“[T]he capable-of-repetition doctrine applies only in exceptional situations, and generally only where the named plaintiff can make a reasonable showing that he will again be subjected to the alleged illegality.”
How later courts described this case
- “[T]he capable-of-repetition doctrine applies only in exceptional situations, and generally only where the named plaintiff can make a reasonable showing that he will again be subjected to the alleged illegality.”
Written by the judges who cited it.
The opinion
THE UNITED STATES DISTRICT COURT
FOR THE MIDDLE DISTRICT OF PENNSYLVANIA
WAYNE LAND AND MINERAL :
GROUP, LLC,
Plaintiff,
V. 3:16-CV-00897
: (JUDGE MARIANI)
DELAWARE RIVER BASIN :
COMMISSION,
Defendant, and :
DELAWARE RIVERKEEPER NETWORK
MAYA K. VAN ROSSUM, THE
DELAWARE RIVERKEEPER,
Intervenors-Defendants.
MEMORANDUA! OPINION
I. INTRODUCTION
Defendant Delaware River Basin Commission’s Suggestion of Mootness and Motion
to Dismiss (Doc. 216) is pending before the Court. With the Motion, Defendant Delaware
River Basin Commission (“DRBC’” “Commission’), requests that the Court dismiss this case
as moot based on regulations promulgated by the DRBC which prohibit high-volume
hydraulic fracturing in the Delaware River Basin (“Basin’). (/d. 9] 7-16.) Plaintiff Wayne
Land and Mineral Group, LLC, (“WLMG’) opposes the Motion, asserting that this case is not
moot: as long as “the Commission’s assertion that it has project review jurisdiction over
WLMG's proposed development under Section 3.8 of the Compact remains, WLMG
continues to be injured by it, and a declaration by this Court would redress the injuries
alleged in WLMG's complaint.” (Doc. 218 at 1.) For the reasons that follow, the Court will
grant Defendant Delaware River Basin Commission’s Suggestion of Mootness and Motion
to Dismiss (Doc. 216).
Il. BACKGROUND
In the Complaint filed on May 17, 2016, Plaintiff asked the Court to
[djeclare that the Commission does not have jurisdiction over, or the authority
to review and approve, or to require WLMG to seek prior approval from the
Commission for, or to otherwise preclude the development of, WLMG’s
proposed well pad, appurtenant facilities or the related activities to be carried
out on the Property.
(Doc. 1 at 18.) In its opinion concerning the DRBC’s motion to dismiss, the Court of Appeals
for the Third Circuit stated that WLMG’s Complaint “sought a ruling in the District Court
under the Declaratory Judgment Act that an interstate compact does not give the Delaware
River Basin Commission authority to review Wayne's proposed fracking activities." Wayne
Land & Min. Grp. LLC v. Delaware River Basin Comm'n, 894 F.3d 509, 515 (3d Cir. 2018).
The Circuit Court noted that the parties’ jointly submitted appendices which include the
statement that WLMG “sought a declaratory judgment from the District Court that the
Commission's jurisdiction extends only to matters fitting the Compact's definition of ‘project’
and that the activities proposed by Wayne do ‘not constitute a ‘project’ under Section 3.8 of
the Compact.” 894 F.3d at 519 & n.2 (citing Joint App. at 77-78).)
WLMG sought the requested relief because it “owns approximately 180 acres of
land, including the natural gas and minerals present on the land, in Wayne County,
Pennsylvania, and approximately 75 acres of the land owned by WLMG is located in the
Basin (the ‘Property’).” (Doc. 1 J 12.) The Property “is located in a part of the Basin that
overlays natural gas reserves in shale formations.” (/d. J 13.) WLMG states that it “acquired
the Property with an intent to explore for, extract and sell the natural gas located in shale
formations associated with the Property and other nearby land in order to recoup, and earn
a reasonable return on, its investment in the Property.” (/d. | 21.)
Defendant Delaware River Basin Commission was created by the Delaware River
Basin Compact (“Compact”), an interstate agreement entered into in 1961 which aimed to
ensure “a unified approach to the conservation, utilization, development, management, and
control of the water and related resources of the Basin.” Wayne Land, 894 F.3d at 515. The
Delaware River Basin is “an area of land surrounding and draining into the Delaware River
that extends through parts of Delaware, New Jersey, New York, and Pennsylvania (the
“Basin States”). /d. The Commission is comprised of the Governors of the Basin States and
a commissioner appointed by the president of the United States. /d.
