Opinion

Cascadia Wildlands v. Adcock

Court
District Court, D. Oregon
Filed
Apr 24, 2025
Cited by
0 cases
Authority
More cited than 34.9%

finding a statement “without meaningful explanation” that a project “would not result in a trend toward federal listing” is insufficient to satisfy NEPA’s “hard look” requirement

How later courts described this case

  • finding a statement “without meaningful explanation” that a project “would not result in a trend toward federal listing” is insufficient to satisfy NEPA’s “hard look” requirement
  • “[T]he binding authority principle applies only to appellate decisions, and not to trial court decisions.”
  • “The purpose of an EA is to provide the agency with sufficient evidence and analysis for determining whether to prepare an EIS or to issue a FONSI.” (citing 40 C.F.R. § 1508.9)
  • holding that the “BLM, in some cases, may adapt its assessment of environmental impacts when the specific locations of an exploration project’s activities cannot reasonably be ascertained until some time after the project is approved”

Written by the judges who cited it.

The opinion

UNITED STATES DISTRICT COURT

DISTRICT OF OREGON

CASCADIA WILDLANDS and Case No. 6:22-cv-01344-MTK

OREGON WILD,

OPINION AND ORDER

Plaintiffs,

vs.

CHERYL ADCOCK and UNITED STATES

BUREAU OF LAND MANAGEMENT,

Defendants.

_________________________________________

KASUBHAI, United States District Judge:

Plaintiffs Cascadia Wildlands and Oregon Wild (“Plaintiffs”) filed this action alleging

violations of the National Environmental Policy Act (“NEPA”) 42 U.S.C. §§ 4321 et seq., and

the Administrative Procedure Act (“APA”) 5 U.S.C. §§ 701 et seq., against the United States

Bureau of Land Management (“BLM”) and Cheryl Adcock in her official capacity as Field

Manager for the BLM’s Siuslaw Field Office (collectively, “Defendants”). Before the Court are

the parties’ cross-motions for summary judgment. ECF Nos. 33, 36. For the reasons below,

Plaintiffs’ motion is granted, and Defendants’ motion is denied.

BACKGROUND

Plaintiffs allege that Defendants violated NEPA in preparing their Siuslaw Harvest Land

Base Landscape Plan Environmental Assessment (“Siuslaw Plan EA”) by failing to take a “hard

look” at the Siuslaw Plan’s environmental impacts and failing to prepare an Environmental

Impact Statement. See Compl. ¶¶ 101-47, ECF No. 1. The Court begins by summarizing the

relevant statutory and regulatory framework and the facts underlying this action.

I. Statutory and Regulatory Framework

A. NEPA

NEPA’s purpose is to require agencies to disclose “relevant environmental considerations

that were given a ‘hard look’ by the agency, and thereby to permit informed public comment on

proposed action and any choices or alternatives that might be pursued with less environmental

harm.” Lands Council v. Powell, 395 F.3d 1019, 1027 (9th Cir. 2005). It “does not mandate

particular results, but simply prescribes the necessary process.” Robertson v. Methow Valley

Citizens Council, 490 U.S. 332, 350 (1989).

To that end, NEPA requires agencies proposing “major Federal actions significantly

affecting the quality of the human environment” to prepare a detailed statement—an

Environmental Impact Statement (“EIS”)—discussing environmental impacts of the proposed

action and a range of alternatives to avoid adverse impacts. 42 U.S.C. § 4332(C). To determine

whether a proposed action will significantly affect the quality of the human environment (and

therefore require an EIS), an agency may prepare an Environmental Assessment (EA). 40 C.F.R.

§ 1501.5. “If an agency decides not to prepare an EIS, it must supply a ‘convincing statement of

reasons’ to explain why a project’s impacts are insignificant.” Cascadia Wildlands v. Bureau of

Indian Affs., 801 F.3d 1105, 1111 (9th Cir. 2015) (quoting Blue Mountains Biodiversity Project

v. Blackwood, 161 F.3d 1208, 1212 (9th Cir.1998)).

B. FLPMA/O&C Act

Under the Federal Land Policy and Management Act (“FLPMA”), the BLM must prepare

Resource Management Plans (“RMPs”) for its districts. 43 U.S.C. § 1712. RMPs “are designed

to guide and control future management actions and the development of subsequent, more

detailed and limited scope plans for resources and uses.” 43 C.F.R. § 1601.0-2. The BLM must

manage lands governed by FLPMA “under principles of multiple use and sustained yield.” 43

U.S.C. § 1732(a). By contrast, lands that are governed by the Oregon and California Railroad

and Coos Bay Wagon Road Grants Lands Act (“O&C Act”) are managed “for permanent forest

production . . . in conformity with the principal [sic] of sustained yield.” 43 U.S.C. § 2601.

However, O&C Act lands are still subject to the procedural requirements of FLPMA, including

preparation of RMPs. See Klamath-Siskiyou Wildlands Ctr. v. U.S. Bureau of Land Mgmt., No.

1:19-cv-02069-CL, 2021 WL 4462886, at *2 (D. Or. Sept. 29, 2021).

The development of an RMP “is considered a major Federal action significantly affecting

the quality of the human environment” requiring the preparation of an EIS under NEPA. 43

C.F.R. § 1601.0-6. Further site-specific actions implementing the RMP must conform to the

governing RMP and require compliance with NEPA. AR 9386.

II. Factual Background

A. 2016 Resource Management Plan

In 2016, the BLM adopted the RMP for Northwestern and Coastal Oregon (“2016

RMP”). AR 7476-77. The 2016 RMP “provides direction for management of resources on

approximately 1.3 million acres of BLM-administered lands in the Coos Bay District, Eugene

District, Salem District, and the Swiftwater Field Office of the Roseburg District.” AR 7476. The

RMP categorizes different portions of the land at issue into various land use allocations, each of

which is subject to different management objectives and directions. AR 7528. The land use

allocation at issue in this case is the Harvest Land Base (“HLB”). Id. Consistent with its

obligations under the O&C Act, the objectives for the HLB allocation include managing “forest

stands to achieve continual timber production,” offering for sale “the declared Allowable Sale

Quantity of timber” (“ASQ”), and “[i]n harvested or disturbed areas, ensur[ing] the

establishment and survival of desirable trees.” AR 7540. The ASQ in the Eugene sustained-yield

unit was set at 53 million board feet. AR 7486-87.

The BLM issued a Final EIS (“2016 RMP FEIS”) that the Ninth Circuit held satisfied its

obligation under NEPA in adopting the 2016 RMP. Rivers v. Bureau of Land Mgmt., 815 F.

App’x 107, 110 (9th Cir. 2020). The 2016 RMP FEIS considered the impacts of both the

Northwestern RMP and the RMP for Southwestern Oregon, encompassing a total of 2.5 million

acres. AR 7482, 9347. The 2016 RMP FEIS acknowledged that the RMPs it evaluated do not

directly authorize implementation of projects and that implementation decisions would require

additional NEPA compliance. AR 9386-87.

