Opinion

Mvl USA, Inc. v. United States

Court
United States Court of Federal Claims
Filed
Jan 21, 2025
Status
Published
On the bench
Ryan T. Holte
Cited by
0 cases
Authority
More cited than 33.7%

“But our task is to apply the language of the statute, not to rewrite it.”

How later courts described this case

  • “But our task is to apply the language of the statute, not to rewrite it.”
  • “Our task is to interpret the statute as written, as we have, not to rewrite it.”
  • “Trial courts are given broad latitude in managing . . . cases.”
  • “We first address whether the [solicitation] provided for full and open competition in light of the [regulatory policy] contained therein. . . . [If not,] we then address whether the agency’s approach was otherwise permissible.”

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

Nos. 24-1057, 24-1077, 24-1144, 24-1219, 24-1398, 24-1433, 24-1461

(Filed: 21 January 2025) *

***************************************

MVL USA, Inc., et al., *

*

Plaintiffs, *

* Nos. 24-1057,

v. * 24-1077, 24-1144,

* 24-1219, 24-1398,

THE UNITED STATES, * 24-1433, 24-1461

*

Defendant. *

*

***************************************

Dirk D. Haire, with whom were Joseph L. Cohen, Payum Sean Milani-nia, David Timm,

Jane Jung Hyoun Han, and Michael J. Brewer, of Fox Rothschild, LLP, all of Washington, DC,

for plaintiff MVL USA, Inc., and consolidated plaintiffs Environmental Chemical Corporation,

JCCBG2, and Harper Construction Company, Inc.

Jacob W. Scott, with whom were Allison G. Geewax, and Mark S. Abrajano, of Smith

Currie Oles LLP, all of Tysons, VA, for consolidated plaintiff Hensel Phelps Construction Co.

William P. Rayel, Senior Trial Counsel, Commercial Litigation Branch, Civil Division,

Department of Justice, with whom were Natalee A. Allenbaugh, Trial Attorney, Commercial

Litigation, Civil Division, Department of Justice, Brian M. Boynton, Principal Deputy Assistant

Attorney General, Patricia M. McCarthy, Director, Douglas K. Mickle, Assistant Director,

Tarrah M. Beavin, Assistant Division Counsel, South Atlantic Division, USACE, J. Alexandra

Fitzmaurice, Associate Counsel, NAVFAC Southeast, and Angelina Calloway, Assistant

Regional Counsel, GSA Region 7, Greater Southwest, all of Washington, DC, for defendant.

OPINION AND ORDER

HOLTE, Judge.

Twelve large construction companies—seven plaintiffs in this consolidated bid protest,

and five plaintiffs with protests now stayed—challenge the legal authority of federal agencies to

mandate prospective contractors to enter project labor agreements with unions for consideration

*

This Opinion was originally filed under seal on 19 January 2025 pursuant to the protective order in this case. The

Court provided the parties an opportunity to review this Opinion for any proprietary, confidential, or other protected

information and submit proposed redactions by 21 January 2025 at 10:00 a.m. (ET). The parties proposed

redactions. The Court accepts the parties’ proposed redactions and reissues the Opinion, with a few minor, non-

substantive corrections and redacted language removed as follows: “[XXXXXX].”

in federal construction projects exceeding $35 million. For the past thirty years, executive orders

surrounding the use of project labor agreements in government construction have “ping-ponged”

from “banning” or “encouraging” to now an unprecedented 4 February 2022 Executive Order

(14063) “mandating” the use of such agreements. Following the 2024 FAR Council

implementation of the mandate, agencies reversed course and required all solicitations to contain

a project labor agreement. By way of example, the 2023 initial market research for one

solicitation determined “project labor agreements were not recommended” because “there was a

shortage of skilled labor in the region of the project,” and project labor agreements would “not

contribute to the economy or efficiency of the project”—the agency nevertheless issued the

solicitation in 2024 with a project labor agreement requirement. See infra Section VI.A.

Another agency “increased the price” of the contract “based on the [project labor agreement]

requirement being included” despite previously concluding a project labor agreement would

negatively affect both competition and price. See infra Section VI.A. Similarly, in another

solicitation, initial 2023 market research found project labor agreements “not suitable for the

project,” but the agency ultimately determined in 2024 “no exception” applied and project labor

agreements would be required. See infra Section I.E. Most illustrative, however, was an

agency’s decision to “delete” prior 2023 market data indicating a project labor agreement “would

reduce competition, increase costs, and create inefficiencies for contractors and procurement

officials,” and “insert” a 2024 project labor agreement requirement simply because President

Biden and the FAR Council made “the policy judgment [that] project labor agreements are

generally good.” See infra Section VI.A. Despite market research consistently showing project

labor agreements would “reduce adequate competition at a fair and reasonable price” for the

solicitations, the agencies’ only support to justify reversal is the “policy determination that’s

been made by the President and the FAR.” See infra Section VI.B.

The agencies’ 2024 implementation of the mandate—ignoring the agencies’ own market

research concluding project labor agreements would be anticompetitive—relying solely on

executive order presidential policy is arbitrary and capricious. Specifically, the functionality of

the mandate as applied to the individual contracts in this case stifles competition and violates the

statutory directive that agencies must promote “full and open competition” in federal

procurements unless a statutory justification is properly invoked. For the following reasons, the

Court grants consolidated plaintiffs’ Motions for Judgment on the Administrative Record and

denies the government’s Cross-Motion for Judgment on the Administrative Record.

I. Factual Background

The Court begins the factual background discussion with brief reference to redactions in

the parties’ briefs—specifically whether redactions to market research on the inclusion of project

labor agreements (“PLA”) was proper under the Protective Order—as it came up at oral

argument. See 19 Sept. 2024 Protective Order, ECF No. 51. The Court then provides a

chronology of approaches to PLAs in government construction contracts by Presidential

Administrations beginning in the early 1990’s ending with the Biden Administration’s Executive

Order (“EO”) 14063. Lastly, the Court provides background for each of the seven consolidated

bid protests in this case and the various agencies’ decisions as to PLA requirements in each.

A. Redactions of the Parties’ Briefing

-2-

As is standard in bid protest cases, parties file all briefs under seal, later redact protected

information, and then refile public versions of the briefs with the redactions. Redactions ensure

the protection of information included in a protective order. See U.S. Ct. Fed. Cl. R. (“RCFC”)

5.2(e). The Court—in the “interest [of] open and public judicial proceedings, especially in bid

protests”—ensures redactions are kept to a minimum and redacted material is truly protected

information. See 16 Jan. 2025 Oral Arg. Tr. (“Tr.”) at 33:1–15, ECF No. 95. When the redacted

briefs were filed in this case, the redactions appeared excessive and primarily related to

information “get[ting] to the heart of the issue of . . . these PLA requirements” and the

Competition in Contracting Act (“CICA”). See Tr. at 38:3–17. At oral argument, the Court

discussed various redactions with government and agency counsel. See Tr. at 27:13–39:19. In

one example, the Court questioned whether certain information pertaining to a market study

commissioned by the U.S. General Services Administration (“GSA”) on the PLA requirement’s

potential impact was properly redacted. See Tr. at 28:3–12. To facilitate open discussion, the

Court sealed the proceeding, see Tr. at 29:23–24, and inquired as to why the government

redacted “many large DB firms interviewed have stated little to no interest in the project if PLAs

are a requirement” and “more contractor interest and thus a more competitive bid environment.”

Tr. at 30:22–31:3. The government stated GSA’s concern was “releasing the fact that there

might be fewer bids with the PLA requirement . . . could alter how contractors choose to submit

a proposal and maybe GSA [would not] get the best proposals.” Tr. at 31:4–14. GSA counsel

said it found the redactions to be “source selection information that could be a competitive

advantage” because it was a part of GSA’s “market research and really part of the planning of a

procurement.” Tr. at 35:6–14. Plaintiffs, however, disagreed with GSA and the government’s

conclusions regarding the necessity of the redactions. See Tr. at 32:2–24. Per plaintiffs, they

even “alerted” the government during meet and confers over redactions they felt were a “bit of

an overredaction.” See id. To avoid making redaction discussions “conflict-rife,” as it is usually

“an expensive and often fruitless process,” plaintiffs did not further challenge the redactions. See

Tr. at 32:19–33:15.

Due to the parties’ disagreement over the redactions’ validity, the Court referred the

parties to the Protective Order, see ECF No. 51, noting: “Protected information . . . as used in

this order means information that must be protected to safeguard the competitive process . . .

including source selection information,” Tr. at 37:9–18. The Court indicated the redacted

information appeared inapposite to information meant to be protected, see Tr. at 37:19–20

(“THE COURT: It sounds to [the Court] that [the redacted] information is the opposite of that

[outlined in the protective order].”), but the government maintained its “[v]iew is that the market

research going into preparation of the solicitation was something that is considered protected and

under source selection information.” See Tr. at 37:21–38:2. At the end of the sealed discussion,

the government agreed the information was not properly protected and the dialogue could be

unsealed. See Tr. at 38:3–39:2.

Though plaintiffs have no pending motion regarding the government’s redactions, the

Court agrees with plaintiffs—the government “overredacted” and the redacted information

should have been available as part of public briefing. See Tr. 32:2–33:15. In reviewing the

sealed and redacted briefs, the government, on numerous occasions, redacted information

unrelated to protecting the competitive process or otherwise allowed by the Protective Order.

-3-

For instance, at oral argument, the government agreed the redacted information concluded a PLA

requirement was likely to affect both competition and price. See Tr. at 31:4–14, 39:23–40:15.

This information “get[s] to the heart of the issue of . . . these PLA requirements and CICA” and

is “appropriate for what the gravamen of the case is about.” Tr. at 38:3–17; see Tr. at 39:3–19

(“[THE COURT:] On [administrative record] page 48, as part of the briefing, there were

unredacted notes about large firms stating little to no interest in the project if PLAs are a

requirement. So similar type language. . . . [GOVERNMENT:] I missed that one, then.”).

While the government agreed to unredact the information addressed at oral argument, see Tr. at

38:3–39:19, the Court will set a deadline for the government to revisit its redactions in the public

briefing and re-file their MJAR briefs, see RCFC 5(d) (“The court may later unseal the filing or

order the person who made the filing to file a redacted version for the public record.”), 18(c)(2)

(granting a wide discretion to the Court to deny motions for redaction), 18(d) (“In the absence of

a motion to redact, the entire decision will be made public within a reasonable time after the 14-

day redaction period has expired.”); see also McGinley v. Franklin Sports, Inc., 262 F.3d 1339,

1357 (Fed. Cir. 2001) (“Trial courts are given broad latitude in managing . . . cases.”). In

ordering a review, the Court emphasizes the importance of redacting only information subject to

the Protective Order. Court filings are open and public by default—redactions are the exception.

See, e.g., Gilead Scis., Inc. v. Sigmapharm Lab’ys, LLC, 584 F. App’x 929, 929–30 (Fed. Cir.

2014) (unpublished) (noting Federal Circuit law “requires the filing of briefs [be] accessible to

the public,” where “protective orders restricting the disclosure of information may only be issued

for ‘good cause,’” and further ordering defendant-appellant “to show cause why th[e] court

should not impose sanctions” for “briefs . . . contain[ing] extensive confidentiality markings”);

Dialect, LLC v. Amazon.com, Inc., No. 23-cv-581-DJN-LRV, ECF No. 225 at 2 (E.D. Va. May

10, 2024) (denying blanket redactions of information not covered by the protective order and

directing proposal of “narrowly tailored redactions” (emphasis original)); see also RCFC 5(d)

(“The court may later unseal the filing or order the person who made the filing to file a redacted

version for the public record.”); infra Section VIII.

B. History of Presidential Administration’s Treatment of PLAs

In 1984, Congress passed CICA, requiring all federal agencies awarding contracts for

services—including construction contracts—to “obtain full and open competition through the use

of competitive procedures.” 41 U.S.C. § 253(a)(1)(A). Congress passed CICA to increase the

number of competitors for government contracts and to increase savings through lower, more

competitive pricing. See Kate M. Manuel, Competition in Federal Contracting: An Overview of

the Legal Requirements, CONG. RSCH. SERV. (June 30, 2011). Under CICA, agencies must

solicit bids and offers “in a manner designed to achieve full and open competition” and “develop

specifications in such a manner as is necessary to obtain full and open competition.” See id. at

18–20 (citing 10 U.S.C. § 2305(a)(1)(A); 41 U.S.C. § 253a(a)(1)(A–C)).

Following the passage of CICA, Presidents for the past 30 years have issued EOs related

to the use of PLAs in government construction contracts and taken various policy stances.

Through EOs, Presidents have fluctuated between prohibiting PLAs, encouraging PLAs, taking a

neutral stance on PLAs, and, most recently, mandating PLAs. See Tr. at 9:15–19 (“[THE

COURT:] [L]ooking at the [] fluctuations [of EOs] over the years since at least the early 1990s

-4-

[directed to PLAs], they had gone back and forth between prohibiting, or generally encouraging,

but never before mandating? [GOVERNMENT:] Correct.”).

Beginning in 1992, President George H.W. Bush issued an EO prohibiting government

agencies from requiring PLAs by any parties to federal construction projects. See EO No.

12818, 57 Fed. Reg. 48713 (Oct. 28, 1992). President Bush issued the EO to “(1) promote and

ensure open bidding on Federal and federally funded construction projects; (2) increase

competition in Federal construction contracts and contracts under Federal grants or cooperative

agreements; (3) reduce construction costs; (4) expand job opportunities, especially for small

businesses; and (5) uphold the associational rights of workers freely to select, or refrain from

selecting, bargaining representatives and to decide whether or not to be union workers, so as to

provide access to employment opportunities on Federal and federally funded construction

projects for all workers . . . .” Id.

In 1993, President Clinton revoked President George H.W. Bush’s EO, and in 1997,

issued a Presidential Memorandum “encouraging . . . agencies . . . to consider [PLAs] as another

tool, one with a long history in governmental contracting, to achieve economy and efficiency in

Federal construction projects” on a “project-by-project basis.” See Memorandum on Use of

Project Labor Agreements for Federal Construction Projects, 1 PUB. PAPERS 705 (June 5, 1997).

President Clinton encouraged the use of PLAs in federal procurements “where a [PLA] w[ould]

advance the Government’s procurement interest in cost, efficiency, and quality and in promoting

labor-management stability as well as compliance with applicable legal requirements governing

safety and health, equal employment opportunity, labor and employment standards, and other

matters . . . .” See id.; see also Tr. at 10:17–11:11 (“[THE COURT:] So the FAR Council did

not actually do anything with President Clinton’s [EO]? [PLAINTIFF]: That’s my

understanding.”).

In 2001, President George W. Bush issued two EOs enacting a new federal government

policy of PLA neutrality. See EO No. 13202, 66 Fed. Reg. 11225 (Feb. 17, 2001); EO No.

13208, 66 Fed. Reg. 18717 (Apr. 6, 2001). These new EOs prohibited government-mandated

PLAs on both federal and federally-assisted construction projects and made clear that contractors

were free to enter into a PLA voluntarily without government interference. See EO No. 13202,

66 Fed. Reg. 11225 (Feb. 22, 2001); EO No. 13208, 66 Fed. Reg. 18717 (Apr. 11, 2001).

Specifically, President Bush directed the government—or “any construction manager acting on

behalf of the [g]overnment”—must not “[r]equire or prohibit bidders, offerors, contractors, or

subcontractors to enter into or adhere to agreements with one or more labor organizations . . .

[or] [o]therwise discriminate against bidders, offerors, contractors, or subcontractors for

becoming or refusing to become or remain signatories or otherwise to adhere to agreements with

one or more labor organizations, on the same or other related construction project(s).” EO No.

13202, 66 Fed. Reg. 11225 (Feb. 17, 2001).

In 2009, President Obama issued yet another new EO directed at PLAs. See EO No.

13502, 74 Fed. Reg. 6985 (Feb. 11, 2009). This EO revoked and replaced President George W.

Bush’s EOs and “encourage[ed] [federal] executive agencies [on a project-by-project basis] to

consider requiring the use of [PLAs] in connection with large-scale construction projects [for

$25 million or more] to promote economy and efficiency in Federal procurement.” Id.; see Tr. at

-5-

14:1–5 (“[GOVERNMENT]: The Obama [EO] rescinded the Bush [EO].”). While the EO

encouraged agencies to consider mandating PLAs, the EO did not mandate federal agencies to

impose PLAs on federal projects. See id. The EO further directed the Federal Acquisition

Regulatory Council (“FAR Council”) to implement the provisions of the EO. See EO No.

13502, 74 Fed. Reg. 6985 (Feb. 6, 2009). On 14 July 2009, the FAR Council rescinded FAR

36.202(d), which prohibited agencies from requiring PLAs. See Federal Acquisition Regulation

(“FAR”); Federal Acquisition Circular 2005-35; Introduction, 74 Fed. Reg. 34206-01 (July 14,

2009); FAR Case 2009-015, Revocation of EO 13202, 74 Fed. Reg. 34206-02 (July 14, 2009);

see also Tr. at 14:6–17 (“[THE COURT:] [T]he FAR Council issued a final rule amending the

FAR to implement Obama’s EO 13502, which encouraged agencies to use PLAs . . . and that

was the final Obama FAR Council amendment? [GOVERNMENT]: That sounds correct.”).

