Opinion

Opinion

Court
District Court, N.D. Alabama
Filed
Jul 21, 2026
Cited by
0 cases
Authority
More cited than 42.0%

The opinion

UNITED STATES DISTRICT COURT

NORTHERN DISTRICT OF ALABAMA

NORTHEASTERN DIVISION

ZP 360 HUNTSVILLE

MOUNTAIN, LLC, et al.,

Plaintiffs,

v. Case No. 5:23-cv-1178-CLM

AEC SITE SOLUTIONS, LLC,

Defendant.

MEMORANDUM OPINION

In early 2022, ZP 360 Huntsville Mountain, LLC (“ZP 360”) and ZP

361 Huntsville Research Park QOZB, LLC (“ZP 361”) (collectively,

“Zimmer”) set out to build two multi-family housing developments in

Huntsville. Zimmer hired a general contractor. The general contractor

then hired a subcontractor, AEC Site Solutions, LLC (“AEC”), and work

began. But within just a few months, things started to go wrong. The

general contractor failed to meet expectations, so Zimmer terminated its

contracts. And less than a year later, after Zimmer filled the general

contractor’s shoes, Zimmer also terminated AEC’s subcontracts. Zimmer

eventually managed to complete the projects. Still, the damage was done.

Constant delays and reworks cost Zimmer time and money.

So Zimmer sued AEC to recoup losses that, it says, are attributable

to AEC and its deficient performance. Zimmer brings two claims for

negligence and two for breach of contract. The parties now move for

summary judgment. AEC asks for summary judgment on each of

Zimmer’s claims. (Docs. 78, 79). Zimmer asks for partial summary

judgment on its breach of contract claims. (Doc. 88). And Zimmer also

seeks to strike AEC’s amended answer and affirmative defenses that it

filed after discovery ended. (Doc. 75). For the reasons stated below, the

court (1) GRANTS IN PART and DENIES IN PART AEC’s motions for

summary judgment, (2) DENIES Zimmer’s partial motion for summary

judgment, and (3) DENIES Zimmer’s motion to strike AS MOOT.

BACKGROUND

This case stems from AEC’s work as a subcontractor for two housing

development projects owned by Zimmer entities. ZP 360 is the owner and

developer of one of those projects, the Terraces at High Mountain (the

“Terraces”). ZP 361 is the owner and developer of the other project, the

Boardwalk at Research Park (the “Boardwalk”). The key facts for the two

projects, and Zimmer’s claims, largely overlap.

A. The Parties and Projects

On February 28, 2022, ZP 360 hired Huffman Contractors

(“Huffman”) to serve as general contractor on its Terraces project.1 (See

doc. 86-4). A little over a week later, on March 8, ZP 361 hired Huffman

to serve as general contractor on its Boardwalk project. (See doc. 80-2).

Huffman then signed subcontracts with AEC for both projects. (See docs.

84-3; 88-9).

1. The Terraces

The Terraces project called for the construction of six apartment

buildings and a clubhouse. Each building was assigned an identification

number, with A1-A6 denoting the apartment buildings and A7 the

clubhouse. Because the Terraces site is located on hillside terrain, the

buildings had to include a “lower-level pad” and an “upper-level pad.”2

(See doc. 85-2, p. 6). After the lower-level pads were completed, “stem

walls or retaining walls were required to be constructed” before the upper-

level pads could be built. (Docs. 81-1, p. 12; 84-2, p. 14). AEC’s job was to

perform site work, “including but not limited to, demolition, erosion

control, grading, paving, utilities and other related services.” (Doc. 6, pp.

4-5). Some of AEC’s tasks under these categories included: preparing the

1 Different Huffman entities served as the general contractors on the projects, but AEC’s

corporate representative confirmed during his deposition that AEC “just knew” them both as

“Huffman.” (See doc. 88-1, p. 46-47). So this opinion treats Huffman as one entity.

2 “Pads” are cleared and leveled areas of land that “allow for follow-on construction of each pad’s

underslab utilities.” (See doc. 85-2, p. 8). Once the underslab utilities are constructed, a concrete

slab goes on top so “vertical construction” can start. (See id.).

building pads, installing sanitary and storm sewers, and completing an

on-site water tie-in. A general layout of the Terraces site is shown below:

ee / J =, □ i ail hi

> UT eet (8 SE on 4 □□□

(Doc. 85-2, p. 7).

2. The Boardwalk

The Boardwalk project was divided into two phases. Phase 1 called

for the construction of four multi-story apartment buildings, Al-A4, and

Phase 2 called for the construction of two additional buildings, A5-A6.

Unlike the Terraces, the Boardwalk site was flat. But AEC’s scope of work

for the Boardwalk was largely the same as its scope of work for the

Terraces. So AEC was again tasked with, among other things: preparing

the building pads, installing sanitary and storm sewers, and completing

an on-site water tie-in. A general layout of the Boardwalk site is shown

below:

ss ili

= pen i 1 if aa 2 a 4 i I i i i

ey a a te) □□ ma i « Pat ~f a

(Id., p. 8).

3. Project Schedules

As general contractor, Huffman developed schedules for both

projects. These schedules purportedly included deadlines for AEC to

complete certain tasks within its scope of work. The parties dispute

whether AEC received some of these schedules or agreed to be bound by

them. But the record evidence shows that, at the very least, AEC received

a milestone chart for the Terraces project on July 20, 2022. The relevant

portion of that chart is below:

UFFMAN Co HC2111 Terraces at High Mountain Chart

Last Printed On: 07/19/2022

itll ett beeslii le: eataly [Telecieta4 pveltr-}| byes titty

— AEG 04/18/2022 04/78/2022 Made

® Building Padi AEC 07/18/2022

# Building Pad 2 □□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□

© Building Pad 3 AEC 08/01/2022

# Building Pad 4 □□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□□

© Building Pad 5 ABC ~—~—~—“CwBNIVD—

* Building Pad 6 AEG 08/21/2022

© Building Pad 7 aC ogj2g2022—~” □□□ ———

#55 AEC 08/17/2022

+ Storm AEC 08/22/2022

Water □□□□□□□□□□□□□□□□□□□□□□□□□

(See doc. 88-10, p. 3). As shown, Huffman “forecast” that AEC would

complete general construction tasks for the Terraces no later than October

2022. Aside from this chart, Zimmer contends that Huffman provided

AEC two other schedules that “fixed” AEC’s construction milestones. (See

doc. 90, pp. 14, 17). One of those schedules applied to the Terraces project

and mostly tracks the deadlines shown in the chart above. (See doc. 88-

11). The other schedule applied to the Boardwalk project. According to

Zimmer, it included the following deadlines for AEC:

a. Building Al: September 12, 2022

b. Building A?: September 19, 2022

c. Building A3: September 26, 2022

d. Building A4: October 3, 2022

e. Building A5: October 10, 2022

f Sanitary Sewer: October 14, 2022

g. Building A6: October 17, 2022

h. Building A7: October 24, 2022

i. Building A8: October 31, 2022

j- Water System: November 9, 2022

k. Storm Drainage: April 18, 2023

1. Curbs/Roadways: February 17, 2023

(See doc. 90, p. 17; see also doc. 88-3). AEC’s owner and 30(b)(6) witness,

Bennett Steele, stated that he had “never [seen] .. . or agreed to” the above

schedule. (See doc. 88-2, pp. 326-27). But email correspondence between

Huffman personnel reflects that the schedule received “some input” from

an AEC employee named Don Byrd—someone Steele said that AEC

employed to assist with “project management” and “pricing.” (See id., p.

