finding a statement “without meaningful explanation” that a project “would not result in a trend toward federal listing” is insufficient to satisfy NEPA’s “hard look” requirement
How later courts described this case
- finding a statement “without meaningful explanation” that a project “would not result in a trend toward federal listing” is insufficient to satisfy NEPA’s “hard look” requirement
- “[T]he binding authority principle applies only to appellate decisions, and not to trial court decisions.”
- “The purpose of an EA is to provide the agency with sufficient evidence and analysis for determining whether to prepare an EIS or to issue a FONSI.” (citing 40 C.F.R. § 1508.9)
- holding that the “BLM, in some cases, may adapt its assessment of environmental impacts when the specific locations of an exploration project’s activities cannot reasonably be ascertained until some time after the project is approved”
Written by the judges who cited it.
The opinion
UNITED STATES DISTRICT COURT
DISTRICT OF OREGON
CASCADIA WILDLANDS and Case No. 6:22-cv-01344-MTK
OREGON WILD,
OPINION AND ORDER
Plaintiffs,
vs.
CHERYL ADCOCK and UNITED STATES
BUREAU OF LAND MANAGEMENT,
Defendants.
_________________________________________
KASUBHAI, United States District Judge:
Plaintiffs Cascadia Wildlands and Oregon Wild (“Plaintiffs”) filed this action alleging
violations of the National Environmental Policy Act (“NEPA”) 42 U.S.C. §§ 4321 et seq., and
the Administrative Procedure Act (“APA”) 5 U.S.C. §§ 701 et seq., against the United States
Bureau of Land Management (“BLM”) and Cheryl Adcock in her official capacity as Field
Manager for the BLM’s Siuslaw Field Office (collectively, “Defendants”). Before the Court are
the parties’ cross-motions for summary judgment. ECF Nos. 33, 36. For the reasons below,
Plaintiffs’ motion is granted, and Defendants’ motion is denied.
BACKGROUND
Plaintiffs allege that Defendants violated NEPA in preparing their Siuslaw Harvest Land
Base Landscape Plan Environmental Assessment (“Siuslaw Plan EA”) by failing to take a “hard
look” at the Siuslaw Plan’s environmental impacts and failing to prepare an Environmental
Impact Statement. See Compl. ¶¶ 101-47, ECF No. 1. The Court begins by summarizing the
relevant statutory and regulatory framework and the facts underlying this action.
I. Statutory and Regulatory Framework
A. NEPA
NEPA’s purpose is to require agencies to disclose “relevant environmental considerations
that were given a ‘hard look’ by the agency, and thereby to permit informed public comment on
proposed action and any choices or alternatives that might be pursued with less environmental
harm.” Lands Council v. Powell, 395 F.3d 1019, 1027 (9th Cir. 2005). It “does not mandate
particular results, but simply prescribes the necessary process.” Robertson v. Methow Valley
Citizens Council, 490 U.S. 332, 350 (1989).
To that end, NEPA requires agencies proposing “major Federal actions significantly
affecting the quality of the human environment” to prepare a detailed statement—an
Environmental Impact Statement (“EIS”)—discussing environmental impacts of the proposed
action and a range of alternatives to avoid adverse impacts. 42 U.S.C. § 4332(C). To determine
whether a proposed action will significantly affect the quality of the human environment (and
therefore require an EIS), an agency may prepare an Environmental Assessment (EA). 40 C.F.R.
§ 1501.5. “If an agency decides not to prepare an EIS, it must supply a ‘convincing statement of
reasons’ to explain why a project’s impacts are insignificant.” Cascadia Wildlands v. Bureau of
Indian Affs., 801 F.3d 1105, 1111 (9th Cir. 2015) (quoting Blue Mountains Biodiversity Project
v. Blackwood, 161 F.3d 1208, 1212 (9th Cir.1998)).
B. FLPMA/O&C Act
Under the Federal Land Policy and Management Act (“FLPMA”), the BLM must prepare
Resource Management Plans (“RMPs”) for its districts. 43 U.S.C. § 1712. RMPs “are designed
to guide and control future management actions and the development of subsequent, more
detailed and limited scope plans for resources and uses.” 43 C.F.R. § 1601.0-2. The BLM must
manage lands governed by FLPMA “under principles of multiple use and sustained yield.” 43
U.S.C. § 1732(a). By contrast, lands that are governed by the Oregon and California Railroad
and Coos Bay Wagon Road Grants Lands Act (“O&C Act”) are managed “for permanent forest
production . . . in conformity with the principal [sic] of sustained yield.” 43 U.S.C. § 2601.
However, O&C Act lands are still subject to the procedural requirements of FLPMA, including
preparation of RMPs. See Klamath-Siskiyou Wildlands Ctr. v. U.S. Bureau of Land Mgmt., No.
1:19-cv-02069-CL, 2021 WL 4462886, at *2 (D. Or. Sept. 29, 2021).
The development of an RMP “is considered a major Federal action significantly affecting
the quality of the human environment” requiring the preparation of an EIS under NEPA. 43
C.F.R. § 1601.0-6. Further site-specific actions implementing the RMP must conform to the
governing RMP and require compliance with NEPA. AR 9386.
II. Factual Background
A. 2016 Resource Management Plan
In 2016, the BLM adopted the RMP for Northwestern and Coastal Oregon (“2016
RMP”). AR 7476-77. The 2016 RMP “provides direction for management of resources on
approximately 1.3 million acres of BLM-administered lands in the Coos Bay District, Eugene
District, Salem District, and the Swiftwater Field Office of the Roseburg District.” AR 7476. The
RMP categorizes different portions of the land at issue into various land use allocations, each of
which is subject to different management objectives and directions. AR 7528. The land use
allocation at issue in this case is the Harvest Land Base (“HLB”). Id. Consistent with its
obligations under the O&C Act, the objectives for the HLB allocation include managing “forest
stands to achieve continual timber production,” offering for sale “the declared Allowable Sale
Quantity of timber” (“ASQ”), and “[i]n harvested or disturbed areas, ensur[ing] the
establishment and survival of desirable trees.” AR 7540. The ASQ in the Eugene sustained-yield
unit was set at 53 million board feet. AR 7486-87.
The BLM issued a Final EIS (“2016 RMP FEIS”) that the Ninth Circuit held satisfied its
obligation under NEPA in adopting the 2016 RMP. Rivers v. Bureau of Land Mgmt., 815 F.
App’x 107, 110 (9th Cir. 2020). The 2016 RMP FEIS considered the impacts of both the
Northwestern RMP and the RMP for Southwestern Oregon, encompassing a total of 2.5 million
acres. AR 7482, 9347. The 2016 RMP FEIS acknowledged that the RMPs it evaluated do not
directly authorize implementation of projects and that implementation decisions would require
additional NEPA compliance. AR 9386-87.