Summarizing the powers and responsibilities of the Commission and Compact
provisions, the Third Circuit stated that the Compact gives the Commission a broad range of
powers to protect water quantity and quality within the Basin. /d. Consistent with the
Commission’s responsibility, the Commission has the authority to review “projects”
undertaken in the Basin if they will have “a substantial effect on the water resources of the
[Bjasin[.]” /d. at 515-16 (quoting Joint App. at 370, § 3.8). The Commission has the power to
promulgate rules “for the procedure of submission, review and consideration of projects|.]”
Id. at 516 (quoting Joint App. at 370, § 3.8). More fully, § 3.8 of the Compact states the
criteria for that review process as follows:
“No project having a substantial effect on the water resources of the [B]asin
shall hereafter be undertaken by any person, corporation or governmental
authority unless it shall have been first submitted to and approved by the
[Clommission, subject to the provisions of Sections 3.3 and 3.5. The
[C]ommission shall approve a project whenever it finds and determines that
such project would not substantially impair or conflict with the comprehensive
plan and may modify and approve as modified, or may disapprove any such
project whenever it finds and determines that the project would substantially
impair or conflict with such plan.”
Wayne Land, 894 F.3d at 516 (quoting Joint App. at 370, § 3.8).
The Compact also gives the Commission power to address pollution within the
Basin. “Under Article 5 of the Compact, “[t]he [C]lommission may undertake investigations
and surveys, and acquire, construct, operate and maintain projects and facilities to control
potential pollution and abate or dilute existing pollution of the water resources of the
[Blasin.” /d. (quoting Joint App. at 372, § 5.1).
As a general matter, “[i]t is plain that the Commission has broad rulemaking and
enforcement powers. Under Article 14 of the Compact, the Commission may ‘[mjake and
enforce reasonable rules and regulations for the effectuation, application and enforcement
of this [Clompact[.!” /d. at 517 (quoting Joint App. at 389, § 14.2(a)).
In the Complaint, WLMG expresses the source of its disagreernent with the
Commission to be the interpretation of § 3.8 which gives the Commission jurisdiction over
natural gas well pads and related facilities and activities based on its determination that well
pads constitute “projects” requiring Commission approval and that the Commission would
not consider applications for well pads until after it adopted relevant regulations. (Doc. 1 9
17-19.) WLMG refers to the DRBC’s position as a “de facto moratorium.” (Doc. 1 ¥] 20.)
The Commission asserted authority over fracking-related activities in the Basin in
2009, when “then-Executive Director of the Commission, Carol Collier, issued a moratorium
banning most natural gas fracking projects located ‘within the drainage area of Special
Protection Waters,’ unless there was prior Commission approval.” Wayne Land, 894 F.3d at
517-18.
The initial 2009 moratorium covered projects that included a “drilling pad
upon which a well intended for eventual production is located, all appurtenant
facilities and activities related thereto and all locations of water withdrawals
used or to be used to supply water to the project.” (Joint App. at 98.) But, at
that time, “[wjells intended solely for exploratory purposes” were not covered
by the moratorium. (Joint App. at 98.)
Collier expanded that moratorium in 2010 in a supplemental notice
letter. She withdrew the exclusion for exploratory wells and stated that “all
natural gas well project sponsors, including the sponsors of natural gas well
projects intended solely for exploratory purposes, ... may not commence any
natural gas well project for the production from or exploration of shale
formations within the drainage area of Special Protection Waters without first”
obtaining the approval of the Commission. (Joint App. at 113 (emphasis
omitted).) Collier said that the inclusion of exploratory wells in the moratorium
would “support the Commission's goal that exploratory wells do not serve as a
source of degradation of the Commission's Special Protection Waters,” by
“remov[ing}] any regulatory incentive” to engage in purportedly “exploratory”
drilling before the Commission could implement final natural gas regulations.
(Joint App. at 113.)
894 F.3d at 518.
The DRBC issued proposed fracking regulations at the end of 2010 and released
revised draft regulations in 2011. /d. at 518 n.5. No final decision had been made on the
draft regulations at the time this action was filed in 2016.1 See id.
