Opinion

HDR Engineering, Inc.

Court
Armed Services Board of Contract Appeals
Filed
Jan 15, 2025
Status
Published
On the bench
O'Connell
Cited by
0 cases
Authority
More cited than 33.9%

describing the problems that ensued when a client required his architect to adhere to a budget for the construction of a home but demanded a house that was worth much more than that budget

How later courts described this case

  • describing the problems that ensued when a client required his architect to adhere to a budget for the construction of a home but demanded a house that was worth much more than that budget

Written by the judges who cited it.

The opinion

DOCUMENT FOR PUBLIC RELEASE

The decision issued on the date below is subject to an ASBCA Protective Order.

This version has been approved for public release.

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - )

)

HDR Engineering, Inc. ) ASBCA No. 62723

)

Under Contract No. W912EP-10-D-0017 )

APPEARANCES FOR THE APPELLANT: Douglas L. Patin, Esq.

Lee-Ann C. Brown, Esq.

Bradley Arant Boult Cummings LLP

Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.

Engineer Chief Trial Attorney

John F. Bazán, Esq.

Patrick Sean Murphy, Esq.

Engineer Trial Attorneys

U.S. Army Engineer District, Los Angeles

OPINION BY ADMINISTRATIVE JUDGE O’CONNELL

Appellant, HDR Engineering, Inc. (HDR), appeals a final decision in which the

United States Army Corps of Engineers (USACE) asserted a government claim for

professional negligence related to the design of a dam. The Board conducted a hearing

from May 13-20, 2024. Both entitlement and quantum are before us. The Board

sustains the appeal.

FINDINGS OF FACT

This appeal arises from a project with a lengthy history. We will start with a

brief description of the overall project, then summarize the three construction

contracts, and finally describe HDR’s design contract and task orders.

The Project

1. The project is known as the C-44 Reservoir/Stormwater Treatment Area,

which is part of a Comprehensive Everglades Restoration Plan (R4, tab 12 at 5 1).

“C-44” is the name of a canal. The water in the C-44 Canal comes from the C-44

Basin, a 202-square-mile area in Martin County, Florida. (R4, tab 12 at 5-6) The

purpose of the project is to improve water quality and slow down the flow of

freshwater during rain events from the canal into the St. Lucie Estuary. The project

1

Citations are to the .pdf page number in the electronic file.

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

pumps water from the C-44 Canal into an elevated reservoir that is surrounded by a

30-foot-high embankment dam. Water from the reservoir then flows by gravity

through a discharge canal to stormwater treatment cells in which aquatic plants remove

nitrogen and phosphorous. Water from the cells is then discharged into collection

canals and then back into the C-44 Canal. (Id. at 5-6, 29; app. supp. R4, tab 2482;

tr. 5/17-19) It takes about two weeks for water to pass through this system (tr. 5/18).

2. In the 2000s, the project was managed by the South Florida Water

Management District (SFWMD), a water district in the state of Florida. Fla. Stat.

§ 373.069(1)(e). SFWMD planned on building the project through a single

construction contract (R4, tab 14 at 8). SFWMD retained HDR as the designer

sometime prior to August 1, 2005 (see app. supp. R4, tab 2154). Between 2005 and

2008 HDR produced extensive documentation for SFWMD (app. supp. R4, tabs

2038-2043, 2154, 2155), including a Basis of Design Report dated April 14, 2006

(app. supp. R4, tab 2040), and drawings marked “Issued for Bid” dated April 18, 2008

(app. supp. R4, tab 2043).

3. At some point between 2008 and 2010, USACE became involved with the

project. USACE and SFWMD decided to divide the construction contract into three

contracts, with USACE responsible for the first two contracts, and SFWMD

responsible for the third (tr. 3/161-62).

4. Contract One was for an intake canal and a project access road. Contract

Two, the contract relevant to this appeal, included the reservoir, an intake pump station

and outlet works, and the embankment dam. The reservoir was designed to have a

storage volume of 50,600 acre-feet 2 of water and had an exterior perimeter of 9.3 miles.

Contract Three included the stormwater treatment areas. (R4, tab 12 at 7, 29; tab 14

at 8; tr. 6/69) The project site covers approximately 12,000 acres (18.75 square miles)

(app. supp. R4, tab 2062 at 6).

5. On July 23, 2010, USACE entered into a contract with HDR. The contract

described the scope of work as “providing engineering services to complete the C-44

Reservoir and STA Project in compliance with USACE standards.” (R4, tab 3 at 1, 17)

The contract provided that HDR would perform the work pursuant to task orders (id.

at 18). The contract incorporated Federal Acquisition Regulation (FAR) 52.236-23,

Responsibility of the Architect-Engineer Contractor (Apr 1984) (the “Architect-Engineer

clause”) (R4, tab 2 at 77). This clause provides:

2

An acre-foot is the volume of water necessary to cover one acre of land with water to

a depth of one foot and is equal to approximately 325,580 U.S. gallons. Stockton

E. Water Dist. v. United States, 583 F.3d 1344, 1349 n.6 (Fed. Cir. 2009).

2

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

(a) The Contractor shall be responsible for the

professional quality, technical accuracy, and the

coordination of all designs, drawings, specifications, and

other services furnished by the Contractor under this

contract. The Contractor shall, without additional

compensation, correct or revise any errors or deficiencies

in its designs, drawings, specifications, and other services.

(b) Neither the Government’s review, approval or

acceptance of, nor payment for, the services required under

this contract shall be construed to operate as a waiver of

any rights under this contract or of any cause of action

arising out of the performance of this contract, and the

Contractor shall be and remain liable to the Government in

accordance with applicable law for all damages to the

Government caused by the Contractor’s negligent

performance of any of the services furnished under this

contract.

(Id.)

6. While this clause specifies the designer’s professional responsibilities, the

contract also required HDR to design within USACE’s budget. The contract

incorporated FAR 52.236-22, Design Within Funding Limitations (Apr 1984), which

provides that: “(a) The Contractor shall accomplish the design services required under

this contract so as to permit the award of a contract, using standard FAR procedures

for the construction of the facilities designed at a price that does not exceed the

estimated construction contract price . . . ” (R4, tab 2 at 76).

7. In August of 2010, HDR appointed Keith Ferguson as the designer of record

for the embankment (tr. 1/18, 126). Mr. Ferguson has Bachelor of Science (1977) and

Master of Science (1979) degrees in Civil Engineering from the University of

Colorado and is a registered Professional Engineer in Florida and several other states

(app. supp. R4, tab 2412 at 1). During his career, Mr. Ferguson has been involved in

over 250 dam projects including numerous embankment dams on which he acted as

the engineer of record, project manager and in other capacities (tr. 1/96; app. supp. R4,

tab 2412 at 4-12). There is no dispute that Mr. Ferguson was well-qualified for this

role.

3

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

The HDR Task Orders

8. Two task orders are relevant to the dispute. Task Order No. 3 in the amount

of $569,882.03 is dated September 30, 2011 (R4, tab 12). The scope of work for this

task order provides that it:

[i]s for the additional data collection, re-evaluation of

existing data, analyses, and technical coordination

necessary for the C-44 Reservoir . . . previously completed

under separate contract to the South Florida Water

Management District . . .

(id. at 5). As evidenced by this description, the work did not include a complete

redesign. However, the task order did provide for seepage analysis of the embankment

(id. at 15).

9. HDR’s 2008 design for SFWMD contained a blanket drain but not a toe

trench drain (app. supp. R4, tab 2043 at 59 (The blanket and toe trench drains are

shown at R4, tab 44 at 25 and app. supp. R4, tab 2476.)). The blanket drain was made

of sand and sat at the bottom of the embankment and on top of the foundation (tr.

