nature of suit
NEW
Cited by
0 cases
Authority
More cited than 42.1%

The opinion

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 1 of 41

NOT FOR PUBLICATION

In the

United States Court of Appeals

For the Eleventh Circuit

____________________

No. 24-13385

____________________

SOUTHEAST DEVELOPMENT PARTNERS, LLC,

a Florida limited liability company,

SOUTHEAST LAND VENTURES, LLC,

a Florida limited liability company,

Plaintiffs-Counter Defendants-Appellants,

versus

ST. JOHNS COUNTY, FLORIDA,

a political subdivision of the State of Florida,

Defendant-Third Party Plaintiff-Counter Claimant-Appellee,

DAYLATE ENTERPRISES, INC.,

a Florida for-profit corporation,

Third Party Defendant-Counter Defendant.

____________________

Appeal from the United States District Court

for the Middle District of Florida

D.C. Docket No. 3:23-cv-00846-CRK-PDB

____________________

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 2 of 41

2 Opinion of the Court 24-13385

Before WILLIAM PRYOR, Chief Judge, and BRANCH and ABUDU,

Circuit Judges.

PER CURIAM:

A developer and a county government contracted to

mitigate the impact a proposed development would have on public

roadways. Now that mitigation costs ballooned past initial

estimates, the parties disagree over who should bear the additional

costs, and each accuses the other of breaching their contract. The

district court granted summary judgment to the county, finding

that the contract unambiguously placed the excess mitigation costs

on the developer. We agree. We also agree with the district court

that the developer breached the contract in several ways, but the

county did not. Nor was the county’s enforcement of the contract

an unconstitutional exaction. But the district court erred by

granting summary judgment against one of the developer’s

associated companies that was assigned no responsibilities under

the contract. Thus, we vacate and remand the district court’s grant

of summary judgment concerning that company’s alleged breach

of the contract and affirm the district court as to the remainder of

the judgment.

I. Background

A. Governing Regulations

In St. Johns County, Florida (the “County”), new

development is governed, in part, by the County’s comprehensive

plan governing development and zoning (the “Comprehensive

Plan”). The Comprehensive Plan discourages the County from

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 3 of 41

24-13385 Opinion of the Court 3

adding development areas unless the developer shows that a

proposed development provides a public benefit. Evaluating a

development’s public benefit includes determining any additional

burden the development would place on public facilities, including

transportation, efficient land use, and the community’s general

infrastructure needs.

Concurrency is Florida’s codified impact mitigation

approach for property development. See Fla. Stat. § 163.3180.

Under Florida law, local governments can implement a

concurrency requirement to ensure that public facilities and

services will be adequate to meet a development’s demands as it

progresses. See Fla. Stat. § 163.3180(5)(d). Counties that

implement a transportation1 concurrency system must allow

developers to mitigate a proposed development’s impact by

entering an agreement “to pay for or construct its proportionate

share of required improvements.” 2 Id. § 163.3180(5)(h)1. The

developer meets this obligation concurrently with the increased

infrastructure demands a project generates. Such agreements

1 Florida law allows for local governments to enact various concurrency

requirements, including sewer, water, or public education facilities. See Fla.

Stat. § 163.3180. Only the County’s use of transportation concurrency is at

issue here.

2 The statute provides instructions for calculating a developer’s proportionate

share “based upon the number of trips from the proposed development.” Fla.

Stat. § 163.3180 (5)(h)2a. Neither party challenges the initial proportionate

share calculation for this development.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 4 of 41

4 Opinion of the Court 24-13385

cannot require a developer to cover existing transportation

infrastructure deficiencies. Id. § 163.8180(5)(h)2.

In short, new developments in the County like the one at

issue must show both a public benefit per the Comprehensive Plan

and how the development will mitigate any costs it generates.

B. The Development Agreement

In September 2016, Southeast Development Partners, LLC

(“Southeast Development”) applied to the County for a large-scale

comprehensive plan amendment for the Grand Oaks Planned Unit

Development (the “Development”). The plan for the Development

was to turn roughly 524 land acres into a mixed-use project

including a maximum of 999 residential units, “100,000 square feet

of commercial use and a maximum of 50,000 square feet of office

use” along the south side of State Road 16 (“SR 16”). The

Development’s plan included an explanation of how the

Development would provide a public benefit and mitigate its

impact on public facilities.

After reviewing Southeast Development’s application, the

Board of County Commissioners (“BOCC”) determined that the

development would increase traffic on public roads beyond their

then-existing capacity, including the parts of SR 16 closest to the

development. In response, Southeast Development proposed that

it would widen three miles of SR 16 around the development’s

entrance (the “SR 16 improvements”), which the parties estimated

would cost $15,013,392.49. Notably, this proposal involved

Southeast Development completing the improvements, as opposed

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 5 of 41

24-13385 Opinion of the Court 5

to paying for the County to complete them. The County agreed

to the proposal, and the parties entered a “Concurrency and Impact

Fee Credit Agreement” (the “Agreement”).

Here is how the parties formalized the proposal in the

Agreement. At a high level, Southeast Development agreed to pay

for and construct the SR 16 improvements, with a portion of the

money it paid counting towards the Development’s proportionate

share to mitigate the Development’s effects on traffic and the

remainder serving as the Development’s public benefit.

Importantly, Southeast acknowledged that the initial calculations

for the SR 16 improvements costs in the Agreement were estimates.

And as we will discuss, Southeast agreed to assume all costs for

those improvements.

Now for the details. As to costs that Southeast Development

agreed to take on: The Agreement’s section 4(a) stated that the

“opinion of probable construction costs estimate” was that the

total cost to “improve all deficient roadways” in the project area

was $42,515,248. Of that estimate, the “proportionate fair share”

for Southeast Development to mitigate the Development’s effects

was $10,132,643. Per section 4(c), the sum of Southeast

Development’s proportionate share contribution and its public

benefit contribution was $15 million. So of the $15 million, and

consistent with the estimate, $10,132,643.00 would count as

Southeast Development’s proportionate share contribution to

mitigate the Development’s transportation impacts, and the

remaining $4,867,357.00 would serve as the project’s public benefit.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 6 of 41

6 Opinion of the Court 24-13385

Section 4(d) explained that Southeast Development would use the

funds to complete the SR 16 improvements, which per the

“preliminary engineering cost estimate for the design, permitting,

and construction” of the project would cost an estimated

$15,013,392.49, which the Agreement defined as the “Estimated

Total Cost.”

The Agreement’s section 4(e) allowed Southeast

Development to fund the SR 16 improvements over time,

concurrent with the BOCC’s approval of new portions of the

development. BOCC would hold Southeast Development’s

payments toward this obligation over time in “a separate escrow

account . . . to be used only for the SR 16 [i]mprovements.” Id.

