Opinion

Walsh Turner Joint Venture II

Court
Armed Services Board of Contract Appeals
Filed
May 8, 2025
Status
Published
On the bench
Osterhout
Cited by
0 cases
Authority
More cited than 36.3%

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - )

)

Walsh Turner Joint Venture II ) ASBCA No. 63665

)

Under Contract No. W912QR-21-C-0027 )

APPEARANCES FOR THE APPELLANT: Larry W. Caudle, Jr., Esq.

Brad C. Friend, Esq.

Kraftson Caudle LLC

McLean, VA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.

Engineer Chief Trial Attorney

James M. Inman, Esq.

Engineer Trial Attorney

U.S. Army Engineer District, Louisville

OPINION BY ADMINISTRATIVE JUDGE OSTERHOUT ON THE

GOVERNMENT’S MOTION TO DISMISS FOR LACK OF JURISDICTON

The U.S. Army Corps of Engineers (the government or USACE) moves to

dismiss this appeal for lack of jurisdiction and for failure to state a claim upon which

relief may be granted. The government argues that the Board lacks jurisdiction to

consider this appeal because the claim was brought by a party that was not the

contracting party. To wit: the original notice of appeal was captioned as “Walsh

Turner Joint Venture” rather than “Walsh-Turner Joint Venture II” which we had

invited appellant to recaption. We deny the government’s motion to dismiss for lack

of jurisdiction because we find that the change in contractor name was a mere

misnomer. Thus, the Board retains jurisdiction.

The government also moves to dismiss this appeal for failure to state a claim.

The dispute leading to this appeal stemmed from a COVID-era executive order

directing contracting agencies to require their contractors to take a number of steps

including vaccinating their workforce. The government issued a request for proposal

(RFP) to Walsh – Turner JV II (WTJV II or appellant) 1 asking it to price its

1

Because one of the issues presently before the Board deals with the name appellant

used when submitting its claim and subsequent notice of appeal, to avoid any

additional confusion, we refer to it as appellant or WTJV II to be consistent

with the Board’s accepted name for the caption. We refrain from using any

compliance with the executive order, though it ultimately never required appellant to

comply with it. Appellant argues that the government’s issuance of the RFP wound up

costing it a significant amount of money. The government here moves to dismiss

under two theories. First, that the executive order at issue here was a sovereign act

thus depriving WTJV II of the relief requested in its claim; and second, that an RFP is

not considered a change under the contract. We agree and dismiss this appeal for

failure to state a claim because an RFP is not a constructive change under the contract.

Since we find appellant failed to state a claim upon which relief may be granted, we

need not consider the government’s sovereign acts doctrine argument. The appeal is

dismissed for the reasons set forth below.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. The government awarded firm-fixed-price Contract No. W912QR-21-C-

0027 to “Walsh-Turner JV II” on August 17, 2021, for the construction of a new

Veteran’s Affairs (VA) medical center in Louisville, KY (R4, tab 4 at 20-21, 32-36). 2

The award letter addressed the contractor as “Walsh-Turner Joint Venture II” (R4,

tab 3). On October 4, 2021, USACE issued the notice to proceed to “Walsh-Turner JV

II,” giving the contractor until January 5, 2026, to complete the project (R4, tab 6;

compl. ¶ 5). At the time appellant filed its complaint with the Board on August 17,

2023, modifications had extended the completion date to January 24, 2026 (compl. ¶

6).

2. The contract incorporated by reference Federal Acquisition Regulation

(FAR) 52.243-4, CHANGES (JUN 2007) which provides, in relevant part:

(b) Any other written or oral order (which, as used

in this paragraph (b), includes direction, instruction,

interpretation, or determination) from the Contracting

Officer that causes a change shall be treated as a change

order under this clause; provided, that the Contractor gives

the Contracting Officer written notice stating

(1) the date, circumstances, and source of the order

and

(2) that the Contractor regards the order as a change

order.

other abbreviations except in explaining how the parties themselves reference

appellant.

