STATE OF LOUISIANA

COURT OF APPEAL, THIRD CIRCUIT

19-295

JOSEPH PALERMO, ET AL.

VERSUS

HOMES AND MORE, INC.

FORFAR

APPEAL FROM THE

FOURTEENTH JUDICIAL DISTRICT COURT

PARISH OF CALCASIEU, NO. 2018-0453

HONORABLE ROBERT LANE WYATT, DISTRICT JUDGE

See ook Ro ek

JUDGE

VAN H. KYZAR

oe oe oe ok oe oe ok oe oe

Court composed of Sylvia R. Cooks, John E. Conery, and Van H. Kyzar, Judges.

WRIT GRANTED

Douglas Robert Holmes

Charles D. Marshall, III

Chaffe McCall

1100 Poydras Street, #2300

New Orleans, LA 70163

(504) 585-7000

COUNSEL FOR DEFENDANT/APPLICANT:

Homes and More, Inc.

Steven Paul Lemoine

Robert H. Schmolke, PLC

9191 Siegen Lane, Building 4-B

Baton Rouge, LA 70810

(225) 292-1717

COUNSEL FOR PLAINTIFF/RESPONDENT:

Joseph Palermo

Jacqueline Mae Manuel Palermo

Ronald Cole Richard

1 Lakeshore Drive, Suite 120

Lake Charles, LA 70629

(337) 494-1900

COUNSEL FOR PLAINTIFF/RESPONDENT:

Joseph Palermo

Jacqueline Mae Manuel Palermo

Kyzar, Judge.

Defendant-Relator, Homes and More, Inc. (“H&M”), seeks supervisory writs

from the judgment of the trial court which denied its motion for partial summary

judgment seeking dismissal of all claims against H&M that are excluded under the

Louisiana New Home Warranty Act (NHWA), La. R.S. 9:3141, et seq., including

plaintiffs’ claims alleging damages due to the presence of “mold” and

“consequential damages.” For the reasons herein, we grant the writ, make it

peremptory, reverse the ruling of the trial court, and enter a partial summary

judgment in favor of H&M dismissing Plaintiffs’ claims relating to mold, mold

damage, and consequential damages with prejudice.

FACTS AND PROCEDURAL HISTORY

On February 1, 2018, Plaintiffs filed suit against H&M, asserting that on or

about October 15, 2015, the parties entered a contract under which H&M agreed to

construct a residential home in Sulphur, Louisiana. Notably, Plaintiffs state in their

petition that Defendant was the contractor of the construction of the subject

property. The petition goes on to allege that H&M improperly constructed the roof,

causing mold and other issues with the property. Regarding the alleged mold in the

home, Plaintiffs sought damages for the cost of any mold removal and the cost of

any expert required to determine the full extent of the damages to the subject

property. Plaintiffs additionally sought consequential damages for, among other

things, the “devaluation of a very expensive home” and the “fair market rental value

of the home” for the time that Plaintiffs were unable to use the subject property.

On May 29, 2018, H&M filed its answer to the petition, admitting that it

agreed to act as a job coordinator for the construction of Plaintiffs’ home.

Thereafter, on December 4, 2018, H&M filed a third-party demand naming Scott

Cormier, d/b/a MSP Construction & Roofing, and Chris Cormier, d/b/a Cormier’s

Roofing & Construction, as third-party defendants. The third-party demand asserted

that H&M hired Scott Cormier and Chris Cormier as subcontractors who supplied

labor and/or materials for Plaintiffs’ home. Therein, H&M specifically pleaded the

NHWA, under which it, as the “builder,” may be found liable to Plaintiffs, as

“owners,” for the defective workmanship or materials of Scott Cormier and/or Chris

Cormier under the Act’s mandatory warranty.

