Opinion

Pearson Construction Company Inc v. the Dailey Company

Court
Michigan Court of Appeals
Filed
Apr 17, 2026
Status
Unpublished
Cited by
0 cases
Authority
More cited than 40.2%

“Any argument that [the] defendant was not clearly aware that the scope of its contractual undertakings encompassed [the] plaintiff is absurd, given the nature of the contract; it was the ‘Marie Vanerian Residence’ job.”

How later courts described this case

  • “Any argument that [the] defendant was not clearly aware that the scope of its contractual undertakings encompassed [the] plaintiff is absurd, given the nature of the contract; it was the ‘Marie Vanerian Residence’ job.”
  • “We continue to believe that the only safe rule is to ascertain with some specificity the range of the witness’ qualifications and to permit testimony within that range.”

Written by the judges who cited it.

The opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to

revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

PEARSON CONSTRUCTION COMPANY, INC., UNPUBLISHED

April 17, 2026

Plaintiff/Counterdefendant-Appellant, 12:13 PM

v No. 369918

Oakland Circuit Court

THE DAILEY COMPANY, LC No. 2022-194484-CB

Defendant-Appellee,

and

HIGH TOP BUDS, LLC,

Defendant/Counterplaintiff-Appellee.

Before: GADOLA, C.J., and MURRAY and M.J. KELLY, JJ.

PER CURIAM.

In this action for breach of a construction contract, plaintiff/counterdefendant Pearson

Construction Company, Inc. appeals as of right from the trial court’s judgment in favor of

defendant/counterplaintiff High Top Buds, LLC, entered following a jury trial. We affirm.

I. FACTUAL AND PROCEDURAL BACKGROUND

HTB contracted with general contractor The Dailey Company1 for the construction of a

commercial cannabis grow facility. In turn, Dailey and Pearson entered into a subcontract for

Pearson to do carpentry work on the project. The subcontract included the installation of fiberglass

reinforced plastic (FRP) walls.

After completing its work on the project, Pearson filed this action against Dailey for breach

of contract and against HTB for unjust enrichment, alleging that it informed Dailey of humidity

1

Dailey is not a party to this appeal.

-1-

issues affecting installation of the FRP, but Dailey directed Pearson to continue the work, and

Pearson completed its portion of the project, but HTB refused to pay Dailey for Pearson’s work.

HTB subsequently filed a countercomplaint against Pearson for breach of duty, both under

the common law and as a third-party beneficiary to the subcontract, alleging that “Pearson

breached its duty to HTB by abiding by Dailey’s instruction to install the FRP paneling despite

unacceptably high humidity levels and against Pearson’s own recommendation that the installation

work not proceed,” resulting in bubbling of the panels. Pearson then moved for summary

disposition of HTB’s breach of duty claim under MCR 2.116(C)(8) and (C)(10), arguing in part

that HTB was barred from bringing a claim as a third-party beneficiary to the subcontract because

the subcontract did not include any express promises or direct benefits to HTB. In its brief in

opposition to Pearson’s motion, HTB argued the court should deny the motion, and instead grant

HTB summary disposition under MCR 2.116(I)(2), because HTB is a third-party beneficiary of

the contract pursuant to MCL 600.1405, and Pearson had a common law duty to HTB to exercise

reasonable care. The court ultimately denied Pearson summary disposition and instead granted

HTB partial summary disposition under MCR 2.116(I)(2), finding HTB to be a third-party

beneficiary of the subcontract between Pearson and Dailey as a matter of law under MCL

600.1405.

Following that ruling, HTB moved for partial summary disposition of Pearson’s claims

against it under MCR 2.116(C)(10), asserting that Pearson breached the subcontract by failing to

install perimeter walls, as required by the subcontract. The trial court agreed, finding the

subcontract language to be clear and unambiguous, and granted the motion.

Ultimately, a jury trial was held, and the jury found Pearson liable in the amount of

$250,000 for its failure to construct the perimeter walls, and in the amount of $751,958.25 for

breach of contract as to the interior walls. This appeal followed.

