Opinion

KOTIS ASSOCIATES, LLC v. United States

Court
United States Court of Federal Claims
Filed
Apr 22, 2025
Status
Published
On the bench
Loren A. Smith
Cited by
0 cases
Authority
More cited than 34.9%

Tucker Act remedy available when government agents’ actions “are pursuant to the good faith implementation of a Congressional Act” (internal citation and quotation marks omitted)

How later courts described this case

  • Tucker Act remedy available when government agents’ actions “are pursuant to the good faith implementation of a Congressional Act” (internal citation and quotation marks omitted)
  • finding that the holder of a dominant ROW “may expand its use of the right-of-way, to the extent of its statutory right, for any legitimate purpose as determined by [its] sound business judgment” (emphasis added)
  • second NITU treated as distinct government action when the government failed to publish the first NITU in the Federal Register and its issuance was “inherently unknowable”
  • “[The property owner] is entitled to the value that the [subject property] would command in the open market in light of the highest and most profitable use to which the acreage might reasonably be devoted in the near future.”

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

No. 20-932

Filed: April 22, 2025

)

KOTIS ASSOCIATES, LLC, et al., )

)

Plaintiffs, )

)

v. )

)

THE UNITED STATES, )

)

Defendant. )

)

Lindsay S.C. Brinton, Lewis Rice LLC, St. Louis, MO, for plaintiffs.

Krystal-Rose Perez, U.S. Department of Justice, Washington, DC, for defendant.

OPINION AND ORDER

SMITH, Senior Judge

This just compensation case arises from the “rails-to-trails” conversion of a 3.1-

mile railroad corridor between Milepost CF-65.6 and Milepost CF-68.7 (“the Corridor”)

in Greensboro, North Carolina. The former railroad right of way (“ROW”) was

converted, with the approval of the Surface Transportation Board (“STB”) and by virtue

of it, into a new easement for trail use subject to preservation for future rail use, known

as an interim trail use and railbanking easement (“ITUR easement”). The former

railroad ROW was owned by Norfolk Southern Railway Company (“Norfolk

Southern”). The new ITUR easement is owned and operated by the City of Greensboro

(“the City”), the trail sponsor.

Plaintiffs are three entities controlled by Mr. William Kotis: Kotis Associates,

LLC; Kotis Holdings, LLC; and Westover Terrace II, LLC (collectively, “Kotis

Entities”). The Kotis Entities together own thirteen parcels underlying and immediately

adjacent to the Corridor. Defendant, the United States, has conceded liability, so that

the only question before the Court is the amount of just compensation owed. The Kotis

Entities presented expert valuation testimony and seek upwards of $44,744,774.00 plus

interest. The United States presented expert rebuttal testimony questioning the

reliability of plaintiffs’ expert, but also maintains that plaintiffs are entitled to no

compensation because (1) their property would have been burdened by an easement

even without the taking; and (2) the ITUR easement is narrow in width and

nonexclusive in scope. Also pending before the Court is plaintiffs’ motion for partial

-1-

summary judgment as to the rate of interest, ECF No. 173, and defendant’s motion to

reopen the trial record, ECF No. 188.

For the reasons provided below, the Court grants plaintiffs’ motion for partial

summary judgment; denies defendant’s motion to reopen the record; and concludes that

the quantum of compensation owed to plaintiffs is far from nominal. The Court awards

just compensation in the amount estimated by plaintiffs’ expert, subject to some

modifications. Interest to be calculated using Moody’s Aaa Corporate Bond Rate,

compounded annually.

I. Background

A rails-to-trails conversion is simply a series of real estate transactions involving

three players: the potential trail sponsor, the railroad company, and local landowners.

The sponsor’s objective is to acquire, within the rail corridor or a portion of it, the right

to establish a trail not subject to interference by another dominant estate. When a party

(whether a railroad or a local landowner) owns the portion in fee and there is no

dominant estate, acquisition is bilateral. But matters are less straightforward when the

estate is split between the railroad and the landowners. This Court’s “rails-to-trails”

jurisprudence involves the scenario where the estate is split thus: The railroad holds a

dominant easement in the corridor for “railroad purposes”—but not for trail purposes;

while the “fee estate[] remain[s] with [adjacent] property owners.” Preseault v. United

States, 100 F.3d 1525, 1530 (Fed. Cir. 1996) (en banc) (plurality opinion) (“Preseault

III”). In this scenario, the sponsor has no straightforward way to acquire an

unencumbered trail easement. The railroad cannot convey the right to use the corridor

for trail purposes because it does not possess that right, and landowners cannot convey

it because their rights are servient to the railroad’s dominant estate.

Sponsors can get around this problem in two ways. First, they can simply wait

for the railroad to abandon the corridor and then make a deal with landowners. Call

this a “post-abandonment” rail-trail conversion. Second, if the railroad refuses to

abandon the corridor, the sponsor’s only hope is to acquire a congressionally-created

ITUR easement under the “Railbanking Provision” of the National Trails System Act

Amendments of 1983 (“Trails Act”). 1 Call this a “pre-abandonment” or “Trails Act”

rail-trail conversion.

The sponsor in this case, the City, acquired two adjacent corridors, one post-

abandonment, and the other—the Corridor that is the subject of this litigation—via the

Trails Act. Although only the second acquisition implicates a federal taking, a

comparison of the two sheds light on how a Trails Act taking alters the rights of

landowners. The Court therefore recounts the legal and factual background for both

acquisitions.

A. Legal Background

1

Pub. L. No. 98-11 § 208(2), 97 Stat. 42, 48 (codified at 16 U.S.C. § 1247(d)).

-2-

1. Post-abandonment rail-trail conversions

A post-abandonment conversion is triggered when a rail corridor no longer finds

it profitable to continue its ownership of a railroad ROW. It may seem counterintuitive

that railroads would want to voluntarily extinguish their property interest, but railroads

have strong incentives to abandon inactive rail lines, as opposed to merely deactivating

or “discontinuing” services. “If the railway company retains the line but discontinues

service . . . , the company accepts significant costs, including taxes and maintenance

expenses, and risks of tort liability. Because abandonment avoids these costs, railway

companies seeking [STB] authorization to cease operations on money-losing lines

naturally prefer abandonment to discontinuance.” Preseault v. United States

(“Preseault II”), 66 F.3d 1167, 1182–83 (Fed. Cir. 1995), vacated, 66 F.3d 1190, rev’d

100 F.3d 1525 (Fed. Cir. 1996) (en banc); see also Glosemeyer v. United States, 45 Fed.

Cl. 771, 775 (2000).

The railroad obtains the STB’s authorization to abandon by initiating one of

several types of abandonment proceedings. The default proceeding is lengthy. 49

U.S.C. § 10903; see Chicago & N.W. Transp. Co. v. Kalo Brick & Tile Co., 450 U.S.

311, 321 (1981). However, the STB has also created so-called “exempt” proceedings,

through which railroads may receive the “authority to abandon” without “prior review

and approval,” for lines that have seen “no local traffic . . . for at least 2 years” and also

meet certain other conditions. 2 49 C.F.R. § 1152.50(b), (c). Railroads initiate this

proceeding by filing a “notice of exemption,” and, in the ordinary course, automatically

receive the authority to abandon the line after fifty days. Id. § 1152.50(d)(3). Once the

railroad exercises its authority to abandon 3—that is, once it “consummates” the

abandonment—the railroad is out of the equation, and the sponsor can acquire an

unencumbered trail easement from the adjacent landowners.

2. Pre-abandonment or Trails Act conversions

Post-abandonment rail-trail conversions may benefit sponsors and landowners, 4

but they also permanently remove the corridor in question from the Nation’s railway

2

The other conditions are: “[A]ny overhead traffic on the line can be rerouted”; and the line is

not subject to an ongoing or recent dispute brought by a shipper. 49 C.F.R. § 1152.50(b).

3

The railroad’s authority to abandon ordinarily expires in one year, and if the railroad does not

consummate the abandonment within that period, “a new proceeding [has] to be instituted if the

railroad wants to abandon the line.” 49 C.F.R. § 1152.29(e)(2).

4

Sponsors may prefer post-abandonment conversions whenever they and landowners share a

mutual interest in tailoring the dimensions of the trail. For example, the parties may agree to narrow or

reroute segments of the trail to enable landowners to make productive use of the land—which would

benefit not just landowners but also the sponsor, if the sponsor’s aim is to promote economic

development along the trail and (when the sponsor is a local government) enhance its tax base. See

Danaya C. Wright & Jeffrey M. Hester, Pipes, Wires, and Bicycles: Rails-to-Trails, Utility Licenses,

and the Shifting Scope of Railroad Easements from the Nineteenth to the Twenty-First Centuries, 27

Ecology L.Q. 351, 357 (2000) (noting that rail-trails “link neighborhoods, schools, and shopping

areas,” and that “the greatest success story of the Rails-to-Trails movement has been the revitalization

-3-

network. The Trails Act addresses this problem by rearranging property rights as

between the railroad and adjacent landowners. The operative provision of the Act, the

Railbanking Provision, provides that an ROW for railroad purposes is not deemed

abandoned if it is converted to a trail, as long as (1) the trail use is “interim,” meaning

that it is “subject to restoration or reconstruction for railroad purposes” (colloquially,

“railbanked”); and (2) the sponsor “is prepared to assume full responsibility for

management of such rights-of-way and for any legal liability arising out of such

transfer or use, and for the payment of any and all taxes that may be levied or assessed

against such rights-of-way.” 16 U.S.C. § 1247(d).

In other words, the Railbanking Provision creates the option of converting the

railroad’s estate to include a “new and different” easement—the ITUR easement.

Toews v. United States, 376 F.3d 1371, 1381 (Fed. Cir. 2004); Preseault III, 100 F.3d at

1550 (“a new easement for [a] new use”). Furthermore, the STB’s implementing

regulations assign the contingent property right—the option of converting a railroad

ROW into an ITUR easement—to the railroad, because the new ITUR easement can be

established only with the railroad’s consent. 49 C.F.R. § 1152.29(b)(2); see also Nat’l

Wildlife Fed’n v. ICC, 850 F.2d 694, 696 (D.C. Cir. 1988) (rejecting, based on Chevron

deference, the argument that the Railbanking Provision “requires the [STB] to transfer

rights-of-way to qualified trail operators even when the railroad opposes such use”).

By assigning the option right to the railroad, the STB grants the railroad an exclusive

trail-use ‘license,’ which they can sell to sponsors in exchange for the transfer of all

costs associated with liability, tax obligations, and corridor maintenance, 16 U.S.C. §

1247(d), plus lumpsum payments—all without losing the right to reactivate rail service

in the future.

In this way, the railroad ROW is transformed from a liability that the railroad

wished to get off its books, into a lucrative asset that the railroad will retain as long as

it expects a current or future sponsor to buy the license.

More specifically, the railroad sells the ITUR license through a proceeding—call

it the trail-use proceeding—created by the STB to implement the Railbanking

Provision. The proceeding is folded into the exemption proceeding described earlier in

this opinion. See Part I.A.1, supra. After the railroad files the notice of exemption and

it is published in the Federal Register, potential trail sponsors have twenty days to file a

“petition for interim trail use.” 49 C.F.R. § 1152.29(b)(1), (2). The petition must

contain, among other things, “[a] map depicting, and an accurate description of, the

right-of-way, or portion thereof . . . , proposed to be acquired or used.” Id. §

1152.29(a)(1). The railroad then informs the STB whether it agrees to negotiate an

ITUR agreement. Id. § 1152.29(b)(2). If the railroad agrees, the STB issues a Notice

of Interim Trail Use (“NITU”), which has the effect of staying the notice of exemption

while the sponsor and the railroad negotiate. See id. §1152.29(d)(2). If negotiations

of innumerable small towns”). Sponsors may also be able to save money by acquiring the corridor

through donations, bargain sales, or land swaps. See Rails to Trails Conservancy, Acquisition Strategy,

https://www.railstotrails.org/trail-building-toolbox/acquisition-strategy/ (last visited on April 22,

2025).

-4-

are successful, the trail sponsor and railroad do not need further approval from the STB;

they can make the NITU permanent simply by “jointly notify[ing] the [STB] within 10

days that the agreement has been reached.” Id. § 1152.29(h). 5 If negotiations fail, the

NITU “automatically converts into an effective . . . notice of abandonment.” Preseault

v. United States, 494 U.S. 1, 7 n.5 (1989) (“Preseault I”); 49 C.F.R. § 1152.29(d)(1).

Even when negotiations fail, however, the Trails Act remains in the picture,

because the railroad can choose not to consummate the abandonment. 29 C.F.R. §

1152.29(e)(2). In that scenario, the railroad retains the authority to file a new notice of

exemption and work with the same sponsor or other sponsors to obtain a follow-on

NITU. See, e.g., Barclay v. United States, 443 F.3d 1368, 1375–78 (Fed. Cir. 2006).

The trail use proceeding resembles a direct condemnation action in some

respects. In the eminent domain context, a third party authorized to exercise a

government’s condemnation power initiates the action by making a condemnation filing

in court. See, e.g., 15 U.S.C. §717f(h). If the taking is valid, the court enters three

judgments through the life of the lawsuit: an initial judgment of possession, a final

judgment transferring title, and a just compensation award. E.g., id. Analogously, a

Trails Act proceeding is initiated by two parties working together to exercise the federal

government’s condemnation power: the railroad and the sponsor. After the railroad

files a notice of exemption, the sponsor makes the condemnation filing—the petition for

interim trail use. 49 C.F.R. § 1152.29(a)(1). While negotiations are ongoing, the NITU

serves as the “initial judgment of immediate possession.” Caldwell v. United States,

391 F.3d 1226, 1234 (Fed. Cir. 2004) (internal quotation marks omitted). If

negotiations succeed, the same NITU acts as the STB’s final judgment extending the

stay of exemption “indefinitely for the duration of recreational trail use subject to the

trail operator’s fulfillment of its agreed-upon obligations.” Id. at 1230. But even if

negotiations fail, the analogy may still hold if multiple NITUs are issued and an ITUR

agreement is ultimately reached. The only difference in such cases is that the STB’s

“judgment” consists of all the NITUs put together, rather than just one. Barclay, 443

F.3d at 1375 (multiple NITUs constitute a “single and continuous government action.”).

