Opinion

Evans v. CMH Homes, Inc

Court
District Court, E.D. Louisiana
Filed
Dec 13, 2024
Cited by
0 cases
Authority
More cited than 33.3%

The opinion

UNITED STATES DISTRICT COURT

EASTERN DISTRICT OF LOUISIANA

MARY EVANS CIVIL ACTION

VERSUS NO. 24-1808

CMH HOMES, INC., ET AL. SECTION: “G”

ORDER AND REASONS

In this litigation, Plaintiff Mary Evans (“Plaintiff”) brings claims against Defendant CMH

Homes, Inc. d/b/a Freedom Homes Gonzalez, LA (“CMH Homes”) for alleged defects in a

manufactured home Plaintiff bought from CMH Homes.1 Pending before the Court is CMH

Homes’ Motion to Stay Pending Arbitration.2 The motion was filed on October 9, 2024, and set

for submission on November 27, 2024.3 Pursuant to Local Rule 7.5, any opposition to the motion

was due eight days before the noticed submission date.4 Plaintiff has not filed an opposition to

the instant motion and therefore the motion is deemed unopposed. A federal district court may

grant an unopposed motion if the motion has merit.5 Having considered the motion, the

memoranda in support, the record, and the applicable law, the Court grants the motion.

1 Rec. Doc. 1-1.

2 Rec. Doc. 8.

3 Rec. Doc. 8-3.

4 See EDLA Local Rule 7.5.

5 See Braly v. Trail, 254 F.3d 1082 (5th Cir. 2001).

I. Background

On June 13, 2024, Plaintiff filed a Petition for Damages against Defendants CMH Homes,

American Bankers Insurance Company of Florida (“American Bankers”), Tiara Hayes-Babbin

(“Babbin”), and Erica Cargo (“Cargo”).6 Plaintiff alleges that there are defects in a manufactured

home she bought from CMH Homes.7 Plaintiff brings claims for return of funds paid, breach of

warranty, tort and breach of contract arising from alleged defects in her manufactured home.8

On July 17, 2024, CMH Homes removed the case to this Court, asserting diversity

jurisdiction pursuant to 28 U.S.C. Section 1332.9 Plaintiff is a citizen of Louisiana.10 CMH Homes

is incorporated in Tennessee with its principal place of business is in Tennessee, and American

Bankers is incorporated in Florida with its principal place of business in Florida.11 CMH Homes

asserts that Babbin and Cargo, both citizens of Louisiana, were fraudulently joined to defeat

diversity.12 American Bankers, Babbin, and Cargo also have not been served. The amount in

controversy exceeds $75,000 as Plaintiff claims she is entitled to a full refund of the purchase

price of the modular home ($89,390.65), in addition to damages.13

On October 9, 2024, CMH Homes filed the instant motion to compel arbitration.14

6 Rec. Doc. 1-1.

7 Id.

8 Id.

9 Rec. Doc. 1.

10 Id.

11 Id.

12 Id.

13 Id.

14 Rec. Doc. 8.

Plaintiff has not filed an opposition to the instant motion and therefore the motion is deemed

unopposed.

II. CMH Homes’ Arguments in Support of the Motion

CMH Homes moves this Court to compel Plaintiff to arbitrate her claims under the terms

of the “Binding Dispute Resolution Agreement” (“Dispute Resolution Agreement”) signed by

Plaintiff when she purchased the manufactured home.15 CMH Homes contends that the agreement

contains a valid arbitration provision governed by the Federal Arbitration Act (“FAA”).16

CMH Homes argues that the Dispute Resolution Agreement requires Plaintiff to arbitrate

“all pre-existing, present, or future disputes, claims, controversies, grievances, and causes of

action” against CMH Homes.17 Finally, CMH Homes argues that no federal statute or policy

renders the claims non-arbitrable.18 Therefore, CMH Homes argues that this litigation should be

stayed pending arbitration.19

III. Legal Standard

In Iberia Credit Bureau, Inc. v. Cingular Wireless LLC, the United States Court of

Appeals for the Fifth Circuit explained that the Federal Arbitration Act was “in large part

motivated by the goal of eliminating the courts’ historic hostility to arbitration agreements.”20

The Fifth Circuit further explained that “Section 2 of the FAA puts arbitration agreements on the

15 Rec. Doc. 8-1 at 2.

16 Id. at 5.

17 Id. at 7.

18 Id. at 8.

19 Id.

20 379 F.3d 159, 166 (5th Cir. 2004).

same footing as other contracts.”21 This means that, “as a matter of federal law, arbitration

agreements and clauses are to be enforced unless they are invalid under principles of state law

that govern all contracts.”22

There is a “strong federal policy in favor of enforcing arbitration agreements.”23 Section

3 of the FAA provides:

If any suit or proceeding be brought in any of the courts of the United States upon

any issue referable to arbitration . . . the court . . . shall on application of one of

the parties stay the trial of the action until such arbitration has been had in

accordance with the terms of the agreement. . . .24

“[I]f the issues in a case are within the reach of that [arbitration] agreement, the district court has

no discretion under section 3 to deny the stay.”25

IV. Analysis

A. Whether the Federal Arbitration Act Applies to this Dispute

In resolving the instant motion before the Court, it is first necessary to determine whether

the FAA governs the dispute between Plaintiff and CMH Homes. The FAA, codified at 9 U.S.C.

