The opinion
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Bryan Ashush JV ) ASBCA No. 64037 1
)
Under Contract No. W912GB-23-C-0005 )
APPEARANCE FOR THE APPELLANT: Casey J. McKinnon, Esq.
Cohen Seglias Pallas Greenhall
& Furman PC
Washington, DC
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Cara M. Mroczek, Esq.
Rebecca L. Bockmann, Esq.
Engineer Trial Attorneys
U.S. Army Engineer District, Middle East
Winchester, VA
OPINION BY ADMINISTRATIVE JUDGE SWEET
ON THE GOVERNMENT’S PARTIAL MOTION TO DISMISS
Appellant Bryan Ashush JV (BAJV or appellant) appeals the deemed denial of
its claim seeking to be excused from performing a contract between it and the
United States Army Corps of Engineers (Corps or government). The government has
moved (Motion) to dismiss or strike portions of BAJV’s complaint (Complaint),
arguing that the Complaint requests injunctive relief that the Board does not possess
jurisdiction to grant. BAJV argues that the Complaint merely requests declaratory
relief that the contract should be terminated for convenience. As discussed in greater
detail below, the Complaint seeks injunctive relief that we do not possess jurisdiction
to grant, and declaratory relief that we do possess jurisdiction to grant. Thus, we grant
the Motion in part, and deny it in part.
1
Appellant has filed two additional notices of appeal, docketed as ASBCA Nos. 64184
and 64185. Those appeals have been consolidated with this appeal; however,
the Corps’ Motion and our opinion deal only with the Complaint filed in
ASBCA No. 64037.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
1. On August 2, 2023, the Corps awarded BAJV Contract No. W912GB-23-C-
0005 (Contract) for the construction of a “Life Support Area” in Israel (R4, tab 3 at 1-
2). The Corps issued an administrative notice to proceed (NTP) on September 12,
2023 (compl. ¶ 10; answer ¶ 10), and planned to issue a construction NTP on
October 15, 2023 (answer ¶ 13).
2. Before it issued that construction NTP, however, a war between Hamas and
Israel began on October 7, 2023 (compl. ¶ 13; answer ¶ 13). The Corps issued a
suspension of work order on November 7, 2023 (compl. ¶ 14), but lifted it on
January 17, 2024 (id. ¶ 15; answer ¶ 15). The Corps did not issue the construction
NTP until June 5, 2024 (compl. ¶ 27; answer ¶ 27).
3. On August 1, 2024, BAJV filed a claim with the contracting officer (CO)
requesting that it be excused from further performance (R4, tab 2 at 1). The claim
alleged that the Corps’ failure to issue the construction NTP until 10 months after
award constituted a material breach, a cardinal change, and rendered performance
impracticable (id. at 2-6). The Corps did not respond to the claim, leading BAJV to
file this appeal as a deemed denial on December 13, 2024.
4. Like its claim, BAJV’s three-count Complaint alleges material breach of
contract, cardinal change, and commercial impracticability. The concluding
paragraphs of the Complaint’s statement of facts, the second count, and the third count
allege that the Corps’ conduct excuses BAJV from further performance under the
contract, “which should be terminated for convenience” (compl. ¶¶ 28, 55, 66).
Similarly, the concluding paragraph of the first count alleges that “BAJV is entitled to
discontinue its performance and have the Contract terminated for convenience” (id.
¶ 44).
5. The Complaint’s prayer for relief makes two requests: that “the Board (1) find
that [BAJV’s] performance obligations under the Contract are excused and (2) direct
the Government to terminate the Contract for convenience” (id. at 10).
DECISION
Analysis
While the Board does not possess jurisdiction over BAJV’s request that we
direct the government to terminate the Contract for convenience, we possess
jurisdiction over BAJV’s request that we find that the government’s material breach, a
cardinal change, and impossibility excuse BAJV’s performance. Under the Contract
Disputes Act (CDA), 41 U.S.C. §§ 7101-09, we do not possess jurisdiction to grant
2
injunctive relief. Lulus Ostrich Ranch, ASBCA Nos. 59252, 59450, 14-1 BCA
¶ 35,769 at 175,000. However, we possess jurisdiction to grant declaratory relief.