Trail use proceedings do differ from third-party condemnation actions at the just

compensation stage, in three ways. In eminent domain actions by third parties, the

same court approves the condemnation and awards just compensation; property owners

are party to the proceedings; and the third party that condemned the property also foots

the bill. See, e.g., Sabal Trail Transmission, LLC v. 18.27 Acres of Land in Levy Cnty.,

59 F.4th 1158, 1161 (11th Cir. 2023). In Trails Act proceedings, the condemnation

“court” is the STB while just compensation is awarded by this Court under the Tucker

Act; the STB can and usually does proceed without property owners present; 6 and

5

The joint notice must once again contain “a map depicting, and an accurate description of, the

involved right-of-way or portion thereof.” 49 C.F.R. §1152.29(h).

6

The STB has “repeatedly considered . . . and declined to adopt” regulations requiring railroads

or trail sponsors to directly notify adjacent landowners of the proceeding even after a NITU has been

issued or an ITUR agreement reached. 84 Fed. Reg. 66,320, 66,324 (Dec. 4, 2019) (STB final rule

amending Trails Act regulations). Compare this with regulations for other stakeholders, including

-5-

compensation is paid by the federal government, not the third parties who initiated the

proceeding (the sponsor and the railroad).

3. Proceedings to alter the terms of a Trails Act conversion

The STB’s procedures for altering the terms of an already-issued NITU are also

relevant to this case. The agency recognizes two routes for modifying a NITU:

“vacatur” and “clarification.” The railroad and the sponsor may request vacatur (also

known as modification, correction, or amendment) of the NITU in whole or in part. 49

C.F.R. § 1152.29(d)(2). When a NITU is vacated, ownership reverts to the railroad,

allowing the railroad to “fully abandon the line segments” pursuant to the notice of

exemption that had been stayed by operation of the NITU. Kan. & Okla. R.R., Inc.—

Aban. Exemption, STB No. AB-853 (Sub-No. 1X), 2007 WL 3353205 at *1 (Nov. 9,

2007). Thus, vacatur returns the affected portion of the corridor to the status quo ex

ante, and the federal government is liable, at best, for a temporary taking. See Hardy v.

United States, 965 F.3d 1338, 1349–50 (Fed. Cir. 2020).

The sponsor may also file a petition for “clarification” of the NITU. The STB

appears to use “clarification” as a legal term of art for (1) relieving the trail sponsor of

its railbanking obligation upon a showing that the portion is not “necessary” for future

rail reactivation, and yet (2) permitting the sponsor to control and even sell that portion

for non-trail, non-rail uses. See Mo. Pac. R.R.—Aban. Exemption, STB No. AB-3 (Sub-

No. 137X), 2021 WL 3235207 at *3–*4 (July 27, 2021); id. at *3 (collecting STB

decisions). Thus, if the STB approves such a petition, the sponsor effectively owns an

easement that is unqualified (that is, without the railbanking obligation and perhaps also

without the trail-use limitation) over the relevant portion of the easement. This is

similar to the state of affairs in the post-abandonment condition, except that the default

owner of the unqualified easement is the sponsor, rather than the landowner.

As a practical matter, property owners may prefer a clarification over a vacatur,

because they find it easier to negotiate with the sponsor than the railroad. Either way,

however, they must rely on the sponsor or railroad to initiate the proceeding.

B. Statement of Facts 7

1. Factual background

The A&Y Greenway. Just north of the rail-trail at issue in this litigation lies the

7.4-mile Atlantic & Yadkin Greenway (“A&Y Greenway”). The City acquired the

A&Y Greenway post-abandonment, by negotiating with property owners. These

private parties such as shippers and labor unions, on whom the railroad is required to serve its notice of

exemption at the outset of the proceeding. 49 C.F.R. § 1152.20(a)(2)(i), (xii).

7

This section constitutes the Court’s principal findings of fact under Rule 52(a) of the Rules of

the United States Court of Federal Claims (“RCFC”). Other findings of fact and rulings on mixed

questions of fact and law are set forth in the Discussion section of this opinion.

-6-

negotiations were successful in part because, as one Greensboro councilmember put it,

“[t]he greenways were established to promote business.” PX77j. The City received

some segments “at almost no cost thanks to negotiations with businesses and residences

along the corridor.” U.S. Fed. Hwy. Admin., Ecusta Rail Trail Planning Study &

Economic Impact Analysis 4-9 (2012). Another portion, the southernmost 1-mile

segment known as the “Battleground Rail Trail,” was acquired from landowners at a

cost of $1,694,752, or just $321 per foot. Id. Mr. Kotis was one of the property owners

who participated in these land transactions. PX338; Tr. 62:5–63:5.

The City also received an easement superior to Trails Act easements because it is

unburdened by the railbanking obligation, making it easier to accommodate neighboring

businesses, which simultaneously increases the City’s tax base and reduces the cost of

acquiring the trail. For example, the City routed the trail around a parking lot owned by

Mr. Kotis, and a “CVS,” a “Total Wine,” and a “Rice Toyota” owned by other property

owners. Tr. 55:20–56:12.

The subject corridor. This case concerns the 3.1-mile Corridor immediately south of,

and abutting, the Battleground Rail Trail. Until 2014–15, Norfolk Southern provided

rail services in the Corridor for the benefit of a single customer, Chandler

Concrete/Piedmont, Inc. PX204, 206. When that customer moved elsewhere, leaving

“no other known active or prospective rail tenants” for the rail service, PX204, the City

sought to convert the Corridor into a greenway by first persuading Norfolk Southern to

abandon the rail easement, and then acquiring the Corridor from landowners. As Jim

Westmoreland, then City Manager, explained in a letter to Mr. Kotis:

[T]he City is not interested in rail-banking the corridor . . . .

We are interested in [Norfolk Southern] corridor

abandonment and then, the City acquiring the needed right

of way from adjacent property owners.

PX 204. Just as in the case of the A&Y Greenway, the City preferred a post-

abandonment conversion because, in the absence of a railbanking obligation, it would

have been free to work with “[Mr. Kotis]/other developers” to “enhanc[e] the economic

and job creation benefits of the corridor.” PX204. Seeing the project as a win-win, Mr.

Kotis took on a leading role in selling the idea to other property owners, PX77j, and

volunteered to design portions of the proposed greenway at his own expense, JX218;

see also JX1447 80:1–17. He has also financially supported “about 200” street art

installations on and along the City’s existing and planned greenways, including the

subject Corridor. Tr. 52:15–17; see, e.g., JX14 at 20 fig.12.

However, under the STB’s regulations implementing the Trails Act, the decision

to abandon the Corridor was in the hands of Norfolk Southern, not the City. Norfolk

Southern let the City know that it would not abandon the Corridor without an ITUR

agreement in hand. JX1447 at 63:21–64:2. At some point before June 2017, the City

buckled and began to negotiate a railbanking agreement with Norfolk Southern. JX106.

The negotiations took place behind closed doors at the railroad’s request. Id.

-7-

Meanwhile, the City simultaneously kept working with Mr. Kotis to route the proposed

greenway in such a way as to maximize the growth potential of downtown Greensboro.

PX218. Matters came to a head on June 14, 2018, when a City employee informed Mr.

Kotis that “[w]hile we’ve not finished negotiations with [Norfolk Southern], the likely

dispensation will be through the rail banking process which would allow for trail usage

only—not roads, driveways, or parking.” PX218. Mr. Kotis then raised “serious

concerns” that the railbanking option would jeopardize “all our planned $150 million

investment alon[g] the former railroad,” PX218, and withdrew his support for the

project.

The abandonment exemption and trail use proceeding. The negotiations between the

City and Norfolk Southern were ultimately successful. On April 12, 2019, the City and

Norfolk Southern entered into a purchase and sale agreement for the entire Corridor,

with the “exact area of land to be purchased . . . to be determined by a survey” of the

Corridor. 8 JX79. The agreement did not provide for any adjustments to the boundaries

of the Corridor—an option contemplated by STB’s regulations, see 49 C.F.R. §

1152.29(a)(1)—and instead provided that the trail “would just go straight down the

middle,” Tr. 76:21–22. The agreement further required the City to: (1) pay the railroad

$8,500,000 for the 3.1-mile corridor (approximately $519 per foot as compared to the

$312 per foot paid to property owners for the Battleground Rail Trail); and (2) assume

railbanking obligations as well as responsibility for all costs associated with the

Corridor, including management, liability, and tax burdens, as required by 49 C.F.R. §

1152.29(a)(2). JX79. It also committed the parties to the sale only if, after the railroad

had filed a notice of exemption and the City had petitioned for trail use, the STB

“imposes a valid [NITU] for . . . interim trail use” on the Corridor. Id.

On August 26, 2019, Norfolk Southern filed a Notice of Exemption with the

STB, requesting permission to abandon an ROW whose “width ranges from 50 feet to

200 feet along the main track centerline.” Notice of Exemption at 31, Norfolk Southern

R.R. Co.—Aban. Exemption [hereinafter Exemption Proceeding], STB No. AB-290

(Sub-No. 404X) (filed on Aug. 26, 2019). The railroad also stated that “not

abandon[ing] the Line and retain[ing] the track in place . . . is not satisfactory,” because

the railroad “would continue to incur opportunity and other holding costs that would

need to be covered by non-existent shippers.” Id. at 32. The exemption went into

effect on September 13, 2019, authorizing the railroad to abandon the line on or before

September 13, 2020, after which the permit would expire automatically. Board

Decision at 3, Exemption Proceeding (issued on Sep. 13, 2019).

On the same day, the City filed its petition for interim trail use and railbanking.

Petition for Interim Trail Use, Exemption Proceeding (filed on Sep. 13, 2019). The

City attached to the petition a map that, consistent with the description in the railroad’s

notice of exemption, depicted a corridor varying between 50 feet and 200 feet in width.

Id. at 4 Ex. A. The City also assumed “full responsibility” for all management costs,

8

Norfolk Southern also agreed to assign to the City its rights under eight lease agreements with

neighboring landowners. JX79.

-8-

liability, and tax associated with the Corridor, and acknowledged its railbanking

obligation. Id. at 2.

On September 20, 2019, the STB’s Office of Environmental Analysis filed its

environmental review report, concluding that an environmental impact statement is

unnecessary. Environmental Assessment, Exemption Proceeding (filed on Sep. 20,

2019). The report was prepared on the assumption that the Corridor had a “width

rang[ing] from 50 to 200 feet along [i.e., counting both sides of] the main track

centerline.” Id. at 1, 3.

On October 11, 2019, the STB issued the NITU, giving the City and Norfolk

Southern 180 days to negotiate an ITUR agreement for “the Line” and “the right-of-

way,” referring to the descriptions in the railroad’s application and the City’s petition,

respectively. JX83 at 1–2. The STB also stated that if the parties failed to reach an

agreement within 180 days, the Norfolk Southern would once again be permitted to

abandon the rail easement. Id. at 3.

On November 8, 2019, the City and Norfolk Southern jointly notified the STB

that they have reached an ITUR agreement covering the “entirety” of the line that “is

the subject of the above-captioned abandonment proceeding.” Notice of

Consummation, Exemption Proceeding (filed on Nov. 8, 2019). On the same day, the

City and Norfolk Southern executed the nonwarranty deed (“the Deed”) contemplated in

the purchase and sale agreement, quitclaiming the railroad’s interest in the Corridor

unto the City subject to the requirements of the Railbanking Provision. JX4. The deed

provided a legal description of the Corridor and a detailed map (the “Survey Map”)

that, consistent with the railroad’s and the City’s representations and the STB’s internal

environmental assessment, depicted an ROW that was up to 200 feet wide (that is, up to

100 feet either side of the centerline). JX4 Exs. A & B.

2. The Subject Properties

The Kotis Entities together own thirteen parcels that abut and underlie the

Corridor. These properties are located all along the Corridor in clusters, with a

combined total frontage of approximately one mile, or one-third of the length of the

Corridor. Tr. 48:4–8. From north to south, the properties are as described below.

Unless noted otherwise, the facts are derived from the parties’ joint stipulations. See Jt.

Stips. Fact Tr. at 2–5, ECF No. 117.

a. “Shops on the Greenway”

2414 Battleground Avenue (“Texas Roadhouse property”). Located at the northern

end of the Corridor, this parcel was owned by Kotis Holdings, LLC on October 11,

2019, the date of the taking. The parcel is 227,383 square feet (“SF”) or approximately

5.22 acres in size, and it is zoned as “Conditional District, Commercial – Medium.”

JX6 at 3, 16–17, 22. Mr. Kotis purchased the property in 2010 to build a hub of shops

and restaurants, which would have been known as “Shops on the Greenway.” Tr.

-9-

102:13–14; 894:1. As of 2019, Mr. Kotis had built two commercial buildings fronting

Battleground Avenue: a 7,393 SF building that currently houses a Texas Roadhouse

steakhouse, and a 5,952 SF building being used as a Mattress Warehouse store. JX6 at

3, 16; DX 232; DX 235. The remainder of the site, which consists of a cell tower,

92,000 SF of paved parking, and currently vacant land, JX6 at 18; DX 237, is suitable

for high-end commercial development. As a result of the taking, 51,849 SF of the land

is encumbered by the ITUR easement. JX117 at 1. The highest and best use of the

property absent the taking is Class A Retail Space with excess land available for

development. The highest and best use of the property after the taking is also Class A

Retail Space but with surplus land.

b. “Westover Galleries”

1430 Westover Terrace (“Core Life property”). This parcel was owned by Kotis

Holdings, LLC, on October 11, 2019. Somewhat uniquely, the property has frontage on

three streets—Westover Terrace to the west, Green Valley Road to the north, and

Battleground Avenue to the east. JX38 at 1. The parcel is 28,445 SF or approximately

0.65 acres in size, and it is zoned as “Commercial – Medium.” JX7 at 3, 21. Mr. Kotis

purchased the property in 2007 because it was located on a “premier corner” with high

visibility. Tr. 122:11–22. He “tore . . . down” an “IHOP” building located on the

property, and built in its place a 4,000-SF commercial space in the northeast corner of

the parcel, abutting Battleground Avenue and Green Valley Road. Tr. 123:3; JX7 at 3,

21. The building currently houses Core Life, a high-end eatery. JX7 at 25. The

remainder of the property consists of 690 SF of outdoor canopy dining space, and

16,000 SF of paved parking connected to the parking lot in the neighboring parcel, 1424

Westover Terrace (which is discussed next). JX7 at 24. As a result of the taking,

nearly half of the parcel—13,800 SF—is encumbered by the ITUR easement. JX38 at

1. The Core Life building is located almost entirely in the encumbered portion. JX38

at 1; JX7 at 48 fig. 20, 49. The unencumbered remainder has no access to Battleground

Avenue or to the parking lot on 1424 Westover Terrace. JX7 at 47 fig.18. The highest

and best use of the property absent the taking is Class “A” retail or office space. As a

result of the taking, the highest and best use is as a vacant commercial site.