§ 4(e)(iv)(b). The payments into escrow amounted to $7,500 per

approved unit for the first 212 units, and $15,000 per unit beginning

with the 213th unit, up to the maximum of 999 units and a total of

$13,395,000 paid into escrow. The Agreement provided for the

escrow funds’ disbursement as follows:

At the time [Southeast Development] achieves

Commencement[ 3], [Southeast Development] may

apply to the County for a release of the Escrow Funds

to [Southeast Development], which [Southeast

Development] shall then have the right to use for

payment of all Pre-Construction Costs, Permits Costs

and costs related to construction of the SR 16

3 The Agreement defines “Commencement” as Southeast Development

“posting a bond for the SR 16 [i]mprovements.” As we will discuss, Southeast

Development never reached that point.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 7 of 41

24-13385 Opinion of the Court 7

[i]mprovements (the “Construction Costs”).

[Southeast Development] understands that the

Escrow Funds shall not be sufficient to pay the

Estimated Total Cost of the SR 16 [i]mprovements

and [Southeast Development] agrees that it shall pay

all costs for the SR 16 [i]mprovements which are in

excess of the Escrow Funds.

(emphasis added). In the event of a default, the escrow funds

would “become non-refundable” and “be used by the County to

construct a portion of the SR 16 [i]mprovements” or another road

improvement project near the proposed development.

With the framework for payments defined, the Agreement

also set out timelines for the parties to satisfy their respective

obligations for mitigation of the development’s impacts. Within

60 days of the Agreement’s effective date, Southeast Development

needed to: (1) commence acquisition of offsite drainage ponds for

the SR 16 improvements and (2) commence design of the SR 16

improvements in coordination with the Florida Department of

Transportation (“FDOT”). The Agreement further required

Southeast Development to complete the pond acquisitions and

road design during the “design period,” which ran from the

Agreement’s effective date to the earlier of either (1) fourteen

months after the effective date, or (2) the BOCC’s approval of a plat

containing the 443rd residential unit. Southeast Development also

had to “apply for and pursue all FDOT, environmental and other

permits and required governmental approval for the SR 16

[i]mprovements” within 30 days after the design period’s end and

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 8 of 41

8 Opinion of the Court 24-13385

obtain all permits and approvals within one year of the design

period’s end.

For its part, the County had to include the SR 16

improvements in the “County’s Five-Year Schedule of Capital

Improvements in the County’s Capital Improvements Element

(‘CIE’) of its Comprehensive Plan at the next scheduled update.” 4

And the County agreed to use the Agreement “as a basis for

granting traffic or transportation concurrency” to the

Development, but both parties expressly acknowledged that state,

federal, and local permits would be necessary to authorize the

Development.

Remedies for breach under section 11 of the Agreement

included “all remedies available at law or in equity, including the

remedies of specific performance and all forms of injunctive relief.”

Further, the Agreement authorized the County to “halt approval

of additional plats or construction plans” until Southeast

Development complied with its obligations under the Agreement.

Also relevant here and included in the Agreement was

“Exhibit C” containing the “SR 16 [i]mprovements and

Engineering Cost Estimate” as prepared by Southeast

Development’s analyst, which echoed the probable cost language

contained in § 4 of the contract. Exhibit C notes a probable

4 We note that the County never included the SR 16 improvements in the CIE.

As we will explain later, this omission did not violate the Agreement, because

the next scheduled update of the CIE never occurred.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 9 of 41

24-13385 Opinion of the Court 9

construction cost for the SR 16 improvements of $15,013,392.09

based on the preliminary design and further notes that costs “may

vary with actual design and the cost of material at the time of

construction.”

Southeast Development and the County executed the

Agreement on September 21, 2018. A short time later, on October

1, 2018, Southeast Development assigned its development rights

under the Agreement to Southeast Land Ventures, LLC

(“Southeast Land”).5 Specifically, the assignment stated that

[Southeast Development] sells, assigns, transfers,

conveys, and allocates to [Southeast Land] all of

[Southeast Development’s] present and future rights,

title and interest, if any, relating to the Property in the

following[]: existing permits, approvals, rights, plans,

reports, studies, site plans, surveys, marketing and

engineering studies and reports, engineering plans,

warranties, utility rights and capacities including all

water and sewer agreements, guaranties, bonds and

similar rights and interests relating solely to the

Property, including but not limited to, all site

improvement construction plans and engineering

drawings together with all other planned unit

development rights, entitlements and concurrency

5 The Agreement, in section 13, provided that “[t]he rights and obligations of

[Southeast Development] may be assigned and delegated to a successor or

owner/developer.”

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 10 of 41

10 Opinion of the Court 24-13385

and impact fee agreements pertaining to or benefiting

the Property issued by [the County]

Shortly after the assignment, Southeast Land asked to toll

several of its deadlines for the Development. First, Southeast Land

sought tolling for the opioid epidemic, Hurricane Maria, and

Hurricane Florence. Then it submitted another request following

Hurricane Dorian. Finally, Southeast Land sought tolling because

of the Covid-19 pandemic.

Southeast Land ran into obstacles as it pursued the SR 16

improvements. In September 2021, Southeast Land learned from

FDOT that Southeast Land’s initial plans required a “complete

redesign” that would increase the SR 16 improvement’s cost to

roughly $57 million. This drastically increased cost from the

original $15 million estimate pushed Southeast Land to seek

changes to the Agreement. After receiving FDOT’s feedback,

Southeast Land proposed to the BOCC that Southeast Land would

pay $15 million to FDOT so that the state could design and

complete the SR 16 improvements in its stead. 6

The BOCC held a hearing on February 21, 2023, on whether

to accept Southeast Land’s proposal to pay $15 million to FDOT in

6 At this point, Southeast Land and its affiliates had begun paying funds toward

the escrow account as the Agreement required and concurrent with the

approval of new plats. The total escrow amount in the account at the time of

the district court proceedings was roughly $5 million, and the parties agree

this amount represents the appropriate payments to that account.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 11 of 41

24-13385 Opinion of the Court 11

lieu of completing the SR 16 improvements itself. The BOCC

rejected Southeast Land’s proposal. And because Southeast Land

had neither acquired the necessary drainage ponds nor finished

designing the SR 16 improvements, the BOCC found Southeast

Land in default of the Agreement. That finding led the BOCC to

order the transfer of the roughly $5 million in the escrow account

to FDOT to begin the SR 16 improvements.

C. Procedural History

On March 14, 2023, Southeast Development sued the

County in Florida state court following the BOCC’s finding that

Southeast defaulted. The County counterclaimed against

Southeast Development and Southeast Land (together,

“Southeast”) seeking either a declaratory judgment that Southeast

breached the contract or a declaratory judgment for specific

performance. 7

Southeast Development brought four causes of action.

Count I sought declaratory relief finding that the County’s

interpretation of the Agreement and finding of default were

invalid, illegal, and unconstitutional. Count II sought a permanent

injunction enjoining the County from continuing alleged breaches8

7 The County also impleaded Day Late, the owner of the to-be-developed

property. The court dismissed Day Late from this case, and Day Late is not

directly involved in any claims on this appeal.