In this factual context, the DRBC filed Defendant Delaware River Basin
Commission’s Motion to Dismiss the Complaint (Doc. 12).With the March 23, 2017,
Memorandum Opinion and Order (Docs. 92, 93), the Court granted DRBC’s motion,
concluding that WLMG’s proposed activities within the Basin constituted a “project” which
required WLMG to submit an application to the Commission. (Doc. 92 at 43.) WLMG
appealed the Court’s decision and the Third Circuit vacated this Court's dismissal based on
its determination that “the meaning of the word ‘project’ as used in the compact is
ambiguous.” Wayne Land, 894 F.3d at 515. The Circuit Court remanded the case “for fact-
finding on the intent of the compact’s drafters.” /d.
Following an extensive discovery period, Defendant Delaware River Basin
Commission filed a Motion for Partial Summary Judgment (Doc. 169) on April 6, 2020, and
Intervenors-Defendants Delaware Riverkeeper Network and Maya Van Rossum filed their
1 In September 2017, the DRBC adopted a resolution instructing its Executive Director to publish
new proposed natural gas fracking regulations by November 30, 2017. Wayne Land, 894 F.3d at 518 n.5.
The proposed regulations were published on that day. /d. As set out in the text infra, relevant regulations
were adopted on February 25, 2021.
Motion for Summary Judgment (Doc. 171) on April 7, 2020. On January 6, 2021, the Court
denied both motions (see Docs. 205-207), concluding that “the ambiguity identified by the
Circuit Court cannot be resolved on summary judgment given the dearth of agreed upon
facts, the parties’ divergent arguments based on citation to extrinsic evidence, [and] issues
of credibility whose resolution is inappropriate on summary judgment.” (Doc. 205 at 38; see
also Doc. 207 at 5.)
On January 14, 2021, the Court scheduled trial to commence on October 18, 2021.
(Doc. 214.) On February 25, 2021, the Court received a letter from Kenneth Warren, the
DRBC’s counsel, informing the Court that the DRBC had adopted final regulations on that
date “prohibiting high volume hydraulic fracturing in hydrocarbon bearing rock formations
within the Delaware River Basin.” (Doc. 215 at 1.)
Section 440.3 of the regulations adopted on February 25, 2021, address high volume
hydraulic fracturing (“HVHF”) and provide as follows:
(a) Determination. The Commission has determined that high volume
hydraulic fracturing poses significant, immediate and long-term risks to the
development, conservation, utilization, management, and preservation of the
water resources of the Delaware River Basin and to Special Protection Waters
of the Basin, considered by the Commission to have exceptionally high scenic,
recreational, ecological, and/or water supply values. Controlling future pollution
by prohibiting such activity in the Basin is required to effectuate the
Comprehensive Plan, avoid injury to the waters of the Basin as contemplated
by the Comprehensive Plan and protect the public health and preserve the
waters of the Basin for uses in accordance with the Comprehensive Plan.
(b) Prohibition. High volume hydraulic fracturing in hydrocarbon bearing rock
formations is prohibited within the Delaware River Basin.
Resolution No. 2021-01, p. 11 (hitps:/Avww.nj.goc/drbc/libraryy/documents/Res2021-
01 HVHF.pdf.}.2 Resolution 2021-01 § C provides that
[tlhe Comprehensive Plan amendments and final rules adopted today replace
the Executive Director Determinations of May 19, 2009, June 14, 2010 and July
23, 2010. The Resolution for the Minutes of May 5, 2010, which postponed the
Commission’s consideration of well pad projects until the adoption of final rules,
expires by its own terms.
Resolution No. 2021-01, p. 5 (https://www.nj.goc/drbc/libraryy/documents/Res2021-
_HVHF.pdf.).
On April 13, 2021, the DRBC filed the motion under consideration here, Defendant
Delaware River Basin Commission’s Suggestion of Mootness and Motion to Dismiss (Doc.
216). As noted above, WLMG argued that the case was not moot. See supra p. 1. WLMG
alternatively requested that the Court stay the case pending the outcome of a case filed in
the United States District Court for the Eastern District of Pennsylvania challenging the
newly-adopted regulatory ban. (Doc. 218 at 5-6.) In its reply brief, the DRBC continued to
maintain that dismissal of the case was the appropriate outcome but stated “[i]f.. . the
Court were to find this case to remain justiciable, .. . DRBC agrees that a stay would be
2 The Definitions section of Resolution 2021-01 provides the following relevant definitions:
High volume hydraulic fracturing (HVHF) - hydraulic fracturing using a combined total of
300,000 or mcre gallons of water during all stages in a well completion, whether the well is
vertical or directional, including horizontal, and whether the water is fresh or recycled and
regardless of the chemicals or other additives mixed with the water.