II. SUMMARY DISPOSITION

A. THIRD-PARTY BENEFICIARY

Pearson first argues that the trial court erred in granting HTB partial summary disposition

pursuant to MCR 2.116(I)(2) and holding that HTB is a third-party beneficiary to the subcontract

between Pearson and Dailey.

We review de novo a trial court’s decision on a motion for summary disposition. Yopek v

Brighton Airport Ass’n, Inc, 343 Mich App 415, 422; 997 NW2d 481 (2022). A motion under

MCR 2.116(C)(10) tests the factual sufficiency of a claim. El-Khalil v Oakwood Healthcare, Inc,

504 Mich 152, 160; 934 NW2d 665 (2019).

When considering such a motion, a trial court must consider all evidence submitted

by the parties in the light most favorable to the party opposing the motion. A

motion under MCR 2.116(C)(10) may only be granted when there is no genuine

issue of material fact. A genuine issue of material fact exists when the record leaves

open an issue upon which reasonable minds might differ. [Id. (quotation marks and

citations omitted).]

-2-

“On the other hand, summary disposition is proper under MCR 2.116(I)(2) if the court determines

that the opposing party, rather than the moving party, is entitled to judgment as a matter of law.”

Rataj v Romulus, 306 Mich App 735, 747; 858 NW2d 116 (2014) (quotation marks and citation

omitted). “We also review de novo the existence and interpretation of a contract as a question of

law.” Bailey v Schaaf, 293 Mich App 611, 623; 810 NW2d 641 (2011).

Pearson argues, as it did below, that it was entitled to summary disposition because HTB

was barred from bringing a counterclaim against it for breach of duty as a third-party beneficiary

to the subcontract. Under MCL 600.1405:

Any person for whose benefit a promise is made by way of contract, as hereinafter

defined, has the same right to enforce said promise that he would have had if the

said promise had been made directly to him as the promisee.

(1) A promise shall be construed to have been made for the benefit of a person

whenever the promisor of said promise had undertaken to give or to do or refrain

from doing something directly to or for said person.

With use of the modifier “directly,” the Legislature

“intended ‘to assure that contracting parties are clearly aware that the scope of their

contractual undertakings encompasses a third party, directly referred to in the

contract, before the third party is able to enforce the contract.’ ” Schmalfeldt v

North Pointe Ins Co, 469 Mich 422, 428; 670 NW2d 651 (2003), quoting Koenig v

South Haven, 460 Mich 667, 677; 597 NW2d 99 (1999). When determining

whether MCL 600.1405 applies to a purported third-party beneficiary, “a court

should look no further than the form and meaning of the contract itself” and should

view the contract objectively. Schmalfeldt, 469 Mich at 428 (quotation marks

omitted). [Boylan v Fifty Eight LLC, 289 Mich App 709, 728-729; 808 NW2d 277

(2010).]

“Only intended, rather than incidental, third-party beneficiaries may sue when a contractual

promise in their favor has been breached.” Kisiel v Holz, 272 Mich App 168, 170; 725 NW2d 67

(2006). In other words:

A third person cannot maintain an action on a simple contract merely because he or

she would receive a benefit from its performance or would be injured by its breach.

Third-party beneficiary status requires an express promise to act to the benefit of

the third party; where no such promise exists, that third party cannot maintain an

action for breach of the contract. Further, a determination that a contract establishes

an intended third-party beneficiary through a direct promise to the third party must

be based on an objective review of the form and meaning of the contract itself. [Id.

at 170-171 (quotation marks and citations omitted).]

Generally, although work performed by a subcontractor ultimately benefits the property

owner, the property owner is not an intended third-party beneficiary of the contract between the

subcontractor and contractor. Id. at 171. “Absent clear contractual language to the contrary, a

property owner does not attain intended third-party-beneficiary status merely because the parties

-3-

to the subcontract knew, or even intended, that the construction would ultimately benefit the

property owner.” Id.

