Opinion

ECC International Constructors, LLC

Court
Armed Services Board of Contract Appeals
Filed
Apr 18, 2025
Status
Published
On the bench
McIlmail
Cited by
0 cases
Authority
More cited than 36.3%

rejecting contention that regulation’s language was “precatory” or “aspirational,” and “thus lacking in operative force” where it “speaks not in vague generalities but in precise terms”

How later courts described this case

  • rejecting contention that regulation’s language was “precatory” or “aspirational,” and “thus lacking in operative force” where it “speaks not in vague generalities but in precise terms”
  • “The testimony and conclusions of one expert clearly were designed to mesh with the Government’s legal theories. His refusal to acknowledge input from counsel in reaching his conclusions were not credible.”
  • discerning “a strong partisan position by [expert] in favor of plaintiff, in conflict with one of his duties as an expert witness to objectively assist the court to understand the facts and issue”
  • contractor’s contemporaneous admissions were “probative evidence that generators did not comply with the contract” (citations omitted)

Written by the judges who cited it.

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - )

)

ECC International Constructors, LLC ) ASBCA No. 59586

)

Under Contract No. W912ER-10-C-0054 )

APPEARANCES FOR THE APPELLANT: R. Dale Holmes, Esq.

Michael H. Payne, Esq.

Cohen Seglias Pallas Greenhall & Furman PC

Philadelphia, PA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.

Engineer Chief Trial Attorney

Martin Chu, Esq.

Katherine M. Smith, Esq.

Engineer Trial Attorneys

U.S. Army Engineer District, Middle East

Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL

In this appeal concerning a contract to design and construct a 20-building

military compound in Afghanistan, appellant, ECCI International, Inc. (ECCI), alleges

government-caused project delay and other matters, and requests $9,035,587 and the

return of 400 days of withheld liquidated damages. 1 In 2020, the Board conducted a

two-week hearing of this and a companion appeal, ASBCA No. 59643. Although the

parties have briefed the two appeals together, ASBCA No. 59643 will be the subject of

a separate opinion. We have previously issued opinions in and related to ASBCA

Nos. 59586 and 59643, and assume familiarity with those opinions.

FINDINGS OF FACT

1. The Contract, Performance, and Design Review

The contract was awarded on September 29, 2010, in the amount of

$29,186,338, and called for ECCI to design and construct a 70,000 square meter

compound whose primary facilities included a communications building. 2 ECCI was

1

App. br. at 116.

2

R4, tab 5 at 2, 179 § 1.1.

to complete the work within 548 days of receipt of the notice to proceed. 3 After

modifications, the revised contract completion date was March 13, 2013. 4

The contract is of the “design-build” type. 5 Section 3.9 of the contract provides

that ECCI’s design submittals were required to be submitted for government approval

at the “Preliminary (65%), Final (95%), and at the Cleared for Construction (100%)

stage[s].” 6 Section 3.9.2, “Final Design Review Submittal (95%),” provides that

“[t]he review of this submittal is to insure that the design is in accordance with

directions provided the Contractor during the design process,” and that “[t]he only

effort remaining between the FINAL DESIGN REVIEW SUBMITTTAL and the

‘CLEARED FOR CONSTRUCTION’ DESIGN REVIEW SUBMITTAL is the

incorporation of the Government Review Comments.” 7

The government approved ECCI’s 95% design on August 23, 2011, providing

56 comments on the communications design, one of the ten components of ECCI’s

proposed design. 8 ECCI submitted its 100% design on November 19, 2011,

incorporating those comments. 9 Most of the project’s buildings were cleared for

construction in December 2011. 10 However, on December 16, 2011, the government

disapproved the 100% design, providing 226 new comments on the communications

design. 11 The government would require ECCI to submit the 100% communications

design for review no fewer than three more times before approving it. 12

On November 16, 2012, nearly a year after ECCI submitted its 100%

communications design, Robert C. Vanoer, Jr., the government’s resident engineer and

contracting officer’s representative (COR), wrote to ECCI that “[t]he lack of an

approved communications design is causing delays to the project.” 13 At the hearing of

3

R4, tab 5 at 39.

4

See gov’t br. at 3; app. reply at 4.

5

See R4, tab 5 at 179 ¶ 1.1.

6

R4, tab 5 at 250.

7

R4, tab 5 at 251 (capitalization in original).

8

R4, tab 742; app. supp. R4, tab 471; tr. 8/97-98; see app. br. at 4 ¶ 23; 32; gov’t br.

at 18.

9

R4, tab 201; see app. br. at 6 ¶ 29; gov’t br. at 18-19.

10

Tr. 1/36.

11

R4, tab 878; tr. 8/97-98; app. br. at 7 ¶ 35; see gov’t br. at 16 ¶ 17.

12

See app. br. at 9 ¶ 46; gov’t br. at 21 (chart).

13

R4, tab 367; tr. 6/87-88.

2

the appeal, Mr. Vanoer stood by that position. 14 Mr. Vanoer also testified that he

agreed, at the time, with an assessment expressed in a November 2012 government

information paper that “the contract has had significant delays due to,” not only

“contractor inefficiencies,” but “design changes” and (in what we take to be a

reference to the government) “user requested changes.” 15 Mr. Vanoer provided further

testimony indicating that a statement in a January 2013 government email chain that

“getting the contractor to comply with our comms and HVAC design review

comments will cause an eight-month delay” to the project was consistent with his own,

contemporaneous understanding. 16

In addition, on December 6, 2012, the government’s Administrative

Contracting Officer (ACO) John Long wrote to ECCI that:

As a result of the ECC’s [sic] failure to date to submit a

proper Communication System Design, I consider this a

contractor caused delay, and the Government is not liable

for any indirect cost(s) for the entire period, including the

time to complete the design, submit the design for

approval, complete installation, testing and obtain the

Government’s acceptance of the Communication System.

...

To mitigate your costs, reduce your delay, and complete

this important project, the Government is prepared to meet

weekly (via teleconference) to assist your subcontractor. 17

Mr. Long did not testify at the 2020 hearing of this appeal.

The government finally approved ECCI’s 100% communications design on

March 14, 2013, 454 days after initially disapproving that design on December 16,

14

Tr. 6/86-89. Mr. Vanoer also agreed that he had “authority to make official

responses to the contractor, request changes for the project, and direct

contractor’s [sic] activities.” Tr. 6/123-24 (concerning app. supp. R4, tab 111).

15

Tr. 6/107-09 (concerning app. supp. R4, tab 755).

16

See tr. 6/110-11 (concerning app. supp. R4, tab 168 at 1).

17

R4, tab 384 at 1.

3

2011. 18 ECCI substantially completed the project on April 19, 2014, 19 402 days after

the March 13, 2013, revised completion date.

2. The Entry Control Point Security Changes

The contract provides that the compound to be constructed would be sited on a

dedicated area located outside the perimeter fencing of an existing military base. 20 In

2012, an International Security Assistance Force completed “an expansion of the base

security fence that encompassed the contract work site, and . . . exercised its authority

to establish, monitor, and enforce all of the security procedures at the worksite.” ECC

Int’l Constructors, LLC (ECCI), ASBCA No. 59138 et al., 19-1 BCA ¶ 37,252

at 18,314; aff’d sub nom. ECC Int’l Constructors, LLC (ECCI) v. Sec’y of the Army,

817 F. App’x 952 (Fed. Cir. 2020) (table).

3. The Claims and Resulting Appeals

a. ASBCA No. 59138: the appeal from the contracting officer’s decision

upon the October 8, 2013 claim

On October 8, 2013, ECCI presented to the contracting officer a claim for

$807,987.56 and 19 days of delay that ECCI said were the result of changes in security

requirements at the site; specifically, ECCI pointed to “changes to the site that were

made after Contract award, that changed [the] project from ‘outside the wire’ to ‘inside

the wire.’” 21 ECCI explained that the costs and delays at issue “start[ed] on April 7,

2012, and [were] continuing” through at least October 7, 2013, the date of the

certification of the claim. 22 On January 18, 2014, the contracting officer issued a final

decision upon that claim, granting an extension of time of 19 calendar days, and

denying the remainder of the claim. 23 ECCI appealed from that decision on

January 22, 2014. The Board docketed that appeal as ASBCA No. 59138. In its

February 13, 2014 complaint in ASBCA No. 59138, ECCI alleged that:

[a]s a direct result of the changed security requirements,

ECCI suffered 19 calendar days of delays to performance

18

App. supp. R4, tab 177; see ex. 2 (demonstrative).

19

Gov’t br. at 3 ¶¶ 12-13; app. reply at 4.

20

R4, tab 5 at 179 § 1.2.

21

R4, tab 70 at 1, 5.

22

See R4, tab 70 at 3, 5-6.

23

See R4, tab 2 at 1, 12.