B. Siuslaw Plan
In March 2022, the BLM approved a plan (the “Siuslaw Plan”) to meet the Siuslaw Field
Office’s obligations under the 2016 RMP and the O&C Act to contribute timber to the ASQ in
the Eugene sustained-yield unit. AR 124. The Siuslaw Plan involves a two-decade commercial
logging project on BLM-administered forestland directly west of Eugene, Oregon. It does not
“authorize any specific action” but instead “outline[s] the strategy” for meeting the Siuslaw Field
Office’s contribution to the relevant ASQ declared in the 2016 RMP. AR 127.
The Siuslaw Plan includes the Siuslaw Plan EA, the Siuslaw Plan Finding of No
Significant Impact (“FONSI”), and the Siuslaw Plan Decision Record (“DR”). AR 1, 117, 10. In
approving the Siuslaw Plan, the BLM evaluated “the effects of five action alternatives that would
conduct timber harvest treatments within 13,225 acres of BLM managed lands in the Harvest
Land Base land use allocation and a no-action alternative.” AR 1. Following scoping and public
involvement, the BLM identified 47 “issues” to be considered but eliminated all but five from
detailed consideration. AR 127-30. The BLM ultimately selected “Alternative 4” which would
produce ASQ volume by harvesting 1,404-2,305 acres per decade, including 278-944 acres
through commercial thinning and 1,126-1,361 though regeneration harvesting. AR 13. Pursuant
to the analysis contained in the EA, the BLM found that the Siuslaw Plan would not have
significant environmental impacts and therefore concluded that an EIS was not necessary. AR 1-
2.
Plaintiffs are Oregon nonprofit corporations that filed this action for declaratory and
injunctive relief on September 8, 2022, alleging NEPA violations based on Defendants’ failure to
(1) adequately analyze and disclose the Siuslaw Plan’s potentially significant environmental
impacts; and (2) prepare an Environmental Impact Statement as required for actions that may
have environmentally significant impacts. Compl. ¶¶ 101-47. Defendants moved to dismiss the
action for lack of jurisdiction on November 14, 2022, and the Court denied the motion on May
24, 2023. ECF Nos. 10, 19, 22 (adopting Findings & Recommendation). Plaintiffs and
Defendants now cross-move for summary judgment. Pls.’ Mot. for Summ. J. (“Pls.’ Mot.”) ECF
No. 33; Defs.’ Mot. for Summ. J. (“Defs.’ Mot.”) ECF No. 36. The Court held oral argument on
the motions on February 8, 2024.
STANDARD OF REVIEW
Plaintiffs allege violations of NEPA and its implementing regulations, which are
reviewed under the Administrative Procedure Act (“APA”). 5 U.S.C. §§ 701-706. The Ninth
Circuit endorses the use of Rule 56 summary judgment motions to resolve such claims. Nw.
Motorcycle Ass’n v. U.S. Dep’t of Agric., 18 F.3d 1468, 1471-72 (9th Cir. 1994). Under the
APA, a court shall hold unlawful and set aside agency action, findings, and conclusions found to
be arbitrary, capricious, or otherwise unlawful. 5 U.S.C. § 706(2). An agency action is arbitrary
and capricious if the agency “entirely failed to consider an important aspect of the problem,” or
offered an explanation “that runs counter to the evidence before the agency.” Lands Council v.
McNair, 537 F.3d 981, 987 (9th Cir. 2008) (quoting Earth Island Inst. v. U.S. Forest Serv., 442
F.3d 1147, 1157 (9th Cir. 2006). Reviewing courts “may not rubber-stamp . . . administrative
decisions that they deem inconsistent with a statutory mandate or that frustrate the congressional
policy underlying a statute.” Friends of Yosemite Valley v. Norton, 348 F.3d 789, 793 (9th Cir.
2003) (alteration in original) (quoting Pub. Citizen v. DOT, 316 F.3d 1002, 1020 (9th Cir.
2003)).
DISCUSSION
The parties each argue that they are entitled to summary judgment on Plaintiffs’ NEPA
claims. Plaintiffs argue that Defendants’ actions violated NEPA because they (1) failed to take a
“hard look” at, and adequately analyze and disclose, the Siuslaw Plan’s potentially significant
environmental impacts; and (2) failed to prepare an Environmental Impact Statement as required
for actions that may have environmentally significant impacts.
I. Threshold Issues
Plaintiffs’ motion begins with several sections that address the BLM’s general approach
to NEPA compliance with respect to the Siuslaw Plan. Plaintiffs argue that Defendants erred in
(1) using a “purpose and need” statement to omit 42 out of 47 environmental issues from detailed
consideration, and (2) inappropriately “tiering”1 the Siuslaw Plan EA to the 2016 RMP FEIS to
the exclusion of analyzing site-specific impacts. Relatedly, Defendants argue broadly that their
use of landscape-level analysis of the Siuslaw Plan’s environmental impacts complies with
NEPA and has been upheld by the Ninth Circuit. See Defs.’ Reply 6-7, ECF No. 42 (citing
Klamath-Siskiyou Wildlands Ctr. v. Bureau of Land Mgmt., No. 22-35035, 2022 WL 17222416
(9th Cir. Nov. 25, 2022)).
A. Purpose and Need Statement
Plaintiffs contend that the BLM improperly omitted from detailed consideration specific
environmental issues because such issues were “not directly correlated with the agency’s purpose
and need of timber production.” Pls.’ Mot. 17. Defendants argue that Plaintiffs misunderstand
the BLM’s approach and that it did not limit its analysis in the manner Plaintiffs contend.
In excluding 42 of 47 identified environmental issues, the BLM explained that issues
only warranted “detailed analysis if (1) analysis of the issue is necessary to provide information
1 With respect to tiering, the applicable regulations provide:
Whenever a broad environmental impact statement has been prepared (such as a
program or policy statement) and a subsequent statement or environmental
assessment is then prepared on an action included within the entire program or
policy (such as a site specific action) the subsequent statement or environmental
assessment need only summarize the issues discussed in the broader statement and
incorporate discussions from the broader statement by reference and shall
concentrate on the issues specific to the subsequent action.
40 C.F.R. § 1502.20.
to the decision-maker to be able to make a reasoned choice between alternatives presented (that
is, it is related to the purpose and need for action); or (2) the analysis of the issue is necessary to
determine the significance of the impacts.” AR 128 (citing BUREAU OF LAND MGMT., H-1790-1,
BLM NATIONAL ENVIRONMENTAL POLICY ACT HANDBOOK (2008), at 41). Plaintiffs argue that
the above statement indicates that some or all of the 42 issues omitted from detailed
consideration were omitted on the basis that they were not consistent with the purpose and need
to produce timber.