Here, as the trial court concluded, although HTB is not a party to the subcontract, Pearson

made direct promises to HTB as “owner” of the property through clear contractual language. First,

the subcontract named the project “High Top Buds – Labar Dr.” See Vanerian v Charles L. Pugh

Co, Inc, 279 Mich App 431, 436; 761 NW2d 108 (2008) (“Any argument that [the] defendant was

not clearly aware that the scope of its contractual undertakings encompassed [the] plaintiff is

absurd, given the nature of the contract; it was the ‘Marie Vanerian Residence’ job.”). And in

several different provisions, Pearson, as the “subcontractor” adopts duties owed directly to the

project’s “owner,” listed as HTB. Section 3.5 states, in part, that the “Subcontractor shall

indemnify and hold Owner and Contractor harmless from and against any and all claims for

nonpayment by sub- subcontractors, suppliers, materialmen, or laborers arising in connection with

the Subcontract Work . . . .” In § 4.2, Pearson agreed to cooperate with the “owner” to participate

in the preparation of coordinated drawings and work schedules. In § 12.1, Pearson agreed to

indemnify the contractor and “owner” from all liability and damages from injury or death sustained

by any person, including the subcontractor’s employees. And, most significantly, § 17.1 states,

“Subcontractor warrants to Contractor and Owner that all material and equipment furnished shall

be new unless otherwise specified, and that all of the Subcontract Work shall be of good quality,

free from faults and defects and in conformance with the Contract Documents,” while § 17.2 states,

in part: “Subcontractor agrees to promptly make good, without cost to Contractor or Owner, any

and all defects in the Subcontract Work due to faulty workmanship and/or materials which may

appear within the guarantee or warranty period established in the Contract Documents . . . .”

Pearson asserts that the introductory clause to Section 12, which states that the

“Subcontractor specifically obligates itself to the Contractor in the following respects,” makes

clear that HTB is simply an incidental beneficiary of Pearson’s obligations in that section. But

even so, that fact would not negate the several other direct promises Pearson makes to HTB

throughout the subcontract.

Finally, Pearson argued in its briefing below that the primary contract for the project

between Dailey and HTB provides that the contract document shall not be construed to create a

contractual relationship between HTB and any subcontractor, and asserts in its reply brief on

appeal that the subcontract expressly incorporates the primary contract. Thus, Pearson contends,

the subcontract is at the very least ambiguous. Indeed, the subcontract states:

The Contract Documents consist of this Subcontract, Drawings per

EXHIBIT “D”, Specifications, all Addenda issued prior to the execution of this

Subcontract, the prime contract between Owner and Contractor, the Project

Schedule as may be amended from time to time, any subsequent modifications or

revisions to any of the foregoing, and any other documents listed in or referred to

by the Prime Contract.

All of the other Contract Documents described above are made a part of this

Subcontract and are fully incorporated herein. Subcontractor acknowledges that it

has carefully examined the Contract Documents and understands them completely.

-4-

And the primary contract between Dailey and HTB, in turn, states, “The Contract Documents shall

not be construed to create a contractual relationship of any kind . . . between the Owner and a

Subcontractor or a Sub-subcontractor.”

“A contract is ambiguous when its provisions irreconcilably conflict. A court may not

ignore provisions of a contract in order to avoid finding an ambiguity.” In re Estate of Koch, 322

Mich App 383, 398; 912 NW2d 205 (2017) (citations omitted). In general, when a contract is

ambiguous, the meaning of the contract is a question of fact for the jury. Id.

As Pearson argues, the primary contract containing the above language appears to conflict

with the subcontract provisions wherein Pearson makes direct promises to HTB, as the owner of

the project. However, even assuming that to be true, Pearson ignores the provision in the

subcontract right below those incorporating the primary contract and other documents, which

states: “Subcontractor is bound to Contractor by the Contract Documents and hereby assumes

toward Contractor, with respect to Subcontractor’s performance, the obligations and

responsibilities, rights and remedies that Contractor assumes toward Owner under the Contract

Documents. In case of conflicts, the Subcontract shall control.” Accordingly, Pearson’s argument

fails, and we hold that the trial court did not err when it granted summary disposition to HTB on

the basis that HTB is a third-party beneficiary to the subcontract.