8 These alleged breaches included failing to adopt the SR 16 improvements

into the County’s CIE, failure to properly account for Southeast’s payments,

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 12 of 41

12 Opinion of the Court 24-13385

of the Agreement and from disbursing the escrow funds to FDOT,

which disbursal Southeast claimed was inappropriate as Southeast

had not breached the contract. Count III sought a finding of

inverse condemnation under the Florida Constitution, article X,

§ 6(a). Finally, Count IV sought a finding of unlawful exaction

under 42 U.S.C. § 1983 because “the County extortionately

leveraged its police powers to require [Southeast] to pay $15

million” for the County to approve the Development and further

“leveraged” those powers to require Southeast to pay the full cost

of the SR 16 improvements when the costs drastically exceeded the

initial $15 million estimate. After the plaintiffs amended their

complaint to add Southeast Land as a co-plaintiff, the County

removed the action to federal court.

Once in federal court, the County counterclaimed, alleging

that both Southeast Development and Southeast Land breached

the Agreement with the County and requested declaratory

judgment confirming the County’s ability (1) “to halt the approval

of additional plats or construction plans,” (2) to retain the escrow

funds in accordance with the Agreement, and (3) to require that

Southeast Land assign the road planning documents and any

permits to the County for no cost. The County also requested a

judgment declaring that the Agreement obligated Southeast to pay

all costs for the SR 16 improvements despite the increase from the

initial $15 million estimate.

failing to maintain Southeast’s payments in a separate escrow account, and

failing to cooperate with Southeast to carry out the Agreement.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 13 of 41

24-13385 Opinion of the Court 13

Each party moved for summary judgment. The district

court granted the County’s motion and denied Southeast’s motion.

As relevant to this appeal, the district court first determined that

the Agreement obligated Southeast to pay “all costs for the SR 16

[i]mprovements” in their entirety, even if they exceeded the $15

million total cost estimate, and that Southeast breached the

Agreement by failing to timely acquire offsite drainage ponds and

coordinate the road design with FDOT. The district court then

outlined the remedies available to the County under the

Agreement and declared that the County could

(1) halt approval of additional plats and construction

plans within the [Development] until and unless

[Southeast Land] complies with the terms and

conditions of Sections 4 and 5 of the Agreement[ 9];

(2) declare the [incremental payments] held in the

separate account as non-refundable . . . [and to] be

used by the County to construct a portion of the SR

16 [i]mprovements or another road improvement

within the project impact area; and (3) require

[Southeast Land] to assign the Road Design

documents and any Permits to the County, free of

charge, within thirty (30) days of the entry of

judgment.

9 Section 4 outlined the “Total Proportionate Share Obligation and Payment

Schedule,” while Section 5 described Southeast’s “Specific Obligations and

Rights.”

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 14 of 41

14 Opinion of the Court 24-13385

The district court also rejected Southeast’s unlawful

exaction claim because it found that Southeast could not show that

the County’s decision to hold Southeast responsible for the

increased SR 16 improvements costs under the Agreement or any

other conditions the County placed on its approval of the

Development “lacked an essential nexus to a public purpose,”

which is all that the Supreme Court requires to defeat an unlawful

exaction claim. 10 Koontz v. St. Johns River Water Mgmt. Dist., 570 U.S.

595, 605–06 (2013). The district court awarded the County its costs

incurred in the action other than attorney’s fees.

Southeast then filed a motion to stay the judgment and the

district court’s costs award pending appeal. In opposing that

motion, the County submitted a letter that stated the property

owner had “on September 20, 2024, . . . terminated its

Development Services Agreement with Southeast Development

Partners, LLC, its assignee Southeast Land Ventures, LLC, and any

and all agents or representative of same.” Further, the letter stated

that the property owner had “on October 2, 2024, . . .terminated its

Purchase and Sale Agreement with Southeast.” 11 The County

argued that these two facts meant that Southeast no longer had any

10 The district court also found that Southeast lacked standing to bring an

inverse condemnation claim. Southeast does not challenge this finding on

appeal, and we do not review it. See Sapuppo v. Allstate Floridian Ins. Co., 739

F.3d 678, 680 (11th Cir. 2014) (“[A] party abandons an issue by failing to list or

otherwise state it as an issue on appeal.” (quotation omitted)).

11 The property owner also sued Southeast in state court alleging breach of a

contract, which the parties later agreed to dismiss without prejudice.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 15 of 41

24-13385 Opinion of the Court 15

legal right to continue work on the Development, so the balance

of equities did not favor staying the judgment. The district court

denied Southeast’s motion.

Southeast timely appealed. The County then moved to

dismiss the appeal for a lack of standing or as moot because

Southeast no longer had the right to proceed with the

development. We carried the motion to dismiss with the case.

II. Discussion

We review orders on summary judgment de novo, applying

the same standard as the district court. Hearn v. McKay, 603 F.3d

897, 901 (11th Cir. 2010). Under that standard, “[t]he court shall

grant summary judgment if the movant shows that there is no

genuine dispute as to any material fact and the movant is entitled

to judgment as a matter of law.” Fed. R. Civ. P. 56(a). We also

consider questions of appellate standing de novo. See Kimberly

Regenesis, LLC v. Lee Cnty., 64 F.4th 1253, 1258 (11th Cir. 2023).

There are four issues before us on appeal. First, the County

argues that we must dismiss this appeal as moot because

Southeast 12 is no longer able to develop the property and thus does

not have appellate standing. Second, Southeast argues that the

12 As noted above, we refer to Southeast Development and Southeast Land

together as Southeast throughout this opinion. For clarity, we continue that

convention in addressing together the arguments of both entities. That said,

for the reasons discussed below, we conclude that only Southeast

Development could breach the Agreement, and nothing in this discussion

should be construed to contradict that conclusion.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 16 of 41

16 Opinion of the Court 24-13385

district court erred in granting summary judgment to the County

on the breach of contract claims for three reasons: (1) the

Agreement did not require Southeast to pay for all costs of the SR

16 improvements; (2) Southeast did not breach the Agreement

because declarations of states of emergency tolled Southeast’s

deadlines for project performance; and (3) the County breached

the Agreement by failing to add the SR 16 improvements to the

County’s schedule of capital improvements. Third, Southeast

argues that the court erred in granting summary judgment to the

County on the unlawful exaction claim. Finally, Southeast

contends that the district court’s entry of judgment against

Southeast Land following the Agreement’s assignment was

improper. We address each issue in turn.

A. Standing and Mootness

The County argues that there has been a “material change

in circumstances in the status of the parties so as to eliminate any

justiciability” of the case. Specifically, Southeast “no longer hold[s]

any interest or rights as to the development” in the wake of the

property owner terminating its contracts with Southeast and the

reversion of the property to the owner. Thus, the County argues

that even if the “County breached the Concurrency Agreement”

and “imposed a monetary exaction with no nexus or

proportionality,” our ruling “would have no practical effect” on

Southeast because Southeast lacks “any right or ability to engage

in any development activities related to that development,” thus

rendering the case moot. The County also argues that Southeast’s

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 17 of 41

24-13385 Opinion of the Court 17

“interest in avoiding liability or prejudice in the state court action

[brought by the property owner] through the Final Judgment does

not establish justiciability” because the property owner was not a

party to the final judgment. And finally, the County argues that an

interest in attorneys’ fees does not establish standing for Southeast.