43).

Despite AEC’s apparent communication with Huffman regarding

the schedules, Steele maintains that “AEC never agreed to a schedule and

no schedule was ever made a part of” the subcontracts. (See docs. 86-1, p.

2; 86-2, p. 2). Both subcontracts show that an “Exhibit C” would provide a

“progress schedule.” (See docs. 84-2, p. 150; 88-9, p. 28). But as best the

court can tell, no filed version of the subcontracts includes an Exhibit C.

And according to AEC, “no schedule was incorporated into Exhibit C.”

(Docs. 91, p. 4; 93, p. 5).

B. The Relevant Contracts

Two sets of contracts are important here: (1) Zimmer’s general

contracts with Huffman and (2) the subcontracts between Huffman and

AEC.

The general contracts required Huffman to “prepare and submit …

critical path schedules showing the relative times for performance of all

significant tasks” assigned to Huffman and its subcontractors. (Doc. 80-2,

p. 73). At minimum, those schedules were to include “permit dates;

procurement dates … and the start/finish dates for construction of all

critical path activities.” (See id.). In § 16.10, Huffman warranted, as the

general contractor for both projects, that it was “qualified and licensed to

perform construction services” in Alabama. (See id., p. 27). Despite these

warranty provisions, the general contracts allowed Zimmer, which is not

a licensed general contractor, to take assignment of any subcontracts

Huffman entered if Zimmer terminated the general contracts and notified

the subcontractors of the assignment in writing. (See id., p. 90).

The subcontracts recognized Huffman’s general contracts with

Zimmer and stated that AEC “agree[d] to perform, as an independent

contractor, the portion of Huffman’s work under the [general contracts] as

set forth in [the subcontracts’] scope of work.” (See docs. 84-3, p. 3; 88-9,

p. 3). To that end, the subcontracts laid out AEC’s scope of work as

described above. (See docs. 84-3, pp. 35-38; 88-9, pp. 35-40). The

subcontracts contained a contingent assignment clause that permitted

Zimmer to fill Huffman’s shoes as the general contractor if Zimmer

terminated Huffman’s general contracts. (See docs. 84-3, p. 25; 88-9, p.

24). The subcontracts also contemplated project scheduling. They required

AEC to “prosecute” its subcontract work “in strict accordance with [the

general contractor’s] schedule and sequencing directives and to otherwise

prosecute the work diligently and in cooperation with others contributing

to the work … so as to not hinder in any way [the general contractor’s]

compliance with its project schedule, milestone dates, and completion

deadlines.” (Docs. 84-3, p. 12; 88-9, p. 11). Art. 3.4 of the subcontracts

required AEC to pay $1,000 in liquidated damages “per calendar day for

each day [AEC] fails to meet the portion of the schedule[s] attributed to

its work or for each calendar day beyond allotted contract time that [AEC]

is not complete with its work.” (Docs. 84-3, p. 12; 88-9, p. 12).

The subcontracts also imposed workmanship and warranty

obligations on AEC. For example, the subcontracts required AEC to

“promptly correct” nonconforming work and bear the costs of correction:

If [the general contractor] rejects the Subcontract Work or

the Subcontract Work is not in conformance with the

Subcontract Documents, [AEC] shall promptly correct the

Subcontract Work whether it has been fabricated,

installed, or completed. [AEC] shall be responsible for the

costs of correcting such Subcontract Work, any additional

testing, inspections, and compensation for services and

expenses of [the general contractor] made necessary by the

defective work.

(Docs. 84-3, p. 9; 88-9, p. 9). Moreover, Exhibit A required AEC to bear all

remedial and corrective costs for work not done in accordance with the

subcontracts. (See docs. 84-3, p. 31, 88-9, p. 31). If AEC failed to comply

with these requirements, then § 7.1.2 of the subcontracts provided a two-

notice termination procedure, which permitted the general contractor to

terminate AEC for cause after a second 48-hour cure period passed.

In the event of termination for cause, the subcontracts allowed the

general contractor “to recover from [AEC] all associated costs, expenses,

and other damages, including but not limited to associated legal fees and

any amounts paid to correct and/or complete the Subcontract Work (plus

15%) that, together with all other funds paid to complete any portion of

the Subcontract Work, exceed the Subcontract Amount established under

[the subcontracts].” (Docs. 84-3, p. 23; 88-9, p. 23).

C. Construction Delays and Contract Terminations

By September 2022, both projects had problems. Construction of the

Terraces’ pads lagged months behind schedule. Progress on the Terraces’

utilities and paving also stalled. Similar problems plagued the Boardwalk

project. The pads for A1 and A2 at the Terraces site were delayed for a

minimum of twelve weeks, and after rock was uncovered under pad A3,

its construction was delayed too. Because the pads were foundational

parts of the projects, vertical construction was hindered.

Unsurprisingly, Zimmer was displeased with the delays. So on

September 16, 2022, Zimmer terminated Huffman from both the Terraces

and Boardwalk projects “for convenience.” (See docs. 87-13, p. 2; 87-14, p.

2). The termination letters noted that Zimmer would “review all

subcontracts … that [were] in place for [the] project[s],” so it could

“determine if any should be assigned to [Zimmer] or simply terminated.”

(Id.). According to Zimmer’s corporate representative, Charles Tucker,

Zimmer terminated Huffman because of its poor management and

because it partly caused the delays. A month later, Zimmer took

assignment of AEC’s subcontracts and effectively filled Huffman’s shoes

as the general contractor. Zimmer notified AEC of the assignment on

October 12, 2022.

Firing Huffman apparently didn’t improve things because Zimmer

contends that, by January 2023, AEC had fallen nearly five months

behind schedule on several items at the Terraces, including pad A1, the

clubhouse pad, the pool pad, the sanitary sewer, and water lines. Similar

delays stalled the Boardwalk project. Zimmer also identified foundational

issues at the Terraces site, “including over-excavation,

unsuitable/reworked fill, and a large deleterious soil/rock stockpile

requiring export.” (Doc. 90, p. 15). Testing showed that the clubhouse pad

at the Terraces “required reworking due to moisture and improper

compaction.” (Id.). And the discovered rock under pad A3 continued to

impede construction.

By April 2023, Zimmer had enough of the delays. So as the assignee

of the subcontracts, Zimmer issued a detailed written notice to AEC for

both projects under § 7.1.2 of the subcontracts. The notices identified

performance, testing, and schedule deficiencies and demanded cure. They

also provided AEC with a new schedule “to keep the project moving.” (See

doc. 89-19, p. 5). After two days passed, Zimmer issued AEC a follow-up

notice reiterating the demand to cure and providing notice of an intention

to terminate the subcontracts. And four days after that, Zimmer sent AEC

a second formal notice of intent to terminate for cause due to AEC’s

default and apparent abandonment of the projects. AEC never cured the

defaults identified in Zimmer’s notices, so on May 3, 2023, Zimmer

terminated AEC for cause on both projects. By the termination date, AEC

had received approximately $4.5 million in payments. Of that total,

Zimmer had paid AEC roughly $3.2 million after it took the assignment

of the subcontracts.