Alliant Techsystems, Inc. v. United States, 178 F.3d 1260, 1271 (Fed. Cir. 1999); Inter-
Continental Equip., Inc., ASBCA No. 44840, 94-2 BCA ¶ 26,655 at 132,609.
“Although the Board does not possess jurisdiction to order injunctive relief such as the
termination of a contract for convenience, the Board possesses jurisdiction to entertain
non-monetary claims, including whether performance of the contract is impossible.”
CDM Constructors, Inc., ASBCA No. 59524, 15-1 BCA ¶ 36,097 at 176,238 (citations
omitted). Similarly, in Philips Lighting N. Am. Corp., we held that a complaint
requesting that we find that the government’s material breach permitted a contractor to
cease performance and seek damages did not seek injunctive relief. ASBCA
No. 61769, 2024 WL 5038837 (Nov. 15, 2024). A contractor bears the burden of
proving the Board’s jurisdiction to hear its appeal. Reynolds v. Army & Air Force
Exch. Serv., 846 F.2d 746, 748 (Fed. Cir. 1988); Kostas Greek Food – Zorbas,
ASBCA No. 62213, 21-1 BCA ¶ 37,750 at 183,208.
Here, the Complaint’s prayer for relief requests that we direct the government
to terminate the Contract for convenience, and that we find that the government’s
material breach, a cardinal change, and impossibility excused BAJV’s performance
obligations under the Contract (SOF ¶ 5). Under CDM Constructors, we do not
possess jurisdiction to direct the government to terminate the Contract for convenience
because that is injunctive relief. See 15-1 BCA ¶ 36,097 at 176,238. However, under
CDM Constructors and Philips Lighting, we possess jurisdiction to determine whether
there was a material breach, a cardinal change, and impossibility which would excuse
BAJV’s performance obligations under the Contract because that is declaratory relief
of the sort that we may provide. See CDM Constructors, 15-1 BCA ¶ 36,097
at 176,238; Philips Lighting, 2024 WL 5038837. 2 Thus, BAJV has not met its burden
of showing that we possess jurisdiction over the Complaint’s request that we direct the
government to terminate the Contract for convenience, but BAJV has met its burden of
showing that we possess jurisdiction over the Complaint’s request that we find that the
government’s material breach, a cardinal change, and impossibility excused BAJV’s
performance obligations under the Contract.
2
The government also moves to strike the mentions of the termination for convenience
contained in paragraphs 28, 44, 55, and 66 of the Complaint (gov’t mot. at 2-3,
5). Those references are a mere expression of BAJV’s opinion concerning what
should happen to the Contract if the Board finds in BAJV’s favor, and do not
request that the Board order, direct, or otherwise require the Corps to terminate
the contract for convenience (SOF ¶ 4). Therefore, we deny the motion to
strike those references.
3
CONCLUSION
For the foregoing reasons, the Motion is granted in part and denied in part. We
strike the Complaint’s second request for relief asking us to “direct the Government to
terminate the Contract for convenience” (SOF ¶ 5 (quoting compl. at 10)).
Dated: October 1, 2025
JAMES R. SWEET
Administrative Judge
Armed Services Board
of Contract Appeals
I concur I concur
OWEN C. WILSON J. REID PROUTY
Administrative Judge Administrative Judge
Acting Chairman Vice Chairman
Armed Services Board Armed Services Board
of Contract Appeals of Contract Appeals
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 64037, Appeal of Bryan
Ashush JV, rendered in conformance with the Board’s Charter.
Dated: October 1, 2025
PAULLA K. GATES-LEWIS
Recorder, Armed Services
Board of Contract Appeals
4