Opinion

Opinion

Court
District Court, N.D. California
Filed
Apr 8, 2026
Cited by
0 cases
Authority
More cited than 41.4%

The opinion

1

2

3

4 UNITED STATES DISTRICT COURT

5 NORTHERN DISTRICT OF CALIFORNIA

6

7 SOLARPARK KOREA CO., LTD., Case No. 23-cv-01181-AMO

8 Plaintiff,

ORDER RE MOTION TO DISMISS

v.

9

Re: Dkt. No. 127

10 SOLARIA CORPORATION, et al.,

Defendants.

11

12

13 The partial motion to dismiss of Defendants The Solaria Corporation and Complete

14 Solaria, Inc. (referred to collectively as “Solaria”) was heard before this Court on February 12,

15 2026. Having read the papers filed by the parties and carefully considered their arguments therein

16 and those made at the hearing, as well as the relevant legal authority, the Court GRANTS the

17 motion in part and DENIES it in part for the following reasons.

18 I. BACKGROUND

19 A. Factual Background1

20 1. The Parties’ Relationship

21 In 2015, Plaintiff SolarPark Korea Co. (“SolarPark”) and Solaria began exploring a

22 business partnership under which SolarPark would mass produce shingled solar modules designed

23 by Solaria. First Amended Compl. (Dkt. No. 120, “FAC”) ¶ 10. SolarPark and Solaria executed

24 an Agreement to Manufacture on April 8, 2016 (the “2016 Agreement”). FAC ¶ 11. The 2016

25 Agreement contained a minimum purchase clause which required Solaria to purchase (i) “a total of

26

27

1 “On a motion to dismiss, a court accepts as true a plaintiff’s well-pleaded factual allegations and

1 25 MWp for the first six (6) months of production” and (ii) “a minimum of 10 MWp per quarter

2 for the remaining six (6) quarters.” FAC ¶ 12.

3 On October 6, 2018, SolarPark and Solaria entered into a Technology License Agreement

4 (the “TLA”) setting forth detailed licensing terms and conditions of their respective intellectual

5 property (“IP”). FAC, Ex. B (Dkt. No. 120-2).

6 In April 2019, Solaria proposed expanding the partnership and ramping up production by

7 adding three new production lines at SolarPark’s factory dedicated to Solaria’s products. This

8 expansion required SolarPark to invest approximately $60 million to install new production lines

9 and also double its workforce. FAC ¶ 15. Solaria’s proposal meant increasing production by

10 approximately five times the minimum purchase requirement under the 2016 Agreement (i.e., over

11 200 MW per year). FAC ¶ 16. The expansion also meant that SolarPark would devote nearly its

12 entire manufacturing capacity to Solaria’s orders. FAC ¶ 17. On June 19, 2019, Solaria and

13 SolarPark entered into an Agreement for Supply (the “2019 Agreement”). FAC ¶ 18. Under

14 Sections 2.2 and 3.4 of the 2019 Agreement, Solaria agreed to purchase a minimum volume of 224

15 MW per year (i.e., 164,656 modules per quarter) for five years through June 2024. FAC ¶ 19.

16 To ramp up production as requested by Solaria, SolarPark had to (i) remove the existing

17 equipment for standard modules, (ii) purchase and install new equipment for shingled modules,

18 (iii) hire about 200 additional employees, and (iv) refurbish the production facilities to

19 accommodate the new equipment and personnel. FAC ¶ 20. SolarPark anticipated that such an

20 undertaking would require a capital investment of tens of millions of dollars. Id. As SolarPark

21 could not afford such significant investment, the parties agreed to explore an alternative pricing

22 scheme to account for the upfront costs. Id. To that end, Solaria and SolarPark executed the Solar

23 Module Sales Agreement (the “MSA”) on August 4, 2019. FAC ¶ 21; FAC, Ex. A (Dkt. No. 120-

24 1). The MSA expressly superseded the 2016 Agreement, but not the TLA nor the 2019

25 Agreement. FAC, Ex. A § 1. The MSA provided that “[a]bsolute quantity conditions applied for

26 each quarter” and that SolarPark would provide a volume discount if more than 164,656 modules

27 were purchased each quarter (the “Absolute Quantity Conditions”). FAC, Ex. A § 5.2(c).

1 For three years following execution of the MSA, SolarPark filled all of Solaria’s orders.

2 FAC ¶ 26. Solaria, however, failed to meet the Absolute Quantity Conditions of 164,656 module

3 orders per quarter throughout the period from 3Q 2019 to 1Q 2022. Id. As a result, SolarPark

4 continued to suffer significant financial difficulties and was forced to shut down one of the two

5 factories dedicated to producing Solaria’s shingled modules temporarily on December 31, 2021.