The same day Zimmer terminated AEC, it hired Buffalo Builders,

LLC to step in as the general contractor for the Terraces and Boardwalk.

The projects were eventually corrected and completed.

D. Zimmer’s Alleged Damages

During discovery, Zimmer estimated damages across both projects

to be $69,589,985.41. Here’s how Zimmer calculates damages for Terraces:

HUNTSVILLE: HIGH MOUNTAIN - DAMAGES

SUM PAR TOTAL

Interest Expense 3 840,512.51

Loss of Rants 3 §,496,4397.14

Opportunity Cost 3 20,474,072.22

Construction Replacement Oo a1 3 5,384, 500.50

onstruction Corrective Work 3 4, 94) Bt

Insurance Expense 3 291,827.00

200 Mgmt 3 175,000.00

Travel Expange 3 13,606.08

Legal Expense 3 549,090.40

Outside Consultants. 3 178,362.52

(Doc. 98-1, p. 6). And here’s how Zimmer calculates damages for the

Boardwalk:

HUNTSVILLE: RESEARCH - DAMAGES

bette Expe née 5 B33,117.79

Loss of fants 5 4,117,127.85

Opportunity Gast 5 28,303, 672.22

Construction Replacenvent Cost 3 1.411, 766.66

Construction Conrective Work 5 141,487.16.

Inéurance Expense 5 84,407.40

Mgmt 3 175,000.08)

Travel Expense 5 13,606.07

Legal Expense 5 549,056.92

Outside Consultants. 5 232,600.39

(Doc. 98-1, p. 25).

Some of these figures are straightforward and don’t require much

explanation. Others are more complex. Using the Terraces as an example,

Zimmeyr’s interest expense category consists of a “preferred” interest

return to an investor and LLC member, CK Management. (See doc. 86-8,

pp. 36-37). Zimmer calculated the “loss of rents” category by assuming an

apartment occupancy rate at 95%, calculating a net operating income

based on projected rents, dividing it by twelve to get a monthly figure, and

then multiplying the remaining value by eighteen (i.e., the number of

months Zimmer claims AEC delayed completion). (See id., pp. 39-40). And

Zimmer calculated its largest category of damages, “opportunity cost,” by

generating a net value for the properties had they been completed on time

with a 4.5% capitalization rate and subtracting the actual net value for

the properties when they were completed with a 6% capitalization rate.

(See id., pp. 41-42; see also doc. 98-1, p. 23). According to AEC’s corporative

representative, the applicable market capitalization rate increased from

4.5% to 6% during the 18-month construction delay, and that rate increase

reduced the value Zimmer could have received by selling the properties

on the open market.?

3 Tucker said during his deposition that Zimmer had received “emails from brokers” inquiring

about the properties. (See doc. 86-3, p. 42). But at the time of Tucker’s deposition, Zimmer was

not actively attempting to sell either the Boardwalk or the Terraces. (See id.).

10

E. Claims and Pending Motions

Zimmer sued AEC on September 5, 2023. AEC answered and

counterclaimed. (See doc. 17). In December 2023, Zimmer filed third-party

claims against Huffman and Travelers Casualty and Surety Company of

America. (See doc. 24). The parties settled those third-party claims, (see

docs. 67, 68), leaving only Zimmer and AEC suing each other.

This order deals with Zimmer’s four claims; two brought by ZP 360

related to the Terraces and two by ZP 361 related to the Boardwalk:

• Count 1: Breach of Contract. As assignee of the Terraces

subcontract, ZP 360 contends that AEC breached its obligations

under the subcontract by performing defective work, failing to

complete its scope of work, overbilling for work not performed,

causing damage to the Terraces site and adjacent properties, failing

to perform timely work, and removing materials from the Terraces

site without permission. (See doc. 6, pp. 8-9).

• Count 2: Negligence. As owner of the Terraces, ZP 360 claims that

AEC owed it a duty to perform work “in a reasonable and prudent

manner and in accordance with the applicable standard of care

exercise[d] by general contractors on the same or similar projects,

and in accordance with applicable Legal Requirements.” (Id., pp. 9-

10). ZP 360 says that AEC breached that duty and caused it to suffer

damages. ZP 360 also contends that AEC’s failure to comply with

applicable Legal Requirements “constitutes negligence per se under

Alabama law.” (Id.).

• Count 3: Breach of Contract. As assignee of the Boardwalk

subcontract, ZP 361 claims that AEC breached its contractual

obligations in the same manner described in Count 1. (See id., pp.

10-11).

• Count 4: Negligence. As owner of the Boardwalk, ZP 361 contends

that AEC breached its duty of care in the same manner described in

Count 2. (See id., pp. 11-12).

LEGAL STANDARD

Summary judgment is appropriate when the pleadings, depositions,

answers to interrogatories, and admissions on file, together with the

affidavits, show there is no genuine issue as to any material fact and that

the moving party is entitled to judgment as a matter of law. Fed. R. Civ.

P. 56(c); Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). The moving

party bears the initial burden of stating the basis for its motion and

identifying those portions of the record showing the absence of genuine

issues of material fact. Celotex, 477 U.S. at 323. The burden can be

discharged if the moving party can show the court that there is “an

absence of evidence to support the nonmoving party’s case.” Id. at 325.

When the moving party has carried its burden, the nonmoving party must

then designate specific facts showing that there is a genuine issue of

material fact. Id. at 324. Issues of fact are “genuine only if a reasonable

jury, considering the evidence present, could find for the nonmoving

party,” and a fact is “material” if it may affect the outcome of the case

under governing law. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-

49 (1986). In determining whether a genuine issue of material fact exists,

the court must consider all the evidence in the light most favorable to the

nonmoving party. Celotex, 477 U.S. at 323.

The standard of review on cross-motions for summary judgment is

no different from the standard applied when only one party files a motion.

Torres v. Rock & River Food Inc., 244 F. Supp. 3d 1320, 1327 (S.D. Fla.

2016) (citing Am. Bankers Ins. Grp. v. United States, 408 F.3d 1328, 1331

(11th Cir. 2005)). “Cross-motions for summary judgment will not, in

themselves, warrant the court in granting summary judgment unless one

of the parties is entitled to judgment as a matter of law on facts that are

not genuinely disputed.” United States v. Oakley, 744 F.2d 1553, 1555

(11th Cir. 1984) (internal quotation marks and citation omitted). Thus, “a

court must consider each motion on its own merits, resolving all

reasonable inferences against the party whose motion is under

consideration.” Torres, 244 F. Supp. 3d at 1327-28 (citing Am. Bankers

Ins. Grp., 408 F.3d at 1331).

DISCUSSION

Both parties move, at least partially, for summary judgment on

Zimmer’s four claims. Zimmer also moves to strike AEC’s amended

answer and affirmative defenses. The court starts by analyzing AEC’s

motions and then moves to Zimmer’s motions.