Effective 13 May 2010, the FAR Council issued a final rule “amending the [FAR] to implement

[EO 13502] . . . encourage[ing] the use of [PLAs] for large-scale Federal construction

projects . . . to promote economy and efficiency in Federal procurement.” FAR: Use of PLAs for

Federal Construction Projects, 75 Fed. Reg. 19168-02 (May 13, 2010). The rule provided:

An agency may, if appropriate, require [a PLA] . . . if the agency decides that the

use of [PLAs] will—

(1) advance the Federal Government’s interest in achieving economy and

efficiency in Federal procurement, producing labor-management stability,

and ensuring compliance with laws and regulations governing safety and

health, equal employment opportunity, labor and employment standards,

and other matters; and

(2) Be consistent with law.

FAR 22.503(b) (2023); see Tr. at 12:9–19 (“[GOVERNMENT:] [The FAR Council] issued

regulations implementing the [Obama EO] in . . . FAR Subpart 22.5.”).

The Trump Administration did not modify President Obama’s EO and maintained the

policy of encouraging agencies to consider requiring PLAs. See FAR: Use of PLAs for Federal

Construction Projects, 87 Fed. Reg. 51044-01 (proposed Aug. 9, 2022); see also Tr. at 17:4–19

(“[GOVERNMENT:] In terms of a policy regarding [PLAs] . . . Obama’s [EO] remained in

place, the FAR regulations remained in place, and those FAR regulations remained in place, and

those FAR regulations [are] what governed the agency’s consideration of including [PLAs] in

their construction contracts up until January 2024 when the Biden [EO] was implemented

through the FAR. THE COURT: . . . [Plaintiff] agree[s] with that? [PLAINTIFF]: I do.”).

On 4 February 2022, as explained infra Section I.C, President Biden issued EO 14063,

revoking the prior executive branch’s PLA policy. The FAR Council’s final rule implementing

EO 14063 was the first executive mandate to use PLAs for all large-scale government contracts.

See FAR 22.503 (Jan. 2, 2024); see also FAR 22.501 (Jan. 2, 2024) (“This subpart prescribes

policies and procedures to implement [EO] 14063, Use of [PLAs] for Federal Construction

Projects . . . .”).

-6-

C. President Biden’s EO Mandating PLA Requirements

In 2022, President Biden issued EO 14063, Use of PLA for Federal Construction

Projects. See EO No. 14063, 87 Fed. Reg. 7363 (Feb. 9, 2022). President Biden based the EO in

“the Constitution and the laws of the United States of America, including [the Federal Property

and Administrative Services Act” (“FPASA”) “to promote economy and efficiency in the

administration and completion of Federal construction projects . . . .” See id. The EO mandated

agencies to include PLAs with “one or more appropriate labor organizations” in “large-scale”

government construction projects exceeding $35 million. See id. at 7363–64. The EO mandated

PLAs because they “are often effective in preventing . . . problems from developing” and

“provide structure and stability to large-scale construction projects.” See id. at 7363.

Specifically, the EO stated PLAs should be mandated to “avoid labor-related disruptions on

projects by using dispute-resolution processes to resolve worksite disputes and by prohibiting

work stoppages, including strikes and lockouts.” Id.

The EO, despite mandating PLAs for all government construction projects over $35

million, provided for narrow exceptions to the PLA requirement under certain circumstances.

See id. at 7364. Particularly, the EO instructed a “senior official within an agency may grant an

exception from the [PLA] requirement . . . for a particular contract by, no later than the

solicitation date” if the senior official provides “a specific written explanation of why at least one

of the following circumstances exists” regarding the contract: (1) “[r]equiring a [PLA] on the

project would not advance the Federal Government’s interests in achieving economy and

efficiency in Federal procurement[;]” (2) “[b]ased on an inclusive market analysis, requiring a

[PLA] on the project would substantially reduce the number of potential bidders so as to frustrate

full and open competition;” and (3) “[r]equiring a [PLA] on the project would otherwise be

inconsistent with statutes, regulations, [EOs], or Presidential Memoranda.” See id. The

“economy and efficiency” exception must be based upon the following factors:

(i) [t]he project is of short duration and lacks operational complexity; (ii) [t]he

project will involve only one craft or trade; (iii) [t]he project will involve

specialized construction work that is available from only a limited number of

contractors or subcontractors; (iv) [t]he agency’s need for the project is of such an

unusual and compelling urgency that a [PLA] would be impracticable; or (v) [t]he

project implicates other similar factors deemed appropriate in regulations or

guidance issued pursuant to section 8 of [EO 14063].

Id. Section 8 of the EO required the FAR Council to propose regulations implementing the order

within 120 days, evaluate comments, and promptly issue a final rule. See id. at 7365. On 22

December 2023, the FAR Council promulgated a final rule implementing EO 14063, mandating

“every contractor and subcontractor engaged in construction on the project agree, for that

project, to negotiate or become a party to a PLA with one or more labor organizations.” See Use

of PLAs for Federal Construction Projects, 88 Fed. Reg. 88708, 88723 (Dec. 22, 2024)

(incorporated in FAR pts. 1, 7, 22, 36, and 52); see also FAR 52.222-33 (Notice of Requirement

for PLA); FAR 52.222-34 (PLA).

-7-

D. MVL USA Inc.’s Protest: USACE Consolidated Rigging Facility at Joint Base

Lewis McChord in Washington

MVL USA Inc.’s protest arises from Request for Proposal (“RFP” or “solicitation”) No.

W912DW24R0024, issued by the United States Army Corps of Engineers (“USACE”) for the

construction of a consolidated rigging facility at Joint Base Lewis-McChord in Washington. See

MVL AR at 3610. USACE issued the solicitation on 30 May 2024, and estimated the magnitude

of construction to be between $25 million and $100 million. See MVL AR at 144 (Working Cost

Estimate), 361 (Solicitation).

The solicitation includes a PLA requirement by incorporating FAR 52.222-33 and

52-222-34. See MVL AR at 4069 (Amendment 4 to the Solicitation). The solicitation requires

“[a]ny PLA submitted with the offer must comply with the requirements for the FAR Provision

52.222-33” and declares “[o]nly Offerors with a PLA that is acceptable and fully in compliance

with the contract requirements will be considered eligible for award.” MVL AR at 4069

(Amendment 4 to the Solicitation).

In January 2023, USACE issued a sources sought notice for the project, see MVL AR at

1–3 (Sources Sought Notice), and then, in April 2023, USACE issued a special notice PLA

survey, see MVL AR at 77 (2023 Special Notice PLA Survey). On 23 May 2023, based on the

PLA survey responses and regulations in force at the time (i.e., the Obama EO and FAR 22.5),

USACE did not recommend a PLA for this solicitation in its memorandum of finding. See MVL

AR at 109–14 (2023 PLA Decision Memorandum). See Tr. at 43:6–22 (“THE COURT: So

[USACE] found, in short, looking at the conclusions here [the PLA mandate] would increase

costs, it would not facilitate training of a skilled workforce, it would not contribute to economy

or efficiency; all of that is correct? . . . [GOVERNMENT:] There was a determination it would

not contribute to economy or efficiency for the project under consideration . . . . THE COURT:

And the final conclusion was that [USACE] concluded that a PLA was not recommended since

the ‘strengths of implementing the PLA are outweighed by the weaknesses and risks to the

stakeholder of the project?’ [GOVERNMENT]: That was the conclusion in 2023.”). Then on

22 January 2024, before USACE issued the solicitation, the solicitation was amended to

implement the Biden EO. See MVL AR at 4368 (2024 PLA Decision Memorandum).

On 12 July 2024, MVL filed this protest. See Compl., ECF No. 1. USACE then

determined the market research and analysis of the PLA requirement was performed pursuant to

the rescinded EO and FAR regulations. See MVL AR at 4368 (2024 PLA Decision

Memorandum). USACE thus issued a special notice PLA survey on 25 July 2024. See MVL

AR at 4136 (2024 Special Notice PLA Survey). The contracting officer (“CO”) analyzed the

Special Notice PLA Survey responses and found no exception applied, so the PLA requirement

remains in the solicitation. See MVL AR at 4373 (2024 PLA Decision Memorandum); compare

Tr. at 86:23–87:7 (“[THE COURT:] What was the [MVL] analysis based under, other than a

new regulation? . . . [GOVERNMENT:] I think in the MVL case there was some additional

market research . . . . [W]e’re not saying . . . that necessarily was the change. The change was

that there was a different analysis to be done of that data under the new . . . regulation . . . .”),

with Tr. at 21:6–19 (“[THE COURT:] Did anything change in the market conditions during the

course of the time [from 2023 to] 2024? [GOVERNMENT]: Not that I am aware of. THE

-8-

COURT: So the only . . . reason the PLA requirement was placed was because of the regulation?

[GOVERNMENT]: Right . . . .”).

E. Harper Construction Company, Inc.’s Protest: USACE KC-46 Two-Bay

Maintenance/Fuel Cell Hangar at March Air Force Reserve Base in California

Harper Construction Company, Inc.’s protest arises from Solicitation No.

W912QR24R0034, issued by USACE for the construction of a KC-46 two-bay maintenance/fuel

cell hangar at March Air Reserve Base in California. See Harper AR at 6021 (Solicitation). The

estimated magnitude of the project was anticipated to be between $100 million and $250 million.

See Harper AR at 6021 (Solicitation). USACE issued the solicitation on 4 September 2024. See

Harper AR at 6021 (Solicitation). The Solicitation stated USACE would award the contract to

“the responsible offeror whose proposal conforms with all the terms and conditions of the

solicitation . . . .” See Harper AR at 6040 (Solicitation). The Solicitation required all offerors to

submit an executed PLA in accordance with FAR 52.222-33 and 52.222-34. See Harper AR at

6053 (Solicitation).

In December 2022, before the FAR provisions implementing the Biden EO were issued,

USACE conducted initial market research for this procurement. See Harper AR at 5–13

(Original Sources Sought Notice), 14–18 (2022 Special Notice PLA Survey), 19–49 (2022

Market Research Report). The market research included a survey seeking comments on whether

to include a PLA requirement in the solicitation. See Harper AR at 14–18 (2022 Special Notice

PLA Survey). USACE received no responses. See Harper AR at 52 (2023 Market Research

Report), 61 (2023 PLA Decision Memorandum). USACE then performed additional market

research, see Harper AR at 53 (2023 Market Research Report), and on 18 January 2023,

determined a PLA should not be required for the project, see Harper AR at 60–62 (2023 PLA

Decision Memorandum); see also Tr. at 23:5–17 (“[THE COURT:] [B]ased on the record,

[USACE] would not have included the PLA requirements [in the Harper solicitation] without the

FAR PLA mandate, correct? [GOVERNMENT]: Correct.”). Specifically, USACE initially

“determine[d] that inclusion of the [FAR] PLA clauses is not suitable for the project, and the use

of a PLA will not be evaluated or approved as part of source selection / award.” Harper AR at

6061 (Solicitation). But in March 2024, USACE made a new determination to include a PLA

requirement, finding “no exception to use of a PLA applie[d]” to the project. See Harper AR at

290.1 (2023 PLA Decision Memorandum).

On 9 September 2024, Harper filed this bid protest. See Compl., Harper Constr. Co.,

Inc. v. United States, No. 24-1398 (Fed. Cl. Sept. 9, 2024), ECF No.1. After the filing of this

protest, USACE’s review of the AR revealed the only market research for this solicitation was

conducted before the Biden EO was implemented, causing USACE to issue another PLA survey

on 17 September 2024. See Harper AR at 6147 (2024 Memorandum for Record on

Determination on Use of a PLA). USACE received no responses by the 1 October 2024

deadline. See Harper AR at 6147 (2024 Memorandum for Record on Determination on Use of a

PLA). The CO then analyzed whether any new Biden EO FAR exceptions to the PLA

requirement applied to this procurement—none did. See Harper AR at 6147–49 (2024

Memorandum for Record on Determination on Use of a PLA). The PLA requirement therefore

-9-

remains in place in the solicitation. See Harper AR at 6147–49 (2024 Memorandum for Record

on Determination on Use of a PLA).

F. Hensel Phelps Construction Company, Inc’s GSA Protest: GSA Bridge of the

Americas Land Port of Entry Modernization Act in Texas

Hensel Phelps Construction Company, Inc.’s (“Hensel” or “HPCC”) GSA protest arises

from Solicitation No. 47PH0824R0007 issued on 7 August 2024. See HPCC GSA AR at 253,

256 (Phase I Solicitation). The solicitation is for the design and construction of a Land of Port of

Entry at the Bridge of the Americas, on the international border separating El Paso, Texas, from

Juarez, Chihuahua, Mexico. See HPCC GSA AR at 253, 256 (Phase I Solicitation). GSA

estimated the project cost to be between $500 and $550 million. See Hensel GSA AR at 258

(Phase I Solicitation).

In April 2024, GSA issued a sources sought notice for the procurement, indicating a PLA

requirement for the project, to which GSA received multiple responses. See HPCC GSA AR at

99–101 (Market Analysis Record). GSA received mixed responses regarding the PLA

requirement: (1) bidders expressed interest in the procurement and indicated concerns about the

PLA requirement, but did not indicate the PLA requirement would prevent submission of a

proposal, see HPCC GSA AR at 124–25 (2024 Sources Sought Responses); (2) bidders did not

address the PLA requirement; see HPCC GSA AR at 129–32 (2024 Sources Sought Responses);

and (3) other bidders indicated they were interested in submitting proposals, but would “make []

final determination[s] based on when the solicitation [was] actually released and available

resources at that time,” see HPCC GSA AR at 129 (2024 Sources Sought Responses); see also

Tr. at 52:3–8 (“[GOVERNMENT:] [R]emoving the PLA requirement would result in more

contractor interest and, thus [a] more competitive bid environment . . .”); Tr. at 53:22–54:3

(“[THE COURT:] [W]hat would the difference be between having a PLA requirement and not

having a PLA requirement as to GSA’s market study conclusion? [GOVERNMENT]: I mean,

the expectation was that there might be less competition and potentially a higher price . . . .”).

GSA then outsourced a market study to a third-party to determine a PLA requirement’s

potential impact, see Tr. at 24:17–25:2 (“THE COURT: So [GSA] pay[s] an outside expert to

analyze the marketplace of potential contractors? [GOVERNMENT]: I don’t know if they’re an

expert or not, but at least an outside firm . . .”), resulting in the following recommendation:

Selecting a Design-Build firm with experience working within a PLA or union

environment will be of benefit to the project; however, many large . . . firms

interviewed have stated little to no interest in the project if PLAs are a requirement.

Removing the PLA requirement would result in more contractor interest and, thus,

a more competitive bid environment. If elimination of the requirement is not an

option, we recommend shifting from FAR 52.222-33 Notice of Requirement for

Project Labor Agreement (Jan 2024) Alternate I (Jan 2024) to FAR 52.222-33

Notice of Requirement for Project Labor Agreement (Jan 2024) Alternate II (Jan

2024) which allows for PLAs to be entered into following BD contract award,

which could potentially increase response by one or more contractors.

- 10 -

HPCC GSA AR at 48 (Market Survey). GSA mandated PLAs for the procurement based on the

totality of its market research, even though a PLA requirement was likely to affect both

competition and price. See HPCC GSA AR at 176 (Acquisition Plan); see also Tr. at 40:18–

41:15 (“[THE COURT:] [T]he GSA’s conclusion, based on the market research report, was that

the PLA requirement would ‘affect both competition and price’ . . . . [GOVERNMENT:] GSA

determined that in doing its independent government estimate, [it would] increase[] the price . . .

based on the PLA requirement . . . .”); see also Tr. at 140:8–11 (“THE COURT: So you agree

that the agency concluded [the PLA mandate] would reduce competition and increase cost?

[GOVERNMENT]: It would be likely to is what GSA concluded, I believe.”). GSA indicated it

would request an exception if there was no competition or unreasonable pricing. See HPCC

GSA AR at 176 (Acquisition Plan). Hensel filed this bid protest on 18 September 2024. See

Compl., Hensel Phelps Constr. Co. v. United States, No. 24-1461 (Fed. Cl. Sept. 18, 2024), ECF

No 1.

G. Hensel Phelps Construction Company, Inc.’s NAVFAC Protest: Engineering

Test Facility at Cape Canaveral Space Force Station in Florida

Hensel Phelps Construction Company Inc.’s Naval Facilities Engineering Systems

Command (“NAVFAC”) protest arises from Solicitation No. N6945024R0065 for the

construction of an engineering test facility for the Trident II Life Extension 2 system at the Cape

Canaveral Space Force Station in Brevard County, Florida. See HPCC NAVFAC AR at 235

(Solicitation). NAVFAC estimated the project magnitude is between $100 million to $250

million. See HPCC NAVFAC AR at 235 (Solicitation). The solicitation issued in August 2024.

See HPCC NAVFAC AR at 235 (Solicitation).

In March 2024, NAVFAC issued a sources sought notice and a request for information

regarding PLA use. See HPCC NAVFAC AR at 30–37 (PLA Special Notice), 38 (PLA

Questionnaire). NAVFAC received several responses, including responses from labor unions,

large construction firms, and a small business. See HPCC NAVFAC AR at 39–56 (PLA

Questionnaire Responses). The labor unions supported including a PLA requirement in the

solicitations and noted they believed the PLA requirement would ensure the government

received more proposals from national contractors while simultaneously promoting smaller

contract involvement. See HPCC NAVFAC AR at 137–39 (Individual Streamlined Acquisition

Plan with Services). The small business similarly supported the PLA requirement, indicating it

would help local building trades. See HPCC NAVFAC AR at 136–37 (Individual Streamlined

Acquisition Plan with Services). The large businesses, however, opposed the PLA requirement,

indicating interest only if there was no PLA requirement or suggesting evaluation of the value

and feasibility of PLA mandated projects would need to occur before bid submission. See HPCC

NAVFAC AR at 55 (PLA Questionnaire Responses).