The Court does not read the BLM’s statement—either alone or in the context of the EA
as a whole—to indicate that the BLM omitted issues from detailed consideration solely because
they were not consistent with the purpose and need. Instead, it is an either/or statement. In other
words, the BLM considered issues in detail if they were either related to the purpose and need of
the project or analysis was necessary to determine the significance of the impacts of the issue.
Whether the BLM’s decision that detailed analysis was not necessary to determine the
significance of those issues’ impacts constituted a failure to take a “hard look” is a separate
question, addressed in the following portions of this opinion. But there is no indication in the
record to suggest that the BLM declined to analyze any issues solely because they were
inconsistent with the purpose and need of the Siuslaw Plan.
B. General Arguments about Landscape-Level Analysis
Both parties raise general arguments about the propriety of landscape-level analysis and
tiering, citing other decisions in this district that each party contends control this Court’s
conclusion.
Plaintiffs argue in Section II of their motion that the BLM’s adoption of the Siuslaw
Plan—a landscape-level plan—required a site-specific analysis of environmental impacts and
that the Siuslaw Plan EA did not contain such analysis. Plaintiffs contend that by tiering to the
2016 RMP FEIS to conclude that the Siuslaw Plan would have no significant impacts, the BLM
failed to consider the impacts specific to the Siuslaw Plan project area. Defendants contend that
what Plaintiffs are advocating is a “sale-by-sale” approach that is not supported in the case law,
and they argue that the Siuslaw Plan EA contained the required site-specificity.
It is unclear to the Court whether this portion of Plaintiffs’ motion is intended to offer a
general statement of the law regarding site-specificity and tiering to provide a framework to
evaluate the particular issues they raise, or whether Plaintiffs seek to have the Court make a
general finding that the use of tiering in the Siuslaw Plan EA was inappropriate with respect to
the BLM’s analysis as a whole. The parties appear to agree that tiering is appropriate in some
cases. Plaintiffs argue that tiering is impermissible here because “none of the documents address
significant issues.” Pls.’ Mot. 18 (quoting Cascadia Wildlands v. Bureau of Land Mgmt.
(“Thurston I”), 410 F. Supp. 3d 1146, 1158-59 (D. Or. 2019)). Thus—as even Plaintiffs’
argument implies—the question before the Court is whether the BLM did, in fact, fail to consider
significant issues here. To resolve that question, the Court must evaluate the BLM’s analysis of
specific issues. To the extent that Plaintiffs ask the Court to make a general finding that the
BLM’s tiering approach throughout the Siuslaw Plan EA violated NEPA, the Court cannot do so
in the abstract.2
Defendants make a similar broad argument in their briefing, claiming that this case is
“resolve[d]” by another decision in this district which challenged another EA that tiered to the
2 Contrary to Plaintiffs’ contention in their brief, the Court did not already make such a general
finding in “Thurston I.” Instead, that opinion evaluated the appropriateness of tiering and NEPA
compliance with respect to the specific issue of fire hazards. See Cascadia Wildlands, 410 F. Supp.
3d at 1157.
same 2016 RMP FEIS at issue here. See Defs.’ Objs. to F&R 13, ECF No. 57 (citing Klamath-
Siskiyou Wildlands Ctr. v. United States Bureau of Land Mgmt. (“North Landscape”), No. 1:19-
cv-01810-CL, 2021 WL 5356969, at *1 (D. Or. Aug. 24, 2021), report and recommendation
adopted, No. 1:19-CV-1810-CL, 2021 WL 5355919 (D. Or. Nov. 16, 2021), aff’d, No. 22-
35035, 2022 WL 17222416 (9th Cir. Nov. 25, 2022)). Defendants contend that because North
Landscape concluded that the EA at issue in that case properly tiered to the same 2016 RMP
FEIS at issue here, see North Landscape, 2021 WL 5356969, at *6, this Court is compelled to
conclude the same.
Defendants’ argument that North Landscape controls the outcome of this case is flawed
for two reasons. First, it suffers from the same logical pitfall as Plaintiffs’ broad argument on the
propriety of tiering to the 2016 RMP FEIS. North Landscape evaluated whether an EA for a
project in the Klamath Falls Resource Area adhered to NEPA requirements when it tiered to the
2016 RMP FEIS in its evaluation of the project’s impacts on Northern Spotted Owl habitat. Id. at
*6-7. This Court is not evaluating the same EA challenged in that case, nor even the same issue.3
As the Court noted with respect to Plaintiffs’ similar argument, the question here is narrow and
confined to the specific issues before the Court rather than a general finding on the propriety of
tiering to the 2016 RMP FEIS.
3 Indeed, even North Landscape pointed out the fact that the 2016 RMP FEIS was upheld by the
Ninth Circuit was not dispositive of the specific challenges to the government’s analysis of the
site-specific project at issue there. See North Landscape, 2021 WL 5356969, at *3. In fact, that
court specifically noted that tiering to the 2016 RMP FEIS had been found appropriate in some
cases but not others. Id. at *7 (“This Court recently found that a site-specific project EA may
properly tier to a programmatic species-level analysis in the FEIS for the 2016 RMP where that
analysis contemplates specific activities within a planning area. . . . By contrast, this Court found
tiering to the analysis about the great grey owl insufficient because it lacked the necessary site-
specific disclosures and merely acknowledged that the great grey owl was at risk.”).
Second, North Landscape is not precedential. See Hart v. Massanari, 266 F.3d 1155,
1174 (9th Cir. 2001) (“[T]he binding authority principle applies only to appellate decisions, and
not to trial court decisions.”). Neither is the Ninth Circuit’s unpublished memorandum opinion
affirming North Landscape controlling. See Circuit Rule 36-3(a) (“Unpublished dispositions and
orders of this Court are not precedent, except when relevant under the doctrine of law of the case
or rules of claim preclusion or issue preclusion.”).
The following sections evaluate whether the BLM’s tiering approach and lack of site-
specificity resulted in a failure to address specific potentially significant issues. But the Court
cannot make a general finding that the BLM’s approach to the Siuslaw Plan EA did not (in the
case of Plaintiffs’ argument) or did (in the case of Defendants’ argument) comply with NEPA
simply because it tiered to the 2016 RMP FEIS.
In sum, neither of the threshold issues resolve the parties’ cross-motions. Instead, the
question is whether the BLM failed to take a “hard look” at significant environmental impacts of
the Siuslaw Plan, and specifically whether the BLM’s use of tiering in this particular instance
was insufficient because neither the Siuslaw Plan EA nor the 2016 RMP EIS considered specific
potentially significant issues.