I. AEC’s Motion for Summary Judgment on Zimmer’s Claims

AEC moves for summary judgment on ZP 360 and ZP 361’s claims

on the same grounds. Those grounds are: (1) Zimmer cannot meet the

elements of negligence per se or negligence and (2) Zimmer’s breach of

contract claims fail under Alabama law.

A. Zimmer’s Negligence Claims: Counts 2 and 4

To begin, AEC contends that Zimmer cannot sustain claims for

negligence per se. While Zimmer does allege in Counts 2 and 4 that AEC’s

deficient work “constitutes negligence per se under Alabama law,”

Zimmer clarified in its response briefs that it only brings claims for

common law negligence. (See doc. 6, pp. 10, 12; see also doc. 101, p. 34).

Because Zimmer has abandoned any claims for negligence per se, the

court will grant AEC’s motion for summary judgment on Counts 2 and 4

as much as they raise claims for negligence per se. With that said, Zimmer

adequately pleads common law negligence. So the court will examine

those claims.

To establish negligence under Alabama law, Zimmer must provide

evidence to support the standard elements: (1) duty, (2) breach, (3)

causation, and (4) damages. See Albert v. Hsu, 602 So. 2d 895, 897 (Ala.

1997). In the operative complaint, Zimmer pleads that (1) AEC owed a

duty “to perform its work in a reasonable and prudent manner in

accordance with the applicable standard of care exercise[d] by general

contractors on the same or similar projects”; (2) AEC “breached its duty of

care … by performing defective work, causing damage to the [projects] and

adjacent properties, … and performing its work on the [projects] in

violation of applicable Legal Requirements”; and (3) as a “direct and

proximate result of [AEC’s] negligence, [Zimmer incurred] substantial

additional construction and repair costs, property damage, and delay

damages[.]” (Doc. 6, pp. 9-10, 12-13).

AEC contests the breach, causation, and damages elements.

Specifically, AEC argues that Zimmer’s negligence claims fail because

(a) AEC cannot be held to Zimmer’s pleaded standard of care (i.e., that of

“general contractors on the same or similar projects”), (b) Zimmer failed

to produce evidence from a licensed subcontractor in AEC’s line of work

that AEC breached the standard of care, (c) Zimmer failed to produce

evidence of defective work, and (d) Zimmer failed to produce evidence

reflecting costs that it incurred from the alleged project damage or

completion costs. (See docs. 91, pp. 18-21; 93, pp. 17-20). AEC also

contends in its reply brief that Zimmer’s negligence claims fail because

they are incompatible with Zimmer’s breach of contract claims. (See doc.

106, p. 14).

1. Standard of Care Argument. Zimmer pleads that AEC owed a

duty “to perform its work in a reasonable and prudent manner and in

accordance with the applicable standard of care exercise[d] by general

contractors on the same or similar projects[.]” (See doc. 6, pp. 9, 12)

(emphasis added). AEC contends this assertion is “problematic” because

“AEC was not the general contractor on the project, rather it was a

subcontractor[.]” (Docs. 91, p. 18; 93, p. 17). AEC is correct that the

applicable standard of care for its conduct is that of a subcontractor—not

a general contractor. But whatever difference that label yields is

inconsequential for purposes of summary judgment. Zimmer’s complaint

makes clear that AEC was a subcontractor and that Zimmer seeks to hold

AEC liable for negligence as a subcontractor. So, looking at the complaint

in its entirety, the court finds no reason to grant AEC summary judgment

based on the technical language Zimmer used in Counts 2 and 4. See

Smith v. Commissioner, Ala. Dep’t of Corr., 2021 WL 4916001, at *2 (11th

Cir. Oct. 21, 2021) (refusing to “prioritize the form of the pleadings over

their substance”); see also Fed. R. Civ. P. 8(e) (“Pleadings must be

construed as to do justice.”).

2. Expert Qualifications Argument. Next, AEC argues that

Zimmer has “failed to meet its burden to maintain its negligence claims”

because it didn’t “produce[] evidence from a licensed subcontractor, who

works in the same line of work of AEC, that AEC breached any standard

of care” on the projects. (See docs. 91, pp. 18-19; 93, pp. 17-18). This

argument fails.

Zimmer’s expert, David Marsh, opined that AEC provided defective

work at both project sites. (See doc. 80-3, pp. 9-14). And while Marsh is

not a “licensed subcontractor,” that gap in his qualifications isn’t

disqualifying. Indeed, courts determine an expert’s qualifications by

assessing his knowledge, skill, education, training, and experience—not

solely his professional licensure. See United States v. Frazier, 387 F.3d

1244, 1260-61 (11th Cir. 2004) (en banc). Marsh is a licensed professional

engineer in Alabama with over 19 years of experience in engineering and

project management. (See doc. 83-1, pp. 4-5). He’s familiar with relevant

industry standards applicable to AEC’s workmanship. And he works for

Engineering Consulting Services, a construction firm in Huntsville that

was involved with the Terraces and Boardwalk projects. So his overall

qualifications render him fit to provide opinions in this case.

At bottom, “a witness is qualified as an expert if he is the type of

person who should be testifying on the matter at hand.” Moore v. Intuitive

Surgical, Inc., 995 F.3d 839, 852 (11th Cir. 2021). Because Marsh fits that

bill, the court will deny AEC’s motion for summary judgment based on

Marsh’s qualifications. AEC, of course, can argue any shortcomings it

perceives in Marsh’s qualifications to a jury.

3. Defective Work Argument. AEC also contends that, even if

Marsh is qualified to provide opinions on defective work, he did not

sufficiently identify property damage caused by AEC at either the

Terraces or Boardwalk sites.

AEC is wrong. According to Marsh’s expert report, AEC inflicted

physical damage to the Boardwalk site by “clearing beyond authorized

construction limits.” (See doc. 80-3, p. 12). More specifically, Marsh says

that AEC left a shear cut in the Boardwalk Phase 2 area and that this cut

is “not stable long-term and should be anticipated to erode and slough.”

(Id.). While Marsh couldn’t quantify how much Zimmer would be forced

to spend to correct this defective work, he noted that it could impose a

“very significant cost” to “restore the area to the pre-development

condition.” (Id.).

Marsh identified even more examples of AEC’s defective work at the

Terraces site. For example, Marsh says in his report that AEC removed

“soil overburden that was suitable for reuse as fill” from the Terraces site.

(Id., p. 13). This was problematic, according to Marsh, because it led to “a

significant deficit in soil material quantity as the final grading

progressed.” (Id.). Marsh also says that AEC damaged the Terraces site

by, once again, “clearing beyond authorized construction limits.” (Id.).

According to Marsh, AEC “cleared and partially graded” a vegetative

buffer at the eastern side of the Terraces site, which “create[d] more

susceptibility of the site to erosive forces” and resulted in “run off faster

than the Civil Engineer designed the site to handle.” (Id.). Finally, Marsh

notes in his report that AEC “overexcavat[ed]” rock beyond the basement

walls for Buildings A1, A2, and A3. (Id.). Marsh says this defective work

“required far greater volume of fill to backfill the [basement] walls and

[caused] significant delay to replace the excessive excavation.” (Id.).