B. Siuslaw Plan

In March 2022, the BLM approved a plan (the “Siuslaw Plan”) to meet the Siuslaw Field

Office’s obligations under the 2016 RMP and the O&C Act to contribute timber to the ASQ in

the Eugene sustained-yield unit. AR 124. The Siuslaw Plan involves a two-decade commercial

logging project on BLM-administered forestland directly west of Eugene, Oregon. It does not

“authorize any specific action” but instead “outline[s] the strategy” for meeting the Siuslaw Field

Office’s contribution to the relevant ASQ declared in the 2016 RMP. AR 127.

The Siuslaw Plan includes the Siuslaw Plan EA, the Siuslaw Plan Finding of No

Significant Impact (“FONSI”), and the Siuslaw Plan Decision Record (“DR”). AR 1, 117, 10. In

approving the Siuslaw Plan, the BLM evaluated “the effects of five action alternatives that would

conduct timber harvest treatments within 13,225 acres of BLM managed lands in the Harvest

Land Base land use allocation and a no-action alternative.” AR 1. Following scoping and public

involvement, the BLM identified 47 “issues” to be considered but eliminated all but five from

detailed consideration. AR 127-30. The BLM ultimately selected “Alternative 4” which would

produce ASQ volume by harvesting 1,404-2,305 acres per decade, including 278-944 acres

through commercial thinning and 1,126-1,361 though regeneration harvesting. AR 13. Pursuant

to the analysis contained in the EA, the BLM found that the Siuslaw Plan would not have

significant environmental impacts and therefore concluded that an EIS was not necessary. AR 1-

2.

Plaintiffs are Oregon nonprofit corporations that filed this action for declaratory and

injunctive relief on September 8, 2022, alleging NEPA violations based on Defendants’ failure to

(1) adequately analyze and disclose the Siuslaw Plan’s potentially significant environmental

impacts; and (2) prepare an Environmental Impact Statement as required for actions that may

have environmentally significant impacts. Compl. ¶¶ 101-47. Defendants moved to dismiss the

action for lack of jurisdiction on November 14, 2022, and the Court denied the motion on May

24, 2023. ECF Nos. 10, 19, 22 (adopting Findings & Recommendation). Plaintiffs and

Defendants now cross-move for summary judgment. Pls.’ Mot. for Summ. J. (“Pls.’ Mot.”) ECF

No. 33; Defs.’ Mot. for Summ. J. (“Defs.’ Mot.”) ECF No. 36. The Court held oral argument on

the motions on February 8, 2024.

STANDARD OF REVIEW

Plaintiffs allege violations of NEPA and its implementing regulations, which are

reviewed under the Administrative Procedure Act (“APA”). 5 U.S.C. §§ 701-706. The Ninth

Circuit endorses the use of Rule 56 summary judgment motions to resolve such claims. Nw.

Motorcycle Ass’n v. U.S. Dep’t of Agric., 18 F.3d 1468, 1471-72 (9th Cir. 1994). Under the

APA, a court shall hold unlawful and set aside agency action, findings, and conclusions found to

be arbitrary, capricious, or otherwise unlawful. 5 U.S.C. § 706(2). An agency action is arbitrary

and capricious if the agency “entirely failed to consider an important aspect of the problem,” or

offered an explanation “that runs counter to the evidence before the agency.” Lands Council v.

McNair, 537 F.3d 981, 987 (9th Cir. 2008) (quoting Earth Island Inst. v. U.S. Forest Serv., 442

F.3d 1147, 1157 (9th Cir. 2006). Reviewing courts “may not rubber-stamp . . . administrative

decisions that they deem inconsistent with a statutory mandate or that frustrate the congressional

policy underlying a statute.” Friends of Yosemite Valley v. Norton, 348 F.3d 789, 793 (9th Cir.

2003) (alteration in original) (quoting Pub. Citizen v. DOT, 316 F.3d 1002, 1020 (9th Cir.

2003)).

DISCUSSION

The parties each argue that they are entitled to summary judgment on Plaintiffs’ NEPA

claims. Plaintiffs argue that Defendants’ actions violated NEPA because they (1) failed to take a

“hard look” at, and adequately analyze and disclose, the Siuslaw Plan’s potentially significant

environmental impacts; and (2) failed to prepare an Environmental Impact Statement as required

for actions that may have environmentally significant impacts.

I. Threshold Issues

Plaintiffs’ motion begins with several sections that address the BLM’s general approach

to NEPA compliance with respect to the Siuslaw Plan. Plaintiffs argue that Defendants erred in

(1) using a “purpose and need” statement to omit 42 out of 47 environmental issues from detailed

consideration, and (2) inappropriately “tiering”1 the Siuslaw Plan EA to the 2016 RMP FEIS to

the exclusion of analyzing site-specific impacts. Relatedly, Defendants argue broadly that their

use of landscape-level analysis of the Siuslaw Plan’s environmental impacts complies with

NEPA and has been upheld by the Ninth Circuit. See Defs.’ Reply 6-7, ECF No. 42 (citing

Klamath-Siskiyou Wildlands Ctr. v. Bureau of Land Mgmt., No. 22-35035, 2022 WL 17222416

(9th Cir. Nov. 25, 2022)).

A. Purpose and Need Statement

Plaintiffs contend that the BLM improperly omitted from detailed consideration specific

environmental issues because such issues were “not directly correlated with the agency’s purpose

and need of timber production.” Pls.’ Mot. 17. Defendants argue that Plaintiffs misunderstand

the BLM’s approach and that it did not limit its analysis in the manner Plaintiffs contend.

In excluding 42 of 47 identified environmental issues, the BLM explained that issues

only warranted “detailed analysis if (1) analysis of the issue is necessary to provide information

1 With respect to tiering, the applicable regulations provide:

Whenever a broad environmental impact statement has been prepared (such as a

program or policy statement) and a subsequent statement or environmental

assessment is then prepared on an action included within the entire program or

policy (such as a site specific action) the subsequent statement or environmental

assessment need only summarize the issues discussed in the broader statement and

incorporate discussions from the broader statement by reference and shall

concentrate on the issues specific to the subsequent action.

40 C.F.R. § 1502.20.

to the decision-maker to be able to make a reasoned choice between alternatives presented (that

is, it is related to the purpose and need for action); or (2) the analysis of the issue is necessary to

determine the significance of the impacts.” AR 128 (citing BUREAU OF LAND MGMT., H-1790-1,

BLM NATIONAL ENVIRONMENTAL POLICY ACT HANDBOOK (2008), at 41). Plaintiffs argue that

the above statement indicates that some or all of the 42 issues omitted from detailed

consideration were omitted on the basis that they were not consistent with the purpose and need

to produce timber.