1424 Westover Terrace (“Brixx Pizza property”). This parcel was owned by

Westover Terrace II, LLC as of October 11, 2019. It fronts Westover Terrace; is 32,234

SF or approximately 0.74 acres in size; and is zoned as “Commercial - Medium.” JX9

at 3, 15, 19. Mr. Kotis purchased the parcel “in the mid-90s” and later built a multi-

tenant commercial space with 11,529 SF of leasable space. Tr. 128:18; JX9 at 17. The

portion of the building fronting Westover Terrace currently houses a Brixx Pizza

restaurant. JX9 at 32; DX207. The rear of the building contains a two-story, multi-

tenant retail/office space which is largely vacant pending the outcome of this litigation.

JX9 at 17; see also DX218. In addition to the commercial space, the property contains

16,400 SF of paved parking which connects to parking spaces in the adjoining parcels.

JX9 at 17. As a result of the taking, nearly half of the parcel—16,100 SF—is burdened

by the ITUR easement. JX40 at 1. The encumbered portion runs through the

retail/office space at the rear of the building and the parking space, and also cuts off the

- 10 -

access points to neighboring parking spaces. JX40 at1; JX9 at 43 fig.20. The highest

and best use of the property absent the taking is Class “A” retail/office space. After the

taking, the highest and best use is as a vacant commercial site.

1420 Westover Terrace (“Chipotle property”). This parcel was owned by Westover

Terrace II, LLC as of October 11, 2019. It fronts Westover Terrace, and the parcel size

is 27,400 SF or approximately 0.629 acres. JX12 at 3, 15. The parcel is zoned as

“Commercial – Medium.” JX12 at 15. Mr. Kotis acquired the property in 1989, and in

1997 the parcel was repurposed from a warehouse to a multi-tenant retail building.

JX12 at 17. The parcel contains a multi-tenant retail/office building with 11,319 SF of

leasable space. JX12 at 3, 15. The space is fully occupied and houses tenants such as a

Chipotle restaurant, a Cherry Pit Café, and a “medspa” called Ideal Image. Tr. 132:1–8;

JX12 at 17; DX190; DX209; DX210; DX218; DX220; DX224. The remainder of the

site includes 9,240 SF of paved parking and an 840-SF covered walkway. JX12 at 17.

The ITUR easement burdens 13,700 SF of the parcel. JX43 at 1. It cuts through the

building and parking space, and encumbers access points to parking spaces in the

neighboring parcels. JX43 at 1; JX12 at 44 fig.19. The highest and best use of the site

absent the taking is Class “A” retail/office space. As a result of the taking, the highest

and best use is as a vacant commercial site.

1410 Westover Terrace (“Orange Theory property”). This parcel was owned by

Westover Terrace II, LLC on October 11, 2019. The parcel fronts Westover Terrace as

well; its size is 56,129 SF or approximately 1.29 acres; and it is zoned as “Conditional

District, Commercial – Medium.” JX11 at 3, 15. This parcel was also converted from a

warehouse to a multi-tenant retail building in 1997, and Mr. Kotis purchased the

property in 2005. JX11 at 17–18. The parcel contains a 22,256 SF multi-tenant retail

building, 31,446 SF of paved parking including an access road to neighboring

properties, and a covered walkway. JX11 at 3, 15, 17. The retail building is fully

occupied. JX11 at 17. Current tenants include Great Outdoor Provisions, an outdoor

sports store; and Orange Theory, a fitness club. Tr. 142:1–4; DX229. The ITUR

easement burdens 28,000 SF of the parcel, encompassing the access road to 1420

Westover Terrace and cutting through the retail building and approximately half of the

parking space for retail customers. JX42 at 1; JX11 at 43 fig.19. The highest and best

use of the site absent the taking is Class “A” retail space. As a result of the taking, the

highest and best use is now as a vacant commercial site.

1310 Westover Terrace (“Publix property”). This parcel was owned by Westover

Terrace II, LLC as of October 11, 2019. The parcel is 180,388 SF or approximately

4.14 acres in size, and it is zoned as “Conditional District, Commercial – Medium.”

JX10 at 3, 14, 20. The property was assembled by Mr. Kotis in multiple stages over an

extended period of time. JX12 at 18. The site is currently improved with 29,016 SF of

commercial space, and 122,902 SF of paved parking including an access road toward

the rear of the property. JX10 at 14, 17. At the time of the taking, the property hosted

restaurants named World of Beer, Osteria and Chicken Salad Chick, and was the site

(along with 1500 Mill Street, discussed below) of a planned high-end, 45,600-SF

grocery supermarket, Publix, for which the plaintiff owner had executed a lease before

- 11 -

the date of the taking. Tr. 117:1–6; DX184; DX192; DX213; DX217; PX308. The

ITUR agreement burdens 63,330 SF of the parcel, and cuts through parking space, the

existing commercial buildings, as well as the footprint of the planned Publix market. 9

JX41 at 1; JX10 at 42; PX294. The highest and best use of the site absent the taking is

Class “A” retail space. As a result of the taking, the highest and best use is now as

vacant land suitable for commercial development.

1500 Mill Street (“Saffron property”). This parcel was owned by Westover Terrace

II, LLC on October 11, 2019. The parcel fronts Mill Street, which connects Westover

Terrace and Battleground Avenue on the south side of the Westover Gallery of Shops.

The parcel is 62,683 SF or approximately 1.439 acres in size, and is zoned as

“Conditional District, Commercial – Medium.” JX13 at 3, 15. The site is improved

with an 18,400-SF multi-tenant retail development which hosts, among other tenants,

two restaurants, Taste of Thai and Saffron, and a dance studio named Fred Astaire. Tr.

894:14–15; JX13 at 3, 15; DX191; DX204; DX206; DX221. The remainder of the

property contains 29,000 SF of paved parking and a 640-SF covered mall area. JX13 at

17. A portion of the parcel was also part of the footprint of the planned Publix

shopping center. PX308 at 55. The ITUR easement burdens 29,989 SF of the parcel,

cutting through the commercial space and the footprint of the planned Publix store.

JX44 at 1. The highest and best use of the property absent the taking is Class B+ retail

or office space. As a result of the taking, the highest and best use of the property is as a

vacant commercial site.

1715 Battleground Avenue (“Take 5 Oil property”). This parcel was owned by Kotis

Associates, LLC on October 11, 2019. The parcel size is a triangular tract between the

properties that comprise the Westover Gallery of Shops and Battleground Avenue. It is

34,458 SF, or approximately 0.79 acres, in area, and it is zoned as “Commercial –

Medium.” JX5 at 3, 18. The tip of the triangular parcel is left vacant for construction

of an access road from Battleground Avenue, a major thoroughfare, to the Westover

Gallery of Shops. Tr. 119:17–20. The base of the triangle houses 1,586 SF of

commercial space in the form an automobile oil-change service station, Take 5 Oil.

JX5 at 18; DX233. The parcel also contains 15,000 SF of paved parking and a two-

sided billboard valued at $60,000 according to county records. JX5 at 18 & n.9, 21.

The ITUR easement burdens 28,685 SF of the parcel—that is, all but a sliver at the base

of the triangle—including most of the Take 5 Oil facility and paved parking, the

entirety of the billboard, and the potential access road to the Westover Gallery of

Shops. JX36 at 1; JX5 at 44 fig.20. The highest and best use of the site absent the

taking is its existing use, specialty street-front retail and billboard use. As a result of

the taking, the property owner no longer has the legal right to put the parcel to any

productive use.

c. Midtown Properties

9

During the pendency of the litigation, the City petitioned the STB to lift the railbanking

obligation from a small portion of the parcel. The petition is discussed later in the opinion.

- 12 -

1305 Battleground Avenue (“Red Cinemas property”). This property was owned by

Westover Terrace II, LLC on October 11, 2019. The parcel size is 251,410 SF

(approximately 5.77 acres), and it is zoned as “Conditional District, Commercial –

Medium.” JX14 at 3, 16. The site, which fronts Battleground Avenue just south of

another arterial road, Wendover Avenue, is currently used for a 44,956 SF multiplex

theater, Red Cinemas. JX14 at 16; DX181. The parcel is also improved with a 33,216-

SF landscaped parking lot. JX14 at 19. Plaintiff purchased the property in 2014 after

which the existing property was “completely gutted and redone” to build the existing

multiplex. Tr. 573:1. The back wall of the theater, which would face the trail if

allowed to remain, features commissioned street art by various famous artists. JX14 at

19, 20 fig.12. The ITUR easement encumbers 98,259 SF of the parcel, which overlaps

with the entire back wall of the cinema complex. JX45 at 1; JX14 at 40 fig.18. As a

result of the building’s “tilt-up masonry structure, with a very specific design as a

multi-plex, the back wall cannot be removed without demolishing the entire structure.”

JX14 at 19. 10 The highest and best use of the site absent the taking is its existing use:

as a multiplex theater. As a result of the taking, the highest and best use is as a vacant

commercial development site.

1211 Battleground Avenue (“Marshall Free House property”). This property was

owned by Westover Terrace II, LLC on October 11, 2019. The parcel is 65,340 SF

(approximately 1.5 acres) in size, and it is zoned as “Conditional District, Commercial

– Medium.” JX17 at 3, 15. The site fronts Battleground Avenue, and it consists of

6,692 SF of commercial space and eighty-seven parking spaces. JX17 at 15, 17. The

building previously housed a restaurant, Marshall Free House, but it is vacant pending

the outcome of this litigation. JX17 at 18. The parcel also shares a two-lane access

road to Battleground Avenue with the neighboring parcel, 1315 Battleground Avenue.

JX17 at 42 fig.20. The ITUR easement encumbers 13,089 SF of the parcel, which

includes access to the common road to Battleground Avenue, and several parking spots.

JX118 at 1; JX17 at 42 fig.20. The highest and best use of the site absent the taking is

Class “A” retail space. As a result of the taking, the highest and best use is a Class “B”

retail or commercial space.

1209 Battleground Avenue (“Burger Warfare property”). This property was owned

by Westover Terrace II, LLC on October 11, 2019. The parcel is 54,886 SF

(approximately 1.26 acres) in size, and it is zoned as “Conditional District, Commercial

– Medium.” JX15 at 3, 15. The site fronts Battleground Avenue and it contains 7,708

SF of multi-tenant retail space, as well as sixty-two lined parking spaces. JX15 at 15,

18. Current tenants include a restaurant, Burger Warfare; a wine shop; and a salon. DX

1643–44. The ITUR easement encumbers 12,250 SF of the parcel, approximately half

of which is vacant land and the other half parking spaces. JX119 at 1; JX15 at 43

fig.18. The highest and best use of the site absent the taking is Class “A” retail space.

As a result of the taking, the highest and best use is a Class “B” retail space.

10

Prior to the taking, the railroad attempted to exercise its right to have the structure demolished.

JX81; PX197–98.

- 13 -

1201 Battleground Avenue (“Midtown Financial property”). This property was

owned by Westover Terrace II, LLC on October 11, 2019. The parcel is triangular in

shape, 31,799 SF (approximately 0.73 acres) in size, and zoned as “Conditional District,

Commercial – Medium.” JX16 at 3, 15. The site fronts Battleground Avenue and it

contains a two-story, 12,080-SF office building with a “unique shape,” as well as forty-

two lined parking spaces. Tr. 446:13; JX16 at 18. Current tenants are Carter Bank on

the ground floor and Midtown Financial Advisors on the second floor. JX16 at 18;

DX185–86. The ITUR easement encumbers 14,750 SF of the parcel, which eliminates

most of the available parking, and leaves just eighteen feet of space between the trail

corridor and the building on the site. JX120 at 1; JX16 at 42 & fig.17. The reduction

in parking makes it more difficult to comply with the City’s ordinance requiring a

minimum of thirty-one parking spaces for the on-site building, given its size of 12,080

SF. See Greensboro, N.C., Land Devp. Ord. § 30-11-5 (requiring, as relevant here, one

parking spot per 400 SF of office space). The highest and best use of the site absent the

taking is Class “A” office space. As a result of the taking, the highest and best use is a

Class “B” office space.

d. The Spring Street Parcel

601–623 Spring Street (“Spring Street property”). This parcel was owned by

Kotis Holdings, LLC on October 11, 2019. The parcel is roughly triangular in shape,

and it is bounded by the railbanked easement to the northeast, an active rail line to the

south, and the Downtown Greenway trail and an elevated highway to the west. JX39 at

1. An abandoned radio transmission tower is located roughly at the center of the lot.

JX8 at 20. Although the total size of the property is 114,548 SF (2.629 acres), an

easement for the active rail line—which is not the subject of this litigation—renders

47,200 SF of the property unusable with or without the railbanked easement. JX8 at 3,

23–24. Thus, the property contains 67,348 SF of developable land. JX8 at 24. The

parcel is located at the edge of downtown Greensboro in close proximity to the

University of North Carolina at Greensboro, and it is zoned as “Central Business,”

which earmarks properties “in the central core of the city . . . [for] high-intensity,

compact urban development.” Greensboro, N.C., Land Devp. Ord. § 30-6-5.5. The

property may be used for mixed and multiple uses, “including office, retail, service,

institutional, and high-density residential developments . . . [that] may be located in the

same building.” Id. The property is exempt from building height restrictions and off-

street parking requirements. Id. §§ 30-7-5.1, 30-11-4.1. The ITUR easement

encumbers 42,755 SF of the parcel, and it blocks the only vehicular access point, thus

foreclosing all productive use of the property. JX39 at 1; JX8 at 10 fig.3. The highest

and best of the property absent the taking is as a vacant development parcel suitable for

a mixed-use high-rise development anchored by student housing or a hotel. As a result

of the taking, the parcel cannot be put to any productive use.