B. LIABILITY FOR PERIMETER PARTITION WALLS

Pearson also argues that the trial court erred when it granted partial summary disposition

to HTB, holding Pearson liable for its failure to construct perimeter partition walls as required by

the subcontract.

As a third-party beneficiary to the subcontract, HTB has the same right to enforce the

subcontract as the parties to the contract. Shay v Aldrich, 487 Mich 648, 665-666; 790 NW2d 629

(2010). When interpreting a contract:

“[I]t is a court’s obligation to determine the intent of the parties by examining the

language of the contract according to its plain and ordinary meaning.” In re Smith

Trust, 480 Mich 19, 24; 745 NW2d 754 (2008). Contracts must be read as a whole,

and words must be considered in context. Henderson v State Farm Fire & Cas Co,

460 Mich 348, 356; 596 NW2d 190 (1999). Courts must “give effect to every word,

clause, and phrase, and a construction should be avoided that would render any part

of the contract surplusage or nugatory.” Royal Prop Group, LLC v Prime Ins

Syndicate, Inc, 267 Mich App 708, 715; 706 NW2d 426 (2005). “Inartfully worded

or clumsily arranged contract terms do not render a contract ambiguous if it fairly

admits of one interpretation.” Village of Edmore v Crystal Automation Sys, Inc,

322 Mich App 244, 262; 911 NW2d 241 (2017). Unambiguous contracts must be

enforced as written. In re Smith Trust, 480 Mich at 24. [Magley v M & W Inc, 325

Mich App 307, 317-318; 926 NW2d 1 (2018).]

The terms of the subcontract, which includes the attached Pre-Award Scope Form,

unambiguously required Pearson to construct perimeter partitions, in accordance with the trial

court’s ruling to that effect. The April 13, 2021 base bid of $694,000 for the project, which was

-5-

incorporated into the Subcontract Pre-Award Form, explicitly included construction of the

perimeter partitions. As provided on that form under “SCOPE OF WORK,” the carpentry work

included installation of “Duramax PVC wall panels (Partition types 17, 18, 19),” and type 18G

refers to the perimeter exterior walls.2 The Pre-Award Form also lists several alternate options

that could be selected to either add or remove work, with associated cost increases and decreases.

“Alt 23” would “DEDUCT Perimeter partitions” at a cost savings of $42,000, and was specifically

“not accepted,” while “Alt 5A,” which would “ADD FRP on DensGlass ilo Duramax panels at

interior partitions only” was accepted, with a corresponding cost increase of $52,000. This

selection increased the total contract amount to $746,000 (the base bid of $694,000 plus Alt 5A at

$52,000).

Pearson argues, as it did below, that by accepting Alternate 5A, Dailey knew that Alternate

2 was void, because the cost for Alternate 5A already included the savings from not constructing

the exterior partition walls, and directs the court’s attention to an April 30, 2021 updated bid. In

that proposed bid, “ALT 5A” would “ADD $52,000.00 FRP on DensGlass in lieu of base bid Truss

Core Panels, deduct perimeter exterior wall at locations described in ALT 2.” It further states,

“(Please note (1) you can select either ALT 4 or ALT 5, but not both, (2) if you select ALT 4A or

ALT 5A, ALT 2 is void)[.]” But the April 30 bid is not included as part of the subcontract. Rather,

the Pre-Award Scope form expressly incorporated into the subcontract and detailed above was

taken from “Bid Package 2 dated 1-11-21,” with the “Base Bid (4-13-21 quote).”

Pearson asserts that the court should have read this language into the subcontract and

denied HTB summary disposition. But “ ‘[p]arol evidence of contract negotiations, or of prior or

contemporaneous agreements that contradict or vary the written contract, is not admissible to vary

the terms of a contract which is clear and unambiguous,’ ” like the subcontract here. Barclae v

Zarb, 300 Mich App 455, 480; 834 NW2d 100 (2013) (citations omitted). And “[w]e cannot read

words into the plain language of a contract.” Northline Excavating, Inc v Livingston Co, 302 Mich

App 621, 628; 839 NW2d 693 (2013). Further, the subcontract contains a merger clause stating

that the “requirements of [the] agreement and referenced specifications listed in this exhibit shall

take precedence over all proposals submitted to date.” If a contract “contains an integration clause,

parol evidence is only admissible (1) to prove that the clause was fraudulent, (2) to invalidate the

entire contract, or (3) if the contract is obviously incomplete on its face.” Zwiker v Lake Superior

State Univ, 340 Mich App 448, 476; 986 NW2d 427 (2022) (citations omitted). None of the

exceptions are applicable here.

