“The interpretation of a contract . . . is a question of law”
How later courts described this case
- “The interpretation of a contract . . . is a question of law”
- affirming lower court’s judgment granting summary judgment
- explaining a court “need[s] to take account of the particular contract at issue in considering a claim of breach of the good-faith-and- fair-dealing duty implicit in that contract”
- denying the government’s Motion to Dismiss for lack of payment because “the parties disagreed as to the amount Spectre paid NASA under the Space Act Agreement”
Written by the judges who cited it.
The opinion
In the United States Court of Federal Claims
No. 16-932
(Filed: 18 August 2025)
***************************************
SPECTRE CORPORATION, *
*
Plaintiff, *
*
v. *
*
THE UNITED STATES, *
*
Defendant. *
*
***************************************
James W. Wiggin III, of Columbus, OH, for plaintiff.
Nelson Kuan, Trial Attorney, Commercial Litigation Branch, Civil Division, of the US
Department of Justice, with whom were Brian M. Boynton, Principal Deputy Assistant Attorney
General, Patricia M. McCarthy, Assistant Director, Martin F. Hockey, Jr., Deputy Director, all
of Washington, DC, for the government.
OPINION AND ORDER
HOLTE, Judge.
Plaintiff Spectre Corporation manufactures and sells pressure sensors to be used across
various industries, including automotive, oil and gas, aviation, and aerospace. Spectre and
NASA executed two contracts to license and commercialize NASA’s patented silicon carbide
pressure sensor technology—a Patent License and Space Act Agreement. Plaintiff alleges
NASA breached both contracts as well as the implied duty of good faith and fair dealing, seeking
compensatory damages and lost profits. On 17 July 2024, the Court dismissed plaintiff’s request
for any lost profits damages. The parties subsequently filed cross-motions for summary
judgment on the government’s alleged breaches. For the following reasons, the Court grants the
government’s Motion for Summary Judgment and denies plaintiff’s Cross-Motion.
I. Factual History 1
1
All facts in this section are undisputed, unless stated otherwise. See RCFC 56(a) (requiring a movant for summary
judgment to demonstrate “there is no genuine dispute as to any material fact”). The Court draws all inferences “in
the light most favorable to the party opposing the motion.” Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475
U.S. 574, 587–88 (1986).
Plaintiff Spectre Corporation and the United States through NASA executed two
agreements to commercialize pressure sensor technology NASA developed and patented. The
first agreement, SAA3-210 (“Space Act Agreement”) executed on 22 December 2011, sets forth
NASA’s and Spectre’s obligations to commercialize NASA’s silicon-carbide sensor technology.
See Compl. Ex. 2 at 5–21 (Space Act Agreement), ECF No. 1-3. The second agreement, DE-456
(“Exclusive License Agreement”) executed on 14 May 2012, granted Spectre a royalty-bearing,
exclusive license to practice the silicon-carbide sensor patents through 25 January 2025, the end
of the patents’ terms, and required Spectre to pay a $50,000 fee to NASA. See Compl. Ex. 1 at
1–31 (Exclusive License Agreement), ECF Nos. 1-1, 1-2, 1-3. Around the same time, Spectre
applied for and received a $1,000,000 grant from the State of Ohio to commercialize the sensor
technology. See Compl. Ex. 3 at 23–84 (Ohio Grant), ECF No. 1-3.
The Space Act Agreement (“SAA”) consists of eleven “Milestones” governing the parties’
responsibilities:
1. NASA completes Pressure Sensing Element Design
2. NASA completes Wafer Fabrication
3. NASA completes Sensing Element Test
4. NASA completes Header Fabrication and Assembly
5. NASA completes Pressure Sensing Module Functional Test
6. NASA delivers Fabrication Run 1 Sensors to Spectre
7. NASA completes Integration in Spectre Sensor Package
8. Spectre Corp. completes Cold Performance Test
9. Spectre Corp. completes Commercial Evaluation
10. Spectre Corp. and NASA complete Review of Design, Integration and
Performance
11. NASA completes Fabrication Run 2 and deliver sensors to Spectre
Compl. Ex. 2 at 5 (Space Act Agreement). The SAA also requires “Spectre . . . to pay
NASA [Glenn Research Center (“GRC”)] $100,000.00 prior to initiation of work under this
agreement, and . . . $80,000.00 prior to the start of Milestone No. 3.” Id. at 6. After delays and
conflicts affecting the performance of obligations under the contracts, including Spectre not
completing its payment requirements prior to the start of Milestone No. 3, NASA terminated the
Exclusive Licensing Agreement and halted its performance under the Space Act Agreement,
allowing the Space Act Agreement to expire by its own terms. Compl. at 4, ECF No. 1. Plaintiff
brought this action for breach of the Space Act Agreement and the Exclusive Licensing
Agreement claiming $215,000 for fees paid to NASA, at least $2,000,000 for money spent on the
failed project, and more than $45,000,000 in lost profits. See Compl. at 43.
II. Procedural History
On 26 July 2022, the Court granted the government’s Motion in Limine to exclude
plaintiff’s fact report on packaging cost information, portions of its expert report on fabrication
cost information, and portions of its fact report on sales projections. Spectre Corp. v. United
States, 160 Fed. Cl. 486, 505 (2022). The Court subsequently granted plaintiff an opportunity to
“prepare and submit a revised report” for each of the three reports based on “admissible
-2-
evidence,” see id., and adopted the parties’ proposed schedule setting a 31 October 2022
deadline to submit the revised reports. See 26 Aug. 2022 Order at 1, ECF No. 135. Plaintiff
missed the deadline, see Gov’t’s Opp’n to Spectre’s Out of Time Mot. for an Enlargement of
Time (“Gov’t’s EOT Resp.”) at 2, ECF No. 137, and instead—one month after the deadline—
filed a motion for enlargement of time, ECF No. 136. The Court denied plaintiff’s motion for
enlargement of time, concluding plaintiff’s “failure to meet the 31 October 2022 deadline
accordingly does not amount to excusable neglect, so a motion for enlargement of time cannot
cure plaintiff’s failure.” Spectre Corp. v. United States, 165 Fed. Cl. 563, 575 (2023) (first citing
RCFC 6(b)(1)(B); and then citing Pioneer Inv. Servs. Co. v. Brunswick Assocs. Ltd. P’ship, 507
U.S. 380, 395 (1993)). As a result, plaintiff had “little evidence to replace the excluded fact
report on packaging costs information, portions of the expert report on fabrication cost
information, and portions of the fact report on sales projections.” See Spectre Corp. v. United
States, 172 Fed. Cl. 159, 162 (2024).
Following the Court’s order granting the government’s Motions in Limine, on 20 June
2023, the government filed an amended motion for partial summary judgment on lost profits.
Gov’t’s Am. Mot. for Partial Summ. J. (“Gov’t’s Am. MPSJ”), ECF No. 146. The Court held
oral argument on 21 March 2024 in Akron, Ohio. See 7 Dec. 2023 Scheduling Order, ECF No.
150. On 17 July 2024, the Court granted the government’s Amended Motion for Partial
Summary Judgment on plaintiff’s claims for lost profits damages, found as moot the
government’s original Motion for Partial Summary Judgment, and dismissed plaintiff’s request
for any lost profits damages, as included in counts III and IV. See Spectre, 172 Fed. Cl. at 186.
On 12 August 2024, the parties submitted a joint status report “detailing the remaining issues in
the case and proposing a schedule for further proceedings.” See 12 Aug. 2024 JSR at 2, ECF No.
155. In the JSR, the parties discussed the possibility of either holding a mini-trial on liability or
resolving dispositive issues by way of summary judgment motions. See id. at 3, 6. The
government also sought the Court to “amend its decision granting [the government]’s motion for
partial summary judgment for lost profits damages to include Counts I and II of the Complaint,
in addition to Counts III and IV as the decision currently provides” because the Court’s
“reasoning nevertheless applies equally to all four counts because plaintiff’s purported evidence
subject to the in limine rulings was not specific to distinct counts of the complaint.” Id. at 6–7.
The government explained the “requested amendment [was] only clerical in nature.” Id. at 7.
The Court then held a substantive status conference on 25 September 2024 to discuss
next steps in the case and a schedule moving forward. See 9 Sept. 2024 Scheduling Order, ECF
No. 156. At the status conference, the parties agreed to a briefing schedule on cross-motions for
summary judgment on liability and the Court adopted the parties’ schedule. See 25 Sept.
Scheduling Order and Formal Clarification, ECF No. 157. During the status conference, “the
Court also discussed with the parties the government’s request for the Court to amend its 17 July
2024 Opinion and Order, Spectre Corp. v. United States, 172 Fed. Cl. 159 (2024), granting the
government’s Motion for partial Summary Judgment for Lost Profits Damages to include Counts
I and II of the Complaint, in addition to Counts III and IV as the decision currently provides.”
Id. at 1 (citing 12 Aug. 2024 JSR). “All parties agree[d] the Court’s decision on lost profits
should apply to all Counts and not just Counts III and IV,” so the Court “formally clarifie[d] its
17 July 2024 Opinion and Order dispose[d] of all of plaintiff’s lost profits claims in this case.”
Id.
-3-
The parties, then, both moved for summary judgment on the issue of liability. The
government filed its opening Motion for Summary Judgment on 25 October 2024. See Gov’t’s
Mot. for Summ. J. (“Gov’t’s MSJ”), ECF No. 158. Plaintiff filed its Cross-Motion for Summary
Judgment and Response on 2 December 2024. See Pl.’s Cross-Mot. for Summ. J. and Resp.
(“Pl.’s CMSJ”), ECF No. 162. The government filed its Reply to plaintiff’s Cross-Motion for
Summary Judgment and Response in Support of its Motion for Summary Judgment on 6 January
2025. See Gov’t’s Reply to Pl.’s CMSJ (“Gov’t’s Reply”), ECF No. 163. Plaintiff filed its
Reply in Support of its Cross-Motion for Summary Judgment on 21 January 2025. See Pl.’s
Reply in Support of Pl.’s CMSJ (“Pl.’s Reply”), ECF No. 164. The Court held oral argument on
the parties’ Cross-Motions for Summary Judgment on 3 April 2025 in Akron, Ohio. See 7 Feb.
2025 Order, ECF No 165.
III. Parties Arguments
The Court begins by summarizing the parties’ arguments regarding the alleged breach of
the Space Act Agreement (“SAA”) and the Patent License and then summarizes the parties’
arguments regarding the alleged breach of the implied duty of good faith and fair dealing for
both.
A. Parties’ Arguments Regarding the Alleged Breach of the Space Act
Agreement
The government, in its motion for summary judgment, argues it did not breach the SAA
because it satisfactorily performed all duties under Milestones 1 and 2 and did not need to
perform past Milestone 2 due to plaintiff failing to complete its payment prior to Milestone 3.
The government argues the “SAA explicitly and repeatedly required Spectre to pay in advance of
NASA’s efforts under the SAA.” Gov’t’s MSJ at 14 (citing App’x at 6). Specifically, the
government argues Spectre “was required to pay NASA at least the initial $100,000 payment and
the first $80,000 milestone payment for a total of $180,000 ‘prior to the start of Milestone 3,’”
but plaintiff “never paid the remaining $15,000 out of the first $80,000 milestone payment.” Id.
(first quoting App’x at 6; then quoting App’x at 90–91). As plaintiff never completed the
milestone payment, the government argues NASA was prevented from further performance
under the SAA and therefore could not have breached the SAA. Id. at 14, 22–23. The
government argues because plaintiff “fail[ed] to complete the $80,000 milestone payment
required prior to the start of Milestone 3 . . . , NASA never had any obligation to go beyond
completing Milestones 1 and 2.” Id. at 16.
The government further argues plaintiff cannot carry its burden to prove NASA breached
the SAA in its performance of Milestones 1 and 2. See Gov’t’s MSJ at 15. The government
argues “NASA’s performance for Milestones 1 and 2 occurred entirely within NASA pursuant to
the terms of the SAA.” Id. (citing App’x at 3–4). The government further argues plaintiffs
alleged breaches fail for three reasons: (1) NASA never reached the Milestone requiring
delivery, so NASA never had an obligation to deliver anything to Spectre; (2) NASA designed
the dies and wafer for Spectre under the SAA and Spectre did not present evidence to the
-4-
contrary; and (3) the “SAA provided only estimated time frames for the milestones” and were
not strict deadlines.” Id. at 16–18.
In response, Spectre argues while “the payment provisions cannot be gainsaid,” it “raises
the question of whether NASA had actually met the Milestone and earned the moneys previously
‘reimbursed’ in advance.” Pl.’s CMSJ at 12. Spectre claims, “NASA did not accomplish
Milestone 1 or 2 and was not entitled to be paid for in advance of Milestone 3 and 8” because
“NASA has presented no facts to establish that wafer DH0852-15 was actually designed and
fabricated for Spectre” and there is “much evidence to suggest it was not.” Id. at 12–14 (citing
Votypka Decl. ¶¶ 25–33). Specifically, plaintiff argues its “demonstrative exhibits regarding
DH08512-15 and Mr. Votypka’s observations” establish “the DH08512-15 wafer was not
purchased for the project” because “there is nothing in the traveler to tie the fabrication of this
wafer to Spectre’s project.” Pl.’s Reply at 7. Plaintiff asserts the government should have
provided testimony from Dr. Okojie explaining NASA performed the design and fabrication
work for Spectre. Id. at 6. Spectre also argues while “it cannot be denied” the SAA allowed
changes in the planned schedule upon notice, Spectre should not have to “assume[] NASA could
simply make change after change to the schedule for no reason . . . without employing
reasonable effort to comply with the schedule.” Pl.’s CMSJ at 12. Plaintiff claims “NASA’s
delays put Spectre in a horrible position, with the State of Ohio refusing to provide further funds
when Spectre could not demonstrate progress” and the government’s “suggestion that Spectre
can not now justify non-payment because NASA was then concealing” the use of “ancient
technology neither designed nor fabricated for Spectre” “is fanciful” and should not be allowed.