§ 1, et seq., provides the basis for the Court’s inquiry. Section 2 of the FAA states that a “contract

evidencing a transaction involving commerce to settle by arbitration a controversy thereafter

arising out of such contract or transaction . . . shall be valid, irrevocable, and enforceable.”26

21 Id.

22 Id.

23 Texaco Expl. & Prod. Co. v. AmClyde Engineered Prod. Co., 243 F.3d 906, 909 (5th Cir. 2001) (quoting

Dean Witter Reynolds Inc. v. Byrd, 470 U.S. 213, 217 (1985)).

24 9 U.S.C. § 3.

25 Texaco Expl. & Prod. Co., 243 F.3d at 909 (quoting Hornbeck Offshore Corp. v. Coastal Carriers Corp.,

981 F.2d 752, 754 (5th Cir. 1993)).

26 9 U.S.C. § 2 (emphasis added).

“Commerce” under Section 1 of the FAA means “commerce among the several States or with

foreign nations.”27 The U.S. Supreme Court has held that the FAA “provide[s] for the

enforcement of arbitration agreements within the full reach of the Commerce Clause” in the

United States Constitution.28

The instant suit involves a dispute between Plaintiff, a Louisiana citizen, and CMH

Homes, a Tennessee corporation.29 Plaintiff bought a manufactured home from CMH Homes.30

In sum, Plaintiff and CMH Homes are citizens of different states who entered a contract. “[A]

contract may involve commerce under the FAA if the parties engaged in the performance of

contract activities are citizens of different states, where such a contract involves interstate travel

of both personnel and payments.”31 Accordingly, the Court finds that the contract entails interstate

commercial activity, and the FAA applies to the present dispute between Plaintiff and CMH

Homes. The Court will now consider whether the arbitration provision in the Dispute Resolution

Agreement is enforceable against Plaintiff.

B. Enforceability of the Arbitration Provisions

To determine if an arbitration clause is enforceable, the Fifth Circuit has established a

two-step inquiry.32 First, a court determines whether the parties agreed to arbitrate.33 This first

27 Id. § 1.

28 Perry v. Thomas, 482 U.S. 483, 490 (1987).

29 Rec. Doc. 1.

30 Rec. Doc. 1-1.

31 See Atl. Aviation, Inc. v. EBM Grp., Inc., 11 F.3d 1276, 1280 (5th Cir. 1994), overruled on other grounds

by Action Industries, Inc. v. U.S. Fidelity & Guar. Co. 358 F.3d 337, 341 n.10 (5th Cir. 2004) (internal

citations omitted).

32 Fleetwood Enters., Inc. v. Gaskamp, 280 F.3d 1069, 1073 (5th Cir. 2002).

33 Id.

step itself is subdivided into two considerations: (a) whether there was a valid agreement to

arbitrate and (b) whether the dispute in question falls within the scope of the arbitration clause.34

If both questions are answered in the affirmative, the court moves on to the second step. Under

the second step, a court determines whether “any federal statute or policy renders the claims

nonarbitrable.”35

1. Whether there was a Valid Agreement to Arbitrate

Under step 1(a) of the Fifth Circuit’s two-step test, the Court must determine whether a

valid agreement to arbitrate exists between the parties. In making this determination, courts apply

“ordinary state-law principles that govern the formation of contracts.”36

Under Louisiana law, a contract is “an agreement by two or more people whereby

obligations are created, modified, or extinguished.”37 An “obligation cannot exist without a lawful

cause.”38 “Cause is the reason why a party obligates himself.”39 Under Louisiana law, “[i]t is

well-settled that a party who signs a written instrument is presumed to know its contents and

cannot avoid its obligations by contending that he did not read it, that he did not understand it, or

that the other party failed to explain it to him.”40

Here, it is undisputed that Plaintiff consented to the Dispute Resolution Agreement, and

34 Id.

35 Jones v. Halliburton Co., 583 F.3d 228, 234 (5th Cir. 2009).

36 Fleetwood Enterprises, 280 F.3d at 1073 (quoting First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938,

944 (1995)).