2

The government’s Rule 4 file is Bates numbered beginning with the prefix GR4

followed by zeros. The prefix and leading zeros are omitted in the citations to

the government’s Rule 4 file.

2

(c) Except as provided in this clause, no order,

statement, or conduct of the Contracting Officer shall be

treated as a change under this clause or entitle the

Contractor to an equitable adjustment.

(d) If any change under this clause causes an

increase or decrease in the Contractor’s cost of, or the time

required for, the performance of any part of the work under

this contract, whether or not changed by any such order,

the Contracting Officer shall make an equitable adjustment

and modify the contract in writing . . . .

(R4, tab 4 at 50)

3. During the COVID-19 pandemic, the President issued Executive Order

14042 (EO 14042 or “the EO”), dated September 9, 2021, Ensuring Adequate COVID

Safety Protocols for Federal Contractors (R4, tab 5). Exec. Order No. 14042, 86 Fed.

Reg. 50,985 (Sept. 9, 2021). The EO directed a task force to establish guidance that

required contractors to be completely vaccinated for COVID-19 by December 8, 2021

(R4, tab 5 at 94; compl. ¶ 14). SAFER FEDERAL WORKFORCE TASK FORCE, COVID 19

WORKPLACE SAFETY: GUIDANCE FOR FEDERAL CONTRACTORS AND

SUBCONTRACTORS, 5 (2021),

https://web.archive.org/web/20210927183021/https://www.saferfederalworkforce.gov/

downloads/Draft%20contractor%20guidance%20doc_20210922.pdf. 3 The Task Force

also directed the FAR Counsel to draft related clauses to be included in all new

covered solicitations and contracts. Id. at 2. In response, the Department of Defense

(DoD) “issued guidance in a Class Deviation 2021-O0009 for implementation of the

EO through a new DFARS[ 4] clause, 252.223-7999 (Ensuring Adequate Safety

COVID-19 Safety Protocols for Federal Contractors)” on October 1, 2021 (gov’t mot.

at 2 (citing R4, tab 7 at 120)).

4. USACE issued a request for proposal, Case 00008 (the RFP), on

November 3, 2021, advising the contractor that the government was considering

adding a COVID safety clause to the contract, in accordance with DoD guidance

“Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors.” The RFP

3

As the original website is no longer active and neither party included the guidance in

the Rule 4 filings, we accessed the Task Force guidance using the Internet

Archive’s Wayback Machine at:

https://web.archive.org/web/20210927183021/https://www.saferfederalworkfor

ce.gov/downloads/Draft%20contractor%20guidance%20doc_20210922.pdf.

4

The DFARS is the Department of Defense Supplement to the FAR.

3

also stated, “[t]his letter does not constitute a notice to proceed with the work

involved. Submit your proposal for this change to the undersigned by November 9,

2021 to facilitate negotiations.” (R4, tab 7 at 118) The RFP was addressed to “Walsh-

Turner JV II” (id.). The cover letter accompanying the RFP was addressed to “Walsh-

Turner Joint Venture II” and explained that “[t]he requirements in the [EO] are being

implemented via a DFARS deviation. The clause in the DFARS deviation will be

incorporated into Louisville District contracts and is effective on the date of the

contracting officer’s signature” (R4, tab 8). The letter continued, “[t]he modification

is mandatory before Louisville District will renew, extend the period of performance

of your contract, or exercise an option” (id.) (emphasis in original). The cover letter

also stated, “[i]f there are costs or time impacts associated with incorporating and

complying with this DFARS deviation, please submit your proposal to the undersigned

[CO] within 5 business days of receipt of this letter” (id.). The RFP included the text

of the new COVID clause, DFARS 252.223-7999, which required compliance with all

guidance implementing the EO (R4, tab 7 at 120).

5. On November 5, 2021, the government granted appellant an extension to

submit its proposal in response to the RFP and scheduled a progress meeting where a

new due date (in December 2021) would be established for submission of the proposal

(R4, tab 10). Ultimately, WTJV II did not submit a proposal (R4, tab 2 at 16).