As shown, Marsh identified specific examples of “defective work” by

AEC that delayed the projects and caused Zimmer to bear remediation

costs. So AEC is not entitled to summary judgment based on its argument

that Marsh failed to identify property damaged caused by AEC.

4. Damages Argument. AEC next contends that Zimmer “failed

to provide any other form of credible evidence reflecting costs it incurred

from the alleged site damage or completion costs.” (Docs. 91, p. 20; 93, p.

19). AEC argues that Zimmer’s claimed damages, reflected in a

spreadsheet and informed by remediation costs submitted by Buffalo

Builders, are speculative and do not specifically identify the costs Zimmer

incurred to fix AEC’s defective work.

AEC is correct that Zimmer’s experts can’t precisely determine the

amount of damages Zimmer incurred because of AEC’s allegedly defective

work. Marsh, for example, attributes blame for the defective shear cut at

the Boardwalk site to AEC but states that Huffman’s “lack of oversight

and control” also contributed to Zimmer’s remediation costs. (See doc. 80-

3, p. 12). But that’s where Alabama rules on tort liability kick in. Under

Alabama law governing joint and several liability, “[a] tort-feasor whose

negligent act or acts proximately contribute in causing an injury may be

held liable for the entire resulting loss.” Holcim (US), Inc. v. Ohio Cas.

Ins. Co., 38 So. 3d 722, 729 (Ala. 2009) (quoting Nelson Bros., Inc. v. Busby,

513 So. 2d 1015, 1017 (Ala. 1987)). Because Zimmer has provided evidence

that AEC engaged in defective work that proximately caused Zimmer to

suffer remediation and delay costs, AEC can be held liable for the entire

resulting loss. Thus, AEC is not entitled to summary judgment based on

Zimmer’s failure to pinpoint the damages AEC caused.

5. Reply Brief Argument. Finally, AEC contends in its reply

brief that Zimmer cannot sustain negligence claims because they arise

from a “breach of promise within the [subcontracts].” (Doc. 106, p. 14).

This argument fails for two reasons. First, AEC waived the argument by

waiting to raise it until the reply brief. See In re Egidi, 571 F.3d 1156,

1163 (11th Cir. 2009) (“Arguments not properly presented in a party’s

initial brief or raised for the first time in the reply brief are deemed

waived.”). Second, even if AEC hadn’t waived the argument, it would still

likely fail because Zimmer can pursue negligence claims based on AEC’s

negligent affirmative conduct in its performance of the subcontracts. See

Morgan v. S. Cent. Bell Tel. Co., 466 So. 2d 107, 114 (Ala. 1985) (stating

that while there is “no tort liability for nonfeasance for failing to do what

one has promised,” there can be tort liability “for misfeasance, or negligent

affirmative conduct in the performance of a promise”). Here, Zimmer

claims that AEC engaged in misfeasance by damaging the project sites.

Those claims sound in tort and are actionable under Alabama law.

——

In sum, the court will grant AEC’s motions on Counts 2 and 4 as

much as Zimmer raises claims for negligence per se. But the court will

deny AEC’s motions as applied to Zimmer’s common law negligence

claims.

B. Zimmer’s Breach of Contract Claims: Counts 1 and 3

AEC next challenges Zimmer’s breach of contract claims in Counts

1 and 3. To prove a breach of contract under Alabama law, Zimmer must

establish (1) the existence of a valid contract binding the parties; (2) its

own performance under the contract; (3) the defendant’s nonperformance;

and (4) damages. S. Med. Health Sys., Inc. v. Vaughn, 669 So. 2d 98, 99

(Ala. 1995).

Zimmer asserts its breach of contract claims as the assignee of the

subcontracts between Huffman and AEC. See Nissan Motor Acceptance

Corp. v. Ross, 703 So. 2d 324, 326 (Ala. 1997) (“A valid assignment gives

the assignee the same rights, benefits, and remedies that the assignor

possesses.”). As assignee, Zimmer claims that AEC breached both

subcontracts by: (a) performing defective work; (b) failing to complete its

scope of work; (c) overbilling ZP for work that was not performed; (d)

causing damage to the project sites and adjacent properties; (e) failing to

timely perform its work; (f) removing materials from the site without

approval; and (g) performing its work in violation of “Legal

Requirements.” (See doc. 6, pp. 8-12).

AEC challenges Zimmer’s breach of contract claims on the following

grounds: (1) Zimmer is prohibited under Alabama law from acting as its

own general contractor; (2) Zimmer’s “contract damages” are misplaced;

(3) Zimmer cannot assert delay damages as assignees of the subcontracts;

(4) AEC was not bound by a project schedule; (5) Zimmer is not entitled to

attorneys’ fees; and (6) Zimmer’s delay damages are barred by accord,

satisfaction, and release. (See docs. 91, p. 2; 93, p. 2). The court walks

through each argument in turn.

1. Legal Prohibition Argument. To start, AEC contends that

Alabama Code § 34-8-1(a) prohibited Zimmer from taking assignment of

the subcontracts because Zimmer lacks an appropriate license to engage

“in the business of general contracting.” (See docs. 91, p. 22; 93, p. 21).

Because AEC’s argument rests on the interpretation of an Alabama

statute, the court starts with its text. When the parties signed the

subcontracts, the Alabama Code defined a “general contractor” as follows:

(a) For the purpose of this chapter, a ‘general contractor’ is

defined to be one who, for a fixed price, commission, fee, or

wage undertakes to construct or superintend or engage in

the construction, alteration, maintenance, repair,

rehabilitation, remediation, reclamation, or demolition of

any building, highway, sewer, structure, site work,

grading, paving or project or any improvement in the State

of Alabama where the cost of the undertaking is fifty

thousand dollars or more, shall be deemed and held to have

engaged in the business of general contracting in the State

of Alabama.

Ala. Code § 34-8-1(a).4 Building on this definition, Ala. Code § 34-8-6(a)

makes it a crime for any person or entity without a valid general

contracting license to engage in the business of general contracting:

(a) Any person, firm, or corporation not being duly

authorized who shall engage in the business of general

contracting in this state, except as provided for in this

chapter, and any person, firm, or corporation presenting or

attempting to file as its own the license certificate of

another, or who shall give false or forged evidence of any

kind to the board, or to any member thereof, in obtaining

a certificate of license, or who falsely shall impersonate

4 The Alabama Legislature amended this provision in 2024 and raised the statutory threshold

from $50,000 to $100,000.

another, or who shall use an expired or revoked certificate

of license shall be deemed guilty of a Class A misdemeanor

and for each offense for which he or she is convicted shall

be punished as provided by law[.]

Alabama courts have applied versions of the above provisions in cases

where an unlicensed contractor seeks to recover against an owner in

contract. See, e.g., Architectural Graphics and Const. Servs., Inc. v.

