The opinion
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Joint Venture WMV Brussels American ) ASBCA No. 62736
School )
)
Under Contract No. W912GB-17-C-0018 )
APPEARANCE FOR THE APPELLANT: Seamus Curley, Esq.
Stroock & Strook & Lavin, LLP
Washington, DC
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Pietro O. Mistretta, Esq.
Herbert J. Aldridge, Esq.
Engineer Trial Attorneys
U.S. Army Engineer District, Europe
OPINION BY ADMINISTRATIVE JUDGE OSTERHOUT
This appeal involves a dispute between the United States Army Corps of
Engineers (USACE or the government) and Joint Venture WMV Brussels American
School (JV WMV or appellant) concerning Contract No. W912GB-17-C-0018 (the
contract). Appellant initially filed the appeal with five counts in its Complaint, although
it and the government later jointly moved to dismiss Counts II through V. The Board
granted the joint motion. 1 Thus, the only portion of the Complaint remaining in this
appeal is Count I.
In Count I of the Complaint, appellant appeals the denial of a contract
interpretation claim submitted by JV WMV on July 8, 2020, arguing that USACE
embedded design specifications in the contract as opposed to performance specifications
as alleged by the government (see compl. 7; R4, tab 3). 2 The Complaint sought “a ruling
from the ASBCA interpreting the Contract to resolve this interpretation dispute, as the
nature of Contract’s specifications has broad implications with respect to the parties’
respective obligations and liabilities, including ultimate liability for the project’s design”
1
Appellant subsequently filed additional appeals with the Board, ASBCA Nos. 63689,
63690, and 63691, pertaining to the same contract. These appeals were settled,
and the Board dismissed them with prejudice on October 25, 2024.
2
Though the contract interpretation claim was signed, it was not purported to be
“certified” by JV WMV (see R4, tab 3 at 9).
(compl. at 15). In the joint request to dismiss Counts II through V, the parties further
addressed Count I, stating, “However, the underlying issue of Count I (i.e., whether the
contract contains design specifications or performance specifications) has manifested
itself in [requests for equitable adjustments (REAs)] that have been filed, including
primarily an REA submitted on 20 April 2021 (the ‘Mechanical REA’) regarding the
mechanical system at the building being erected under the parties’ contract.” (Joint
Partial Motion to Dismiss at 1) JV WMV anticipated submitting the Mechanical REA at
the time it filed its complaint with the Board and that this REA would “seek a substantial
price adjustment and approximately one additional year in schedule relief” (see compl.
at 31). Indeed, the Mechanical REA sought more than 5.1 million euros 3 in damages and
910 days of schedule relief (app. resp. at 4). The parties provided further details about
the Mechanical REA in their motion, including that appellant had already submitted part
of an REA; was in the process of submitting supplemental REAs on the mechanical issue;
and that it “intends to convert the referenced REA and its supplements into one [or] more
[Contract Disputes Act (CDA)] claims, which Respondent will then respond to with a
Contracting Officer’s Final Decision, as required by the CDA.” (Joint Partial Motion to
Dismiss at 2)
The government filed a motion to dismiss the appeal due to a lack of jurisdiction.
In it, the government requested two possible forms of relief: 1) dismiss paragraphs 26
through 33 of the Complaint; or 2) dismiss ASBCA No. 62736 (gov’t mot. at 1). The
government opined that paragraphs 26 through 33 had not yet been presented to the
contracting officer for a final decision (id. at 2). Regarding dismissing the appeal in full,
the government stated that appellant’s request for contract interpretation has now been
converted to a monetary claim that has not been presented to the contracting officer, and
a final decision has not been requested (id.). The government argued that Count I now
concerns the Mechanical REA and that dismissing the appeal without prejudice would be
in everyone’s best interest for efficiency and would eliminate two rounds of litigation.