6. The district court for the Eastern District of Kentucky enjoined enforcement

of EO 14042 on November 30, 2021 (R4, tab 11). Kentucky v. Biden, 571 F.Supp.3d

715 (E.D. Ky. 2021). The government then rescinded the RFP in a letter addressed to

“Walsh – Turner JV II, ATTN: Ben Wells” on December 2, 2021, stating, “[a]

proposal for this effort is no longer required. If a proposal is needed later the

government will reinitiate the request with a new letter requesting a proposal” (R4,

tab 12). By letter dated December 3, 2021, appellant expressed that

[w]hile this new letter rescinds the RFP, it cannot rescind

the deleterious and cascading effects which have already

occurred as a result of the issuance of the RFP. The

impacts of the RFP are broad reaching and touch everyone

that is or will become part of this project. Such impacts

include, but are not limited to, loss of interest from

subcontractors, lack of progress on key submittals, loss of

production slots, general procurement impacts, late

deliveries, expediting costs, escalation costs, labor impacts,

overtime costs, unnecessary expending of Walsh-Turner

management costs, labor and the overall time impact to the

project resulting from this RFP being issued and rescinded.

4

(R4, tab 14 at 160) This letter was sent on Walsh Turner letterhead and referred to the

contractor as “Walsh-Turner” throughout; the signature block reads “Benjamin Wells,

Sr. Project Manager, Walsh – Turner Joint Venture II” (id. at 160-61). The email

transmitting this letter came from Mr. Wells; his signature block included

Walsh / Turner JV II as the contractor’s name and the email referred to the contractor

as “Walsh – Turner JV II” (app. supp. R4, tab 4).

7. On December 3, 2021, the government issued Modification No. P0004

(Mod. 4) which exercised option K (R4, tab 15). The COVID clause, DFARS

252.223-7999, was not included in the modification (gov’t mot. at 3 (citing compl.

¶ 23); see R4, tab 15). Mod. 4 used “Walsh – Turner JV II” for the contractor’s name

(R4, tab 15 at 166).

8. By letter dated February 7, 2022, appellant explained the impact of the RFP

on awarding its subcontract for steel, the one-month delay on both the cost of steel,

and the shorter time frame to meet deadlines (R4, tab 16). Appellant included as

enclosures correspondence from steel subcontractors outlining the additional costs for

both the increase in the materials and forecasted acceleration costs for the delay in

awarding the subcontracts because of the issuance of the RFP (id. at 174-77). This

letter was on Walsh Turner letterhead and the contractor referred to itself as “Walsh –

Turner” throughout the letter; the signature block reads “Benjamin Wells, Project

Manager, Walsh – Turner Joint Venture II” (id. at 169). The signature block in the

email transmitting this letter used “Walsh / Turner JV II” for the contractor’s name

(R4, tab 17).

9. The project’s area engineer responded to appellant’s February 7, 2022 letter,

characterizing it as an “unsolicited cost proposal” on March 3, 2022 (R4, tab 18). The

government indicated that the contract is firm-fixed-price which “places upon the

contractor maximum risk and full responsibility for all costs and resulting profit or

loss. However, a contractor may be entitled to recover for cost escalation if it can

demonstrate that government-caused delay pushed performance into a time when costs

had escalated” (id.). The government then requested that the contractor respond to

some inquiries about the negotiations and timeline of the steel subcontracting (id.).

The letter was addressed to “Walsh-Turner Joint Venture II” and the text of the letter

referred to the contractor as “Walsh-Turner Joint Venture II (Walsh-Turner)” (id.).

10. WTJV II responded to the government’s letter on March 18, 2022 (R4,

tab 19). This letter was also on Walsh Turner letterhead, the contractor referred to

itself as “WTJV” throughout the text of the letter, and included Mr. Wells’ signature

block “Benjamin Wells, Project Manager, Walsh – Turner Joint Venture II” (id.).