Southeast argues to the contrary: because of its ongoing state court

litigation with the property owner, which may reinstate its right to

develop the property as initially intended, Southeast claims it has

an ongoing interest in the development of the property. We find

that Southeast has standing to bring this appeal because it was

injured by the district court’s decision below and the case is not

moot.

The U.S. Constitution limits the jurisdiction of federal

courts to actual “Cases” and “Controversies.” U.S. Const. art. III,

§ 2. Accordingly, “[l]itigants must establish their standing not only

to bring claims, but also to appeal judgments.” Wolff v. Cash 4 Titles,

351 F.3d 1348, 1353 (11th Cir. 2003). “To establish appellate

standing, a litigant must ‘prove that he has suffered a concrete and

particularized injury that is fairly traceable to the challenged

conduct, and is likely to be redressed by a favorable judicial

decision.’” United States v. Amodeo, 916 F.3d 967, 971 (11th Cir. 2019)

(quoting Hollingsworth v. Perry, 570 U.S. 693, 704 (2013)). The

requirements for appellate standing resemble the standing

requirements that plaintiffs must meet to bring a case in the first

instance. See Steel Co. v. Citizens for a Better Env’t, 523 U.S. 83, 103–

04 (1998) (noting that Article III standing to sue requires the “triad

of injury in fact, causation, and redressability”).

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 18 of 41

18 Opinion of the Court 24-13385

But, while they are “similar and overlapping, the doctrines

of appellate standing and trial standing are not identical.” Wolff,

351 F.3d at 1353. “The ‘most obvious difference’ is that ‘standing

to appeal’ requires an ‘injury caused by the judgment’ while

‘standing to bring suit’ requires an ‘injury caused by the underlying

facts.’” Kimberly Regenesis, 64 F.4th at 1259 (quoting 15A Charles A.

Wright & Arthur R. Miller, Federal Practice and Procedure § 3902 (3d

ed. & Supp. Sept. 2022)). “In other words, ‘in the context of

appellate standing, the primary meaning of the injury requirement

is adverseness: Only a litigant who is arieved by the judgment or

order may appeal.’” Id. (quoting Amodeo, 916 F.3d at 971) (alteration

adopted) (emphasis added).

In Kimberly Regenesis, we addressed whether two appellants,

a county and a county commissioner, had standing to appeal the

district court’s determination that the county commissioner was

subject to a deposition subpoena in a case brought against the

county and that quasi-judicial immunity did not apply. Kimberly

Regenesis, 64 F.4th at 1259–64. We noted that the county lacked

standing because, while it had lost when it was a party litigating

this issue below, the judgment did not actually aggrieve the county

because the appeal addressed “the commissioner’s quasi-judicial

immunity, not the county’s.” Id. at 1259. Thus, “[b]ecause the

immunity does not belong to the county, the county [was] not

aggrieved by the district court denying the immunity,” and the

county could not appeal the judgment. Id. at 1260.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 19 of 41

24-13385 Opinion of the Court 19

The commissioner lacked appellate standing as well, but for

a different reason: he was never a party to the case. Id. at 1260–61.

We observed that a person may have an interest in a case without

being a named party, but that interest normally arises for persons

who either (1) intervene in the case or (2) are nonparties who

“participated in the case before the district court.” Id. (emphasis in

original). Because the commissioner qualified for neither

exception and did not appear in the case until it was on appeal, he

lacked appellate standing. Id. at 1262.

Here, Southeast possesses appellate standing because, unlike

the parties in Kimberly Regenesis, Southeast was not only a named

party and active participant in the case below, but the district

court’s final judgment also injured Southeast. See Amodeo, 916 F.3d

at 971. The district court ruled that the Agreement obligated

Southeast to pay all costs for the SR 16 improvements in their

entirety, including those above the $15 million estimate, and

awarded the County its costs. The judgment injured Southeast,

and reversal would redress the injury. So, Southeast’s appeal

satisfies the triad – there is an injury the judgment caused that is

redressable and Southeast has standing. See id.

The County’s claim that the case is moot is incorrect. “[A]

case is moot when the issues presented are no longer ‘live’ or the

parties lack a legally cognizable interest in the outcome.” Soliman

v. U.S. ex rel. INS, 296 F.3d 1237, 1242 (11th Cir. 2002) (quoting Powell

v. McCormack, 395 U.S. 486, 496 (1969)). A live case requires that the

court be able to grant meaningful relief; “‘if events that occur

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 20 of 41

20 Opinion of the Court 24-13385

subsequent to the filing of a lawsuit or an appeal deprive the court

of the ability to give the plaintiff or appellant meaningful relief,

then the case is moot and must be dismissed.’” Id. (alteration

adopted) (quoting Al Najjar v. Ashcroft, 273 F.3d 1330, 1336 (11th Cir.

2001)).

Here, Southeast’s dispute with the property owner may

curtail its ability to develop the property. But if we were to reverse

the district court and find that the County breached the

Agreement, Southeast would have remedies under the section 11

of the contract against the County, including “all remedies

available at law or in equity.” These remedies could include a

declaratory judgment that Southeast did not breach and did not

have to pay the entire cost of the SR 16 improvements. Thus, a

“live” issue remains that allows the Court to grant relief, and the

case is not moot. 13 See Soliman, 296 F.3d at 1242. Accordingly, we

deny the County’s motion to dismiss this appeal for lack of

standing or mootness. 14

B. Summary Judgment Merits

We now turn to the merits of this appeal. Southeast claims

that the County was not entitled to summary judgment on the

13 We do not address Southeast’s alternative suggestion that we vacate the

district court’s judgment because we find that this appeal is not moot.

14 The Florida state court’s dismissal without prejudice of the state court suit

between Southeast and the landowner does not change our analysis because

Southeast has appellate standing and the case is not moot regardless of any

state court action.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 21 of 41

24-13385 Opinion of the Court 21

breach of contract claims because (1) the Agreement did not

require Southeast to pay all costs related to the SR 16

improvements; (2) Southeast did not breach the Agreement

because declarations of states of emergency tolled Southeast’s

deadlines for project performance; and (3) the County breached

the Agreement by not adding the SR 16 improvements to the

County’s schedule of capital improvements. We address each

contention and conclude that the district court did not err in

rejecting each one.

1. The Agreement required Southeast to pay all costs for the

SR 16 improvements.

Southeast argues that the district court erred in finding that

the Agreement required Southeast to pay all costs for the SR 16

improvements in their entirety, including those beyond the initial

$15 million estimate. In Southeast’s view, the Agreement requires

Southeast to “pay all costs for the SR 16 [i]mprovements which are

in excess of the Escrow Funds,” but only up to that $15 million

estimate, a number mentioned in the calculation of Southeast’s

obligations and close to the $15,013,392.49 probable construction

cost included in Exhibit C attached to the Agreement. Southeast

contends that interpreting the contract without a cap on its

payments toward the SR 16 improvements would be absurd and

that Southeast would not have agreed to such a term.