Hydraulic Fracturing - a technique used to stimulate the production of oil and natural gas
from a well by injecting fracturing fluids down the wellbore under pressure to create and
maintain induced fractures in the hydrocarbon-bearing rock of the target geologic form ation.
Resolution No. 2021-01, p. 11 (https:/Awww.nj.goc/drbc/libraryy/documents/Res2021-01_HVHF.pdf,).
appropriate.” (Doc. 219 at 9.) The Court conducted a telephone conference on May 18,
2021, to determine the viability of a stipulated stay given the procedural posture of the case.
(See Docs. 220- 223.) The parties agreed that a stay was appropriate given the then-
pending Eastern District litigation concerning the validity of the regulations banning HDHF in
the Basin. The parties submitted a draft stipulation for the Court's approval. (Doc. 224.) The
Court approved the Stipulation by Order of May 21, 2021. (Doc. 225.)
Thereafter, the parties filed the required status reports (Docs. 227-229), culminating
with the report that the relevant litigation had been concluded with the Third Circuit's
decision in Yaw v. DRBC, 49 F.4th 302 (3d Cir. 2022), which affirmed the District Court's
dismissal of the action for lack of standing. (Doc. 229 at 4.) With the established regulations
remaining intact, DRBC suggested a stipulation to dismiss this case without prejudice;
WLMG did not agree. (/d.) Given this procedural posture, Defendant Delaware River Basin
Commission's Suggestion of Mootness and Motion to Dismiss (Doc. 216) is ripe for
disposition.
Ill. ANALYSIS
As set out above, the DRBC requests that the Court dismiss this case as moot
based on regulations promulgated by the DRBC which prohibit high-volume hydraulic
fracturing in the Delaware River Basin. (Doc. 216 J] 7-16.) WLMG opposes the Motion,
asserting that this case is not moot: as long as “the Commission's assertion that it has
project review jurisdiction over WLMG's proposed development under Section 3.8 of the
Compact remains, WLMG continues to be injured by it, and a declaration by this Court
would redress the injuries alleged in WLMG’s complaint.” (Doc. 218 at 1.) For the reasons
that follow, the Court concludes that this case is moot.
Article Ill of the Constitution dictates that a federal court may adjudicate “only actual,
ongoing cases or controversies.” Lewis v. Continental Bank Corp., 494 U.S. 472, 477
(1990); Burkey v. Marberry, 556 F.3d 142, 147 (3d Cir. 2009). “This case-or-controversy
requirement subsists through all stages of federal judicial proceedings [and for jurisdiction to
exist the] parties must continue to have a ‘personal stake in the outcome’ of the lawsuit.”
Spencer v. Kemna, 523 U.S. 1, 7 (1998) (quoting Lewis v. Continental Bank Corp., 494 U.S.
472, 477-78 (1990)); see also Uzuegbunam v. Preczewski, 592 U.S. 279, 282 (2021).
Uzuegbunam explains that
[tlhe doctrine of standing generally assesses whether that interest exists at the
outset, while the doctrine of mootness considers whether it exists throughout
the proceedings. To demonstrate standing, the plaintiff must not only establish
an injury that is fairly traceable to the challenged conduct but must also seek a
remedy that redresses that injury. And if in the course of litigation a court finds
that it can no longer provide a plaintiff with any effectual relief, tie case
generally is moot.
592 U.S. 279, 282: see also Road-Con, Inc. v. City of Philadelphia, 120 F.4'h 346, 356 (3d
Cir. 2024). The question of mootness “turns on the relief sought.” Road-Con, 120 F.4' at
356 (citing Doe v. Delie, 237 F.3d 309, 314 (3c Cir. 2001)).
The Court of Appeals for the Third Circuit provided a comprehensive analysis of
Article |! mootness in Gulden v. Exxon Mobil Corp., 119 F.4th 299 (3d Cir. 2024), beginning
10
with the general proposition that “a case [is] moot in the Article Ill sense, [if] all plaintiffs who
once had Article Ill standing . . . have lost it, and none of the recognized exceptions to
mootness can apply.” /d. at 305 (citing Chafin v. Chafin, 568 U.S. 165, 172 (2013)).