6 FAC ¶ 27.

7 On January 19, 2022, Solaria sent a letter to SolarPark purporting to terminate the MSA as

8 of February 18, 2022. FAC ¶ 28. Although the parties thereafter negotiated a deal to resume

9 production and compensate SolarPark for the losses caused by Solaria’s failure to order minimum

10 volumes, Solaria did not follow through. FAC ¶ 29.

11 On June 28, 2022, Solaria sent a letter to SolarPark purporting to terminate the TLA as of

12 August 31, 2022. FAC ¶ 31.

13 On November 7, 2022, Solaria merged with Complete Solar to form Defendant Complete

14 Solaria, of which Solaria became a wholly owned subsidiary. FAC ¶ 33. Complete Solaria began

15 trading on Nasdaq on July 17, 2023. FAC ¶ 43. On September 20, 2023, Complete Solaria

16 announced that it entered into an Asset Purchase Agreement with Maxeon Solar Technologies,

17 Ltd., and sold off its shingled cell solar panel technology and dealer operations. Id. On

18 September 24, 2024, Complete Solaria purchased certain assets from SunPower Corporation.

19 FAC ¶ 44. On April 21, 2025, Complete Solaria announced its rebrand to SunPower and that its

20 Nasdaq ticker would change to “SPWR.” Id.

21 2. The SIAC Arbitration

22 Solaria commenced an arbitration against SolarPark before the Singapore International

23 Arbitration Centre (“SIAC”) in June 2022 (Case No. ARB160/22/WXZ; the “Arbitration”). FAC

24 ¶ 40; Dkt. No. 127 at 9; Dkt. No. 32-2 ¶ 51. On July 30, 2022, SolarPark counterclaimed against

25 Solaria for breach of the MSA and fraudulent inducement to enter into the MSA (collectively, the

26 “Arbitration Claims”). FAC ¶ 40; Dkt. No. 127 at 9-10; Dkt. No. 115-5.

27 Solaria submitted its Statement of Claim in the Arbitration on February 10, 2023. Dkt. No.

1 May 12, 2023. Dkt. No. 32-3. On November 15, 2023, after being compelled to arbitrate in this

2 action, SolarPark, Solaria, and Complete Solaria reached an agreement to (i) arbitrate Counts III

3 through VI in Plaintiff’s original complaint (Tortious Interference with Contractual Relations

4 against Complete Solaria, Inducement to Breach Contract against Complete solaria, Violation of

5 California’s Unfair Competition Law against all Defendants, and Civil Conspiracy against all

6 Defendants), and (ii) join Complete Solaria as a party to the Arbitration. Dkt. No. 127 at 10; Dkt.

7 No. 103-6. On December 15, 2023, SolarPark submitted in the Arbitration its Statement of

8 Rejoinder and Reply to Counterclaims, in which SolarPark added Counts III through VI of the

9 original complaint to its counterclaims pursuant to the Parties’ agreement. Dkt. No. 127 at 10;

10 Dkt. No. 103-7. On February 16, 2024, Solaria submitted in the Arbitration their Rejoinder to

11 Counterclaims and Response to Additional Claims, in which Solaria pleaded their defenses to both

12 the Arbitration Claims and Counts III through VI. Dkt. No. 103-9.

13 Both SolarPark and Solaria failed to pay their respective portions of the SIAC fees. Dkt.

14 No. 103-3 at 4; Dkt. No. 113-3 at 2, 6, 10, 17; Dkt. No. 105-11 at 2; Dkt. No. 105-14. Due to the

15 nonpayment, on June 26, 2024, the SIAC Registrar notified the parties that their claims and

16 counterclaims were considered withdrawn without prejudice to the Parties reintroducing them in

17 another proceeding. Dkt. No. 127 at 5; Dkt. No. 103-18; see also SIAC Rule 34.6(b) (Dkt. No.