The County argues that concluding Southeast assumed the

burden of all costs to pay for the SR 16 improvements is consistent

with the Agreement’s plain language. The County further

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 22 of 41

22 Opinion of the Court 24-13385

contends that nothing in Exhibit C or in the Agreement itself limits

Southeast’s “obligation to fund the SR 16 [i]mprovements to

certain portions, phases, or particular designs of the construction.”

Under Florida law 15, contract interpretation begins with a

review of the contract’s plain language, which is the “best evidence

of the parties’ intent . . . .” Taylor v. Taylor, 1 So. 3d 348, 350 (Fla.

1st DCA 2009) (per curiam); Sugar Cane Growers Coop., Inc. v.

Pinnock, 735 So. 2d 530, 538 (Fla. 4th DCA 1999). Courts applying

Florida law interpret words and phrases “in their ordinary sense”

and do not apply “a strained, forced, or unrealistic construction.”

Siegle v. Progressive Consumers Ins. Co., 819 So. 2d 732, 736 (Fla. 2002)

(quoting Gen. Accident Fire & Life Assurance Corp. v. Liberty Mut. Ins.

Co., 260 So. 2d 249, 253 (Fla. 4th DCA 1972)). Courts determine

the legal effect of a contract’s provisions from the words of the

entire contract, and it is error for a court to construe a contract in

a manner which leaves out words and phrases. Sugar Cane Growers,

735 So. 2d at 535. “[I]t is never the role of a trial court to rewrite a

contract to make it more reasonable for one of the parties.”

Ferreira v. Home Depot, 12 So. 3d 866, 868 (Fla. 1st DCA 2009) (per

curiam).

15 The parties both cite Florida law in support of their contract interpretation

arguments. Section 14 of the Agreement also provides that the Agreement

“shall be governed by, construed under and enforced in accordance with the

laws of the State of Florida.” For these reasons, and because “state law governs

issues of contract interpretation,” we apply Florida state law in analyzing the

breach of contract claims. AFC Franchising, LLC v. Purugganan, 43 F.4th 1285,

1290 (11th Cir. 2022).

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 23 of 41

24-13385 Opinion of the Court 23

The Agreement unambiguously requires Southeast to

construct the SR 16 improvements without a cost limitation.

Pursuant to state law, as part of its planned development, Southeast

had to show the County that it would both mitigate the

development’s transportation infrastructure effects and show how

the development would provide a public benefit. See Fla. Stat.

§ 163.3180. The Agreement provided that Southeast would pay

roughly $10 million as its proportionate share of the SR 16

improvements as mitigation and an additional estimated $5 million

beyond its proportionate share representing the project’s public

benefit. But as section 4(a) of the Agreement makes clear, those

amounts were based on the “probable construction costs

estimate.” And § 4(d) acknowledged that $15,013,392.49 was the

Estimated Total Cost, based on the preliminary cost estimate for

the design, permitting, and construction costs of the SR 16

improvements. Exhibit C also acknowledged the uncertain nature

of the total project costs and explained that the “estimated

construction costs” were based on the “preliminary design . . . and

may vary with actual design and the cost of material at the time of

construction.” And section 4(e) the Agreement specifically notes

that these amounts are estimates only: “[Southeast] understands

the Escrow Funds shall not be sufficient to pay the Estimated Total

Cost of the SR 16 [i]mprovements and [Southeast] agrees that it

shall pay all costs for the SR 16 [i]mprovements which are in excess

of the Escrow Funds.” That language, in the ordinary sense,

requires Southeast to “pay all costs for the SR 16 [i]mprovements,”

in their entirety. See Siegle, 819 So. 2d at 736. In entering the

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 24 of 41

24 Opinion of the Court 24-13385

Agreement, Southeast acknowledged that what it paid into escrow

was not the total cost of the SR 16 improvements or the limit of

what it would bear, and in agreeing to the “all costs” language,

Southeast accepted that it would pay the entire burden of the SR

16 improvements.

Southeast asks us to read into the contract an implied limit

of $15 million on the costs it assumed under the Agreement. We

decline to do so. See Ferreira, 12 So. 3d at 868. Nothing in the

Agreement limits Southeast’s costs to the $15 million estimate to

design and construct the SR 16 improvements. Indeed, the initial

estimate in Exhibit C was $15,013,392.49, in excess of $15 million,

and, as discussed above, the Agreement included language

acknowledging that the estimate acknowledged that the $15

million was only the parties’ best estimate at the time for the SR 16

improvements cost that Southeast would bear. The Agreement

therefore recognized that Southeast was agreeing to pay “all costs”

for the SR 16 improvements, even if the costs exceeded the initial

estimate.

Southeast’s reliance on the $15,013,392.49 estimated

amount listed in Exhibit C for an implied cap to its costs is similarly

unavailing. As noted above, that estimate includes the notation

that the estimated costs were based on a preliminary design and

“may vary with actual design and the cost of material at the time

of construction.” While Section 4(e) of the Agreement contains

language that the escrow funds would “count toward” Southeast’s

obligations under the Agreement, both parties knew the costs

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 25 of 41

24-13385 Opinion of the Court 25

would exceed the escrow amount. Though, under the

Agreement’s section 4(e), Southeast would no longer need to

contribute to the escrow funds when the account totaled

$13,395,000 or when construction commenced, the Agreement still

required Southeast to meet the Agreement’s design, permitting,

and construction requirements if the amount in escrow was

insufficient to cover all costs. As Exhibit C noted, the costs were

based on preliminary design; the actual design required for FDOT

approval when it required a “complete redesign” was much more

expensive. So far from providing the cap that Southeast argues for,

Exhibit C actually confirms that Southeast knew its costs would

exceed $15 million at the time it entered the Agreement.

To be sure, this interpretation means the Agreement does

not cap Southeast’s exposure. But under Florida law, where a

contract is unambiguous, our “task is to apply the parties’ contract

as written, not rewrite it under the guise of judicial construction.”

City of Pompano Beach v. Beatty, 222 So. 3d 598, 600 (Fla. 4th DCA

2017) (quotation omitted). We cannot vary a contract simply

because a provision turns out to be ill-advised, and we cannot say

that a sophisticated party assuming the potential risk or benefit in

negotiating a contract is absurd, particularly when Southeast did

not include an explicit cap to their costs in the Agreement. See

Ferguson v. Ferguson, 54 So. 3d 553, 554 (Fla. 3d DCA 2011) (“[T]he

bedrock principle of contract law . . . [is] that bad deals are as

enforceable in the law as good deals.”); Seritage SRC Fin., LLC v.

Town Ctr. at Boca Raton Tr., 397 So. 3d 44, 46 (Fla. 4th DCA 2024)

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 26 of 41

26 Opinion of the Court 24-13385

(holding that an agreement between sophisticated parties was

unambiguous).

Southeast also argues that under Florida law, it should not

be “responsible for the cost of reducing or eliminating existing

deficiencies” because concurrency only requires it to mitigate the

development’s infrastructure effects, not pay for otherwise needed

improvements that its development did not cause. See Fla. Stat.