II. Failure to Analyze and Disclose Potentially Significant Environmental Impacts
Plaintiffs argue that Defendants violated NEPA by failing to take the requisite “hard
look” at several issues in the Siuslaw Plan EA. “In NEPA, Congress recognized the ‘profound
impact’ of human activities, including ‘resource exploitation,’ on the environment and declared a
national policy ‘to create and maintain conditions under which man and nature can exist in
productive harmony.’” Ctr. for Biological Diversity v. U.S. Dep’t of Interior, 623 F.3d 633, 642
(9th Cir. 2010) (quoting 42 U.S.C. § 4331(a)). To this end, NEPA and its implementing
regulations set forth “action-forcing” procedures designed to (1) ensure agencies take a “hard
look” at the environmental effects of proposed actions and (2) foster meaningful public
participation. Robertson, 490 U.S. at 349.
Because the BLM has “irreversibly and irretrievably” committed resources to the Siuslaw
Plan, it was obligated to take a “hard look” at the Siuslaw Plan’s direct, indirect, and cumulative
impacts. See Conner v. Burford, 848 F.2d 1441, 1446 (9th Cir. 1988); W. Watersheds Project v.
Abbey, 719 F.3d 1035, 1050 (9th Cir. 2013). A “hard look” requires consideration of all
foreseeable direct, indirect, and cumulative impacts. Idaho Sporting Cong. v. Rittenhouse, 305
F.3d 957, 963 (9th Cir. 2002); 40 C.F.R. § 1508.25(c) (2019) (stating that an agency “shall
consider” direct, indirect, and cumulative impacts). This includes evaluation of the additive
impacts of the action on top of the environmental baseline, see 40 C.F.R. § 1502.15 (2019)
(requiring that agencies “describe the environment of the area(s) to be affected”), and a
comparison to other alternative courses of action, see 40 C.F.R. § 1508.25(b) (2019) (agency
“shall consider” alternatives). An agency fails to take a “hard look” when an EA is speculative
and conclusory. See Greenpeace Action v. Franklin, 14 F.3d 1324, 1335-36 (9th Cir. 1992).
Importantly, if the “hard look” reveals the effects of the action “may” be significant, the
decision-maker cannot approve the action “unless it is either analyzed in an EIS or modified to
avoid significant effects.” AR 13730; accord Nat’l Parks & Conservation Ass’n v. Babbitt, 241
F.3d 722, 730 (9th Cir. 2001). At the same time, “NEPA documents must concentrate on the
issues that are truly significant to the action in question, rather than amassing needless detail.” 40
C.F.R. § 1500.1(b) (2019).
Plaintiffs challenge the BLM’s failure to give sufficiently detailed consideration to 42
environmental issues. AR 201-60 (eliminating 42 issues from “detailed consideration”). As the
Court addressed above, it cannot make a finding that the BLM’s general approach to the 42
issues violated NEPA but instead must make that determination with respect to such issues the
BLM allegedly failed to properly consider. In their briefing, Plaintiffs target four specific issues,
arguing that Defendants failed to take a “hard look” at (1) soil disturbance, (2) noxious weeds
and invasive species, (3) special status species, and (4) the Siuslaw Plan’s cumulative impacts on
the environment.
A. Soil Disturbance
The Northwestern RMP requires the BLM to “[l]imit detrimental soil disturbance from
forest management operations to a total of < 20 percent of the harvest unit area.” AR 7570. In its
EA Specialist Report for Soils and Geology, the BLM stated:
A determination of the Harvest Land Base (HLB) project impacts on soil quality is
made using the same methods and assumptions described in the RMP, but is
quantified at the project-area and treatment-unit scale utilizing local spatial data,
soils and geology information sources, and treatment information. The finer spatial
scale of this analysis enables greater precision, historic disturbance quantification,
and site-specificity in assessing local soil quality impacts than the spatial scale of
the RMP.
AR 3839. However, in the Siuslaw Plan EA itself, the BLM concluded that “individual field site
assessment was not feasible at the scale of this analysis,” and instead assessed baseline soil
conditions across the entire 13,225-acre Siuslaw Plan area. AR 1768-69.
Plaintiffs contend that by failing to conduct a harvest-level analysis of soil disturbance—
despite the BLM’s acknowledgement that a site-specific approach was available—the BLM
failed to take a hard look at how the Siuslaw Plan would comply with the Northwestern RMP’s
management direction regarding soil impacts. Defendants argue that the BLM did conduct the
requisite “hard look” through its baseline averaging and proposed mitigation measures.
1. The BLM’s Averaging Approach
The Ninth Circuit has cautioned that averaging environmental impacts across a larger
project area can be “grossly misleading.” Or. Nat. Res. Council Fund v. Brong, 492 F.3d 1120,
1129-30 (9th Cir. 2007). Specifically, the Ninth Circuit explained that the averaging in that case
was an attempt by the BLM “to dilute the effects of its proposed activities” and that “an agency
cannot try to ‘minimize’ the environmental impact of an activity by simply adopting a scale of
analysis so broad that it marginalizes the site-level impact of the activity on ecosystem health.”
Id. at 1130.
Here, the BLM conducted averages across the entire 13,225-acre Siuslaw Plan area. AR
3839 (“The spacial scale for this analysis is the 13,225-acre project area.”). This is thirteen times
the size of the project area averaged in Brong. 492 F.3d at 1129 (1,004-acre project area). In fact,
the BLM acknowledged that this averaging system was based on guesswork. In an email
exchange, one of the BLM’s foresters reported findings based on “just [a] real quick guess on
what would be logged in certain ways.” AR 923. The BLM’s specialists also expressed
confusion regarding which logging methods were proposed when making such averaging
calculations. Compare AR 922-23 (noting that one employee from the BLM stated, “I had 4
years with an approx 90 10 split and one year[] with a 75 cable 25 ground and one that was 55
45” and the other employee stated, “I ran my numbers assuming 17% ground based, and things
were right on the threshold”) with AR 3841 (“Based on these considerations, this analysis
assumed an HLB logging system design that would treat 17% of the treated acres with ground-
based or specialized harvest methods, and 83% with cable or aerial harvest methods.”). This
averaging system distorted the data contained in the EA, rendering the resulting FONSI irrational
and inadequate under NEPA. See Env’t Def. Ctr. v. Bureau of Ocean Energy Mgmt., 36 F.4th
850, 882 (9th Cir. 2022) (“[The defendants] relied on flawed assumptions in the EA that
distorted and rendered irrational their finding of no significant impact. . . . This failure to take the
requisite ‘hard look’ renders the EA inadequate under NEPA.”).
Defendants argue that the Ninth Circuit does not endorse the level of site-specificity
Plaintiffs urge is required. To support this argument, the BLM cites N. Alaska Env’t Ctr. v.
Kempthorne, 457 F.3d 969 (9th Cir. 2006). There, the Ninth Circuit held that failing to conduct a
parcel-by-parcel analysis of the environmental consequences of a projected action is not a per se
violation of NEPA. Id. at 977. While this is true, the Ninth Circuit adopted this rule in part
because the project entailed a multistage process involving inherent uncertainty, and because the
plaintiffs would have additional opportunities to comment on future stages requiring an EIS. Id.