The Court does not read the BLM’s statement—either alone or in the context of the EA

as a whole—to indicate that the BLM omitted issues from detailed consideration solely because

they were not consistent with the purpose and need. Instead, it is an either/or statement. In other

words, the BLM considered issues in detail if they were either related to the purpose and need of

the project or analysis was necessary to determine the significance of the impacts of the issue.

Whether the BLM’s decision that detailed analysis was not necessary to determine the

significance of those issues’ impacts constituted a failure to take a “hard look” is a separate

question, addressed in the following portions of this opinion. But there is no indication in the

record to suggest that the BLM declined to analyze any issues solely because they were

inconsistent with the purpose and need of the Siuslaw Plan.

B. General Arguments about Landscape-Level Analysis

Both parties raise general arguments about the propriety of landscape-level analysis and

tiering, citing other decisions in this district that each party contends control this Court’s

conclusion.

Plaintiffs argue in Section II of their motion that the BLM’s adoption of the Siuslaw

Plan—a landscape-level plan—required a site-specific analysis of environmental impacts and

that the Siuslaw Plan EA did not contain such analysis. Plaintiffs contend that by tiering to the

2016 RMP FEIS to conclude that the Siuslaw Plan would have no significant impacts, the BLM

failed to consider the impacts specific to the Siuslaw Plan project area. Defendants contend that

what Plaintiffs are advocating is a “sale-by-sale” approach that is not supported in the case law,

and they argue that the Siuslaw Plan EA contained the required site-specificity.

It is unclear to the Court whether this portion of Plaintiffs’ motion is intended to offer a

general statement of the law regarding site-specificity and tiering to provide a framework to

evaluate the particular issues they raise, or whether Plaintiffs seek to have the Court make a

general finding that the use of tiering in the Siuslaw Plan EA was inappropriate with respect to

the BLM’s analysis as a whole. The parties appear to agree that tiering is appropriate in some

cases. Plaintiffs argue that tiering is impermissible here because “none of the documents address

significant issues.” Pls.’ Mot. 18 (quoting Cascadia Wildlands v. Bureau of Land Mgmt.

(“Thurston I”), 410 F. Supp. 3d 1146, 1158-59 (D. Or. 2019)). Thus—as even Plaintiffs’

argument implies—the question before the Court is whether the BLM did, in fact, fail to consider

significant issues here. To resolve that question, the Court must evaluate the BLM’s analysis of

specific issues. To the extent that Plaintiffs ask the Court to make a general finding that the

BLM’s tiering approach throughout the Siuslaw Plan EA violated NEPA, the Court cannot do so

in the abstract.2

Defendants make a similar broad argument in their briefing, claiming that this case is

“resolve[d]” by another decision in this district which challenged another EA that tiered to the

2 Contrary to Plaintiffs’ contention in their brief, the Court did not already make such a general

finding in “Thurston I.” Instead, that opinion evaluated the appropriateness of tiering and NEPA

compliance with respect to the specific issue of fire hazards. See Cascadia Wildlands, 410 F. Supp.

3d at 1157.

same 2016 RMP FEIS at issue here. See Defs.’ Objs. to F&R 13, ECF No. 57 (citing Klamath-

Siskiyou Wildlands Ctr. v. United States Bureau of Land Mgmt. (“North Landscape”), No. 1:19-

cv-01810-CL, 2021 WL 5356969, at *1 (D. Or. Aug. 24, 2021), report and recommendation

adopted, No. 1:19-CV-1810-CL, 2021 WL 5355919 (D. Or. Nov. 16, 2021), aff’d, No. 22-

35035, 2022 WL 17222416 (9th Cir. Nov. 25, 2022)). Defendants contend that because North

Landscape concluded that the EA at issue in that case properly tiered to the same 2016 RMP

FEIS at issue here, see North Landscape, 2021 WL 5356969, at *6, this Court is compelled to

conclude the same.

Defendants’ argument that North Landscape controls the outcome of this case is flawed

for two reasons. First, it suffers from the same logical pitfall as Plaintiffs’ broad argument on the

propriety of tiering to the 2016 RMP FEIS. North Landscape evaluated whether an EA for a

project in the Klamath Falls Resource Area adhered to NEPA requirements when it tiered to the

2016 RMP FEIS in its evaluation of the project’s impacts on Northern Spotted Owl habitat. Id. at

*6-7. This Court is not evaluating the same EA challenged in that case, nor even the same issue.3

As the Court noted with respect to Plaintiffs’ similar argument, the question here is narrow and

confined to the specific issues before the Court rather than a general finding on the propriety of

tiering to the 2016 RMP FEIS.

3 Indeed, even North Landscape pointed out the fact that the 2016 RMP FEIS was upheld by the

Ninth Circuit was not dispositive of the specific challenges to the government’s analysis of the

site-specific project at issue there. See North Landscape, 2021 WL 5356969, at *3. In fact, that

court specifically noted that tiering to the 2016 RMP FEIS had been found appropriate in some

cases but not others. Id. at *7 (“This Court recently found that a site-specific project EA may

properly tier to a programmatic species-level analysis in the FEIS for the 2016 RMP where that

analysis contemplates specific activities within a planning area. . . . By contrast, this Court found

tiering to the analysis about the great grey owl insufficient because it lacked the necessary site-

specific disclosures and merely acknowledged that the great grey owl was at risk.”).

Second, North Landscape is not precedential. See Hart v. Massanari, 266 F.3d 1155,

1174 (9th Cir. 2001) (“[T]he binding authority principle applies only to appellate decisions, and

not to trial court decisions.”). Neither is the Ninth Circuit’s unpublished memorandum opinion

affirming North Landscape controlling. See Circuit Rule 36-3(a) (“Unpublished dispositions and

orders of this Court are not precedent, except when relevant under the doctrine of law of the case

or rules of claim preclusion or issue preclusion.”).

The following sections evaluate whether the BLM’s tiering approach and lack of site-

specificity resulted in a failure to address specific potentially significant issues. But the Court

cannot make a general finding that the BLM’s approach to the Siuslaw Plan EA did not (in the

case of Plaintiffs’ argument) or did (in the case of Defendants’ argument) comply with NEPA

simply because it tiered to the 2016 RMP FEIS.

In sum, neither of the threshold issues resolve the parties’ cross-motions. Instead, the

question is whether the BLM failed to take a “hard look” at significant environmental impacts of

the Siuslaw Plan, and specifically whether the BLM’s use of tiering in this particular instance

was insufficient because neither the Siuslaw Plan EA nor the 2016 RMP EIS considered specific

potentially significant issues.