§ 163.3180(5)(h)2 (“[A] local government may not require payment

or construction of transportation facilities whose costs would be

greater than a development’s proportionate share of the

improvements necessary to mitigate the development’s impacts.”).

But Southeast leaves unexplained how its agreement to pay all

associated costs violates this anti-deficiency provision. After all,

Southeast agreed to pay more than its proportionate share to satisfy

its public benefit obligations. As stated in the Agreement’s § 4(a),

Southeast’s proportionate share, based on initial estimates, was

$10,132,643.00. And per § 4(b), Southeast agreed to pay

$4,867,357.00 in addition to that proportionate share as its public

benefit contribution. The $15 million total of those two amounts

from §§ 4(a) and 4(b) was roughly equivalent to the $15,013,392.49

in Exbibit C. But § 4(e) also notes that Southeast “understands that

the Escrow Funds shall not be sufficient to pay the Estimated Total

Cost of the SR 16 improvements and [Southeast] agrees that it shall

pay all costs for the SR 16 improvements which are in excess of the

Escrow Funds.” Southeast did not negotiate contract language

stating that it would pay all costs for the SR 16 improvements which

are in excess of the Escrow Funds up to the amount of the Estimated

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 27 of 41

24-13385 Opinion of the Court 27

Total Cost of the SR 16 improvements (which the Agreement defined

as $15,013,392.49). The Agreement says all costs.

Southeast chose how it wanted to meet the County’s public

benefit requirement for the Development. The Comprehensive

Plan does not specifically define a developer’s public benefit

contribution. Instead, it requires only that an applicant for a

development demonstrate that there is one, and nothing precludes

a developer from agreeing to a potentially variable amount in

meeting this obligation. We also note that Florida law allows for a

developer to contract to satisfy its proportionate share obligation

by “construct[ing] its proportionate share,” which Southeast chose

to do when it agreed to cover all costs associated with the SR 16

improvements. Fla. Stat. § 163.3180(5)(h)c(I). By agreeing to

construct the improvements in lieu of contributing its

proportionate share payment under the statute, Southeast assumed

the risk of the development costing more or less than it might

otherwise have to spend, if for instance it had instead contracted to

pay the County $15 million to construct the SR 16 improvements.

Southeast was familiar with the distinction; it attempted to modify

the Agreement and pay $15 million to the County instead before

the County declared Southeast in breach. Under the ordinary

meaning of the contract, Southeast agreed to that variable amount,

knowing that the initial estimate was just that—an estimate—and

that actual construction costs might vary.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 28 of 41

28 Opinion of the Court 24-13385

Accordingly, we find that the Agreement unambiguously

meant what it said: Southeast must pay all costs associated with the

SR 16 improvements.

2. Southeast breached the Agreement.

Under section 4(e) of the Agreement, Southeast had to meet

various benchmarks, including acquiring offsite drainage ponds

during the design period, designing the SR 16 improvements, and

obtaining the needed permits for the SR 16 improvements after the

design period ended. Southeast had to begin these tasks with 60

days of the Agreement’s effective date and conclude the design

period at the earlier of 14 months later or at the time of the

County’s approval of the 443rd residential unit. The Agreement

required Southeast to apply for and obtain all the needed permits

for the Development within one year of the design period’s end.

Southeast did not achieve these timing benchmarks. The district

court found that the Agreement did not qualify for tolling under

Florida state statute because it was not a development permit or

order and at most was a step toward a permit, and that because

Southeast had not performed its obligations, Southeast had

breached the Agreement.

Southeast argues that the district court incorrectly found

that it breached the Agreement because five states of emergency in

Florida tolled the deadlines for Southeast’s performance of these

obligations, meaning it had not yet missed a deadline when the

County declared Southeast in default. The County responds that

Southeast breached the Agreement because (1) Southeast did not

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 29 of 41

24-13385 Opinion of the Court 29

perform according to the stipulated timelines; (2) the Florida

statute providing for the tolling of deadlines related to states of

emergency does not apply to the Agreement; and (3) even if the

statute did, Southeast did not properly notify the County of the

deadlines Southeast wanted tolled.

The relevant Florida law provides that

[t]he declaration of a state of emergency by the

Governor tolls the period remaining to exercise the

rights under a permit or other authorization for the

duration of the emergency declaration. Further, the

emergency declaration extends the period remaining

to exercise the rights under a permit or other

authorization for 6 months in addition to the tolled

period.

Fla. Stat. § 252.363(1)(a) (2018). 16

The parties signed the Agreement in 2018. At the time, the

tolling provision in § 252.363(1)(a) applied to:

1. The expiration of a development order issued by a

local government.

16 Florida law applies the statutory scheme in effect at the time the parties enter

an agreement. See Fla. Beverage Corp. v. Div. of Alcoholic Bevs. & Tobacco, Etc,

503 So. 2d 396, 398 (Fla. 1st DCA 1987) (“The laws in force at the time of the

making of a contract enter into and form a part of the contract as if they were

expressly incorporated into it.”). Florida has since amended this statute, but

as the parties entered the Agreement in 2018, we apply the version in effect at

the time.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 30 of 41

30 Opinion of the Court 24-13385

2. The expiration of a building permit.

3. The expiration of a permit issued by the

Department of Environmental Protection or a water

management district pursuant to part IV of chapter

373.

4. The buildout date of a development of regional

impact, including any extension of a buildout date

that was previously granted as specified in s.

380.06(7)(c).

Fla. Stat. § 252.363(1)(a) (2018). The statute also explains that “[i]f

the permit or other authorization for a phased construction project

is extended, the commencement and completion dates for any

required mitigation are extended such that the mitigation activities

occur in the same timeframe relative to the phase as originally

permitted.” Id § 252.363(1)(c).

The County argues that the statute did not include

development agreements such as the Agreement at issue here.17

Southeast contends that the Agreement is not a development

agreement and is instead a “proportionate share agreement

pursuant to section 163.3180,” apparently arguing that such a

proportionate share agreement that sets out mitigation

requirements would qualify for tolling. But we need not decide

17 The Florida legislature did add development agreements to the tolling

statute, see Fla. Stat. § 252.363(1)(a)(6) (2021), but not until 2021, well after the

Agreement’s effective date.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 31 of 41

24-13385 Opinion of the Court 31

whether the Agreement qualifies as either type because the tolling

statutes lists neither proportionate share agreements nor

development agreements among those permits a state of

emergency would extend. See Fla. Stat. § 252.363(1)(a) (2018). The

statute lists development orders, building permits, environmental

permits, and developments of regional impact, but no other

“permit or other authorization.” See id. And the statute’s

references to mitigation is tied to the extension of “permits or

other authorizations” described in the statute, which the

Agreement is not. See id. § 252.363(1)(c).

Nor does the Agreement qualify as a development order (not

to be confused with the County’s assertion that it is a development

agreement.)18 A “development order” is “any order granting,

denying, or granting with conditions an application for a

development permit,” Fla. Stat. § 163.3164(15) (2018).