On December 10, 2018, H&M filed a motion for partial summary judgment

seeking a dismissal of all claims asserted by Plaintiffs that are excluded under the

NHWA, namely claims for consequential damages and damages due to the presence

of mold. Louisiana Revised Statutes 9:3144(B) states: “Unless the parties otherwise

[c]onsequential damages ... [and] (19) [mJold and mold damage.” Thereafter,

on February 28, 2019, Plaintiffs filed an opposition memorandum to H&M’s motion,

asserting that a genuine issue of material fact exists as to whether H&M meets the

definition of a “builder” under the NHWA, La.R.S. 9:3143, especially given its own

self-characterization as a “job coordinator.” In response, H&M’s reply

memorandum sought to demonstrate that, regardless of the characterizations used by

the parties, H&M served the role and functions of a general contractor and is, thus,

subject to the NHWA.

On March 21, 2019, the motion for partial summary judgment was heard

before the trial court.! Therein, H&M argued that as a general contractor, it is

' At the hearing on the motion. H&M offered. filed, and introduced two exhibits into the

record: Exhibit 1, Plaintiffs’ petition and Exhibit 2, the sworn affidavit of Marcus Benny, Sr.. a

part owner of H&M. Plaintiffs offered no evidence in opposition to the motion.

2

considered a “builder” under the NHWA and thus Plaintiffs must pursue their claims

under the Act, subject to its exclusions. See La.R.S. 9:3143 and 9:3144. H&M also

clarified that a granting of its motion would not dismiss the case, but rather advances

the case and merely sets forth the issues in a new home construction case against a

builder. In response, Plaintiffs asserted it would be a mistake to conclude that all

general contractors are “builders,” because of the fact that H&M characterized itself

as a “job coordinator.”

The trial court orally denied H&M’s motion at the hearing, finding that it

was “not convinced” just yet, especially in light of Plaintiffs’ argument that

discovery would help answer remaining questions. The judgment was signed on

April 2, 2019. In this writ application, H&M presents one question for this court’s

consideration: whether a general contractor qualifies as a “builder” under the

NHWA, such that it was entitled to a grant of partial summary judgment dismissing

only those claims relating to mold, mold damages, and consequential damages.

DISCUSSION

Louisiana Code of Civil Procedure Article 966, which governs the summary

judgment procedure, provides that a party may move for a summary judgment for

all, or part, of the relief for which he has prayed. La.Code Civ.P. art. 966(A). Under

La.Code Civ.P. arts. 966(E) and 1915, a partial summary judgment may be rendered

which disposes of a particular issue, theory of recovery, cause of action, or defense

in favor or one or more parties, even though the granting of summary judgment does

not dispose of the entire case.

The summary judgment procedure is favored and shall be construed to secure

the just, speedy, and inexpensive determination of an action. La.Code Civ.P. art.

966. When the mover will not bear the ultimate burden of proof at trial, he must

only point out the absence of factual support for one or more essential elements of

3

the adverse party’s claim. La.Code Civ.P. art. 966(D)(1). Thereafter, it becomes

the adverse party’s burden to produce sufficient factual support demonstrating the

existence of a genuine issue of material fact or that the mover is not entitled to

summary judgment as a matter of law. /d. The adverse party must respond with

competent summary judgment evidence setting forth specific facts showing that a

material fact is genuinely in dispute; he may neither rest on the allegations of his

pleading, nor the mere possibility that a factual issue could be raised. La.Code Civ.P.

art. 967. If he does not so respond, summary judgment, if appropriate, shall be

rendered against him and in favor of the mover. /d.

Appellate courts review the grant or denial of a motion for summary judgment

de novo, “using the same criteria that govern the trial court’s determination of

whether summary judgment is appropriate; i.e., whether there is any genuine issue

of material fact and whether the mover is entitled to judgment as a matter of law.”

Samaha v. Rau, 07-1726, p. 4 (La. 2/26/08), 977 So.2d 880, 882-83. Where the

threshold question in reviewing a trial court’s grant of summary judgment is whether

a genuine issue of material fact exists, such a determination must be viewed in light

of the relevant substantive law. Romero v. Allstate Ins. Co., 08-256 (La.App. 3 Cir.

5/13/09), 11 So.3d 579, writ denied, 09-1325 (La. 10/9/09). “Here, however, the

determination of the motion depends more upon the legal character of the claims

pleaded rather than upon any dispute as to material fact.” Barnett v. Watkins, 06-

2442, p. 9 (La.App. | Cir. 9/19/07), 970 So.2d 1028, 1034, writ denied, 07-2066 (La.