3. Events after the Trails Act conversion was complete.

As the descriptions above indicate, many parcels contain permanent structures

located partially or wholly within the footprint of the Corridor. After the ITUR

easement went into effect in November 2019, the legal status of these structures—the

- 14 -

parties call them “encroachments” but this opinion with refer to them as “overlying

structures” 11—was thrown into uncertainty. Mr. Kotis asked the City to clarify whether

it had the right to eject the existing overlying structures and prevent new overlying

structures from being built; and, if so, whether it intended to exercise that right.

According to City Attorney Charles Watts, the conversation focused primarily, though

not exclusively, on the planned Publix development, and specifically, the planned

loading dock at the back of the development, which would extend into the Corridor.

JX1446 at 41:8–19. The City took a cooperative stance and sought to “help Mr. Kotis

figure out how to encroach on the right of way.” JX1446 at 29:2–4. Nonetheless, it

ultimately concluded, after engaging an outside attorney who practices before the STB,

that:

if we facilitate or allow encroachment on the right of way,

we could potentially lose the entire Greenway . . . [b]ecause

the [STB] has taken that ability away from us and we’re an

agent of them and we don’t have discretion to grant

encroachments on the right of way.

JX1446 at 43:11–20; 49:6–11 (emphasis added). Ultimately, the City settled on a

policy of enforcing its right “not [to] allow any new construction” in the Corridor; and

retaining, but not enforcing, its right to eject the pre-existing overlying structures.

JX1448 at 242:12–14 (Interim Deputy City Manager Christian Wilson confirming that

the City “could” remove existing overlying structures “in the future”); JX1448 at

237:5–11 (Wilson stating that the City “hasn’t given any assurances that [existing

overlying structures] won’t be removed,” nor would it be “appropriate for the City to

give those assurances”).

Once it became clear that the City would not act without the STB’s approval, Mr.

Kotis initiated a dialogue with the federal government by reaching out to Senator

Richard Burr, who in turn reached out to the STB. Tr. 90:21–91:7. Senator Burr later

relayed the STB’s response to Mr. Kotis, in which the STB stated that “rather than the

trail sponsor authorizing the fringe encroachments by adjacent landowners, the better

practice might be to come to the board . . . to shrink the rail bed corridor.” JX155.

Furthermore, Mr. Kotis lacked standing to initiate such a proceeding: only the City

could seek a decision “clarifying” that the portion “is no longer part of the NITU[].”

11

Although recent opinions of this Court have adopted the term “encroachment,” see, e.g.,

Agapion v. United States, 167 Fed. Cl. 761, 770 (2023); Cheshire Hunt, Inc. v. United States, 158 Fed.

Cl. 101, 102 (2022), the Court now believes that it is misleading. “Encroachment” carries with it an

implication of illegality. See Encroachment, Black’s Law Dictionary (12th ed. 2024) (“An interference

with or intrusion onto another’s property.”). However, in the “before” or “but-for” condition where

landowners own their respective parcels in unfettered fee simples, see § III.B.1.a, infra, it is undisputed

that the structures would be legal. And, counterintuitively, the defendant maintains that the structures

are and have always been legal. See § III.B.1.b.ii, infra (describing the government’s argument that the

structures were legal, and continue to be legal, because they do not conflict with rail use, trail use, or

railbanking). Given that the legality vel non of these structures prior to the issuance of the NITU plays

at best a minor role in the legal analysis—and that both parties agree that the structures are legal in at

least some scenarios—the value-neutral term “overlying structure” is less distracting and more

appropriate.

- 15 -

JX154 at 1. To prevail, the City would have to “demonstrate” to the STB that the

portion at issue “is not needed to reactivate rail service.” JX154 at 1.

Taking the STB’s cue, on December 7, 2022—while this litigation was ongoing

and a week before trial—the City filed a clarification petition with the STB. Petition

for Clarification, Exemption Proceeding (filed on Dec. 7, 2022) [PX343]. The petition

asked the STB to “clarify” that the width of the Corridor along one of the thirteen

subject parcels, the Publix property, is “at most 50 feet in connection with a land sale to

Kotis Properties . . . to develop an important grocery store.” Id. at 1. The City asserted

that the “remaining [50-feet-wide] right-of-way that would continue to be subject to the

NITU is sufficient to permit the future reestablishment of rail service,” and asked the

STB to lift the railbanking obligation on the tract outside the 50-feet-wide area so that

the City may “convey[]” or “sell” the tract to Kotis Properties. Id. at 2, 7–9. 12 Norfolk

Southern opposed the petition, arguing that (1) the STB should require the City to file

an adverse abandonment application instead of a clarification petition; and (2) the

portion could be needed for future rail use as a site for “a future storage yard, siding, or

communication tower.” Reply of Norfolk Southern, Exemption Proceeding (filed on

Dec. 27, 2022). The STB ruled that a petition for clarification is the appropriate

procedural vehicle, and exercised jurisdiction over the City’s petition to narrow the

railbanked portion of the Corridor from 200 feet to 50 feet, while specifically noting

that the United States’ position before this Court is that “the easement is not 200 feet

[wide].” Board Decision at 2 & n.3, Exemption Proceeding (issued on June 28, 2023).

Several months later, the railroad dropped its objections, and the STB granted the

City’s petition on the merits. Board Decision at 1, Exemption Proceeding (issued on

Jan. 4, 2024) [hereinafter Clarification Decision]. That last decision is the subject of

defendant’s motion to reopen the trial record, see Section II, infra.

II. Procedural History

Plaintiffs filed their complaint on July 30, 2020. Compl., ECF No. 1. On

December 16, 2020, the parties stipulated to the following: Plaintiffs owned title to the

subject properties at the time of the taking; the railroad held an easement over the

properties for “railroad purposes” only; and the subject properties underlie and abut the

ROW described in the NITU. Jt. Title Stips. at 1, ECF No. 10. In a bid to settle the

case, the parties jointly engaged an appraiser, Mr. Thomas Taylor, who completed his

report sometime prior to August 16, 2021. Jt. Status Rep. at 1, ECF No. 24. On

November 9, 2021, plaintiffs informed the Court that the parties had failed to reach a

settlement. Pls.’ Status Rep. at 1, ECF No. 38.

12

At trial, Mr. Kotis took issue with the City’s effort to “sell me my own land to eliminate the

easement.” Tr. 202:3–6. He further noted that City’s proposed narrowing was not sufficient to allow

the Publix project to go forward because, while it would remove the footprint of the loading dock at the

rear of the planned Publix development from the Corridor, the service road that leads to the loading

dock would still overlie the narrowed Corridor. Tr. 864:11–20.

- 16 -

Defendant’s motion for summary judgment. On August 22, 2022, defendant filed a

motion for summary judgment arguing that the evidence to be presented at trial

supports, at best, “a nominal award” that, according to the defendant, “this Court lacks

jurisdiction to provide.” Def.’s Mot. Summ. J. at 9 [hereinafter Def.’s MSJ], ECF No.

88. On September 1, 2022, the Court issued an order that, among other things, stayed

the plaintiffs’ Response. Order at 1, ECF No. 99.

Motions in limine. On August 31, 2022, the parties filed three motions in limine to

exclude the testimonies and declarations of several potential witnesses. First, plaintiffs

moved to exclude the testimony and declarations from representatives of Norfolk

Southern Railway, including the railway’s Director of Real Estate, Ms. Kristi D. Blair.

Pls.’ Mot. in Limine Excl. Test. of Norfolk S. R.R. at 1, 5, ECF No. 96. Second,

defendant moved to exclude the testimony of plaintiffs’ appraiser, Dr. John A.

Kilpatrick. Def.’s Motion in Limine Excl. Test. of John A. Kilpatrick at 1, ECF No.

97. Lastly, plaintiffs sought to exclude the testimony of defendant’s rebuttal witness,

Mr. Stephen Roach. Pls.’ Mot. in Limine Excl. Test. of Stephen Roach at 2, ECF No.

98.

On October 6, 2022, the Court denied plaintiffs’ and defendant’s motions to

exclude the testimony of Mr. Roach and Dr. Kilpatrick, respectively, Order at 1, ECF

No. 122, but granted plaintiffs’ motion to exclude the testimony and declarations of

Norfolk Southern representatives, including Ms. Blair, Order at 1, ECF No. 123.

Defendant submitted an offer of proof to preserve its claim of error as to the granted

motion. See Def.’s Offer of Proof, ECF No. 150. In that filing, defendant stated that

Blair’s testimony would have established that Norfolk Southern would not have

abandoned its easement—and the Corridor would therefore not have reverted to

landowners—without an ITUR agreement in hand. Id. at 2. Defendant argued that this

testimony is relevant because it tends to show that the “proper ‘before’ condition” of

the properties for calculating just compensation is fee title subject to the railroad

easement (as opposed to fee title free and clear of any easement). Id. at 1; see also

Def.’s Pre-Tr. Mem. at 11, ECF No. 90.

Plaintiffs’ motion for partial summary judgment. Also pending before the Court is

plaintiffs’ motion for partial summary judgment as to the applicable interest rate, filed

on March 6, 2023. See Pls.’ Mot. for Partial Summ. J., ECF No. 173. Plaintiffs argue

that post-taking interest on the just compensation award should be based on Moody’s

Composite Index of Yields on Aaa Long Term Corporate Bonds (“Moody’s Rate”), and,

further, that the interest should be compounded. Id. at 1. Defendant filed a response on

April 19, 2023, arguing that the Court should apply the One-Year Treasury Bond rate,

which is the “rate that would apply in a direct condemnation,” compounded annually.

Def.’s Resp. Pls.’ Mot. Partial Summ. J. at 2, ECF No. 179. Plaintiffs filed their reply

on April 26, 2023. See Pls.’ Reply Supp. Mot. Partial Summ. J., ECF No. 180.

Trial. On December 13, 2022, the Court conducted a site inspection of the properties,

and the valuation trial commenced on December 14, 2022, in Greensboro, North

Carolina. On December 14 and 15, plaintiffs presented a portion of their case-in-chief.

The remainder of the trial took place via live video conferencing on the following dates

- 17 -

in 2023: January 11 and 12, and February 22. The parties filed post-trial briefs on

February 28, 2023. See Def.’s Post-Tr. Br., ECF No. 171; Pls.’ Post-Tr. Br., ECF No.

172.

Defendant’s motion to reopen the trial record. On January 9, 2024, defendant moved to

reopen the case for the purpose of considering new evidence. Def.’s Mot. Reopen Case,

ECF No. 188. The evidence proposed for introduction was the STB’s decision

approving the City’s “clarification” petition lifting the railbanking obligation from a

portion of the Corridor abutting the Publix property. Id. at 1; see Clarification

Decision, Exemption Proceeding. On January 23, 2024, plaintiffs filed their response.

Pls.’ Resp. Def.’s Mot. Reopen Case, ECF No. 192. Defendant replied on February 20,

2024. Def.’s Reply Supp. Mot. Reopen Case, ECF No. 195. On April 2, 2024, the

Court denied defendant’s motion orally, with a written explanation to follow in this

opinion.

III. Overview of Trial Testimony

Several witnesses testified during the valuation trial. For the plaintiffs, the

witnesses were Mr. Kotis in his capacity as the majority owner and designated

representative of all three plaintiff entities; and Dr. John A. Kilpatrick, an expert

appraiser who provided opinions of value. The defendant called one witness: Mr.

Stephen D. Roach, a real estate appraiser and consultant. Mr. Roach did not offer

opinions of value. Instead, his testimony focused on rebutting Dr. Kilpatrick’s

methods, assumptions, and conclusions. In addition, the parties stipulated to the

admission of prior testimony and declarations of several City officials, including Mr.

Charles Watts, then-City Attorney; and Mr. Christian Wilson, then-Interim Deputy City

Manager.

A. Mr. Kotis’s Testimony

In testimony that lasted two days, Mr. Kotis described the unique features of the

thirteen parcels at issue in this litigation, as well as his interactions with the City, the

STB, Norfolk Southern, and state and federal employees before, during, and after the

Trails Act conversion. Tr. 38–339. He testified that pre-existing development on the

properties significantly overlaps with the Corridor, and that removal would impact “all

of [the Kotis Entities’] planned . . . $150 million investment . . . along the former

railroad corridor.” Tr. 78:12–15. 13 He also outlined his ultimately unsuccessful efforts

to persuade the STB and the City to narrow the corridor to remove any cloud on all pre-

existing and planned overlying structures, or alternatively, to obtain assurances from

the City that it would not seek to remove the existing overlying structures. E.g., Tr.

95–96.

B. The City Officials’ Prior Testimony and Declarations

13

Mr. Kotis is not an expert appraiser, and the Court heard his valuation testimony only for the

purpose of understanding his investment-backed expectations, and his dealings with the City, the STB,

and the railroad.

- 18 -

In this case, the parties disagree about the scope of the property interest at stake

both in the “before” or “but-for” condition, and in the “after” condition. Defendant also

seeks to reopen the trial record so that it may account for the STB’s clarification order.

Finally, defendant argues that plaintiffs double-count severance damages, and in any

event have failed to meet their burden of proving how much just compensation is due.

The Court considers each question in turn.

A. Scope of the Property Interest Taken

1. Summary of arguments and the Court’s conclusions

The parties have stipulated to a taking, but they may as well not have.

According to the Kotis Entities, in the “after” condition, the ITUR easement

encumbering their properties is up to 100 feet wide on either side of the centerline as

depicted in the Survey Map, and they have no legal right to maintain existing overlying

structures or build new overlying structures within the Corridor. Pls.’ Post-Tr. Br. at 1

n.3, 3–5. They also argue that this encumbrance is a taking, because Norfolk Southern

would have abandoned the railroad ROW in the “before” or “but-for” condition, leaving

them with unfettered fee-simple ownership of their property all the way up to the

centerline. Id. at 2–3.

The government presents a starkly different vision of the scope of the taking. As

to the “after” condition, it argues that the Corridor is no more than 65 feet wide either

side of the centerline, or, alternatively, no more than 50 feet either side of the

centerline; and that even the narrow easement is “nonexclusive,” meaning that plaintiffs

have the right to maintain and build overlying structures within it as long as the

structures do not interfere with trail use or future rail reactivation. Def.’s Post-Tr. Br.

at 4–8. The government further argues that in the “before” or “but-for” condition,

Norfolk Southern would not have abandoned the railroad ROW, meaning that the

government took only the additional burden imposed by the ITUR easement as

compared to the old railroad ROW. Def.’s Mot. Summ. J. at 9–13. Finally, it argues

that plaintiffs have failed to prove that any compensation is due for the additional

burden.