Pitman, 417 So. 2d 574, 576-77 (Ala. 1982). In those cases, courts have

consistently refused to enforce commercial contracts that exceed the

statutory threshold because, according to the courts, the parties entered

into the contracts illegally. See id.; see also Hawkins v. League, 398 So. 2d

232, 237 (Ala. 1981) (reversing a judgment for an unlicensed general

contractor because it did not have a valid general contractor’s license).

With that background law in mind, AEC contends that Zimmer’s

claims for breach of the subcontracts must fail because, when Zimmer took

assignment of the subcontracts from Huffman, it did not hold a valid

general contractor’s license. Put differently, AEC asks the court to find

the assignments (and by extension, the subcontracts) void because

enforcing them would be to enforce illegal contracts.

AEC is right that Zimmer didn’t hold a general contractor’s license

when it took assignment of the contracts. But that doesn’t matter.

Remember, Ala. Code § 34-8-1(a) defines a “general contractor” as one who

“for a fixed price, commission, fee, or wage” undertakes construction

projects in Alabama above the statutory threshold cost. Zimmer didn’t

take assignment of the subcontracts and then charge itself a “fixed price,

commission, fee or wage[.]” So it doesn’t meet the statute’s definition of a

“general contractor” “engaged in the business of general contracting.” And

since it doesn’t meet that definition, the illegality provisions found in § 34-

8-6(a) don’t apply to the assignments.

This interpretation is strengthened by a neighboring “owner’s

exemption” provision found in Ala. Code § 34-8-7(a)(3). That provision

exempts “a person, firm, or corporation constructing a building or other

improvement on his, her or its own property” from licensing requirements

“provided that any of the work contracted out complies with the definition

in this chapter for general contractor.” Zimmer, while assignee of the

subcontracts, still maintained its status as an entity “constructing a

building or other improvements” on its own property. Coupled with the

plain reading of § 34-8-1(a)’s definition of a general contractor, this

provision shows that Alabama’s statutory scheme doesn’t invalidate the

subcontract assignments.

Likely sensing that the statute’s language cuts against its position,

AEC latches on to Ala. Admin. Code r. 230-X-1-.07, which provides:

A person, firm, or corporation which undertakes to

construct a building or other improvements on his/her own

real property (Exception--is long term lease with option to

extend/or purchase as in an Industrial Development Board

situation) is not required to be licensed as a general

contractor if the person, firm or corporation’s own forces

(non-contractual) are used. An owner/builder may only let

and/or award contracts for work in the amount of $50,000

($5,000 for swimming pools) or greater to a properly

licensed prime contractor.

According to AEC, this administrative code provision makes Zimmer an

unlicensed general contractor because, at the time it took assignment of

the subcontracts, the project work was being performed by subcontractors

rather than Zimmer’s employees.

The court rejects this argument for a few reasons. First, the

Alabama Supreme Court has cautioned courts from reading

administrative codes in a way that narrows or alters statutes, and

adopting AEC’s reading of the administrative code would do exactly that

here. See Ex Parte Jones Mfg. Co., 589 So. 2d 208, 210-11 (Ala. 1991) (“[A]

regulation cannot subvert or enlarge [a] statutory policy” and a general

grant of regulatory authority “cannot override the specific provision” of a

statute). Second, AEC cannot point to any binding Alabama case law that

adopted and applied AEC’s view of the administrative code on a similar

set of facts. And third, Alabama case law suggests that courts shouldn’t

enforce the licensing statutes to void contracts unless it’s shown that an

unlicensed general contractor intended to circumvent licensing

requirements. See Med Plus Props. v. Colock Const. Grp., Inc., 628 So. 2d

370, 375 (Ala. 1993). AEC hasn’t made that showing here.

To sum up, the court finds that Zimmer’s assignment of the

subcontracts is not voided by Alabama’s general contractor licensing

requirements. So the court will deny AEC’s motion for summary judgment

on that ground.

2. Misplaced Damages Argument. AEC next contends that

Zimmer cannot recover certain categories of damages it claims because

the damages “do not flow from its capacity as assignee to the

[subcontracts]” but instead “reflect financial losses which are uniquely

limited to [Zimmer’s] capacity as the project owner.” (See docs. 91, p. 25;

93, p. 24). These challenged damages categories include: (1) interest

expense for an investor in Zimmer; (2) loss of rents that may have been

earned had the projects been completed on time; (3) opportunity costs

Zimmer incurred because of market condition changes that occurred

between the projected date of completion and the actual date of

completion; and (4) increased management costs incurred by Zimmer

between the projected date of completion and the actual date of

completion.

AEC is right that Zimmer can’t recover these damages. Under

Alabama law, “a valid assignment gives the assignee the same rights,

benefits, and remedies that the assignor possesses.” Nissan Motor Corp.,

703 So. 2d at 326. So Zimmer, as assignee, gets the “same rights, benefits,

and remedies” that Huffman would have possessed if Huffman had

remained the general contractor. See id. Section 7.1.2 to the subcontracts

expressly permits the general contractor to recover from AEC “all

associated costs, expenses, and other damages, including but not limited

to associated legal fees and any amounts paid to correct and/or complete

the Subcontract Work (plus 15%) that, together with all other funds paid

to complete any portion of the Subcontract Work, exceed the Subcontract

Amount established under [these] agreement[s].” (See docs. 84-2, p. 144;

88-9, p. 23). Exhibit A to the subcontracts also states that AEC is

“responsible [for] all remedial/corrective costs” if its work fails to comply

with the subcontracts. (See docs. 84-2, p. 152; 88-9, p. 31). But nothing in

the subcontracts permits Zimmer—standing in Huffman’s shoes as the

subcontractor assignee—to recover damages only relevant to Zimmer’s

role as the owner of the Terraces and Boardwalk.

Zimmer admits that completion and correction costs “are the

strongest category of damages because they are explicitly contemplated

by the [subcontracts] that AEC assigned.” (See doc. 102, p. 33). Yet

Zimmer still contends that “AEC’s challenges to [Zimmer’s] recovery of

consequential damages such as lost rents, interest expenses, or

opportunity costs go the measure of damages at trial—not to whether

[Zimmer] is entitled to any recovery.” (Id.). That’s not entirely correct.

While it’s true that certain categories of damages being unavailable

doesn’t doom Zimmer’s breach of contract claims, it’s not true that all

“consequential damages … go to the measure of damages at trial.” (See

id.). Zimmer filled Huffman’s shoes under the subcontracts, so Zimmer

can only recover what Huffman could’ve recovered had the subcontracts

not been assigned and Huffman sued AEC. See Nissan Motor Corp., 703

So. 2d at 326 (“A valid assignment gives the assignee the same rights,

benefits, and remedies that the assignor possesses.”) (emphasis added).

Because Huffman couldn’t have recovered opportunity costs or any other

damages unique to Zimmer as the owner of Terraces and Boardwalk,

Zimmer can’t either. The court will therefore grant in part AEC’s motion

for summary judgment on Counts 1 and 3. Zimmer may not seek to recover

breach of contract damages at trial except those that are specifically

available to it as assignee of the subcontracts.