II. Failure to Analyze and Disclose Potentially Significant Environmental Impacts

Plaintiffs argue that Defendants violated NEPA by failing to take the requisite “hard

look” at several issues in the Siuslaw Plan EA. “In NEPA, Congress recognized the ‘profound

impact’ of human activities, including ‘resource exploitation,’ on the environment and declared a

national policy ‘to create and maintain conditions under which man and nature can exist in

productive harmony.’” Ctr. for Biological Diversity v. U.S. Dep’t of Interior, 623 F.3d 633, 642

(9th Cir. 2010) (quoting 42 U.S.C. § 4331(a)). To this end, NEPA and its implementing

regulations set forth “action-forcing” procedures designed to (1) ensure agencies take a “hard

look” at the environmental effects of proposed actions and (2) foster meaningful public

participation. Robertson, 490 U.S. at 349.

Because the BLM has “irreversibly and irretrievably” committed resources to the Siuslaw

Plan, it was obligated to take a “hard look” at the Siuslaw Plan’s direct, indirect, and cumulative

impacts. See Conner v. Burford, 848 F.2d 1441, 1446 (9th Cir. 1988); W. Watersheds Project v.

Abbey, 719 F.3d 1035, 1050 (9th Cir. 2013). A “hard look” requires consideration of all

foreseeable direct, indirect, and cumulative impacts. Idaho Sporting Cong. v. Rittenhouse, 305

F.3d 957, 963 (9th Cir. 2002); 40 C.F.R. § 1508.25(c) (2019) (stating that an agency “shall

consider” direct, indirect, and cumulative impacts). This includes evaluation of the additive

impacts of the action on top of the environmental baseline, see 40 C.F.R. § 1502.15 (2019)

(requiring that agencies “describe the environment of the area(s) to be affected”), and a

comparison to other alternative courses of action, see 40 C.F.R. § 1508.25(b) (2019) (agency

“shall consider” alternatives). An agency fails to take a “hard look” when an EA is speculative

and conclusory. See Greenpeace Action v. Franklin, 14 F.3d 1324, 1335-36 (9th Cir. 1992).

Importantly, if the “hard look” reveals the effects of the action “may” be significant, the

decision-maker cannot approve the action “unless it is either analyzed in an EIS or modified to

avoid significant effects.” AR 13730; accord Nat’l Parks & Conservation Ass’n v. Babbitt, 241

F.3d 722, 730 (9th Cir. 2001). At the same time, “NEPA documents must concentrate on the

issues that are truly significant to the action in question, rather than amassing needless detail.” 40

C.F.R. § 1500.1(b) (2019).

Plaintiffs challenge the BLM’s failure to give sufficiently detailed consideration to 42

environmental issues. AR 201-60 (eliminating 42 issues from “detailed consideration”). As the

Court addressed above, it cannot make a finding that the BLM’s general approach to the 42

issues violated NEPA but instead must make that determination with respect to such issues the

BLM allegedly failed to properly consider. In their briefing, Plaintiffs target four specific issues,

arguing that Defendants failed to take a “hard look” at (1) soil disturbance, (2) noxious weeds

and invasive species, (3) special status species, and (4) the Siuslaw Plan’s cumulative impacts on

the environment.

A. Soil Disturbance

The Northwestern RMP requires the BLM to “[l]imit detrimental soil disturbance from

forest management operations to a total of < 20 percent of the harvest unit area.” AR 7570. In its

EA Specialist Report for Soils and Geology, the BLM stated:

A determination of the Harvest Land Base (HLB) project impacts on soil quality is

made using the same methods and assumptions described in the RMP, but is

quantified at the project-area and treatment-unit scale utilizing local spatial data,

soils and geology information sources, and treatment information. The finer spatial

scale of this analysis enables greater precision, historic disturbance quantification,

and site-specificity in assessing local soil quality impacts than the spatial scale of

the RMP.

AR 3839. However, in the Siuslaw Plan EA itself, the BLM concluded that “individual field site

assessment was not feasible at the scale of this analysis,” and instead assessed baseline soil

conditions across the entire 13,225-acre Siuslaw Plan area. AR 1768-69.

Plaintiffs contend that by failing to conduct a harvest-level analysis of soil disturbance—

despite the BLM’s acknowledgement that a site-specific approach was available—the BLM

failed to take a hard look at how the Siuslaw Plan would comply with the Northwestern RMP’s

management direction regarding soil impacts. Defendants argue that the BLM did conduct the

requisite “hard look” through its baseline averaging and proposed mitigation measures.

1. The BLM’s Averaging Approach

The Ninth Circuit has cautioned that averaging environmental impacts across a larger

project area can be “grossly misleading.” Or. Nat. Res. Council Fund v. Brong, 492 F.3d 1120,

1129-30 (9th Cir. 2007). Specifically, the Ninth Circuit explained that the averaging in that case

was an attempt by the BLM “to dilute the effects of its proposed activities” and that “an agency

cannot try to ‘minimize’ the environmental impact of an activity by simply adopting a scale of

analysis so broad that it marginalizes the site-level impact of the activity on ecosystem health.”

Id. at 1130.

Here, the BLM conducted averages across the entire 13,225-acre Siuslaw Plan area. AR

3839 (“The spacial scale for this analysis is the 13,225-acre project area.”). This is thirteen times

the size of the project area averaged in Brong. 492 F.3d at 1129 (1,004-acre project area). In fact,

the BLM acknowledged that this averaging system was based on guesswork. In an email

exchange, one of the BLM’s foresters reported findings based on “just [a] real quick guess on

what would be logged in certain ways.” AR 923. The BLM’s specialists also expressed

confusion regarding which logging methods were proposed when making such averaging

calculations. Compare AR 922-23 (noting that one employee from the BLM stated, “I had 4

years with an approx 90 10 split and one year[] with a 75 cable 25 ground and one that was 55

45” and the other employee stated, “I ran my numbers assuming 17% ground based, and things

were right on the threshold”) with AR 3841 (“Based on these considerations, this analysis

assumed an HLB logging system design that would treat 17% of the treated acres with ground-

based or specialized harvest methods, and 83% with cable or aerial harvest methods.”). This

averaging system distorted the data contained in the EA, rendering the resulting FONSI irrational

and inadequate under NEPA. See Env’t Def. Ctr. v. Bureau of Ocean Energy Mgmt., 36 F.4th

850, 882 (9th Cir. 2022) (“[The defendants] relied on flawed assumptions in the EA that

distorted and rendered irrational their finding of no significant impact. . . . This failure to take the

requisite ‘hard look’ renders the EA inadequate under NEPA.”).

Defendants argue that the Ninth Circuit does not endorse the level of site-specificity

Plaintiffs urge is required. To support this argument, the BLM cites N. Alaska Env’t Ctr. v.

Kempthorne, 457 F.3d 969 (9th Cir. 2006). There, the Ninth Circuit held that failing to conduct a

parcel-by-parcel analysis of the environmental consequences of a projected action is not a per se

violation of NEPA. Id. at 977. While this is true, the Ninth Circuit adopted this rule in part

because the project entailed a multistage process involving inherent uncertainty, and because the

plaintiffs would have additional opportunities to comment on future stages requiring an EIS. Id.