4

of the work from early April 2012 through the end of July

2012. 24

ECCI requested $806,732.10, “19 calendar days of time extension,” and a “finding that

the change of site access and security requirements was a compensable change under

the Changes Clause . . . .” 25

b. February 12, 2014 Claim

On February 12, 2014, ECCI presented a claim (Letter H-155) to the

contracting officer, requesting $13,519,913.91 and 329 days of delay for

(1) “[c]hanges directed by the Government to address security requirements for the

contract”; (2) “[t]he 95% and 100% communications design submissions”; and

(3) “[o]ther directives to perform additional work or to change the requirements of the

contract.” 26 In that claim, ECCI represented that from May 15, 2012, through

October 26, 2013, the project experienced 205 days of delay due to changes in the

security posture of the work site (also known as changes to “entry control points”

(ECPs)). 27 More specifically, ECCI explained that from September 29, 2010, through

October 26, 2013, “the project experienced 205 days of ECP [security changes] delays,

and a total of 389 days of Design delays of which 205 days were concurrent to the

ECP delays.” 28 ECCI relied upon the work of Lombardia Consultants for that delay

analysis. 29 No one from Lombardia testified at the hearing of this appeal.

c. Liquidated Damages

On April 9, 2014, an administrative contracting officer (not Mr. Long) assessed

and withheld $940,273.98 in liquidated damages for 402 days of delay, at $2,338.99

per day. 30 ECCI Int’l Constructors, LLC (ECCI), ASBCA No. 59586, 22-1 BCA

38,131 at 185,228. ECCI has not appealed from that assessment.

24

ASBCA No. 59138 compl. at 7 ¶ 39.

25

ASBCA No. 59138 compl. at 10.

26

R4, tab 72 at 1.

27

R4, tab 72 at 59-61, 65. Despite such assertions, ECCI says that “[s]ecurity was

never claimed as a delay issue.” App. br. at 61; see also app. reply at 4, 15, 44.

Nor does ECCI currently say that the ECP security changes constitute an

excusable delay entitling it to remission of liquidated damages. See app. br.

at 26 ¶ 127; reply at 4.

28

R4, tab 72 at 65-66.

29

See tr. 1/241; R4, tab 72 at 273, 333, 608; app. br. at 61.

30

Gov’t br. at 33; R4, tab 816 at 2.

5

d. ASBCA No. 59586: the pending appeal from the deemed denial of the

February 12, 2014 claim

On September 18, 2014, ECCI noticed to the Board its appeal from what ECCI

evidently mischaracterized as the deemed denial of its “May 2, 2014” claim. ECCI

further explained that its “May 2, 2014” claim “was in the amount of ‘$13,519,913.01

and 329 calendar days of delay.’” Despite its references to “May 2, 2014,” we

understand ECCI’s September 18, 2014 notice to appeal from the deemed denial of its

February 12, 2014 claim (Letter H-155) for $13,519,913.91 and 329 days of delay.

The Board docketed ECCI’s September 18, 2014 appeal as ASBCA No. 59586.

On October 23, 2014, ECCI filed a three-count complaint in ASBCA No. 59586.

Count I of the complaint alleges that “[a]s a direct result of the changed security

requirements” at the work site, “ECCI suffered significant delays to performance of

the work from early April 2012 through the end of the project.” 31 Count II alleges

government delays in reviewing “ECCI’s 95%, 100%, and 100% redesign submittals,”

as well as the government’s “directives to perform additional work.” 32 Count III

alleges that the government directed ECCI to perform several specified items of

allegedly extra-contractual work. 33 Count III further alleges that:

[a]s a direct result of all of the directed changes included in

Count III, ECCI incurred critical delays to completion of

the project; the delay costs associated with the directed

changes are included in this claim, while the actual

increase in design, procurement, shipping and construction

costs are included in ECCI’s separate May 2, 2014

Certified Claim.” 34

In its prayer for relief, ECCI again requested $13,519,913.91 and 329 days of delay. 35

31

ASBCA No. 59586 compl. at 7 ¶ 39.

32

ASBCA No. 59586 compl. at 10.

33

ASBCA No. 59586 compl. at 27-38 ¶¶ 156-229. Count III of the complaint in

ASBCA No. 59586 includes allegations of government-directed changes that

are not addressed in ECCI’s briefing of ASBCA No. 59586. To the extent

those allegations appear in ECCI’s briefing of ASBCA No. 59643, we reserve

them for decision in ASBCA No. 59643; otherwise, they are waived. See

Bannum, Inc. v. United States, 779 F.3d 1376, 1382 (Fed. Cir. 2015).

34

ASBCA No. 59586 compl. at 38 ¶ 228.

35

ASBCA No. 59586 compl. at 38.

6

e. ASBCA No. 59643: the pending appeal from the deemed denial of the

May 2, 2014 claim

On May 2, 2014, ECCI presented a claim (Letter H-158) to the contracting

officer, requesting “$3,767,856.32 for the cost impacts” that ECCI claimed were

“directly attributable to the extra work caused and directed by the Government during

execution of the project.” 36 On October 24, 2014, ECCI noticed its appeal from the

deemed denial of that claim, and filed a complaint requesting $3,767,856.32, and that

the Board find that the government “caused additional costs through its handling of the

design review process” and “directed performance of changed work.” 37 The Board

docketed the appeal as ASBCA No. 59643.

f. ASBCA No. 60284: the dismissed appeal from the deemed denial of the

August 11, 2015 claim

On August 11, 2015, ECCI presented to the contracting officer a claim for

$227,987, alleging “directed changes that occurred during the design and construction

of this project.” 38 On October 14, 2015, ECCI noticed its appeal from what it

characterized as the deemed denial of that claim. The Board docketed that appeal as

ASBCA No. 60284. In its October 31, 2015 complaint in that appeal, ECCI requested

$227,986.54, including for “accelerated and phased turnover.” 39 In a pre-hearing brief

filed in ASBCA Nos. 59138, 59586, 59643, and 60284 on February 7, 2020, in which

ECCI requested $13,698,255.40, ECCI again requested $227,986.54 of that amount

based upon the allegation that the government had directed ECCI “to turnover [sic]

buildings in a phased completion.” 40 On February 21, 2020, ECCI requested dismissal

of ASBCA No. 60284 with prejudice. The Board dismissed ASBCA No. 60284 with

prejudice on February 24, 2020. 41

36

R4, tab 75 at 1, 6.

37

ASBCA No. 59643 compl. at 14.

38

October 14, 2015, notice of appeal.

39

ASBCA No. 60284 compl. at 5. We understand the terms “phased turnover” and

“phased handover” to be synonymous.

40

App. prehearing br. at 24-26.

41

During the hearing, ECCI’s counsel confirmed that although the claim for

acceleration damages set forth in ASBCA No. 60284 was no longer before the

Board, the “acceleration claim in the delay claim” (presumably set forth in

ASBCA No. 59586), and its associated alleged damages, were still before the

Board. Tr. 9/49-50.

7

g. Summary Judgment

On January 24, 2019, in ASBCA Nos. 59138 and 59586, the Board ruled upon

the parties’ cross-motions for partial summary judgment upon the question, referring

to the ECP security changes, “whether, when a third party controlling a military base

interfered with access to a compound that the government contracted appellant to build

outside the base, an express contract warranty was breached, entitling appellant to

recover for a constructive change to the contract.” ECCI, 19-1 BCA ¶ 37,252

at 181,314. The Board denied ECCI’s motion for summary judgment and granted the

government’s request for partial summary judgment that “[t]he change to the security

posture of the . . . Compound was not a constructive change to the Contract for which

[ECCI] is entitled to Compensation.” Id. at 181,314-15. Specifically, the Board

granted the government’s cross-motion for partial summary judgment “on the issue of

entitlement with regard to ASBCA No. 59183 and Count I of ASBCA No. 59586 . . .

to the extent set forth” in the Board’s decision. Id. at 181,315. On June 5, 2020, the

United States Court of Appeals for the Federal Circuit affirmed the Board’s opinion,

explaining that the government was not liable for increased costs caused by the

changes in the security posture of the project. ECCI, 817 F. App’x at 953.

h. Expert Delay Report of William Schwartzkopf

On January 3, 2020, nearly a year after the Board ruled that the ECP security

changes at the worksite were not compensable, a delay expert, William Schwartzkopf,

of Sage Consulting, issued a report in support of ECCI’s delay claims. 42

Mr. Schwartzkopf opined that crediting for time extensions, the project experienced

three periods of compensable critical path delay totaling 420 days: (1) 290 days from

March 23, 2012 through March 14, 2013, for the communications redesign;

(2) 53 days from May 28, 2013, through September 15, 2013, for “[a]dded

communications outlets,” and (3) 77 days from November 5, 2013, through

February 28, 2014, for “dedicated electrical panels in communication rooms.” 43

Mr. Schwartzkopf explained that, in arriving at that conclusion, he modeled “[t]wenty-

two impact events—including both potential ECCI-caused delays and potential

Government-caused delays . . . with [Time Impact Analysis (TIA)] schedules to

determine what, if any, impact these issues had on Project Completion.” 44 And in an

undated supplemental “concurrency analysis” to his expert report, presumably

completed after the date of the expert report itself but no later than February 24, 2020

42

App. supp. R4, tab 1251; tr. 3/48, 91, 102.