“‘Development permits’ include[] any building permit, zoning

permit, subdivision approval, rezoning, certification, special

exception, variance, or any other official action of local

government having the effect of permitting the development of

land.” Fla. Stat. § 163.3164(16) (2018). We agree with the district

court that, at most, the Agreement served as a step toward

Southeast seeking the permits the Development required.

18 Neither party argues that the Agreement qualifies as a building permit,

environmental permit, or development of regional impact. Accordingly, we

do not analyze whether the Agreement fits these categories.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 32 of 41

32 Opinion of the Court 24-13385

The Agreement says as much. In Section 6(a), the

Agreement emphasizes that the parties still had to obtain necessary

permits for the Development. And under section 9, Southeast

agrees to obtain those permits in accordance with federal, state,

and local requirements. Given that the Agreement acknowledges

the need for permits that it does not grant, we cannot conclude that

the Agreement is “an official action of local government having the

effect of permitting the developed land,” Fla. Stat. § 163.3164(16)

(2018), or that the County entering the Agreement with Southeast

represented a “grant[] with conditions [of ] an application for a

development permit.” Fla. Stat. § 163.3164(15). Thus, the

Agreement is not a development order subject to tolling under

§ 252.363(1)(a). 19

Accordingly, because the Florida states of emergency did not

toll the timelines specified in the Agreement, and Southeast did not

perform under the original timelines, Southeast breached the

Agreement.

3. The County did not materially breach the Agreement

Southeast argues that the County breached the Agreement

by failing to adopt “the SR 16 [i]mprovements into its Five-Year

Schedule of Capital Improvements in the Capital Improvements

19 Southeast contends that the development order it sought to toll was the

authorization for the Development, which it asserts would qualify as a

development order, not the Agreement. But the requirements for design and

obtaining permits were part of the Agreement, which does not qualify for

tolling, as explained above.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 33 of 41

24-13385 Opinion of the Court 33

Element of its Comprehensive Plan” as section 7 of the Agreement

required. Doing so, Southeast argues, would have given the

Development “some level of priority by the County, as well as

visibility to the general public” and allowed the County to “enter[]

into other proportionate share agreements to put funds towards

the roadway or identif[y] other funding sources.” The County

responds that it did not breach the Agreement because, while the

Agreement requires the County to add the improvements into the

schedule at its first update, it has not yet updated the schedule. The

County also argues that, even if the failure to do so was a breach,

it was not a material breach, because adding the improvements into

the plan would not have changed the costs Southeast agreed to bear

and did not go to the essence of the Agreement.

Breach of contract claims in Florida require a party to

establish “(1) the existence of a contract; (2) a material breach of

that contract; and (3) damages resulting from that breach.”

Marchisio v. Carrington Mortg. Servs., LLC, 919 F.3d 1288, 1313 (11th

Cir. 2019) (quoting Vega v. T-Mobile USA, Inc., 564 F.3d 1256, 1272

(11th Cir. 2009) (emphasis omitted). A party materially breaches

when he “fail[s] to perform a duty that goes to the essence of the

contract and is of such significance that it relieves the injured party

from further performance of its contractual duties.” Burlington &

Rockenbach, P.A. v. L. Offs. of E. Clay Parker, 160 So. 3d 955, 960 (Fla.

5th DCA 2015). “[T]rivial noncompliance and minor failings do

not constitute material breaches.” Id.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 34 of 41

34 Opinion of the Court 24-13385

As an initial matter, the record does not show that the

County breached the Agreement. The Agreement required that

[t]he County will adopt [Southeast’s] Transportation

Contribution . . . into the County’s Five-Year

Schedule of Capital Improvements in the County’s

Capital Improvements Element (“CIE”) of its

Comprehensive Plan at the next scheduled update.

Southeast argues that Florida law requires the County to review its

Capital Improvements Element “on an annual basis.” Fla. Stat. §

163.3177(3)(b). That may be so. But reviewing a plan and updating

it are not the same thing. The district court correctly noted that

the Agreement only requires inclusion of the SR 16 improvements

“at the next scheduled update.” The record does not indicate when

the “next scheduled update” to the plan was to occur or if it even

has. It also does not show the County’s failure to update the plan

at that indeterminate time.

But even if the County did breach the Agreement in failing

to update the plan, such failure was immaterial. As we have

discussed, the Agreement obligated Southeast Development (and

no one else) to pay “all costs” of the improvements. Southeast does

not explain why inclusion of the improvements into the plan would

have resulted in state or local government funding priority for a

project that Southeast had already agreed to pay for. Nor does

Southeast explain why the County would have solicited additional

proportionate share agreements to fund those same

improvements. Thus, such inclusion would not have materially

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 35 of 41

24-13385 Opinion of the Court 35

affected Southeast’s burden under the Agreement. And even if

adding the improvements to the CIE would have increased their

“visibility to the general public,” such visibility did not go to the

“essence” of the contract, and any noncompliance on this point

was trivial. See Burlington, 160 So. 3d at 960.

C. Unlawful Exaction

The district court granted the County summary judgment

on Southeast’s § 1983 claim that the County holding Southeast

accountable for the increase in the costs of SR 16 improvements

amounts to an unconstitutional exaction. Southeast argues that the

district court erred because enforcing the Agreement amounts to a

taking that lacks an essential nexus to a legitimate state interest and

was not roughly proportionate to the development project’s

impacts. The County responds that requiring Southeast to pay the

increased costs of the SR 16 improvements is not an unlawful

exaction because Southeast, in the Agreement, assumed the

burden of any price increase when it agreed to construct the

improvements rather than negotiating to merely pay the estimate

improvement costs upfront, as it tried to do shortly before the

County declared Southeast in breach. Southeast replies that the

unconstitutional burden overcame the Agreement and rendered it

unenforceable.

The Supreme Court established the test for an unlawful

exaction in Koontz. 570 U.S. at 606. As explained in Koontz, “the

government may choose whether and how a permit applicant is

required to mitigate the impacts of a proposed development, but it

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 36 of 41

36 Opinion of the Court 24-13385

may not leverage its legitimate interest in mitigation to pursue

governmental ends that lack an essential nexus and rough

proportionality to those impacts.” Id. If there is no nexus and the

demands are not roughly proportional to the impacts, the demands

are extortionate. Id. Monetary exactions must satisfy the same

nexus and proportionality requirements. Id. at 612. An

unconstitutional land-use exaction occurs when the government

requires the landowner to surrender property in exchange for land-

use permits, unless the transfer meets the nexus and

proportionality requirements. Id. at 606; see generally Nollan v. Cal.

Coastal Comm’n, 483 U.S. 825 (1987); Dolan v. City of Tigard, 512 U.S.

374 (1994).

