Opinion

Govwave, LLC v. United States

Court
United States Court of Federal Claims
Filed
Feb 27, 2025
Status
Published
On the bench
Marian Blank Horn
Cited by
0 cases
Authority
More cited than 34.3%

discussing duty to verify bids under FAR Part 14

How later courts described this case

  • discussing duty to verify bids under FAR Part 14
  • “Bid protest actions are subject to the standard of review established under section 706 of title 5 of the Administrative Procedure Act (‘APA’
  • “Under FAR 52.212-1(g), the Government may waive “informalities and minor irregularities.’”
  • “Following passage of the APA in 1946, the District of Columbia Circuit in Scanwell Labs., Inc. v. Shaffer, 424 F.2d 859 (D.C. Cir. 1970

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

Nos. 24-172C; 24-406C; 24-446C; 24-448C; 24-461C; 24-467C; 24-471C

Filed: February 3, 2025

Redacted Version Issued for Publication: February 27, 20251

* * * * * * * * * * * * * * * * *

*

GOVWAVE, LLC, et al., *

*

*

Protestors,

*

v. *

*

UNITED STATES,

*

Defendant.

*

* * * * * * * * * * * * * * * * **

Eric Valle and Jonathan Williams, PilieroMazza PLLC, Washington, DC, for

protestor GovWave, LLC.

Taylor Holt and Emily Chancey, Maynard Nexsen PC, Huntsville, AL, for

protestor Futron, Inc.

Kathy Potter and Sharon Roach, Potter & Murdock, P.C., Washington, DC, for

protestor Government Acquisitions, Inc.

John Tolle, Baker, Cronogue, Tolle & Werfel, LLP, McLean, VA, for protestor DH

Technologies, Inc.

Nicole Pottroff and Greg Weber, Koprince McCall Pottroff LLC, Lawrence, KS,

for protestor Enterprise Technology Solutions, Inc.

Matthew Long, Moore & Lee, McLean, VA, for protestor Unicom Government, Inc.

Olivia Lynch and Emily Golchini, Crowell & Moring LLP, Washington, DC, for

protestor Advanced Computer Concepts, Inc.

Kristin Olson, Department of Justice, Commercial Litigation Branch, Civil

Division, Washington, DC, for defendant. With her were Miles J. Wright, Trial Attorney,

1 This Opinion was issued under seal on February 3, 2025. The parties were asked to

propose redactions prior to public release of the Opinion. This Opinion is issued with the

some of the redactions that the parties proposed in response to the court’s request. Words

which are redacted are reflected with the notation: “[redacted].”

Commercial Litigation Branch, Isabelle Aubrun, Trial Attorney, Commercial Litigation

Branch, Corinne A. Niosi, Assistant Director, Commercial Litigation Branch, Patricia M.

McCarthy, Director, Commercial Litigation Branch, and Brett A. Shumate, Acting

Assistant Attorney General, Civil Division. Of counsel Maj. James Kim and Maj. Joshua

Fix, Trial Attorneys, Contract Litigation & Intellectual Property Division, U.S. Army Legal

Services Agency, Fort Belvoir, VA, and Alex M. Cahill, Attorney-Advisor, Army Materiel

Command Legal Center-Rock Island Arsenal, Rock Island, IL.

OPINION

HORN, J.

Protestors GovWave, LLC (GovWave), Futron, Inc. (Futron), Government

Acquisitions, Inc. (Government Acquisitions), DH Technologies, Inc. (DH Technologies),

Enterprise Technology Solutions, Inc. (Enterprise Technology Solutions) Unicom

Government, Inc. (Unicom), and Advanced Computer Concepts, Inc. (Advanced

Computer Concepts) each filed pre-award bid protests in the United States Court of

Federal Claims challenging the decision of the Department of the Army, Army Contracting

Command – Rock Island (Army) to exclude the protestors’ offers in response to

Solicitation W52P1J-20-R-0082 (the Solicitation).2 Each of the seven protestors were

eliminated from the competition for failing to comply with the Army’s “strict compliance

requirements” during Step 1 of the evaluation process.

FINDINGS OF FACT

The Army’s April 15, 2021 Acquisition Plan related to the Solicitation at issue in the

above captioned protests explains:

This acquisition is a follow-on to the Information Technology Enterprise

Solutions-3 Hardware (ITES-3H) Multiple Award Indefinite Delivery

Indefinite Quantity (IDIQ) contracts awarded in February 2016. The purpose

of this acquisition is to support Army, Department of Defense (DoD) and all

Federal Agency Information Technology (IT) infrastructure and infostructure

goals with a full range Commercial Off-The-Shelf (COTS) hardware and

related incidental software and services that meet the definition in Federal

Acquisition Regulation (FAR) 2.101, Definitions, for “commercial items.”

Army Contracting Command – Rock Island (ACC-RI), in support of CHESS

[Computer Hardware, Enterprise Software and Solutions], intends to award

2 The court notes that although the agency has not yet made awards under the

Solicitation, and, therefore, the protestors cannot protest an award decision to another

offeror or offerors in a post-award bid protest, at this time, unlike a pre-award protest in

which offerors challenge the Solicitation itself, the seven protestors have been evaluated,

at the first step of a three step evaluation procedure for the procurement established by

the agency, and eliminated from the competition by the agency for non-compliance.

2

at least 17 Firm Fixed Price (FFP) IDIQ contracts, with up to 7 awards

reserved for small business. The ITES-4H ceiling is $10,000,000,000.00

with a five-year base period and one five-year option period. Ordering will

be decentralized and open to all DoD and Federal Agencies. The IDIQs will

allow the Government to realize cost savings, provide visibility and oversight

through contractor reporting and analysis of CHESS IT e-Mart data, and

streamline the acquisition process.

(capitalization in original; alteration added).3 The April 15, 2021 Acquisition Plan

continued:

The intention of this acquisition is to integrate, modernize and refresh the

existing IT equipment for client, server, storage, and network environments

while providing standardized interfaces. The acquisition provides an

ordering vehicle for authorized users to meet equipment requirements. The

contractors will be required to perform in a fully responsive, complete and

flexible manner over the entire contract life, recognizing the dynamic nature

of the IT environment: changes in the requirements of users, standards,

regulations, and technology, as well as the various commercial alternatives

available for purchase, leasing and licensing.

The Solicitation, as amended, projects evaluating offers in three separate steps in

order to make a best value award. The Solicitation provides:

EVALUATION FACTORS FOR AWARD

M.1 BASIS FOR CONTRACT AWARD

The awards will be made based on the best overall (i.e., best value)

proposals that are determined to be the most beneficial to the Government,

with appropriate consideration given to the four evaluation factors:

3 As explained on the Army’s website:

Computer Hardware, Enterprise Software and Solutions (CHESS) is the

Army’s designated primary source for commercial IT. CHESS provides a

no-fee, flexible procurement strategy through which an Army user may

procure commercial-off-the-shelf (COTS) IT hardware, software, and

services via an e-commerce (IT e-mart) based process. CHESS offers

simple, straightforward contract vehicles through its online Army e-

commerce ordering system, the IT e-mart (https://chess.army.mil). These

contracts provide continuous vendor competition for best value and

consolidation of requirements to maximize cost avoidance and leverage the

Army’s buying power.

https://www.eis.army.mil/programs/chess (last visited Feb. 27, 2025).

3

Technical Factor, Price, Past Performance, and Small Business

Participation. In the evaluation, the technical factor is more important than

the Past Performance factor and the past performance factor is more

important than Small Business Participation. All non-priced factors

combined are significantly more important than Price. Although Price is not

the most important factor, the closer the ratings in the non-price factors, the

more significant price becomes. The Government will perform a trade-off

analysis of the non-priced factors with price to select the best value

proposals that provide the best value to the Government. To receive

consideration for award, a rating of no less than Acceptable must be

achieved for the technical factor (to include each subfactor) and the Small

Business Participation factor. Additionally, any Other Than Small Business

Offeror must have an acceptable Small Business Subcontracting Plan to

receive an award in accordance with FAR 19.702(a). Offerors are cautioned

that awards may not be made to the lowest priced proposal. An award will

not be made to any Offeror with a deficiency in any factor.

M.2 NUMBER OF CONTRACT AWARDS

The Government intends to award at least 17 Firm Fixed Price (FFP),

Indefinite Delivery, Indefinite Quantity (IDIQ) type contracts as a result of

this solicitation. Each contract will have a base period of 5 years, with one

available 5-year option period.

i. The Government will first reserve an anticipated seven awards for small

businesses. The Government will select these small business awardees

based on a trade-off analysis of all factors, including price, to select the

small business Offerors who represent the best value to the Government.

ii. Next, the Government will consider all remaining Offerors, without regard

to size status, to make the remaining awards. The Government anticipates

making at least 10 additional awards to the remaining Offerors without

consideration of size status. These Offerors will be selected on a trade-off

analysis of all factors, including price, to select the Offerors who represent

the best value to the Government.

M.3 EVALUATION METHODOLOGY

This is a competitive best value source selection in which competing

Offerors will be evaluated against four evaluation factors: Technical, Price,

Past Performance, and Small Business Participation. The contract award

decisions will be determined based upon the evaluation of each Offeror's

complete proposal against the evaluation criteria identified below. Selection

of awardees will be accomplished as follows:

4

Step 1 - STRICT COMPLIANCE REQUIREMENT: Proposals will be

reviewed to determine if all compliance requirements set forth in the

Instructions to Offerors are satisfied. Failure to provide proposals in

compliance with the instructions specified as STRICT COMPLIANCE

REQUIREMENTS in the Instructions to Offerors of this RFP [Solicitation]

shall render the Offerors proposal [sic4] non-compliant. Any Offeror’s

proposal determined non-compliant will not be evaluated and will not be

further considered for award. Only Offerors whose proposals are

determined compliant will move to Step 2 of the evaluation process.

Step 2 - Review of Part A - Equipment List: The Offerors Equipment List will

be evaluated on an Acceptable/Unacceptable basis. To determine technical

acceptability, the Government will evaluate an Offerors Equipment List

using statistical sampling. In this regard, the Government will evaluate a

percentage of the proposed items in the Equipment List (i.e., the statistical

sample) to determine if the Offerors proposed Equipment List meets the

Governments minimum requirements indicated in Column C of Attachment

0002.[5] All Offerors Equipment Lists will be evaluated for the same items

4 The Army in the Solicitation and evaluation documents consistently and incorrectly uses

the phrase “the Offerors proposal.” The court does not add a “[sic]” after each

grammatically incorrect use of the phrase “the Offerors proposal” going forward in the

Opinion.

5 The Solicitation included a list of attachments to the Solicitation:

5

as part of the statistical sample. In the context of this evaluation, Acceptable

is defined as the Government determining that all items evaluated in the

statistical sample meet or exceed the Governments minimum requirements

as identified in Column C of Attachment 0002. Unacceptable is defined as

the Government determining through statistical sampling that the Offerors

Equipment List does not meet the minimum requirements identified in

Column C of Attachment 0002. If the Government determines through

statistical sampling that an Offeror does not meet a minimum requirement

identified in Column C of Attachment 0002, the Government will not further

evaluate the Offerors Equipment List and the statistical sampling evaluation

will stop. The Offerors proposal will be deemed Unacceptable and will not

proceed to Step 3.

Step 3 - Evaluation of Part B - Technical, Past Performance, Price and

Small Business Participation proposals: The Government intends to

evaluate proposals and may conduct discussions. If discussions are

determined to be necessary by the Government, a Competitive Range

consisting of the most highly rated proposals based on the Technical Part

B, Past Performance, Price and Small Business Factors will be established.

The Government may engage in Communications under FAR 15.306(b) as

necessary to determine which Offerors should be included in the

Competitive Range. The Competitive Range, if necessary, will be

established considering the Governments intent to make seven awards to

small businesses, and thereafter make at least 10 unrestricted awards to all

remaining Offerors. Any proposal, which does not have a realistic chance

of receiving award, will not be included in the Competitive Range.

Relevant to the above captioned protests, Attachment 0005 was removed by Amendment

0029. Attachment 0005 was titled: “Price Model - Option Period - Five Year,” and the

Solicitation explained

Attachment 0004 - Price Model - Base Period - 5 Years. Attachment 0004

has been revised to include a tab at the bottom for Option Period pricing

input, in lieu of separate documents for the base period and option periods.

Offerors are required to utilize this revised Price Model for their proposal

submission. Failure to utilize the revised Price Model will deem the Offerors

submission noncompliant and will receive no further evaluation or eligibility

for award. . . .

b. Delete the following attachments in their entirety:

i. Attachment 0005 - Price Model - Option Period - Five Years, Attachment

0005 has been deleted in its entirety as a result of the revisions made to

Attachment 0004.

(omission added).

6

M.4 DISCUSSIONS

a. After receipt of proposals, the Government will conduct an evaluation.

During the conduct of this acquisition, the Acquisition Source Selection

Interactive Support Tool (ASSIST) will be used by the Government to

support the proposal evaluation and source selection process. A separate

tool, the ASSIST2Industry, will be used in conjunction with ASSIST to

facilitate exchanges with Offerors after receipt of proposals pursuant to FAR

15.306.

(capitalization in original; emphasis, alterations and footnotes added). The Solicitation

continued:

M.5 EVALUATION FACTORS

The following evaluation factors and subfactors will be used to evaluate

each proposal. Awards will be made to the Offerors whose proposals are

most advantageous to the Government based upon an integrated

assessment of the evaluation factors and subfactors described below.

FACTOR 1: Technical Factor is divided into the following:

PART A - Equipment List (Acceptable/Non-Acceptable as evaluated at Step

2)

PART B - Technical Narrative (Overall Adjectival Rating)

SUBFACTOR 1 - Compliant IT Equipment (Adjectival Rating)

KEY POINT #1 - Compliant Solutions

KEY POINT #2 - Catalog Management

KEY POINT #3 - Technical Migration Management

SUBFACTOR 2 - Quality Programs (Adjectival Rating)

KEY POINT #1 - Quality Qualifications

KEY POINT #2 - Quality Methodology

KEY POINT #3 - Supply Chain Risk Management (SCRM)

KEY POINT #4 - Contract Management

7

Factor 2: Price (No Rating Assigned)

Factor 3: Past Performance (Relevancy/Confidence Rating)

Factor 4: Small Business Participation (Adjectival Rating; applies only to

Other than Small Business).

M.6 RELATIVE IMPORTANCE

Factor 1: Technical is the most important factor. An overall Technical Part

B factor rating will be assigned to each Offeror. Within Part B Technical

Narrative, Subfactor 1 - Compliant IT Equipment is more important than

Subfactor 2 - Quality Programs. Within Subfactor 1, all key points are of

equal importance. Within Subfactor 2, all key points are of equal

importance. Factor 1 – Technical Part B is significantly more important that

Price, Past Performance and Small Business Participation.

The past performance factor is more important than Small Business

Participation. All non-priced factors combined are significantly more

important than Price. Although Price is not the most important factor, the

closer the ratings in the non-price factors, the more significant price

becomes. The Government will perform a trade-off analysis of the non-

priced factors with price to select the best value proposals that provide the

best value to the government.

M.7 EVALUATION RATINGS

M.7.1 Ratings for Technical Evaluation Part A

Table 1 Technical Acceptable/Non-acceptable Ratings (Part A)

Adjectival Rating Description

Acceptable The Government determining that all

items evaluated in the statistical sample

meet or exceed the Governments

minimum requirements as identified in

Column C of Attachment 0002.