1/108-09, 120-21; app. supp. R4, tabs 2476, 2482, 2483). It collects seepage that

passes through the embankment. The seepage flows into a slotted pipe and then is

discharged into a drainage swale. (App. supp. R4, tab 2036 at 38; R4, tab 44 at 3-4)

10. During HDR’s work on Task Order No. 3, two characteristics of the

existing design and the site became relevant. First, as already stated, the reservoir was

to be elevated. When it was completely full the reservoir would have an elevation

20 feet higher than a perimeter canal to be built outside the embankment to collect

seepage. Second, the existing soil in the foundation (below the embankment) was

highly permeable. As a result, water from the reservoir would seep through the

foundation to the perimeter canal. HDR discovered through computer modeling that

upwards pressure from this seepage could build and possibly cause a failure of the

dam. HDR conveyed this concern to USACE. (Tr. 1/109-11, 126-27, 131).

11. On April 4-5, 2012, HDR met with USACE and SFWMD, and discussed

HDR’s analysis concerning the potential failure of the dam. The discussions played a

role in USACE issuing the second relevant Task Order No. 4. (App. supp. R4,

tab 2033 at 70-71; tr. 1/130-32).

12. Task Order No. 4 is dated September 27, 2012 and is in the amount of

$3,456,293.64. The purpose of the task order was to prepare the construction contract

for Contract Two (the reservoir and appurtenant features). The work included a

requirement that HDR “[p]erform a limited qualitative risk analysis” of the

4

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

embankment with and without a “trench drain” to determine if this would be an

effective drainage feature to prevent the failure of the dam. (R4, tab 14 at 1, 6, 42)

13. Mr. Ferguson testified that HDR conducted additional computer modeling

and determined that a single-stage toe trench drain would be adequate for the site

because seepage through the embankment was relatively low (tr. 1/133-34; see

findings 26, 57 (describing single and two-stage toe trench drains)).

The Independent Panel Review

14. HDR decided to obtain an opinion on the toe trench drain and other issues

from experts outside of the company. On January 8, 2013, HDR obtained approval from

USACE for a three-person independent technical review panel (tr. 1/134; 5/33; app.

supp. R4, tab 2054 at 1). The panel included Mr. James R. Talbot, who was a

preeminent expert on dam seepage and filters/drains. 3 Mr. Talbot had taught and written

extensively on the topic. (Tr. 1/86; 3/143; 4/76; 6/36; R4, tabs 2102, 2104-06, 2108-09)

15. HDR met with the independent panel on January 28-29, 2013. The panel

issued a report dated February 5, 2013. (App. supp. R4, tab 2011) The panel stated

that a toe trench drain around the entire dam would “greatly reduce the potential for

seepage problems developing . . . ” (id. at 3). The panel recognized that a toe trench

drain would be “expensive” and “complex” (id.). The panel “strongly

recommend[ed]” a toe trench drain for at least part of the dam, but also recommended

that HDR present other alternatives to USACE so that USACE could “decide how

much risk they are willing to take with the consideration of the cost and complexity of

constructing the trench drain” (id.). The discussions between HDR and the panel

focused upon a single-stage drain because a two-stage drain would be even more

expensive (tr. 1/140).

16. HDR later submitted the February 5, 2013 report to USACE as part of a

design documentation report required by the contract (tr. 5/37 (citing app. supp. R4,

tab 2062 at 2521)).

3

There appears to be some imprecision in the use of the words “filter” and “drain” in

the context of embankment dams. The U.S. Bureau of Reclamation (USBR)

states that different authors have different meanings. Part of the confusion may

stem from the fact that a single material can act as both a filter and a drain.

(App. supp. R4, tab 2010 at 21) USBR states that in a two-stage system, both

stages provide filtration and drainage, but the emphasis of the first stage is

filtering and the second stage is draining (id. at 24). The Board generally uses

“drain” in this opinion unless the cited testimony or document uses “filter.”

5

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

17. On February 6, 2013, HDR, USACE, and SFWMD met for a Special Topic

Meeting. Ten representatives of USACE attended, including Dan Blaydes, USACE’s

Chief of Soils Design, plus at least two geotechnical engineers, as well as three

representatives from SFWMD, including a senior civil engineer (app. supp. R4,

tab 2056 at 13-14; tr. 1/145; tr. 5/51-53).

18. The meeting minutes state that HDR “introduced” the independent

technical review panel, but it does not appear that they actually attended (app. supp.

R4, tab 2056 at 1, 13-14). The parties discussed adding the toe trench drain to the

design. The discussion included the observation that toe trench drains had not always

been a standard feature on dams and it appears that there was some reluctance by

USACE. HDR stated that it believed that there was a “strong justification” for adding

the toe trench drain and recommended adding it around the entire perimeter of the

reservoir. The government representatives asked questions about how much a toe

trench drain would cost and an estimate of $200-$400 per linear foot was discussed,

or a total of $12 to $24 million. The government asked about offsets for the costs. (Id.

at 5-6; tr. 1/148).

19. The meeting minutes do not specify that a single-stage toe trench drain was

discussed. However, in unrebutted testimony, Mr. Ferguson testified that the

discussion concerned a single-stage toe trench drain. He further testified that no one

from USACE or SFWMD questioned the use of a single-stage toe trench drain instead

of a two-stage drain (tr. 1/149-50). The Board found this testimony credible.

20. On February 15, 2013, HDR met again with four USACE employees,

including Mr. Dan Blaydes and the two geotechnical engineers, and SFWMD. The

minutes reflect an awareness by the participants that they were discussing an issue that

could lead to “partial or full dam failure.” USACE stated that it had analyzed the

information presented on February 6, 2013, and asked why the toe trench drain could

not be eliminated on the northern portion of the reservoir. The minutes state that

“USACE felt this is a higher level discussion based on risk and cost; will defer

discussion to Wed 20th meeting . . . .” (App. supp. R4, tab 2057 at 3, 5).

21. USACE did not call as witnesses any of the USACE employees who

participated in these meetings.

22. There are no documents in the record that evidence a Wednesday,

February 20, 2013 meeting, either between USACE and HDR, or internally

at USACE. USACE has not presented any evidence that establishes how it analyzed

the risks and costs of adding, or not adding, a toe trench drain. In fact, USACE’s

presentation ignores that any of this ever happened.

6

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

23. The next event evidenced by the record is a March 2, 2013 email from

Mr. Ferguson to Mr. Talbot (of the technical review panel) stating that HDR and

USACE had agreed to construct a single-stage toe trench drain around the entire

perimeter of the reservoir. Mr. Talbot replied on March 4, 2013, stating that he

“particularly like[d] using one gradation for the filter material” and that the design “is

adequate for filtering” the soil at the site. (App. supp. R4, tab 2122 at 1-2) “[O]ne

gradation” means a single-stage drain/filter (tr. 1/143).

24. On April 5, 2013, Mr. Talbot again wrote to HDR, stating that “I believe

the present design with a trench drain at the downstream toe for full length of the

embankment and drainage in the bottom of the perimeter canal will provide adequate

protection against the piping failure mode” (R4, tab 2012 at 1).

25. Mr. Talbot is deceased and did not testify at the hearing (tr. 4/76).

The Toe Trench Drain

26. The single-stage toe trench drain that HDR designed in 2013 was a trench

filled with sand that was 3-feet wide and up to 14-feet deep so that it would extend

two feet into the existing layer of pervious soil in the foundation. Water from the

elevated reservoir would flow by gravity through this pervious soil and then up

through the sand in the trench until it reached a pipe. The pipe contained slots so that

water would enter and flow to manholes, where it would go into another pipe that

conveyed it to the perimeter canal. In a single-stage design, sand surrounds the pipe.