In its July 2024 acquisition plan, NAVFAC analyzed the PLA request-for-information

responses and declined to pursue an exception to the Biden EO PLA mandate. See HPCC

NAVFAC AR at 136–39 (Individual Streamlined Acquisition Plan with Services). NAVFAC

recommended a PLA requirement because it could not “be definitively determined, based on the

responders’ comments that two proposals would not be received” and that the small business and

labor unions supported a PLA requirement. See HPCC NAVFAC AR at 129 (Individual

- 11 -

Streamlined Acquisition Plan with Services). Of the proposals NAVFAC ultimately received,

only Hensel protested the PLA requirement. See HPCC NAVFAC MJAR Ex. 1 (Declaration of

Hensel’s Regional VP). Hensel filed this bid protest on 13 September 2024. See Compl., Hensel

Phelps Constr. Co. v. United States, No. 24-1433 (Fed. Cl. Sept. 13, 2024), ECF No. 1.

H. Hensel Phelps Construction Company, Inc.’s Protest: USACE Consolidated

Communications Facility at Patrick Space Force Base in Florida

Hensel Phelps Construction Company Inc.’s USACE protest arises from Solicitation No.

W9127823R0115 for the construction of a consolidated communications facility at Patrick Space

Force Base in Brevard County, Florida. See HPCC USACE AR at 4961 (Solicitation

Amendment 01). The estimated magnitude of the construction was between $25 million to $100

million. See HPCC USACE AR at 4969 (Solicitation Amendment 01). USACE issued the

solicitation in May 2024. See HPCC USACE AR at 4968 (Solicitation Amendment 01).

In July 2023, USACE conducted market research for the project, and on 31 July 2023,

issued a sources sought notice and a PLA survey, to which nine firms, including Hensel,

responded, expressing interest in the procurement. See HPCC USACE AR at 77–79 (2023

Sources Sought Notice). All respondents recommended USACE not require contractors to enter

into a PLA. See HPCC USACE AR at 79.3–79.11 (PLA Responses). In August 2023, in

accordance with the FAR PLA regulations under the Obama EO, USACE determined it would

not mandate a PLA for this project as a “PLA would not contribute to the economy or efficiency

for the project under consideration. See HPCC USACE AR at 155.1–155.3 (First PLA

Memorandum).

In February 2024, after the FAR was amended to implement the Biden EO, USACE

issued another PLA survey. See HPCC USACE AR at 253 (Second PLA Market Survey). In

analyzing the responses, USACE concluded a “majority of respondents indicated that a PLA

mandate would reduce competition, increase costs, and create inefficiencies for contractors and

procurement officials.” See HPCC USACE AR at 284 (Acquisition Plan Addendum 1).

USACE, however, was unable to determine if requiring a PLA would “reduce the number of

potential offerors to such a degree that adequate competition at a fair and reasonable price could

not be achieved.” See HPCC USACE AR at 284 (Acquisition Plan Addendum 1). Thus, based

on the Biden EO, USACE found no exception to the use of PLAs applied. See HPCC USACE

AR at 284 (Acquisition Plan Addendum 1). Hensel then filed a bid protest in this case on 15

July 2024. See Compl., Hensel Phelps Construction Co. v. United States, No. 24-1077 (Fed. Cl.

July 15, 2024), ECF No. 1.

In August 2024, the CO issued a new determination regarding a PLA requirement for the

project. See HPCC USACE AR at 311–15 (D&F PLA Addendum). The new determination was

issued to comply with a July 2024 USACE policy clarification, which required the memorandum

to include a discussion of any responses to the PLA survey and other information to determine

whether an exception applies. See HPCC USACE AR at 314 (D&F PLA Addendum). The CO

examined what he believed to be the relevant responses to the February 2024 market survey,

which were mixed: some strictly opposed including a PLA requirement, some were neutral, and

some were generally in favor. See HPCC USACE AR at 313–14 (D&F PLA Addendum). The

- 12 -

CO thus found none of the FAR exceptions applied to exempt the project from the PLA

requirements. See HPCC USACE AR at 314–15 (D&F PLA Addendum). Specifically, the CO

found “[g]iven the mixed results of the market survey” he could not “conclude that requiring a

PLA on this project would substantially reduce the number of potential offerors to such a degree

that adequate competition at a fair and reasonable price could not be achieved.” HPCC USACE

AR at 314 (D&F PLA Addendum). The CO further found the notice amending the FAR

addressed some respondents’ arguments that a PLA requirement would increase project costs by

twelve to twenty percent; the notice found numerous studies finding no definitive and

compelling evidence PLAs increase costs for federal construction projects. See HPCC USACE

AR at 314–15 (D&F PLA Addendum). The CO also stated the PLA requirement would not be

inconsistent with any law, regulation, or other executive policy declaration. See HPCC USACE

AR at 313 (D&F PLA Addendum). The CO ultimately concluded “[l]ooking at the market

survey results as a whole, along with feedback received from the union officials/trade councils,

there is no basis to support an exception” to the PLA requirement. See HPCC USACE AR at

315 (D&F PLA Addendum).

In September 2024, the CO updated the PLA determination memorandum because

Hensel’s July 2023 PLA survey response was used instead of its February 2024 PLA survey

response. See HPCC USACE AR at 338.1–338.6 (D&F PLA Addendum 2). The CO, however,

determined Hensel’s position had not changed between the two responses regarding PLAs, and

thus, found no reason to alter its previous finding that no exception to the PLA requirement

applied. See HPCC USACE AR at 338.6 (D&F PLA Addendum2).

I. Environmental Chemical Corporation’s Protest: USACE Cyber & DoD

Information Network Facility (Signal School) at Fort Eisenhower in Georgia

Environmental Construction Company’s (“ECC”) protest arises from Solicitation No.

W912HN24B4002, issued by USACE’s Savannah District, for the construction of a cyber and

Department of Defense Information Network Facility (“Signal School”) at Fort Eisenhower,

Georgia. See ECC AR at 400 (Solicitation). USACE issued the solicitation in May 2024. See

ECC AR at 400 (Solicitation). The solicitation estimated the magnitude of the project to be

between $100 million and $250 million. See ECC AR at 400 (Solicitation). Before issuing the

solicitation, USACE conducted market research to determine if an exception to the PLA

requirement under FAR 22.503(b) applied. ECC AR at 47 (Sources Sought Notice). On 8

January 2024, USACE issued a sources sought notice with questions related to the PLA

requirement. See ECC AR at 47–49 (Sources Sought Notice), 62–63 (Sources Sought-Market

Survey). Of the firms that responded to the PLA surveys: (1) one stated a PLA would not

advance the government’s interests in this procurement, see ECC AR at 122–34 (Sources Sought

Response); (2) one did not respond, see ECC AR at 68 (Sources Sought Response); and (3) one

stated a “PLA could help transparency between the client and service provider,” but noted the

PLA could lead to a drastic miscalculation for cost, enormous growing pains, and future

disruptions, see ECC AR at 138–39 (Sources Sought Response). Despite not responding to the

market research survey, ECC later submitted a request urging USACE to find an exception to the

PLA requirement. See ECC AR at 280–83 (CO Acknowledgement of ECC Request to Consider

PLA Exception), 336 (Market Research Report). USACE, however, determined an exception

did not apply. See ECC AR at 300–01 (PLA Decision Memorandum). In doing so, USACE

- 13 -

reasoned even if it took “at face value the assertions of the [] firms which expressed concerns

about the inclusion of a PLA requirement” other bidders “did not express these concerns” and

the “response from industry does not indicate the inclusion of a PLA would result in an unduly

restricted pool of bidders” for the project. See ECC AR at 301 (PLA Decision Memorandum).

ECC then filed this protest on 26 July 2024. See Compl., Env’t Chem. Corp. v. United States,

No. 24-1144 (Fed. Cl. July 26, 2024), ECF No. 1.

J. JCCBG2’s Protest: USACE Lab and Lab Annex Buildings for the Department

of Agriculture in Alabama

JCCBG2’s protest arises from Solicitation No. W9127824R0013, issued by USACE’s

Mobile Contracting Division, for the construction of the Department of Agriculture’s Agriculture

Research Service lab and lab annex buildings located in Auburn, Alabama. See JCCBG2 AR at

1044 (Solicitation). USACE estimated the magnitude of this project was about [XXXXXXX].

See JCCBG2 AR at 1029 (Independent Government Estimate–Market Research & Analysis).

USACE issued the solicitation in February 2024. See JCCBG2 AR at 1044, 1066 (Solicitation).

The deadline for proposals was set at 21 May 2024. See JCCBG2 AR at 1044, 4266

(Solicitation).

Since issuance, the solicitation has: (1) required offerors to submit an executed PLA with

their proposal; (2) provided for evaluation of the PLA on an Acceptable/Unacceptable basis; and

(3) incorporated FAR 52.222-33 and 53.222-34. See JCCBG2 AR at 1068, 1086–87, 1090, 1115

(Solicitation). In July 2024, USACE issued Amendment 8 to the solicitation, deleting the

specific requirements for offeror PLAs and replacing those provisions with a reference to FAR

52.222-33(c) requirements. See JCCBG2 AR at 4846, 4858–59 (Amendment 8 to Solicitation).

In November 2023, USACE issued a sources sought notice for the procurement,

expressly requesting respondents to address the anticipated impact to cost and schedule from the

PLA requirement. See JCCBG2 AR at 157–59 (PLA Determination and Findings). All

respondents expressed concern about the inclusion of a PLA requirement, with a majority

indicating they would not submit a proposal if the solicitation mandated a PLA. See, e.g.,

JCCBG2 AR at 155, 160–66, 170–74, 180–83 (PLA Determination and Findings); Tr. at 106:1–

12 (“[PLAINTIFF:] [In] the JCCBG2 example, there were [] contractors who responded, and []

of the [] said . . . either they wouldn’t propose on the project with a PLA, or they were unlikely

to.”). In a January 2024 memorandum, the CO summarized and considered the respondents’

concerns and ultimately determined “none of these concerns provide an exception” to remove the

PLA requirement from the solicitation. See JCCBG2 AR at 155 (PLA Determination and

Findings); see, cf. Tr. at 106:18–107:11 (“[PLAINTIFF:] [I]n actuality, on the JCCBG2

[example], they did, in fact, only get [] offers.”). The CO therefore “determined that use of a

PLA is suitable for the subject project.” See JCCBG2 AR at 156 (PLA Determination and

Findings). The memorandum did, however, indicate USACE would not require a PLA until after

the award of the contract. See JCCBG2 AR at 156 (PLA Determination and Findings). But in

July 2024, the CO issued an addendum to the January 2024 memorandum explaining it based its

decision to require offerors to submit an executed PLA with their proposals on an updated

USACE policy issued shortly after the January 2024 memorandum was signed. See JCCBG2

- 14 -

AR at 1032 (New PLA Determination on the Use). JCCBG2 filed this protest on 8 August 2024.

See Compl., JCCBG2 v. United States, No. 24-1219 (Fed. Cl. August 8, 2024), ECF No. 1.

II. Procedural History

On 12 July 2024, MVL filed its Complaint in this pre-award bid protest. See Compl.,

ECF No. 1. On 15 July 2024, Hensel filed its Complaint in Hensel Phelps Construction Co. v.

United States, No. 24-1077 (Fed. Cl. July 15, 2024), along with a notice the protest is directly

related to MVL USA, Inc., No. 24-1057. See Compl., Hensel Phelps Constr. Co., No. 23-1077,

ECF No. 1; Notice of Directly Related Cases, ECF No. 10. That day, Hensel also filed a Motion

for Preliminary Injunction and Motion for Temporary Restraining Order. See Mot. Prelim. Inj.

and TRO, ECF No. 4.

On 18 July 2024, the parties filed a joint motion for protective order in the MVL USA,

Inc. case, see Jt. Mot. for Protective Order, ECF No. 6, which the Court granted, see 19 July

2024 Order, ECF No. 13. On 22 July 2024, the parties filed a joint status report (“JSR”)

proposing a case schedule. See 22 July 2024 JSR at 1, ECF No. 16; 22 July 2024 JSR, Hensel

Phelps Constr. Co., No. 23-1675, ECF No. 16.

On 24 July 2024, the Court held a status conference with MVL and Hensel and the

government. See 19 July 2024 Order, MVL USA, Inc., No. 24-1057, ECF No. 13; 19 July 2024

Order, Hensel Phelps Constr. Co., No. 23-1077, ECF No. 14. During the status conference, the

parties agreed case Nos. 24-1057 and 24-1077 should be consolidated under RCFC 42. See 24

July 2024 Consolidation Order at 1–2, MVL USA, Inc., No. 24-1057, ECF No. 18. On 24 July

2024, the Court issued an order consolidating the cases (“Consolidated Bid Protests”) and

designating MVL USA, Inc., No. 24-1057, as the lead case in this matter. See id. at 1–2. On 26

July 2024, the Court issued a protective order. See 26 July 2024 Protective Order, ECF No. 19.

On 26 July 2024, ECC filed its Complaint along with a Notice stating its protest is

directly related to the Consolidated Bid Protests. See Compl., Env’t Chem. Corp. v. United

States, No. 24-1144 (Fed. Cl. July 26, 2024), ECF No. 1; Notice of Directly Related Case, ECF

No. 2. On 30 July 2024, the Court consolidated EEC’s bid protest with the previously

consolidated cases—with MVL USA, Inc. serving as the lead case. See 30 July 2024

Consolidation Order at 1–2, MVL USA, Inc., No. 24-1057, ECF No. 28. On 30 July 2024, the

Court reissued the Protective Order with an updated case caption reflecting the newly

consolidated case. See 30 July 2024 Protective Order at 1, ECF No. 29.

On 8 August 2024, JCCBG2 filed its Complaint along with a Notice this protest is

directly related to the Consolidated Bid Protests. See Compl., JCCBG2 v. United States, No.

24-1219 (Fed. Cl. August 8, 2024), ECF No. 1; Notice of Directly Related Case, ECF No. 2. On

12 August 2024, the Court consolidated JCCBG2’s bid protest with the Consolidated Bid

Protests per the parties’ agreement. See 12 Aug. 2024 Consolidation Order at 1–2, MVL USA,

Inc., No. 24-1057, ECF No. 30. That day, Court also reissued the Protective Order with an

updated case caption reflecting the newly consolidated case. See 12 Aug. 2024 Protective Order

at 1, ECF No. 31.

- 15 -

On 27 August 2024, the government filed notice of its filing the administrative record

(“AR”) in the Consolidated Bid Protests. See Gov’t Notice of Filing the AR at 1, ECF No. 32.

On 5 September 2024, the government filed a motion to amend the AR with USACE policy

documents, which the Court granted the same day. See Gov’t Unopposed Mot. to Amend the

AR at 1, ECF No. 38.

On 9 September 2024, Harper filed its Complaint along with a Notice this protest is

directly related to the Consolidated Bid Protests. See Compl., Harper Constr. Co., Inc. v. United

States, No. 24-1398 (Fed. Cl. Sept. 9, 2024), ECF No. 1; Notice of Directly Related Case, ECF

No. 2. Additionally, on 13 September 2024, Hensel launched a second bid protest, filing its

Complaint along with a Notice its protest is directly related to the Consolidated Bid Protests. See

Compl., Hensel Phelps Constr. Co. v. United States, No. 24-1433 (Fed. Cl. Sept. 13, 2024), ECF

No. 1; Notice of Directly Related Case, ECF No. 7. On 16 September 2024, the Court

consolidated Harper and Hensel’s bid protests with the Consolidated Bid Protests per the parties’

agreement. See 16 Sept. 2024 Consolidation Order at 1–2, MVL USA, Inc., No. 24-1057 (Fed.

Cl. July 19, 2024), ECF No. 41; 16 Sept. 2024 Consolidation Order at 1–2, ECF No. 42. The

Court reissued the Protective Order with an updated case caption reflecting the newly

consolidated case. See 16 Sept. 2024 Protective Order at 1, ECF No. 43.

On 18 September 2024, Hensel began a third bid protest, filing its Complaint along with

a Notice its protest is directly related to the Consolidated Bid Protests. See Compl., Hensel

Phelps Constr. Co. v. United States, No. 24-1461 (Fed. Cl. Sept. 18, 2024), ECF No. 1; Notice of

Directly Related Case, ECF No. 7. On 19 September 2024, the Court consolidated Hensel’s bid

protest with the Consolidated Bid Protests, see 19 Sept. 2024 Consolidation Order at 1–2, MVL

USA, Inc., No. 24-1057, ECF No. 50, and issued the Protective Order with an updated case

caption reflecting the newly consolidated case, see also 19 Sept. 2024 Protective Order at 1, ECF

No. 51.

On 23 September 2024, the government filed a motion for leave to amend the AR, which

the Court granted. See Gov’t Unopposed Mot. for Leave to Amend, ECF No. 54. On 24

October 2024, the government filed another motion for leave to amend the AR, which the Court

granted. See Gov’t Unopposed Mot. for Leave to Amend, ECF No. 62. On 25 October 2024, all

seven consolidated plaintiffs filed their Motions for Judgment on the Administrative Record

(“MJAR”). See MVL MJAR, ECF No. 64; ECC MJAR, ECF No. 65; JCCBG2 MJAR, ECF No.

66; Harper MJAR, ECF No. 67; HPCC GSA MJAR, ECF No. 68; HPCC NAVFAC MJAR, ECF

No. 69; HPCC USACE MJAR, ECF No. 70. On 22 November 2024, the government filed its

Cross-Motion and Response to plaintiffs’ MJARs. See Gov’t Cross-MJAR and Resp., ECF No.