Appellant explained its timeline for negotiating steel subcontracts and, at the time it

was written, appellant had still not yet entered into a subcontract for the steel (id.

5

at 192). Additionally, appellant noted that the RFP “impeded WTJV’s ability to award

steel when the cost of steel was significantly less” (id. at 193).

11. The project’s area manager responded by letter dated April 12, 2022, 5

addressing the contractor as “Walsh-Turner Joint Venture II” and relayed the

government’s position that it did not delay the contractor, but if WTJV II disagreed, it

could submit a request for equitable adjustment (REA) or a claim to the contracting

officer (CO) (R4, tab 20).

12. Appellant submitted its certified claim, on Walsh Turner letterhead, to

USACE on December 29, 2022, for $1,694.899.21 for increased steel costs it alleges

were a result of the heightened COVID-19 safety protocols required by EO 14042 (R4,

tab 21 at 197-98, 207). Throughout the letter appellant referred to itself as “Walsh

Turner Joint Venture (‘WTJV’)” and the letter was signed by “Benjamin Wells,

Project Executive” (id.).

13. On April 13, 2023, the CO issued his final decision (COFD) denying

appellant’s claim finding that the higher steel costs were part of the risk of performing

a firm-fixed-price contract and that the issuance of the RFP was not a change under the

Contract (R4, tab 2 at 15-17). The COFD was addressed to “Mr. Ben Wells, Walsh

Turner Joint Venture” and stated, “this letter responds to Walsh Turner Joint Venture’s

(‘WTJV’) letter dated 29 December 2022, which requested a final decision on its claim

that WTJV is entitled to reimbursement for the alleged increased steel costs WTJV

incurred” due to the issuance of the RFP (R4, tab 2 at 11). The government referred to

appellant as “WTJV” throughout the COFD, including in the first finding of fact where

the CO says the contract “was awarded by the U.S. Army Corps of Engineers

(‘USACE’) to WTJV on 17 August 2021 . . .” (id. at 11).

14. Appellant timely filed its notice of appeal on July 12, 2023, under the name

Walsh Turner Joint Venture; that was the name the Board used to docket this appeal.

As noted above (SOF ¶¶ 12-13), the certified claim and COFD both used “Walsh

Turner Joint Venture (WTJV)” in reference to the contractor.

15. The government submitted its Rule 4 file on August 11, 2023. After

reviewing it, the Board noted that the contract, W912-Q5-21-C-0027, identified the

contractor as “Walsh-Turner JV II.” By Order dated August 17, 2023, the Board

5

The letter is dated March 12, 2022, but the CAC signature indicates it was signed by

the area manager on April 12, 2022. We assume the March 12, 2022, date is an

error as this letter is clearly responding to the contractor’s correspondence dated

March 18, 2022 (R4, tab 19) so that is the date we use here. In addition, the

government used the April 12, 2022, date in the index it submitted along with

the Rule 4 file.

6

directed the parties to “explain the discrepancy in the contractor’s name and identify

the correct name of the entity bringing this appeal” (Bd. corr. ltr. dtd. August 17,

2023).

16. By correspondence dated August 17, 2023, appellant responded to the

Board’s Order stating, “[t]he original filing contained a misnomer in that it omitted the

“II” from the entity’s legal name. Appellant seeks a formal change in the party name

to ‘Walsh Turner Joint Venture II.’” By Order dated August 18, 2023, the Board

changed the caption to Walsh Turner Joint Venture II in accordance with appellant’s

August 17, 2023, representations (Bd. corr. ltr. dtd. August 18, 2023).

