Opinion

Robert T. Williams, Owen Honeysuckle, Rose White, Wayne Nunnerly, Lela Burns, and Barbara Mitchell Hicks v. City of Sherwood, Arkansas; And Charles Harmon, Kenneth Keplinger, Kevin Lilly, Marina Brooks, Mary Jo Heye, Mike Sanders, Tim McMinn, and Toni Butler, in Their Official Capacities as Aldermen of the City of Sherwood, Arkansas

  • 2019 Ark. App. 487
Court
Court of Appeals of Arkansas
Filed
Oct 23, 2019
Status
Published
Cited by
0 cases
Authority
More cited than 36.5%

The opinion

Cite as 2019 Ark. App. 487

Digitally signed by Elizabeth Perry

ARKANSAS COURT OF APPEALS

Date: 2022.08.04 12:19:11 -05'00' DIVISION III

Adobe Acrobat version: No. CV-19-91

2022.001.20169

ROBERT T. WILLIAMS, OWEN Opinion Delivered: October 23, 2019

HONEYSUCKLE, ROSE WHITE,

WAYNE NUNNERLY, LELA BURNS, APPEAL FROM THE PULASKI

AND BARBARA MITCHELL HICKS COUNTY CIRCUIT COURT,

THIRD DIVISION

APPELLANTS [NO. 60CV-14-4864]

V. HONORABLE CATHLEEN V.

COMPTON, JUDGE

CITY OF SHERWOOD, ARKANSAS;

AND CHARLES HARMON,

KENNETH KEPLINGER, KEVIN

LILLY, MARINA BROOKS, MARY JO

HEYE, MIKE SANDERS, TIM

MCMINN, AND TONI BUTLER, IN

THEIR OFFICIAL CAPACITIES AS

ALDERMEN OF THE CITY OF

SHERWOOD, ARKANSAS

APPELLEES AFFIRMED

WAYMOND M. BROWN, Judge

This case is the latest in a series of challenges to issues addressed in and related to the

Pulaski County Circuit Court’s order entered in October 2005 in which Central Arkansas

Water (“CAW”) was appointed as receiver for Brushy Island Public Water Authority. In

the instant appeal, appellants argue that the circuit court erred in denying their petition for

declaratory judgment and granting summary judgment in favor of appellees City of

Sherwood et al. Finding no justiciable controversy, we affirm.

The Brushy Island community was annexed into the City of Sherwood as a result of

the 1974 and 1982 general elections. Water service was provided to Brushy Island residents

exclusively from the Brushy Island Water Association, Inc., a nonprofit corporation. On

July 15, 2003, during an annual membership meeting, Brushy Island Water Association, Inc.

was converted to a public water authority known as Brushy Island Public Water Authority

(“Authority”) pursuant to and in accordance with Arkansas Code Annotated section 4-35-

202 (Supp. 2003). Some residents of the Brushy Island community challenged the

conversion vote; however, on October 18, 2005, the Pulaski County Circuit Court entered

an order denying the challenge, granting the Authority’s motion for appointment of a

receiver, and appointing CAW as receiver for the Authority. 1

Based on evidence indicating the state of disrepair of the Authority’s water-system

facilities, CAW was ordered to, within six months of the date of the order, contract for and

begin construction on the improvements necessary to bring the system up to the standards

of other water systems operated by CAW. Specifically, CAW was ordered to install

improvements, detailed in the order as follows:

The Improvements consist of the installation of approximately 4400 Linear

Feet (LF) of 24-inch Ductile Iron (DI) pipe, 4900 LF of 12-inch DI pipe,

4900 LF of 8-inch DI pipe, 4300 LF of 3–inch PVC pipe, and 5900 LF of 2-

inch PVC pipe and appurtenances. The Improvements will also include the

installation of 10 new Fire Hydrants, 320 new service meters and Pressure

Regulators, as well as repair and/or replacement of existing service lines as

required.