Pl.’s CMSJ at 14–15.
B. Parties’ Arguments Regarding the Implied Duty of Good Faith and Fair
Dealing of the Space Act Agreement
The government argues NASA did not breach any duty of good faith and fair dealing
under the SAA as a matter of law. Gov’t’s MSJ at 18. The government asserts “because the
SAA required Spectre to pay in advance of NASA’s efforts, Spectre’s refusal to complete the
$80,000 payment prior to the start of Milestone 3 meant that Spectre did not have any reasonable
expectations to NASA’s performance under Milestone 3 and beyond.” Id. at 19. The
government also argues the “benefit of the bargain works both ways, and Spectre’s refusal to
provide funding for NASA’s efforts to be performed in support of later milestones preclude any
reliance upon NASA’s performance of those later milestones.” Id. In the government’s view,
the “fact that Spectre never completed the payment due ‘prior to the start of Milestone 3’ . . . is
enough for the Court to reject Spectre’s arguments based on efforts contemplated under the SAA
further downstream.” Gov’t’s Reply at 8. The government contends, “[w]ithout a tether to a
contractual duty, Spectre’s good faith fair and dealing [argument] falls apart.” Id. at 8–9. In
response to Spectre’s accusation the government pulled a “bait-and-switch” by sending Spectre
an already-designed wafer instead of designing a new wafer, the government argues Spectre fails
to prove such a bait-and-switch: “to prove [a] bait-and-switch, Spectre must prove that NASA
made a material misrepresentation in its proposal with an intent to deviate from the proposal”
and “Spectre fails to allege, much less prove, any specific misrepresentation by NASA or the
requisite intent.” Id. at 10. The government argues “[w]hile Spectre was in ar[r]ears, its
assumption that NASA should have delivered sensor modules using dies from Fabrication Run
-5-
1[—]not due until Milestone 6[—]was unreasonable and at odds with the plain language of the
SAA,” and “it is further irrational for Spectre to turn its unreasonable assumptions into
allegations of fraud or bad faith by NASA.” Id. at 11.
In response, Spectre argues the government breached the implied duty of good faith and
fair dealing. While the government “raises the old argument that a breach of the duty of good
faith and fair dealing cannot be based on a contract that expressly covers certain matters,”
Spectre postulates, “[t]he point is that every contract, however[] detailed, has interstitial spaces
that must be filled in” by good faith and fair dealing. Pl’s CMSJ at 18. Spectre describes
multiple instances allegedly evident of the government’s breach of good faith and fair dealing:
“lying about [the] design and fabrication progress, stealing materials purchased for the Project to
use on other projects, using Grant funds to attend professional conferences, working a bait-and-
switch and foisting old technology on Spectre while representing it was designed and fabricated
specifically for Spectre, refusing to allow Spectre personnel to witness and videotape fabrication
steps, refusing to provide CAD files for mask preparation when the SAA clearly called for it,
delivering a handful of non-conforming pressure modules and then blaming their failure to
perform as specified on Spectre’s incompetence.” Pl.’s Reply at 9–10. Spectre further argues
NASA pulled a bait-and-switch by delivering, without prior explanation, “a handful of sensor
modules, only one of which was to specification and which Spectre discovered years later had
not been designed and fabricated to Spectre’s specifications, but had been designed and
fabricated years earlier for some other, unexplained purpose,” despite contracting to provide “a
total of 36 to 60 functional pressure sensor modules and hundreds of loose dies after the first
fabrication run, all of which had been designed and fabricated to Spectre’s specifications.” Id. at
10.
C. Parties’ Arguments Regarding the Alleged Breach of the Patent License
The government argues it did not breach the Patent License as a matter of law. See
Gov’t’s MSJ at 19. The government explains, according to the patent license, the government
may unilaterally terminate the license for any of the reasons in Article 19.4—including for
failure to submit reports—provided it notifies plaintiff at least 30 days in advance of the intended
termination. Id. at 20 (citing App’x at 43 (Patent License)). As plaintiff did not submit the
required reports, the government contends its “termination of the License plainly complied with
the License’s terms.” Id. The government additionally notes Spectre “concedes that NASA gave
notice on May 15, 2014 to terminate the License effective June 18, 2014 and identified Spectre’s
failure to comply with Articles 19.4(a), (b), and (d) as NASA’s reasons for the termination.” Id.
(citing Compl. ¶¶ 103, 150). The government further argues “Spectre’s alleg[ation] that NASA’s
May 15, 2014 notice to terminate the License effective June 18, 2014 gave no opportunity to
cure,” id. (citing Compl. ¶¶ 103, 150), “has no merit” because the Patent License only required
NASA to provide notice of terminations, id. (citing App’x at 43 (Patent License)).
While Spectre agrees “NASA followed the regulatory requirements for granting Spectre’s
License Application,” Spectre argues there “surely exists a genuine issue of material fact as to
whether the Project’s problems were the result of Spectre’s financial condition (which it denies)
or NASA’s subterfuge.” Pl.’s CMSJ at 13. Spectre also admits the Patent License requires
Spectre to submit periodic reports, but “suggests under the circumstances, it should be excused
-6-
from the Annual Report submittal requirement, which NASA used as a pretext to terminate
without notice.” Id. Despite plaintiff admitting it cannot carry its burden to prove NASA
breached the Patent License because “NASA’s notice of termination stated unconditionally that
it was terminating the Patent License as of a date certain,” Spectre maintains “the notice did not
allow that Spectre could attempt to show cause why the license should not be terminated.” Pl.’s
Reply at 13. Spectre further believes, “[r]egardless of what the Patent License itself said,
NASA’s notice was unconditional and allowed nothing,” which Spectre argues was a violation.
Id.
D. Parties’ Arguments Regarding the Implied Duty of Good Faith and Fair
Dealing of the Patent License
The government argues NASA did not breach any duty of good faith and fair dealing
under the Patent License as a matter of law. See Gov’t’s MSJ at 22. The government argues it
asserted “a legitimate contract right under the [Patent] License to terminate” and such a
termination “‘cannot be considered as violative of a duty of good faith and fair dealing.’” Id.
(quoting Scott Timber Co. v. United States, 692 F.3d 1365, 1375 (Fed. Cir. 2012)). The
government further argues “NASA in no way prevented Spectre from submitting its periodic
reports required by the License,” which resulted in a legitimate reason for NASA to terminate the
Patent License. Id. at 23. The government also asserts “Spectre must prove by clear and
convincing evidence that NASA lacked a rational basis for terminating the License,” but argues
Spectre “offers no proof to support its ‘suggest[ion] that under the circumstances, it should be
excused from’ the periodic reporting requirement.” Id. (quoting Pl.’s CMSJ at 13). The
government also argues Spectre did not “prove that NASA acted with an improper motive” in
terminating the license, so Spectre “failed again to carry its ‘heavy burden of proof’ to overcome
the presumption that public officials act conscientiously in the discharge of their duties in
terminating the license.” Gov’t’s Reply at 15.
In response, plaintiff argues “[w]hile in ordinary situations patent holder[s] may have no
relationship with the licensee, here Spectre and NASA were bound as collaborators in the Grant
Project and parties to the Space Act Agreement,” and “as such, reporting progress to NASA
would have been a pointless exercise because it would provide NASA with no more information
than it already had.” Pl.’s Reply at 13. In plaintiff’s view “while [the lack of reports] may have
given NASA a pretextual reason for terminating the License Agreement, it did not give NASA a
good-faith or rational reason for doing so.” Id. Specifically, Spectre argues termination of the
Patent License “was pretextual and in bad faith because the reason Spectre could not successfully
reduce to practice within three years was NASA’s delay, its refusal to transfer the CAD files for
fabrication masks and packaging information, and its refusal to perform further under the SAA.”
Id. Spectre further argues “NASA’s bad faith is especially egregious now that it is known that
through discovery NASA pulled a bait-and-switch, and that its real motivation for terminating
Spectre was because of threats from Meggit[—another patent licensee of NASA—]not to enter
into a multi-hundred thousand dollar Space Act Agreement with NASA unless NASA terminated
Spectre.” Id. at 13–14.
III. Applicable Law
-7-
As an initial matter, despite the parties disagreeing on the applicable law throughout the
briefing, the parties agreed on the law when asked at oral argument. See 3 April 2025 OA Tr.
(“Tr.”) at 5:19–6:13 (detailing party agreement on the standard for summary judgment); 6:14–
7:12 (detailing party agreement on the standard for breach of contract); 128:7–129:2 (detailing
the standard for breach of the implied duty of good faith and fair dealing). As such, the Court
details the applicable law for summary judgment, breach of contract, and breach of the implied
duty of good faith and fair dealing below.
A. Summary Judgment Standard
The Court may grant a motion for summary judgment “if the movant shows that there is
no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of
law.” RCFC 56(a). A court shall not grant summary judgment if “the dispute about a material
fact is ‘genuine.’” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). An issue is
considered genuine if the “evidence is such that a reasonable [fact finder] could return a verdict
for the nonmoving party.” Id. “In determining whether there is a genuine issue of material fact,
the trial court must assume that the evidence presented by the non-movant is credible and draw
all justifiable inferences therefrom in the non-movant’s favor.” Monon Corp. v. Stoughton
Trailers, Inc., 239 F.3d 1253, 1257 (Fed. Cir. 2001) (citing Anderson, 477 U.S. at 255). “‘Only
disputes over facts that might affect the outcome of the suit under the governing law will
properly preclude the entry of summary judgment.’” Id. (quoting Anderson, 477 U.S. at 248).
“Contract interpretation is a matter of law and thus is amenable to decision on summary
judgment.” Gov’t Sys. Advisors, Inc. v. United States, 847 F.2d 811, 812 n.1 (Fed. Cir. 1988);
see, e.g., NVT Techs. Inc. v. United States, 370 F.3d 1153, 1159 (Fed. Cir. 2004) (“The
interpretation of a contract . . . is a question of law”); H.B. Mac, Inc. v. United States, 153 F.3d
1338, 1345 (Fed. Cir. 1998) (discussing the same proposition).
The party seeking summary judgment bears the burden of establishing the absence of any
genuine issues of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 322–23 (1986). When
the moving party has met this burden, the burden shifts to the non-movant who must present
sufficient evidence to show a dispute over a material fact allowing a reasonable factfinder to rule
in its favor. Anderson, 477 U.S. at 256–57. The evidence does not need to be admissible, but
mere denials, conclusory statements, or evidence not significantly probative will not defeat
summary judgment. Celotex, 477 U.S. at 322–24.
B. Breach of Contract
To establish a breach of contract claim, plaintiff must show a valid contract between
parties, an obligation or duty arising from the contract, breach of that duty, and damages caused
by that breach. San Carlos Irrigation & Drainage Dist. v. United States, 877 F.2d 957, 959
(Fed. Cir. 1989). A court must consider the contract as a whole and interpret it as to harmonize
and give reasonable meaning to all its parts. See McAbee Constr., Inc. v. United States, 97 F.3d
1431, 1434–35 (Fed. Cir. 1996); Gould, Inc. v. United States, 935 F.2d 1271, 1274 (Fed. Cir.
1991) (quoting Arizona v. United States, 575 F.2d 855, 863 (Ct. Cl. 1978)) (“‘[P]rovisions of a
contract must be so construed as to effectuate its spirit and purpose . . . an interpretation which
gives a reasonable meaning to all of its parts will be preferred to one which leaves a portion of it
-8-
useless, inexplicable, inoperative, void, insignificant, meaningless, superfluous, or achieves a
weird and whimsical result.’”). If a contract’s “provisions are clear and unambiguous, they must
be given their plain and ordinary meaning, and the court may not resort to extrinsic evidence to
interpret them.” McAbee, 97 F.3d at 1435 (cleaned up). “To permit otherwise would cast ‘a
long shadow of uncertainty over all transactions’ and contracts.” Id. (quoting Trident Ctr. v.
Connecticut Gen. Life Ins. Co., 847 F.2d 564, 569 (9th Cir. 1988)). “The general rule is that
extrinsic evidence will not be received to change the terms of a contract that is clear on its face.”
Beta Sys., Inc. v. United States, 838 F.2d 1179, 1183 (Fed. Cir. 1988) (citing SCM Corp. v.
United States, 675 F.2d 280, 284 (Ct. Cl. 1982)).
C. Breach of the Implied Duty of Good Faith and Fair Dealing
“Every contract, including one with the federal government, imposes upon each party an
implied duty of good faith and fair dealing in its performance and enforcement.” Dobyns v.
United States, 915 F.3d 733, 739 (Fed. Cir. 2019) (citing Metcalf Const. Co., Inc. v. United
States, 742 F.3d 984, 990 (Fed. Cir. 2014)). “A party breaches the contract when it fails to abide
by this implied duty, which includes ‘the duty not to interfere with the other party’s performance
and not to act so as to destroy the reasonable expectations of the other party regarding the fruits
of the contract.’” Id. (quoting Centex Corp. v. United States, 395 F.3d 1283, 1304 (Fed. Cir.