For the reasons below, the Court concludes that the ITUR easement is up to 100

feet wide either side of the centerline, as depicted in the Survey Map; that plaintiffs

have no legal or functional right to use their property within the Corridor; and that

plaintiffs would have owned their property free and clear of any easement in the

“before” or “but-for” condition. The Court also denies the government’s motion to

reopen the record.

2. The “After” Condition of the Property

a. Width of the Easement

Start with the dimensions of the ITUR easement. The Kotis Entities maintain

that the easement is up to 100 feet wide either side of the centerline, as depicted in the

- 21 -

Survey Map. Pls.’ Reply Br. at 6. The government argues that the true width of the

former railroad ROW was either “65 feet or less” at every subject property, as depicted

in the 1927 valuation map, or “50 feet” or less at every subject property, based on

Norfolk Southern’s alleged “historical use” of plaintiffs’ property. Def.’s Br. at 4. The

government further contends that the ITUR easement is similarly narrow because “the

railroad cannot give what it does not have.” Id. (quoting Toews v. United States, 376

F.3d 1371, 1376 (Fed. Cir. 2004)). As for the Survey Map, the government considers it

irrelevant because the nonwarranty deed to which the map is attached “neither warrants

nor professes that the title is valid.” Id. at 5 (quoting Thompson v. United States, 101

Fed. Cl. 416, 421 n.4 (2011)).

i. The Corridor description adopted by the STB is

dispositive.

The parties incorrectly presume that the Court can determine the width of the

ITUR easement de novo. An alleged taking by the federal government can give rise to

two types of actions. First, property owners can challenge the taking wholly or in part.

See, e.g., Preseault I, 494 U.S. at 14 (assuming without deciding that a Trails Act

conversion is a taking, then declining to invalidate it). Second, they can bring a claim

for just compensation—but to do so, they must concede the validity of the government

actions that resulted in the alleged taking. Gahagan v. United States, 72 Fed. Cl. 157,

161 (2006) (citing Florida Rock Indust., Inc. v. United States, 791 F.2d 893, 898 (Fed.

Cir. 1986)). As a result of this two-tiered structure, a court’s powers depend on

whether it is deciding an invalidation claim or a just compensation claim. In the first

kind of case—which is properly brought in federal district courts, not this Court—

judges have leeway to construe the scope of a taking narrowly to “avoid[] . . . a

constitutional difficulty.” United States v. Riverside Bayview Homes, Inc., 474 U.S.

121, 128 (1985) (citing Ashwander v. TVA, 297 U.S. 288, 341–56 (1936) (Brandeis, J.,

concurring)).

In the second kind of proceeding, however, courts must first ask whether “the

legislative branch and executive agencies to which the legislature has delegated

condemnation authority . . . [have already] determine[d] the scope of taking necessary

for the public purpose.” Narramore v. United States, 960 F.2d 1048, 1050 (Fed. Cir.

1992). If the answer is yes, then the court’s only job is to “fix[] the amount of just

compensation—‘the price of the taking’—for the property described in the

[condemnation] filing.” Id. (emphasis added). Indeed, in just compensation

proceedings, “[f]ederal court jurisdiction does not extend beyond the scope of the

[condemnor’s] filing.” Id. And it certainly does not extend beyond the condemnation

court’s judgment approving the condemnor’s filing. Id.

Although our Court sits as a just compensation court, Preseault I, 494 U.S. at 14,

the Narramore principle seldom has bite in our cases because usually there is no

authoritative document that constitutes the final word of the Legislature or the

Executive. For example, in “flood-taking” cases, see, e.g., Arkansas Fish & Game

- 22 -

Comm’n v. United States, 568 U.S. 23 (2012), the scope of the implicit taking is

determined by hydrological forces, not an official pronouncement.

Trails Act takings are different, however, because they are something of a hybrid

between direct condemnations and inverse condemnations. They are inverse

condemnations in the sense that the government does not pre-emptively acknowledge

that a taking has occurred. The government has good reason not to admit a taking ex

ante because not all Trails Act conversions effect a taking. See, e.g., Rogers v. United

States, 814 F.3d 1299 (Fed. Cir. 2015). But whatever the reason, the taking is implicit

all the same, making “Rails-to-Trails takings . . . markedly different from . . . direct

condemnations” for some purposes, such as selecting the rate at which interest accrues

on just compensation owed. Hardy v. United States, 138 Fed. Cl. 344, 350 (2018).

But Trails Act takings are markedly similar to direct condemnations in another

respect: The taking is effected as a result of formal filings by the railroad and trail

sponsor, and there is an official document approving the putative taking, the NITU.

Indeed, the analogy between a condemnation court’s judgments and the NITU is

foundational to the rails-to-trails jurisprudence: In Caldwell v. United States, a seminal

case, the Federal Circuit concluded that the NITU is the sole government action that

could effect a taking by analogizing the NITU to a condemnation court’s “judgment”

initially permitting “immediate possession” and eventually sealing “the formal passage

of title.” 391 F.3d at 1234 (discussing United States v. Dow, 357 U.S. 17 (1958)).

Thus, Narramore applies in Trails Act cases, and our inquiry begins with the

NITU. If the NITU adopts a description of the ITUR easement, then the inquiry ends

there too, for our Court, being a just compensation court, may not attempt to “expand or

contract” the scope of the NITU. 960 F.2d at 1050 (emphasis added). 14 This remains

true even if the NITU approves a wider ITUR easement than that contemplated under

the Trails Act, because the STB’s actions, though contrary to statute, would still be

“authorized” for purposes of the Tucker Act. See Part IV.A.2.a.iii, infra; Del-Rio

Drilling Programs, Inc. v. United States, 146 F.3d 1358, 1362 (Fed. Cir. 1998) (Tucker

Act remedy available when government agents’ actions “are pursuant to the good faith

implementation of a Congressional Act” (internal citation and quotation marks

omitted)). Therefore, the NITU is the authoritative document through which Congress

and the STB impose an ITUR easement, Caldwell, 391 F.3d at 1234, and the corridor

description adopted therein is binding on this Court.

No more is needed to fix the dimensions of the Corridor. The NITU clearly

adopts the Survey Map on which plaintiffs rely. Throughout the exemption proceeding,

Norfolk Southern and the City made clear that they seek a NITU as to a corridor up to

100 feet wide either side of the centerline (up to 200 feet in total). The railroad’s

14

The Narramore principle applies to all just compensation courts, including those that otherwise

have the power to award equitable relief. But it applies with special force to this Court because we

cannot issue equitable relief as a general matter, Ministerio Roca Solida v. United States, 778 F.3d

1351, 1355 n.2 (Fed. Cir. 2015), and “none of the limited exceptions” to the general rule “apply to

enjoining takings,” Graves v. United States, 160 Fed. Cl. 562, 574 (2022).

- 23 -

notice of exemption stated, per 49 C.F.R. § 1152.22(a)(4), that “[t]he right-of-way

width ranges from 50 feet to 200 feet along the main track centerline.” Notice of

Exemption at 31, Exemption Proceeding (filed on Aug. 26, 2019). The City’s petition

for interim trail use, which was required to include an “accurate description” of the

proposed ROW under 49 C.F.R. § 1152.29(a)(1), similarly clarified that “[t]he right-of-

way which pertains to this request is the same as that described in [Norfolk Southern’s

notice of exemption],” and the petition included a bird’s-eye-view version of the Survey

Map. Petition for Trail Use at 2, 4, Exemption Proceeding (filed on Sep. 13, 2019).

The STB’s staff then performed its environmental analysis based on the assumption that

“the right-of-way width ranges from 50 to 200 feet along the main track centerline.”

Environmental Assessment at 1, Exemption Proceeding (filed on Sep. 20, 2019).

Finally, the NITU permitted Norfolk Southern and the City to negotiate an agreement

“for trail use [of] the Line”—a term defined earlier in the NITU as referring to the

ROW described in the railroad’s notice of exemption. JX83 at 3 (emphasis added).

Thus, the NITU adopted the Survey Map, and the Court must treat that description as

given for purposes of determining just compensation.

Given the STB’s clear-eyed approval of the Survey Map, one might wonder why

the government is arguing that this Court should not rely on it. The answer is that the

STB disclaims any authority or obligation to inspect the substance of the railroad’s and

the sponsor’s submissions in a trail-use proceeding. Even though the agency presides

over the proceeding, it has decided to “play no part in the parties’ negotiations,” going

so far as to decline to even “analyze . . . [the] trail use agreements.” Geo. Great S.

Div., S.C. Cent. R.R.—Aban. & Discontinuance Exemption, STB No. AB 389 (Sub-No.

1X), 2003 WL 21132515 at *4 (May 9, 2003). The STB believes that its practice is not

just permitted but mandatory: It must approve trail-use petitions because Congress has

assigned the agency an “essentially ministerial” role in administering the Trails Act.

JX74 at 2 (quoting Goos v. ICC, 911 F.2d 1283, 1295 & n.8 (8th Cir. 1990)).

That assertion does not hold water. For starters, it may not even be legally

relevant. Assuming that Congress assigned merely a ministerial role to the STB,

Congress has essentially pre-approved whatever description of the new easement

railroads and trails sponsors choose to include in their condemnation filings. With

respect to Narramore, then, the only difference would be that the Survey Map was

adopted by the “legislative branch [instead of] executive agencies.” 960 F.2d at 1048.

Furthermore, if the STB’s role is indeed ministerial, the new easement is not only

“authorized” under Del-Rio, but legal, because Congress of course has the authority,

under its eminent domain power, to replace an assumedly narrow railroad ROW with a

wider ITUR easement.

In any event, the STB’s position is dubious for two reasons. First, the decision

on which the STB relies merely held that the STB “lacked any discretion to decide

whether rail banking and [trail use] is desirable for a particular line,” and could not

deny petitions for trail use on that basis. Goos, 911 F.2d at 1295. But in this case, the

government is arguing that the old railroad ROW is narrower than the STB supposed—

meaning that the STB acted outside its jurisdiction in approving the City’s petition to

- 24 -

impose an ITUR easement on the outer reaches of the Corridor-as-surveyed. Nothing in

Goos supports the extraordinary conclusion that Congress prohibited the STB from

determining the extent of its own jurisdiction in trail-use proceedings.

Second, the STB’s position is flatly contradicted by its practice of sometimes

requiring railroads to disclose the nature of their property interest. See Metro. Transit

Auth. Harris Cnty., Tex.—Acquisition Exemption, STB Nos. FD 35846& 35847, AB-33

(Sub-Nos. 156, 253X), 2015 WL 331065 (Jan 26, 2015); S. Pac. Transp. Co.—Aban.,

ICC No. AB-12 (Sub-No. 108) (Aug. 26, 1986). Turns out, the STB can peer behind the

curtain after all.

In sum, the government’s problem is entirely of its own making. The STB

should, properly speaking, ascertain the physical extent of its own jurisdiction instead

of blindly relying on representations made by railroads and sponsors. Had it done so,

the federal taxpayer may have saved a lot of money, and not just in this case. See Dave

Owen, The Realities of Takings Litigation, 47 BYU L. Rev. 577, 610 fig.2 (2022)

(nearly three-fourths of the federal government’s total just compensation bill

attributable to Trails Act takings). And it would have saved the monies in the

constitutional way: by taking all the land needed to fully vindicate the mandate of the

Trails Act, but no more. But regardless of the wisdom of the STB’s current practice,

one thing is clear: This Court’s powers do not increase merely because the STB has

decided to shrink its own.

ii. Defendant is judicially estopped from arguing that the

STB adopted the wrong description of the Corridor.

The Court further holds that, even if a just compensation court could disregard

the description of the ITUR easement adopted in the NITU, defendant is judicially

estopped from making that request, because the STB continues to take conflicting legal

positions in its own proceedings. During the pendency of this litigation, the City

petitioned the STB for “clarification” that the NITU “may be narrowed [along a 264-

feet-long stretch of the Corridor] from a width of 100 feet from the center line to at

most 50 feet in connection with a land sale to Kotis Properties.” PX343.

In response to the City’s petition, the railroad argued that the City should have

filed a petition to vacate, or initiated an adverse abandonment proceeding, but the STB

permitted the City’s clarification petition to proceed. Board Decision, Exemption

Proceeding (issued on June 28, 2023). The STB then granted the City’s petition, thus

lifting the railbanking obligation from the relevant portion of the Corridor.

Clarification Decision, Exemption Proceeding.

Recall, at this point, that “clarification” petitions are different from petitions for

partial vacatur of the NITU. A vacatur reverses the taking and restores the status quo,

and it can therefore be understood as a mea culpa by the STB. In contrast, a

“clarification” lifts the railbanking obligation—dropping the “I” and “R” from

“ITUR”—from the sponsor’s easement, modifying the legal relationship between the

- 25 -

City and the STB, but restoring nothing to the only parties that owned any interest in

the corridor pre-conversion, the landowners and the railroad.

It is unclear why the STB thinks that lifting the railbanking obligation would not

immediately trigger abandonment in the property owners’ favor. See 28 U.S.C. §

1247(d) (providing that interim trail use “shall not be treated . . . as an abandonment of

the use of [the subject] rights-of-way for railroad purposes” but only as long as “such

interim use is subject to restoration or reconstruction for railroad purposes”). But

putting that problem aside, by granting the City’s clarification petition or even reaching

its merits, the STB necessarily decided that it had jurisdiction over the portion to be

“clarified”—which extends up to 100 feet each side of the centerline.

The STB thus took a position directly in conflict with the government’s position

in this litigation—as its decision expressly noted. Board Decision at 2 n.3, Exemption

Proceeding (issued on June 28, 2023). The government is thus simultaneously claiming

(through the STB) that it took a wide easement, but (through the Department of Justice)

that it need only pay for a narrow easement.