12/14/07), 970 So.2d 537.

Plaintiffs contend that disputed facts exist regarding the status of H&M solely

by virtue of the differences in characterization of H&M in the pleadings, without

having submitted any evidence at the hearing nor having contested any of the facts

set forth in H&M’s affidavit. The issue presented in the instant case, therefore, turns

4

on the legal question of whether a general contractor qualifies as a “builder” under

the NHWA, such that the Act governs claims of owners against their general

contractors. Because this is a legal issue raised on summary judgment, we review

the matter de novo.

General Contractor

Before addressing this legal issue, we turn to the undisputed facts of this case

in order to determine whether H&M is, in fact, a general contractor.

Plaintiffs’ petition alleged that Plaintiffs and Defendant entered into a contract

wherein Defendant agreed to construct a residential home in Sulphur, Louisiana, and

that Defendant was the contractor of the construction of the property. The petition

also alleged, inter alia, that H&M was negligent for failing to properly supervise the

employees and sub-contractors working on the property. In response to this

allegation, H&M’s answer stated that it agreed to act as a job coordinator for the

construction of a home for Plaintiffs. Moreover, the affidavit submitted in support

of the motion for partial summary judgment stated that H&M contracted for the

construction of a home, though the actual construction work was to be performed by

subcontractors and coordinated by H&M.

A “General Contractor” is someone who “contracts for the completion of an

entire project, including purchasing all materials, hiring and paying subcontractors,

and coordinating all the work.” BLACK’sS LAW DICTIONARY (11th ed. 2019).? Here,

Plaintiffs’ petition clearly identifies H&M as the general contractor hired to

construct their home. The affidavit submitted by H&M explicitly states that H&M

> H&M cites an older version of this definition as it appeared in the fourth circuit’s decision

in Regions Bank v. Breland, 10-1793, pp. 3-4 (La.App. 4 Cir. 35/18/11) (unreported opinion, 2011

WL 9165416), which similarly provides: “A General Contractor is ‘one who contracts for the

construction of an entire building or project. rather than for a portion of the work. The general

contractor hires subcontractors. coordinates all work and is responsible for payment to

subcontractors.” Black's Law Dictionary.”

acted as a “job coordinator.” Given BLACK’s definition, H&M’s admission simply

reiterates that H&M _ performed the primary function of a general contractor in

coordinating the construction of the home. Additionally, Plaintiffs’ claims of

negligent supervision over subcontractors clearly implicates a general contractor’s

role in a construction job. From the undisputed facts alleged in the petition and

attested to in the affidavit, there appears to be no legitimate question regarding the

scope of H&M’s responsibilities in this situation. We find no merit in Plaintiffs’

assertion that the differences in H&M’s title of contractor or job coordinator, as

supplied by the parties, gives rise to a genuine issue of material fact. The distinction

as to H&M’s title role as referred to by the parties is one of semantics only and does

not change the role actually performed by H&M. It is readily apparent that H&M

served as the general contractor to construct Plaintiffs’ home, and Plaintiffs’ failed

to submit any evidence contradicting this fact.

New Home Warranty Act

Having determined that H&M meets the definition of a general contractor, we

now turn to the question of whether a general contractor is a builder as contemplated

by the NHWA.

The stated policy objective of the NHWA is as follows:

The legislature finds a need to promote commerce in Louisiana

by providing clear, concise, and mandatory warranties for the

purchasers and occupants of new homes in Louisiana and by providing

for the use of homeowners’ insurance as additional protection for the

public against defects in the construction of new homes. This need can

be met by providing a warranty for a new home purchaser defining the

responsibility of the builder to that purchaser and subsequent

purchasers during the warranty periods provided herein.

La.R.S. 9:3141. As such, the NHWA goes on to explicitly state that “[t]his Chapter

provides the exclusive remedies, warranties, and peremptive periods as between

builder and owner relative to home construction and no other provisions of law

relative to warranties and redhibitory vices and defects shall apply.” La.R.S. 9:3150

(emphasis added). Here, the parties do not dispute that Plaintiffs are the owners or

that the claims asserted are relative to home construction. The only question that

arises is whether a general contractor is a “builder.”