1

The circuit court’s October 18, 2005 order was affirmed in Williams v. Brushy Island

Public Water Authority, 368 Ark. 219, 243 S.W.3d 903 (2006). A second challenge to the

validity of the conversion vote was affirmed in Davis v. Brushy Island Public Water Authority

of State, 375 Ark. 249, 290 S.W.3d 16 (2008).

2

Additionally, financing for the improvements to the water system was addressed in

the order as follows:

37. CAW has estimated that the costs for construction and completion of

the Improvements will be approximately $1,949,100 (the “Project Costs”).

38. CAW shall contribute approximately $165,690 toward payment of the

Project Costs.

39. The City of Jacksonville, Arkansas has agreed to pay CAW, for the use

and benefit of Brushy Island, the sum of approximately $554,703 as a

contribution toward payment of the Project Costs.

40. The City of Sherwood, Arkansas has agreed to pay CAW, for the use

and benefit of Brushy Island, the sum of $170,000 as a contribution toward

payment of the Project Costs.

41. Brushy Island is currently indebted to Arkansas Natural Resources

Commission in the approximate amount of $100,000 (the “Old Debt”).

Arkansas Natural Resources Commission shall forgive all late fees and other

default charges due on the Old Debt and refinance the outstanding amount

of the Old Debt in the new financing as provided in paragraph 42 hereof.

42. Within sixty (60) days of the date of this Order, Arkansas Natural

Resources Commission shall enter into an agreement with CAW, as receiver

for Brushy Island, to loan Brushy Island the remaining balance of the Project

Costs, including any costs overruns, and the refinancing of the Old Debt, after

crediting the contributions referred to in paragraphs 38, 39 and 40 hereof,

provided such amount does not exceed $1,353,600 (the “New Debt”), in

accordance with the terms set forth on the term sheet attached hereto as

Exhibit “C” and such other terms and conditions as are usual and customary

in Arkansas Natural Resources Commission financings, provided such terms

and conditions are acceptable to CAW, as receiver, and not contrary to any

terms or conditions of this Order.

43. Brushy Island, not CAW, shall be solely responsible for repayment of

the New Debt.

44. CAW, as receiver for Brushy Island, is hereby empowered to execute

all documents on behalf of Brushy Island and enter into the necessary

agreements for the borrowing of the New Debt.

3

45. In addition, CAW, as receiver for Brushy Island, is at liberty and is

hereby empowered to borrow by way of a revolving credit or otherwise, such

monies from time to time as it may consider necessary or desirable, provided

that the outstanding principal amount does not exceed $250,000 (or such

greater amount as this Court may by further order authorize) at any time, at

such rate or rates of interest as it deems advisable for such period or periods

of time as it may arrange, for the purpose if funding the exercise of the powers

and duties conferred upon CAW by this order, including interim

expenditures.

On December 30, 2014, appellants—residents of the Brushy Island section of the

City of Sherwood—filed a petition for declaratory judgment against CAW and the City of

Sherwood, stating in part:

10. On February 24, 2003, City’s then serving alderman approved

Resolution No. 3–2003 (a copy of which is attached hereto as Exhibit F and

incorporated by reference), which obligated the City to pay CAW the

approximate sum of $170,373.00 for the City’s share of the costs of fire

protection improvements to the BIWA. Prior to the vote on said Resolution,

then City Mayor Bill Harmon spoke in favor of the Resolution as follows:

“Central Arkansas Water Systems has agreed to help pay for a 24 [inch] water

main which would benefit Jacksonville and Sherwood. This will allow for

the entire City [of Sherwood] to have ample pressure throughout the City

with the exception of the Sylvan Hills School area.” (Minutes of said

February 24, 2003 meeting are attached hereto as Exhibit G and incorporated

by reference.) Ultimately, the City paid $170,000.00 to CAW as its share of

the project per the receipt attached hereto as Exhibit H and incorporated by

reference.