18 48-2 at 37) (permitting registrar to deem claims withdrawn without prejudice due to the litigants’

19 nonpayment of deposits). On July 1, 2024, the SIAC Tribunal confirmed the withdrawal of claims

20 and counterclaims. Dkt. No. 127 at 5; Dkt. No. 103-13. On November 18, 2024, the SIAC

21 Registrar notified the parties regarding the final settlement of their accounts. Dkt. No. 103-20.

22 B. Procedural History

23 SolarPark initiated this lawsuit on March 16, 2023. Dkt. No. 1. In May 2023, SolarPark

24 filed a motion for preliminary injunction, Dkt. No. 28, after which Solaria filed a motion to

25 dismiss, Dkt. No. 32. Both motions were heard and decided together. See Dkt. No. 68. The Court

26 granted in part and denied in part SolarPark’s motion for preliminary injunction, granted

27 SolarPark’s request for expedited discovery, denied Solaria’s motion to dismiss, and granted

1 In early 2025, the parties provided a status report that stated they were discussing next

2 steps in this case following SIAC’s dismissal of their arbitration. See Dkt. No. 99. SolarPark filed

3 a motion to lift the stay and to amend the complaint in July 2025. Dkt. No. 104. The Court

4 granted the motion to lift the stay and for leave to amend on August 14, 2025. Dkt. No. 119.

5 SolarPark filed its FAC on August 28, 2025. Dkt. No. 120. Solaria filed the instant

6 motion to dismiss portions of the FAC on October 14, 2025. Dkt. No. 127.

7 II. DISCUSSION

8 Solaria’s partial motion to dismiss under Federal Rule of Civil Procedure 12(b)(6) seeks to

9 dismiss Count II (breach of contract against Solaria), Count III (fraudulent inducement against

10 Solaria), Count IV (tortious interference with contractual relations against Complete Solaria), and

11 Count V (injunctive relief against all Defendants) of the FAC. See Dkt. No. 127 (leaving

12 untouched Count I, misappropriation of trade secrets). Defendants’ bases for the motion are three-

13 fold: (1) that SolarPark’s breach of contract claim and fraudulent inducement claim are time-

14 barred; (2) that SolarPark has not plead sufficient facts for Counts II, III, and IV; and (3) that

15 Count V for injunctive relief does not reflect a real cause of action. After setting forth the legal

16 standard, the Court takes up these arguments in turn.

17 A motion to dismiss under Federal Rule of Civil Procedure 12(b)(6) tests for the legal

18 sufficiency of the claims alleged in the complaint. Ileto v. Glock, 349 F.3d 1191, 1199-1200 (9th

19 Cir. 2003). Under Federal Rule of Civil Procedure 8, which requires that a complaint include a

20 “short and plain statement of the claim showing that the pleader is entitled to relief,” Fed. R. Civ.

21 P. 8(a)(2), a complaint may be dismissed under Rule 12(b)(6) if the plaintiff fails to state a

22 cognizable legal theory, or has not alleged sufficient facts to support a cognizable legal theory.

23 Somers v. Apple, Inc., 729 F.3d 953, 959 (9th Cir. 2013).

24 While the court is to accept as true all the factual allegations in the complaint, legally

25 conclusory statements, not supported by actual factual allegations, need not be accepted. Ashcroft

26 v. Iqbal, 556 U.S. 662, 678-79 (2009). The complaint must proffer sufficient facts to state a claim

27 for relief that is plausible on its face. Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555, 558-59

1 pleads factual content that allows the court to draw the reasonable inference that the defendant is

2 liable for the misconduct alleged.” Iqbal, 556 U.S. at 678 (citation omitted). “[W]here the well-

3 pleaded facts do not permit the court to infer more than the mere possibility of misconduct, the

4 complaint has alleged – but it has not ‘show[n]’ – that the pleader is entitled to relief.” Id. at 679.

5 Review is generally limited to the contents of the complaint, although the court can also

6 consider a document on which the complaint relies if the document is central to the claims asserted

7 in the complaint, and no party questions the authenticity of the document. See Sanders v. Brown,

8 504 F.3d 903, 910 (9th Cir. 2007). The court may consider matters that are properly the subject of

9 judicial notice, Knievel v. ESPN, 393 F.3d 1068, 1076 (9th Cir. 2005); Lee v. City of Los Angeles,

10 250 F.3d 668, 688-89 (9th Cir. 2001), and may also consider documents referenced extensively in

11 the complaint and documents that form the basis of the plaintiffs’ claims. See No. 84 Emp’r-

12 Teamster Jt. Council Pension Tr. Fund v. Am. W. Holding Corp., 320 F.3d 920, 925 n.2 (9th Cir.

13 2003).

14 If dismissal is warranted, it is generally without prejudice, unless it is clear that the

15 complaint cannot be saved by any amendment. Sparling v. Daou, 411 F.3d 1006, 1013 (9th Cir.

16 2005). “Leave to amend may also be denied for repeated failure to cure deficiencies by previous

17 amendment.” Abagninin v. AMVAC Chem. Corp., 545 F.3d 733, 742 (9th Cir. 2008).