73. On 9 December 2024, MVL, ECC, JCCBG2, and Harper filed their Reply in Support of their

MJARs and Response to the government’s Cross-MJAR. See Pls.’ Reply and Resp., ECF No.

79. Contemporaneously, JCCBG2 filed a separate additional response addressing the

government’s arguments as to the timeliness of JCCBG2’s protest. See JCCBG2 Resp. to Gov’t

Cross-MJAR at 1–4, ECF No. 78. That day, Hensel filed its combined Reply in Support of its

three separate MJARs and Response to the government’s Cross-MJAR. See HPCC Reply and

Resp., ECF No. 80. On 23 December 2024, the government filed its Reply in Support of its

Cross-MJAR. See Gov’t Reply, ECF No. 84. On 16 January 2025, the Court held oral

argument. See 16 Dec. 2024 Order, ECF No. 81.

- 16 -

Contemporaneous to the briefing schedule in the Consolidated Bid Protests, five

additional directly related bid protests were filed: (1) Harper Constr. Co., Inc. v. United States,

No. 24-1532 (Fed. Cl. Sept. 30, 2024); (2) W.M. Jordan Co., Inc. v. United States, No. 24-1648

(Fed. Cl. Oct. 15, 2024); (3) Harper Constr. Co., Inc. v. United States, No. 24-2054 (Fed. Cl.

Dec. 13, 2024), (4) Harper Constr. Co., Inc. v. United States, No. 24-2055 (Fed. Cl. Dec. 13,

2024); and (5) Harper Constr. Co., Inc. v. United States, No. 25-36 (Fed. Cl. Jan. 1, 2025). As

these cases all challenged the inclusion of PLAs in the various cases’ respective solicitations, the

parties agreed to stay the cases pending the Court’s resolution of the Consolidated Bid Protests

and voluntarily stay award of the solicitations of the various procurements pending the resolution

of this case. See 7 Oct. 2024 Order Staying Case, Harper, No. 24-1532, ECF No. 10; 25 Oct.

2024 Order Staying Case, W.M. Jordan, No. 24-1648, ECF No. 11; 14 Jan. 2025 Order Staying

Case, Harper, No. 24-2054, ECF No. 10; 14 Jan. 2025 Order Staying Case, Harper, No.

24-2055, ECF No. 10; 14 Jan. 2025 Order Staying Case, Harper, No. 25-36, ECF No. 9.

III. Parties’ MJAR Arguments

A. Plaintiffs’ Argument the PLA Requirements Violate CICA

Plaintiffs argue the PLA requirements in all solicitations violate CICA’s “full and open

competition” procedure by disqualifying otherwise responsible offerors who do not enter into a

PLA with a labor union, even though the offerors may otherwise be determined to be the best

value offeror. See MVL MJAR at 15–16; ECC MJAR at 20; JCCBG2 MJAR at 19; Harper

MJAR at 15; see also HPCC GSA MJAR at 8–13; HPCC NAVFAC MJAR at 7–12; HPCC

USACE MJAR at 15–21. Rather than specify an agency’s needs for a solicitation’s particular

procurement, the PLA requirements regulate market-wide labor concerns by requiring every

prospective responsible contractor on a large-scale construction project to enter into a PLA with

a labor union although contractors may not use PLAs to supply labor to their projects. See MVL

MJAR at 17; ECC MJAR at 22; JCCBG2 MJAR at 21; Harper MJAR at 17; see also HPCC

GSA MJAR at 15; HPCC NAVFAC MJAR at 14; HPCC USACE MJAR at 22. Plaintiffs argue

the PLA requirements must be expressly authorized by statute, concluding the PLA requirements

are not evaluation criteria, but an exclusionary policy unlawfully restricting full and open

competition MVL MJAR at 19; ECC MJAR at 24; JCCBG2 MJAR at 23; Harper MJAR at 20

see also HPCC GSA MJAR at 13–15; HPCC NAVFAC MJAR at 12–14; HPCC USACE MJAR

at 21–23. In turn, plaintiffs argue the agencies cannot rely on the Biden EO as the requisite

statutory authorization and should therefore be deemed void and unenforceable. See MVL

MJAR at 20; ECC MJAR at 24; JCCBG2 MJAR at 23; Harper MJAR at 20.

The government responds, arguing “[a]n entity is not a ‘responsible source’ for a

particular procurement if it cannot meet the [g]overnment’s minimum capacity and experience

requirements for that procurement.” Gov’t Cross-MJAR and Resp. at 32–33 (quoting FAR §

9.104-1). The government explains, “the solicitation’s capability and experience requirements

do not cause the solicitation to provide for less than full and open competition simply because

those requirements render some prospective contractors ineligible for award.” Id. at 33. The

government characterizes the PLA requirement in each of the seven solicitations as “simply one

of the many requirements that offerors must meet to perform the contract at issue.” Id. at 34.

- 17 -

Accordingly, the government concludes the plaintiffs’ inability to meet the PLA requirements

does not mean the solicitations provide for less than full and open competition, but it does mean

plaintiffs are not “responsible sources” for the procurements. See id. at 35 (quoting 41 U.S.C. §

107).

In reply, plaintiffs argue the PLA requirements cannot qualify as mere performance

specifications because the PLA requirements apply on a class-wide basis and exclude from

competition all contractors unable or unwilling to enter into a PLA with one or more labor

unions for projects over $35 million in value—irrespective of any procurement’s specific needs.

See Pls.’ Reply at 4–5; HPCC Reply and Resp. at 3–8.

B. Plaintiffs’ Argument the PLA Requirements Are an Unauthorized

Socio-Economic Set-Aside in Violation of CICA

Plaintiffs argue “[t]he Court must hold that the PLA requirements . . . constitute

statutorily unauthorized socioeconomic set-asides [that] are unlawful under CICA.” MVL

MJAR at 31. In particular, plaintiffs allege the PLA requirements contradict and nullify the

seven individual solicitations’ common “full and open” competition requirement. See MVL

MJAR at 27; ECC MJAR at 42; JCCBG2 MJAR at 35; Harper MJAR at 33. Plaintiffs reason the

PLA requirements arbitrarily and capriciously mandate plaintiffs—as entities, otherwise

responsible offerors—enter a PLA agreement with a labor union to be eligible for award under

the solicitation. See MVL MJAR at 27; Harper MJAR at 33. Plaintiffs note the FAR expressly

prescribes policies and procedures for providing for full and open competition after excluding

one or more sources, but the PLA requirements do not have a “set-aside” designation under the

FAR or statute. See MVL MJAR at 28. According to plaintiffs, if the government intends to

enforce the PLA requirements without violating CICA’s full and open competition requirement,

Congress must first enact a statute authorizing set-aside procurements for PLAs and then the

FAR Council would have to create a specific set-aside requirement for PLAs. See MVL MJAR

at 29–30.

The government counters, arguing “any responsible source who can satisfy the agencies’

requirements, including the PLA requirements, may compete for contracts.” Gov’t Cross-MJAR

at 37. “Moreover, the fact that the source of the PLA requirements are [FAR] provisions

implementing an [EO] does not transform the procurements into restricted competitions or ‘set

asides.’” Id. at 2. The government boils this case down to choice: “the inability or

unwillingness of a particular contractor to comply with a FAR clause incorporated into a

solicitation does not mean that the solicitation provides for less than full and open competition.”

See id.

In reply, plaintiffs argue even if the PLA requirements were performance specifications,

the government’s argument must fail “because the PLA requirements are unauthorized by statute

and are therefore unauthorized by law.” Pls.’ Reply at 13–14; see also HPCC Reply and Resp. at

3–8. Plaintiffs explain CICA expressly reserves set-aside authority for Congress, not the

President, as possible exceptions to full and open competition must be mandated expressly by a

statute. Pls.’ Reply at 14; see, e.g., 41 U.S.C. § 3304(a)(5); 41 U.S.C. § 3301(a); see also HPCC

Reply and Resp. at 3–8. Plaintiffs argue the EO violates FPASA because Congress expressly

- 18 -

reserved to itself the right to create socioeconomic set-asides to CICA. See Pls.’ Reply at 15; see

also HPCC Reply and Resp. at 3–8. According to plaintiffs, “the President cannot implement

policy through orders that contravene Congressional action and which are not otherwise

authorized by Congress or the Constitution.” See Pls.’ Reply at 15; see also HPCC Reply and

Resp. at 3–8. Plaintiffs argue the EO is unenforceable because the EO fails to cite the operative

provision of FPASA. See Pls.’ Reply at 15; see also HPCC Reply and Resp. at 3–8. Finally,

even if the Court were to adopt the government’s interpretation of FPASA, plaintiffs argue the

AR contradicts the government’s assertion the EO promotes economy and efficiency. See Pls.’

Reply at 15; see also HPCC Reply and Resp. at 3–8.

1. Plaintiffs’ Argument CICA Expressly Reserves Set-Aside Authority for

Congress—Not the President

Plaintiffs argue Congress expressly reserved to itself the right to create socioeconomic

set-asides to CICA “[b]ecause Congress specifically preserved its authority to legislate in

CICA,” and Congress “could not have delegated those same powers to the President in FPASA.”

See Pls.’ Reply at 14. When an EO or FAR regulations violate a statute—as plaintiffs allege in

this case—the EO and FAR provisions “are void and enforceable.” See id. According to

plaintiffs, a presidential directive can stand only if the subordinate officials have the authority

that they are told to exercise. See id. at 15.

The government argues FPASA authorizes the President to “prescribe policies and

directives that the President considers necessary to carry out this subtitle,” so long as the policy

and directives are “consistent with this subtitle.” See Gov’t Cross-MJAR at 47 (quoting 40

U.S.C. § 121(a)). The government argues the agencies here hold “broad discretion” in the

“determination of [the government’s] minimum needs,” and the PLA requirements are necessary

to satisfy the needs of the agencies. See id. at 42. According to the government, “[n]othing

prohibits agencies from relying on Presidential policy and generally applicable FAR clauses in

determining their needs for particular procurements.” Id. The government argues “the

President’s duty [is] to ‘take Care that the Laws be faithfully executed,’” quoting U.S. Const. art

II, § 3, which “includes guidance and supervision of agencies in implementing [c]ongressional

direction to specify their needs.” Id.

2. Plaintiffs’ Argument the EO Is Unauthorized Under Article II of the

Constitution

Plaintiffs argue the President’s authority to implement policy is not unlimited because the

President is not a lawmaker. See Pls.’ Reply at 15. “[T]he President cannot implement policy

through EOs that contravene [c]ongressional action and which are not otherwise authorized by

Congress or the Constitution.” Id. According to plaintiffs, the EO violated CICA’s “specified

source” restriction because the mandate “excludes a specified source—offerors who are

unwilling or unable to enter into a PLA with a labor union—from receiving a large-scale

construction contract, and there is no [c]ongressional authorization for this restriction.” Id. at 16.

Plaintiffs broadly conclude the EO “is unauthorized under Article II of the Constitution.” Id.

- 19 -

The government characterizes as “erroneous” plaintiffs’ argument President Biden lacked

the authority to issue the EO. Id. at 45. According to the government, the EO was authorized

under both Article II of the Constitution and FPASA. See Gov’t Cross-MJAR at 45. The

government argues the PLA requirements are “authorized by law” under 10 U.S.C. §

3206(a)(2)(B) and 41 U.S.C. § 3306(a)(2)(B), because the PLA requirements are based on

regulations having the force and effect of law. See id. at 44. The government argues “[t]he [EO]

was authorized under both Article II of the Constitution and FPASA.” Id. The government

acknowledges the President’s authority “is not without limits” as the President is not “a

lawmaker,” yet the President’s “faithful execution of the laws enacted by Congress . . . ordinarily

allows and frequently requires the President to provide guidance and supervision to his

subordinates.” Id. (citations omitted). Given the EO “contains an exception to the PLA

requirements,” the government concludes the EO was designed to “ensur[e] that its terms do not

run afoul of statutes or regulations.” Id. at 47.

3. Plaintiffs’ Argument the FPASA Does Not Support Presidential Action of

this Kind and Magnitude

Plaintiffs argue “the [g]overnment fails to cite to any operative provision of the FPASA

that grants President Biden authority to enact the PLA [r]equirements.” See Pls.’ Reply at 20

(emphasis in original). Plaintiffs note the EO “does not cite to any specific operative provision

of FPASA,” but rather, “simply cites to the purpose section of FPASA to implement the PLA

[r]equirements.” Id. Plaintiffs assert a non-operative provision “cannot confer freestanding

powers upon the President unbacked by operative language elsewhere in the statute.” See id.

(citations omitted). Accordingly, without relying on operative statutory language, the

President—through the EO—“cannot use FPASA to exert a power that Congress has never

conferred upon him.” Id.

The government acknowledges FPASA includes a statement providing “the purpose of

this subtitle is to provide the . . . [g]overnment with an economical and efficient system for the

following activities . . . [p]rocuring and supplying property and nonpersonal services, and

performing related functions including contracting, inspection, storage, issue, [and] setting

specifications.” Gov’t Reply at 21 (quoting 40 U.S.C. § 101(1)). The government argues this

purpose statement “vests the President with broad authority to set . . . policies [respecting] its

own procurement decisions.” Id. Furthermore, “Congress authorized the President to issue

directives that he ‘considers necessary to carry out this title.’” See id. (quoting 40 U.S.C.

§ 121(a) (emphasis added)). According to the government, the EO is valid if it “bears a

sufficiently close nexus to the statutory objectives of economy and efficiency. See id. at 21

(citation omitted).

Plaintiffs, however, argue “the administrative record demonstrates that the PLA

[r]equirements lack a nexus to economy and efficiency in federal procurements. See Pls.’ Reply

at 25. Plaintiffs point to the PLA market survey responses, where respondents all agree “a PLA

would increase costs and scheduling while reducing the competition” and “would not contribute

to the economy or efficiency of the project, not promote the agency’s long term program

interests.” See id. (citations omitted).

- 20 -

4. Plaintiffs’ Argument the PLA Requirements Impermissibly Delegate

Procurement Responsibility Determinations to Private Labor Unions

Even if Congress had delegated to the President authority under FPASA to issue the EO ,

plaintiffs argue the PLA requirements impermissibly delegate procurement responsibility

determinations to private labor unions. See Pls.’ Reply at 26. By tasking third parties with the

responsibility of selecting awardees, the government foregoes the direct competitive

procurement process in violation of procurement law. See id. “The unions’ ability to direct the

pricing and prime contractor award decision by choosing which contractor it will execute a PLA

with gives the unions control if an otherwise successful offeror will be held responsive or not,

without any ability by the [g]overnment to take this control from the unions and make award to

the otherwise responsible offeror who is either the low bidder or the best value.” Id. at 27.

The government counters, arguing “if the President’s authority under 40 U.S.C. § 121(a)

was limited to merely carrying out some specific reference in the statute, it would render a

portion of the statute superfluous.” Gov’t Cross-MJAR and Resp. at 52 (citation omitted).

Finally, the government argues “Congress has implicitly ratified the . . . President’s authority

under FPASA” because, in 2002, Congress recodified both FPASA’s purpose statement and

Section 121. See id. at 50.

C. The Timeliness of JCCBG2’s Protest

The government argues one plaintiff, JCCBG2, “forfeited its objections to the PLA

requirements in the solicitation it challenges by failing to protest the PLA requirement before the

deadline for the submission of proposals.” See Gov’t Cross-MJAR and Resp. at 31. According

to the government, when a plaintiff can object to solicitation terms containing a patent error but

fails to do so before the close of the bidding process, that plaintiff waives its ability to raise the

same objection in a subsequent bid protest action. See id. (citations omitted). The government

contends JCCBG2 should have formally protested before the close of bidding. See id. Given

proposals were due by 21 May 2024, the government acknowledges JCCBG2 “submitted a

timely proposal,” but argues JCCBG2 “did not formally protest the solicitation’s inclusion of the

PLA requirements until August 2024,” so JCCBG2 “forfeited its challenge to the solicitation’s

PLA requirements.” See id. at 312.

In response, JCCBG2 argues its objection was timely made before the close of the

bidding process. See JCCBG2 Resp. to Gov’t Cross-MJAR at 1, ECF No. 78. JCCBG2 argues

the relevant inquiry is whether JCCBG2 objected to the terms of the solicitation “prior to the

close of the bidding process.” See id. (citations omitted) (emphasis added). According to

JCCBG2, the government’s application of the “narrower timing requirements of GAO regulation

4 C.F.R. § 21.2(a)(1)” is inapplicable here as the GAO regulation imposes the wrong legal

standard. See id. at 6. Further, the government has not awarded the solicitation and has agreed

to suspend the award pending JCCBG2’s protest, which JCCBG2 argues obviates any concern

JCCBG2 could be attempting to obtain an unfair advantage. See id. at 7.

The government counters, arguing “JCCBG2’s protest must be rejected regardless of the

merits of its objections because JCCBG2 forfeited its challenge by failing to protest before the

- 21 -

deadline for submission of proposals.” Gov’t Reply at 2. Rejecting JCCBG2’s argument, the

close of the bidding process is the award of the contract, not the proposal submission deadline.

See id. The government argues “this Court has held that protest grounds challenging solicitation

terms were waived in pre-award protests because the plaintiffs raised those protests grounds

after the deadline for the submission of proposals.” See id. Further, “JCCBG2 acknowledges

that challenges to solicitation terms must generally be brought at GAO before the proposal

submission deadline,” which “is further evidence that ‘close of the bidding process’ means the

deadline for the submission of bids, proposals, or quotes.” Id. at 3.