17. Appellant submitted its complaint via email on August 17, 2023, though

the document is dated August 17, 2022 (compl. ¶ 1). The caption to the complaint lists

appellant’s name as “Walsh Turner Alberici Joint Venture” (id.). The first paragraph

of the complaint reads: “Walsh Turner Joint Venture (‘WTJV’), Appellant, is the

prime contractor for the construction of the New Veterans Affairs Medical Center

(‘VAMC’) in Louisville, Kentucky” (compl. ¶ 1). Throughout the complaint,

appellant refers to itself as WTJV (see, e.g., compl. ¶¶ 5-6, 12, 15-21, 24-31, 35-42).

In its prayer for relief, appellant again refers to itself as “Appellant Walsh Turner Joint

Venture” (compl. ¶ 9).

18. The government filed this motion to dismiss on August 31, 2023. The

caption of the government’s motion identified appellant as “Walsh Turner Joint

Venture” (gov’t mot. at 1). Based on the record, this appears to be the first time the

government raised the issue of the name under which appellant filed its claim. We

find that the government did not raise the issue prior to the Board identifying it.

DECISION

The Parties’ Contentions

The government moves to dismiss for both lack of jurisdiction and failure to

state a claim. Each has two components. First, the government argues that the Board

lacks jurisdiction here because the contracting party was WTJV II and it was Walsh

Turner Joint Venture (no inclusion of “II”) that submitted first the certified claim and

then the notice of appeal. The government next argues that the complaint fails to state

a claim upon which relief can be granted for two reasons (gov’t mot. at 6, 9). First,

that the issuance of EO 14042 and, thus, the RFP that was issued to comply with the

EO is a sovereign act (id. at 10-13). Second, that the issuance of the RFP is not a

change under the contract and appellant is not entitled to an equitable adjustment (id.

at 13-16).

7

Appellant opposes the government’s motion, asserting that the Board retains

jurisdiction over this appeal because “the omission by appellant of ‘II’ from the entity

name on the certified claim and in the notice of appeal constitutes a misnomer, and the

government was neither surprised nor prejudiced by such omission” (app. opp’n at 1).

Appellant also disputes the government’s argument that the issuance of the EO was a

sovereign act because it was not “public or general” and argues that the RFP was a

constructive change under the contract (id. at 7, 22-23).

Jurisdiction

The Board’s jurisdiction arises out of the Contract Disputes Act of 1978

(CDA), 41 U.S.C. §§ 7101-7109. The CDA defines “contractor” as “a party to a

Federal Government contract other than the Federal Government.” 41 U.S.C.

§ 7101(7). Additionally, under the CDA the Board “only possesse[s] jurisdiction to

adjudicate appeals taken by a contractor.” Nassar Group Int’l N.G.I. S.A.L. (Offshore)

R.C., dba NGI Afghanistan for Contracting, ASBCA No. 58451 et al., 22-1 BCA

¶ 38,206 at 185,546 (citing Afghan Washington Constr. Co., ASBCA No. 60856, 18-1

BCA ¶ 37,009 at 180,242).

We will discuss the party identity on the notice of appeal first since it was the

subject to which the parties have devoted the most attention. With regard to

misnomers, the Board has previously held that “[o]ur Board rules do not specifically

mention correction of a misnomer in a pleading as a ground for amending a pleading.

Nevertheless, we think that the established practice under Rule 15 of the Federal Rules

of Civil Procedure permits amendment to correct a misnomer of a party to the action,”

and a “[m]ere technical defect[] in a pleading do[es] not provide a basis for dismissal.”

Jardineria Iglesias, S.L., ASBCA No. 42967, 93-3 BCA ¶ 26,244 at 130,554 (citing

Jones v. State of La. through Board of Trustees, 764 F.2d 1183, 1185-86 (5th Cir.

1985); Huse v. Consolidated Freightways, Inc., 227 F.2d 425, 428-29 (7th Cir. 1955);

6 CHARLES ALAN WRIGHT & ARTHUR R. MILLER, FED. PRACTICE & PROCEDURE

§ 1474).

In Jardineria, the contract and its modifications were issued to “Antonio

Iglesias Mateos;” the claim correspondence used “Antonio Iglesias Mateo” or “A.