Non-Acceptable The Government determining through

statistical sampling that the Offerors

Equipment List does not meet the

minimum requirements identified in

Column C of Attachment 0002.

M.7.2 Ratings for Technical Evaluation Part B

8

Table 2 Combined Technical/Risk Ratings (Part B)

Adjectival Rating Description

Outstanding Proposal indicates an exceptional

approach and understanding of the

requirements and contains multiple

strengths, and risk of unsuccessful

performance is low.

Good Proposal indicates a thorough approach

and understanding of the requirements

and contains at least one strength, and

risk of unsuccessful performance is low

to moderate.

Acceptable Proposal meets requirements and

indicates an adequate approach and

understanding of the requirements, and

risk of unsuccessful performance is no

worse than moderate.

Marginal Proposal has not demonstrated an

adequate approach and understanding

of the requirements, and/or risk of

unsuccessful performance is high.

Unacceptable Proposal does not meet requirements of

the solicitation, and thus, contains one or

more deficiencies, and/or risk of

unsuccessful performance is

unacceptable. Proposal is unawardable.

In accordance with the Army Source Selection Supplement (28 November 2017),

Section 3.1, the Army methodology for evaluating Technical Approach and Related

Risk is the Combined Technical/Risk Rating, (see Table 1 above). This

methodology considers risk, in conjunction with the significant strengths, strengths,

weaknesses, significant weaknesses, uncertainties, and deficiencies in

determining technical ratings.

M.7.3 Relevancy Ratings for Past Performance Evaluation

9

Table 3 Past Performance Relevancy Ratings

Rating Definition

Very Relevant

Present/Past Performance effort that has a

value of at least $2,000,000.00 with delivery of

items that correspond to four (4) or more of the

ITES-4H catalogs.

Relevant Present/Past Performance effort that has a

value of at least $1,000,000.00 with delivery of

items that correspond to three (3) or more of the

ITES-4H catalogs.

Somewhat Relevant Present/Past Performance effort that has a

value of at least $250,000.00 with delivery of

items that correspond to two (2) or more of the

ITES-4H catalogs.

Not Relevant Present/Past Performance effort that has a

value of $249,999.99 or less with delivery of

items that correspond to one (1) or less of the

ITES-4H catalogs.

M.7.4 Confidence Ratings for Past Performance Evaluation

Table 4 Past Performance Confidence

Adjectival Rating Definition

Substantial Confidence Based on the Offerors recent/relevant

performance record, the Government

has a high expectation that the Offeror

will successfully perform the required

effort.

Satisfactory Confidence Based on the Offerors recent/relevant

performance record, the Government

has a reasonable expectation that the

Offeror will successfully perform the

required effort.

Limited Confidence Based on the Offerors recent/relevant

performance record, the Government

has a low expectation that the Offeror will

successfully perform the required effort.

10

No Confidence Based on the Offerors recent/relevant

performance record, the Government

has no expectation that the Offeror will be

able to successfully perform the required

effort.

Unknown (Neutral) Confidence No recent/relevant performance record is

available, or the Offerors performance

record is so sparse that no meaningful

confidence assessment rating can be

reasonably assigned. The Offeror may

not be evaluated favorably or unfavorably

on the factor of past performance.

M.7.5 Adjectival Ratings for Small Business Participation Evaluation

Table 5 Small Business Participation Ratings

Rating Description

Outstanding Proposal indicates an exceptional

approach and understanding of the small

business objectives.

Good Proposal indicates a thorough approach

and understanding of the small business

objectives.

Acceptable Proposal indicates an adequate

approach and understanding of the small

business objectives.

Marginal Proposal has not demonstrated an

adequate approach and understanding

of the small business objectives.

Unacceptable Proposal does not meet small business

objectives.

(capitalization and emphasis in original).

In the instructions to offerors, the Solicitation stated:

INSTRUCTIONS TO OFFERORS

11

L.1 OVERVIEW

The Army is conducting the ITES-4H competition in order to enter into

contracts to acquire the information technology required to meet the Armys

[sic] information technology mission.

The U.S. Army Computer Hardware, Enterprise Software and Solutions

(CHESS) in coordination with the Army Contracting Command Rock Island

(ACC-RI), requires contracts to support the Armys [sic] requirements both

Continental United States (CONUS) and Outside the Continental United

States (OCONUS), including remote OCONUS, covering a full range of

Information Technology (IT) equipment for client, server, storage, and

network environments; for related incidental services and software; for

maintenance/warranty of legacy IT equipment; and for warranty variations

as part of an Information Technology Enterprise Solutions 4 Hardware

(ITES-4H) solution. The equipment and services shall be commercial in

accordance with the definition of commercial items in Federal Acquisition

Regulation (FAR) 2.101.

L.2 PROPOSAL SUBMISSION REQUIREMENTS

a. Each Offeror shall submit only one comprehensive and complete

proposal, which consists of all required information with associated

attachments each in their appropriate file formats, that addresses all

Government requirements outlined in the solicitation. Submission of a

proposal shall be on an all or none basis. Partial proposals are not

acceptable and shall not be evaluated. If the Government has not received

the Offerors proposal by the due date and time, the proposal will be

considered incomplete and will not be further considered for award.

(capitalization in original; alterations added). The Solicitation continued:

L.3 STRICT COMPLIANCE REQUIREMENT

All volumes and files have strict compliance requirements and strict

compliance to those requirements will be evaluated. Any items identified as

a STRICT COMPLIANCE REQUIREMENT will be evaluated for compliance

prior to any further evaluation of the Offerors proposal. Failure to abide by

the strict compliance requirements for any of these factors will deem the

Offerors proposal non-compliant and will eliminate it from further

consideration. Factors and subfactors with strict compliance requirements

are clearly identified throughout these instructions.

(capitalization in original).

Regarding the format of the offerors’ proposals, the Solicitation explained:

12

L.4 PROPOSAL FORMAT

This section specifies the format each Offeror shall use in preparing its

proposal. The intent is not to restrict the manner in which proposals are

prepared, but rather to ensure a certain degree of uniformity in proposal

format for evaluation purposes. The proposal shall be prepared in a clear,

legible, practical manner. Five separate volumes shall be submitted. These

volumes shall be self-contained and shall not be cross-referenced. The

Government will not assume the duty to search for data or information to

cure problems discovered in any proposal submitted.

...

L.4.1.2 Each Offeror shall submit ONLY one proposal and that proposal

shall address all of the requirements of the Request for Proposals (RFP).

To be considered for this requirement, the Offeror must submit a complete

response to this RFP using the instructions provided in Section L. STRICT

COMPLIANCE REQUIREMENT: If the Offeror’s proposal fails to meet the

terms and conditions of the RFP or takes exception to any of the terms and

conditions of the RFP, it will render the Offeror’s proposal unacceptable and

will not be further considered for award.

L.4.1.2 (a) Each Offeror shall submit the most current versions of

Attachments 0002, 0004, 0006, 0007 and 0013 required for this RFP. The

Government will verify that the Offerors submission contains the most

current RFP Attachments 0002, 0004, 0006, 0007 and 0013 that were

provided by email with this Amendment.

L.4.1.2 (b) STRICT COMPLIANCE REQUIREMENT: Failure to provide the

most current versions of the RFP Attachments 0002, 0004, 0006, 0007 and

0013 shall render the Offerors proposal non-compliant and will not be

further considered for award. To be considered for award the Offeror must

submit a response to this solicitation in full to include the most recent

attachments provided.

L.4.1.3 A proposal is presumed to represent the Offerors best efforts to

respond to the RFP. The Offeror must provide adequately detailed

information that complies with the solicitation requirements, allows for

meaningful review by the Government evaluators, and affirmatively

demonstrates the merits of its proposal. The Offeror shall provide sufficient

detail to substantiate the validity of all stated assertions and must not merely

repeat the RFP requirements, but rather must provide convincing

documentary evidence of how contract requirements will be met. Data not

submitted with the proposal, but submitted previously, or presumed to be

known (i.e., previous projects performed for the United States Government

(USG)) will not be considered. Clarity and completeness are essential.

13

(capitalization in original; omission added).

Regarding the Technical Factor, the Solicitation provided:

L.5 SPECIFIC PROPOSAL INSTRUCTIONS

L.5.1 VOLUME I - Technical Factor. The volume shall be organized into the

following sections:

L.5.1.1 PART A - Equipment List. STRICT COMPLIANCE REQUIREMENT:

ANY cells marked for Contractor Fill-In on the Equipment List that are left

blank or are unintelligible as to the product the Offeror is proposing shall

render the Offerors proposal non-compliant and will not be further

considered for award.

This portion of the proposal shall include a completed Equipment List

spreadsheet (Attachment 0002) considering the following instructions:

a. The Offerors proposed configuration for each, and every System

Description identified on each Catalog (Catalog I through Catalog VII); The

Offeror shall complete the Equipment List at Attachment 0002 by providing,

in the proposed configuration column, its proposed item to meet each

requirement; and

b. An Offerors annotation with technical detail identifying that every

Requirement related to each System Description in the proposed

configuration is met or exceeded as to be confirmed by the Government. All

proposed configuration cells must contain content for the Offerors proposal

to receive consideration. STRICT COMPLIANCE REQUIREMENT: Cells

that contain linked content are non-compliant. Additionally, modification of

the Equipment List outside of indicated proposed configuration inputs are

not permitted and will result in a proposal being determined non-compliant

and not further evaluated; and

c. An identification of each Offerors proposed configuration product

Description providing identification of (brand/model) within the Offerors

proposed configuration for each and every System Description; and

d. Each Catalog Identification per each Description (brand/model) and

every Platform addition, inclusive to aid in associating equipment list to price

models.

e. The Offeror may also complete the Catalog Identification column to

coordinate association between equipment list and price models. The

burden of proof that the proposed item meets or exceeds the minimum

requirements remains with the Offeror.

14

f. The minimum processor types are defined for Catalogs I and II. Offerors

may propose a different base processor if the Offeror provides proof that

the processor meets or exceeds the minimal architecture of the processor

listed in the Equipment List.

g. Equipment List, electronic copy: Equipment List must remain in native

MS Excel file format. Offerors proposed configuration information must be

directly input in the proposed configuration field. Equipment List must not

be password protected. Offeror proposed configuration input is only

permitted in column D. STRICT COMPLIANCE REQUIREMENTS: Failure

to provide the most current version of the RFP Attachment 0002 shall render

the Offerors proposal non-compliant and will not be further considered for

award. Unauthorized modifications to the Equipment List are not permitted

and will render an Offerors proposal non-compliant and not further

considered for evaluation. Linked inputs are not permissible and will render

a proposal non-compliant.

h. The items in the Price Model that refer to the hardware and their detailed

specifications are in the Equipment List (Attachment 0002). The pricing

proposed in the Price Model (Attachment 0004) shall be for the same

products and configurations proposed in the Equipment List (Attachment

0002). Any discrepancy between the product proposed in the Equipment

List vs. the product proposed and priced out in the Price Model may result

in an unfavorable finding in the Offerors proposal.

(capitalization in original). The Solicitation at L.5(c)-(d) provides:

c. Executed copies of all amendments. Each Offeror shall complete (fill-in

and sign) the solicitation amendment sections (Standard Form 30

AMENDMENT OF SOLICTIATION/MODIFICATION OF CONTRACT,

Contract Administration Data Representations, Clause fill-ins, Certification

and Other Statements of Offerors) using the file provided with the

solicitation amendment. An authorized official of the firm shall sign the SF

30s and all certifications requiring original signature. An Acrobat PDF file

shall be created to capture the signatures for submission.

d. Should an amendment be issued against the solicitation; the Offeror shall

acknowledge by signing one copy of the Standard Form (SF) 30 entitled

Amendment of Solicitation/Modification of Contract and include it in the

proposal submission. In Accordance With (IAW) FAR 52.215-1(b),

acknowledgement of solicitation amendments issued after the proposal due

date shall be submitted via email to usarmy.ria.acc.mbx.ites-4h-

rfp@army.mil no later than date and time identified in the Amendment.

(capitalization in original).

15

As the defendant explained in its omnibus cross-motion for judgment on the

Administrative Record for all of the above captioned bid protests:

The Equipment List is a product catalog of various items the Government

may purchase. The Equipment List contains seven catalogs and identifies

the various “Product Descriptions” the Army requires, along with a System

Description and the necessary “Minimum Requirement” for each system.

The Army completed Columns A, B and C with its pre-configured inputs.

The Army marked the top of Column D as “Proposed Configuration” and

marked the top of Column E as “Catalog Identification.”

(internal references omitted). Therefore, in order to comply with the strict compliance

requirement for the Equipment List under the Technical Factor at Step 1, an offeror would

have to complete each box for Column D and Column E.

Regarding Price, the Solicitation provided:

L.5.2 VOLUME II - Price Factor.

The volume shall be organized as follows:

(1) Electronic Copy. Price submission requirements: Files contained in the

Volume II Price submission may not be password protected. Electronic links

are not permissible. The Offeror shall not include pivot tables in Excel

spreadsheets. The Offeror shall complete the Price Model in full. Offerors

must ensure that Attachment 0004 is completed and submitted with the

proposals. STRICT COMPLIANCE REQUIREMENT: All cells contain an

appropriate value. Any cells marked as contractor fill-in that are blank or

unintelligible in Attachment 0004 will render the Offerors submission as non-

compliant and the Offerors proposal will receive no further consideration or

evaluation. Offerors intending to propose zero dollars for a particular cell

must ensure the appropriate cell contains a 0. The Government will not

assume a blank cell in Attachment 0004 represents a zero as any blank cell

will result in the Offerors proposal being deemed non-compliant and not

further considered for award.

(2) General Instructions. In accordance with FAR 15.402 and FAR 15.403-

1, certified cost or pricing data is not required based on the fact that

adequate competition is expected for this procurement. If after receipt of

proposals the Contracting Officer determines that there is insufficient

information available to determine price reasonableness, the Offeror may

be required to submit other than certified cost or pricing data. Information

other than certified cost or pricing data may be submitted in contractors

chosen format to provide sufficient information in order to support price

reasonableness. There are no page limitations for this volume. Proposal

information included in this volume that is not directly related to Price will be

16

disregarded. Proposed dollar values shall be identified in US Dollars with

only two decimal places. Any cells with more than two decimal places will

be rounded up or down to the next whole cent.

L.5.2.1 Instructions for the Price Model

a. A price must be proposed for every item in each catalog identified in the

Price Model. Proposed prices shall be for new items/equipment only.

b. DO NOT alter any part of the Price Model other than the cells shaded in

yellow and orange.

c. Do not enter any formulas into the Price Model.

d. Offerors shall completely fill out the updated Price Model (Attachment

0004) included with this Amendment. Failure to provide prices for all items

and catalogs identified in the Price Model of the solicitation will render the

Offeror ineligible for award. Further, all proposed prices and numbers shall

be stated in U.S. Dollars, rounded, and displayed to two decimal places. It

will be assumed that rows/columns containing zeros instead of prices are

intentional and shall be considered as having no cost to the Government.

e. Pricing for catalog items, as discounted, shall not exceed the Offerors

lowest available General Services Administration (GSA) Federal Supply

Schedule price, other Government contract vehicle price, commercial

catalog, or publicly published price list.

f. The Government anticipates receiving competitive proposals and using

competition to determine price reasonableness. The Government reserves

the right to request other than certified cost or pricing data to establish the

reasonableness of the proposed contract and/or subcontract prices after

receipt of proposals.

(capitalization in original).