D. Plaintiffs’ Argument the Court Should Issue a Permanent Injunction

Plaintiffs seek injunctive relief, asserting “the PLA Requirements that constitute . . .

unauthorized socioeconomic set-asides must be preliminarily and permanently enjoined as

arbitrary and capricious . . . .” See MVL MJAR at 32; ECC MJAR at 47; JCCBG2 MJAR at 40;

Harper MJAR at 38; see also HPCC GSA MJAR at 18–20; HPCC NAVFAC MJAR at 17–19;

HPCC USACE MJAR at 25–27. The government argues this request should be denied because

plaintiffs did not address their entitlement to an injunction and plaintiffs have not succeeded on

the merits. See Gov’t Cross-MJAR and Resp. at 78. Plaintiffs counter, arguing the government

is incorrect because: (1) the government emailed plaintiffs on 16 July 2024, stating the

“voluntary stay should obviate the need for proceedings regarding preliminary injunctive

relief[;]” (2) in each bid protest complaint, plaintiffs included a section titled “Basis for

Injunctive Relief” and requested an injunction; and (3) “it is not uncommon that a court will

enjoin the [g]overnment from awarding a contract based on a solicitation that has been

determined to violate procurement law . . . even where an injunction would prolong the

[g]overnment’s procurement efforts.” Pls.’ Reply at 30; see also HPCC GSA MJAR at 18–20;

HPCC NAVFAC MJAR at 17–19; HPCC USACE MJAR at 25–27.

IV. Legal Standards

A. Bid Protest Jurisdiction and APA Standard of Review

The Tucker Act, as amended by the Administrative Dispute Resolution Act (“ADRA”),

provides this court jurisdiction over “action[s] by an interested party objecting to a solicitation by

a federal agency for bids or proposals for a proposed contract or to a proposed award or the

award of a contract or any alleged violation of statute or regulation in connection with a

procurement or a proposed procurement.” Administrative Dispute Resolution Act, Pub. L. No.

104-320, 28 U.S.C. § 1491(b)(1) (1996). The term “interested party” means “actual or

prospective bidders or offerors whose direct economic interest would be affected by the award of

the contract or by failure to award the contract.” Am. Fed’n of Gov’t Emps. v. United States, 258

F.3d 1294, 1302 (Fed. Cir. 2001). “[T]o prevail in a protest the protester must show not only a

significant error in the procurement process, but also that the error prejudiced it.” Data Gen.

Corp. v. Johnson, 78 F.3d 1556, 1562 (Fed. Cir. 1996).

The Court evaluates bid protests under the framework laid out in Section 706 of the

Administrative Procedure Act. 28 U.S.C. § 1491(b)(4); see also Impresa Construzioni Geom.

Domenico Garufi v. United States, 238 F.3d 1324, 1332 (Fed. Cir. 2001); MATTHEW H.

- 22 -

SOLOMSON, COURT OF FEDERAL CLAIMS: JURISDICTION, PRACTICE, AND PROCEDURE § 8-37

(2016) (footnote omitted) (first citing 28 U.S.C. § 1491(b)(4); and then quoting 5 U.S.C.

§ 706(A), (D)); 28 U.S.C. § 1491(b)(4) (2024) (“In any action under this subsection, the courts

shall review the agency’s decision pursuant to the standards set forth in section 706 of title 5.”)).

“[T]he proper standard to be applied in bid protest cases is provided by 5 U.S.C. § 706(2)(A): a

reviewing court shall set aside the agency action if it is ‘arbitrary, capricious, an abuse of

discretion, or otherwise not in accordance with law.’” Banknote Corp. of Am., Inc. v. United

States, 365 F.3d 1345, 1350–51 (Fed. Cir. 2004) (quoting Adv. Data Concepts, Inc. v. United

States, 216 F.3d 1054, 1057–58 (Fed. Cir. 2000)). An agency’s action is arbitrary, capricious, or

an abuse of discretion if “the agency ‘entirely failed to consider an important aspect of the

problem, offered an explanation for its decision that runs counter to the evidence before the

agency, or . . . is so implausible that it could not be ascribed to a difference in view or the

product of agency expertise.’” Ala. Aircraft Indus., Inc.-Birmingham v. United States, 586 F.3d

1372, 1375 (Fed. Cir. 2009) (quoting Motor Vehicle Mfrs. Ass’n of U.S., Inc. v. State Farm Mut.

Auto. Ins. Co., 463 U.S. 29, 43 (1983)). Since the arbitrary and capricious standard is “highly

deferential,” a reviewing court must “sustain an agency action evincing rational reasoning and

consideration of relevant factors.” Adv. Data Concepts, 216 F.3d at 1058 (citing Bowman

Transp., Inc. v. Ark.-Best Freight Sys., Inc., 419 U.S. 281, 285 (1974)). A court, therefore, will

not “substitute its judgment” for the agency’s so long as the agency’s decision was reasonable.

Dell Fed. Sys., L.P. v. United States, 906 F.3d 982, 998–99 (Fed. Cir. 2018) (quoting R & W

Flammann GmbH v. United States, 339 F.3d 1320, 1322 (Fed. Cir. 2003)).

B. Judgment on the Administrative Record in a Bid Protest

“[RCFC] 52.1(c) provides for judgment on the administrative record.” Huntsville Times

Co. v. United States, 98 Fed. Cl. 100, 104 (2011); see also Bannum, 404 F.3d at 1353–54. The

court may set aside an agency action if plaintiff has proven “either: (1) the procurement

official’s decision lacked a rational basis; or (2) the procurement procedure involved a violation

of regulation or procedure.” Impresa, 238 F.3d at 1332. The rational basis test requires the court

to ask “whether the contracting agency provided a coherent and reasonable explanation of its

exercise of discretion.” Dell Fed. Sys., L.P., 906 F.3d at 992 (quoting Banknote, 365 F.3d at

1351). “When a challenge is brought on the second ground, the disappointed bidder must show

‘a clear and prejudicial violation of applicable statutes or regulations.’” Impresa, 238 F.3d at

1333 (quoting Kentron Haw., Ltd. v. Warner, 480 F.2d 1166, 1169 (D.C. Cir. 1973)). “[D]e

minimis errors do not require the overturning of an award.” Grumman Data Sys. Corp. v.

Dalton, 88 F.3d 990, 1000 (Fed. Cir. 1996). A bid protest plaintiff must establish alleged “errors

in the procurement process significantly prejudiced” plaintiff by showing “there was a

‘substantial chance’ it would have received the contract award but for the errors.” Bannum, 404

F.3d at 1353 (quoting Info. Tech. & Applications Corp. v. United States, 316 F.3d 1312, 1319

(Fed. Cir. 2003)).

C. Permanent Injunction

When deciding whether a permanent injunction is warranted, a court considers:

- 23 -

(1) whether, as it must, the plaintiff has succeeded on the merits of the case; (2)

whether the plaintiff will suffer irreparable harm if the court withholds injunctive

relief; (3) whether the balance of hardships to the respective parties favors the grant

of injunctive relief; and (4) whether it is in the public interest to grant injunctive

relief.

PGBA, LLC v. United States, 389 F.3d 1219, 1228–29 (Fed. Cir. 2004). If the Court awards

injunctive relief, it may fashion its own remedy to fit the contours of the decision. See Turner

Constr. Co. v. United States, 645 F.3d 1377, 1388 (Fed. Cir. 2011) (explaining “the Court of

Federal Claims has broad equitable powers to fashion an appropriate remedy”).

V. Executive Authority Under FPASA

As an initial matter, plaintiffs challenge the President’s authority to issue PLA policies

under the Federal Property and Administrative Services Act (“FPASA”). See Pls.’ Reply at 20;

see also Tr. at 120:6–19 (“THE COURT: So FPASA does not give the Executive Branch

authority to make directives related to project labor in this way? [PLAINTIFFS]: That is [our]

view. [We] don’t think Congress has ever spoken to this either . . . . [T]his has been a ping-pong

. . . between different administrations, and never has Congress weighed in at all.”). For the last

thirty years, presidential administrations since President George H.W. Bush have issued EO PLA

policies relying generally on FPASA as the source of their authority. See, e.g., EO No. 14063,

87 Fed. Reg. 7363 (Feb. 9, 2022) (President Biden’s EO); EO No. 13502, 74 Fed. Reg. 6985

(Feb. 11, 2009) (President Obama’s EO); See EO No. 13202, 66 Fed. Reg. 11225 (Feb. 17, 2001)

(President George W. Bush’s EO); EO No. 13208, 66 Fed. Reg. 18717 (Apr. 6, 2001) (President

George W. Bush’s EO); EO No. 12818, 57 Fed. Reg. 48713 (Oct. 28, 1992) (President George

H.W. Bush’s EO). Despite fluctuating PLA polices, every EO began with a common

introductory sentence: “By the authority vested in me as President by the Constitution and the

laws of the United States of America, including the Federal Property and Administrative

Services Act of 1949, 40 U.S.C. 471 et seq. . . . ” See id. According to plaintiffs, merely citing

FPASA is not sufficient legal authority to ground presidential policy without specific statutory

reference. See Tr. at 125:4–15 (“[PLAINTIFFS:] [A] regulation must reasonably be able to

conclude that the grant of authority contemplates the regulations issued.”).

In Georgia v. President of the United States, the Eleventh Circuit opined on the

President’s authority under FPASA, explaining “[t]he President must stay within the confines of

[FPASA] of course; but his actions must also be consistent with the policies and directives that

Congress included in the statute.” 46 F.4th 1283, 1294 (11th Cir. 2022) (emphasis added).

Applying this limitation to the CICA context, the Eleventh Circuit reasoned the “explicit

legislative polices” which cabin the President’s authority “include the rule that agencies must

‘obtain full and open competition’ through most procurement procedures.” Id. (quoting 41

U.S.C. §§ 3301(a), 3306). According to the Eleventh Circuit, the Supreme Court’s decision in

Chrysler Corp. v. Brown, 441 U.S. 281 (1976), suggests “the President’s authority should be

based on a ‘specific reference’ within [FPASA]” if the President is going to solely rely on

FPASA as his authority to implement policies. Id. (quoting Chrysler, 441 U.S. at 304 n. 34). In

Chrysler, the Supreme Court reviewed an EO prohibiting employment discrimination by federal

contractors based upon the Procurement Act. See Chrysler, 441 U.S. at 304–06. Though the

- 24 -

Supreme Court identified other potential statutory sources to support the President’s policy, the

Supreme Court observed in a footnote that while FPASA “explicitly authorizes Executive Orders

‘necessary to effectuate [its] provisions,’” FPASA makes no “specific reference to employment

discrimination.” See id. at 304 n. 34 (quoting 40 U.S.C. 486(a)). The Eleventh Circuit

interpreted the footnote as an indication the Supreme Court “doubted [] the Procurement Act on

its own delegated sufficient authority” to support the EO. Georgia, 46 F.4th at 1294.

The government disagrees with the Eleventh Circuit’s reading of Chrysler as a limitation

on the President’s authority under FPASA. See Tr. at 128:13–17 (“THE COURT: Do you agree

with the . . . 2022 Georgia decision? [GOVERNMENT]: No.”). The government agreed at oral

argument, however, the President would need to identify a specific statutory reference to support

the PLA mandate if the Court were to adopt the Eleventh Circuit’s reading of Chrysler. See id.

at 129:6–9 ([GOVERNMENT:] [I]f the Court were to agree with the analytical framework of

Georgia . . . even if we need a specific reference . . . we do still have [Section] 3306, which . . .

authorizes agencies to specify their needs . . . .”); see also 41 U.S.C. § 3306(2)(B) (“Each

solicitation under this division shall include specifications that . . . include restrictive provisions

or conditions only to the extent necessary to satisfy the needs of the executive agency or as

authorized by law.”). The government also acknowledged the FAR Council PLA mandate does

not address CICA. See infra Section V.B. Still, the government argued the President holds

broad authority to implement PLA policies as Congress has implicitly ratified its view of the

President’s authority under FPASA through decades of inaction. See Tr. at 131:4–14

(“[GOVERNMENT:] Congress hasn’t done anything about it.”). The government urged the

Court to find the reauthorization of FPASA in 2002 as determinative here. See Tr. at 131:4–14

(“[GOVERNMENT:] Congress reauthorized FPASA in 2002 and it didn’t reject the

interpretation that Presidents have had . . . multiple administrations at that point, when it

reauthorized it and when it . . . recodified the language.”).

Though the parties offer little by way of precedential authority on this issue, the Court

agrees with plaintiffs: the Eleventh Circuit’s reasoning in Georgia is helpful here. See Tr. at

125:4 –126:4 (arguing the applicability of Georgia); see also Georgia, 46 F.4th at 1294–95.

While the Court finds the Eleventh Circuit’s reading of Chrysler persuasive, the Supreme Court

and Federal Circuit have not addressed this issue, so the Court leaves to Congress the matter of

addressing the President’s authority under FPASA to issue expansive construction industry labor

policies. See 41 U.S.C. § 3306.

VI. Whether the FAR Council’s Regulations Violate CICA

When reviewing whether a regulation violates CICA’s full and open competition

requirement, the Court begins with the Federal Circuit’s guidance in National Government

Services, Inc. v. United States (“NGS”). 1 923 F.3d 977 (Fed. Cir. 2019). There, the Federal

1

While the parties do not agree on the extent of the applicability of National Government Services, Inc. v. United

States to the facts here, the Court finds the Federal Circuit’s analysis in NGS instructive. 923 F.3d 977 (Fed. Cir.

2019); see Tr. 97:15–21 (“[GOVERNMENT:] NGS . . . was really a very unique situation where you had . . . an

award limitations policy that was purely about the eligibility of the offeror to receive the contract. It didn’t

govern . . . contract performance in any way.”); Tr. at 143:17–144:3 (“[PLAINTIFFS:] [I]n [our] read of [NGS], the

[g]overnment’s order to use union instead of nonunion labor is an exclusion of the source. It’s specifically the

exclusion of nonunion labor, simply because the [g]overnment administration speculates that union labor is going to

- 25 -

Circuit reviewed a pre-award bid protest challenging contract award limitations imposed in

solicitations for proposals for the administration of Medicare claims and benefits as violative of

CICA’s full and open competition requirement. See id. at 981–82. As in NGS, the Court here

must first “address whether the [] solicitation provided for full and open competition in light of

[the PLA requirement] contained therein.” Id. at 982. If the Court concludes the solicitation

“did not provide for full and open competition,” the Court must then “address whether the

agency’s approach was otherwise permissible.” Id. When a case challenging a regulation’s

validity involves a federal contract, the Federal Circuit’s recent decision in Boeing Co. v. United

States instructs “the Court of Federal Claims has exclusive jurisdiction to review the validity of

the challenged regulation.” 2 119 F.4th 17, 24–25 (Fed. Cir. 2024) (“[W]hen the action is a

contract case—and more importantly, a contract case that is subject to the CDA—the Court of

Federal Claims has exclusive jurisdiction to review the validity of the challenged regulation.”).

Under CICA, Congress generally requires procuring agencies to “obtain full and open

competition through the use of competitive procedures.” 41 U.S.C. § 3301(a); see NGS, 923

F.3d at 982. In full, Section 3301 states:

(a) IN GENERAL. Except as provided in sections 3303, 3304(a), and 3305 of this

title and except in the case of procurement procedures otherwise expressly

authorized by statute, an executive agency in conducting a procurement for

property or services shall—

(1) obtain full and open competition through the use of competitive

procedures in accordance with the requirements of this division and the

[FAR]; and

(2) use the competitive procedure or combination of competitive procedures

that is best suited under the circumstances of the procurement.

41 U.S.C. § 3301(a) (emphasis added). CICA defines “competitive procedures” as “procedures

under which an executive agency enters into a contract pursuant to full and open competition.”

41 U.S.C. § 152. Regarding federal procurements regulated under CICA, “full and open

produce a preferred contract outcome. Much as the same as the capacity caps in NGS where assuming that a . . .

better outcome would be desired by limiting competition to those who were below a certain amount of government

contracts volume at the time of the procurement.”); Tr. at 144:4–8 (“[GOVERNMENT:] NGS dealt with not a

contract requirement, but simply an eligibility criterion for the . . . contract award. You know, it was completely a

pre-award thing to determine . . . .”).

2

Although the Federal Circuit has yet to weigh in on the applicability of Boeing to bid protests challenging the

validity of federal procurement regulations—like the seven consolidated bid protests here—plaintiffs read Boeing as

recognizing the Court’s exclusive jurisdiction to review the agencies’ inclusion of the PLA requirement in each

solicitation. See Tr. at 65:7–15 (“[PLAINTIFFS:] If the [g]overnment’s position were correct, then you would

never be able to file a bid protest challenging . . . a term of a solicitation if it was based on a regulation. If the

regulation is what is causing the impropriety in the solicitation, then you have to be able to challenge that.”). The

Court notes the Federal Circuit’s Boeing instruction may be read as acknowledging the Court of Federal Claims’

exclusive jurisdiction to review agency regulations impacting federal contract cases just as the Federal Circuit has

permitted within the tax context. See, e.g., Balestra v. United States, 803 F.3d 1363 (Fed. Cir. 2015) (reviewing a

Treasury Department tax regulation and conducting a full APA analysis).

- 26 -

competition . . . means that all responsible sources are permitted to submit sealed bids or

competitive proposals on the procurement.” 41 U.S.C. § 107.