18 A. Timeliness

19 SolarPark alleges breaches of the MSA, which was executed in August 2019, and which is

20 governed by New York law. See Dkt. No. 120-1, MSA § 18.3. Solaria argue that SolarPark’s

21 breach of contract claim, Count II, is barred by the four-year limitation period under New York

22 U.C.C. § 2-725, and that the fraudulent inducement claim (Count III) is barred under New York

23 C.P.L.R. § 213(8). Dkt. No. 127 at 16-18.

24 Under New York law, the statute of limitations for breach of contract is four years from

25 when breach occurs, regardless of whether SolarPark had knowledge of the breach at the time it

26 purportedly occurred. N.Y. U.C.C. Law § 2-725 (McKinney). New York Civil Practice Law and

27 Rules (“N.Y.C.P.L.R.”) § 204(b) tolls statutes of limitations while claims are presented for

1 Where it shall have been determined that a party is not obligated to

submit a claim to arbitration, the time which elapsed between the

2 demand for arbitration and the final determination that there is no

obligation to arbitrate is not a part of the time within which an action

3 upon such claim must be commenced. The time within which the

action must be commenced shall not be extended by this provision

4 beyond one year after such final determination.

5 SolarPark’s breach of contract and fraudulent inducement claims were “originally raised in

6 the SIAC Arbitration” in its Response to the Notice of Arbitration submitted in July 2022. Dkt.

7 No. 127 at 6, 11, 24. Solaria does not contend the claims were untimely when submitted in July

8 2022. Rather, it argues that the tolling provisions of N.Y.C.P.L.R. § 204(b) do not apply to the

9 period when the parties were engaged in arbitration because “[t]he purpose of CPLR 204 (b) is to

10 preserve a remedy to a litigant who has mistaken his forum,” not to preserve claims properly

11 submitted to arbitration in the first instance. See Dkt. No. 130 at 12 (quoting Provenzano v. Ioffe,

12 784 N.Y.S.2d 138, 140 (2004)). However, Provenzano does not stand for such a limited

13 interpretation of the tolling available to litigants while they present their claims for arbitration

14 pursuant to a valid arbitration agreement; rather, “[t]he function of CPLR 204(b) is similar to that

15 of CPLR 205. The two provisions serve to extend the time for commencing a second action after

16 a timely action has been terminated in a manner other than by voluntary discontinuance, a

17 dismissal for neglect to prosecute, or a final judgment on the merits.” Provenzano, 12 A.D.3d at

18 355 (citing Bright v. Pagan, 236 A.D.2d 350, 351 (1997)). In this case, SolarPark’s breach of

19 contract and fraudulent inducement claims were originally and timely raised in the SIAC

20 Arbitration through its Response to the Notice of Arbitration submitted in July 2022. See FAC

21 ¶ 40; Dkt. No. 127 at 9-10; Dkt. No. 115-5. According to N.Y.C.P.L.R. § 204(b), the statute of

22 limitations periods applicable to SolarPark’s breach of contract and fraudulent inducement claims

23 were tolled from July 2022, when SolarPark first submitted those claims in the Arbitration, to

24 August 14, 2025, when the Court granted SolarPark’s motion to amend. N.Y.C.P.L.R. § 204(b);

25 see also Perez v. Paramount Commc’ns, Inc., 92 N.Y.2d 749, 755-56 (1999) (holding that filing a

26 motion for leave to amend the complaint was “sufficient to toll the statute of limitations” until the

27 court’s order granting the motion). Therefore, SolarPark’s breach of contract and fraudulent

1 Solaria contends that the Arbitration does not toll the statute of limitations period because,

2 under the holding in Stewart v. Acer, Inc., No. 22-CV-04684-VC, 2023 WL 1463413 (N.D. Cal.

3 Feb. 1, 2023), tolling is only available if arbitrable claims are “first brought in the district court,

4 the district court case is stayed, and then the stay is lifted.” Dkt. No. 127 at 17-18. Solaria

5 misreads Stewart. The Stewart court held instead that statute of limitations periods are often tolled

6 “when parties pursue dispute resolution via arbitration before ever filing a suit in court.” Stewart,

7 2023 WL 1463413, at *1. Indeed, the court’s reasoning remains particularly relevant here, where

8 it stated,

9 [I]t is not clear why a statute of limitations period wouldn’t remain

tolled while a dispute is with an arbitrator. Statute of limitations

10 periods are often tolled, at least in certain contexts, when parties

pursue dispute resolution via arbitration before ever filing a suit in

11 court. . . . So long as they filed a timely lawsuit in the first place,

it’s difficult to imagine a basis for rejecting a tolling argument for

12 the period it takes for an arbitrator to conclude that the case is not

subject to arbitration.