The toe trench drain was to be installed near the toe of the slope of the embankment,

on the far side from the reservoir. (App. supp. R4, tabs 2475A, 2476, 2481-82, 2484,

2485A, 2486; tr. 1/107, 109-12, 123-24) The perforated pipe was designed so that

USACE would be able to inspect and maintain it (app. supp. R4, tab 2056 at 5;

tr. 1/147).

27. HDR submitted an interim design in April 2013. In their comments on the

design, multiple USACE reviewers continued to question the need for a toe trench

drain, either in whole or around the entire 9.3-mile perimeter of the reservoir. (App.

supp. R4, tab 2133 at comment 5164782; see app. supp. R4, tab 2036 at 65-66).

28. USACE and SFWMD performed multiple reviews of the design. These

reviews included a quality assurance review by the Jacksonville District of USACE

and SFWMD, including by structural and geotechnical engineers. In addition, there

was an agency technical review by USACE’s Louisville District. Further, USACE

retained the firm Gannett Fleming, a designer of dams and embankments, to perform

an independent expert review. The SFWMD hired another design consultant firm,

Ardaman & Associates, to perform its own outside review. After all of these reviews

had been completed, USACE performed a “bid ability, constructability, operability

7

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

and environmental” review of the design. In all, the design was subject to review by

approximately 50 technical experts. While the reviewers posted approximately 1,000

comments, none of the experts at USACE, SFWMD, Gannett Fleming, or Ardaman

& Associates questioned the use of a single-stage toe trench drain. (Tr. 5/41-46, 67)

29. USACE did not call as witnesses anyone from SFWMD, Gannett Fleming,

or Ardaman & Associates.

30. We will address here one aspect of USACE’s claim. Comments on the

design were posted on a web-based platform known as Dr. Checks. While USACE

does not allege that either USACE or the other commenters mentioned a two-stage toe

trench drain in the comments, it does contend that HDR was negligent because it failed

to respond to some comments concerning the toe trench drain (gov’t br. at 5-7, 19-20).

The problem for USACE is that this contention was largely undercut by its principal

fact witness on direct examination when he testified that HDR “must have” resolved

the comments (tr. 3/106-07; see also tr. 3/133). In addition, the record demonstrates

that a contracting officer (CO) wrote to HDR on October 30, 2013 stating “[m]y

understanding is that all comments in [Dr. Checks] have been addressed and are, or

will be, closed shortly” (R4, tab 29 at 1). The Board finds that USACE has not proven

that HDR failed to respond to any relevant Dr. Checks comments.

The Construction Contract

31. On September 11, 2015, USACE awarded Contract Two to Barnard

Construction Company, Inc. (Barnard), in the base amount of $197,700,321.85 (R4,

tab 83 at 2).

The Toe Trench Drain Flood Test

32. The contract required Barnard to construct a 300-foot section of the toe

trench drain and then conduct a flood test. The purposes of the flood test included

determining whether Barnard could achieve sufficient compaction of the soil. The test

was not intended to simulate operating conditions of the toe trench drain. (Tr. 1/45,

114, 2/128; app. supp. R4, tab 2069 at 32) The test was conducted years before the

reservoir was filled so that the “driving force” for the seepage did not exist (tr. 1/111,

3/120-21).

33. Two other characteristics of the site and design must be mentioned at this

point. The soil at the site contains high amounts of iron. When iron encounters water,

it forms what the parties variously call iron oxide, iron ochre, or simply rust. 4 There

4

We will use iron oxide in this opinion because USACE’s geologist indicated a

preference for this term (tr. 2/153). HDR’s expert stated in her report that iron

8

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

must be oxygen in the water to form iron oxide, otherwise the iron remains dissolved.

Groundwater is not exposed to the air and is generally depleted of oxygen. HDR was

aware of the presence of the iron in the soil and designed the toe trench drain pipe to

be below groundwater level so that the water would be anoxic and the iron would

remain dissolved. (Tr. 1/22, 45, 62, 114; 2/113-14; 6/109)

34. To perform the flood test, Barnard pumped groundwater at the site into an

open-air metal tank. It then pumped water from the tank into a manhole where the toe

trench drainpipe ended. The water flowed through that drainpipe. In other words, the

test required Barnard to pump water backwards through the system (or backwards

compared to the design) (tr. 1/115-16, 158-60, 6/87).

35. The test had two flaws, at least so far as they pertain to the present dispute.

First, in the initial test in the fall of 2016 (R4, tab 82 at 1) there was dirt or sediment in

the metal tank (tr. 1/179-80, 2/43). After the test was complete, USACE noticed rusty

coloration in the toe trench drain sand and on top of the drainpipe (tr. 1/199). USACE

also began noticing rusty discoloration in the drain canals (tr. 2/17).

36. Barnard addressed the issue with the cleanliness of the tank and conducted

a second test in April 2017, but the results were similar in terms of the rusty water

coming from the system (tr. 2/61-63).

37. This brings us to the second flaw in the flood test. As stated above, HDR

designed the toe trench drainpipe so that it would be below the level of groundwater,

meaning that the water that entered the pipe would be anoxic (finding 33). When the

test water was stored in the open-air metal tank and pumped into the manholes, it had

the opportunity to react with the atmospheric oxygen and produce iron oxide, which

likely caused higher levels of iron oxide than if the system had been operated as

designed. (App. supp. R4, tab 2035 at 18-20)

38. Because of this exposure to oxygen, and because the reservoir had not been

built, the Board finds that USACE – the party with the burden of proof – has not

proven that the flood tests were a reasonably accurate method for determining how

HDR’s single-stage drain would have performed if built and operated as designed.

39. There is no evidence that Barnard conducted a flood test of the blanket

drain.

ochre forms when iron oxide mixes with iron-oxidizing bacteria (app. supp. R4,

tab 2035 at 14).

9

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

The Expert Analyses of the Clogging Rates

40. The perforations (or slots) in the toe trench drainpipe designed by HDR

were 0.9 millimeters (mm) wide (R4, tab 44 at 3). Because these slots were so narrow,

USACE became concerned that the iron oxide observed in the flood test would clog

the pipes after the project was completed. USACE tasked one of its geologists with

analyzing how quickly the slots would become clogged (R4, tab 105 at 2).

41. The USACE geologist issued a report dated July 17, 2017 analyzing the

chemical reactions that would occur based upon the levels of iron and oxygen at the

site. For some reason she did not analyze the actual 0.9 mm slots designed by HDR

but rather considered 12.5 mm, 7.5 mm, and 3.2 mm slots. Not surprisingly, she found

that the narrower the slot, the quicker it would become clogged. She concluded that

the 3.2 mm slots could clog in as little as 21 days. (R4, tab 105 at 1, 5) The Board

finds that this would be quite troubling, if it were true.

42. After filing this appeal, HDR retained Karen J. Murray, Ph.D., an expert in

geochemistry and environmental chemistry (app. supp. R4, tab 2035; tr. 6/79).

Dr. Murray concluded that the USACE geologist failed to take into account the law of

conservation of mass, and failed to recognize that, as the dissolved iron reacted with

oxygen and became iron oxide, the overall concentration of iron would become

smaller and the reaction would slow (app. supp. R4, tab 2035 at 25-28). After

analyzing the USACE calculation that the pipes could clog in as little as 21 days,

Dr. Murray concluded that the calculation had a 234-fold overstatement of the amount

of iron in the system, or, as she opined: “99.6% of the [iron oxide] that the USACE

modeled in their maximum estimate of iron fouling was created out of thin air and

could not be present based on the law of conservation of mass” (id. at 28 (emphasis in

original); tr. 6/102).