This doublespeak is a transparent attempt to circumvent the Kotis Entities’

constitutional right to just compensation. United States v. Dickinson, 331 U.S. 745, 750

(1947) (“[F]or all that the Government takes it must pay.”). Courts have the inherent

equitable power to foreclose just such a result by applying the doctrine of judicial

estoppel. The doctrine, which applies both within a single proceeding and across

multiple proceedings arising from the same set of facts, is “designed to protect the

integrity of the judicial process by preventing a party from prevailing in one phase of a

case on an argument and then relying on a contradictory argument to prevail in another

phase.” Haggart v. Woodley, 809 F.3d 1336, 1345 (Fed. Cir. 2016) (alterations and

internal quotation marks omitted). Although the doctrine is “not reducible to any

general formulation or principle,” the “main factors” that counsel application of the

doctrine are whether “(1) a party’s later position is clearly inconsistent with its prior

position, (2) the party successfully persuaded a court to accept its prior position, and (3)

the party would derive an unfair advantage or impose an unfair detriment on the

opposing party if not estopped.” Id. (internal quotation marks omitted). “Judicial

estoppel applies just as much when one of the tribunals is an administrative agency as it

does when both tribunals are courts.” Trustees in Bankr. of N. Am. Rubber Thread Co.

v. United States, 593 F.3d 1346, 1354 (Fed. Cir. 2010).

The STB’s exercise of jurisdiction over land 100 feet away from the centerline in

the “clarification” orders is clearly inconsistent with the government’s position in this

Court that the ITUR easement is no wider than 65 feet on each side. The STB’s view

was also “successful” by definition because it was the adjudicator, not merely a

litigant. 15 Finally, adopting the defendant’s position in this Court would unfairly

15

At least in the takings context, it is immaterial that the STB is technically not a litigant in

proceedings before itself. Although the NITU authorizes a transaction between third parties (the

railroad and the trail sponsor), the transaction is permissible only because it is for a “public use.” U.S.

Const. Amend. V. The federal government, standing in for the public, is therefore a legal beneficiary

- 26 -

burden plaintiffs because they would receive compensation for the taking of the

narrower tract even as the City, as the trail operator and as the agent of the STB,

continues to exercise control over the wider tract. Thus, the test for judicial estoppel is

met, and defendant is barred from arguing that the NITU adopted an incorrect

description of the ITUR easement. 16

iii. The width of the railroad’s former ROW does not

control the scope of the City’s ITUR easement.

Finally, the Court turns to the government’s argument from common law. As the

Court understands it, the government appears to break down the analysis into two parts.

First, it argues that “the rail easement pre-transfer and post-transfer is identical as a

matter of law,” Def.’s Mot. Summ. J. at 12 (emphasis added), “because the quitclaim or

nonwarranty deed executed between Norfolk Southern and the City “could not have

conferred more property interest that [the railroad] actually owned,” id. (citing, inter

alia, Van Rensselaer v. Kearney, 52 U.S. 297, 322 (1850)). Second, the government

acknowledges that there is no rail easement post-transfer, but nonetheless argues that

the ITUR easement can be no wider. Id. As for compensation, the government

acknowledges that the ITUR easement may impose an additional burden as compared to

the railroad ROW, but requests judgment in its favor on the grounds that plaintiffs

“have developed no evidence” proving the amount of just compensation due for the

additional burden. Id. at 13–14.

The government falters at the very first step. The scope of the taking is defined

not by the quitclaim deed, but by the “only government action in the railbanking

process” that gives rise to a taking—the NITU. Caldwell, 391 F.3d at 1233 (emphasis

in original). If it were true that the Corridor is narrower than the STB supposed, the

government would have proven merely that the NITU deprived the property owner of a

wider tract than the railroad owned. Although it is true that “[t]he consent of the

railroad to the new use . . . does not change the equation—the railroad cannot give

what it does not have,” Toews, 376 F.3d at 1376 (emphasis added), the STB, exercising

Congress’s eminent domain power, can give what the railroad does not have. To the

extent that this raises concerns about the STB running afoul of the Trails Act, the

proper course would have been for the STB to rescind, post haste, the NITU as to the

excess land. Since the STB has failed to do so and the Court has no trouble concluding

of the transaction. And because the government is a beneficiary, when the STB aggressively asserts

jurisdiction over a wide tract, the government extracts an “advantage,” Haggard, 809 F.3d at 1345, for

itself. Furthermore, the condemnation proceeding before the STB and the just compensation suit in this

Court are but two “phase[s]” of the same case, id., in the eyes of the Fifth Amendment. The doctrine of

judicial estoppel is therefore appropriately triggered.

16

Alternatively, on the merits, plaintiffs are correct that the Survey Map accurately depicts the

width of the ITUR easement taken. The Court reaches that conclusion for the reasons explained in

Agapion, 167 Fed. Cl. at 773–74. In that case, the Court considered the same NITU and easements, and

the parties presented very similar (though not exactly the same) evidence at trial regarding the width of

the easement.

- 27 -

that its actions were “authorized” even if contrary to statute, just compensation is

available as to the entire Corridor. Del-Rio, 146 F.3d at 1362.

iv. The government’s motion to reopen the trial record is

denied.

The Court now turns to the government’s motion to reopen the trial record, in

which it asks the Court to admit into evidence the STB’s decision granting the City’s

“clarification” petition, which narrowed a 264-foot strip of the 3.1-mile Corridor

abutting two subject parcels, 1310 Westover Terrace and 1500 Mill Street, 17 from 100

feet to 26 feet. The Court has the discretion to admit additional evidence. Zenith Radio

Corp. v. Hazeltine Rsch., Inc., 401 U.S. 321, 331 (1971). The primary consideration is

whether the proferred evidence has probative value. Precision Pine & Timber, Inc. v.

United States, 596 F.3d 817, 834 (Fed. Cir. 2010).

The motion is denied. The government thinks that the evidence is relevant

because the STB’s decision (1) restores the strip at issue to the status quo ex ante, thus

“convert[ing] the [permanent] taking into a ‘temporary’ one,” Def.’s Mot. Reopen Tr.

Rec. at 4 (quoting First English Evangelical Lutheran Church v. Cty. of Los Angeles,

482 U.S. 304, 320 (1987)) (alterations added); and (2) undermines Dr. Kilpatrick’s

assumptions about the width of the Corridor and the extent to with its overlaps with

existing and planned development on the subject properties, id. at 5–7.

Both arguments are incorrect for the same reason: The STB’s decision merely

expands the City’s rights over the Corridor; it does not restore any rights to the

plaintiffs. The City’s petition did not request vacatur but a “clarification.” Petition for

Clarification at 1, Exemption Proceeding (filed on Dec. 7, 2022). It sought to have the

strip “narrowed from a width of 100 feet from [the] center line to at most 50 feet in

connection with a land sale to Kotis Properties . . . to develop an important grocery

store.” Id. at 1 (emphasis added); see also id. at 7–8 & Ex. 3 at 7. The City fully

understood that the petition, if successful, would lift the railbanking obligation and

allow the City to sell the land back to Mr. Kotis. See id. at 7–8. And with good reason:

The STB decision on which it relied allowed the trail sponsor to “convey the [clarified]

50-foot-wide portion to” a third party, the Texas Department of Transportation, “to

improve a segment of U.S. Highway 82”—a non-rail, non-trail purpose. Mo. Pac. R.R.

Co.—Aban. Exemption, STB No. AB 3 (Sub No. 137X), 2021 WL 3235207 at *2 (July

27, 2021).

It is of course possible that the STB granted the City’s petition without adopting

the City’s view of the legal consequences, but that is not what happened here. The STB

narrowed the railbanking obligation on the southside—where the Corridor abuts the

subject properties—from 100 feet to 26 feet. Clarification Decision, Exemption

Proceeding. It found that portion of the Corridor at issue was not needed for future rail

reactivation, and specifically stated that the decision did not vacate the NITU. Id. at 2.

17

The total length of the border between the Corridor and those parcels is 952 feet. See JX41,

JX44.

- 28 -

And although it did not explicitly mention that the City may sell the strip to a third

party, throughout the discussion, it relied principally on the Missouri Pacific decision.

Id. at 2–3. Thus, the NITU did not alter the landowners’ property rights in any way,

only the City’s.

The government finds it relevant that the City intended to convey the strip back

to Mr. Kotis for two reasons. As to each ground, the government’s position is

understandable, but ultimately incorrect.

The government first argues that the putative conveyance would render the

taking temporary. That is untrue. Although it is true that “[i]f the NITU expires, is

revoked, or is modified to exclude land, then a temporary—not permanent—taking may

be effected,” Def.’s Reply Mot. Reopen Tr. Rec. at 4, ECF No. 195, a clarification

order does none of those things. It claims to narrow the scope of the NITU, but, in the

same stroke of the piston, hands the non-railbanked property over to the sponsor, who,

recall, would have held no interest in the property had the NITU never been issued in

the first place. Mo. Pac. at *2, STB No. AB 3 (Sub No. 137X). Therefore, the taking is

not reversed either in size or scope, nor is Dr. Kilpatrick’s analysis undermined in any

way.

Second, the government suggests that if Mr. Kotis was able to buy his property

back from the City for less than fair market value, the compensation amount should be

reduced accordingly. Def.’s Reply Reopen Tr. Rec. at 7 n.3. That is also incorrect. A

transaction between the City and Mr. Kotis, assuming that it has taken place at all, is a

“[d]ecision rest[ing] solely in the hands of” parties other than the government. Memmer

v. United States, 50 F.4th 136, 146 (Fed. Cir. 2022). As such, it does not diminish the

government’s “responsib[ility] for mandating the continuation of the easement.” Id.

Nor would Mr. Kotis be double-dipping. Landowners who persuade local governments

to sell property at below-market rates often “pay” in the form of non-monetary

concessions. The Court will not inquire into how the political sausage is made.

Thus, the STB’s clarification decision does not affect the taking and just

compensation analysis in any way, and the motion to reopen the trial record is denied.

b. Exclusivity of the Easement

The parties also disagree about whether the ITUR easement is exclusive.

Plaintiffs argue that it is, because the City and the STB can dictate the use of the entire

corridor for trail use and potential rail reactivation, respectively. Pls.’ Post-Tr. Br. at

3–5. This position, if correct, implies that plaintiffs have no right to maintain current

overlying structures or build new overlying structures, and should therefore be

compensated for the attendant loss in the fair market value of each parcel as a whole.

The government makes two interrelated arguments in opposition. First, it asserts

that the easement is nonexclusive, meaning that property owners have the legal right to

use the Corridor as long as the use does not conflict with trail use and railbanking.

- 29 -

Def.’s Post-Tr. Br. at 6. Baked into this argument is the assertion that nonexclusivity is

functionally meaningful, in that the Kotis Entities’ existing and planned commercial

uses of portions of the Corridor do not conflict with trail use and railbanking, and

therefore cannot be removed or blocked by the City and the STB. Id. Second, it argues

that easement is functionally nonexclusive even if the Kotis Entities’ use of the

Corridor conflicts with interim trail use and railbanking, because the City and the STB

will not require property owners to remove existing structures or prevent them from

building new ones. Id. at 7–8.

Plaintiffs have the better of the argument. Our Court often finds that a fee

simple landowner effectively loses all property rights within the corridor of a Trails Act

easement. See, e.g., Jackson v. United States, 155 Fed. Cl. 689, 702 (2021) (collecting

cases). Through a Trails Act transfer, the trail sponsor obtains the authority to dictate

how much of the corridor it needs, or will need in the future, to construct and operate

the recreational trail. See 16 U.S.C. § 1247(d); Caquelin, 959 F.3d at 1367. And the

STB retains the authority to decide whether the full corridor might be needed for

purposes of reactivating the rail line at some point in the future. See Caldwell, 391

F.3d at 1229 (observing that “the STB retains jurisdiction for possible future railroad

use” in Trails Act corridors). The intended consequence of this allocation of control is

that the landowner retains no right to use the encumbered portion of the corridor in the

face of a conflicting position taken by the City or the STB. See Hardy, 141 Fed. Cl. at

16–17 (“[P]laintiffs have no remaining use of the land burdened by the trail easement . .

. .”).

The Court sees no basis to reach a different conclusion here. The taking for

which plaintiffs are entitled to just compensation is the destruction of their property

interest within the Corridor, see Caquelin, 959 F.3d at 1367–68, and the resulting

reduction in the value of their land associated with this loss of property interest, see

Otay Mesa, 670 F.3d at 1364. To build or maintain overlying structures on a portion of

the Corridor, the Kotis Entities must have the legal right to exclude the City and the

railroad from that portion in the event of a conflicting use, now and in the future.

Caquelin, 959 F.3d at 1367 (observing that the Trails Act creates “a coerced easement

that impairs the landowner’s right to exclude by allowing others’ occupation.”).

Plaintiffs undoubtedly lack that right. In its capacity as the trail operator, the

City has exclusive control over all uses within the Corridor while it is used for a

recreational trail. Illig v. United States, 58 Fed. Cl. 619, 631 (2003); Jackson, 155 Fed.

Cl. at 701. This gives the City the inherent ability to determine whether another’s use

of the easement conflicts with its own trail needs and to revise that determination when

its plans change. See Norfolk S. Ry. Co. v. Smith, 169 N.C. App. 784, 789 (N.C. Ct.

App. 2005) (finding that the holder of a dominant ROW “may expand its use of the

right-of-way, to the extent of its statutory right, for any legitimate purpose as

determined by [its] sound business judgment” (emphasis added)); see also Trevarton v.

South Dakota, 817 F.3d 1081, 1087 (8th Cir. 2016). The City’s current plan may well

be to use only a narrow strip near the centerline for trail purposes, JX103 36:20–37:5,

but the record shows quite concretely that that might change in the future. For

example, the City’s greenway system—of which the subject trail would be a part—

- 30 -

contains the following: upgrades that enable “some level of passive programming,

environmental education”; “parklets” to host “things like exercise classes”; “Ebike[]”

stations; “[w]ater fountains”; “[r]estrooms”; and land set aside for conservation

purposes. JX103 35:10–12, 14–16, 18–21, 36:4–5, 36:20–37:5; JX1448 228:13. If and

when the City upgrades the Corridor to include such features, the City’s right to trail

use will conflict with, and supersede, plaintiffs’ right to maintain or build overlying

structures. And although the current City administration might refrain from exercising

its right to demolish existing overlying structures, administrations change. Thus, the

City’s trail use easement is exclusive for all intents and purposes.