13

14 Stewart, 2023 WL 1463413, at *1 (internal quotation marks and citation omitted). The same

15 rationale applies with equal force to the present circumstances – it is not clear why a statute of

16 limitations would not remain tolled while the parties timely pursued their claims in arbitration in

17 accordance with their prior agreements in the MSA and TLA.2 See FAC, Exs. A & B.

18 Solaria argues further that the applicable statute of limitations was not effectively tolled

19 because the withdrawal of the SIAC Arbitration was voluntary or due to neglect to prosecute. Not

20 so. SolarPark’s claims in the Arbitration were deemed as withdrawn not due to voluntary

21 discontinuance, neglect to prosecute, or a final judgment on the merits, but due to both SolarPark’s

22 and Solaria’s respective failures to pay the SIAC fees. Dkt. No. 103-3 at 4; Dkt. No. 113-3 at 2, 6,

23 10, 17; Dkt. No. 105-11 at 2; Dkt. No. 105-14. Though not resolved on the merits, SIAC resolved

24 the matter pursuant to its rules by closing the Arbitration due to nonpayment. See MSA (FAC, Ex.

25 A) § 18.4; see also SIAC Rule 34.6(b) (Dkt. No. 48-2 at 37) (permitting registrar to deem claims

26

2 Solaria’s arguments that the arbitration did not effectively toll SolarPark’s breach and fraudulent

27

inducement claims are difficult to credit in light of Solaria’s successful effort to stay this action

1 withdrawn without prejudice due to the litigants’ nonpayment of deposits). Therefore, the

2 Arbitration was “had in accordance with the terms of the [arbitration] agreement.” Tillman v.

3 Tillman, 825 F.3d 1069, 1074 (9th Cir. 2016) (holding that an arbitration had been “had” in

4 accordance with the Federal Arbitration Act (“FAA”) despite the arbitration’s termination by

5 AAA due to unpaid deposits); see also Lifescan, Inc. v. Premier Diabetic Servs., Inc., 363 F.3d

6 1010, 1013 (9th Cir. 2004) (“Under the terms of the FAA, there was no ‘failure, neglect, or

7 refusal’ by Premier to arbitrate in this case; the arbitration has proceeded pursuant to the parties’

8 agreement and the rules they incorporated.”). Solaria fails to establish that the statutory tolling of

9 SolarPark’s breach of contract and fraudulent inducement claims, first raised in the Arbitration,

10 should not apply here.

11 Because the Court concludes that the applicable limitations periods were effectively tolled

12 while the parties engaged in arbitration, it need not reach SolarPark’s alternative arguments

13 regarding timeliness, including that the claims were in fact timely under New York law because

14 the contract involved services rather than sale of goods (services contracts have a longer

15 limitations period) and that the doctrine of “relation back” to the original complaint preserved

16 these claims under Federal Rule of Civil Procedure 15(c).

17 B. Sufficiency of Allegations

18 Solaria argues that the FAC fails to state a claim upon which relief can be granted for

19 Count II (breach of contract against Solaria), Count III (fraudulent inducement against Solaria),

20 and Count IV (tortious interference with contractual relations against Complete Solaria). It further

21 argues that injunctive relief should be dismissed as a separate cause of action because it is instead

22 a form of potential relief. The Court examines each claim in turn.

23 1. Breach of Contract

24 The elements of breach of contract under New York law are “(1) the existence of a contract

25 between itself and that defendant; (2) performance of the plaintiff’s obligations under the contract;

26 (3) breach of the contract by that defendant; and (4) damages to the plaintiff caused by that

27 //

1 defendant’s breach.” Diesel Props S.r.l. v. Greystone Business Credit II LLC, 631 F.3d 42, 52 (2d

2 Cir. 2011).3

3 On the first element, Solaria does not contest the validity of the MSA as a contract. Dkt.

4 No. 32 (first motion to dismiss) at 1.

5 Solaria argues that SolarPark fails to satisfy the second prong on the basis that SolarPark

6 fails to fully allege performance of its obligations under the contract. Dkt. No. 127 at 13. But

7 SolarPark’s allegation that “Plaintiff performed its obligations under the MSA by fulfilling all of

8 Solaria’s orders without fail” is sufficient to plead plaintiff’s performance under the contract. See

9 FAC ¶ 55; JTRE Manhattan Ave. LLC v. Cap. One, N.A., 585 F. Supp. 3d 474, 482 (S.D.N.Y.

10 2022) (holding the allegation “in all material respects [the plaintiff] complied with its obligations

11 under the Lease” was sufficient to allege plaintiff’s performance). To the extent Defendants

12 counter that SolarPark failed to fulfill its contractual obligations, its closure of one of the two

13 factories dedicated to manufacturing Solaria’s shingled modules does not mean that SolarPark had

14 “failed its obligations . . . to supply shingled solar modules to Solaria.” Dkt. No. 127 at 16; cf.