Recognized standing elements are: “(i) an injury-in-fact; (ii) fairly traceable to the
defendant's conduct; and (iii) capable and likely of being prevented or redressed through
the exercise of traditional judicial powers.” /d. (citing Spokeo, Inc. v. Robins, 578 U.S. 330,
338 (2016)). Gulden further provides that
the loss of one or more of those elements during the pendericy of the litigation,
if established by the defendant, subjects the affected claims or requests for
relief to potential dismissal on mootness grounds. . . . The loss of Article Ill
standing by itself, however, does not moot a case; the defendant must also
demonstrate that no mootness exception applies... . Thus, a case cannot be
moot if a plaintiff establishes Article IIl standing, and the defendant is unable to
demonstrate both the loss of standing and the inapplicability of the exceptions
to mootness.
119 F.4th at 305 (internal citations omitted). Gulden proceeds with the mootness analysis by
first assessing whether the defendant established that the plaintiff had lost standing based
on the absence of a required element and then considers whether a recognized exception
to mootness existed. /d. at 306-10. The Court will proceed in a similar manner.
A. Continuation of Standing Requirements
Early in this litigation, the DRBC sought dismissal of WLMG‘%s complaint on
numerous grounds, including that the Court did not have subject matter jurisdiction based
on WLMG's lack of standing. (See Doc. 92 at 24.) The Court found that WLMG had
standing based on the following analysis of the requisite elements.
11
The Court is satisfied that WLMG has met its burden to demonstrate it
has standing. First, WLMG’s Complaint sufficiently alleges that it is suffering an
injury in fact. WLMG intends to construct a well pad, drill an exploratory well
on its Property, and commence hydraulic fracturing “as soon as the uncertainty
and threat of fines, penalties and other sanctions resulting from the
Commission’s assertion of jurisdiction is resolved.” (Doc. 22, at 30). “Absent
the relief requested in its Complaint, WLMG cannot develop the natural gas on
its Property in a reasonable and timely manner.” Id. In the Complaint, WLMG
further alleges that it “has incurred, and will continue to incur, economic injury
by being prevented from exploring for, extracting and selling natural gas
associated with the Property and also from benefitting from an increase in the
market value of the property.” /d. The Court is satisfied that WLMG has
demonstrated an injury in fact.
Second, the Court agrees with WLMG that its injury has a sufficient
causal connection to the DRBC’s conduct. As WLMG notes, “[t]he material and
adverse effect on WLMG's rights to use the Property and to conduct a lawtul
business activity is caused by the Commission's ... assertion of jurisdiction,
not simply by the existence of the Compact,” (/d. at 31), and “[n]o action of a
third party is a more immediate cause of these harms.” /d.
Finally, there is a likelihood that WLMG's injury will be redressed by a
favorable decision of this Court. A decision in favor of WLMG would permit it
to plan and develop the Property without first submitting an application to the
DRBC for its approval.
(Doc. 92 at 27-28.)
Turning to whether the DRBC has shown that the standing elements are no longer
satisfied, the DRBC asserts that declaratory relief would not redress WLMG’s alleged injury.
(Doc. 217 at 11; Doc. 219 at 2.) The DRBC first contends that “the final regulations
prohibit high-volume hydraulic fracturing in the Basin regardless of whether the planned
activities constitute a ‘project.’ A declaration that the Compact’s definition of ‘project’ does
12
not encompass WLMG's planned activities would not alter the prohibition or redress the
alleged harm.” (Doc. 217 at 11-12.)
The Court agrees. Here, no declaratory judgment by this Court will allow WLMG to
proceed with its plan to pursue HDHF on its land within the Basin. Based on the DRBC’s
authority to control pollution within the Basin pursuant to Article 5 of the Compact, the
relevant regulatory provision clearly prohibits ALL HDHF activity in the Basin as that term is
defined in the regulation. See supra pp. 7-8 & n.2. Although the Court found at the outset of
the litigation that WLMG’s claimed injury would likely be redressed by a favorable decision
because “[a] decision in favor of WLMG would permit it to plan and develop the Property
without first submitting an application to the DRBC for its approval” (Doc. 92 at 28), that
possibility is now foreclosed by the regulation prohibiting WLMG’s planned development of
the Property.