3. Delay Damages Argument. AEC also attacks Zimmer’s claim

for “delay damages” on the grounds that it’s disallowed by Art. 3.4 of the

subcontracts. Art. 3.4 provides:

Delays Caused by Subcontractor. In the event

liquidated damages are provided for and assessed by

Owner against Huffman under the Prime Contract,

Huffman may, in addition to any other available remedies

or damages, assess against or otherwise recover from

Subcontractor a share of the damages in proportion to the

Subcontractor’s share of the responsibility for the

damages. Subcontractor may be assessed a minimum of

$1,000 per calendar day for each day the Subcontractor

fails to meet the portion of the schedule attributed to its

work or for each calendar day beyond allotted contract

time that Subcontractor is not complete with its work.

(Docs. 84-3, p. 12; 88-9, p. 12). AEC interprets this provision to limit

Zimmer’s right “to assert delay damages against AEC only to the extent

it asserted liquidated damages against Huffman.” (Docs. 91, p. 28; 93, p.

27). And because Zimmer didn’t assert liquidated damages against

Huffman before settling its claims with Huffman, AEC says that Zimmer

cannot seek delay damages now as assignee of the subcontracts.

Zimmer argues in response that its delay damages stem from §

7.1.2’s broad damages provision—not Art. 3.4’s narrow one. According to

Zimmer, § 7.1.2 applies in instances where the general contractor

terminates the subcontracts “for cause,” which is what happened here. So,

Zimmer says, AEC’s reading of Art. 3.4 “would render the termination-

for-cause remedies meaningless by eliminating delay damages in every

case where the owner settled with the general contractor without seeking

liquidated damages.” (See docs. 101, pp. 30-31; 102, p. 31).

Zimmer has the better argument. Art. 3.4, by its plain language,

only applies “in the event liquidated damages are provided for and

assessed by [Zimmer] against Huffman under the Prime Contract.” (Docs.

88-5, p. 3; 88-9, p. 12) (emphasis added). Further, Art. 3.4 specifically

notes that Zimmer (as assignee) may possess “any other available

remedies or damages.” (Id.). So Zimmer’s claim for delay damages isn’t

cabined by Art. 3.4.

AEC argues in the alternative that, even if “delay damages were

recoverable, … AEC is only responsible for its share of responsibility for

the same.” (Docs. 91, p. 28; 93, p. 27). According to AEC, Zimmer’s delay

expert John Dillon “could not allocate responsibility for delays at [the

projects],” so Zimmer can’t maintain claims for delay damages under the

subcontracts. Perhaps, but the court finds this issue is better suited for

resolution at trial because Dillon could identify certain delays caused

solely by AEC. (See doc. 85-2, p. 10). It may turn out that Zimmer can’t

attribute all (or even most) delays to AEC, but that doesn’t bar the delay

damages at the Rule 56 stage because Zimmer provides enough evidence

to allow a reasonable juror to assess some delay damages. So the court

will deny AEC’s motion for summary judgment on Counts 1 and 3 based

on its delay damages argument.

4. Project Schedule Argument. AEC separately argues that,

even if Zimmer can recover delay damages under the subcontracts, “AEC

was not bound by a schedule for the [projects],” so there is no basis to find

that a delay occurred. (See docs. 91, p. 29; 93, p. 28). This argument is also

best reserved for trial. The subcontracts contemplated that AEC would

“prosecute” its work “in strict accordance with [the general contractor’s]

schedule and sequencing directives and to otherwise prosecute the work

diligently and in cooperation with others contributing to the work … so as

to not hinder in any way [the general contractor’s] compliance with its

project schedule, milestone dates, and completion deadlines.” (See doc. 84-

2, p. 133). But there is conflicting evidence on whether the parties adopted

a binding schedule.

On one hand, Zimmer contends that Huffman provided AEC with

schedules for the Terraces and Boardwalk projects, and there are email

communications between Huffman and AEC personnel that show, at the

very least, Huffman and AEC exchanged “forecast” schedules. (See docs.

88-3, p. 2; 88-10, p. 3). On the other hand, AEC’s corporate representative,

Bennett Steele, states in his affidavit that “AEC never agreed to a

schedule and no schedule was ever made part of the [subcontracts].” (Docs.

86-1, p. 2; 86-2, p. 2). And when Zimmer’s corporate representative was

asked during his deposition whether he had seen any email

communications “where AEC agreed to be bound by any schedule(s) for

the time frame [Huffman] was on the job,” he said he had not. (See doc.

87-4, p. 18; see also doc. 86-3, p. 13). It could be the case that Huffman

should have provided AEC a definitive schedule for the projects and

neglected to do so. It could also be the case that Huffman treated the

circulated schedules as binding under the subcontracts. But that’s a

genuine fact question this court can’t answer. Instead, the court must

assume at the Rule 56 stage that the jury would side with Zimmer (the

nonmoving party). As a result, the court will deny AEC’s motion for

summary judgment on Counts 1 and 3 based on the argument that AEC

never agreed to project schedules.

5. Attorneys’ Fees Argument. AEC also argues that Zimmer

cannot recover attorneys’ fees for its breach of contract claims. A few

different provisions in the subcontracts discuss attorneys’ fees, so the

court outlines them below.

Art. 6.1 of the subcontracts acts as an indemnitee provision and

states, in relevant part:

Subcontractor agrees to defend, indemnify, and hold

harmless Huffman, Owner, General Contractor,

[collectively, “Indemnitees”]… from and against any and

all claims, actions, suits, causes of action, losses, damages,

fines, judgments (including amounts paid in settlement),

and all other costs, expenses, and charges of every kind

and nature whatsoever (including reasonable attorneys’

fees), incurred by or asserted against any of the

Indemnitees, which arise out of or relate to the

performance or nonperformance of the Subcontract Work

or any breach of this Agreement by Subcontractor, or any

other act, omission, or neglect by Subcontractor or any of

Subcontractor’s subcontractors, subsidiaries, or affiliates,

… in connection with or otherwise relating to the

Project[s], without regard to the cause or causes thereof[.]

(Docs. 84-3, p. 18; 88-9, p. 18). Section 7.1.2 also discusses attorneys’ fees

but in the termination for cause context:

[I]f Subcontractor fails to commence and diligently

continue correction to the satisfaction of [general

contractor] within 48 hours of [the second notice of breach]

[general contractor] may issue a notice terminating this

Agreement for cause and shall be entitled to recover from

Subcontractor all associated costs, expenses, and other

damages, including, but not limited to, associated legal

fees and any amounts paid to correct and/or complete the

Subcontract Work (plus 15%) that, together with all other

funds paid to complete any portion of the Subcontract

Work, exceed the Subcontract Amount established under

this Agreement.

(Docs. 84-3, p. 23; 88-9, p. 23). Finally, § 7.4.2 discusses attorneys’ fees in

the bankruptcy context:

If Subcontractor is not performing in accordance with the

Progress Schedule at the time a petition in bankruptcy is

filed, or at any subsequent time, [general contractor], while

awaiting the decision of the Subcontractor or its trustee to

reject or to assume this Agreement and provide adequate

assurance of its ability to perform, may avail itself of such

remedies under this Article as are reasonably necessary to

maintain the Progress Schedule. [General contractor] may

offset against any sums due to or become due to

Subcontractor all costs incurred in pursuing any of the

remedies provided including … attorneys’ fees.