Iglesias” or “Jardineria Iglesias;” the claim letter used “A. Iglesias” and “Antonio

Iglesias, on behalf of Jardineria Iglesias, S.L.;” and the notice of appeal used

“Jardineria Iglesias, represented by Antonio Iglesias Mateos.” 93-3 BCA ¶ 26,244

at 130,554. We denied the government’s motion to dismiss for lack of jurisdiction,

which argued that the notice of appeal was filed by a party that was not a party to the

contract, in part, because the motion “d[id] not contend that [the government] was

surprised or prejudiced in any way by the name ‘Jardineria Iglesias, S.L.” Id. Both

the Court of Federal Claims and the Civilian Board of Contract Appeals (CBCA) have

8

cited Jardineria in more recent decisions. 6 See Focus Revision Partners v. United

States, 161 Fed. Cl. 711, 730 (2022); Eastco Bldg. Servs. v. Gen. Servs. Admin.,

CBCA 5272, 17-1 BCA ¶ 36,670 at 178,558.

In addition to Jardineria, appellant has also cited Applied Precision Optics,

Inc., ASBCA No. 21635, 77-2 BCA ¶ 12,695, to bolster its misnomer argument (app.

opp’n at 5). Applied Precision Optics is helpful because it illustrates that even in an

appeal in which the corporate identity of the contractor changed during contract

performance (from a sole proprietorship to a differently-named corporation) without a

novation agreement, the appeal being filed by the newly-named corporation should be

considered, at most, a misnomer, because the government knew who it was dealing

with and it was not prejudiced. See Applied Precision Optics, 77-2 BCA ¶ 12,695

at 61,605-07. Though Applied Precision Optics, being issued in 1977, predates the

CDA, it underscores the point that it has long been the Board’s practice to look to

prejudice to the government and permit revision of the caption when there is a

harmless misnomer.

The government’s argument is not nearly as persuasive. It largely relies on

LaTella, Inc. d/b/a Advanced Electronic Systems (see gov’t mot. at 8-9), in which we

granted a government motion to dismiss. That appeal, however, involved a situation in

which the party bringing the appeal was not the business awarded the contract; was not

the successor in interest to that business; there was no novation agreement; and there

was no assignment of claims. The case was not about whether the wrong name was

initially used on the notice of appeal as we have here; rather, it was about whether a

completely different corporation could prosecute the appeal. See ASBCA No. 55653,

07-1 BCA ¶ 33,521 at 166,082-83. Another case raised by the government was

Redwood Furniture Co. Ltd., Tuncay Ticaret, and Estetik Mobilya, ASBCA No. 54944

et al., 06-2 BCA ¶ 33,317 (see gov’t reply at 2-3). But this is a case where we ruled in

favor of the appellant, allowing the correction of the misnomer where only the first

claimant was named in the appeal, but the other two were meant to be included and

had been in the initial claim. See 06-2 BCA ¶ 33,317 at 165,195. We find it hard to

see Redwood as imposing a more restrictive read on misnomers than what we would

have here, where the flaw was leaving out the Roman numeral II.

Throughout the parties’ course of dealing as reflected in the record, appellant

referred to itself variously as “WTJV,” “Walsh – Turner,” “Walsh – Turner JV II,” and

“Walsh – Turner Joint Venture II” in its correspondence with the government (see

6

The government argues in its reply brief that Jardineria is not persuasive because it

has been rarely cited in subsequent decisions (gov’t reply at 2-3). This is

simply inaccurate; moreover, it may merely reflect that, in light of the clear law,

the government rarely makes challenges to the correction of obvious

misnomers.