2005)); see also Restatement (Second) of Contracts § 205 cmt. d (stating potential breaches of
the implied duty of good faith and fair dealing include “evasion of the spirit of the bargain, lack
of diligence and slacking off, willful rendering of imperfect performance, abuse of a power to
specify terms, and interference with or failure to cooperate in the other party’s performance”).
“Cases in which the government has been found to violate the implied duty of good faith
and fair dealing typically involve some variation on the old bait-and-switch.” Precision Pine &
Timber, Inc. v. United States, 596 F.3d 817, 829 (Fed. Cir. 2010). A “bait-and-switch” consists
of two steps: (1) “the government enters into a contract that awards a significant benefit in
exchange for consideration;” and (2) “the government eliminates or rescinds that contractual
provision or benefit through a subsequent action directed at the existing contract.” Id.
IV. Analysis of Whether NASA Breached the Space Act Agreement
The Court analyzes whether NASA breached the SAA by examining: (1) whether NASA
was required to perform work past Milestone 2 based on the payments Spectre completed; (2)
whether the timelines for work in the SAA could be changed; (3) when the SAA required
delivery; and (4) whether NASA completed Milestones 1 and 2 of the SAA.
A. Whether Spectre’s Non-Payment Prevented NASA from Performing Work
Past Milestone 2 Under the SAA
Spectre contrives an assortment of grievances in an effort to distract the Court from
NASA’s basic right to receive funding in advance for any work under the SAA. The government
argues despite the many grievances Spectre asserts, NASA did not breach the SAA as a matter of
law because Spectre failed to complete the Milestone payments as required, which prevented
NASA from further performance under the SAA. Gov’t’s MSJ at 13. The government argues
-9-
the SAA “explicitly and repeatedly required Spectre to pay in advance of NASA’s efforts under
the SAA” because according to the SAA, “‘[p]ayment must be made by [Spectre] in advance of
initiation of NASA’s efforts . . . . NASA will not provide services or incur costs beyond the
available funding amount.’” Id. at 14 (quoting App’x at 6 (SAA Article 6)).
The government further argues “Spectre can no longer avoid the fact that it failed to pay
the Milestone payment as required by the SAA” because there “is no longer any disagreement on
the facts”—under the SAA, “Spectre was required to pay NASA at least the initial $100,000
payment and the first $80,000 milestone payment for a total of $180,000 ‘prior to the start of
Milestone No. 3,’” and “Spectre never paid the remaining $15,000 out of the first $80,000
milestone payment.” Id. at 13–14 (citations omitted). In the government’s view, “[s]atisfication
of the $80,000 milestone payment was . . . a condition precedent to NASA starting to work on
Milestone 3.” Id. at 14 (citing Restatement (Second) Contracts § 225(1)). The government
concludes “NASA’s inability to complete Milestones 3–6 under the SAA faithfully adhered to
the terms of the SAA.” Id. at 15.
Despite admitting “the payment provisions [of the SAA] cannot be gainsaid,” Pl.’s CMSJ
at 12, Spectre argues the “SAA in plain language states that each Milestone begin with the
complet[ion] of the activities for a previous Milestone, which presumably had been paid for in
advance,” Pl.’s Reply at 8. Spectre asserts “NASA’s full performance of the SAA contemplated
that NASA would actually be performing the work upon which those payments had been made
before seeking additional payment.” Pl.’s CMSJ at 9 (citing Decl. of Jack Keller ¶ 4, ECF No.
162-6). Spectre, therefore, asserts it “completely agrees with the government’s statement . . .
that ‘in essence’ Spectre is asking the Court to find that the SAA required payment after the
completion of Milestone 2 rather than ‘as its explicit language states,’ prior to the start of
Milestone 3 because that is a distinction without a difference: Milestone 3 starts with the
completion of Milestone 2.” Pl.’s Reply at 9. Spectre admits it “is well aware of the contractual
requirement that NASA be paid in advance, but that does not mean NASA did not have to earn
its fees.” Id. at 4. In Spectre’s view, “[t]he [g]overnment further argues—somewhat
disingenuously—that Spectre cannot force NASA to ‘earn’ its contract payments as ‘predicate’
for future payments because NASA must be paid in advance” is not correct because “Spectre did
not argue that NASA had to prove it had performed work before it could be paid for that work[;]
it argued [instead] that NASA had to prove it had performed the work for which Spectre had
already paid before qualifying for another pre-payment.” Id.
In interpreting the contract, the court begins with the contract’s plain language, McAbee
Const. Inc. v. United States, 97 F.3d 1431, 1435 (Fed. Cir. 1996) (citations omitted), and gives
unambiguous contract terms their plain and ordinary meaning, Landmark Land Co., Inc. v. Fed.
Deposit Ins. Corp., 256 F.3d 1365, 1373 (Fed. Cir. 2001) (citations omitted). Article 5 of the
SAA entitled “Financial Obligations” provides for Spectre’s payment obligations:
1. Partner agrees to reimburse NASA a total estimated cost of $428,335.00 for
NASA to carry out is responsibilities under this agreement. . . . Payment must be
made by Partner in advance of initiation of NASA’s efforts.
- 10 -
Spectre Corp. agrees to pay NASA GRC $100,000 prior to initiation of work under
this agreement, and as follows:
$80,000.00 prior to the start of Milestone No. 3 and
$80,000.00 prior to the start of Milestone No. 8 and
$168,335.00 prior to the start of Milestone No. 11.
Advance payments shall be scheduled to ensure that funds are resident with NASA
before Federal obligations are incurred in support of this agreement.
....
3. NASA will not provide services or incur costs beyond the available funding
amount. Although NASA has made a good faith effort to accurately estimate its
costs, it is understood that NASA provides no assurance that the proposed effort
under this Agreement will be accomplished for the above estimated amount.
Should the effort cost more than the estimate, Partner will be advised by NASA as
soon as possible. Partner shall pay all costs incurred and have the option of
canceling the remaining effort, or providing additional funding in order to continue
the proposed effort under the revised estimate. Should this Agreement be
terminated, or the effort completed at a cost less than the agreed-to estimated cost,
NASA shall account for any unspent funds within One (1) year after completion of
all effort under this Agreement, and promptly thereafter, return any unspent funds
to Partner.
4. Notwithstanding any other provision of this Agreement, all activities under or
pursuant to this Agreement are subject to the availability of funds, and no provision
of this Agreement shall be interpreted to require obligation or payment of funds in
violation of the Anti-Deficiency Act, Title 31 U.S.C. § 1341.
App’x at 6–7 (SAA Article 5) (emphasis added).
As an initial matter, Article 5 does not state NASA needs to “earn its fees,” as suggested
by Spectre. See Pl.’s Reply at 4 (“Spectre is well aware of the contractual requirement that
NASA be paid in advance, but that does not mean NASA did not have to earn its fees.”). In fact,
Spectre confirmed at oral argument it was required to make all payments under the SAA “in
advance of NASA’s efforts.” See Tr. at 73:10–14 (“[THE COURT:] All payments were to be
made by Spectre to NASA under the Space Act Agreement, ‘in advance of NASA’s efforts.’
[PLAINTIFF:] That’s correct.”). Additionally, when pressed at oral argument on whether
“anything in the Space Act Agreement . . . requires the [g]overnment to have proven it has
earned its fees prior to the deliverable in Milestone 6,” plaintiff admitted “[n]o, there’s nothing
that requires it to prove it.” See Tr. at 84:19–85:9. Spectre further admitted at oral argument it
had to pay the $80,000 prior to the start of Milestone 3 for NASA to begin work on Milestone 3
and beyond. See Tr. at 81:11–14 (“THE COURT: Under the contract, the $80,000 had to be
paid by Milestone 4 in order for NASA to start working on Milestone 3. [PLAINTIFF:] Yes.”).
As such, under the plain language of Article 5—which controls Spectre’s payment
responsibilities—Spectre was required to make all payments to NASA prior to any work being
performed and NASA was not required to “earn its fees.” See McAbee, 97 F.3d at 1434–35
- 11 -
(cleaned up) (“If the contract’s provisions are clear and unambiguous, they must be given their
plain and ordinary meaning.”).
Notably, Spectre does not dispute the amount it was supposed to pay NASA under the
SAA. See Tr. at 73:15–74:9 (detailing Spectre admitting, based on the payment schedule in
Article 5, it was to pay NASA $100,000 up front and $80,000 prior to the start of Milestone 3).
While plaintiff agrees Article 5 provides for the payments Spectre was to make under the SAA,
Spectre maintains NASA had to “earn its fees.” See Pl.’s CMSJ at 8–9. As discussed supra, the
Court already determined the SAA’s plain language placed no “earn its fees” requirement on
NASA; rather, the SAA only required Spectre to pay NASA a total of $180,000 prior to the start
of Milestone 3. See App’x at 6 ($80,000.00 prior to the start of Milestone No. 3”); see McAbee,
97 F.3d at 1434–35 (cleaned up) (“If the contract’s provisions are clear and unambiguous, they
must be given their plain and ordinary meaning.”).
As the SAA required Spectre to pay NASA a total of $180,000 prior to the start of
Milestone 3, the Court now analyzes whether Spectre’s actual payments prevented NASA from
further performance under the SAA. At oral argument, Spectre agreed it had only paid NASA
$165,000 under the SAA, and agreed it was $15,000 short of what was due prior to the start of
Milestone 3. See Tr. at 74:7–17 (“[THE COURT:] So the total [paid] under the Space Act
Agreement was [$]165,000? [PLAINTIFF:] Right. . . . THE COURT: So just to confirm,
Spectre was $15,000 short of what was due prior to the start of Milestone 3? [PLAINTIFF:]
That’s correct.”). The government argues because Spectre failed to complete the payments prior
to the start of Milestone 3, NASA was prevented from further performance under the SAA. See
Gov’t’s MSJ at 22–23. As established supra, the SAA required Spectre to pay in advance for all
of NASA’s initiatives, and NASA therefore could not have continued work under the SAA
without receiving payment. When pressed on this fact at oral argument, Spectre capitulated
“under the four corners” of the SAA it had to complete the payments for NASA to begin work
under Milestone 3. See Tr. at 79:3–17 (“THE COURT: But at the end of the day, under the four
corners of the contract, . . . Spectre had to complete the payments in order to begin Milestone 3?
[PLAINTIFF:] Yes, it did.”). As such, under the plain language of the SAA, NASA was not
required to complete any work beyond Milestone 2 because Spectre failed to make the payments
as required. See McAbee, 97 F.3d at 1434–35 (cleaned up) (“If the contract’s provisions are
clear and unambiguous, they must be given their plain and ordinary meaning.”).
Having established the plain language of the SAA required Spectre to make all payments
prior to NASA performing work and Spectre did not complete the required payments under the
SAA, the Court analyzes whether Spectre had a contractual reason to not complete its payment
obligations. The fact Spectre never completed the $80,000 payment due “prior to the start of
Milestone 3” as required by the SAA, is no longer in dispute—Spectre paid NASA $165,000
under the SAA. Compare Spectre Corp. v. United States, 132 Fed. Cl. 626, 628 (2017) (denying
the government’s Motion to Dismiss for lack of payment because “the parties disagreed as to the
amount Spectre paid NASA under the Space Act Agreement”); with Tr. at 74:7–9 (“[THE
COURT:] So the total [paid] under the Space Act Agreement was [$]165,000? [PLAINTIFF:]
Right.”). Spectre, as discussed supra, was therefore $15,000 short on the pre-Milestone 3
payment. See Tr. at 74:14–17. When pressed at oral argument on why Spectre did not pay the
additional $15,000 owed under the SAA, Spectre explained it became “frustrated” with NASA’s
- 12 -
lack of deliverables but recognized there was nothing in the SAA to excuse payment. See Tr. at
85:10–22 (“THE COURT: [I]n an email from Spectre[—]this was Spectre Exhibit 4944.
Spectre said, ‘We will not pay one dime more till 90 percent of deliverables in sensors on-site
training of one-run scrap are completed.’ [PLAINTIFF:] Oh yes. My client got a little excited
when he wrote that . . . . [THE COURT:] And fully utilized the shift key for capitalization, too . .
. . Is there any basis in the Space Act Agreement to support that requirement? [PLAINTIFF:]
No.”). Spectre also explained it “didn’t have the money,” despite having received “upwards of
$900,000 from the State of Ohio,” because Spectre had to pay for other operating costs. See Tr.
at 76:8–77:7, 90:20–24 (“[THE COURT:] [I]s there any reason why Spectre did not simply
complete paying the $15,000 before Milestone 3? [PLAINTIFF:] It didn’t have the money . . . .
They had opened a factory in Ohio . . . . They were operating and . . . they had started with
totally new employees who they trained to build these completed sensor units. And the State of
Ohio had recognized that part of the funds could be used for training new employees because . . .
that was part of the purpose of the grant, . . . to have new employees doing things, new things
that would increase the tax base.”). Spectre’s choice to use the money from the State of Ohio for
general operating costs, however, was its choice—and did not excuse Spectre from making the
required payments under the SAA because the money was meant to go to NASA. See Tr. at
78:6–19. In fact, NASA originally wanted the full amount, $428,335.00, for work under the
SAA up front, but agreed to a payment plan to benefit Spectre. See Tr. at 89:20–90:5 (“THE
COURT: Under the original terms of the contract, Spectre was required to pay the entire
estimate cost, but then NASA agreed to . . . payment steps? [PLAINTIFF:] NASA started off
wanting all the money up front. That’s true . . . . THE COURT: NASA agreed to a payment
schedule that would benefit [Spectre]? [PLAINTIFF:] Well, right.”). Thus, Spectre failed to
provide a contractual reason for not completing its payment obligations required by Article 5 of
the SAA—it only had an out-of-contract reason for not completing the payments.