(“Any later plan for actual exploration by lessees will be subject to a period of review before
being accepted, rejected or modified by the Secretary. Plaintiffs will have an opportunity to
comment on any later EIS.” (internal citation omitted)). The Ninth Circuit has also allowed
broader landscape-level plans in exploration projects where specific locations cannot reasonably
be ascertained. Te-Moak Tribe of W. Shoshone v. U.S. Dep’t of Interior of Nev., 608 F.3d 592,
600 (9th Cir. 2010) (holding that the “BLM, in some cases, may adapt its assessment of
environmental impacts when the specific locations of an exploration project’s activities cannot
reasonably be ascertained until some time after the project is approved”). An example of such
project is a mining operation where the exact location of minerals to be extracted is necessarily
uncertain without implementation of the plan. Id.
Here, the landscape-level analysis was not sufficient to satisfy NEPA. This is not a case
where the BLM will conduct another EIS or EA prior to implementing plan—as was the case in
N. Alaska Env’t Ctr., discussed above. As this Court has already found, “logging will certainly
occur when the BLM implements the Landscape Plan.” ECF No. 19 at 8. The BLM stated in its
EA that it could not select the “no action” alternative, so logging is sure to occur with
implementation of the plan. AR 131-32. Once an agency determines no significant
environmental impact and issues a FONSI, the NEPA review process concludes. Env’t Def. Ctr.,
36 F.4th at 869. Further, this is not a circumstance where further implementation of the plan is
necessary due to an inherent uncertainty, as was the case in Te-Moak Tribe of West Shoshone of
Nevada. Unlike the project at issue there, this project is not an exploratory plan akin to that of
mineral extraction. Rather, this is a logging plan where the location of the areas to be logged is
well-suited to standard site-specific analysis. The BLM mapped out specific areas designated as
potential harvest units under the plan. AR 3328. The BLM acknowledged that field surveys will
occur only after the NEPA process concludes. AR 3839. Because Plaintiffs will not have an
opportunity to comment on any further agency action, and this is not a situation of inherent
uncertainty, the landscape-level analysis was insufficient to satisfy NEPA.
2. Mitigation Measures
Defendants also argue that any deficiencies with the BLM’s averaging approach are
cured by future pre-treatment and harvest soil surveys at the timber-sale level. While mitigation
measures are necessary for NEPA analysis, they “are not alone sufficient to meet the [agency’s]
NEPA obligations to determine the projected extent of the environmental harm to enumerated
resources before a project is approved.” N. Plains Res. Council, Inc. v. Surface Transp. Bd., 668
F.3d 1067, 1084 (9th Cir. 2011) (emphasis in original); accord Great Basin Res. Watch v.
Bureau of Land Mgmt., 844 F.3d 1095, 1104 (9th Cir. 2016) (“[A] post-[FONSI] analysis—
conducted without any input from the public—cannot cure deficiencies in [a FONSI].”).
Likewise, the BLM cannot rely on future site-specific field surveys because such surveys would
occur only once the BLM has made a determination of NEPA adequacy (“DNA”)—which is not
a NEPA document. AR 3839; see also N. Alaska Env’t Ctr. v. U.S. Dep’t of Interior, 965 F.3d
705, 710 n.3 (9th Cir. 2020) (“A DNA is not itself a NEPA document; it is not subject to public
comment or consultation with other federal agencies.”).
Because the BLM will not have to conduct any further NEPA analysis for the Siuslaw
Plan, its large-scale averaging approach failed to take a “hard look” at how the Siuslaw Plan
would comply with the RMP’s management direction regarding soil impacts. Failing to do so
and relying on future surveys and mitigation violated NEPA.
B. Noxious Weeds and Invasive Species
Plaintiffs also argue that Defendants failed to take a “hard look” at noxious weeds and
invasive species. Defendants argue that (1) Plaintiffs failed to adequately raise this issue during
the comment period and therefore waived this argument, and (2) the Siuslaw Plan did take the
necessary “hard look” at noxious weeds.
1. Waiver
As an initial matter, Defendants contend that Plaintiffs did not properly raise their claims
regarding noxious weeds and invasive species because Plaintiffs allegedly failed to address these
issues with the necessary specificity during the public comment period. Plaintiffs challenging an
agency action must participate in the public comment period in such a way that their statements
alert the agency to the issues raised and “allow the agency to give the issue[s] meaningful
consideration.” Barnes v. U.S. Dep’t of Transp., 655 F.3d 1124, 1132 (9th Cir. 2011); accord
Havasupai Tribe v. Robertson, 943 F.2d 32, 34 (9th Cir. 1991) (holding that the plaintiff’s claims
could not form the basis for agency reversal where it raised those claims after the public
comment period had ended). A plaintiff need not invoke “magic words” during the comment
period “to leave the courtroom door open to a challenge.” Barnes, 655 F.3d at 1133 (quoting
Idaho Sporting Cong., 305 F.3d at 966).
Here, Plaintiffs provided Defendants with the required notice to pursue claims related to
noxious weeds. In 2019, Plaintiffs provided comments to the BLM regarding the Siuslaw Plan.
AR 6206-43. Plaintiffs stated the following: “Logging and roads will expose spread weeds by
exposing mineral soil, transporting seeds, and removing native vegetation thus giving more light
and nutrients to weeds. Inventories show that weeds are closely associated with roads and
recently logged areas. Consider alternatives that avoid creating the conditions to spread weeds.”
AR 6229. In 2021, Plaintiffs restated these concerns by calling for a site-specific impacts
analysis in an EIS to address various issues, including noxious weeds. AR 484-85. These
comments establish that Plaintiffs sufficiently raised the issue of noxious weeds in their
comments to allow Defendants to respond. See Barnes, 655 F.3d at 1132. Defendants also
addressed this issue in their DR, demonstrating that they were sufficiently apprised of the claims
raised by Plaintiffs. AR 24. Plaintiffs have therefore not waived this argument.
2. “Hard Look” Review
Plaintiffs argue that Defendants failed to take the requisite “hard look” at the potential
impacts of noxious weeds and invasive species. Defendants contend that they did take a “hard
look” at noxious weeds by tiering the Siuslaw Plan EA to the 2016 RMP FEIS and by curing any
potentially significant impacts through mitigation measures.
a) Tiering
“Ordinarily, an agency can avoid some of the burdens of the NEPA process by ‘tiering’
to a prior document that has itself been the subject of NEPA review.” All. for the Wild Rockies,
907 F.3d at 1118. However, the Ninth Circuit has stated that tiering is insufficient when both the
programmatic EIS and the project EA contain merely general statements about an issue rather
than site-specific information. Klamath-Siskiyou Wildlands Ctr. v. Bureau of Land Mgmt., 387
F.3d 989, 997 (9th Cir. 2004). Here, tiering was insufficient because neither the 2016 RMP FEIS
nor the Siuslaw Plan EA contained adequately site-specific information or analysis.