43. After making what she deemed the appropriate corrections, Dr. Murray

recalculated the clogging rate for a pipe with 3.2 mm slots using the same assumptions

that the USACE geologist had used. Dr. Murray concluded that the pipe would take

7,775 days to clog. In other words, instead of clogging in 21 days, it would take over

21 years. For the 0.9 mm slots specified by HDR, Dr. Murray calculated that it would

take 2,404 days to clog. (R4, tab 2035 at 87)

44. The Board was skeptical that USACE would go to a hearing with such a

flawed analysis and expected USACE to vigorously challenge Dr. Murray’s

calculations at the hearing. However, USACE had no response.

45. USACE’s geologist prepared a rebuttal report of approximately one page.

In this report, she admitted that her July 2017 report “may have errors.” Nevertheless,

she insisted that her analysis was “sound.” However, she did not revise her

10

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

calculations, nor did she dispute or challenge Dr. Murray’s calculation of the clogging

rates. (R4, tab 106) At the hearing, she testified “[t]here were errors in my

calculations. I acknowledge that.” (Tr. 2/187).

46. USACE did not provide any other evidence that challenged Dr. Murray’s

conclusions. The Board finds that Dr. Murray’s analysis is persuasive and unrebutted,

and that Dr. Murray was a credible witness.

47. In its post-hearing brief, USACE ignores these unpleasant developments

and continues to cite the 21-day clogging scenario as if this were a viable assertion

(gov’t br. at 14). The Board finds that USACE has not proven that the pipes specified

by HDR were likely to become clogged in an unreasonably short period of time, taking

into account planned maintenance of the pipes (see tr. 3/120-121 (discussing plan to

clean the pipes at “[a] little more than two years” after USACE began filling the

reservoir)).

48. USACE’s geologist did not perform any analysis of a clogging rate for the

blanket drainpipe (R4, tabs 105-06; tr. 2/126-27).

The Change to Two-Stage Drains

49. On February 14, 2017, before Barnard had even conducted the second

flood test, USACE began to discuss a two-stage drain with HDR (R4, tab 44 at 8).

50. HDR wrote to USACE on February 16, 2017. It stated that prior

agriculture on the site was the likely source of the high levels of iron at the site. It

opined that the iron would be flushed out over time through operation of the reservoir.

HDR recommended a limited installation of two-stage drains with follow-up testing of

water quality and geochemical modeling to determine if there were long-term water

quality concerns and whether a two-stage drain was necessary. (R4, tab 36 at 3)

51. The USACE Jacksonville District asked the USACE Philadelphia District

to review the toe trench drain design. Daniel M. Sirkis, the Chief of the Philadelphia

Geo-Environmental Section, issued a four-page memorandum on March 6, 2017.

Among other things, Mr. Sirkis expressed concern about the narrowness of the slots

and the thickness of the pipes in the HDR design because they would make it difficult

to clean the slots through water jetting. He stated that the pipes might need to be

cleaned on an annual basis. He also opined that the custom pipe specified by HDR

would be costly and that there might be problems with manufacturing quality. He

recommended mass-produced, commercially available, pipe. (App. supp. R4, tab 2087

at 2-3)

11

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

52. Mr. Sirkis also opined that the HDR design “should have been more

robust” with respect to the formation of iron oxide. He proposed a two-stage “filter

pack” for both the toe trench and blanket drains, opining that it would “provide a

superior pack for drainage and maintenance.” (Id. at 3) However, he acknowledged

that a two-stage system “may be somewhat more difficult to install and more

expensive than a single stage filter.” He emphasized that “careful quality control and

quality assurance will be needed due to the increased complexity of this design and

increased difficulty of construction.” (Id.)

53. In 2017, USACE did not contend that HDR had committed professional

negligence and did not demand that HDR design the two-stage drain at no charge. In

fact, USACE paid HDR to perform the redesign (tr. 5/76). While HDR performed the

redesign, it did not believe it was necessary (tr. 5/78).

54. Consistent with its earlier concerns about the costs of a single-stage toe

trench drain, USACE quickly became concerned about the costs of two-stage drains,

which it viewed as “excessive,” due, in large part, to the additional sand and gravel

costs (R4, tab 44 at 11).

55. In early July 2017, USACE formulated a plan it referred to as “Optimize

C” that reduced the amount of drain sand and would be faster to construct. USACE

would achieve this by substituting a geotextile for some of the drain sand. (Id.)

56. The problem with this idea was that various guidelines – including

USACE’s – seemed to prohibit the use of geotextile in an embankment dam.

Nevertheless, USACE sought and obtained internal approval to use the geotextile.

(R4, tab 121 at 1-2)

57. HDR designed the two-stage drain that USACE had selected. The drain

continued to have sand in the bottom part of the trench, but the pipe was surrounded

by gravel and a geotextile fabric instead of sand, and the pipe had larger perforations

(app. supp. R4, tab 2485A; tr. 1/124-25).

The Modifications to the Barnard Contract

58. USACE issued two contract modifications to Barnard for the change to

two-stage blanket and toe trench drains. The first, Modification No. P00014 dated

August 4, 2017, increased the contract price by $2,338,864.55. This modification

addressed the additional gravel that would be required. (R4, tab 87 at 2, 4; tr. 2/67)

59. Because USACE had concluded that the 0.9 mm slots on the pipe specified

by HDR were too small and the pipe was too thick and would be difficult to clean

(gov’t br. at 5-7; finding 51), the modification also changed the pipe. However,

12

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

because the new pipe was cheaper, this resulted in cost savings to USACE (R4, tab 87

at 3-4).

60. The second Modification No. P00015, issued on September 27, 2017,

increased the contract price by $12,529,030.87 and included the work of constructing

the two-stage drains. The modification granted 76 days of delay priced

at $3,809,332.49 (R4, tab 88 at 2-4, 7-8; tab 90).

61. After Barnard installed the two-stage toe trench drain, USACE did not

require Barnard to perform a flood test (tr. 2/97). Accordingly, there is no flood test

data to compare the performance of the single-stage drain to the two-stage. The Board

finds that USACE has not proven that the two-stage drain would have performed

better in a comparable flood test.

The Professional Negligence Claim

62. In October 2017, the USACE Jacksonville District’s Engineering Division

began an investigation (R4, tab 137 at 18). On January 29, 2018, CO Susan Forchette

provided HDR “formal notification of potential Architect-Engineering (A-E) liability

for a design deficiency discovered by the Government . . . ” and stated that USACE

had begun an investigation (R4, tab 43).