43

App. supp. R4, tab 1251 at 35-36.

44

App. supp. R4, tab 1251 at 32.

8

(when the hearing of these appeals began), Mr. Schwartzkopf explained, referring to

his 22-item set of potential project delay events, that:

For each of the following impact events, which include

potential [government]-caused delays and known potential

contractor-caused delays, a fragnet—a fragmentary

network, which is a sequence of linked activities—was

built to represent the development and resolution of the

issue[.] 45

A “fragnet” is “a sequence of new activities and/or activity revisions, logical

relationships, and resource changes added to an existing schedule to demonstrate the

influence of a new activity on the schedule.” Nassar Grp. Int’l N.G.I. S.A.L.

(Offshore) R.C., Doing Bus. As NGI Afghanistan for Contracting, ASBCA No. 58451

et al., 22-1 BCA ¶ 38,206 at 185,549 n.15.

The government at least implies that Mr. Schwartzkopf’s opinion is not

credible, noting that absent from the 22 items for which Mr. Schwartzkopf created

fragnets are the ECP security changes that—prior to our 2019 opinion denying ECCI’s

summary judgment motion and granting the government’s summary judgment motion

upon the ECP security changes—ECCI represented had delayed the work from early

April 2012, through the end of the project. 46 Indeed, Mr. Schwartzkopf did not subject

the ECP security changes to the type of analysis to which he subjected the other

22 items, as his testimony on cross-examination makes clear:

Q. Do you have a fragnet for the entry control point

delay?

A. I do not. 47

Although Mr. Schwartzkopf was aware that ECCI had, in its February 12, 2014 claim,

asserted that the security change had delayed the project, 48 he testified in a remarkably

conclusory fashion that “[t]here was no point in modeling [the ECP security changes]

45

Ex. 6 at 2 (emphasis added).

46

Gov’t br. at 29; ASBCA No. 59586 compl. at 7 ¶ 39.

47

Tr. 2/275-76.

48

Tr. 2/273-74.

9

because it couldn’t have delayed design.” 49 When asked whether his analysis

considered “all of the delay events that impacted the project,” he answered:

There were several others that, just looking at them, it was

apparent that they did not cause a critical delay, or the

security change, where we looked at when it happened,

and the construction was on the critical path. 50

And although Mr. Schwartzkopf characterized the security change as insignificant, he

simultaneously testified that he listed the security change in his expert report as one of

several “known significant delays” that were “not incorporated in [his] model.” 51

Despite the testimony indicating that he “looked” at the ECP security

changes, 52 ECCI says that Mr. Schwartzkopf’s delay report “analyzes all potentially

significant delays on the project to establish the critical path delays.” 53 ECCI also says

that “[Mr.] Schwartzkopf testified that he analyzed all delays on the project.” 54

Neither is the case. Mr. Schwartzkopf did not analyze all the potential delay issues on

the project; nor did he testify that he did: specifically, Mr. Schwartzkopf did not

analyze the ECP security changes, at least not in the manner that, as ECCI recites in its

initial post-hearing brief, he analyzed the 100% communications design issue, the

communications outlets issue, and the dedicated electrical panels issue. That is,

Mr. Schwartzkopf did not make the ECP security changes the subject of a fragnet. 55

Again, although he was aware of the ECP security change issue when he issued his

expert report, in order “to evaluate whether the ECP delays may have caused a critical

path delay,” Mr. Schwartzkopf only “looked” at the ECP security changes; 56 he did

not subject that issue to the fragnet-based analysis to which he subjected 22 other

potential delay issues, evidently deliberately.

Indeed, one only has to refer to page 61 of ECCI’s initial post-hearing brief to

see the difference in the analyses performed by Mr. Schwartzkopf (and advanced by

ECCI). Regarding the dedicated electrical panels issue, ECCI says that

Mr. Schwartzkopf “analyzed this delay using a fragnet,” whereas, regarding the ECP

49

Tr. 2/254-55.

50

Tr. 2/254 (emphasis added).

51

Tr. 7/214 (alteration added).

52

See also tr. 3/55-56.

53

App. br. at 43.

54

App. br. at 52; see app. reply at 4.

55

App. br. at 57-62.

56

See app. supp. R4, tab 1251 at 21, 137-38.

10

security changes, ECCI says that Mr. Schwartzkopf “analyzed the security change,” 57

avoiding any reference to a fragnet, as ECCI must when discussing Mr. Schwartzkopf

and the ECP security changes, because Mr. Schwartzkopf did not “use a fragnet” to

analyze the ECP security changes.

ECCI says that “anyone looking at [the project] would see that security was

never the driving delay,” and that “the original analysis in ECCI’s claim showed

delays other than security were longer.” 58 We understand this to be not only a nod to

Mr. Schwartzkopf’s statement that he “looked” at the ECP security changes 59 (which

we take to mean that Mr. Schwartzkopf looked at what Lombardia had said about it),

but also a reference to Lombardia’s report, which we understand was a basis for

ECCI’s February 12, 2014 claim to the contracting officer. 60 Leaving aside for the

moment what Lombardia concluded—particularly because no one from Lombardia

ever testified in this appeal—if that is what ECCI means by delay analysis, we find it

no analysis at all.

What’s more, Mr. Schwartzkopf failed to create a fragnet for the ECP security

change issue even though he agreed that there was contemporaneous evidence in

ECCI’s project records that reflected that workers were delayed in getting through the

entry control points. 61 Indeed, Roger Khoury, the managing partner of Sabaton Salim

Construction Company (SSCC), a subcontractor to ECCI on the project, testified by

sworn declaration dated February 3, 2020, that “[t]he inefficient process of getting

workers through the base security ECP never got better from the time it was

implemented on June 1, 2012, until the project was completed.” 62 Mr. Khoury further

testified that “[a]s a direct result of the changes in security process for access to the

project site, SSCC incurred additional [costs] of 3 types over the 130 days of

Government caused delays, within the period February 2013 to November 2013.” 63

Mr. Khoury’s account is corroborated by Ajmal Imtiaz, the president of another

ECCI subcontractor at the worksite—IMTIAZ Group Construction (IGC)—whose

February 4, 2020 sworn declaration states—in language virtually identical to

Mr. Khoury’s—that “[t]he inefficient process of getting workers through the base

security ECP never got better from the time it started on June 1, 2012, until the project

57

App. br. at 61-62.

58

App. br. at 62.

59

See tr. 2/254.

60

See R4, tab 72 at 273, 333, 608; tr. 1/241-45; app. br. at 61.

61

See tr. 2/272.

62

Ex. 12 at 1, 5-6, 17 (emphasis added).

63

Ex. 12 at 9 (emphasis added).

11

was completed,” and that “[a]s a direct result of the security procedures, IGC incurred

additional costs of 3 types over the 130 days of Government caused delays, within the

period February 2013 to November 2013.” 64 Indeed, Mr. Imtiaz agreed that “[t]he

ECP delay caused more delay to [IGC’s] work on the project than the refinishing after

communications installation,” 65 at least suggesting that the ECP security changes

outlasted the 100% communications design issue as a delay event. And of course,

ECCI admits in its complaint in this appeal that ECP security changes delayed the

project from “April 2012, through the end of the project.” 66 Because

Mr. Schwartzkopf omitted the ECP security changes from the fragnet-based delay

analysis to which he subjected 22 other potential delay issues, we find his delay

opinion not credible, and reject it.

DECISION

In its initial, post-hearing brief in ASBCA No. 59586, ECCI sets forth the

following claims: (1) “improper design review of ECCI’s 95% design submittal;” 67

(2) 420 days of compensable and excusable project delay due to (a) the government’s

allegedly improper review of ECCI’s 100% communications design (290 days), (b) a

government-directed increase in the quantity of communication outlets (53 days), and

(c) a government-directed requirement to provide dedicated electrical panels in

communications rooms (77 days); 68 (3) apparently in support of that improper review

claim, a breach of the implied duty of good faith and fair dealing; 69 (4) that the

government failed to reimburse ECCI for all of ECCI’s Defense Base Act (DBA)

payments; 70 and (5) that the government constructively accelerated the project

schedule. 71

64

Ex. 13 at 1, 5, 6-7, 15 (emphasis added).