Spectre acknowledged it was not a breach of the SAA for NASA to require payment prior
to the start of Milestone 3. See Tr. at 86:23–87:2 (“[THE COURT:] Was NASA’s requirement
for payment a breach of the Space Act Agreement? [PLAINTIFF:] No.”). As Spectre failed to
complete the required payments under the SAA, and Spectre was to pre-pay for all of NASA’s
work, see App’x at 6 (“Payment must be made by [Spectre] in advance of initiation of NASA’s
efforts.”), the Court agrees with the government NASA was not required to perform any work
past Milestone 2 under the plain language of the SAA. See Tr. 83:22–84:14 (“[THE COURT:]
NASA did not move on to Milestone 3 or beyond because Spectre did not meet the Space Act
Agreement payment obligations.” [GOVERNMENT:] That’s correct. And just the funds were
exhausted. . . . [THE COURT:] And just to confirm, the [g]overnment believes that NASA was
excused from contemplating anything past Milestone 2 because of Spectre’s incomplete
payment? [GOVERNMENT:] That’s correct. Because the SAA Article 5 says. ‘The payments
shall be made in advance of any NASA efforts.”); see also McAbee, 97 F.3d at 1434–35 (cleaned
up) (“If the contract’s provisions are clear and unambiguous, they must be given their plain and
ordinary meaning.”).
B. Whether Delays in the Timeline Were Permissible Under the SAA
The parties dispute whether the change in the SAA’s timeline was allowed under the
SAA. Spectre argues NASA should have abided by the SAA’s timelines as detailed in Article 4
- 13 -
entitled “Schedules and Milestones.” See Pl.’s Reply at 5–6. Despite Spectre recognizing the
“SAA allow[ed] NASA to change the planned schedule upon notice,” Spectre argues the
language allowing for a change in the schedule “must be interpreted to allow NASA reasonable
extensions for legitimate reasons.” Id. at 9. Spectre agrees NASA giving notice “its MEMS
laboratory would be closed for a month in late 2012 and that no deep reactive ion etching could
be performed, and that it would be closed during the [g]overnment shutdown which began on
October 1, 2013 . . . . were reasonable, unavoidable delays . . . . But NASA never gave notice or
explanation as to delays that caused the project to lag far behind the Grant Schedule.” Id. The
government argues the SAA “provided only estimated time frames for the milestones.” Gov’t’s
MSJ at 17 (citing App’x at 5 (SAA Schedules and Milestones)). The government emphasizes the
SAA “explicitly stated that any schedule or milestone therein was based upon the parties’
‘understanding of the projected availability of NASA personnel, facilities and equipment.’” Id.
(citing App’x at 7 (SAA Priority of Use)). The government argues the SAA “required only that
Spectre ‘shall be given reasonable notice of that change.’” Id. (citing App’x at 7 (SAA Priority of
Use)). In the government’s view, “any estimated schedule was voided once Spectre failed to pay
according to the SAA.” Id. (citing App’x at 6–7 (SAA Financial Obligations))
(“Notwithstanding any other provision of this Agreement, all activities under or pursuant to this
Agreement are subject to the availability of funds.”). The government argues “Spectre’s
difficulties starting in August 2012 in paying the first $80,000 milestone payment, even in
installments, undermine any contention it has that NASA breached the SAA by any delay.” Id.
In interpreting the contract, the Court begins with the contract’s plain language, McAbee
Const. Inc. v. United States, 97 F.3d 1431, 1435 (Fed. Cir. 1996) (citations omitted), and gives
unambiguous contract terms their plain and ordinary meaning, Landmark Land Co., Inc. v. Fed.
Deposit Ins. Corp., 256 F.3d 1365, 1373 (Fed. Cir. 2001) (citations omitted). When interpreting
a contract, the document must be considered as a whole and interpreted to harmonize and give
reasonable meaning to all its parts. See McAbee, 97 F.3d at 1434–35. Article 4 of the SAA
entitled “Schedule and Milestones” provides for the original timeline contemplated by the
parties:
ARTICLE 4. SCHEDULE AND MILESTONES
The planned major milestones for the activities defined in the “Responsibilities”
clause are as follows:
1. NASA completes Pressure Sensing end of Month 3 from
Element Design signing
2. NASA completes Wafer Fabrication end of Month 3 from
signing
3. NASA completes Sensing Element Test end of Month 5 from
signing
4. NASA completes Header Fabrication and end of Month 5 from
Assembly signing
- 14 -
5. NASA completes Pressure Sensing Module end of Month 6 from
Functional Test signing
6. NASA delivers Fabrication Run 1 Sensors end of Month 6 from
to Spectre signing
App’x at 5 (SAA Schedule and Milestones). Article 6 of the SAA entitled “Priority of Use”
allows for changes to the schedule and explains “[a]ny schedule or milestone in this Agreement
is estimated based upon the Parties’ current understanding of the projected availability of NASA
personnel, facilities and equipment” and “[i]n the event that NASA’s projected availability
changes, [Spectre] shall be given reasonable notice of that change, so that the schedule and
milestones may be adjusted accordingly.” App’x at 7 (SAA Priority of Use) (emphasis added).
Article 5, as discussed supra, further provides “[n]otwithstanding any other provision of this
Agreement, all activities under or pursuant to this Agreement are subject to the availability of
funds.” App’x at 6–7 (SAA Financial Obligations).
As the Court must consider the document as a whole and interpret to harmonize and give
reasonable meaning to all its parts, see McAbee, 97 F.3d at 1434–35, the Court must look at all
the various Articles relied upon by the parties to determine whether the SAA’s timeline was
rigid. Under the plain language of the Articles, while the SAA provided a timeline for work
under the SAA, the timeline was based upon NASA’s availability to perform the work. See
supra. Additionally, the SAA allowed for changes in the schedule upon notice of the change.
See supra. The work to be performed under the timeline, however, is subject to the availability
of funds because, as discussed supra, Spectre was required to pre-pay for all work performed by
NASA. Spectre even admitted the Schedule and Milestones in Article 5 were only estimates and
not strict requirements in the contract. See Tr. at 73:3–8 (“[THE COURT:] [A]t the end of the
day, Article [4], Schedule and Milestones, these were just estimates. It was not strict
requirements in the contract. [PLAINTIFF:] That’s correct.”). As such, under the plain
language of the SAA, the timeline was an estimate—subject to change—and not a strict
requirement in the contract. See McAbee, 97 F.3d at 1434–35 (cleaned up) (“If the contract’s
provisions are clear and unambiguous, they must be given their plain and ordinary meaning.”).
Having determined the timeline for work to be performed under the SAA was subject to
change with proper notice, the Court analyzes whether the delays constituted breach of contract.
To begin, Spectre noted at oral argument there were delays from the beginning and “the initial
delays were in negotiating and putting these contracts in place after the grant was awarded.” Tr.
at 13:6–13. Before even signing the SAA, Spectre was aware delaying payment would result in
NASA’s performance also being delayed. See Tr. at 45:18–46:7 (“[GOVERNMENT:] [I]n the
submissions to that were provided to the Court, [prior to oral argument,] . . . Spectre knew back
before the Space Act [Agreement] was signed . . . [according to] an email dated October 17th[,
2011] . . . Spectre [was] pleading with the State of Ohio. They had said to the state of Ohio that,
per our conversation with NASA, any delays in NASA funding can dramatically delay the Space
Act Agreement and delivery of prototypes due to scheduling conflicts in their laboratories . . . . It
shows that Spectre knew . . . if they delayed their payments, they would delay NASA’s
activities.”). Spectre, therefore, knew a delay in payment would result in a delay of work under
the SAA, and as such, Spectre should have known failing to complete the payment before
- 15 -
Milestone 3, see supra Section IV.A, would delay the original SAA timeline. This is further
supported by the email records Spectre’s counsel submitted to the Court prior to oral argument, 2
demonstrating Spectre’s continuous delay of payments to NASA—ultimately delaying NASA’s
performance. See Tr. at 116:24–120:8 (“[THE COURT:] These were emails that [Spectre’s
Counsel] attached on 31 March [to the Court]. So there was an email . . . from Robert
Kistemaker, October 1st, 2012. The subject there is, ‘Important considerations on
Spectre/NASA Collaboration Agreement.’ And it begins, ‘Today is October 1st, 2012. NASA
GRC still has not received any monies from your firm under the Space Act Agreement to
proceed with ongoing work.’ . . . So that email seems to contemplate and explicitly says that
[NASA] asked for the entire amount of $80,000. And then there’s further emails as we get into
2013, where it seems like between October of 2012 and then January of 2013 where things were
paid . . . So did NASA get paid the $80,000? [GOVERNMENT:] NASA never got paid the full
[$]80,000. THE COURT: So October 1st, 2012, NASA is demanding money due and says
amount [due] by October 5th, 2012, did NASA get that? [GOVERNMENT:] NASA got, on
October 10th, 2012, $30,000. . . . [THE COURT:] ‘So per the below email traffic, as a courtesy
on August 20th, 2012, NASA GRC offered a stretch-out payment plan to accommodate Spectre.
We now rescind that offer and ask for the entire amount of $80,000 by Friday, October 5th,
2012.’ . . . ‘We will have to stop all work if no payment received.’ [GOVERNMENT:] [U]pon
receiving only [$]30,000, NASA went ahead and continued. . . . THE COURT: So then if we
fast forward to January 4th, 2013, another email says, ‘Our NASA Space Agreement is about to
run out of funds. As accounting records show there’s less than $1,500 on account for Dr. Okojie
labor.’ So there is a formal notice. But Spectre . . . was in debt. . . . [GOVERNMENT:] [A]s of
that date [Specter was] still owing [$50,000]. And then on . . . January 7th, [Spectre] pa[id] only
$20,000 towards that [$]50,000.”).
While the government was not able to point the Court to a specific email informing
Spectre it was deficient on the $80,000 payment due prior to the start of Milestone 3, the
government relied on Spectre’s submissions to demonstrate NASA was continually seeking
payment from Spectre to continue work under the SAA. See Tr. at 122:7–13
(“[GOVERNMENT:] Other than just email[s] like this one, just requesting continued payment
from Spectre, I don’t believe there was a formal letter to inform Spectre that they are deficient.”).
Despite NASA continually seeking payment from Spectre—and Spectre having received the
funds from the State of Ohio to pay NASA—Spectre never completed the required payment and
contributed to delay. See Tr. at 96:17–23 (“[GOVERNMENT:] [T]he evidence, especially the
audit from the State of Ohio, shows that Spectre actually received . . . pre-reimbursement from
the State of Ohio that . . . Spectre should have paid NASA, but they didn’t.”). As such, there was
no breach from NASA’s delayed performance because under the plain language of the SAA
NASA was not required to perform any work without the appropriate funds—meaning NASA
could not continue to perform without payment from Spectre. See McAbee, 97 F.3d at 1434–35
(cleaned up) (“If the contract’s provisions are clear and unambiguous, they must be given their
plain and ordinary meaning.”); San Carlos Irrigation & Drainage Dist. v. United States, 877
F.2d 957, 959 (Fed. Cir. 1989).
2
While these email submissions were not included in summary judgment briefing, they were part of the record and
included Bates Numbers. Additionally, the email submissions were extensively discussed and quoted at oral
argument without objection by the parties, and the parties were intimately familiar with the email submissions.
- 16 -
C. When Delivery Was Contemplated Under the SAA
The parties initially disputed whether the Space Act Agreement reached a point where
delivery by NASA was required. Compare Pl.’s CMSJ at 6 (“Although [NASA] continued to
report fabrication of the first wafer, testing, and shipment to its subcontractor for packaging and
testing, NASA failed to make delivery within promised durations and no reason was ever
given.”), with Gov’t’s MSJ at 16 (“NASA’s first obligation to deliver to Spectre any sensors and
necessary data to reproduce the sensors in Milestone 6 never came due.”). At oral argument,
however, the parties agreed delivery was not contemplated or required by the SAA until
Milestone 6. See Tr. at 60:5–19 (“[THE COURT:] The delivery was contemplated at Milestone
6. [PLAINTIFF:] Right.”); 72:19–22 (“[THE COURT:] NASA actually had no delivery
obligation until Milestone 6? [GOVERNMENT:] Exactly.”). The SAA also supports delivery
was not required under the SAA until Milestone 6: under Article 3 of the SAA entitled
“Responsibilities,” the first time “delivery” is contemplated is under the responsibilities for
Milestone 6. See App’x at 4 (SAA Responsibilities) (“NASA will deliver a minimum of 36 die
mounted onto headers that meet minimum specifications . . . NASA will deliver a report to
Spectre . . . NASA will provide all data . . . NASA will share data . . . .”). Likewise, Article 4 of
the SAA provides “NASA delivers Fabrication Run 1 Sensors to Spectre” in Milestone 6. See
App’x at 5 (SAA Schedule and Milestones). Based on the parties’ agreement and the plain
language of the SAA, the Court determines the SAA did not require delivery by NASA until
Milestone 6. See McAbee, 97 F.3d at 1434–35 (cleaned up) (“If the contract’s provisions are
clear and unambiguous, they must be given their plain and ordinary meaning.”).