Regarding Past Performance Factor, the Solicitation provided:

L.5.3 VOLUME III - Past Performance Factor. The Government will assess

the degree of confidence it has that the Offeror will successfully complete

the requirements in accordance with the contract terms based on the

Offerors demonstrated record of recent and relevant past performance.

Offerors shall provide a specific narrative explanation of each contract listed

in Section II of the past performance questionnaire describing the contract

requirements achieved and detailing how the effort is relevant to the

requirements of this solicitation.

17

L.5.3.1 Past Performance Contract References: The Offeror shall submit

with its initial proposal up to five contract references for itself. If the contract

reference the Offeror is submitting is an ordering type contractual vehicle

(e.g., an Indefinite Delivery “D” type contract, Blanket Purchase Agreement,

Basic Ordering Agreement, etc.), PPQ [Past Performance Questionnaire]

references are only acceptable after issuance of a delivery/task order where

performance is ongoing or has occurred.

a. Contract references may be provided for any combination of CONUS

and/or OCONUS locations.

b. The Government will only consider those references in which the Offeror

is identified as the Prime or First-tier subcontractor.

L.5.3.2 Specific Proposal Instructions. This volume shall be organized into

the following sections:

a. Contract Reference Information and ITES-4H PPQ POC List (Attachment

0013): The Government will not accept just the basic contract ordering

number for ordering type contractual vehicles. Given this, an individual

order (or orders) under the basic ordering contract vehicle must be

submitted in lieu of just the basic ordering contract itself. Each submitted

order shall be counted as one contract reference. For example, if an offeror

has performance on an IDIQ type contract, the Offeror must provide the

specific orders it desires the Government to evaluate. The Offeror must not

provide just the basic IDIQ contract number. All contract reference(s) shall

represent recent and relevant performance as a prime and/or first-tier

subcontractor under Government Agency contracts (i.e., Department of

Defense: Army, Navy, Air Force, Marine Corps, Defense Logistics Agency

(DLA) etc.; Federal, Department of Homeland Security, Department of

State, etc.). If submitting a reference as a first-tier subcontractor, Offeror is

expected to provide the name of the Prime contractor under which it worked.

If the Offeror has no Government Agency contracts, commercial references

may be provided. The recency period is 25 October 2019 through 16

October 2023. STRICT COMPLIANCE REQUIREMENT: The Offeror must

submit a completed ITES-4H PPQ POC List (Attachment 0013) of all the

POCs who received a questionnaire with the submission of the proposal.

Failure to provide a completed ITES-4H PPQ POC List will render the

proposal non-compliant and will not be further considered for award. The

past performance questionnaire (Attachment 0007) shall be used for each

contract reference submitted. The completed PPQs are excluded from the

page count for Past Performance.

b. Adverse Contract Performance: STRICT COMPLIANCE

REQUIREMENT: In addition to the contract references, the Offeror shall

identify any recent and relevant Government contract(s) it was awarded that

18

encountered any performance problems related to deliverables; services,

security violations (i.e. data, physical, virtual, etc.), Environmental

Protection Agency (EPA) violations, and every contract that was terminated

(termination for default or termination for cause only), in whole or in part

from 25 October 2019 through 16 October 2023. If there are no contracts

that meet the description above, the Offeror shall state as such and include

a statement in the Volume III of the proposal. The number of contract

references provided in response to this paragraph is unlimited. Submission

of Adverse Contract Performance information shall not count as part of the

page count for Past Performance.

For any contract falling under the Adverse Contract Performance

description above, provide all the information listed as follows:

1. Contract number and Order number.

2. Define the performance problem and/or Type of Termination or Breach.

3. Describe the performance problem that caused the adverse action,

termination, and/or breach.

4. Describe the corrective actions taken to resolve issues; and provide

date(s) of issue/resolution.

5. Provide a copy of any Letter of Concern, cure notice, or show cause

letters received.

6. Identify reasons for any Terminations for Default or Terminations for

Cause.

7. Describe in detail any performance problems that include

internal/external customer complaints and/or Contract Deficiency Reports

(CDRs), EPA violations.

8. Provide points of contact who can confirm the success of the corrective

measures to include email address and a valid telephone number.

The Government is under no obligation to search for additional past

performance references for any Offeror as the Government intends to

evaluate an Offerors past performance based on the information submitted

as part of an Offerors proposal. However, the Government reserves the

right to use data provided in the Offeror's proposal and data obtained from

other sources. To ensure inclusion of all references in the evaluation

process, the Offeror is encouraged to provide the Government with the most

current data on each reference.

(capitalization in original; alteration added).

Regarding the Small Business Participation Factor, the Solicitation provided:

L.5.4 VOLUME IV - Small Business Participation Factor. THIS

REQUIREMENT APPLIES TO OTHER THAN SMALL BUSINESS

OFFERORS ONLY. IAW 13 CFR 125.3(g), Small Business Offerors will be

given the maximum score, credit, or rating without having to submit any

19

information in connection with this factor. An Offeror is considered a Small

Business if it can certify Small Business status under North American

Industry Classification System (NAICS) 334111. STRICT COMPLIANCE

REQUIREMENT: Failure to submit Attachment 0006 will render the

Offeror's proposal non-compliant.

The Offeror shall demonstrate small business participation by detailing its

proposed approach to meet the requirements under this factor by

addressing the following two areas in its Small Business Participation

proposal:

a. Proposed Small Business Participation Commitment Document in

performance of the potential contract (applies only to Other Than Small

Businesses). The Offeror shall complete the Small Business Participation

Commitment Document at Attachment 0006 to show maximum practicable

opportunities to Small Businesses to compete on this requirement in

accordance with FAR 52.219-8, Utilization of Small Business concerns.

b. Commitment to Small Business:

i. Payment Procedures The Offeror shall include a written statement of its

established procedures to ensure timely payments to small business

subcontractors in accordance with FAR 52.219-8, Utilization of Small

Business Concerns, (for those contracts under which it was required within

the period of 25 October 2019 through 16 October 2023). If not required in

any recent contracts, the Offeror shall so state.

ii. Compliance with Small Business Subcontracting Plan - Offerors must be

in compliance with terms and conditions of FAR 52.219-9, Small Business

Subcontracting Plan (if required on recent contracts). The Offeror shall

provide three Individual Subcontracting Reports for recent contracts (where

performance occurred within the period of 25 October 2019 through 16

October 2023) that included a subcontracting plan. Offerors submitting

Commercial Subcontracting Plans shall provide three Summary

Subcontract Reports (SSRs) and the associated Commercial

Subcontracting Plan for each SSR. Caution: SSRs based on Individual

Subcontracting Plans will not be accepted. If Small Business

Subcontracting Plans were not required in any recent contracts, the Offeror

shall so state. If the Offeror has less than three recent contracts, the Offeror

shall provide the most recent Individual Subcontracting Report (or SSR for

Commercial Subcontracting Plans) for each contract it has, and state that

the Offeror does not have three recent contracts.

(capitalization in original).

20

The Solicitation was originally issued by the Army on August 25, 2021. Prior to

receiving the responses to the Solicitation, the Army issued 26 amendments to the

Solicitation, mostly in responses to questions and requests for clarifications from potential

offerors to the Solicitation. It appears that the Army received 96 offerors when the

Solicitation closed on October 25, 2022. In response to an agency level protest and a

subsequent protest at the United States Government Accountability Office (GAO), the

Army took partial corrective action, and issued two additional amendments, Amendment

27, and Amendment 28, with revised proposals due by January 23, 2023. The Army

subsequently issued Amendments 29, 30, and 31, addressing further questions and

ultimately making proposals due by October 16, 2023.

In October 2023, the Branch Chief Shanna Henao and the Procuring Contracting

Officer Carrie Lansing issued a Memorandum for Record for the Solicitation. The October

2023 Memorandum for Record provided in full:

MEMORANDUM FOR RECORD 11 Oct 2023

SUBJECT: Determination to Amend Solicitation W52P1J-20-R-0082 for the

ITES-4H requirement in support of Program Executive Office-Enterprise

Information Systems (PEO-EIS).

BLUF[6]: Determination to amend the above-mentioned solicitation in an

effort to update and revise the Tech evaluation process, past performance

process, as well as adding additional members to the technical team in

order to streamline the acquisition process and re-solicit for new proposals

to evaluate in a more effective and efficient manor with the goal of an award

in 1st quarter FY25, calendar year 2024 instead of an award in 1st quarter

FY26, calendar year 2025.

Background and Justification: The above-mentioned solicitation was issued

on 25 AUG 2021 and closed on 25 OCT 2022. An agency-level protest was

received by the closing date of the solicitation. The Army took partial

corrective action in response to the protest and denied the remaining

grounds. Subsequently, the protester filed a protest at the Government

Accountability Office (GAO), which was ultimately dismissed. Due to the

need to take partial corrective action in response to the agency-level

protest, two amendments were issued (Amendments 0027 and 0028) that

allowed offerors to submit revised proposals. Thus, evaluations for ITES-

4H began on 15 FEB 2023.

From FEB 2023 to APR 2023 both the Army Contracting Command-Rock

Island (ACC-RI) and the PEOCHESS team worked together several times

a week over the three-month period to go over the past performance

evaluations, the technical evaluations as well as the small business and

price evaluations. While progress was being made, it was not at the rate per

6 “BLUF” is an acronym for “Bottom Line Up Front.”

21

the anticipated milestones and therefore the award date was moving further

to the right. It was determined that the technical team did not have the staff

necessary to keep up with 89 technical proposals and complete the 2.5

evaluations necessary per week to make the scheduled award. Part of the

issue taking a significant amount of time regarded the extensive number of

items technical evaluators had to review as part of the Equipment List along

with reading through a lengthy 25 page narrative for Sub-factors 1 and 2.

Combined, this technical evaluation approach was significantly slowing the

Technical team, especially due to some poor proposal quality issues from

offerors. The Technical team also experienced several issues in terms of

proposal quality. The past performance team also encountered issues with

offerors providing a base IDIQ contract number without identifying any

specific delivery or task orders for the Army to evaluate. Due to these

difficulties, both the Past Performance and Technical evaluation teams

were behind schedule.

After a meeting with senior Army leaders in April 2023, it was determined

that the team, both PEO and ACC-RI, needed to come up with several

Courses of Action (COAs)/opportunities in order to streamline the process

of evaluating the large amount of interested offerors to make an award

much more quickly and efficiently than the current method. From APR 2023

– JUL 2023 ACC-RI assigned a new PCO and lead specialist to the team

and PEO committed to assigning additional personnel to the technical team.

It was determined that the RFP required an amendment to revise the

evaluation criteria in order to streamline the evaluation process. Several

amendments starting with Amendment 0029 have been issued. The

following highlights the main areas that were revised in the amendments as

well as the rationale for the change. Not every specific RFP change is

discussed below, however, the key changes to the RFP are noted below:

(a) Added Strict Compliance Requirements: The solicitation that initially

closed in October 2022 already contained some Strict Compliance

requirements for this solicitation in the form of Attachment 0014. This

amendment will increase the number of items with a strict compliance

requirement in order to enable the Army to efficiently evaluate and deal with

proposals that fail to provide the necessary information requested. In this

regard, Strict Compliance Requirements are notably being added to the

Equipment List to respond to situations where offerors leave blank cells in

the Equipment List. Providing a complete Equipment List (along with a

complete proposal) is essential to ensuring not only that the offeror complies

with the terms of the solicitation, but failing to provide a complete proposal

and Equipment List also significantly slows the evaluation process. Indeed,

this issue (blank cells on the Equipment List) significantly slowed the

Technical Evaluation Team during its evaluation. By adding strict

compliance to the Equipment List, and other material RFP requirements,

the Army can ensure it is spending its substantive evaluation time (i.e.,

22

reviewing Technical, Past Performance, Price, and Small Business) on only

complete proposals, rather than wading through numerous proposals that

are fundamentally incomplete. The RFP will clearly note what requirements

are considered matters of strict compliance and also will clearly note that

offerors deemed non-compliant will not be further evaluated or considered

for award.

(b) Added a “Phased” or “Step” Approach: Prior to this amendment, the RFP

contemplated the Technical, Past Performance, Price and Small Business

Evaluations occurring following the initial compliance check. This

amendment will add a “phased” or “Step” approach where offerors will

undergo the Step 1 compliance check and then have the Equipment List

Reviewed for Technical Acceptability. The Equipment List was already

being evaluated on an Acceptable/Unacceptable basis; however, it was

combined with the Subfactor 1 and Subfactor 2 evaluation. Now, the

Equipment List will be reviewed at Step 2 and only offerors who receive an

Acceptable will proceed to receive further consideration of Technical Sub-

factors 1 and 2, along with Past Performance, Small Business, and Price.

By using this additional Step 2 approach where offerors must provide an

acceptable Equipment List prior to receiving further evaluation, the Army

can ensure it is spending its substantive evaluation resources on proposals

that are not only complete, but also provide an acceptable baseline

Equipment List. Prior to this amendment, even if the Technical Team

determined an offeror had an unacceptable Equipment List, the team still

had to complete a full Technical evaluation of Sub-factors 1 and 2 in case

the SSA decided to include an unacceptable proposal as part of

discussions. Additionally, unacceptable proposals would still receive past

performance, price and small business evaluations. With this new

approach, the Army can streamline its evaluation by ensuring evaluation

resources are only spent on proposals with an acceptable equipment list,

which should assist the Army in meeting its award date goals.

(c) Added a Statistical Sampling Evaluation Methodology to Step 2: The

Equipment List is a large document comprising of seven product catalogs

offerors must complete with over 900 cells of data for review. Previously,

the Army was going line by line validating each product proposed by every

offeror, which was taking significant time, especially with 89 proposals to

evaluate. Now, this amendment will introduce a statistical sampling

evaluation method to more efficiently evaluate the Equipment List. In this

regard, it was determined that the Army will sample 35% of the data, which

the technical team believes will provide a sufficient sample size to determine

an offeror Technically Acceptable. All offerors will be evaluated for the same

sample of products from the various catalogs. The sampling will be as

follows:

23

Catalog 1: first 50 cells due to limited number of cells in the catalog;

Catalog 2: The sample will begin at row 299 and evaluate 50 odd numbers,

which provides a more diverse product sampling;

Catalog 3: first 50 cells to allow for maximum diversity in the catalog;

Catalog 4: first 50 cells due to limited number of cells in the catalog;

Catalog 5: There are only 44 cells; as such, all 44 will be evaluated;

Catalog 6: 50 cells beginning at row 8; all even numbers will be evaluated;

Catalog 7: There are only 41 cells; as such, all 41 will be evaluated.

(d) Reduced Technical Page Count: Offerors were provided with 25 pages

to demonstrate an approach for Technical sub-factors 1 and 2. Upon review

by the Technical Team, it was determined that 25 pages was greatly in

excess of what an offeror needs in order to submit a proposal that fully

addresses the sub-factor 1 and 2 requirements. Specifically, the Technical

evaluators noted that many offerors included a lot of banal commentary

throughout the 25 page narrative that served more as promotional material

rather than illustrated the merits of an offerors Technical approach. In order

to streamline the evaluation process and encourage offerors to succinctly

present the merits of their proposal, the page count for Technical Part B

(sub-factors 1 and 2) was reduced to eight pages as part of Amendment

0029. However, following extensive consideration of offeror feedback

following the issuance of Amendment 0029, it was determined that fourteen

pages would both meet the requests of offerors to increase the page count

from the previously identified page count of 8 pages in Amendment 0029,

while also satisfy the Army’s desire to reduce the page count as compared

to what offerors provided at the initial closing date of the solicitation (25

October 2022). Fourteen pages is a reasonable number as it effectively

provides offerors two pages for each Key Point. Additionally, fourteen pages

still allows an offeror to provide the merits of its approach to meeting the

Government’s requirements, but will encourage offerors to “skip the fluff”

and include succinct statements noting how an offeror will provide a solution

in response to the RFP’s requirements.