Both the 2016 RMP FEIS and the Siuslaw Plan EA acknowledge that noxious weeds are
a problem in Oregon generally. The 2016 RMP FEIS stated that the impact of noxious weeds “in
any specific watershed would depend on a variety of project-specific, watershed-specific, and
species-specific factors that cannot be analyzed at this scale of analysis.” AR 9818. In the
Siuslaw Plan EA, the BLM recognized that the Siuslaw Plan area is at high risk for increased
spread of weeds based on the 2016 RMP FEIS. AR 202 (“The project area falls in watersheds
considered at high to highest risk due to timber harvest, and road construction.”). The EA also
discussed how timber sales in the Siuslaw Plan area will increase weed infestation. AR 201
(“Several studies have documented increased weed infestation after timber sales, and timber
sales in and near the project area have shown this effect as well.” (internal citation omitted)).
Despite these acknowledgments, the BLM declined to analyze this issue in detail in the EA. AR
202 (“For these reasons, the BLM considered this issue but did not analyze it in detail. Because
analysis of this issue isn’t necessary to evaluate how the alternatives respond to the Purpose and
Need and there is no potential for significant effects beyond those described in the Proposed
RMP / Final EIS.”).
Moreover, the BLM’s botanist recognized during the Siuslaw Plan EA’s drafting phase
that invasive species would inform which alternative to select. In an initial draft, the EA stated:
“The BLM considered this issue but did not analyze it in detail because it does not inform the
decision.” AR 3514. The BLM’s botanist rewrote this provision to say, “The BLM considered
this issue but did not analyze it in detail because the BLM is not proposing to use the differences
in invasive species effects to inform the decision.” Id. In a comment, the botanist explained, “[a]s
mentioned above, this wording is a little misleading. We could, for example, choose the all
thinning alternative to lessen effects.” Id. The BLM did not fully disclose how each of the
alternatives would affect noxious weeds despite recognizing that the project may create a
significant impact on noxious weeds in the project area. Because the BLM made merely
conclusory statements and failed to gather site-specific data in either the 2016 RMP FEIS or the
Siuslaw Plan EA, Defendants failed to take the requisite “hard look” at noxious weeds.
b) Mitigation Measures
Defendants also argue that the inclusion of mitigation measures satisfied the “hard look”
requirement with respect to this issue. The Court disagrees for two reasons
First, while the BLM did consider mitigation techniques in the 2016 RMP FEIS, it did
“not detail their extent or expected level of success.” AR 202. The Siuslaw Plan EA did propose
possible mitigation techniques prescribed by the BLM. AR 202. However, after detailing these
possible techniques, the EA stated the following:
An indirect effect of the project is that it adds to the overall inability to successfully
control weeds on the Siuslaw Field Office. Weeds are generally widespread over
Siuslaw Field Office lands, as evidenced through weed mapping efforts. More
acreage of infestations has been documented than can be controlled with current
resources and methods. Recent financial resources have allowed weed control of
high priority species and Scotch broom in the Siuslaw Field Office. High priority
species such as false brome, shining geranium, and meadow knapweed are species
that are not yet abundant, but have a potential for severe impacts. Control measures
have been concentrating on these high priority species and Scotch broom along
roadsides. Roadside infestations are prioritized as they have a high likelihood of
being spread along the road. A lack of financial and personnel resources has often
led to off-road infestations not being controlled. Blackberry has generally not been
controlled as it sprouts from underground after cutting, and herbicides have not
been available, although they have become available in 2020 with the Integrated
Invasive Plant Management for the Northwest Oregon District Environmental
Analysis. It is likely that much of the weed infestations expected to result from the
action alternatives will not be adequately controlled given current resources.
Id. The BLM must provide analytical data supporting mitigation measures; otherwise, such
measures constitute “a mere listing” and fail to satisfy NEPA. Idaho Sporting Cong. v. Thomas,
137 F.3d 1146, 1151 (9th Cir. 1998), overruled on other grounds by Lands Council, 537 F.3d
981 (9th Cir. 2008).
Second—as this Court has already explained with respect to soil disturbance—
“mitigation measures, while necessary, are not alone sufficient to meet [an agency’s] NEPA
obligations to determine the projected extent of the environmental harm to enumerated
resources before a project is approved.” N. Plains Res. Council, 668 F.3d at 1084. The BLM
could not use mitigation alone to cure its failure to adequately consider noxious weeds and
therefore failed to take a “hard look” at the impacts of noxious weeds and invasive species.
C. Special Status Species
Plaintiffs argue that the BLM failed to take a “hard look” at special status species because
it failed to conduct site-specific analyses of the Siuslaw Plan’s impacts on those species.
Defendants respond that the BLM properly tiered its analysis of this issue to the 2016 RMP FEIS
and provided further analysis in the Siuslaw Plan EA, both of which satisfy its NEPA
requirements. Although a larger programmatic EIS need not conduct site-specific analysis, an
EA that tiers to such programmatic EIS must conduct site-specific analysis where “a critical
decision has been made to act on site development.” ‘Ilio’ulaokalani Coal. v. Rumsfeld, 464 F.3d
1083, 1094 (9th Cir. 2006). Here, the Court has already explained that such a critical decision
has been made, and site-specific analysis of impacts on special status species was required in
either the 2016 RMP FEIS or the Siuslaw Plan EA.
The 2016 RMP FEIS did not analyze site-specific impacts on special status species
because its scope was the entire 2.6-million-acre project. Regarding former Survey and Manage
species, the 2016 RMP FEIS stated that the BLM “lack[ed] complete and species-specific survey
information for most Survey and Manage species. It would be exorbitantly expensive and time-
consuming to conduct random surveys across the decision area for all Survey and Manage
species.” AR 9098. Instead, the 2016 RMP FEIS discussed general consequences that the larger
plan would have on these species. See AR 9097-103.
Neither did the Siuslaw Plan EA contain any site-specific analysis of impacts on special
status species. The BLM acknowledged that the following species were either possibly or likely
present in the Siuslaw Field Office: bald eagle, fringed myotis, golden eagle, Oregon red tree
vole, pallid bat, Townsend’s big-eared bat, water flea, bufflehead, coastal greenish blue butterfly,
Haddock’s Rhyacophilan caddisfly, Johnson’s hairstreak butterfly, monarch butterfly, Oregon
coast coho salmon, Oregon coast spring chinook salmon, pacific lamprey, and Oregon coast
steelhead trout. AR 272-77, 296-97. In the Siuslaw Plan EA, if the species were deemed “likely”
to be in the project area, the BLM concluded that the project was unlikely to cause a trend
toward listing; determined that it could employ mitigation measures to prevent any possible trend
toward listing; or both. AR 269-91.