(“Any later plan for actual exploration by lessees will be subject to a period of review before

being accepted, rejected or modified by the Secretary. Plaintiffs will have an opportunity to

comment on any later EIS.” (internal citation omitted)). The Ninth Circuit has also allowed

broader landscape-level plans in exploration projects where specific locations cannot reasonably

be ascertained. Te-Moak Tribe of W. Shoshone v. U.S. Dep’t of Interior of Nev., 608 F.3d 592,

600 (9th Cir. 2010) (holding that the “BLM, in some cases, may adapt its assessment of

environmental impacts when the specific locations of an exploration project’s activities cannot

reasonably be ascertained until some time after the project is approved”). An example of such

project is a mining operation where the exact location of minerals to be extracted is necessarily

uncertain without implementation of the plan. Id.

Here, the landscape-level analysis was not sufficient to satisfy NEPA. This is not a case

where the BLM will conduct another EIS or EA prior to implementing plan—as was the case in

N. Alaska Env’t Ctr., discussed above. As this Court has already found, “logging will certainly

occur when the BLM implements the Landscape Plan.” ECF No. 19 at 8. The BLM stated in its

EA that it could not select the “no action” alternative, so logging is sure to occur with

implementation of the plan. AR 131-32. Once an agency determines no significant

environmental impact and issues a FONSI, the NEPA review process concludes. Env’t Def. Ctr.,

36 F.4th at 869. Further, this is not a circumstance where further implementation of the plan is

necessary due to an inherent uncertainty, as was the case in Te-Moak Tribe of West Shoshone of

Nevada. Unlike the project at issue there, this project is not an exploratory plan akin to that of

mineral extraction. Rather, this is a logging plan where the location of the areas to be logged is

well-suited to standard site-specific analysis. The BLM mapped out specific areas designated as

potential harvest units under the plan. AR 3328. The BLM acknowledged that field surveys will

occur only after the NEPA process concludes. AR 3839. Because Plaintiffs will not have an

opportunity to comment on any further agency action, and this is not a situation of inherent

uncertainty, the landscape-level analysis was insufficient to satisfy NEPA.

2. Mitigation Measures

Defendants also argue that any deficiencies with the BLM’s averaging approach are

cured by future pre-treatment and harvest soil surveys at the timber-sale level. While mitigation

measures are necessary for NEPA analysis, they “are not alone sufficient to meet the [agency’s]

NEPA obligations to determine the projected extent of the environmental harm to enumerated

resources before a project is approved.” N. Plains Res. Council, Inc. v. Surface Transp. Bd., 668

F.3d 1067, 1084 (9th Cir. 2011) (emphasis in original); accord Great Basin Res. Watch v.

Bureau of Land Mgmt., 844 F.3d 1095, 1104 (9th Cir. 2016) (“[A] post-[FONSI] analysis—

conducted without any input from the public—cannot cure deficiencies in [a FONSI].”).

Likewise, the BLM cannot rely on future site-specific field surveys because such surveys would

occur only once the BLM has made a determination of NEPA adequacy (“DNA”)—which is not

a NEPA document. AR 3839; see also N. Alaska Env’t Ctr. v. U.S. Dep’t of Interior, 965 F.3d

705, 710 n.3 (9th Cir. 2020) (“A DNA is not itself a NEPA document; it is not subject to public

comment or consultation with other federal agencies.”).

Because the BLM will not have to conduct any further NEPA analysis for the Siuslaw

Plan, its large-scale averaging approach failed to take a “hard look” at how the Siuslaw Plan

would comply with the RMP’s management direction regarding soil impacts. Failing to do so

and relying on future surveys and mitigation violated NEPA.

B. Noxious Weeds and Invasive Species

Plaintiffs also argue that Defendants failed to take a “hard look” at noxious weeds and

invasive species. Defendants argue that (1) Plaintiffs failed to adequately raise this issue during

the comment period and therefore waived this argument, and (2) the Siuslaw Plan did take the

necessary “hard look” at noxious weeds.

1. Waiver

As an initial matter, Defendants contend that Plaintiffs did not properly raise their claims

regarding noxious weeds and invasive species because Plaintiffs allegedly failed to address these

issues with the necessary specificity during the public comment period. Plaintiffs challenging an

agency action must participate in the public comment period in such a way that their statements

alert the agency to the issues raised and “allow the agency to give the issue[s] meaningful

consideration.” Barnes v. U.S. Dep’t of Transp., 655 F.3d 1124, 1132 (9th Cir. 2011); accord

Havasupai Tribe v. Robertson, 943 F.2d 32, 34 (9th Cir. 1991) (holding that the plaintiff’s claims

could not form the basis for agency reversal where it raised those claims after the public

comment period had ended). A plaintiff need not invoke “magic words” during the comment

period “to leave the courtroom door open to a challenge.” Barnes, 655 F.3d at 1133 (quoting

Idaho Sporting Cong., 305 F.3d at 966).

Here, Plaintiffs provided Defendants with the required notice to pursue claims related to

noxious weeds. In 2019, Plaintiffs provided comments to the BLM regarding the Siuslaw Plan.

AR 6206-43. Plaintiffs stated the following: “Logging and roads will expose spread weeds by

exposing mineral soil, transporting seeds, and removing native vegetation thus giving more light

and nutrients to weeds. Inventories show that weeds are closely associated with roads and

recently logged areas. Consider alternatives that avoid creating the conditions to spread weeds.”

AR 6229. In 2021, Plaintiffs restated these concerns by calling for a site-specific impacts

analysis in an EIS to address various issues, including noxious weeds. AR 484-85. These

comments establish that Plaintiffs sufficiently raised the issue of noxious weeds in their

comments to allow Defendants to respond. See Barnes, 655 F.3d at 1132. Defendants also

addressed this issue in their DR, demonstrating that they were sufficiently apprised of the claims

raised by Plaintiffs. AR 24. Plaintiffs have therefore not waived this argument.

2. “Hard Look” Review

Plaintiffs argue that Defendants failed to take the requisite “hard look” at the potential

impacts of noxious weeds and invasive species. Defendants contend that they did take a “hard

look” at noxious weeds by tiering the Siuslaw Plan EA to the 2016 RMP FEIS and by curing any

potentially significant impacts through mitigation measures.

a) Tiering

“Ordinarily, an agency can avoid some of the burdens of the NEPA process by ‘tiering’

to a prior document that has itself been the subject of NEPA review.” All. for the Wild Rockies,

907 F.3d at 1118. However, the Ninth Circuit has stated that tiering is insufficient when both the

programmatic EIS and the project EA contain merely general statements about an issue rather

than site-specific information. Klamath-Siskiyou Wildlands Ctr. v. Bureau of Land Mgmt., 387

F.3d 989, 997 (9th Cir. 2004). Here, tiering was insufficient because neither the 2016 RMP FEIS

nor the Siuslaw Plan EA contained adequately site-specific information or analysis.