65

Tr. 4/43, 62.

66

ASBCA No. 59586 compl. at 7 ¶ 39 (emphasis added).

67

ASBCA No. 59586 compl. at 26-27 ¶ 155.

68

App. br. at 1, 20, 23, 57-62, 110-11. Regarding delay periods and liquidated

damages, ECCI variously references 400 days, 402 days, and 420 days. App.

br. at 62, 111, 116; app. reply at 4, 44. Although the three components of

ECCI’s delay claim total 420 days, app. br. at 26 ¶ 127, ECCI seeks $940,274

in withheld liquidated damages (app. br. at 110; reply at 4), which at 2,338.99

per day equates to 402 days; that $940,274 is equivalent to the $940,273.98

(unrounded) that the government assessed and withheld.

69

App. br. at 14.

70

App. br. at 29-30.

71

App. br. at 19 ¶¶ 81, 86-87; see gov’t br. at 42 ¶ 48 (citing R4, tab 72).

12

I. Review of 95% Design Submittal

In its complaint in ASBCA No. 59586, ECCI presents a claim for recovery

related to the alleged “improper design review of ECCI’s 95% design submittal.” 72

Because we find in ECCI’s post-hearing briefing no separate claim for “improper

design review of ECCI’s 95% design submittal,” that claim is waived or abandoned. 73

See Bannum, 779 F.3d at 1382; SmithKline Beecham Corp. v. Apotex Corp., 439 F.3d

1312, 1319 (Fed. Cir. 2006); Sarro & Assocs., Inc. v. United States, 152 Fed. Cl. 44,

58-59 (2021).

II. Delay Claims

A. Jurisdiction

Again, in ASBCA No. 59586, ECCI claims 420 days of compensable and

excusable project delay due to (a) the government’s allegedly improper review of

ECCI’s 100% communications design (290 days), (b) a government-directed increase

in the quantity of communication outlets (53 days), and (c) a government-directed

requirement to provide dedicated electrical panels in communications rooms (77 days).

The government challenges whether those claims have been presented to the

contracting officer. 74 For the Board to possess jurisdiction to entertain a claim, the

claim must first have been presented to a contracting officer. CDM Constructors, Inc.,

ASBCA No. 59524, 15-1 BCA ¶ 36,097 at 176,238. ECCI’s February 12, 2014 claim

to the contracting officer claims project delay allegedly caused by (1) the

government’s 100% design review, 75 (2) government direction to increase the quantity

72

ASBCA No. 59586 compl. at 26-27 ¶ 155.

73

The government challenges other items that ECCI asserted in a spreadsheet

presented during the hearing (1) an “unpaid balance,” (2) claim preparation

costs, and (3) bond costs (app. reply at 43). (Gov’t br. at 40, 45-46; app. supp.

R4, tab 305; tr. 1/290). ECCI does not assert those three claims in its initial

post-hearing brief, although two of those claims (claim preparation costs and

bond costs) are referenced in ECCI’s reply brief. App. reply at 21, 43. Those

items are waived. See Bannum, 779 F.3d at 1382.

74

Gov’t br. at 4.

75

R4, tab 72 at 8.

13

of electrical outlets, 76 and (3) government direction to provide dedicated electrical

panels. 77 Consequently, we possess jurisdiction to entertain those claims. 78

With respect to liquidated damages, the contract provides that “[i]f the

Contractor fails to complete the work within the time specified in the contract, the

Contractor shall pay liquidated damages to the Government in the amount of

$2,338.99 for each calendar day of delay until the work is completed or accepted.” 79

Both parties claim entitlement to some $940,274 in liquidated damages. 80 On April 9,

2014, the government assessed and withheld $940,273.98 in liquidated damages for

402 days of delayed completion, at the contract rate of $2,338.99 per day. 81 ECCI,

22-1 BCA ¶ 38,131 at 185,228. That assessment is a government claim. Parsons

Evergreene, L.L.C., ASBCA No. 57794, 12-2 BCA ¶ 35,092 at 172,347; K-Con Bldg.

Sys., Inc. v. United States, 107 Fed. Cl. 571, 587 (2012).

B. Mr. Schwartzkopf’s expert delay opinion is not credible

For ECCI to recover for a compensable delay, it “must prove that the

government was the sole cause of the delay and that the appellant did not contribute to

or concurrently cause such delay.” Insulation Specialties, Inc., ASBCA No. 52090,

03-2 BCA ¶ 32,361 at 160,101. Additionally, ECCI “‘must show that the

government’s actions affected activities on the critical path of [ECCI’s] performance

of the contract.’” O-Tech Sols., LLC, ASBCA Nos. 61898, 62095, 23-1 BCA ¶ 38,338

at 186,169. To establish entitlement to an extension based on excusable delay, ECCI

must show that the delay resulted from unforeseeable causes beyond the control and

without the fault or negligence of ECCI, and that the unforeseeable cause delayed the

overall contract completion; that is, the delay must have affected the critical path of

performance. Sauer Inc. v. Danzig, 224 F.3d 1340, 1345 (Fed. Cir. 2000).

To demonstrate that the government delayed project performance, ECCI relies

primarily upon the opinion of Mr. Schwartzkopf. To be credible, a contractor’s delay

76

R4, tab 72 at 29-31.

77

R4, tab 72 at 49-50.

78

In ECC Int’l Constructors, LLC, ASBCA No. 59586, 24-1 BCA ¶ 38,489

at 187,083-84, we denied the government’s motion that we dismiss certain

claims, for lack of jurisdiction, for failure to state sums certain.

79

R4, tab 5 at 39 ¶ 52.211-12(a) (FAR 52.211-12(a), LIQUIDATED DAMAGES –

CONSTRUCTION (SEP 2000)).

80

See app. br. at 110-11, 116; gov’t br. at 2-3, 40, 120; app. reply at 4.

81

Gov’t br. at 3; FAR 52.211-12(a), LIQUIDATED DAMAGES – CONSTRUCTION

(SEP 2000) (R4, tab 5 at 39).

14

analyst must take into account, and give appropriate credit for, all of the delays that

were alleged to have occurred. See Gulf Contracting, Inc., ASBCA No. 30195,

89-2 BCA ¶ 21,812 at 109,759; aff’d, 23 Cl. Ct. 525 (1991); aff’d per curiam,

972 F.2d 1353 (Fed. Cir.) (table) (June 5, 1992); see also Pathman Constr. Co.,

ASBCA No. 23392, 85-2 BCA ¶ 18,096 at 90,837, 90,846-47 (rejecting delay analysis

with “built-in bias”). We have found that Mr. Schwartzkopf deliberately omitted from

the crux of his delay analysis the ECP security changes that—until we ruled against

ECCI upon that issue—ECCI had alleged delayed its performance. That is,

Mr. Schwartzkopf did not make the ECP security changes the subject of a fragnet, as

he did 22 other potential delay events. That renders Mr. Schwartzkopf’s opinion not

credible, and therefore, not helpful to us or to ECCI’s case. Cf. Fireman’s Fund Ins.

Co. v. United States, 92 Fed. Cl. 598, 669-70 (2010) (“Cross-examination assaulted

[plaintiff’s delay expert’s] inclusion of all concrete activity on plaintiffs’ as-built

critical path—which extends through the construction of the floating guidewalls—

at the expense of omitting the installation of the Project’s control systems in the

control tower”); E. Minerals Int’l Inc. v. United States, 39 Fed. Cl. 621, 627 (1997)

(“The testimony and conclusions of one expert clearly were designed to mesh with the

Government’s legal theories. His refusal to acknowledge input from counsel in

reaching his conclusions were not credible.”), judgment rev’d on other grounds,

appeal dismissed sub nom., Wyatt v. United States, 271 F.3d 1090 (Fed. Cir. 2001);

Mega Constr. Co. Inc., v. United States, 29 Fed. Cl. 396, 434 (1993) (discerning “a

strong partisan position by [expert] in favor of plaintiff, in conflict with one of his

duties as an expert witness to objectively assist the court to understand the facts and

issue”). “We are free to reject expert testimony [that] we find intrinsically

unpersuasive,” Reflectone, Inc., 98-2 BCA ¶ 29,869 at 147,829, and here, we find

Mr. Schwartzkopf’s opinion intrinsically unpersuasive.

Indeed, what Mr. Schwarztkopf did conflicts with what ECCI’s counsel forecast

on the first day of the hearing of this appeal. Counsel offered the following

explanation of how delay experts conduct a “time impact analysis” (TIA) of the type

that Mr. Schwartzkopf performed, pointing out the importance of making potential

delay events the subject of fragnets in order to determine what delayed a project’s

critical path:

[T]hey chop the project into different sections of time

based on the delay events, and then they do the time-

impact analysis doing the fragnets . . . .