(e) Added a Key Point to Sub-factor 2: Key Point 4 is added to Sub-factor 2

in order to provide the Government will a description of how the offeror

support and comply with the Statement of Work and the offeror’s processes

to support contract management. This is added in order to ensure a

successful offeror can manage a complex undertaking such as ITES-4H.

(f) Revised Past Performance: The past performance factor also was

changed in several key respects. First, if an offeror is submitting an ordering

type vehicle contract reference (e.g., IDIQ), the offeror is required to provide

the specific Delivery Order (DO) or Task Order (TO) it desires the Army to

evaluate. When the Army initially received proposals in October 2022,

numerous offerors simply provided the Army with the base IDIQ contract

number as a contract reference rather than provide a specific delivery or

24

task order. Because performance on an IDIQ type contract occurs at the

DO or TO level, the Army revised the terms of the RFP to ensure the Army

receives specific DO’s or TO’s where the offeror actually performed. This

will also ensure the Army knows exactly which references the offeror

desires the Army to evaluate. It will also help the Army ensure an efficient

evaluation process by not requiring the Army to guess or review potentially

thousands of DO’s or TO’s issued off of an IDIQ type contract.

Second, the Army revised the relevancy metrics as part of the Amendment

process. In this regard, the RFP now sets out specific dollar values and

number of catalogs an offeror must meet to receive a particular relevancy

rating. Offerors are expected to maintain an active role through extensive

participation over the life of the ITES-4H contract. ITES-4H is valued at

$10B over the 10-year period. CHESS expects total sales across all

awardees to equal approximately $1B per year. The relevancy dollar figures

were determined based on ITES-3H historical data points. CHESS looked

at the lowest total sales by a single vendor during a single year over the life

of the contract and structured the ratings based on that number.

Specifically, CHESS determined that the lowest sales by a single vendor

during a single year over the life of the contract was $1 million. Because $1

million was the lowest sales by a single vendor, the Army deems this value

to equate to a “Relevant” contract reference. Using the lowest total sales of

around $1,000,000.00 for a single year of performance allows room for

consideration of small business that could compete. Sales above

$2,000,000.00 would constitute as very relevant due to the historical data

from ITES-3H showing most vendors consistently sold above this number

and positively complied with all contract requirements. In addition, CHESS

determined anything under the Simplified Acquisition Threshold would be

the cutoff for relevant orders from a dollar value perspective. Considering

that the total contract value for ITES-4H is $10 billion, the Army’s dollar

value metrics for relevancy are very reasonable and are on the lower end

of the expected amount an awardee would receive as part of this contract

effort. The Army has specifically considered the lower threshold numbers in

order to promote competition for this effort. Further, the Army has set up the

past performance criteria to allow an offeror to meet the dollar value

requirements through combining up to five contract references. Overall, the

Government has set these dollar figure parameters because it is vital an

offeror can manage multiple contracts of higher value during a given period

of time. If an offeror is unable to complete multiple orders at a time due to

the magnitude of cost that could pose high risk to ITES-4H.

The relevancy definitions also provide a specific number of catalogs an

offeror must meet to align with a certain relevancy rating. Similar to the

dollar values, the Army has provided great leniency to offerors to meet the

requirements. ITES-4H has a total of seven catalogs. Here, to receive a

“Very Relevant” rating, an offeror would only need to provide contract

25

references meeting 4 catalogs (along with the associated dollar value) to

receive the highest rating. The Army believes its needs can adequately be

met through the aligned catalog numbers and also believes that because

the RFP allows offerors to provide up to five references, the Army’s catalog

relevancy requirements are more than reasonable and do not unduly restrict

competition.

I have also considered these amendments in light of the Federal Acquisition

Regulation (FAR) requirements at FAR 15.206. Specifically, I do not deem

these amendments to meet the requirements of FAR 15.206(e), which

would necessitate cancelling the solicitation. In this regard, the

requirements for ITES-4H have not changed. The Statement of Work

remains the same and the solicitation continues to require offerors provide

products that meet the Government’s requirements. What is changing is

portions of the evaluation criteria and how the Government intends to re-

structure the evaluation process to ensure the Army can award ITES-4H

requirement in a timely and efficient manner to meet the Army’s needs.

Because the fundamental ITES-4H requirement remains unchanged in

terms of the Army’s needs, I do not deem these amendments so substantial

that additional sources would have likely submitted offers. Indeed, the

changes in these amendments do not so significantly alter the purpose or

the nature of the contract. I also note that the RFP was released in August

2021 and did not close until October 2022—over a year for prospective

offerors to decide whether to submit a proposal. Ultimately, the Army

received 96 proposals in October—a significant amount of industry interest.

After conducting the initial compliance checks, 89 proposals remain, which

again is a large number offerors. This large number of offerors gives me

confidence that the field of competition for ITES-4H would not change based

on this amendment. Further, offerors have spent considerable time, effort

and money preparing proposals, thus, it is not in the interest of either the

Government or offerors to completely cancel the RFP. Based on these

considerations, I do not believe the ITES-4H solicitation requires

cancellation. Instead, several amendments starting with Amendment 0029

were issued and offerors will be allowed the opportunity to submit revised

proposals.

Additionally, the 7 offerors initially deemed non-compliant and removed

from the competition will not be re-instated. FAR 15.206(c) notes that

“Amendments issued after the established time and date for receipt of

proposals shall be issued to all offerors that have not been eliminated from

the competition.” Because the 7 were already eliminated, the FAR does not

require their reinstatement. Further, and importantly, the basis for which the

offerors were deemed non-compliant would not change as a result of this

amendment because the amendment is not relaxing any of the terms for

which the 7 offerors were removed.

26

(capitalization in original; footnote, alteration, and emphasis added).

Most relevant to the above captioned bid protests was the addition of the “Added

Strict Compliance Requirements,” which, as described above stated:

(a) Added Strict Compliance Requirements: The solicitation that initially

closed in October 2022 already contained some Strict Compliance

requirements for this solicitation in the form of Attachment 0014. This

amendment will increase the number of items with a strict compliance

requirement in order to enable the Army to efficiently evaluate and deal with

proposals that fail to provide the necessary information requested. In this

regard, Strict Compliance Requirements are notably being added to the

Equipment List to respond to situations where offerors leave blank cells in

the Equipment List. Providing a complete Equipment List (along with a

complete proposal) is essential to ensuring not only that the offeror complies

with the terms of the solicitation, but failing to provide a complete proposal

and Equipment List also significantly slows the evaluation process. Indeed,

this issue (blank cells on the Equipment List) significantly slowed the

Technical Evaluation Team during its evaluation. By adding strict

compliance to the Equipment List, and other material RFP requirements,

the Army can ensure it is spending its substantive evaluation time (i.e.,

reviewing Technical, Past Performance, Price, and Small Business) on only

complete proposals, rather than wading through numerous proposals that

are fundamentally incomplete. The RFP will clearly note what requirements

are considered matters of strict compliance and also will clearly note that

offerors deemed non-compliant will not be further evaluated or considered

for award.

(capitalization in original).

The Administrative Record for the above captioned protests reflects that in response to

the Solicitation, the Army received 83 proposals, including from the seven protestors.7

7 Tab 120 of the Administrative Record, titled “Proposal Tracking Sheet,” reflects that, of

the 87 proposals the Army expected to receive, 52 proposals were compliant with the

strict compliance requirement of Step 1 and moved to Step 2, 28 proposals were non-

compliant with the strict compliance requirement of Step 1, 3 proposals were submitted

late, and 4 offerors did not submit a proposal. As reflected above, the October 2023

Memorandum for Record states that “the RFP was released in August 2021 and did not

close until October 2022—over a year for prospective offerors to decide whether to submit

a proposal. Ultimately, the Army received 96 proposals in October,” although the October

2023 Memorandum for Record did not indicate a specific year when the 96 proposals

were received. The October 2023 Memorandum for Record continues: “After conducting

the initial compliance checks, 89 proposals remain, which again is a large number

offerors.” The Administrative Record does not address the discrepancy between the

remaining “89 proposals” in the October 2023 Memorandum for Record and the 83

27

As indicated above, all seven protestors who filed the above captioned bid protests

were eliminated during Step 1 of the Army’s ongoing evaluations.

Protestors’ Strict Compliance Evaluations

GovWave

The Army reviewed GovWave’s proposal and found GovWave’s proposal Past

Performance proposal non-compliant under Step 1. The January 12, 2024 Memorandum

for Record for GovWave’s evaluation provided:

Proposal submitted by GovWave, LLC. Dated 16 October 2023

The purpose of this memorandum is to document the determination that

made the above referenced proposal submitted by GovWave, LLC. Non-

Compliant per the terms and conditions of subject solicitation for the

Information Technology Enterprise Solutions – 4 Hardware (ITES-4H)

multiple award IDIQ base contracts. The proposal was reviewed against the

strict compliance requirements identified throughout the solicitation. The

United States Government (USG) performed initial Step 1 Compliance

Checks to ensure the accuracy of proposals and reduce risk to the

Government. Adherence to the Strict Compliance requirements identified

throughout the solicitation is vital to ensure the Government receives a

complete and high-quality proposal. Strict Compliance requirements

proposals the Army ultimately received. Amendment 0029 was issued on August 16,

2023, made significant changes to the evaluation scheme, and changed the proposal due

date to October 2, 2023. Amendment 0030 was issued on September 14, 2023, answered

questions from offerors, and changed the proposal due date to October 16, 2023.

Amendment 0031 was issued on September 28, 2023, made changes to the Solicitation

such that “revised proposals are REQUIRED,” and maintained the October 16, 2023 due

date for proposals. (capitalization in original). Because the contracting officer could not

know, when she electronically signed the October 2023 Memorandum for Record, that

the Army would receive 96 proposals on October 16, 2023, the 96 proposals referenced

by the Memorandum for Record may be referencing the number of proposals the Army

received in October 2022, which are not germane to the above captioned bid protests.

The defendant added to the confusion by stating in its omnibus cross-motion for judgment

on the Administrative Record: “The Army received eighty-seven proposals on October 16,

2023 in response to the updated RFP, including proposals from GovWave, Futron, ETSI,

GAI, DHT, UNICOM and ACC.” As summarized above, the Army received 83 proposals

in response to the Solicitation, and moreover, given that 3 proposals were received late,

it is not clear that the 3 proposals were submitted on October 16, 2023. At a hearing, the

court asked the defendant to address the number of proposals actually submitted to the

Army, but the defendant was unable offer clarity at the hearing.

28

encourage consistency and accuracy of information presented. Further,

ensuring the offeror has provided all necessary information is essential to

the efficient evaluation of proposals. The following are excerpts directly from

the Instructions to Offerors (Section L) and Evaluation Factors for Award

(Section M) of the RFP:

a. L.3 STRICT COMPLIANCE REQUIREMENT: All volumes and files have

strict compliance requirements and strict compliance to those

requirements will be evaluated. Any items identified as a STRICT

COMPLIANCE REQUIREMENT will be evaluated for compliance prior to

any further evaluation of the Offerors proposal. Failure to abide by the

strict compliance requirements for any of these factors will deem the

Offerors proposal non-compliant and will eliminate it from further

consideration. Factors and subfactors with strict compliance

requirements are clearly identified throughout these instructions.

b. L.4.1.3 – A proposal is presumed to represent the Offeror’s best efforts to

respond to the RFP. The Offeror must provide adequately detailed

information that complies with the solicitation requirements, allows for

meaningful review by the Government evaluators, and affirmatively

demonstrates the merits of its proposal. The Offeror shall provide sufficient

detail to substantiate the validity of all stated assertions and must not merely

repeat the RFP requirements, but rather must provide convincing

documentary evidence of how contract requirements will be met. Data not

submitted with the proposal, but submitted previously, or presumed to be

known (i.e., previous projects performed for the United States Government

(USG) will not be considered. Clarity and completeness are essential.

c. M.3 EVALUATION METHODOLOGY: Step 1 - STRICT COMPLIANCE

REQUIREMENT: Proposals will be reviewed to determine if all compliance

requirements set forth in the Instructions to Offerors are satisfied. Failure to

provide proposals in compliance with the instructions specified as “STRICT

COMPLIANCE REQUIREMENTS” in the Instructions to Offerors of this RFP

shall render the Offeror’s proposal non-compliant. Any Offeror’s proposal

determined non-compliant will not be evaluated and will not be further

considered for award. Only Offerors whose proposals are determined

compliant will move to Step 2 of the evaluation process.

2. Based upon a review of the strict compliance requirements set forth in

the solicitation, the following findings contributed to the determination that

above referenced proposal is non-compliant:

a. Volume 3 – Past Performance / Adverse Performance. The Offeror’s

Proposal did not acknowledge or include a statement regarding any adverse

past performance. The STRICT COMPLIANCE REQUIREMENT identified

in the solicitation states:

29

L.5.3.2 (b) Specific Proposal Instructions. Adverse Contract Performance:

STRICT COMPLIANCE REQUIREMENT: In addition to the contract

references, the Offeror shall identify any recent and relevant Government

contract(s) it was awarded that encountered any performance problems

related to deliverables; services, security violations (i.e. data, physical,

virtual, etc.), Environmental Protection Agency (EPA) violations, and every

contract that was terminated (termination for default or termination for cause

only), in whole or in part from 25 October 2019 through 16 October 2023. If

there are no contracts that meet the description above, the Offeror shall

state as such and include a statement in the Volume III of the proposal. The

number of contract references provided in response to this paragraph is

unlimited. Submission of Adverse Contract Performance information shall

not count as part of the page count for Past Performance.

FINDING 1 – No Statement Acknowledging Adverse Performance: It is

critical to the evaluation process that an Offeror provide a statement

regarding whether any adverse past performance has occurred or not

occurred. Acknowledgement of this requirement is important so that the

USG [United States Government] may gather information about an Offeror's

past performance in an efficient manner that allows for the evaluation of a

proposal to reflect the Offeror's past performance record. When an Offeror's

proposal is silent about whether it has any adverse past performance, that

silence effectively creates ambiguity and does not equate to a clear

statement that the Offeror has none. If Offeror has no history of adverse

contract performance, offeror must provide a statement as such.

3. Based upon the above findings and in accordance with the terms of the

RFP, Offeror CI [GovWave8] is determined to be non-compliant, and its

proposal is removed from consideration for award. A letter communicating

the details that make its proposal non-compliant will be provided along with

a written debriefing.

(capitalization and emphasis in original; alterations and footnote added).

8 The Army’s evaluation system created a labelling code for each offer in response to the

Solicitation. The following codes were used for the protestors in the above captioned bid

protests:

CI – GovWave

CG - Futron

AL - Government Acquisitions

DT -DH Technologies

AM - Enterprise Technology Solutions

AU - Unicom

CM - Advanced Computer Concepts

30

As reflected on the Army’s “Proposal Compliance Checklist” for GovWave, for the

column, “Meets terms and conditions of RFP?” the Army indicated: “NO,” with the

explanation: “Overall, this proposal is NON-COMPLIANT. Did not acknowledge

requirement to identify/discuss any potential adverse contract performacnce [sic].”