15 FAC ¶ 27. SolarPark sufficiently alleges performance of its allegations under the contract.

16 Defendants argue further that SolarPark fails on the fourth prong because SolarPark fails to

17 plausibly allege damages in the amount of $82 million. Dkt. No. 127 at 13-14 (challenging

18 sufficiency of allegation, “[d]ue to Solaria’s breaches, Plaintiff was harmed as it was denied the

19 profit that it would have earned had the MSA been performed fully. Plaintiff is entitled to

20 compensatory damages in an exact amount to be proven at trial but not less than $82 million,”

21 FAC ¶ 59). However, SolarPark’s damages allegation is sufficient for the purposes of stating a

22 claim for breach of contract, as SolarPark’s burden at this stage is to plead facts that demonstrate it

23

3 As noted above, SolarPark’s claim for breach of contract is governed by New York law, the

24

governing law of the MSA. FAC ¶ 54; see also MSA § 18.3 (Dkt. No. 120-1 at 19) (stating in all-

caps that the agreement shall be “governed by and construed in accordance with the laws of the

25

State of New York, U.S.A.”). Defendants base their motion exclusively on Ninth Circuit cases

applying California law, however, and they fail to demonstrate why the FAC’s pleading is

26

insufficient under New York law. See Dkt. No. 127 at 12-16 (citing Langan v. United Servs. Auto.

Ass’n, 69 F. Supp. 3d 965 (N.D. Cal. 2014)); Levitt v. Yelp! Inc., 765 F.3d 1123 (9th Cir. 2014);

27

Brown v. U.S. Bancorp, No. CV116125CASPJWX, 2011 WL 13221011 (C.D. Cal. Dec. 19,

1 suffered damages, not necessarily the amount it seeks. See Meng v. New Sch., 686 F. Supp. 3d

2 312, 321 (S.D.N.Y. 2023) (“To state a claim for breach of contract, the damages a plaintiff

3 alleges . . . must be reasonably certain, and such only as actually follow or may follow from the

4 breach of the contract. However, certainty, as it pertains to general damages, refers to the fact of

5 damage, not the amount. When it is certain that damages have been caused by a breach of

6 contract, and the only uncertainty is as to their amount, there can rarely be good reason for

7 refusing, on account of such uncertainty, any damages whatever for the breach.”) (internal

8 quotation marks and citation omitted). Even if SolarPark were required to offer support of the

9 amount of damages it seeks, it has done so by highlighting a quantum expert report that was

10 submitted in the Arbitration – a report which Defendants received in December 2023 and

11 extensively addressed in their responsive submission in February 2024. Dkt. No. 103-7, ¶¶ 128-

12 131 at 45-48; Dkt. No. 103-9, ¶¶ 262-302 at 60-69. Solaria, having reviewed the expert report

13 underlying SolarPark’s asserted damages, may disagree with the sum calculated, but such

14 disagreement does not invalidate SolarPark’s claim that it has been damaged as a result of the

15 alleged breach of contract.

16 Solaria proceeds to challenge SolarPark’s contentions of breach as to each of the MSA

17 provisions identified in the FAC. SolarPark sufficiently identifies not only the specific provisions

18 breached (§§ 5.2.c, 5.3, 18.10, and 14.10), but also how Solaria allegedly breached those

19 provisions. FAC ¶¶ 56-58 at 12-13. Defendants’ challenges to these allegations are defenses to

20 the claim of breach, essentially Defendants’ own competing interpretations of the MSA provisions

21 rather than a demonstration that no breach occurred. Dkt. No. 127 at 13-16. For example,

22 Defendants aver that their obligation to perform was excused by SolarPark’s failure to perform

23 when it closed one of its production facilities, but this dispute requires resolution of factual

24 disputes and competing interpretations of the agreement. Compare Dkt. No. 127 at 16 with Dkt.