37 La. Civ. Code art. 1906.

38 La. Civ. Code art. 1966.

39 La. Civ. Code art. 1967.

40 Coleman v. Jim Walter Homes, Inc. 2008–1221 (La.3/17/09); 6 So. 3d 179, 183.

Plaintiff does not argue that the agreement is not supported by a lawful cause. Therefore, Plaintiff

consented to the Dispute Resolution Agreement’s terms, and Plaintiff does not argue that any

other issues affected the formation of the agreement in this case. Accordingly, the Court finds

that the Dispute Resolution Agreement constitutes a valid agreement to arbitrate between Plaintiff

and CMH Homes.

2. Whether Plaintiff’s Claims fall within the Arbitration Provisions

Under step 1(b) of the Fifth Circuit’s two-step test, the question is whether Plaintiff’s

claims fall within the scope of the Dispute Resolution Agreement’s arbitration provision. Courts

apply a strong presumption in favor of arbitrability when deciding whether a party’s claims fall

within the scope of an arbitration provision.41 Any doubt about the arbitrability of a dispute should

be resolved in favor of arbitration.42 The party resisting arbitration bears the burden of proving

that a dispute is not arbitrable.43 To overcome the presumption in favor of arbitrability, clear

evidence must exist that the parties did not intend the claim at issue to be arbitrated.44

In this case, the arbitration provision states:

This Agreement applies to all pre-existing, present, or future disputes, claims,

controversies, grievances, and causes of action against Seller, including, but not

limited to, common law claims, contract and warranty claims, tort claims, statutory

claims, administrative law claims, and any other matter in question, not otherwise

excepted herein, arising out of or relating to (i) the modular or manufactured

home(s) purchased, sold, owned, occupied and/or delivered in any transaction with

Buyer or Beneficiaries (the “Home”), (ii) the documents related to the purchase

and sale of the Home (including, but not limited to, the Retailer closing

Agreement, any Purchase or Sales Agreement, buyer’s order, supplemental

invoice, and other instruments and agreements whereby Seller purports to convey

or receive any goods or services to or from Buyer or Beneficiaries (collectively,

41 AT & T Techs., Inc. v. Commc'ns Workers of Am., 475 U.S. 643, 648 (1986).

42 See Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24–25 (1983).

43 Am. Heritage Life Ins. Co. v. Lang, 321 F.3d 533, 539 (5th Cir. 2003).

44 Moses H. Cone Mem’l Hosp., 460 U.S. at 24–25.

the “Contract”)), (iii) any products, goods, services, insurance, supplemental

warranty, service contract, and real property (including improvements to the real

property) sold under or referred to in the Contract, (iv) any events leading up to

the Contract, (v) the collection and servicing of the Contract, (vi) the design and

construction of the home, and (vii) the interpretation, scope, validity and

enforceability of the Contract (collectively referred to as the “Claim” or

(Claims”).45

Plaintiff’s breach of warranty, tort, and breach of contract claims clearly fall under the terms of

this provision.

This case is not a close call but, even if it were, any doubts concerning the scope of an

arbitration clause is resolved in favor of arbitrability.46 Plaintiff has not attempted to overcome

that strong presumption in favor of arbitrability and has failed to file any opposition to the instant

motion. Therefore, the Court finds that Plaintiff’s claims fall within the scope of the arbitration

provision in the Dispute Resolution Agreement.

3. Whether any Federal Policy or Federal Statute Forecloses Arbitration of

Plaintiff’s EFTA Claims

Under Step 2 of the Fifth Circuit’s two-part test, the Court determines whether any federal

statute or policy renders a party’s claims non-arbitrable.47 Here, Plaintiff does not point to any

federal statute or policy that would render Plaintiff’s claims non-arbitrable. Because no federal

policy or statute forecloses arbitration of Plaintiff’s claims, the FAA therefore requires the Court

to enforce the arbitration provision in the Dispute Resolution Agreement.

V. Conclusion

Under Section 3 of the FAA, if a federal court determines that the parties’ transaction

entails interstate commerce and the FAA governs the litigation, a federal court has the authority

45 Rec. Doc. 8-2 at 11.

46 Harvey v. Joyce, 199 F.3d 790, 793 (5th Cir. 2000).

47 Jones v. Halliburton Co., 583 F.3d at 234.

to stay the litigation pending arbitration.** As the Fifth Circuit observed, Section 3 of the FAA is

mandatory because it provides that federal courts “shall on application of one of the parties stay

the trial of the action.”

Accordingly,

IT IS HEREBY ORDERED that CMH Homes’ Motion to Stay Pending Arbitration™ is

GRANTED. The above captioned matter is STAYED and ADMINISTRATIVELY CLOSED

pending arbitration.

NEW ORLEANS, LOUISIANA, this _13th_ day of December, 2024.

D ersette obuett 0s

NANNETTE IVETTE BROWN (our

CHIEF JUDGE

UNITED STATES DISTRICT COURT

BOUSC. § 3.

000 Memt, Inc. v. Residuos Industriales Multiquim, S.A. de C.V., 372 F.3d 339, 342-43, 346 (Sth Cir.

Rec. Doc. 8.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.