Pearson’s argument that Dailey never intended Pearson to build the perimeter partitions

also lacks merit. As provided above, evidence of the parties’ intent beyond the terms of the

2

Alternate 2, which will be discussed more fully below, provides the option to deduct from the

scope of work the perimeter exterior walls, including type 18G, and Pearson states in its brief on

appeal that “[t]he parties do not dispute that Partition Type 18 is the exterior perimeter partition

walls in the grow rooms.”

3

The Alternates are also listed on Page 4, ¶ 12 of the Subcontract Pre-Award Form, with “ALT 2”

described in more detail as the option to “DEDUCT walls at the perimeter exterior walls in these

locations: (Type 2G – Room 107 & 117/Type 18G – Rooms 101 thru 106; 112 thru 116).”

-6-

unambiguous contract may not be applied to alter the terms of the contract. Barclae, 300 Mich

App at 480. Finally, Pearson asserts, correctly, that HTB did not allege a breach of the subcontract

for failure to install perimeter partitions in its countercomplaint, but fails to elaborate or

specifically argue that the trial court erred in granting summary disposition on this basis.

Accordingly, any argument to that effect is abandoned. See Lashbrook v Grasak, ___ Mich App

___, ___; ___ NW3d ___ (2025) (Docket No. 369669); slip op at 5.

III. MANIFEST INJUSTICE

Pearson next argues that the trial court’s decision to allow its erroneous summary

disposition ruling holding Pearson liable for failure to install the perimeter walls to be presented

to the jury amounted to manifest injustice.

In his opening statement and closing argument, HTB’s counsel framed the issues as: (1) a

determination of damages for Pearson’s failure to install perimeter panels, for which the court

already found Pearson liable, and (2) whether Pearson breached its guarantee of good

workmanship on the interior FRP walls, and to what extent. The trial court instructed the jury to

that effect, and the verdict form asked the jury to award damages for the perimeter walls without

making its own finding of liability.

As HTB contends, Pearson’s argument here appears to be just another way to challenge

the trial court’s ruling on HTB’s partial motion for summary disposition that Pearson was liable

under the subcontract for failure to install perimeter partitions. Pearson essentially argues that the

trial court should not have instructed the jury, nor should the verdict form have included, that

Pearson was liable to HTB under the subcontract for failure to install the perimeter partitions,

because the trial court erred in granting summary disposition on that ground. However, as

concluded above, the trial court did not err in granting summary disposition on that ground.

Accordingly, HTB counsel’s statements regarding the court’s ruling as to Pearson’s liability, the

court’s instructions to that effect, and the verdict form including that ruling did not amount to

manifest injustice.

IV. EXPERT QUALIFICATION

Pearson next argues that the trial court abused its discretion by qualifying HTB’s liability

expert, Terry Buschert, as an expert witness.

We review

for an abuse of discretion a trial court’s determination of the qualifications of a

proposed expert witness. This Court likewise reviews for an abuse of discretion a

trial court’s decision whether to admit evidence, although admission of legally

inadmissible evidence is necessarily an abuse of discretion. The interpretation of

an evidentiary rule is reviewed de novo in the same manner as the examination of

the meaning of a court rule or a statute. Rules of evidence are construed in the same

way as statutes. [Chapin v A&L Parts, Inc, 274 Mich App 122, 126; 732 NW2d

578 (2007) (quotation marks and citations omitted).]

-7-

“An abuse of discretion occurs when a circuit court chooses a result that falls outside the range of

reasonable and principled outcomes.” Lenawee Co v Wagley, 301 Mich App 134, 162; 836 NW2d

193 (2013).