Both the 2016 RMP FEIS and the Siuslaw Plan EA acknowledge that noxious weeds are

a problem in Oregon generally. The 2016 RMP FEIS stated that the impact of noxious weeds “in

any specific watershed would depend on a variety of project-specific, watershed-specific, and

species-specific factors that cannot be analyzed at this scale of analysis.” AR 9818. In the

Siuslaw Plan EA, the BLM recognized that the Siuslaw Plan area is at high risk for increased

spread of weeds based on the 2016 RMP FEIS. AR 202 (“The project area falls in watersheds

considered at high to highest risk due to timber harvest, and road construction.”). The EA also

discussed how timber sales in the Siuslaw Plan area will increase weed infestation. AR 201

(“Several studies have documented increased weed infestation after timber sales, and timber

sales in and near the project area have shown this effect as well.” (internal citation omitted)).

Despite these acknowledgments, the BLM declined to analyze this issue in detail in the EA. AR

202 (“For these reasons, the BLM considered this issue but did not analyze it in detail. Because

analysis of this issue isn’t necessary to evaluate how the alternatives respond to the Purpose and

Need and there is no potential for significant effects beyond those described in the Proposed

RMP / Final EIS.”).

Moreover, the BLM’s botanist recognized during the Siuslaw Plan EA’s drafting phase

that invasive species would inform which alternative to select. In an initial draft, the EA stated:

“The BLM considered this issue but did not analyze it in detail because it does not inform the

decision.” AR 3514. The BLM’s botanist rewrote this provision to say, “The BLM considered

this issue but did not analyze it in detail because the BLM is not proposing to use the differences

in invasive species effects to inform the decision.” Id. In a comment, the botanist explained, “[a]s

mentioned above, this wording is a little misleading. We could, for example, choose the all

thinning alternative to lessen effects.” Id. The BLM did not fully disclose how each of the

alternatives would affect noxious weeds despite recognizing that the project may create a

significant impact on noxious weeds in the project area. Because the BLM made merely

conclusory statements and failed to gather site-specific data in either the 2016 RMP FEIS or the

Siuslaw Plan EA, Defendants failed to take the requisite “hard look” at noxious weeds.

b) Mitigation Measures

Defendants also argue that the inclusion of mitigation measures satisfied the “hard look”

requirement with respect to this issue. The Court disagrees for two reasons

First, while the BLM did consider mitigation techniques in the 2016 RMP FEIS, it did

“not detail their extent or expected level of success.” AR 202. The Siuslaw Plan EA did propose

possible mitigation techniques prescribed by the BLM. AR 202. However, after detailing these

possible techniques, the EA stated the following:

An indirect effect of the project is that it adds to the overall inability to successfully

control weeds on the Siuslaw Field Office. Weeds are generally widespread over

Siuslaw Field Office lands, as evidenced through weed mapping efforts. More

acreage of infestations has been documented than can be controlled with current

resources and methods. Recent financial resources have allowed weed control of

high priority species and Scotch broom in the Siuslaw Field Office. High priority

species such as false brome, shining geranium, and meadow knapweed are species

that are not yet abundant, but have a potential for severe impacts. Control measures

have been concentrating on these high priority species and Scotch broom along

roadsides. Roadside infestations are prioritized as they have a high likelihood of

being spread along the road. A lack of financial and personnel resources has often

led to off-road infestations not being controlled. Blackberry has generally not been

controlled as it sprouts from underground after cutting, and herbicides have not

been available, although they have become available in 2020 with the Integrated

Invasive Plant Management for the Northwest Oregon District Environmental

Analysis. It is likely that much of the weed infestations expected to result from the

action alternatives will not be adequately controlled given current resources.

Id. The BLM must provide analytical data supporting mitigation measures; otherwise, such

measures constitute “a mere listing” and fail to satisfy NEPA. Idaho Sporting Cong. v. Thomas,

137 F.3d 1146, 1151 (9th Cir. 1998), overruled on other grounds by Lands Council, 537 F.3d

981 (9th Cir. 2008).

Second—as this Court has already explained with respect to soil disturbance—

“mitigation measures, while necessary, are not alone sufficient to meet [an agency’s] NEPA

obligations to determine the projected extent of the environmental harm to enumerated

resources before a project is approved.” N. Plains Res. Council, 668 F.3d at 1084. The BLM

could not use mitigation alone to cure its failure to adequately consider noxious weeds and

therefore failed to take a “hard look” at the impacts of noxious weeds and invasive species.

C. Special Status Species

Plaintiffs argue that the BLM failed to take a “hard look” at special status species because

it failed to conduct site-specific analyses of the Siuslaw Plan’s impacts on those species.

Defendants respond that the BLM properly tiered its analysis of this issue to the 2016 RMP FEIS

and provided further analysis in the Siuslaw Plan EA, both of which satisfy its NEPA

requirements. Although a larger programmatic EIS need not conduct site-specific analysis, an

EA that tiers to such programmatic EIS must conduct site-specific analysis where “a critical

decision has been made to act on site development.” ‘Ilio’ulaokalani Coal. v. Rumsfeld, 464 F.3d

1083, 1094 (9th Cir. 2006). Here, the Court has already explained that such a critical decision

has been made, and site-specific analysis of impacts on special status species was required in

either the 2016 RMP FEIS or the Siuslaw Plan EA.

The 2016 RMP FEIS did not analyze site-specific impacts on special status species

because its scope was the entire 2.6-million-acre project. Regarding former Survey and Manage

species, the 2016 RMP FEIS stated that the BLM “lack[ed] complete and species-specific survey

information for most Survey and Manage species. It would be exorbitantly expensive and time-

consuming to conduct random surveys across the decision area for all Survey and Manage

species.” AR 9098. Instead, the 2016 RMP FEIS discussed general consequences that the larger

plan would have on these species. See AR 9097-103.

Neither did the Siuslaw Plan EA contain any site-specific analysis of impacts on special

status species. The BLM acknowledged that the following species were either possibly or likely

present in the Siuslaw Field Office: bald eagle, fringed myotis, golden eagle, Oregon red tree

vole, pallid bat, Townsend’s big-eared bat, water flea, bufflehead, coastal greenish blue butterfly,

Haddock’s Rhyacophilan caddisfly, Johnson’s hairstreak butterfly, monarch butterfly, Oregon

coast coho salmon, Oregon coast spring chinook salmon, pacific lamprey, and Oregon coast

steelhead trout. AR 272-77, 296-97. In the Siuslaw Plan EA, if the species were deemed “likely”

to be in the project area, the BLM concluded that the project was unlikely to cause a trend

toward listing; determined that it could employ mitigation measures to prevent any possible trend

toward listing; or both. AR 269-91.