President Biden’s EO instructed the “agencies shall require every contractor or

subcontractor engaged in construction on the project to agree, for that project, to negotiate or

become a party to a [PLA] with one or more appropriate labor organizations.” EO 14063, 87

Fed. Reg. 7363, 7364 (Feb. 9, 2022) (Section 3. PLA Presumption) (emphasis added). Effective

22 January 2024, the FAR Council implemented Biden’s EO, mandating: “When awarding a

contract in connection with a large-scale construction project . . . agencies shall require use of

[PLAs] for contractors and subcontractors engaged in construction on the project.” 48 C.F.R. §

22.503(b) (Dec. 22, 2023) (emphasis added). Quoting Biden’s EO verbatim, the FAR Council’s

PLA mandate enumerates narrow exceptions to the PLA requirement:

(i) Requiring a [PLA] on the project would not advance the Federal Government’s

interests in achieving economy and efficiency in Federal procurement. The

exception shall be based on one or more of the following factors:

(A) The project is of short duration and lacks operational complexity.

(B) The project will involve only one craft or trade.

(C) The project will involve specialized construction work that is available

from only a limited number of contractors or subcontractors.

(D) The agency’s need for the project is of such an unusual and compelling

urgency that a [PLA] would be impracticable.

Compare 48 C.F.R. § 22.504(d)(i), with EO 14063, 87 Fed. Reg. 7363 (Feb. 9, 2022). Also,

FAR 22.504 contemplates two additional exceptions—which do not directly quote Biden’s EO

but generally track its language—permitting an agency to forego a PLA when:

(ii) Market research indicates that requiring a [PLA] on the project would

substantially reduce the number of potential offerors to such a degree that adequate

competition at a fair and reasonable price could not be achieved . . . A likely

reduction in the number of potential offerors is not, by itself, sufficient to except a

contract from coverage under this authority unless it is coupled with the finding

that the reduction would not allow for adequate competition at a fair and reasonable

price.

(iii) Requiring a [PLA] on the project would otherwise be inconsistent with Federal

statutes, regulations, [EOs], or Presidential memoranda.

48 C.F.R. § 22.504(d)(1)(ii)–(iii).

- 27 -

Each of the solicitations at issue in this case incorporate the PLA mandate by referencing

the FAR provisions implementing Biden’s EO. 3 For example, in USACE’s solicitation for the

construction of a two-bay maintenance/fuel cell hangar at March Air Reserve Base in California,

the solicitation stated USACE would award the contract to “the responsible offeror whose

proposal conforms with all the terms and conditions of the solicitation . . . .” See Harper AR at

6040 (Harper Solicitation). Specifically, the solicitation mandated: “ALL OFFERORS ARE

REQUIRED TO SUBMIT AN EXECUTED PROJECT LABOR AGREEMENT. All

offerors shall submit a [PLA] in accordance with FAR Solicitation Provision 52.222-23 and FAR

Clause 52.222-34.” Harper AR at 6053 (Solicitation) (emphasis in original). As to MVL’s

protest related to the consolidated rigging facility at Joint Base Lewis McChord in Washington,

the USACE solicitation stated: “[i]n compliance with [EO] 14063, the [PLA] FAR Provision

52.222-33 and FAR Clause 52.222-34 are included in the solicitation.” MVL AR at 364 (MVL

Solicitation). With this background information in mind, the Court now turns to whether the

individual solicitations provide for full and open competition “in light of” the PLA requirements

mandated by the FAR Council and Biden’s EO. See NGS, 923 F.3d at 982.

Consistent with the Federal Circuit’s approach in NGS, the Court addresses whether the

solicitations here provided for full and open competition. See id. (“We first address whether the

[] solicitation provided for full and open competition in light of the [regulatory policy] contained

therein. . . . [If not,] we then address whether the agency’s approach was otherwise

permissible.”). First, the Court examines the unique operation of how Biden’s EO FAR

regulations function as compared to prior administrations’ PLA policies. See id. The Court then

examines whether the agencies’ decision to include the PLA requirement in the solicitation

despite previously deciding not to was arbitrary and capricious. See id. As exemplars, the Court

reviews the market survey responses and agency determinations related to USACE’s

consolidated rigging facility project in Washington and NAVFAC’s engineering test facility

project in Florida. Finally, the Court examines the applicability of CICA’s § 3301 express

statutory authorization exception to the PLA mandate. See id. For the following reasons, the

Court finds the FAR requirements in the solicitations violate CICA as applied to the contracts at

issue here. See id.

A. New Operation of the FAR Council’s Regulations as Compared to Prior PLA

Requirements

3

Under the final FAR regulation, the solicitation must include the “basic [PLA] provision” and two alternative PLA

provisions may be selected by the CO in certain circumstances. See FAR 52.222-33 (2024) (Notice of Requirement

for PLA). Specifically, the FAR permits the “basic provision” language to be substituted by the “Alternate I”

language as prescribed in FAR 22.505(a)(2), and “Alternate II” language can replace the “basic provision” under

FAR 22.505(a)(3). See id. At oral argument, plaintiffs’ counsel explained, “[t]he new FAR provisions repeat the

requirements of [] Biden[’s] [EO] and make it a requirement that the [g]overnment place a PLA . . . one of the two

PLA provisions from the FAR, into each solicitation for a large-scale construction contract that’s greater than $35

million.” Tr. at 104:4–9. The government described the application of this requirement at oral argument, explaining

the recommendation GSA received to shift from using “Alternate I” language to “Alternate II” language in the Land

Port of Entry project solicitation. See Tr. at 25:17–26:6 (“[GOVERNMENT:] [The market survey author] made a

recommendation that . . . if elimination [of the PLA] is not an option, [they] recommend[ed] shifting to the . . .

alternate 1 of FAR 52.222-33 to the alternate 2 of that regulation to allow the . . . awardee to enter into the PLA after

the contract is awarded.”).

- 28 -

While President Biden’s EO shares some formal similarities with prior PLA EOs, it is

substantively and operationally different. By way of example, under the Obama-era PLA policy,

the FAR regulations encouraged, but did not require, federal agencies to mandate PLAs on a

case-by-case basis for large-scale federal construction projects. See Tr. at 12:1–19 (“THE

COURT: [Obama’s EO] did direct the FAR Council to implement the provisions of the [EO]

which encouraged agencies to consider requiring the use of PLAs on large-scale construction

projects on a case-by-case basis . . . . [GOVERNMENT]: Yes . . . [the FAR Council] issued

regulations implementing the [EO] in at least FAR [s]ubpart 22.5, and I believe 52.22-34 and 24

as well.”). The Biden EO policy supplanted the Obama EO policy, raised the applicable contract

threshold for PLA requirements from $25 million to $35 million, and removed agency discretion.

See Tr. at 104:11–14 (“[PLAINTIFFS:] The old rule was discretionary, encouraging them to

consider it for -- at the time they considered large-scale construction projects to be those with an

estimated value of $25 million or greater.”).

In fundamental operation, the Biden EO flipped the status quo from giving agencies

broad discretion to apply PLAs on a case-by-case basis, to mandating PLAs as the new default

requirement subject to exceptions. See Tr. at 101:3–4 (“[GOVERNMENT:] [Biden’s EO] did

give more discretion to agencies than [Obama’s EO] did.”); Tr. at 103:21–104:1

(“[PLAINTIFFS:] [T]he mandatory nature of [Biden’s EO] and the implementing regulations

. . . is different from the discretionary nature of the prior FAR rules.”); Tr. at 176:24–177:9

(“THE COURT: But here it’s stated, oddly, the rule swallows the exception in large part,

whereas before, the rule was weaker? [GOVERNMENT]: I guess you could say the rule was

weaker before . . . . THE COURT: In short, there was more discretion before this FAR Council

rule? [GOVERNMENT]: Yes.”). Under the Obama and Trump Administrations, agencies

enjoyed discretion to “opt in” to using a PLA in a solicitation, whereas, under the Biden

Administration, the FAR regulations enumerate only narrow exceptions the agencies may apply

to “opt out” of the PLA requirement. See Tr. at 101:2–11 (“[GOVERNMENT:] [Under

Obama’s EO] it was still discretionary whether to include the PLA. . . . [Biden’s EO] said . . .

you have to include the PLA requirement unless one of these exceptions applies . . . .”). Even

then, to apply an exception to the current PLA regulations, the agency’s senior procurement

executive must provide a specific written explanation of why at least one of the enumerated

conditions exists for the particular contract. See EO 14063, 87 Fed. Reg. 7363, 7364 (Feb. 9,

2022) (Section 3. PLA Presumption) (“A senior official within an agency may grant an

exception . . . providing a specific written explanation of why at least one of the following

circumstances exists with respect to that contract . . . .”). In sum, the government said it best:

“the President made the policy determination that . . . generally, [PLAs] can help resolve some of

the issues that can occur with these large-scale construction contracts, so he set up a framework

so that you include the requirement for a PLA unless certain exceptions apply.” Tr. at 82:15–21.

Functionally, the FAR Council’s new PLA framework produces entirely different

outcomes than those achieved under the previous Obama Administration’s discretionary PLA

policy. To illustrate, before the PLA mandate, USACE conducted its initial market research in

2023 for the consolidated rigging facility at Joint Base Lewis McChord in Washington—the

contract specialist found “a PLA was not recommended because . . . ‘there was a shortage of

skilled labor in the region of the project,’ and a PLA would ‘not contribute to the economy or

efficiency of the project.’” See Tr. at 18:1–12 (quoting MVL AR at 113–14 (2023 USACE PLA

- 29 -

Determination Tool)). USACE determined not to include a PLA under the Obama-era FAR

regulations based on data and market analysis. See Tr. at 85:9–22 (“[GOVERNMENT]: When

it was determined under the . . . regulations implementing [Obama’s EO] . . . . [t]he agency used

data and market analysis . . . it did consider those things.”). Nothing in the administrative record

indicates whether USACE intended to include a PLA requirement in the solicitation before the

new FAR provisions. See Tr. at 18:13–17 (“[THE COURT:] Is there anything in the record

indicating whether [USACE] intended to include a PLA requirement in the solicitation prior to

the new FAR provisions? [GOVERNMENT]: Prior to the new FAR provisions, no.”).

Nevertheless, when USACE issued its solicitation in 2024, USACE included a PLA requirement

by incorporating FAR 52.222-33 and 52-222.34 in the solicitation. See MVL AR at 4069

(Amendment 4 to the Solicitation).

When pressed at oral argument about USACE’s decision to include a PLA requirement

after the market survey recommendation against it, the government agreed the agency based its

reversal on nothing more than the new PLA mandate alone. See Tr. at 19:2–14 (“[THE

COURT:] [M]y question is what’s different between 2023 and 2024 other than 12 months?

[GOVERNMENT]: Just in terms of the . . . timeline really . . . there w[ere] new regulations in

place implementing the new [EO] . . . it was appropriate to conduct additional market research to

determine whether any of the exceptions apply under FAR 22.504(d). THE COURT: So the

difference was the new regulations? [GOVERNMENT]: Yes.”). At oral argument, government

counsel was not aware of any market changes between 2023 and 2024 to warrant the agency’s

reversal. See Tr. at 21:11–13 (“[THE COURT:] Did anything change in the market conditions

during the course of the time in 2024? [GOVERNMENT]: Not that I’m aware of.”). The

government clarified, the new PLA mandate was the only reason the solicitation included the

PLA requirement. See Tr. at 21:14–13 (“THE COURT: So the only . . . reason the PLA

requirement was placed was because of the regulation? [GOVERNMENT]: Right, because

there was a new regulation and that the agency rationally determined that those exceptions were

not met.”). The government explained, “[t]here was a determination made [a PLA] would not

contribute to economy or efficiency for the project under consideration, under the factors

considered in [Obama’s EO], or the regulations implementing [Obama’s EO].” See Tr. at 43:6–

16.

According to the government, USACE’s only justification for its reversal on the inclusion

of the PLA “is the policy determination that’s been made by the President and the FAR.” See Tr.

at 81:8–12 (“[THE COURT:] [W]hat does the PLA do for this particular project? . . .

[GOVERNMENT:] [T]his is the policy determination that’s been made by the President and the

FAR.”). Without additional support undergirding USACE’s decision, the government speculated

a PLA could require terms to prevent lockouts and strikes and would provide a mechanism for

dispute resolution. See generally Tr. at 81:19–82:12. The government, however, was not aware

of any issues related to strikes or lockouts in Washington that may apply to this solicitation. See

Tr. at 82:12–21 (“THE COURT: Is there anything in the record that notes there’s a specific

problem with respect to strikes and lockouts in Washington State, in that area?

[GOVERNMENT]: I don’t know that there is, but the President made a policy determination . . .

that generally, [PLAs] can help resolve some of the issues that can occur with these large-scale

construction contracts, so he set up a framework so that you include the requirement for a PLA

unless certain exceptions apply.”). Aside from the President’s “policy determination,” the

- 30 -

government could not point to any record evidence supporting the PLA’s inclusion. See Tr. at

82:12–83:16. The Court therefore finds USACE’s decision to disregard the market survey

results indicating a PLA would be anticompetitive and to include a PLA requirement against the

recommendations of the agency’s hired outside industry specialist “runs counter to the evidence

before the agency,” makes a PLA effectively mandatory, and is arbitrary and capricious. See

Ala. Aircraft Indus., Inc.-Birmingham v. United States, 586 F.3d 1372, 1375 (Fed. Cir. 2009)

(“Courts have found an agency’s decision to be arbitrary and capricious when the agency

‘entirely failed to consider an important aspect of the problem, offered an explanation for its

decision that runs counter to the evidence before the agency, or [the decision] is so implausible

that it could not be ascribed to a difference in view or the product of agency expertise.’” (quoting

Motor Vehicle Mfrs. Ass’n of U.S., Inc. v. State Farm Mut. Auto. Ins. Co. (“MVM”), 463 U.S. 29,

43 (1983))).

In another illustration of the functional effect of the FAR Council’s PLA mandate,

USACE’s 4 March 2024 Acquisition Plan Addendum (“Addendum”) related to the consolidated

communications center at Patrick Space Force Base in Florida outlined the agency’s intention to

“DELETE” and “INSERT” language in the Acquisition Plan. See HPCC USACE AR at 283–84

(2024 Acquisition Plan Addendum). At oral argument, the government explained the Addendum

made several amendments to the prior Acquisition Plan’s language following the PLA mandate.

See Tr. at 45:16–46:5. USACE issued the Addendum after determining the market analysis

conducted under the previous EO was effectively obsolete under the new FAR PLA mandate.

See Tr. at 85:18–86:5. Though USACE concluded a PLA would neither contribute to economy

nor efficiency, USACE amended the Acquisition Plan to include a PLA simply because of the

PLA mandate. See Tr. at 86:14–87:7 (“[THE COURT:] [USACE] concluded on its own, based

under the processes of [Obama’s EO], the PLA would not contribute to the economy or

efficiency, then it was not new data or new market research, it was only a new regulation that

came to a different conclusion? [GOVERNMENT]: That provided for a different analysis,

correct. Yes.”). At oral argument, the government clarified USACE then undertook new market

analysis to support the new regulation. See Tr. at 87:4–7 (“[GOVERNMENT:] The change was

that there was a different analysis to be done of that data under the new . . . regulation that the

FAR [rules] . . . implementing [Biden’s EO].”).

In the “Acquisition Considerations” portion of the Space Force Base Addendum, USACE

determined to “DELETE” three paragraphs from the project labor market survey summarizing

USACE’s prior findings a PLA would be anticompetitive and ought to be included. See HPCC

USACE AR at 283 (2024 Acquisition Plan Addendum). The Addendum then directed to

“INSERT” two new paragraphs related to Biden’s EO and industry concerns. See HPCC

USACE AR at 284 (2024 Acquisition Plan Addendum). Specifically, the previous “DELETE”

market research found “a PLA mandate on the project would reduce competition, increase costs,

and create inefficiencies for contractors and procurement officials.” See HPCC USACE AR at

283 (2024 Acquisition Plan Addendum). The new “INSERT” analysis, by contrast, determined

USACE was “unable to determine if waiving the PLA w[ould] reduce the number of potential

offerors to such a degree that adequate competition at a fair and reasonable price could not be

achieved as outlined in FAR 22.504(d)(1)(ii).” See HPCC USACE AR at 284 (2024 Acquisition

Plan Addendum). USACE determined to include a PLA even though “[t]he majority of

respondents indicated that a PLA mandate would reduce competition, increase costs, and create

- 31 -

inefficiencies for contractors and procurement officials.” See HPCC USACE AR at 284 (2024

Acquisition Plan Addendum) (emphasis added). At oral argument, the government attempted to

justify this confounding decision by arguing the prior market survey results would be irrelevant

as to the new PLA requirements and exceptions, and should be deleted. See Tr. at 47:2–17

(“[GOVERNMENT]: [T]hat particular statement isn’t particularly relevant to the exceptions

under . . . the current version of FAR 22.504(d). THE COURT: Not relevant to the new FAR

Council rule? [GOVERNMENT]: Exactly, yes.”). When asked whether USACE has reliable

evidence suggesting PLAs promote on-time completion of federal construction projects, the

government could only point to “[t]he policy judgment as to whether PLAs are generally

good . . . made by the President and then implemented by the FAR Council.” See Tr. at 50:2–

51:13. In support of this conclusion, the government cited generally to Biden’s EO and FAR

Council’s regulations as evidence “PLAs are helpful.” See Tr. at 50:17–19. The Court finds

USACE’s decision to require a PLA, relying solely on the President’s “policy judgment” as

implemented by the FAR Council, rather than actual market survey data supporting USACE’s

prior determination to not include a PLA is arbitrary and capricious. See Ala. Aircraft, 586 F.3d

at 1375 (“Courts have found an agency’s decision to be arbitrary and capricious when the agency

. . . ‘offered an explanation for its decision that runs counter to the evidence before the

agency . . . .’”) (quoting MVM, 463 U.S. at 43).