Under MRE 702:

The admission of expert testimony requires that (1) the witness be an expert,

(2) there are facts in evidence that require or are subject to examination and analysis

by a competent expert, and (3) the knowledge is in a particular area that belongs

more to an expert than to the common man. The party presenting the expert bears

the burden of persuading the trial court that the expert has the necessary

qualifications and specialized knowledge that will aid the fact-finder in

understanding the evidence or determining a fact in issue. A witness may be

qualified as an expert by knowledge, skill, experience, training, or education.

[Surman v Surman, 277 Mich App 287, 308; 745 NW2d 802 (2007). (citations

omitted).]

The trial court serves as the gatekeeper under MRE 702, requiring

them “to review all expert opinion testimony” for admissibility under that rule.

Craig v Oakwood Hosp, 471 Mich 67, 82; 684 NW2d 296 (2004). “This gatekeeper

role applies to all stages of expert analysis. MRE 702 mandates a searching inquiry,

not just of the data underlying expert testimony, but also of the manner in which

the expert interprets and extrapolates from those data.” Gilbert v DaimlerChrysler

Corp, 470 Mich 749, 782; 685 NW2d 391 (2004). [Platt Convenience, Inc v Ann

Arbor, ___ Mich App ___, ___; ___ NW3d ___ (2024) (Docket No. 359013); slip

op at 11.]

During direct examination, Buschert testified extensively regarding his qualifications,

stating that he had worked for a company called Architectural Metals for 36 years, and had

expertise in wall systems, roofs, and the full envelope system through running jobs and directing

the service department which helped customers deal with problematic buildings. He also gained

knowledge and skills regarding envelope systems through training with the National Center for

Construction Education and Research, which led him to teaching. Further, Pearson’s counsel

conducted voir dire, and the court asked Buschert additional questions regarding his background

and experience.

Pearson challenges Buschert’s qualifications on the basis that he did not graduate from

high school and is neither an architect nor engineer. While Buschert did testify that he is not an

architect or engineer, there is no indication in the record that Buschert did not graduate from high

school. And the test for qualifying a witness under MRE 702 is broad and not necessarily

dependent on education alone. See Mulholland v DEC Int’l Corp, 432 Mich 395, 403-404; 443

NW2d 340 (1989). Indeed, an expert witness may be qualified based on practical experience in a

specific field, see id. at 403-407, which Buschert undoubtedly had.

Pearson also asserts that Buschert lacked specific experience in the installation of FRP on

DensGlass, making him unqualified to testify as HTB’s expert on Pearson’s work quality.

-8-

Buschert did acknowledge that he had never installed Crane Composites FRP panels on

DensGlass, as Pearson contracted with Dailey to do on the project. “Where the subject of the

proffered testimony is far beyond the scope of an individual’s expertise—for example, where a

party offers an expert in economics to testify about biochemistry—that testimony is inadmissible

under MRE 702.” Gilbert, 470 Mich at 789. But the record here demonstrates that Buschert’s

testimony was not beyond the scope of his expertise. Again, Buschert had extensive experience

with wall and envelope systems, and he testified regarding his method of evaluating Pearson’s

work on the project, which included acquiring the architect’s prints and spec book, studying the

Crane Composites instruction manual, and examining the work on site. Moreover, the court did

not qualify Buschert as an expert in the installation of FRP on DensGlass, but rather as an expert

on envelope systems, thereby limiting his testimony on that basis. See Mulholland, 432 Mich at

406 (“We continue to believe that the only safe rule is to ascertain with some specificity the range

of the witness’ qualifications and to permit testimony within that range.”). Finally, any gaps in an

expert’s knowledge affect the weight of his or her testimony rather than the admissibility.

Woodruff v USS Great Lakes Fleet, Inc, 210 Mich App 255, 260; 533 NW2d 356 (1995). On the

basis of the above, we hold that the trial court did not abuse its discretion when it qualified Buschert

as HTB’s expert on liability.