63. USACE appointed Mr. Bradley Cox, a lead geotechnical engineer, to

conduct the investigation (tr. 3/64, 97). He testified that he opposed the investigation,

but he was appointed anyway (tr. 3/151). Mr. Cox interviewed Mr. Blaydes, the Chief

of Soils Design who was the senior USACE official meeting with HDR during the

approval of the single-stage toe trench drain (findings 17, 20). But Mr. Cox did not

ask Mr. Blaydes a basic question: why did Mr. Blaydes and dozens of other experts

approve the single-stage toe trench drain? (Tr. 3/148)

64. On February 4, 2018, USACE issued a memorandum authored by Mr. Cox,

and signed by Mr. Blaydes and three other USACE officials containing the findings of

fact of the investigation. In this memorandum, USACE identified what it contended

were errors or omissions by HDR and stated that HDR should be held liable for

negligence in the design. The memorandum relied, in part, upon the USACE

geologist’s erroneous conclusion that the pipes could clog in as little as 21 days. (R4,

tab 44 at 1, 13, 23)

65. The memorandum does not contain a clear explanation for the replacement

of the single-stage blanket drain. The memorandum notes that the blanket drain does

not collect the iron-rich groundwater but rather water from the reservoir. Accordingly,

the memorandum acknowledges that USACE lacks evidence that the pipe would be

susceptible to clogging. Nevertheless, the memorandum supports replacement of the

13

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

single-stage blanket drain stating, without elaboration, that the two-stage design is

“industry standard.” (Id. at 18)

66. During the hearing, Mr. Cox testified that the purpose of redesigning the

toe trench and blanket drains was to reduce maintenance and the potential for clogging

(tr. 3/84).

67. USACE convened an Architect Engineer Responsibility Board (AERB).

Of the 76 days of delay granted in the Barnard modification, the AERB concluded that

HDR should be held liable for only 21 days because Barnard had taken 55 days to

respond to USACE’s request for proposal (app. supp. R4, tab 2341 at 5; tr. 3/176).

68. On October 15, 2020, CO Katrina Hills-Denson issued a final decision

asserting a government claim for $4,185,003.71. Without explanation, she rejected the

recommendation of the AERB to hold HDR liable for only 21 days of delay. The

majority of the damages was the $3,809,332.49 for the 76 days of delay paid to Barnard.

The claim was based upon the contention that HDR committed negligence and/or a

breach of contract in its design of the dam. The CO relied upon FAR 52.236-23, the

Responsibility of the Architect-Engineer Contractor clause. (Finding 5; R4, tab 65 at 14)

69. The CO contended that there were two errors in the design. First, she

contended that HDR failed to follow “agency and industry standards.” She cited

guidelines published by USACE, the Bureau of Reclamation (USBR), and the Federal

Emergency Management Agency (FEMA). She stated that if HDR had “followed

agency and industry standards, the original design would have incorporated a second

drainage media around the pipe (also known as a two-stage drain) in lieu of the

single-stage drain specified for construction.” (R4, tab 65 at 5)

70. Second, the CO contended that HDR failed to identify the necessity for a

two-stage design based on the water chemistry test results showing high iron

concentrations at the site and failed to design the dam to reduce maintenance (id. at 9).

71. The final decision focuses upon the toe trench drain. However, the

decision contained the same conclusory assertion from Mr. Cox’s memorandum that a

two-stage blanket drain is “industry standard” (R4, tab 65 at 9; finding 65)). At the

hearing, USACE did not present any evidence that documented an industry standard

for two-stage blanket drains.

72. HDR filed a timely appeal on November 11, 2020.

14

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

Applicable Standards and Guidelines

73. Both parties cite standards or guidelines published by USACE, USBR, and

FEMA concerning the design of dams and filters/drains. In its opening brief, USACE

refers to the relevant documents as “guidelines” and states that HDR was not required

to follow them (gov’t br. at 22). However, in its reply brief USACE refers to them as

“Federal regulations” (gov’t reply at 11). In any event, we summarize the relevant

provisions concerning one and two-stage drains.

USACE Engineering Manual (EM) 1110-2-2300 (July 30, 2004)

74. EM 1110-2-2300 is entitled “General Design and Construction

Considerations for Earth and Rock-Fill Dams” (app. supp. R4, tab 2091). In section

6.3, Earth Foundations, the EM lists various methods for controlling “underseepage,”

including trench drains. In section, 6.3(g), the EM provides that “[w]hen a complete

cutoff is not required or is too costly, a trench drain may be used in conjunction with

other underseepage control measures . . . ” (app. supp. R4, tab 2091 at 42).

75. In appendix B, Filter Design, EM 1110-2-2300 further provides: “[i]n

many instances a filter material meeting the criteria given by Table B-2 and Equation

B-1 relative to the material being drained is too fine to meet the criteria given by

Equation B-2. In these instances, multilayered or ‘graded’ filters are required.” (Id.

at 92)

76. The Board reads this provision to mean that “in many instances” a multi-stage

filter is required, which would imply that in some cases a one-stage filter is appropriate.

EM 1110-2-1901

77. EM 1110-2-1901 is entitled Seepage Analysis and Controls for Dams

(April 30, 1993) (app. supp. R4, tab 2089). This EM provides that:

All earth and rock-fill dams are subject to seepage through

the embankment, foundation, and abutments. Seepage

control is necessary to prevent excessive uplift pressures,

instability of the downstream slope, piping through the

embankment and/or foundation, and erosion of material by

migration into open joints in the foundation and abutments.

(Id. at 144)

78. This EM further provides that a “trench drain usually contains a perforated

pipe surrounded by filter gravel, and backfilled with sand . . . ” (id. at 246). Due to the

15

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

reference to both sand gravel, the Board understands this to be a reference to a two-stage

drain. Thus, the Board understands this to mean that a trench drain “usually” is a

two-stage drain.

USBR Embankment Dams Design Standards No. 13 (Nov. 2011)

79. Chapter 5 of this publication is entitled “Protective Filters” (app. supp. R4,

tab 2010). In section 5.1.5, Scope, it discusses the balance of cost, constructability,

and reliability in an effective design:

Economical design requires the use of materials that

protect against failure yet are easily constructed. Since

filter materials are some of the most costly materials used

in a dam, effort is made to minimize the amount of

material used. Therefore, the balance of cost,

constructability, and reliability go hand in hand in

providing an economically safe structure.

(Id. at 25)

80. In section 5.2, Applications, it states:

Historically, many small dams (<50 feet high) have been

built without any filter or drainage zones, especially those

constructed prior to 1980. Additionally, many mid-size

dams (50 to 300 feet high) have been built without

‘modern’ filters, although they do contain graded transition

zones. Many of the dams in each of these categories have

performed successfully for many decades. On the other

hand, there have been notable dam failures, including all

dam sizes, that have resulted in loss of life and extensive

property damage.

(Id. at 33)

81. USBR states that the failure of some dams led to the addition of filters in

the 1970s. Interestingly, USBR casts some doubt on the efficacy of the filters because

it also states: “It should be noted, however, that since the advent of the dam safety

movement in the late 1970s, the failure rate of embankment dams due to internal

erosion has remained about the same.” (Id. at 33-34)

16

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

82. In section 5.2.3.2, Toe Drains, the document states:

Toe drains should consist of a perforated pipe surrounded

by a gravel drain which, itself, is surrounded by a sand

filter. This arrangement is known as a two-stage toe drain.

. . . While foundation conditions vary, this arrangement is

considered the minimum necessary for an effective drain. .

. . Single stage toe drains (a drain consisting of only filter

sand and a drain pipe) may also be considered in the

interest of minimizing costs. Again, single stage toe drains

are not recommended due to uncertainties in foundation

conditions and structure performance upon first filling.

(Id. at 53) (emphasis added)

83. While USBR clearly recommends against single-stage drains in the

above-quoted text, three pages later it strikes a more permissive tone if there is low

seepage:

5.2.3.2.2 One-Stage Versus Two-Stage Design

Historically, toe drains have incorporated one-stage and

two-stage designs as shown in figure 5.2.3.2-1. One-stage

designs are used when small amounts of seepage are

expected. Two-stage designs are used when a large

amount of seepage is expected.