In setting out to define the actors subject to the exclusivity of its provisions,

the NHWA defines a “builder” as “any person, corporation, partnership, limited

liability company, joint venture, or other entity which constructs a home, or addition

thereto[.]” La.R.S. 9:3143(1). While Plaintiffs correctly point out that the NHWA’s

definition of “builder” makes no explicit mention of contractors or job coordinators,

a cursory review of the jurisprudence makes it abundantly clear that virtually every

circuit has held the NHWA applicable to claims of new homeowners against their

3

general contractors.” Nonetheless, no court has ever set out to explicate why a

general contractor is a “builder” under the Act. Thus, while it is readily apparent

3 In Barnett. 970 So.2d at 1031. “plaintiffs entered into a written contract with Ashland

Homes, Inc. (Ashland), as general contractor. for the construction of their residence.” The first

circuit affirmed the trial court’s ruling dismissing all claims by the plaintiff against the general

contractor’s insurer that were excluded under the NEITWA.

In Nolan v. Roofing Supply. 36.403. p. 1 (La.App. 2 Cir. 11/26/02), 833 So.2d 1026, 1027

the plaintiff sued “Frank Stone & Son. Inc., the builder” for defective installation of a roof. “In

1994 [plaintiff] hired Stone as general contractor.” /d. The second circuit simply held: “As the

exclusive remedy, warranty, and prescriptive period between the builder, Stone and the

homeowner, Nolan, the [NHWA]| applies in this dispute.” /d. at 1032.

In Regions Bank v. Breland, 10-1793 (La.App. 4 Cir. 5/18/11) (unreported opinion, 2011

WL 9165416), the fourth circuit addressed the issue of general contractors, albeit in the context of

the Private Works Act. Nevertheless, it concluded that one was a general contractor based on the

following:

According to the record, and by Mr. Butler’s own admission. Mr.

Butler constructed the (entire) house . . . as per a contract between himself

and Ms. Breland. Mr. Butler impliedly served as a general contractor. The

record supports that Mr. Butler was not subcontracted nor did he construct

only a portion of the house.

Breland, at p. 4.

Finally, in Campo v. Sternberger, 15-52, pp. 3-4 (La.App. 5 Cir. 11/19/15), 179 So.3d 908,

910-11, the fifth circuit affirmed the trial court’s judgment awarding the plaintiffs damages against

“[d]efendant-builder. Randy Sternberger” under the NHWA where plaintiffs “retained Sternberger

to construct the home.”

from the jurisprudence that an owner’s remedy against his/her general contractor

falls exclusively under the NHWA, the question posed here nevertheless presents

this court with a res nova issue: whether a general contractor qualifies as a “builder”

under the NHWA.

In an attempt to raise doubt regarding the classification of a general contractor

as a builder, Plaintiffs rely on two cases to conclude that the defining feature of a

”4 While not wholly incorrect,

builder is that it must “construct the entire home.

Plaintiffs cite caselaw that is simply incongruous with the facts of this case. First,

Plaintiffs argue that this court’s decision in Taylor v. Leger Const., LLC, 10-749

(La.App. 3 Cir. 12/8/10), 52 So.3d 1098, is factually similar to this case. According

to Plaintiffs’ interpretation of Tay/or, this court reversed the trial court’s grant of an

exception of no cause of action because the plaintiffs’ petition contained no express

allegation that the defendant was a builder. Because the petition merely alleged that

the defendant furnished the labor, material, and design for the construction of the

foundation and the foundation system of their residence, this court held that the

defendant failed to establish that it was a “builder” of a home under La.R.S. 9:3143,

and, thus, the NHWA did not apply to dismiss the plaintiffs’ allegations. /d.

However, we note that the plaintiffs in Tay/or initially instituted suit under the

NHWA against subcontractors, not general contractors. In fact, we held: “While it

is true that the NHWA provides protection to new homeowners against builders, we

do not interpret the NHWA so broadly that a subcontractor would be considered a

builder, because subcontractors do not construct the entire structure and deliver it to

the owner as a new home.” /d. at 1102 (quoting Cosman v. Cabrera, 09-265

(La.App. 1 Cir. 10/23/09), 28 So.3d 1075). Thus, we find Taylor inapplicable here.