Or maybe new delay items came into the picture

and the expert has to use his professional judgment to say

well there’s some new delay issues that are starting, so I

15

need to start a new window and then I need to do a new

impact window for that analysis and new fragnets for

those.

...

You need to do a time impact for each potential delaying

issue . . . .

But if you’ve not looked at all the other issues that

are potentially delaying, like the contractor’s issues or

other government issues, then you’re not going to know

which one is actually the critical path delay. 82

Even Mr. Schwartzkopf’s testimony highlights, although in awkward phrasing, the

importance of fragnets in delay analysis:

Q: But if the 100 percent design was never on the critical

path, how could it have become critical at all?

A: Well, any activity can become critical if it’s extended or

pushed out. When we put a fragnet in, the model that it will

push out [sic]. 83

And ECCI concisely describes how, in analyzing the alleged communications outlets

delay, Mr. Schwartzkopf relied upon a fragnet:

A fragnet was created and inserted, showing the increased

outlets as a driving delay. 84

Even judged by ECCI’s own standard, then, by not making the ECP security

issue the subject of a fragnet, Mr. Schwartzkopf cannot know—and so neither from his

opinion can the Board know—whether the ECP security changes were a critical path

delay. Moreover, Mr. Schwartzkopf failed to meet the standard that he used to

82

Tr. 1/86-88.

83

Tr. 3/67-68 (emphasis added).

84

App. br. at 60. ECCI apparently uses the term “driving delay” to refer to the

concept of critical path delay. See, e.g., app. br. at 25, 56 n.10.

16

criticize the government’s delay expert for allegedly “dropp[ing] the design issue as a

factor” for consideration:

But that’s one of the flaws when you do an as-built versus

and-planned, is the scheduler can make judgments about

what he wants to analyze. They chose not to analyze it,

and it’s a huge issue on this case and on this project. 85

In response to what it says is the charge that “ECCI has changed its delay claim

from the security issue to the communications re-design,” ECCI counters that

“[s]ecurity was never claimed as a delay issue; design delays and directed extra work

were always the primary delay claim.” 86 In support, ECCI quotes the testimony of

ECCI Senior Program Manager, Scott Hayward, referring to Lombardia: 87

Well, at the very beginning prior to getting Lombardia, you

know, [ECCI]’s own internal analysis of the first few

months basically found that security wasn’t the driving

delay. Lombardia’s analysis found the same thing. 88

ECCI’s reliance on that quote is a weak and ineffective explanation of

Mr. Schwartzkopf’s omission of the ECP security changes from the set of nearly

two dozen items for which he created fragnets. First, Lombardia created fragnets for

the ECP security changes, and its delay report is replete with references to those

fragnets. 89 Indeed, of Lombardia’s analysis, which was completed no later than the

submission of the February 12, 2014 ECCI claim in which that analysis is

incorporated, 90 ECCI explained in that claim that:

For each change and/or delay issue that is discussed as part

of [the February 12, 2014 claim], a Fragmentary Network

(fragnet) was created demonstrating how the work was

incorporated into the project schedule. 91

85

Tr. 1/38.

86

App. br. at 61.

87

Id.; ex. 1 at 1; see tr. 1/241.

88

App. br. at 61 (quoting tr. 1/245).

89

See generally R4, tab 72 at 72-103.

90

R4, tab 72 at 72-103.

91

R4, tab 72 at 64.

17

Second, in its February 12, 2014 claim, ECCI identified the “two categories” of

schedule impacts “that run in parallel tracks to each other as they affected the project

progress”; namely, “the ‘ECP Impacts,’” and “‘Design Delays and Additional Work

Directive Impacts’ (Design Delays),” 92 at least suggesting that both events were on the

project’s critical path.

Third, as the government points out, 93 Lombardia—unlike Mr. Schwartzkopf—

actually analyzed the ECP security changes in relation to the design delay, as the

following example illustrates:

Figure 21 below indicates that during this period, the

project experienced 42 days of Design delay, and 18 days

of ECP delay. These two type [sic] of delays were

occurring concurrent to each other. When this concurrency

is recognized, the critical Design Delays for this period is

quantified as 24 days (42 days of Design Delay – 18 days

of ECP Delay). 94

Aside from not creating any fragnets for the ECP security changes, nowhere

does Mr. Schwartzkopf provide the type or level of comparative analysis of that issue

provided by Lombardia. Although in his expert report he references the ECP security

changes and Lombardia’s analysis, he performs no such analysis of his own, on the

one hand disavowing any opinion upon the issue while on the other actually offering

such an opinion (however half-hearted), but ultimately brushing aside the possibility

that the ECP security changes could have delayed the project:

I have no opinion regarding whether the ECP delays

impacted production on the Project, but to the extent that

there was an impact, it was on construction work, not

design, which was the driving delay to Project completion

until the design was approved in March 2013. Also, any

impact from the security protocols was incorporated into

the schedule via actual dates in the contemporaneous

schedules used for the concurrency analysis. 95

92

R4, tab 72 at 64.

93

Gov’t br. at 29.

94

R4, tab 72 at 86.

95

App. supp. R4, tab 1251 at 137-38 (emphasis added).

18

Finally, Lombardia’s opinion does not address project delays that post-date or

continue beyond the February 12, 2014 claim into which that opinion is incorporated.

But “a proper TIA [would assess] the project schedule from the [notice to proceed] to

completion, and [would have] considered all delays and their impacts to the project

activities.” See Nassar Grp., 22-1 BCA ¶ 38,206 at 185,552 (bracketed material and

emphasis added). In its February 12, 2014 claim, ECCI provides an explanation that

illustrates the limitations of Lombardia’s analysis, and how that analysis may not be

the last word on whether and how the ECP security changes might have affected the

project even after Lombardia completed its work:

The ECP Impacts started to affect the project schedule in

May 2012, continued without interruption, and are still

affecting the project progress as of this writing. Due to the

continuous nature of this impact, the ECP Impact analysis

was performed for each schedule reporting period starting

with the CC15 schedule with the data date of 15 May

2012. It should be noted that, even though the ECP

Impacts were continuing to affect the project progress as

of this writing, the analysis for this REA was performed

through 26 October 2013. The continuing bearings of the

ECP Impacts after 26 October 2013, can be quantified

starting with the 27 October 2013 progress schedule

update. 96

The implications of that qualification are that Lombardia’s analysis cannot be

relied upon to explain the progress of the work after October 26, 2013, and that the

ECP security changes were at least a potential delay event as late as February 12,

2014, which, of course is nearly a year after the government finally approved the

100% communications design on March 14, 2013. Indeed, despite the suggestion in

ECCI’s February 12, 2014 claim that Lombardia’s analysis is helpful only through

October 26, 2013, a passage in that claim at least hints that the ECP security changes

might have “driven” delay of the project after that date, and perhaps, as ECCI alleged

in its complaint in this appeal, “through the end of the project”:

Delays Incurred After 10/26/13

As of 10/27/13, per the schedule update CC71 with the

data date of 10/27/13, the ACMILE0040 project

completion milestone was projecting a 12/24/13

96

R4, tab 72 at 64 (emphasis added).

19

completion date. This completion date signifies a [sic]

58 days of remaining contract work as of 10/27/13. To our

knowledge, the ECP impacts continued to affect the

production rates in the field after 10/26/13. If the average

30% production loss rate of September and October 2013

would be applied to this remaining 58 days of work, the

ECP delays would be accountable for another 18 days.

...

This 18 days of additional delay, on top of the

301 days of delay quantified through 10/26/13, would

adjust the Contract Completion Date as 1/7/2014. There

were additional “Design delays” impacts during this

timeframe as well. These include the half of the

Additional Communications Installation Work, Legrand

Floor Boxes, Dedicated Communications Rooms Electrical

Panels, and HVAC Start Up and Commissioning Expert

Ban. Conservatively estimating that these issues delayed

the project critical path 10 days in addition to the

continuing ECP 18 day delay results in an additional

28 day delay during the months of November 2013 through

February 2014. 97

Moreover, the project was not substantially completed until April 19, 2014,

some four months after Lombardia completed its delay analysis, and some two months

after ECCI presented its February 12, 2014 claim to the contracting officer.

All of this is to say that there is evidently more to the ECP security changes

than Mr. Schwartzkopf gave credit, and that in view of ECCI’s loss (at least in its

estimation, perhaps) upon the ECP security changes issue, Mr. Schwartzkopf decided

not to analyze that issue as a potential project delay, and ECCI decided not to pursue it

as such. Indeed, the government alludes to this, saying that “after receipt of the

Board’s [summary judgment] Opinion, ECCI realized that it had to eliminate its

security delay claim in order to maximize its request for delay damages,” 98 and that

Mr. Schwartzkopf “entirely failed to include fragnets showing delays caused by the

change in security posture.” 99 ECCI counters that “[a]t no time has [ECCI] asserted

97

R4, tab 72 at 103 (emphasis added).