V. DIRECTED VERDICT

Finally, Pearson argues that the trial court erred by denying its motion for directed verdict

because HTB’s damages expert, Lance Hazel, was not qualified as an expert witness and his

damages calculations lacked foundation.

We review

de novo a trial court’s decision on a motion for directed verdict. A directed verdict

is appropriate only when no factual question exists upon which reasonable minds

could differ. In reviewing a directed verdict, we review all the evidence presented

up to the time of the motion to determine whether a question of fact existed. In

deciding whether a directed verdict is appropriate, the trial court must view the

testimony and all legitimate inferences from the testimony in the light most

favorable to the nonmoving party; we review the evidence in the same manner. The

trial court may not substitute its judgment for that of the jury when the evidence

could lead reasonable jurors to disagree. [Anaya v Betten Chevrolet, Inc, 330 Mich

App 210, 215-216; 946 NW2d 560 (2019) (citations omitted).]

Indeed, “where reasonable minds could differ regarding the level of certainty to which damages

have been proved, this Court is careful not to invade the fact finding of the jury and substitute its

own judgment.” Severn v Sperry Corp, 212 Mich App 406, 415-416; 538 NW2d 50 (1995).

“The party asserting a breach of contract has the burden of proving its damages with

reasonable certainty, and may recover only those damages that are the direct, natural, and

proximate result of the breach.” Alan v Custom Homes, Inc v Krol, 256 Mich App 505, 512; 667

NW2d 379 (2003). “In an action based on contract, the parties are entitled to the benefit of the

bargain as set forth in the agreement.” Ferguson v Pioneer State Mut Ins Co, 273 Mich App 47,

54; 731 NW2d 94 (2006). Accordingly, “[t]he proper measure of damages for a breach of contract

-9-

is the pecuniary value of the benefits the aggrieved party would have received if the contract had

not been breached.” Id. (quotation marks and citation omitted).

On appeal, Pearson asserts that the trial court erred in denying its motion for directed

verdict because Hazel was not qualified as an expert but does not appear to challenge Hazel’s

qualifications specifically or elaborate further. Regardless, Pearson waived this argument by

failing to raise it below. Tolas Oil & Gas Exploration Co v Bach Servs & Mfg, LLC, 347 Mich

App 280, 289-290; 14 NW3d 472 (2023).

Pearson further challenges HTB’s assertion of damages on the basis that Hazel’s damages

calculations lacked any foundation.

It is true that damages that are speculative or based on conjecture are not

recoverable. Ensink v Mecosta Co Gen Hosp, 262 Mich App 518, 525; 687 NW2d

143 (2004). However, it is not necessary that damages be determined with

mathematical certainty; rather, it is sufficient if a reasonable basis for computation

exists. Id. [Chelsea Investment Group LLC v Chelsea, 288 Mich App 239, 255;

792 NW2d 781 (2010).]

Consistent with Pearson’s arguments, Hazel testified on cross-examination that he did not

obtain subcontractor estimates for the heating, cooling, ventilating, plumbing, and electrical work

that would be done ancillary to replacement of the FRP panels, and acknowledged he had no

foundation or basis for some of these estimates. But he clarified on redirect that he and Buschert

work as a team to create estimates, and that Buschert provides him with the estimated man hours

needed on a project to assist in calculating the overall estimate. Indeed, in his testimony on direct

examination, Hazel stated that Buschert conducted the inspection of the project and reported back

on what would be needed to redo the work. He also asserted that the figures for the various trades

work were formed using his years of experience developing these estimates. On this record, a

reasonable basis for Hazel’s computation of damages exists.

Moreover, the jury had the opportunity to weigh the evidence before it and returned a

verdict with damages lower than those requested by HTB for replacement of the FRP panels.

HTB’s counsel asked the jury to award over $1 million for replacement of the interior FRP panels,

but the jury ultimately awarded $751,958. Thus, we will not “invade the fact finding of the jury

and substitute [our] own judgment.” Severn, 212 Mich App at 415-416.

Affirmed.

/s/ Michael F. Gadola

/s/ Christopher M. Murray

/s/ Michael J. Kelly

-10-

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.