JV WMV responded, contending that paragraphs 26 through 33 were simply
factual recitations, not an attempt to recover for the REAs (app. resp. at 6). Although not
a model of clarity, we read the remainder of appellant’s response as broadly requesting
that Count I of the Complaint be permitted to proceed solely as a contract interpretation
claim, but that, whatever the Board decided was “appropriate,” 4 it should by no means
3
Although the Euro/Dollar exchange rate fluctuates, we take judicial notice that it is
typically around 1:1.
4
A fair reading of appellant’s response is that it had no objection to the Board deciding to
take whatever course of action we deemed most practical (see app. resp. at 8,
“deferring” to the Board’s choice on the matter). As tempting as it would be for
case management purposes to simply dismiss this appeal while proceeding on
later-filed appeals of the newer REAs, we will not do so without a more direct and
explicit request from appellant.
2
dismiss the appeal with prejudice because the determination of whether the specifications
were design specifications or performance specifications would be necessary for the
upcoming monetary claims (id. at 7-9).
DECISION
We grant the government’s motion because in the circumstances here, where a
decision will necessarily have significant monetary consequences well greater than the
statutory threshold of $100,000, a contractor must submit a certified claim to the
contracting officer, which JV WMV has not done.
Though not cited by either party, a case of ours with analogous facts dictates the
results here: Greenland Contractors I/S, ASBCA Nos. 61113, 61248, 19-1 BCA
¶ 37,259. In Greenland Contractors, the contractor appealed the government’s
interpretation of a contract at a time that it, the contractor, had already incurred costs in
performing in accordance with the government’s interpretation. Thus, the contractor had
been able to submit a monetary claim to the contracting officer but did not do so. See
Greenland Contractors, 19-1 BCA ¶ 37,259 at 181,330-32. Relying on precedent from
the Civilian Board of Contract Appeals 5 and the United States Court of Appeals for the
Federal Circuit, we held that the bare contract interpretation appeal should be dismissed
(without prejudice) because it was, in reality, a demand for money damages for which a
claim had not been submitted by the contractor. Id. at 18,331-32 (citing Securiforce
International America, LLC v. United States, 879 F.3d 1354, 1360 (Fed. Cir. 2018) and
Duke University v. Dept. of Health and Human Services, CBCA No. 5992, 18-
1 BCA ¶ 37,023)
Here, JV WMV did initially submit a contract interpretation claim to the
contracting officer. However, at the time that claim was submitted, JV WMV had
already begun incurring the costs reflected in the subsequently submitted Mechanical
REA and thus, the interpretation claim was, in fact, an uncertified demand for money
damages. The CDA requires that a claim valued at over $100,000 be certified with
statutorily-prescribed language attesting to its accuracy and that it was made in good
faith. 41 U.S.C. § 7103(b). A claim that contains a defective certification may be
remedied, but one without any certification at all is not considered a valid claim, and thus
an appeal resting upon such a claim must be dismissed for lack of jurisdiction.
Kamaludin Slyman CSC, ASBCA Nos. 62006, 62007, and 62008, 20-1 BCA ¶ 37,694
at 182,998 (citing multiple cases).
Here, the amount of money in dispute is well over the $100,000 threshold, as
demonstrated by the Mechanical REA, and the claim is not certified. Hence, the only
5
CBCA decisions are not binding upon us but may be considered as persuasive authority.
3
remaining count of the Complaint, which completely relies upon that claim, must be
dismissed. But it is dismissed without prejudice as this is a jurisdictional dismissal.
CONCLUSION
Thus, we grant the government’s motion to dismiss. The appeal is dismissed
without prejudice.
Dated: December 5, 2024
HEIDI L. OSTERHOUT
Administrative Judge
Armed Services Board
of Contract Appeals
I concur I concur
OWEN WILSON J. REID PROUTY
Administrative Judge Administrative Judge
Acting Chairman Vice Chairman
Armed Services Board Armed Services Board
of Contract Appeals of Contract Appeals
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 62736, Appeal of Joint
Venture WMV Brussels American School, rendered in conformance with the Board’s
Charter.
Dated: December 5, 2024
PAULLA K. GATES-LEWIS
Recorder, Armed Services
Board of Contract Appeals
4