(capitalization and emphasis in original; alteration added). For Volume 3, the Proposal

Compliance Checklist reflected that Volume 3 was submitted and for the column “Adverse

Contract Performance,” the Army indicated “NO,” with the explanation: “Not Mentioned in

Volume 3, renders proposal non-compliant.” (capitalization and emphasis in original).

For the column “Volume 3 Meets Requirements,” the Army indicated “NO.”

(capitalization and emphasis in original).

Futron

The Army reviewed Futron’s proposal and found its Equipment List non-compliant

under Step 1. The February 15, 2024 Memorandum for Record for Futron’s evaluation

provided:

Proposal submitted by Futron, Inc., dated 16 October 2023

1. The purpose of this memorandum is to document the determination that

made the above referenced proposal submitted by Futron, Inc. Non-

Compliant per the terms and conditions of subject solicitation for the

Information Technology Enterprise Solutions – 4 Hardware (ITES-4H)

multiple award IDIQ base contracts. The proposal was reviewed against

the strict compliance requirements identified throughout the solicitation.

The United States Government (USG) performed initial Step 1

Compliance Checks to ensure the accuracy of proposals and reduce risk

to the Government. Adherence to the Strict Compliance requirements

identified throughout the solicitation is vital to ensure the Government

receives a complete and high- quality proposal. Strict Compliance

requirements encourage consistency and accuracy of information

presented. Further, ensuring the offeror has provided all necessary

information is essential to the efficient evaluation of proposals. The

following are excerpts directly from the Instructions to Offerors (Section

L) and Evaluation Factors for Award (Section M) of the RFP:

a. L.3 STRICT COMPLIANCE REQUIREMENT: All volumes and files have

strict compliance requirements and strict compliance to those requirements

will be evaluated. Any items identified as a STRICT COMPLIANCE

REQUIREMENT will be evaluated for compliance prior to any further

evaluation of the Offerors proposal. Failure to abide by the strict compliance

requirements for any of these factors will deem the Offerors proposal non-

compliant and will eliminate it from further consideration. Factors and

subfactors with strict compliance requirements are clearly identified

throughout these instructions.

31

b. L.4.1.3 – A proposal is presumed to represent the Offeror’s best efforts

to respond to the RFP [Request for Proposal]. The Offeror must provide

adequately detailed information that complies with the solicitation

requirements, allows for meaningful review by the Government evaluators,

and affirmatively demonstrates the merits of its proposal. The Offeror shall

provide sufficient detail to substantiate the validity of all stated assertions

and must not merely repeat the RFP requirements, but rather must provide

convincing documentary evidence of how contract requirements will be met.

Data not submitted with the proposal, but submitted previously, or

presumed to be known (i.e., previous projects performed for the United

States Government (USG) [sic] will not be considered. Clarity and

completeness are essential.

c. M.3 EVALUATION METHODOLOGY: Step 1 - STRICT COMPLIANCE

REQUIREMENT: Proposals will be reviewed to determine if all compliance

requirements set forth in the Instructions to Offerors are satisfied. Failure to

provide proposals in compliance with the instructions specified as “STRICT

COMPLIANCE REQUIREMENTS” in the Instructions to Offerors of this RFP

shall render the Offeror’s proposal non-compliant. Any Offeror's proposal

determined non-compliant will not be evaluated and will not be further

considered for award. Only Offerors whose proposals are determined

compliant will move to Step 2 of the evaluation process.

2. Based upon a review of the strict compliance requirements set forth in

the solicitation, the following findings contributed to the determination that

above referenced proposal is non-compliant:

a. Volume 1 – Equipment List (Part A). Offeror’s Equipment List

(Attachment 0002) contained a blank cell. Please see table below for the

specific cell that is material to the evaluation process and was found blank:

Equipment List Compliance Check

Tab Blank Cell in Column D – Proposed Configuration

[redacted] [redacted]

The STRICT COMPLIANCE REQUIREMENT identified in the solicitation

states:

• L.5.1.1 PART A - Equipment List. STRICT COMPLIANCE REQUIREMENT:

ANY cells marked for Contractor Fill-In on the Equipment List that are left

blank or are unintelligible as to the product the Offeror is proposing shall

render the Offeror’s proposal non-compliant and will not be further

considered for award.

32

FINDING 1 – Blank Cell in Column D – Proposed Configuration: It is critical

to the evaluation process that all fillable cells in Column D of the Equipment

List are complete, as required by the solicitation. Completeness ensures

that the Offeror’s proposed configuration for each System Description

identified on each Catalog (Catalog I through Catalog VII) identifies clear

technical detail. Blank cells present a risk of ambiguity and misinterpretation

to the USG, as well as impede the efficient evaluation of proposals because

a blank cell does not allow the Government to clearly identify which

product/item an Offeror is proposing. Offerors are required to provide a

proposed configuration for every System Description; thus, a complete

Equipment List is important to the Government’s evaluation. Here, the

Government cannot determine if the offeror meets the requirement

associated with [redacted] regarding “[redacted]” because the Offeror has

provided a blank cell.

3. Based upon the above findings and in accordance with the terms of the

RFP, Offeror CG [Futron] is determined to be non-compliant, and its

proposal is removed from consideration for award. A letter communicating

the details that make its proposal non-compliant will be provided along with

a written debriefing.

(capitalization and emphasis in original; first alteration in original).

As reflected on the Army’s “Proposal Compliance Checklist” for Futron, for the

column, “Meets terms and conditions of RFP?” the Army indicated “NO,” with the

explanation: “Overall, this proposal is NON-COMPLIANT.” (capitalization and emphasis

in original). The Proposal Compliance Checklist reflected that Volume 1 was submitted

and the Equipment List at Attachment 0002 was submitted as an Excel file. For the

column “All contractor filled cells are completed? (blank/unintelligible fills are prohibited),”

the Army indicated “NO,” with the explanation:

1 Blank in required Proposal Configuration fill-ins, 508 Blanks in catalog ID.

PLEASE NOTE: The blanks in the Catalog ID (Column E) are waived from

the non-compliance IAW L.5.1.1(e) “The Offeror may also complete the

Catalog Identification column to coordinate association between equipment

list and price models.” (emphasis added.)

(capitalization and emphasis in original). For the column “Volume 1 Meets

Requirements,” the Army indicated “NO.” (capitalization and emphasis in original).

Government Acquisitions

The Army reviewed Government Acquisitions’ proposal and found its Price

proposal non-compliant under Step 1. The January 11, 2024 Memorandum for Record

for Government Acquisitions’ evaluation provided:

33

Proposal submitted by Government Acquisitions, Inc. (GAI), dated 16

October 2023

1. The purpose of this memorandum is to document the determination that

made the above referenced proposal submitted by Government

Acquisitions, Inc. (GAI) Non-Compliant per the terms and conditions of

subject solicitation for the Information Technology Enterprise Solutions – 4

Hardware (ITES-4H) multiple award IDIQ base contracts. The proposal was

reviewed against the strict compliance requirements identified throughout

the solicitation. The United States Government (USG) performed initial Step

1 Compliance Checks to ensure the accuracy of proposals and reduce risk

to the Government. Adherence to the Strict Compliance requirements

identified throughout the solicitation is vital to ensure the Government

receives a complete and high-quality proposal. Strict Compliance

requirements encourage consistency and accuracy of information

presented. Further, ensuring the offeror has provided all necessary

information is essential to the efficient evaluation of proposals. The following

are excerpts directly from the Instructions to Offerors (Section L) and

Evaluation Factors for Award (Section M) of the RFP:

a. L.3 STRICT COMPLIANCE REQUIREMENT: All volumes and files have

strict compliance requirements and strict compliance to those requirements

will be evaluated. Any items identified as a STRICT COMPLIANCE

REQUIREMENT will be evaluated for compliance prior to any further

evaluation of the Offerors proposal. Failure to abide by the strict compliance

requirements for any of these factors will deem the Offerors proposal non-

compliant and will eliminate it from further consideration. Factors and

subfactors with strict compliance requirements are clearly identified

throughout these instructions.

b. L.4.1.3 – A proposal is presumed to represent the Offeror’s best efforts

to respond to the RFP. The Offeror must provide adequately detailed

information that complies with the solicitation requirements, allows for

meaningful review by the Government evaluators, and affirmatively

demonstrates the merits of its proposal. The Offeror shall provide sufficient

detail to substantiate the validity of all stated assertions and must not merely

repeat the RFP requirements, but rather must provide convincing

documentary evidence of how contract requirements will be met. Data not

submitted with the proposal, but submitted previously, or presumed to be

known (i.e., previous projects performed for the United States Government

(USG) [sic] will not be considered. Clarity and completeness are

essential.

c. M.3 EVALUATION METHODOLOGY: Step 1 - STRICT COMPLIANCE

REQUIREMENT: Proposals will be reviewed to determine if all compliance

requirements set forth in the Instructions to Offerors are satisfied. Failure to

34

provide proposals in compliance with the instructions specified as “STRICT

COMPLIANCE REQUIREMENTS” in the Instructions to Offerors of this RFP

shall render the Offeror’s proposal non-compliant. Any Offeror’s proposal

determined non-compliant will not be evaluated and will not be further

considered for award. Only Offerors whose proposals are determined

compliant will move to Step 2 of the evaluation process.

2. Based upon a review of the strict compliance requirements set forth in

the solicitation, the following findings contributed to the determination that

above referenced proposal is non-compliant:

a. Volume 2 – Price Model. Offeror’s Price Model (Attachment 0004) contains

one blank cell on Tab Catalog III-O, Cell G6 Fixed Discount for Warranty

Variations.

The STRICT COMPLIANCE REQUIREMENT identified in the solicitation

states:

• L.5.2 VOLUME II - Price Factor (1) STRICT COMPLIANCE

REQUIREMENT: All cells contain an appropriate value. Any cells marked

as ‘contractor fill-in’ that are blank or unintelligible in Attachment 0004 will

render the Offeror’s submission as non-compliant and the Offeror’s

proposal will receive no further consideration or evaluation. Offeror’s

intending to propose zero dollars for a particular cell must ensure the

appropriate cell contains a “0.” The Government will not assume a blank cell

in Attachment 0004 represents a zero as any blank cell will result in the

Offeror’s proposal being deemed non-compliant and not further considered

for award.

• L.5.2.1 (d) Instructions for the Price Model: Offerors shall completely fill out

the updated Price Model (Attachment 0004) included with this Amendment

[Amendment 0031]. Failure to provide prices for all items and catalog

identified in the Price Model of the solicitation will render the Offeror

ineligible for award.

FINDING 1 – A cell that is color-coded for “contractor fill-in” is blank. Full

completion of all highlighted/color coded cells required to be filled in by the

Offeror is essential to ensure the Government clearly understands the price

proposed in order to perform an accurate and complete evaluation. Blank

cells present a risk of ambiguity and misinterpretation to the USG, create

uncertainty as to the proposed price, as well as impede the efficient

evaluation of proposals because a blank cell does not allow the Government

to clearly identify if or what is the Fixed Discount for Warranty Variation for

Tab Catalog III-O. This information is important to ensuring the Government

knows the pricing associated with the Offeror’s proposal.

35

3. Based upon the above findings and in accordance with the terms of the

RFP, Offeror AL [Government Acquisitions] determined to be non-

compliant, and its proposal is removed from consideration for award. A letter

communicating the details that make its proposal non-compliant will be

provided along with a written debriefing.

(capitalization, emphasis, and second alteration in original).

As reflected on the Army’s “Proposal Compliance Checklist” for Government

Acquisitions, for the column, “Meets terms and conditions of RFP?” the Army indicated:

“No.” (capitalization and emphasis in original). The Proposal Compliance Checklist

reflected that Volume 2 was submitted and Attachment 0004 was submitted as an Excel

file. For the column “All contractor filled cells are completed? (blank/unintelligible fills are

prohibited),” the Army indicated “No,” with the explanation: “Blank cells

identified.”(emphasis in original). For the column “Volume 2 Meets Requirements,” the

Army indicated “No.” (capitalization and emphasis in original).

DH Technologies

The Army reviewed DH Technologies’ proposal and found its Price proposal non-

compliant under Step 1. The February 12, 2024 Memorandum for Record for DH

Technologies’ evaluation provided:

Proposal submitted by DH Technologies, LLC. Dated 16 October 2023

1. The purpose of this memorandum is to document the determination that

made the above referenced proposal submitted by DH Technologies, LLC.

Non-Compliant per the terms and conditions of subject solicitation for the

Information Technology Enterprise Solutions – 4 Hardware (ITES-4H)

multiple award IDIQ base contracts. The proposal was reviewed against the

strict compliance requirements identified throughout the solicitation. The

United States Government (USG) performed initial Step 1 Compliance

Checks to ensure the accuracy of proposals and reduce risk to the

Government. Adherence to the Strict Compliance requirements identified

throughout the solicitation is vital to ensure the Government receives a

complete and high-quality proposal. Strict compliance requirements

encourage consistency and accuracy of information presented. Further,

ensuring the Offeror has provided all necessary information is essential to

the efficient evaluation of proposals. The following are excerpts directly from

the Instructions to Offerors (Section L) and Evaluation Factors for Award

(Section M) of the RFP:

a. L.3 STRICT COMPLIANCE REQUIREMENT: All volumes and files have

strict compliance requirements and strict compliance to those requirements

will be evaluated. Any items identified as a STRICT COMPLIANCE

REQUIREMENT will be evaluated for compliance prior to any further

36

evaluation of the Offerors proposal. Failure to abide by the strict compliance

requirements for any of these factors will deem the Offerors proposal non-

compliant and will eliminate it from further consideration. Factors and

subfactors with strict compliance requirements are clearly identified

throughout these instructions.

b. L.4.1.3 – A proposal is presumed to represent the Offeror’s best efforts

to respond to the RFP. The Offeror must provide adequately detailed

information that complies with the solicitation requirements, allows for

meaningful review by the Government evaluators, and affirmatively

demonstrates the merits of its proposal. The Offeror shall provide sufficient

detail to substantiate the validity of all stated assertions and must not merely

repeat the RFP requirements, but rather must provide convincing

documentary evidence of how contract requirements will be met. Data not

submitted with the proposal, but submitted previously, or presumed to be

known (i.e., previous projects performed for the United States Government

(USG) [sic] will not be considered. Clarity and completeness are

essential.

c. M.3 EVALUATION METHODOLOGY: Step 1 - STRICT COMPLIANCE

REQUIREMENT: Proposals will be reviewed to determine if all compliance

requirements set forth in the Instructions to Offerors are satisfied. Failure to

provide proposals in compliance with the instructions specified as “STRICT

COMPLIANCE REQUIREMENTS” in the Instructions to Offerors of this RFP

shall render the Offeror’s proposal non-compliant. Any Offeror’s proposal

determined non-compliant will not be evaluated and will not be further

considered for award. Only Offerors whose proposals are determined

compliant will move to Step 2 of the evaluation process.

2. Based upon a review of the strict compliance requirements set forth in

the solicitation, the following findings contributed to the determination that

the above referenced proposal is non-compliant:

a. Volume 2 – Price Model. Offeror’s Price Model (Attachment 0004)

contained material blank cells. Please see table below for specific cells that

were found blank:

Price Model Compliance Check

Tab Column D – Proposed Configuration

Catalog I-O D29, D30

The STRICT COMPLIANCE REQUIREMENT identified in the solicitation

states:

• L.5.2 VOLUME II - Price Factor (1) STRICT COMPLIANCE

REQUIREMENT: All cells contain an appropriate value. Any cells marked

as contractor fill-in that are blank or unintelligible in Attachment 0004 will

37

render the Offeror’s submission as non-compliant and the Offeror’s

proposal will receive no further consideration or evaluation. Offeror’s

intending to propose zero dollars for a particular cell must ensure the

appropriate cell contains a “0.” The Government will not assume a blank cell

in Attachment 0004 represents a zero as any blank cell will result in the

Offeror’s proposal being deemed non-compliant and not further considered

for award.