The BLM’s repeated statements in the Siuslaw Plan EA that the Siuslaw Plan would not

cause a trend towards listing are conclusory, speculative, and devoid of any site-specific analysis.

Site-specific analysis is a critical inquiry that the Ninth Circuit has determined NEPA requires.

Anderson v. Evans, 314 F.3d 1006, 1019-20 (9th Cir. 2002) (“Even if the eastern Pacific gray

whales overall or the smaller PCFA group of whales are not significantly impacted by the Makah

Tribe’s whaling, the summer whale population in the local Washington area may be significantly

affected. Such local effects are a basis for a finding that there will be a significant impact from

the Tribe’s hunts.”). The BLM’s conclusory statements about the likelihood of a trend towards

listing are insufficient to satisfy NEPA. See Earth Island Inst. v. U.S. Forest Serv., 442 F.3d

1147, 1172 (9th Cir. 2006), abrogated on other grounds by Winter v. Nat. Res. Def. Council,

Inc., 555 U.S. 7 (2008) (finding a statement “without meaningful explanation” that a project

“would not result in a trend toward federal listing” is insufficient to satisfy NEPA’s “hard look”

requirement).

Neither do the BLM’s statements that it would employ mitigation to prevent trends

towards listing satisfy its NEPA obligations. As explained above in the context of soil

disturbance and noxious weeds, “mitigation measures, while necessary, are not alone sufficient

to meet [an agency’s] NEPA obligations to determine the projected extent of the environmental

harm to enumerated resources before a project is approved.” N. Plains Res. Council, 668 F.3d at

1084. The BLM’s failure in either the 2016 RMP FEIS or the Siuslaw Plan EA to evaluate site-

specific impacts on special status species therefore violated NEPA.

D. Cumulative Impacts

Plaintiffs next argue that Defendants failed to analyze and disclose cumulatively

significant impacts. A “hard look” under NEPA requires consideration of cumulative impacts.

Idaho Sporting Cong., 305 F.3d at 963; 40 C.F.R. § 1508.25(c) (agency “shall consider” direct,

indirect, and cumulative impacts). Such analysis “must be more than perfunctory; it must provide

a useful analysis of the cumulative impacts of past, present, and future projects.” Klamath-

Siskiyou Wildlands Ctr., 387 F.3d at 994 (quoting Ocean Advocs. v. U.S. Army Corps of Eng’rs,

361 F.3d 1108, 1128 (9th Cir. 2004)).

Plaintiffs argue that the BLM failed to consider the cumulative impacts of the Siuslaw

Plan in combination with the “N126 Project,” which “overlap[] in time and space.” Pls.’ Mot.

31-32. They note that both projects identify similar effects, compare AR 1992-93 with AR 128-

30, and in some of the same geographic locations, compare AR 3328 with AR 2128, but the

Siuslaw Plan EA did not consider the cumulative impacts of these issues. To illustrate the

problem with the BLM’s analysis, Plaintiffs contend that while both projects will create early

successional ecosystems that have impacts on certain wildlife species, the Siuslaw Plan EA fails

to consider the cumulative impacts of such creation. Defendants contend Plaintiffs have

erroneously conflated two distinct issues—“early successional ecosystems” for the Siuslaw Plan

with “early-successional habitat” for the N126 Project—each of which have different meanings

and impacts.

The Court agrees that Defendants failed to consider the cumulative effects of the N126

Project and the Siuslaw Plan. As Plaintiffs point out, the N126 EA identifies several of the same

impacts as the Siuslaw Plan EA. Compare AR 1992-93 with AR 128-30. Yet the Siuslaw Plan

EA omits consideration of the cumulative effects of these impacts. While it discusses the

cumulative impacts of road construction on sediment delivery to streams for both projects, AR

215-16, it is otherwise completely silent on the cumulative impacts of these projects.

Defendants’ arguments about the technical distinction between “early successional ecosystems”

and “early-successional habitat” fail to explain the general lack of discussion of cumulative

impacts of the Siuslaw Plan and the N126 Project. Rather, the Court understands Plaintiffs’

discussion of the early successional issue to be illustrative of the BLM’s failure throughout the

EA to address cumulative impacts, not the sum total of Plaintiffs’ argument.

The cases cited by Plaintiffs establish that an adequate cumulative impacts analysis must

consider the impacts of nearby timber sales. See, e.g., Kern v. U.S. Bureau of Land Mgmt., 284

F.3d 1062, 1077-78 (9th Cir. 2002) (holding that the BLM’s NEPA analysis insufficient because

it made “no attempt to analyze the cumulative impacts of the Sandy-Remote timber sales when

combined with ‘reasonably foreseeable future actions’ (such as other timber sales) outside the

Sandy-Remote Area”); Blue Mountains Biodiversity Project v. Blackwood, 161 F.3d 1208, 1215

(9th Cir. 1998) (holding that the BLM’s NEPA analysis insufficient where it failed to consider

cumulative impacts of reasonably foreseeable timber sales within the same watershed);

Neighbors of Cuddy Mountain v. U.S. Forest Serv., 137 F.3d 1372, 1380 (9th Cir. 1998)

(“Because the three proposed sales in this case were ‘reasonably foreseeable,’ the Forest Service

was obligated to assess the cumulative impact of all sales on the availability of old growth

habitat for the pileated woodpecker.”). In omitting almost all consideration or discussion of the

cumulative impacts of the Siuslaw Plan and the N126 Project despite the overlap in time, space,

and types of anticipated effects, the BLM violated NEPA’s requirement to consider cumulative

impacts.

III. Failure to Prepare an Environmental Impact Statement

Plaintiffs next argue that Defendants failed to prepare an EIS as required by NEPA.

NEPA requires federal agencies to prepare and publicly disclose a “detailed statement”

describing the environmental impacts of, and alternatives to, any major federal action that may

“significantly affect[] the quality of the human environment.” 42 U.S.C. § 4332(C). Commonly

known as an environmental impact statement, or “EIS,” the statement must contain a “full and

fair discussion of significant environmental impacts” and describe “reasonable alternatives which

would avoid or minimize adverse impacts.” 40 C.F.R. §§ 1508.11, 1502.1; accord Te-Moak

Tribe of W. Shoshone of Nev., 608 F.3d at 602.

To determine whether an action will have significant environmental effects, an agency

may prepare an EA. 40 C.F.R. § 1501.5(a)-(c). Although less comprehensive than an EIS, an EA

must contain detailed analyses of project impacts and alternatives. Te-Moak Tribe of W.

Shoshone of Nev., 608 F.3d at 602-03 (citing 40 C.F.R. § 1508.9(b)). If the agency does not

prepare an EIS, it must provide a “convincing statement of reasons to explain why [the] project’s

impacts are insignificant” in a FONSI. 350 Mont. v. Haaland, 29 F.4th 1158, 1163 (9th Cir.