25 No. 128 at 21. Defendants’ alternative interpretations of the MSA do not require resolution at the

26 Rule 12(b)(6) stage. Lamoureux v. Trustco Bank, 592 F. Supp. 3d 14, 27 (N.D.N.Y. 2022)

27 (“Courts may dismiss breach-of-contract claims on a Rule 12(b)(6) motion to dismiss where the

1 ‘has an arguable claim under the contract.’ ” (citations omitted)). Therefore, SolarPark has

2 sufficiently alleged its claim for breach of contract, and the motion must be denied as to this cause

3 of action.

4 2. Fraudulent Inducement

5 To state a claim for fraudulent inducement, a plaintiff must adequately allege “(1) that the

6 defendant made a representation, (2) as to a material fact, (3) which was false, (4) and known to be

7 false by the defendant, (5) that the representation was made for the purpose of inducing the other

8 party to rely upon it, (6) that the other party rightfully did so rely, (7) in ignorance of its falsity

9 (8) to his injury.” Duckett v. Williams, 86 F. Supp. 3d 268, 274 (S.D.N.Y. 2015). Moreover, a

10 fraudulent inducement claim is subject to the heightened pleading standards of Rule 9(b) of the

11 Federal Rules of Civil Procedure, which require “a party to state with particularity the

12 circumstances constituting fraud or mistake.” Id. (“the complaint must: (1) specify the statements

13 that the plaintiff contends were fraudulent, (2) identify the speaker, (3) state where and when the

14 statements were made, and (4) explain why the statements were fraudulent” (citations omitted));

15 Fed. R. Civ. P. 9(b).

16 SolarPark alleges Solaria fraudulently induced SolarPark to enter the MSA by making

17 representations that it intended to “ramp up” production and would agree to minimum purchase

18 commitments. FAC ¶ 62. In so alleging, SolarPark fails to identify the specific speaker of the

19 alleged statements or where and when they were made, as required under Rule 9(b). SolarPark

20 further fails to identify what specific statements were made beyond general assertions that Solaria

21 represented that it intended to “ramp up” production and would agree to minimum purchase

22 commitments. See FAC ¶ 62. Such general allegations fail as insufficient to establish fraudulent

23 inducement.

24 In its opposition, SolarPark points to its allegations regarding the parties’ conduct leading

25 up to execution of the MSA, including Defendants’ commitment to make a minimum purchase

26 volume. See Dkt. No. 128 at 22 (citing FAC ¶¶ 15-21, 62). This portion of the FAC does not

27 present any additional factual support for the fraudulent inducement allegations; rather, they

1 Defendants failed to live up to that commitment. Such a factual circumstance reflects a potential

2 breach of contract, not fraudulent inducement, particularly where there is no sign of falsehood or

3 misrepresentation. Therefore, the motion must be granted as to this claim, but with leave to

4 amend.

5 3. Tortious Interference

6 SolarPark alleges that Complete Solaria tortiously interfered via two sets of actions: first,

7 “making a clean slate for Solaria was a precondition for a contemplated merger” and second, by

8 allegedly disclosing “SPK Manufacturing IP.” FAC ¶¶ 31, 37. Specifically, SolarPark alleges

9 that Complete Solaria tortiously interfered by “inducing Solaria to terminate the existing

10 contracts,” “preventing Solaria from executing the [letter of intent] to continue to perform under

11 the MSA and the TLA,” and “disclosing or instructing the disclosure of Plaintiff’s Manufacturing

12 IP and other confidential information to third parties.” FAC ¶ 69. Defendants argue that

13 SolarPark fails to plead its tortious interference claim against Complete Solaria because Complete

14 Solaria (i) “was not formed until November 2022” and (ii) “was not a disinterested third party.”

15 Dkt. No. 127 at 21-27.

16 “Under California law, the elements for the tort of intentional interference with contractual

17 relations are (1) a valid contract between plaintiff and a third party; (2) defendant’s knowledge of

18 this contract; (3) defendant’s intentional acts designed to induce a breach or disruption of the

19 contractual relationship; (4) actual breach or disruption of the contractual relationship; and

20 (5) resulting damage.” United Nat. Maint., Inc. v. San Diego Convention Ctr., Inc., 766 F.3d

21 1002, 1006 (9th Cir. 2014).