The Land Port of Entry project solicitation’s history offers yet another example of the

functional effect of the FAR Council’s PLA mandate. After the PLA mandate was in place,

GSA hired an outside specialist to conduct a market survey related to PLAs. See Tr. at 24:8–

25:11 (“THE COURT: So [GSA] pay[s] an outside expert to analyze the marketplace of

potential contractors? [GOVERNMENT]: I don’t know if they’re an expert or not, but at least

an outside firm that would . . . . do this survey for them. THE COURT: So GSA paid money for

the survey? [GOVERNMENT]: That’s my understanding.”). As the government explained at

oral argument, “[t]he general conclusion” of the post-PLA mandate market survey was

“removing the PLA requirement would result in more contractor interest, and thus, [a] more

competitive bid environment.” See Tr. at 52:3–8. If the PLA requirement could not be removed,

then the specialist recommended the use of “Alternate II” in the solicitation. See Tr. at 52:8–13

(“[GOVERNMENT:] [B]ut alternatively, switching to . . . alternate version 2 of [52.222-]33

would be good . . . .”). “Alternate II” required offerors to submit only a draft PLA at the time of

proposal and then later finalize the PLA post-award. See Tr. 26:2–6 (“[GOVERNMENT:] And

so that’s reflected in the solicitation that in stage 2 of that procurement, the offerors are required

to submit a draft PLA only . . . . [T]he actual PLA comes after award.”). The government

acknowledged, however, the market research primarily recommended “there would be a more

competitive bid environment if there was no PLA requirement in this particular procurement.”

See Tr. at 26:16–24 (emphasis added). Specifically, “the study’s author made the following

recommendation: Selecting a design build firm with experience working with a PLA or union

environment will be of benefit to the project; however many large [design build] firm[s]

interviewed have stated little to no interest in the project if PLAs are a requirement. Removing

the PLA requirement would result in more contractor interest, and . . . a more competitive bid

environment.” Tr. at 40:5–22 (emphasis added). “GSA concluded the PLA requirement was

likely to affect both competition and price, but found no basis for an exception to the PLA

requirement in [Biden’s EO].” Tr. at 40:14–22 (emphasis added). After conducting “its

independent government estimate,” GSA “increased the price” of the contract “based on the PLA

- 32 -

requirement being included” but determined including a PLA would not “reduce the number of

potential offerors to such a degree that adequate competition and a fair and reasonable price

could not be achieved . . . under [Biden’s EO] exception.” See Tr. at 41:1–15. At oral argument,

when the government could not point to evidentiary support of an agency’s decision to proceed

with a PLA despite the recommendations a PLA would increase costs and decrease interest, the

government generally concluded the “determination of economy and efficiency was made . . . by

the President and the FAR Council.” Tr. at 99:11–18. While the government recognized

“agencies determine their own needs,” see Tr. at 87:8–11, and the agencies enjoyed more

discretion under prior administrations’ PLA policies, see infra Section V.B., the government

remarked “agencies are subject to the President. The President is the head of the Executive

agency,” see Tr. at 87:11–16. The Court finds GSA’s decision to proceed with the Alternative II

PLA requirement as a mandate based solely on the President’s policy—wholly disregarding the

post-PLA market survey recommendation to remove the PLA entirely because a PLA would

increase price and reduce competition—is arbitrary and capricious as it runs counter to any

evidence presented to the agency. See Ala. Aircraft, 586 F.3d at 1375 (“[A]n agency’s decision

[is] arbitrary and capricious when the agency . . . ‘offered an explanation for its decision that

runs counter to the evidence before the agency . . . .’”) (quoting MVM, 463 U.S. 43).

B. Whether the FAR’s New PLA Mandate Violates CICA’s Full and Open

Competition Requirement

Consistent with the Federal Circuit’s approach in NGS, the Court now addresses whether

the solicitations here provided for “full and open competition” generally in accordance with

CICA. See NGS, 923 F.3d at 982 (“We first address whether the [solicitation] provided for full

and open competition in light of the [regulatory policy] contained therein. . . . [If not,] we then

address whether the agency’s approach was otherwise permissible.”). As an initial matter,

plaintiffs agreed at oral argument if the Court were to find the solicitations’ PLA mandates

violate CICA’s full and open competition requirement, the Court need not address plaintiffs’

alternative theories. See Tr. at 115:24–116:8 (“[PLAINTIFFS]: [We] believe that if the Court

rules that CICA has been violated and, therefore, the solicitations are invalid, then I don’t think

you would have to address any of the other arguments . . . . If it violates CICA, for whatever

reason, and there is not an enumerated exception that it falls under, then I don’t believe you have

to go any further.”). As helpful background, the Court notes the FAR Council’s final rules

implementing Biden’s EO PLA mandate did not address CICA or how the new regulations relate

to CICA. See generally FAR pts. 1, 7, 22, 36, 52. The FAR Council did address, however,

“numerous” public comments expressing concerns the regulations violate CICA’s full and open

competition requirement. 4 See Tr. at 133:2–19 (“THE COURT: So just to confirm, it’s not in

the FAR Council regulations? [GOVERNMENT:] It’s not in the regulation itself, it’s in the

promulgation of the final rule. [THE COURT]: Just comments? [GOVERNMENT]: Yes.”).

Given the PLA mandate itself does not address CICA, and the FAR Council has only weighed in

4

In response to the FAR Council’s notice and comment period before promulgating the PLA mandate, “[n]umerous

respondents asserted that the rule violates the requirement for full and open competition in CICA because PLAs

discriminate and injure competition among potential bidders who are not signatories to CBAs.” See Tr. at 132:20–

24.

- 33 -

on the issue insofar as quoting CICA’s definition of “full and open competition,” 5 the Court

begins with the Federal Circuit’s CICA-analysis steps in NGS. 923 F.3d at 982.

In NGS, the Federal Circuit considered whether a pre-award protest challenge to an

agency’s inclusion of “workload caps” violated CICA’s “full and open competition” requirement

because the policy “preclude[d] a successful best value offeror from receiving [an] award where

the contract award would cause that offeror to exceed the . . . workload caps.” Id. at 981. The

Federal Circuit reasoned, “a responsible offeror that would exceed the workload caps is not

given the same opportunity to win an award as other offerors that submitted awardable

proposals.” Id. at 985. The government argued an offeror’s “submission may not always be

meaningless because offerors that would exceed the workload caps at the time of submission

[could] nonetheless win an award in two scenarios.” Id. at 984. The Federal Circuit concluded

neither scenario “demonstrate[d] that it would not be futile for an offeror that would exceed the

workload caps to submit a proposal.” See id. Given “a responsible offeror that would exceed the

workload caps is not given the same opportunity to win an award as other offerors that submitted

awardable proposals,” the mere “fact that an offeror that would exceed those caps was able to

submit a proposal [did] nothing to address [the Federal Circuit’s] concern.” Id. at 985 (emphasis

in original). The Federal Circuit ultimately held the workload caps imposed by the agency

violated CICA’s full open and competition requirement. See NGS, 923 F.3d at 978.

The government argues under NGS, “[w]here a solicitation permits all prospective

contractors to submit bids or proposals, the solicitation’s capability and experience requirements

do not cause the solicitation to provide for less than full and open competition simply because

those requirements render some prospective contractors ineligible for award.” Gov’t

Cross-MJAR at 33 (citing NGS, 923 F.3d at 985). According to the government, “the

solicitations at issue in these consolidated cases permit all responsible sources to compete for the

contracts.” Id. at 34 (emphasis added). The government emphasizes, “[t]o the extent that

plaintiffs are unable to meet the PLA requirements, that does not mean that the solicitations

provide for less than full and open competition; rather, it means that the plaintiffs are not

‘responsible sources’ for the procurements.” Id. at 35 (quoting 41 U.S.C. § 107). The argument

continues, “[i]f a prospective contractor cannot enter into a PLA to perform the contracts at

issue, then it lacks the ability to ‘perform all contract requirements.’” Id. (quoting FAR 9.104-1

(2024)). Distilling this case to mere choice, the government argues plaintiffs’ “unwillingness”

“to compete for the contracts on the terms set forth by the [g]overnment . . . does not change the

fact that ‘all responsible sources are permitted to submit sealed bids or competitive proposals on

the procurement.’” Id. (quoting 41 U.S.C. § 107). According to the government, NGS cannot be

instructive here because the PLA requirements are essentially contract requirements that

5

In response to market respondents’ concerns about the new regulations violating CICA, the FAR Council

comments quoted CICA’s definition of full and open competition and concluded neither the regulations nor the EO

bar responsible sources from submitting sealed bids or competitive proposals. See Tr. at 133:20–134:10 (“THE

COURT: What does it say? Go ahead and read it? [GOVERNMENT]: ‘The EO and final rule do not violate

CICA, which generally requires full and open competition through competitive procedures that are best suited under

the circumstances of the procurement. CICA defines full and open competition as meaning ‘that all responsible

sources are permitted to submit sealed bids or competitive proposals on the procurement.’ See 41 U.S.C. 107.

Neither the EO nor final rule bar any responsible sources from submitting sealed bids or competitive proposals, nor

do they provide a preference for contractors already a party to a CBA. Section 4 of the EO requires a PLA to allow

all contractors and subcontractors to compete without regard to whether they are otherwise party CBAs.”).

- 34 -

“govern[] how the contract will be performed.” Id. at 36 (emphasis added). Yet the record

indicates a PLA requirement has no bearing on whether plaintiffs can perform the contract at

issue. See Tr. at 87:25–88:8 (“[THE COURT:] [I]s there anything in the record indicating that

[p]laintiffs were unable to comply with the required or proposed performance schedule or any

technical skills and ability to obtain them? [PLAINTIFFS]: No, Your Honor. THE COURT:

So why the change, then? [PLAINTIFFS]: I mean, the [g]overnment says the change was solely

on the basis of the regulation being issued and not on any performance requirements.”). Indeed,

at oral argument, plaintiffs confirmed the actual building specifications did not change—the only

change was the inclusion of the mandatory FAR PLA language. See Tr. at 88:15–18

(“[PLAINTIFFS:] [We] think it’s important to note that not a single word in the building

specifications for how that building gets built changes at all whether there’s a PLA requirement

or not a PLA requirement.”); Tr. at 93:2–94:20 (“[GOVERNMENT:] [T]he PLA requirement

doesn’t require that . . . employees be members of the union.”); Tr. 139:25–140:11

(“[GOVERNMENT:] GSA did determine that it was likely . . . [a PLA requirement] would

reduce competition and increase cost[s].”).

The record evidence for these solicitations clarify agencies will exclude an otherwise

responsible offeror under the PLA mandate regardless of that offeror’s capability to perform the

contract. See, e.g., Tr. at 74:18–75:17(“[GOVERNMENT:] [W]e’re not even saying MVL is

not capable of entering into the contract with a PLA. To the extent that they’re not, they would

not be . . . a responsible source for the procurement at issue because the procurement at issue

requires a -- to be performed with a [PLA] . . . . To the extent that . . . the offeror would have

otherwise been responsible to perform . . . this contract . . . that doesn’t mean that full and open

competition is violated. That doesn’t mean that there’s a violation of CICA.”); see also supra

Section V.A. NGS instructs the mere ability to submit an offer is not sufficient to demonstrate a

regulation does not violate full and open competition when the record shows a non-PLA

offeror’s proposal submission would be meaningless. See NGS, 923 F.3d at 985 (explaining

when an anticompetitive regulation excludes otherwise responsible offerors for non-compliance

with the regulation, merely permitting an offeror to “submit a proposal does nothing to address

t[he] concern”).

The government further argues, “because the PLA requirements did not cause the

solicitations to provide for less than full and open competition, there was no need for the

agencies to invoke an exception . . . and comply with any procedural requirements for such an

exception.” See Gov’t Cross-MJAR at 37. Yet when the agencies ignore the PLA exceptions,

the agencies make those exceptions effectively meaningless. See Tr. at 105:8–106:4 (“THE

COURT: So if we look at the exception that [the government] pointed to, 504(d)(ii), ‘Market

research indicates that requiring a [PLA] on the project would substantially reduce the number of

offerors to such a degree that adequate competition at a fair and reasonable price could not be

achieved.’ . . . . Is that exception just meaningless? . . . [PLAINTIFFS]: The way it’s being

implemented by the agency makes it meaningless, because they’re ignoring the exceptions . . . .

[I]t’s a discretionary evaluation as to what would . . . reduce adequate competition at a fair and

reasonable price.”); see also supra Section VI.A. By way of example in supra Section VI.A,

even when the market research indicated “a significant reduction” in the number of offerors if

the PLA requirement remained—the agency included the PLA requirement and only received

two offerors. See Tr. at 106:4–23 (emphasis added). Plaintiffs argue the “likely reduction in the

- 35 -

number of potential offerors” contained in the FAR 22.504 exception is not only made

meaningless by agency inaction, but the exception itself violates CICA by permitting the

reduction of competition amongst an entire class without statutory support. See Tr. at 107:6–11

(“[PLAINTIFFS]: We believe that it’s a violation of competition because there’s no statute that

specifically says that you can reduce competition to create a class of offerors that is limited to

[PLA-contractors].”); see also FAR 22.504(d)(1)(ii) (2024).

When compared to the prior administration’s discretionary policy, the PLA mandate’s

exceptions—though theoretically discretionary—are rendered functionally meaningless if the

agencies take the uniform approach of never seeking an exception regardless of the strength of

the market survey data recommending against the inclusion of a PLA. See supra Section VI.A.

Indeed, agencies now look only to “studies supporting the use of PLAs” cited by Biden’s EO and

the FAR Council, rather than tailoring their decisions to the market data evidence for each

specific project specification. See, e.g., Tr. at 48:4–16 (“[THE COURT:] So the conclusion . . .

is ‘there is no reliable evidence suggesting PLAs promote on-time completion of federal

construction projects and significant reliable evidence to the contrary.’ Would you agree with

that, based on . . . the [administrative record] that the [g]overnment itself had conducted . . . ?

[GOVERNMENT]: No, Your Honor, because the FAR Council looked at this question and

determined that there w[ere] . . . studies supporting the use of [PLAs] on large-scale construction

contracts.”); see also Tr. at 91:25–92:10 (“[THE COURT:] [I]n your briefing, where is the

discussion of a PLA mandate being tailored to the needs of an agency or the needs of a

procurement? [GOVERNMENT]: Well . . . it’s tailored in the sense that there’s exceptions, and

so agencies can look at those exceptions and determine not to apply it.” (emphasis added)).

Even when presented with data supporting an exception by third-party market researchers

the agencies themselves commissioned, the agencies declined to pursue an exception. See, e.g.,

Tr. at 24:18–25:21 (“[GOVERNMENT:] GSA went and . . . basically contracted with someone

to . . . take a look at the market, they interviewed various . . . construction firms . . . [to] help

determine how to proceed with the procurement . . . . THE COURT: So GSA paid money for

the survey? [GOVERNMENT:] That’s my understanding. THE COURT: And what did the

outside specialists conclude related to PLAs? . . . . [GOVERNMENT:] [T]hey made a

recommendation that . . . removing the PLA requirement would result in more contractor

interest and thus a more competitive bid environment.” (emphasis added)); see also supra

Section VI.A. The functional application of FAR 22.504 requires a PLA regardless of market

data, declines to seek an exception regardless of market data, and generally justifies those

decisions by citing the President and the FAR Council’s policy judgment. See Tr. at 49:1–15

(“[THE COURT:] [W]e’ve looked at third-party reports that the [g]overnment has paid for and

we have looked at [USACE] and GSA conclusions regarding projects. Now this is an offeror

who’s submitting their own review of a PLA requirement. It seems like everything that we’ve

seen supports what they’re saying here. You’re disagreeing with that? [GOVERNMENT]:

Right. Yeah, we are disagreeing . . . the President made a different judgment and so did the FAR

Council.”); see also Tr. at 50:9–16 (“[GOVERNMENT:] [T]hat policy judgment was made by

the President and the FAR Council already . . . .”).

“[D]espite the government’s efforts to show that it would be meaningful for [a non-PLA]

offeror . . . to submit a proposal,” the Court is not persuaded. See NGS, 923 F.3d at 985. Under

- 36 -

the PLA mandate, the Court finds “a responsible offeror that [declines to enter a PLA] is not

given the same opportunity to win an award as other offerors that submitted awardable

proposals.” See id. As discussed supra, the record teems with examples of how the Biden EO

PLA mandate excludes non-PLA offerors on that basis alone: (1) the terms of the contract do

not change if a PLA is included or excluded; (2) the government recognizes plaintiffs are likely

otherwise capable of performing the contracts; (3) the agencies can point only to the PLA

mandate to justify including PLAs in the solicitations; (4) the agencies declined to seek an

exception even after the agencies commissioned market research recommending against the use

of PLAs; and (5) even when the agencies received overwhelming data indicating PLAs would

increase price, reduce economy and efficiency, and stifle competition—the agencies declined to

pursue an exception. See supra Section VI.A; see also supra Section I.D–J. In sum, the PLA

mandate “precludes full and open competition by effectively excluding [a non-PLA] offeror from

winning an award”—both in the function of the mandatory rule itself and in the apparent policy

to deny exceptions even when the agency itself commissions data indicating an exception should

be made. See NGS, 923 F.3d at 990. Accordingly, the Court finds the PLA mandates have no

substantive performance relation to the substance of the solicitations at issue and violate CICA’s

requirement that procuring agencies “obtain full and open competition through the use of

competitive procures.” 41 U.S.C. § 3301(a) (emphasis added); see also NGS, 923 F.3d at 982.