The BLM’s repeated statements in the Siuslaw Plan EA that the Siuslaw Plan would not
cause a trend towards listing are conclusory, speculative, and devoid of any site-specific analysis.
Site-specific analysis is a critical inquiry that the Ninth Circuit has determined NEPA requires.
Anderson v. Evans, 314 F.3d 1006, 1019-20 (9th Cir. 2002) (“Even if the eastern Pacific gray
whales overall or the smaller PCFA group of whales are not significantly impacted by the Makah
Tribe’s whaling, the summer whale population in the local Washington area may be significantly
affected. Such local effects are a basis for a finding that there will be a significant impact from
the Tribe’s hunts.”). The BLM’s conclusory statements about the likelihood of a trend towards
listing are insufficient to satisfy NEPA. See Earth Island Inst. v. U.S. Forest Serv., 442 F.3d
1147, 1172 (9th Cir. 2006), abrogated on other grounds by Winter v. Nat. Res. Def. Council,
Inc., 555 U.S. 7 (2008) (finding a statement “without meaningful explanation” that a project
“would not result in a trend toward federal listing” is insufficient to satisfy NEPA’s “hard look”
requirement).
Neither do the BLM’s statements that it would employ mitigation to prevent trends
towards listing satisfy its NEPA obligations. As explained above in the context of soil
disturbance and noxious weeds, “mitigation measures, while necessary, are not alone sufficient
to meet [an agency’s] NEPA obligations to determine the projected extent of the environmental
harm to enumerated resources before a project is approved.” N. Plains Res. Council, 668 F.3d at
1084. The BLM’s failure in either the 2016 RMP FEIS or the Siuslaw Plan EA to evaluate site-
specific impacts on special status species therefore violated NEPA.
D. Cumulative Impacts
Plaintiffs next argue that Defendants failed to analyze and disclose cumulatively
significant impacts. A “hard look” under NEPA requires consideration of cumulative impacts.
Idaho Sporting Cong., 305 F.3d at 963; 40 C.F.R. § 1508.25(c) (agency “shall consider” direct,
indirect, and cumulative impacts). Such analysis “must be more than perfunctory; it must provide
a useful analysis of the cumulative impacts of past, present, and future projects.” Klamath-
Siskiyou Wildlands Ctr., 387 F.3d at 994 (quoting Ocean Advocs. v. U.S. Army Corps of Eng’rs,
361 F.3d 1108, 1128 (9th Cir. 2004)).
Plaintiffs argue that the BLM failed to consider the cumulative impacts of the Siuslaw
Plan in combination with the “N126 Project,” which “overlap[] in time and space.” Pls.’ Mot.
31-32. They note that both projects identify similar effects, compare AR 1992-93 with AR 128-
30, and in some of the same geographic locations, compare AR 3328 with AR 2128, but the
Siuslaw Plan EA did not consider the cumulative impacts of these issues. To illustrate the
problem with the BLM’s analysis, Plaintiffs contend that while both projects will create early
successional ecosystems that have impacts on certain wildlife species, the Siuslaw Plan EA fails
to consider the cumulative impacts of such creation. Defendants contend Plaintiffs have
erroneously conflated two distinct issues—“early successional ecosystems” for the Siuslaw Plan
with “early-successional habitat” for the N126 Project—each of which have different meanings
and impacts.
The Court agrees that Defendants failed to consider the cumulative effects of the N126
Project and the Siuslaw Plan. As Plaintiffs point out, the N126 EA identifies several of the same
impacts as the Siuslaw Plan EA. Compare AR 1992-93 with AR 128-30. Yet the Siuslaw Plan
EA omits consideration of the cumulative effects of these impacts. While it discusses the
cumulative impacts of road construction on sediment delivery to streams for both projects, AR
215-16, it is otherwise completely silent on the cumulative impacts of these projects.
Defendants’ arguments about the technical distinction between “early successional ecosystems”
and “early-successional habitat” fail to explain the general lack of discussion of cumulative
impacts of the Siuslaw Plan and the N126 Project. Rather, the Court understands Plaintiffs’
discussion of the early successional issue to be illustrative of the BLM’s failure throughout the
EA to address cumulative impacts, not the sum total of Plaintiffs’ argument.
The cases cited by Plaintiffs establish that an adequate cumulative impacts analysis must
consider the impacts of nearby timber sales. See, e.g., Kern v. U.S. Bureau of Land Mgmt., 284
F.3d 1062, 1077-78 (9th Cir. 2002) (holding that the BLM’s NEPA analysis insufficient because
it made “no attempt to analyze the cumulative impacts of the Sandy-Remote timber sales when
combined with ‘reasonably foreseeable future actions’ (such as other timber sales) outside the
Sandy-Remote Area”); Blue Mountains Biodiversity Project v. Blackwood, 161 F.3d 1208, 1215
(9th Cir. 1998) (holding that the BLM’s NEPA analysis insufficient where it failed to consider
cumulative impacts of reasonably foreseeable timber sales within the same watershed);
Neighbors of Cuddy Mountain v. U.S. Forest Serv., 137 F.3d 1372, 1380 (9th Cir. 1998)
(“Because the three proposed sales in this case were ‘reasonably foreseeable,’ the Forest Service
was obligated to assess the cumulative impact of all sales on the availability of old growth
habitat for the pileated woodpecker.”). In omitting almost all consideration or discussion of the
cumulative impacts of the Siuslaw Plan and the N126 Project despite the overlap in time, space,
and types of anticipated effects, the BLM violated NEPA’s requirement to consider cumulative
impacts.
III. Failure to Prepare an Environmental Impact Statement
Plaintiffs next argue that Defendants failed to prepare an EIS as required by NEPA.
NEPA requires federal agencies to prepare and publicly disclose a “detailed statement”
describing the environmental impacts of, and alternatives to, any major federal action that may
“significantly affect[] the quality of the human environment.” 42 U.S.C. § 4332(C). Commonly
known as an environmental impact statement, or “EIS,” the statement must contain a “full and
fair discussion of significant environmental impacts” and describe “reasonable alternatives which
would avoid or minimize adverse impacts.” 40 C.F.R. §§ 1508.11, 1502.1; accord Te-Moak
Tribe of W. Shoshone of Nev., 608 F.3d at 602.
To determine whether an action will have significant environmental effects, an agency
may prepare an EA. 40 C.F.R. § 1501.5(a)-(c). Although less comprehensive than an EIS, an EA
must contain detailed analyses of project impacts and alternatives. Te-Moak Tribe of W.
Shoshone of Nev., 608 F.3d at 602-03 (citing 40 C.F.R. § 1508.9(b)). If the agency does not
prepare an EIS, it must provide a “convincing statement of reasons to explain why [the] project’s
impacts are insignificant” in a FONSI. 350 Mont. v. Haaland, 29 F.4th 1158, 1163 (9th Cir.