Despite delivery not being required until Milestone 6, and NASA only being required to
complete Milestones 1 and 2 because of Spectre’s payments, see supra Section IV.A, NASA
made several out of contract deliveries to accommodate Spectre. To begin, “Spectre had
expressed to NASA that they needed package[d] sensors early to test their system[s]” and were
“demanding a lot of packaged sensors . . . even though those efforts were not due yet under the
Space Act Agreement.” Tr. at 64:7–16. Spectre, despite acknowledging it was not “expecting
delivery,” was “hoping for” and demanding delivery from NASA. See Tr. at 60:21–61:3 (“[THE
COURT:] So at this point, assuming that we’re in Milestone 1 and Milestone 2, your client
would not expect anything. [PLAINTIFF:] Well, [it] wasn’t expecting delivery, but [it] was
hoping for delivery because the goal [of the SAA] was to get . . . things designed, get them made,
and get them out into the market because this was a commercialization project, and time is
money.”). Spectre even made requests for premature delivery from NASA. See Tr. at 68:16–
69:25 (“[THE COURT:] [W]as there an additional request from Spectre? . . . [PLAINTIFF:]
[Y]es. Because of the delays, they did ask. . . . [THE COURT:] Did Spectre ask for [completed
sensor modules] prematurely? [PLAINTIFF:] They asked if there was any way that NASA
could provide something for them to use for testing of the electric boards that they were
developing because they didn’t have anything to test the boards with.”). Spectre further clarified
it understood delivery was not yet required under the SAA but had become frustrated with
NASA and requested delivery. See Tr. at 79:1–12 (“[PLAINTIFF:] Well, part of the
problem . . . was that my client was getting very frustrated with the fact that NASA was not
[making progress] and [Spectre] know[s] that . . . the delivery hadn’t come up.”).
- 17 -
In an attempt to accommodate Spectre’s early delivery demands, NASA had to expend
funds from the money Spectre already paid. See Tr. at 70:12–19 (“THE COURT: [H]ow much
money did the [g]overnment spend in order to early accommodate? . . . [GOVERNMENT:]
[B]ased on the package[d] sensors that were provided . . . . That would have been $15,000.”).
While NASA acknowledged this cost was not much compared to the money Spectre already
paid, the funds were depleting because Spectre was not paying as they were required under the
SAA. See Tr. at 70:20–71:2 (“[THE COURT:] But that’s not much compared to how much had
been paid by Spectre, right? [GOVERNMENT:] It was not much, . . . [but] at that point,
[NASA] was really just scraping by with a few thousand dollars here and there. And that was
what made [the] work very difficult because [NASA] did not have sufficient funding to continue
[the] work.”). Despite depleting funds, NASA delivered sensors to be tested and packaged, see
Tr. at 114:9–12 (“[THE COURT:] NASA also did send sensors to Sienna Technologies for
testing and packaging, correct? [GOVERNMENT:] Yes.”), and gave Spectre pre-fabricated
dies to allow Spectre to begin testing, see Tr. at 69:23–70:1 (“[PLAINTIFF:] [NASA] gave
[Spectre] an old[—]and this was known to be an old sensor that was mounted and packaged.
And [NASA] gave that to [Spectre] to use for testing to develop the electric boards.”). NASA
believes, “in retrospect,” making early deliveries at the request of Spectre was a “bad idea” but
was just “trying to be cooperative.” See Tr. at 71:17–22; see also Tr. at 68:10–16
(“[GOVERNMENT:] [These deliveries were] an additional requirement or request from Spectre.
So . . . those sensors that were delivered early were not strictly part of the milestones. It was just
an effort that was made to accommodate Spectre.”).
Despite NASA making early, out-of-contract deliveries and exhausting the SAA’s funds
at Spectre’s request, Spectre maintains the deliveries violated the SAA because they were not
“fabricated and designed” for Spectre. See Tr. at 111:2–14 (“THE COURT: What language of
the Space Act Agreement would [sending pre-fabricated dies] violate? [PLAINTIFF:] The
language that says, ‘For the money it’s being paid, NASA will design and fabricate dies to
Spectre’s specifications,’ which [means] sending them something that was not designed to and
fabricated to their specification . . . breaches the agreement.”). The government, however,
argues the SAA does not prohibit NASA from “using old dies for those extra packaged sensors
sent to Spectre.” See Tr. at 110:13–18 (“[GOVERNMENT:] But for the . . . additional
package[d] sensors that were sent prior to Milestone 4 and Milestone 6, there’s nothing in the
SAA to prohibit NASA from using old dies for those extra packaged sensors sent to Spectre
because those were not required by the SAA.”). In fact, at oral argument, Spectre agreed it was
not an issue for NASA to make out-of-contract deliveries and use old dies to accommodate
Spectre’s requests. See Tr. at 113:24–114:8 (“[THE COURT:] If NASA was not required to
deliver anything until Milestone 6, how is it problematic that NASA delivered something prior to
being required? [PLAINTIFF:] It’s not problematic.”). Delivery was not required prior to
Milestone 6, and Spectre did not complete payments to allow work progression past Milestone 2,
see supra Section IV.A, so the out-of-contract deliveries made by NASA are not a breach of the
SAA. See McAbee, 97 F.3d at 1434–35 (cleaned up) (“If the contract’s provisions are clear and
unambiguous, they must be given their plain and ordinary meaning.”); San Carlos Irrigation &
Drainage Dist. v. United States, 877 F.2d 957, 959 (Fed. Cir. 1989).
D. Whether NASA Completed Milestones 1 and 2 of the SAA
- 18 -
Having established the SAA only progressed to the end of Milestone 2, see supra Section
IV.A, the Court next analyzes what NASA was required to complete during Milestones 1 and 2
under the SAA and examines whether NASA completed those Milestones.
1. SAA Requirements Under Milestones 1 and 2
Milestone 1 of the SAA was “Pressure Sensing Element Design,” and required NASA to
“define the necessary wafer processing steps to yield desired performance in each of three
pressure ranges stated” in the SAA (i.e., 0–150 psi, 0–500 psi, and 0–1000 psi). App’x at 3
(SAA Responsibilities). The parties do not dispute what was required under Milestone 1 and
confirmed at oral argument Milestone 1 was the “design phase,” which required NASA to
“define the necessary wafer processing steps.” See Tr. at 40:5–7 (“[PLAINTIFF:] Milestone 1
is completion of the sensor design work.”); 44:10–14 (“[THE COURT:] Milestone 1 . . . was
[the] design paragraph. . . . [GOVERNMENT:] Yes.”). Accordingly, Milestone 1 required
NASA to complete the design for the wafer and define the necessary wafer processing steps. See
McAbee, 97 F.3d at 1434–35 (cleaned up) (“If the contract’s provisions are clear and
unambiguous, they must be given their plain and ordinary meaning.”).
Milestone 2 was for “Wafer Fabrication” wherein:
NASA will fabricate one or more boron-doped silicon carbide wafers as necessary
to meet delivery of a minimum of 12 and maximum of 20 finished pressure sensing
modules for each of three pressure ranges. NASA will record process steps, masks,
and other data as necessary to allow Spectre or one of its vendors to reproduce
results. The fabrication will be performed in the clean room of the Silicon Carbide
Micro-fabrication Laboratory at NASA GRC. Each die will be identified with the
wafer number and die address (row/column) of its origin. All wafer material, used
or unused, whether functioning or non-functioning die or sensing elements, will
become property of Spectre Corporation.
App’x at 3–4 (SAA Responsibilities). The parties do not dispute Milestone 2 was the
“fabrication” step and when NASA would “complete wafer fabrication.” See Tr. at 61:24–62:2
(“[GOVERNMENT:] The fabrication, yes. So that’s Milestone 2.”); Pl.’s Reply at 5 (“Under
Milestones 1 and 2, NASA was to have completed wafer design and the first fabrication run.”);
see also Tr. at 56:21–58:21. Accordingly, under Milestone 2, NASA was to complete the wafer
fabrication and “record process steps, masks, and other data as necessary to allow Spectre or one
of its vendors to reproduce results.” See McAbee, 97 F.3d at 1434–35 (cleaned up) (“If the
contract’s provisions are clear and unambiguous, they must be given their plain and ordinary
meaning.”).
2. Whether NASA Completed Milestone 1
Having determined Milestone 1 was the “design” phase and Milestone 2 was a
“fabrication” phase, see supra, the Court now analyzes whether there is a genuine dispute of
material fact as to whether NASA completed both Milestones. The government relies upon the
traveler for Wafer Number DH0851-15 as evidence to demonstrate NASA’s completion of
- 19 -
Milestone 1 and 2. See Gov’t’s MSJ at 9 (citing App’x at 65–71 (Wafer Traveler)) (“NASA
completed Milestones 1 and 2 demonstrated by at least a traveler for Wafer Number DH0852-
15.”). According to the government, a traveler is a “set of documents that follow the wafer as it
works its way through a semiconductor lab or semiconductor production facility.” Tr. at 46:23–
47:3; see Tr. at 47:4–8 (“[GOVERNMENT:] [The government] analogiz[es] making a wafer or
a wafer fabrication with baking a pizza. . . . [I]n that analogy, the wafer traveler would be sort of
the kitchen ticket that sort of just slides across when it moves to different stations.”). The
government argues the traveler “identified the mask set number NASA_01162013 designed
pursuant to Milestone 1 as well as the associated wafer processing steps defined for the same
design,” and claimed the “traveler also recorded the details of fabrication processing steps
performed by NASA on at least Wafer Number DH0852-15 pursuant to Milestone 2 from March
2013 through August 2013.” Gov’t’s MSJ at 9 (citations omitted). Despite the government
presenting the traveler as evidence of Milestone 1 and 2 being completed by NASA, Spectre
argues the traveler is not evidence NASA completed Milestones 1 and 2 because the government
did not present any facts to establish the DH08512-15 wafer was “actually designed and
fabricated” for Spectre—in Spectre’s view, this means “NASA failed to complete Milestones 1
and 2 under the SAA.” Pl.’s CMSJ at 13–14; see id. (citing Votypka Decl. ¶¶ 25–33) (“As set
forth [in plaintiff’s Cross-Motion for Summary Judgment] and in the Declaration of Jeff
Votypka, NASA has presented no facts to establish that wafer DH0852-15 was actually designed
and fabricated for Spectre and much evidence to suggest it was not.”). Specifically, Spectre
asserts “the DH08512-15 wafer was not purchased for the project” and argues “there is nothing
in the [DH08512-15 wafer] traveler to tie the fabrication of this wafer to Spectre’s project.” Pl.’s
Reply at 7. At oral argument, Spectre clarified its “primary argument . . . [was] that Milestones 1
and 2 were not met because [Spectre] disagree[d] with the evidence [the government]
submitted,” and claimed “Mr. Votypka’s after-the-fact investigation [] support[s] the wafer []
was not fabricated [or] design[ed] for Spectre.” Tr. at 92:3–20.
The government argues the traveler demonstrates “[NASA] completed Milestone 1 . . . in
January 2013.” See Tr. at 46:11–20. Specifically, the government explains the traveler has a
“Pressure Sensor Mask Number [of] NASA_01162013” showing the date of January 2013 as
“the absolute conclusion of Milestone 1.” See Tr. at 103:10–15, 107:19–21. When asked
whether NASA completed Milestone 1, Spectre argued it “do[es]n’t think so” because “there is
no evidence that this wafer or any of the other wafers were actually fabricated for or designed for
Spectre.” Tr. at 47:18–25; see Tr. at 49:21–50:3 (“[THE COURT:] [The government] pointed to
a specific piece of evidence . . . . And why does that not satisfy Milestone 1? [PLAINTIFF:]
Because there’s no proof . . . that [the] work actually was done to design those dies to my client’s
specifications”). When pressed on whether there was any additional evidence to refute NASA
completed Milestone 1, Spectre responded: “[T]here’s no evidence, other than Dr. Okojie, who
repeatedly lied, there’s no evidence that he actually designed [DH0852-15 wafer] for [Spectre].”
Tr. at 56:16–19. Spectre, however, was neither able to identify any evidence in Dr. Okojie’s
deposition supporting the DH0852-15 wafer was not made for Spectre or undermining the
traveler, see Tr. at 99:10–15 (“THE COURT: So could [Spectre], . . . point to . . . anything in the
deposition from Dr. Okojie that points to the DH0852-15 wafer not being made for Spectre or
undermines anything related to the traveler? [PLAINTIFF:] No.”), nor could it provide
evidence Dr. Okojie was lying about the DH0852-15 wafer being designed and fabricated for
Spectre, see Tr. at 100:2–5 (“[THE COURT:] But what shows that [Dr. Okojie] was lying? I’m
- 20 -
asking . . . for the evidence. [Spectre’s Counsel] said it was in the deposition. [PLAINTIFF:]
[Spectre] never said that [Dr. Okojie] . . . lied about DH[0852-15].”). In fact, Spectre only
referenced deposition testimony from Dr. Okojie which supported the wafer was designed and
fabricated for Spectre. See Tr. at 100:5–16 (reading portions of Dr. Okojie’s deposition
testimony into the record) (“[PLAINTIFF:] ‘Was it your belief that the material you sent to me
belongs to Spectre? ‘Yes.[’] ‘And that was because you made these dies for Spectre.
‘ANSWER: It is part of the Space Act Agreement.’”). Instead of providing a citation to the
deposition testimony, Spectre tells the Court “it’s reasonable to infer” Dr. Okojie lied about
designing and fabricating the DH0852-15 wafer for Spectre. See Tr. at 100:17–21. Despite
Spectre having eight hours to question Dr. Okojie at his deposition and press him about the
traveler to determine whether he was lying, Spectre chose not to do so. See Tr. at 51:6–12
(“[GOVERNMENT:] Although [Spectre’s counsel] did have the opportunity to depose Dr.