98

Gov’t br. at 26.

99

Gov’t br. at 29.

20

that security delays were the driving or critical delays on the [] project,” 100 but that

misses, perhaps deliberately, the point that prior to our opinion regarding the ECP

security changes, ECCI relied upon a delay opinion—Lombardia’s—that created

fragnets to analyze the potential delay effect upon the project of the ECP security

changes, and that after our ECP security change opinion, ECCI abandoned

Lombardia’s opinion, and relied upon a new opinion—Mr. Schwarzkopf’s—that

created no fragnets for the ECP security changes. We determine that

Mr. Schwarzkopf’s opinion is fatally tainted by litigation bias in favor of ECCI. For

all these reasons, we find not credible, and we reject, Mr. Schwartzkopf’s delay

opinion, as well as, with the exception set forth below, ECCI’s delay claim itself. 101

C. The government admits that the 100% communications design issue

delayed the project

Although Mr. Schwartzkopf’s opinion is not credible, ECCI points out that the

government, in the persons of COR Vanoer and ACO Long, communicated to ECCI

by letter that the issues with the 100% communications design were delaying the

project. 102 Mr. Vanoer, wrote his letter on November 16, 2012; Mr. Long on

December 6, 2012. 103 The government says that “[t]he communications redesign was

never shown to cause an actual delay to construction,” 104 but does not address the

statements of Mr. Vanoer and Mr. Long. 105 We determine these are admissions

against the government’s interest that the delay in approving the

100

App. reply at 15.

101

The government’s expert, Mark Doran, also did not assign a fragnet to the ECP

security changes: Mr. Doran explained that because of our opinion upon

summary judgment, his report “does not address any claims regarding alleged

delays as a result of the relocated entry control point (ECP) and associated

revised security procedures” (R4, tab 1168 at 5). As the government at least

implies with respect to Mr. Shwartzkopf’s opinion, Mr. Doran’s decision not to

analyze the ECP security changes renders his delay opinion also not credible.

102

App. br. at 17 ¶ 74; app. reply at 11; R4, tabs 367, 384.

103

R4, tabs 367, 384.

104

Gov’t br. at 39.

105

The government does say, however, that “the contemporaneous documentation,

created during performance of the Contract, is the most reliable source of fact

for events occurring on the Project” (gov’t sur-reply at 4). Along those lines, a

November 1, 2012, government information paper states that the project “has

had significant delays due to design changes” and “user requested changes”

(which we take as a reference to government-requested changes), in addition to

“contractor inefficiencies” (app. supp. R4, tab 755 at 3(b)(1); tr. 6/108-09).

21

100% communications design delayed project completion, such delay beginning no

later than November 16, 2012. Furthermore, we draw the reasonable inference that the

delay was critical path delay, because we expect that Mr. Vanoer, and, particularly,

Mr. Long, the contracting officer, would not have informed ECCI that the design delay

was delaying the project—a position that neither has recanted or otherwise explained

away—if that were not the case. 106 See generally Raytheon Co., ASBCA No. 57743 et

al., 16-1 BCA ¶ 36,335 at 177,147 (distinguishing between evidentiary admissions and

judicial admissions); cf. Reliable Contracting Grp. v. Dep’t of Veterans Affairs,

779 F.3d 1329, 1334-35 (Fed. Cir. 2015) (contractor’s contemporaneous admissions

were “probative evidence that generators did not comply with the contract” (citations

omitted)); ITT Gilfillan Div., ASBCA No. 37834, 92-1 BCA ¶ 24,490 at 122,227-28

(statement in Turkish Air Force report that radar was “operational but degraded” was

admission against interest proving radar was capable of passing contractually-required

operational test); Milam Builders, Inc., ASBCA No. 29700, 85-1 BCA ¶ 17,709 at

88,376 (“Appellant has claimed $1,573 although its evidence did not establish this

amount; accordingly, the amount estimated by the Government will be considered an

admission against interest. Appellant is therefore entitled to $1,542.”); Phillips

Constr. Co., ASBCA No. 5831 et al., 70-2 BCA ¶ 8,363 at 38,893 (“The testimony of

75 days delay was therefore in the nature of an admission against interest or at least in

diminution of appellant's principal case.”); Larco-Indus. Painting Corp., ASBCA

No. 14647 et al., 73-2 BCA ¶ 10,073 at 47,325 (“In an admission against interest,

Mr. Parks before his departure on 11 December 1969 from Fort Chaffee told

Mr. Roberts that respondent had as much of a problem with personnel as did the

contractor . . . [w]e accept his appraisal.”). We also find that the delay began on

November 16, 2012, when the government first admitted that the lack of an approved

communication design was causing delays to the project, and ended on March 14,

2013, when the government finally approved the 100% communications design: a

period of 119 days, fewer than the 290 days that ECCI seeks. 107

106

We have already found not credible the opinion of Mr. Doran. We further conclude

that with respect to whether the delay in approving the 100% communications

design delayed project completion, that opinion is otherwise unhelpful.

Mr. Doran opined that the 100% design delay ended on December 16, 2011,

and that, “[t]herefore, [the] 100% Design Review did not delay the Project”

(R4, tab 1168 at 49). Even ACO Long stated that, as late as December 6, 2012,

the communications design was delaying the project (R4, tab 384 at 1).

Although Mr. Doran testified at the hearing, he did not address Mr. Long’s

statement. Tr. 7/6-207.

107

App. br. at 60; see tr. 8/115-16.

22

However, for purposes of determining compensable delay, we must also

consider concurrent delay not attributable to the government; consequently, we take

into account our opinion upon summary judgment, affirmed by the Court of Appeals,

that the ECP security changes were not compensable, and that, prior to that opinion,

ECCI admitted that from September 29, 2010, through October 26, 2013 (a period of

1,124 days), “the project experienced 205 days of ECP [security changes] delays, and

a total of 389 days of Design delays of which 205 days were concurrent to the ECP

delays.” 108 Because those 205 days of concurrent, non-government delay exceed what

we determine are not 389 days but only 119 days of design delay, we determine that

ECCI is not entitled to any compensable delay.

D. Whether the 100% communications design delay is nevertheless

excusable

The question is whether despite failing to prove entitlement to compensable

delay, ECCI is entitled to remission of liquidated damages because of excusable delay

on the same facts. 109 The contract includes (Federal Acquisition Regulation)

FAR 52.249–10, DEFAULT (FIXED–PRICE CONSTRUCTION) (APR 1984), which

provides, at (b)(1): “[t]he Contractor’s right to proceed shall not be terminated nor the

Contractor charged with damages under this clause, if—[t]he delay in completing the

work arises from unforeseeable causes beyond the control and without the fault or

negligence of the Contractor.” 110 ECCI has the burden of establishing by a

preponderance of the evidence the existence of any such excusable delay. 111 See

Sauer, 224 F.3d at 1347. ECCI says that “the question is not whether [the

government] was correct in [its] objections to ECCI’s design, but rather, did [the

government] act in a timely and reasonable manner.” 112 In apparent reliance upon

section 3.9.2 of the contract, 113 ECCI says that it submitted its 100% communications

design “under the reasonable belief that only the comments made to the 95% design

required response, based on the Contract.” 114 In essence, ECCI argues that so long as

its 100% “cleared for construction” design review submittal incorporated the

“government review comments” generated by the government’s review of the

95% “final design review submittal,” section 3.9.2 required that its

108

R4, tab 72 at 65-66 (emphasis added).

109

App. br. at 110-11, app. reply at 4.

110

R4, tab 5 at 105-06.

111

Although ECCI does not express it as such, we regard its request for remission of

liquidated damages as including by way of excusable delay.

112

App. br. at 38.

113

App. br. at 6 ¶ 31.

114

App. br. at 66 ¶ 170.

23

100% communications design review submittal be approved, and cleared for

construction.

We agree. Section 3.9.2 provides that “[t]he only effort remaining between the

FINAL DESIGN REVIEW SUBMITTAL and the ‘CLEARED FOR

CONSTRUCTION’ DESIGN REVIEW SUBMITTAL is the incorporation of the

Government Review Comments.” 115 That section does not contemplate or authorize

months more of back-and-forth between the government and the contractor in which

the government presents dozens if not hundreds of additional, new design comments

that the contractor must analyze and respond to as a condition of approval of its

100% design, and clearance for construction. In response to ECCI’s 95% design

submission, the government made 56 comments, on the communications design. 116

When ECCI responded with a 100% communications design that incorporated those

56 comments, ECCI was entitled to the approval of that design, and clearance for

construction. Instead, the government responded with 226 new comments, 117

triggering a delay period that we conclude is attributable to the government.