2022) (alteration in original) (quoting Bark v. U.S. Forest Serv., 958 F.3d 865, 869 (9th Cir.
2020)); accord Metcalf v. Daley, 214 F.3d 1135, 1143 (9th Cir. 2000) (“The purpose of an EA is
to provide the agency with sufficient evidence and analysis for determining whether to prepare
an EIS or to issue a FONSI.” (citing 40 C.F.R. § 1508.9)).
To prevail on a claim that the agency violated NEPA by failing to prepare an EIS, a
claimant need not show that significant effects will occur; it is enough to raise “substantial
questions” whether a project may have a significant effect on the environment. See Greenpeace
Action v. Franklin, 14 F.2d 1324, 1332 (9th Cir. 1992). As the Ninth Circuit has consistently
held, this is a low standard. See, e.g., Klamath Siskiyou Wildlands Ctr. v. Boody, 468 F.3d 549,
562 (9th Cir. 2006). Significance is evaluated using context and intensity factors. 40 C.F.R. §
1508.27. A single intensity factor may require preparation of an EIS. Ocean Advocs. v. U.S.
Army Corps of Eng’rs, 402 F.3d 846, 865 (9th Cir. 2005). Here, Plaintiffs argue that Defendants
violated NEPA because (1) the BLM’s reasons for not preparing an EIS are flawed; and (2)
substantial questions exist over whether the Siuslaw Plan may have significant impacts.
First, with respect to whether the BLM provided a convincing statement of reasons for
not preparing an EIS, the Court has already addressed the ways in which the BLM failed to take
the requisite “hard look” at various environmental impacts of the Siuslaw Plan. The resulting
FONSI and supporting statement of reasons are unconvincing for the same reasons. Second, the
Court agrees that substantial questions exist regarding whether the Siuslaw Plan may have
significant impacts. Regulations identify several intensity factors to consider in evaluating the
significance of impacts. See 40 C.F.R. § 1508.27(b) (listing intensity factors). Plaintiffs argue
that several intensity factors raise substantial questions here:
• 40 C.F.R. § 1508.27(b)(7) (“Whether the action is related to other actions with
individually insignificant but cumulatively significant impacts. Significance exists if it is
reasonable to anticipate a cumulatively significant impact on the environment.
Significance cannot be avoided by terming an action temporary or by breaking it down
into small component parts.”). Here, as addressed above, the cumulative impacts of the
Siuslaw Plan with those of the N126 Project may be significant but are unaddressed in
the EA and FONSI.
• 40 C.F.R. § 1508.27(b)(9) (“The degree to which the action may adversely affect an
endangered or threatened species or its habitat that has been determined to be critical
under the Endangered Species Act of 1973.”). Here, the record raises substantial
questions about the adverse effects on numerous threatened species and their critical
habitat, including marbled murrelets, the northern spotted owl, Oregon Coast Coho
Salmon, and Upper Willamette River Chinook Salmon. See AR 192-93.
• 40 C.F.R. § 1508.27(b)(5) (“The degree to which the possible effects on the human
environment are highly uncertain or involve unique or unknown risks.”). Here, as
addressed above, the lack of information about several site-specific impacts of the
Siuslaw Plan and the ability of those impacts to be mitigated render such effects highly
uncertain.
Individually, and certainly cumulatively, the Court finds that several intensity factors
raise substantial questions over whether the Siuslaw Plan may have significant impacts.
IV. Remedy/Relief
While contesting the Court’s findings on the merits,4 Defendants agree that vacatur of
the Siuslaw Plan Decision Record is the appropriate remedy based on those findings. Defs.’
Remedy Brief 3-4, ECF No. 48. However, Defendants contend that rather than instructing the
BLM to prepare an EIS, the Court should instead instruct the BLM to conduct further analysis
and explanation. Plaintiffs contend that Ninth Circuit case law requires the Court to order the
BLM to prepare an EIS for the Siuslaw Plan in light of the Court’s finding that substantial
questions exist regarding whether the Siuslaw Plan may have significant impacts.
“[P]reparation of an EIS is not mandated in all cases simply because an agency has
prepared a deficient EA or otherwise failed to comply with NEPA.” Ctr. for Biological Diversity
v. Nat’l Highway Traffic Safety Admin., 538 F.3d 1172, 1178 (9th Cir. 2008). If the court “cannot
determine whether the proposed rule or project may have a significant effect,” then the correct
approach is to remand for the preparation of an EA. Id. But “if the court determines that the
agency’s proffered reasons for its FONSI are arbitrary and capricious and the evidence in a
complete administrative record demonstrates that the project or regulation may have a significant
impact, then it is appropriate to remand with instructions to prepare an EIS.” Id. at 1179. Ninth
4 A substantively identical decision on the merits of the parties’ motions was originally issued as
a now-vacated Findings and Recommendation. See ECF No. 44. That Findings and
Recommendation deferred the decision on remedy, ordering that “[s]hould the district court
adopt this Findings and Recommendation, the parties are directed to contact the Court within 30
days of that order to arrange a status conference to discuss a briefing schedule for the appropriate
remedy.” Id. at 27-28. The parties ultimately did brief the issue of remedy in the course of filing
a motion to amend or correct the Findings and Recommendation, and in their objections to the
Findings and Recommendation. See ECF Nos. 48, 49, 51, 52, 57, 58. When it vacated the
Findings and Recommendation, the Court noted that it would consider the parties’ arguments and
authority on this issue as supplemental briefing in support of their motions for summary
judgment. See ECF No. 61. The Court has done so in reaching its conclusions here.
Circuit case law is clear that “[a]n EIS must be prepared if ‘substantial questions are raised’” as
to whether a project may have significant impacts. Blue Mountains Biodiversity Project, 161
F.3d at 1212 (quoting Idaho Sporting Cong. v. Thomas, 137 F.3d at 1149).
This is not a case where the Court was unable to determine whether there may be
significant effects. Rather, the Court has explicitly found in Section III of this opinion that
substantial questions exist over whether the Siuslaw Plan may have significant impacts. Under
the clear rule set forth in the case law cited above, an EIS must be prepared in light of that
finding.
CONCLUSION
For the reasons above, Defendants’ Motion for Summary Judgment (ECF No. 36) is
DENIED. Plaintiffs’ Motion for Summary Judgment (ECF No. 33) is GRANTED. The Siuslaw
Plan EA, DR, and FONSI are vacated and the matter is remanded to the BLM for the preparation
of an EIS. The parties are ordered to confer and jointly submit a proposed judgment consistent
with this Opinion and Order within 30 days.
DATED this 24th day of April 2025.
s/ Mustafa T. Kasubhai
MUSTAFA T. KASUBHAI (He / Him)
United States District Judge