In addition, the City’s obligation to railbank imposes a second layer of

exclusivity within the Corridor. The STB can continuously regulate any uses of the

Corridor that may conflict with rail use now or in the future. See 49 U.S.C. § 10501(b)

(The STB’s jurisdiction over rail line construction and maintenance is “exclusive”);

Caldwell, 391 F.3d at 1230 (“[T]he STB retains jurisdiction for possible future railroad

use.”); Preseault III, 100 F.3d at 1552; Dana R. Hodges Trust, 111 Fed. Cl. at 457. The

STB’s definition of a conflict is open-ended: “[N]othing [can] occur[] that would

preclude a railroad’s right to reassert control over the ROW at some future time to

revive rail service.” King Cnty., Wa—Acquisition Exemption, STB Fin. Dkt. No. 35148,

2009 WL 2979430 at *3 (Sept. 17, 2009). A use is deemed to be conflicting even if it

has “little actual, practical effect on current plans for active railroad operations”

because “circumstances can change.” Jie Ao & Xin Zhou—Pet. for Decl. Order, STB

Dkt. No. FD 35539, 2012 WL 2047726 at *7 (June 4, 2012). Furthermore, although the

STB does “allow[] for the possibility of shared use,” Norfolk S. Ry., Co. v. Dille Rd.

Recycling, LLC, 94 F.4th 517, 525 (6th Cir. 2024) (citing Jie Ao, 2012 WL 2047726 at

*6–*7), the analysis proceeds patch by patch. A shared use is not viable if the property

owner is “carving out property that is part of a railroad [ROW]” and thus not

“allow[ing] the railroad to access” the carved-out portion of the property. Id. Thus,

plaintiffs have no legal right to build or maintain overlying structures in any portion

within the Corridor for the additional reason that the STB—or the City, as its delegate

for railbanking purposes—may determine, now or in the future, that structures conflict

with the use of that portion for potential rail reactivation. Id.; Caldwell, 391 F.3d at

1229; Illig, 58 Fed. Cl. at 631. 18

18

In the next section of this opinion, the Court rejects defendant’s argument that the subject

properties would have been burdened by the former railroad ROW in the “before” or “but-for”

condition. Even if defendant were right about the “but-for” condition of the property, the holding in

this section would still apply. Although the government thinks that the additional burden caused by an

ITUR easement is synonymous with the additional burden of trail use, that is a false equivalence.

Railbanking is more burdensome than a railroad ROW, especially an inactive one. A property owner is

much more likely to succeed—not only in practice, but as a matter of law—in acquiring the right to use

a portion of a railroad ROW than an ITUR easement. While the railroad still owns the ROW, the

property owner need not obtain regulatory approval from the STB before leasing the corridor from the

railroad. See, e.g., Consol. Rail Corp.—Petition for Decl. Ord., STB Fin. Dkt. No. 33296, 1996 WL

714556, at *2 (Dec. 10, 1996). A party petitioning to let the property owner use the Corridor is also

not required to argue that he would “reuse . . . [the] right-of-way for a public purpose.” See Petition

for Clarification at 1, Exemption Proceeding (quoting Baltimore & Ohio R.R. Co.—Aban. &

Discontinuance of Service, STB No. AB-19 (Sub-No. 112), 1990 WL 287371 at *2 (Feb. 22, 1990). In

- 31 -

3. The “Before” or “But-For” Condition of the Subject Parcels

The Court now turns to the “before” or “but-for” condition of the subject

properties. Our task is to first ascertain, as a matter of law, “which ‘but-for’ world the

effects of the [government action] are measured against.” Ideker Farms, Inc. v. United

States, 71 F.4th 964, 981–82 (Fed. Cir. 2023) (emphasis added). Then, we make

findings of fact about the scope of the plaintiffs’ property interest in that but-for world.

Memmer, 50 F.4th at 145; Caquelin, 959 F.3d at 1372–73; see also St. Bernard Parish

Gov’t v. United States, 887 F.3d 1354, 1366–69 (Fed. Cir. 2018).

The Kotis Entities argue that they would have owned the properties free and

clear of any easement but for the taking, because: The appropriate inquiry is what the

state of the property would have been “but for the Trails Act”; and Norfolk Southern

would have abandoned the former railroad ROW but for the operation of the Trails Act.

Pls.’ Post-Tr. Br. at 3. This position is grounded in a long line of cases holding that in

the but-for condition, landowners have “possession of their property unencumbered by

[any] easement.” Ladd v. United States, 630 F.3d 1015, 1023 (Fed. Cir. 2010); accord

Memmer, 50 F.4th at 146 (“[H]ad a trail-use agreement been reached during the NITU,

a taking of [the landowners’] property would have occurred.”); Barclay, 443 F.3d at

1373; Caldwell, 391 F.3d at 1236; see also Nicholson v. United States, 170 Fed. Cl.

399, 410 (2024) (collecting our Court’s cases).

The government is not unaware of the weight of the precedent. It admits that

courts “generally assume[] that the railroad would have consummated abandonment” in

the absence of a taking, and that “[a]s such, the ‘before’ scenario ordinarily used is the

fee simple value of a plaintiff’s property unburdened by an easement for either railroad

or [ITUR] use.” Def.’s MSJ at 10. The government nonetheless asks the Court to adopt

the theory—which it has advanced in a bevy of cases in recent months—that the

appropriate legal counterfactual is the scope of the plaintiffs’ property rights “in the

absence of the NITU.” Id. at 10 (quoting Caquelin, 959 F.3d at 1363). It then argues

that under the but-for-the-NITU standard, Norfolk Southern would not have abandoned

the former ROW. Id. As proof, the government has repeatedly sought to admit the

declaration and deposition testimony of Ms. Kristi D. Blair, the Director-Real Estate of

Norfolk Southern. See Offer of Proof Ex. A, ECF No. 159-1 [hereinafter “Blair

Decl.”]; id. Ex. B, ECF No. 159-2. Her declaration states that “[i]f a final trail use

agreement had not been reached, Norfolk Southern would not have abandoned the

Line.” Id. at 2. She further states that it is Norfolk Southern’s policy not to abandon

rail easements unless doing so is “advantageous or necessary.” Id.

The Court holds that Norfolk Southern would have abandoned the Corridor but

for the taking, and reiterates that Ms. Blair’s declaration is of no probative value—if

anything, it proves that plaintiffs have the better of the argument.

contrast, after the corridor is railbanked, STB approval is required; a showing of public use is required;

and the STB applies a heightened standard of review. See King Cnty., 2009 WL 2979430 at *3.

- 32 -

a. The correct legal standard is whether Norfolk Southern

would have abandoned the Corridor but for the Trails

Act project.

The first question is how the but-for test should be framed. As defendant

correctly notes, the broad inquiry is whether Norfolk Southern would have abandoned

the former ROW “even in the absence of the Trails Act.” Def.’s MSJ at 9. The Court’s

task is to reduce that principle to a precise test.

Takings law is subject to ordinary but-for causation principles. Caquelin, 959

F.3d at 1371. The burden of proof is on the plaintiff. St. Bernard Parish, 887 F.3d at

1362. To ascertain whether the government took a plaintiff’s property, courts ask

“‘what would have occurred’ if the government had not acted.” Id. (quoting United

States v. Archer, 241 U.S. 119, 132 (1916)). A property interest has been taken if “in

the ordinary course of events, absent government action,” plaintiffs would have retained

the interest. Id.; Caquelin, 959 F.3d at 1371.

The critical question is what it means for government “not [to have] acted.” St.

Bernard Parish, 887 F.3d at 1362. Any given property in our country is touched by

multiple federal programs, which in turn usually authorize officials to take multiple

actions. Which of these actions should we imagine were never taken by the government

when asking “what would have occurred”? No court has provided a comprehensive

answer to that question, but this much is clear: we may not slice and dice government

initiatives. Under the scope of the project rule, courts must ignore “the positive or the

negative impact of any decision the Government makes within the scope of the project

that prompted the taking.” Love Terminal Partners, L.P. v. United States, 889 F.3d

1331, 1347 (Fed. Cir. 2018) (citation omitted). There is “no bright line rule” to

determine whether two actions are within the scope of the same project, Ideker Farms,

71 F.4th at 982 (quoting United States v. Reynolds, 397 U.S. 14, 18 (1970)), but the

relevant factors are whether: (1) “reasonable property owners at the time the taking

occurred” thought that the actions are part of the same project; (2) the government made

the same representation; (3) the action taken later in time was foreseeable at the time of

the initial action; and (4) the actions were close in time, id. For example, if the

government condemns multiple parcels of real property to build a reservoir, the

condemnation actions are part of the same project—meaning that in the just

compensation phase of every condemnation action, the relevant question is what would

have occurred had none of the properties been condemned. United States v. Miller, 317

U.S. 369, 370 (1943).

The Federal Circuit’s rails-to-trails precedents sometimes appear to imply that

the scope of a Trails Act project is never in dispute because there is only one relevant

government action: ‘the’ NITU. See, e.g., Hardy v. United States, 965 F.3d 1338 (Fed.

Cir. 2020) (quoting Caquelin, 959 F.3d at 1363) (“[T]he NITU takes nothing from the

landowner that the landowner would have had in the absence of the NITU.”); Caldwell,

391 F.3d at 1233 (“The issuance of the NITU is the only government action that

operates to prevent abandonment of the corridor.” (emphasis deleted)). Taking a cue

- 33 -

from those statements, the government equates “the absence of the Trails Act” with the

nonissuance of the NITU issued by the STB on October 11, 2019. Def.’s MSJ at 10.

But matters are more nuanced than that. Had the NITU not issued on October

11, 2019, Norfolk Southern could have decided not to consummate the abandonment

and seek another NITU (and another, and another) until a Trails Act conversion was

successful. Thus, if the Court adopted Caquelin’s but-for-the-NITU test in the context

of a successful Trails Act conversion, there would be no guarantee that plaintiffs would

be free from a taking in the but-for condition. By the very definition of the term “but

for,” that is a paradox.

Fortunately, circuit precedent also illuminates a path for avoiding the absurdity.

A NITU is not the taking, just the “finite start” of one. Caldwell, 391 F.3d at 1235. Its

hypothetical absence, therefore, would merely imply that the taking would not start on

the day it did—here, October 11, 2019. The only way to ensure that a taking does not

occur at all is to assume that no NITU will ever be issued as to the subject corridor.

After all, Congress’s “project” in enacting the railbanking provision was to “preserve

railroad rights-of-way,” 19 Bywaters v. United States, 670 F.3d 1221, 1225 (Fed. Cir.

2012) (emphasis added)—a long-term program implemented by extending a standing

offer to approve a rails-to-trails conversion whenever the railroad finds a willing

sponsor. Thus, the relevant question is not what would have happened but for the

issuance of the NITU; rather, it is what would happened if, on October 11, 2019, the

STB made clear that it would never issue a NITU as to the Corridor.

The but-for-any-NITU test is not just consistent with precedent—it is the only

way to make sense of the rules governing rails-to-trails conversions under two different

fact patterns. The first is presented in Caquelin. There, the STB issued a NITU;

negotiations failed; and after searching in vain for a replacement trail sponsor, the

railroad opted to abandon the line. 959 F.3d at 1362. Upon abandonment, the STB was

immediately divested of jurisdiction over the line—including jurisdiction to issue

NITUs as to the line. Jenkins v. United States, 102 Fed. Cl. 598, 613 (2011) (citing

Nat’l Wildlife Fed’n v. ICC, 850 F.2d 694, 702 (D.C. Cir. 1988)). With the legal

authority to issue NITUs extinguished, ‘but for any NITU’ reduces to ‘but for the

NITU.’ There is, therefore, no contradiction. To the extent that any doubt remains, the

appeals court later confirmed in Memmer—a case with virtually the same facts as

Caquelin—that Caquelin did not work a radical change in the law governing successful

Trails Act conversions. 50 F.4th at 146 (“[H]ad a trail-use agreement been reached

during the NITU, a taking of . . . property would have occurred.”).

19

The Trails Act works in concert with other legal provisions to preserve rail corridors. See, e.g.,

49 U.S.C. § 10905 (authorizing the Board to impose so-called public use conditions in an exemption

proceeding if the Corridor is “appropriate for use for public purposes, including highways, other forms

of mass transportation, conservation, energy production or transmission, or recreation”). The Court is

not asked to decide whether such statutes are also within the scope of the same project.

- 34 -

The second fact pattern arises when an ITUR easement is successfully

established, but only after the STB issues multiple NITUs as to the same corridor. See,

e.g., Barclay v. United States, 443 F.3d 1368, 1375 (Fed. Cir. 2006). In these

circumstances, the NITUs are considered a “single and continuous government

action,” 20 id., again confirming that relevant “project” is the STB’s standing offer to

issue NITUs whenever the railroad can find a willing trail sponsor.

Thus, the Court applies the but-for-any-NITU test, under which the causal

inquiry is whether Norfolk Southern would have abandoned its ROW had the STB (1)

declined to issue the October 11, 2019 NITU, and (2) announced that it would deny all

future NITU requests as to the Corridor.

b. Norfolk Southern would not have abandoned the

Corridor but for the Trails Act.

To determine whether Norfolk Southern would have abandoned its ROW if the

STB had declined to issue any NITUs on or after October 11, 2019, the Court turns to

the STB’s Trails Act regulations and the factual record. Memmer, 50 F.4th at 145;

Caquelin, 959 F.3d at 1372–73; St. Bernard Parish, 887 F.3d at 1366–69.

At the very outset, the legal backdrop creates a strong presumption that railroads

would abandon inactive corridors if the Trails Act were taken off the table. It is

indisputable that, as a general matter, inactive corridors are unprofitable, leaving

abandonment as “the only real financial option” available to railroads. See, e.g.,

Testimony of Am. Assoc. Railroads at 9, STB Ex Parte No. 690 (filed June 29, 2009).

That is the problem Congress set out to solve. Preseault I, 494 U.S. at 5. Furthermore,

the STB’s regulations foreclose many of the possible reasons why a particular inactive

corridor might buck the general trend by ensuring that commercially viable corridors

continue to be used for railway purposes. An exemption proceeding cannot even begin

if a shipper has recently used or wants to use the rail line, since the railroad is required

to certify that “no local traffic has moved over the line for at least 2 years” and “no

formal complaint . . . regarding cessation of service is pending.” 49 C.F.R. §

1152.50(b). Furthermore, a Trails Act conversion is an option of last resort. If a third

party (such as a small town serviced by the line) makes an “offer of financial

assistance” for continued rail service in the corridor, the STB gives the offer “priority

over a trail use proposal because of the strong congressional intent to preserve rail

service wherever possible.” N. Coast R.R. Auth.—Aban. Exemption, STB No. AB

1305X, 2022 WL 1561434 at *7 (May 15, 2022); see 49 U.S.C. § 10904; 49 C.F.R. §

1152.29(d).