9

SOF ¶¶ 6, 8, 10, 12). The government also did not consistently address

correspondence to or reference appellant in its correspondence by the full name listed

on the contract, “Walsh-Turner JV II,” and referred to it variously as “Walsh-Turner

JV II,” “Walsh-Turner Joint Venture II,” “Walsh Turner Joint Venture,” and “WTJV”

(see SOF ¶¶ 1, 4, 6, 7, 9, 11, 13). It is clear from the parties’ correspondence and the

COFD that the government knew it was dealing with WTJV II, the contracted party,

and that the parties both occasionally abbreviated the full name, including the “II,” as

they saw fit. Additionally, the same representative from appellant, Mr. Wells, signed

all of the relevant correspondence contained in the record on behalf of appellant and

usually included appellant’s full name as it appears in the contract in his signature

block (SOF ¶¶ 6, 8, 10, 12). There was no confusion here that prejudiced the

government, and we agree with appellant that this was a misnomer. The situation here

is strikingly similar to that in Jardineria. Like that appeal, the government here

communicated with Mr. Wells and did not appear to be confused at any point as to

whether “WTJV” or “Walsh-Turner” were different business entities than the

contractor awarded the contract, “Walsh – Turner JV II.”

Similar reasoning applies to the issue of the claim before the contracting

officer. To be sure, the claim was submitted by “Walsh-Turner Joint Venture” and the

COFD responded to the same, but both the claim and the COFD referred to the correct

contract number and we can entertain no serious doubt that the parties knew exactly

who they were dealing with, as it had been the practice of both to use the slightly

different variations of WTJV II’s name interchangeably throughout performance of the

contract. In these circumstances, the deletion of the “II” in the claim is no more

consequential than leaving off an “Inc.” at the end of a company’s name in a case

where all parties were familiar with the company and there was no chance of

confusion. The result requested by the government would be a triumph of form over

substance not required by the law. Accordingly, the government’s motion to dismiss

for lack of jurisdiction is denied.

Failure to State a Claim

Having decided that we retain jurisdiction over this appeal, we turn to the

government’s two arguments that appellant failed to state a claim upon which relief

can be granted. For the non-moving party to prevail in a motion to dismiss for failure

to state a claim, “a complaint must contain sufficient factual matter, accepted as true,

to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662,

678 (2009) (citing Bell Atlantic v. Twombly, 550 U.S. 544, 570 (2007)). When

deciding a motion to dismiss for failure to state a claim, the Board “must accept well-

pleaded factual allegations as true and must draw all reasonable inferences in favor of

the claimant.” Lockheed Martin Integrated Sys., Inc., ASBCA Nos. 59508, 59509,

17-1 BCA ¶ 36,597 at 178,281 (quoting Kellogg Brown & Root Servs., Inc. v. United

States, 728 F.3d 1348, 1365 (Fed. Cir. 2013)). “For purposes of assessing whether the

10

claim before us states a claim upon which relief can be granted, the primary document

setting forth the claim is not the complaint, per se, but is either the contractor’s claim

or the government’s claim, the latter asserted in a contracting officer’s final decision as

required by the Contract Disputes Act, 41 U.S.C. §7103(a)(3).” Lockheed Martin,

17-1 BCA ¶ 36,597 at 178,281.

We address the government’s second argument first. Here, the government

argues that “[a]ppellant wrongly contends the issuance and rescission of RFP-0008

constitute a constructive change, entitling it to an equitable adjustment” (gov’t mot.

at 13). Further, “[u]nder the Changes Clause, an RFP is not a constructive change

because it is not a direction, instruction, or determination changing the work under the

contract” (id.). Appellant counters that “RFP 0008 constituted a direction from the

Contracting Officer for Appellant to prepare a proposal and pricing for the impact

associated with adding DFARS 252.223-7999 to the Contract” (app. opp’n at 17) and

this “direction” constituted a constructive change.

Appellant “has the burden of establishing by a preponderance of the evidence

that the government’s actions amounted to a constructive change to the contract.”