Okojie during deposition . . . and [the government] went back and looked and search for the
times it mentioned DH. It was barely two pages. And so [Spectre’s counsel] made a clear
choice to not ask Dr. Okojie further about the DH.”); 92:16–24 (“[PLAINTIFF:] I did not go
back . . . I deposed Dr. Okojie for eight hours. I had a lot of things to cover that day.).
Strikingly, the deposition testimony referenced by Spectre actually supports NASA
completed Milestone 1 and the DH0852-15 wafer was designed and fabricated for Spectre. See
Tr. at 99:15–22 (“[PLAINTIFF:] [Dr. Okojie] told . . . [plaintiff’s counsel] that it was made for
Spectre. . . . [Dr. Okojie] says that he sent it to [plaintiff’s counsel] because it belonged to
Spectre, . . . it was made for Spectre.”). Other evidence also supports the traveler and DH0852-
15 was completed for Spectre according to Milestone 1. The traveler contained the mask number
indicating the design was completed at the latest in January 2013, see supra, and there was a
contemporaneous email from Dr. Okojie to Spectre dated 22 December 2012 indicating the
design required under Milestone was met by providing a document “listing the process steps”—
which Spectre confirmed it received. See Tr. at 55:21–56:13 (“[PLAINTIFF:] [T]here was no
documentation sent over and no communication sent over that said, now I really have designed
something for you. THE COURT: Well, the [g]overnment also mentioned a contemporaneous
email related to design having been met. . . . [GOVERNMENT:] [I]t was December 22nd, . . . of
2012. It didn’t explicitly sa[y] that the design was done, but it was transferring . . . a document
listing the process steps . . . as a piece of information for Spectre to learn how to do this process.
[PLAINTIFF:] Yes. They sent us the process steps.”). Even in Spectre’s briefs, it does not
explain how Dr. Okojie’s deposition supported Spectre’s position; instead, Spectre instructed the
Court to “take the time to read Exhibit 12 to the Okojie Deposition . . . and consider the shocking
lack of contract performance by NASA.” Pl.’s CMSJ at 13. Spectre could point to no evidence
to support NASA did not complete Milestone 1—it only asserted Dr. Okojie was “lying.” See
Tr. at 107:11–14 (“THE COURT: Does Spectre have any other evidence that NASA did not
complete Milestones 1 and 2. [PLAINTIFF:] No.”). As Spectre was unable to present any
evidence to refute the traveler or present any evidence demonstrating NASA did not complete
Milestone 1, the Court determines there is no genuine dispute of material fact over whether
NASA completed Milestone 1 under the SAA. See Sweats Fashions, Inc. v. Pannill Knitting
Co., 833 F.2d 1560, 1563 (Fed. Cir. 1987) (affirming lower court’s judgment granting summary
judgment) (quoting Celotex Corp. v. Catrett, 477 U.S. 317, 325 (1986)) (“[T]he burden is not on
the movant to produce evidence showing the absence of a genuine issue of material fact.
‘Instead, as we have explained, the burden on the moving party may be discharged by
- 21 -
“showing”—that is, pointing out to the . . . Court—that there is an absence of evidence to
support the nonmoving party’s case.’”); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248
(1986) (explaining a genuine issue of material fact exists if the “evidence is such that a
reasonable [fact finder] could return a verdict for the nonmoving party.”).
3. Whether NASA Completed Milestone 2
The government further relies on the traveler as evidence NASA completed Milestone 2.
See Tr. at 57:8–9 (“[GOVERNMENT:] Again, [the government] point[s] to the DH wafer
traveler.”). The government argues the traveler is evidence NASA satisfied Milestone 2 because
the traveler includes “process steps, masks, and other data” and demonstrates the “completion of
the wafer fabrication being the last etching step on August 16, 2013.” Tr. at 71:8–13; App’x at
3–4 (SAA Responsibilities). When asked at oral argument whether NASA completed Milestone
2, Spectre explained its position was the wafer NASA produced did not actually meet the
requirements of the SAA—but provided no evidence rebutting the traveler “record[ed] process
steps, masks, and other data as necessary to allow Spectre or one of its vendors to reproduce
results” as required by Milestone 2. See Tr. at 57:18–58:23; App’x at 3–4 (SAA
Responsibilities). In other words, while Spectre argued the wafer must be made for them and
satisfy the specifications set forth in the SAA, it provided no evidence (nor did it point to
anywhere in the record) showing the wafer did not satisfy those specifications—instead, Spectre
attempted to discount the traveler by arguing it is a “debacle of a production” that “took place
over many months.” See Tr. at 57:22–24. Despite acknowledging the traveler was a true
summary of the actual wafer produced, see Tr. at 57:18–22 (“THE COURT: [I]s [] the [traveler]
that were looking at is not a true summary of an actual wafer that was produced? [PLAINTIFF:]
Oh, no.”), Spectre maintained the traveler and DH0852-15 wafer did not match the lithography
given to Spectre a year before the date of the traveler. See Tr. at 58:8–23 (“THE COURT: And
so Plaintiff’s position is that the wafer that was produced did not actually meet the requirement?
[PLAINTIFF:] Because, Your Honor, in July of 2012, Dr. Okojie said, ‘I have completed the
lithography.’ Meaning, the geometric design of the three wafers of all three pressure ranges.
And he produced a document to us, which if you look at it, shows four different dies on it to be,
you know, replicated onto one wafer.”). Spectre instead relies on the observations of one of its
engineers, Mr. Votypka, to support the traveler was not for something designed and fabricated
for Spectre under Milestone 2. See Tr. at 101:13–16 (“[THE COURT:] [Spectre] also point[s] to
Mr. Votypka’s observations related to his assessment of Milestones 1 and 2; is that correct?
[PLAINTIFF:] Yes.”). Specifically, Spectre argues Mr. Votypka’s observations demonstrated
the DH0852-15 wafer “was not the same design that [NASA] had shown [Spectre] in July of
2012 when [Dr. Okojie] said, ‘The lithography is complete for your dies,’” and the traveler is a
“document that had four different dies on it.” Tr. at 101:24–102:10. In response, the
government argues Dr. Okojie never said the lithography was complete and asserts “in his
deposition [he] said that he did not know anything about it.” Tr. at 102:12–17. The government
further argues Mr. Votypka’s comparison of a design from 2012 to the 2013 design present in the
traveler does not mean the DH08512-15 wafer was not designed and fabricated for Spectre
because “what was presented in 2012 . . . has no bearing to what was done in 2013, and certainly
does not disprove or somehow prove that NASA did not make th[e] DH wafer for Spectre.” Tr.
at 102:18–103:2. Spectre also relies upon Mr. Votypka’s declaration to support its position the
wafer DH was not fabricated and designed as part of the SAA, but instead was designed as part
- 22 -
of NASA’s ongoing research and development projects. See Tr. at 92:12–20 (“THE COURT:
Related to those milestones being met, is there any evidence separate from Mr. Votypka’s after-
the-fact investigation to support that the wafer DH was not fabricated [or] design[ed] for Spectre.
[PLAINTIFF]: Your Honor, I believe that if you had Dr. Okojie in the witness stand and I was
cross-examining him, you would find, as the trier of fact that the wafer was part of his ongoing
research and development project.”). Spectre, however, was once again unable to provide any
evidence the DH0852-15 wafer was being used for any other purposes. See Tr. at 107:5–10
(“THE COURT: Is there any evidence that the dies from Wafer DH0852-15 were used for any
other purpose? [PLAINTIFF:] I’m not aware of any evidence. Except, well, they were . . . sent
to me in the mail.”).
While NASA proffered evidence of it recording steps, masks, and other data to allow
Spectre to reproduce the fabrication as required by the SAA, see App’x at 3–4 (SAA
Responsibilities), Spectre failed to present evidence supporting its claim NASA did not complete
the requirements set forth in the SAA regarding Milestone 2. See Tr. at 107:11–14 (“THE
COURT: Does Spectre have any other evidence that NASA did not complete Milestones 1 and
2? [PLAINTIFF:] No.”); Tr. at 107:5–10 (“THE COURT: Is there any evidence that the dies
from Wafer DH0852-15 were used for any other purpose? [PLAINTIFF:] I’m not aware of any
evidence.”). As Spectre was unable to present any evidence to refute the traveler or present any
evidence demonstrating NASA did not complete Milestone 2, the Court determines there is no
genuine dispute of material fact over whether NASA completed Milestone 2 under the SAA.
Given NASA completed Milestone 2 under the SAA and did not need to complete any other
Milestones because of Spectre’s failure to pay the remaining $15,000 required prior to Milestone
3, the Court finds NASA did not breach the SAA as a matter of law. See Sweats Fashions, Inc.
v. Pannill Knitting Co., 833 F.2d 1560, 1563 (Fed. Cir. 1987) (affirming lower court’s judgment
granting summary judgment) (quoting Celotex Corp. v. Catrett, 477 U.S. 317, 325 (1986))
(“[T]he burden is not on the movant to produce evidence showing the absence of a genuine issue
of material fact. ‘Instead, as we have explained, the burden on the moving party may be
discharged by “showing”—that is, pointing out to the . . . Court—that there is an absence of
evidence to support the nonmoving party’s case.’”); Anderson v. Liberty Lobby, Inc., 477 U.S.
242, 248 (1986) (explaining a genuine issue of material fact exists if the “evidence is such that a
reasonable [fact finder] could return a verdict for the nonmoving party”).
V. Analysis of Whether NASA Breached the Implied Duty of Good Faith and Fair
Dealing Under the Space Act Agreement
Having determined NASA did not breach the SAA, see supra Section IV, the Court next
analyzes whether NASA breached the implied duty of good faith and fair dealing. During oral
argument Spectre confirmed to prove a breach of the implied duty of good faith and fair dealing
a specific promise in the contract must be undermined. See Tr. at 128:9–15 (“[THE COURT:]
[T]he Federal Circuit in Dobyns notes . . . that ‘while there’s not a requirement of a violation of
an express provision, a specific promise must be undermined for the implied duty of good faith
and fair dealing to be violated,’ correct? [PLAINTIFF:] Yes.”). Spectre further confirmed the
Court cannot rely on parol evidence to add or otherwise modify the terms of the contract. See Tr.
at 128:17–23 (“[THE COURT:] [T]he Court also cannot rely on parol evidence to add or
otherwise modify the terms of the written agreement in instances where the written agreement
- 23 -
has been adopted by the parties as an expression of final understanding, right? [PLAINTIFF:]
Yes.”). The Court, therefore, analyzes whether NASA undermined a “specific promise” or
obligation in violation of the implied duty of good faith and fair dealing. See Dobyns v. United
States, 915 F.3d 733, 739 (Fed. Cir. 2019) (“[A] specific promise must be undermined for the
implied duty [of good faith and fair dealing] to be violated.”); see also Metcalf Const. Co, Inc. v.
Unites States, 742 F.3d 984, 992 (Fed. Cir. 2014) (explaining a court “need[s] to take account of
the particular contract at issue in considering a claim of breach of the good-faith-and-fair-dealing
duty implicit in that contract”).
When asked by the Court to identify a specific promise in the SAA that was undermined,
all Spectre could offer as evidence was NASA violating the SAA’s reasonable efforts clause.
See Tr. at 129:3–130:17 (“[THE COURT:] So what is the specific promise of the Space Act
Agreement looking at the document that has been violated? [PLAINTIFF:] Well, . . . all of
NASA’s Space Act Agreements . . . have this reasonable efforts clause in them. . . . [THE
COURT:] [W]hat specifically, can you point to me, the provision, the reasonable efforts
clause, . . . what paragraph is that in[?] [PLAINTIFF:] It’s the preface. . . . It’s on page 3, . . .
Right before NASA’s responsibilities. . . . [THE COURT:] So that’s the specific promise that
was broken? [PLAINTIFF:] Right.”). After identifying the reasonable efforts clause as the
specific promise NASA violated, Spectre explained it is not “a reasonable effort to take your
customer’s money and substitute something . . . instead of doing what you’re supposed to do.”
Tr. at 130:14–17. Spectre, however, agreed because it never completed the payment prior to
Milestone 3, NASA no longer had to make reasonable efforts beyond Milestones 1 and 2. See
Tr. at 130:18–131:23 (“THE COURT: But [Spectre] agree[s] . . . that [p]laintiff’s payment due
by the end of Milestone 2, prior to the beginning of Milestone 3, meant that NASA no longer had
any reasonable efforts to make, other than Milestones 1 and 2? [PLAINTIFF:] Right.”).
Spectre argues NASA breached the implied duty of good faith and fair dealing due to
NASA’s non-completion of Milestones 1 and 2 and insufficient production of sensors under the
SAA. See Tr. at 130:23–131:5 (“[PLAINTIFF:] If [NASA] actually completed Milestones 1
and 2, which they claimed they completed . . . the face is that [NASA] was nowhere near . . . 36
sensors in three different pressure ranges made [as required under the SAA].”). This argument
fails for two reasons: (1) the Court already determined NASA completed Milestones 1 and 2,
see supra Section IV.D.2–D.3; and (2) NASA was not required to complete any further
Milestones because of Spectre’s non-payment prior to the start of Milestone 3, see supra Section
IV.A. As such, NASA could not have breached an implied duty of good faith and fair dealing
through the reasonable expectation clause because there was no reasonable expectation for
NASA to perform past Milestone 2. See Dobyns, 915 F.3d at 739 (“[A] specific promise must be
undermined for the implied duty [of good faith and fair dealing] to be violated.”); see also
Metcalf Const., 742 F.3d at 992 (explaining a court “need[s] to take account of the particular
contract at issue in considering a claim of breach of the good-faith-and-fair-dealing duty implicit
in that contract”).