The government says:

[section 3.9.2] is not relevant to the contractor’s remaining

effort after submission of the 100% [communications]

design and upon receipt of the government’s 100%

[communications] design comments. The contractor’s

incorporation of the government’s 95% design comments

did not relieve ECCI of its responsibility to submit designs

in strict conformance with the contract, nor prohibit the

government from requiring correction to non-compliant

design or construction during any phase of the contract. 118

The government also cites section 3.7.1, which provides that “[t]he work under

contract will be subject to continuous review by representatives of the Contracting

Officer.” 119 The government further cites section 3.7.4, “Government Review,” which

provides that:

115

R4, tab 5 at 251 (capitalization in original, italicized emphasis added).

116

R4, tab 742; tr. 8/97-98.

117

Tr. 8/97-98.

118

Gov’t br. at 18-19 (emphasis omitted).

119

Gov’t br. at 69-70 ¶ 84 (citing R4, tab 5 at 247).

24

The contractor shall not begin construction work until the

Government has reviewed the contractor’s design and has

cleared it for construction. Clearance for construction does

not mean Government approval. 120

We agree that “clearance for construction” is not immunity from further

government review. In addition to the sections that the government cites, section

1.2.1, “Design Submittals,” provides that “[c]learance for construction shall not be

construed as meaning Government approval,” and that, “[u]nless otherwise indicated,

the risk for the design is the sole responsibility of the Design-Build Contractor.” 121

Nevertheless, the question here is whether ECCI, having incorporated the

government’s comments in response to it 95% design, was entitled to approval of its

100% communications design, and the clearance for construction that goes with it.

(Indeed, section 3.8.5 of the contract, Commencement of Construction, provides that

“[c]onstruction of work may begin after receipt of the clearance for construction

(Notice to Proceed) for each design phase.) 122 The answer pursuant to section 3.9.2 of

the contract is yes. 123 We will not speculate upon what would have been the case had

the government timely approved the 100% communications design (as submitted on

November 19, 2011), thus clearing that design for construction, and only thereafter

interjected new comments raising issues with that design. 124

If the answer were otherwise, section 3.9.2 would be merely aspirational; the

position that the government expressly took during the hearing of these appeals, but

notably does not assert in its post-hearing briefing. 125 We do not regard section 3.9.2

as aspirational; that provision is not “too amorphous to provide any basis to identify

120

R4, tab 5 at 247-48; see gov’t br. at 16.

121

R4, tab 5 at 232 (emphasis added).

122

R4, tab 5 at 250 (emphasis added).

123

Contract interpretation aside, as a practical matter, as ECCI points out (app. reply

at 32), the designer whom ECCI hired for the project testified that “[t]here is no

reason why any of [the government’s] substantive 100% design review

comments should not have been given on the 95% design submittal.” Ex. 11

at 2, 8. The government does not address that statement.

124

ECCI invokes the duty of good faith and fair dealing in support of its

section 3.9.2 argument (app. br. at 42-43). In view of our conclusion here, we

need not address that issue. Consequently, the government’s October 16, 2020

motion to exclude or strike that invocation, which the government repeats in its

December 21, 2020 post-hearing sur-reply brief (gov’t sur-reply at 29), is

denied as moot.

125

See tr. 4/108, 230; tr. 6/16.

25

concrete obligations.” Kellogg Brown & Root Servs., Inc., ASBCA Nos. 59385,

59744, 20-1 BCA ¶ 37,656 at 182,827. Rather, section 3.9.2 speaks in precise terms.

Thomas Jefferson Univ. Hosp. v. Shalala, 512 U.S. 504, 517 (1994) (rejecting

contention that regulation’s language was “precatory” or “aspirational,” and “thus

lacking in operative force” where it “speaks not in vague generalities but in precise

terms”).

For these reasons, we conclude that ECCI is entitled to an excusable delay of

119 days from November 16, 2012, thorough March 14, 2013, for the government

having delayed the project by delaying the approval of the 100% communications

design, at $2,338.99 per day, for a total of $278,339.81 in remitted liquidated damages.

We have considered the government’s other, related points on this issue, 126 and are not

persuaded by them, including because many of those points relate to events occurring

before Mr. Vanoer and Mr. Long made their statements in late 2012. The government

also points to statements of ECCI in early 2014, regarding other potential delays that

the government apparently attributes to ECCI, but does so without adequately, if at all,

identifying the specific periods of such delay. 127 None of this changes our conclusion

that ECCI is entitled to the remission of 119 days of liquidated damages for excusable

delay. Moreover, we do not regard this conclusion as precluded by our summary

judgment opinion regarding the ECP security changes. We note that ECCI’s

February 12, 2014 claim to the contracting officer for 329 days of delay preceded the

contracting officer’s April 9, 2014 assessment of liquidated damages, and that the

government has represented that the Board possesses jurisdiction to entertain ECCI’s

claim for remission of liquidated damages. 128

III. Defense Base Act (DBA) Insurance Premium Payments

ECCI requests $174,124 for allegedly unpaid Defense Base Act (DBA)

insurance premiums. 129 Specifically, ECCI says:

Throughout performance of the contract, ECCI and

subcontractor Garda World paid DBA insurance premiums

to Rutherford. Audits of ECCI’s and Garda World’s

advance premium payments determined that ECCI had

paid premiums in excess of the premiums actually due in

126

Gov’t br. at 33-37.

127

Gov’t br. at 38.

128

Gov’t May 11, 2021 filing at 6.

129

App. br. at 29.

26

the amount of $42,162, which was refunded to [the

government] instead of ECCI.

Throughout performance of the contract, ECCI was paid

$145,415 by [the government], compared to the $277,377

in audited actual premium payments made by ECCI and

Garda World. Considering the $277,377 in audited

premium payments excludes the $42,162 that had been

paid by ECCI but refunded to [the government, the

government] has underpaid ECCI $174,124 for DBA

insurance premiums. 130

The government says that we lack jurisdiction to entertain ECCI’s DBA claim

because, it says, ECCI has not presented that claim to the contracting officer. 131 ECCI

points to several pages of its February 12, 2014 claim to the contracting officer that

appear to consist of spreadsheets that list costs, including DBA costs. 132 However,

ECCI does not quote or even reference any language in that claim that explains to the

contracting officer that ECCI has paid DBA premiums in excess of premiums actually

due, which excess was refunded to the government instead of to ECCI, and is due to

ECCI. Consequently, ECCI’s DBA claim is dismissed for lack of jurisdiction. See

41 U.S.C. § 7103(a).

IV. Constructive Acceleration

During the hearing, counsel for ECCI described the status of ECCI’s

acceleration claims:

The phase [sic] completion originally had damages in the

delay claim, [ASBCA No. 59586], I think it was, related to

additional management that came from the phase

completion acceleration. There is [sic] damages in that

one because of that event.

Then the directive cost claim, [ASBCA No. 59643], it has

damages associated with the requirement to change HVAC

suppliers and air freight in those materials to meet these

phase completions. Those two claims still have a phase

130

App. br. at 29 ¶¶ 146-47 (citations omitted).

131

Gov’t br. at 46.

132

App. reply at 44.

27

completion damage component. [ASBCA No.] 60284 was

a claim for phase completion, but it had separate damages

related to multiple re-commissioning and mobilizing

HVAC testers. That one has been dropped. 133

Counsel for the government agreed with that explanation. 134 However, we are

not bound by the parties’ representations; indeed, the Board has an obligation to satisfy

itself of its own jurisdiction. See Weeks Marine, Inc. v. United States, 575 F.3d 1352,

1359 (Fed. Cir. 2009).

A. Jurisdiction

The government says that we are without jurisdiction to entertain the

acceleration claim that ECCI presents to us, because, the government says, that claim

has not been presented to the contracting officer. 135 The Board does not possess

jurisdiction, within a given appeal, to entertain a claim that is new to the appeal. Env’t

Chem. Corp., ASBCA No. 58871, 15-1 BCA ¶ 36,110 at 176,286-87. However, rigid

adherence to the exact language or structure of the original claim is not required. Id.

The Board possesses jurisdiction to entertain claims that arise from the same operative

facts as those presented to the contracting officer, claim essentially the same relief, and

merely assert differing legal theories for that recovery. Id. New or modified

allegations that do not change the operative facts of the claim to the contracting

officer, or change the essential nature of those facts, do not constitute a new claim. Id.

And an area of costs in addition to those requested of the contracting officer but

related to the operative facts of the claim presented to the contracting officer is within

our jurisdiction. See Am. Consulting Servs., Inc., ASBCA No. 52923, 00-2 BCA

¶ 31,084 at 153,485; Miller Elevator Co. v. United States, 30 Fed. Cl. 662, 701

(1994).