(Doc. 92 at 27-28.)
The DRBC also contends that the case is moot because “WLMG’s obligation to
submit plans to conduct hydraulic fracturing activities to the Commission for its review and
approval no longer exists.” (Doc. 217 at 12.) WLMG disagrees with this assertion, claiming
that it “continues to be injured by the Commission’s assertion of Section 3.8 project review
jurisdiction over its project. That WLMG is, now, also injured by a new regulatory ban does
not mean that its injury flowing from the Commission’s assertion of Section 3.8 jurisdiction
has somehow evaporated.” (Doc. 218 at 3.)
13
With its argument, WLMG disregards the adopting Resolution’s clear statement in
paragraph C that
[t]he Comprehensive Plan amendments and final rules adopted today replace
the Executive Director Determinations of May 19, 2009, June 14, 2010 and July
23, 2010. The Resolution for the Minutes of May 5, 2010, which postponed the
Commission's consideration of well pad projects until the adoption of final rules,
expires by its own terms.
Resolution No. 2021-01, p.5 (httos:/Avww.nj.goc/drbc/libraryy/documents/Res2021-
01 HVHF.pdf.) (emphasis added). The referenced 2009 and 2010 Executive Director
Determinations are those which exerted § 3.8 project review over WLMG’s proposed HDHF
activities in the Basin. See supra pp. 5-6 (see also Doc. 22 at 11-12; Doc. 92 at 11 & n.3;
Doc. 216 J 2). They are no longer in effect based on paragraph C of Resolution 2021-01.
Therefore, the DRBC’s former designation of WLMG's proposed activity as a “project” is
unrelated to the comprehensive regulatory ban currently in effect--the implementation of the
provision negates previously established 2009 and 2010 Executive Director Determinations
establishing § 3.8 project review. See supra pp. 5-8. In that the DRBC no longer asserts §
3.8 project review jurisdiction over WLMG’s desired activities within the Basin, WLMG’s
contention that it continues to be harmed by the DRBC’s assertion of § 3.8 project review
jurisdiction is without merit.
14
For the foregoing reasons, the DRBC has shown that the redressability requirement
is no longer met. Therefore, this case is moot unless an exception to the mootness doctrine
exists.°.
B. Mootness Exceptions
The parties recognize that the mootness doctrine contains two exceptions: voluntary
cessation and conduct capable of repetition yet evading review. (Doc. 217 at 9-10; Doc. 218
at 3.)
1. Voluntary Cessation
“The voluntary-cessation exception applies when a defendant ceases the allegedly
illegal conduct that caused the injury but remains ‘free to return to his old ways.” Gulden,
119 F.4'" at 308 (quoting United States v. W.T. Grant Co., 345 U.S. 629, 632 (1953)). The
rationale for this exception is that “the voluntary cessation of challenged conduct does not
ordinarily render a case moot because a dismissal for mootness would permit a resumption
of the challenged conduct as soon as the case is dismissed.” /d. (quoting Knox v. Serv.
Emps. Int'l Union, Local 1000, 567 U.S. 298, 307 (2012)). Gulden cites Los Angeles County
v. Davis, 440 U.S. 625, 631 (1979), for the proposition that “the voluntary-cessation
exception can be defeated when (1) it can be said with assurance that there is no
3 The Court acknowledges that Defendant notes the Third Circuit has recognized a court’s ability to
exercise its discretionary power to withhold injunctive and declaratory relief on prudential grounds even in a
case that is not constitutionally moot. (Doc. 217 at 8-9 (citing Blanciak v. Allegheny Ludlum Corp., 77 F.3d
690, 700 (3d Cir. 1996) (citing S-1 v. Spangler, 832 F.2d 294, 297 (4'" Cir. 1987); United States v. W.T.
Grant, 345 U.S. 629 (1953); A.L. Mechling Barge Lines, Inc., v. U.S., 368 U.S. 324 (1961)).) Discussion of
this issue is not warranted in that the DRBC does not develop application of the issue to this case. (See id.)