Spectre also claims a bait-and-switch occurred when NASA “pawn[ed] off old sensors
designed and fabricated for somebody else for some other purpose” and “pawned off ancient
technology as something that is good enough.” Pl.’s CMSJ at 2, 6–7, 18. When asked at oral
argument about the bait-and-switch, Spectre confessed NASA only needed to complete
- 24 -
Milestones 1 and 2 and was not required to deliver any sensors until Milestone 6. See Tr. at
131:16–132:15 (“[THE COURT:] [Spectre] argue[s] . . . that there was a bait and switch, where
NASA contracted to provide a total of 36 of 60 functional pressure sensor modules and hundreds
of loose dies after the first fabrication run, all of which had been designed and fabricated to
Spectre’s specification. But under the Space Act Agreement, none of that delivery was required
until Milestone 6, so how could anything have been due before then? [PLAINTIFF:] Well,
Milestone 1 and 2 were due.”) As delivery was not required prior to Milestone 6, see supra
Section IV.C., NASA’s non-delivery of functional pressure sensor modules and loose dies was
not a breach of the implied duty of good faith and fair dealing. See Dobyns, 915 F.3d at 739
(“[A] specific promise must be undermined for the implied duty [of good faith and fair dealing]
to be violated.”); see also Metcalf Const., 742 F.3d at 992 (explaining a court “need[s] to take
account of the particular contract at issue in considering a claim of breach of the good-faith-and-
fair-dealing duty implicit in that contract”).
Finally, Spectre argues NASA breached the implied duty of good faith and fair dealing
by performing research and development under the SAA because “[d]espite the precatory
language, the purpose of the SAA was not to develop prototypes as a feasibility study, it was to
pay NASA to jumpstart the . . . Project by designing and fabricating the first two waves of SiC
pressure modules.” Pl.’s CMSJ at 10–11. Spectre claims while the SAA in the introductory
section explains the purpose of the contract “is to produce a sufficient number of sensor modules
to determine ‘suitability for the commercial market,’ . . . all parties (except perhaps Dr. Okojie)
knew that the technology was ready to be commercialized.” Id. at 11. Specifically, Spectre
argued the “State of Ohio made clear that the purpose of all this funding, these grants, was not
for research and development, it had to be for commercialization because they wanted to build
the tax base” and “the Space Act Agreement was not for NASA to do research and development”
because “the invention was already made” and NASA “was just specifying the pressure [Spectre]
want[ed].” Tr. at 19:7–25. NASA agreed the primary purpose of the SAA was to “produce a
sufficient quantity of silicon carbide-based pressure sensor modules fabricated according to the
NASA patents,” but argued the context shows “this was still in development.” Tr. at 20:17–21:4.
The government argues while the SAA “was to produce a sufficient quantity to demonstrate
certain properties and certain feasibility,” “it does not mean it was a production environment . . .
especially with the combination of different things [NASA] was trying.” Tr. at 21:6–15. In the
government’s view, the SAA was “essentially a research and development” contract because “it
was very much a[t a] prototyping stage.” See Tr. at 21:16–22:3 (“THE COURT: So the
[g]overnment’s position is that the Space Act Agreement was a research and development
agreement? [GOVERNMENT:] It was, yes.”). The Court agrees with the government that
while the SAA was for commercialization, the SAA contemplated research and development.
To begin, Milestones 1 through 10 of the SAA required testing, packaging, and further testing of
the modules in Run 1 and then in Run 2 NASA would improve upon the first run—
demonstrating research and development was contemplated to improve upon Run 1 in Run 2.
See Tr. at 27:10–18 (“[GOVERNMENT:] [T]he discussion of the different milestones did show
that it was a research and development. Because Milestone 1 through 10 was to do one run, one
sort of complete spin of this process of design through testing, through packaging, and then
further testing of the modules. And then only in Run 2, [NASA] would improve and apply all
the learnings [NASA] had. So that does show that it was a research [and] development.”).
- 25 -
The SAA itself also contemplates research and development in “Article 2. Purpose,”
stating, “the first fabrication run will provide Spectre with sufficient sensor modules to verify
final packaging arrangement, to conduct necessary validation testing, and to conduct initial field
trials with potential customers.” App’x at 1–2 (SAA Purpose). As explained at oral argument,
verifying final packaging arrangements is important to this type of technology because the
packaging is what protects the sensors and allows them to function. See Tr. at 28:9–19 (“THE
COURT: Can [the government] provide a little bit more context, what does the language mean,
‘verify final packaging arrangement,’ and why is that important for this type of technology?
[GOVERNMENT:] Well, packaging, generally speaking, in sensors are a humungous challenge.
Especially in this case, we’re talking about high-temperature application. So the packaging that
surrounds the chip, surrounds the semiconductor die, needs to survive that and not cause the
degradation, in the performance of the die itself.”). This packaging was contemplated as part of
Spectre’s responsibilities, see App’x at 2 (SAA Responsibilities) (“Spectre will take all
necessary steps to put the sensing modules provided by NASA into housing with any necessary
condition electronics, boards, fixtures, etc. to present as prototype components for evaluation by
Spectre customers.”), as well as third parties (Sienna Technologies, Inc.) contemplated in
Milestone 4, see App’x at 4 (SAA Responsibilities) (“The header fabrication and attachment of
sensors to the headers will be performed by Sienna Technologies, Inc, Woodinville, WA at
NASA’s expense under NASA’s direction.”). Under the SAA, NASA would subcontract the
packaging to Sienna, and this is part of the larger multi-step process under the SAA of creating a
commercially viable product. See Tr. at 31:24–32:5 (“[THE COURT:] [T]he functionality of
the agreement, it’s that money would come into NASA for the purposes of perfecting
commercialization. As part of NASA’s work, NASA would actually have money going out to
other parties in order to create the full packaging of the system? [GOVERNMENT:] Yes.”); Tr.
at 38:5–10 (“THE COURT: So these modules, in order to put together a module, there’s a multi-
step process that involves creating dies, shipping them across the country, having a production
run by Sienna, having them ship items back, things like that? [GOVERNMENT:] Yes.”). As
clarified by the government based on the record, the work performed by Sienna under the SAA
would not have been considered a “production run” because the cost was far greater than
commercialization and involved many technical steps to create viable, finished packaging for
later commercialization demonstrates research and development regarding packaging was
required. See Tr. at 38:10–39:8 (“[GOVERNMENT:] Just one clarification about what Sienna
would do. I do not believe that they consider that a production run because just looking at the
cost, they were quoting $50,000 for . . . 36. That is an incredibly high number for production.
And I believe that they were doing that as a prototype. . . . [b]ecause the unit cost of $1,500 per
package would be uneconomical in the industry. And so I believe that also shows that this was a
research and development process because the cost that was quoted was Sienna was not feasible
commercially. THE COURT: . . . [I]n order to produce 30 modules, Sienna quoted NASA a
charge of around $50,000. [The government’s] point is that that high-cost shows that Sienna is
also having do a lot of technical steps. [GOVERNMENT:] Yes . . . And that unit cost of $1,500
each shows that it was more of a one-off instead of a true production.”). As the SAA
contemplated many aspects of research and development, particularly regarding packaging, and
many factors needed to be determined prior to commercialization, NASA’s research and
development occurring during early milestones of the SAA was not a breach of the implied duty
of good faith and fair dealing. See Dobyns v. United States, 915 F.3d 733, 739 (Fed. Cir. 2019)
(“[A] specific promise must be undermined for the implied duty [of good faith and fair dealing]
- 26 -
to be violated.”); see also Metcalf Const. Co, Inc. v. Unites States, 742 F.3d 984, 992 (Fed. Cir.
2014) (explaining a court “need[s] to take account of the particular contract at issue in
considering a claim of breach of the good-faith-and-fair-dealing duty implicit in that contract”).
VI. Analysis of Whether NASA Breached the Patent License
Despite claiming in in its brief “Spectre Cannot Carry Its Burden to Prove that NASA
Breached the Patent License,” Spectre explained during oral argument its brief included further
“typos.” See Tr. at 124:6–15 (“THE COURT: So [Spectre’s] Roman Numeral III, the heading is
“Spectre cannot carry its burden to prove that NASA breached the patent license.” Is that, like, a
rhetorical statement or something, or is it a typo? [PLAINTIFF:] You know, I think I copied
this . . . so that was another typo. . . . I was using the heading that the [g]overnment had used and
replying to them.”); see also Tr. at 91:10–92:2 (detailing a similar typo where Spectre stated
“NASA did not breach the Space Act Agreement as a matter of law”). The Patent License was
the second agreement executed between Spectre and NASA. See App’x at 18–47 (Patent
License). Spectre paid NASA $50,000 for the royalty-bearing, exclusive license to practice
NASA’s silicon-carbide sensor patents. See id. NASA granted Spectre the Patent License
pursuant to the authority in the Bayh-Dole Act, 35 U.S.C. § 200, et seq., and its implementing
regulations at 37 C.F.R. § 404. See App’x at 21 (Patent License). The Bayh-Dole Act allows
NASA to grant patent licenses to “promote the utilization of inventions arising from federally
supported research or development.” 35 U.S.C. § 200. Patent licenses, however, can be granted
under the Bayh-Dole Act “only if the applicant has supplied the Federal agency with a
satisfactory plan for development or marketing of the invention, or both, and with information
about the applicant’s capability to fulfill the plan.” 37 C.F.R. § 404.5(a)(1). Consistent with the
Bayh-Dole Act, the Patent License requires a licensee to achieve practical application of the
patents in accordance with a specific schedule and file periodic reports on its progress. See
App’x at 27, 30–32 (Patent License). Spectre agrees “NASA followed the regulatory
requirements for granting Spectre’s License Application,” Pl.’s CMSJ at 13, but argues NASA’s
termination of the Patent License was in violation of the Bayh-Dole Act because NASA’s
“notice did not allow . . . Spectre . . . to show cause why the license should not be terminated,”
Pl.’s Reply at 13. The government, however, argues the Patent License required Spectre to, at a
minimum, submit periodic reports and failure to submit such reports was a valid basis under the
Patent License for NASA to terminate. See Gov’t’s MSJ at 6–8, 21. As the only issue is
whether NASA properly terminated the Patent License, the Court next analyzes whether
NASA’s termination of the Patent License was a breach by first determining what was required
under the contract for NASA to terminate and then examining whether NASA’s termination was
proper.
Under Article VIII of the Patent License entitled “Reports,” Spectre, as the licensee, was
required to “submit to [NASA] written reports within thirty (30) calendar days of the end of
every ACCOUNTING PERIOD whether or not royalties are due.” App’x at 30 (Patent License)
(emphasis in original). Article VII Section 8.2 of the Patent License also detailed what needed to
be included in Spectre’s reports: “a narrative description of the steps taken or being taken to
reduce the LICENSED INVENTION to practice” and “a narrative description of the steps taken
or being taken to create a market demand for the LICENSED INVENTION, to commercialize
the LICENSED INVENTION, and to meet market demand for the LICENSED INVENTION.”
- 27 -
See App’x at 30–31 (Patent License) (emphasis in original). The plain language of the Patent
License therefore required Spectre to submit periodic reports, even if no royalties to NASA were
due. See McAbee, 97 F.3d at 1434–35 (cleaned up) (“If the contract’s provisions are clear and
unambiguous, they must be given their plain and ordinary meaning.”).
Article XIX of the Patent License entitled “Termination or Modification,” specifically
Section 19.4, detailed when NASA could terminate the License. See App’x at 42 (Patent
License). Section 19 allows “terminat[ion] by LICENSOR, in whole or in part, if:
(a) LICENSOR determines that the LICENSEE has failed or will fail to meet
milestone in accordance with the schedule set forth in the APPENDIX to this
AGREEMENT, . . . or to achieve or maintain PRACTICAL APPLICATION of the
LICENSED INVENTION as provided by ARTICLE V.
(b) LICENSOR determines that LICENSEE has failed or will fail to reduce to
practice or substantially manufacture the LICENSED INVENTION in the United
States as provided by Section 6.1.
...
(d) LICENSEE fails to pay royalties or submit reports as provided by ARTICLE
VII and VIII.”
App’x at 42 (Patent License) (emphasis in original). Section 19.7 further provides “[b]efore
LICENSOR unilaterally . . . terminates this AGREEMENT for any cause, LICENSOR will
deliver to LICENSEE . . . a written notice stating LICENSOR’s intention to . . . terminate the
AGREEMENT and the reasons therefor. LICENSEE . . . will be allowed thirty (30) calendar
days after . . . such notice of intention to . . . terminate the AGREEMENT to remedy any
BREACH or the AGREEMENT or show cause why the AGREEMENT should not be
unilaterally . . . terminated.” App’x at 43 (Patent License) (emphasis in original). Under the
plain language of the Patent License, NASA was therefore allowed to unilaterally terminate the
license agreement if Spectre failed to submit reports and NASA was only required to provide
written notice and allow 30 days for Spectre to remedy the breach or show cause why the Patent
License should not be terminated. See McAbee, 97 F.3d at 1434–35 (cleaned up) (“If the
contract’s provisions are clear and unambiguous, they must be given their plain and ordinary
meaning.”).