Where a claim alleges that an unlawful exaction has

occurred in conjunction with the granting of a development

permit, we first consider whether an “essential nexus” exists

between a “legitimate state interest” and the permit condition

exacted by the government. See Dolan, 512 U.S. at 386 (citing Nollan,

483 U.S. at 837). After establishing that an essential nexus exists, the

Court “must then decide the required degree of connection

between the exactions and the projected impact of the proposed

development.” Id. Stated simply, the government may “condition

approval of a permit on the dedication of property to the public so

long as there is a ‘nexus’ and ‘rough proportionality’ between the

property that the government demands and the social costs of the

applicant’s proposal.” Koontz, 570 U.S. at 605–06.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 37 of 41

24-13385 Opinion of the Court 37

Assuming the County must establish that the agreement

meets the nexus and proportionality requirements, the

requirements are satisfied here. But see Koontz, 570 U.S. at 604–05

(explaining that nexus and proportionality are implicated “when

owners apply for land-use permits” (emphasis added)). The

Agreement between Southeast and the County allows Southeast to

mitigate the development’s transportation impacts, a legitimate

state interest. See Dolan, 512 U.S. at 387–88 (explaining that

attempts to reduce local traffic congestion by a municipality qualify

as a legitimate public purpose). And the concurrency mechanism

allows developers to pay costs that are roughly proportionate to

their projects’ effects upon agreement with the local government.

See Fla. Stat. § 163.3180(5)(h)1. So to the extent Southeast argues

that the proportionate fair share it agreed to pay as part of the

concurrency agreement was an unlawful exaction, that argument

fails. But the variable cost (the “public benefit” from section 4(b)

of the agreement) is also not an unlawful exaction. Southeast’s

conduct explains why.

In signing the Agreement, Southeast confirmed what

contribution amount it considered roughly proportionate to its

development proposal when it agreed to construct the SR 16

improvements estimated to cost more than $15 million. Southeast

had a choice between paying for the SR 16 improvements or

constructing them itself, and it chose the latter. See Fla. Stat.

§ 163.3180(5)(h)1.c. In doing so, it voluntarily assumed full

responsibility for completion of the SR 16 improvements to satisfy

its concurrency requirements as well as its public benefit

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 38 of 41

38 Opinion of the Court 24-13385

demonstration. It did so despite the availability of alternative

avenues to satisfy its mitigation and public benefit requirements,

and cannot now argue that the conditions it put forward and agreed

to are unconstitutional. If the improvements had cost less than the

Agreement estimated they would, then Southeast would have

benefited from that windfall. We will not declare the Agreement

unconstitutional simply because it shifted from a boon to a burden

for Southeast. See Ferreira, 12 So. 3d at 868.

Nor can Southeast claim that the concurrency agreement

became an exaction after the fact when the SR 16 improvements

costs increased. Per Koontz, an exaction is not unlawful if it meets

the nexus and rough proportionality requirements. 570 U.S. at 605–

06. The parties agreed that the SR 16 improvements were

necessary to meet both Southeast’s traffic mitigation and public

benefit demonstration requirements. The agreement estimated the

SR 16 improvements costs. The nexus between the SR 16

improvements and approval of the Development remained even

when the costs to complete the improvements ballooned because

the development would still generate the need for the

improvements. And as for rough proportionality, section 4(a) of

the Agreement calculated Southeast’s proportionate share amount

based on the estimates available at the time. Southeast offered to

pay the difference between what mitigation required and what the

SR 16 improvements cost as the Development’s public benefit. We

see no violation of rough proportionality when a developer’s costs

increase at the same time the cost of the overall project increases,

especially when those costs were known to be variable at the time

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 39 of 41

24-13385 Opinion of the Court 39

of the Agreement.20 At bottom, we conclude that Southeast

accepted an arrangement to advance its Development that resulted

in a variable cost. Southeast’s desire not to pay that variable cost is

not a basis for us to overturn the contract.

Thus, the County has shown as a matter of law that holding

Southeast to the terms of the Agreement was an unconstitutional

exaction, and the district court properly granted summary

judgment to the County.

D. The Assignment’s Effects

One final matter remains. The district court granted the

County’s motion for summary judgment as to all counts in the

amended complaint and the second amended counterclaim.

Southeast argues that decision was error because Southeast

Development only assigned its rights under the contract to

Southeast Land and that Southeast Land could not breach

responsibilities it did not accept. To the extent the district court’s

judgment found that Southeast Land breached the Agreement, that

was error.

20 We note that there are no allegations in the record that any of the parties

intentionally misstated the estimated costs of the SR 16 improvements to force

Southeast to bear the significantly higher costs that became necessary to

complete the project. Rather, the record reflects that the costs increased due

to FDOT requirements unknown at the time the parties entered the

Agreement. Thus, we need not consider whether an unlawful exaction occurs

when a local government intentionally underestimates the costs of a project

in order to force an applicant to bear the higher actual costs that the

government knew were necessary.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 40 of 41

40 Opinion of the Court 24-13385

Under Florida law, an assignment of rights does not include

an assumption of liabilities by the assignee unless the assignee

expressly agrees. See Jenkins v. City Ice & Fuel Co., 118 Fla. 795, 801

(1935) (“The assignment of a personal contract does not give to the

other party to the original agreement a right of action against the

assignee for its breach, nor is the mere assignee liable unless he has

expressly agreed to become bound or has promised upon a

sufficient consideration to perform for the benefit of a third party.”)

The Agreement allowed Southeast Development to assign

its “right and obligations . . . to a successor or

owner/developer . . . .” Southeast Development chose to assign all

its “present and future rights, title, and interest, if any” to Southeast

Land, including “concurrency and impact fee agreements

pertaining to or benefiting” the development. In short, Southeast

Development assigned its rights under the Agreement to Southeast

Land, but not its obligations, which go unmentioned in the

assignment. It is axiomatic that a party cannot breach a contract

that it has no responsibilities under, and thus judgment against

Southeast Land on the breach of contract claim was error. 21

We therefore vacate the district court’s judgment against

Southeast Land concerning breach of contract, and remand for the

21 The County did not contest the issue of the assignment of obligations to

Southeast Land in its brief, and counsel for the County at oral argument

conceded that judgment was appropriate only against Southeast Development

and not Southeast Land on the County’s breach of contract claim because of

the assignment.

USCA11 Case: 24-13385 Document: 38-1 Date Filed: 08/07/2026 Page: 41 of 41

24-13385 Opinion of the Court 41

district court to modify the judgment to indicate that only

Southeast Development breached the Agreement and was

obligated under the Agreement to pay all costs for the SR 16

improvements.22

III. Conclusion

For the foregoing reasons, we deny the County’s motion to

dismiss this appeal, and we affirm the district court’s grant of

summary judgment to the County except as to the judgment

against Southeast Land on the breach of contract claims. We

vacate and remand for the district court to modify the judgment

and clarify that only Southeast Development breached the

Agreement.

AFFIRMED IN PART, VACATED IN PART, AND

REMANDED.

22 We note that even though Southeast Land could not breach an agreement

under which it had no responsibilities, the district court did not err in declaring

the County’s authority under the contract to “halt approval of additional

plats,” declaring the escrow payments forfeit, and requiring the assignment of

“the Road Design documents and any Permits to the County.” Those

remedies were consistent with the County’s rights to enforce the Agreement

upon a breach.