In its February 12, 2014 claim to the contracting officer (which claim is the

predicate for this appeal, ASBCA No. 59586), ECCI presented a constructive

acceleration claim that consists of assertions that the government: (1) delayed the 95%

and 100% design process; (2) held ECCI to the original schedule; (3) directed extra-

contractual work; (4) issued unsatisfactory interim performance ratings; (5) assessed

liquidated damages; (6) criticized ECCI for allegedly being late; 136 and (7) “directed

133

Tr. 5/87.

134

See tr. 5/87.

135

Gov’t br. at 43-44.

136

R4, tab 72 at 9.

28

the acceleration of the turnover of Building I” 137 and the “phase[d] . . . turnover of

facilities.” 138 ECCI alleged that those actions “forced ECCI to augment staff to

manage the extensive security efforts and additional work,” 139 and that “subsequent to

the Government’s direction to accelerate and phase the turnover of facilities, ECCI

determined it was unable to use the approved Carrier brand [HVAC units] and had to

switch to more expensive Aaon and Trane units in order to meet the directed

accelerated and phased turnover of facilities.” 140

By comparison, in its briefing to the Board in this appeal, ASBCA

No. 59586, 141 ECCI sets forth an acceleration claim consisting of the following

assertions: (1) “[b]ecause of the late issuance of modifications for time extensions,

ECCI accelerated performance, including air freighting Pre-Engineered Buildings and

HVAC equipment,” and by adding additional management staff, 142 (2) “[i]n early

2013, [the government] . . . directed ‘phased completion’ and sequenced handover of

buildings; this accelerated the project, 143 (3) “ECCI notified the government that [the

government’s] direction for phased completion had accelerated ECCI’s schedule and

was a change,” 144 (4) the government directed ECCI to meet accelerated phased

completion dates, 145 (5) because of the “direction to accelerate and handover buildings

out of sequence,” ECCI “switch[ed] HVAC suppliers and airfreight[ed] equipment,”

and “[m]obiliz[ed] significantly more management staff to focus on priority

buildings”; 146 and (6) “ECCI provided notice that it was being accelerated, and

incurred additional costs to air freight PEBs and add management resources, which

were necessary to meet the unreasonably short schedule.” 147

137

R4, tab 72 at 48, 62-63.

138

R4, tab 72 at 161.

139

R4, tab 72 at 11.

140

R4, tab 72 at 45. ECCI went on to say that “[t]his issue will be addressed in a

follow-on [Request for Equitable Adjustment] for the construction costs

associated with the Government’s improper direction to change the

requirements of the contract. Only the costs associated with the delays

discussed above are included in this REA.” Id.

141

ECCI sets forth additional acceleration allegations in ASBCA No. 59643. See app.

br. at 86-87.

142

App. br. at 19-20 ¶¶ 81, 87 (citations omitted).

143

App. br. at 19 ¶ 83 (citations omitted).

144

App. br. at 19 ¶ 85 (citations omitted.

145

App. br. at 19 ¶ 86 (citations omitted).

146

App. br. at 19 ¶ 87 (citations omitted).

147

App. br. at 64. We understand the term “PEB” to refer to “Pre-Engineered

Building.”

29

Distilling the assertions recited above, we conclude that the constructive

acceleration claim set forth in ECCI’s February 12, 2014 claim and its post-hearing

briefing share the following same set of operative facts: that the government directed

the phased turnover, handover, or completion of the buildings to be constructed,

causing ECCI to increase management staff and purchase alternative air conditioning

equipment. 148 Because, except for this “phased handover” element, the two claims are

not based upon the same set of operative facts, we possess jurisdiction in this appeal to

entertain only the phased handover claim. Consequently, all but the phased handover

claim—the remainder having to do with an alleged government-directed requirement

to use UL-listed refrigerant—is dismissed for lack of jurisdiction. We further

conclude that ECCI’s specific requests here for compensation for having air-freighted

HVAC equipment and PEBs are related to the operative facts of the constructive

acceleration claim presented to the contracting officer, and so are within our

jurisdiction. 149

B. Merits

Regarding the merits of ECCI’s phased-turnover constructive acceleration

claim, constructive acceleration often occurs when the government demands

150

compliance with an original contract deadline, despite excusable delay by the

contractor: a contractor must prove that: (1) the contractor encountered a delay that is

excusable under the contract; (2) the contractor made a timely and sufficient request

for an extension of the contract schedule; (3) the government denied the contractor’s

request for an extension or failed to act on it within a reasonable time; (4) the

government insisted on completion of the contract within a period shorter than the

period to which the contractor would be entitled by taking into account the period of

excusable delay, after which the contractor notified the government that it regarded the

alleged order to accelerate as a constructive change in the contract; and (5) the

contractor was required to expend extra resources to compensate for the lost time and

remain on schedule. IAP Worldwide Servs., Inc., ASBCA Nos. 59397, et al., 17-1

148

The government does not, in reliance upon the February 24, 2020 dismissal of

ASBCA No. 60284 with prejudice, assert any affirmative defense to ECCI’s

assertion in this appeal of a phased-turnover acceleration claim.

149

We note that in its May 2, 2014 claim to the contracting officer and in ASBCA

No. 59643, ECCI also seeks the cost of airfreighting HVAC units. See app. br.

at 82 ¶ 256; R4, tab 75 at 7.

150

App. br. at 62-64; gov’t br. at 44-45, 118.

30

BCA ¶ 36,763 at 179,158. The government apparently contests only the fourth and

fifth of those elements, effectively conceding the first three. 151

1. Air-Freighting PEBs

Presumably regarding whether ECCI was required to expend extra resources to

compensate for the lost time and remain on schedule, and specifically concerning the

air-freighting of PEBS, the government points the finger at ECCI, saying that ECCI’s

subcontractor did not order the PEB buildings “in a timely manner, left the site in

November 2011, and was terminated by ECCI in December 2011.” 152 ECCI does not

address that contention. 153 On September 4, 2011, ECCI informed its subcontractor,

Folad Masih Co. (FMC), that ECCI was concerned with FMC’s progress regarding

Pre-Engineered Buildings (PEBs). 154 On October 4, 2011, ECCI wrote again to FMC

of ECCI’s concerns with FMC’s progress. 155 On November 27, 2011, ECCI informed

FMC that PEBs would be “removed and terminated” from FMC’s subcontract. 156 On

December 10, 2011, ECCI terminated FMC’s contract, stating that “FMC[’]s lack of

performance to date on the awarded contract has prevented ECCI from competing the

associated tasks that were awarded and has significantly delayed the project activities

that are required to complete the project in a timely manner.” 157 ECCI does not, in this

appeal, address FMC’s performance; consequently, we are not persuaded that

government constructive acceleration was responsible for ECCI air freighting PEBS to

Afghanistan, and we deny this component of ECCI’s constructive acceleration claim.

2. Air-Freighting HVAC Equipment

With respect to ECCI’s claim that government-caused constructive acceleration

required ECCI to air-freight HVAC equipment, ECCI’s post-hearing briefing does not

identify any amount for that claim. The government points us to an ECCI spreadsheet

presented during the hearing, 158 which lists $372,796 for “air shipment,” but identifies

that amount as for “Airshipment of PEB.” 159 ECCI having failed to identify a specific

151

See gov’t br. at 42.

152

Gov’t br. at 42 ¶ 51.

153

App. br. at 41-43.

154

R4, tab 164 at 1.

155

R4, tab 945.

156

R4, tab 947 at 1.

157

R4, tab 948.

158

Gov’t br. at 2, 42 ¶ 49; tr. 1/290; see app. supp. R4, tab 305.

159

App. supp. R4, tab 305.

31

dollar amount for air-freighting HVAC equipment, that claim is denied. See ESCgov,

Inc., ASBCA Nos. 61358 et al., 17-1 BCA ¶ 36,772 at 179,189.

CONCLUSION

We have considered the parties’ other arguments and find them unnecessary to

address. We dismiss for lack of jurisdiction ECCI’s claims for additional

compensation for (1) allegedly unpaid Defense Base Act (DBA) insurance payments,

and (2) the claim that an alleged government-directed requirement to use UL-listed

refrigerant constructively accelerated contact performance. The appeal is otherwise

sustained in part and denied in part: ECCI is awarded $278,339.81, plus interest in

accordance with 41 U.S.C. § 7109, from February 12, 2014, the putative date that the

contracting officer received ECCI’s claim, until the date of payment.

Dated: April 18, 2025

TIMOTHY P. MCILMAIL

Administrative Judge

Armed Services Board

of Contract Appeals

I concur I concur

OWEN C. WILSON MICHAEL N. O’CONNELL

Administrative Judge Administrative Judge

Acting Chairman Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

32

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA No. 59586, Appeal of ECC

International Constructors, LLC, rendered in conformance with the Board’s Charter.

Dated: April 18, 2025

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

33

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.