(Id. at 56 (emphasis in original))

84. In Chapter 5, section 5.3.3, Cost, a general section applying to filter

designs, USBR again strikes a more permissive tone with respect to single-stage

drains:

The design of a filter should result in the minimal cost

necessary to satisfy the requirements of the application and

provide for reasonable anticipated construction

methods. . . .

Another cost topic is single stage versus two stage (or

greater) filter/drain systems. For some projects, a single

element may serve as both filter and drain. In others,

certainly including more critical and probably larger

projects, two stage systems are appropriate.

(Id. at 71-72)

17

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

85. HDR disputes the applicability of the USBR guidance, contending that

when USBR uses the term “toe drain,” it is referring to something that is different

from a toe trench drain. HDR notes that USBR’s rendering of a toe drain is a wide,

trapezoidal construction, which is different than the narrow, rectangular trench that it

designed (app. supp. R4, tab 2010 at 53). HDR points to language in section 5.2.3.2

stating that a purpose of a toe drain is to collect seepage from the blanket drain (id.).

In unrebutted testimony, Mr. Ferguson testified that, while there is such a drain in the

dam at issue, it is separate from the toe trench drain in question (tr. 1/75-77).

86. HDR cites Chapter 8 (Seepage) of this USBR publication, which makes a

clear distinction between a toe drain and a drainage trench. As in Chapter 5 cited

above, Chapter 8 states that toe drains collect water from the embankment’s internal

drainage system and that they “typically” contain two stages. With respect to drainage

trenches, USBR states that:

Downstream drainage trenches running parallel to the toe

of the dam can be used when downstream drainage of the

foundation is needed beyond what is normally provided by

a toe drain. In essence, the deeper trenches provide relief

of pressures and a filtered outlet for seepage layers that are

located at a greater depth than would be encountered with

a typical toe drain. . . . As with a toe drain, a perforated or

slotted collector pipe is typically included and set at the

lowest possible elevation that will still allow downstream

outfall.

(App. supp. R4, tab 2114 at 84)

87. The Board agrees with HDR that the single-stage drain that it designed is

consistent with USBR’s description of a drainage trench (see finding 26 (toe trench

drain extended as far as 14 feet below the surface into the permeable layer)). It is

notable, therefore, that USBR states that the trench provides drainage “beyond” that of

a toe drain. It is also notable that USBR does not speak of the drainage trench as

having two stages.

88. USACE has not responded to these contentions. Even though HDR’s

contentions are unrebutted, the Board is reluctant to accept them in full. USBR

Chapter 5, despite the trapezoidal rendering of the toe drain, speaks of a toe drain as

having either a trapezoidal or a rectangular geometry (app. supp. R4, tab 2010 at 54).

Nevertheless, HDR has succeeded in identifying an inconsistency in the USBR

guideline.

89. USBR Chapter 5 also discusses blanket drains. While it mentions

18

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

two-stage blanket drains, it does not contain a discussion of the advantages

of two-stage drains compared to one-stage. (Id. at 48-52)

FEMA, Filters for Embankment Dams (Oct. 2011)

90. This FEMA manual is very similar to the USBR guideline, perhaps because

the author of the USBR document is also one of the authors of the FEMA document

(compare R4, tab 100 at 6, with tab 101 at 14). The FEMA guideline contains the same

or very similar provisions as those quoted above from USBR Chapter 5 (R4, tab 101

at 32, 44, 65-68). However, it does not include the discussion in USBR section 5.3.3,

Cost.

FEMA, Technical Manual: Plastic Pipes Used in Embankment Dams

(Nov. 2007) 5

91. Chapter 4 of this manual is entitled Drainpipes and Filters (R4, tab 101

at 499). In section 4.2.1, Zoning, it provides:

Drainpipes have been designed in single and double stage

configurations. A single stage system consists of one zone

of filter material, usually sand, surrounding a drainpipe.

The double stage system consists of a coarse drainage zone

(gravel) surrounding the pipe and a filter (sand) zone

surrounding the coarse element. . . .

Single stage designs have been used on smaller jobs, such

as low hazard potential dams in the interest of reducing

costs and simplifying construction.

(Id. at 512)

92. This section further states:

Two stage filter/drain combinations have higher

permeability and will be more efficient in collecting

seepage than single stage filters. For these reasons, single

stage filters should be avoided and [sic] high hazard

potential dams and two stage filters are preferred by

designers. However, for economy and simplicity,

sometimes single stage drainage elements are used in low

hazard potential dams.

5

This document begins at page 363 of R4, tab 101.

19

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

(Id. at 513)

93. The dam at issue is a high hazard dam (R4, tab 44 at 16).

94. Finally, section 4.2.1 states that “If single stage filters are used, slots should

be no larger than the D50 of the filter” (R4, tab 101 at 514).

95. HDR sized the slots using the D50 of the filter, which means that 50% of the

materials are finer than the opening and 50% are coarser (tr. 1/153).

Guidelines Conclusion

96. USACE has cited guidelines that establish that a two-stage toe trench drain

provides superior performance to a one-stage drain and that the two-stage drain is the

recommended or usual choice. However, the Board also finds that the guidelines are

not entirely consistent, such as in the USBR discussion of toe drains and drainage

trenches (findings 85-87). The guidelines do not prohibit or completely rule out a

single-stage drain. Rather, they acknowledge that minimizing cost is important, and

that a single-stage drain may function properly if there are low amounts of seepage.

(Findings 79, 83-84)

97. In its post-hearing brief, USACE contends that the guidance from FEMA,

USBR, and USACE “regarding TTD design all required a Two-Stage TTD” (gov’t br.

at 6) (emphasis added). The Board disagrees and finds that this is an overstatement or

oversimplification.

98. The Board also finds that USACE has not cited any guidance stating that a

two-stage blanket drain performs better and is recommended in favor of a one-stage

blanket drain.

99. During the hearing, the parties focused on the toe trench drain. Based upon

our review of the transcript, the parties referred to the toe trench drain through a

variety of terms (for example, “TTD” or “toe drain”) approximately 479 times,

whereas the word “blanket” was used in reference to a drain only 44 times.

Expert Witnesses on Embankment Design

100. David Sykora, Ph.D., P.E., testified on behalf of HDR as an expert in

geotechnical engineering for dams and embankments (tr. 6/15). Dr. Sykora opined that

the guidance cited above (USACE, FEMA, USBR) did not bar the use of a single-stage

drain. He concluded that the guidance permits the designer to make a site-specific

analysis of conditions and allows the designer to optimize a system so that it is

functional, constructable, and cost efficient (tr. 6/35; app. supp. R4, tab 2036 at 27).

20

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

101. Dr. Sykora’s opinion was consistent with the testimony of Mr. Ferguson,

who testified that HDR prepared a “site specific design” (tr. 1/78). He testified that

this requires the designer “to consider many factors, amongst which are site geology,

site conditions, and the properties of the materials you’re dealing with” and to develop

models and perform testing (tr. 1/164). Mr. Ferguson cited the costs and

constructability that USACE requested HDR achieve, as well as HDR’s seepage

models that showed it would provide the required pressure reduction, as factors

leading to selection of the one-stage toe trench drain (id. at 134, 154). Mr. Ferguson’s

testimony on these issues was credible and unrebutted.

102. Dr. Sykora performed calculations to assess the efficacy of the system

designed by HDR. His calculations confirmed that the toe trench drain “sufficiently

reduce[d] the seepage gradients at the downstream tail of the dam” (tr. 6/45). He

concluded that HDR accurately calculated peak flows into the pipe and appropriately

applied a safety factor of 10 when selecting the pipe, meaning that it calculated the peak

flow and then used a number 10 times higher (app. supp. R4, tab 2036 at 75-76, 139).