(Docs. 84-3, p. 24; 88-9, p. 24).

Neither Art. 6.1 nor § 7.4.2 offer Zimmer the option to recover

attorneys’ fees in this case. Art. 6.1 doesn’t apply because it is an

indemnitee provision that requires AEC to “defend, indemnify, and hold

harmless” the general contractor and Zimmer when they are sued for

damages caused by AEC’s performance under the subcontracts. And §

7.4.2 doesn’t apply because its sole application arises in the bankruptcy

context.

Section 7.1.2 is different. It broadly permits the general contractor

(here, Zimmer as the assignee) “to recover from [AEC] all associated

costs, expenses, and other damages, including but not limited to,

associated legal fees and any amounts paid to correct and/or complete the

Subcontract Work (plus 15%)” that relate to AEC’s termination and

defective work. (Docs. 84-3, p. 23; 88-9, p. 23) (emphasis added). For

relevant purposes, Zimmer sued AEC to recover costs it expended by

terminating AEC and hiring other contractors to repair and finish AEC’s

work. So Zimmer’s attorneys’ fees can fit within § 7.1.2’s gamut.5

To be sure, Zimmer’s corporate representative struggled to identify

how all of Zimmer’s claimed attorneys’ fees and legal expenses related to

AEC’s breach and termination. (See doc. 86-3, pp. 60-62). But that is not

a reason to grant summary judgment because the court finds that at least

some of Zimmer’s claimed attorneys’ fees may be recoverable. At trial,

Zimmer must be able to show how its claimed attorneys’ fees fit within §

7.1.2.

6. Accord, Satisfaction, and Release Argument. Finally, AEC

contends that Zimmer’s claims for delay damages are barred by accord,

5 ZP 361 did not respond to AEC’s attorneys’ fees argument. Even so, the court must examine

the evidentiary record—including the subcontracts—to determine whether AEC is entitled to

summary judgment. See Ogwo v. Miami Dade Cnty. Sch. Bd., 702 Fed. App’x 809, 810 (11th Cir.

2017) (“The non-movant’s failure to respond to a defendant’s motion for summary judgment is

not fatal; rather, the court must determine if the facts in the record illustrate that the movant

is entitled to summary judgment.”). Because the court finds that the record undercuts AEC’s

argument on attorneys’ fees, ZP 361’s failure to respond does not warrant summary judgment.

satisfaction, and release because Zimmer settled with Huffman rather

than asserting delay damages against Huffman.6 The court presumes that

AEC is relying on Art. 3.4 of the subcontracts, which provides a

mechanism for recovering liquidated damages if AEC caused delays. (See

supra part I.B.3). There are a few problems with this argument. For one,

the court has already determined that AEC can seek delay damages under

§ 7.1.2 of the subcontracts. For another, the settlement agreement

released Huffman—not AEC. AEC can be held independently liable for its

alleged breaches of the subcontracts.

——

In sum, the court will grant in part and deny in part AEC’s motion

for summary judgment on Counts 1 and 3. Counts 1 and 3 will proceed to

trial, but Zimmer may only seek to recover damages as permitted by the

subcontracts. The parties (and the court, if necessary) will work to define

the available damage categories in the pretrial order.

II. Zimmer’s Partial Motion for Summary Judgment on its

Claims

Zimmer moves for partial summary judgment on its breach of

contract claims in Counts 1 and 3. As a refresher, Zimmer must prove the

following breach of contract elements: (1) the existence of a valid contract

binding the parties; (2) Zimmer’s own performance under the contract; (3)

AEC’s nonperformance; and (4) damages. Vaughn, 669 So. 2d at 99.

As the court has found, genuine disputes of material fact preclude

summary judgment for AEC on Counts 1 and 3 (see supra part I.B). Those

genuine disputes of material fact likewise preclude summary judgment in

Zimmer’s favor. The court provides some examples below.

1. Fact Dispute: Binding Schedules. To start, there is a genuine

dispute whether binding schedules governed AEC’s subcontract work. As

discussed, Zimmer has provided emails showing that, at the very least,

6 AEC says that Zimmer’s “claims are barred by accord and satisfaction and release,” (docs. 91,

p. 32; 93, p. 31) (emphasis added), but its argument focuses on Zimmer’s claimed delay damages.

Huffman and AEC exchanged “forecast” schedules. But Zimmer’s

corporate representative admitted during his deposition that he had not

seen any proof that AEC agreed to a final schedule for its work. And AEC’s

corporate representative maintains that “AEC never agreed to a schedule

and no schedule was ever made part of the [subcontracts].” (Docs. 86-1, p.

2; 86-2, p. 2). So the court cannot say based on the current record whether

a definitive schedule governed the subcontracts. And because a reasonable

juror could go either way, the court must allow the delay issue to be tried.

2. Fact Dispute: Zimmer’s Damages. The parties also dispute

the availability and scope of Zimmer’s damages. Zimmer’s experts can’t

rule out whether Huffman or others contributed to or outright caused

certain delays. For example, the parties dispute when the necessary

“forms” to complete the Terraces’ retaining walls arrived. (Compare doc.

82-2, p. 40 with doc. 81-1, p. 49). This matters because Huffman was

supposed to build the retaining walls, and AEC could not complete the

upper-level pads without them. Under AEC’s version of events, the forms

didn’t arrive until April 2023—months after Zimmer claims that AEC

should have finished the upper-level pads. The parties’ expert reports

further lay bare disputes about whether AEC caused certain delays

Zimmer claims damages for.

3. Fact Dispute: AEC’s Defective Work. The parties also dispute

whether AEC engaged in defective work. For example, Zimmer’s damages

expert says in his report that AEC “overexcavat[ed]” rock beyond the

basement walls for Buildings A1, A2, and A3 at the Terraces, which

“required far greater volume of fill to backfill the [basement] walls and

[caused] significant delay to replace the excessive excavation.” (See doc.

80-3, p. 12). But AEC’s expert counters that AEC’s actions were justified

and necessary. (See doc. 82-2, p. 35).

——

The court could go on, but the point is made. Genuine disputes of

material fact prevent the court from deciding whether and to what extent

AEC breached the subcontracts and what damages Zimmer may recover.

Thus, the court will deny Zimmer’s partial motion for summary judgment

on Counts 1 and 38.

III. Zimmer’s Motion to Strike

Zimmer moves to strike AEC’s amended answer and affirmative

defenses because AEC added the affirmative defense of accord,

satisfaction, and release after its deadline to amend had passed. (See doc.

75). Because the court examined and rejected AEC’s accord, satisfaction,

and release argument, the court will deny Zimmer’s motion to strike as

moot.

CONCLUSION

For these reasons, the court (1) GRANTS IN PART and DENIES

IN PART AEC’s motions for summary judgment (docs. 78, 79); (2)

DENIES Zimmer’s partial motion for summary judgment (doc. 88); and

(3) DENIES Zimmer’s motion to strike AS MOOT (doc. 75). The court

will enter an accompanying order carrying out its ruling.

DONE and ORDERED on July 21, 2026.

COREY‘L. MAZE

UNITED STATES DISTRICT JUDGE

31

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.