4 Plaintiffs cited no authority to the district court in support of the argument that a general

contractor is not a builder under the NHWA when subcontractors perform the actual construction

work at issue.

8

Plaintiffs further rely on the first circuit’s decision in Cosman, 28 So.3d 1075,

which dealt with similar facts to that of Taylor, to again argue that in order to qualify

as a builder, the putative party must construct the entire house. Plaintiffs reasoning,

however, is flawed for several reasons. First, a clear reading of the statute reveals

that a “builder” is one that “constructs a home, or addition thereto[.]” La.R.S.

9:3143(1) (emphasis added). Therefore, a builder need not construct the entire home

to qualify as a builder, where the construction of a mere addition to a home suffices.

Plaintiffs’ argument also suffers because it clearly ignores an essential portion of the

holdings in Cosman and Taylor, which is that, a subcontractor cannot be a “builder”

because it does not construct the entire structure “and deliver it to the owner as a

new home.” To ignore the conjunctive “and” here divests these holdings of any

significance where one must undertake both the construction and the delivery in

order to be considered a “builder.”

In addition to their failure to adduce any factual support demonstrating that

H&M built less than the entire structure, the allegations in Plaintiffs’ petition

contemplate that H&M had obligated itself to deliver the construction to them as a

new home. We find that the fatal defect here lies not in the existence of a genuine

issue of material fact, as Plaintiffs contend, but rather in their own interpretations.

Even if this court were to accept Plaintiffs’ singular line of reasoning, arguendo, we

remember that BLACK’s defines a general contractor as “someone who contracts

for the completion of an entire project.” BLACK’S LAW DICTIONARY (11th ed. 2019).

Applying this definition to the NHWA, this would include anyone contracting to

provide an entire, completed new home or a completed new addition to an existing

home.

Regarding the foregoing jurisprudence, we find the true import of these cases

seems to entreat the question: but for the putative builder’s involvement in the

9

construction, would a new, completed home have been delivered to the owner?

While perhaps a general contractor does not itself construct the home in a literal

sense, it orchestrates the planning and construction of the home by directing

subcontractors to build portions of the home and eventually delivers the completed

home to the prospective owners. Simply put, without a general contractor, there

would be no laborers hired to perform the construction, nor any materials supplied

with which to construct the home. The general contractor is responsible for making

sure the structure is built and delivering the final, finished property to the owners as

anew home. Accordingly, a general contractor may be a “builder” as contemplated

by the NHWA, La.R.S. 9:3143, depending on the facts of the particular case.

Here, the pleadings demonstrate that Plaintiffs hired H&M as the contractor

to construct the entirety of their home, and in order to do so, H&M hired

subcontractors to supply labor and materials. In turn, Plaintiffs expected and

received a new, completed home that now allegedly bears defects as a result of

H&M’s construction. Therefore, under the facts of this case, we find H&M, acting

as a general contractor, meets the requirements to be a “builder” as contemplated by

the NHWA for purposes of excluding Plaintiffs’ claims for mold, mold damages,

and consequential damages. See La.R.S. 9:3144.

WRIT GRANTED: We find that the trial court erred in denying H&M’s motion

for partial summary judgment. H&M clearly acted as the general contractor of the

construction at issue, and as such, H&M qualifies as a “builder” under the Louisiana

New Home Warranty Act, La. R.S. 9:3141, et seg. See Barnett, 970 So.2d 1028.

Thus, Plaintiffs’ remedies against it are defined exclusively pursuant to the Act.

Moreover, Plaintiffs’ failure to submit any evidence in opposition of the motion

suggests not only that they did not meet their burden of proof, but also mandates the

granting of the motion, dismissing those of Plaintiffs’ claims that are specifically

excluded under the Act.

We grant the writ, make it peremptory, reverse the ruling of the trial court,

enter a partial summary judgment in favor of H&M dismissing Plaintiffs’ claims

relating to mold, mold damage, and consequential damages with prejudice, and

remand this matter to the trial court for proceedings in accordance therewith.

11