20

Unusual circumstances aside. See, e.g., Ladd v. United States, 713 F.3d 648, 653 (Fed. Cir. 2013) (second

NITU treated as distinct government action when the government failed to publish the first NITU in the Federal

Register and its issuance was “inherently unknowable”).

- 35 -

In other words, the railroad is only eligible for a NITU when most other avenues

for financial viability have been exhausted. Special proof is needed to show that it

would have retained the corridor even if NITUs were not available.

The record lacks the requisite proof—quite the opposite. Norfolk Southern lost

its only customer on the line, Chandler/Piedmont, Inc., by 2015 at the latest, and the

line had remained fallow for four years at the time of the issuance of the NITU. There

were no potential customers on the horizon: In the words of Norfolk Southern, “not

abandon[ing] the Line and retain[ing] the track in place . . . [was] not [a] satisfactory”

alternative, because Norfolk Southern “would continue to incur opportunity and other

holding costs that would need to be covered by non-existent shippers.” Notice of

Exemption at 32, Exemption Proceeding (emphasis added). That Norfolk Southern had

no commercial use for the Corridor is further confirmed by its decision to begin

negotiations with the City almost as soon as the line reached two years of inactivity,

making it eligible for both abandonment and Trails Act conversion. JX106; 49 C.F.R. §

1152.50(b).

The government thinks that Norfolk Southern employee Ms. Blair’s testimony

points the other way, but it does not. Ms. Blair stated that “Norfolk Southern would not

have abandoned the Line” absent the 2019 NITU and instead waited for the next

“advantageous” opportunity to dispose of the Corridor. Blair Decl. at 2. The only

concrete advantageous opportunity the Court can identify is an offer from future

potential trail sponsors. Ms. Blair or the government do not point to any other type of

opportunity. In other words, far from providing special proof that this case is

exceptional, her testimony merely confirms that Norfolk Southern would have

abandoned its ROW but for the Trails Act. 21

21

Nothing in this decision should be taken to mean that a successful Trails Act conversion, in and

of itself, ends the causation inquiry. In a recent case with unusual facts, Hardy v. United States, the

government supplied the special proof needed and persuaded our Court that the railroad would not have

abandoned a segment of a rail corridor even absent the Trails Act.

In Hardy, the railroad and the sponsor successfully negotiated an ITUR agreement but

discovered three years later that the railroad’s notice of exemption and the NITU had “improperly

described the location of milepost E-65.80,” which marked one end of the ITUR corridor. 965 F.3d

1338, 1342 (Fed. Cir. 2020). Upon being notified of the error, the STB vacated the initial NITU as to

the segment between the supposed location and the real location of the milepost. Id. When landowners

sued for a temporary taking of that segment, the Federal Circuit held that the appropriate inquiry was

whether “the Railroad would have abandoned [the segment included in error] absent the NITU,” and

remanded the case for an evidentiary determination. Id. On remand, the government presented

compelling evidence that the case presented the “rare situation” where the railroad had made a

“mistake,” and that the railroad’s actions after the NITU was originally issued “actively contradicted”

any indication of an intent to abandon the line. Hardy v. United States, 153 Fed. Cl. 287, 296 (2021).

In particular, the Court found it significant that when the railroad filed its notice of exemption, it also

had “active leases” on the segment, made “steady improvements” to it, and even tried to negotiate a

“decades-long lease” to operate rail services on the segment. Id. In other words, the government

prevailed precisely because it was able to prove that the disputed portion was not the sort of “money-

losing line[]” that railroads have an incentive to abandon. Preseault II, 66 F.3d at 1183.

- 36 -

4. Summing Up

Based on a comparison of the “but-for” and “after” condition, the Court

concludes that government took an exclusive ITUR easement in the corridor depicted in

the Survey Map.

***

One final point. The government suggests that the reading adopted by the Court

fails to offset the government’s liability by the benefits—the “boon”—that property

owners may yet reap because of proximity to “the City’s planned greenway extensions.”

Def.’s Post-Tr. Br. at 4. That assertion misunderstands the federal government’s role.

At least in this case, greenway development in the Corridor is not attributable to federal

intervention.

The federal government gets the credit for trail-creation when the trail would not

have been built for the Trails Act. For example, if the rail corridor will be “lost

irretrievably” 22 (through fragmentation) upon abandonment, the Trails Act can properly

be treated as the reason for the creation of the trail. Here, however, the record shows

that abandonment would likely have resulted in the creation of a trail, just as it did

north of the Corridor. In fact, the City appears to have preferred a post-abandonment

conversion to a Trails Act conversion. All the STB did was impede the City’s designs

by handing Norfolk Southern a veto over trail creation. Granted, forcing sponsors to

railbank serves the public’s interest in preserving our Nation’s rail network, but the fact

remains that had the City been free not to take the Trails Act route, the greenway may

well have been built earlier and on a smaller budget, with the City and property owners

agreeing to tailor the boundaries to accommodate neighboring developments. It is for

those harms—which arise not from greenway development as such, but from the federal

government handing railroads the ability and incentive to foreclose the post-

abandonment option—that just compensation is owed.

B. Valuation

The Court now turns to the quantum of compensation. As noted previously, only

plaintiffs’ expert Dr. Kilpatrick provided opinions of value. The Court finds his

methodology and conclusions credible, except for his opinion that just compensation

includes the cost of building privacy walls.

1. Legal Standard

Just compensation equals the “fair market value” of the property assuming that it

is put to its highest and best use. Olson v. United States, 292 U.S. 246, 255 (1934); see

also Rasmuson v. United States, 807 F.3d 1343, 1346 n.1 (Fed. Cir. 2015). The Court’s

22

Jeffrey Alan Bandini, The Acquisition, Abandonment, and Preservation of Rail Corridors in

North Carolina: A Historical Review and Contemporary Analysis, 75 N.C. L. Rev. 1989, 1990 (1997).

- 37 -

objective is to make property owners whole—no less and no more. See United States v.

564.54 Acres of Land, 441 U.S. 506, 516 (1979).

The fair market value for the taking of an easement is determined using the

“before-and-after method” (the “Federal Rule”), which is “the difference between the

value of the property before and after the Government’s easement was imposed.”

McCann Holdings, Ltd. v. United States, 111 Fed. Cl. 608, 614 (2013) (quoting Otay

Mesa, 670 F.3d at 1364). In all events, the plaintiff bears the burden of demonstrating

the quantum of compensation owed “with reasonable certainty, which requires more

than a guess, but less than absolute exactness.” Gadsden Indus. Park, LLC v. United

States, 956 F.3d 1362, 1371 (Fed. Cir. 2020) (internal quotation marks and alterations

omitted). A plaintiff meets its burden when it presents “credible market evidence

combined with accurate factual and legal assertions.” Agapion v. United States, 167

Fed. Cl. 761, 774 (2023).

For the taking of an easement, just compensation includes “severance damages,”

which is the “diminution in value of the owner’s remaining property.” Childers v.

United States, 116 Fed. Cl. 486, 497 (2013) (citation omitted); Uniform Appraisal

Standards for Federal Land Acquisitions § 1.7.1.1 (6th ed. 2016) [hereinafter “Yellow

Book”]. The government may pay the cost to cure in lieu of the diminution in value if

the cost to cure is less than the diminution. McCann Holdings, 111 Fed. Cl. at 614.

2. Calculation of Compensable Damages

As discussed previously, Dr. Kilpatrick calculated just compensation for each

parcel as the sum of (1) the difference between the “before” and “after” value of the

entire parcel, and (2) the cost of building a privacy wall between the ITUR easement

and the remainder of the parcel. The Court concludes that Dr. Kilpatrick improperly

added the cost of building a privacy wall, but that his conclusions are otherwise

reliable.

a. The property owners are not entitled to recover the cost

of building a privacy wall in this case.

The Court will disregard the cost of building a privacy wall. The before-and-

after difference in market value is presumed to account for privacy-related harms and

Dr. Kilpatrick did not attempt to rebut the presumption. The Court reaches this

conclusion for the reasons stated in Agapion. 167 Fed. Cl. at 776–79. In that case, Dr.

Kilpatrick used the same methodology, and the parties’ briefs made the same arguments

for and against including the additional component in the just compensation amount.

b. Dr. Kilpatrick’s estimates of the before and after values

are credible and methodologically sound.

The Court next turns to Dr. Kilpatrick’s valuation of the subject properties in

their before and after conditions. Dr. Kilpatrick submitted a separate report for each

- 38 -

subject property, JX5–JX17, and later submitted an erratum correcting some of his

reports, PX82. He estimated the value of the parcels using the income approach, sales

comparison approach, and cost approach, and then arrived at his opinion of the “before”

value by reconciling the results of the three approaches. E.g., JX5 at 28–39.

His method for estimating the after value varied depending on the effect of the

taking on the remainder of the parcel. For parcels where there was “no physically

possible use of the remainder,” such as the Take 5 Oil property, he concluded that the

after value was $0. Id. at 44. For parcels where the taking led to “loss of functionality

of the remainder”—for example, the remainder of the Midtown Financial property was

downgraded from a “Class A” to “Class B” commercial property—Dr. Kilpatrick first

estimated the “after” value of the remainder by using one or more of the income

approach, sales comparison approach, and cost approach. JX16 at 41–44. He then

calculated the just compensation amount by adding the value of the easement taken to

the diminution in value of the remainder. Id. at 44. Finally, for parcels where the

taking did not diminish the desirability of the remainder, such as the Texas Roadhouse

property, he calculated the value of the easement taken by multiplying the area of the

taking with the per-square-foot value of the parcel in the “before” condition. JX6 at 47.

The government’s expert, Mr. Stephen Roach, submitted a rebuttal report

asserting that Dr. Kilpatrick’s methodology is inconsistent with standard appraisal

practices and his conclusions are not credible. DX44. Relying on the report, the

government argues that the Court should disregard Dr. Kilpatrick’s opinion because it is

not based on “‘sufficient facts or data’” and does not apply “‘reliable principles and

methods.’” Def.’s Post-Tr. Br. at 8 (quoting Fed. R. Evid. 702(b)–(d)).

The Court is unpersuaded. In his report, Mr. Roach raises a host of objections,

including “theory errors, methodology errors, data errors, and inconsistencies.” DX44

at 108. The Court has studied the entire report carefully. In the interest of conciseness,

this opinion addresses only those objections that the government highlighted in its post-

trial brief.

Defendant first argues that Dr. Kilpatrick’s valuation estimates based on the

income approach are unreliable, because he derived the capitalization rate from a

national survey, the CBRE National Cap Rate Survey for the second half of 2019.

Def.’s Post-Tr. Br. at 9; DX44 at 33–34. According to the defendant, Dr. Kilpatrick

should instead have “market support” for his estimates using local market data, or at

least relied on a national survey that specifically surveyed the Greensboro market. Id.

(citing Yellow Book § 1.5.4).

The Court finds that Dr. Kilpatrick’s methodology was sound. It is reasonable

for expert appraisers to rely solely on survey data to estimate the capitalization rate.

For example, in Hardy, both the plaintiffs’ and the government’s appraisers derived the

capitalization rate based solely on a national survey (Realty Rates), and the Court found

that “it was reasonable for the experts to rely on Realty Rates data.” 141 Fed. Cl. at 60.

Similarly, in Franconia Associations v. United States, both experts relied on another

- 39 -

national survey (the Korpacz Real Estate Survey) without any objection from the Court.

61 Fed. Cl. 718, 765–66 (2004). Further, in both cases, the national surveys appear not

to have specifically surveyed the township where the taking occurred. That is

unsurprising, because the whole point of national surveys is to identify trends that can

plausibly be extrapolated to towns and cities not surveyed. 23

Second, turning to the sales comparison approach, defendant argues that Dr.

Kilpatrick erred by “ignor[ing] recent [pre-NITU] sales of three subject properties” and

choosing comparables of a “completely different character” than the subject property.

Def. Post-Tr. Br. at 9–10; DX44 at 22–25.

The Court rejects the first argument because it incorrectly presumes that the sale

price prior to the issuance of the NITU—when the subject properties were encumbered

by the railroad ROW—is relevant to the valuation exercise. As the Court has already

explained at length, it is not. The state of the tract “before” and “after” the taking is

unencumbered fee title and title encumbered by the ITUR easement, respectively. For

the second argument, defendant points to the Take 5 Oil property, noting correctly that

none of Dr. Kilpatrick’s chosen comparable properties house an oil-change facility.

Def.’s Post-Tr. Br. at 10; DX44 at 24. But when an appraiser concludes that the highest

and best use of a property differs from its existing use, he must account for that

difference when choosing comparable properties. See Bd. of Cnty. Sup’rs of Prince

William Cnty., Va. v. United States, 116 F.3d 454, 457 (Fed. Cir. 1997) (“[The property

owner] is entitled to the value that the [subject property] would command in the open

market in light of the highest and most profitable use to which the acreage might

reasonably be devoted in the near future.”). That is the case here. Dr. Kilpatrick

reasonably determined that the property is clearly adaptable for use as street-front

retail, JX5 at 7, and properly chose comparable properties accordingly. 24

Finally, defendant argues that Dr. Kilpatrick erred by excluding post-NITU sales

in the Greensboro market. The Court rejects that argument for the reasons articulated

in the Agapion case. 167 Fed. Cl. at 778–79.

C. The Court’s Just-Compensation Findings

After considering the totality of the record, the Court concludes as follows.

1. Taking

The Court adopts the difference between Dr. Kilpatrick’s before- and after-

value findings as the just compensation owed to the plaintiffs. The allocation of

compensation (before interest) is:

23

Defendant also asserts that Dr. Kilpatrick ignored “the subject properties’ actual rental history.” Def.’s

Post-Tr. Br. at 9; DX44 at 30–32. That is factually incorrect. For example, he used the actual rent of the Core Life

property while calculating its value under the income approach. JX7 at 37.

24

Defendant also raises errors that Dr. Kilpatrick corrected of his own accord. Def.’s Post-Tr. Br. at 10;

PX82. The Court does not find them relevant to the assessment of his credibility.

- 40 -