15
reasonable expectation that the alleged violation will recur, and (2) interim relief or evertts
have completely and irrevocably eradicated the effects of the alleged violation.” 119 F.4" at
308 n.3 (internal quotation omitted)). The Supreme Court has stated that, in a voluntary-
cessation case, the standard for the party asserting mootness is “stringent”: “A case might
become moot if subsequent events made it absolutely clear that the allegedly wrongful
behavior could not reasonably be expected to recur.” Friends of the Earth, Inc. v. Laidlaw
Environmental Services (TOC), Inc., 528 U.S. 167, 189 (2000) (quoting United States v.
Concentrated Phosphate Export Ass'n, 393 U.S. 199 (1968).
The inquiry concerning the recurrence of the allegedly wrongful behavior centers on
the reason for the change.
To be sure, the defendant's reason for changing its behavior is often
probative of whether it is likely to change its behavior again. We will
understandably be skeptical of a claim of mootness when a defendant yields in
the face of a court order and assures us that the case is moot because the
injury will not recur, yet maintains that its conduct was lawful all
along. See Knox v. SEIU, Local 1000, 567 U.S. 298, 307, 132 S.Ct. 2277, 183
L.Ed.2d 281 (2012): see also 13C Charles Alan Wright, Arthur R. Miller, &
Edward H. Cooper, Federal Practice and Procedure § 3533.5, at 248 (3d ed.
2008). On the other hand, if the defendant ceases because of a new statute or
a ruling in a completely different case, its argument for mootness is much
stronger. See, @.g., Lighthouse Inst. for Evangelism, Inc. v. City of Long
Branch, 510 F.3d 253, 260 (3d Cir. 2007); Khodara Envtl., Inc. ex rel. Eagle
Envtl., 2. P. v. Beckman, 237 F.3d 186, 193 (3d Cir. 2001) (Alito, J.).
In short, the touchstone of the voluntary-cessation doctrine is not how
willingly the defendant changed course. Rather, the focus is on whether the
defendant made that change unilaterally and so may “return to [its] old ways”
later on. Friends of the Earth, 528 U.S. at 189, 120 S.Ct. 693 (quoting City of
Mesquite v. Aladdin's Castle, Inc., 455 U.S. 283, 289 n.10, 102 S.Ct. 1070, 71
L.Ed.2d 152 (1982)).
16
Hartnett v. Pennsylvania State Educ. Ass'n, 963 F.3d 301, 306-07 (3d Cir. 2020).
The DRBC asserts that the purpose of the exception is “to deter a ‘manipulative
litigant [from] immunizing itself from suit indefinitely, altering its behavior long enough to
secure a dismissal and then reinstating it immediately after.” (Doc. 217 at 9 (quoting Town
of Portsmouth, R.I. v. Lewis, 813 F.3d 54, 59 (18 Cir. 2016)).) The DRBC contrasts this
scenario with the situation where the doctrine may not apply at all because the voluntary
cessation was initiated before litigation began. (Doc. 217 at 9 (citing Drenth v. Bookvar, Civ.
A. No. 1:20-CV-00829, 2020 WL 4805621, at *6 (M.D. Pa. Aug. 18, 2020) (citing Hartnett,
963 F.3d at 306); Fed’n of Adver. Indus. Representatives, Inc. v. City of Chi., 326 F.3d 924,
929-30 (7th Cir. 2003)).)
The DREBC first argues that, in this case, “the rulemaking process predates the
Complaint, and the February 2021 regulation, following notice and comment, is the action of
sovereign entities working within the congressionally approved Compact structure to make a
binding decision impacting each state in the Basin.” (Doc. 217 at 10.) The DRBC is correct
that the rulemaking process predates the Complaint in that the DRBC first released
proposed fracking regulations in 2010. See supra p. 6.
The Court concludes that the timeline of the rulemaking process and the source of
the relevant regulation support the DRBC’s mootness argument. This is not a case where
Defendant DRBC “yield[ed] in the face of a court order.” Hartnett, 963 F.3d at 306 (citations
omitted). Rather, the rulemaking was systematically undertaken over an extended period of
17
time which began years before this action was filed. See supra p. 6 & n.1. Further, itis a
case where Defendant DRBC “cease[d]’ its assertion of § 3.8 project review over WLMG's
proposed activities because of a new regulation, a situation which makes the “argument for
mootness much stronger.” Hartnett, 963 F.3d at 307 (citations omitted). Further, the DRBC
is not “free to return to [its] old ways,” Gulden, 119 F.4" at 308, because the basis for the
asserted project review, i.e., the 2009 and 2010 Executive Director determinations asserting
§ 308 project review, have been replaced by the regulation banning HDHF in the Basin, see
supra. Thus, there is no returning to old ways: any potential assertion of project review over
HDHF activities in the Basin would necessarily be preceded by repeal of the relevant
regulation and a new assertion of project review authority.