103. The Board finds that Dr. Sykora’s testimony on this issue was unrebutted.

The Board also observes that the analysis of Mr. Talbot from the independent technical

review panel is consistent with the testimony of Dr. Sykora and Mr. Ferguson

(findings 23-24).

104. USACE submitted an expert report dated October 6, 2020 and testimony

from Thomas L. Brandon, Ph.D., P.E. (R4, tab 75). Dr. Brandon’s analysis is largely

based on his review of technical guidelines, including those discussed above. He did

not perform any independent analysis of HDR’s single-stage design to determine if it

would have provided sufficient pressure reduction. Dr. Brandon’s report

acknowledges guidance stating that a single-stage filter offers the advantage of lower

cost and is easier to construct than a two-stage filter (id. at 2). However, he read the

design guidelines as providing “no leeway at all” to select a single-stage filter, and he

opined that, if HDR believed a single-stage filter was appropriate, it should have

submitted a written justification (tr. 4/59-60, 67).

105. Dr. Brandon seemed to have read only a limited number of documents and

spent only 20-30 hours preparing his October 6, 2020 report. The value of his

testimony was limited by his lack of preparation. He testified that he did not

adequately re-familiarize himself with his report and he contradicted himself as to

whether he had read Dr. Sykora’s report. This may have been because USACE did not

enter into a contract with him until shortly before the hearing began, which also

deprived HDR of the opportunity to depose him. (Tr. 4/58, 70, 78-80, 87, 6/152-53)

He did not interview any of the USACE employees involved in the decision to approve

the single-stage toe trench drain, nor any other USACE employee (tr. 4/88).

21

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

106. Dr. Brandon’s report undercut USACE’s position somewhat with respect

to the iron-rich groundwater clogging the pipes. He stated that “there isn’t a standard

design procedure to definitively deal with it” but opined that the narrow slots specified

by HDR “would exacerbate the problem” (R4, tab 75 at 6).

DECISION

The Board has held that under FAR 52.236-23, the Architect-Engineer clause, a

designer is obligated “to exercise its architectural skill, ability and judgment with

reasonable care and without negligence.” Brunson Assocs., Inc., ASBCA No. 41201,

94-2 BCA ¶ 26,936 at 134,152; (see finding 5). The clause does not impose on

designers “strict liability for mistakes, ambiguities, or so-called ‘defects’ in the

specification it prepared.” Ralph M. Parsons Co., ASBCA No. 24347, 85-1 BCA

¶ 17,787 at 88,899.

In Ralph M. Parsons, the Board cited Corpus Juris Secundum (C.J.S.), as

containing “what has been perceived as the ‘applicable law’ within the meaning of the

‘Responsibility of the Architect-Engineer’ clause.” Id. The current version of C.J.S.

provides:

An architect must exercise such care, skill, and diligence as

others who are engaged in the profession would ordinarily

exercise under similar circumstances. . . . [I]n the absence

of an express agreement to the contrary, an architect, like a

physician or lawyer, does not guaranty, imply, or warrant a

perfect plan or favorable or satisfactory results. It follows

that an architect’s work can be inaccurate or imperfect

without being an actionable deviation from the standard of

care.

6 C.J.S. Architects § 16 (Dec. 2024 Update) (footnotes omitted).

C.J.S. and precedent equate the standard of care for architects with other

professions. E.g., Bonadiman-McCain, Inc. v. Snow, 183 Cal. App. 2d 58, 70, 6 Cal.

Rptr. 52 (1960) (“The engineer’s undertaking in respect to the plans he prepares is

comparable to that of an architect . . . .”); City of Mounds View v. Walijarvi,

263 N.W.2d 420, 424 (Minn. 1978). Similarly, the Architect-Engineer clause makes

no distinction between the standard for an architect and that for an engineer. Thus,

while HDR is an engineering firm, the Board considers precedent involving architects

as applicable to this appeal.

The Board’s decisions and those of many other jurisdictions provide that a

designer can commit an error without departing from the professional standard of care.

22

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

As the Supreme Judicial Court of Maine held in a 19th century case, “[a]n error of

judgment is not necessarily evidence of a want of skill or care, for mistakes and

miscalculations are incident to all the business of life.” Coombs v. Beede, 36 A. 104,

105 (Me. 1896). Similarly, the Supreme Court of Minnesota explained that:

Architects, doctors, engineers, attorneys, and others deal in

somewhat inexact sciences and are continually called upon

to exercise their skilled judgment in order to anticipate and

provide for random factors which are incapable of precise

measurement. The indeterminate nature of these factors

makes it impossible for professional service people to

gauge them with complete accuracy in every instance.

Thus, doctors cannot promise that every operation will be

successful. . . . Because of the inescapable possibility of

error which inheres in these services, the law has

traditionally required, not perfect results, but rather the

exercise of that skill and judgment which can be

reasonably expected from similarly situated professionals.

City of Mounds View, 263 N.W.2d at 424. In Bonadiman-McCain, a California court

stated:

The services of experts are sought because of their special

skill. They have a duty to exercise the ordinary skill and

competence of members of their profession, and a failure

to discharge that duty will subject them to liability for

negligence. Those who hire such persons are not justified

in expecting infallibility, but can expect only reasonable

care and competence. They purchase service, not

insurance.

Bonadiman-McCain, 183 Cal. App. 2d at 70 (citations omitted).

USACE states in its brief that the “seminal case” for architect-engineer liability

is Parsons Main, Inc., 02-2 BCA ¶ 31,886 (gov’t br. at 18). In those appeals, the

Board identified three elements that the government must prove under the Architect-

Engineer clause: “(1) Did the construction contractor substantially comply with the

[Architect-Engineer]’s design in the manner intended by the A-E? (2) Did the

[Architect-Engineer] exercise its skill, ability and judgment negligently, instead of

with reasonable care, with respect to the design? (3) Was the [Architect-Engineer]’s

defective design the proximate cause of damage to the Government?” Parsons Main,

Inc., ASBCA Nos. 51355, 51717, 02-2 BCA ¶ 31,886 at 157,537.

23

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

First Prong of Parsons Main: Compliance with the Design

USACE contends that it has met the first prong of the test because Barnard

constructed the test section (finding 32; gov’t br. at 18). The Board disagrees. We

will assume without deciding that constructing a 300-foot test section of a 9.3-mile toe

trench drain could be enough to satisfy the test. But we believe that for a 300-foot test

section to suffice, it would have to be built and operated as designed by HDR. That

never happened. When the test was conducted the reservoir had not been constructed

and filled, which meant that the “driving force” of water from an elevated reservoir

was not present (finding 32). The purpose of the test was not to determine if the

single-stage toe trench drain was sufficient to relieve the pressure (id.), and USACE

and Barnard did not attempt to simulate operational conditions. And while the test did

cause water to flow through the pipe (albeit backwards), the water was exposed to

atmospheric oxygen (finding 37). As a result, it likely had higher levels of oxygen,

and higher levels of iron oxide, than if the system had been operated as designed, and

would have been more likely to clog the pipes.

Accordingly, we have found that the test was not a reasonable approximation of

operational conditions (finding 38). The test did not demonstrate that HDR’s single-

stage toe trench drain would risk dam failure, nor did it demonstrate that the drainpipes

would become clogged in an unreasonably short amount of time.

USACE also has not presented any evidence that the single-stage blanket drain

was ever built or tested.

USACE has failed to prove the first prong of the Parsons Main test.