C. Whether Exceptions to CICA’s Full and Open Competition Requirement

Apply to the PLA Mandate

The Court now turns to whether an exception to CICA’s full and open competition

requirement may apply to the anticompetitive PLA mandate. Absent the limited statutory

exceptions enumerated by Congress in CICA, see generally 41 U.S.C. §§ 3303, 3304(a), 3305,

“Congress specifically outlined the circumstances under which an agency may avoid CICA’s full

and open competition requirement,” NGS, 923 F.3d at 986 (citing 41 U.S.C. § 3301(a)). One

such possible exception to CICA’s full and open competition requirement occurs in the case of

“procurement procedures otherwise expressly authorized by statute.” See id. (quoting 41 U.S.C.

§ 3301(a)). If an agency seeks to violate CICA’s full and open competition requirement, the

government must demonstrate express statutory authority to do so. See 41 U.S.C. § 3301(a)

([E]xcept in the case of procurement procedures otherwise expressly authorized by statute, an

executive agency in conducting a procurement . . . shall obtain full and open competition through

the use of competitive procedures in accordance with the requirements of this division and

[FAR] . . . .” (emphasis added). Instructively, the Federal Circuit noted that “broad provisions”

of statutory text “cannot serve as the express authority necessary to meet [Ssection 3301]

exception,” otherwise “seemingly any requirement could be justified regardless of its effect on

full and open competition.” NGS, 923 F.3d at 988.

The government conceded at oral argument if the Court were to find the PLA

requirements violate CICA, the government has not invoked Section 3301 or any other statutory

exceptions. See Tr. at 113:11–23 (“[GOVERNMENT:] [I]f the Court were to find the

solicitations didn’t provide . . . for full and open competition, the agencies haven’t invoked a

statutory exception to full and open competition from that. I mean, I wouldn’t necessarily say

that [Section] 3301 doesn’t apply . . . our position is that it’s providing . . . for full and open

competition. If it’s not full and open competition, then we haven’t invoked those statutory

- 37 -

exceptions.”). The government further acknowledged if it were required to identify a specific

statutory reference to support its PLA mandate, it would rely on Section 3306, which “authorizes

agencies to specify their needs.” Tr. at 129:6–9 (“[GOVERNMENT:] [I]f the Court were to

agree with the analytical framework of Georgia . . . even if we need a specific reference . . . we

do still have 3306, which . . . authorizes agencies to specify their needs . . . .”); see also 41

U.S.C. § 3306(2)(B) (“Each solicitation under this division shall include specifications that . . .

include restrictive provisions or conditions only to the extent necessary to satisfy the needs of the

executive agency or as authorized by law.”). When pressed, however, the government argued

the President—not the agencies—ultimately determines the agencies’ needs under the PLA

mandate. See Tr. at 129:3–20 (“[GOVERNMENT:] I mean, we do still have [Section] 3306,

which . . . authorizes agencies to specify their needs . . . . So, I mean, there is a specific reference

to contract specifications in FPASA. You know, there is not a specific reference to PLAs, I

suppose, but still, FPASA clearly talks about . . . the ability to set specifications of contracts.

And again, . . . it’s the President’s . . . duty and authority to supervise his subordinates.”). By

arguing the FAR provisions are “authorized by law” because the FAR provisions are “properly

promulgated, substantive agency regulations,” Gov’t Cross-MJAR at 44, the government, in

effect, is asking the Court to take a red pen to § 3301 and add a caret to read as “expressly

authorized by statute or Federal Acquisition Regulation.” The Court, however, is tasked with

interpreting statutes, not rewriting them. See Versata Dev. Grp., Inc. v. SAP Am., Inc., 793 F.3d

1306, 1340 (Fed. Cir. 2015) (“But our task is to apply the language of the statute, not to rewrite

it.”); Laguna Hermosa Corp. v. United States, 671 F.3d 1284, 1290 (Fed. Cir. 2012) (“Our task

is to interpret the statute as written, as we have, not to rewrite it.”). Without invoking any other

statutory authority, the government’s argument the PLA mandate is “authorized by law” falls

short of the express statutory authorization mandated by Congress in § 3301(a) of CICA. See

NGS, 923 F.3d at 988 (“[T]he broad provisions cited by the government cannot serve as the

express authority necessary to meet [Section 3301] exception. If these provisions could suffice

to show such express authorization, seemingly any requirement could be justified regardless of

its effect on full and open competition.”).

VII. The Timeliness of JCCBG2’s Challenge Under Blue & Gold

The government separately argues JCCBG2 cannot demonstrate success on the merits

“because JCCBG2 forfeited its challenge by failing to protest before the deadline for submission

of proposals.” See Gov’t’s Reply at 2; Gov’t Cross-MJAR at 31–32. Although “JCCBG2

submitted a timely proposal” before the 21 May 2024 deadline, the government argues JCCBG2

“did not formally protest the solicitation’s inclusion of [the] PLA requirements until August

2024.” See Gov’t Cross-MJAR at 31–32. JCCBG2 counters, arguing the relevant inquiry under

Blue & Gold is whether JCCBG2 objected to the terms of the solicitation “prior to the close of

the bidding process.” See JCCBG2’s Resp. to Gov’t Cross-MJAR at 1, ECF No. 78 (quoting

Blue & Gold Fleet, LP v. United States, 492 F.3d 1308, 1313 (Fed. Cir. 2004)) (emphasis added).

Under the Federal Circuit’s Blue & Gold precedent, “a party who has the opportunity to

object to the terms of a government solicitation containing a patent error and fails to do so prior

to the close of the bidding process waives its ability to raise the same objection subsequently in a

bid protest action in the Court of Federal Claims.” See id. at 1313 (emphasis added). The

Federal Circuit applied the doctrine of patent ambiguity—“an exception to the general rule of

- 38 -

contra proferentem”—used by courts “to construe ambiguities against the drafter.” See id.

(quoting E.L. Hamm & Assocs., v. England, 379 F.3d 1334, 1342 (Fed. Cir. 2004)). The Federal

Circuit explained “a government contractor has a duty to seek clarification from the government,

and its failure to do so precludes acceptance of its interpretation in a subsequent action against

the government.” See id. (quoting Stratos Mobile Networks USA, LLC v. United States, 213 F.3d

1375, 1381 (Fed. Cir. 2000)) The Federal Circuit’s analysis instructed the doctrine of patent

ambiguity was established to: (1) “prevent contractors from taking advantage of the

government;” (2) “protect other bidders by assuring that all bidders bid on the same

specifications;” and (3) “materially aid the administration of government contracts by requiring

that ambiguities be raised before the contract is bid, thus avoiding costly litigation after the fact.”

See id. at 1313–14 (quoting Cmty. Heating & Plumbing Co. v. Kelso, 987 F.2d 1575, 1580 (Fed.

Cir. 1993)).

Quoting the language of Blue & Gold, the government argues JCCB2 should have filed

its protest “prior to the close of bidding” to be timely. See Gov’t Cross-MJAR at 31 (quoting

Blue & Gold, 494 F.3d at 1313). The government argues “this Court has held that protest

grounds challenging solicitation terms were waived in pre-award protests because the plaintiffs

raised those protests grounds after the deadline for the submission of proposals.” See Gov’t

Reply at 2 (citing Oracle America, Inc. v. United States, 144 Fed. Cl. 88, 117 (2019), aff’d, 975

F.3d 1279 (Fed. Cir. 2020); Northeast Constr., Inc. v. United States, 119 Fed. Cl. 596, 608–12

(2015); Alamo Travel Grp., LP v. United States, 108 Fed. Cl. 224, 230–32 (2012). The

government also argues Federal Circuit precedent “demonstrates that ‘close of the bidding

process’ means the deadline for the submission of bids, proposals, or quotes, not the award of a

contract.” See id. at 2–3 (citing COMINT Sys. Corp. v. United States, 700 F.3d 1377 (Fed. Cir.

2012). The government notes “JCCBG2 cites to no decisions where a court has denied a Blue &

Gold forfeiture objection on the basis that the plaintiff’s protest of the original solicitation terms

was submitted after the proposal submission deadline, but before award.” See id. at 4. Thus,

according to the government, “JCCBG2 has forfeited its challenge to the solicitation’s PLA

requirements.” See id. at 5.

The Court, however, finds the language of the Blue & Gold decision most instructive

here. At oral argument, the parties agreed the operative language of Blue & Gold is “close of the

bidding process.” See Tr. at 163:10–17 (“[THE COURT:] Your conclusion is that the language

that’s operative of Blue & Gold is ‘close of the bidding process,’ and ‘close of the bidding

process’ [occurs] when the award is made? [PLAINTIFFS]: Yes. THE COURT: And, you

agree . . . that’s the language, ‘close of the bidding process?’ [GOVERNMENT]: Right.”).

Furthermore, plaintiffs confirmed, under their analysis, the “bidding process” has not yet

concluded because no solicitation award has been made. See Tr. at 161:3–12 (“[PLAINTIFFS:]

[T]he bidding process has not concluded yet. I would also point out that the Blue and Gold

[C]ourt relief heavily on the doctrine of patent ambiguity, and held that the policy behind that is

they don’t want offerors to wait until the selection of another contractor to raise the challenge

. . . . [T]here has been no award made here, so they brought the challenge months before an

award decision. To my knowledge, it hasn’t affected anything in the procurement.”). The

government itself even recognized JCCBG2 unlikely gained no unfair advantage as to

information about the number or identity of other bidders as a result of the timing of its protest.

See Tr. at 159:25–160:2 (“[GOVERNMENT:] [T]ypically even the number of offerors is not

- 39 -

disclosed until the award is made . . . I don’t see how the Plaintiff here would be aware of the

other offerors at this time.”); see also Tr. at 160:19–25 (“THE COURT: So you agree that

there’s no unfair advantage? . . . . [GOVERNMENT]: I don’t know that there is an unfair

advantage of whether it’s filed in August or May, but . . . they didn’t comply with the rule under

Blue & Gold. They didn’t file by the close of bidding, and that’s the waiver rule.”).

The government then relies on the Federal Circuit’s holding in COMINT to bolster its

argument. COMINT, however, is dicta at best. In COMINT, an unsuccessful bidder brought a

bid protest challenge after failing to file its protest before the agency awarded the contract. 700

F.3d at 1383–84. The Federal Circuit was not persuaded by the protester’s timeliness argument,

because the protestor sought to restart the bidding process after the agency had awarded the

contract—a scenario Blue & Gold forbids and not is neither the procedure nor request by

JCCBG2 in this case. See id. at 1384. JCCBG2’s protest is a different matter entirely as the

parties agree no contract has been awarded—further indicating the “bidding process” has not

closed. See supra Sections I.J, III.C, V.–VI. In fact, as of the date of oral argument, ten

amendments to the solicitation had been issued. Tr. at 158:21–159:4 (“[PLAINTIFFS:] As of

yesterday, there have now been 10 amendments to that solicitation that have been issued, and so,

you know, the protest was filed shortly after the initial submissions. There has been . . . five or

six months of continuing procurement activity without an award in that particular

procurement.”). Even if the Court were persuaded by the government’s speculations, COMINT

explained “the reasoning of Blue & Gold [to prevent unfair advantage] applies to all situations in

which the protesting party had the opportunity to challenge a solicitation before the award and

failed to do so.” See Tr. at 161:13–162:23; see also COMINT, 700 F.3d at 1382–84; Blue &

Gold, 492 F.3d at 1313–14. Indeed, the parties agree JCCBG2’s bid protest was filed before the

award of the contract—and amendments to the solicitations appear to be ongoing—so COMINT

is not applicable here. See Blue & Gold, 492 F.3d at 1313–14. Given the language of Blue &

Gold permits a bid protest challenge prior to the close of bidding (i.e., before the award of a

contract), and the government agrees JCCBG2 is gaining no competitive advantage through

manipulation of the bid protest process, the Court reads the phrase “close of the bidding process”

to include JCCBG2’s pre-award protest as timely, even though the protest was filed after the

bid’s submission. See id. at 13 (“[A] party who has the opportunity to object to the terms of a

government solicitation containing a patent error and fails to do so prior to the close of the

bidding process waives its ability to raise the same objection subsequently in a bid protest action

in the Court of Federal Claims.” (emphasis added)).

VIII. Injunctive Relief

The Court finally considers the following factors when determining whether to issue a

permanent injunction: “(1) whether . . . the plaintiff has succeeded on the merits of the case; (2)

whether the plaintiff will suffer irreparable harm if the court withholds injunctive relief; (3)

whether the balance of hardships to the respective parties favors the grant of injunctive relief;

and (4) whether it is in the public interest to grant injunctive relief.” PGBA, LLC v. United

States, 389 F.3d 1219, 1228–29 (Fed. Cir. 2004). If the Court awards injunctive relief, it may

fashion its own remedy to fit the contours of the decision. See Turner Constr. Co. v. United

States, 645 F.3d 1377, 1388 (Fed. Cir. 2011) (explaining “the Court of Federal Claims has broad

equitable powers to fashion an appropriate remedy”).

- 40 -

At oral argument, the parties disputed what relief was appropriate and how the Court

should tailor the injunctive relief if it were to find the PLA requirements violated CICA. See Tr.

167:14–175:11. By way of example, plaintiffs assert the Court could issue “a general injunction

against the PLA being used in each of the[] solicitations” and the agencies “could take action

to . . . remove the PLA from the requirement and . . . the agencies [c]ould send out a best and

final offer,” Tr. at 168:24–169:19, or the Court could issue a “specific injunction” of “blanket

applicability” which is “specific about the effects” of “PLAs violat[ing] CICA” and “not allow

the agenc[ies] to go back, re-evaluate, decide if it would still like to keep the PLA in, and then

decide if it wants to continue with the procurement with a new type of justification,” 170:15–

171:14. The government, however, asserts the Court should “enjoin the awards[s] unless and

until the agencies justify the PLA requirements consistent with the Court’s view of the law in the

opinion.” Tr. at 167:23–168:6.

As the Court already determined plaintiffs have succeeded on the merits of their case, the

first factor weighs in their favor. See supra Section VI. The Court, however, need not analyze

the other factors as the parties agree the procurements in this case are still ongoing and the

government’s agreement that each individual agency should be afforded an opportunity to review

their solicitations and reconsider the PLA determinations. Tr. at 178:12–23

(“[GOVERNMENT:] [I]f the Court’s holding were that this regulation violates CICA . . . I think

the agency could still make a determination that, yes, a PLA is necessary to meet our needs

without . . . applying the rebuttable presumption . . . I’m not saying whether the agencies would,

in fact, make that determination in these cases, but they should be given the opportunity to

consider that, if that’s how they wanted to proceed.”). At oral argument, the parties also raised a

number of unique differences for each individual solicitation when discussing an appropriate

injunction. For instance, the government indicated the “current state of where [one of the

NAVFAC cases is] in the procurement [likely means] that there wouldn’t be any basis for a[

PLA] exception at this time,” Tr. at 166: 18–167:4, and the GSA solicitation, which is a “two

phased process” with only “three offerors [] mov[ing] forward . . . to submit proposals for phase

2,” phase 1 decision is “expected to be made [] next week” and “caus[ing] a mootness issue or

perhaps a challenge from [Hensel] to the decision,” Tr. at 180:15–181:12. Accordingly, the

Court in its “broad equitable powers to fashion an appropriate remedy” finds the circumstances

surrounding the individual solicitations and the varying needs of three different agencies

(USACE, NAVFAC, and GSA) warrants the agencies be afforded a short period of time to

reassess their PLA decision on an individual basis. Input/Output Tech., Inc. v. United States, 44

Fed. Cl. 65, 72 n.9 (1999) (Firestone, J.) (“[T]his court’s role is not to second guess what the

[procuring agency] has determined to be its needs.”); Off. Design Grp. v. United States, 951 F.3d

1366, 1373 (Fed. Cir. 2020). The parties therefore shall file a joint status report explaining the

agencies plan for each solicitation moving forward on or by 3 February 2025. See Turner

Constr. Co. v. United States, 645 F.3d 1377, 1388 (Fed. Cir. 2011) (explaining “the Court of

Federal Claims has broad equitable powers to fashion an appropriate remedy”).

IX. Conclusion

For the foregoing reasons, the Court (1) GRANTS plaintiff MVL’s Motion for Judgment

on the Administrative Record, ECF No. 64; (2) GRANTS plaintiff ECC’s Motion for Judgment

- 41 -

on the Administrative Record, ECF No. 65; (3) GRANTS plaintiff JCCBG2’s Motion for

Judgment on the Administrative Record, ECF No. 66; (4) GRANTS plaintiff Harper’s Motion

for Judgment on the Administrative Record, ECF No. 67; (5) GRANTS plaintiff Hensel’s

Motions for Judgment on the Administrative Record, ECF Nos. 68, 69, 70; and (6) DENIES the

government’s Cross-Motion for Judgment on the Administrative Record, ECF No. 73. The

parties SHALL FILE revised versions of the parties’ briefs removing redactions from the

information discussed at oral argument on or before 3 February 2025. Finally, the government,

in consultation with the agencies, SHALL FILE a joint status report within on or before 3

February 2025 detailing the agencies’ proposed timeframe required to properly address each

contract.

IT IS SO ORDERED.

s/ Ryan T. Holte

RYAN T. HOLTE

Judge

- 42 -

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.