Having determined the Patent License allowed for unilateral termination by NASA if
Spectre did not comply with the Patent License’s requirements—including submitting periodical
reports—the Court now examines whether NASA’s termination of the Patent License was
proper. Spectre “suggests that under the circumstances, it should be excused from the Annual
Report submittal requirement.” Pl.’s CMSJ at 13. When discussing the termination of the Patent
License in its brief, Spectre retorts, “Have we not already addressed this?” only then to proceed
and admit “Yes, Spectre did not make the Annual Reports,” and Spectre not complying with the
reporting requirements “was a foul without harm because there was nothing to report other than
NASA was delaying the Project.” Pl.’s CMSJ at 16. Under the express terms of the Patent
License, Spectre was required to submit reports, and not submitting reports was grounds for
unilateral termination by NASA. See App’x at 30–31 (Patent License) (requiring reports even if
- 28 -
no royalties were due), id. at 42 (Patent License) (permitting licensor to terminate if “LICENSEE
fails to . . . submit reports as provided by ARTICLE VII and VIII.”) (emphasis in original). At
oral argument, Spectre agreed NASA could terminate the Patent License for any reason listed in
Section 19.4 and confessed it did not provide the reports to NASA as required by the Patent
License. See Tr. at 124:16–125:2 (“[THE COURT:] [D]oesn’t the license allow NASA to
terminate the [P]atent [L]icense for any reason listed in article 19.4. [PLAINTIFF:] Yes. . . .
[THE COURT:] [A]t a minimum, 19.4D, which required annual reports, I think [p]laintiff
admits that Spectre did not give periodic reports? [PLAINTIFF:] That’s right.”). As such,
Spectre’s failure to submit reports was not “a foul without harm” because it was an express
requirement under the Patent License and allowed NASA to unilaterally terminate the license in
whole pursuant to Section 19.4(d) of the Patent License. See McAbee, 97 F.3d at 1434–35
(cleaned up) (“If the contract’s provisions are clear and unambiguous, they must be given their
plain and ordinary meaning.”); San Carlos Irrigation & Drainage Dist. v. United States, 877
F.2d 957, 959 (Fed. Cir. 1989).
Spectre further argues NASA did not give Spectre the “right to cure or an opportunity to
contest [an] appeal, it simply informed Spectre that its license would be terminated effective in
30 days.” Pl.’s CMSJ at 16. The Patent License, however, only required NASA to provide
written notice of termination explaining the reason NASA was terminating and allow Spectre the
opportunity to cure or show cause. See App’x at 42–43 (Patent License). At oral argument,
Spectre acknowledged NASA provided notice it was terminating the Patent License on 15 May
2014 but averred the notice was invalid because “it’s arguable that there’s a notice and
opportunity to cure.” Tr. at 124:20–23. But Spectre was given an opportunity to respond to the
notice of termination. See Tr. at 126:18–127:5 (“THE COURT: Did NASA give Spectre the
opportunity to cure . . . and to respond? [GOVERNMENT:] They did because the termination
was not going to be effective until more than 30 days . . . after the notice. And that was the
opportunity for Spectre to cure if they wished to. They . . . knew they had 30 days, in fact, a
little bit over 30 days, and they did nothing during that period.”). Spectre itself admitted “it
do[esn]’t think that [it] responded effectively” in response to NASA’s notice regarding the Patent
License’s termination. See Tr. at 127:16–128:6. When pressed on why it did not cure or show
cause, Spectre said it believed it was “too little, too late.” See Tr. at 125:14–24 (“THE COURT:
Did Spectre request the 30-day opportunity to cure or show cause, or how did Spectre respond?
[PLAINTIFF:] Well, at that point, Your Honor. NASA had already announced it was not going
to do any more work under the Space Act Agreement, so it was a little futile. I think, if I recall,
my client went out and hired a sol[o] practitioner to try to argue some things on [Spectre’s]
behalf, but it was too little, too late, and it didn’t go anywhere.”). As NASA provided Spectre
notice of termination and allowed thirty days for Spectre to cure or show cause according to the
terms of the Patent License—and Spectre failed to effectively respond, cure, or show cause—the
termination of the Patent License was not a breach. See McAbee, 97 F.3d at 1434–35 (cleaned
up ) (“If the contract’s provisions are clear and unambiguous, they must be given their plain and
ordinary meaning.”); San Carlos Irrigation & Drainage Dist. v. United States, 877 F.2d 957, 959
(Fed. Cir. 1989).
VII. Analysis of Whether NASA Breached the Implied Duty of Good Faith and Fair
Dealing Under the Patent License
- 29 -
Spectre argues NASA breached the implied duty of good faith and fair dealing by
terminating the Patent License in “bad faith.” Pl.’s CMSJ at 2. Specifically, Spectre purports
“NASA terminated the Patent License on the ground that it appeared Spectre would not be able
to reduce the inventions to practice within the contractually required 36 months and that Spectre
had failed to make progress reports which were specious grounds raised in breach of NASA’s
duty of good faith and fair dealing because NASA was the cause of the delay and of Spectre’s
inability to reduce the patent to practice.” Pl.’s Reply at 3. As discussed supra, to determine if
there was a breach of the implied duty of good faith and fair leading, the Court must determine
whether NASA undermined a “specific promise” or obligation in violation of the implied duty of
good faith and fair dealing. See Dobyns v. United States, 915 F.3d 733, 739 (Fed. Cir. 2019)
(“[A] specific promise must be undermined for the implied duty [of good faith and fair dealing]
to be violated.”); see also Metcalf Const. Co, Inc. v. Unites States, 742 F.3d 984, 992 (Fed. Cir.
2014) (explaining a court “need[s] to take account of the particular contract at issue in
considering a claim of breach of the good-faith-and-fair-dealing duty implicit in that contract”).
NASA did nothing to prevent Spectre from submitting the periodic reports required under the
Patent License, and Spectre even admits it did not submit the reports even though it was
required. See supra Section VI. Additionally, NASA followed Patent License’s requirements
for unilaterally terminating by providing written notice of termination to Spectre. See supra
Section VI. NASA’s termination of the Patent License, therefore, was not “wrongful” as Spectre
claims, but was according to the terms of the Patent License. See supra Section VI. As it was
Spectre, not NASA, who caused the delay in the Project and NASA followed the requirements of
the Patent License, Spectre’s claims do not support NASA breached of the implied duty of good
faith and fair dealing under the Patent License. See Dobyns, 915 F.3d at 739 (“[A] specific
promise must be undermined for the implied duty [of good faith and fair dealing] to be
violated.”); see also Metcalf Const., 742 F.3d at 992 (explaining a court “need[s] to take account
of the particular contract at issue in considering a claim of breach of the good-faith-and-fair-
dealing duty implicit in that contract”).
Spectre further argues “NASA’s bad faith is especially egregious now that it is known
that through discovery that NASA pulled a bait-and-switch, and that its real motivation for
terminating Spectre was because of threats from Meggitt not to enter into a multi-hundred
thousand dollar Space Act Agreement with NASA unless NASA terminated Spectre.” Pl.’s
Reply at 13–14. Spectre claims “[d]iscovery showed that Meggitt—which had licensed that
same patents from NASA in 2007[—]had been protesting and putting pressure on NASA ever
since discovering Spectre’s Patent License in the Spring of 2012.” Id. at 14. Despite claiming
discovery revealed pressure on NASA from Meggitt, Spectre did not include the emails
supporting these claims in its summary judgment briefing, nor did it provide any citations to the
record; rather, Spectre sent copies of the emails to the Court prior to oral argument in response to
the Court’s questions regarding items mentioned in the summary judgment briefing. The
government did not object but argues the emails between Meggitt and NASA were not part of
evidence to be considered for oral argument. See Tr. at 137:9–11 (“[GOVERNMENT:]
Frankly, we believe [Spectre’s reliance on the Meggitt emails] is grounds for waiver as well
because [Spectre] should have submitted th[em] with [its] opening brief.”). Although the
Meggitt emails were not included with Spectre’s opening brief to support its claim NASA
breached the implied duty of good faith and fair dealing under the Patent License, the emails
were extensively discussed at oral argument, read into the record, and the parties did not object
- 30 -
to discussing the emails. The Court therefore analyzes whether the emails support Spectre’s
allegations of bad faith based upon the discussion at the oral argument.
To begin, the government explains Meggitt was a licensee of some of the same NASA
patents as Spectre. See Tr. at 133:23–134:7 (“[THE COURT:] Who is Meggitt, and how are the
related to the Space Act Agreement? [GOVERNMENT:] So my understanding is that Meggitt
is . . . or probably at least was a licensee of at least some . . . of the same patents that Spectre
licensed, and they were basically adjacent licensees. So Meggitt has certain fields of use, and
Spectre has other fields of use.”). Despite admitting there are emails from Meggitt to NASA in
which Meggitt was “complaining” about NASA’s Patent License with Spectre in 2012, the
government revealed NASA ignored Meggitt’s threats for at least two years until it terminated
the Patent License in 2014. See Tr. at 134:8–25 (“THE COURT: Did Meggitt pressure NASA
into terminating with Spectre? [GOVERNMENT:] Well, . . . I see that as just one licensee
complaining against another. Just like, . . . for example, somebody living in a dorm saying that
they have a loud neighbor. It doesn’t mean . . . it was a pressure. THE COURT: But Meggitt
specifically said that the work that NASA was doing with Spectre was in violation of the contract
that Meggitt had? [GOVERNMENT:] I believe there were some threats, perhaps, if at that. But
again, that is just a complaint, and I believe that was first launched in 2012. And . . . NASA did
nothing about it for at least two years.”). Spectre agreed with this timeline at oral argument and
confirmed NASA did nothing for two years. See Tr. at 136:5–23 (“THE COURT: [Spectre]
agree[s] . . . with what [the government] said about the timeline, is that Meggitt told NASA that
the patent license with Spectre is in conflict back in 2012 . . . but NASA didn’t do anything until,
at the earliest, at some point in 2014? [PLAINTIFF:] Well, they . . . hoped that Meggitt would
just forget about it and go away.”). The government also confirmed it informed Meggitt the
licenses between Meggitt and Spectre did not overlap and were not in conflict based on NASA’s
due diligence prior to entering the licenses. See Tr. at 136:24–137:8 (“[THE COURT:] [I]s
there any communication and evidence where NASA said to Meggitt that the agreement with
Spectre was of no concern with Meggitt or disagrees with Meggitt’s representations in the the[]
emails? [GOVERNMENT:] Yes. . . . There are letters like that. THE COURT: But they’re not
in evidence now? [GOVERNMENT:] Yes. Because we were not aware [] because [Spectre]
did not submit [the Meggitt emails] with [its] brief.”); 138:7–12 (“[THE COURT:] [W]hy did
NASA sign a license with Spectre after it had signed an exclusive license with Meggitt?
[GOVERNMENT: Because the fields of views were different. And based on NASA’s
determination there were no overlap[s].”). Even though the correspondences between Meggitt
and NASA were not properly part of summary judgment because they were not submitted with
Spectre’s Cross-Motion for Summary Judgment brief, discussion of the correspondences during
oral argument demonstrates Meggitt did not pressure NASA to terminate Spectre’s Patent
License. See Tr. at 134:8–25, 136:5–23. As such, this evidence does not support Spectre’s claim
NASA breached the implied duty of good faith and fair dealing under the Patent License. See
Dobyns v. United States, 915 F.3d 733, 739 (Fed. Cir. 2019) (“[A] specific promise must be
undermined for the implied duty [of good faith and fair dealing] to be violated.”); see also
Metcalf Const. Co, Inc. v. Unites States, 742 F.3d 984, 992 (Fed. Cir. 2014) (explaining a court
“need[s] to take account of the particular contract at issue in considering a claim of breach of the
good-faith-and-fair-dealing duty implicit in that contract”).
VIII. Parties’ Previous Settlement Discussions
- 31 -
Although not included in the parties’ summary judgment briefing, the Court notes at oral
argument the parties discussed multiple settlement discussions before this case was filed and
during this litigation. Initially, prior to this litigation, NASA offered to repay Spectre the full
$215,000 paid under the SAA and Patent License. This was confirmed by the draft Termination
Agreement of the SAA and Patent License from 27 March 2014 provided to the Court by
plaintiff’s counsel before oral argument. The draft Termination agreement noted upon
termination NASA would return to Spectre the $165,000 it paid under the SAA and the $50,000
it paid under the Patent License—which Spectre confirmed at oral argument. See Tr. at 139:17–
140:18 (“[THE COURT:] [C]ertainly, based on the communications that occurred prior to
litigation, it looked like NASA had suggested repayment, which was contemplated . . . as part of
the end of the Space Act Agreement. . . . [PLAINTIFF:] There were original settlement talks
before the agreements were terminated. But my client got back to NASA too late, and NASA
said, ‘Oh, the deal’s off.’ And so they were originally agreeing to refund, but [NASA] said,
‘Sorry, that’s gone.’”). The Court substantively discussed the parties revisiting settlement
discussions based on the current record and possible options the parties could explore in
attempting to resolve the case. See Tr. at 139:17–150:14 (discussing settlement options). The
Court subsequently ordered a JSR regarding the parties’ settlement discussions. 4 April 2025
Order, ECF No. 168. In the JSR, the parties informed the Court no agreement could be reached.
8 April 2025 JSR at 4, ECF No. 169.
IX. Conclusion
For the foregoing reasons, the Court determines NASA did not breach: (1) the SAA, see
supra Section IV; (2) the implied duty of good faith and fair dealing under the SAA, see supra
Section V; (3) the Patent License, see supra Section VI; or (4) the implied duty of good faith and
fair dealing under the Patent License, see supra Section VII. The Court therefore GRANTS the
government’s Motion for Summary Judgment, ECF No. 158, and DENIES plaintiff’s Cross-
Motion for Summary Judgment, ECF No. 162. The Clerk’s Office is DIRECTED to enter
judgment accordingly.
IT IS SO ORDERED.
s/ Ryan T. Holte
RYAN T. HOLTE
Judge
- 32 -