22 SolarPark’s claim cannot survive because Complete Solaria was not formed until

23 November 7, 2022. FAC ¶ 33. This was (i) after the working relationship between Solaria Corp.

24 and SolarPark ended, (ii) after Solaria Corp. had initiated arbitration against SolarPark, and

25 (iii) after SolarPark responded to the Notice of Arbitration. FAC ¶ 33. SolarPark offers no factual

26 grounds or explanation how Complete Solaria could have tortiously interfered with a contractual

27 relationship before Complete Solaria existed. Instead, SolarPark alleges that Complete Solaria

1 letter of intent for the parties to reengage in their manufacturing partnership. FAC ¶ 69.

2 SolarPark fails to identify any cases in which an entity faced liability for tortious interference with

3 contract prior to the entity’s existence, and therefore, the claim for tortious interference generally

4 fails.

5 Though SolarPark presents an alternative theory in its opposition brief, that Complete

6 Solaria could be held liable for the tortious interference of Solaria as corporate successor, that

7 theory also fails because the necessary element of a third party would still be missing from the

8 allegations. See Dkt. No. 128 at 24. “[T]he tort duty not to interfere with the contract falls only

9 on strangers – interlopers who have no legitimate interest in the scope or course of the contract’s

10 performance.” Applied Equip. Corp. v. Litton Saudi Arabia Ltd., 7 Cal. 4th 503, 514 (1994).

11 Raising successor liability cuts directly against the viability of a tortious interference claim: the

12 very actors whose conduct SolarPark seeks to impute to Complete Solaria – Solaria’s corporate

13 insiders and affiliates – are, by definition, not “strangers” to the contracts. Once formed,

14 Complete Solaria was so closely aligned with Solaria Corp. that it could not be considered a

15 disinterested third party under California law. See LP Ins. Servs., LLC v. Heffernan Ins. Brokers,

16 2025 WL 2097466, at *3 (N.D. Cal. July 25, 2025) (“a party cannot commit the tort of interfering

17 with their own contract” (citing Applied Equip., 7 Cal. 4th at 514)). The FAC fixes all operative

18 conduct before November 2022, when Complete Solaria did not exist, and the actors it identifies

19 were non‑strangers with a direct contractual interest, and fail as a matter of law. Therefore, the

20 claim for tortious interference must be dismissed with prejudice.

21 4. Injunctive Relief

22 SolarPark pleads a separate cause of action, its fifth, for “Injunctive Relief.” FAC ¶¶ 72-

23 77. Solaria argues that this separate claim for injunctive relief should be dismissed with prejudice

24 because “injunction is a remedy, not a separate claim or cause of action.” Dkt. No. 127 at 27-28.

25 In opposition, SolarPark points to Minkley v. Eureka City Schools, in which the court held, “[a]s a

26 potential remedy, not a stand-alone claim, [injunctive relief] is not subject to dismissal under Rule

27 12(b)(6) for ‘failure to state a claim upon which relief can be granted.’ ” Dkt. No. 128 at 25

1 In response, Solaria points to Saloojas, Inc. v. Aetna Health of California, Inc., in which

2 || the court held, “[aJn injunction is a form of relief, not a substantive claim creating liability.

3 [Citation]. It may properly appear in a complaint’s prayer for relief, not as a claim or cause of

4 || action. Accordingly, Defendant’s motion to dismiss this claim is granted, without leave to

5 || amend.” See Saloojas, No. 22-CV-02887-JSC, 2022 WL 4775877, at *5 (N.D. Cal. Sept. 30,

6 || 2022); see also Dkt. No. 130 at 20 (citing the same).

7 The Court agrees with Solaria. SolarPark is not entitled to proceed with a separate cause

8 of action for injunctive relief even if SolarPark continues to seek injunctive relief as a remedy.

9 || The motion must be granted as to the fifth cause of action for injunctive relief with prejudice; and

10 || to the extent injunctive relief appears in the FAC’s prayer for relief, it will not be dismissed or

11 stricken.

%L I. CONCLUSION

13 For the foregoing reasons, the Court GRANTS in part and DENIES in part Defendants’

14 motion to dismiss. The motion is DENIED as to SolarPark’s claim for breach of contract; the

3 15 motion is GRANTED as to SolarPark’s claims for fraudulent inducement, tortious interference,

a 16 || and separate claim for injunctive relief. SolarPark may file a second amended complaint within 28

17 || days from the date of this Order — SolarPark may amend the claim for fraudulent inducement but

Zz 18 || not the claims for tortious interference or injunctive relief. No new claims or parties may be added

19 || to the amended pleading without leave of Court or stipulation of Defendants.

20

21 IT IS SO ORDERED.

22 || Dated: April 8, 2026

23 □ □ 7

24 :

ARACELI MARTINEZ-OLGUIN

25 United States District Judge

26

27

28

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.