• L.5.2.1 (d) Instructions for the Price Model: Offerors shall completely fill out

the updated Price Model (Attachment 0004) included with this Amendment

[Amendment 0031]. Failure to provide prices for all items and catalogs

identified in the Price Model of the solicitation will render the Offeror

ineligible for award.

FINDING 1 – Two cells that are color-coded for Contractor Fill-in are blank.

Full completion of all highlighted/color coded cells required to be filled in by

the Offeror is essential to ensure the Government clearly understands the

price proposed for a particular product in order to perform an accurate and

complete evaluation. Additionally, it is particularly critical to the evaluation

process that all fillable cells in Column D – Proposed Configuration of the

Price Model are complete to ensure that the Price Model can be cross

walked with Column D of the Equipment List. This ensures that the Offeror

consistently proposed its items on both solicitation attachments; the Catalog

ID does not provide enough information. Blank cells present a risk of

ambiguity and misinterpretation to the USG, create uncertainty as to the

product and price an offeror is proposing, as well as impede the efficient

evaluation of proposals because a blank cell does not allow the Government

to clearly identify the product associated with a particular price.

A Note Regarding Finding 1: The Army does note that the Offeror has

placed information regarding the Catalog Identification in Column E for the

associated blank cells. However, the information contained in Column E that

is associated with D29 and D30 is insufficient to find this offeror compliant

for the following reasons:

1) As noted above, it is important to the evaluation of proposals that Offerors

ensure consistency between the Equipment List and Price Matrix. This

ensures that not only can the Government adequately evaluate and assess

the price for the products an offeror is proposing, but also makes certain

that the offeror does not list one item on the Equipment List and list an

entirely different and potentially unacceptable item on the Price Matrix. The

Equipment List and the Price Matrix must be consistent, especially in

regards to column D, to ultimately ensure the Government is receiving

products that meet the Government’s minimum requirements at a fair and

reasonable price. By only providing the catalog identification number, the

38

Offeror does not clearly note what product it is proposing at the associated

price.

2) To the extent the offeror asserts that the Army, for the purposes of the

compliance check, should cross-reference the Offeror’s Equipment List to

the Price Matrix, such an assertion would be contrary to the terms of the

RFP. The RFP provides at L.4.1 that “Five separate volumes shall be

submitted. These volumes shall be self-contained and shall not be cross-

referenced. The Government will not assume the duty to search for data or

information to cure problems discovered in any proposal submitted.” Thus,

based on the clear language of L.4.1, the burden was on the offeror to

ensure volumes are self-contained and contain all necessary information for

the Government to evaluate.

3) It is also noted that It is an offeror’s responsibility to submit a well-written

proposal, with adequately detailed information which clearly demonstrates

compliance with the solicitation requirements and allows a meaningful

review by the Army. It is not the Army’s responsibility to scour through

various proposal documents to try and make an offeror compliant. Rather,

as the RFP notes, it is the offeror’s responsibility to comply with the clear

solicitation requirements and place all information in the correct volume in

order to allow the Government to conduct an efficient and effective

evaluation.

4) Fundamentally, without a clear description of the product proposed in

cells D29 and D30, the Army cannot know what product is being proposed

at the price noted in the Price Matrix, which materially inhibits the

evaluation.

3. Based upon the above findings and in accordance with the terms of the

RFP, Offeror DT [DH Technologies] is determined to be non-compliant, and

its proposal is removed from consideration for award. A letter

communicating the details that make its proposal non-compliant will be

provided along with a written debriefing.

(capitalization and emphasis in original; second alteration in original).

As reflected on the Army’s “Proposal Compliance Checklist” for DH Technologies,

for the column, “Meets terms and conditions of RFP?” the Army indicated “No,” with the

explanation: “Overall, this proposal is NON-COMPLIANT.” (capitalization and emphasis

in original). For Volume 1, the Proposal Compliance Checklist reflected that Volume 1

was submitted and the Equipment List at Attachment 0002 was submitted as an Excel

file. The Army indicated for the column “All contractor filled cells are completed?

(blank/unintelligible fills are prohibited),” “Yes,” with the explanation: “Catalog ID has

blanks, L.5.1.1(e) provided that: ‘The Offeror may also complete the Catalog

Identification column to coordinate association between equipment list and price

39

models.’ (emphasis added.) Non-compliance for this issue will be waived.” (emphasis

in original). For the column “Volume 1 Meets Requirements,” the Army indicated “Yes.”

(emphasis in original). As reflected on the Proposal Compliance Checklist for Volume 2,

the Proposal Compliance Checklist reflected that Volume 2 was submitted and for the

column “All contractor filled cells are completed? (blank/unintelligible fills are prohibited),”

the Army indicated “NO,” with the explanation:

1. Catalog I-O, Cells D29, D30 are blank.

2. Catalog Identification (Cell B6) on the top of some Tabs is blank.

These blank cells are immaterial as it is clear what catalog the offeror is

proposing to because each Tab is already labeled by the Government

as to the respective catalogs.

(capitalization and emphasis in original). For the column “Volume 2 Meets

Requirements,” the Army indicated “NO.” (capitalization and emphasis in original).

Enterprise Technology Solutions

The Army reviewed Enterprise Technology Solutions’ proposal and found its Price

proposal non-compliant under Step 1. The January 29, 2024 Memorandum for Record

for Enterprise Technology Solutions’ evaluation provided:

Proposal submitted by Enterprise Technology Solutions, Inc. (ETSI), dated

16 October 2023

1. The purpose of this memorandum is to document the determination that

made the above referenced proposal submitted by Enterprise Technology

Solutions, Inc. (ETSI) Non-Compliant per the terms and conditions of

subject solicitation for the Information Technology Enterprise Solutions – 4

Hardware (ITES-4H) multiple award IDIQ base contracts. The proposal was

reviewed against the strict compliance requirements identified throughout

the solicitation. The United States Government (USG) performed initial Step

1 Compliance Checks to ensure the accuracy of proposals and reduce risk

to the Government. Adherence to the Strict Compliance requirements

identified throughout the solicitation is vital to ensure the Government

receives a complete and high-quality proposal. Strict Compliance

requirements encourage consistency and accuracy of information

presented. Further, ensuring the offeror has provided all necessary

information is essential to the efficient evaluation of proposals. The following

are excerpts directly from the Instructions to Offerors (Section L) and

Evaluation Factors for Award (Section M) of the RFP:

a. L.3 STRICT COMPLIANCE REQUIREMENT: All volumes and files have

strict compliance requirements and strict compliance to those requirements

will be evaluated. Any items identified as a STRICT COMPLIANCE

40

REQUIREMENT will be evaluated for compliance prior to any further

evaluation of the Offerors proposal. Failure to abide by the strict compliance

requirements for any of these factors will deem the Offerors proposal non-

compliant and will eliminate it from further consideration. Factors and

subfactors with strict compliance requirements are clearly identified

throughout these instructions.

b. L.4.1.3 – A proposal is presumed to represent the Offeror’s best efforts

to respond to the RFP. The Offeror must provide adequately detailed

information that complies with the solicitation requirements, allows for

meaningful review by the Government evaluators, and affirmatively

demonstrates the merits of its proposal. The Offeror shall provide sufficient

detail to substantiate the validity of all stated assertions and must not merely

repeat the RFP requirements, but rather must provide convincing

documentary evidence of how contract requirements will be met. Data not

submitted with the proposal, but submitted previously, or presumed to be

known (i.e., previous projects performed for the United States Government

(USG) [sic] will not be considered. Clarity and completeness are

essential.

c. M.3 EVALUATION METHODOLOGY: Step 1 - STRICT COMPLIANCE

REQUIREMENT: Proposals will be reviewed to determine if all compliance

requirements set forth in the Instructions to Offerors are satisfied. Failure to

provide proposals in compliance with the instructions specified as “STRICT

COMPLIANCE REQUIREMENTS” in the Instructions to Offerors of this RFP

shall render the Offeror’s proposal non-compliant. Any Offeror’s proposal

determined non-compliant will not be evaluated and will not be further

considered for award. Only Offerors whose proposals are determined

compliant will move to Step 2 of the evaluation process.

2. Based upon a review of the strict compliance requirements set forth in

the solicitation, the following findings contributed to the determination that

above referenced proposal is non-compliant:

a. Volume 2 – Price Model. Offeror’s Price Model (Attachment 0004)

contained multiple blank cells. Please see table below for specific cells that

are material to the evaluation process and were found blank with no

additional explanations on the excel sheet:

41

Price Model Compliance Check

Tab Column D Column E Column H

Proposed Configuration Catalog Item Number Catalog Unit Price

[redacted] [redacted] [redacted] [redacted]

[redacted] [redacted] [redacted] [redacted]

[redacted] [redacted] [redacted] [redacted]

[redacted] [redacted] [redacted] [redacted]

[redacted] [redacted] [redacted] [redacted]

[redacted] [redacted] [redacted] [redacted]

The STRICT COMPLIANCE REQUIREMENT identified in the solicitation

states:

• L.5.2 VOLUME II - Price Factor (1) STRICT COMPLIANCE

REQUIREMENT: All cells contain an appropriate value. Any cells marked

as contractor fill-in that are blank or unintelligible in Attachment 0004 will

render the Offeror’s submission as non-compliant and the Offeror’s

proposal will receive no further consideration or evaluation. Offeror’s

intending to propose zero dollars for a particular cell must ensure the

appropriate cell contains a “0.” The Government will not assume a blank cell

in Attachment 0004 represents a zero as any blank cell will result in the

Offeror’s proposal being deemed non-compliant and not further considered

for award.

• L.5.2.1 (d) Instructions for the Price Model: Offerors shall completely fill out

the updated Price Model (Attachment 0004) included with this Amendment

[Amendment 0031]. Failure to provide prices for all items and catalogs

identified in the Price Model of the solicitation will render the Offeror

ineligible for award.

FINDING 1 – Multiple cells that are color-coded for contractor-fill in are

blank. Full completion of all highlighted/color coded cells required to be filled

in by the Offeror is essential to ensure the Government clearly understands

the price proposed in order to perform an accurate and complete evaluation.

Additionally, it is particularly critical to the evaluation process that all fillable

cells in Column D – Proposed Configuration of the Price Model are complete

to ensure that the Price Model can be cross walked with Column D of the

Equipment List. This ensures that the offeror consistently proposed its items

on both solicitation attachments. Blank cells present a risk of ambiguity and

misinterpretation to the USG, create uncertainty as to the proposed price,

as well as impede the efficient evaluation of proposals because a blank cell

does not allow the Government to clearly identify the proposed price for a

particular product.

3. Based upon the above findings and in accordance with the terms of the

RFP, Offeror AM [Enterprise Technology Solutions] is determined to be

42

non-compliant, and its proposal is removed from consideration for award. A

letter communicating the details that make its proposal non-compliant will

be provided along with a written debriefing.

(capitalization, emphasis, and second alteration in original).

As reflected on the Army’s “Proposal Compliance Checklist” for Enterprise

Technology Solutions, for the column, “Meets terms and conditions of RFP?” the Army

indicated: “No.” (capitalization and emphasis in original). The Proposal Compliance

Checklist reflected that Volume 2 was submitted and Attachment 0004 was submitted as

an Excel file. For the column “All contractor filled cells are completed? (blank/unintelligible

fills are prohibited),” the Army indicated “No,” with the explanation:

(1) Material Blank cells identified as Non-Compliant, which is described in

the compliance MFR.

(2) PLEASE NOTE: the USG reviewed Blanks Cells in Column E of all

Catalogs. Except those noted in the compliance MFR, the remaining

blanks in Column E are immaterial because of the offeror’s response in

Column D. The Offeror has noted that the [redacted], thus the offeror

has provided a reason for not assigning a catalog number. The

compliance MFR notes cells where the offeror did not provide any

rationale in Column D or E as to the blank cells.

(3) PLEASE NOTE: The Government noted that there is a blank Unit

Price [redacted] in Catalog [redacted] and in Catalog [redacted].

Because the Offeror has noted that [redacted] the Government does not

find the Offeror non-compliant for these cells. Effectively, the Offeror has

provided a reason as to why some cells were left blank. Thus, based on

the particular circumstances of this Offeror’s Price Model, the

Government does not find the Offeror non-compliant for these blank

cells.

(capitalization and emphasis in original). For the column “Volume 2 Meets

Requirements,” the Army indicated “No.” (capitalization and emphasis in original).

Unicom

The Army reviewed Unicom’s proposal and found its Equipment List non-compliant

under Step 1. The February 15, 2024 Memorandum for Record for Unicom’s evaluation

provided:

Proposal submitted by UNICOM Government, Inc, [sic] dated 16 October

2023

43

1. The purpose of this memorandum is to document the determination that

made the above referenced proposal submitted by UNICOM Government,

Inc. Non-Compliant per the terms and conditions of subject solicitation for

the Information Technology Enterprise Solutions – 4 Hardware (ITES-4H)

multiple award IDIQ base contracts. The proposal was reviewed against the

strict compliance requirements identified throughout the solicitation. The

United States Government (USG) performed initial Step 1 Compliance

Checks to ensure the accuracy of proposals and reduce risk to the

Government. Adherence to the Strict Compliance requirements identified

throughout the solicitation is vital to ensure the Government receives a

complete and high-quality proposal. Strict Compliance requirements

encourage consistency and accuracy of information presented. Further,

ensuring the offeror has provided all necessary information is essential to

the efficient evaluation of proposals. The following are excerpts directly from

the Instructions to Offerors (Section L) and Evaluation Factors for Award

(Section M) of the RFP:

a. L.3 STRICT COMPLIANCE REQUIREMENT: All volumes and files have

strict compliance requirements and strict compliance to those requirements

will be evaluated. Any items identified as a STRICT COMPLIANCE

REQUIREMENT will be evaluated for compliance prior to any further

evaluation of the Offerors proposal. Failure to abide by the strict compliance

requirements for any of these factors will deem the Offerors proposal non-

compliant and will eliminate it from further consideration. Factors and

subfactors with strict compliance requirements are clearly identified

throughout these instructions.

b. L.4.1.3 – A proposal is presumed to represent the Offeror’s best efforts

to respond to the RFP. The Offeror must provide adequately detailed

information that complies with the solicitation requirements, allows for

meaningful review by the Government evaluators, and affirmatively

demonstrates the merits of its proposal. The Offeror shall provide sufficient

detail to substantiate the validity of all stated assertions and must not merely

repeat the RFP requirements, but rather must provide convincing

documentary evidence of how contract requirements will be met. Data not

submitted with the proposal, but submitted previously, or presumed to be

known (i.e., previous projects performed for the United States Government

(USG) [sic] will not be considered. Clarity and completeness are

essential.

c. M.3 EVALUATION METHODOLOGY: Step 1 - STRICT COMPLIANCE

REQUIREMENT: Proposals will be reviewed to determine if all compliance

requirements set forth in the Instructions to Offerors are satisfied. Failure to

provide proposals in compliance with the instructions specified as “STRICT

COMPLIANCE REQUIREMENTS” in the Instructions to Offerors of this RFP

shall render the Offeror’s proposal non-compliant. Any Offeror's proposal

44

determined non-compliant will not be evaluated and will not be further

considered for award. Only Offerors whose proposals are determined

compliant will move to Step 2 of the evaluation process.