Wright Bros., Bldg. Co., Eagle LLC, ASBCA No. 62285, 23-1 BCA ¶ 38,255

at 185,779 (citing CDM Constructors, Inc., ASBCA No. 60454 et al., 18-1 BCA

¶ 37,190 at 181,011). An RFP is not generally considered a change to a contract

because it is not a direction or order, but rather, a mechanism to solicit proposals from

the contractor. See FAR 15.203(a) (explaining that RFPs “are used in negotiated

acquisitions to communicate Government requirements to prospective contractors and

to solicit proposals.”). The contract incorporated the Changes Clause by reference,

which reads, in relevant part, “[a]ny other written or oral order (which as used in this

paragraph (b), includes direction, instruction, interpretation or determination) from the

Contracting Officer that causes a change shall be treated as a change order . . .” (SOF

¶ 2). A contractor must show that “(1) it performed work beyond the contract

requirements, and (2) that the additional work was ordered, expressly or impliedly, by

the government” to establish that a constructive change occurred. Bell/Heery v. United

States, 739 F.3d 1324, 1335 (Fed. Cir. 2014) (citing The Redland Co. v. United States,

97 Fed. Cl. 736, 755-56 (2011)).

First, appellant did not actually perform outside the requirements of the contract

and the COVID clause was never adopted into the contract. Before and after the

issuance and subsequent recission of the RFP, the contract required appellant to

procure steel for this project. Appellant indicates that the costs of steel increased over

the approximate one month the RFP was issued, but appellant never responded to the

RFP by the November 2021 deadline, and in fact, requested an extension until

11

December 2021 (SOF ¶ 5), and ultimately the RFP was later rescinded (SOF ¶ 6). 7

Second, appellant has not shown that the government ordered, either expressly or

impliedly, any additional work. The government expressly did not order any work as

part of the RFP stating “this letter does not constitute a notice to proceed with the work

involved. Submit your proposal for this change . . . to facilitate negotiations” (SOF

¶ 4 (emphasis added)). To be sure, WTJV II alleges that the issuance of the RFP

imposed upon it a duty to require that its subcontractors’ bids comply with EO 14042

and the corresponding new DFARS provision, thereby increasing its costs (see app.

opp’n at 9-10), but this argument is unpersuasive. It rests upon the allegation in its

complaint that the mere issuance of the RFP imposed this duty upon WTJV II (see

app. opp’n at 9 (citing compl. ¶ 15)), when by its very terms the RFP imposes no

obligations upon WTJV II except to submit a proposal.

A generous reading of the factual allegations in WTJV II’s complaint might

support some sort of argument that other directions given by the CO with respect to

the future incorporation of the new DFARS provision into the contract would impose

changes upon performance (see, e.g., compl. ¶¶ 9 10, 12). However, the actual legal

basis for relief as claimed in the complaint rests solely on the government’s issuance

and then recission of the RFP (see compl. ¶¶ 35-38). Because the RFP explicitly

directs that it is not a notice to proceed, it cannot be a constructive change to the

contract. Thus, even drawing all reasonable inferences in favor of appellant and

accepting all facts in the claim as true, appellant has not met its burden to establish that

the government’s issuance of the RFP amounted to a constructive change to the

contract.

Because we rule in favor of the government on the RFP issue, we need not

decide its sovereign acts defense.

7

Additionally, as of March 18, 2022, appellant had still not entered into a subcontract

for the required steel for this project (SOF ¶ 10), which raises questions about

whether the RFP was in fact the only factor preventing WTJV II from securing

its steel subcontract.

12

CONCLUSION

The government’s motion to dismiss for lack of jurisdiction is denied; the

government’s motion to dismiss for failure to state a claim is granted on the RFP issue

and the appeal is dismissed with prejudice for failure to state a claim upon which relief

can be granted.

Dated: May 8, 2025

HEIDI L. OSTERHOUT

Administrative Judge

Armed Services Board

of Contract Appeals

I concur I concur

OWEN C. WILSON J. REID PROUTY

Administrative Judge Administrative Judge

Acting Chairman Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA No. 63665, Appeal of Walsh

Turner Joint Venture II, rendered in conformance with the Board’s Charter.

Dated: May 8, 2025

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

13

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.