2022) (alteration in original) (quoting Bark v. U.S. Forest Serv., 958 F.3d 865, 869 (9th Cir.

2020)); accord Metcalf v. Daley, 214 F.3d 1135, 1143 (9th Cir. 2000) (“The purpose of an EA is

to provide the agency with sufficient evidence and analysis for determining whether to prepare

an EIS or to issue a FONSI.” (citing 40 C.F.R. § 1508.9)).

To prevail on a claim that the agency violated NEPA by failing to prepare an EIS, a

claimant need not show that significant effects will occur; it is enough to raise “substantial

questions” whether a project may have a significant effect on the environment. See Greenpeace

Action v. Franklin, 14 F.2d 1324, 1332 (9th Cir. 1992). As the Ninth Circuit has consistently

held, this is a low standard. See, e.g., Klamath Siskiyou Wildlands Ctr. v. Boody, 468 F.3d 549,

562 (9th Cir. 2006). Significance is evaluated using context and intensity factors. 40 C.F.R. §

1508.27. A single intensity factor may require preparation of an EIS. Ocean Advocs. v. U.S.

Army Corps of Eng’rs, 402 F.3d 846, 865 (9th Cir. 2005). Here, Plaintiffs argue that Defendants

violated NEPA because (1) the BLM’s reasons for not preparing an EIS are flawed; and (2)

substantial questions exist over whether the Siuslaw Plan may have significant impacts.

First, with respect to whether the BLM provided a convincing statement of reasons for

not preparing an EIS, the Court has already addressed the ways in which the BLM failed to take

the requisite “hard look” at various environmental impacts of the Siuslaw Plan. The resulting

FONSI and supporting statement of reasons are unconvincing for the same reasons. Second, the

Court agrees that substantial questions exist regarding whether the Siuslaw Plan may have

significant impacts. Regulations identify several intensity factors to consider in evaluating the

significance of impacts. See 40 C.F.R. § 1508.27(b) (listing intensity factors). Plaintiffs argue

that several intensity factors raise substantial questions here:

• 40 C.F.R. § 1508.27(b)(7) (“Whether the action is related to other actions with

individually insignificant but cumulatively significant impacts. Significance exists if it is

reasonable to anticipate a cumulatively significant impact on the environment.

Significance cannot be avoided by terming an action temporary or by breaking it down

into small component parts.”). Here, as addressed above, the cumulative impacts of the

Siuslaw Plan with those of the N126 Project may be significant but are unaddressed in

the EA and FONSI.

• 40 C.F.R. § 1508.27(b)(9) (“The degree to which the action may adversely affect an

endangered or threatened species or its habitat that has been determined to be critical

under the Endangered Species Act of 1973.”). Here, the record raises substantial

questions about the adverse effects on numerous threatened species and their critical

habitat, including marbled murrelets, the northern spotted owl, Oregon Coast Coho

Salmon, and Upper Willamette River Chinook Salmon. See AR 192-93.

• 40 C.F.R. § 1508.27(b)(5) (“The degree to which the possible effects on the human

environment are highly uncertain or involve unique or unknown risks.”). Here, as

addressed above, the lack of information about several site-specific impacts of the

Siuslaw Plan and the ability of those impacts to be mitigated render such effects highly

uncertain.

Individually, and certainly cumulatively, the Court finds that several intensity factors

raise substantial questions over whether the Siuslaw Plan may have significant impacts.

IV. Remedy/Relief

While contesting the Court’s findings on the merits,4 Defendants agree that vacatur of

the Siuslaw Plan Decision Record is the appropriate remedy based on those findings. Defs.’

Remedy Brief 3-4, ECF No. 48. However, Defendants contend that rather than instructing the

BLM to prepare an EIS, the Court should instead instruct the BLM to conduct further analysis

and explanation. Plaintiffs contend that Ninth Circuit case law requires the Court to order the

BLM to prepare an EIS for the Siuslaw Plan in light of the Court’s finding that substantial

questions exist regarding whether the Siuslaw Plan may have significant impacts.

“[P]reparation of an EIS is not mandated in all cases simply because an agency has

prepared a deficient EA or otherwise failed to comply with NEPA.” Ctr. for Biological Diversity

v. Nat’l Highway Traffic Safety Admin., 538 F.3d 1172, 1178 (9th Cir. 2008). If the court “cannot

determine whether the proposed rule or project may have a significant effect,” then the correct

approach is to remand for the preparation of an EA. Id. But “if the court determines that the

agency’s proffered reasons for its FONSI are arbitrary and capricious and the evidence in a

complete administrative record demonstrates that the project or regulation may have a significant

impact, then it is appropriate to remand with instructions to prepare an EIS.” Id. at 1179. Ninth

4 A substantively identical decision on the merits of the parties’ motions was originally issued as

a now-vacated Findings and Recommendation. See ECF No. 44. That Findings and

Recommendation deferred the decision on remedy, ordering that “[s]hould the district court

adopt this Findings and Recommendation, the parties are directed to contact the Court within 30

days of that order to arrange a status conference to discuss a briefing schedule for the appropriate

remedy.” Id. at 27-28. The parties ultimately did brief the issue of remedy in the course of filing

a motion to amend or correct the Findings and Recommendation, and in their objections to the

Findings and Recommendation. See ECF Nos. 48, 49, 51, 52, 57, 58. When it vacated the

Findings and Recommendation, the Court noted that it would consider the parties’ arguments and

authority on this issue as supplemental briefing in support of their motions for summary

judgment. See ECF No. 61. The Court has done so in reaching its conclusions here.

Circuit case law is clear that “[a]n EIS must be prepared if ‘substantial questions are raised’” as

to whether a project may have significant impacts. Blue Mountains Biodiversity Project, 161

F.3d at 1212 (quoting Idaho Sporting Cong. v. Thomas, 137 F.3d at 1149).

This is not a case where the Court was unable to determine whether there may be

significant effects. Rather, the Court has explicitly found in Section III of this opinion that

substantial questions exist over whether the Siuslaw Plan may have significant impacts. Under

the clear rule set forth in the case law cited above, an EIS must be prepared in light of that

finding.

CONCLUSION

For the reasons above, Defendants’ Motion for Summary Judgment (ECF No. 36) is

DENIED. Plaintiffs’ Motion for Summary Judgment (ECF No. 33) is GRANTED. The Siuslaw

Plan EA, DR, and FONSI are vacated and the matter is remanded to the BLM for the preparation

of an EIS. The parties are ordered to confer and jointly submit a proposed judgment consistent

with this Opinion and Order within 30 days.

DATED this 24th day of April 2025.

s/ Mustafa T. Kasubhai

MUSTAFA T. KASUBHAI (He / Him)

United States District Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.