2. Based upon a review of the strict compliance requirements set forth in

the solicitation, the following findings contributed to the determination that

above referenced proposal is non-compliant:

a. Volume 1 – Equipment List (Part A). Offeror’s Equipment List

(Attachment 0002) contained one blank cell in [redacted]. This cell is

material to the evaluation process.

The STRICT COMPLIANCE REQUIREMENT identified in the solicitation

states:

• L.5.1.1 PART A - Equipment List. STRICT COMPLIANCE REQUIREMENT:

ANY cells marked for Contractor Fill-In on the Equipment List that are left

blank or are unintelligible as to the product the Offeror is proposing shall

render the Offeror’s proposal non-compliant and will not be further

considered for award.

FINDING 1 – Blank Cell in Column D – Proposed Configuration: It is critical

to the evaluation process that all fillable cells in Column D of the Equipment

List are complete, as required by the solicitation. Completeness ensures

that the Offeror’s proposed configuration for each System Description

identified on each Catalog (Catalog I through Catalog VII) identifies clear

technical detail. Blank cells present a risk of ambiguity and misinterpretation

to the USG, as well as impede the efficient evaluation of proposals because

a blank cell does not allow the Government to clearly know what

product/item an Offeror is proposing. Offerors are required to provide a

proposed configuration for every System Description; thus, a complete

Equipment List is important to the Government’s evaluation. Here, the

Government cannot determine if the offeror meets the requirement

associated with [redacted] because the offeror has provided a blank cell.

3. Based upon the above findings and in accordance with the terms of the

RFP, Offeror AU [Unicom] is determined to be non-compliant, and its

proposal is removed from consideration for award. A letter communicating

the details that make its proposal non-compliant will be provided along with

a written debriefing.

(capitalization and emphasis in original; alterations added).

As reflected on the Army’s “Proposal Compliance Checklist” for Unicom, for the

column, “Meets terms and conditions of RFP?” the Army indicated: “No.” (capitalization

and emphasis in original). The Proposal Compliance Checklist reflected that Volume 1

45

was submitted and the Equipment List at Attachment 0002 was submitted as an Excel

file. For the column “All contractor filled cells are completed? (blank/unintelligible fills are

prohibited),” the Army indicated “No,” with the explanation:

1. 1 blank cell in Catalog II configuration that is material: [redacted]

2.Note: Blank cells were also identified in the Catalog ID column.

However, due to a solicitation ambiguity, these blank cells in Column E

do not make the Offeror non-compliant. See MFR regarding the

ambiguity for further details.

(emphasis in original). For the column “Volume 1 Meets Requirements,” the Army

indicated “No.” (capitalization and emphasis in original). Similarly for Volume 2, the

Proposal Compliance Checklist reflected that Volume 2 was submitted and for the column

“All contractor filled cells are completed? (blank/unintelligible fills are prohibited),” the

Army indicated “No,” with the explanation:

Please note [redacted]. As it pertains to this Offeror’s proposal, these

cells are immaterial as the Offeror input a response in Column D noting

its proposed technical approach, which explains why the cells are blank.

Here, [redacted]. Because the Offeror has explained why the cells are

blank, these cells are immaterial to the Step 1 evaluation.

(capitalization and emphasis in original). The Proposal Compliance Checklist asked if

“Volume 2 Meets Requirements,” and the Army indicated “No.”

Advanced Computer Concepts

The Army reviewed Advanced Computer Concepts’ proposal and found its

Equipment List non-compliant under Step 1. The February 14, 2024 Memorandum for

Record for Advanced Computer Concepts’ evaluation provided:

Proposal submitted by Advanced Computer Concepts, dated 16 October

2023

1. The purpose of this memorandum is to document the determination that

made the above referenced proposal submitted by Advanced Computer

Concepts Non-Compliant per the terms and conditions of subject solicitation

for the Information Technology Enterprise Solutions – 4 Hardware (ITES-

4H) multiple award IDIQ base contracts. The proposal was reviewed against

the strict compliance requirements identified throughout the solicitation. The

United States Government (USG) performed initial Step 1 Compliance

Checks to ensure the accuracy of proposals and reduce risk to the

Government. Adherence to the Strict Compliance requirements identified

throughout the solicitation is vital to ensure the Government receives a

complete and high-quality proposal. Strict Compliance requirements

46

encourage consistency and accuracy of information presented. Further,

ensuring the offeror has provided all necessary information is essential to

the efficient evaluation of proposals. The following are excerpts directly from

the Instructions to Offerors (Section L) and Evaluation Factors for Award

(Section M) of the RFP:

a. L.3 STRICT COMPLIANCE REQUIREMENT: All volumes and files have

strict compliance requirements and strict compliance to those requirements

will be evaluated. Any items identified as a STRICT COMPLIANCE

REQUIREMENT will be evaluated for compliance prior to any further

evaluation of the Offerors proposal. Failure to abide by the strict compliance

requirements for any of these factors will deem the Offerors proposal non-

compliant and will eliminate it from further consideration. Factors and

subfactors with strict compliance requirements are clearly identified

throughout these instructions.

b. L.4.1.3 – A proposal is presumed to represent the Offeror’s best efforts

to respond to the RFP [Request for Proposal]. The Offeror must provide

adequately detailed information that complies with the solicitation

requirements, allows for meaningful review by the Government evaluators,

and affirmatively demonstrates the merits of its proposal. The Offeror shall

provide sufficient detail to substantiate the validity of all stated assertions

and must not merely repeat the RFP requirements, but rather must provide

convincing documentary evidence of how contract requirements will be met.

Data not submitted with the proposal, but submitted previously, or

presumed to be known (i.e., previous projects performed for the United

States Government (USG) [sic] will not be considered. Clarity and

completeness are essential.

c. M.3 EVALUATION METHODOLOGY: Step 1 - STRICT COMPLIANCE

REQUIREMENT: Proposals will be reviewed to determine if all compliance

requirements set forth in the Instructions to Offerors are satisfied. Failure to

provide proposals in compliance with the instructions specified as “STRICT

COMPLIANCE REQUIREMENTS” in the Instructions to Offerors of this RFP

shall render the Offeror’s proposal non-compliant. Any Offeror’s proposal

determined non-compliant will not be evaluated and will not be further

considered for award. Only Offerors whose proposals are determined

compliant will move to Step 2 of the evaluation process.

2. Based upon a review of the strict compliance requirements set forth in

the solicitation, the following findings contributed to the determination that

above referenced proposal is non-compliant:

a. Volume 1 – Equipment List (Part A). Offeror’s Equipment List

(Attachment 0002) contained blank cells. Please see table below for the

specific cell that is material to the evaluation process and was found blank:

47

Equipment List Compliance Check

Tab Blank Cells in Column D – Proposed Configuration

[redacted] [redacted]

The STRICT COMPLIANCE REQUIREMENT identified in the solicitation

states:

• L.5.1.1 PART A - Equipment List. STRICT COMPLIANCE

REQUIREMENT: ANY cells marked for Contractor Fill-In on the Equipment

List that are left blank or are unintelligible as to the product the Offeror is

proposing shall render the Offeror’s proposal non-compliant and will not be

further considered for award.

FINDING 1 – Blank Cells in Column D – Proposed Configuration: It is critical

to the evaluation process that all fillable cells in Column D of the Equipment

List are complete, as required by the solicitation. Completeness ensures

that the Offeror’s proposed configuration for each System Description

identified on each Catalog (Catalog I through Catalog VII) identifies clear

technical detail. Blank cells present a risk of ambiguity and misinterpretation

to the USG, as well as impede the efficient evaluation of proposals because

a blank cell does not allow the Government to clearly identify which

product/item an Offeror is proposing. Offerors are required to provide a

proposed configuration for every System Description; thus, a complete

Equipment List is important to the Government’s evaluation. Here, the

Government cannot determine if the offeror meets the requirement

associated with [redacted] regarding “[redacted]” because the offeror has

provided a blank cell.

3. Based upon the above findings and in accordance with the terms of the

RFP, Offeror CM [Advanced Computer Concepts] is determined to be non-

compliant, and its proposal is removed from consideration for award. A letter

communicating the details that make its proposal non-compliant will be

provided along with a written debriefing.

(capitalization and emphasis in original; first alteration in original).

As reflected on the Army’s “Proposal Compliance Checklist” for Advanced

Computer Concepts, for the column, “Meets terms and conditions of RFP?” the Army

indicated: “No,” with the explanation: “Overall, this proposal is NON-COMPLIANT. Blanks

in Equipment List.” (capitalization and emphasis in original). The Proposal Compliance

Checklist reflected that Volume 1 was submitted and the Equipment List at Attachment

0002 was submitted as an Excel file. For the column “All contractor filled cells are

completed? (blank/unintelligible fills are prohibited),” the Army indicated “No,” with the

explanation:

48

1. 1 blank cell in [redacted] configuration that is material: [redacted].

2. Note: Blank cells were also identified in the Catalog ID column. However,

due to a solicitation ambiguity, these blank cells in Column E do not make

the Offeror non-compliant. See MFR regarding the ambiguity for further

details.

(capitalization and emphasis in original). For the column “Volume 1 Meets

Requirements,” the Army indicated “NO.” (capitalization and emphasis in original).

Additionally, for price, the Proposal Compliance Checklist reflected that Volume 2

was submitted and Attachment 0004 was submitted as an Excel file. For the column “All

contractor filled cells are completed? (blank/unintelligible fills are prohibited),” the Army

indicated “No,” with the explanation:

Please note [redacted]. As it pertains to this Offeror’s proposal, these cells

are immaterial as the Offeror input a response in Column D noting its

proposed technical approach, which explains why the cells are blank. Here,

[redacted]. Because the Offeror has explained why the cells are blank,

these cells are immaterial to the Step 1 evaluation.

Although noting that there were “33 Total Blank cells in Price Model,” for the column

“Volume 2 Meets Requirements,” the Army indicated “YES.” (capitalization and

emphasis in original).

As described above, in response to being eliminated by the Army under Step 1 of

the evaluation process, each of the seven protestors filed a pre-award bid protest in the

United States Court of Federal Claims, the above captioned bid protests, alleging the

Army arbitrarily and capriciously eliminated them from further evaluation of their proposals

for possible award of the procurement.

Protestors’ Complaints

GovWave

As stated above, the Army reviewed GovWave’s proposal and found GovWave’s

Past Performance proposal non-compliant under Step 1. In its amended complaint,

GovWave argues that the Army eliminated GovWave’s proposal

because, after its initial review of GovWave’s proposal, the Agency is

unsure whether GovWave has any adverse past performance. The Army

made this decision even though Solicitation No. W52P1J20R0082 required

offerors with adverse past performance to identify such contracts in their

proposal and provide various details and documents about their adverse

past performance, and GovWave’s proposal includes none of this

information because it does not have any adverse past performance to

address. The Army also made this decision despite several statements in

49

GovWave’s proposal that, like the absence of any identified contracts or

further details about adverse past performance, confirm it does not have

adverse past performance. For example, GovWave’s proposal states that

[redacted].

(internal references and footnote omitted). GovWave continues:

The Army believes it is justified in removing GovWave from the competition

(and the opportunity to provide ITES hardware for the next ten years) before

conducting a full evaluation of its proposal because the Army claims the

Solicitation contained a so-called “strict compliance requirement”

mandating that GovWave use specific language to state that it does not

have any adverse past performance. Yet, the Solicitation did not include

“magic language” that offerors had to use if they do not have adverse past

performance and, moreover, the Solicitation did not identify this instruction

as a strict compliance requirement. The operative strict compliance

requirement in the Solicitation only applied to the identification of recent and

relevant contracts that encountered performance problems, which, again,

GovWave does not have. There are other flaws in the Agency’s decision,

insofar as it indicates the Agency used an unstated evaluation criterion and

that it abused its discretion in not seeking clarification of the perceived

ambiguity or waiving an obvious and minor informality in GovWave’s

proposal. Indeed, this matter could be easily and quickly resolved through

clarification in a one-sentence email or a brief phone call through which

GovWave would confirm what it believes is already clear from its proposal:

namely, that it does not have any recent and relevant contracts that

encountered performance problems. Such a clarification would not require

a revision to GovWave’s proposal, would not delay the procurement any

longer than it takes the Agency to ask, “please confirm you have no adverse

past performance,” and would ensure the Agency has the benefit of

GovWave’s strong proposal in the competition for the Solicitation.

GovWave’s amended complaint has five counts: In Count One, GovWave alleges that

“[t]he Agency’s interpretation of the strict compliance requirement for adverse contract

performance is contrary to the Solicitation and constitutes use of an unstated evaluation

criterion.” (alteration added). In Count Two, GovWave alleges “[t]he Agency’s finding that

GovWave’s proposal does not comply with the instructions for adverse contract

performance is arbitrary and capricious.” (alteration added). In Count Three, GovWave

contends “[i]f the Agency had any doubt about whether GovWave had adverse Past

Performance, it should have sought clarification of GovWave’s proposal.” (alteration

added). In Count Four, GovWave alleges, “[i]n the alternative, the Agency’s decision to

exclude GovWave’s proposal for an obvious informality or minor irregularity is arbitrary,

capricious, and an abuse of discretion.” (alteration added). In Count Five, GovWave

argues “[a]lternatively, the Solicitation contained a latent ambiguity.” (alteration added).

In Count Six, GovWave argues that “[t]he Agency engaged in disparate treatment and

unequally evaluated GovWave’s proposal to its prejudice.” (alteration added). GovWave

asks this court to declare “the Agency’s evaluation of GovWave’s proposal arbitrary,

50

capricious, and contrary to law,” order the Army to “rescind its elimination of GovWave’s

exclusion from the competition and reinstate GovWave into Step 2 of the evaluation

process,” or, alternatively, “require the Agency to clarify its requirements in an amended

Solicitation, resolicit revised proposals, and evaluate proposals in accordance with the

law.”

Futron

As reflected above, the Army reviewed Futron’s proposal and found its Equipment

List non-compliant under Step 1. Futron’s complaint has a single count and alleges that

“[t]he Army abused its discretion by failing to allow Futron to correct the omission through

clarification,” arguing that “the agency “excluded Futron from competition because Futron

left one cell blank in its equipment list. Excluding Futron instead of seeking clarification

was improper. First, the error is minor and can easily be corrected. All information

pertaining to the [redacted] is featured in the cells above and below the blank,” and,

furthermore, that “the Army was on notice of the error.” (alteration added). Futron further

alleges that “[t]he Solicitation requirement also does not serve a substantive purpose or

deprive the Army of any substantive information.” (alteration added). Futron asks the court

to determine “that the Army’s decision to eliminate Futron from consideration was

arbitrary, capricious and irrational,” and “[r]equire the Army to evaluate Futron’s proposal.”

(alteration added).