11. CAW, as Receiver for the Authority, entered into a contract

for the installation of the 24–inch water Transmission main and other work

(the “Project”), about three-fourths of which is located in the City, the other

one-fourth located in Pulaski County. The total cost of the project was

$2,243,993.00, paid as follows: $1,353, 600.00 paid by the Authority water

users (this includes the satisfaction of the Authority’s then outstanding bonded

indebtedness of $122,000.00); $165,690.39 paid by CAW; $170,000.00 paid

by the City and, $554,702.61 paid by the Jacksonville Water Works, per

Exhibit J attached hereto and incorporated by reference. The $1,353,600.00

final cost of the Project allocated to Authority water users is payable in

monthly installments for a period of 30 years at the rates set forth in said

Exhibit J.

4

12. The Project improved the City’s ISO (Insurance Services

Office, Inc.) rating. Effective December 1, 2000, the City achieved a public

protection Class Four (4) rating, per the September 15, 2000 ISO letter

attached hereto as Exhibit K and incorporated by reference. Effective July 1,

2005, the City achieved a public protection Class 3/9 rating, per the March

31, 2005 ISO letter attached hereto as Exhibit L and incorporated by

reference. Effective June 1, 2007, after the completion of the Project, the

City achieved a public protection Class 2/9 rating, per the March 19, 2007

letter attached hereto as Exhibit M and incorporated by reference.

13. The City is charging CAW a franchise fee based on CAW’s

gross revenues from its operation, maintenance and extension of water service

to the City pursuant to Ordinance No. 1978, an unexecuted copy of which

is attached hereto as Exhibit N and incorporated by reference.

WHEREFORE, Petitioners, Robert T. Williams, Owen

Honeysuckle, Rose White, Wayne Nunnerly, Lela Burns and Barbara

Mitchell pray judgment against Respondents City of Sherwood and Central

Arkansas Water declaring their rights, status and other legal relations affected

by City Resolution No. 3–2003 and City Ordinance No. 1978 as follows:

A. The City of Sherwood has delegated to Central Arkansas Water

the right and duty to provide water service to all residents of the City of

Sherwood;

B. Petitioners and all other water users in the Brushy Island Public

Water Authority are receiving no greater benefit from the 24–inch water

Transmission main and other work than the other residents of the City of

Sherwood who are not paying a monthly assessment fee for that project;

C. Those City of Sherwood residents who are not members of the

Brushy Island Public Water Authority are receiving a benefit by way of the

Class 2/9 ISO rating for which they are making no monthly payment for the

24–inch water Transmission main and other work; and,

D. Petitioners are entitled to all other legal, equitable and proper

relief.

The City of Sherwood and CAW separately filed timely answers. CAW then filed

a motion for summary judgment and brief in support arguing that CAW was entitled to

judgment as matter of law for three reasons: (1) the petition failed to raise a justiciable

5

controversy; (2) any justiciable issue was barred by the claim-preclusion facet of res judicata;

and (3) the claims were barred because petitioners did not seek leave from the Third

Division of the Pulaski County Circuit Court prior to filing the petition, which was in

violation of the receivership order. The City of Sherwood moved to adopt CAW’s

summary-judgment motion and brief; however, no order was entered. Just before the

hearing on the summary-judgment motion, appellants filed a motion to dismiss CAW

pursuant to Rule 41(a)(1) of the Arkansas Rules of Civil Procedure; the circuit court granted

the motion and entered an order dismissing CAW. However, at the hearing, the City of

Sherwood orally moved to adopt all arguments made by CAW in its motion for summary

judgment and brief in support. The circuit court granted the City of Sherwood’s motion

to adopt and the hearing on the City of Sherwood’s motion for summary judgment was

held.

On September 13, 2018, the circuit court entered an order finding that

[a]fter a review of all pleadings, I grant the Motion for Summary Judgment.

Sherwood simply has no relief to offer the Petitioners. This case is guided by

the 2005 order of receivership. There being no justiciable controversy, nor

any relief that Sherwood could offer, I have no option but to grant the

Motion. Because I have granted the Motion for Summary Judgment, the

Petition for Declaratory Judgment is denied.