Second Prong of Parsons Main: Reasonable Care

After consideration of the record, including six days of testimony, the Board

concludes that HDR acted with reasonable care and judgment. This is not to say that a

single-stage toe trench drain was the optimal choice for the project from a purely

engineering perspective (finding 96). However, one major aspect of exercising

professional judgment is weighing the optimal engineering solution versus what the

client is willing to pay for and making reasonable tradeoffs. The record demonstrates

that, in addition to the guidelines that recommend a two-stage drain (finding 96), HDR

had to weigh the site conditions, including the geology and the properties of the site

materials, the amount of projected seepage (findings 83, 101), and the budget and

demands of a sophisticated client (findings 18-20, 27, 54-57).

HDR’s client, USACE, primarily was the Jacksonville District, but there were

dozens of highly sophisticated people that HDR had to contend with. The Philadelphia

and Louisville Districts also made appearances along with USACE’s consultant,

24

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

Gannett Fleming (findings 28, 51). The SFWMD was a constant presence, along with

its consultant, Ardaman & Associates (findings 11, 17-20, 28). The record

demonstrates that at least some employees or representatives of USACE were

skeptical of the need for a toe trench drain (findings 18, 20, 27). The record also

demonstrates that a single-stage toe trench drain is expensive and complex and that a

two-stage drain is even more expensive and complex (finding 15). The contractual

requirement for HDR to design within USACE’s budget (finding 6) and USACE’s

budget constraints placed limits on what HDR could do. HDR could not force

USACE to choose a more expensive drain or to obtain more funds. See Coombs,

36 A. at 106 (describing the problems that ensued when a client required his architect

to adhere to a budget for the construction of a home but demanded a house that was

worth much more than that budget).

The Board’s review of precedent establishes that expert testimony is often

crucial in a professional negligence claim. E.g., Ralph M. Parsons, 85-1 BCA

at 88,896-98. Even though the single-stage toe trench drain was never built, and

despite the absence of a clear-cut event demonstrating a defective design such as a

collapse of the dam, USACE perhaps could have proved that HDR was negligent

through expert analysis. Both parties presented expert testimony, but it was so

lopsided in favor of HDR that it was impossible for USACE to meet its burden of

proof.

A. The Geologist/Geochemistry Experts

USACE had the right idea when it tasked its geologist with determining how

quickly the single-stage toe trench drain pipes with 0.9 mm slots would clog (finding 40).

But the geologist acknowledged in her testimony that she had made errors (finding 45).

HDR presented persuasive, unrebutted testimony from an expert who demonstrated that

the USACE geologist had vastly overstated the clogging rates (findings 42-43).

Accordingly, USACE’s geologist failed to prove that HDR negligently designed an

embankment with a pipe that would become clogged in an unreasonably short period of

time.

The Board acknowledges that USACE had multiple concerns about the original

pipe specified by HDR. USACE decided to change from a single-stage drain to a

two-stage drain sometime after the Philadelphia District opined that the pipes specified

by HDR were too thick, would be custom-made and might have manufacturing

defects, and would be too difficult to clean with water jetting (finding 51). While this

is merely theoretical because there were no reported manufacturing defects and there is

no evidence that anyone attempted to waterjet the pipes specified by HDR, we do not

disregard these concerns. But the record shows that USACE switched to a pipe that

addressed these perceived shortcomings and that was also less expensive (finding 59).

USACE’s overstatement of the rate at which the pipes would clog, combined with the

25

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

switch to a pipe that would be easier to clean, together mean that USACE cannot

demonstrate that the single-stage drain would have become clogged in a short period

of time.

B. The Embankment Experts

USACE also could have presented an analysis and calculations as to whether the

single-stage toe trench drain would have sufficiently relieved pressure in the

embankment, but it failed to do so. The Board heard testimony and evidence on this

topic from HDR’s designer of record, Mr. Ferguson, who testified that seepage would be

low and that HDR’s computer models showed that the single-stage drain would be

sufficient (finding 13). The Board received the report and testimony of HDR’s expert,

Dr. Sykora, whose calculations showed that HDR’s design was sufficient (finding 102).

The Board found both Mr. Ferguson and Dr. Sykora to be credible witnesses. HDR also

submitted into evidence documents authored by the late Mr. James Talbot, an expert on

seepage, who had calculated that HDR’s design was sufficient (findings 23-24). By

contrast, the Board found the testimony of USACE’s expert, Dr. Brandon, to be

unhelpful based on his lack of preparation, his failure to perform his own calculations,

and failure to interview any witnesses (findings 104-05). In sum, the evidence with

respect to whether the single-stage drain would have worked on this specific site was

almost completely one-sided in favor of HDR.

USACE bases almost its entire case upon its interpretation of various design

guidelines. USACE admits that the guidelines are not mandatory (at least in its

opening brief), and it has shown a willingness to waive them when it deems it

appropriate (findings 56, 73). As we have found, USACE incorrectly asserts that the

guidelines prohibit single-stage toe trench drains (finding 97).

USACE’s dam expert, Dr. Brandon, based his opinion on these guidelines and

comparable resources (finding 104). Dr. Brandon made the best argument USACE has

left, which is that, even if the guidelines do not completely bar single-stage toe trench

drains, the guidelines discourage them to the point that HDR should have created a

record where it provided a clear explanation as to why it had selected a single-stage

drain instead of a two-stage drain (id.).

There are several problems with this argument. USACE did not call as

witnesses any of the USACE or SFWMD employees involved in the toe-trench drain

discussions with HDR (findings 21, 29). Perhaps if they had testified that they were

misled somehow by HDR we would have a different case. But the record is clear that

they were aware that they were discussing an issue that could result in failure of the

dam and that their decision required a weighing of risk versus cost (finding 20). The

record is also clear that they pushed for at least partial elimination of the toe trench

drain (findings 20, 27). Dozens of technical experts from USACE, SFWMD, Gannett

26

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

Fleming, or Ardaman & Associates examined the design (finding 28) and the Board

believes that it is reasonable to assume that at least some of these people were

competent and had read the relevant guidelines. The most reasonable interpretation of

what happened is the one HDR has offered: based on USACE’s budget, the low

amount of seepage, the types of soil at the site, HDR’s computer modeling and

calculations, and the location of the pipes below groundwater (to prevent formation of

iron oxide), the single-stage drain was a reasonable solution for this project.

USACE also has failed to prove that it was professional negligence for HDR to

design a single-stage blanket drain. As we have found, USACE devoted very little

attention to the blanket drain in terms of testimony at the hearing, expert opinion, or

other documentary evidence (finding 99). USACE seems to have proceeded based on

an underlying assumption that if it proved that the two-stage toe drench drain was

necessary this would also prove the necessity for a two-stage blanket drain, but it

failed to prove its toe trench drain claim. Accordingly, USACE’s blanket drain claim

suffers from a complete failure of proof.

USACE has not proven the second prong of the Parsons Main test.

Third Prong of Parsons Main

Having ruled that USACE failed to meet the first two elements of the test, the

Board will not reach the third element of the test.

CONCLUSION

For the foregoing reasons, the appeal is sustained.

Dated: January 15, 2025

MICHAEL N. O’CONNELL

Administrative Judge

Vice Chairman

(Signatures continued) Armed Services Board

of Contract Appeals

27

NOT FOR PUBLIC DISTRIBUTION

This document contains protected material and is subject to the terms of an ASBCA

Protective Order.

I concur I concur

OWEN C. WILSON THOMAS P. McLISH

Administrative Judge Administrative Judge

Acting Chairman Armed Services Board

Armed Services Board of Contract Appeals

of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA No. 62723, Appeal of HDR

Engineering, Inc., rendered in conformance with the Board’s Charter

Dated:

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

28

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.