Government Acquisitions

As indicated above, the Army determined Government Acquisitions’ Price proposal

was non-compliant under Step 1. Government Acquisitions’ amended complaint begins

by alleging

GAI’s [Government Acquisitions’] summary exclusion from evaluation under

the Army Contracting Command Solicitation W52P1J-20-R-0082 for

Information Technology Enterprise Solutions 4 Hardware was in error. The

Agency’s exclusion of GAI was arbitrary, capricious, an abuse of discretion,

and was otherwise contrary to law for the following reasons: the Agency’s

interpretation of Strict Compliance is arbitrary, capricious, and otherwise not

in accordance with law; the Agency’s finding that GAI’s proposal does not

comply with the instructions for cell completion is arbitrary, capricious and

otherwise not in accordance with law; the Agency abused its discretion by

not waiving the blank cell as a minor informality or irregularity; the Agency’s

failure to seek clarification was arbitrary, capricious, and was otherwise not

in accordance with law; the Solicitation was latently ambiguous; the Agency

failed to comply with stated evaluation criteria and applied unstated

evaluation criteria to the evaluation of offers; and the Agency disparately

evaluated proposals.

(internal references omitted; alteration added). Government Acquisitions’ amended

complaint noted that for the pricing information, the

51

data had to be entered manually. The use of formulae to populate the

spreadsheet was not permitted, and the spreadsheet was password

protected. Offerors could not use common programs both internal and

external to Excel to prepare or review the Amendment 31 spreadsheet.

Offerors were given 18 calendar days to complete the 1,352 cells in the

pricing spreadsheet. In the course of manually moving the data from the

original spreadsheets Amendment 31 spreadsheet, GAI left Cell G6, Fixed

Discount for Warranty Variations, on Tab Catalog III-O blank. It was GAI’s

understanding that the government would not assign a 0 to a blank cell.

Normally when a column is summed in an Excel spreadsheet, it only sums

the numbers occurring after the blank space. For example, if there are 10

rows in a column of numbers and the 6th row is a blank, the system will only

sum the last 4 rows. When this happens, the user is alerted that there must

be a blank cell somewhere because the total number will be off. Apparently,

contrary to what the solicitation stated regarding blank cells, the government

had an algorithm embedded in the spreadsheet that assigned a zero value

to the blank cell, or its formula construction led to that result. Had the

spreadsheet provided by the Army not assigned a 0 value to the blank cell,

the whole column would not have been included in the total and GAI would

have been alerted that the total was dramatically different than expected

and would have gone looking for a blank cell. GAI’s Total Contract Line

Price was only [redacted] higher than presented by GAI’s initial submission,

so that did not raise any red flags for GAI.

(internal references omitted; emphasis in original). Government Acquisitions’ amended

complaint has seven counts, in Count One, Government Acquisitions alleges that “[t]he

Agency's interpretation of the strict compliance requirement regarding blank cells is

arbitrary, capricious, and otherwise not in accordance with law.” (alteration added). In

Count Two, Government Acquisitions argues “[t]he Agency's finding that GAI's proposal

does not comply with the instructions for cell completion is arbitrary and capricious.”

(alteration added). In Count Three, Government Acquisitions alleges that “[t]he Agency

abused its discretion by not waiving the blank cell G6 as a minor informality or irregularity.”

(alteration added). In Count Four, Government Acquisitions claims that “[i]f the Agency

had any doubt about GAI’s discount percentage it should have sought clarification of

GAI's proposal.” (alteration added). In Count Five, Government Acquisitions alleges that

“[t]he Solicitation was latently ambiguous.” (alteration added). In Count Six, Government

Acquisitions alleges that “[t]he Agency’s failure to comply with the stated evaluation

criteria was arbitrary and capricious.” (alteration added). In Count Seven, Government

Acquisitions argues that “[t]he Agency evaluated offers unequally.” (alteration added).

Government Acquisitions asks the court to order “the Agency to rescind its elimination of

GAI's exclusion from the competition and reinstate GAI into Step 2 of the evaluation

process,” or “[a]lternatively, require the Agency to clarify its requirements in an amended

Solicitation, resolicit revised proposals, and evaluate proposals in accordance with the

law.” (alteration added).

52

DH Technologies

As referenced above, the Army reviewed DH Technologies’ proposal and found its

Price proposal non-compliant under Step 1. Prior to filing a complaint, and then an

amended complaint in this court, DH Technologies filed a bid protest at the GAO “that

was dismissed by the GAO as a result of other protests being filed at the Court.” DH

Technologies’ amended complaint in this court has five counts. In Count One, DH

Technologies alleges that “[t]he very information that the Agency rejected DH Tech’s

proposal for being missing was actually found in other parts of its proposal in the same

volume,” and “[w]hile the Solicitation did contain a prohibition on cross-referencing the

five separate volumes as each volume self-contained,” “there was no prohibition in the

Solicitation on the Agency cross-referencing within a particular volume. Since the alleged

missing information was in the proposal, albeit in another place than where the Agency

found it to be missing, it was still in the same volume proposal.” (alterations added;

internal references omitted). In Count Two of the amended complaint, DH Technologies

alleges the “Army improperly rejected DH Tech’s proposal for failure to meet a minor and

immaterial defect.” In Count Three, DH Technologies alleges that “[t]he Agency should

have waived the requirement.” (alteration added). In Count Four, DH Technologies’

amended complaint argues that the “Agency evaluated offerors unequally.” In Count Five,

DH Technologies alleges that the “Agency engaged unequal clarifications/discussions.”

DH Technologies requests the court find the Army’s actions were “irrationally based [sic],

arbitrary, capricious, and contrary to applicable statutes and regulations,” and “require the

Agency to properly evaluate Plaintiff’s proposal.” (alteration added).

Enterprise Technology Solutions

As referenced above, the Army reviewed Enterprise Technology Solutions’

proposal and found its Price proposal non-compliant under Step 1. Enterprise Technology

Solutions’ amended complaint argues that

[t]he Army deviated from its own Solicitation criteria in its evaluation of

ETSI’s [Enterprise Technology Solutions’] proposal—but followed such

criteria for other proposals that moved on to step two of the evaluation; and

thus, it unequally evaluated offerors. The Army engaged in unfair and

unequal clarifications with offerors. It failed to provide an administrative

record sufficiently justifying its evaluation decisions. And the Army was

latently ambiguous as to the utilization of the price model spreadsheet for

this Solicitation. Were proposals properly evaluated, ETSI would have

advanced in this competition, with a substantial chance of award.

(alterations added; internal references omitted). Enterprise Technology Solutions’

amended complaint argues that

[t]he Administrative Record produced by the Army for this case shows

multiple offerors deemed compliant and allowed to move on to step two that

had blank fields in their price model—blank fields identical to the blank fields

53

in ETSI’s price model that the Army specifically relied on to deem ETSI non-

compliant. The Administrative Record shows multiple offerors deemed

compliant and allowed to move on to step two that filled out their price

models in the same and/or similar fashion as ETSI. The Administrative

Record shows multiple offerors deemed compliant and allowed to move on

to step two that included non-numerical explanations (i.e., “N/A”) in fields of

their price models the same as and/or similar to ETSI’s non-numerical

explanations in those same fields of ETSI’s price model, upon which Army

specifically relied to deem ETSI non-compliant. The Administrative Record

even shows at least one offeror excluded from the competition at step one

purportedly based on blank fields in another proposal attachment—but

which had some of the same blank fields and similar non-numerical

explanations in certain fields of its price model as ETSI’s price model was

excluded for—and which: (i) received a notification from the Army of non-

compliance and exclusion from competition for blank fields in another

proposal attachment; (ii) apparently, subsequently sent the Army a

response or responses to (or otherwise communicated with the Army

responding to) the Army’s notification of its noncompliance and exclusion

from competition; (iii) received a second notification letter from the Army

amending the Army’s position on its compliance as a result of the offeror’s

communicated responses; and (iv) was then allowed back in the

competition and promoted to step two of the competition.

(emphasis in original; alteration added). In Count One of five counts in Enterprise

Technology Solutions’ amended complaint, the protestor alleges that “[t]he Army’s

evaluation of ETSI deviated from the Solicitation.” (alteration added). In Count Two,

Enterprise Technology Solutions’ amended complaint alleges “[t]he Army engaged in

unequal evaluation of offerors.” (alteration added). In Count Three, Enterprise Technology

Solutions alleges that “[t]he Army engaged in unequal clarifications with offerors.”

(alteration added). In Count Four of the amended complaint, Enterprise Technology

Solutions alleges that “[t]he Army inadequately documented its evaluation.” (alteration

added). In Count Five, Enterprise Technology Solutions alleges that “[t]he debrief shows

a latent ambiguity/contra proferentem.” (alteration added). Enterprise Technology

Solutions seeks an order from this court declaring “that the Army’s evaluation of ETSI’s

proposal and resulting elimination of ETSI from competition were arbitrary and

capricious,” and instructing the “Army to conduct a re-evaluation of certain or all

proposals, in line with its equal evaluation requirements, consistent with the reasonable

interpretation ETSI (and potentially others) applied,” or, “[a]lternatively, require the Army

to officially clarify its requirements related to the price model attachment in the Solicitation

in an amended Solicitation, ensure the input the Army is requiring for each field is not

limited by the spreadsheet, and allow for relevant revisions to all proposals,” and

subsequently require the Army to re-evaluate all the proposals. (alteration added).

Unicom

54

As described above, the Army reviewed Unicom’s proposal and found its

Equipment List non-compliant under Step 1. Unicom’s complaint in this court alleges

[c]ontrary to the express terms of the Solicitation, the Agency impermissibly

broadened its Step 1 evaluation and disqualified UGI’s [Unicom’s] proposal

based on an alleged “material” omission in UGI’s proposal. Specifically, the

Agency eliminated UGI’s proposal based on a Solicitation term that was not

a “Strict Compliance Requirement” and UGI’s inadvertent and immaterial

omission of information from one cell of a fifty-four (54) page, seven (7) tab

Excel spreadsheet that UGI should have been permitted to correct.

(alterations added). Unicom’s complaint continues:

The Agency contends that exclusion of UGI from the competitive range was

proper because UGI failed to comply with a “Strict Compliance

Requirement” of the Solicitation, compliance with which was to be evaluated

at Step 1 of a three-step proposal evaluation process. The Agency’s

position is unsupported by the terms of the Solicitation. Completion of the

missing cell was not a Strict Compliance Requirement under the Solicitation

and, therefore, was not subject to the Step 1 evaluation. Moreover, the

omission of information from a single spreadsheet cell was an obvious,

immaterial, and clerical error. The relevant information was reflected

elsewhere in UGI’s proposal.

(internal references omitted). Unicom’s complaint has four counts. Count One alleges

“[t]he Agency failed to properly perform its ‘Step 1’ evaluation in accordance with the

terms of the Solicitation and applied unstated evaluation criteria.” (alteration added).

Count Two alleges “[t]he Agency’s finding that UGI’s proposal does not comply with the

Solicitation instructions and exclusion of UGI’s proposal from the Step 2 evaluation is

arbitrary and capricious.” (alteration added). Unicom’s complaint at Count Three alleges

“[i]f the Agency had any doubt about whether UGI’s proposed Performance Notebook

(GSS High End Laptop) product included [redacted], the Agency should have permitted

UGI to correct or clarify an obvious and immaterial clerical error in its proposal.” (alteration

added). Count Four alleges “[i]n the alternative, the Agency’s decision to exclude UGI’s

proposal for an obvious informality or minor irregularity is arbitrary, capricious, and an

abuse of discretion.” (alteration added). Unicom seeks a court order that “the Agency’s

evaluation of UGI’s Proposal was arbitrary, capricious, and contrary to law,” and “requiring

the Agency to rescind its elimination of UGI’s exclusion from the competitive range and

reinstate UGI into Step 2 of the Solicitation evaluation process,” requiring “the Agency to

permit UGI to clarify and confirm that its proposed Performance Notebook (GSS High End

Laptop) [redacted],” and requiring “the Agency to advance UGI’s Proposal to Step 2 of

the evaluation process.”

55

Advanced Computer Concepts

As indicated above, the Army reviewed Advanced Computer Concepts’ proposal

and found its Equipment List non-compliant under Step 1. Prior to filing a complaint in this

court, Advanced Computer Concepts filed a bid protest at the GAO. The GAO

subsequently “dismissed the protest because the ‘matter involved is currently pending

before a court of competent jurisdiction.’” Advanced Computer Concepts’ complaint in this

court alleges that Advanced Computer Concepts’

proposed Equipment List contained one minor typographical error—among

over a thousand cells that needed to be completed in the Equipment List,

ACC [Advanced Computer Concepts] inadvertently a [sic] word from one

single cell—[redacted]. In [redacted], ACC was to confirm that the [sic] its

[redacted] met the requirement to include a [redacted]. Despite the single

blank cell (which the Agency expected to be completed using the word,

“meets”), ACC’s proposal made an unequivocal commitment to provide a

solution that met all of the RFP’s requirements—including the requirement

for a [redacted]. Based upon the contents of ACC’s proposal, there could

have been no doubt in the evaluators’ minds that ACC’s solution was fully

compliant with all of the RFP requirements. However, rather than waiving

this minor typographical error or conducting a clarification to allow ACC to

add the word, “meets” to [redacted] of its Equipment List, the Army

improperly elevated form over substance, concluding that this single

missing word—a word that had no material impact on ACC’s proposal—

justified ACC’s elimination from the procurement. The Army had no rational

basis to eliminate ACC’s proposal, rather than waiving or clarifying the

immaterial missing word. The Army’s decision to eliminate ACC entirely

failed to consider an important aspect of the issue: that ACC’s proposal

made clear—even without the missing word—that its performance laptop

met the requirement to include [redacted]. Indeed, because ACC’s

Equipment List affirmatively stated that its solution included [redacted] and

that it would provide a computer using Windows 10 or higher, ACC’s

solution, by definition, included a [redacted]. It would have been impossible

to offer ACC’s solution without a [redacted]. As a result, there should have

been no doubt in the evaluators’ minds that ACC’s solution met the

requirement for a [redacted].

(emphasis in original; alterations added; internal reference omitted). Advanced Computer

Concepts’ complaint has three counts. In Count One of Advanced Computer Concepts’

complaint, Advanced Computer Concepts alleges that “[t]he Army’s elimination of ACC’s

proposal based on its blank [redacted] was arbitrary and capricious.” In Count Two,

Advanced Computer Concepts alleges that “[t]he Army acted in an arbitrary and

capricious manner by failing to waive the minor informality in ACC’s proposal.” (alteration

added). In Count Three, Advanced Computer Concepts alleges “[t]he Army acted in an

arbitrary and capricious manner by failing to engage in clarifications with ACC regarding

[redacted].” (alteration added). Computer Concepts requests the court to “enjoin the Army

56

from making award under the Solicitation until the flawed described above are remedied,”

and Advanced Computer Concepts additionally requests the court order “the Army to

include ACC in the competition and reinstate ACC into Step 2 of the evaluation process.”

In response to the pre-award bid protests, the court held a series of hearings to

address the various bid protests and determine how to proceed in all seven bid protests.

After discussions with the parties, the court instructed the defendant to file the

Administrative Record. Subsequently, the parties briefed cross-motions for judgment on

the Administrative Record and the court held oral argument in all seven bid protests.

DISCUSSION

Cross-Motions for Judgment on the Administrative Record

Regarding the parties’ arguments in the cross-motions for judgment on the

Administrative Record, as indicated by the United States Court of Appeals for the Federal

Circuit:

Cross-motions for judgment on the administrative record are governed by

Rule 52.1(c) of the Rules of the United States Court of Federal Claims. “In

deciding these motions, the [Claims Court] considers ‘whether, given all the

disputed and undisputed facts, a party has met its burden of proof based on

the evidence of record.’”

XOtech, LLC v. United States, 950 F.3d 1376, 1379–80 (Fed. Cir. 2020) (alteration in

or

This text is long and has been trimmed here. Open the source document for the complete record.