Appellants filed a motion for new trial on September 19, 2018. Following the

deemed denial of the motion for new trial, appellants now timely bring this appeal.

On appeal, appellants argue that in denying their declaratory-judgment petition and

granting the City of Sherwood’s motion for summary judgment, the circuit court erred in

finding (1) no justiciable controversy; (2) the City of Sherwood could provide no relief; and

6

(3) the case is guided by the 2005 receivership order, i.e., claims are barred by the claim-

preclusion facet of res judicata.

The purpose of the declaratory judgment statute is “to settle and to afford relief from

uncertainty and insecurity with respect to rights, status and other legal relations.” 2

Declaratory relief will lie when (1) there is a justiciable controversy; (2) it exists between

parties with adverse interests; (3) those seeking relief have a legal interest in the controversy;

and (4) the issues involved are ripe for decision. 3 Our declaratory-judgment act was not

intended to allow any question to be presented by any person; the matters must first be

justiciable. 4 To satisfy the first requirement and to show the existence of a justiciable

controversy, the complaint must show a reason to answer the question posed. 5 On appeal,

the question of whether there was an absence of a justiciable issue shall be reviewed de novo

on the record of the circuit court. 6

Appellants argue that there is some uncertainty regarding City Resolution No. 3–

2003 and whether the $170,373 it authorized the mayor of the City of Sherwood to

contribute toward the improvements of the Brushy Island water system was to be applied

2

Ark. Code Ann. § 16-111-102(a) (Repl. 2006).

3

Baptist Health Sys. v. Rutledge, 2016 Ark. 121, 488 S.W.3d 507.

4

Lewis v. Hobbs, 2014 Ark. 407, 443 S.W.3d 530.

5

Andres v. First Ark. Dev. Fin. Corp., 230 Ark. 594, 324 S.W.2d 97 (1959).

6

Baptist Health Sys., supra.

7

to the Authority’s $1,219,002.15 share of the cost of the project. 7 Appellants further

contend there are uncertainties as to whether the appellants are “paying more than their fair

share in terms of the value they received compared to the value received by all other

residents (non-Authority members) of Sherwood, who are making no payment toward

satisfaction of the $1,219,002.15 bonded indebtedness.” Appellants argue that due to the

uncertainties, the circuit court erred in finding there is no justiciable controversy.

Specifically, appellants urge that the justiciable controversy presented in the petition

for declaratory judgment to the circuit court was “the issue of the allocation of the cost of

the Project . . . .” However, the allocation of the cost of the project was sufficiently detailed

in the receivership order entered by the circuit court in October 2005 and affirmed in

Williams. 8 Appellants’ contention that there are “uncertainties” regarding funding of the

project is not supported by the evidence. Instead, we find that appellants’ argument that

the City of Sherwood is unfairly benefiting from the project is an attempt to in some way

modify the financing and contribution arrangements outlined in the receivership order,

which we decline to do.

Additionally, the uncertainties of which appellants complain are related to the

financing of the project as outlined in the receivership order. Because the City of Sherwood

has no control over the receivership or the handling or financing of the projects undertaken

pursuant to its authority, any declaration of “fairness” will have no effect as the City of

7

Appellants make the same argument with respect to the contributions made by the

City of Jacksonville; however, the City of Jacksonville is not a party to this action.

8

Supra.

8

Sherwood is not in a position to provide relief, nor have appellants asserted that the City of

Sherwood can provide any relief. Appellants have shown no reason to answer any question

posed in its petition for declaratory judgment. Therefore, we affirm the circuit court’s denial

of appellant’s petition for declaratory judgment finding that no justiciable controversy exists.

Because we find no justiciable controversy exists, we need not address appellants’

remaining arguments on appeal.

Affirmed.

GLADWIN and MURPHY, JJ., agree.

James F. Lane, P.A., by: James F. Lane, for appellants.

Stephen Cobb, Sherwood City Attorney, for appellee.

9