Further, the regulation at issue has been challenged in the Eastern District of
Pennsylvania and the Third Circuit Court of Appeals and remains intact. See Yaw v. DRBC,
49 F.4tn 302 (3d Cir. 2022). With the relevant regulation remaining intact and the asserted §
3.8 project review no longer in existence, “the voluntary-cessation exception [is] defeated
[because] (1) it can be said with assurance that there is no reasonable expectation that the
alleged violation will recur, and (2) interim relief or events have completely and irrevocably
eradicated the effects of the alleged violation.” Gulden, 119 F.4"" at 308 n.3 (internal
quotation omitted).
For similar reasons, the capable-of-repetition-yet-evading-review exception does not
apply here. “The capable-of-repetition prong of the exception requires ‘a reasonable
18
expectation’ or a ‘demonstrated probability’ that ‘the same controversy will recur involving
the same complaining party.” Gulden, 119 F.4'n at 309 (quoting FEC v. Wis. Right to Life,
Inc., 551 U.S. 449, 463 (2007) (emphasis added in Gulden) (internal quotation omitted))
(citing City of Los Angeles v. Lyons, 461 U.S. 95, 109 (1983) (“[T]he capable-of-repetition
doctrine applies only in exceptional situations, and generally only where the named plaintiff
can make a reasonable showing that he will again be subjected to the alleged illegality.”)).
As discussed above, the same controversy will not likely occur because the regulation
banning HDHF controls WLMG’s planned activities in the Basin and would have to be
repealed before the DRBC could assert project review authority over the activities.
Assuming arguendo that the first prong were satisfied, analysis of the second prong
does not support application of this mootness exception. “[T]o satisfy the evading-review
prong of the exception, ‘the challenged action [must be] in its duration too short to be fully
litigated prior to its cessation or expiration[.]” Gulden, 119 F.4" at 309 (quoting Weinstein v.
Bradford, 423 U.S. 147, 149 (1975) (per curiam)). Here, should the relevant regulation be
repealed and the DRBC assert project review over WLMG's activities in the Basin, there
would be no durational concern regarding potential litigation contesting project review
authority. WLMG asserts that the DRBC “should not be able to pivot back and forth between
barriers asserted to WLMG’s proposed development.” (Doc. 218 at 5.) This characterization
does not fairly summarize the actions taken by the DRBC where the adoption of Resolution
19
No. 2021-01 is the culmination of a multi-year information-gathering and rulemaking
process. Thus, neither prong of the second mootness exception applies in this case.
C. Prudential Considerations
WLMG also asserts that, in addition to the mootness exceptions, “prudential
considerations weigh against mooting this case.” (Doc. 218 at 5 (citing Bhd. of Boilermakers
v. Kelly, 815 F.2d 912, 915 (3d Cir. 1987) (“In addition to its threshold constitutional
dimension, mootness doctrine incorporates prudential considerations as well.”)).) WLMG’s
rationale is that
{t]his case has been extensively litigated by the parties, including two trips to
the Court of Appeals and multiple decisions by this Court. The parties are
prepared to proceed to trial. The Court should not eviscerate the investment of
time and resources by the parties and the Court because the Commission,
faced with a trial over its flawed assertion of Section 3.8 project review
jurisdiction, has decided to erect a new regulatory barrier to WLMG’s proposed
development.
(Doc. 218 at 5.)
The Court rejects this argument for the reasons discussed in the previous sections of
this Memorandum Opinion. The fundamental flaw in WLMG's position is its failure to
acknowledge that § 3.8 project review jurisdiction over WLMG’s proposed activities is no
longer in existence. As this is the only prudential basis asserted to defeat mootness, the
Court finds that it presents no barrier to concluding that this case is moot.
20
IV. CONCLUSION
For the foregoing reasons, the Court will grant Defendant Delaware River Basin
Commission’s Suggestion of Mootness and Motion to Dismiss (Doc. 216). An appropriate
rn
Order will enter. wee
LO MANU
Robert'D. Mariani
United States District Judge
21